west gode irrigation project report on flood protection
TRANSCRIPT
Somali Regional State
Irrigation and Basin Development Bureau
West Gode Irrigation Project
Report on
Flood Protection, Rehabilitation and Maintenance Work
November 2019, Jijiga
Project, Flood Protection, Rehabilitation & Maintenance Works
Somali Regional State Page 2
Irrigation and Basin Development Bureau
Contents
1 Introduction .......................................................................................................... 3
2. Background and Present Situation ...................................................................... 5
2.1 Background .................................................................................................. 5
2.2 Present Situation ........................................................................................... 6
2.2.1 Head Works ............................................................................................ 6
2.2.2 Main Canal and Main Canal Structures .................................................. 6
2.2.3 Farm Works ............................................................................................ 7
2.3 Major Constraints Observed.......................................................................... 7
2.3.1 General ................................................................................................... 7
2.3.2 Engineering (Technical) Constraints ....................................................... 8
3 Flood Protection and Maintenance Works at the Headwork .............................. 10
3.1 General ....................................................................................................... 10
3.2 Anticipated Flood at the Headwork ............................................................. 10
3.3 Flood From the Western Escarpment ......................................................... 10
3.4 Flood From Wabi Shebelle .......................................................................... 12
3.4.1 General ................................................................................................. 12
3.4.2 Flood Mitigation Measures at The Headwork ....................................... 13
3.5 Proposed Remedial Measures for Head Works and Main Canal ................ 15
4 Flood Protection and Maintenance Works at Farm Work .................................. 19
4.1 General ....................................................................................................... 19
4.2 Anticipated Flood at the Farm Work ............................................................ 19
4.3 Present Situation ......................................................................................... 20
4.3.1 Farm Works .......................................................................................... 20
4.4 Proposed Remedial Measures for Farm Works .......................................... 21
Project, Flood Protection, Rehabilitation & Maintenance Works
Somali Regional State Page 3
Irrigation and Basin Development Bureau
List of Figures
Figure 3-1, Flood Generated From Western Escarpment 1 ................................................. 11
Figure 3-2, Flood Scenario After Construction of Gode-West/Gode Road 1 ........................ 12
Figure 3-3, Anticipated Flood at Headwork & Proposed Mitigation Measures 1................... 14
Figure 3-4, Flood Mitigation Measures Af2013 Flood 1 ....................................................... 15
Figure 3-5, Profile & Cross Section of W/Dyke 1 ................................................................. 17
Figure 3-6, New Dyke from IP-A up to 2km Downstream1 .................................................. 18
Figure 4-1, Flood Generating Wadis 1 ................................................................................ 20
Figure 4-2, Location and Layout of Floodway 1 ................................................................... 22
Figure 4-3, Typical Cross Section of the Floodway 1........................................................... 23
Project, Flood Protection, Rehabilitation & Maintenance Works
Somali Regional State Page 4
Irrigation and Basin Development Bureau
1 Introduction
This is a field mission Report for flood protection, rehabilitation and maintenance works to
be done at West-Gode Irrigation Project. The report presents the findings of the field
assessment team and elaborates measures to be taken with full justification and
validation based on the knowhow, experience and empirical knowledge of the team.
To this end, a team comprising a Senior Hydraulic/Structural Eng., Elector-Mechanical
Eng. and a Senior Eng. from Irrigation Bureau has visited the project site from 30/10/2019
to 2/11/2019. Apart from this the project personnel at the site have given valuable input
for the contents of this report.
To keep the consistency of the present study and maintenance work with earlier works in
Gode-West area, former design reports and design criterion as prepared by
NEDECO/WRDA were closely referred and used. Moreover, drawings as well as
hydrological studies prepared by NEDECO/WRDA, SWWDSE/YESHI-BER Consult were
of immense assistance in the preparation this report.
It is believed that a small briefing secession in combination with this report will give the
Irrigation Bureau in particular and the policy makers of the region in general a good
insight on the envisaged flood protection, rehabilitation and maintenance work proposed
for Gode-West Irrigation Project.
Project, Flood Protection, Rehabilitation & Maintenance Works
Somali Regional State Page 5
Irrigation and Basin Development Bureau
2. Background and Present Situation
2.1 Background
In the early 1980’s the Ethiopian Government has intended to start intensive agricultural
development program on a total of 27,600 ha land at Gode West and Gode South. The
prevailing physical conditions of the area, climate, soils and water, allows year round
irrigated agricultural practices on large number of crop commodities in West and South
Gode (7,600ha in West Gode and 20,000 ha land in South Gode).
Water for irrigation will be won from the prominent Wabi Shebelle River by means of the
already constructed diversion structure. The entire irrigation water both for Gode West
and Gode South will be diverted at West Gode and will be conveyed via a main canal
that runs along the left bank of the river (Gode West Side).
