western orbital study phase 1 - citydeal-live.storage ... · this growth trend is likely to...
TRANSCRIPT
![Page 1: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/1.jpg)
Western Orbital Study Phase 1 Appendices Cambridge City Deal Partnership
September 2015
![Page 2: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/2.jpg)
Western Orbital Study
Appendices
Appendix A. SWOT Analysis, Planning Objectives and Background Information
A.1. SWOT Analysis and Planning Objectives Presentation
![Page 3: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/3.jpg)
Western Orbital Study
Appendices
![Page 4: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/4.jpg)
Western Orbital Study
Appendices
![Page 5: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/5.jpg)
Western Orbital Study
Appendices
![Page 6: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/6.jpg)
Western Orbital Study
Appendices
![Page 7: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/7.jpg)
Western Orbital Study
Appendices
A.2. Current Local Characteristics- Background Information
Social and demographic characteristics Population – At the time of the 2001 Census, the population within the study area stood at
approximately 59,001 and by 2011 had grown by approximately 28% to 75,600. This growth was accompanied by an increase in households from approximately 21,500 to over 27,000 over the same period. This growth trend is likely to increase as land is allocated for development under the Local Plans.
Employment – unemployment in the study area was 2.3% (2011), compared to 3% in Cambridgeshire and 3.2% in England and Wales. Employment within the study area is skewed towards highly skilled occupations and industries.
Car Ownership – 85% of households own a car, and 42% own two or more cars (2011). Overall car ownership is high in comparison to the average for England (74%) and Wales (77%).
Deprivation – 0.9% of the working age population claimed Job Seekers Allowance, compared to 2% across England and Wales, and 1.4% in Cambridgeshire (2011).
Journey to work (Census 2011)– travel demand data demonstrates that the car is the dominant mode of transport. Travel to work data for the study area, shows that typically around two-thirds of journeys to work are made by car. The largest use of bus is in Comberton (6%), Hardwick and Cambridge (5% respectively). Overall, walking and cycling comprises less than 10% of journeys made to work. However there is a considerable range in cycle and walking use between the areas.
Land use and environmental characteristics Relevant land use and environmental characteristics are summarised below. Many of which represent physical and legal constraints to any transport intervention within the corridor.
Water environment – the main water features are the River Cam, the wider flood plain and the associated network of drainage ditches, and groundwater. The attributes of these include water supply, transport and dilution of waste water, biodiversity, aesthetics, recreation, value to economy and conveyancing of flow and flood waters. The study area affected by potential improvements falls within the Environment Agency Flood Zone 3.
Biodiversity (SSSI, ancient woodland, protected species habitats) – there are several Sites of Special Scientific Interest within the study area, Caldecote Meadows, Hardwick Wood, Madingley Wood, Barrington Chalk Pit and Whittlesford Thriplow Hummocky Fields. Madingley Wood is also classified as ancient woodland. Byron’s Pool Local Nature reserve is located between Grantchester and Trumpington.
Green Belt – the submitted Cambridge and South Cambridgeshire Local Plans provide for the continued protection of the Cambridge Green Belt, the River Cam corridor and the setting of the historic city. The need for jobs and homes has to be considered within the context of a tightly-drawn Green Belt, which aims to prevent the city merging with the ring of necklace villages. Small Green Belt releases are permitted where exceptional circumstances can be argued.
High quality agricultural land-use – Agricultural land forms the greatest proportion of the land-use west of the M11, and also immediately adjacent to the motorway on the east. Much of the land in the area is some of the best and most versatile, in Grade 1 (Excellent) and Grade 2 (Very Good), the latter mostly between junctions 12-13 on the M11 and along the watercourses. The majority of the land is under intensive arable farming, typical of Grade 1 and 2 land.
Landscape Character – Cambridge and its surrounding landscape are located within Bedfordshire and Cambridgeshire Claylands National Character Area (NCA) as identified by the Countryside Agency’s National Character Map. The NCA is a broad, gently undulating, lowland plateau dissected by shallow river valleys that gradually widen as they approach The Fens NCA in the east.
Air quality – The boundary of the Air Quality Management Area is defined by the inner ring road and some extension along radial routes, including north of Junction 13 on the M11. As such the area in this study is outside this zone of influence.
Barton Road Rifle Range – is a MOD gallery range north of the A603 and to the west of the M11 near Cambridge. The range faces north and has a bridal path crossing the range.
Land owners – the land in the study area is under the ownership of a number of different landowners.
Key employment areas and trip attractors
Cambridge City Centre - Cambridge is the centre of a wider travel to work and housing market area. The city’s area of influence, both as a sub-regional centre and a major focus for employment, includes most of Cambridgeshire, and parts of West Suffolk, Bedfordshire, Essex and North
![Page 8: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/8.jpg)
Western Orbital Study
Appendices
Hertfordshire. It has a prosperous and dynamic economic base in high technology, research and development and related service sector industries. Cambridge and South Cambridgeshire provide over 152,800 employee jobs (ONS: Annual Business Inquiry 2008 cited in Nomis [online], 2013), approximately 88,100 of which are based within the city boundary. Cambridge’s total jobs figure is 100,000. Labour demand is higher than its available workforce, with a jobs-to-working age population ratio of 1.13 (ONS: Jobs Density 2008 cited in Nomis [online], 2013) leading to high levels of in-commuting.
Cambridge Biomedical Campus, Addenbrooke’s – Cambridge Biomedical Campus, located at the southern edge of Cambridge, is one of the largest centres of health science and medical research in the world and the largest such centre in Europe. It is an accredited UK academic health science centres and home to Addenbrooke’s Hospital and the university's medical school. There are approximately 7,000 healthcare professionals and research scientists working onsite. Astra Zeneca is moving its headquarters to the Cambridge Biomedical Campus where they will employ 2,000 people. A further 13,000 new jobs are planned for the site, which will also house the relocated Papworth Hospital. The campus will eventually have a working population of around 30,000, making it one of the largest biomedical sites in the world.
Cambridge Science Park – The Science Park has a concentration of science and technology related businesses, and has strong links with the nearby University of Cambridge. It is located 3 km to the north of Cambridge city centre, by junction 33 of the A14, and covers 152 acres. Over 100 companies operate onsite, employing c. 5,000 people.
Cambridge Northern Fringe East – development of the Cambridge Northern Fringe East area is proposed in the submitted Cambridge and South Cambridgeshire Local Plans. Employment from new development and the opening of the new Cambridge North railway station are likely to make this area a trip attractor.
University of Cambridge – Cambridge is formed from a variety of institutions which include 31 constituent colleges and over 100 academic departments which are organised into six Schools. The university occupies buildings throughout the town and is a major trip attractor.
A.3. Current Transport Characteristics- Background Information
Highways Key highways within the study area are the A10 and A603 which run from the south-west towards Cambridge city. The M11 also carries a large number of vehicles on a daily basis and borders Cambridge on the western side of the city, meeting the A10 at junction 11 and the A603 at junction 12.
The A10 and A603 are predominantly single carriageway, with small sections of dual carriageway immediately east and west of the M11.
Current traffic levels Figure -2 illustrates the traffic flow from Road Side Interview data (RSI) collected by Intelligent Data at a number of locations within the corridor.
The largest traffic flows for both the AM and PM peaks are between Junction 11 and Junction 12 on the M11, reaching up to 3500 vehicles on the road per hour in each direction. High flows are also present around each junction.
The A1309 experiences high traffic flows during the AM peak northbound to Addenbrooke’s Road (with up to 2000 vehicles on the road per hour) in addition to high traffic flows during the PM peak southbound to Junction 11.
Both Barton Road and the A603 experience slight AM peaks eastbound to the City Centre and slight PM peaks westbound, although these flows never exceed 1000 vehicles on the road per hour. . The Barton Road queue therefore could be due to the pedestrian crossing or interaction with Grange Road.
Grantchester Road shows no significant AM or PM peaks.
Bus services There is a lack of priority for bus services along the Western Orbital area. No buses travel along the M11, therefore bus services connecting peripheral locations are indirect and passengers usually need to travel into Cambridge and out again.
![Page 9: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/9.jpg)
Western Orbital Study
Appendices
Bus operations in the corridor are primarily conducted by Stagecoach and Whippet Coaches. Stagecoach provides regular city based and P&R services during the weekday peak period.
Table -1 shows the timetabled services operating in proximity to the M11.
Table -1 Bus Services in the Western Orbital Area
Route No
Route Frequency Operator
27 Guilden Morden-Cambridge Once daily Monday to Friday
Stagecoach
26 Cambridge-Royston Hourly Monday to Friday Stagecoach
31 Barley-Fowlmere-Cambridge 3 Afternoon Services Monday to Saturday
Whippet Coaches
Citi 7 Cambridge- Addenbrooke’s- Duxford/Saffron Walden
Every 20 mins Monday to Sunday
Stagecoach
UNI 4 Addenbrooke’s - City Centre - West Cambridge - Madingley Road Park & Ride
Every 20mins Stagecoach
75 Cambridge-Wrestlingworth 6 services a day
Monday to Friday
Whippet Coaches
18 Cambridge - Longstowe Hourly Monday to Saturday
Stagecoach
77 Madingley Road P&R – Newmarket Road P&R
Every 10mins Stagecoach
88 Trumpington P&R – City Centre Every 10mins Stagecoach
A number of fare and ticket variants exist for the above services ranging from the city based Dayrider ticket, the Dayrider plus ticket which serves areas slightly further away from Cambridge (see Figure -1) and a Megarider which allows unlimited travel on the Stagecoach network in Cambridgeshire. They are currently priced at £4.10 per day, £6.40 per day and £24 per week (July 2015).
![Page 10: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/10.jpg)
Western Orbital Study
Appendices
Figure -1 Stagecoach Dayrider / Dayrider Plus Zone (Stagecoach Website)
Park and Ride The Madingley Road and Trumpington Park and Ride sites intercept car users before they add to congestion in the city itself, but do not help to ease congestion on the routes into the city further afield.
The Madingley Road Park and Ride site is located on the northern side of the A1303 to the east of the M11 whilst the Trumpington Road Park and Ride site can be accessed via the A1309 (Hauxton Road), north of M11 Junction 11. Patronage figures available from the most recent Traffic Monitoring Report show a 5% decrease in patronage for Park and Ride in Cambridge between 2013 and 2014, potentially as a result of the introduction of a £1 parking charge.
![Page 11: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/11.jpg)
Western Orbital Study
Appendices
Table -2 Annual Park and Ride Patronage
2009 2010 2011 2012 2013
Madingley Rd/ Newmarket Rd 1,415,641 1,406,038 1,394,289 1,340,131 1,407,276
Trumpington Rd 896,088 871,817 934,019 917,491 907,852
TOTAL 2,311,729 2,277,855 2,328,308 2,257,622 2,315,128
Walking and cycling The eastern part of the study area, closer to the city, provides plenty of footpaths, pedestrian crossings and cycle lanes which help to promote walking and cycling, however in the western end of the corridor, footpaths become more fragmented and cycle ways are infrequent.
