what does this all mean?washingtondc.alumclub.mit.edu › s › 1314 › images › gid29 › ...dec...
TRANSCRIPT
-
What does this all mean?
The JIA created:• The ITER Organization (IO), a public international
organization, as the agent for the 7 Members to realize the purpose of the ITER – to demonstrate the scientific and technological feasibility of fusion energy for peaceful purposes.
• The ITER Council, the governing board of directors, a group of equals from the Members (meets twice/year).
• The Council, aided by advisory committees, directs the IO
The Director General (DG) of the IO reports to the ITER Council
The Council approves the DG and the DG’s management structure and establishes performance expectations
41
-
What does this all mean?
42
ITER Organization Structure
-
What does this all mean?
Each Member is committed to supply to the IO its share of in-kind hardware, personnel, and cash for construction
The European Union, as host, has a 5/11th (45.45%) share of construction. The U.S., as one of 6 non-host Members, has a 1/11th (9.09%) share of construction
The U.S. Department of Energy is the sole U.S. agency responsible for satisfying the U.S. commitments of the JIA
43
Value Proposition: With a ~ 10% investment, the U.S. gets 100% of the intellectual property obtained from ITER operation
-
What does this all mean?
As its agent, DOE created the U.S. ITER Project Office to manage the process of meeting its commitments
The project office is located at Oak Ridge National Laboratory
There are 2 other partners – Princeton Plasma Physics Laboratory and Savannah River National Laboratory
Similarly, each Member has created its own Domestic Agency (DA)
44
-
Toroidal Field Coils (18)
Poloidal Field Coils (6)
Cryostat
Thermal Shield
Vacuum Vessel
Feeders (31)
Who Manufactures What?
Divertor Central Solenoid (6)Correction Coils (18)
Blanket
-
US In-kind Hardware Contributions
ORNL100% Central Solenoid
Windings+ JA Support
ORNL8% of Toroidal
Field Conductor+ JA Support
ORNL100% Pellet Injector
100% Disruption Mitigation
ORNLBlanket/Shield
(design only)
ORNL100% Tokamak Cooling
Water System
PPPL 75% Steady StateElectrical Network
PPPL14% of Port-based
Diagnostics
ORNL88% Ion Cyclotron
Transmission Lines
ORNL88% Electron
Cyclotron Transmission Lines
PPPLIn-Vessel Coils
(prelim. design only)
ORNL100% Roughing Pumps,
Vacuum Standard Components
SRNL100% Tokamak Exhaust
Processing System
46
-
Over 80% of Project Funding will be Spent in the US
As of December 2013, over $572M has been awarded to US industry and universities, and obligated to DOE national laboratories in 40 states plus the District of Columbia.
Note: This data does not reflect contracts awarded to US Industry by the EU (>$55M) or Korea (>$23M)
-
So where are we now?
48
The site has been prepared since 2009
Civil construction began in 2010 and is accelerating
R&D and Design are winding down; fabrication of the In-Kind Hardware is accelerating
The first major U.S. delivery of In-Kind hardware to the IO will be made January 2015 (5 massive, nuclear-grade, drain tanks)
Members assert that the commitment exists to follow through with funding requirements yet the schedule is still being determined
-
The ITER era has begun: Building construction is underway
CEA Cadarache Site
ITER Temporary Headquarters
ITER siteHQ construction
Tokamak pit excavation
PF coil winding buildingconstruction
A general view of the 42-hectare ITER platform (~100 acres), December 2010
49
-
Civil Construction is well underway
50
-
Progress:Tokamak Pit
51
-
Major Progress:Assembly Building
52
Photo: ITER Organization • June 2013
-
Major Progress: Poloidal Field Coil Winding Facility
53
-
Major Progress:ITER Cryostat Building
54
-
Major Progress:ITER Headquarters Building
FESAC/Sauthoff 55
-
56
Fabrication of ITER Components by Global Partners is UnderwayFabrication of ITER Components by Global Partners is Underway
-
TF Conductor Fabrication by 6 Domestic Agency Contributors
57
-
EU – Buildings, TF Coils, Vacuum Vessel, and Neutral Beam Injection
First double pancake prototype being wound for toroidalfield conductor
A mock-up of the under-port portion of the vacuum vessel
58
Full scale NBI tests will be conducted at Padua site now under construction.
-
1MW gyrotron for plasma heating ¤t drive and mode suppression
Japan – TF Coilsand 170 GHz Gyrotron
B3Segment
TF Coil ~325 metric tons16 m tall x 9 m wide
59
-
Korea – Vacuum Vessel Segmentsand Power Convertor Systems
Prototype of the AC/DC power converter for the ITER vertical stabilization coils.