To this end the Ethiopian Government and SRS in association with international
consultants and local experts has completed the detailed study and design of;
a. A Diversion Weir which can abstract water for the overall irrigation of West and South
Gode Area.
b. A Main Canal that conveys the diverted water to West Gode and up to the river
crossing site to South Gode (the total length of the main canal up to the river crossing
site is 27km)
c. A River crossing structure (Siphon) to covey water beneath Wabi Shebele river to
South Gode
d. Flood protection works
e. Detailed on farm work design on 7,600 ha land in West Gode
Ever since 1987, the development of the project was transformed to the construction
stage and to date the construction of the following works is substantially completed.
Head works, including diversion weir, scouring sluice, desilting basin, sediment
ejector and protection works
Main canal, 13.75 km main canal and associated main canal structures
Farm work development on 3,200 ha
Project, Flood Protection, Rehabilitation & Maintenance Works
Somali Regional State Page 6
Irrigation and Basin Development Bureau
2.2 Present Situation
2.2.1 Head Works
At present the project is not functioning at its full capacity. This is mainly due to a number
of obstacles. At the head works, the major bottle neck observed is the siltation of the
main canal and the desilting basin as well as the non-functionality of the electro-
mechanical parts of the gates and hoisting devices.
Currently the sluice gates are staked and are not functioning. Although the two intake
gates are open their desirable maneuverability is not guaranteed, while the remaining
two intake gates are stacked and nonfunctional. Moreover, large amount of debris are
accumulated at the intake gates. Except for one major divide wall all civil works at the
intake are found to be in good shape.
Since the two desilting basins are totally silted up, the sediment ejectors and the vortex
tube are not functional and the gates that control the flow through them are stacked.
Another major problem at the head works is the damage inflicted by external flooding.
During the site visit it was observed that the flood coming from the Northern escarpment
has breached the main canal and has caused considerable damage.
2.2.2 Main Canal and Main Canal Structures
The total length of the main canal that is constructed has a total length of 13.75 km and
have a capacity of 46.6m3/s. After Km 13+750 (immediately downstream of CR-2) the
main canal ends at a dead end. The flow quantity (46.6m3/s) is the total discharge
required to irrigate both Gode West and Gode South. The constructed main canal
structures include a bridge at the head end of the canal, four main off-takes, two head
regulators and two rejection spillways.
At present due to various reasons the main canal is silted up and its conveyance
capacity is very much reduced. In some places the sedimentation is critical that siltation
has taken place from bed level up to the bank of the canal. From the visual inspection
made, the inlet, transition and out let of the four main off-takes was found intact contrary
to this all main off-take gates and their hoisting devices are staked and lifting of the gates
is impossible.
As for Head Regulator-1, except for minor maintenance, involving plastering and
pointing further maintenance is not required. However, due to over loading and heavy
Project, Flood Protection, Rehabilitation & Maintenance Works
Somali Regional State Page 7
Irrigation and Basin Development Bureau
traffic Head Regulator-2 requires heavy maintenance. On both head regulators the stop
logs are stacked in their grooves and have started to rot in place.
2.2.3 Farm Works
The command area at Gode West is about 7,560 ha. The irrigable area is divided into six
primary command units. Based on geographic positioning the first primary unit is situated
on the Northern side while the other five primary command units are on the Southern
side.
The first primary unit comprises of 1,920 ha land while primary unit two and three
combined have 1,740 ha and the area under primary unit four is 2,070 ha and the
combined command area of primary unit five and six is 1,880 ha.
During the site visit the general condition and status of the constructed canals, drains
and irrigation infrastructures was assessed. It was observed that most of the canals and
drains suffer siltation due to lack of maintenance. Further, some part of the embankment
of Primary Canal-1,2 and 3 is damaged as a result of inferior fill material, poor
workmanship and lack of preventive and regular maintenance.
With respect to external floods, as in any low land irrigation project Gode Irrigation
project should be protected from external floods. The flood generated from the Norther
wadis (Wady Bu-Y) and the floods from the Eastern boundary of the farm are major
concerns. To safe guard the farm area from the recent flood, mainly from wadi Bu-Y, an
interception drain is being excavated on the northern boundary of the farm that run
parallel with embankment of primary canal GW1-00. However, it was observed that the
excavation of the intercepting drain has major technical issues and should be rectified
immediately.
2.3 Major Constraints Observed
2.3.1 General
During the site visit a number of constraints and problems were observed on the
sectoral, technical and managerial aspects of the project. These observed constraints
have imposed a barrier for the full functioning of the system to the extent that water
diversion to the farms in West Gode is impossible. Unless proper corrective measures
are taken now, it is believed that the far reaching negative effects of the constraints
could hamper the smooth operation of the project in the future.
