Civil - Summary

WEEKLY PROGRESS REPORT

CIVIL WORKSFrom : August 04, 2015 To : August 10,2015Report No. 11

PROJECT TITLEQASSIM-5 380/132/13.8 KV BSP#9059CONTRACTORALMASHRIQCONTRACT NO.4400005408SUBCONTRACTOR ( CIVIL WORKS )AL - FAHD CompanyWEATHERHotSUBCONTRACTOR ( PRECAST )PRAINSA

PROJECT COMPLETIONCONTRACTPREVIOUSTHIS WEEKTO DATEBALANCEJuly 22, 2017100%

BASIS / REFERENCES1Progress accomplishments percentages will be based on Over all Project Time Schedule (Civil Works Only)2Progress accomplishments percentage (Plan and Actual) as of July 27, 2015 ( to be Referred to detail Project schedule and Monitoring)3Detailed Construction schedule will be based on Al Fahd Contracting Co. Schedule.SCHEDULE REFERENCES AT BUILDINGS :PARTICULARSCHEDULEREMARKSSuspended Slab and Beam DonePrecast installReady for electrical worksReady Equiptment erectionUpdate Suspended Slab and Beam as of March 5, 2015PlanActualPlanActualPlanPlanStart FinishStart FinishStart FinishStart FinishStart FinishStart Finish1.0380 KV GIS BUILDING......Datas will be properly filled up upon receiving Approved Overall Project Time Schedule1.10Basement cable tunnel (Tunnel A)....1.205m Cable Tunnel ( screed laying completed and rebars fixing is in progress.2 Aug 20015on going2.0132 KV GIS BUILDING.......2.101st Half Area(Screed laying completed)..26 July 201526 July 20152.202nd Half Area (screed laying completed)..26 July 201526tJuly 20153.0CONTROL BUILDING BASEMENT........

CONTROL BUILDING ISOLATED FOOTING.......

4.013.8 KV SWICHGEAR BUILDING( laying of two layers of water proofing membrane and screed completed)..05 August 201510 August 2015....

NOTES : DATE FINISHED PLAN & ACTUAL ON SUSPENDED SLABS AND BEAMS TO BE BASED ON DATE CONCRETED.OPEN , ONGOING AND SCHEDULE ACTIVITIES AS FOLLOWS : PARTICULARSPLANACTUALACCOMPLISHMENTREMARKSStartFinishStartFinishPreviousThis PeriodTo Date1.10380 KV GIS BUILDING1.1.1Excavation29-Jun-1520-Jul-15100%0%100%Completed1.1.2Backfilling/Leveling and Compaction21-Jul-1523-Jul-1521-Jul-1523-Jul-15100%0%100%Completed1.1.3Testing (FDT)21-Jul-1521-Jul-1522-Jul-1522-Jul-15100%0%100%Completed1.1.4Lean Concrete21-Jul-1521-Jul-1522-Jul-1522-Jul-15100%0%100%Completed1.1.5Installation of Water Proofing Membrane27-Jul-153-Aug-1529-Jul-151-Aug-15100%0%100%Completed1.1.6Concrete Screed4-Aug-154-Aug-152-Aug-152-Aug-15100%0%100%Completed1.1.7Shuttering for Raft Foundation5-Aug-156-Aug-156-Aug-150%50%50%On-going1.1.8Rebar Fixing for Raft/Columns/Wall8-Aug-1513-Aug-158-Aug-150%30%30%On-going1.1.9FDT testing on isolated footing area28-Jul-153-Aug-1550%0%50%Yet to complete1.20132 KV GIS BUILDING1.2.1Excavation23-Jun-155-Jul-1523-Jun-1520-Jul-15100%0%100%Completed1.2.2Backfilling/Leveling and Compaction20-Jul-1521-Jul-1520-Jul-1521-Jul-15100%0%100%Completed1.2.3FDT testing on raft foundation bed21-Jul-1521-Jul-1522-Jul-1522-Jul-15100%0%100%Completed1.2.4Lean Concrete25-Jul-1525-Jul-1526-Jul-1526-Jul-15100%0%100%Completed1.2.5Installation of Water Proofing Membrane1-Aug-156-Aug-152-Aug-156-Aug-1550%50%100%Completed1.2.6Concrete Screed6-Aug-156-Aug-158-Aug-158-Aug-150%100%100%Completed1.2.7Shuttering for Raft Foundation0%0%0%Preparatory Works (yet to start)1.2.8Rebar Fixing for Raft/Columns/Wall0%0%0%Preparatory Works(yet to start)1.30CONTROL BUILDING BASEMENT AREA1.3.1Excavation20-Jul-1527-Jul-1520-Jul-1527-Jul-15100%0%100%Completed1.3.2Backfilling/Leveling and Compaction20-Jul-1530-Jul-1520-Jul-151-Aug-1590%0%90% to be Completed1.3.3Testing (FDT)1-Aug-151-Aug-150%0%0%Awaits schedule of FDT1.3.4Lean Concrete1-Aug-151-Aug-150%0%0%To Follow1.3.5Installation of Water Proofing membrane5-Aug-1512-Aug-150%0%0%To Follow1.3.6Concrete Screed12-Aug-1512-Aug-150%0%0%To Follow1.4013.8 KV SWICHGEAR BUILDING1.4.1Excavation20-Jul-1520-Jul-1520-Jul-1520-Jul-15100%0%100%Completed1.4.2Backfilling/Leveling and Compaction21-Jul-1522-Jul-1521-Jul-1523-Jul-15100%0%100%Completed1.4.3Testing (FDT)25-Jul-1525-Jul-1528-Jul-1528-Jul-15100%0%100%Completed1.4.4Lean Concrete1-Aug-151-Aug-1530-Jul-1530-Jul-15100%0%100%Completed1.4.5Installation of Water Proofing membrane5-Aug-1512-Aug-156-Aug-158-Aug-150%100%100%Completed1.4.6Concrete Screed12-Aug-1512-Aug-1510-Aug-1510-Aug-150%100%100%Completed1.4.7Shuttering for Raft Foundation0%0%0%To Follow1.4.8Rebar Fixing for Raft/Columns/Wall0%0%0%To Follow1.50CABLE TUNNELS1.5.1Excavation25-Jun-155-Jul-151-Jul-159-Jul-15100%0%100%Completed1.5.2Backfilling/Leveling and Compaction0%0%0%Not Yet Started1.5.3Testing (FDT)0%0%0%To Follow1.5.4Lean Concrete0%0%0%To Follow1.5.5Installation of Water Proofing membrane0%0%0%To Follow1.5.6Concrete Screed0%0%0%To Follow

MAJOR SAFETY AND SECURITY ISSUEStill Perimeter Fence not yet Completed, No Security Personnel Deployed, Barricade installed on Excavated Areas still not as per SEC Standard MAJOR QA/QC ACTIVITIES ISSUEHard copies of FDTs and concrete testing have not submitted. Approved works schedule,Organization chart of the contractor M/S Al Mashriq,copies of approved drawings and approved material/vedors list are not available on site. FINDINGS & OBSERVATION Site Office lack in follwoing FacilitiesToilets for Consultant use, Car Parking with Shade,File Cabinets,Computer Printers & scanners Digital Camera for taking photos of ongoing works and Telephone/fax etc. Still Manpower/Tools are not yet organized for Planned activities. RECOMMENDATION /ACTION All above mentioned safety/security & QA/QC issues and findings& observations need urgent attention and action.Instructed again Contractor to deploy skilled Workers and to make preparations for equipment/tools needed for the scheduled/plan activities especially the coming Concreting of 380 kV Raft Foundation. Likewise to closely supervise on-going works to achieve desired accomplishments.

MANPOWERSAIn Direct LaborContractor (Almashariq)August ' 2015Reqrd per dayRemarks456789101Project Manager011FRIDAY1112Project Engineer0001013Site Manager0111114Site Civil Engineer1111115Site Electrical Engineer1111116QA/QC Engineer (Electrical)1111117Safety Engineer1111118Safety Officer1111119Driver12111110Foreman Electrician12222211Electrician11111112Tea Boy11111113Helper02223214Fencing Contractor330026Sub Total121814151721Sub Contractor(Al-Fahd)August ' 2015Reqrd per dayRemarks456789101Project Manager011FRIDAY1102Civil Engineer1111123Safety Engineer1111114Office Boy011111Sub Total244444Total Manpower (Indirect Labor )142218192125BDirect LaborSub Contractor (Al Fahd)August ' 2015Reqrd per dayRemarks456789101Surveyor/Assistant Surveyor101FRIDAY0112Instrument Man1010113Foremen/Leadman1000024Driver / Operator5978895Steel Fixer00088186Carpenter5554447Mason3224418Labor5297679Waterproofing Installer444000Sub Total252229313243Total Manpower (direct labor)252229313243GRAND TOTAL (DIRECT + INDIRECT LABOR)3944475053681EQUIPTMENTSASub Contractor (Al Fahd)August ' 2015Reqrd per dayRemarks456789101Excavator010FRIDAY0002Roller Compactor0110013Payloader0001004Grader1111115Bulldozer0111116Water Tanker1111117Dump Truck353333SubTotal5107767Total Equipments5107767

PHOTOS

This Week Photos August 04-10, 2015. Shuttering and Fixing of Bottom Steel Reinforcements for Raft Foundation.

380 kV BUILDING CABLE TUNNEL AREA

This Week Photos August 04-10, 2015. Completed Installation of 1st & 2nd Layer of Waterproofing Membrane and Screed Concrete Pouring.

132 kV BUILDING BASEMENT AREA

This Week Photos August 04-10, 2015. Completed Bitumin Painting, Installation of 1st & 2nd Layer Waterproofing Membrane and Screed Concrete Pouring.

13.8 kV SWGR BUILDING AREA

This Week Photos August 04-10, 2015. Rechecking of Elevation and Application of Water prior to Compaction.CONTROL BUILDING AREA

This Week Photos August 04-10, 2015. Continue Backfilling, Grading and Compaction of the Proposed Road inside Substation.