Manufacturing of an ITER vacuum vessel segment in Korea
60
-
Russia – Poloidal Field Magnet Conductor Development and 170 GHz Gyrotron
1MW gyrotron for plasma heating andcurrent drive plus mode suppression
A copper dummy conductor fabricated for the PF1 coil
61
-
China – Poloidal Field Conductor
Poloidal field dummy conductor was delivered from China to the ITER site in June 2013.
Poloidal field dummy conductor was loaded on a ship bound for France in April 2013.
62
-
India – Cryostat andDiagnostic Neutral Beam
A cryostat component full-scale mock-up. Photo: IN DA
Cryostat modelImage: ITER Organization
High voltage power supply for Diagnostic Neutral Beam. Photo: IN DA
63
-
6404/09/
FESAC/Sauthoff
US ITER Scope and Progress
-
About 80% of US ITER funding is for in-kind hardware contributions built in U.S.
In-kind hardware contributionsmanaged at U.S. ITER Project Office (at Oak Ridge National
Laboratory)
65
-
SCALE
ORNL100% Central Solenoid(using JA conductor)
ORNL8% of Toroidal
Field Conductor
ORNL100% Pellet Injector
ORNL100% Disruption
Mitigation (up to capped value)
ORNL100% Tokamak Cooling
Water System
PPPL75% Steady StateElectrical Network
PPPL14% of Port-based
Diagnostics
ORNL100% Ion CyclotronTransmission Lines
ORNL100% Electron
Cyclotron Transmission Lines
ORNLBlanket/Shield
(design support)
ORNL100% Roughing Pumps,
Vacuum Auxiliary System
SRNL100% Tokamak Exhaust
Processing System
66
US Scope
-
Over 75 hardware prototypes under development & testing
67
-
Central Solenoid
Specs: 6 independent coil packs of cable-in-conduit conductor (produced in up to 910 m lengths), plus pre-compression structure• 13 Tesla • 5.5 GJ • 30 kV • 1.2 T/s • 45 kA• 710 metric tons
ITER Partner: Japan (conductor)
Status:• Final Design Review completed• Fabrication of tooling stations complete• First pancakes of mock-up coil wound
Key Vendors: General Atomics (modules) with Tauring, Ridgway,
Babcock Noel, Seco Warwick (tooling stations) G&G Steel (prototype tie plates) Major Tool & Machine, Inc. (prototype tie plates)
Pancake-Wound Segmented Stack
CS Module(1 of 7)
CS integrated w
ith structure
68
-
Anatomy of the Central Solenoid
69
6 coil modules in stack
Single CS module, 553 turns
The final stack
Conductor from Japan
-
Fabrication of the Central Solenoid
70
-
Tokamak Cooling Water System
A nuclear-grade safety system
Configuration:36 km (22 mi) of piping, ~108 major industrial components
Status:In fabrication: Drain tanksIn design: Integrated system and 230 pieces of equipment
Key Partner: ITER Organization
Key Vendors: AREVA Federal Services (design, Title III) with Joseph Oat Corporation and ODOM Industries (drain tank manufacture)
Drain tank heads from Odom Industries (Milford, OH) were delivered to Joseph Oat, Corp. for tank fabrication.
Drain tank assembly is underway at Joseph Oat, Corp.(Camden, NJ).
