week-5 - cesecbcesecb.weebly.com/uploads/5/3/2/2/53221971/sewer_design_5-8.pdf · acidity of ww is...
TRANSCRIPT
Sewer Appurtenances
i. Manholes, Drop manholes
ii. Inlets, Catch basins
iii. Oil and grease traps
iv. Flush tanks
v. Inverted siphons
vi. Pumping station
These are devices, other than sewers
Essential for the efficient operation of sewer systems.
These include;
i) Man-holes
a) Purpose of providing the manholes are as followings:
Are openings on sewer line either circular or rectangular in shape
Cleaning and Flushing
Inspection
House connections
Serve as ventilators for sewer by providing perforated man-hole covers
Facilitate laying of sewers in convenient length
Junction of two or more sewers
Change in direction i.e. At every change in direction
Change in size i.e. Where two pipes having different sizes are to be
connected
Change in slope i.e. pipes having different slopes are to be connected
b) Criteria for provision of manholes is given as below:
c) Distance or Spacing between manholes
Depends upon the size of sewer.
Recommended spacing of WASA are given below.
Sewer Size
(mm)
Spacing b/w Manholes
(m)
255 -350 100
460-760 120
>760 150
in Pakistan, generally spacing > 100 feet is not provided
Larger spacing can offer
difficulty in connection of houses
cleaning of sewer lines.
Drop man-hole
When lateral or sub-mains join in a
deeper sewer. (Diff > 2 feet)
When drop is < 2 feet adjustment
of grade is made instead of drop
manhole and sewage is dropped
in slopping channel without
splashing.
Upper Sewer is kept at reasonable
grade.
Incoming sewer is dropped outside
and joined in manhole chamber.
Assembly saved excavation .
The sewer line intersects the MH
wall, provision for cleaning
/rodding of branch can be kept
Construction of Manholes
Large cities Standardized Design and plans .
Have cast- iron frame and cover with a 500 to 600 mm (20 to 24 inches) clear opening.
The frame rest on corbelled brickwork (stone or timber projection from wall) to form an opening not less than 1 m (40 inches) and usually 1.5 m (3 – 5 feet) below the manhole.
The 1.25 m cylinder is continued downward until it reaches the sewer.
If the total depth < 4m (12 feet), the walls are made 200 mm (9”) thick.
An extra 200 mm thickness should be added for each addition 2 m (6 feet) depth.
Concrete walls (Cost of const. increases)
Usually bottom is made of concrete (1:2:4).
Slightly Slopped bottom from upper surface towards the open channel or, which are continuous of the sewer pipes.
I any case the channel depth should be nearly equal to pipe diameter to prevent sewage from spreading over the manhole.
Inlets
Inlets are the openings through which storm water is admitted
and conveyed to the storm sewer or combined sewer. The inlets
are located by the sides of pavement with maximum spacing of
30 m.
i. Curb Opening Inlet
iii) Catch Basins
Small settling chambers ( Dia = 60 - 90 cm & depth = 60 - 75 cm)
Constructed below the street inlets.
Interrupt the velocity of storm water entering through the inlets
Grit, sand, debris and other such matter settle in the basin,
sewers.
Inverted siphons
These are depressed portions of sewers,
Flow full under pressure more than the atmospheric
pressure as flow line being below the hydraulic grade line.
Provided when a sewer crosses a stream or deep cut or
road or railway line.
To clean the siphon pipe sluice valve is opened, thus
increasing the head causing flow.
The increased velocity washed away deposits of siphon
pipe into the sump, from where they are removed.
Pumping Station
Continuation of gravity flow is no longer feasible.
Basements of buildings are below the grade of the sewer
Any obstacle lies in the path of sewer
Receiving stream is higher than the sewer
Sewage is to be delivered to an above ground treatment plant
A sewage pumping station consists of following components
Components of Sewage Pumping Station
i) Screen
Function is to remove the floating matter to avoid damages to
pumping machinery etc.
ii) A wet well
Function of wet well is to receive the sewage
Important Consideration for Size of Wet Well
Prevention of too frequent starting and stopping of pumps.
Keep Size small to avoid septic action in the sewage.
Slopped bottom towards the pumps inlets to prevent accumulation of
solids.
Recommended D.T in the wet well should be less than 30 minutes.
Provide Ventilation of the wet well (Avoid excessive condensation &
odors).
Provide a MH or any other mean of entrance in wet well.
Used to install the pumps and switches etc.
Small stations are made entirely underground
In large Station, a house is built for the installation of these
things.
iii) Dry well
Size of dry well
Depends upon the size and number of pumps to be installed.