Walking also forms a key part of any public transport trip, providing a means of gaining access to the bus stop. According to National Census data, walking accounts for 7% of journeys to work nationally compared to 10% and 5% within Cambridge and South Cambridgeshire respectively.
The national average proportion of journeys to work by cycle is 2%. However, Cambridge and South Cambridgeshire have higher averages of 18% and 6% respectively. Currently, cycling may be discouraged by the high traffic volumes and perceived dangers due to narrow lanes and high speed vehicles along the corridor. As there is limited cycle infrastructure to the west, there may be a suppressed demand for longer distance cycle journeys.
![Page 12: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/12.jpg)
Western Orbital Study
Appendices
Figure -2 South Cambridgeshire Traffic Flows
![Page 13: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/13.jpg)
Western Orbital Study
Appendices
A.4. Current Problems and Background Information
Journey time variability Two roads were considered on the west side of Cambridge: the A10 and the A603. Journey times have been assessed on the A10 between the A505 and Fen Causeway, and on the A603 between the A1198 and Fen Causeway. They are both single lane carriageways for the majority of these lengths, with short sections of dual carriageway in the area around the M11.
A10
Figure -3 and Figure -4 present journey time variability for the A10 northbound and southbound in the AM Peak, while Figure -5 and Figure -6 present northbound and southbound journey time variability in the PM Peak. Locations of high journey time variability are:
AM PEAK
Trumpington Road between Fen Causeway and Brooklands Avenue – southbound;
A10 – Foxton Level Crossing – southbound;
A10 between Melbourne and the Moor– northbound;
A10 – Foxton Level Crossing – northbound;
From M11 Junction 11 to Trumpington Road junction with Fen Causeway, especially junction of Trumpington Road and Brooklands Avenue – northbound;
PM PEAK
From Trumpington Road junction with Fen Causeway to M11 Junction 11 – southbound;
A10 – Foxton Level Crossing – southbound;
A10 between Melbourne and the Moor– northbound;
A10 – Foxton Level Crossing – northbound;
A1309 junction with Shelford Road to Trumpington Road junction with Fen Causeway, especially junction of Trumpington Road and Brooklands Avenue – northbound.
![Page 14: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/14.jpg)
Western Orbital Study
Appendices
Figure -3 Journey Time Variability for A10, southbound, morning peak hour
![Page 15: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/15.jpg)
Western Orbital Study
Appendices
Figure -4 Journey Time Variability for A10, northbound, morning peak hour
![Page 16: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/16.jpg)
Western Orbital Study
Appendices
Figure -5 Journey Time Variability for A10, southbound, evening peak hour
![Page 17: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/17.jpg)
Western Orbital Study
Appendices
Figure -6 Journey Time Variability for A10, northbound, evening peak hour
![Page 18: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/18.jpg)
Western Orbital Study
Appendices
A603
Figures 7 and 8 present journey time variability for the A603 northbound and southbound in the AM Peak, while Figures 9 and 10 present northbound and southbound journey time variability in the PM Peak. Locations of high journey time variability are:
AM PEAK
A603 between Harlton and Orwell – southbound, AM Peak;
A603 between M11 junction 12 and Barton Road/Fen Causeway junction – northbound, AM Peak;
PM PEAK
Barton Road between Grange Road and M11 junction 12 – southbound, PM Peak;
Barton Road from Grantchester Road to Fen Causeway – northbound, PM Peak.
![Page 19: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/19.jpg)
Western Orbital Study
Appendices
Figure -7 Journey Time Variability for A603, southbound, morning peak hour
![Page 20: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/20.jpg)
Western Orbital Study
Appendices
Figure -8 Journey Time Variability for A603, northbound, morning peak hour
![Page 21: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/21.jpg)
Western Orbital Study
Appendices
Figure -9 Journey Time Variability for A603, southbound, evening peak hour
![Page 22: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/22.jpg)
Western Orbital Study
Appendices
Figure -10 Journey Time Variability for A603, northbound, evening peak hour
![Page 23: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/23.jpg)
Western Orbital Study
Appendices
Congestion Congestion has been assessed on the A10 and A603 corridors, based on neutral term-time weekday average traffic master speeds (2012-13). This data has been displayed visually Figure -11 and Figure -12.
The most congested areas on the A10 during the morning peak are:
Northbound section at the Foxton level crossing with average speeds below 30 mph;
High Street in Harston in both directions: northbound speed below 20 mph, southbound below 30 mph;
Section from M11 to Cambridge city centre.
The most congested areas on the A603 during the morning peak are:
Northbound section around Barton starting from the merge with Haslingfield Road with average speeds between around 10-20 mph;
Northbound from M11 junction 12 to Cambridge city centre with average speeds below 10 mph.
The most congested areas on the A10 during the evening peak are:
Northbound section at the Foxton level crossing with speeds below 30 mph;
Southbound section before Foxton with speeds below 20 mph;
High Street in Harston in both directions with speeds below 30 mph;
Section from M11 to Cambridge city centre.
There is minor congestion present on the A603 during the evening peak, predominantly around Barton.
![Page 24: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/24.jpg)
Western Orbital Study
Appendices
Figure -11 AM Peak average speeds (Traffic Master)
A603
A10
![Page 25: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/25.jpg)
Western Orbital Study
Appendices
Figure -12 PM Peak average speeds (Traffic Master)
A603
A10
![Page 26: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/26.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 26
Road Safety A summary of accidents for the period from January 2010 to April 2015 along the M11, Madingley Road (from the M11 junction to Northampton St), Barton Road (from the M11 junction roundabout to the Barton Rd sports ground) and Trumpington Road (from the M11 junction to the Trumpington P&R entrance) is shown in Table -3 classified as slight, serious or fatal dependent upon the nature of any injuries. sustained.
61 accidents were recorded along the M11 from junction 11 to junction 13. 44, 24 and 6 accidents were recorded on Madingley Road, Barton Road and Trumpington Road respectively. The majority of accidents involved motorised vehicles, with 35 accidents involved pedal cycles.
While the majority of recorded accidents were slight in nature, there have been a number of serious incidents.
Table -3 Location of accidents recorded on the Western Orbital Corridor 2010-2015
Section
Slig
ht
Seri
ous
Fata
l
Tota
l
Involv
ed
Ped
al
Cycle
s
M11 Junction 13 (incl. slip road and road section) 3 1 0 4 0
M11 Junction 12 to 13 5 1 0 6 0
M11 Junction 12 (incl. slip road and road section) 14 0 0 14 2
M11 Junction 11 to 12 6 1 0 7 0
M11 Junction 11 (incl. slip road and road section) 26 4 0 30 6
Madingley Road from M11 to Queen’s Road 38 6 0 44 19
Barton Road 19 5 0 24 7
Trumpington Road (from the M11 junction to the Trumpington P&R entrance)
5 1 0 6 1
![Page 27: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/27.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 27
A.5. SWOT Analysis Table
Strengths: Strong appetite for development at both ends of the link Orbital route possible because of the presence of the M11 Clearly defined catchment – internal city trips and trips along radial routes from south and south west
Weaknesses: Significant journey time variability along radial routes, east of M11 Lack of bus services and bus priority along radial routes from south and south west radials No P&R provision on the A603 Barton Road options are limited High cost – provision of structures over the M11 Capacity constraints on CGB at Trumpington
Opportunities: Intercept trips from the outset Enhance busway network Build on proposals for A428 Inbound queuing east of M11 acts as incentive to use alternative mode Potential for safeguarding off-line route alignment Current levels of cycle use on A603 Limited crossing points on M11 M11 Smart Motorway New Addenbrooke’s station Coordination with East West Rail Foxton Rail Station Removal of rat running through Grantchester
Threats: Unknown impact of traffic growth as economy grows Future travel patterns likely to become more diverse Unknown impacts of A14 improvements Two rail tracks between Cambridge and Great Shelford Unknown impact of future M11 traffic growth Visual intrusion Physical, legal and institutional constraints Statutory undertakers Public transport operators City Deal political and funding processes
![Page 28: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/28.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 28
Appendix B. Option Development
B.1. Option Maps The following maps correspond to those options selected for further assessment following the initial option sift (see Appendix B3 for the table used for the initial sift).
Option 1
A: New P&R M11 Junction 11 (Trumpington)
F: New bus link from New P&R M11 Junction 11 to guideway at Trumpington
M: New cycle link from Park & Cycle at Trumpington across M11
![Page 29: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/29.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 29
Option 5
A: New P&R M11 Junction 11 (Trumpington)
F: New bus link from New P&R M11 Junction 11 to guideway at Trumpington
M: New cycle link from Park & Cycle at Trumpington across M11
D: New P&R M11 Junction 12 (Barton)
E: Barton Road bus improvements
![Page 30: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/30.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 30
Option 7
A: New P&R M11 Junction 11 (Trumpington)
B: Busway / Online bus service on M11 to Junction 12
C: Busway / Online bus service to Junction 13 and Madingley Road
F: New bus link from new P&R M11 Junction 11 to guideway at Trumpington
H: Cycling improvements on Barton Road
I: Barton Road Park & Cycle
K: Bus service through Cambridge North-West
M: New cycle link from Park & Cycle at Trumpington across M11
![Page 31: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/31.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 31
Option 9
A: New P&R M11 Junction 11 (Trumpington)
B: Busway / Online bus service on M11 to Junction 12
C: Busway / Online bus service to Junction 13 + Madingley Road
F: New bus link from New P&R M11 Junction 11 to guideway at Trumpington
L: Cicular bus service via M11, Cambridge North-West, Science Park, City Centre, Addenbrooke’s.
M: New cycle link from Park & Cycle at Trumpington across M11
![Page 32: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/32.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 32
Option 13
A: New P&R M11 Junction 11 (Trumpington)
B: Busway / Online bus service on M11 to Junction 12
C: Busway / Online bus service to Junction 13 and Madingley Road
D: New P&R M11 Junction 12 (Barton)
F: New bus link from new P&R M11 Junction 11 to guideway at Trumpington
L: Circular bus service via M11, Cambridge North-West, Science Park, City Centre, Addenbrooke’s
M: New cycle link from Park & Cycle at Trumpington across M11
![Page 33: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/33.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 33
Option 16
A: New P&R M11 Junction 11 (Trumpington)
B: Busway / Online bus service on M11 to Junction 12
D: New P&R M11 Junction 12 (Barton)
F: New bus link from New P&R M11 Junction 11 to guideway at Trumpington
H: Cycling improvements on Barton Road
M: New cycle link from Park & Cycle at Trumpington across M11
![Page 34: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/34.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 34
Option 19
C: Busway / Online bus service on M11 to Junction 12
D: New P&R M11 Junction 12 Barton
H: Cycling improvements on Barton Road
I: Barton Road Park & Cycle
L: Circular bus service via M11, Cambridge North-West, Science Park, City Centre, Addenbrooke’s
![Page 35: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/35.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 35
Option 20
B: Busway / Online bus service on M11 to Junction 12
D: New P&R M11 Junction 12 (Barton)
F: New bus link from New P&R M11 Junction 11 to guideway at Trumpington
H: Cycling improvements on Barton Road
![Page 36: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/36.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 36
Option 22
A: New P&R M11 Junction 11 (Trumpington)
B: Busway / Online bus service on M11 to Junction 12
C: Busway / Online bus service to Junction 14 and Madingley Road
D: New P&R M11 Junction 12 (Barton)
F: New bus link from New P&R M11 Junction 11 to guideway at Trumpington
H: Cycling improvements on Barton Road
M: New cycle link from Park & Cycle at Trumpington across M11
![Page 37: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/37.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 37
Option 30
L: Orbital bus service via M11, Cambridge North-West, Science Park, City Centre, Addenbrooke’s.
