watson trail park playground improvements gds …

46
WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12 SECTION 02200 - EARTHWORK 1 SECTION 02200 EARTHWORK PART 1 - GENERAL: RELATED DOCUMENTS: Drawings and general provisions of Contract, including General and Supplementary Conditions and Division I Specification Sections, apply to this Sections. SUMMARY: This Section includes the following: Excavation and preparing of subgrade for footings, walks and pavements. DEFINITIONS Excavation consists of removal of material encountered to subgrade elevations indicated and subsequent disposal of materials removed. Subgrade: The undisturbed earth or the compacted soil layer immediately below granular subbase, drainage fill, or topsoil materials. If applicable, Owner will provide a third-party soil and compaction test services. QUALITY ASSURANCE Perform excavation work in compliance with applicable requirements of authorities having jurisdiction. Owner will employ and pay for a qualified independent geotechnical testing and inspection laboratory to perform compaction/soil testing and inspection services during earthwork operations. PROJECT CONDITIONS Locate existing underground utilities in areas of excavation work. If utilities are indicated to remain in place, provide adequate means of support and protection during earthwork operations. Protection of Persons and Property: Barricade open excavations occurring as part of this work and post with warning lights. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earthwork operations. PART 2 - PRODUCTS SOIL MATERIALS A. Subbase Material: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, crushed slag, and natural or crushed sand. B. Backfill and Fill Materials: Satisfactory soil materials free of clay, rock, or gravel larger than two

Upload: others

Post on 27-Dec-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02200 - EARTHWORK 1

SECTION 02200

EARTHWORK

PART 1 - GENERAL:

RELATED DOCUMENTS:

Drawings and general provisions of Contract, including General and Supplementary Conditions and

Division I Specification Sections, apply to this Sections.

SUMMARY:

This Section includes the following:

• Excavation and preparing of subgrade for footings, walks and pavements.

DEFINITIONS

Excavation consists of removal of material encountered to subgrade elevations indicated and subsequent

disposal of materials removed.

Subgrade: The undisturbed earth or the compacted soil layer immediately below granular subbase,

drainage fill, or topsoil materials.

If applicable, Owner will provide a third-party soil and compaction test services.

QUALITY ASSURANCE

Perform excavation work in compliance with applicable requirements of authorities having jurisdiction.

Owner will employ and pay for a qualified independent geotechnical testing and inspection laboratory to

perform compaction/soil testing and inspection services during earthwork operations.

PROJECT CONDITIONS

Locate existing underground utilities in areas of excavation work. If utilities are indicated to remain in

place, provide adequate means of support and protection during earthwork operations.

Protection of Persons and Property: Barricade open excavations occurring as part of this work and post

with warning lights.

Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement,

lateral movement, undermining, washout, and other hazards created by earthwork operations.

PART 2 - PRODUCTS

SOIL MATERIALS

A. Subbase Material: Naturally or artificially graded mixture of natural or crushed gravel, crushed

stone, crushed slag, and natural or crushed sand.

B. Backfill and Fill Materials: Satisfactory soil materials free of clay, rock, or gravel larger than two

Page 2: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02200 - EARTHWORK 2

inches in any dimension, debris, waste, frozen materials, vegetation, and other deleterious

matters.

C. Topsoil: Topsoil to be clean friable and of organic quality free of debris available on-site.

PART 3 - EXECUTION

EXCAVATION

A. Excavation is unclassified and includes excavation to subgrade elevations as indicated,

regardless of character of materials and obstruction encountered.

STABILITY OF EXCAVATIONS

A. Comply with local codes, ordinances, and requirements of agencies having jurisdiction.

B. Slope sides of excavations to comply with local codes, ordinances, and requirements of agencies

having jurisdiction. Shore and brace where sloping is not possible because of space restrictions

or stability of material excavated. Maintain sides and slopes of excavations in safe condition until

completion of backfilling.

DEWATERING

A. Prevent surface water and subsurface or ground water from flowing into excavations and flooding

project site and surrounding areas.

STORAGE OF EXCAVATED MATERIALS

A. Dispose of excess excavated soil material and materials not acceptable for use as backfill or fill

off the site.

EXCAVATION FOR PAVEMENTS

A. Cut surface under pavements to comply with cross sections, elevations, and grades as indicated.

COLD WEATHER PROTECTION

A. Protect excavation bottoms against freezing where atmospheric temperature is less than 35

degrees F.

BACKFILL AND FILL

A. Place soil material in layers to required subgrade elevations and to facilitate forms.

B. Backfill excavations as promptly as work permits, but not until completion of the following:

C. Acceptance of construction below finish grade.

D. Removal of trash and debris from excavation and dispose of off the site.

Page 3: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02200 - EARTHWORK 3

PLACEMENT AND COMPACTION

A. Ground Surface Preparation: Remove vegetation, debris, unsatisfactory soil materials,

obstructions, and deleterious materials from the ground surface prior to placement of fills. Plow,

strip, or break up sloped surfaces steeper than one vertical to four horizontal so that fill material

will bond with existing surface.

B. Place backfill and fill materials in layers not more than eight inches in loose depth for material

compacted by heavy compaction equipment, and not more than four inches in loose depth for

material compacted by hand-operated tampers.

C. If high plastic clays are encountered during excavation, these shall not be placed within any

subgrade for structures and slabs.

D. Percentage of Maximum Density Requirements: Compact soil to not less than the following

percentages, in accordance with ASTM D-1557:

E. Under structures, building slabs and steps, and pavements - 90 percent maximum density and

optimum moisture content.

F. Under walkways - 90 percent maximum density and optimum moisture content.

G. Rock base course for pavements and slabs - 95 percent maximum density and optimum moisture

content.

H. Moisture Control: Remove and replace, or scarify and air dry, soil material that is too wet to

permit compaction to specified density.

I. Stockpile or spread soil material that has been removed because it is too wet to permit

compaction. Assist drying by discing, harrowing, or pulverizing until moisture content is reduced

to a satisfactory value.

J. Grade areas adjacent to building lines to drain away from structures and to prevent ponding.

Finish surfaces with topsoil free from irregular changes.

K. After grading, compact subgrade surfaces to the depth and indicated percentage of maximum or

relative density for each area classification.

FIELD QUALITY CONTROL

A. Allow Third-Party testing service to inspect and approve work as deemed necessary as per the

direction of the Owner.

B. As deemed necessary, Third-Party testing service will perform at least three field density tests for

subgrade of paved and fill layered areas.

EROSION CONTROL

A. Provide erosion control methods in accordance with requirements of authorities having

jurisdiction.

B. Inspection of the erosion control devices shall be done daily with accumulation of silt and deposits

removed promptly.

Page 4: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02200 - EARTHWORK 4

MAINTENANCE

A. Protect newly graded areas from traffic and erosion. Keep free of trash and debris.

B. Repair and re-establish grades in settled, eroded, and rutted areas.

C. Scarify surface, reshape, and compact areas disturbed by construction or adverse weather to

required density prior to further construction.

D. Where settling is measurable or observable at excavated areas during the project warranty

period, remove surface, add backfill material, compact and replace surface treatment.

E. Restore appearance, quality, and condition of surface or finish to match adjacent work and

eliminate evidence of restoration to the greatest extent possible.

DISPOSAL OF EXCESS AND WASTE MATERIALS

A. Remove waste materials, including unacceptable excavated material, trash, and debris, and

dispose of it off the property at no additional cost.

END OF SECTION - 02200

Page 5: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02212 – SUBGRADE PREPARATION 1

SECTION 02212 SUBGRADE PREPARATION PART 1 - GENERAL: The work shall consist of furnishing all material, equipment, labor to prepare subgrade for the aggregate base course. Subgrade is defined as earth fill for the aggregate base course and as aggregate base course for the portland cement concrete pavement and rubber mulch areas. ACCEPTANCE:

A. The Contractor shall examine areas and conditions under which subgrade preparation is to be performed and notify Owner’s Representative in writing of conditions detrimental to proper and timely completion of work. Subgrade preparation shall not commence until site is acceptable to the Contractor or that written exceptions have been waived by the Owner’s Representative.

DISPOSAL OF SURPLUS MATERIAL:

A. Surplus or waste material, resulting from the construction operation, shall be disposed of offsite by the Contractor.

PART 2 - EQUIPMENT:

A. Use equipment as necessary in preparing subgrade to achieve uniform density and meet minimum compaction and moisture content requirements.

PART 3 - EXECUTION CONSTRUCTION REQUIREMENTS:

A. Subgrade shall be graded to those lines, elevations, and cross-sections shown on the plans. Subgrade shall be uniform in density and meet minimum compaction and moisture content requirements. Soft areas not meeting these requirements shall be scarified to a depth of at least eight (8") inches, brought to the proper moisture content, recompacted and graded. Ruts and irregularities caused by hauling operations shall be reshaped and rerolled before the base or surfacing is placed. The subgrade shall be prepared in such a manner that drainage is always maintained. Ditches and storm sewers shall be kept open by the Contractor. Areas which will not drain when constructed to elevations and lines shown on the plans will immediately be brought to the attention of the Owner’s Representative.

B. All subgrades shall be rolled smooth for pavements and slabs at 95 percent maximum density

and optimum moisture content. Subgrade elevations shall be checked after rolling and, if not at

the proper elevation at all points, sufficient material shall be removed or added and compacted to

bring all portions of the subgrade to the required elevation and density. Earth subgrade shall

conform to within 0.10' plus or minus of the elevations, lines, and cross-sections shown on the

plans. Aggregate base subgrade shall conform to within 3/4 inch (0.06') plus or minus of the

elevations, lines, and cross-sections shown on the plans. Variations in thickness from minimum

to maximum thickness tolerances shall be gradual and compensating. PROTECTION AND CLEANUP:

A. Contractor shall have the responsibility to protect all surface structures such as manholes, catch basins, valve boxes, etc. Removal of siltation in storm sewers caused by Contractors operations will be his responsibility.