Pumps along with motor, valves, pipes and control penal
etc.
More than one pump are required to allow the flexibility
of operation
iv) Pumps
It is the time between the 2 successive start up of motor of pump.
Generally 10-20 minutes minimum.
The vol. of the wet well is designed on the basis of mini. cycle time.
Capacity of the Pump
Should be equal to the maximum flow of the sewage.
Gate valve
Gate valves are needed in the suction line and in the discharge line.
Should be all iron wedge type with rising stem to avoid corrosion.
Check valve
Should be placed between the pump and the gate valve in the
discharge pipe.
Should be an all-iron swing type with outside level and weight to
reduce slam.
Cycle Time
ON OFF ON OFF
Cycle Time
Cycle Time = Time of run (Time of emptying) + Time Off (Time of filling)
Or
t = V/(P-Q) + V/Q ------------(I)
where
V = Storage volume
P = Pump Discharge
Q = the influent flow
Differentiating Equation No.(I) W.r.t. Q and equating equal to zero
dt/dQ = V / (P-Q)2 – V / Q2 = 0
V / Q2 = V / (P-Q)2
Q2 = (P-Q)2
By Solving
Q = P/2
tmin = V / (P – P/2) + V/(P/2) = 4V / P
V = (tmin P) / 4
Volume of wet well can be found from above relation
Location of Pumping Station
Important consideration are as following:
i. Sewage pumping station should not be located in flood plain
ii. Sewage Pumping Station must be safe from fire hazard.
iii. Power and other fuel supply required to run the sewage
pumping station be available.
iv. Site must be large enough to cope the future expansion
requirement.
v. Site should be environmentally and socially accepted.
Example: Design a wet well of the flow is Qmin = 0.74 Cfs,
Qave = 1.547 Cfs and Qmax = 5.415
Sol
V = (tmin P) / 4
Let
tmin = 20 minutes (assumed 10 – 20 minutes
This time is minimum for Qmax = 5.425 Cfs. Hence
pumping rate , P = 5.415 Cfs
V = (20x60x5.415) / 4 = 1624.5 ft3
Now to check for “t” for Qmin = 0.74 Cfs
T = 1624.5 / (5.415-0.74) + 1624.5 / 0.74
= 42 minutes > 20 minutes
And for Qave. = 1.547 Cfs
t = 1624.5 / (5.415 – 1.547) + 1624.5 / 1.547)
= 24.5 minutes > 20 minutes
A wet well of operating volume of 1600 ft3 was designed for minimum cycle time
of a motor pump of 5 MGD (million gallons per day) capacity. Calculate the
inflow rate at which the cycle time will be twice the minimum cycle time (1 MGD
= 1.547 Cfs)
Example
Solution V = 1600 ft3
P = 5 MGD = 5 x 1.547
= 7.74 cfs
Inflow Rate = Q = ?
V = (tmin P) / 4
tmin = (4 x 1600) / 7.74 = 82.687 Sec
T = 13.78 min = 14 minutes
t = V/(P-Q) + V/Q
Here t = 2 tmin = 2 x 14 = 28 min
28 x 60 = 1600 / (7.74-Q) + 1600 / Q
= Q2 - 7.74Q + 7.74
Q = 6.56 cfs , 1.18 cfs
Sewage Characteristics
Wastewater Treatment
Consists of 99.9 % of the water and
Remaining as solids (Organic or inorganic ), Have very significant effect
Characteristics are determined by various analysis / tests.
Only few are used.
a) Physical Characteristics
Solids Determination
Total Solids
TS = Suspended Solids (SS), Settle-able Solids and the Diss. Solids
Determine by evaporating a known volume or weight of sewage
sample and weighing the residue.
Expressed in mg/l.
Settle-able Solids help in selection of treatment process design and
operation.
VS are ignitable at 550 0C and represent the amount of OM in WW.
Ignite the sample at about 550 0C.
Some of the solids will be evaporated.
VS = Original Weight - weight of residue (ash)
Non-VS / ash and are rough measure of the mineral content in WW.
Volatile Solids(VSS)
SS indicates the amount of sludge to be produced & Removed in PST.
Indicate the strength of sewage and amount of treatment required.
Also indicate the efficiency of wastewater treatment plant.
Both SS & Dissolved Solids determination require filtration of the
sample.
Settle-able Solids (SS)
Fresh sewage has a slightly ---------oily odour, which does not have
objectionable smell.
