welcome! building coordinator program quarterly meeting · 24/10/2018  · welcome! building...

71
Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018

Upload: others

Post on 26-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

Welcome!

Building Coordinator ProgramQuarterly MeetingFriday, October 26, 2018

Page 2: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

Facilities Maintenance and Operations:

A Strategic Approach

Jeff BenjaminExecutive DirectorFacilities Services

E-mail: [email protected]

Page 3: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

Facilities/Construction Management

Maintenance and Operations: A Strategic

Approach

3/22/2016 3

Page 4: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

The day-to-day activities necessary for the building/built structure, its systems and equipment, and its occupants/users to perform their intended function.

The Challenge: Determining when and where these activities take place to maximize optimal performance within existing budget and labor constraints while meeting the end user’s needs and desires.

University of Houston

OPERATIONS & MAINTENANCE

Facilities/Construction Management 4

Page 5: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

Begin with establishing the ground rules:

• Develop common definitions• Develop clear processes and timelines• Established metrics to track performance• Prioritize efforts strategically to miximize

facility investment

Today’s goal is to introduce this effort and obtain feedback from our stakeholders

University of Houston

OPERATIONS & MAINTENANCE

Facilities/Construction Management 5

Page 6: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

BACKGROUND

• Since 2015, F&CM receives on average 4300 work orders each month• Of these, 56% are corrective, 44% are Preventive• The average Corrective WO takes 4.4 hrs and costs $287, this equates to an

FTE of 74 personnel assuming a .85 productivity rate.• The average Preventive WO takes 1.63 hrs and costs $70, this equates to an

FTE of 21 personnel assuming a .85 productivity rate.• Annual estimated spend: $9.9 Million• Per capita spend: $0.68/gsf• For every $1 spent on the stewardship of buildings, you offset $4 or more

in capital investment

Facilities/Construction Management 6

Page 7: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

BACKGROUND (Con’t)

• WO’s are largely triaged by Call Center and dispatched based on trade/shop

• WO’s are also triaged by a structured but undefined work group consisting of MIC, FS, Planning, FPC reps.

• WO’s are typically funded by E&G, or Auxiliaries, SHRL, CRWC, Student Life and Departments

• The backlog of WO’s was purged in December, and has steadily climbed since that time.

• There is a need for a strategic approach to how work is classified, prioritized, and accomplished

Facilities/Construction Management 7

Page 8: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

KEY DEFINITIONS

• Alteration • Capital Project• Corrective Maintenance• Deferred Maintenance• Emergency Work Order/R-1 Emergency Work

Order• Facility• Maintenance Project• Minor Project • Minor In-house Construction (MIC)• Linear Facility• New Construction• Preventive Maintenance

• Project• Renovation/Restoration• Repair• Routine Work Order• Urgent Work Order• Work Request• Work Order• Work Request Triage Committee

Facilities/Construction Management 8

Page 9: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

ALTERATION

The work required for interior or exterior rearrangements of an existing facility or part thereof to improve the use of the facility for its current purpose. This includes associated real property equipment. Additions, expansions and extensions are not alterations. An alteration should never result in a change in facility’s functional purpose.

Facilities/Construction Management 9

Page 10: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

CAPITAL PROJECT

• Any project whose total project cost exceeds $1 million.• May be new construction, alteration, renovation, repair, or

maintenance.

Facilities/Construction Management 10

Page 11: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

CORRECTIVE MAINTENANCEThe recurring, day-to-day, periodic, or scheduled work required to sustain a facility to such a condition that it may be used for its designated purpose. The term includes work undertaken to prevent damage to a facility that otherwise would be more costly to repair.

There are three main types of maintenance:• Emergency/R-1 Emergency• Urgent• Routine

Extensive maintenance, such as Boiler Inspections/Chiller Over-hauls, etc… may result in a maintenance project.

Facilities/Construction Management 11

Page 12: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

DEFFERED MAINTENANCE

The practice of postponing maintenance activities such as repairs on both real property (i.e. infrastructure) and personal property (i.e. machinery) in order to save costs, meet budget funding levels, or realign available budget monies.• Maintenance/Repair that is required to maintain/return the building

in optimal design condition that does not directly impact health, life safety, research or operations.