END OF SECTION

Page 6: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02511B - AGGREGATE BASE COURSE 1

SECTION 02511B - AGGREGATE BASE COURSE

A. General:

a. This work shall consist of furnishing all labor, materials, and equipment necessary to

construct the aggregate base course to the elevations, lines, cross-sections, and

thicknesses shown on the plan or as established by the Engineer.

B. Subgrade Preparation:

a. Subgrade shall be prepared in accordance with the "Subgrade Preparation" section of

these specifications.

b. Fine grading of the pavement and surface areas shall be done parallel to the centerline,

observing the profiles and cross-sections shown on the plans.

C. Materials:

a. Aggregate base course materials shall conform to all applicable requirements per the St.

Louis County Specifications. Material shall be mixed at the source to contain the proper

proportion of water to facilitate compaction.

b. Copies of all weight tickets shall be provided to the Owner prior to final acceptance and

payment.

D. Placing:

a. Base material shall be deposited and spread in layers of uniform thickness and width. The

maximum compacted thickness of any one layer shall not exceed six (6") inches.

Spreading equipment shall be equipped with strike off templates or screeds that can be

adjusted or controlled to secure the required thickness of the aggregate.

b. Thickness of spread material shall be such that when compacted it meets or exceeds the

thickness specified on the plans.

c. Dumping base material out of trucks into piles will not be permitted. Hauling over the

uncompacted base course will not be permitted. No material shall be placed on snow or

on a soft, muddy, or frozen Subgrade.

E. Compacting:

a. Compaction of base material shall immediately follow placement operation and be

performed in such a manner that uniform density and thickness is achieved.

b. Aggregate base course shall be compacted in 90-100 percent maximum dry density as

determined by Standard Compaction Test made in accordance with AASHTO T99, Method

C.

c. During compaction operations, the moisture content shall be maintained at the level

necessary to meet compaction requirements. Final rolling shall be accomplished by a self-

propelled smooth wheeled roller weighing not less than 10 tons. In areas inaccessible to

rollers, the base course material shall be tamped thoroughly with mechanical tampers.

F. Testing:

a. If necessary, the Owner will engage the services of a testing laboratory to sample and

make tests of material, placement and compaction, to ensure attainment of the specified

thickness and density of paving, and compliance with drawings and specifications. Testing

and control procedures, however, will not necessarily be limited to the above.

b. All direct charges for tests and testing will be paid by the Owner.

Page 7: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02511B - AGGREGATE BASE COURSE 2

G. Drainage:

a. The surface of the Subgrade and base course shall be well drained at all times. If at any

time, the compacted aggregate base or Subgrade becomes unstable, it shall be the

Contractor’s responsibility to restore, at his expense, the earth Subgrade and the

aggregate base to the required grade, cross-section, and density.

H. Disposal of Unsuitable Material:

a. Disposal of unsuitable material caused by Contractor operations shall be disposed of off-

site and replaced with suitable material complying with these specifications.

b. Contaminated material or materials which have segregated because of blading and

shaping shall be removed from the site.

END OF SECTION

Page 8: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02515 – PORTLAND CEMENT CONCRETE 1

SECTION 02515

PORTLAND CEMENT CONCRETE PART 1 - GENERAL This work shall consist of furnishing all materials, equipment, and labor necessary to construct portland cement concrete items as shown on the plans and herein described. This work shall include subgrade preparation, forming, placement of reinforcing steel and concrete; concrete finishing, curing, and testing, and cleanup. PART 2 – PRODUCTS MATERIALS:

A. Portland Cement - ASTM C-150 Type I. Only one brand of cement shall be used on exposed concrete throughout the project.

B. Normal Weight Aggregate - ASTM C-33. Local aggregate which can be shown by special test or

actual service to produce concrete of adequate strength and durability may be used with the approval of the Engineer. Frozen materials or materials containing snow or ice shall not be used.

C. Water - Potable

D. Air-Entraining Admixture - ASTM C-260

E. Water Reducing Admixture - ASTM C-494, Type A - Use is permitted only with written

authorization of the Engineer.

F. Expansion Joint Materials 1/2" thick cane fiber conforming to ASTM D-1751.

G. Membrane - Forming Curing Compound - ASTM C-309, Type I

H. Reinforcing Steel - Deformed Steel Bars - ASTM A-615, Grade 60

I. Welded Wire Fabric - Welded plain cold-drawn wire fabric - ASTM A-185

J. Joint Dowel Bars - Plain billet steel bars - ASTM A-615, Grade 40

K. Wire bar type reinforcing steel supports shall be used where a firm base is provided. Where concrete is cast against earth such as in footings, reinforcing steel may be supported by solid concrete brick.

L. Form Coatings - Commercial formulation that will not bond with, stain, or impair subsequent

treatments of concrete surfaces.

M. Sealer - "Porfill" as manufactured by Masury Columbia Company or "JX4000" as manufactured by Johnson Wax.

CONCRETE MIX DESIGN:

A. Design mixes for each type and strength of concrete shall be prepared by the concrete supplier and furnished to the Owner Representative at least 15 days prior to start of work. Mix design shall be in accordance with applicable provisions of ASTM C-94. Concrete mix design shall be submitted in written form to the Owner Representative by an independent testing facility and/or prepared by a Professional Engineer. Design of concrete mixes shall be at Contractor's expense.

Page 9: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02515 – PORTLAND CEMENT CONCRETE 2

Design mixes shall provide normal weight concrete with the following properties:

A. Sidewalks, curbs, and concrete pavement 4000 psi - 28-day compressive strength. CONCRETE MIXING AND DELIVERY:

A. Concrete shall comply with requirements of ASTM C-94, and as herein specified.

B. During hot weather, or under conditions contributing to rapid setting of concrete, a shorter mixing

time than specified in ASTM C-94 may be required. When air temperature is between 85oF

(30oC) and 90

oF (32

oC), reduce mixing and delivery time from 1-1/2 hours to 75 minutes, and

when air temperature is above 90oF (32

oC), reduce mixing and delivery time to 60 minutes.

C. When air temperature is below or expected to fall below 40oF within 24 hours after concrete is

placed, the aggregates, water, or both shall be heated before mixing to obtain a concrete

temperature of not less than 50oF and not more than 80

oF at point of placement. When hot

weather conditions exist that would impair placement or strength, mixing water shall be chilled or

chopped ice may be used to control concrete temperature. Concrete shall be cooled to 90oF or

below at the time of placement. ADMIXTURES:

A. All exposed, exterior concrete shall contain an air entrainment admixture. The amount used shall result in concrete having an air content at the point of placement in the range of 5.0% to 7.0%. All other concrete shall be limited to a maximum air content of 7.0%.

B. Use of water-reducing, calcium chloride or, any admixture which accelerates, retards the set, or

decreases the strength of the concrete mixture will not be permitted without prior written approval by the Engineer.

SLUMP LIMITS:

A. The concrete slump at the point of placement shall be between 2-1/2" and 4". Slump shall be adjusted within this range as required to provide proper consolidation, strikeout and surface finish.

FORMS:

A. Construct forms complying with ACI 347, to sizes, shapes, lines and dimensions shown, and to obtain accurate alignment, location, grades, level and plumb work in finished structures. Use selected materials to obtain required finishes. Solidly butt joints and provide back-up at joints to prevent leakage of cement paste. Provide form material with sufficient thickness to withstand the pressure of fluid concrete without bow or unacceptable deflection.

B. Coat contact surfaces of forms with form-release compound before forms are set. Care shall be

taken to prevent form release compound from getting on concrete bonding surfaces. PART 3 -EXECUTION SURFACE PREPARATION:

A. Prior to delivery of concrete, the subgrade shall be brought to the line and grade shown on the plans, free of irregularities, bumps, or depressions. Subgrade shall be compacted with a steel

Page 10: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02515 – PORTLAND CEMENT CONCRETE 3

wheel roller or tamper and all soft spots repaired or replaced. PLACING REINFORCEMENT:

A. Comply with Concrete Reinforcing Steel Institute's recommended practice for "Placing Reinforcing Bars," for details and methods of reinforcement placement and supports, and as herein specified.

B. Accurately position, support and secure reinforcement against displacement by formwork,

construction, or concrete placement operations. Locate and support reinforcing by metal chairs, runners, bolsters, spacers, and hanger, as required.

C. Install welded wire fabric in as long lengths as practicable. Lap adjoining pieces at least one full

mesh and lace splices with wire. Offset end laps in adjacent widths to prevent continuous laps in either direction. Welded wire reinforcement shall be supplied in flat sheets in lieu of rolls.

CONCRETE PLACEMENT:

A. Comply with ACI 304, and deposit concrete continuously and in layers of such thickness that no concrete will be placed on concrete which has hardened sufficiently to cause the formation of seams or planes of weakness. If a section cannot be placed continuously, provide construction joints as herein specified. Deposit concrete within five feet of its final location to avoid segregation. Chutes or pipes shall be used where the vertical drop or reinforcing steel may cause segregation.

B. Consolidate placed concrete by mechanical vibrating equipment supplemented by hand-spacing,

rodding or tamping. Use equipment and procedures for consolidation of concrete in accordance with ACI recommended practices. Consolidate concrete during placing operations so that concrete is thoroughly worked around reinforcement and other embedded items and into corners.

C. Bring slab surfaces to correct level with a straightedge and strikeoff. Use bull floats or darbies to

smooth surface, free of humps or depressions. Do not disturb slab surfaces prior to beginning finishing operations.

D. Maintain reinforcing in proper position during concrete placement operations.

E. Protect concrete work from physical damage or reduced strength which could be caused by frost,

freezing actions, or low temperatures, in compliance with ACI 306 and as herein specified. Concrete shall be covered and be heated as required to keep surrounding air and contact

surfaces at 40oF or above.