OTHER WORKS INSIDE SUBSTATION

This Week Photos August 04-10, 2015. Continue Perimeter Fence Installation and Provisions of Two (2) Units PC at Consultant's Office,

SITE OFFICE & FACILITIES

PREPARED BY :FRANCISCO SUMCAD, JR.FAIZ UR REHMANCIVIL ENGINEERPROJECT ENGINEER (CIVIL)Saudi Engineering group International Saudi Engineering group international

Civil - Schedule & Monitoring

DETAILED CONSTRUCTION SCHEDULE & PROJECT MONITORING

(N/A As approved work schedule and planned values not available, have to provide by the contractor) CIVIL WORKS

Report No. 1

PROJECT TITLEQASSIM-5 380/132/13.8 kV BSP@9059ContractorALMASHARIQContract No.4400005408Subcontractor (Civil works)AL FAHD Contracting Co.WeatherHotSubcontractor 9Precast)PRAINSA

Detailed Civil Works Schedule Activities and Progress Percentages tabulation:Item No.Work DiscriptionScheduleCivil Works Contract % FactorProgress per 100% work itemsProgress per contract % work itemsPlannedActualRemarksPlanned/RequiredPreviousThis WeekTo dateBalanceRemarksPreviousThis WeekTo dateDurationStartFinishStartFinish1.0Mobilization and Preparation of Civil WorksCompleted0.76%0.76%0.76%0.76%0.76%100%100%100%0%Completed0.760%0.000%0.760%2.0380 kV Building Civil WorkOct 25'14Apr 12'14Oct 25'141.45%2.1380 kv contol cable basement tunnel87Oct 25'14Feb 2 '15Oct 25'140.30%2.1.1Earthworks4Oct 25'14Oct 28 '14Oct 25'14Oct 28'14Completed0.01%0.01%0.01%100%100%100%0%Completed0.007%0.000%0.007%2.1.2Basement (Raft Fdn/Base Slab)32Oct 29'14Dec 4 '140.06%0.06%2.1.2.1Lean Concrete-Grid Line 1-22/A-C 1Oct 29'14Oct 29'14Nov 9'14Nov 9'14Delayed(Completed)0.00%100%100%100%0%Completed0.001%0.000%0.001%2.1.2.2Waterproofing System for basement -Grid Line 1-12/A-C5Oct 30'14Nov 4'14Nov13'14Nov 24'14Delayed(Completed)0.01%100%100%100%0%Completed0.006%0.000%0.006%2.1.2.3Waterproofing System for basement -Grid Line 13-1-22/AC7Nov 1'14Nov 8'14Nov12'14Nov 24'14Delayed(Completed)0.01%100%100%100%0%Completed0.008%0.000%0.008%2.1.2.4RC base slab and raft fdn Grid Line 1-8/A-C9Nov 5'14Nov 15'14Nov30 '14Dec 10 '14Delayed(Completed)0.01%100%100%100%0%Completed0.011%0.000%0.011%2.1.2.5RC base slab and raft fdn Grid Line 9-12/AC9Nov 12'14Nov22'140.01%100%100%100%0%Completed0.011%0.000%0.011%2.1.2.6RC base slab and raft fdn Grid Line 13-17/A-C8Nov 19'14Nov 27'140.01%100%100%100%0%Completed0.009%0.000%0.009%2.1.2.7RC base slab and raft fdn Grid Line 18-22/A-C9Nov 25'14Dec 4 '140.01%100%100%100%0%Completed0.011%0.000%0.011%2.1.3Basement (RC Walls and Collum)31Nov16 '14Dec 21'140.05%0.05%2.1.3.1Grid Line 22 / A-C10Nov 16 '14Nov 26 '14Dec 20'14Jan 12'15Delayed(Completed)0.01%100%100%100%0%Completed0.014%0.000%0.014%2.1.3.2Grid Line 1-22 / B10Nov 23 '14Dec 3 '140.01%100%100%100%0%Completed0.014%0.000%0.014%2.1.3.3Grid Line 1 / A-C10Dec 4' 14Dec 14 ' 140.01%100%100%100%0%Completed0.014%0.000%0.014%2.1.3.4Grid Line 1-22 / C10Dec 10 '14Dec 21 ' 140.01%100%100%100%0%Completed0.014%0.000%0.014%2.1.4Basement ( Suspended slab and beams)50Dec 2' 14Jan 28 '150.09%0.09%2.1.4.1RC works Top slab Grid Line1-127Dec 2 '14Jan 4 ' 14Jan 9'15Feb 5'15Delayed(Completed)0.01%100%100%100%0%Completed0.014%0.000%0.014%2.1.4.2RC works Top slab Grid Line 13-2337Dec 17'14Jan 28'14Feb 1'15Feb 10'15Delayed(Completed)0.07%100%100%100%0%Completed0.075%0.000%0.075%2.1.5Waterproofing works (Retaining walls)27Dec 28'14Jan 27 '150.05%0.05%2.1.5.1GL Along A-C/18 ( along 380 kv Tunnel )5Dec 28'14Jan 1'14Jan '15Jan 27,15Partialy Completed0.01%100%95%95%5%On going0.009%0.000%0.009%2.1.5.2GL Along A-C/18 ( along 380 kv Tunnel )7Jan 13'15Jan 20'150.01%100%95%95%5%On going0.013%0.000%0.013%2.1.5.3Grid Line Along GL 1/A-C7Jan 18'15Jan 25'150.01%100%95%95%5%On going0.013%0.000%0.013%2.1.5.4Grid Line Along GL 18/A-C5Jan 22'15Jan 27 '150.01%100%95%95%5%On going0.009%0.000%0.009%2.1.6Backfiling and Compaction works27Jan 3 '15Feb 2 '150.05%0.05%2.1.6.1Along A-C/1-8 (along 380 kv Tunnel)5Jan 3'15Jan 7'15Jan 18'15On going (Not critical works)0.01%100%90%90%10%On going0.011%0.000%0.011%2.1.6.2Along A-C/14-22 (along 380 kv Tunnel)5Jan 21'15Jan 26'150.01%100%90%90%10%On going0.011%0.000%0.011%2.1.6.3Along GL 1/A-C5Jan 26'15Jan 31'150.01%100%90%90%10%On going0.011%0.000%0.011%2.1.6.4Along GL 18/A-C5Jan 28'15Feb 2'150.01%100%90%90%10%On going0.011%0.000%0.011%2.2Foundations works (isolated)23Nov16 '14Dec11 '140.08%0.08%0.08%2.2.1Footing11Nov 16 '14Nov 27'14Delayed(No Activity)0.04%100%2.2.2Column Neck/Plinth13Nov 27'14Dec 11'14Delayed(No Activity)0.04%100%2.3Grade beam12Jan 19 '15Feb 1'15Delayed(No Activity)0.04%0.04%0.04%0.04%100%2.4Grade slab29Jan 13 '15Feb 15'150.10%0.10%0.10%2.4.1Grid Line 1-13 A/C17Jan 13'15Feb 1'15Delayed(No Activity)0.05%100%2.4.2Grid Line 14-22 A/C17Jan 27'15Feb 15'15Delayed(No Activity)0.05%100%2.5380kv 5m Cable tannel85Oct 29'14Feb 4'150.30%100%2.5.1Earthworks4Oct 29'14Nov 2 '14Oct 25'14Nov 10'14Delayed(Completed)0.01%0.01%0.01%100%100%100%0%Completed0.007%0.000%0.007%2.5.2Basement (Raft Fdn/Base Slab)32Nov 3 '14Dec 9 '140.06%0.06%2.5.2.1Lean Concrete1No 3'14Nov 3'14Nov 11'14Nov 11'14Delayed(Completed)0.00%100%100%100%0%Completed0.001%0.000%0.001%2.5.2.2Waterproofing System for basement -Grid Line 1-12/A-C5Nov 4'14Nov 9'14Nov 15'14Nov 29'14Delayed(Completed)0.01%100%100%100%0%Completed0.006%0.000%0.006%2.5.2.3Waterproofing System for basement -Grid Line 13-1-22/AC7Nov 5'14Nov 12'140.01%100%100%100%0%Completed0.009%0.000%0.009%2.5.2.4RC base slab and raft fdn Grid Line 1-8/ E-F9Nov 10'14Nov 19'14Dec 8'14Dec 20'14Delayed(Completed)0.01%100%100%100%0%Completed0.011%0.000%0.011%2.5.2.5RC base slab and raft fdn Grid Line 9-12/ E-F9Nov 17'14Nov 26 '140.01%100%100%100%0%Completed0.011%0.000%0.011%2.5.2.6RC base slab and raft fdn Grid Line 13-17/ E-F8Nov 24'14Dec 2'140.01%100%100%100%0%Completed0.010%0.000%0.010%2.5.2.7RC base slab and raft fdn Grid Line 18-23/E-F9Nov 30'14Dec 9 '140.01%100%100%100%0%Completed0.011%0.000%0.011%2.5.3Basement (RC Walls and Collum)27Nov20 '14Dec 21'140.05%0.05%2.5.3.1Grid Line 1-8/A-C11Nov 20'14Dec 2'14Dec 28'14Feb 10'15Delayed(Completed)0.01%100%100%100%0%Completed0.013%0.000%0.013%2.5.3.2Grid Line 9-12/AC10Nov 27'14Dec 8'140.01%100%100%100%0%Completed0.012%0.000%0.012%2.5.3.3Grid Line 13-17/A-C10Dec 4' 14Dec 15'140.01%100%100%100%0%Completed0.012%0.000%0.012%2.5.3.4Grid Line 18-22/A-C10Dec 10 '14Dec21'140.01%100%100%100%0%Completed0.012%0.000%0.012%2.5.4Basement ( Suspended slab and beams)46Dec 7'14Jan 28 '150.09%0.09%2.5.4.1RC works Top slab Grid Line1-1229Dec 7'14Jan 8'15Feb 9'15Feb 12'15Delayed(Completed)0.04%100%100%100%0%Completed0.038%0.000%0.038%2.5.4.2RC works Top slab Grid Line 13-2337Dec 17'14Jan 28'15Feb 12'15Feb 24'15Delayed(On going)0.05%100%100%100%0%Completed0.048%0.000%0.048%2.5.5Waterproofing