• Work may be deferred because of building age, utilization, planned recapitalization, planned obsolescence or other business decisions.

Facilities/Construction Management 12

Page 13: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

EMERGENCY/R-1 EMERGENCY

• Damage to facility, risk to health or life safety, shut down of critical operations/research. Response will arrest emergency (i.e. prevent further damage, or risk to health and life safety).

• Immediate response (Call out if after hours) • Arrest Emergency in less than 2 hours• Arrests emergency condition only• Once arrested, assess corrective measures required. If easily fixed do so;

otherwise, close work order and issue new Work Order with appropriate classification for corrective work (Urgent/Routine, or Project).

• R-1 emergencies historically applied to labs and other critical systems and spaces where work or sensitivity requires immediate response.

Facilities/Construction Management 13

Page 14: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

FACILITY

A building, structure, or linear structure, including all associated components, dedicated solely to supporting the mission and necessary for making it complete and usable. Components include real property equipment associated with the facility.

Facilities/Construction Management 14

Page 15: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

MAINTENANCE PROJECT

A project that involved maintaining a facility or linear facility, where the scope and magnitude of work typically requires expertise or man-power that exceed the capabilities of the in-house shops.Examples include:

High Voltage Substation PMsStorm Sewer Clean-outBuilding Exterior Cleaning

Facilities/Construction Management 15

Page 16: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

MINOR PROJECT

A project whose total project cost is less than $300,000, but may be approved for amounts up to $1,000,000. These projects may include maintenance, repair, alteration, restoration, or new foot print.

Facilities/Construction Management 16

Page 17: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

MINOR IN-HOUSE CONSTRUCTION

• In house shop that specializes in minor renovations, repairs, and alterations.

• Trades are mostly concentrated in carpentry, but the shop can coordinate minor electrical, HVAC, plumbing, and other subs as needed to execute a project.

• Organized under the Minor Planned Projects Director

Facilities/Construction Management 17

Page 18: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

LINEAR FACILITY

A facility whose function requires that it traverse land (such as a road, rail line, pipeline, pavement, or utility distribution system). Includes distribution systems that provide a common service or commodity to more than one building or structure. The individual assets associated with this system are components of that linear structure; such as, valves, distribution lines, switches, or manholes.

Facilities/Construction Management 18

Page 19: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

NEW CONSTRUCTION

Construction addressing facility requirement deficiencies. This includes both construction of new facilities and expansion of existing facilities.

Facilities/Construction Management 19

Page 20: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

PREVENTIVE MAINTENANCE

• The care and servicing by personnel for the purpose of maintaining equipment in satisfactory operating condition by providing for systematic inspection, detection, and correction of incipient failures either before they occur or before they develop into major defects.

• The primary goal of maintenance is to avoid or mitigate the consequences of failure of equipment. This may be by preventing the failure before it actually occurs which Planned Maintenance and Condition Based Maintenance help to achieve. It is designed to preserve and restore equipment reliability by replacing worn components before they actually fail.

Facilities/Construction Management 20

Page 21: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

PROJECT

• Maintenance/Repair/Alteration/Renovation that is required to maintain/return the building in/to its optimal design condition that does not directly impact health, life safety, research or operations.

• Typically requires >32 Labor Hours, or costs more than $10,000• Respond as quickly as possible, but complete within an agreed upon

timeframe that takes into account scope complexity, budget, and customer needs/desires.

• Example: Restroom renovation, Drainage Issues, Building Envelope repairs, Electrical Panel Installation to provide additional power to a building, Full Panel Street Repair

• Shops may accomplish, but also may be aggregated to Minor Planned Projects, Small Capital Projects, or Capital Projects groups or deferred based on Triage Committee, MPEC, or by other decision makers

Facilities/Construction Management 21

Page 22: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

URGENT WORK ORDER

Facilities/Construction Management 22

• Work has a large impact on operations, comfort, or mission of customer but does not endanger life or health, research, or operations

• Respond as quickly as possible, but complete within 24 hours.

• Address issue and correct underlying cause if possible within 7 days, may require reclassification.