F. When hot weather conditions exist that would impair placement, strength, or finish, concrete shall

be placed in accordance with ACI 305 and as herein specified. Mists of cool water shall be sprayed on forms, reinforcing steel, and subgrade, to cool and dampen, immediately prior to placing concrete.

CONCRETE FINISHES:

A. Slabs shall be broom finished by drawing a fine-haired broom lightly across the surface after completion of floating and when excess moisture or surface sheen has disappeared. Brooming shall be perpendicular to normal traffic flow.

B. Islands, sidewalks, and other horizontal slabs shall be broom finished as noted on drawings.

C. Curbs shall be steel troweled to a hard, dense finish with corners, intersection, and terminations

slightly rounded. Curbs shall be hand rubbed on exposed faces to fill and smooth honeycomb, air

Page 11: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02515 – PORTLAND CEMENT CONCRETE 4

pockets, fins, and other imperfections. CONCRETE-CURING AND PROTECTION:

A. Protect freshly placed concrete from premature drying and excessive cold or hot temperature.

B. Start initial curing as soon as free water has disappeared from concrete surface after placing and finishing. Weather permitting; keep continuously moist for not less than 72 hours. Begin final curing procedures immediately following initial curing and before concrete has hardened. Continue final curing for at least 7 days in accordance with ACI 301 procedures. Avoid rapid drying at end of final curing period.

C. Perform curing of concrete by moist curing, by moisture-retaining cover curing, by membrane

curing, or by combinations of these.

D. Provide moisture curing by keeping concrete surface continuously wet by covering with water, or continuous water-fog spray or covering concrete surface with specified absorptive cover thoroughly saturating cover with water and keeping continuously wet. Place absorptive cover to provide coverage of concrete surfaces and edges, with 4" lap over adjacent absorptive covers.

E. Provide moisture-cover curing by covering concrete surfaces with moisture retaining cover for

curing concrete, placed in widest practicable width with sides and ends lapped at least 3" and sealed by waterproof tape or adhesive. Immediately repair any holes or tears during curing period using cover material and waterproof tape.

F. Provide membrane curing by applying membrane-forming curing compound to concrete surfaces

as soon as final finishing operations are complete (within 2 hours). Apply uniformly in continuous operation by power-spray or roller in accordance with manufacturer's directions. Recoat areas subjected to heavy rainfall within 3 hours after initial application. Maintain continuity of coating and repair damage during curing period.

QUALITY CONTROL:

A. The Owner’s Representative may employ an independent laboratory to perform quality control testing of concrete. These tests may include moisture testing of aggregates, batch weight observation, slump and air contact tests, compression strength tests, etc. Both Owner’s Representative and Contractor will be provided test results. When these tests indicate that concrete does not meet with the requirements of the plans or these specifications, the Contractor shall remove the deficient concrete or conduct additional tests, at his expense, to prove its adequacy. Contractor shall afford the representatives of the testing laboratory every opportunity to observe and sample concrete materials as may be required to perform their work.

QUALITY ASSURANCE:

A. Codes and Standards: Comply with provisions of the following codes, specifications and standards, except where more stringent requirements are shown or specified:

ACI 311 “Recommended Practice for Concrete Inspection”

ACI 318 “Building Code Requirements for Reinforced Concrete”

ACI 347 “Recommended Practice for Concrete Formwork” ACI 304 “Recommended Practice for Measuring, Mixing, Transporting and Placing

Concrete”

Page 12: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02515 – PORTLAND CEMENT CONCRETE 5

GUARANTEE:

A. The Contractor shall guarantee all portland cement concrete for a period of one (1) year from the date of final acceptance. All work which is found to be defective in materials or workmanship, together with adjacent work which requires repair or replacement because of the defective work shall be repaired or replaced to the satisfaction of the Owner’s Representative and at no additional expense to him. This guarantee shall be provided to the Owner’s Representative in the form of a written warranty executed at the time of contract award by the Contractor. Defective work is defined to include uncontrolled cracking, spalling, and abnormal deuteriation.

MATERIAL CERTIFICATES: A. Provide materials certificates in lieu of materials laboratory test reports when permitted by

Engineer. Material certificates shall be signed by manufacturer and Contractor, certifying that each material item complies with, or exceeds, specified requirements.

SURFACE TOLERANCES:

A. The surface of each layer shall be substantially free from waves or irregularities. The final surface pavement shall not vary from a 10-foot straightedge, applied perpendicular to the contours or parallel to driving lanes by more than 1/4 inch

BARRICADES:

A. Protect the concrete work from damage until accepted by the Owner’s Representative. Exclude traffic from pavement until concrete has attained its design compressive strength. It is the Contractor's responsibility to provide the necessary tests to show that the strength has been obtained.

JOINTS: GENERAL:

A. Construct expansion and weakened-plane (contraction) joints, true-to-line with face perpendicular to surface of the curb and gutter or pavement unless otherwise indicated. Construct transverse joints at right angles to the curb centerline, unless otherwise indicated.

CONSTRUCTION JOINTS:

A. Construction joints shall be formed only at the end of day's pour unless otherwise shown on the plan. Construction joints shall be keyed and slab thickness increased by four (4") inches for a distance of twelve (12") inches from the edge of joint.

CONTRACTION JOINTS:

A. Contraction joints shall be placed in all walks and pavement in a uniform pattern such that unbroken concrete area is not less than sixteen (16) square feet nor more than thirty six (36) square feet. Control joints shall be tooled or formed with 1/4" radii to twenty (20) percent or more of slab thickness.

EXPANSION JOINTS:

A. Furnish and install expansion joints where slab, pavements, sidewalk, etc. abuts a vertical surface and fifty (50') feet maximum on center. Joints shall be evenly spaced on a rectangular pattern. Joints in curb or walls shall align with sidewalk and slab joints. Expansion joints shall be 1/2" thick, full depth of slab. Set filler approximately 1/2" below finished surface and fill with

Page 13: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02515 – PORTLAND CEMENT CONCRETE 6

polyurethane sealant. Edges of expansion joints shall be rounded with a 1/4" radius edging tool.

B. Place expansion joints at the end of pours and at locations where placement operations are topped for a period of more than 1/2 hour.

C. Where load transfer-slip dowel devices are used, install units so that one end of each dowel bar is

free to move.

D. Provide premolded joint filler for expansion joints abutting catch basins, manholes, inlets, structures, walks, and other fixed objects.

FILLERS AND SEALANTS:

A. Comply with the requirements of St. Louis County Department of Highways and Traffic Standard Specifications for preparation of joints, materials, installation, and performance.

B. Curbs shall be formed so that the finished concrete will conform to the proper dimensions and

contours. The curb shall be constructed in sections having a length of about ten (10) feet. The length of these sections may be reduced where necessary for closures, but no section less than four (4) feet will be permitted. The face and top of the curb shall be floated smooth and the edges shall be rounded as shown in typical section. Curbs shall be constructed straight with smooth grade transitions.

THICKNESS AND STRENGTH REQUIREMENTS:

A. Average strength of all compression test samples shall meet or exceed the design requirements. All concrete areas represented by samples with compressive strength less than 90 percent of specified shall be removed and replaced at Contractor's sole expense. Average thickness of all samples shall not be less than the specified thickness.

END OF SECTION - 02515

Page 14: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02620 - SUBDRAINAGE 1

SECTION 02620 - SUBDRAINAGE

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplemental

Conditions and Division 01 Specifications, apply to this section.

B. Section 02300 Earthworks for grading, base course and additional geotextiles; Section 02630

Storm Drainage; Section 02811 Sports Field Irrigation; Section 02822 Sports Field Construction;

Section 02926 Sports Field Seeding; Section 02791 Synthetic Turf Playground Surfacing and

Section 02792 Synthetic Sports Field Surfacing.

1.2 SUMMARY

A. Section Includes:

1. Perforated-pipe and fittings.

2. Geo-Composite lateral drainpipe and fittings.

3. Drainage conduits (under-drains, collector pipes).

4. Geotextile filter fabrics.

1.3 ACTION SUBMITTALS

A. Product Data:

1. For all specified piping products, including rated capacities.

2. Geotextile filter fabrics.

3. Test Results.

B. Other Data:

1. Record drawings indicating actual pipe and connection locations and elevations of

installations. Provide key dimensions, tied to permanent improvements, for future

location purposes. Maintain record data as work progresses.

2. Submit final “As-Built” drawings to Owner at completion of project.

3. Manufacturer’s installation instructions for all products specified.

C. QUALITY ASSURANCE

1. Pre-Construction Conference: Conduct a pre-construction conference at the project

site.

2. Material equipment and methods of installation shall comply with all applicable codes,

city and state regulations and ASTM standards in regard to materials to be used in

subsurface drainage systems.

Page 15: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02620 - SUBDRAINAGE 2

3. Contractor shall provide documentation of completed subdrainage systems for the

scope of work included in the Project. Provide documentation and references for 5

successfully completed projects including description, project location and reference

contact information.

D. PROJECT CONDITIONS

1. Protect existing and new work from damage as work progresses.

2. Do not conduct work when site conditions are detrimental to the quality of the finished

work.

3. Coordinate locations of subsurface drainage drains to avoid conflicts with other field

construction components and other trades work. Notify Owner and obtain prior approval

for necessary adjustments required to avoid conflicts.

4. Coordinate subsurface drainage work with other trades to avoid delays.

5. All piping, fittings and drainage structures shall be kept clean of obstructions during

storage and progression of the work. Store and handle all products in accordance with

the Manufacturer’s instructions to avoid damage.

PART 2 - PRODUCTS

2.1 PERFORATED-PIPES AND FITTINGS

A. Perforated PE Pipe and Fittings:

1. NPS 6and Smaller: ASTM F 405 or AASHTO M 252, Type CP; corrugated, for

coupled joints.

