web-based class project on rock mechanics report prepared as part of course cee 544: rock mechanics...
TRANSCRIPT
Web-based Class Projecton Rock Mechanics
Report prepared as part of course CEE 544: Rock Mechanics
Winter 2015 SemesterInstructor: Professor Dimitrios Zekkos
Department of Civil and Environmental Engineering University of Michigan
Polyurethane Resin Grouting for Stabilization
Prepared by:
Clark Green
With the Support of:
Contents 1.0 Introduction
2.0 Types of Polyurethanes
3.0 Effects on Fractured Rock Masses
4.0 Implementation and Design Considerations
5.0 Advantages and Disadvantages
6.0 Case Study◦ West Virginia Roof and Pillar Coal Mine ◦ Poudre Canyon Tunnel
7.0 Conclusions
1.0 Introduction Polyurethane Resin = PUR
◦ Subset of the broader “polyurethane” chemical grout category
Purpose of PUR grouting◦ To consolidate and strengthen a fractured rock mass by injection grouting◦ “Rock Gluing”
Applications◦ Coal mine roof and/or longwall stabilization (1960’s – present)
◦ Standard method for stabilization in Germany since 1970’s
◦ Rock slope stabilization against rock falls (since the 2000’s)◦ Recently researched by FHWA
2.0 Types of Polyurethanes Single Stage Polyurethane (PU)
◦ One component polyurethane chemical, one component water◦ HYDROPHILIC – REQUIRES WATER FOR REACTION◦ Expansive reaction due to production of CO2 foam◦ Sealant/Water Cutoff
Polyurethane Resin (PUR)◦ Two components polyurethane chemical◦ HYDROPHOBIC – DOES NOT REQUIRE WATER FOR REACTION◦ Some PUR may react with water by design◦ Strength/Stabilization
Epoxy◦ Not used for large-scale grouting
Expansion potential of polyurethane (Joyce 1992)
2.0 Types of PolyurethanesProperty Polyurethane (PU) Polyurethane Resin (PUR) EpoxyMixing Components One Two Two
Reaction with Water Hydrophilic (required) Hydrophobic Hydrophobic
Density Low to Medium 3 - 50 pcf
Medium to High20 – 70 pcf
Low to High5 – 60 pcf
Compressive/Tensile Strength
Low10 – 500 psi
Low to High15 – 20,000 psi
Medium to High5,000 to 20,000 psi
Viscosity Low to Medium Low to High Very Low to High
Relative Cost Low Mid to High High
Adapted from (Arndt et al 2008)
3.0 Effects on Fractured Rock Masses
Penetrates fractures◦ As small as 0.5 mm apertures
Chemically binds to rock◦ Consolidation of rock mass◦ Increased strength of rock mass
Creates impermeable barrier◦ Grout curtains aid in design
injection sequence
Creates water cutoff◦ Provided all void spaces are filled
Rock – Dark colored materialPUR – Light colored material
(Molinda 2004)
PUR seams infiltratingfracture pattern
4.0 Implementation General PUR grouting procedure
◦ Drill grout borehole◦ Sequence and spacing of boreholes to be discussed later
◦ Insert grouting assembly into borehole◦ Pressure transfer from grout tube into borehole◦ Target zones along borehole for improvement
◦ Mix components◦ Perform mixing as close as possible to the injection site
◦ Inject grout through fractures along borehole◦ Stop injection when PUR is seen visibly extruding from
surface of rock or spike in back pressure is observedExample grout pump. Small and easy to mobilize (Bodi 2012)
4.0 Design Considerations Rock mass characterization
◦ Target zones for improvement◦ Estimate void space◦ Estimate amount of PUR required◦ Estimate moisture content for hydrophilic PUR
Injection sequence◦ Determine borehole dimensions and spacing◦ Determine location of grout curtains/barriers◦ Drill and fill one at a time
Monitor injection pressures
Be aware of temperature effects◦ Viscosity and set time of PUR
Handling PUR components◦ Some PUR components may be skin and eye
irritants
Cured PUR resin is chemically and environmentally inert
5.0 Advantages and DisadvantagesADVANTAGES
Low viscosity◦ Penetrates small fractures
High control resolution◦ Viscosity◦ Expansion properties◦ Set time (seconds)◦ Strength
Strength◦ 3 – 4 times the strength of cementitious grouts
Easily mobilized and environmentally inert
Aesthetics
DISADVANTAGES
Infiltration is unknown◦ Invasive techniques required for verification
Hydrofracturing◦ Too much injection pressure may cause rock falls
High Cost
6.0 Case StudiesWEST VIRGINIA COAL MINE
Experiencing multiple roof falls per year
Moisture sensitive shale roof
Roof supports restricting passage through mine
PUR injection chosen for stabilization of roof at intersections
POUDRE CANYON TUNNEL
75 ft long tunnel through vertically foliate gneiss
Western portal prone to rock falls
Previously stabilized with non-tensioned rock dowels
PUR chosen to demonstrate effectiveness of technique
FHWA demonstration project performed by the Colorado Department of Transportation
West Virginia Coal Mine
Standing supports not doing so well (Molinda 2008) Plan view of roof falls and planned injection sites (Molinda 2008)
West Virginia Coal Mine Plan view
◦ 11 boreholes per intersection, staggered◦ 10 ft center-to-center spacing
Cross section◦ Target zone between 2 – 6 ft above roof chosen
to create grout “beam” for stabilization◦ Initial injection performed at perimeter angled
45 degrees to create grout curtain◦ Sequential injection of targeted zone
Injection design (Molinda 2004) Stabilization design (Molinda 2008)
West Virginia Coal Mine 100% filling of voids
◦ 9 of 16 boreholes
Partial filling of voids◦ 4 of 16 boreholes◦ 43% to 93%
No filling of voids◦ 3 of 16 boreholes◦ 0%, 1%, and 9% observed
The boreholes showing no filling of voids were supported with standing supports.