Gives objectionable smell when the sewage become septic releases
Hydrogen Sulphide (H2S).
Odour
Temp. slightly more than the temperature of the water supplied
Generally the temperature of the sewage ranges between 10 – 12 0C.
Effect disposal of sewage will increase temp. of final receiving water
body and thus release its oxygen - will effect the aquatic life.
Temperature
Fresh sewage has a grey colour
As sewage becomes septic the colour changes to
black.(Decomposition of OM)
Colour
b) Chemical Characteristics
Important for the control of processes of wastewater treatment plant
1. Inorganic chemicals.
2. Gases
3. Organic
i. pH.
ii. Acidity,
iii. Alkalinity
iv. Chlorides,
v. Nitrogen and
vi. Sulfur
vii. heavy metals
1. Inorganic Chemicals
i) pH
Indicates acidic or alkaline condition of water.
Expressed on a scale ranging from 0 to 14, Common logarithm of the reciprocal of the hydrogen ion concentration.
Plays an important role in WWT & Operation of treatment plant.
ii) Acidity
Acidity of WW is a measure of its capacity to neutralise bases.
Acidity in water may be caused by the presence of uncombined carbon dioxide, mineral acids and salts of strong acids and weak bases.
Acidity in WW may due to addition of industrial discharges
It is expressed as mg/l in terms of calcium carbonate.
iii) Alkalinity
Alkalinity is a measure of capacity WW to neutralise acids.
It is expressed as mg/l in terms of calcium carbonate. Forms include
(a) hydroxide alkalinity,
(b) carbonate alkalinity,
(c) hydroxide plus carbonate alkalinity,
(d) carbonate plus bicarbonate alkalinity, and
(e) bicarbonate alkalinity,
Alkalinity is an important parameter in evaluating the optimum
coagulant dosage.
Ordinary sewage is slightly alkaline.
Treatment of wastewater require alkaline conditions.
iv) Chlorides
Sources - Human and animal urine.
High concentrations indicate addition of industrial WW in the sewage.
v) Nitrogen
Nitrogen in wastewater may exist in five (05) forms
a) Ammonia Nitrogen (free ammonia due to decomposition of
organic matter.)
b) Ammonia Nitrogen (Albuminoid which is measure of
decomposable Proteins)
c) Organic Nitrogen
d) Nitrates
e) Nitrites
N & P (Nutrients) - essential to the growth of protista and plants.
Nitrogen data - evaluate biological treatability of WW.
To control algal growth in receiving waters,
Removal of N in wastewater prior to its discharge is desirable.
SO”4 + Organic Matter Bacteria S-2 + H2O + O2
S-2 + 2H H2S
Microorganisms reduced Sulfates under anaerobic condition to
sulfide.
Sulfides combine with hydrogen to form hydrogen sulfide (H2S).
Accumulated H2S can be oxidized biologically to H2SO4 which
causes sewer corrosion
vi) Sulfur
vii) Heavy Metals
Metals having specific gravity ___ time the water are called
heavy metals.
Major source - Industrial effluents
Heavy metals have adverse health effects on human and
animals.
Mainly include oxygen (O2) and Hydrogen Sulphide (H2S)
Oxygen in WW is necessary for
aerobic conditions i.e. growth of microorganism to avoid
adverse effects on aquatic life.
Hydrogen gas in higher concentrations is lethal for life.
Whereas, H2S gas in sewers results in “Crowning of
Sewers”
2. Gases
Coliforms
Pathogens
Worms
Bacterial counts in raw sewage may range from 500,000 / ml to
5,000,000 / ml.
Concerns in wastewater reuse of agricultural irrigation.
c) Bacteriological Characteristics
3. Organic Matter
Includes Carbohydrates, Proteins, and Fats.
Total quantity of OM is measured by
biochemical oxygen demand (BOD),
Chemical Oxygen Demand (COD) and
Total Organic Carbon (TOC).
The method generally employed are as followings:
Measurement of Organic Contents
1) Biochemical Oxygen Demand (BOD5)
2) Chemical Oxygen Demand (COD)
3) Total Organic Carbon
1) Biochemical Oxygen Demand (BOD5)
It is defined as the amount of oxygen required by the bacteria for
stabilizing the decomposable organic matter under aerobic condition.
Significance :
a) An indicator of organic pollution-ie.
(strength of the sewage & industrial wastewater)
a) Larger the BOD more oxygen demand of bacteria i.e. more the
depletion of O2 in receiving water body.
b) Used to design the WWTP
c) Determines It is used to determine the biological treatment efficiency
of WWTP.
d) Stream and effluent standards are generally based on BOD5 at 20 0C
Biological Oxidation of Organic Matter.