2. NPS 8and Larger: ASTM F 667; AASHTO M 252, Type CP; or AASHTO M 294, Type

CP; corrugated; for coupled joints.

3. Couplings: Manufacturer's standard, band type.

B. Perforated PVC Sewer Pipe and Fittings for Bio-Retention Areas and Permeable Pavement

(Asphalt, Concrete and Pavers): ASTM D 3034, SDR 35 with bell-and-spigot ends for gasketed

joints with ASTM F 477, elastomeric seals. Perforations shall meet AASHTO M278 Highway

Underdrain Specifications. Perforations shall be circular holes 3/8” diameter arranged in rows

parallel to the axis of the pipe. The rows of perforations shall be arranged in two equal groups

placed symmetrically on either side of a lower unperforated segment, corresponding to the

flowline of the pipe. The spacing of rows shall be uniform. The distance between the centerlines

of rows shall be not less than 1-inch. There shall be 2 holes per row with the centerline of holes

2-inches off the bottom of pipe.

C. High Density Polyethylene Pipe (HDPE) and Corrugated Polyethylene Pipe associated with

sports field and playground drainage:

1. HDPE core pipe, used for collection of water on the field, with integrally formed

smooth waterway. Nominal size shall be oblong shape. Pipe and fittings shall be made

Page 16: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02620 - SUBDRAINAGE 3

from PE compounds which conform to the requirements of cell class 323410C or

333410C per ASTM D3350.

2. HDPE pipe used for connections with integrally formed smooth waterway. Nominal

size shall have a full circular cross-section, with an outer corrugated pipe wall and

smooth inner wall. Pipe and fittings shall be made from PE compounds which conform to

the requirements of cell class 324420C per ASTM D3350.

3. HDPE material requirements shall be as follows:

Product Average Test Value ASTM Method

Compressive Strength at 9,200 lbs./ft2ASTM D1621

Maximum deflection of 20%

Flow Rate at 10 psi & 21 gpm/ft width ASTM D4716

Gradient of 0.1

Peel Strength (Fabric Core) 35 lbs/ft width ASTM D1876

4. Pipe fittings shall not impair or reduce the integrity of the drainage system. Use only

fittings approved by pipe manufacturer.

5. Geo-Composite lateral drainage pipe (Basis of Design - natural and synthetic turf

fields) shall be Hydraway 2000 drainage pipe as indicated on the drawings and as

manufactured by Midwest Diversified Technologies, Inc., Belleville, IL (618) 398-5503,

http://www.hydraway.net/residential/hydraway_2000.php, or functional equivalent.

Provide product with the following properties:

a. Composite construction consisting of rigid polyethylene lattice matrix with a

geotextile fabric wrapping permanently bonded to the external surface to exclude

clogging particles.

b. Sizes shall be 6” or 12” as indicated on the drawings.

c. Lattice Physical Properties

Compressive Strength: ASTM D695/1621-II – Value 11,400 PSF

Flow Rate: ASTM D4716 – Value 21 GPM/Ft. Width

Peel Strength: ASTMD1876 – Value 35 Lbs/Ft. Width

d. Geotextile Wrapping Physical Properties

Weight: Min. 4.5 Oz/SY

Elongation: ASTM D4632 – Value 50%

Grab Strength: ASTM D4632 – Value 120 Lbs

Flow Rate: ASTM D4491 – Value 135 GPM/Ft3

Page 17: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02620 - SUBDRAINAGE 4

e. Other acceptable manufacturers and products include 6” MVP (for natural turf

field) and 12” MVP (synthetic turf fields) as manufactured by “J” Drain, http://j-

drain.com or functional equivalent.

6. Corrugated Polyethylene Pipe shall be perforated with integrally formed, smooth

waterway. Nominal size shall have a full circular cross-section, with an outer corrugated

pipe wall and smooth inner wall. Pipe and fittings shall be made from virgin PE

compounds conforming to the requirements of cell class 424420C per ASTM D3350.

7. The minimum parallel plate stiffness values, when tested in accordance with ASTM

D2412 shall be as follows:

Pipe Dia. Pipe Stiffness

4 inch 50 psi

8 inch 50 psi

10 inch 50 psi

12 inch 50 psi

8. Pipe fittings shall not impair or reduce the integrity of the drainage system. Use only

fittings approved by pipe manufacturer. Where indicated on the drawings or required by

pipe manufacturer, a neoprene or rubber gasket shall be provided.

9. Corrugated PE pipe shall be N-12 HDPE drainage pipe as manufactured by Advanced

Drainage Systems or functional equivalent.

2.2 SOIL MATERIALS

A. Soil and base materials are specified in Section 02300 "Earthwork."

2.3 GEOTEXTILE FILTER FABRIC

A. Pipe Sock Structure Type: Nonwoven, needle-punched polypropylene fibers.

1. Grab Tensile Strength ASTM D4632 120 Lbs.

2. Grab Tensile Elongation ASTM D4632 50%

3. Trapezoid Tear Strength ASTM D4533 50 Lbs.

4. Mullen Brust Strength ASTM D3786 230 psi

5. Puncture Strength ASTM D4833 65 Lbs

6. UV Resistance After 500 Hrs. ASTM D4355 70% Strength

7. Apparent Opening Size ASTM D4751 70 U.S. Sieve

8. Permittivity ASTM D4491 1.5/sec

B. Refer to Section 02300 Earthwork for material properties of additional geotextile fabrics for

the various subsurface drainage applications included in the Project.

Page 18: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02620 - SUBDRAINAGE 5

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine surfaces and areas for suitable conditions where subdrainage systems are to be

installed. Verify dimensions, elevations, and acceptable conditions to proceed with the Work.

Sports field require use of laser equipment for grading and verification of grading, slopes, and

elevations.

B. Locate and mark existing utilities, underground structures, and aboveground obstructions

before beginning installation and avoid disruption and damage of services.

C. Notify owner of any discrepancies and proceed with installation only after unsatisfactory

conditions have been corrected.

3.2 EARTHWORK

A. Excavating, trenching, and backfilling are specified in Section 02300 "Earthwork."

3.3 PERMEABLE PAVEMENT UNDERDRAIN INSTALLATION

A. Grade bottom of permeable pavement areas as specified in Section 02300 "Earthwork" and

as shown on the drawings.

B. Lay geotextile filter fabric in permeable pavement areas and sides.

C. Install drainage conduits as indicated in Part 3 "Piping Installation" Article. Connect fabric

sections with adhesive or tape as required.

D. Add drainage courses to top of drainage conduits to a depth of not less than as shown on

drawings.

E. Fill to Grade: Place pavement structure over drainage courses as shown on the drawings.

3.4 SPORTS FIELD AND PLAYGROUND UNDERDRAIN INSTALLATION

A. Grade bottom of trench as specified in Section 02300 "Earthwork" and as shown on the

drawings.

B. Lay flat-style geotextile filter fabric in trench and sides of collector drains for both synthetic

turf and natural turf fields. For synthetic turf field also lay geotextile filter on subgrade prior to

installing horizontal, composite field drain laterals and stone drainage base. On natural turf field,

geotextile fabric in not required in the narrow-slit trenches with vertical composite drain laterals.

For playgrounds follow the procedures identified for the synthetic turf field or as recommended

by the playground turf manufacturer.

C. Install drainage conduits as indicated in Part 3 "Piping Installation" Article and as indicated on

drawing details. Connect fabric sections with adhesive or tape as required.

1. At natural turf sports fields the bottom of trenches for the geo-composite drains shall

be a minimum of 12 inches below finish grade unless otherwise shown on the drawings

and laid in the pattern and at slopes indicated on the drawings.

Page 19: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02620 - SUBDRAINAGE 6

2. All trenches for vertically oriented geo-composite drains shall be 4 inched wide. Drain

shall be stabilized and centered in the trench during backfill operations.

3. Collection pipe trenches shall be a minimum of two (2) times the pipe diameter and

lined with the specified geotextile fabric. Slope pipes as indicated on the drawings. Install

in accordance with manufacturer’s instructions.

4. Geo-composite drains under synthetic playground surfacing shall be laid horizontal in

the pattern and at slopes indicated on the drawings. Place drains after completing

subgrade preparation and laying geotextile fabric over prepared subgrade. Install in

accordance with manufacturer’s instructions.

5. Contractor shall take all precautions to avoid damage to prepared subgrades.

D. Add drainage courses to top of drainage conduits to a depth of not less than as shown on

drawings.

E. Fill to Grade: Place remaining sports field fill material and playground fill material over

drainage courses as shown on the drawings.

3.7 RETAINING-WALL DRAINAGE INSTALLATION

A. Lay flat-style geotextile filter fabric in trench and overlap trench sides.

B. Place supporting layer of drainage course over compacted subgrade to compacted depth of

not less than 4 inches.

C. Install drainage piping as indicated in Part 3 "Piping Installation" Article for retaining wall

subdrainage.

D. Add drainage course to width of at least 6 inches on side away from wall and to top of pipe to

perform tests.

E. After satisfactory testing, cover drainage piping to width of at least 6 inches on side away

from footing and above top of pipe to within 12 inches of finish grade.

F. Place drainage course in layers not exceeding 3 inches in loose depth; compact each layer

placed and wrap top of drainage course with flat-style geotextile filter fabric.

G. Place layer of flat-style geotextile filter fabric over top of drainage course, overlapping edges

at least 4 inches.

H. Fill to Grade: Place satisfactory soil fill material over compacted drainage course. Place

material in loose-depth layers not exceeding 6 inches. Thoroughly compact each layer. Fill to

finish grade.

3.8 PIPING INSTALLATION

A. Install piping beginning at low points of system, true to grades and alignment indicated, with

unbroken continuity of invert. Bed piping with full bearing in filtering material. Install gaskets,

seals, sleeves, and couplings according to manufacturer's written instructions and other

requirements indicated.

