WELDING MATERIAL CONTROL PROCEDURE *note: this is the sample document for the related job only *author: [email protected] TABLE OF CONTENTS 1. SCOPE 2. REFERENCE 3. RESPONSIBILITIES 3.1 SITE MANAGER 3.2 QC MANAGER 3.3 QA ENGINEER 3.4 QC INSPECTOR 4. WELDING MATERIAL CONTROL 1.0 SCOPE This procedure shall outline the control of welding materials in welding works for the EPCC of Two (2) Nos crude Storage Tank 2.0 REFERENCE 1) PTS 64.51.01.31 - STANDARD VERTICAL TANKS ERECTION & TESTING (Section 6.5 – Welding Consumables) 2) IS/D-322 - FIELD INSPECTION & TESTING PROCEDURE 3) IS/D-310 - MATERIAL CONTROL PROCEDURE 4) KOBE / ESAB - MANUFACTURE RECOMENDATION 3.0 RESPONSIBILITIES 3.1 Site Manager Shall be responsible for the full implementation of this procedure. He shall assign knowledgeable Material Controllers / Welding Foreman who will be able to distinguish all types welding consumables. 3.2 QC Manager Shall be responsible for ensuring that all personnel involved are indoctrinated and shall assign personnel to conduct monitoring and audits for compliance to this procedure. 3.3 QA Engineer Shall be responsible for Supervision of Inspection activities, monitoring and documenting inspection / monitoring activities. 3.4 QC Inspector Shall inspect welding material control on daily basis and document any deviation from this procedure.

Upload: jacquesmayol

Post on 18-Apr-2017

223 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Welding Material Control Procedures

WELDING MATERIAL CONTROL PROCEDURE*note: this is the sample document for the related job only*author: [email protected]

TABLE OF CONTENTS

1. SCOPE 2. REFERENCE 3. RESPONSIBILITIES3.1 SITE MANAGER 3.2 QC MANAGER3.3 QA ENGINEER3.4 QC INSPECTOR4. WELDING MATERIAL CONTROL

1.0 SCOPE This procedure shall outline the control of welding materials in welding works for the EPCC of Two (2)Nos crude Storage Tank

2.0 REFERENCE1) PTS 64.51.01.31 - STANDARD VERTICAL TANKS ERECTION & TESTING (Section 6.5 –Welding Consumables)2) IS/D-322 - FIELD INSPECTION & TESTING PROCEDURE3) IS/D-310 - MATERIAL CONTROL PROCEDURE4) KOBE / ESAB - MANUFACTURE RECOMENDATION

3.0 RESPONSIBILITIES3.1 Site ManagerShall be responsible for the full implementation of this procedure. He shall assign knowledgeableMaterial Controllers / Welding Foreman who will be able to distinguish all types welding consumables.3.2 QC ManagerShall be responsible for ensuring that all personnel involved are indoctrinated and shall assignpersonnel to conduct monitoring and audits for compliance to this procedure.3.3 QA EngineerShall be responsible for Supervision of Inspection activities, monitoring and documentinginspection / monitoring activities.

3.4 QC InspectorShall inspect welding material control on daily basis and document any deviation from this procedure.

4.0 WELDING MATERIAL CONTROL4.1 All welding materials shall be received by the Material Controller / Welding Foreman. He shall checkwelding material condition, damage, material identification and batch / lot / heat / number. All weldingmaterials received shall be accompanied by an Inspection Certification form manufacturer or supplier. The QA Engineer shall review the manufacturers inspection certificates for compliance to thespecifications and if acceptable sign and stamp “Issued For Construction”. The certificate shall besubmitted to contractor for review

Page 2: Welding Material Control Procedures

4.2 The Material Controller / Welding Foreman shall check that sufficient quantity is stored in baking /holding oven for daily use. The Material Controller / Welding Foreman shall issue as follows:1. Issue electrodes by priority,a. re-baked electrodesb. first baked electrodesc. new electrodes2. Check size and type of welding material to be issued3. Issued maximum quantity of 5kg for each portable oven4. For GTAW rods, original containers shall be issued. For stainless steels the container or welders quiver shall be clearly marked by paint or colored tape with the same color identification asgiven by the consumable manufacturer. 5. Issue of portable oven marked with Welders no only to respective welders.6. Issues of consumables are to be recorded on Consumable Issue Report.

4.3 The Material Controller / Welding Foreman shall monitor / check his welder’s portable oven (quivers)are plugged to power source all the time. At the end of the day, he shall gather all quivers and take tothe welding material control room.

4.4 After receiving all portable ovens the Material Controller / Welding Foreman shall place all segregatedelectrodes and place at top portion of baling oven and shall be issued first on the next day. Returnedelectrodes shall be re baked only once. There after they shall disposed of as scrap.