week - know how...harry styles niall horan camille rowe camille rowe zayn malik cheryl cole louis...
TRANSCRIPT
-
Harry Styles
027 123 4567
29 Feb 2018
All FH utes on site
At Harrys ute
week
Homes Chapel Rd link (see attached)
N/A
Harry / Niall / Camille
in all FH utes on site
on all FH utes on site
Simon Cowell 027 123 4666
Camille Rowe No# 54678
10030
In Harry’s ute
City Med 44 Main Rd 09 1234567
7 March 18
14 March 18
N/A
N/A
N/A resource consent________
________N/A
N/A
TBC
N/A
F72/67 CCC NOC
44M060
Monday 29 Feb
initial team briefing - review Life Saving Rules - site risk review focusing on critical risks and controls
- site walkover - review consent - check plant and supplies - review close approach permit
- mark out job - complete digging & excavating permit requirements - start on pits A&B
- monitor controls
Tuesday 1st March
daily team briefing including reviewing yesterdays work - risk review and controls update
- check plant - complete pits A&B and do quality checks - continually monitor controls
Thursday 3rd March
same as above plus - complete pits C&D and do quality checks - close permits
Wednesday 2nd March
same as above plus - start pits C&D - continually monitor controls
Install four pits in four days
Pass all quality checks and note any variations (council to inspect prior to back fill)
Monitor consent conditions (full copy in the crew hut)
Control all discharges - wet cement - concrete dust and slurry - noise
No subcontractors expected - concrete mixed on site
stormwater
catch pits x4
drainage team work area for the week
29 Feb - 6 March
BBQ Thursday
4.00pm
it’s Nialls bir
thday
his shout!!
weather forec
ast is not gre
at
for the week
so please have
your wet wea
ther gear
and warm PP
E
Remember to stop if
something goes wrongor you don't feel safe
pit A
parkin
g
pit B
pit C
pit D
....
Install 4 stormwater catchpits (average one per day) as marked on attached plan - no live services
Basic plan for the week below - Make sure the site and equipment is secure each night
Note public holiday on Friday
cheers Harry
check out the new
Life Saving Rules
on the notice board
sample
-
Harry Styles
Niall Horan
Camille Rowe
Camille Rowe
Zayn Malik
Cheryl Cole
Louis Tomlinson
Gigi Hadid
yes yes yes yes yes
YES YES YES YES YES
y y y y y
yes yes yes yes yes
YES YES YES YES YES
yesyes yes yes yes
YES YES YES YES YES
y y y y y
Site setup - Managing traffic (public and site)
- Unloading and loading plant and equipment
- Site security (including after hours)
Activities - Lifting (manual handing)
- Handling wet cement
- Cutting concrete
- Working near underground services
- Digging and excavating (planned depth 750mm)
- small excavator and light truck operation
- small tools use
S
S
S
S
S
S
S
S
S
S
M 9
L 5
M 9
M 14
M 9
L 5
L 5
M 10
L 5
L 5
E
E
When cutting concrete use PPE as detailed
on HowTo guide. Full cover and hard hat is a site requirement
HJS
HJS
NH
LJP
Cammie
ZDM
CCC
LMT
GIH
29 Feb 2018
29 21Holiday
3 4
29 Feb 2018
29 Feb 2018
29th Feb
29/2/18
29/2/18
29/02/18
29/02/2018
Fulton Hogan drainage
Fulton Hogan EC
FH drainage
FH traffic
FH drainage
FHFulton Hogan
Fulton Hogan Gizzy
Install 4 stormwater catchpits (average one per day)
struck and injured by public or moving plant
personal injury - damage or loss of property effective barriers and fencing checked regularly - use spotters at busy times
struck or caught between - plant rollover exclusion zones - eye contact with operators - spotters
falling into hole - trench collapse - engulfment
electrocution or burns from hitting cables - bio risk from sewer
electrocution - cuts sprains strains - eyes hearing breathing damage
body strain, sprains, cuts and abrasions multi person lifts - used lifting equipment - wear gloves - change methods
edge barriers - follow digging / excavating permit requirements
follow digging / excavating permit requirements (and use your locator)
skin burns from lime / cement - water pollution
rollovers - struck by or caught between plant seatbelts on - spotters keep clear - plant checks - certified strops etc
avoid contact use correct PPE - change into dry gear when finished
plant checks - tag and tested - use correct PPE - trained operators
slurry run off - dust is breathed in - large cuts, eye, hearing damage bund runoff - suppress dust with water - follow concrete saw HowTo guide
monitor TMP - use spotters - keep separation from workers
sample
Page 1Page 2