Page 20: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02620 - SUBDRAINAGE 7

1. Permeable Pavement Subdrainage: Install piping pitched down in direction of flow, at

a minimum slope of 0.5 percent and with a minimum cover as shown on the drawings.

2. Playground Subdrainage: Install piping pitched down in direction of flow, at the

minimum slopes and with the minimum cover as indicated on the drawings.

3. Lay perforated pipe with perforations down.

4. Excavate recesses in trench bottom for bell ends of pipe. Lay pipe with bells facing

upslope and with spigot end entered fully into adjacent bell.

B. Use increasers, reducers, and couplings made for different sizes or materials of pipes and

fittings being connected. Reduction of pipe size in direction of flow is prohibited.

C. Install PVC sewer piping according to ASTM D 2321.

3.9 PIPE JOINT CONSTRUCTION

A. Join perforated PE pipe and fittings with couplings according to ASTM D 3212 with loose

banded, coupled, or push-on joints.

B. Join perforated PVC sewer pipe and fittings according to ASTM D 3212 with loose bell-and-

spigot, push-on joints.

C. Special Pipe Couplings: Join piping made of different materials and dimensions with special

couplings made for this application. Use couplings that are compatible with and fit materials and

dimensions of both pipes.

D. Geo-composite drains shall utilize manufacturer’s standard connections for all types of

connections required by the drainage system layout and various piping materials. Install all

connections in accordance with manufacturer’s instructions.

3.10 CLEANOUT INSTALLATION

A. Comply with requirements for cleanouts specified in Section 02630 "Storm Drainage."

B. Cleanouts for Subdrainage:

1. Install cleanouts from piping to grade. Locate cleanouts at beginning of piping run as

shown on the drawings. Install fittings so cleanouts open in direction of flow in piping.

2. In vehicular-traffic areas, use pipe and fittings as shown on the drawings. Set cleanout

frames and covers in a cast-in-place concrete collar, 18 by 18 by 12 inchesdeep. Set top

of cleanout flush with grade

3. In nonvehicular-traffic areas, use pipe and fittings as shown on the drawings. Set top of

cleanout flush with or at a maximum of 1 inch above grade.

3.11 CONNECTIONS

A. Comply with requirements for piping specified in Section 02630 "Storm Drainage." Drawings

indicate general arrangement of piping, fittings, and specialties.

Page 21: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02620 - SUBDRAINAGE 8

3.12 FIELD QUALITY CONTROL

A. Tests and Inspections:

1. After installing drainage course to top of piping, test drain piping with water to ensure

free flow before backfilling.

2. Remove obstructions, replace damaged components, and repeat test until results are

satisfactory.

3. Notify Owner a minimum of 24 hours in advance to allow for observation of testing

procedures.

B. Drain piping will be considered defective if it does not pass tests and inspections.

C. Prepare test and inspection reports and submit to Owner.

3.13 PROTECTION AND CLEANING

A. Protect in-progress and completed Work form damage. Any damage shall be removed and

replaced to specified requirements.

B. Clear interior of installed piping and structures of dirt and other superfluous material as work

progresses. Maintain swab or drag in piping and pull past each joint as it is completed. Place

plugs in ends of uncompleted pipe at end of each day or when work stops.

C. Remove all extra materials and waste materials and legally dispose of off the project site.

END OF SECTION 02620

Page 22: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02661 - GENERAL PROVISION – PLUMBING 1

SECTION 02661 - GENERAL PROVISION – PLUMBING PART 1 – GENERAL 1.01 DESCRIPTION

A. The Plumbing Contractor shall furnish all labor, materials, tools and equipment necessary to complete the Plumbing work indicated on the drawings and as specified herein.

B. The Plumbing Contractor shall include all plant, labor, material and services required to complete the installation of all equipment as hereinafter specified and shown on all drawings, and comply with applicable provisions of Division “0” and “1”.

C. The Plumbing Contractor shall carefully examine the site, plans, and specifications, and carry on the Plumbing work in such a manner as not to delay or interfere with the work of other contractors.

D. The drawings detail (1) work which must be done expeditiously at the beginning of the contract period to allow site excavation for the new building, and (2) work which must be done later in the contract period as construction progresses.

1.02 CONTRACT DRAWINGS

A. All contract drawings, supplemental or revised drawings, and specifications, complete with any addenda, shall be part of this Contract and shall be kept at the job site.

B. The drawings and these specifications shall be considered as cooperative. The work or materials called for on one and not mentioned on the other shall be done in as faithful and as thorough a manner as though treated by both.

C. The location of all equipment, piping, conduit, duct work, etc., is shown on the drawings. Do not scale the drawings for exact locations; if any discrepancies occur between drawings and actual conditions, the Sub-contractors shall contact the Engineer before starting work.

1.03 ACCURACY OF DATA

A. Whenever the location of wiring or equipment is governed by Engineer features, establish the exact location by reference to the dimensions on the Engineer drawings. Do not scale the drawings for exact dimensions.

1.04 CODES, ORDINANCES, PERMITS AND FEES

A. The Plumbing Contractor shall perform all work specified herein to conform to the latest rules, regulations, codes and ordinances of the various departments of the Local, State, and National authorities having jurisdiction.

B. All local, state and national codes shall be in force and will be the basis for design, equipment and installation for this project

C. The Plumbing system shall comply with the Life Safety Code and National Fire Protection Association.

D. Nothing in these specifications shall be interpreted to conflict with any Local, State, Federal or Fire Underwriters requirements, which apply to this class of work. Should any such conflict exist, advise the Owner Representative of it and be guided by the law or requirements whichever are stricter.

E. If during the progress of the work, upon completion of the work or at any time during the period covered under “Warranty”, it shall be found that the work was not installed as specified according to any and all the regulations and codes stated herein, and in force at

Page 23: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02661 - GENERAL PROVISION – PLUMBING 2

the time the Contract is signed, the Plumbing Contractor shall be held responsible and make the work installed conform to these regulations and codes at no additional cost.

F. The Plumbing Contractor shall secure and pay for all necessary permits for the installation of equipment and materials. Upon completion of the work, submit to the Engineer a certificate of final inspection and approval from the inspection authorities.

1.05 WORK JURISDICTION

A. The Plumbing Contractor shall comply with required jurisdiction as to which particular trade shall install any part or parts of any work or equipment specified under the heading of “Plumbing Section” and include costs for work by other trades specified as being included in the Plumbing Contract.

1.06 TIME OF COMMENCEMENT AND COMPLETION

A. The Plumbing Contractor shall commence work under this contract on the date specified by the Owner or his Construction Manager and thereafter coordinate the work with the work of the General Contractor and other Contractors, so that the work will be complete within the completion time fixed by the owner or his/her Construction Manager.

1.07 MATERIAL AND WORKMANSHIP

A. All work called for in these specifications and on the drawings, shall be executed in a thorough, substantial and workmanlike manner. All material shall be new and of the best quality in every respect, and subject to review by the Engineer.

B. The material and workmanship throughout the project must conform in every way to the latest requirements of the National Board of Fire Underwriters.

1.08 TOOLS AND EQUIPMENT

A. Furnish all transportation, labor, apparatus, equipment, tools, lights, barricades, and ladders for the due, faithful and safe performance of the work according to the true intent and meaning of these specifications and drawings which accompany them.

1.09 PROTECTION OF EQUIPMENT

A. Take precautions as may be necessary to properly protect materials and equipment from damage during construction. Failure to comply with the above, to the entire satisfaction of the Engineer, will be sufficient cause for the rejection of the damaged materials.

1.10 LOCATION OF EQUIPMENT AND MATERIALS

A. The approximate locations of water service lines and connections, etc., are indicated on the drawings. These drawings are not intended to give complete and accurate details in regard to exact location of the above items. Exact locations are to be determined by reference to the drawings and by the actual measurements of the building and site.

1.11 REMOVAL OF RUBBISH AND CLEANING OF EQUIPMENT

A. The Plumbing Contractor shall not allow the accumulation of rubbish and debris caused by the installation of the Plumbing work. All rubbish and debris shall be specifically removed

Page 24: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02661 - GENERAL PROVISION – PLUMBING 3

when so directed by the Engineer. On completion of the work, all rubbish and debris created by the installation of the Plumbing work shall be entirely removed, so as to leave the premises clean and ready for use by the Owner.

B. Exterior surfaces of all exposed fixtures, etc., shall be thoroughly cleaned before the apparatus will be accepted by the owner. All marred finishes shall be repaired, touched-up or replaced as directed.

1.12 SHOP DRAWINGS

A. Submit, in brochure or book form, catalog cuts, printed line drawings, printed descriptions, and specification sheets to fully illustrate and describe each item of equipment as required for Shop Drawings, Product Data and Samples.

B. In submitting shop drawings or printed material of this nature for review clearly mark each shop drawing, catalog cut, pamphlet, etc. with the applicable section of specification for purposes of identification and record. No shop drawing will be reviewed without the signature of the Contractor, which shall signify that he/she has checked drawings for accuracy and dimensions.

C. Shop and working drawings, catalog cuts, pamphlets, specification data, etc., shall have thereon the signed or stamped review of the Engineer and no drawings will be allowed on the building site without this review.

D. These shop drawings will be required regardless of whether materials supplied are substitutions or as specified.

E. Shop drawings for the following equipment or material shall be submitted where applicable: 1. Water distribution design layout. 2. Plumbing fixtures. 3. Pipe, Connections, Fittings.

1.13 SUPERVISION AND COOPERATION

A. All work must be done to the complete satisfaction of the Owner and there shall be no major deviations from these drawings or specifications without review and acceptance by the Owner and Engineer.

B. Cooperate to the fullest extent, with other trades and execute the work, so as to have as little interference as possible with the other trades.

