Page 1: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

WHHT

ACUTE REDEVELOPMENT OPTIONS

INDICATIVE PLANS

HVCCG/WHHT Joint Board 6th June 2019

These indicative plans are under development and will evolve throughout the duration of the project

Page 2: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS New Main Entrance for WGH

Page 3: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

Option 1

WGH • Main investment on WGH

• New beds

• New block for acute services

+ HHH • New UTC

• Create planned medical focus

• Land released for housing development

+ SACH • Create planned surgical & cancer focus

• New diagnostics centre

Page 4: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

Watford

General

Hospital

Page 5: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

Level 1 : Trust Offices

Level 2 : Trust Offices

Level 3: Trust Offices

Level 4 : Staff Accommodation

Block P

Level -1 : Plant Car park

Level 0 : Plant

Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension

Level 2 : OPD)

Paeds OPD Mat OPD Renal Dining

Level 3 : NICU Special care baby unit Delivery suite WACS

Level 4 : Theatre suite WACS

Level 5 : Theatre suite HSSU

Level 6 : Theatre suite

Block O 24000m² + 8000m²

Level 1 : Pathology & Cytology Stores Mortuary Assessment Cancer Unit

Level 2 : 60 Beds

Level 3 : 60 Beds

Level 4 : 60 Beds

Level 5 : 60 Beds

New Shrodells 1 & 2 6400m² + 6400 m²

Level 1 : Medical records Nursing Stores

Level 2 : H.R Training Admin

Block I

Level 1 : Emergency Department

Level 2 : Imaging OPD Fracture Clinic

Level 3 : Beds Endoscopy Vascular lab

Level 4 : Beds

Level 5 : Beds

Level 6 : Beds

PMoK

Level 1 : Ward

Level 2 : Imaging Pharmacy Cath lab

Dispensary Stores

Level 3 : Ward

AAU

WGH – Proposed Development

Land released

New Construction

Existing

WGH expansion

MSCP

Green Text: New Services

Blue Text: Refurbishment

Refurbished

Listed Building

New Construction, not confirmed

Land Disposal • Approx. 22,000sqm land released for development. (2.20 Hectares) • Approx. 7,500sqm for WGH Future Expansion. (0.75 Hectares)

Completion

Page 6: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS WGH Option 1 – Overview

Page 7: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

Decant

Demolition

Decant Off Site

Refurbishment

New Construction

Temporary

Buildability - WGH Phasing Summary

Phase 1 Phase 2

Phase 4 Phase 3

Page 8: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS WGH Option 1 – Redevelopment of Clinical Buildings

Page 9: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS Key Adjacencies – Schematic Sections – WGH

Section AA

Section BB

Page 10: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS Ward Refurbishment – Multi-bed rooms

Existing standard room_

6 beds

Proposed Refurbished standard room_

4 beds

HBN 00-03 Clinical Admin Space

* Review of en-suite to be concluded.

4 beds room _ Lane Fox Remeo Centre_MPA

Page 11: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

Hemel

Hempstead

Hospital

Page 12: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

Level 1 : Pharmacy Therapy Education meeting Paeds OPD

Level 2 : Dermatology GP’s CATS OPD Cardio Gynae OPD Café Phlebotomy

Level 3 : Mortuary ? Diabetes Elderly Chest Vacant Plant

Verulam

Level 1 : UTC

Level 2 : UTC

UTC Block

1500m²

Homes England car park

HHH - Proposed – Option 1

Land Disposal • Approx. 21,000sqm land released for development. (2.1 Hectares)

Completion

Car park • Homes England car par relocated to current car park area. • Extension of current car park. MSCP to be considered.

Green Text: New Services Blue Text: Refurbishment

Land released

New Construction

Existing

External Carpark

Indicative housing development

Housing Development • Potential of 200 – 240 housing units achieved

within the released land.

