week 4 – risk handling & monitoring. risk handling & monitoring proactively handle/monitor...

50
Week 4 – Risk Handling & Monitoring

Upload: leona-fowler

Post on 18-Jan-2016

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Week 4 –Risk Handling &

Monitoring

Page 2: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Risk Handling & Monitoring Proactively handle/monitor all Medium

& High risks Beneficial to handle/monitor Low risks

if Low risk rating was recently assigned Considerable development activity

remains Other systems/processes still in

development could affect this issue Final integration & test is not complete

Page 3: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Risk Handling Process that identifies, evaluates,

selects & implements options to set risk at an acceptable level

Goal: Identify appropriate management activities To reduce the likelihood of an event

occurring To reduce the severity of

consequences if event occurs

Page 4: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Risk Handling Actions

Reduce uncertainty as a result of handling actions

Handling actions address Specific events schedules Success criteria

Page 5: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Handling Actions are Proactive

Identify specifically Handling options for each risk event How to deal with the risks if realized When to act Who is responsible Identify cost & schedule impact of

handling actions

Page 6: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Risk Handling Options

Avoidance Assumption Control Transfer

Select based on level of acceptable risk

Page 7: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Selecting Handling Strategy

Evaluate each risk event for Feasibility of handling option Cost & schedule implications of option Potential impact to system technical

performance Consider secondary risk impacts

Page 8: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Inputs to Selecting Strategy Prioritized risk list Causes of each risk Requirements, contract provisions Probabilities of achieving cost &

schedule objectives Potential risk responses Trends in qualitative & quantitative

risk analysis results

Page 9: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Structured Risk Handling

Select risk handling strategy/option

THEN determine the implementation activity Tendency to select activity without

evaluating all options If high risk, may have back-up

handling strategies

Page 10: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Risk Handling Tools

Program risk handling audit Periodic program risk reviews Earned value analysis Technical performance

measurement Additional risk handling planning

Page 11: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Risk Avoidance Eliminates sources of high risk, replaces

with lower risk alternatives Approach

Apply early in program Change concept, specifications, practices Re-evaluate operational requirements

Remove if no strong basis Cost-effectiveness trade-studies

Cost As an Independent Variable (CAIV)

Page 12: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Risk Avoidance Requires understanding of priorities

& constraints May be appropriate to:

Reduce scope to avoid high-risk activities

Add resources or time Use familiar approach vs. untested Avoid a sub with insufficient experience Choose spiral development approach

Page 13: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Risk Avoidance Pitfalls

May discourage life cycle risk management

Using to reduce requirements should be a last resort

Page 14: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Risk Assumption

Acknowledge existence of a specific risk & consciously accept it Risks may be inherent Residual risks - result from other

control actions Best suited for low level risks

Page 15: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Successful Risk Assumption

Contingency plans Identify resources & actions for

overcoming if event happens Have administrative plans/contracts

ready to activate Set aside schedule & cost reserve

If not, may have to lower capability or cancel effort if cannot meet objectives

Page 16: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Risk Assumption Pitfalls Are declaring worst case outcome

as being acceptable level of capability

Difficult to set aside reserve on DoD programs

Requires well-planned monitoring – cannot ignore

Quick reporting of risk event and implementation of actions

Page 17: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Risk Control

Seeks to reduce or mitigate risk Monitors/manages risk

Reduce probability of occurrence Reduce severity of outcome

Most commonly used in defense programs

Page 18: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Common Control Mechanisms

Multiple development efforts Alternative designs Trade studies Prototyping Incremental development Technology maturation Reviews, walk-throughs, inspections

Page 19: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

More Control Mechanisms

Design of experiments Open systems Mock-ups Modeling & simulation Demonstration/test events Process proofing

Page 20: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Successful Risk Control

Conduct regular risk reviews Formal agenda Review risks, ratings, prioritization

Audit use of risk control mechanisms

Verify risks are continuously assessed

Page 21: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Risk Control Pitfalls

Control steps require commitment of resources & time

Strike balance between resources req’d and benefit of reduced probability or severity

May increase program costs Potential for secondary effects

Page 22: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Risk Transfer

Reallocation of risk from one part of the system to another or between program entities

System level requirements are still met

Cannot transfer unless recipient has ability to control & manage the risk

Page 23: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Risk Transfer Consideratons

Early in program Net result should be overall reduction

in risk, not just reassignment Valid transfer mechanism – not vengeance Seamless assumption of delegated

activity Not beyond recipient’s ability to handle

Page 24: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Risk Transfer Techniques

In design Modularity Functional partitioning From hardware to software – e.g.,

timing

Page 25: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Risk Transfer Techniques

Between customer & contractor Technology Processing Cost control

warranties performance incentives FFP contracts

Page 26: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Successful Risk Transfer Contractors more suited to accept

risks for Technology Processes

Government better able to affect Funding Schedule External impacts on program

requirements

Page 27: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Risk Transfer Pitfalls

New risk owner lacks ability to handle the risk Either to manage or absorb in

processes Combined risk exposure is not

reduced

Page 28: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Example: Handling Concurrency

What strategies are being used? Insure Adequate Test Resources Are

Available Rapid Corrective Action Process Established Effective Transition to Production Process

Defined Phase Production to Allow for Early Testing Use Modular Designs When Retrofits Are

Expected

Page 29: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Risk Handling Plan Output of risk handling phase Documents the risk actions to be taken

Task descriptions of handling actions Resources required Proposed schedule & relationship to

program milestones Cost impact

Documents ground rules & assumptions

Page 30: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Handling Plan Schedule

Page 31: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Risk Handling Exercise Identify the process steps that should be

taken to develop handling actions for the following to Peace Whey risk events. Select a different handling action for each event.