![Page 38: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/38.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 38
B.2. Sector Map
![Page 39: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/39.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 39
![Page 40: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/40.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 40
Table -4 Sector Labels Key
Meplan Sector Sector Name
1 Grantchester
2 Trumpington
3 A603 Corridor
4 A10 Corridor
5 Royston
6 Shelford and Stapleford
7 M11 Corridor
8 Science Park and Business Park
9 Addenbrooke’s
10 Central Cambridge
11 Cambridge Railway Station
12 West Cambridge
13 East Cambridge
14 South Cambridge
15 North Cambridge
16 Newmarket Road, Airport and Cherry Hinton
17 A428 Corridor
0 Other
![Page 41: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/41.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 41
B.3. Option Sifting Summary Table
![Page 42: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/42.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 42
Intercept traffic crossing M11 to: A428 to: Orbital links between:
Demand count (2031 AM) 1529
338
491
843 363 41
387
216
City Centre West Camb Science Pk Biomedical Biomedical Science Pk-Biomed SP-W Camb Biomed-W Camb
Option Optioneering Exercise Planning Objectives Total
Demand % 2031 Demand PO1a Demand PO1b Demand PO1c Demand PO1d Demand PO3 Demand P04a Demand P04b Demand P04c Demand
1 A+F+M+busway 1 306 0 0 0 0 1 169 1 73 0 0 0 0 0 0 547 14%
2 A+B+E 1 306 0 0 0 0 0 0 0 0 0 0 0 0 0 0 306 8%
3 A+B+D+E 1 306 0 0 0 0 0 0 0 0 0 0 0 0 0 0 306 8%
4 A+B+C 0 0 1 68 0 0 0 0 0 0 0 0 0 0 0 0 68 2%
5 A+D+E+F+H+M 1 306 0 0 1 98 1 169 1 73 0 0 0 0 0 0 645 16%
6 A+B+C+K 0 0 1 68 1 98 0 0 0 0 0 0 1 39 0 0 205 5%
7 A+B+C+F+H+I+K+M 1 306 1 68 1 98 1 169 1 73 1 8 1 39 1 43 804 20%
8 A+B+C+L 0 0 1 68 1 98 1 169 1 73 1 8 1 39 1 43 498 12%
9 A+B+C+F+L+M 1 306 1 68 1 98 1 169 1 73 1 8 1 39 1 43 804 20%
10 A+B+D+K 0 0 0 0 0 0 0 0 0 0 0 0 1 39 0 0 39 1%
11 A+B+C+D+K 1 306 1 68 1 98 0 0 0 0 0 0 1 39 0 0 511 13%
12 A+B+D+L 0 0 0 0 0 0 0 0 0 0 1 8 1 39 0 0 47 1%
13 A+B+C+D+F+L+M 1 306 1 68 1 98 1 169 1 73 1 8 1 39 1 43 804 20%
14 B+C+F 0 0 0 0 0 0 0 0 1 73 0 0 0 0 1 43 116 3%
15 C+D 1 306 1 68 0 0 0 0 0 0 0 0 0 0 0 0 374 9%
16 A+B+D+F+H+M 1 306 0 0 0 0 1 169 1 73 0 0 0 0 1 43 591 15%
17 D+E 1 306 0 0 0 0 0 0 0 0 0 0 0 0 0 0 306 8%
18 C+D+K 1 306 1 68 1 98 0 0 0 0 0 0 1 39 0 0 511 13%
19
C+D+H+L
1 306 1 68 1 98 1 169 1 73 1 8 1 39 1 43 804 20%
20 B+D+F+H 1 306 0 0 1 98 1 169 1 73 0 0 0 0 1 43 689 17%
21 C+G 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0%
22 A+B+C+D+F+H+M 1 306 1 68 0 0 1 169 1 73 0 0 0 0 1 43 659 16%
23 E+G 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0%
24 H+I 1 306 0 0 0 0 0 0 0 0 0 0 0 0 0 0 306 8%
25 J+M 1 306 0 0 0 0 1 169 0 0 0 0 0 0 0 0 475 12%
27 K 0 0 0 0 0 0 0 0 0 0 0 0 1 39 0 0 39 1%
28 A+B+C+F+K 1 306 1 68 1 98 1 169 1 73 1 8 1 39 1 43 804 20%
30 L 0 0 0 0 0 0 0 0 0 0 1 8 1 39 1 43 90 2%
33 N 1 306 0 0 1 98 1 169 0 0 1 8 0 0 0 0 581 14%
34 Citi 4 bus (Do Min) 1 306 0 0 0 0 0 0 1 73 0 0 1 39 0 0 418 10%
![Page 43: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/43.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 43
B.4. Option Descriptions
Option 1 (elements A, F & M)
A. New P&R M11 Junction 11 (Trumpington) - instead of or as well as existing P&R F. New bus link from New P&R M11 Junction 11 to guided busway at Trumpington M. New cycle link from Park & Cycle at Trumpington across M11
A new Park and Ride site would be located near Junction 11 (Trumpington) of the M11 in addition or as a replacement to the existing Park and Ride site and would mean traffic from M11 Northbound and A10 would not have to cross the M11 Junction 11 to access the Park and Ride. A bus link (using existing or new infrastructure) would run from the new Park and Ride site to the guided busway at Trumpington. This link would provide priority for buses from the new Park and Ride site across Junction 11 and adjacent to A1309 Hauxton Road, avoiding queuing traffic and enabling access to the existing Busway for journeys to Addenbrooke’s, City Centre and the Science Park. Furthermore, a new cycle link would be constructed from the Park and Ride at Trumpington and across the M11. However, this option does not intercept traffic from A603/B1064 at Junction 12, and may result in the duplication of the Trumpington Park and Ride. Additionally, it does not offer public transport alternatives for travel between peripheral employment hubs (for example, it does not provide services between Cambridge West and the Biomedical campus).
Total travel time savings:
AM: 0 hours
PM: 0 hours
Variations:
The most likely configuration is to utilise elements A, M and F2. Option F2 involves the installation of traffic signals (to avoid collisions) on an existing 3.5 m wide accommodation bridge north of Junction 11. Variations on this plan include the building of a new bridge (F1) or linking the Park and Ride to the A1309 via a signalised junction and using the existing Junction 11 roundabout (F3).
Assumptions:
It is assumed that the current user of the existing accommodation bridge would consent to sharing its use, and that development within the Green Belt (for the link road) is permitted.
![Page 44: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/44.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 44
Option 5 (elements A, D, E, F, H & M)
A. New P&R M11 Junction 11 (Trumpington) - instead of or as well as existing P&R D. New P&R M11 Junction 12 Barton E. Barton Road bus improvements (very constrained) F. New bus link from New P&R M11 Junction 11 to guided busway at Trumpington H. Cycling improvements on Barton Road M. New cycle link from Park & Cycle at Trumpington across M11
New Park and Ride sites would be located near Junction 11 (Trumpington) of the M11 and near Junction 12 (Barton) in addition or as a replacement to the existing Park and Ride site. The site at Junction 11 would intercept traffic from M11 Northbound and A10 without needing to cross the M11 Junction 11 to access the Park and Ride. A bus link (using existing or new infrastructure) would run from the new Park and Ride site to the guided busway at Trumpington. There would be priority for buses from the new Park and Ride site across Junction 11 and adjacent to A1309 Hauxton Road avoiding queuing traffic and enabling access to the existing Busway for journeys to Addenbrooke’s, City Centre and the Science Park. Furthermore, a new cycle link would be constructed from the Park and Ride at Trumpington and across the M11. Additionally, bus and cycle link improvements would take place on Barton Road. Option 5 intercepts traffic from A603/B1046 heading for the city centre and Science Park in addition to southbound M11 traffic which cannot access Madingley Road Park and Ride. However, it does not offer public transport alternatives for travel between peripheral employment hubs (for example, it does not provide services between Cambridge West and the Biomedical campus). There would be no services from the Barton Road Park and Ride site to the peripheral hubs, and there is the risk of potential duplication of the Trumpington Park and Ride.
Total travel time savings:
AM: 106 hours
PM: 215 hours
Variations:
The most likely configuration is to utilise element F2. Option F2 involves the installation of traffic signals (to avoid collisions) on an existing 3.5 m wide accommodation bridge north of Junction 11. Variations on this plan include the building of a new bridge (F1) or linking the Park and Ride to the A1309 via a signalised junction and using the existing Junction 11 roundabout (F3).
Assumptions:
It is assumed that the current user of the existing accommodation bridge would consent to sharing its use, and that development within the Green Belt (for the link road) is permitted.
![Page 45: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/45.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 45
Option 7 (elements A, B, C, F, H, I, K & M)
A. New P&R M11 Junction 11 (Trumpington) B. Bus link & service parallel to M11 to Junction 12 C. Bus link & service to Junction 13 (+ Madingley Road improvements) F. New bus link from New P&R M11 Junction 11 to guided busway at Trumpington H. Cycling improvements on Barton Road I. Barton Road Park & Cycle K. Bus service through Cambridge NW (say, to Cambridge North station) M. New cycle link from Park & Cycle at Trumpington across M11
New Park and Ride site would be located near Junction 11 (Trumpington) of the M11 in addition or as a replacement to the existing Park and Ride site and would mean traffic from M11 Northbound and A10 would not have to cross the M11 Junction 11 to access the Park and Ride. There would be a bi-directional Western Orbital bus service running between Addenbrooke’s and Cambridge North Station, with intermediate stops at the existing Trumpington Pak and Ride, the new Junction 11 Park and Ride, Cambridge West, Madingley Road Park and Ride, Cambridge NW, Darwin Green, and the Science Park. A bus link (using existing or new infrastructure) would run from the new Park and Ride site to the guided busway at Trumpington. There would be priority for buses from the new Park and Ride site across Junction 11 and adjacent to A1309 Hauxton Road avoiding queuing traffic and enabling access to the existing Busway for journeys to Addenbrooke’s, City Centre and the Science Park. Bus links and services would be provided parallel to the M11 to Junction 12, through to Cambridge NW and at Junction 13. Cycling improvements would be made on Barton Road, including the introduction of a Park and Cycle at Junction 12. An orbital bus connection between peripheral employment hubs and the Cambridge North station would be established. There would also be the potential to run some services from Madingley Mulch Park and Ride (proposed as part of the A428 options) via the bus links to the Biomedical Campus. However, this option would not directly intercept all A601/B1046 traffic.