Page 13: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

St

Albans

City

Hospital

Page 14: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

Level 1 : Fracture clinic Hydrotherapy

Level 2 : Urology

Level 3 : Breast care

Runcie Wing

Level 1 : Plant Admin

Level 2 : Admin HDU POA

Level 3 : POA

Level 4 : Rehabilitation

Level 5 : Ward Ophthalmology

Level 6 : Ward

Moynihan Wing

Level 1 : TLC Nursery

Waverley Wing

Level 2 : UTC Antenatal OPD Renal Dermatology

Level 1 : Day Surgery (Total of 6

theatres. Theatre 5

replacement & upgrade of

Theatre 6 theatres)

Admin Admissions Lounge

Gloucester Wing

Level 1 : Imaging

Level 2 : Imaging Endoscopy

Diagnostics Block 2000m²

Land released

New Construction

Existing

External Carpark

Level 1 : Support Energy source

Level 2 : Estate Office

Support Block 700m²

Land for redevelopment: • Approx. 4,000sqm land released for development, potentially for additional car parking. (0.40 Hectares)

Green Text: New Services Blue Text: Refurbishment

SACH - Proposed - Option 1

Completion

Page 15: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS Key Adjacencies – Schematic Sections – SACH

Section BB

Section AA

Page 16: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

Option 2

Not developed further due

to poor qualitative score

WGH • Reduced investment at WGH

• Reduced provision of new beds

• New block for acute services

• New theatres block

+ SACH • Significant investment at SACH

• New planned medical care focus

• Planned surgical & cancer care focus

• New diagnostics centre

+ HHH • Hospital closed. Site available for housing

Page 17: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

Option 3

WGH • Reduced investment on WGH

• New beds, but less provision

• New block for Acute Services

• No new theatres

+ HHH • More investment on HHH

• New surgical & cancer block

• New multi storey car park

• Reduced footprint

+ SACH • Hospital closed. Site available for housing

Page 18: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

Watford

General

Hospital

Page 19: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

Level 1 : Trust Offices

Level 2 : Trust Offices

Level 3: Trust Offices

Level 4 : Staff Accommodation

Block P

Level -1 : Plant Car park

Level 0 : Plant

Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension

Level 2 : OPD Paeds OPD Mat OPD Renal Dining

Level 3 : NICU Special care baby unit Delivery suite WACS

Level 4 : Theatre suite Obs & Gynae Theatre

Block O 16000m² + 8000m²

Level 1 : Pathology & Cytology Stores Mortuary Assessment Cancer Unit

Level 2 : 60 Beds

Level 3 : 60 Beds

Level 4 : 60 Beds

New Shrodells 1 & 2 6400m² + 6400 m²

Level 1 : Medical records Nursing Stores

Level 2 : H.R Training Admin

Block I

Level 1 : Emergency Department

Level 2 : Imaging OPD Fracture Clinic

Level 3 : Beds Endoscopy

Vascular lab

Level 4 : Beds

Level 5 : Beds

Level 6 : Theatre Critical Care

PMoK

Level 1 : Ward

Level 2 : Imaging Pharmacy Cath lab Dispensary Stores

Level 3 : Ward

AAU

WGH - Proposed – Option 3

Not included on Option 3

Land released

New Construction

Existing

WGH expansion

MSCP

Green Text: New Services Blue Text: Refurbishment

Refurbished

Listed Building

New Construction, not confirmed

Land Disposal • Approx. 22,000sqm land released for development. (2.20 Hectares) • Approx. 7,500sqm for WGH Future Expansion. (0.75 Hectares)

Completion

Page 20: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

Hemel

Hempstead

Hospital

Page 21: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

Multi storey Car Park

5 floors 720 bays

Level 1 : Pharmacy Breast Care Antenatal Education meeting Paeds OPD

Level 2 : UTC GP’s CATS OPD Cardio Gynae OPD Café Phlebotomy

Level 3 : Mortuary ? Dermatology Diabetes Elderly Chest Endoscopy Plant

Verulam

Level 3 : Day Surge POA

Level 4 : Day Surge Beds

Surgical Block 9400m²

Level 2 : Ophtalmology Therapy Rehab.

Level 1 : Imaging Fracture Clinic

HHH - Proposed – Option 3

Green Text: New Services Blue Text: Refurbishment

Land released

New Construction

Existing

External Carpark

Indicative housing development

New Construction, not confirmed

Land Disposal • Approx. 17,000sqm land released for development. (1.7 Hectares)

Car park • MSCP proposed, circa 720 bays. Additional external car park

to be located over Verulam roof, circa 100 bays.