You have __ minutes for this exercise. Be prepared to present your results.

Tracking id

Criti- cality

Proba- bility

Conse- quence Title Description

R01 H 60% Critical Delay in AJS certification

Weather and test site availablity issues could cause a delay in the Airborne Jamming System being flight certified, delaying further system testing

R02 M 90% Serious Follow-on proposal effort initiated

Key Peace Whey engineers and managers are subject matter experts whose imput is required for successful follow-on proposal effort.

R03 L 40% Minor Increase overhead rates

Loss of business base may increase overhead rates charged against the program in the accounting system causing a reduction in program reserve.

Page 32: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Trade Studies Support functional analyses Allocation of performance requirements Identification of design constraints May be formal or informal

Document formal decisions – e.g., at milestones

Basis for informal engineering choices Cost-effectiveness is a special case

trade study

Page 33: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

TS Basic Principles

Criteria are established as the basis for the decision Must have agreed upon approach for

measuring against criteria – why? Results must be easily

communicated to decision-makers

Page 34: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Basic TS Process

Similar to risk management process

Page 35: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Utility Curves Normalize decision factors for comparison Relative factor value as increases across range Shows constant, continuous or stepped values

Page 36: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Decision Matrix Relative values establish weighting

factors for each decision factor

Page 37: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Sensitivity Analysis

Use to determine how solutions change as utility or weighting change Evaluation criteria should be sensitive to

major drivers Involve entire team & customer in

definition process Utility curves & decision matrices are

models – verify, validate, accredit

Page 38: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Trade Study Example Define Study Parameters:

Define decision criteria from requirements, parametric experience, …

Define ranking weights to be used for criteria, ex.0 (not imp.) to 3 (most imp.)

Define range for utility scores, ex. 0 to 10, with 5=exactly meets

Qualitatively or quantitatively evaluate each alternative, assign utility scores

utility

0

1

2

3

4

5

3.85 3.9 3.95 4 4.05 4.1 4.15

weight

uti

lity

+/-

fro

m 'm

eets

'

Page 39: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

TS Example

Page 40: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Risk Monitoring Systematically track & evaluate

performance of handling plan Monitor predictors for risk events Monitor status of identified risks Track handling actions Compare predicted to achieved

results Disseminate information Update plan as required

Page 41: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Successful Risk Monitoring Key – Selection of most effective metrics

True state of risk events Status of handling actions

On-going, proactive process Identify new risks & handling options Retire risks as project matures

Keep monitoring progress visible Timely reporting of results An agenda item at management reviews Relate to cost, schedule & performance

objectives

Page 42: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Possible Activities Resulting from Monitoring

Documenting process work-arounds Activating contingency plans Requests for change in program

scope Reassessing risks due to change in

Probability Consequence Program assumptions

Page 43: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Risk Monitoring Outputs Program metrics Technical reports Earned value reports Risk tracking watch list Schedule performance report Critical risk process reports

Establish a reporting frequency

Page 44: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Monitoring

May define color codes for plan tasks

Color Interpretation

Anticipated Probability of

Failure

Blue Task is complete 0%

Green Task is on schedule 10%

YellowTask may not be completed on schedule 50%

RedTask considered non-executable 100%

Page 45: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Monitoring

Status of technical performance measures

Page 46: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Monitoring

Status of earned value cost metrics

Page 47: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Successful Monitoring Attention to risks associated with

program schedule Monitor low risks for changes to status Be aware of trends, continuously

evaluate metrics Indicator system must be accurate,

timely & relevant Recognize project parameters &

assumptions can change

Page 48: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Monitoring Pitfalls Using as a problem solving

technique Ignoring low risks Going on ‘auto-pilot’ Revisit metrics selection for

accuracy, timeliness & relevance Focus on internal environment to

exclusion of external & interface concerns

Page 49: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Risk Monitoring Exercise Identify the process steps that should be

taken to monitor the following to Peace Whey risk events. Relate to the handling actions identified earlier.

You have __ minutes for this exercise. Be prepared to present your results.

Tracking id

Criti- cality

Proba- bility

Conse- quence Title Description

R01 H 60% Critical Delay in AJS certification

Weather and test site availablity issues could cause a delay in the Airborne Jamming System being flight certified, delaying further system testing

R02 M 90% Serious Follow-on proposal effort initiated

Key Peace Whey engineers and managers are subject matter experts whose imput is required for successful follow-on proposal effort.

R03 L 40% Minor Increase overhead rates

Loss of business base may increase overhead rates charged against the program in the accounting system causing a reduction in program reserve.

Page 50: Week 4 – Risk Handling & Monitoring. Risk Handling & Monitoring Proactively handle/monitor all Medium & High risks Beneficial to handle/monitor Low risks

Next Time: Special Topics

Read Risk Management Guide, sections 5.8, 5.9

Special Topics Software Risk Management Risk Management Tools Commercial vs. DoD Perspective

Final exam, turn in Part II of project