As the primary WCR 49 Corridor project construction comes to an end, Weld County is pleased to announce the starting of the last phase of the project. The last key link to the WCR 49 Corridor is construction of WCR 47 from WCR 60 ½ to SH 392 which will complete four lanes of traffic from I-76 to SH 392. This construction will begin in the Fall of 2017. To expedite the completion date and decrease the overall construction time, WCR 47 will be closed during construction. Cross Roads such as WCR 62 and 64 will remain open during this time for cross traffic. A detour plan has been prepared to accommodate the cross traffic during construction. The map below shows the anticipated closure locations and the recommended detour map. Weld County Public Works will be hosting an October neighborhood meeting to discuss. For more information related to the meeting and the upcoming closure please contact us at [email protected]. WCR 47 Closure and Detour Weld County Department of Public Works September 2017 Newsletter Weld County Road 49 Corridor Project Weld County Road 49 Corridor Project Open 5 lanes through Weld County Road (WCR) 44 Completion of WCR 34 intersection Anticipated September 2017 Project Milestones Join us at the public meeting as we kick off construction of WCR 47. When? Tuesday October 3, 2017 What time? 6 pm to 7:30 pm Where? Weld County Administration Building, Events Room 1150 O St., Greeley, Colorado 80631 Join us at the public meeting! website: www.weldgov.com email: [email protected] WeldCountyGovernment @WeldGov WeldCountyCO Contact Information 970•573•6800 DETOUR DE T OUR WCR 49 WCR 51 WCR 45 WCR 43 WCR 41 WCR 53 WCR 49 WCR 47 WCR 60.5 WCR 49 WCR 62 16th St 18th St Fern Ave WCR 64 WCR 66 Greeley-Weld County Airport Greeley Greeley 85 34 D E T O U R DETOUR 8th St

Upload: others

Post on 16-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Weld County Road 49 Corridor Project - Weld County, Colorado · Weld County received a $40,000 grant from the State of Colorado to install a state of the art Roadside Weather Information

As the primary WCR 49 Corridor project construction comes to an end, Weld County is pleased to announce the starting of the last phase of the project. The last key link to the WCR 49 Corridor is construction of WCR 47 from WCR 60 ½ to SH 392 which will complete four lanes of traffic from I-76 to SH 392. This construction will begin in the Fall of 2017.

To expedite the completion date and decrease the overall construction time, WCR 47 will be closed during construction. Cross Roads such as WCR 62 and 64 will remain open during this time for cross traffic.

A detour plan has been prepared to accommodate the cross traffic during construction. The map below shows the anticipated closure locations and the recommended detour map. Weld County Public Works will be hosting an October neighborhood meeting to discuss.

For more information related to the meeting and the upcoming closure please contact us at [email protected].

WCR 47 Closure and Detour

Weld County Department of Public Works September 2017 Newsletter

Weld County Road 49 Corridor ProjectWeld County Road 49 Corridor Project

Open 5 lanes through Weld County Road (WCR) 44

Completion of WCR 34 intersection

Anticipated September 2017 Project Milestones

Join us at the public meeting as we kick off construction of

WCR 47.

When? Tuesday October 3, 2017

What time? 6 pm to 7:30 pm

Where? Weld County Administration Building, Events Room 1150 O St., Greeley, Colorado 80631

Join us at the public meeting!

website: www.weldgov.com

email: [email protected]

WeldCountyGovernment

@WeldGov

WeldCountyCO

Contact Information

970•573•6800

DE

TO

UR DETOUR

WCR

49

WCR

51

WCR

45

WCR

43

WCR

41

WCR

53

WCR

49

WCR

47

WCR 60.5

WCR 49

WCR 62

16th St18th St

Fern

Ave

WCR 64

WCR 66

Greeley-WeldCountyAirport

GreeleyGreeley

85

34

DETOUR

DE

TO

UR

8th St

Page 2: Weld County Road 49 Corridor Project - Weld County, Colorado · Weld County received a $40,000 grant from the State of Colorado to install a state of the art Roadside Weather Information

Weld County received a $40,000 grant from the State of Colorado to install a state of the art Roadside Weather Information System (weather station) along WCR 49 to communicate the weather patterns with Weld County, surrounding cities, as well as the Colorado Department of Transportation in real time.

The weather station will be able to observe both air and roadway temperatures to aid the county in determining maintenance needs during weather events. In addition, the weather station will be able to communicate via existing fiber lines along the corridor with the incident management desk at the Weld County Public Works Office.

The primary benefit of this weather station is to improve safety for travelers and commuters in the region during extreme weather conditions. The operations crew for Weld County can instantly find out about the weather and plan on deploying snowplows and applying deicer accordingly. The weather station can also alert the county public Works, Office of Emergency Management, as well as the Sheriff’s office of potential flooding.

Sign up to receive these newsletters at www.weldgov.com

Winter is coming!

Project Progress

Weld County Department of Public Works

Weld County Road 49 Corridor Project

The weather station will ultimately provide for a safer CR 49 Corridor.

Removal of the old WCR 49. Completed cut and fill.

Last remaining portion of old WCR 49 pavement on the project.