WBS-Construction of House cont. Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al- Araki, sept. 2013 1 Earlier topics: [WBS], [Dictionary of WBS] and [OBS] Responsibility Assignment Matrix (RAM) Technical Approach, Scope of Work, Specifications, Risk Management and Resource Allocation based on WBS The 100% Rule

Upload: margaret-barnett

Post on 14-Jan-2016

217 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: WBS-Construction of House cont. Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept. 2013 1 Earlier

WBS-Construction of House cont.Lecture by Junaid Arshad Department of

Engineering ManagementAbridged and adapted by A. M. Al-Araki,

sept. 2013

1

•Earlier topics: [WBS], [Dictionary of WBS] and [OBS]

•Responsibility Assignment Matrix (RAM)

•Technical Approach, Scope of Work, Specifications, Risk•Management and Resource Allocation based on WBS

•The 100% Rule

Page 2: WBS-Construction of House cont. Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept. 2013 1 Earlier

Responsibility Assignment Matrix (RAM) Merging WBS and OBS = RAM or Responsibility Assignment Matrix, the lowest level of both. This identifies specific responsibility for specific tasks.

-- -- -- -- --

--

--

--

--

--

WBS: Lowest level

OB

S:

Low

est

level

2

Page 3: WBS-Construction of House cont. Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept. 2013 1 Earlier

The lowest level of the WBS appears across the top The lowest level of the OBS appears on the vertical axis

Hours mentioned in the graphic below can be replaced by the intersection of the WBS task and OBS personnel. The cross-section between the task, framing the exterior walls, and the responsible person, Mr. Sites shows that Mr. Sites has 300 hours to frame the exterior walls, 250 hours to frame the interior walls and 175 hours to install the roofing trusses.

Performing Dept. Manager

Pour Foundation

1.1.1.1Install Patio

1.1.1.2

Pour Stairway 1.1.1.3

Frame Exterior Walls

1.1.2.1

Frame Interior Walls

1.1.2.2

Install Roofing Trusse 1.1.2.3

Install Water Lines

1.1.3.1

Install Gas Lines

1.1.3.2

Install B/K Fixtures 1.1.3.3

CONCRETE DEPT 6010 Manning 200 125 85MASONRY DEPT 6020 Greams 50TEST DEPT 6030 Neumann 20 10 5CARPENTRY DEPT 5010 Sites 300 250 175ROOFING DEPT 5020 Taylor 100DRYWALL DEPT 5030 Smith 275WIRING DEPT 4010 JohnsonHOOKUP/TIE-IN DEPT 4020 OttisWATER/SEWER DEPT 3010 Wells 100 15GAS DEPT 3020 Oriely 125 25

1.1.3PLUMBINGCONCRETE

1.1.1FRAMING

1.1.2

3

Page 4: WBS-Construction of House cont. Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept. 2013 1 Earlier

Technical Approach and WBS

4

It is recommended, before attempting to develop the WBS, to develop the

technical approach identifying the major tasks that will be performed and how

(level of effort, quality) these tasks will be performed.

Scope of Work Based on WBS

Specifications based on WBS

WBS and Risk Management

Page 5: WBS-Construction of House cont. Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept. 2013 1 Earlier

Scope of Work Based on WBSThe scope of work describes or represents the details (in terms of level of effort, quality of performance, resources supplied, materials used, etc.) of the work that is graphically displayed in WBS. The WBS serves to outline the scope of work. Using the WBS as an outline, the names of major tasks can become text headings for the various sections of the scope of work. In a similar fashion the subtasks names can become text subheadings and so on.

Specifications based on WBSRegardless of how all the specifications are presented, an effort must be made to identify them by considering the WBS at the work package level.

WBS and Risk ManagementThe WBS allows the project planning team to consider potential risk events at the work package level. Once possible risks have been identified, methods of managing those risks can be considered.

5

Page 6: WBS-Construction of House cont. Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept. 2013 1 Earlier

The 100% Rule

The 100% Rule states that the WBS includes 100% of the work defined by the project scope and captures all deliverables i.e. internal, external, interim; in terms of the work to be completed, including project management.

The WBS should not include any work that falls outside the actual scope of the project, that is, it cannot include more than 100% of the work.

6

Page 7: WBS-Construction of House cont. Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept. 2013 1 Earlier

7

Example - The 100% Rule