71
-
Tokamak Cooling Water System
Recent Achievements:
Drain tank fabrication progressing; First tank completed; Delivery to France in early CY 2015
Arrangements between US ITER and the ITER Organization to complete the final TCWS design, and procure and pre-fabricate piping on behalf of US ITER
Completed the design documentation review and transferred a hierarchical set of documents into a searchable database that shows the implementation requirements
Drain tank heads and shells are being fitted and assembled at Joseph Oat Corporation (Camden, NJ). Photo: US ITER
72
-
Toroidal Field Conductor
Specs:US contribution includes over 4 miles of conductor, which is constructed from 40 tons/over 6000
miles of niobium-tin superconducting strand 18 toroidal field coils being produced by partners
– Total magnetic energy of 41 gigajoules– Maximum magnetic field of 11.8 tesla
Status: In FabricationStrandProduction completed
CablingDummy cable completed 1st production cable completed
Jacketing 800 m dummy conductor completed Preparation for shipment is under way with
shipment planned for Fall 2014
Key Vendors: Luvata Waterbury, Inc. Oxford Superconducting TechnologiesNew England Wire Technologies, Inc.High Performance Magnetics
Strand at Luvata Waterbury, Inc. (Waterbury, CT)
73
-
Toroidal Field Conductor
Completed 800 m dummy conductor at High Performance Magnetics (Tallahassee, FL)
Completed batch of production cable at New England Wire Technologies(Lisbon, NH)
74
-
Ion Cyclotron Transmission Lines
Specs: Deliver up to 6 MW per transmission line from 8
transmitters to 2 power launchers Load-tolerant tuning over 40-55 MHz 1.5 km of transmission line
Status: In Preliminary Design
Key Vendors: Mega, Dielectric, Comet, General Atomics, National Instruments, Cincinnati Fan
Ion Cyclotron resonant loop test stand at ORNL
75
-
Electron Cyclotron Transmission Lines
Specs: Provide efficient power transfer from
170 GHz gyrotron sources to launchers Provide 20 MW of plasma heating
power 4 km of transmission line, with 24
sources to 56 feeds
Status: In Final Design
Key Vendors: General Atomics Dymenso Calabazas Creek ARMEC
76
A waveguide short gap expansion unit prototype permits expansion and contraction during cycles
-
Pellet Injection System
Specs:• Continuous and reliable H/D/T fueling and mode control• Frozen hydrogen pellets accelerated by high pressure gas• Extruder nozzle produces adjustable length pellets for fueling
or mode triggering
Status: In Preliminary DesignProcurement Arrangement signed with ITER Organization in December 2013
Key Contributor: Oak Ridge National Laboratory
77
-
Disruption Mitigation
78
Specs: Massive gas injection and shattered pellet injection will be used to limit impacts of plasma current disruptions and suppress the formation and deleterious effects of high-energy runaway electrons.
Status: In Preliminary Design• Massive gas injection developed
and tested on ASDEX-U, C-Mod, DIII-D and JET
• Radiation asymmetry characterized• Large valve developed for JET
being redesigned for ITER use• Shattered pellet injection tested on
DIII-D• Multiple barrel design being
developed for ITER use• ITER environment, delivery
distance and required reliability and response time is a design challenge
Experiment on DIII-D: Massive gas injection (MGI) results in reduction in upper strike point wall temperature and more uniform heat distribution on main chamber walls.
Unmitigated upward vertical displacement event (VDE)
Upward VDE mitigated with MGI 10 ms before VDE thermal quench time
-
Disruption Mitigation
79
Prototype 3-Barrel Shattered Pellet Injector
A prototype 3-barrel shattered pellet injector with 16 mm barrels is under development at ORNL. Shown here installed in vacuum chamber. Photo: US ITER
-
Tokamak Exhaust Processing
Specs:
• Separates hydrogen isotopes from non-hydrogen in the gas exhaust system
• Delivers hydrogen isotopes to EU’s hydrogen isotope separation system
Status: In Preliminary Design
Key Contributor: Savannah River National Laboratory
80
-
Steady State Electrical Network
Scope: 75% of the equipment used to supply electrical power to all conventional (steady state) loads in ITER facility, including
– HV Disconnect Switches– HV Circuit Breakers– HV Current Transformers– HV Potential Transformers– HV Surge Arresters– HV Substation Transformers– HV Substation Hardware– HV Control & Protection– Earthing Resistors– 22kV Switchgear
Status: In Fabrication & Delivery
Key Vendors:Hyundai Corporation (USA)Eaton CorporationABB, Inc.Siemen’s Industry, Inc.
Future location of substation
81
-
Steady State Electrical Network Scope
82
Equipment provided by US noted above (~ $30M).(Design, installation, and 25% of equipment provided by EU.)
-
What ITER Means for the US
Create, understand, and control a reactor-prototypical fusion plasma Demonstrate the scientific and technological feasibility
of a promising virtually inexhaustible and relatively clean energy source Position the US to provide fusion-reactor technology Create high-tech jobs and work in the US International partnership: working together toward a
global goal.
83
-
84
Thank you
-
85
Questions?
-
A few relevant websites
The DOE Office of Science: www.science.energy.govThe ITER Organization website: www.iter.orgThe US ITER Project Office: www.usiter.org
Los Alamos National Laboratory: www.lanl.govLawrence Livermore National Laboratory: www.llnl.govMIT Plasma Science and Fusion Center: www.psfc.mit.edu/Oak Ridge National Laboratory: www.ornl.govPrinceton Plasma Physics Laboratory: www.pppl.govSavanah River National Laboratory: www.srnl.doe.govGeneral Atomics: http://fusion.gat.com/global/Home
The Fire Place: http://fire.pppl.gov/
99
MIT Talk 12-10-2014