Page 1: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 1Financial Project ID Number: 437942-1

From the Halifax River Bridge to State Road (S.R.) A1A in Volusia County

Corridor Improvements Project

Virtual Public Hearing

International Speedway Boulevard (U.S. 92)

Welcome

Page 2: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 2

Technical Information - Issues

I am unable to hear the presenter

Entire hearing is being recorded for later viewing

Page 3: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 3

Technical Information - Audio

Page 4: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 4

Technical Information – Comments & Questions

Typed comment or request to speak via the Questions Pane

During hearing

www.cflroads.com

Online In-person

Fill out a comment form

Fill out a speaker card to request to

speak at the microphone

John Smith, I wish to speak

Page 5: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 5

Technical Information – Comments & Questions

Kathleen EnotFDOT Project Manager 719 South Woodland Boulevard MS 542 DeLand, Florida 32720 Phone: 386-943-5149 Email: [email protected]

Project Contact Information

Page 6: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 6

• Comments and Questions will not be responded to during the hearing. Written responses will be provided at a later date.

• All comments and questions received by:

Monday Oct. 12, 2020will be included as a part of this hearing record.

Technical Information – Comments & Questions

www.cflroads.com

*PLEASE NOTE*

Page 7: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 7

This public hearing is conducted in accordance with:

• Chapter 23, United States Code 128

• Title 40, Code of Federal Regulations, Parts 1500 through 1508

• Section 339.155, Florida Statutes

And pursuant to Florida Statute 355.199, the Florida Department of Transportation is conducting this public hearing concerning access management changes to State Road 600. This hearing is being held to afford persons the opportunity to express their views relative to the proposed improvements.

Public Hearing Compliance

Page 8: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 8

Title VI

All inquiries or complaints will be handled according to FDOT procedure in a prompt and courteous manner.

This hearing, project, or study is being conducted without regard to race, color, national origin, age, sex, religion, disability or family status. Persons wishing to express their concerns relative to FDOT compliance with Title VI may do so by contacting:

Jennifer SmithFDOT District Five Title VI Coordinator 719 South Woodland BoulevardDeLand, Florida 32720 [email protected]

Jacqueline ParamoreState Title VI Coordinator 605 Suwannee Street, Mail Station 65Tallahassee, FL [email protected]

Page 9: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 9

Project Location

Page 10: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 10

Stakeholders

Page 11: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 11

• September 2013 - City of Daytona Beach, Conceptual Design Study

• Possible roundabouts at 3 intersections along International Speedway Boulevard, including S.R. A1A

• November 2015 - U.S. 92 Corridor Master Management Plan Final Report

• Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to S.R. A1A

• October 2017 - FDOT U.S. 92 Corridor Management Plan Study Update

• Study completed

• May 2020 - Additional Analysis Requested• The ISB coalition requested further analysis at the intersection of S.R.

A1A for a signal option• Congestion from beach traffic was the main concern• FDOT is analyzing the operations of a signal at S.R. A1A

Project History and Need

Page 12: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 12

Proposed Improvements from the Halifax River Bridge to Grandview Ave.

Overall widening to provide wider travel lanes and a raised median

ADA compliant sidewalks and curb ramps throughout the corridor

Signals reconstructed at Halifax Ave., Peninsula Dr. (S.R. 441) and Grandview Ave.

Page 13: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 13

Proposed Improvements at the S.R. A1A Intersection

Signal OptionRoundabout

Page 14: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 14

Proposed Typical Section - International Speedway Boulevard

Page 15: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 15

Existing Access along International Speedway Boulevard

• Non-Restrictive – allows turns at any point along the roadway

Page 16: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 16

Proposed Access along International Speedway Boulevard

Signal Option

Roundabout

Page 17: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 17

Proposed Access at Halifax Avenue and Peninsula Drive

Page 18: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 18

Proposed Access at Grandview Avenue

Page 19: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 19

Proposed Access at S.R. A1A - Signal Option

Page 20: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 20

Proposed Access at S.R. A1A - Roundabout Option

Page 21: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 21

Signal Option for International Speedway Boulevard at S.R. A1A - Proposed Turn Lanes

Proposed Signal at S.R. A1A• Add right turn lane on eastbound

International Speedway Boulevard

• Add right turn lane on southbound S.R. A1A

Page 22: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 22

What is Level of Service (LOS)?

• Level of service is a grading system for amount of traffic congestion.

• Reflects average seconds of delay per vehicle at intersections.