Total travel time savings:
AM: 94 hours
PM: 169 hours
Variations:
The most likely configuration is to utilise elements A, M and F2. Option F2 involves the installation of traffic signals (to avoid collisions) on an existing 3.5 m wide accommodation bridge north of Junction 11. Variations on this plan include the building of a new bridge (F1) or linking the Park and Ride to the A1309 via a signalised junction and using the existing Junction 11 roundabout (F3).
To provide uncongested bus travel on the M11, the current assumption is that the only infrastructure required will be widening the slip roads to provide bus priority at these locations, which is where congestion is worst (options B3 & C3). This assumption remains to be tested, and other alternatives include the introduction of an offline busway (C1), buses travelling on lane 1 (C4) or introducing a new bus lane by widening the entire stretch of the motorway between junctions (C2).
Assumptions:
It is assumed that the current user of the existing accommodation bridge would consent to sharing its use, and that development within the Green Belt (for the link road) is permitted.
There will be a bus route available for use through the Cambridge North West and Darwin Green developments.
The park and cycle location is shown east of Junction 12 of the M11, but it may be beneficial to locate it west of the junction to avoid queues at this location. This assumption will be tested in more detail during phase 2 of the study.
![Page 46: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/46.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 46
To provide uncongested bus travel on the M11, the current assumption is that the only infrastructure required will be widening the slip roads to provide bus priority at these locations, which is where congestion is worst. This assumption remains to be tested as part of phase 2.
![Page 47: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/47.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 47
Option 9 (elements A, B, C, F, L & M)
A. New P&R M11 Junction 11 (Trumpington) B. Bus link & service parallel to M11 to Junction 12 C. Bus link & service to Junction 13 (+ Madingley Road improvements) F. New bus link from New P&R M11 Junction 11 to guided busway at Trumpington L. Orbital bus service via M11, Cambridge NW, Science Park, CC, Addenbrooke’s M. New cycle link from Park & Cycle at Trumpington across M11
A new Park and Ride site would be located near Junction 11 (Trumpington) of the M11 in addition or as a replacement to the existing Park and Ride site and would mean traffic from M11 northbound and A10 would not have to cross the M11 Junction 11 to access the Park and Ride. A bus link (using existing or new infrastructure) would run from the new Park and Ride site to the guided busway at Trumpington. There would be priority for buses from the new Park and Ride site across Junction 11 and adjacent to A1309 Hauxton Road avoiding queuing traffic and enabling access to the existing Busway for journeys to Addenbrooke’s, City Centre and the Science Park. Bus links and services would be established parallel to M11 to Junction 12, and to Junction 13. An orbital bus service via M11, Cambridge NW, City Centre and Addenbrooke’s would also be introduced. Option 9 provides orbital connection between peripheral employment hubs, all three of which would be connected through a circular bus service. The scheme also holds the potential to run some services from Madingley Mulch Park and Ride (proposed as part of the A428 options) via the bus links to the Biomedical Campus. It does not, however, directly intercept all A603/B1406 traffic, and the circular service could prove difficult to operate reliably.
Total travel time savings:
AM: 265 hours
PM: 457 hours
Variations:
The most likely configuration for F is to utilise element F2. Option F2 involves the installation of traffic signals (to avoid collisions) on an existing 3.5 m wide accommodation bridge north of Junction 11. Variations on this plan include the building of a new bridge (F1) or linking the Park and Ride to the A1309 via a signalised junction and using the existing Junction 11 roundabout (F3).
To provide uncongested bus travel on the M11, the current assumption is that the only infrastructure required will be widening the slip roads to provide bus priority at these locations, which is where congestion is worst (options B3 & C3). This assumption remains to be tested, and other alternatives include the introduction of an offline busway (C1), buses travelling on lane 1 (C4) or introducing a new bus lane by widening the entire stretch of the motorway between junctions (C2).
Assumptions:
It is assumed that the current user of the existing accommodation bridge would consent to sharing its use, and that development within the Green Belt is permitted.
To provide uncongested bus travel on the M11, the current assumption is that the only infrastructure required will be widening the slip roads to provide bus priority at these locations, which is where congestion is worst. This assumption remains to be tested as part of phase 2.
![Page 48: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/48.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 48
Option 13 (elements A, B, C, D, F, L & M)
A. New P&R M11 Junction 11 (Trumpington) B. Bus link & service parallel to M11 to Junction 12 C. Bus link & service to Junction 13 (+ Madingley Road improvements) D. New P&R M11 Junction 12 Barton F. New bus link from New P&R M11 Junction 11 to guided busway at Trumpington L. Orbital bus service via M11, Cambridge NW, Science Park, CC, Addenbrooke’s M. New cycle link from Park & Cycle at Trumpington across M11
New Park and Ride sites would be located on Junction 12 near Barton and near Junction 11 (Trumpington) of the M11 in addition or as a replacement to the existing Park and Ride site and would mean traffic from M11 Northbound and A10 would not have to cross the M11 Junction 11 to access the Park and Ride. A bus link (using existing or new infrastructure) would run from the new Park and Ride site to the guided busway at Trumpington. There would be priority for buses from the new Park and Ride site across Junction 11 and adjacent to A1309 Hauxton Road, avoiding queuing traffic and enabling access to the existing Busway for journeys to Addenbrooke’s, City Centre and the Science Park. Bus links and services would be established parallel to M11 to Junction 12, and to Junction 13. An orbital bus service via M11, Cambridge NW, City Centre and Addenbrooke’s would also be introduced. Option 13 provides orbital connection between peripheral employment hubs, all three of which would be connected through a circular bus service. The scheme also holds the potential to run some services from Madingley Mulch Park and Ride (proposed as part of the A428 scheme) via the bus links to the Biomedical Campus. Additionally, it intercepts traffic coming in from the A603/B1046 in addition to Southbound traffic which cannot access Madingley Rise Park and Ride. However, serving Barton Road Park and Ride would require an extra stop/diversion for orbital services.
Total travel time savings:
AM: 278 hours
PM: 492 hours
Variations:
The most likely configuration for F is to utilise element F2. Option F2 involves the installation of traffic signals (to avoid collisions) on an existing 3.5 m wide accommodation bridge north of Junction 11. Variations on this plan include the building of a new bridge (F1) or linking the Park and Ride to the A1309 via a signalised junction and using the existing Junction 11 roundabout (F3).
To provide uncongested bus travel on the M11, the current assumption is that the only infrastructure required will be widening the slip roads to provide bus priority at these locations, which is where congestion is worst (options B3 & C3). This assumption remains to be tested, and other alternatives include the introduction of an offline busway (C1), buses travelling on lane 1 (C4) or introducing a new bus lane by widening the entire stretch of the motorway between junctions (C2).
Assumptions:
It is assumed that the current user of the existing accommodation bridge would consent to sharing its use, and that development within the Green Belt is permitted.
To provide uncongested bus travel on the M11, the current assumption is that the only infrastructure required will be widening the slip roads to provide bus priority at these locations, which is where congestion is worst. This assumption remains to be tested as part of phase 2.
![Page 49: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/49.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 49
Option 16 (elements A, B, D, F, H & M)
A. New P&R M11 Junction 11 (Trumpington) B. Bus link & service parallel to M11 to Junction 12 D. New P&R M11 Junction 12 Barton F. New bus link from New P&R M11 Junction 11 to guided busway at Trumpington H. Cycling improvements on Barton Road M. New cycle link from Park & Cycle at Trumpington across M11
New Park and Ride sites would be located on Junction 12 near Barton and near Junction 11 (Trumpington) of the M11in addition or as a replacement to the existing Park and Ride site and would mean traffic from M11 Northbound and A10 would not have to cross the M11 Junction 11 to access the Park and Ride. A bus link (using existing or new infrastructure) would run from the new Park and Ride site to the guided busway at Trumpington. There would be priority for buses from the new Park and Ride site across Junction 11 and adjacent to A1309 Hauxton Road, avoiding queuing traffic and enabling access to the existing Busway for journeys to Addenbrooke’s, City Centre and the Science Park. Furthermore, a new cycle link would be constructed from the Park and Ride at Trumpington and across the M11. A new bus link from the new Park and Ride at Junction 11 (Trumpington) to the guided busway at Trumpington would be established. Cycling improvements would also be made on Barton Road. Option 16 intercepts traffic coming from the A603/B1604 and Southbound M11 traffic which cannot access Madingley Rise Park and Ride, offering direct services from Barton Road Park and Ride to the Biomedical Campus (and the City Centre via the pre-existing busway). However, this option does not offer uncongested public transport alternatives for trips to peripheral employment hubs from the M11/A10, or for orbital trips between peripheral employment hubs. Additionally, orbital bus capacity is likely to be limited as services may have a high degree of interaction with general traffic between Junctions 12 and 13, with adverse impacts on journey times and reliability. There is also the risk of the potential duplication of the Trumpington Park and Ride. Although Option 16 intercepts the A603/B1604 traffic, there is no direct link to the City Centre, Cambridge NW or the Science Park.
Total travel time savings:
AM: 0 hours
PM: 0 hours
Variations:
The most likely configuration for F is to utilise element F2. Option F2 involves the installation of traffic signals (to avoid collisions) on an existing 3.5 m wide accommodation bridge north of Junction 11. Variations on this plan include the building of a new bridge (F1) or linking the Park and Ride to the A1309 via a signalised junction and using the existing Junction 11 roundabout (F3).
To provide uncongested bus travel on the M11, the current assumption is that the only infrastructure required will be widening the slip roads to provide bus priority at these locations, which is where congestion is worst (option B3). This assumption remains to be tested, and other alternatives include the introduction of an offline busway (B1), buses travelling on lane 1 (B4) or introducing a new bus lane by widening the entire stretch of the motorway between junctions (B2).
Assumptions:
It is assumed that the current user of the existing accommodation bridge would consent to sharing its use, and that development within the Green Belt is permitted.
To provide uncongested bus travel on the M11, the current assumption is that the only infrastructure required will be widening the slip roads to provide bus priority at these locations, which is where congestion is worst. This assumption remains to be tested as part of phase 2.
![Page 50: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/50.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 50
Option 19 (elements C, D, H & L)
C. Bus link and service between Junctions 12 and 13 (+ Madingley Road improvements) D. New P&R M11 Junction 12 Barton H. Cycling improvements on Barton Road L. Circular bus service via Cambridge NW, Science Park, city centre and Biomedical campus (running on M11 between Junctions 11 and 12).