◦ Verification of infiltration extremely important
Verification of PUR infiltration (Molinda 2008)
6.0 Case StudiesWEST VIRGINIA COAL MINE
Experiencing multiple roof falls per year
Moisture sensitive shale roof
Roof supports restricting passage through mine
PUR injection chosen for stabilization of roof at intersections
POUDRE CANYON TUNNEL
75 ft long tunnel through vertically foliate gneiss
Western portal prone to rockfalls
Previously stabilized with non-tensioned rock dowels
PUR chosen to demonstrate effectiveness of technique
FHWA demonstration project performed by the Colorado Department of Transportation
Poudre Canyon Tunnel Injection sequence
◦ Bottom of rock face to top (generally)
Borehole geometry◦ 1.5 in diameter◦ 10 – 12 ft depth
Pumping sequence◦ Initial injection to allow gravity flow downward through
fractures◦ Second injection to force resin outward and upward
Pumping halted when PUR was seen extruding above current borehole
Pumping pressures kept below 50 psi
No intrusive verification performedPoudre Canyon Tunnel with injection sequence overlay (Arndt et al 2008)
FHWA Recommendations Context Sensitive Rock Slope Design Solutions Manual (2011)
◦ Apply PUR to fracture apertures greater than 2 mm◦ Space injection boreholes 8 – 16 ft apart
◦ PUR may flow 10 – 15 ft away from borehole through fracture pattern
◦ Boreholes should intersect major discontinuities at 90 degree angles◦ Inject PUR from bottom to top using staged pumping◦ Keep pressures below 250 psi
PUR is recommended by the FHWA to be used only as a supplemental method of stabilization
7.0 Conclusions PUR consolidates and strengthens rock masses
◦ Penetrates and fills fractures as small as 0.5 mm in aperture
Control of important engineering properties◦ Viscosity◦ Set time◦ Strength◦ Expansion properties
Important design considerations◦ Rock mass characterization◦ Borehole and injection sequencing◦ Verification
Proven in the coal mine and transportation industries
References Arndt, B., DeMarco, M., and Andrew, R. (2008). Polyurethane Resin (PUR) Injection for Rock Mass Stabilization, Federal Highway Administration Central Federal Lands Highway Division, Lakewood, CO.
Bodi, J., Bodi, Z., Scucka, J., and Martinec, P. (2012). “Chapter 14: Polyurethane Grouting Technologies, Polyurethane” InTech, <http://www.intechopen.com/books/polyurethane/ polyurethane-grouting-technologies> (Mar. 3, 2015)
Joyce, J. T. (1992). “Polyurethane Grouts.” Concrete Construction, The Aberdeen Group, <http://www.concreteconstruction.net/concrete-articles/polyurethane-grouts.aspx>
Molinda, G. (2004). “Evaluation of Polyurethane Injection for Beltway Roof Stabilization in a West Virginia Coal Mine.” Proceedings of the 23rd International Conference on Ground Control in Mining, West Virginia University, Morgantown, WV, 190-196.
Molinda, G. (2008). “Reinforcing Coal Mine Roof with Polyurethane Injection: 4 Case Studies.” J. Geotech. Geol. Eng., 26(5), 553-566.
More Information
More detailed technical information on this project can be found at:
http://www.geoengineer.org/education/web-based-class-projects/rock-mechanics