“Monomolecular Reaction”(i.e. First order Chemical Reaction).
A chemical reaction in which the rate of reaction is proportional
to the concentration of the reactants present”
i.e.
dL/dt = -KL
where
L = Concentration of Organic Mater
K = Reaction Rate Constant
Lt t
dL/dt = - K
dt
L0 to
Where
Lt = Organic Matter remaining at time “t” ie. Remaining BOD at time “t”
Lo = Original Concentration of Organic matter i.e. Ultimate BOD
ln Lt / Lo = -Kt
Lt = Lo e –kt ----------I
Let “y” be the concentration of OM (BOD) consumed upto time “t”
Then
y = Lo – Lt
Putting from (i)
y = Lo - Lo e –kt
y = Lo (1- e –kt) ie
BOD Consumed = Ultimate BOD ( 1- e –kt)
Also
t = Time in days
K = BOD reaction rate constant and
K = Its value for domestic sewage is 0.23 per day at 20 0C
However, value of reaction rate constant depends upon the temperature by
following relation
KT = K20 (10.047) T-20
Determination of BOD
Methods used are as followings:
1) Director Method
2) Dilution methods
1) Direct Method
i) Take sample
ii) Aerate the sample so that sufficient sample should be available
at time of incubation
iii) Measure Dissolved Oxygen (DO) at “ Zero day”
iv) Measure Dissolved Oxygen (DO) at 05 days.
v) The difference of these two readings is BOD of the sample and it
is reported in mg/l at 20 0C.
Used where BOD is less than 7 mg/l.
Used for very polluted sample.
Polluted samples – Large OM render sample O2 deficient in half
day. Dilution is done with specially prepared dilution water.
In toxic industrial samples, bacteria would have killed, therefore
seeding (addition of bacteria) 30 – 40 % of volatile solids.
BOD (mg/l) = [ ( DOsi – DO sf ) – (DOdi – DO df ) ]
Dilution Factor
Where
DOsi and DOsf = Initial and final Dissolved Oxygen (DO) in the diluted
sewage /sample
and
DOdi and DOdf = Initial and final Dissolved Oxygen (DO) in the dilution
water.
(This amount is to be subtracted to account for the
amount of Oxygen consumed by seeds)
( DOdi - DOdf ) = 0 (if dilution water used is not seeded)
2) Dilution Method
Example
If the 5 days BOD of the sewage is 154 mg/l, what would be
its 3 day BOD. Take K=0.1day-1
Sol.
T = 5 days
Lt = 154 mg/l
L = ?
K = 0.1 day-1
We have
Lt = L(1-e-Kt)
154 = L( 1-e-5x0.1)
L = 391 mg/l
Now for 3days BOD
Lt=3 = 391(1-e-3x0.1) = Lt=3 = 101 mg/l
2) Chemical Oxygen Demand (COD):
It is defined as the amount of oxygen required to oxidize the
organic matter chemically by using a strong oxidizing agent
(K2Cr2O7) in an acidic medium (H2SO4).
COD > BOD because materials like fats and lignin are also
oxidized with the help of chemicals, which are otherwise
biodegrade slowly.
No clear co-relation exist between BOD and COD
Co-relation is possible at a particular treatment plant.
Advantages :
Rapid test - Requires 2 hours as compared to BOD5
BOD/COD ratio indicates the extent of biodegradability of WW
BOD/COD correlation may help in rapid assessment of BOD.
COD of a sample is always more than BOD
Measurement of COD
i. Acid oxidation with Potassium dichromate.
ii. A measured amount of Potassium dichromate and acidified
sample is boiled for two hours.
iii. Allow to cool the sample.
iv. Titrate sample with ferrous ammonium sulphate to determine
remaining dichromate.
3) Total Organic Carbon:
i. Indicates the TOC present in a wastewater sample.
ii. Rapid and accurate test
iii. Correlates moderately well with BOD.
iv. Involve high cost of analysis.
Example
The 5-days BOD of the sewage is 276 mg/l. The ultimate BOD
of the sewage is reported to be 380 mg/l. At what rate the
sewage sample was oxidized
Sol.
T = 5 days
Lt = 276 mg/l
L = 380 mg/l
K = ?
We have
Lt = L(1-e-Kt)
276 = 380( 1-e-5K)
0.726 = ( 1-e-5K) = e-5K = 0.274
Log10 0.274 = -5K K = 0.112 day-1