A bus link and service between Junctions 12 and 13 of the M11 would be established. There would be a new Park and Ride site on Junction 12 of the M11 near Barton, and a circular bus service via Cambridge NW, the Science Park, the City Centre and the Biomedical campus running on the M11 between Junctions. Cycling improvements would also be made on Barton Road. This scheme intercepts traffic from A603/B1604 and M11/A10 South heading for Cambridge NW and the Science Park (and potentially the City Centre). All three of the peripheral employment hubs would be linked via the circular bus service (albeit via a longer route than the M11 corridor, or subject to M11 congestion). Option 19 intercepts Southbound traffic from the M11 which cannot access the Madingley Road Park and Ride. However, this option provides no benefits for M11/A10 South traffic heading for the Biomedical Campus and this traffic is unlikely to travel via Barton Road Park and Ride to access the City Centre. Additionally, orbital bus capacity is likely to be limited as services may have a high degree of interaction with general traffic with adverse impacts on journey times and reliability. The option has limited benefits for A428 and A603/B1406 traffic heading for the Biomedical Campus as there would not be priority for services on the M11 between Junctions 11 and 12.
Total travel time savings:
AM: 203 hours
PM: 308 hours
Variations:
To provide uncongested bus travel on the M11, the current assumption is that the only infrastructure required will be widening the slip roads to provide bus priority at these locations, which is where congestion is worst (option C3). This assumption remains to be tested, and other alternatives include the introduction of an offline busway (C1), buses travelling on lane 1 (C4) or introducing a new bus lane by widening the entire stretch of the motorway between junctions (C2).
Assumptions:
To provide uncongested bus travel on the M11, the current assumption is that the only infrastructure required will be widening the slip roads to provide bus priority at these locations, which is where congestion is worst. This assumption remains to be tested as part of phase 2.
![Page 51: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/51.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 51
Option 20 (elements B, D, F, H & Busway)
B. Bus link/service between M11 Junctions 11 and 12. D. New P&R M11 Junction 12 Barton F. New bus link from New P&R M11 Junction 11 to guided busway at Trumpington H. Cycling improvements on Barton Road
New bus links would be established on the M11 between Junction 11 and Junction 12 and between a new Junction 11 M11 Park and Ride site to the guided busway at Trumpington. Another new Park and Ride site at Junction 12 of the M11 near Barton would be introduced. Additionally, cycling improvements would be made on Barton Road. Option 20 intercepts the A603/B1406 traffic bound for the Biomedical Campus or the City Centre (via the existing guided busway) and also the Southbound M11 traffic which cannot access the Madingley Rise Park and Ride. However, this option does not provide benefits for M11/A10 South or A428 traffic and does not connect the peripheral employment hubs via uncongested services. From the Barton Road Park and Ride there is no direct link to the City Centre, which is the area that sees the highest demand.
Total travel time savings:
AM: 0 hours
PM: 0 hours
Variations:
The most likely configuration is to utilise element F2, which involves the installation of traffic signals (to avoid collisions) on an existing 3.5 m wide accommodation bridge north of Junction 11, and B3 in which only online slips are widened. Variations on this plan include the building of a new bridge (F1) or linking the Park and Ride to the A1309 via a signalised junction and using the existing Junction 11 roundabout (F3). Other alternatives for travel on the M11 include the introduction of an offline busway (B1), buses travelling on lane 1 (B4) or introducing a new bus lane by widening the entire stretch of the motorway between junctions (B2).
Assumptions
It is assumed that the current user of the existing accommodation bridge would consent to sharing its use, and that development within the Green Belt is permitted.
To provide uncongested bus travel on the M11, the current assumption is that the only infrastructure required will be widening the slip roads to provide bus priority at these locations, which is where congestion is worst. This assumption remains to be tested as part of phase 2.
![Page 52: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/52.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 52
Option 22 (elements A, B, C, D, F, H & M)
A. New P&R M11 Junction 11 (Trumpington) B. Bus link & service parallel to M11 to Junction 12 C. Bus link & service to Junction 13 (+ Madingley Road improvements) D. New P&R M11 Junction 12 Barton F. New bus link from New P&R M11 Junction 11 to guided busway at Trumpington H. Cycling improvements on Barton Road M. New cycle link from Park & Cycle at Trumpington across M11
New Park and Ride sites would be introduced at Junction 11 of the M11 (Trumpington) and Junction 12 of the M11 (Barton). New bus links and services would be established parallel to the M11 at Junction 12, Junction 13 and from the new Park and Ride on the M11 at Junction 11 to the guided busway at Trumpington. Cycling improvements would be made on Barton Road, in addition to a new cycle link from the Park and Cycle at Trumpington across the M11. Option 22 intercepts traffic coming from A603/B1604 and M11/A10 bound for Cambridge NW, the City Centre and the Biomedical Campus, as well as Southbound M11 traffic which cannot access Madingley Rise Park and Ride. The option provides orbital bus connection between peripheral employment hubs. There is also potential to run some services from Madingley Mulch Park and Ride (proposed as part of the A428 scheme) via the bus links to the Biomedical Campus. Furthermore, the option provides opportunities for cycle trips to employment sites from Park and Ride Sites. However, Option 22 does not provide a link to the Science Park for A603/B1406, and M11/A10 South traffic, although connection to Cambridgeshire Guided Busway could be an option from the South and South-West via the Biomedical Campus, Cambridge Station and City Centre. The option does not provide a link between the Science Park and Cambridge North West.
Total travel time savings:
AM: 0 hours
PM: 0 hours
Variations:
The most likely configuration for F is to utilise element F2. Option F2 involves the installation of traffic signals (to avoid collisions) on an existing 3.5 m wide accommodation bridge north of Junction 11. Variations on this plan include the building of a new bridge (F1) or linking the Park and Ride to the A1309 via a signalised junction and using the existing Junction 11 roundabout (F3).
To provide uncongested bus travel on the M11, the current assumption is that the only infrastructure required will be widening the slip roads to provide bus priority at these locations, which is where congestion is worst (option C3). This assumption remains to be tested, and other alternatives include the introduction of an offline busway (C1), buses travelling on lane 1 (C4) or introducing a new bus lane by widening the entire stretch of the motorway between junctions (C2).
Assumptions
It is assumed that the current user of the existing accommodation bridge would consent to sharing its use, and that development within the Green Belt is permitted.
To provide uncongested bus travel on the M11, the current assumption is that the only infrastructure required will be widening the slip roads to provide bus priority at these locations, which is where congestion is worst. This assumption remains to be tested as part of phase 2.
![Page 53: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/53.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 53
Option 30 (element L)
L. Circular bus service via M11, Cambridge NW, Science Park, city centre, Biomedical campus and M11
A circular bus service via the M11, Cambridge NW, the Science Park, the City Centre, the Biomedical Campus and the M11. This option provides a circular bus service that would connect all the key peripheral employment sites and the city centre. However, buses would run with general traffic on the M11 and throughout most of the route and therefore be subject to any delays on the M11 and through the city centre, affecting journey times and journey time reliability.
Total travel time savings:
AM: 172 hours
PM: 263 hours
Variations:
N/A
Assumptions:
N/A
![Page 54: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/54.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 54
B.5. Option List
No. Brief description Variants
1 New Park & Ride site west of the M11 at Junction 11 in Trumpington. Associated cycle and guideway links into city centre.
On-line/off-line busway links
Bus prioritisation on existing infrastructure
Infrastructure improvements – use of accommodation bridge
2 New Park & Ride site west of the M11 at Junction 11 in Trumpington. Bus service (north) along the M11 route to junction 12 with improvements along Barton Road into the City.
M11 route on-line, off-line options
Bus route on East/West side of M11
3 New Park & Ride site west of the M11 at Junction 11 in Trumpington. Bus service (north) along the M11 route to junction 12 with improvements along Barton Road into the City. This option includes an additional Park & Ride site at Junction 12.
Position of P&R along A603 (East/West of M11)
M11 route on-line, off-line options
Bus route on East/West side of M11
Future of P&R’s in other areas/capacity
4 New Park & Ride site west of the M11 at Junction 11 in Trumpington. Bus service (north) along the M11 route to junction 12 and 13.
M11 route on-line, off-line options
Bus route East/West side of M11
Intersections/interactions with existing infrastructure.
5 New Park & Ride site west of the M11 at Junction 11 –Trumpington and Junction 12 – Barton Road. Associated cycle and guideway links into city centre
On-line/off-line busway links
Bus prioritisation on existing infrastructure
Infrastructure improvements
6 New Park & Ride site west of the M11 at Junction 11 in Trumpington. Bus service (north) along the M11 route to junction 12 and 13. Linking with new bus service through NW Cambridge development to the New Rail Station (Cambridge North).
M11 route on-line, off-line options
Bus route East/West side of M11
Intersections/interactions with existing infrastructure.
Routing and times of services
7 New Park & Ride site west of the M11 at Junction 11 in Trumpington. Associated guideway links into city centre. Bus service (north) along the M11 route to junction 12 and 13, with the addition of a Park & Cycle site and cycle lane improvements along Barton Road. Linking with new bus service through NW Cambridge development to the New Rail Station (Cambridge North).
M11 route on-line, off-line options
Bus route East/West side of M11
Intersections/interactions with existing infrastructure.
Routing and times of services
Position of P&R and P&C sites
8 New Park & Ride site west of the M11 at Junction 11 in Trumpington. Bus service (north) along the M11 route to junction 12 and 13. Linking with new bus service through NW Cambridge development via the New Rail Station (Cambridge North) continuing through city to Addenbrooke’s.
M11 route on-line, off-line options
Bus route East/West side of M11
Intersections/interactions with existing infrastructure.
Routing and times of services
9 New Park & Ride site west of the M11 at Junction 11 in Trumpington. Associated cycle and guideway links into city centre. Bus service (north) along the M11 route to junction 12 and 13. Linking with new bus service through NW Cambridge development via the New Rail Station (Cambridge North) continuing through city to Addenbrooke’s
On-line/off-line busway links
Bus prioritisation on existing infrastructure
Infrastructure improvements – use of accommodation bridge
Bus route East/West side of M11
Intersections/interactions with existing infrastructure.
Routing and times of services
10 New Park & Ride site west of the M11 at Junction 11 in Trumpington. Bus service (north) along the M11 route to junction 12 with improvements along Barton Road into the City. This option includes an additional Park & Ride site at Junction 12. New bus service through NW Cambridge development to the New Rail Station (Cambridge North).
Position of P&R along A603 (East/West of M11)
M11 route on-line, off-line options
Bus route on East/West side of M11
Future of P&R’s in other areas/capacity
Routing and times of services
![Page 55: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/55.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 55
No. Brief description Variants
11 New Park & Ride site west of the M11 at Junction 11 in Trumpington. Bus service (north) along the M11 route to junction 12 and 13, With additional P&R site on A603/Barton Road. Linking with new bus service through NW Cambridge development to the New Rail Station (Cambridge North).
M11 route on-line, off-line options
Bus route East/West side of M11
Intersections/interactions with existing infrastructure.