For proper functioning of the project the existing constraints on the project should be
addressed and alleviated sustainably. As the whole work on the project i.e. head works,
main canal and farm works are connected and interrelated, the problems of the project
Project, Flood Protection, Rehabilitation & Maintenance Works
Somali Regional State Page 8
Irrigation and Basin Development Bureau
should be approached from a system point of view. To address the problems of the
project in its entirety the observed constraints are classified in to the following two
categories;
Engineering (Technical) Constraints
Sectoral Constraints
2.3.2 Engineering (Technical) Constraints
Currently, most of the technical constraints of the project are being addressed. However,
it is worth mentioning the crucial constraints observed;
All gates and hoisting devises on the head work are not functional
Heavy sedimentation is observed at the intake and the under sluice as well as on the
sediment basin
The entire reach of the main canal is silted up (on some places from bed to the bank
top level)
Although constructed, the western flood protection dyke for the head works was not
constructed as per the working drawing prepared
At the head works and at the beginning of the main canal, the flood coming from the
western escarpments is developing its own course and is endangering the sediment
basin and the main canal.
All main canal off-take gates and head regulator stop-logs are silted up and are
stacked inside the sliding grooves
The second head regulator on the main canal is dilapidated and need major
maintenance
Most of the primary, secondary and tertiary canals are silted up and most all of the
off-take gates and hoisting devices are stalked.
The flood protection dyke along west Gode command area and the flood drain are
not constructed and Primary GW1-00 could easily be breached and cause severe
damage on the farm land.
The following major aspects are believed to contribute for the problems observed;
Lack of operation and maintenance of the head works including the electro-
mechanical parts and in particular the operation of the under sluice gate was not
done as per the rules and regulations
The sedimentation basin was not operated as per the standard norm and rules plus
the vortex tube downstream of the sediment basin was not functional for a prolonged
time
Project, Flood Protection, Rehabilitation & Maintenance Works
Somali Regional State Page 9
Irrigation and Basin Development Bureau
The sedimentation of the main canal and the malfunctioning of main canal structures
is attributable to quite a number of factors such as hydrologic, hydraulics, operation
and maintenance
Hydrologic: from hydrologic point of view the main canal should be protected from
external floods. In fact the left bank of the main canal acts as a dyke to protect itself
from external flood. Due to unaccounted external flood the main canal is breached in
some places and sedimatation is observed at these locations
Hydraulics: From hydraulic point of view although the main canal is constructed to
convey water for both Gode West and Gode South (46.6 m3/s) it has never been
operated to carry this design flow. Rather, the estimated flow in the main canal has
never been more than 3 m3/s, this situation has led to low velocity in the main canal
than the design non silting/non scouring velocity of flow, which highly encourages
sediment deposition along the canal reach.
Operation: The operation of the under sluice, intakes, the main canal and the
sedimentation basin has never been according to the standard rules and regulations
Maintenance: The main canal and the desilting basin should have been maintained
as per the rules and regulations after every irrigation season. However, neither
preventive nor regular maintenance has been done so far.
Regarding the farm works most of the problems are due to non-functionality of the
system for a prolonged time as well as lack of preventive and regular maintenances.
In addition part of the problem is due to lack of construction quality control. Other
major attribute for the problem on the farm works is the damage caused by external
floods and wind erosion and deposition. Parallel with this, the internal drainage of the
system is not well constructed/maintained and the main drain that evacuates excess
runoff from the system is not built.
Project, Flood Protection, Rehabilitation & Maintenance Works
Somali Regional State Page 10
Irrigation and Basin Development Bureau
3 Flood Protection and Maintenance Works at the Headwork
3.1 General
In this section the flood protection works and other maintenance works needed at the
headwork is elaborated.
Being no exception the design of the head-works for Gode Irrigation Project was based
on probabilistic values of certain return periods. The return period for the design of any
hydraulic structure depends on the degree of risk (mainly safety and economy) that the
designer runs in designing a structure during its anticipated service life.
Accordingly the following return periods were adopted for the design of the head-works
of Gode Irrigation Project;
The diversion weir was designed for a 1:100 yrs. return period flood volume
(discharge).
The Western Dyke, abutment and key walls of the weir were designed for a 1:50 yrs.
return period flood height (stage).
Thus;
The diversion weir has a total crest length of 100m, which can safely accommodate a
flood magnitude of 1:100 yrs.
