weekly report - alamo.eduweekly report st. phillip’s college — norris technical building...
TRANSCRIPT
![Page 1: WEEKLY REPORT - alamo.eduWEEKLY REPORT St. Phillip’s College — Norris Technical Building February 24— February 28 This week activities: Next week activities: Complete Level 2](https://reader034.vdocuments.us/reader034/viewer/2022042023/5e7bcd432f7c9138320f8e32/html5/thumbnails/1.jpg)
WEEKLY REPORT St. Phillip’s College — Norris Technical Building
March 16 — March 20
This week activities: Next week activities:
Cont. Exterior Framing on South Elevation
Start fur-downs Level 4
Elevator Shaft Protection
Start Prime & 1st coat of Paint Level 4
Star Data Cable Install Double Sided Walls Level 1
Cont. Exterior Framing on South Elevation
Cont. Final Paint on Level 4 Walls
Cont. Data Cable Install Cont. Framing and Drywall at Ele-
vator Shaft
Cont. Prime & 1st coat of Paint Level 4
![Page 2: WEEKLY REPORT - alamo.eduWEEKLY REPORT St. Phillip’s College — Norris Technical Building February 24— February 28 This week activities: Next week activities: Complete Level 2](https://reader034.vdocuments.us/reader034/viewer/2022042023/5e7bcd432f7c9138320f8e32/html5/thumbnails/2.jpg)
Fur down at Level 4 Final Paint Level 4
Data Cable Elevator Shat Protection
Drywall Level 1 Spray Fireproofing