C. Consult ALL drawings and specifications for space allotments and coordination. The Plumbing Contractor shall revise, at his/her own cost, any Plumbing work installed without regard for the work of others.

D. Be responsible for coordination of all equipment, devices, and conductors with reference to the Plumbing and thermal characteristics of equipment.

1.14 ERECTION OF APPARATUS

A. The work shall be done under the direction of a competent foreman, who shall layout all work. Should any difficulty arise in installing the system or its components, promptly report same to the Owner Representative.

1.15 INSPECTIONS

Page 25: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02661 - GENERAL PROVISION – PLUMBING 4

A. All work shall remain uncovered for periodic inspections required by inspection regulations.

The Owner or Owner Representative shall have the right to inspect the work whenever advisable in his/her judgment. The Plumbing Contractor shall have a representative present on each inspection and give such assistance as may be required. Changes required due to unacceptable work or materials required by the Inspector, or Engineer, shall be promptly carried out, and all unsatisfactory material and workmanship, replaced at no additional cost and without delaying the project completion date.

1.16 INTERPRETATIONS

A. If an interpretation of the specifications is required, or some contradiction of the specifications and/or drawings is found, contact the Engineer, and the Owner Representative will interpret the specification as to the intent.

1.17 PRODUCT DELIVERY, STORAGE AND HANDLING

A. All products shall be delivered to the project in manufacturer’s containers, stored and protected from damage during handling and installation procedures.

1.18 QUALITY ASSURANCE

A. All materials and equipment shall bear the Underwriters Laboratories label and shall meet the requirements of the National Plumbing Code and the National Plumbing Manufacturer’s Association.

B. All materials shall be installed in strict conformance to manufacturers written installation instructions. Nothing in these drawings and specifications shall be construed to vary from manufacturers written installation instructions, unless specifically confirmed in writing by the Owner Representative.

1.19 ADJUSTMENT AND TESTING

A. Before final Owner acceptance is made, the Plumbing Contractor shall adjust all apparatus and place same in satisfactory service as required by the Owner Representative. Furnish all equipment, labor and materials to perform the tests as hereinafter specified.

B. After all pipes, fixtures, etc., are in place and connected, the system shall be tested for pressure and leaks and be in general acceptable operation. If system defects in material or workmanship are found, they shall be, repaired, removed and/or replaced.

C. Acceptance Tests 1. The Plumbing Contractor shall perform Acceptance Demonstrations to prove

satisfactory performance characteristics of the Plumbing and auxiliary systems. 2. The Acceptance Demonstration shall be conducted in the presence of the Owner

and all faults discovered therein shall be immediately corrected. D. Demonstrations

1. The Plumbing Contractor shall demonstrate to the Owner’s authorized personnel the essential features of the Plumbing systems and auxiliary systems.

2. The systems shall be demonstrated once only on a date to be agreed upon, in writing, by the Owner or his/her representative.

3. The demonstration of the work installed by the Plumbing Contractor shall be held by the Plumbing Contractor in the presence of the Owner or his/her designated

Page 26: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02661 - GENERAL PROVISION – PLUMBING 5

representative, the Owner Representative, and the major equipment manufacturer’s representative.

1.20 WARRANTY A. Furnish a written warranty in triplicate, warranting all materials, equipment, and labor furnished

to be free of defects for a period of one (1) year from date of final acceptance by the Owner. Further warrant that all equipment shall meet the characteristics, capacities, and workmanship specified and should any defects appear or performance of equipment is inadequate within the warranty period, the defects and/or equipment will be replaced or made good without cost to the Owner.

END OF SECTION

Page 27: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02832 - SEGMENTAL RETAINING WALLS

1

SECTION 02832 - SEGMENTAL RETAINING WALLS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specifications, apply to this Section. Design of segmental retaining walls shall also be in accordance with the National Concrete Masonry Association, the City of University City Building Codes and project geotechnical report.

1.2 SUMMARY

A. This Section includes single and multiple depth segmental retaining walls with soil reinforcement.

B. Related Sections:

1. Section 02300 - Earthwork

1.3 PERFORMANCE REQUIREMENTS

A. Delegated Design: Contractor shall design segmental retaining walls, including comprehensive engineering analysis by a qualified professional engineer, using performance requirements and design criteria indicated.

B. Global Stability: Contractor shall provide comprehensive engineering analysis of global stability and settlement by a qualified professional engineer using performance requirements and design criteria indicated.

C. Structural Performance: Engineering design shall be based on the following loads and be according to NCMA's "Design Manual for Segmental Retaining Walls."

1. Gravity loads due to all applied pressures resulting from grades and sloped backfill indicated.

2. Superimposed loads (surcharge) indicated on Drawings.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of product indicated.

B. Samples for Initial Selection: Concrete unit and cap.

C. Samples for Verification: For each color and texture of concrete unit required. Submit full-size units.

1. Include one full-size unit for each type of concrete unit required.

D. Delegated-Design Submittal: For segmental retaining walls indicated to comply with performance requirements and design criteria, including analysis data and drawings (typical sections, and elevation views, etc.) signed and sealed by the qualified professional engineer responsible for their preparation. Obtain any necessary permits and submittal approvals for the wall design.

1. Compliance Review: Qualified professional engineer responsible for segmental retaining wall design shall review and approve submittals and source and field quality-control reports for compliance of materials and construction with design prior to design submittal. Submit certification of compliance with design submittal.

1.6 INFORMATIONAL SUBMITTALS

A. Qualification Data: For qualified professional engineer and testing agency.

Page 28: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02832 - SEGMENTAL RETAINING WALLS

2

B. Product Certificates: For segmental retaining wall units and soil reinforcement, from manufacturer.

1. Include test data for shear strength between segmental retaining wall units according to ASTM D 6916.

2. Include test data for connection strength between segmental retaining wall units and soil reinforcement according to ASTM D 6638.

C. Product Test Reports: Based on evaluation of comprehensive tests performed by a qualified testing agency, for segmental retaining wall units and soil reinforcement.

1. Include test data for freeze-thaw durability of segmental retaining wall units.

2. Include test data for shear strength between segmental retaining wall units according to ASTM D 6916.

3. Include test data for connection strength between segmental retaining wall units and soil reinforcement according to ASTM D 6638.

1.7 QUALITY ASSURANCE

A. Testing Agency Qualifications: Qualified according to ASTM E 329 or approved equivalent for testing indicated.

B. Mockups: Build mockups to verify selections made under sample submittals and to demonstrate aesthetic effects.

1. Build mockup of segmental retaining wall as shown on Drawings approximately 72 inches long by not less than 18 inches high above finished grade at front of wall.

a. Include typical soil reinforcement.

b. Include typical base and cap or finished top construction.

c. Include backfill to typical finished grades at both sides of wall.

d. Include typical end construction at one end of mockup.

e. Include 36-inch return at 1 end of mockup, with typical corner construction.

2. Approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion.

1.8 DELIVERY, STORAGE, AND HANDLING

A. Store and handle concrete units and accessories to prevent deterioration or damage due to contaminants, breaking, chipping, or other causes. Follow manufacturer’s instructions.

B. Store geosynthetics in manufacturer's original packaging with labels intact. Store and handle geosynthetics to prevent deterioration or damage due to sunlight, chemicals, flames, temperatures above 160 deg F or below 32 deg F, and other conditions that might damage them. Verify identification of geosynthetics before using and examine them for defects as material is placed.

PART 2 - PRODUCTS

2.1 SEGMENTAL RETAINING WALL UNITS

A. Concrete Units: ASTM C 1372, Normal Weight, except that maximum water absorption shall not exceed 7 percent by weight and units shall not differ in height more than plus or minus 1/16 inch from specified dimension.

Page 29: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02832 - SEGMENTAL RETAINING WALLS

3

1. Manufacturers: Subject to compliance with requirements, provide products by available manufacturers offering products similar or functional equivalent to VERSA-LOK Mosaic - Weathered Block, manufactured by Kirchner Block and Brick, Inc., 12901 St. Charles Rock Road, Bridgeton, MO 63044.

2. Provide units that comply with requirements for freeze-thaw durability.

3. Provide units that interlock with courses above and below by means of pins or similar aligning/locking features.

B. Color: As selected by Owner from manufacturer's full range.

C. Shape and Texture: Provide units matching basic shape, dimensions, and face texture similar to the Standard - Weathered block.

D. Batter: Provide units that offset from course below to provide at least 1:8 batter.

E. Cap Units: Provide cap units of same shape as other units with smooth, as-cast top surfaces without holes or lugs.

F. Special Units: Provide corner units, end units, and other shapes as needed to produce segmental retaining walls of dimensions and profiles indicated and to provide texture on exposed surfaces similar to Standard - Weathered cap units.

2.2 INSTALLATION MATERIALS

A. Pins: Product supplied by segmental retaining wall unit manufacturer for use with units provided, made from nondegrading polymer reinforced with glass fibers.

B. Clips: Product supplied by segmental retaining wall unit manufacturer for use with units provided, made from nondegrading polymer reinforced with glass fibers.

C. Cap Adhesive: Product supplied or recommended by segmental retaining wall unit manufacturer for adhering cap units to units below.

D. Leveling Base: Comply with requirements for base material as designated by wall designer:

1. Leveling Course: As designated by wall designer.

E. Drainage Fill: Comply with requirements as designated by wall designer.

F. Reinforced-Soil Fill: Comply with requirements as designated by wall designer.

G. Reinforced-Soil Fill: Crushed limestone, 1 inch clean or 1 inch minus, quarry produced, and as specified by wall design engineer, free of debris, waste, frozen materials, vegetation, and other deleterious matter;

H. Nonreinforced-Soil Fill: Comply with requirements in Section 02300 Earthwork for satisfactory soils and as designated by wall designer.