The crest levels of the Western Dyke, abutment and key walls of the weir were fixed
at 328.50 m (a.m.s.l)
3.2 Anticipated Flood at the Headwork
During the study and design of the headwork, two flood cases were considered and flood
protection works were proposed for the same. Then it was noted that the headwork
could be vulnerable from floods that are generated from;
Flood from the Western Escarpment
Flood from Wabi Shebelle River
3.3 Flood From the Western Escarpment
Figure-3.1 shows the general flood scenario that could be generated from the Western
Escarpment. The Western catchment area which brings flood to the head works (at
beginning of the main canal) generates its flow from the local escarpments. The total
catchment area of the North-Western escarpment is estimated to be 5-10 km2. The
Figure shows the general condition at the headwork prior to the construction of the old
Project, Flood Protection, Rehabilitation & Maintenance Works
Somali Regional State Page 11
Irrigation and Basin Development Bureau
Gode-West/Gode road. As shown in Figure-3.1, the flood that could be generated from
the western escarpments is localized and of small magnitude. The flood from this
escarpment will spread on the land between the escarpment and the main canal before
reaching the headwork. Moreover, inspecting the local topography, the excess runoff
from this escarpment will be encouraged to flow along the gently sloping terrain into the
large flood plain between the headwork
Figure 3-1, Flood Generated From Western Escarpment 1
and the irrigation area of West Gode. Hence, except for a spoil bank, which is 1m high,
that runs parallel to the main canal, as such no major flood protection was provided for
the flood from the Western Escarpment.
After the construction of the old Gode-West/Gode road, the original flood scenario as
given in Figure-3.1 is totally changed. And the flood that is generated from the western
escarpment has become one major concern for the safety of the headwork and the main
canal. Figure-3.2 shows the flood generated from the western escarpment after the
construction of old Gode/Gode-West road. Now the runoff from the escarpment crates a
concentrated flow that is channeled between the Western Dyke and the old Gode/Gode-
West road. This is mainly because the embankment of the road has blocked the
Wes
tern
Escar
pmen
t
Wes
tern
Dyke
N
Head Works
Wabi Shebelle
Wabi Shebelle
Main Canal
Figure-3.1
Wabi Shebelle
Wes
tern
Escar
pmen
t
1m High Spoil
Bank
Flood Plain
324
323
322 321 320
325
326
327
328
329
Flood Generated From Western Escarpment
Project, Flood Protection, Rehabilitation & Maintenance Works
Somali Regional State Page 12
Irrigation and Basin Development Bureau
transition of the runoff from the escarpment into the flood plain. Further, the excess
runoff that is coming along the embankment of the old Gode/Gode-West road has
started to create its own channel adding more for further breaching and sedimentation of
the main canal.
Figure 3-2, Flood Scenario After Construction of Gode-West/Gode Road 1
3.4 Flood From Wabi Shebelle
3.4.1 General
As floods generated from the highlands of Bale are regulated by the Melka Wakena
Dam, some 600 km upstream of Imi, the high flood volume that is generated within the
upper valley is significantly attenuated and their influence on the high stage of Wabi
Shebelle is minimal. As a result of this the flow of Wabi Shebelle in the lower valley
(where Gode West Irrigation Project is located) is influenced by the runoff generated in
the middle valley. Within the middle valley quite a number of tributaries join the Wabi
Shebelle both on its right and left banks. Notable tributaries worth mentioning are Ramis,
Golocha, Darole which join Wabi Shebelle on the right bank and Fafen, Ereer and
Daketa which join Wabi Shebelle on its left bank.
Wes
tern
Escar
pmen
t
Wes
tern
Dyke
N
Head Works
Wabi Shebelle
Wabi Shebelle
Main Canal
Figure-3.2
Wabi Shebelle
Wes
tern
Escar
pmen
t
1m High Spoil
Bank
Flood Plain
32
4
323
322 321 320
325
326
327
328
329
Flood Generated From Western Escarpment After The Construction of Gode West/Gode Road
Road From Gode
To Camp
Con
cent
rate
d Flo
w
Con
cent
rate
d R
unof
f
Flood F
rom
North
Eas
tern E
scar
pmen
t
Project, Flood Protection, Rehabilitation & Maintenance Works
Somali Regional State Page 13
Irrigation and Basin Development Bureau
The flow through most of these tributaries is seasonal flush flood with vehement
characteristic. Along the reach where these tributaries join Wabi Shebelle, up to about
30 km upstream of Imi, Wabi Shebelle River flows in a very deep gorge steeply sloping
down to the first five kilometers (25 m/km) after which the gradient gradually decreases.
As a result the river flow is well contained within its banks and flood hazard is
insignificant.
Between Imi and Gode, Madiso River (with a catchment area of about 12,295 km2) joins
Wabi Shebelle on the left bank. From Imi to the frontier, the Wabi Shebelle flows in a
vast alluvial plain with very gentle slope of 0.25 to 0.35 m/km. These small gradients
entail low velocity thereby retarding the incision power of the river. As a result of which
the natural free board of the river (the difference between the river bank and the water
surface) is minimal to accommodate any flow larger than the base flow. Thus, whenever
the river stage is high the entire stretch of land starting from Imi up to the frontiers is
always at high flooding risk.
As West Gode Irrigation Project is situated within the high risk flood zone it has been
affected quit a number of times where the recent major damage observed was by the
floods of 2014.