• Example: Hot/Cold Calls, loss of water/hot water, power outage to an outlet or small portion of a building, clogged toilets, etc…

Page 23: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

RENOVATION/RESTORATION

Renovation or reconstruction activities (including facility replacements) needed to keep existing facilities modern and relevant in an environment of changing standards and missions. Restoration extends the service life of facilities, restores lost service life, or updates and or alters a facility for adaptive reuse.

Example: The Campus Core Projects

Facilities/Construction Management 23

Page 24: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

REPAIR

The work required to restore “a facility, system, or component to such a condition that it may effectively be used for its designated functional purpose.”

Consideration should be made as to whether full replacement will be more cost effective.

Facilities/Construction Management 24

Page 25: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

ROUTINE WORK ORDER

• Maintenance/Repair/Alteration/Renovation that is required to maintain/return the building in/to its optimal design condition that does not directly impact health, life safety, research or operations.

• Respond as quickly as possible, but complete within 30 days.• Address issue and correct underlying cause if possible (less than 32

labor hours/$10,000).• If exceeds threshold, triage and create project work order.• Example: Roof patching, replace cracked window, repair

carpet/floor/wall, minor electrical repairs, replace ceiling tiles, patch pot-hole, etc…

Facilities/Construction Management 25

Page 26: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

WORK REQUEST

• A formal request, made through the centralized maintenance management system (FAMIS) to report a need for repair, alteration, or construction.

• Typically entered by customer through FIX-IT.• The starting process for any work order or project.

Facilities/Construction Management 26

Page 27: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

WORK ORDERS

• Work Orders for maintenance or repair will typically be handled by the appropriate shop.

• Emergencies will always be addressed by the first available technician who will arrest the emergency and then determine the next course of action to conduct any repairs or restore operations as required.

• Work Orders for all other types of work, or those Maintenance and Repair items that exceed the Project Threshold will be assessed by the WORK REQUEST TRIAGE COMMITTEE

Facilities/Construction Management 27

Page 28: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

WORK REQUEST TRIAGE COMMITTEE

A group consisting of representatives from General Maintenance, Minor Planned Projects, Planning, Plant Operations, and Minor In-House Construction that review all work orders that exceed 32 man-hours or $10,000 to determine the best method of execution and to plan work loads for incoming work requests and to insure that requests are consistent with University policies, procedures, and master plans.

Facilities/Construction Management 28

Page 29: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

WORK ORDER CATAGORIES

Establish five categories for the disposition of work orders (response time):

• Emergency (< 2 hours)• Urgent (< 24 hours)• Routine (< 30 days)• Project (varies depending on complexity, cost, available budget)• Deferred (Indefinite)

Facilities/Construction Management 29

FIX-IT Call Center

Triage Committee/MPEC

Page 30: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

WORK ORDER CLASSIFICATION

• The WORK REQUEST TRIAGE COMMITTEE will meet on a weekly basis to review work orders for alterations, renovations, new construction and Maintenance and Repair Work Orders exceeding the Project threshold.

• The committee will make a determination as to whether the project should go to planning, MPP, MIC, or to the shops for scheduling and execution.

• Project Work Orders will be identified as Maintenance, Repair, Alteration, Renovation, or New Construction.

• These Work Orders will be tracked separately from Maintenance and Repair Work Orders.

• Estimated completion dates will be determined based on criticality, complexity, cost, availability of funds, and on campus priority as determined by the MPEC committee.

Facilities/Construction Management 30

Page 31: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

PROJECT TYPES• Maintenance - A project that involved maintaining a facility or

linear facility, where the scope and magnitude of work typically requires expertise or man-power that exceed the capabilities of the in-house shops.

• Minor In-House Construction - In house shop that specializes in minor renovations, repairs, and alterations. Trades are mostly concentrated in carpentry, but the shop can coordinate minor electrical, HVAC, plumbing, and other subs as needed to execute a project.

• Minor Project - A project whose total project cost is less than $300,000, but may be approved for up to $1,000,000, that includes maintenance, repair, alteration, restoration, or new foot print.