Completion

Housing Development • Potential of 160 – 200 housing units achieved

within the released land.

Page 22: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

Option 4

WGH • Less additional provision of beds

• New block for acute services

• No new theatres

+ New Site • New planned care centre

+ HHH & SACH • Sites available for disposal

Page 23: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

Watford

General

Hospital

Page 24: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

Level 1 : Trust Offices

Level 2 : Trust Offices

Level 3: Trust Offices

Level 4 : Staff Accommodation

Block P

Level -1 : Plant Car park

Level 0 : Plant

Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension

Level 2 : OPD Paeds OPD Mat OPD Renal Dining

Level 3 : NICU Special care baby unit Delivery suite WACS

Level 4 : Obs & Gynae Theatres

Block O 16000m² + 8000m²

Level 1 : Medical records

Nursing Stores

Level 2 : H.R Training Admin

Block I

Level 1 : Emergency Department

Level 2 : Imaging OPD Fracture Clinic

Level 3 : Beds Endoscopy Vascular lab

Level 4 : Beds

Level 5 : Beds

Level 6 : Theatre Critical Care

PMoK

Level 1 : Ward

Level 2 : Imaging Pharmacy Cath lab Dispensary Stores

Level 3 : Ward

AAU

Level 1 : Pathology & Cytology Stores Mortuary

Assessment Cancer Unit

Level 2 : 30 Beds

Level 3 : 30 Beds

Level 4 : 30 Beds

Level 5 : 30 Beds

New Shrodells 1 6400m²

WGH - Proposed – Option 4

Land Disposal • Approx. 22,000sqm land released for development. (2.20 Hectares) • Approx. 7,500sqm for WGH Future Expansion. (0.75 Hectares)

Not included on Option 4

Land released

New Construction

Existing

WGH expansion

MSCP

Green Text: New Services Blue Text: Refurbishment

Refurbished

Listed Building

New Construction, not confirmed

Completion

Page 25: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

New Site

Page 26: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS New Planned Care Centre - Proposed – Option 4

Ward Cancer Unit

Level 1 : Endoscopy Pharmacy OPD Admin FM Plant

Level 2 : OPD Imaging UTC Rehabilitation

Level 3 :

Planned Care Centre 17000m²

Level 4 : Theatres

Multi storey Car Park

5 floors 720 bays

New Construction

Green Text: New Services Blue Text: Refurbishment

New Construction, not confirmed

Operating Theatre:

Luton & Dunstable Hospital

External Images:

Chase Farm Planned Care Centre

• HHH & SACH will closed. Both sites will be land for disposal. • No site has been confirmed at the moment.

Completion

M1

Hemel

Hempstead

Hospital

St Albans

City Hospital

M25

New Site

Indicative

Location

Page 27: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

thank you

Page 28: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

WHHT

ACUTE REDEVELOPMENT OPTIONS

SUPPLEMENTARY INFORMATION

HVCCG/WHHT Joint Board 6th June 2019

Page 29: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

Watford

General

Hospital

Page 30: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

Level 1 : Plant Stores

Level 2 : Paediatric OPD Ante-Natal clinic Ophthalmology

Level 3 : Elizabeth ward

Level 4 : Wards

Level 5 : Special care baby unit Delivery Theatre Neonatal

WACS

Level 1 : Med.l records Nursing Stores

Level 2 : H.R Training Admin

Block I

Level 1 : Ambulatory care

Level 2 : Ambulatory care

Level 3 : Ambulatory

care

Level 4 : Plant

Shrodells

Level 1 : Emergency Department Fracture Clinic

Level 2 : OPD Imaging FOH Staff Support

Level 3 : Ward Endoscopy Vascular lab

Level 4 : Wards

Level 5 : Wards

Level 6 : Theatres HSSU Intensive care

Level 7&8 : Plant

PMoK

Level 0 : Cytology Mortuary NEQAS

Level 1 : Pathology

Level 2 : Pathology

Pathology

Level 1 : Trust Offices

Level 2 : Staff Accommod.

Level 3 : Staff Accommod.