Routing and times of services
12 New Park & Ride site west of the M11 at Junction 11 in Trumpington. Bus service (north) along the M11 route to junction 12 with improvements along Barton Road into the City. This option includes an additional Park & Ride site at Junction 12. New bus service through NW Cambridge development via the New Rail Station (Cambridge North) continuing through city to Addenbrooke’s
Position of P&R along A603 (East/West of M11)
M11 route on-line, off-line options
Bus route on East/West side of M11
Future of P&R’s in other areas/capacity
Routing and times of services
13 New Park & Ride site west of the M11 at Junction 11 in Trumpington. Associated guideway links into city centre. Bus service (north) along the M11 route to junction 12 and 13, With additional P&R site on A603/Barton Road. New bus service through NW Cambridge development via the New Rail Station (Cambridge North) continuing through city to Addenbrooke’s
Position of P&R along A603 (East/West of M11)
M11 route on-line, off-line options
Bus route on East/West side of M11
Future of P&R’s in other areas/capacity
Routing and times of services
14 New busway/services running along M11 route using Trumping to and Madingley roads to access city
M11 route on-line, off-line options
Service distribution
Links into City
15 New Park & Ride at Barton Road/Junction 12 site with bus route running between Junction 12 and 13
Position of P&R along A603 (East/West of M11)
M11 route on-line, off-line options
16 New Park & Ride site west of the M11 at Junction 11 in Trumpington. Associated guideway links into city centre. Bus service (north) along the M11 route to junction 11 and 12, Park & Ride at Barton with cycle lane improvements along Barton Road.
M11 route on-line, off-line options
Bus route East/West side of M11
17 P&R at Barton Road site with bus service/lane improvements into the City
P&R site location
Service frequencies
Infrastructure improvements (on-line/off-line)
18 New Park & Ride at Barton Road/Junction 12 site with bus route running between Junction 12 and 13, linking with new bus service through NW Cambridge development to the New Rail Station (Cambridge North).
P&R site location
M11 route on-line, off-line options
Service distribution/routes through new development
19 New Park & Ride at Barton Road/Junction 12 site with bus route running between Junction 12 and 13. New bus service through NW Cambridge development via the New Rail Station (Cambridge North) continuing through city to Addenbrooke’s
P&R site location
M11 route on-line, off-line options
Service distribution/routes through new development
20 New Park & Ride at Barton Road/Junction 12 site with bus service (north) along the M11 route to junction 11 and 12, with cycle lane improvements along Barton Road.
P&R site location
M11 route on-line, off-line options
Service distribution/routes through new development
21 New bus stop on new bus route between Junction 12 and 13, at Barton road end.
Bus stop location
M11 route on-line, off-line options
22 New Park & Ride site west of the M11 at Junction 11 in Trumpington. Associated guideway links into city centre. Bus service (north) along the M11 route to junction 11 and 13, Park & Ride at Barton with cycle lane improvements along Barton Road.
M11 route on-line, off-line options
Bus route East/West side of M11
23 New bus stop and bus improvements along Barton road. Bus stop location
Type of improvements (on-line/off-line)
24 Park & Cycle site and cycle lane improvements along Barton Road.
P&C Location
![Page 56: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/56.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 56
No. Brief description Variants
25 Park & Cycle site and cycle lane improvements along Trumpington Road.
P&C location
26 Park & Cycle in Trumpington P&C location
27 New bus service through NW Cambridge development via the New Rail Station (Cambridge North)
Service routes and timings
28 New Park & Ride site west of the M11 at Junction 11 in Trumpington, with associated bus links to City. Bus service (north) along the M11 route to junction 11 and 13. Linking with new bus service through NW Cambridge development to the New Rail Station (Cambridge North).
M11 route on-line, off-line options
Bus route East/West side of M11
Intersections/interactions with existing infrastructure.
Routing and times of services
29 Orbital services via M11 through new NW developments and science park back down to Addenbrooke’s.
Routing and timing of services
30 New Park & Ride site west of the M11 at Junction 11 in Trumpington, with associated bus links to City. Bus service (north) along the M11 route to junction 11 and 13. New bus service through NW Cambridge development via the New Rail Station (Cambridge North) continuing through city to Addenbrooke’s
M11 route on-line, off-line options
Bus route East/West side of M11
Intersections/interactions with existing infrastructure.
Routing and times of services
31 Park & Rail site a Foxton with additional rail services via Addenbrooke’s through to new station (Cambridge North)
P&R location
Rail line improvements/Capacity
![Page 57: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/57.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 57
Appendix C. Engineering and Modelling Input
C.1. Engineering Input Cost Information £1.377 million => Per km of New Route £1.1232 million => Per km of Single Lane Widening £1.265 million => Per km of Bus Priority Facilities Park and ride => £3.2 million Signalised Roundabout =>£4.9 million Timescale Information Existing Cambridge Guided Bus = 25km over 3 years= 8.3km/year Minor Structure = 8 weeks (2 months) Major Structure = 6 months Major Bridge = 11 months Minor Junction = 12 weeks (3 months) Major Junction = 7 months New Signals = 12 weeks (3 months) Signalised Roundabout = 16 weeks (4 months)
Information produced using Highway Agency Area 8 Website. (Not taking into account stats.)
![Page 58: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/58.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 58
Option 1 A, F & M
Cost A. Park and ride- £3.2million
F. Offline link:
1.
Offline Bus link- £4million
New Bridge over M11- £10 to 30million
Culverts - £1.15million
Signalised junction - £120,000
OR
Using Existing Bridge: Offline Bus link- £4million
Culverts - £1.15million
OR
Link to Existing Road: Bus priority - £1.4million
M. New cycle link- £390,000
With offline link: Estimated cost £38.86million
Using existing bridge: Estimated cost £8.74million
Without new bridges: Estimated cost £4.99million
Land Take A. Park and ride: 80,000 m2
F. Offline link: 1.5km x 18.5m = 27,750 m2
Using Existing Bridge: No land take required
Link to Existing Road: 1.1km X 10m = 11,000m2
M. New cycle link 1.3km x 5m = 6,500m2
Estimated land take = 114,250 m2
Timescales A. Park and ride: 12 months
F. Offline link: 18 months
Using Existing Bridge: 6 months
Link to Existing Road: 8 months
M. New cycle link 2 months
Offline link option: Max timescale - 32months
Min (concurrent) timescale - 14months
Link to existing road option: Max timescale - 20months
Min (concurrent) timescale - 12months
![Page 59: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/59.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 59
Using existing bridge option: Max timescale - 22months
Min (concurrent) timescale - 12months
Note: Retention period after construction not included, usually 12months.
![Page 60: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/60.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 60
Option 5 A, D, E, F, H & M
Cost A. Park and ride- £3.2million
D. Park and ride- £3.2million
E. Single lane widening with bus priority- £6.9million
F. Offline link:
2.
Offline Bus link- £4million
New Bridge over M11- £10 to 30million
Culverts - £1.15million
Signalised junction - £120,000
OR
Using Existing Bridge: Offline Bus link- £4million
Culverts - £1.15million
OR
Link to Existing Road: Bus priority - £1.4million
H. Cycle improvements - £1.05million
M. New cycle link- £390,000
With offline bus link: Estimated cost £50.01million
Using existing Bridge: Estimated cost £19.89million
Link to existing road: Estimated cost £16.14million
Land Take A. Park and ride: 80,000 m2
D. Park and ride: 80,000 m2
E. Single lane widening with bus priority
2.5km x 5m = 12,500m2
F. Offline link: 1.5km x 18.5m = 27,750 m2
Using Existing Bridge: No land take required
Link to Existing Road: 1.1km X 10m = 11,000m2
H. Cycle improvements 3.5km x 5m = 17,500 m2
M. New cycle link 1.3km x 5m = 6,500 m2
Estimated land take = 217,750 m2
Timescales A. Park and ride: 12 months
![Page 61: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/61.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 61
D. Park and ride: 12 months
E. Single lane widening with bus priority
5 months
F. Offline link: 18 months
Using Existing Bridge: 6 months
Link to Existing Road: 8 months
H. Cycle improvements 5 months
M. New cycle link 2 months
Offline link option: Max timescale - 54months
Min (concurrent) timescale - 14months
Link to existing road option: Max timescale - 42months
Min (concurrent) timescale - 12months
Using existing bridge option: Max timescale – 44 months
Min (concurrent) timescale - 12months
Note: Retention period after construction not included, usually 12months.
![Page 62: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/62.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 62
Option 7 A, B, C, F, H, I & K
Cost A. Park and ride- £3.2million
B. Offline Busway:
Busway link to M11 J12- £9.78million
Bridges over River Cam and Bourn Brook- £7.3million
Culverts - £3.5million
OR
Online widening full stretch: Widening CR/Verge - £8.4million
Bus priority- £9.4million
Concrete Barrier - £3.7million
Variable message signs - £900,000
OR
Online widening slip roads only: Widening to verge - £1.5million
Bus Priority- £1.6million
Variable message signs - £1.2million
OR
Online Lane 1: no construction costs estimated
C. Offline busway: Offline route - £8.45million
Culvert - £580,000
OR
Online widening full stretch: Widening to CR/Verge - £6million Variable message boards- £2.4million
Central concrete barrier- £2.7million
Bus priority - £7million
OR
Online widening slip roads only: Widening to verge - £1.4million
Bus priority - £1.4million
Variable message boards - £1.2million
OR
Online Lane 1: no construction costs estimated
F. Offline link:
3.
Offline Bus link- £4million
New Bridge over M11- £10 to 30million
Culverts - £1.15million
Signalised junction - £120,000
OR
![Page 63: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/63.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 63
Using Existing Bridge: Offline Bus link- £4million
Culverts - £1.15million
OR
Link to Existing Road: Bus priority - £1.4million
H. Cycle improvements - £1.05million
I. Park and cycle - £3.2million
M. New cycle link- £390,000
With offline busway, bus link and link to existing road: Estimated cost £38.85million
Online widening full stretch with link to existing road: Estimated cost £49.74million
Online widening slip roads with link to existing road: Estimated cost £17.54million
Online Lane 1 running with link to existing road: Estimated costs £9.24million
Land Take A. Park and ride: 80,000 m2
B. Offline Busway: 3.7km x 18.5m = 68,450 m2
Online widening full stretch: No land take required
Online widening slip roads only: No land take required
Online Lane 1: No land take required
C. Offline busway: 3.2km x 18.5m = 59,200 m2
Online widening full stretch: No land take required
Online widening slip roads only: No land take required
Online Lane 1: No land take required
F. Offline link: 1.5km x 18.5m = 27,750 m2
Using Existing Bridge: No land take required
Link to Existing Road: 1.1km X 10m = 11,000m2
H. Cycle improvements 3.5km x 5m = 17,500 m2
I. Park and cycle 80,000 m2
M. New cycle link 1.3km x 5m = 6,500 m2
Estimated land take = 259,400m2
Timescales A. Park and ride: 12 months
B./ Offline Busway: 40 months
![Page 64: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/64.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 64
C. Online widening full stretch: 34 months
Online widening slip roads only: 4 months
Online Lane 1: 0 months
F. Offline link: 18 months
Using Existing Bridge: 6 months
Link to Existing Road: 8 months
H. Cycle improvements 5 months
I. Park and cycle 12 months
M. New cycle link 2 months
Offline link option: Max timescale - 75months
Min (concurrent) timescale - 20months
Online widening full stretch option:
Max timescale - 69months
Min (concurrent) timescale - 20months
Online widening slip roads only option:
Max timescale - 39months
Min (concurrent) timescale - 12months
Online line 1 option:
Max timescale - 35months
Min (concurrent) timescale - 12months
Note: Retention period after construction not included, usually 12months.
