westfield state university · 2020. 2. 14. · copy & mail receiving mascac union photo gym...
TRANSCRIPT
WESTFIELD STATE UNIVERSITY
PARENZO & SCANLON HALLTown Hall
February 14, 2020
2
• Introductions
• Project Goals
• Program Space by Building
• Cost Challenges
• Project Scope Summary
• Next Steps
• Question and Answers
AGENDA
Westfield State University - Parenzo Hall – February 14, 2020
3
INTRODUCTIONS
Division of Capital Asset Management and Maintenance (DCAMM)• Mila Mendoza
Miller Dyer Spears Architects (MDS)• James Loftus – Principal • Nereyda Rodriguez – Project Manager• Kelsey Holmes – Project Architect
Westfield State University - Parenzo Hall – February 14, 2020
4
WORKING GROUPS
o Academic: Gabriel Aquino, Chair, Sociology Vanessa Diana, Director of Honors Program Hugh Jo, Chair, Political Science Megan Kennedy, Chair, Education Nora Padykula, Chair, Social Work Shoba Rajgopal, Chair, Ethnic and Gender Studies Emily Todd, Dean, College of Arts, Humanities and Social
Sciences Hugo M. Viera, Chair, Language and Culture Studies Nicholas P. Wojtowicz, Associate Director, Academic Technical
Services Chris Hirtle, Executive Director, Academic Information Services- University Media Services
o Student Success: Celeste Donovan, TRIO Christina Swaidan, Undergraduate Studies Azanda Seymour, Urban Education Laurie Simpson, Academic Advising Monique Lopez, Registrar Junior Delgado, Career Center Enrique Morales-Diaz, Dean of Faculty Scott Clark, Information Technology Services Maureen McCartney, Academic Advising Nicole West, Retention/Academic Achievement Sarah Lazare, Banacos Academic Center Catherine Savini, Reading & Writing
o CoLab: Brian Conz, Department of Geography and Regional
Planning Jennifer Hixon, Department of Health Sciences Susan Leggett, Office of the President Juline Mills (Co-Chair), College of EHHS John McDonald, Department of Environmental Science Tom Raffensperger (Co-Chair), Academic IS & Library
Director Kimberly Sherman, Department of Economics and
Management Tamara Smith, Sociology, Coordinator, Civic Engagement Jessica Tansey, Program Development and Outreach Chris Hirtle, Executive Director, Academic Information
Services- University Media Services
o Parenzo Working Group: Erica Broman, Institutional Advancement Celeste Donovan, Student Success Working Group Tricia Oliver, Office of the President Mila Mendoza, DCAMM Diane Prusank, Provost/Academic Affairs Tom Raffensperger, Co-chair Center for Innovation David Riggles, Facilities Maureen Socha, Facilities Steve Taksar, Administration and Finance Emily Todd, Chair, Academic Departments James Loftus, Principal MDS Architects Nereyda Rodriguez, Project Manager, MDS
Architects Kelsey Holmes, Project Architect, MDS Architects
Westfield State University - Parenzo Hall – February 14, 2020
5
Renovate Parenzo Hall to renew functionality and maximize use• Replace building systems
• Address accessibility, life-safety and building code issues
• Upgrade technology platform
• Removal of Mod Hall
• Modernize Dever Auditorium to provide accessibility, air conditioning & updated facilities
Expand and deepen programmatic collaborations• Create Center for Student Success as a lively hub for student services
• Foster innovation and collaboration between WSU and community partnerships through creation of CoLab
• Update Academic departments in Parenzo Hall (Political Science & Education)
• Move Honors from Mod Hall but not the other academic departments
• Flexible classrooms with robust technology
PROJECT GOALS
Westfield State University - Parenzo Hall – February 14, 2020
6
PARENZO REMAINS IN MOD HALL SCANLON
Academic Affairs
Dean of EHHS
Grants & Contracts
Institutional Research
International Studies
Facilities and Operations
Faculty Center
Lockshop
Language & Culture Studies
Social Work
EGST
Sociology
Center for Student Success
CoLab
Classrooms – 5 or 6
Education
Political Science
Media Services
Copy & Mail
Receiving
MASCAC
Union
Photo
Gym & Intramural Offices
Conferencing & Collaboration Spaces
UPDATED PROGRAM SPACE BY BUILDING
BATES
No work
Westfield State University - Parenzo Hall – February 14, 2020
7
July 2019
Project Budget $40,000,000
October 2019
December 2019
Total Project Cost Estimates
