welcome to boulder valley school district. cspma – agenda – 2/21/14 8:00 – 8:30 meet &...

34
WELCOME TO BOULDER VALLEY SCHOOL DISTRICT

Upload: sara-diddle

Post on 30-Mar-2015

215 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

WELCOME

TO

BOULDER VALLEY SCHOOL DISTRICT

Page 2: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

CSPMA – Agenda – 2/21/14• 8:00 – 8:30 Meet & Greet• 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Operations)• 8:40 - 9:15 Taking Energy Savings to Next Level – Jeff Medwetz• 9:15 – 10:00 Flood Recovery “Crest View” – Mike Cuskelly• 10:00 – 10:15 Break• 10:15 – 11:00 Flood Recovery – Boulder High – Tom Blahak• 11:00 – 11:30 CSPMA Business• 11:30 – 12:00 Round Table Discussions• 12:00 – 12:30 Lunch • 12:30 – 12:45 Closing Remarks - Adjourn

Page 3: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

BVSD - Flood Recovery Overview

• BVSD incurred costs close to $4.8 Million• Closed all schools - 4 days • Crest View Elementary - closed for 12 days

– Temporary facilities YMCA for a portion of students

• Jamestown Elementary – Temporary facilities– Building okay - closed due to town infrastructure

• 50 of 56 schools were affected – 25 minor – mostly roof leaks – ceiling tile– 17 moderate – site & building damage– 8 significant damage - site and buildings

Page 4: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

BVSD - Flood Recovery To Date

• 95% complete with restoration work, most completed by end of November 2013

• Remaining work– Landscaping, flooring, sewer line, stadium repairs, & creek bank

stabilization

• Working with FEMA, Flood Insurance, CSDSIP– Flood insurance for three of the worst hit sites

• Crest View• Foothill• Boulder High

• CSDSIP – Treated District as one event - $100k Deduct.

• Coverage Order – Flood Insurance, CSDSIP, then hopefully FEMA covers the remaining.

Page 5: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Crestview & Boulder Flood Recovery

• Crest View Site & Building– Flooded 4 times from 9/11 – 9/16 by Four Mile Creek– 75% of building flooded – 49,225 Sq. Ft.– 58 rooms damaged– 80% of site flooded

• Boulder High sports fields– Major flooding from Boulder Creek – Over 3,300 cubic yards mud/debris left on 4 acres– Practice fields, softball field, volley ball pits severely damaged– Sanitary Sewer line across Boulder Creek - gone

Page 6: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Crestview Elementary Flooding

– Flooding video– Arial pictures before & during– Look at Damage– Recovery Plan / Strategy / Challenges– Look at Work Accomplished– Follow up work– Cost Summary– Lessons Learned

Page 7: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Crest View Flooding – Bring a boat !!

Page 8: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Crest View Flooding - Playground

Page 9: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Crest View Flooding – New Cafeteria

Page 10: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Crest View Flooding – Classroom wing

Page 11: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Crest View Flooding – Air intake/Univent

Page 12: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Crest View Flooding – Main Hallway

Page 13: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Crest View Flooding – 25 Classrooms

Page 14: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Crest View Flooding – New Kindergarten wing

Page 15: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Crest View Flooding – Work Room

Page 16: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Crest View Flood Damage – around building

Page 17: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Crest View Flood Damage – around building

Page 18: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Crest View Flood Damage – inside building

Page 19: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Crest View Flood Damage - Kitchen

Page 20: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Crest View Flood Damage - Cafeteria

Page 21: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Crest View Flood Damage - Classroom

Page 22: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Crest View Flood - Library

Page 23: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Area of Crest View Damaged

Page 24: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Crestview Flood Recovery

• Flooding started 9/11, brought in Servpro the 9/12 Thu• • Servpro had extracted water & mucked out several times

and removed a lot of carpet by Mon 9/16 – (video)

• Flood water was still coming in the building - Mon 9/16

• Tuesday morning 9/17 met with Justin, Brandon, & Danaya

• They felt one month we could have the school ready

Page 25: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Crestview Flood Recovery

• Reported back to the Crisis Team

• Superintendent’s Directive – Open 9/30 – 2 weeks!