![Page 65: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/65.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 65
Option 9 A, B, C, F, L & M
Cost A. Park and ride- £3.2million
B. Offline Busway:
Busway link to M11 J12- £9.78million
Bridges over River Cam and Bourn Brook- £7.3million
Culverts - £3.5million
OR
Online widening full stretch: Widening CR/Verge - £8.4million
Bus priority- £9.4million
Concrete Barrier - £3.7million
Variable message signs - £900,000
OR
Online widening slip roads only: Widening to verge - £1.5million
Bus Priority- £1.6million
Variable message signs - £1.2million
OR
Online Lane 1: no construction costs estimated
C. Offline busway: Offline route - £8.45million
Culvert - £580,000
OR
Online widening full stretch: Widening to CR/Verge - £6million Variable message boards- £2.4million
Central concrete barrier- £2.7million
Bus priority - £7million
OR
Online widening slip roads only: Widening to verge - £1.4million
Bus priority - £1.4million
Variable message boards - £1.2million
OR
Online Lane 1: no construction costs estimated
F. Offline link:
4.
Offline Bus link- £4million
New Bridge over M11- £10 to 30million
Culverts - £1.15million
Signalised junction - £120,000
OR
![Page 66: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/66.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 66
Using Existing Bridge: Offline Bus link- £4million
Culverts - £1.15million
OR
Link to Existing Road: Bus priority - £1.4million
M. New cycle link £390,000
With offline busway, bus link and link to existing road: Estimated cost £34.60million
Online widening full stretch with link to existing road: Estimated cost £45.49million
Online widening slip roads with link to existing road: Estimated cost £13.29million
Online Lane 1 running with link to existing road: Estimated costs £4.99million
Land Take A. Park and ride: 80,000 m2
B. Offline Busway: 3.7km x 18.5m = 68,450 m2
Online widening full stretch: No land take required
Online widening slip roads only: No land take required
Online Lane 1: No land take required
C. Offline busway: 3.2km x 18.5m = 59,200 m2
Online widening full stretch: No land take required
Online widening slip roads only: No land take required
Online Lane 1: No land take required
F. Offline link: 1.5km x 18.5m = 27,750 m2
Using Existing Bridge: No land take required
Link to Existing Road: 1.1km X 10m = 11,000m2
L. Orbital bus services No land take required
M. New cycle link 1.3km x 5m = 6,500 m2
Estimated land take = 239,300 m2
Timescales A. Park and ride: 12 months
B./
C.
Offline Busway: 40 months
Online widening full stretch: 34 months
Online widening slip roads only: 4 months
Online Lane 1: 0 months
F. Offline link: 18 months
![Page 67: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/67.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 67
Using Existing Bridge: 6 months
Link to Existing Road: 8 months
M. New cycle link 2 months
Offline link option: Max timescale – 60 months
Min (concurrent) timescale – 20 months
Online widening full stretch option: Max timescale – 54 months
Min (concurrent) timescale - 20months
Online widening slip roads only option: Max timescale – 24 months
Min (concurrent) timescale – 12 months
Online line 1 option: Max timescale – 20 months
Min (concurrent) timescale – 12 months
Note: Retention period after construction not included, usually 12 months.
![Page 68: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/68.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 68
Option 13 A, B, C, D, F & L
Cost A. Park and ride- £3.2million
B. Offline Busway:
Busway link to M11 J12- £9.78million
Bridges over River Cam and Bourn Brook- £7.3million
Culverts - £3.5million
OR
Online widening full stretch: Widening CR/Verge - £8.4million
Bus priority- £9.4million
Concrete Barrier - £3.7million
Variable message signs - £900,000
OR
Online widening slip roads only: Widening to verge - £1.5million
Bus Priority- £1.6million
Variable message signs - £1.2million
OR
Online Lane 1: no construction costs estimated
C. Offline busway: Offline route - £8.45million
Culvert - £580,000
OR
Online widening full stretch: Widening to CR/Verge - £6million Variable message boards- £2.4million
Central concrete barrier- £2.7million
Bus priority - £7million
OR
Online widening slip roads only: Widening to verge - £1.4million
Bus priority - £1.4million
Variable message boards - £1.2million
OR
Online Lane 1: no construction costs estimated
D. Park and ride- £3.2million
F. Offline link:
5.
Offline Bus link- £4million
New Bridge over M11- £10 to 30million
![Page 69: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/69.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 69
Culverts - £1.15million
Signalised junction - £120,000
OR
Using Existing Bridge: Offline Bus link- £4million
Culverts - £1.15million
OR
Link to Existing Road: Bus priority - £1.4million
M. New cycle link £390,000
With offline busway, bus link and link to existing road: Estimated cost £37.80million
Online widening full stretch with link to existing road: Estimated cost £48.69million
Online widening slip roads with link to existing road: Estimated cost £16.49million
Online Lane 1 running with link to existing road: Estimated costs £8.19million
Land Take A. Park and ride: 80,000 m2
B. Offline Busway: 3.7km x 18.5m = 68,450 m2
Online widening full stretch: No land take required
Online widening slip roads only: No land take required
Online Lane 1: No land take required
C. Offline busway: 3.2km x 18.5m = 59,200 m2
Online widening full stretch: No land take required
Online widening slip roads only: No land take required
Online Lane 1: No land take required
D. Park and ride: 80,000 m2
F. Offline link: 1.5km x 18.5m = 27,750 m2
Using Existing Bridge: No land take required
Link to Existing Road: 1.1km X 10m = 11,000m2
L. Orbital bus services No land take required
M. New cycle link 1.3km x 5m = 6,500 m2
Estimated land take = 321,900 m2
Timescales A. Park and ride: 12 months
![Page 70: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/70.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 70
B./
C.
Offline Busway: 40 months
Online widening full stretch: 34 months
Online widening slip roads only: 4 months
Online Lane 1: 0 months
D. Park and ride: 80,000 m2
F. Offline link: 18 months
Using Existing Bridge: 6 months
Link to Existing Road: 8 months
M. New cycle link 2 months
Offline link option: Max timescale – 70 months
Min (concurrent) timescale – 20 months
Online widening full stretch option: Max timescale – 64 months
Min (concurrent) timescale - 20months
Online widening slip roads only option:
Max timescale – 34 months
Min (concurrent) timescale – 12 months
Online line 1 option: Max timescale – 30 months
Min (concurrent) timescale – 12 months
Note: Retention period after construction not included, usually 12 months.
![Page 71: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/71.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 71
Option 16 A, B, D, F, H &M
Cost A. Park and ride- £3.2million
B. Offline Busway:
Busway link to M11 J12- £9.78million
Bridges over River Cam and Bourn Brook- £7.3million
Culverts - £3.5million
OR
Online widening full stretch: Widening CR/Verge - £8.4million
Bus priority- £9.4million
Concrete Barrier - £3.7million
Variable message signs - £900,000
OR
Online widening slip roads only: Widening to verge - £1.5million
Bus Priority- £1.6million
Variable message signs - £1.2million
OR
Online Lane 1: no construction costs estimated
D. Park and ride- £3.2million
F. Offline link:
6.
Offline Bus link- £4million
New Bridge over M11- £10 to 30million
Culverts - £1.15million
Signalised junction - £120,000
OR
Using Existing Bridge: Offline Bus link- £4million
Culverts - £1.15million
OR
Link to Existing Road: Bus priority - £1.4million
H. Cycle improvements- £1.05million
M. New cycle link- £390,000
With offline busway, bus link and link to existing road: Estimated cost £29.82million
Online widening full stretch with link to existing road: Estimated cost £31.64million
![Page 72: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/72.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 72
Online widening slip roads with link to existing road: Estimated cost £13.54million
Online Lane 1 running with link to existing road: Estimated costs £9.24million
Land Take A. Park and ride: 80,000 m2
B. Offline Busway: 3.7km x 18.5m = 68,450 m2
Online widening full stretch: No land take required
Online widening slip roads only: No land take required
Online Lane 1: No land take required
D. Park and ride: 80,000 m2
F. Offline link: 1.5km x 18.5m = 27,750 m2
Using Existing Bridge: No land take required
Link to Existing Road: 1.1km X 10m = 11,000m2
H. Cycle improvements 3.5km x 5m = 17,500 m2
M. New cycle link 1.3km x 5m = 6,500m2
Estimated land take = 280,200 m2
Timescales A. Park and ride: 12 months
B. Offline Busway: 32 months
Online widening full stretch: 21 months
Online widening slip roads only: 4 months
Online Lane 1: 0 months
D. Park and ride: 12 months
F. Offline link: 18 months
Using Existing Bridge: 6 months
Link to Existing Road: 8 months
H. Cycle improvements 5 months
![Page 73: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/73.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 73
M. New cycle link 2 months
Offline link option: Max timescale – 69 months
Min (concurrent) timescale – 14 months
Online widening full stretch option: Max timescale – 58 months
Min (concurrent) timescale - 12months
Online widening slip roads only option:
Max timescale – 41 months
Min (concurrent) timescale – 12 months
Online line 1 option: Max timescale – 37 months
Min (concurrent) timescale – 12 months
Note: Retention period after construction not included, usually 12 months.
![Page 74: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/74.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 74
Option 19 C, D, H & L
Cost C. Offline busway: Offline route - £8.45million
Culvert - £580,000
OR
Online widening full stretch: Widening to CR/Verge - £6million Variable message boards- £2.4million
Central concrete barrier- £2.7million
Bus priority - £7million
OR
Online widening slip roads only: Widening to verge - £1.4million
Bus priority - £1.4million
Variable message boards - £1.2million
OR
Online Lane 1: no construction costs estimated
D. Park and ride- £3.2million
H. Cycling improvements- £1.05millions
With offline busway and bus link: Estimated cost £13.28million
Online widening full stretch: Estimated cost £22.35million
Online widening slip roads: Estimated cost £8.25million
Online Lane 1 running: Estimated costs £4.25million
Land take C. Offline busway: 3.2km x 18.5m = 59,200 m2
Online widening full stretch: No land take required
Online widening slip roads only: No land take required
Online Lane 1: No land take required
D. Park and ride: 80,000 m2
H. Cycling improvements 3.5km x 5m = 17,500 m2
Estimated land take = 156,700 m2
Timescales C. Offline Busway: 15months
Online widening full stretch: 19 months
Online widening slip roads only: 4 months
Online Lane 1: 0 months
![Page 75: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/75.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 75
D. Park and ride: 12 months
H. Cycle improvements 5 months
Offline link option: Max timescale – 32 months
Min (concurrent) timescale – 12 months
Online widening full stretch option: Max timescale – 36 months
Min (concurrent) timescale – 12 months
Online widening slip roads only option: Max timescale – 21 months
Min (concurrent) timescale – 12 months
Online line 1 option: Max timescale – 17 months
Min (concurrent) timescale – 12 months
Note: Retention period after construction not included, usually 12 months.