3.4.2 Flood Mitigation Measures at The Headwork
During the design of the headwork for West Gode Irrigation Project, special attention was
given to safe guard the headwork from the flood that will be generated from the high
stage of Wabi Shebelle. To alleviate the flood hazard due to overflow of Wabi Shebelle
at the headwork, a flood protection dyke with a 300 m long emergency spillway was
taken as the best solution course. Based on its geographic orientation with respect Gode
the flood protection dyke was designated as Western Dyke.
Figure-3.3 shows the mitigation measure for flood that could be generated from the Wabi
Shebelle. The Figure shows the general condition at the headwork prior to the
construction of the old Gode/Gode-West road. As illustrated in Figure-3.3, since the flood
from the over flow of Wabi Shebelle is of considerable magnitude, should the design
flood stage (i.e. 328.50) be exceeded a 300 m long emergency spillway was provided to
evacuate the flow before the Western Dyke is overtopped.
Project, Flood Protection, Rehabilitation & Maintenance Works
Somali Regional State Page 14
Irrigation and Basin Development Bureau
Figure 3-3, Anticipated Flood at Headwork & Proposed Mitigation Measures 1
The expected flood phenomenon given in Figure-3.3 was made in 1987 well before
the old Gode/Gode-West road was constructed and the effect of the road was not
taken into account. Due to this fact, after the construction of the old Gode/West-
Gode road, the original flood scenario is totally changed as given in Figure-3.4.
Now the flood that is generated from the western escarpment and the flood that
would be spilled over the Western Dyke has become one major concern for the
safety of the headwork and the main canal.
Evidently, the embankment of the road, see Figure 3-2, has partially blocked the
flood plain which was supposed to be a safe outlet for excess flood both from the
over flow of Wabi Shebelle and the western escarpment.
Recently (in 2013) the flood generated from the western escarpment was channeled
by the road embankment towards the main canal and the spoil bank was breached
at two locations, and serious damage was inflicted on both banks of the main canal.
To Wabi Shebelle
Flushing Channel
Sediment Ejector
Wabi Shebelle Diversion Channel
Spoil Bank (OGL+1m)
Spoil Bank (OGL+1m)
Wes
tern
Dyk
e (C
L=
328.
50)
Left Compartment Desilting Basin
Right Compartment Desilting Basin
Wei
r Axi
s
Intake
Main Canal
Under
Sluice
Escar
pmen
t
Geb
er-J
ebiy
e Se
tllm
ent
Wabi Shebelle
Wabi Shebelle
Wab
i She
belle
Wabi Shebelle
Clo
sure
Dam
Pro
pose
d 30
0m L
ong
Em
erge
ncy
Spi
llw
ay
Vehicle Bridge
Spoil Bank (OGL+1m)
Flood Plain
Figure-3.3Anticipated Flood Phenomenon at Headwork & Proposed Mitigation Measures
324
325
327
328
326
Project, Flood Protection, Rehabilitation & Maintenance Works
Somali Regional State Page 15
Irrigation and Basin Development Bureau
To alleviate this problem, in 2013 five ford crossings along the old Gode-W/Gode
road were proposed and a meter ditch provided to encourage the flow of the excess
runoff from the escarpment via the ford crossings into the flood plain. Further the 1m
spoil bank along the main canal was proposed to be replaced by a 2m high and 2Km
long compacted earth fill starting from IP-A.
In Figure-3-4 the flood mitigation measures proposed after the 2013 flood are given.
Figure 3-4, Flood Mitigation Measures After 2013 Flood 1
3.5 Proposed Remedial Measures for Head Works and Main Canal
Based on existing situation and the analysis given thereof and experience from
earlier remedial works the following flood protection and maintenance works are
forwarded for the head works and the main canal;
Newly Constructed 2,000m Long Compacted Fill Dyke
Spoil Bank (OGL+1m)
To Wabi Shebelle
Flushing Channel
Wabi Shebelle D
iversion Channel
Spoil Bank (OGL+1m)
Wes
tern
Dyk
e (C
L=
328.5
0)
Left Compartment Desilting Basin
Right Compartment Desilting Basin
Wei
r Axi
s
Intake
Main Canal
Under
Sluice
Geb
er-J
ebiy
e Se
tllm
ent
Wabi Shebelle
Wabi Shebelle
Wab
i Sh
ebel
le
Wabi Shebelle
Clo
sure
Dam
Vehicle Bridge
324
325
327
328
326
Escar
pmen
t
Figure-3.5 Flood Mitigation Measures Taken After The 2013 Flood
Flood Plain
Sediment Ejector
Gode-W
/Gode R
oad
Gode-W/Gode Road
RL
RL
FLO
W
FLO
W
RL
RL
FL
OW
FL
OW
Fo
rd C
/L
RL
FL
OW
FL
OW
Fo
rd C
/L
5 No. Modified
Ford Crossings
Project, Flood Protection, Rehabilitation & Maintenance Works
Somali Regional State Page 16
Irrigation and Basin Development Bureau
a. The operation and maintenance of the head work and the main canal is the
mandate of the Federal Government. With this regard the SRS should request
the concerned federal institution to expedite its responsibility.
