wccusd bond program project status report citizen bond oversight committee measure m, d, j, d-2010...
TRANSCRIPT
WCCUSD Bond Program Project Status Report
Citizen Bond Oversight CommitteeMeasure M, D, J, D-2010 & E-2012
Coronado Elementary School:Replacement Campus
Coronado Elementary School: Replacement Campus
Construction Contract Value:
$26,974,910
Percent Complete:
15%
Change Orders: $0 (0%)
Notice to Proceed:
1/6/14
Completion Date:
5/31/15
El Cerrito High School: Stadium
El Cerrito High School: Stadium
Construction Contract Value:
$13,438,000
Percent Complete:
14%
Change Orders: $0 (0%)
Notice to Proceed:
1/27/14
Completion Date:
9/27/15
Gompers / LPS: Replacement Campus
Gompers / LPS: Replacement Campus
Construction Contract Value:
$53,887,350
Percent Complete:
55%
Change Orders:
$673,2971.23%
Notice to Proceed: 8/20/12
Completion Date:
8/15/15
Helms Middle School: Sports Field
Helms Middle School: Sports Field
Construction Contract Value:
$5,951,048
Percent Complete:
99%
Change Orders:
$212,694 (3.45%)
Notice to Proceed:1/7/13
Completion Date:
4/21/14
Kennedy High School: Science Wing Renovation
Kennedy High School: Science Wing Renovation
Construction Contract Value:
$4,136,303
Percent Complete:
83%
Change Orders: $81,893 (1.94%)
Notice to Proceed: 9/16/13
Completion Date:
9/16/14
Kennedy High School: Richmond Swim Center
Kennedy High School: Richmond Swim Center
Construction Contract Value:
7,642,921
Percent Complete:
5%
Change Orders: $0 (0%)
Notice to Proceed: 4/28/14
Completion Date:
4/28/15
Montalvin Elementary School: New Classroom Building
Montalvin Elementary School: New Classroom Building
Construction Contract Value:
$2,843,000
Percent Complete:
15%
Change Orders: $0 (0%)
Notice to Proceed: 2/3/14
Completion Date:
10/31/14
Ohlone Elementary School: West Campus Replacement
Ohlone Elementary School: West Campus Replacement
Construction Contract Value:
$16,961,000
Percent Complete:
90%
Change Orders:
$1,645,876 (8.85%)
Notice to Proceed: 8/1/11
Completion Date:
9/25/14
Pinole Valley High School: Detention Basin, Utilities, & Paving
Pinole Valley High School: Detention Basin, Utilities, & Paving
Construction Contract Value:
$2,126,744
Percent Complete:
90%
Change Orders: $0 (0%)
Notice to Proceed: 11/12/13
Completion Date:
3/22/14
Pinole Valley High School: Interim Housing Campus
Pinole Valley High School: Interim Housing
Construction Contract Value:
$5,530,000
Percent Complete:
10%
Change Orders: $0 (0%)
Notice to Proceed: 4/7/14
Completion Date:
8/15/14
Portola Middle School: Campus Replacement
Portola Middle School: Campus Replacement
Construction Contract Value:
$42,762,406
Percent Complete:
34%
Change Orders:
$88,792 (.20%)
Notice to Proceed:5/13/13
Completion Date:
12/29/15