Cherry Tree

Level 0 : Boiler house

Level 1 : Boiler house

Level 2 : Boiler house

Boiler House

AAU

Level 1 : Ward

Level 2 : Imaging Pharmacy Cath lab Dispensary Stores

Level 3 : Ward

Level 1 : Med records Dermatology Renal Clinic Eng.

Level 2 : PGMC

H Block

Level 1 : Kitchen

Level 2 : Dining TLC Nursery

Kitchen

Surge Unit

Level 1 : Surge Unit

Level 1-4: Offices

Trust Off.

Level 1,2 & 3 :

Cardiology Cardiology

Level 1,2 & 3 :

Sycamore House Diabetes

Level 1:

Helen Donald

Maxillofacial Cancer Unit

WGH - Existing Site

Page 31: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

Hemel

Hempstead

Hospital

Page 32: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS HHH – Existing Site

Level 1 : Pharmacy Therapy Education meeting Paeds OPD Simpson Ward

Level 2 : Pathology OPD Admin Cardio Gynae OPD Café Phlebotomy

Level 3 : Mortuary POA Diabetes Elderly Chest St Peter’s Ward Plant

Verulam

Level 1 : Vacant

Level 2 : Vacant

Level 3 : Vacant

Level 4 : Vacant

Windsor

Level 1 : Vacant

Level 2 : Vacant

Level 3 : Vacant

Level 4 : Vacant

Tudor & Halsey House

Level 1 : Vacant

Cheere House

Existing

Vacant

Level 1 : MRI POA Medical records

Level 2 : Admin Fractures Boiler House CATS GP Urgent care

Level 3 : Pharmacy Dermatology I.T

Main block & Jubilee Wing

Level 1 : Estates Workshop

Estates

Level 2 : Dermatology

Marnham

Level 1 : Vacant

Pensions & Wages

Level 3 : IT Support

QE Block

Level 2 :

Level 1 : Medical Records Occupational

therapy

Page 33: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS Key Adjacencies – Schematic Sections – HHH

Section AA

Page 34: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

St

Albans

City

Hospital

Page 35: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS SACH – Existing Site

Level 1 : GUM Clinic

Waverley Wing

Level 1 : Day Surgery Plant Admin

Level 2 : Diagnostics UTC Breast care Outpatients Dermatology Renal

Gloucester Wing

Level 1 :

Podiatry PGMC Dental

Level 2 :

Admin

Catering

Level 1 : Boiler House

Boiler House

Level 1 : Workshops

Estate Offices

Level 1 : Fracture Clinic OPD Hydrotherapy

Level 2 : POA

Level 3 : POA

Runcie Wing

Level 1 : TLC Nursery

TLC Nursery

Level 1 : Plant Admin

Level 2 : Admin / Vacant

Level 3 : Vacant

Level 4 : Rehabilitation

Level 5 : Ward Ophthalmology

Level 6 : Ward

Moynihan Wing Existing

Vacant

Page 36: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS Key Adjacencies – Schematic Sections – SACH

Section BB

Section AA

Page 37: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

Watford

General

Hospital

PHASING PLAN (DRAFT)

Page 38: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

1A

Phase 1A • Refurbishment of Neonatal on Level 5 of WACS

• Decant off site of Diabetes on Sycamore House

Phase 1B • Decant of Fracture Clinic to Sycamore House (temporary)

• ED refurbishment and extension, including the demolition

of porta cabin.

• Hoarding and Demolition of left wing of Shrodells.

Phase 1

1B

1B

Decant

Demolition

Decant Off Site

Refurbishment

New Construction

Temporary

1B

1A

Phasing

Page 39: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

2A

Phase 2A: • Construction of New Shrodells 01.

Total floor of 5. 4 of the floors for beds, 30 beds per floor.

Ground floor to allocate additional Assessment Area

• Temporary link to AAU/PMoK.

Phase 2B: • Demolition of redundant beds of Surge Unit.

Phase 2C: • Demolition of redundant beds on Shrodells.

• Decant of Pathology, Cytology and Mortuary hot

services into a temporary porta cabin, location to be

agreed.

• Subsequent demolition of Pathology and Cytology

buildings.