b. Maintain all gates and electro-mechanical works at the intake, under sluice,
sediment ejector and vortex tube and make all gates and their hoisting
devices functional. It is recommended to give priority for the under sluice
gates so that they should be operational before the coming flood.
c. Remove all debris and obstructions from the intake and the under sluice and
re-fix of the trash racks.
d. Remove silt along the entire reach of the main canal from cahinage Km 0+000
up to Km 13+750 and maintain the cross section of the main canal as per the
levels and dimensions of the working drawing.
e. The twin segment basins should be reconstructed to the lines and dimensions
of their working drawing.
f. At present the main canal has a dead end at Km 13+600 (downstream of
cross regulator-2). This dead end combined with the hydraulic effects of the
cross regulator has greatly contributed for the sedimentation of the main canal
upstream. Further, the capacity of the two rejection spillways up stream of
Head Regulator-1 and Head Regulator-2 cannot accommodate the design
flow and will further endangers the stability of the head regulators and also
could lead the breaching of the main canal. Therefore, the construction of the
main canal from Km 13+750 up to the head land of South Gode should
commence as soon as possible. In due course, the two rejection spillways up
stream of Head Regulator-1 and Head Regulator-2 will be demolished and
their function will be overtaken by a new rejection spillway to be constructed
up stream of the head land of Gode South.
g. The Western Dyke should be fully maintained as per Figure 4-5.
h. The 2km long spoil bank that runs parallel to the main canal, starting IP-A up
to 2km should be replaced by a compacted fill embankment as shown in
Figure 3-6.
Project, Flood Protection, Rehabilitation & Maintenance Works
Somali Regional State Page 17
Irrigation and Basin Development Bureau
Figure 3-5, Profile & Cross Section of W/Dyke 1
i. On the left side of the main canal from km 3+500 up to Km 9+500 the entire
flat land is supposed to be a flood storage area for the excess flood that would
be generated from Wadi Bu-y. Therefore, during maintaining the left bank of
the main canal along this stretch special attention should be given (attention
both in fill material quality and workmanship quality).
j. Along the main canal starting from Km 0+750 up to km 9+400 there is no
crossing structure over the main canal. As there is no other access to the
river, this situation has forced the local community and their cattle to cross the
main canal at any place thereby adding much to the damage of the canal
banks and deposition of sediments. Therefore, to alleviate this problem
appropriate crossing should be designed and constructed between Km 0+750
until km 9+400.
k. The stop logs at Cross Regulator-1 and 2 should be replaced by a standard
gate with hoisting devices
l. All main off-take gates and their hoisting devise should be maintained.
Cross Section at Cha 0+000 Cross Section at Cha 2+000 Cross Section at Cha 3+000
328.50328.50 328.50
326.50 327.25 327.50 328.50
326.00
326.50
327.00
327.50
328.00
328.50
200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 3000 3200 3400 3600 3800 4000
Cross Section at Cha 4+000
328.50
OGL
Western Dyke Top Level
WesternEscarpment
Rt. Abutment of
Diversion Weir
Figure-3.7Longitudinal Profile of Western Dyke and Cross Sections
Chainage in m
Ele
vat
ion m
Proposed
Spillway
Project, Flood Protection, Rehabilitation & Maintenance Works
Somali Regional State Page 18
Irrigation and Basin Development Bureau
Figure 3-6, New Dyke from IP-A up to 2km Downstream 1
(OGL+2)
OGL 1
2
1
2
~75m
Dike
C/L Main Canal
C/L
2000
10000
Main
Canal
C/LOGLOGL
0 100 200 300 400 500 2000 2100 2200 2300 2400 2500 2600 2700
ENDIP-A
OGL
(OGL+2)
Ele
vati
on
(m
)
Distance (m)
Longitudinal Profile (Not to Scale)
Plan (Scale 1:100) Section A-A (Scale 1:100)
A A
Project, Flood Protection, Rehabilitation & Maintenance Works
Somali Regional State Page 19
Irrigation and Basin Development Bureau
4 Flood Protection and Maintenance Works at Farm Work
4.1 General
In this section the flood protection works and other maintenance works needed at
West Gode farm area is elaborated.
As in any low land irrigation project West-Gode Irrigation scheme is susceptible for
external floods and should be protected from the adverse effect of the same.
In earlier designs, adequate measures were taken to safeguard the farm area from
external floods. Then it was proposed to construct a dike and a flood way to transit
external floods before reaching the farm work. As a result the left bank of primary
canal GW1-00 (which takes off from the main canal and traverses along the eastern
and northern boundaries of Gode-West) was supposed to act as a dyke to protect
the farm area from floods that are coming from the Western and Northern areas. The
height of the left bank of primary canal GW1-00 was 3m above the natural ground
level.