I. Drainage Geotextile: Nonwoven needle-punched geotextile, manufactured for subsurface drainage applications, made from polyolefins or polyesters; with elongation greater than 50 percent.

1. Apparent Opening Size: No. 70 to 100sieve, maximum; ASTM D 4751.

2. Minimum Grab Tensile Strength: 110 lb; ASTM D 4632.

3. Minimum Weight: 4 oz./sq. yd.

Page 30: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02832 - SEGMENTAL RETAINING WALLS

4

J. Subdrainage Pipe: Comply with requirements as designated by wall designer.

K. Soil Reinforcement: Product specifically manufactured for use as soil reinforcement and as designed by wall designer.

2.3 SOURCE QUALITY CONTROL

A. Direct manufacturer to certify each roll of soil reinforcement at the factory meet minimum average roll values for geosynthetic index property tests, including the following:

1. Weight.

2. Roll size.

3. Grab or single-rib strength.

4. Aperture opening.

5. Rib or yarn size.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine areas and conditions, with Installer present, for compliance with requirements for excavation tolerances, condition of subgrades and subsoils, and other conditions affecting performance of segmental retaining walls.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 RETAINING WALL INSTALLATION

A. General: Place units according to NCMA's "Segmental Retaining Wall Installation Guide" and segmental retaining wall unit manufacturer's and wall design engineer’s written instructions.

1. Lay units in running bond.

2. Form corners and ends by using special units or cutting units with motor-driven saw.

B. Leveling Base: Place and compact base material to thickness indicated and with not less than 95 percent maximum dry unit weight according to ASTM D 698.

1. Leveling Course: At Contractor's option, unreinforced lean concrete may be substituted for upper 1 to 2 inches of base. Compact and screed concrete to a smooth, level surface, and “wetset” blocks to assure full bearing of base block.

C. First Course: Place first course of segmental retaining wall units for full length of wall. Place units in firm contact with each other, properly aligned and level.

1. Tamp units into leveling base as necessary to bring tops of units into a level plane.

D. Subsequent Courses: Remove all excess fill and debris from tops of units in course below. Place units in firm contact, properly aligned, and directly on course below.

Page 31: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02832 - SEGMENTAL RETAINING WALLS

5

1. For units with lugs designed to fit into holes in adjacent units, lay units so lugs are accurately aligned with holes, and bedding surfaces are firmly seated on beds of units below.

2. For units with lips at front of units, slide units as far forward as possible for firm contact with lips of units below.

3. For units with lips at bottom rear of units, slide units as far forward as possible for firm contact of lips with units below.

4. For units with pins, install all pins and align units.

5. For units with clips, install all clips and align units.

E. Cap Units: Place cap units and secure with cap adhesive per manufacturer’s guidelines.

3.3 FILL PLACEMENT

A. General: Comply with requirements in Section 02300 Earthwork and NCMA's "Segmental Retaining Wall Installation Guide," and segmental retaining wall unit manufacturer's written instructions.

B. Fill voids between and within units with drainage fill. Place fill as each course of units is laid.

C. Place, spread, and compact drainage fill and soil fill in uniform lifts for full width and length of embankment as wall is laid. Place and compact fills without disturbing alignment of units. Where both sides of wall are indicated to be filled, place fills on both sides at same time. Begin at wall and place and spread fills toward embankment.

1. Compact nonreinforced-soil fill to comply with Section 02300 Earthwork and as per wall design specifications.

D. Place drainage geotextile and drainage fill as per wall design.

E. Place a layer of drainage fill at least 12 inches wide behind wall as shown on wall design. Place a layer of drainage geotextile between drainage fill and soil fill.

F. Place sub-drainage pipe in drainage fill as indicated, sloped not less than 0.5 percent to drain.

G. Place and compact to project specifications impervious fill over top edge of drainage fill layer.

H. Slope grade at top of wall away from wall as per plans. Slope grade at base of wall away from wall. Provide uniform slopes that will prevent ponding.

I. Place soil reinforcement in horizontal joints of retaining wall where indicated on wall design plans and according to soil-reinforcement manufacturer's written instructions. Embed reinforcement a minimum of 8 inches into retaining wall and stretch tight over compacted backfill. Anchor soil reinforcement before placing fill.

1. Place additional soil reinforcement at corners and curved walls to provide continuous reinforcement.

2. Place geosynthetics with seams, if any, oriented perpendicular to segmental retaining walls.

3. Do not dump fill material directly from trucks onto geosynthetics.

4. Place at least 6 inches of fill over reinforcement before compacting with tracked vehicles or 4 inches before compacting with rubber-tired vehicles.

5. Do not turn vehicles on fill until first layer of fill is compacted and second layer is placed over each soil-reinforcement layer.

Page 32: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02832 - SEGMENTAL RETAINING WALLS

6

3.4 CONSTRUCTION TOLERANCES

A. As-built variation from Level: For bed-joint lines along walls, do not exceed 3/4 inches in 10 feet, 1 1/2 inches maximum.

B. Variation from Indicated Batter: For slope of wall face, do not vary from indicated slope by more than 2 degrees.

C. Variation from Indicated Wall Line: For walls indicated as straight, do not vary from straight line by more than 2 inches.

3.5 FIELD QUALITY CONTROL

A. Testing Agency: Engage a qualified testing agency, acceptable to Owner, to perform tests and inspections.

B. Comply with requirements in Section 02300 Earthwork for field quality control and all testing specified in the wall design plans.

1. In each compacted backfill layer, perform at least 1 field in-place compaction test for each 50 feet or less of segmental retaining wall length.

2. In each compacted backfill layer, perform at least 1 field in-place compaction test for each 12 inches of fill depth and each 50 feet or less of segmental retaining wall length.

C. Contractor shall coordinate and obtain approved inspections by municipal inspection agency.

3.6 ADJUSTING

A. Remove and replace segmental retaining wall construction of the following descriptions:

1. Broken, chipped, stained, or otherwise damaged units. Units may be repaired if Owner approves methods and results.

2. Segmental retaining walls that do not match approved Samples and mockups.

3. Segmental retaining walls that do not comply with other requirements indicated.

B. Replace units so segmental retaining wall matches approved Samples and mockups, complies with other requirements, and shows no evidence of replacement.

3.7 WALL PERFORMANCE

A. Wall settlement, rotation, leaning, cracking or gapping shall not exceed the following criteria within a 1 year warranty period;

B. Post-Construction Deflection Criteria

1. Maximum Vertical Total Settlement: 1 inch

2. Maximum Horizontal Ship: ½ inch

3. Maximum Differential Settlement within a 10 ft. length: ½ inch

4. Maximum Wall Batter: 1/6 inch

Page 33: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02832 - SEGMENTAL RETAINING WALLS

7

5. Maximum Cap between units: ½ inch

6. Maximum Crack in Precast Block: ¼” inch

END OF SECTION 02832

Page 34: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02860 – RUBBERIZED PLAY SURFACE 1

SECTION 02860 RUBBERIZED PLAY SURFACE Provide rubberized play surface system (Poured-in-Place) designed and constructed for the following minimum. DESIGN STANDARDS

A. Provide all materials and installation required to construct proposed “Poured-In-Place” or approved equal rubberized play surface package. Surface or approved equal package consists of a special formulation of EPDM and SBR rubber granules and a high-quality polyurethane binder. When used around play equipment or in play areas, recycled rubber strands are combined with the same polyurethane binder. When cured these ingredients provide a cushioned, long lasting wearing surface suitable for use in most athletic and play areas.

B. Attached drawings outline material and configuration of rubberized play surface

area. DESIGN IMPACT CONDITIONS

A. Poured-in-Place rubberized play surface systems shall be designed to meet or exceed the Consumer Product Safety Commission (CPSC) and the National Bureau of Standards.

B. Impact Testing: "Or equal" systems shall provide independent testing for shock

absorbing properties in accordance with ASTM F-1292-91 for 6-foot height. MATERIAL AND CONSTRUCTION MINIMUM REQUIREMENTS

A. All materials furnished by the Contractor shall be of type, quality, color, thickness, and manufacturer as approved by the "Owner’s Representative."

B. Base of min. 4” compacted limestone, and or a 4" poured fiber mesh concrete

provided by "Contractor."

C. Poured-in-place rubberized play surface system shall serve as a minimum standard for performance, durability, ease of installation or repair, and configuration. “Or equal” shall meet or exceed these minimum standards: 1. Primer shall be a single component, moisture cured polyurethane. 2. Binder shall be a proprietary, elastic polyurethane pre-polymer, MDI

based. 3. SBR Black rubber shall be from recycled materials cryogenically

processed and shredded 3/8" granules with less than 4% dust. Depth of SBR shall be not less than 1-7/8".

4. EPDM colored granules of 1mm to 3mm size. Depth shall not be less than 3/8". Contractor shall assist Owner’s Representative in choice of color scheme.

D. Safety surfacing shall hinder vandalism by having a self-sealing property.

Surface resists punctures through its porous construction and the elastic qualities provided by polyurethane binding agents.

Page 35: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02871 – PLAYGROUND EQUIPMENT

1

SECTION 02871 PLAYGROUND EQUIPMENT SUBMITTALS

A. Shop drawings: Layout of structure with dimensions, details, and finishes of components, accessories, and post foundations.

B. Product data: Manufacturer’s catalog cuts indicating material compliance and

specified options. C. Samples: Color selection finishes. If requested, samples of materials. DESIGN STANDARDS

A. Furnish all labor, materials, tools, equipment, necessary incidentals, and supervision required for the installation of playground equipment as herein specified, and as shown on the construction drawings, subject to the requirements of the Project Manual.

B. Work Included:

1. Installation of “Bidder” supplied playground equipment. “Bidder” shall only be responsible for installation of his own equipment.

2. Excavate and pour concrete as required. 3. Backfill, compact, and restore earthwork around concrete footings. 4. Remove excess dirt from excavated area and dispose as required. Provide finish grade. 5. Purchase and on-site delivery of playground equipment.

