west valley college measure c master plan schedule january 6, 2013
DESCRIPTION
WEST VALLEY COLLEGE MEASURE C MASTER PLAN SCHEDULE JANUARY 6, 2013. COMPLETED. MEASURE H. IN CONSTRUCTION. INTERIM HOUSING 2013 - 2014. FACILITIES BLDG . CONSTRUCTION 2015 - 2017. W&F. LIBRARY. INTERIM. SM. PLANETARIUM CONSTRUCTION 2014 - 2015. SS. LA. SM. NWP. AAS - PowerPoint PPT PresentationTRANSCRIPT
WEST VALLEY COLLEGEMEASURE C MASTER PLAN SCHEDULEJANUARY 6, 2013
WEST VALLEY COLLEGE 2013 MEASURE C PROJECTS – PH I
LIBRARY
Golf
AAS
LASS
SM
SM
FOX
CAMPUSCENTER
INTERIM
NWP
INT.
COMPLETED
MEASURE H
IN CONSTRUCTION
BUSINESS
SS
VASONA CR.CC-2
W&F
FACILITIES BLDG.
CONSTRUCTION2015 - 2017
SS
PLANETARIUMCONSTRUCTION
2014 - 2015
CREEK RESTORATIONPHASED CONST
2013 – 2016
AASCONSTRUCTION
2014 - 2016
INTERIM HOUSING2013 - 2014
OPTION FOR FUTURE INTERIM HOUSING
WEST VALLEY COLLEGE 2016 MEASURE C PROJECTS – PH II
LIBRARY
Golf
AAS
LASS
SM
SM
FOX
CAMPUSCENTER
INTERIM
NWP
INT.
COMPLETED
MEASURE H
IN CONSTRUCTION
COMPLETED
BUSINESS
SS
VASONA CR.CC-2
W&F
STUDENT SERVICESCONSTRUCTION
2016-2018
CAMPUS CTR PH 2CONSTRUCTION
2016 - 2018
CREEK RESTORATIONPHASED CONST
2013 - 2016
WEST VALLEY COLLEGE 2018 MEASURE C PROJECTS – PH III
LIBRARY
Golf
AAS
LASS
SM
SM
FOX
CAMPUSCENTER
INTERIM
NWP
INT.
COMPLETED
MEASURE H
IN CONSTRUCTION
COMPLETED
BUSINESS
SS
VASONA CR.CC-2
W&F
PE
HUM/FA
LIBRARYPHASED CONST
2018 – 2020*POTENTIAL STATE
FUNDING
BUSINESSCONSTRUCTION
2018 - 2020
WEST VALLEY COLLEGE 2020 MEASURE C PROJECTS – PH IV
LIBRARY
Golf
AAS
LASS
SM
SM
FOX
CAMPUSCENTER
INTERIM
NWP
INT.
COMPLETED
MEASURE H
IN CONSTRUCTION
COMPLETED
BUSINESS
SS
VASONA CR.CC-2
W&F
PE
HUM/FA
FINE ARTS / HUM FINE ARTSPHASED CONST
2020 - 2022
PE RENOVATIONPHASED CONST
2020 - 2023