works (Retaining walls)25Jan 1 '15Jan 29 '150.05%0.05%2.5.5.1GL Along A-C/18 ( along 5 m wide Tunnel )5Jan 1'15Jan 6 '15Jan 14'15Partialy started (Not critical activity)0.01%100%95%95%5%On going0.009%0.000%0.009%2.5.5.2GL Along A-C/18 ( along 5 m wide Tunnel )7Jan 13'15Jan 20'150.01%100%95%95%5%On going0.012%0.000%0.012%2.5.5.3Grid Line Along GL 1/A-C8Jan 18'15Jan 26'150.01%100%95%95%5%On going0.014%0.000%0.014%2.5.5.4Grid Line Along GL 18/A-C6Jan 24'15Jan 29 '150.01%100%95%95%5%On going0.010%0.000%0.010%2.5.6Backfiling and Compaction works25Jan 7 '15Feb 4'150.05%0.05%2.5.6.1Along A-C/1-8 (along 5 m wide Tunnel)5Jan 7 '15Jan 12'15Jan 25'15Partialy started (Not critical activity)0.01%100%90%90%10%On going0.010%0.000%0.010%2.5.6.2Along A-C/14-22 (along 5 m wide Tunnel)5Jan 21'15Jan 26'150.01%100%90%90%10%On going0.010%0.000%0.010%2.5.6.3Along GL 1/A-C5Jan 27'15Feb 1'150.01%100%30%60%90%10%On going0.003%0.007%0.010%2.5.6.4Along GL 18/A-C5Jan 31'15Feb 4'150.01%100%30%60%90%10%On going0.003%0.007%0.010%2.6Precast works (by Others)30Feb 1 '15Mar 7 '15Feb 14'15Delayed(On going)0.10%0.10%0.10%0.10%100%70%5%75%25%On going0.073%0.005%0.078%2.7Roof water proofing sytem and roof finishes30Mar 8 '15Apr 11'14All activities delays in start and completion base on plan schedule due to delayed on prerequisite activities to complete.0.10%0.10%0.10%0.10%100%2.8Reinforced concrete shear wall24Feb11'15Mar10 '150.08%0.08%0.08%2.8.1Grid Line (A/1-2)(E/1-4)(2Nos)24Feb11'15Feb 19'150.04%100%2.8.2Grid Line (A/20-22)(E/20-22)(2Nos)24Feb 11'15Mar 10'150.04%100%2.9Reinforced concrete stair14Mar 7 '15Mar22 '150.05%0.05%0.05%2.9.1Stair # 17Mar 7 '15Mar 14'150.02%100%20%5%25%75%On going0.005%0.001%0.006%2.9.2Stair # 27Mar 15'15Mar 22'150.02%100%2.10Painting works43Feb22 '15Apr 12'140.15%0.15%0.15%0.15%100%2.11Finishing of basement of 280 kv Tunnel24Jan 29'15Feb25 '150.08%0.08%0.08%0.08%100%10%5%15%85%On going0.008%0.004%0.013%2.12Specialties15Feb 22'15 Mar 10'150.05%0.05%0.05%0.05%100%3.0132 kV Building Civil WorksOct 25'14Apr 8'15Oct 25'141.08%3.1132 kv Basements113Oct 25'14Mar 4'15Oct 25'140.37%3.1.1Earthworks4Oct 25'14Oct 28 '14Oct 25'14Oct 28'14Completed0.01%0.01%0.01%100%100%100%0%Completed0.008%0.000%0.008%3.1.2Basement (Raft Fdn/Base Slab)38Oct 29'14Dec 11'140.08%0.08%100%100%100%0%Completed3.1.2.1Lean Concrete2Oct 29'14Oct 30'14Nov 5,14Nov 5,14Delayed(Completed)0.00%100%100%100%0%Completed0.003%0.000%0.003%3.1.2.2Waterproofing System for basement -Grid Line 1-7/A-G5Nov 6'14Nov 11'14Nov 11'14Nov 19'14Delayed(Completed)0.01%100%100%100%0%Completed0.008%0.000%0.008%3.1.2.3Waterproofing System for basement -Grid Line 8-16/AG7Nov 8'14Nov 15'14Nov 10'14Nov 15'14Completed0.01%100%100%100%0%Completed0.011%0.000%0.011%3.1.2.4RC base slab and raft fdn Grid Line 1-4/A-G10Nov12'14Nov 23'14Nov 17'14Dec 4 '14Completed 0.02%100%100%100%0%Completed0.015%0.000%0.015%3.1.2.5RC base slab and raft fdn Grid Line 5-7/AG10Nov 19'14Nov 30'140.02%100%100%100%0%Completed0.015%0.000%0.015%3.1.2.6RC base slab and raft fdn Grid Line 8-12/A-G9Nov 26'14Dec 6'140.01%100%100%100%0%Completed0.014%0.000%0.014%3.1.2.7RC base slab and raft fdn Grid Line 12-16/A-G8Dec 03'14Dec11 '140.01%100%100%100%0%Completed0.012%0.000%0.012%3.1.3Basement (RC Walls and Collum)29Nov 26'14Dec 29'140.06%0.06%3.1.3.1Grid Line 16 / A-E14Nov 26'14Dec 09'14Dec 6'14Dec 20'14Delayed(Completed)0.02%100%100%100%0%Completed0.015%0.000%0.015%3.1.3.2Grid Line 1-16 / B15Dec 3'14Dec 17'140.02%100%100%100%0%Completed0.016%0.000%0.016%3.1.3.3Grid Line 1 / B -E14Dec 10 '14Dec 23'14Dec 21'14Jan 3'15Delayed(Completed)0.02%100%100%100%0%Completed0.015%0.000%0.015%3.1.3.4Grid Line 1-16 / E13Dec 15'14Dec 27'140.01%100%100%100%0%Completed0.014%0.000%0.014%3.1.4Basement ( Suspended slab and beams)47Dec 17'14Feb 9'150.10%0.10%3.1.4.1RC works Top slab Grid Line1-735Dec 17'14Jan 10'15Dec 25'14Jan 27,15Delayed(Completed)0.05%100%100%100%0%Completed0.048%0.000%0.048%3.1.4.2RC works Top slab Grid Line 8-1636Dec 30'14Jan 24'15Jan 21,15Feb 2,15Delayed(Completed)0.05%100%100%100%0%Completed0.050%0.000%0.050%3.1.5Waterproofing works (Retaining walls)31Jan 19'15Feb 23'150.06%0.06%3.1.5.1GL Along 1-4/A-G9Jan 19'15Jan 28'15Jan10'15Partialy Completed0.02%100%95%95%5%On going0.016%0.000%0.016%3.1.5.2GL Along 5-7/A-G9Feb 2'15Feb 11'150.02%100%95%95%5%On going0.016%0.000%0.016%3.1.5.3GL Along 8-12/A-G9Feb 9'15Feb 18'150.02%100%95%95%5%On going0.016%0.000%0.016%3.1.5.4GL Along 12-16/A-G7Feb 16'15Feb 23'150.01%100%95%95%5%On going0.013%0.000%0.013%3.1.6Backfiling and Compaction works30Jan 29'15Mar 4'150.06%0.06%3.1.6.1Along B/1-166Jan 29'15Feb 4'15Jan 20'15Partialy started (Not critical activity)0.02%100%80%80%20%On going0.012%0.000%0.012%3.1.6.2Along 16/A-H6Feb 12'15Feb 18'150.02%100%80%80%20%On going0.012%0.000%0.012%3.1.6.3Along E/1-166Feb 19'15Feb 25'150.02%100%60%5%65%35%On going0.009%0.001%0.010%3.1.6.4Along 1/A-H6Feb 26'15Mar 4'150.02%100%60%5%65%35%On going0.009%0.001%0.010%3.2Foundations works (isolated)13Mar 5'15Mar 19'150.04%0.04%0.04%3.2.1Footing8Mar 5'15Mar 14'150.02%100%100%100%0%Completed0.024%0.000%0.024%3.2.2Column Neck/Plinth6Mar 14'15Mar 19'150.02%100%95%95%5%On going0.017%0.000%0.017%3.3Grade beam14Feb 7'15Feb 22'150.05%0.05%0.05%0.05%100%95%95%5%On going0.044%0.000%0.044%3.4Grade slab6Feb 5'15Feb11'150.02%0.02%0.02%0.02%100%95%95%5%On going0.019%0.000%0.019%3.6Precast works (by Others)32Jan25'15Mar 2'15Jan 31'15CRITICAL (On going)0.11%0.11%0.11%0.11%100%85%5%90%10%On going0.090%0.005%0.095%3.7Roof water proofing sytem and roof finishes25Mar 3'15Mar 31'150.08%0.08%0.08%0.08%100%3.8Reinforced concrete shear wall33Feb9'15Mar 18'150.11%0.11%0.11%3.8.1Grid Line 1-2 / B/A(2Nos)33Feb 9'15Mar 18'15On going0.06%100%95%95%5%On going0.060%0.000%0.060%3.8.2Grid Line 15-16 / (2Nos)24Feb 9'15Mar 8'15On going0.05%100%85%10%95%5%On going0.039%0.005%0.043%3.9Reinforced concrete stair14Mar 4'15Mar 19'150.05%0.05%0.05%3.9.1Stair # 17Mar 4'15Mar 11'15On going0.02%100%100%100%0%Completed0.023%0.000%0.023%3.9.2Stair # 27Mar 12'15Mar 19'15On going0.02%100%100%100%0%Completed0.023%0.000%0.023%3.10Painting works28Mar 8 '15Apr 8'15On going0.09%0.09%0.09%0.09%100%35%5%40%60%On going0.032%0.005%0.037%3.11Finshing of basement 28Feb 3'15Mar7'15On going0.09%0.09%0.09%0.09%100%100%100%0%Completed0.092%0.000%0.092%3.12Specialties22Mar 3'15Mar 28'150.07%0.07%0.07%0.07%100%15%15%85%On going0.011%0.000%0.011%4.0Control Building Civil WorksNov 29'14Jul 1'152.25%4.1Control Building Basements103Dec 3'14Apr 1'15Nov 9'140.50%4.1.1Earthworks4Nov 29'14Dec 2'15Nov 9'14Nov 19;14Completed0.02%0.02%0.02%100%100%100%0%Completed0.016%0.000%0.016%4.1.2Basement (Raft Fdn/Base Slab)23Dec 3'14Dec 29'140.09%0.09%4.1.2.1Lean