• Capitol Project - Any project whose total project cost exceeds $1 million, that includes maintenance, repair, alteration, restoration, or new foot print.

Facilities/Construction Management 31

Page 32: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

QUESTIONS?

Facilities/Construction Management 32

Jeffrey L. Benjamin, P.E., DBIAExecutive DirectorFacilities Services

UNIVERSITY of HOUSTON4211 Elgin St. Rm 171KHouston, TX 77204-1000o: 713-743-6439 c: [email protected]

Page 33: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

Facilities/Construction Management

Facilities Maintenance and Operations: A Strategic

Approach to Water Management

3/22/2016 33

Page 34: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

The strategic and operational initiatives we put in place to reduce water consumption, reduce water loss, and promote conservation and re-use of this important resource.

University of Houston

What Is Water Managment

Facilities/Construction Management 34

Page 35: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

In a sense, everyone who is a part of the campus community contributes to this effort.

• Individuals who use water on a daily basis

• Maintenance staff who search out and repair leaks

• Operations staff who run the Steam and Chill Water Systems

• Staff, Faculty and Students who utilize water in their business functions, research, food service, etc…

University of Houston

Who Is involved?

Facilities/Construction Management 35

Page 36: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

Why Do We Care?

• With the increasing scarcity of high-quality raw water sources, drinking water utilities may be forced to consider treatment and use of alternative sources, such as impacted surface waters, aquifer recharge and recovery, or reuse.

• There are an estimated 240,000 water main breaks per year in the United States, wasting over two trillion gallons of treated drinking water.

• University of Houston uses on average 436 Million gallons of water per year with an average cost of $4.4 Million per year.

• Chill water and Steam make up water account for 8% of our total usage or $350,000/yr plus addition cost of treatement chemicals.

Facilities/Construction Management 36

Page 37: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

What Are We Doing?

• Specifying the use of water conserving devices in our new facilities and in the renovations of our older buildings

• Seeking out leaks and other sources of water loss and quickly repairing them.

• Looking for projects to replace old irrigation systems with reclaimed water or wells and other types of projects that promote conservation

• Responding quickly to water breaks, leaks and other sources of loss by reporting them to FIX-IT

Facilities/Construction Management 37

Page 38: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

What Are We Doing?

• Metering and building sub-metering to identify high use customers and target water consumption measures where they will have the biggest impact.

• Building inspections to search for illicit connections to water, chill water and steam systems

• Building walkthroughs to identify leaks and other sources of water loss.

Facilities/Construction Management 38

Page 39: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

When Is This All Taking Place?

• Metering and building sub-metering project funds have been approved and this will begin this year starting with Auxiliary buildings then moving to E&G spaces next.

• Building inspections have begun. In the following slide, I will share a few examples of what we found.

• Improvements to our aged water distribution system are in the works with a replacement project.

• Irrigation projects are funded and underway to make repairs to damaged and leaking systems.

Facilities/Construction Management 39

Page 40: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

A Few Examples

Facilities/Construction Management 40

A Lab Chill Water System has a drain pipe to drain Chill Water in the loop before entering into a piece of equipment. One of three drain valves is kept opened (highlight using a red circle in Figure 1) and drains to the waste water sink. .12-cents per gallon then this would be 43,800Gallons per/yr. x.12 cents/gal = $5256.00 per year for just this one pipe not including the cost of chemicals

Page 41: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

A Few Examples

Facilities/Construction Management 41

We add, among other things, a blue die to our chill water system, to allow us to better identify the source of leaks. We add corrosion inhibiters and other chemicles. When we lose chill water from the system, we have to constantly add more chemicals to keep the balance correct.

Here you can see where a piece of equipment is hooked up to the Chill Water System, but the water is dumped instead of returned to the system.

Page 42: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

A Few Examples

Facilities/Construction Management 42

We do support customer needs.

In this instance, you can see that pre-installed connection points.

When equipment is properly connected, it uses the chill water system in a closed loop. The chill water is returned to the system after use.

Page 43: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

How You Can Help

• Report leaks immediately to FIX-IT whenever you encounter them. (sinks, toilets, urinals, water fountains that continue to run, fire sprinklers or pipes, or any other water source that may be leaking)

• Coordinate with Facility Services before connecting equipment or other devices to building steam, chill water, or drinking water systems.

