wekiwa springs septic tank retrofit – project update utilities department march 10, 2015 1

21
Wekiwa Springs Septic Tank Retrofit – Project Update Utilities Department March 10, 2015 1

Upload: jason-harrison

Post on 17-Dec-2015

215 views

Category:

Documents


0 download

TRANSCRIPT

Wekiwa Springs Septic Tank Retrofit – Project

Update

Utilities Department

March 10, 2015

1

Presentation Outline

Background

Wekiwa Springs Project Update

Project Next Steps

Additional Projects

Questions?

2

Presentation Outline

Background

Wekiwa Springs Project Update

Project Next Steps

Additional Projects

Questions?

3

Background

BCC Workshop – 9/23/14–Presented existing retrofit policy

BCC Public Hearing – 10/21/14–Code amendment authorizing Utilities to fund up

to 25% of a septic tank or potable well retrofit project when other programs cover at least 75% of all project costs–Approved offering 25% funding to homeowners

for the Wekiwa Springs Septic Tank Retrofit project• Subject to 75% grant funding from SJRWMD and FDEP

4

Background

Sewer retrofit of up to 367 lots –State contribution of

approximately $5.0 million (75% of total costs)–Evaluating alternatives and

updating cost estimates• Locating pump stations• Low pressure sewer option

5

Presentation Outline

Background

Wekiwa Springs Project Update

Project Next Steps

Additional Projects

Questions?

6

Wekiwa Springs Project Update

Alternatives Study Completed–Low pressure sewer alternative recommended–Significantly less disruptive to community

Total project cost of up to $9.0 million– Includes 25% contingency–Design entire system–Construct in phases if total costs exceed $6.65 million

SJRWMD and FDEP support recommendation

7

Presentation Outline

Background

Wekiwa Springs Project Update

Project Next Steps

Additional Projects

Questions?

8

Project Next Steps

Apply for additional grant funding–March 13, 2015 deadline

Community Meeting–Present study recommendations–Discuss low pressure sewer system components–Present voting ballot – 67% YES required

Design project 18 monthsConstruction 18 to 24 months

9

Presentation Outline

Background

Wekiwa Springs Project Update

Project Next Steps

Additional Projects

Questions?

10

Additional Projects

Commissioner Nelson called stakeholders meeting in January 2015.

Wekiwa Springs Meeting

Additional Projects

Stakeholders collaborated on local and regional projects that will improve water quality for Wekiwa Springs

Existing and New Technologies explored:

Existing New Street sweeping Modular wetlands Curb inlet baskets Bold & Gold™ filter media Nutrient baffle boxes

All regional projects dependent upon cooperative funding.

Additional Projects

Emerging technology developed by UCF Proprietary mix of sand,

sawdust, and recycled tire crumb Septic drainfield application is

pending FDOH approval 2 ongoing stormwater pilot

projects in advanced phases More pilot projects for septic

and other stormwater applications needed

Additional Projects

Bay Lake Retrofit (EPD)

Estates at Lake Clarice(Stormwater Management)

Modular wetland with Bold & Gold Treats street runoff Monitoring phase

Out flow filter with Bold & Gold Treats pond overflow to Lake Roper Construction planned August 2015

Additional Projects

Septic Drainfield Retrofits

Stormwater Pond Retrofits

Need private property volunteers Access is required for continuous

monitoring & study Work with FDOH

Projects at existing ponds Easements may be needed for

construction & monitoring Work with SJRWMD

Additional Projects

Prevention at the source Increase frequency, expand coverage Standalone solution or combine

with other Best Management Practices (BMPs)

Measurable Results

Expand Street Sweeping Program

Additional Projects

Prioritize projects Negotiate collaborative funding from stakeholders Request funding from State Legislature (FY2016)

Presentation Outline

Background

Wekiwa Springs Project Update

Project Next Steps

Additional Projects

Questions?

18

Questions?

19

Wekiwa Springs Septic Tank Retrofit – Project

Update

Utilities Department

March 10, 2015

20

Modular WetlandsNutrient Removal from Surface Water Using Chambers, Filters, and Biomass Uptake

Sequesters nutrient loads from stormwater runoff Current EPD pilot on east shore of Bay Lake