Concrete2Dec 3'14Dec 4 '14Nov20'14Nov 22'14Completed 0.01%100%100%100%0%Completed0.006%0.000%0.006%4.1.2.2Waterproofing System for basement -Grid Line B-G/10-175Dec 6'14Dec 10'14Nov 24'14Dec 2 '14Completed 0.01%100%100%100%0%Completed0.014%0.000%0.014%4.1.2.3Waterproofing System for basement -Grid Line G-M/7-175Dec 7'14Dec 11'140.01%100%100%100%0%Completed0.014%0.000%0.014%4.1.2.4RC base slab and raft fdn Grid Line A-P/11-1816Dec 11'14Dec 29'14Dec 21'14Jan 13'15Delayed(Completed)0.04%100%100%100%0%Completed0.044%0.000%0.044%4.1.2.5RC base slab and raft fdn Grid Line G-M/7-105Dec 23'14Dec 28'140.01%100%100%100%0%Completed0.014%0.000%0.014%4.1.3Basement (RC Walls and Collum)23Dec 30'14Feb 16'150.09%0.09%4.1.3.1Grid Line B-G/10-1717Dec 30'14Jan 18'15Jan 14'15Jan 22'15Completed0.03%100%100%100%0%Completed0.028%0.000%0.028%4.1.3.2Grid Line G-M/7-1714Jan 10'15Jan 25'150.02%100%100%100%0%Completed0.023%0.000%0.023%4.1.3.3RC Column(Basement) Grid Line B-G/10-1713Jan 19'15Feb 2'15Jan 24'15Feb 1,15Completed0.02%100%100%100%0%Completed0.021%0.000%0.021%4.1.3.4RC Column (Basement)Grid Line B-G/7-1712Feb 3'15Feb 16'150.02%100%100%100%0%Completed0.020%0.000%0.020%4.1.4Basement ( Suspended slab and beams)38Feb 17'15Apr 1'15Feb 2'15On going0.15%0.15%0.15%100%70%10%80%20%On going0.106%0.015%0.121%4.1.5Waterproofing works for RC wall13Mar 21'15Apr 4'150.05%0.05%4.1.5.1Retaining wall works GL 7/G-M,10/C-G4Mar 21'15Mar 24'150.01%100%80%5%85%15%On going0.012%0.001%0.013%4.1.5.2Retaining wall works Sequence 0210Mar 24'15Apr 4'150.04%100%80%5%85%15%On going0.030%0.002%0.031%4.1.6Backfiling and Compaction works24Mar 25'15Apr 21'150.10%0.10%0.10%100%4.2Foundations works (isolated)78Jan 24'15Apr 23'15Dec 16'140.38%0.38%0.38%4.2.1Grid Line 1-2/A-P34Jan 24'15Mar 3'15Dec 16'14No activity0.09%100%30%5%35%65%On going0.028%0.005%0.033%4.2.2Grid Line 3-4/A-P35Jan 25'15Mar 5'150.10%100%30%5%35%65%On going0.029%0.005%0.034%4.2.3Grid Line 5-6/A-P46Jan 26'15Mar 19'150.13%100%30%5%35%65%On going0.038%0.006%0.045%4.2.4Grid Line 7-11/A-P21Mar 31'15Apr 23'150.06%100%30%5%35%65%On going0.017%0.003%0.020%4.3Grade beam27Mar 21'15Apr 20'150.13%0.13%0.13%0.13%100%4.4Grade slab16Apr 21'15May 9'150.08%0.08%0.08%0.08%100%4.6Precast works (by Others) For Basements41Mar 17'15May 3'150.20%0.20%0.20%0.20%100%4.7Precast works (by Others) For Isolated Footings41Apr20'15Jan 6'150.20%0.20%0.20%0.20%100%4.8Reinforced concrete stair16Mar17'15Apr 4'150.08%0.08%0.08%4.8.1Stair # 110Mar 17'15Mar 28'150.04%100%4.8.2Stair # 210Mar 24'15Apr 4'150.04%100%4.9Masonry Works-Control Room10Apr8'15Apr 9'150.05%0.05%0.05%0.05%100%4.10Masonry Works-Misc.Offices and Power room18May 12'15Jun 1,150.09%0.09%0.09%0.09%100%4.11Misc.Finishes For Control Roon53Feb 28'15Apr 29'150.26%0.26%0.26%0.26%100%4.12Misc.Finishes 26Jun 2'15Jul 1'150.13%0.13%0.13%0.13%100%4.13Finishing Works For Basements25Apr 2'15Apr 30'150.12%0.12%0.12%0.12%100%4.14Specialties11May 4'15May 16'150.05%0.05%0.05%0.05%100%5.013.8 kV Building Civil WorksDec 28'14May 17'150.76%5.113.8 kv Basements73Dec 29'14Mar 23'15Nov 13'140.25%5.1.1Earthworks1Dec 29'14Dec29'14Nov 13'14Nov 20'14Completed0.00%0.00%0.00%100%100%100%0%Completed0.002%0.000%0.002%5.1.2Basement (Raft Fdn/Base Slab)15Dec 30'14Jan 15'15Nov 24'14On going0.03%0.03%5.1.2.1Lean Concrete1Dec 30'14Dec 30'14Nov 24'14Nov 24'14Completed0.00%100%100%100%0%Completed0.001%0.000%0.001%5.1.2.2Waterproofing System for basement -Grid Line 1-7/A - D4Dec 31'14Jan 4 ' 15Nov 29'14Dec 8'14Completed0.01%100%100%100%0%Completed0.006%0.000%0.006%5.1.2.3Waterproofing System for basement -Grid Line 7-13 /A - D4Jan 1'14Jan 5'15Completed0.01%100%100%100%0%Completed0.006%0.000%0.006%5.1.2.4RC base slab and raft fdn Grid Line 1-7/A-D6Jan 5'15Jan 11'15Jan 4'15Jan 22'15Delayed(Completed)0.01%100%100%100%0%Completed0.009%0.000%0.009%5.1.2.5RC base slab and raft fdn Grid Line 7-13/A-D6Jan 10'15Jan 15'150.01%100%100%100%0%Completed0.009%0.000%0.009%5.1.3Basement (RC Walls and Collum)22Jan 12'15Feb 3'150.05%0.05%5.1.3.1Grid Line 1-7/A-D11Jan 12'15Jan 21'15Feb1'15On going0.02%100%100%100%0%Completed0.023%0.000%0.023%5.1.3.2Grid Line 7-13/A-D11Jan 25'15Feb 3'150.02%100%100%100%0%Completed0.023%0.000%0.023%5.1.4Basement ( Suspended slab and beams)50Jan 25'15Feb 28'150.10%0.10%5.1.4.1RC works Top slab Grid Line1-739Jan 25'15Feb15'15Feb 23'15On going0.05%100%70%30%100%0%Completed0.036%0.016%0.052%5.1.4.2RC works Top slab Grid Line 8-1339Feb 7'15Feb28'150.05%100%40%60%100%0%Completed0.021%0.031%0.052%5.1.5Waterproofing works (Retaining walls)17Feb 24'15Mar 7 '150.04%0.04%5.1.5.1Grid Line 1-4/A-G6Feb 24'15Mar 2'150.02%100%5.1.5.2Grid Line 5-7/A-G6Mar 9'15Mar 15'150.02%100%5.1.6Backfiling and Compaction works15Mar 3'15Mar 19'150.03%0.03%0.03%100%5.2Precast works (by Others)48Mar 1'15Apr 25'150.16%0.16%0.16%0.16%100%5.3Roof water proofing sytem and roof finishes19Apr 26'15May 17'150.07%0.07%0.07%0.07%100%5.4Reinforced concrete stair6Mar 24'15Mar 30'150.02%0.02%0.02%0.02%100%5.5Masonry Works5Mar 24'15Mar 29'150.02%0.02%0.02%0.02%100%5.6Painting works20Apr 6'15May 9'150.07%0.07%0.07%0.07%100%5.7Finshing Works for basement 14Mar 24'15Apr 8'150.05%0.05%0.05%0.05%100%5.8Specialties37Mar 31'15May 12'150.13%0.13%0.13%0.13%100%6.0RC Cable Tannels (5m wide)Jan 11'15Nov29'151.80%6.1RC Tannel From132kv To Control Building71Jan11'15Apr 2'15Nov 19'140.17%6.1.1Earthworks6Jan 11'15Jan 17'15Nov 19'14Jan 8'15Completed0.01%0.01%0.01%100%100%100%0%Completed0.013%0.000%0.013%6.1.2Basement (Raft Fdn/Base Slab)16Jan 18'15Feb 4'150.03%0.03%6.1.2.1Lean Concrete1Jan 18'15Jan 18'15Completed0.00%100%100%100%0%Completed0.002%0.000%0.002%6.1.2.2Waterproofing System for basement4Jan 19'15Jan 22'15Feb 3'15Delayed(Completed)0.01%100%100%100%0%Completed0.009%0.000%0.009%6.1.2.3RCBase slab and Raft foundation10Jan 25'15Feb 4'15Feb 4'15Feb 9,15Delayed(Completed)0.02%100%100%100%0%Completed0.022%0.000%0.022%6.1.3Basement (RC Walls and Collum)11Feb 5'15Feb 17'150.02%0.02%0.02%100%70%70%30%On going0.016%0.000%0.016%6.1.4Basement ( Suspended slab and beams)38Feb 18'15Apr 2'150.08%0.08%0.08%100%6.1.5Waterproofing works (Retaining walls)6Mar 23'15Mar 29'150.01%0.01%0.01%100%6.1.6Backfiling and Compaction works2Mar30'15Mar 31'150.00%0.00%0.00%100%6.2RC Tannel From132kv To SGT Transformer - 471Jan 18'15Apr 9'15Dec 8'140.17%6.2.1Earthworks5Jan 18'15Jan 22'15Dec 8'14On going0.01%0.01%0.01%100%40%40%60%On going0.005%0.000%0.005%6.2.2Basement (Raft Fdn/Base Slab)18Jan 24'15Feb 12'15Dec 18'14No activity0.04%0.04%6.2.2.1Lean Concrete1Jan 24'15Jan 24'15Dec 18'14On going0.00%100%40%40%60%On going0.001%0.000%0.001%6.2.2.2Waterproofing System for basement4Jan 25'15Jan 28'15Dec 24'14On going0.01%100%40%40%60%On going0.005%0.000%0.005%6.2.2.3RCBase