$41,688,252
COST CHALLENGES
Hazmat 4%
Exterior Envelope
6%
MEP/FP 21%
Site 0%
Interior Fit Out 18%
GC, GR, Contingencies, escalation, Permitting, &
Insurance 34%
Design Fees, Other Consultants, FF&E,
Advertising, Printing, etc. 17%
Westfield State University - Parenzo Hall – February 14, 2020
$61,356,373
$44,332,400 (cost per sf, not including swing space)
December 2019 cost breakdown
8
COST CHALLENGES
Westfield State University - Parenzo Hall – February 14, 2020
Strategies to get the project on budget
• Reduce the level of renovation to Scanlon Hall First Floor
• Do not reconfigure the Banacos area
• Do not reconfigure the Parenzo Basement
• Existing Academic Department Offices located in Mod Hall to remain
• Do not renovate Bates Hall
9
PARENZO LOWER LEVEL PLAN • No reconfiguration or reprograming of the spaces• All major mechanical, plumbing, fire protection, and electrical upgrades• Limited finish upgrades included paint, ceilings, and flooring
Westfield State University - Parenzo Hall – February 14, 2020
10
PARENZO FIRST FLOOR PLAN • Complete reconfiguration and renovation of the space to create the new CSSE & CoLab• All major mechanical, plumbing, fire protection, and electrical upgrades• No work in the gym except for the addition of sprinklers & no work in Banaco’s suite & adjacent bathrooms
Westfield State University - Parenzo Hall – February 14, 2020
POTENTIAL COPY/MAIL/
CENTRAL RECEIVING SWING SPACE
11
PARENZO DEVER AUDITORIUM• Make the auditorium fully accessible• All major mechanical, plumbing, fire protection, and electrical upgrades• New Audio Visual for auditorium including sound system, projection screen, and system control
Existing Condition:526 seats, 5 HC
New Plan:440-460 seats, 6 HC
Westfield State University - Parenzo Hall – February 14, 2020
12
PARENZO DEVER AUDITORIUM• Make the auditorium fully accessible• All major mechanical, plumbing, fire protection, and electrical upgrades• New Audio Visual for auditorium including sound system, projection screen, and system control
Westfield State University - Parenzo Hall – February 14, 2020
13
PARENZO SECOND FLOOR PLAN• Complete reconfiguration & renovation to create new Classrooms, Education & Political Science offices.• All major mechanical, plumbing, fire protection, and electrical upgrades
Westfield State University - Parenzo Hall – February 14, 2020
14
PARENZO EXTERIOR• Replace all windows with new storefront except the glass block at the gym and banacos, some doors, and new signage• Allowance for removal and replacement of brick jambs for PCB window removal
Westfield State University - Parenzo Hall – February 14, 2020
15
SCANLON LOWER LEVEL
Westfield State University - Parenzo Hall – February 14, 2020
POTENTIAL COPY/MAIL
SWING SPACE
16
SCANLON FIRST FLOORCreation of new Academic Affairs, Grants & Contracts, Institutional Research, Dean of EHHS, International Programs and Facilities Offices.
Westfield State University - Parenzo Hall – February 14, 2020
17
SCANLON SWING SPACE SECOND FLOOR
• Academic Achievement
• Academic Advising• Academic Retention• Banacos• Reading and Writing• Registrar• Trio• Urban Education
Westfield State University - Parenzo Hall – February 14, 2020
18
SCANLON SWING SPACE THIRD FLOOR
• Education• English Adjuncts• ICEI Studio• Media Services• Emergency
Management• Photo• Political Science• Union Office• Intramural Athletics
and Mascac
Westfield State University - Parenzo Hall – February 14, 2020
19
PROJECT SCHEDULE
February 14, 2020
Westfield State University - Parenzo Hall – February 14, 2020
20
NEXT STEPS & COMMUNITY INPUT
• February 18th – Introduction to Move Manager and review of move plan
• March/April 2020 – One-on-one meetings between Design Team and Chairs/Directors to review space layouts of department suites
• September 2020 – One-on-one meetings between Design Team and Chairs/Directors to review final furniture, fixtures, and equipment layouts.
• Fall 2020 – Town Hall
• Winter Break 2021 - Move out of Parenzo into temporary space in Scanlon Hall during construction
• Summer 2023 - Move into renovated Parenzo Hall
Westfield State University - Parenzo Hall – February 14, 2020
21
BREAKOUT SESSION
Westfield State University - Parenzo Hall – February 14, 2020