![Page 76: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/76.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 76
Option 20 B, D, F, H, Busway
Cost B. Offline Busway:
Busway link to M11 J12- £9.78million
Bridges over River Cam and Bourn Brook- £7.3million
Culverts - £3.5million
OR
Online widening full stretch: Widening CR/Verge - £8.4million
Bus priority- £9.4million
Concrete Barrier - £3.7million
Variable message signs - £900,000
OR
Online widening slip roads only: Widening to verge - £1.5million
Bus Priority- £1.6million
Variable message signs - £1.2million
OR
Online Lane 1: no construction costs estimated
D. Park and ride- £3.2million
F. Offline link:
7.
Offline Bus link- £4million
New Bridge over M11- £10 to 30million
Culverts - £1.15million
Signalised junction - £120,000
OR
Using Existing Bridge: Offline Bus link- £4million
Culverts - £1.15million
OR
Link to Existing Road: Bus priority - £1.4million
H. Cycle improvements- £1.05million
With offline busway, bus link and link to existing road: Estimated cost £26.23million
Online widening full stretch with link to existing road: Estimated cost £28.17million
Online widening slip roads with link to existing road: Estimated cost £9.95million
Online Lane 1 running with link to existing road: Estimated costs £5.65million
Land take B. Offline Busway: 3.7km x 18.5m = 68,450 m2
Online widening full stretch: No land take required
![Page 77: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/77.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 77
Online widening slip roads only: No land take required
Online Lane 1: No land take required
D. Park and ride: 80,000 m2
F. Offline link: 1.5km x 18.5m = 27,750 m2
Using Existing Bridge: No land take required
Link to Existing Road: 1.1km X 10m = 11,000m2
H. Cycle improvements 3.5km x 5m = 17,500 m2
Estimated land take = 193,700 m2
Timescales B. Offline Busway: 32 months
Online widening full stretch: 21 months
Online widening slip roads only: 4 months
Online Lane 1: 0 months
D. Park and ride: 12 months
F. Offline link: 18 months
Using Existing Bridge: 6 months
Link to Existing Road: 8 months
H. Cycle improvements 5 months
Offline link option: Max timescale – 55 months
Min (concurrent) timescale – 14 months
Online widening full stretch option: Max timescale – 44 months
Min (concurrent) timescale - 12months
Online widening slip roads only option: Max timescale – 27 months
Min (concurrent) timescale – 12 months
Online line 1 option: Max timescale – 23months
Note: Retention period after construction not included, usually 12 months.
![Page 78: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/78.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 78
Option 22 A, B, C, D, F, H & M
Cost A. Park and ride- £3.2million
B. Offline Busway:
Busway link to M11 J12- £9.78million
Bridges over River Cam and Bourn Brook- £7.3million
Culverts - £3.5million
OR
Online widening full stretch: Widening CR/Verge - £8.4million
Bus priority- £9.4million
Concrete Barrier - £3.7million
Variable message signs - £900,000
OR
Online widening slip roads only: Widening to verge - £1.5million
Bus Priority- £1.6million
Variable message signs - £1.2million
OR
Online Lane 1: no construction costs estimated
C. Offline busway: Offline route - £8.45million
Culvert - £580,000
OR
Online widening full stretch: Widening to CR/Verge - £6million Variable message boards- £2.4million
Central concrete barrier- £2.7million
Bus priority - £7million
OR
Online widening slip roads only: Widening to verge - £1.4million
Bus priority - £1.4million
Variable message boards - £1.2million
OR
Online Lane 1: no construction costs estimated
D. Park and ride- £3.2million
F. Offline link:
8.
Offline Bus link- £4million
New Bridge over M11- £10 to 30million
![Page 79: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/79.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 79
Culverts - £1.15million
Signalised junction - £120,000
OR
Using Existing Bridge: Offline Bus link- £4million
Culverts - £1.15million
OR
Link to Existing Road: Bus priority - £1.4million
H. Cycle improvements- £1.05million
M. New cycle link- £390,000
With offline busway, bus link and link to existing road: Estimated cost £38.85million
Online widening full stretch with link to existing road: Estimated cost £49.74million
Online widening slip roads with link to existing road: Estimated cost £17.54million
Online Lane 1 running with link to existing road: Estimated costs £9.24million
Land Take A. Park and ride: 80,000 m2
B. Offline Busway: 3.7km x 18.5m = 68,450 m2
Online widening full stretch: No land take required
Online widening slip roads only: No land take required
Online Lane 1: No land take required
C. Offline busway: 3.2km x 18.5m = 59,200 m2
Online widening full stretch: No land take required
Online widening slip roads only: No land take required
Online Lane 1: No land take required
D. Park and ride: 80,000 m2
F. Offline link: 1.5km x 18.5m = 27,750 m2
Using Existing Bridge: No land take required
Link to Existing Road: 1.1km X 10m = 11,000m2
H. Cycle improvements 3.5km x 5m = 17,500 m2
M. New cycle link 1.3km x 5m = 6,500 m2
Estimated land take = 339,400 m2
![Page 80: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/80.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 80
Timescales A. Park and ride: 12 months
B./
C.
Offline Busway: 40 months
Online widening full stretch: 34 months
Online widening slip roads only: 4 months
Online Lane 1: 0 months
D. Park and ride: 12 months
F. Offline link: 18 months
Using Existing Bridge: 6 months
Link to Existing Road: 8 months
H. Cycle improvements 5 months
M. New cycle link 2 months
Offline link option: Max timescale – 77 months
Min (concurrent) timescale – 20 months
Online widening full stretch option: Max timescale – 71 months
Min (concurrent) timescale - 20months
Online widening slip roads only option: Max timescale – 41 months
Min (concurrent) timescale – 12 months
Online line 1 option: Max timescale – 37 months
Min (concurrent) timescale – 12 months
Note: Retention period after construction not included, usually 12 months.
Option 30 L
Cost L. Circular bus service - No construction cost anticipated
Land take L. Circular bus service - No land take required
Timescales L. Circular bus service - No timescale to be estimated
![Page 81: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/81.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 81
C.2. Modelling input
Demand Analysis
The 2011 and 2031 CSRM models have been used to extract a sectored demand matrix of all the trips in the Western Orbital catchment area. For each option, a slightly different set of origins / destinations are likely to be served and therefore the total demand each option can cater for is slightly different. The origins / destinations served by each option were agreed and the appropriate demand from the model was summed for each option to provide an indication of the maximum level of demand for each scheme. The maximum demand available to each scheme can be seen in Table -5. Figure -13 to Figure -15 diagrammatically represent the differences in trip numbers between 2011 and 2031 by zones.
Figure -13 Increase in AM peak trips from 2011 to 2031 for main trip attractors in the City
![Page 82: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/82.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 82
Figure -14 Increase in AM peak trips from 2011 to 2031 for main trip generators in the City
Figure -15 Increase in AM peak trips from 2011 to 2031 for main generators outside the City
![Page 83: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/83.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 83
Table -5 Forecast Demand in Scope by year, time period and option
Option Number 1 5 7 9 13 16 19 20 22 30
2011 AM Peak Period Demand in Scope (3 hours) 1,252 3,234 5,311 22,768 24,336 1,771 22,600 469 1,771 18,870
2011 PM Peak Period Demand in Scope (3 hours) 1,349 3,273 5,577 18,557 20,300 2,026 18,652 554 2,026 14,635
2011 AM + PM Demand in Scope (6 hours) 2,601 6,507 10,888 41,325 44,636 3,797 41,252 1,023 3,797 33,505
2031 AM Peak Period Demand in Scope (3 hours) 1,614 3,623 7,933 35,368 36,979 2,578 34,781 799 2,578 30,916
2031 PM Peak Period Demand in Scope (3 hours) 1,811 3,937 8,230 28,709 30,721 3,087 28,561 1,021 3,087 23,949
2031 AM + PM Demand in Scope (6 hours) 3,425 7,560 16,163 64,077 67,700 5,665 63,342 1,820 5,665 54,865
Table -6 2031 Average Forecast Journey Time Savings and Demand Benefits per Option
Metric Optn 1 Optn 5 Optn 7 Optn 9 Optn 13 Optn 16 Optn 19 Optn 20 Optn 22 Optn 30
2031 AM Average Journey Time Saving Per Person (mins)
0.000 3.804 3.384 3.920 3.809 0.000 4.082 0.000 0.000 4.089
2031 PM Average Journey Time Saving Per Person (mins)
0.000 6.080 5.005 3.894 4.023 0.000 3.441 0.000 0.000 3.397
2031 Demand that would benefit from reduced travel time, AM peak period (people)
0 1,677 1,659 4,056 4,381 0 2,978 0 0 2,520
2031 Demand that would benefit from reduced travel time, PM peak period (people)
0 2,126 2,026 7,046 7,345 0 5,379 0 0 4,654
Total 2031 travel time saving (average saving * demand) , AM peak (Hours)
0 106 94 265 278 0 203 0 0 172
Total 2031 travel time saving (average saving * demand) , PM peak (Hours)
0 215 169 457 492 0 308 0 0 264
Total 2031 travel time saving (average saving * demand) , AM + PM peak (Hours)
0 322 263 722 771 0 511 0 0 435
![Page 84: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/84.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 84
Appendix D. Options Appraisal
D.1. Workshop #2
![Page 85: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/85.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 85
![Page 86: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/86.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 86
![Page 87: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/87.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 87
![Page 88: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/88.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 88
![Page 89: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/89.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 89
![Page 90: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/90.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 90
![Page 91: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/91.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 91
![Page 92: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/92.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 92
![Page 93: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/93.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 93
![Page 94: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/94.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 94
![Page 95: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/95.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 95
![Page 96: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/96.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 96
![Page 97: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/97.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 97
![Page 98: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/98.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 98
Appendix E. Appraisal Summary Table
![Page 99: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/99.jpg)
Western Orbital Study
Appendices
Atkins Western Orbital Study Appendices | Version 1.0 | 24 July 2015 | 5137624 99
![Page 100: Western Orbital Study Phase 1 - citydeal-live.storage ... · This growth trend is likely to increase as land is allocated for development under the Local Plans. Employment – unemployment](https://reader034.vdocuments.us/reader034/viewer/2022050100/5f3f81368393f7303b2c98d2/html5/thumbnails/100.jpg)
© Atkins Ltd except where stated otherwise. The Atkins logo, ‘Carbon Critical Design’ and the strapline ‘Plan Design Enable’ are trademarks of Atkins Ltd.
Atkins Cambridge Office 5 Wellbrook Court Girton Road Cambridge Cambridgeshire CB3 0NA Telephone: +44(0)1223 276002 Fax: +44(0)1223 277529