slab and Raft foundation9Feb 3'15Feb 12'15Jan 8'15On going0.03%100%40%40%60%On going0.010%0.000%0.010%6.2.3Basement (RC Walls and Collum)12Feb 14'15Feb 26'15Feb 3'150.03%0.03%0.03%100%40%40%60%On going0.011%0.000%0.011%6.2.4Basement ( Suspended slab and beams)31Feb 28'15Apr 4'150.07%0.07%0.07%100%6.2.5Waterproofing works (Retaining walls)6Apr 1'15Apr 7'150.01%0.01%0.01%100%40%40%60%On going0.005%0.000%0.005%6.2.6Backfiling and Compaction works2Apr 8'15Apr 9'150.00%0.00%0.00%100%40%40%60%On going0.002%0.000%0.002%6.3RC Tannel From132kv To SGT Transformer - 368Jan 20'15Apr 8'15Dec 2'140.16%6.3.1Earthworks6Jan 20'15Jan 26'15Dec 2'14On going0.01%0.01%0.01%100%40%40%60%On going0.005%0.000%0.005%6.3.2Basement (Raft Fdn/Base Slab)14Jan 27'15Feb 15'15Dec 18'14No activity0.03%0.03%6.3.2.1Lean Concrete1Jan 27'15Jan 27'15Dec 18'14On going0.00%100%40%40%60%On going0.001%0.000%0.001%6.3.2.2Waterproofing System for basement4Jan 28'15Feb 1 '15Dec 24'14On going0.01%100%40%40%60%On going0.004%0.000%0.004%6.3.2.3RCBase slab and Raft foundation9Feb 2'15Feb 11'15Jan 6'15On going0.02%100%40%40%60%On going0.008%0.000%0.008%6.3.3Basement (RC Walls and Collum)12Feb12'15Feb 25'15Feb 4'150.03%0.03%0.03%100%40%40%60%On going0.011%0.000%0.011%6.3.4Basement ( Suspended slab and beams)31Feb 26'15Apr 2'150.07%0.07%0.07%100%6.3.5Waterproofing works (Retaining walls)6Mar 31'15Apr 6'150.01%0.01%0.01%100%40%40%60%On going0.005%0.000%0.005%6.3.6Backfiling and Compaction works2Apr 7'15Apr 8'150.00%0.00%0.00%100%40%40%60%On going0.002%0.000%0.002%6.4RC Tannel From132kv To SGT Transformer - 268Jan 20'15Apr 8'15Nov 27'140.16%6.4.1Earthworks6Jan 20'15Jan 26'15Nov 27'14On going0.01%0.01%0.01%100%40%40%60%On going0.005%0.000%0.005%6.4.2Basement (Raft Fdn/Base Slab)14Jan 27'15Apr 2'15Dec 18'14No activity0.03%0.03%6.4.2.1Lean Concrete1Jan 27'15Jan 27'15Dec 18'14On going0.00%100%40%40%60%On going0.001%0.000%0.001%6.4.2.2Waterproofing System for basement4Jan 28'15Feb 1'15Dec 24'14On going0.01%100%40%40%60%On going0.004%0.000%0.004%6.4.2.3RCBase slab and Raft foundation9Feb 2'15Feb 11'15Jan 4'15On going0.02%100%40%40%60%On going0.008%0.000%0.008%6.4.3Basement (RC Walls and Collum)12Feb 2'15Feb 25'150.03%0.03%0.03%100%40%40%60%On going0.011%0.000%0.011%6.4.4Basement ( Suspended slab and beams)31Feb 26'15Apr 2'150.07%0.07%0.07%100%6.4.5Waterproofing works (Retaining walls)6Mar 31'15Apr 6'150.01%0.01%0.01%100%40%40%60%On going0.005%0.000%0.005%6.4.6Backfiling and Compaction works2Apr 7'15Apr 8'150.00%0.00%0.00%100%40%40%60%On going0.002%0.000%0.002%6.5RC Tannel From 380kv To Control Building92Jan 18'15May 4'15Jan 5'150.22%6.5.1Earthworks13Jan 18'15Feb 1'15Jan 5'15On going0.02%0.02%0.02%100%50%50%100%0%Completed0.011%0.011%0.022%6.5.2Basement (Raft Fdn/Base Slab)22Feb 2'15Feb 26'150.04%0.04%6.5.2.1Lean Concrete1Feb 2'15Feb 15'15On going0.00%100%50%50%100%0%Completed0.001%0.001%0.001%6.5.2.2Waterproofing System for basement -Phase 15Feb 3'15Feb 8'15Completed0.01%100%100%100%0%Completed0.007%0.000%0.007%6.5.2.3Waterproofing System for basement -Phase 25Feb 4'15Feb 9'150.01%100%6.5.2.4RC base slab and raft fdn Sequence 18Feb 9'15Feb 17'15Feb 23'15Completed0.01%100%100%100%0%Completed0.011%0.000%0.011%6.5.2.5RC base slab and raft fdn Sequence 28Feb 18'15Feb 26'150.01%100%6.5.3Basement (RC Walls and Collum)17Feb 18'15Mar 9'150.03%0.03%6.5.3.1Sequence-19Feb 18'15Feb 28'15On going0.01%100%50%50%100%0%Completed0.007%0.007%0.015%6.5.3.2Sequence-29Feb 28'15Mar 9'150.01%100%6.5.4Basement ( Suspended slab and beams)48Mar 10'15May 4'150.08%0.08%6.5.4.1RC Works Top Slab Phase 133Mar 10'15Apr 16'150.04%100%6.5.4.2RC Works Top Slab Phase 232Mar 29'15May 4'150.04%100%6.5.5Waterproofing works (Retaining walls)10Apr 6'15Apr 16'150.02%0.02%6.5.5.1Sequence-15Apr 6'15Apr 11'140.01%100%6.5.5.2Sequence-25Apr 12'15Apr 16'150.01%100%6.5.6Backfiling and Compaction works15Apr 12'15Apr 28'150.03%0.03%6.5.6.1Right Wing10Apr 12'15Apr 22'150.01%100%6.5.6.2Left Wing10Apr 18'15Apr 28'150.01%100%6.6RC Tannel From 380kv To Boundary Wall East (GL 2-5)97Jul 9'15Oct29'150.23%6.6.1Earthworks7Jul 9'15Jul16'150.01%0.01%0.01%100%6.6.2Basement (Raft Fdn/Base Slab)36Jul 18'15Aug 27'150.04%0.04%6.6.2.1Lean Concrete1Jul 18'15Jul 18'150.00%100%6.6.2.2Waterproofing System for basement -Phase 14Jul 19'15Jul 22'150.00%100%6.6.2.3Waterproofing System for basement -Phase 24Jul 20'15Jul 23'150.00%100%6.6.2.4RC base slab and raft fdn Sequence 18Jul 23'15Aug 1'150.01%100%6.6.2.5RC base slab and raft fdn Sequence 28Aug 2'15Aug 10'150.01%100%6.6.2.6RC base slab and raft fdn Sequence 37Aug 11'15Aug 18'150.01%100%6.6.2.7RC base slab and raft fdn Sequence 48Aug 19'15Aug 27'150.01%100%6.6.3Basement (RC Walls and Collum)33Aug 2'15Sep 8'150.04%0.04%6.6.3.1Sequence 19Aug 2'15Aug 11'150.01%100%6.6.3.2Sequence 29Aug 12'15Aug 22'150.01%100%6.6.3.3Sequence 39Aug 19'15Aug 29'150.01%100%6.6.3.4Sequence 49Aug 30'15Sep 8'150.01%100%6.6.4Basement ( Suspended slab and beams)57Aug 23'15Oct 27'150.07%0.07%6.6.4.1RC Works Top Slab Phase 142Aug 23'15Oct 10'150.03%100%6.6.4.2RC Works Top Slab Phase 242Sep 9'15Oct 27'150.03%100%6.6.5Waterproofing works (Retaining walls)31Sep 24'15Oct 29'150.04%0.04%6.6.5.1Sequence 15Sep 24'15Sep 29'150.01%100%6.6.5.2Sequence 25Oct 12'15Oct 17'150.01%100%6.6.5.3Sequence 35Oct 18'15Oct 22'150.01%100%6.6.5.4Sequence 46Oct 24'15Oct 29'150.01%100%6.6.6Backfiling and Compaction works25Sep 30'15Oct 28 '150.03%0.03%6.6.6.1Right Wing10Sep 30'15Oct 11'150.02%100%6.6.6.2Left Wing10Oct 18'15Oct 28'150.02%100%6.7RC Tannel From 380kv To Boundary Wall East (GL 19-23)92Jul 18'15Nov 1'150.22%6.7.1Earthworks7Jul 18'15Jul 25'150.01%0.01%0.01%100%6.7.2Basement (Raft Fdn/Base Slab)21Jul 26'15Aug 18'150.03%0.03%6.7.2.1Lean Concrete1Jul 26'15Jul 26'150.00%100%6.7.2.2Waterproofing System for basement -Phase 14Jul 27'15Jul 30'150.01%100%6.7.2.3Waterproofing System for basement -Phase 25Jul 28'15Aug 2'150.01%100%6.7.2.4RC base slab and raft fdn Sequence 18Aug 1'15Aug 9'150.01%100%6.7.2.5RC base slab and raft fdn Sequence 28Aug 10'15Aug 18'150.01%100%6.7.3Basement (RC Walls and Collum)18Aug 19'15Sep 8'150.03%0.03%6.7.3.1Sequence 19Aug 19'15Aug 29'150.01%100%6.7.3.2Sequence 29Aug 30'15Sep 8'150.01%100%6.7.4Basement ( Suspended slab and beams)54Aug 30'15Oct 31'150.08%0.08%6.7.4.1RC Works Top Slab Phase 142Aug 30'15Oct 17'150.04%100%6.7.4.2RC Works Top Slab Phase 245Sep 9'15Oct 31'150.04%100%6.7.5Waterproofing works (Retaining walls)17Oct 1 '15Oct 20'150.03%0.03%6.7.5.1Sequence 15Oct 1'15Oct 6'150.01%100%6.7.5.2Sequence 25Oct 15'15Oct 20'150.01%100%6.7.6Backfiling and Compaction works22Oct 7'15Nov 1'150.03%0.03%6.7.6.1Right Wing10\\oct 7'15Oct 18'150.02%100%6.7.6.2Left Wing10Oct 21'15Nov 1'150.02%100%6.8RC Tunnel