• Conserve water where you can

Facilities/Construction Management 43

Page 44: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

University of Houston

How You Can Help

• If you have equipment that uses water, steam or chill water, already connected to these systems, please let us know so we can work with you to insure they are not wasting water.

• Don’t leave faucets running longer than needed.• Let us know if you think you have an issue, we can help

Facilities/Construction Management 44

Page 45: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

Door Prize!

Jennifer ReaFacilities Communications

E-mail: [email protected]

Page 46: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

Project Planning and Construction

Nick TamayoSenior Facilities Planner

Facilities Planning and ConstructionE-mail: [email protected]

Page 47: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

47

Facilities Planning & Construction

Page 48: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

48

Planning Overview

Planning at a Glance

• Space Management/Reporting

• University Architect

• In-house Engineering Team

• Interior Design Team (FF&E)

• Project Planning

Page 49: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

49

Facilities Planning & Construction

New to the team

Planning Org Chart

Page 50: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

Planning Overview

Space Management (UH Campus Only)

• Curator of current space allocations

• Curator of UH building floor plans

• THECB space reporting

• Developing “Campus Space Policies”

Page 51: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

Planning Overview

University Architect

• Master Planning

• Master Specs & Guidelines

• Design Reviews

• Campus Sustainability

Page 52: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

Planning Overview

Mechanical & Electrical Engineers

• Master Specs and Guidelines

• Design Reviews

• Site Inspections

• Trouble Shooting

• Optimization

Page 53: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

Planning Overview

Interior Design Services

• Design Reviews

• Finish Standards (Guidelines & Master Specs)

• Space Standards

• Furniture Selections & Procurement

Page 54: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

Planning Overview

Project Planning

Page 55: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

55

Planning Overview

SYSTEM

SYSTEM

SYSTEM

Work Request Arrival

Page 56: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

Work RequestFIXIT

“Triage”

Planning

General Maintenance

• Project Development for MPP & Capital Projects

MIC

• Scope Development• Budget • Construction

• Scope Development• Work Billed Hourly

Planning Overview

FPCPlanning

Project Assignment

Page 57: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

Planning Overview

Project Development (non-cap)• Planner Assigned

Scope

PM Assignment (collaboration)

Budget (estimator)

Funding Approval & Transfer of Funds

Turned over to the Project Management Team

Page 58: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

Project Management

Project Management Structure• <$1M –Minor Planned Projects Team

Design varies

JOC, CSP, In-house

• >$1M – Project Management Team

Full design

CMAR, CSP

Page 59: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

Questions

Page 60: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

Campus Carry

Chief Ceaser MooreAVC POLICE OPS/CHIEF OF POLICE

E-mail: [email protected]

Page 61: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

Door Prize!

Jennifer ReaFacilities Communications

E-mail: [email protected]

Page 62: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

Flyers in the Buildings

Craig WhitfieldManager, Facilities Management Zone

Local Maintenance ServicesE-mail: [email protected]

Page 63: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance
Page 64: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance
Page 65: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance
Page 66: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance
Page 67: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

More Informationon Bikes

Craig WhitfieldManager, Facilities Management Zone

Local Maintenance ServicesE-mail: [email protected]

Page 68: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

Jacquie VargasBuilding Coordinator Program Director, Assistant Director of Customer Service

Facilities/Construction ManagementE-mail: [email protected]

Project Evaluations

Page 69: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

Jacquie VargasBuilding Coordinator Program Director, Assistant Director of Customer Service

Facilities/Construction ManagementE-mail: [email protected]

Announcements

Page 70: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

Door Prize

Jennifer ReaFacilities Communications

E-mail: [email protected]

Page 71: Welcome! Building Coordinator Program Quarterly Meeting · 24/10/2018  · Welcome! Building Coordinator Program Quarterly Meeting Friday, October 26, 2018. ... optimal performance

Jacquie VargasBuilding Coordinator Program Director, Assistant Director of Customer Service

Facilities/Construction ManagementE-mail: [email protected]

Adjournment