As the flood from the Northern catchment is huge (about of 580 m3/s) a flood way
was proposed to evacuate the flood generated from this area before it reaches the
farm.
4.2 Anticipated Flood at the Farm Work
Figure 4-1 shows the depicted catchment areas that culminate flood to the farm
area. The two important flood generating areas are;
The Northern catchment area (wadi Bu-y) that is responsible for the flood that
endangers the irrigation system on the Northern boundary. The total catchment
area of Wadi Bu-Y is estimated to be 10,500 km2 with a total flood magnitude of
about 580 m3/s (NEDECO/WRDA 1986).
The North-Eastern catchment area was estimated to be around 500 km2 with a
flood magnitude of 260 m3/s (NEDECO/WRDA 1986).
On the Easter side the flood coming from the Northern wadis are combined with the
flood generated from Eastern wadis that could cause huge danger to the entire farm.
Project, Flood Protection, Rehabilitation & Maintenance Works
Somali Regional State Page 20
Irrigation and Basin Development Bureau
Unless the flood drain and the embankment of primary canal GW1-00 are
constructed (for layout and arrangement of the flood way see Section 4.3) the
occurrence of the maximum probable flood of Wady Bu-y could even negatively
affect the main canal starting from Km 3+500 up to Km 9+500.
Figure 4-1, Flood Generating Wadis 1
4.3 Present Situation
4.3.1 Farm Works
During the site visit the general condition and status of the constructed canals, drains
and irrigation infrastructures was assessed. It was observed that most of the canals
and drains suffer siltation due to lack of maintenance. All of the primary canals are
silted up and primary off-take gates need maintenance.
In the course of the site visit the team has observed the ongoing excavation of an
interceptor drain on the Northern boundary of the farm that runs parallel to primary
canal GW1-00. This is mainly to transit the flood coming from Wadi Bu-y into Wabi
Shebelle. It was noted that the excavation is a kind of makeshift excavation to block
the current flood from entering the farm area. The interceptor drain under excavation
has no defined cross section and other geometric parameters such as depth, bed
slope, side slope etc.
By and large, most of the problems at the farm work are due to lack of preventive
and regular maintenances. In addition part of the problem is due to lack of
Main Canal
Wabi Shebelle
Main
Dra
inN
/E F
lood D
rain
Main CanalLegend
Main Drain
DykeFlood Drain
Esc
arpm
ent
Wes
tern
Dyke
Road From Gode
N
Head Works
To Camp
Wabi Shebelle
Wabi Shebelle
Breached
Main Canal
Main Canal
To Gode
Depicted Catchment Areas at Gode West
Main Canal
To South Gode
Esc
arpm
ent
Escarpment
Esc
arp
ment
Figure 5-4
Northern CatchmentArea (Wadi Bu-y)
North-E
astern
Catchm
ent Area
Nor
th-W
este
rn
Cat
chm
ent A
rea
Project, Flood Protection, Rehabilitation & Maintenance Works
Somali Regional State Page 21
Irrigation and Basin Development Bureau
construction quality control. As stated above, the other major attribute for the
problem on the farm works is the damage caused by external floods. Parallel with
this the internal drainage of the system is dilapidated and the main drain that
evacuates excess runoff from the system is totally silted up.
4.4 Proposed Remedial Measures for Farm Works
Based on existing situation and the analysis given thereof and experience from
earlier remedial works the following flood protection and maintenance works are
forwarded for the farm work;
a. On the outset, the Irrigation Bureau should reestablish a scheme
administration unit that will look after the operation, maintenance and water
management matters. The scheme administration unit should be well
organized and equipped; both in manpower and equipment and its duties and
responsibilities shall be defined.
b. Once the scheme administration unit is reestablished, Water Users
Associations shall be established at Tertiary, and Primary level. The Water
User Associations shall be established based on appropriate bylaw.
c. All primary canals should be desilted and their side and long slope shall be
reconstructed to the levels and dimensions of their working drawings.
d. The left side embankment of primary Canal GW1-00 shall be inspected and
shall be compacted to the levels and dimensions as per the working drawing.
e. Invariably all existing irrigation canals should be desilted and drainage canals
should be deweeded and desilted. Parallel with primary off-take gates and
hoisting devises should be inspected and maintained and/or replaced. As
most of the farm plots are infested by weeds and wild bushes they should be
devoid of any obstacle by clearing and grabbing.
f. Once the left side embankment of of primary canal GW1-00 is built to its
levels and dimensions a flood way that could intercept the flood from Wadi
Bu-y and the flood from the Eastern Wadis should be excavated. The location,
layout and cross sections of the flood way is given in Figure 4-2 and Figure 4-
3.