From 380kv To Boundary Wall North109Jul 26'15Nov 29'150.26%6.8.1Earthworks8Jul 26'15Aug 3'150.01%0.01%0.01%100%6.8.2Basement (Raft Fdn/Base Slab)38Aug 4'15Sep 16'150.05%0.05%6.8.2.1Lean Concrete2Aug 4'15Aug 5'150.00%100%6.8.2.2Waterproofing System for basement -Phase 17Aug 6'15Aug 13'150.01%100%6.8.2.3Waterproofing System for basement -Phase 25Aug 8'15Aug 12'150.00%100%6.8.2.4RC base slab and raft fdn Sequence 19Aug 15'15Aug 24'150.01%100%6.8.2.5RC base slab and raft fdn Sequence 29Aug 23'15Sep 1'150.01%100%6.8.2.6RC base slab and raft fdn Sequence 38Aug 31'15Sep 8'150.01%100%6.8.2.7RC base slab and raft fdn Sequence 49Sep 7'15Sep 16'150.01%100%6.8.3Basement (RC Walls and Collum)35Aug 25'15Oct 4'150.04%0.04%6.8.3.1Sequence 110Aug 25'15Sep 5'150.01%100%6.8.3.2Sequence 210Sep 6'15Sep 16'150.01%100%6.8.3.3Sequence 310Sep 12'15Sep 22'150.01%100%6.8.3.4Sequence 410Sep 23'15Oct 4'150.01%100%6.8.4Basement ( Suspended slab and beams)59Sep 17'15Nov 24'150.08%0.08%6.8.4.1RC Works Top Slab Phase 144Sep 17'15Nov 7'150.04%100%6.8.4.2RC Works Top Slab Phase 244Oct 5'15Nov 24'150.04%100%6.8.5Waterproofing works (Retaining walls)33Oct 22'15Nov 29'150.04%0.04%6.8.5.1Sequence 16Oct 22'15Oct 28'150.01%100%6.8.5.2Sequence 26Nov 9'15Nov 15'150.01%100%6.8.5.3Sequence 36Nov16'15Nov 22'150.01%100%6.8.5.4Sequence 46Nov 23'15Nov 26'150.01%100%6.8.6Backfiling and Compaction works27Oct 29'15Nov 29'150.03%0.03%6.8.6.1Right Wing12Oct 29'15Nov 11'150.02%100%6.8.6.2Left Wing12Nov 16'15Nov 29'150.02%100%6.9RC Tunnel From 132kv To Boundary Wall (East) Twin Tunnel99Jul 27'15Nov 18'150.23%6.9.1Sequence 1 (60 meters) - Twin Tunnel85Jul 27'15Nov 2'15Jan 7'150.08%6.9.1.1Earthworks8Jul 27'15Aug 4'15Jan 7'15On going0.01%0.01%100%100%100%0%Completed0.006%0.000%0.006%6.9.1.2Basement (Raft Fdn/Base Slab)27Aug 5'15Sep 5'150.02%6.9.1.2.1Lean Concrete3Aug 5'15Aug 8'150.002%100%6.9.1.2.2Waterproofing System for basement6Aug 6'15Aug 12'150.004%100%6.9.1.2.3RCBase slab and Raft foundation20Aug 13'15Sep 5'150.014%100%6.9.1.3Basement (RC Walls and Collum) 3 Walls22Sep 5'15Sep 29'150.02%6.9.1.3.1Wall and Column 1-30 meters11Sep 5'15Sep 16'150.01%100%6.9.1.3.2Wall and Column 2-30 meters11Sep 17'15Sep 29'150.01%100%6.9.1.4Basement ( Suspended slab and beams)40Sep 17'15Nov 2'150.03%0.03%100%6.9.1.5Waterproofing works (Retaining walls)6Oct 22'15Oct 28'150.00%0.00%100%6.9.1.6Backfiling and Compaction works2Oct 29'15Oct 31'150.00%0.00%100%6.9.2Sequence 2 (60 meters) - Twin Tunnel75Aug 5'15Oct 31'150.07%6.9.2.1Earthworks7Aug 5'15Aug 12'150.005%0.00%100%10%10%90%0.00000%0.00048%0.00048%6.9.2.2Basement (Raft Fdn/Base Slab)27Aug 13'15Sep 13'150.02%6.9.2.2.1Lean Concrete3Aug 13'15Aug 16'150.00%100%6.9.2.2.2Waterproofing System for basement6Aug 15'15Aug 20'150.00%100%6.9.2.2.3RCBase slab and Raft foundation20Aug 22'15Sep 13'150.01%100%6.9.2.3Basement (RC Walls and Collum) 3 walls22Sep 2'15Sep 27'150.02%6.9.2.3.1Wall and Column 1-20 meters11Sep 2'15Sep 14'150.01%100%6.9.2.3.2Wall and Column 2-20 meters11Sep 15'15Sep 27'150.01%100%6.9.2.4Basement ( Suspended slab and beams)40Sep 15'15Oct 31'150.03%0.03%100%6.9.2.5Waterproofing works (Retaining walls)6Oct 20'15Oct 26'150.00%0.00%100%6.9.2.6Backfiling and Compaction works2Oct 27'15Oct 28'150.00%0.00%100%6.9.3Sequence 3 (60 meters) - Twin Tunnel84Aug 13'15Nov 18'150.08%6.9.3.1Earthworks8Aug 13'15Aug 22'150.01%0.00%100%6.9.3.2Basement (Raft Fdn/Base Slab)27Aug 23'15Sep 20'150.02%6.9.3.2.1Lean Concrete3Aug 23'15Aug 25'150.00%100%6.9.3.2.2Waterproofing System for basement6Aug 24'15Aug 30'150.00%100%6.9.3.2.3RCBase slab and Raft foundation18Aug 31'15Sep 20'150.01%100%6.9.3.3Basement (RC Walls and Collum) 3 Walls22Sep 21'15Oct 15'150.02%6.9.3.3.1Wall and Column 1-20 meters11Sep 21'15Oct 31'150.01%100%6.9.3.3.2Wall and Column 2-20 meters11Oct 4'15Oct 15'150.01%100%6.9.3.4Basement ( Suspended slab and beams)40Oct 4'15Nov 18'150.03%0.03%100%6.9.3.5Waterproofing works (Retaining walls)6Nov8'15Nov14'150.00%0.01%100%6.9.3.6Backfiling and Compaction works2Nov 15'15Nov16'150.00%0.00%100%7.0Transformer 500 MVA T-1 & FirewallMar 23'15May 25'150.18%7.1Earthworks3Mar 24'15Mar 26'15Nov 29'14Nov 30'14Completed0.01%0.01%0.01%0.01%100%100%100%0%Completed0.009%0.000%0.009%7.2Reinforced Concrete Works41Mar 28'15May 13'150.12%0.12%0.12%7.2.1Lean Concrete2Mar 28'15Mar 29'150.01%100%100%100%0%Completed0.006%0.000%0.006%7.2.2RC Raft Foundation17Mar 30'15Apr 18'150.05%100%70%70%30%On going0.035%0.000%0.035%7.2.3RC Wall -117Apr 19'15May 7'150.05%100%50%50%50%On going0.025%0.000%0.025%7.2.4RC Wall -25May 9'15May 13'150.01%100%7.3WaterProofing Retaining Wall Works4May 14'15May 18'150.01%0.01%0.01%0.01%100%7.4Backfilling and Compaction4May 19'15May 23'150.01%0.01%0.01%0.01%100%7.5Finishing Works 4May 14'15May 18'150.01%0.01%0.01%0.01%100%7.6Specialties6May 19'15May 25'150.02%0.02%0.02%0.02%100%8.0Transformer 500 MVA T-2 & Firewallmar 22'15Jun 9'150.18%8.1Earthworks2Mar 23'15Mar 24'15Nov 27'14Nov 29'14Completed0.01%0.01%0.01%0.01%100%100%100%0%Completed0.005%0.000%0.005%8.2Reinforced Concrete Works53Mar 29'15May 28'150.13%0.13%0.13%8.2.1Lean Concrete2Mar 29'15Mar 30'150.01%100%100%100%0%Completed0.007%0.000%0.007%8.2.2RC Raft Foundation4Apr 16'15Apr 20'150.01%100%50%50%50%On going0.007%0.000%0.007%8.2.3RC Wall -117Apr 21'15May 10'150.06%100%50%50%50%On going0.029%0.000%0.029%8.2.4RC Wall -216May 11'15May 28'150.06%100%8.3WaterProofing Retaining Wall Works2May 30'15May 31'150.01%0.01%0.01%0.01%100%8.4Backfilling and Compaction4Jun 1'15Jun 4'150.01%0.01%0.01%0.01%100%8.5Finishing Works 4May 30'15Jun 2'150.01%0.01%0.01%0.01%100%8.6Specialties6Jun 3'15Jun 9'150.02%0.02%0.02%0.02%100%9.0Transformer 500 MVA T-3 & FirewallMar 22'15May 20'150.18%9.1Earthworks2Mar 23'15Mar 24'15Nov 25'14Nov 27'14Completed0.01%0.01%0.01%0.01%100%100%100%0%Completed0.006%0.000%0.006%9.2Reinforced Concrete Works39Mar 25'15May 9'150.12%0.12%0.12%9.2.1Lean Concrete6Mar 25'15Mar 26'150.02%100%100%100%0%Completed0.017%0.000%0.017%9.2.2RC Raft Foundation4Mar 28'15Mar 31'150.01%100%50%50%50%On going0.006%0.000%0.006%9.2.3RC Wall -117Apr 1'15Apr 20'150.05%100%50%50%50%On going0.024%0.000%0.024%9.2.4RC Wall -216Apr 21'15May 9'150.05%100%9.3WaterProofing Retaining Wall Works2May 10'15May 11'150.01%0.01%0.01%0.01%100%9.4Backfilling and Compaction4May 12'15May 16'150.01%0.01%0.01%0.01%100%9.5Finishing Works 4May 10'15May 13'150.01%0.01%0.01%0.01%100%9.6Specialties6May 14'15May 20'150.02%0.02%0.02%0.02%100%10.0Transformer 67 MVA T-1May 13'15Jun 27'150.06%10.1Earthworks1May 14'15May 14'150.00%0.00%0.00%0.00%100%10.2Reinforced Concrete Works31May 16'15Jun 20'150.04%0.04%0.04%10.2.1Lean Concrete5May 16'15May 17'150.01%100%10.2.2RC Raft Foundation3May 18'15May 20'150.00%100%10.2.3RC