Phase 2

2B

2C

Decant

Demolition

Decant Off Site

Refurbishment

New Construction

Temporary

Phasing

2C

Page 40: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS

Phase 3A.1 • Construction of Block O. A total of 6 floors and circa

24000sqm. 2 extra floors “on legs” for carpark/plant or future

expansion.

• Construction of Boulevard and link between PMoK & Block O.

• Construction of New Shrodells 02.

4 of the floors for beds, 30 beds per floor.

Ground floor to allocate hot services of Pathology, Mortuary

& Cytology and Cancer Unit.

• Construction of final link in between PMoK – AAU & New

Shrodells.

Phase 3A.2

• Demolition of Boiler House.

• Construction of Boulevard Canopy & Walkway link to MSCP.

Phase 3B

• ED extension into Level 1 Block O.

• Level 2 Refurb of OPD including Cardiology, Renal & Fracture

Clinic. Imaging discharge lounge refurb and extension.

Phase 3C

• Decant to Block O: WACS, Dining, Kitchen, Clinical Eng.,

Maxillofacial and Theatres (from PMoK),

Phase 3D

• PMoK level 3,4,5 and 6 new and refurb of beds.

Phase 3E.1 & 2

• Construction of Block P, 4 floors, circa 3500sqm. Trust offices

and Staff accommodation decanted.

Phase 3

3A.1

Decant

Demolition

Decant Off Site

Refurbishment

New Construction

Temporary

Phasing

3A.1

3A.2

3B 3D

3C

3C 3C

3E.2

3B

3C

3C 3E.1

3E.1

3A.2

Ambulance Entrance

Page 41: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS Phasing

Phase 4A

• Decant off site of Admin on I Block.

• Decant off site Dermatology from Block H.

Phase 4B • Demolition of:

WACS Cardiology Centre

4A

Sycamore House Kitchen

Helen Donald Willow House

I Block Cherry Tree

Phase 4C • Landscaping and Highway works.

Phase 4

Decant

Demolition

Decant Off Site

Refurbishment

New Construction

Temporary

4B

4A

4B

4B 4B

4B 4B

Page 42: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS WGH – Option 1 Variant – ED located within new O block

Level 1 : Trust Offices

Level 2 : Trust Offices

Level 3: Trust Offices

Level 4 : Staff Accommodation

Block P

Level -1 : Plant Car park

Level 0 : Plant

Level 1 : Emergency Department

Level 2 : OPD Paeds OPD Mat OPD Renal Dining

Level 3 : NICU Special care baby unit Delivery suite WACS

Level 4 : Theatre suite WACS

Level 5 : Theatre suite HSSU

Level 6 : Theatre suite

Block O 24000m² + 8000m²

Level 1 : Pathology & Cytology Stores Mortuary Assessment Cancer Unit

Level 2 : 60 Beds

Level 3 : 60 Beds

Level 4 : 60 Beds

Level 5 : 60 Beds

New Shrodells 1 & 2 6400m² + 6400 m²

Level 1 : Medical records Nursing Stores

Level 2 : H.R Training Admin

Block I

Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC

Level 2 : Imaging OPD Fracture Clinic

Level 3 : Beds Endoscopy Vascular lab

Level 4 : Beds

Level 5 : Beds

Level 6 : Beds

PMoK

Level 1 : Ward

Level 2 : Imaging Pharmacy Cath lab Dispensary Stores

Level 3 : Ward

AAU

Land released

New Construction

Existing

WGH expansion

MSCP

Green Text: New Services

Blue Text: Refurbishment

Refurbished

Listed Building

New Construction, not confirmed

Land Disposal • Approx. 22,000sqm land released for development. (2.20 Hectares) • Approx. 7,500sqm for WGH Future Expansion. (0.75 Hectares)

Completion

Page 43: WHHT ACUTE REDEVELOPMENT OPTIONS INDICATIVE PLANS · Level -1 : Plant Car park Level 0 : Plant Level 1 : Clinical engineering Stores TLC nursery Kitchen PGMC ED Extension Level 2

WHHT - Development Control Plans

MURPHYPHILIPPS Department Distance

1½ to 2 Minutes

1 Minute

½ Minute

Theatres

Emergency

Maternity

Beds