Project, Flood Protection, Rehabilitation & Maintenance Works
Somali Regional State Page 22
Irrigation and Basin Development Bureau
Figure 4-2, Location and Layout of Floodway 1D
W2-00
31,0
00.0
0
32,0
00.0
0
33,0
00.0
0
34,0
00.0
0
35,0
00.0
0
36,0
00.0
0
37,0
00.0
0
48,000.00
47,000.00
46,000.00
45,000.00
DW2-00
DW2-00
38,0
00.0
0
39,0
00.0
0
40,0
00.0
0
41,0
00.0
0
42,0
00.0
0
44,000.00
43,000.00
Legend
Main Drain
Flood Drain
30,0
00.0
0
29,0
00.0
0
28,0
00.0
0
27,0
00.0
0
49,000.00
50,000.00
51,000.00
52,000.00
53,000.00
54,000.00
48,000.00
47,000.00
46,000.00
45,000.00
49,000.00
50,000.00
51,000.00
52,000.00
53,000.00
GW
1-0
0
GW
1-00-04
DW1-01
DW1-00
DW1-00
GW1-00
GW
1-0
0
DW
1-00
DW
-00
DW-00
Secondary Drain
Tertiary Drain
FW
-1
FW-1
FW-1CHA 0+000 (FW-1)
Project, Flood Protection, Rehabilitation & Maintenance Works
Somali Regional State Page 23
Irrigation and Basin Development Bureau
Figure 4-3, Typical Cross Section of the Floodway 1
21
GW1-00
C/L
(OGL+3)
FW-1
C/L
Typical Section Km 0+000 - End of GW1-00
21
30m Min.
GW1-00-04
C/L
Typical Section End of GW1-00 - End ofGW1-00-04
(OGL+3)
Typical Section End of GW1-00-04 - 11+700
1:21:2
45m
OGLBL
FW-1
C/L
30m Min.
1:21:2
45m
OGLBL
FW-1
C/L
1:21:2
45m
OGLBL
Spoil Tip To Dump Excavated
Material Spoil Tip To Dump Excavated
Material
Spoil Tip To Dump Excavated
Material
10m Min. 10m Min.
10m Min.
10m Min. 10m Min.
OGL
Project, Flood Protection, Rehabilitation & Maintenance Works
Somali Regional State Page 24
Irrigation and Basin Development Bureau
5. Tentative Cost Estimate
West-Gode Irrigation Project Cost Estimate For
Flood Protection, Rehabilitation & Maintenance Work
1 Flood Protection at Headwork Unit Qty. Rate Amount
1.1 Rehabilitation and maintenance of Western Dyke m3 15,000
1.2 Compacted fill for new dyke from IP-A up to 2km d/s m3 24,000
2 Headwork
2.1 Electro-Mechanical Work
2.1.1 Clearing debris from the under sluice and intake gates LS 15,000
2.1.2 Supply and install intake gates and hoisting devices No. 4
2.1.3 Supply and install under sluice gates and hoisting devices No. 2
2.1.4 Supply and install sediment ejector gates and hoisting devices No. 4
2.1.5 Supply and install vortex tube gates and hoisting devices No. 2
2.1.6 Supply and install trash racks Set 1
2.2 Civil Work
2.2.1 Divide wall from intakes to sediment basin transition m3
2.2.2 Channel Excavation for Desilting Basin m3 16,800
2.2.3 Channel Excavation for Desilting Basin m3 5,800
2.2.4 Excavation in Open Cut m3 6,400
2.2.5 Non Woven Fabric m2 13,000
2.2.6 Dry Stone Pitching m3 5,800
3 Main Canal
3.1 Electro-Mechanical Work
3.1.1 Supply and install Main off take gates and hoisting devices No. 4
3.1.2 Supply and install gates and hoisting devices at cross regulator 1 & 2 No. 8
3.2 Civil Work (Main Canal & Main Road)
3.2.1 Excavation m3
3.2.2 Channel Excavation m3 320,000
3.2.3 Compacted Fill m3 150,000
3.2.4 Supply & Compact Gravel Material for Road m3 50,000
3.2.5 Maintenance work on cross regulator-1 and 2 LS 75,000
3.2.6 Maintenance work for emergency spillway-1 LS 25,000
3.2.7 Maintenance work for emergency spillway-2 LS 80,000
4 Farm Work
4.1 Excavation of Floodway m3 2,199,600
4.2 Compacted fill for the left embankment of primary canal GW1-00 m3 388,200
4.2 Clearing silt and forming primary canals PQ 85,000
4.3 Maintaining, forming and gravel surfacing of all connecting roads m3 25,000
4.3 Maintenance work on all primary canal off take gates No. 8
4.4 Clearing silt and forming tertiary canals PQ 15,000
4.5 Clearing silt and forming tertiary drains PQ 15,000
4.6 Clearing silt and forming secondary drains PQ 10,000