• I didn’t think it was possible – too many issues.

• Met again with Justin, Brandon, & Danaya…they felt it could be done…everything had to go right

• That evening on 9News Superintendent announced we will

open 9/30!

• With work underway revised plan to occupy in 2 weeks.

Page 26: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Plan to Occupy in Two Weeks

• Complete hazard removal - asbestos / contaminants / mold / testing certification

• Wall demo/reconstruction – sheetrock fire taped, painted if possible

• Unit Ventilators cleaned & sanitized• Bare concrete floors – area rugs / carpet remnants• Temporary work tops less cabinets• Temporary/donated Crates / boxes / make-shift shelving• Temporary electrical where needed• Temporary Cafeteria / Serving line / food brought in

– Paper plates / disposable forks, knives, spoons

Page 27: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Crestview Flood Recovery – Success!

• Amazingly Crest View opened for school 13 days later!• Keys to Success was a strong and experienced TEAM

– SERVPRO – 75 staff– Adolfson & Peterson – 25 staff

• US Engineering• Lundquist• Accent Electric

– Colorado Hazard Control – 10 staff– Blue Mesa Environmental– Bailey’s Moving– BVSD Maintenance & Operations staff– Teachers, parents, and numerous other Volunteers

• 110 plus people - working 24/7 for two weeks• A lot of resources with a tremendous effort!

Page 28: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Crestview Flood Recovery Strategy

• Phased approach with Servpro, A & P, & CHC – Four Phase Asbestos removal plan – with containment – Over-night testing results

• Servpro – Demolition / Remediation in non-asbestos areas, exterior clean-up

• A & P – Sheet rock install/finish, work tops, shelving plumbing, electrical, univents

• Servpro / A & P worked in areas non containment areas

• Coordinated approach by tasks with teams

Page 29: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Challenges

• Asbestos – 35% of damaged area• Unit Ventilators - contaminated• Kitchen / Walk-in Freezer / Cooler• Cafeteria / Boulder County Health Dept.• Hazardous mud & muck around building• Sinks in countertops & casework• Contaminated casework – woodwork

– Base cabinets, closet support pedestals, shelving

• Lost desks, shelving, other storage

Page 30: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Pictures of Challenges & Work

Page 31: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Follow-up Work – After hours/weekends

• Library Furniture / Desks, bookcases - Nov• Kitchen completed - Nov• Carpet completed - Dec• Casework completed – Feb• Utilized Bailey’s moving for carpet & casework• Epoxy flooring kitchen/bathrooms - Oct• Vinyl floor in Cafeteria / art room – spring break• Trim painting / punch list – spring break• Playgrounds, site work, sports fields - Nov

Page 32: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Cost Summary of Total Restoration

Clean-up, Remediation, Demolition $1.38 M

Asbestos Removal / Testing $ 220 K

Re-construction, mechanical, electrical $ 666 K

Flooring – carpet / sheet vinyl $ 241 K

Site restoration – sports fields / playground $ 274 K

Building contents $ 150 K

Moving $ 18 K

YMCA Flood Camp $ 70 K

Maintenance labor $ 20 K

IAQ Testing $ 10 K

Total to date $3.05 M$49 / SF Building only

Page 33: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Lessons Learned

A 75% flood damaged school can open two weeks later!

Put the maximum amount of highly qualified resources to accomplish the task!

Page 34: WELCOME TO BOULDER VALLEY SCHOOL DISTRICT. CSPMA – Agenda – 2/21/14 8:00 – 8:30 Meet & Greet 8:30 – 8:40 Introductions – Don Orr (Asst. Superintendent

Lessons Learned

It was more fun doing the actual work versus the accounting with FEMA