Wall -110May 21'15Jun 1'150.01%100%10.2.4RC Wall -216Jun 2'15Jun 20'150.02%100%10.3WaterProofing Retaining Wall Works2Jun 21'15Jun 22'150.00%0.00%0.00%0.00%100%10.4Backfilling and Compaction2Jun 23'15Jun 24'150.00%0.00%0.00%0.00%100%10.5Finishing Works 2Jun 21'15Jun 22'150.00%0.00%0.00%0.00%100%10.6Specialties4Jun 23'15Jun 27'150.01%0.01%0.01%0.01%100%11.0Transformer 67 MVA T-2May 30'15Jul 12'150.06%11.1Earthworks1May 31'15May 31'150.00%0.00%0.00%0.00%100%11.2Reinforced Concrete Works30Jun 1'15Jul 5'150.04%0.04%0.04%11.2.1Lean Concrete5Jun 1'15Jun 2'150.01%100%11.2.2RC Raft Foundation3Jun 3'15Jun 6'150.00%100%11.2.3RC Wall -19Jun 7'15Jun 16'150.01%100%11.2.4RC Wall -216Jun 17'15Jul b5'150.02%100%11.3WaterProofing Retaining Wall Works2Jul 6'15Ju 7'150.00%0.00%0.00%0.00%100%11.4Backfilling and Compaction2Jul 8'15Jul 9'150.00%0.00%0.00%0.00%100%11.5Finishing Works 2Jul 6'15Jul 7'150.00%0.00%0.00%0.00%100%11.6Specialties4Jul 8'15Jul 12'150.01%0.01%0.01%0.01%100%12.0Transformer 67 MVA T-3May 9'15Jun 23'150.06%12.1Earthworks1May 10'15May 10'150.00%0.00%0.00%0.00%100%12.2Reinforced Concrete Works32May 11'15Jun 16'150.04%0.04%0.04%12.2.1Lean Concrete2May 11'15May 12'150.00%100%11.2.2RC Raft Foundation4May 13'15May 17'150.01%100%11.2.3RC Wall -110May 18'15May 28'150.01%100%11.2.4RC Wall -216May 30'15Jun 16'150.02%100%12.3WaterProofing Retaining Wall Works2Jun 17'15Jun 18'150.00%0.00%0.00%0.00%100%12.4Backfilling and Compaction2Jun 20'15Jun 21'150.00%0.00%0.00%0.00%100%12.5Finishing Works 2Jun 17'15Jun 18'150.00%0.00%0.00%0.00%100%12.6Specialties4Jun 20'15Jun 23'150.01%0.01%0.01%0.01%100%13.047 MVA Reactor-1Jun 20'15Jul 14'150.06%13.1Earthworks1Jun 21'15Jun 21'150.00%0.00%0.00%0.00%100%13.2Reinforced Concrete Works14Jun 22'15Jul 7'150.03%0.03%0.03%13.2.1Lean Concrete2Jun 22'15Jun 23'150.00%100%13.2.2RC Raft Foundation3Jun 24'15Jun 27'150.01%100%13.2.3RC Wall -19Jun 28'15Jul 1'150.02%100%13.2.4RC Wall -25Jul 2'15Jul 7'150.01%100%13.3WaterProofing Retaining Wall Works2Jul 8'15Jul 9'150.00%0.00%0.00%0.00%100%13.4Backfilling and Compaction2Jul 11'15Jul 12'150.00%0.00%0.00%0.00%100%13.5Finishing Works 2Jul 8'15Jul 9'150.00%0.00%0.00%0.00%100%13.6Specialties4Jul 11'15Jul 14'150.01%0.01%0.01%0.01%100%14.047 MVA Reactor-2Jul 6'15Jul 30'150.06%14.1Earthworks1Jul 7'15Jul 7'150.00%0.00%0.00%0.00%100%14.2Reinforced Concrete Works14Jul 8'15Jul 23'150.03%0.03%0.03%14.2.1Lean Concrete2Jul 8'15Jul 9'150.00%100%14.2.2RC Raft Foundation3Jul 11'15Jul 13 '150.01%100%14.2.3RC Wall -14Jul 14'15Jul 18'150.01%100%14.2.4RC Wall -25Jul 19'15Jul 23'150.01%100%14.3WaterProofing Retaining Wall Works2Jul 25'15Hul 26'150.00%0.00%0.00%0.00%100%14.4Backfilling and Compaction2Jul 27'15Jul 28'150.00%0.00%0.00%0.00%100%14.5Finishing Works 2Jul 25'15Jul 26'150.00%0.00%0.00%0.00%100%14.6Specialties4Jul 27'15Jul 30'150.01%0.01%0.01%0.01%100%15.047 MVA Reactor-3Jun16'15Jul 11'150.06%15.1Earthworks1Jun 17'15Jun 17'150.00%0.00%0.00%0.00%100%15.2Reinforced Concrete Works14Jun 18'15Jul 4'150.03%0.03%0.03%15.2.1Lean Concrete2Jun 18'15Jun 20'150.00%100%15.2.2RC Raft Foundation3Jun 21'15Jun 23'150.01%100%15.2.3RC Wall -14Jun 24'15Jun 28'150.01%100%15.2.4RC Wall -25Jun 29'15Jul 4'150.01%100%15.3WaterProofing Retaining Wall Works2Jul 5'15Jul 6'150.00%0.00%0.00%0.00%100%15.4Backfilling and Compaction2Jul 7'15Jul 8'150.00%0.00%0.00%0.00%100%15.5Finishing Works 2Jul 5'15Jul 6'150.00%0.00%0.00%0.00%100%15.6Specialties4Jul 7'15Jul 11'150.01%0.01%0.01%0.01%100%16.0Power Duct BanksJun 11'15Aug 29'150.36%16.1Power Duck bank (3x200mmDiameter 158 meters28Jun 13'15Jul 15'150.08%0.08%0.08%16.1.1Earthworks3Jun 13'15Jun 15'150.01%100%16.1.2Lean Concrete3Jun 16'15Jun 18'150.01%100%16.1.3Piping Works4Jun 20'15Jun 23'150.01%100%16.1.4RC Works7Jul 1'15Jul 18'150.02%100%16.1.5Waterproofing works 2Jul 9'15Jul 11'150.01%100%16.1.6Backfill4Jul 12'15Jul 15'150.01%100%16.2Power Duck bank (3x200mmDiameter 252.5 meters36Jun 16'15Jul 27'150.10%0.10%0.10%16.2.1Earthworks4Jun 16'15Jun 20'150.01%100%16.2.2Lean Concrete4Jun 21'15Jun 24'150.01%100%16.2.3Piping Works7Jun 25'15Jul 2'150.02%100%16.2.4RC Works11Jul 7'15Jul 19'150.03%100%16.2.5Waterproofing works 2Jul 20'15Jul 21'150.01%100%16.2.6Backfill5Jul 22;15Jul 27'150.02%100%16.3Power Duck bank (10x200mmDiameter 622 meters60Jun 21'15Aug 29'150.17%0.17%0.17%16.3.1Earthworks8Jun 21'15Jun 29'150.02%100%16.3.2Lean Concrete4Jun 30'15Jul 4'150.01%100%16.3.3Piping Works16Jul 5'15Jul 22'150.04%100%16.3.4RC Works25Jul 16'15Aug 13'150.07%100%16.3.5Waterproofing works 3Aug 15'15Aug 17'150.01%100%16.3.6Backfill10Aug 18'15Aug 29'150.03%100%17.0Communication Duct BanksJun 17'15Aug 1'150.12%17.1Communication Duck bank (2x110mm 217 meters38Jun 18'15Aug 1'150.07%0.07%0.07%17.1.1Earthworks6Jun 18'15Jun 24'150.01%100%17.1.2Lean Concrete3Jun 25'15Jun 28'150.01%100%17.1.3Piping Works12Jun 29'15Jul 12'150.02%100%17.1.4RC Works15Jul 11'15Jul 27'150.03%100%17.1.5Waterproofing works 2Jul 28'15Jul 29'150.00%100%17.1.6Backfill2Jul 30'15Aug 1'150.00%100%17.2Communication Duck bank (2x110mm 157 meters28Jun 25'15Jul 27'150.05%0.05%0.05%17.2.1Earthworks4Jun 25'15Jun 29'150.01%100%17.2.2Lean Concrete2Jun 30'15Jul 1'150.00%100%17.2.3Piping Works6Jul 2'15Jul 8'150.01%100%17.2.4RC Works9Jul 14'15Jul 23'150.02%100%17.2.5Waterproofing works 1Jul 25'15Jul 25'150.00%100%17.2.6Backfill2Jul 26'15Jul 27'150.00%100%18.0Bust Duck foundations51Jun 20'15Aug 18'150.18%0.18%0.18%0.18%18.1Earthworks3Jun 21'15Jun 23'150.01%100%18.2Lean Concrete3Jun 24'15Jun 27'150.01%100%18.3RC Works38Jun 28'15Aug 10'150.13%100%18.4Waterproofing works 3Aug 11'15Aug 13'150.01%100%18.5Backfill4Aug 15'15Aug 18'150.01%100%19.0Gantry foundations36Jun 22'15Aug 3'150.16%0.16%0.16%0.16%19.1Earthworks5Jun 23'15Jun 28'150.02%100%19.2Lean Concrete3Jun 29'15Jul 1'150.01%100%19.3RC Works23Jul 2'15Jul 28'150.10%100%19.4Waterproofing works 2Jul 29'15Jul 30'150.01%100%19.5Backfill3Aug 1'15Aug 3'150.01%100%20.0External LP,LM,SLP Foundation37Oct 6'15Nov 18'150.49%0.49%0.49%0.49%20.1Earthworks3Oct 7'15Oct 10'150.04%100%20.2Lean Concrete3Oct 11;15Oct 13'150.04%100%20.3RC Works28Oct 14'15Nov 15'150.37%100%20.4Waterproofing works 1Nov 16'15Nov 16'150.01%100%20.5Backfill2Nov 17'15Nov 18'150.03%100%21.0Boundary Wall Reinforced concrete works120Aug 20'15Jan 7'160.67%0.67%0.67%0.67%21.1Earthworks7Aug 22'15Aug 29'150.04%100%21.2Lean Concrete2Aug 30'15Aug 31'150.01%100%21.3RC Works107Sep 11'15Jan 3'160.60%100%21.4Waterproofing works 2Jan 4 '16Jan 5 '160.01%100%21.5Backfill2Jan 6'16Jan 7'160.01%100%22.0Earthworks (external site works) & Other civil works30Dec 5;'15Jan 7'161.02%1.02%1.02%1.02%1.02%100%TOTAL CONTRACT PERCENT CIVIL WORKS12.00%12.00%12.00%12.00%12.00%OVERALL PECENTAGES ACCOMPLISHMENTS26.9217%1.1987%28.120%