Traffic Efficiency Comparison

LOS

Roundabout

Delay

(seconds per vehicle)

Signalized

Intersection Delay

(seconds per vehicle)

A ≤ 10 ≤ 10

B 11-15 11-20

C 16-25 21-35

D 26-35 36-55

E 36-50 56-80

F >50 >80

Page 23: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 23

Weekday Peak Hour

Year Roundabout Signal Option

Level-of-Service2025 A C

2045 B C

Average Intersection Delay (Seconds per vehicle)

2025 6.8 26.6

2045 10.4 30.6

Traffic Comparison - Roundabout vs Signal

Saturday Peak Hours

Roundabout Signal Option

B C

C D

12.7 33.6

19.0 38.5

Page 24: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 24

Pedestrian Travel Comparison - Roundabout vs Signal

RoundaboutSignal Option

Signalized Crossing

3 Legs All Legs

Crossing Distances

1 to 2

Lanes

(with

Median

Refuge)

4 to 6

Lanes

Crossing Conflicts

Fewer Greater

Travel Distances (between crossings)

Longer Shorter

• Pedestrian Hybrid Beacons

• 2-Stage crossings with median refuge

• Shorter crossing distance (2 lanes max)

Raised Crosswalk

• Signalized Crossings • Longer crossing distance

(4 to 6 lanes)

Signal OptionRoundabout

Page 25: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 25

Roundabout Pedestrian Crossings

Page 26: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 26

Bicycle Travel Comparison - Roundabout vs Signal

Signal OptionRoundabout

Option 1 – Travel on wide sidewalk

Option 1 – Travel on wide sidewalk

Option 2 – Navigate through as a vehicle

Option 2 – Navigate through as a vehicle

Not all possible bicycle movements are shown on the graphic above

Page 27: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 27

Travel Comparison - Roundabout vs Signal

5x Normal Speed

Page 28: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 28

Safety Comparison - Roundabout vs Signal

Page 29: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 29

Roundabout vs Signal Comparison

Signal OptionRoundabout

Page 30: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 30

• Permitting Agency• St. Johns River Water

Management District

• Exempt from Permitting

• Maintain existing treatment areas

• Conveyance System• Existing pipes in

poor condition

• New storm sewer system

Stormwater Management

Permitted

Unpermitted

ExistingFDOT Pond

Page 31: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 31

• U.S. 92 PD&E Study Newsletters • Notify the public for public hearings

• Show the project location

• Describe project impacts and need

• Information on future events

• Public Notifications• Elected, appointed, and agency officials

• Property owners/tenants within 300-feet of project corridor

• Other key stakeholders and interested parties

• Florida Administrative Register

• Email

• Project website

Public Involvement

Page 32: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 32

• Design phase• Currently underway

• Scheduled for completion in late 2020

• Right of Way Acquisition • Expected to begin in early 2021

• Construction• Expected to begin in early 2023

• This schedule is based on the current roundabout design. Changes to the design may affect the schedule. All efforts will be made to start construction as currently scheduled.

Project Schedule

Page 33: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 33

Providing Comments – After this Hearing

Kathleen EnotFDOT Project Manager 719 South Woodland Boulevard MS 542 DeLand, Florida 32720 Phone: 386-943-5149 Email: [email protected]

Project Contact Information

www.cflroads.com

Comments can be submitted via mail

Comments can be submitted via email

Comments can be submitted via telephone

Comments are always accepted throughout the life of the project. To have your comments included as part of the public record please have them submitted or postmarked by:

October 12, 2020

Page 34: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 34

• Browse to www.cflroads.com

• Click on the search icon

• Enter 437942-1 into the search box

• Hit “Go”

• Select the “437942-1 US 92 from the Halifax River Bridge to SR A1A” in the resulting list.

Project Website

Page 35: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 35

Public Testimony

Type comments or request to speak via the

Questions Pane

Online In-person

Fill out a speaker card to request to

speak at the microphone

John Smith, I wish to speak

Kathleen EnotFDOT Project Manager 719 South Woodland Boulevard MS 542 DeLand, Florida 32720 Phone: 386-943-5149Email: [email protected]

Dial-In Only

Please provide your comments or question directly

to the project manager

Page 36: Welcome []...2020/10/01  · •November 2015 - U.S. 92 Corridor Master Management Plan Final Report •Summarized recommended improvement for overall U.S. 92 Corridor from I-4 to

October 1, 2020| 36Financial Project ID Number: 437942-1

From the Halifax River Bridge to State Road (S.R.) A1A in Volusia County

Corridor Improvements Project

Virtual Public Hearing

International Speedway Boulevard (U.S. 92)

Thank You for Attending