PreviousThis WeekTo date

PREPARED BY :FRANCISCO SUMCAD JRFAIZ UR REHMANCIVIL ENGINEER PROJECT ENGINEER (CIVIL)SAUDI ENGINEERING GROUP INTERNATIONAL SAUDI ENGINEERING GROUP INTERNATIONAL

S-curve

WEEKLY PROJECT MONITORING

(N/A as approved work schedule and planned values not available and have to provided by the contractor)

As of August 10,2015Report No. 11

PROJECT TITLEQASSIM - 5 (UNAYZAH) 380/132/13.8 KV BSP # 9059Contract No.4400005408ContractorAL MASHARIQ CO.WeatherHotSubcontractorAL FAHD Co.

Item No.Work DiscriptionScheduleContract % Factor%201520152016JunJulAugDecJanFebMarchAprilMayJuneJulyAugustSepOctNovDecJanDurationStartFinish1530153115301531153115281531153015311530153115311530153115301531151Mobilization and Preparation of Civil Works46JunAug0.760%6.3%6.3%100.0%102832282100.001.11PLANNED (CUMULATIVE)99.00%0.6331.7732.0271.7730.1276.332ACTUAL (CUMULATIVE)97.90%2380 kV Building Civil Work146Oct 25'14Apr 12'151.450%12.1%12.1%96.80%468910121210986697.82100.002.11PLANNED (CUMULATIVE)95.70%0.4830.7250.9671.0871.2081.4501.4501.2081.0870.9670.7250.72512.082ACTUAL (CUMULATIVE)94.60%3132 kV Building Civil Works143Oct 25'14Apr 8'151.080%9.0%9.0%93.50%488810111210988493.27100.003.11PLANNED (CUMULATIVE)92.40%0.3600.7200.7200.7200.9000.9901.0800.9000.8100.7200.7200.3609.002ACTUAL (CUMULATIVE)91.30%4Control Building Civil Works185Nov 29'14Jul 1'152.250%18.8%18.8%90.20%1666778108877666190.16100.004.11PLANNED (CUMULATIVE)89.10%0.1881.1251.1251.1251.3131.3131.5001.8751.5001.5001.3131.3131.1251.1251.1250.18818.752ACTUAL (CUMULATIVE)88.00%88.87513.8 kV Building Civil Works120Dec 28'14May 17'150.760%6.3%6.3%86.90%2810121414121097286.04100.005.11PLANNED (CUMULATIVE)85.80%0.1270.5070.6330.7600.8870.8870.7600.6330.5700.4430.1276.332ACTUAL (CUMULATIVE)84.70%6RC Cable Tannels (5m wide)277Jan 11'15Nov29'151.800%15.0%83.60%82.50%82.856.1RC Tannel From132kv To Control Building71Jan11'15Apr 2'151.39%81.40%61618221916380.61100.001PLANNED (CUMULATIVE)80.30%0.0830.2220.2500.3060.2640.2220.0421.392ACTUAL (CUMULATIVE)79.20%78.936.2RC Tannel From132kv To SGT Transformer - 171Jan 18'15Apr 9'151.39%78.10%16181918181177.27177.271PLANNED (CUMULATIVE)77.00%0.2220.2500.2640.2500.2500.1531.392ACTUAL (CUMULATIVE)75.90%75.246.3RC Tannel From132kv To SGT Transformer - 268Jan 20'15Apr 8'151.33%74.80%141820201810100.001PLANNED (CUMULATIVE)73.70%0.1860.2390.2660.2660.2390.1331.332ACTUAL (CUMULATIVE)72.60%73.126.4RC Tannel From132kv To SGT Transformer - 368Jan 20'15Apr 8'151.33%71.50%141820201810100.001PLANNED (CUMULATIVE)70.40%0.1860.2390.2660.2660.2390.1331.332ACTUAL (CUMULATIVE)69.30%70.236.5RC Tannel From 380kv To Control Building92Jan 18'15May 4'151.80%68.20%12131414151414467.31100.001PLANNED (CUMULATIVE)7.2%67.10%0.2160.2340.2520.2520.2700.2520.2520.0721.802ACTUAL (CUMULATIVE)66.00%6.6RC Tannel From 380kv To Boundary Wall East (GL 2-5)97Jul 9'15Oct29'151.90%64.90%64.05513141514141312100.001PLANNED (CUMULATIVE)63.80%0.0950.2470.2660.2850.2660.2660.2470.2281.902ACTUAL (CUMULATIVE)62.70%62.066.7RC Tannel From 380kv To Boundary Wall East (GL 19-23)92Jul 18'15Nov 1'151.80%61.60%121314161614132100.001PLANNED (CUMULATIVE)60.50%0.2160.2340.2520.2880.2880.2520.2340.0361.802ACTUAL (CUMULATIVE)59.40%59.796.8RC Tunnel From 380kv To Boundary Wall North109Jul 26'15Nov 29'152.13%58.30%41212141412121010100.001PLANNED (CUMULATIVE)57.20%0.0850.2560.2560.2980.2980.2560.2560.2130.2132.132ACTUAL (CUMULATIVE)56.10%56.846.9RC Tunnel From 132kv To Boundary Wall (East) Twin Tunnel99Jul 27'15Nov 18'151.94%55.00%4121313141413134100.001PLANNED (CUMULATIVE)53.90%0.0770.2320.2520.2520.2710.2710.2520.2520.0771.942ACTUAL (CUMULATIVE)52.80%53.607Transformer 500 MVA T-154Mar 23'15May 25'150.180%1.50%1.50%51.70%1224242416100.007.11PLANNED (CUMULATIVE)50.60%0.1800.3600.3600.3600.2401.502ACTUAL (CUMULATIVE)49.50%48.668Transformer 500 MVA T-268Mar 22'15Jun 9'150.180%1.50%1.50%48.40%101822201812100.008.11PLANNED (CUMULATIVE)47.30%0.1500.2700.3300.3000.2700.1801.502ACTUAL (CUMULATIVE)46.20%9Transformer 500 MVA T-351Mar22'15May 20'150.180%1.50%1.50%45.10%1225282510100.009.11PLANNED (CUMULATIVE)44.00%0.1800.3750.4200.3750.1501.502ACTUAL (CUMULATIVE)42.90%43.2310Transformer 67 MVA T-138May 13'15Jun 27'150.060%0.5%0.5%41.80%6363622100.0010.11PLANNED (CUMULATIVE)40.70%0.0300.1800.1800.1100.502ACTUAL (CUMULATIVE)39.60%11Transformer 67 MVA T-238May30'15Jul 12'150.060%0.5%0.5%38.50%37.483343528100.0011.11PLANNED (CUMULATIVE)37.40%0.0150.1700.1750.1400.502ACTUAL (CUMULATIVE)36.30%12Transformer 67 MVA T-339May 9'15Jun 23'150.060%0.5%0.5%35.20%10343620100.0012.11PLANNED (CUMULATIVE)34.10%0.0500.1700.1800.1000.502ACTUAL (CUMULATIVE)33.00%1347 MVA Reactor-121Jun 20'15Jul 14'150.060%0.5%0.5%31.90%31.844555100.0013.11PLANNED (CUMULATIVE)30.80%0.2250.2750.502ACTUAL (CUMULATIVE)29.70%1447 MVA Reactor-222Jul 6'15Jul 30'150.060%0.5%0.5%28.60%4060100.0014.11PLANNED (CUMULATIVE)27.50%0.2000.3000.502ACTUAL (CUMULATIVE)26.40%26.451547 MVA Reactor-321Jun16'15Jul 11'150.060%0.5%0.5%25.30%5842100.0015.11PLANNED (CUMULATIVE)24.20%0.2900.2100.502ACTUAL (CUMULATIVE)23.10%16Power Duct Banks67Jun 11'15Aug 29'150.360%3.0%3.0%22.00%20.9451820222015100.0016.11PLANNED (CUMULATIVE)20.90%0.1500.5400.6000.6600.6000.4503.002ACTUAL (CUMULATIVE)19.80%17Communication Duct Banks38Jun 17'15Aug 1'150.120%1.00%1.00%18.70%18.482435383118.4817.11PLANNED (CUMULATIVE)17.60%0.2400.3500.3800.0301.002ACTUAL (CUMULATIVE)16.50%16.7918Bust Duck foundations51Jun 20'15Aug 18'150.180%1.50%1.50%15.40%15.04162428266115.0418.11PLANNED (CUMULATIVE)14.30%0.2400.3600.4200.3900.0901.502ACTUAL (CUMULATIVE)13.20%13.4319Gantry foundations36Jun 22'15Aug 3'150.160%1.33%1.33%12.10%12.291638388112.2919.11PLANNED (CUMULATIVE)11.00%0.2130.5070.5070.1071.332ACTUAL (CUMULATIVE)9.90%10.5010.5120External LP,LM,SLP Foundation37Oct 6'15Nov 18'150.490%4.1%4.1%8.80%8.901638388108.9020.11PLANNED (CUMULATIVE)7.70%0.6531.5521.5520.3274.082ACTUAL (CUMULATIVE)6.60%6.608.496.817.8421Boundary Wall Reinforced concrete works120Aug 20'15Jan 7'160.670%5.6%5.6%5.50%810101012141210104100.0021.11PLANNED (CUMULATIVE)4.40%0.4470.5580.5580.5580.6700.7820.6700.5580.5580.2235.582ACTUAL (CUMULATIVE)3.30%5.2822Earthworks (external site works) & Other civil works30Dec 5;'15Jan 7'161.020%8.5%8.5%2.20%2.41304723100.0022.11PLANNED (CUMULATIVE)1.10%2.5503.9951.9558.502ACTUAL (CUMULATIVE)0.00%0.6312.0%100%107%PLAN CUMMULATIVE PERCENTAGE ACCOMPLISTMENTS 0.632.45.288.4910.513.4316.7920.9426.4531.8437.4843.2348.6653.6056.8459.7962.0664.0567.3170.2373.1275.2477.2778.9380.6182.8586.0488.8790.1693.2797.82100.0100.0ACTUAL CUMMULATIVE PERCENTAGE ACCOMPLISTMENTS 6.606.817.848.9010.5112.2915.0418.4826.9028.12VARIANCE1.3-1.7-2.7-4.5-6.3-8.7-11.4-13.4-10.6-10.3

PREPARED BY :FRANCISCO SUMCAD JRFAIZ UR REHMANCIVIL ENGINEERPROJECT ENGINEER(CIVIL)SAUDI ENGINEERING GROUP INTERNATIONALSAUDI ENGINEERING GROUP INTERNATIONAL

28.12%38.41%