C. A preliminary layout of the play structure has been depicted which the Contractor shall meet or exceed the requirements as stated on the drawings and in the specifications. Contractor shall submit shop drawings of the final play structure layout for review and approval prior to fabrication, delivery, and installation. GENERAL REQUIREMENTS

A. The construction drawings, specifications, and the project site shall be carefully examined for thorough familiarization with all existing conditions and limitations and their relationship to and effect upon the work included under this section of the specifications. No extra allowance will be made for failure to do so.

PRODUCTS

A. BIG KID AREA – Age Group 5–12-year-olds - Playbooster/Evos – Hybrid Design

#8 by Landscape Structures (OWNER FURNISHED CONTRACTOR TO

INSTALL) Refer to Attachment “A”

B. LITTLE KID AREA – Age Group 2-5-year-olds - Smart Play – Motion Design #3923

(OWNER FURNISHED CONTRACTOR TO INSTALL) Refer to Attachment “B”

C. SWING SET AREA - New 5-Place Single Post Swing Set (2) Belt Seats, (2) ADA

Seats and (1) Friendship Swing by Landscape Structures OR APPROVED

EQUAL

D. MUSIC AREA - (1) Rhapsody Animato Metallophone, (1) Rhapsody Grandioso

Chimes, (1) Rhapsody Vivo Metallophone by Landscape Structures OR

APPROVED EQUAL

Page 36: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02871 – PLAYGROUND EQUIPMENT

2

E. ROCK CLIMBER WITH NETTING - AdventureScapes Design 1 by Landscape

Structures or APPROVED EQUAL

F. COOL MISTER SINGLE POST - by Landscape Structures or APPROVED

EQUAL

G. ZIP LINE AREA - ZipKrooz 50' w/Aluminum Posts by Landscape Structures or

APPROVED EQUAL (ADD ALTERNATE #1)

H. WHEELCHAIR GLIDER – Freedom Glider by Incord Play (OWNER FURNISHED

CONTRACTOR TO INSTALL) Refer to Attachment “C”

I. TURNABOUT – Turnabout Surface Spinner by Little Tikes (OWNER FURNISHED

CONTRACTOR INSTALLED) Refer to Attachment “D”

MATERIALS

A. All play equipment furnished by the “Bidder” shall be of the type, quantity, model, and manufacturer as shown, or an Owner’s Representative approved equal. Equipment shall meet or exceed the following performance standards, dimensions, materials, quality, or quantities: 1. Custom Play Structures

a. Support Posts- Steel or Aluminum tubing with a minimum yield strength of 55,000 psi and tensile strength of 50,000 psi. b. Decks- 80-100 mil plastisol coated perforated 12-gauge flat steel and plain flat steel welded angles. c. Plastic Panels, Slides or other parts- rotationally molded, single or double wall, linear low-density polyethylene, ultraviolet stabilized, resists color fading, with a 2,250 psi at 2 minutes. d. Attachment Fittings- cast of high tensile strength aluminum to comply with ASTM B-179-73, B-72, B-26-72, B-108-73, and QQA-371F, 601D, 596E. e. Finish- after fabrication, shall be free of weld spalls, excess weld, and burrs. Washed in phosphoric acid, fluoridic acid, water rinse and non-chromated rinse with sealer. Oven dried component shall have an electrostatically applied polyester dry powder coating and be oven cured at minimum 350 degrees and tested in accordance to ASTM B-117. f. Hardware- All connecting hardware such as bolts, nuts, set screws, etc. shall be stainless steel.

INSTALLATION: GENERAL

A. Installation shall be done in accordance with the manufacturer’s instructions, construction drawings, and as specified herein. Where the manufacturer’s instructions differ from the construction drawings and specifications, the contractor shall contact the Architect/Engineer/Landscape Architect for clarification prior to proceeding.

B. The location of the play equipment shall be in accordance with the lines and grades

as shown on the “Bidders” construction drawings.

C. Contractor shall stake out location of all play equipment and shall receive Owner’s Representative approval prior to installation.

D. The backfill, compaction, and replacing of the earthwork around the concrete

flatwork shall be done after the concrete has cured and hardened for not less than two days. Concrete Work by “Bidder” shall have strength of not less than 4000 psi @ 28 calendar days.

Page 37: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 02871 – PLAYGROUND EQUIPMENT

3

E. Play equipment supports, braces, and legs on concrete flatwork, shall be mounted

to include not less than four (4) fasteners to concrete, unless otherwise noted.

F. Horizontal members of the play equipment shall be level. Vertical members shall be plumb. All angled supports shall be as specified by manufacturer.

G. Play equipment shall be held firmly in place and out of use until the concrete has

hardened for not less than seven (7) calendar days.

H. Any equipment not installed properly as determined by the Owner’s Representative shall be removed and re-installed at no cost to the Owner’s Representative.

I. Component parts of the play structures to be provided by the Contractor shall be

pre-manufactured and delivered ready for assembly and installation, with only occasional minor modification required. The parts shall be modular and interchangeable for ease of installation and to accommodate future changes.

MAINTENANCE INSTRUCTIONS AND WARRANTY

A. Furnish such special wrenches, spare parts, and other tools and written instructions for proper maintenance of the equipment.

B. The Contractor shall warrant in writing that any defect in the workmanship

discovered and made known to him within one (1) year after acceptance by Owner’s Representative will be made good by him without any additional expense to the Owner’s Representative. A warranty from the manufacturer has already been provided for the play equipment, but the Contractor shall warranty the erection, protecting against damage to the equipment during installation, or the improper installation of equipment.

C. The Contractor shall arrange an inspection and written approval by manufacturer’s

representative for the proper installation of equipment. Project Manager shall be notified before inspection of the exact date and time it is to occur.

Page 38: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

1 SECTION 02900 - LANDSCAPE WORK

SECTION 02900 - LANDSCAPE WORK PART 1 - GENERAL 1.1 SECTION INCLUDES

Landscape work; including planting bed soil mix, plant materials, and maintenance contract. 1.2 QUALITY ASSURANCE

Plant size and quality: All plant material shall be in accordance with the current issue of the American Standard for Nursery Stock published by the American Association of Nurserymen and conform in general to representative species.

1.3 WARRANTY AND MAINTENANCE CONTRACT

Maintenance, Cleanup, and Protection: Maintain plant material immediately after planting and until complete project acceptance by Owner. Maintenance of material shall consist of watering, pruning, cultivation, weeding, repairs, mulching and spraying. Clean work area in an acceptable manner after each day’s operations.

Final Inspection and Acceptance: Warrant all plant material for a minimum of one year. When landscape work is completed, the Owner and or Landscape Architect will, upon request, inspect to determine acceptability. Landscape work may be inspected for acceptance in portions as acceptable to the Owner and or Landscape Architect, provided each portion of work offered for inspection is complete. If inspected landscape work does not comply with requirements, replace rejected work and continue specified maintenance until re-inspected by Owner and or Landscape Architect and found to be acceptable. Remove rejected plants and materials within 1 week from project site. Replace any plant or grass that has died, regardless of reason.

Owner or Landscape Architect reserves the right to reject any material or workmanship deemed not acceptable by the requirements and expectations of this specification. Any deviation of the plans or specifications by the contractor must be submitted prior to execution in a written request to the Landscape Architect for approval.

1.4 REQUIREMENTS

Submit planting schedule showing coordination of planting times between March 1 through June 30 or September 1 through November 30 relating with construction schedule of other trades. Notify Owner and or Landscape Architect for inspection and selection of trees at the job site prior to installation.

1.5 PRE-INSTALLATION MEETINGS

Notify Owner’s Representative a minimum of 48 hours prior to installing phases of the work for in field plant placement verification for no more than a total of two such meetings. Some minor location adjustment may occur.

PART 2 - PRODUCTS 2.1 TOPSOIL

Use on-site supply of topsoil to supplement backfill, finish grading of planting beds. Topsoil to be clean, friable, fertile and natural with 5% organic material minimum. Reuse stockpiled topsoil if acceptable or obtain from a local site.

2.2 SOIL ADMENDMENTS

Planting Soil Amendments shall as specified on plans.

Page 39: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

2 SECTION 02900 - LANDSCAPE WORK

2.3 PLANT MATERIALS Refer to the Drawings.

2.5 MULCH

Shredded Bark/Leaf Mold Mulch: A 50/50 mix of hardwood bark and leaf mold mulch free of growth or germination-inhibiting ingredients. Mulch shall be at least 2-3 inches thick.

2.6 LANDSCAPE WEED BARRIER FABRIC

Filter fabric shall be Contech 4 oz grade or approved equal. Fabric shall be of good condition free of tears, rips or other defects. Install per manufacturers recommendations.

PART 3 - EXECUTION 3.1 PREPARATION

Remove substantial stones, limbs, wire banding, construction debris, and like items. Leave the lot in finished grade condition with finish contours to match approved site plan elevations +/- 0.2 inches, allowing 4 inches for spreading topsoil.

3.2 PLANTING

Planting of Native Perennials: Prepare planting bed by cultivating with specified planting bed soil amendments. Rake and smooth surface and place a 2-3" layer of well-aged, shredded bark/leaf mold mulch for perennials. Fertilize plant bed with 10-10-10 fertilizer applied at 3 lb. per 1000 sq. ft. Install plants as indicated on drawings. Dig holes large enough to allow for spreading of roots and backfill with specified planting bed soil amendment and existing soil mix. Work soil around roots to eliminate air pockets. Water thoroughly after planting, taking care not to cover crowns of plants with wet soils.

3.5 MULCHING

Placing Shredded Bark Mulch: Mulch shall be applied within (1) one day after planting. Mulch shall be free of extraneous material and evenly spread to a depth as specified.

END OF SECTION

Page 40: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 32 18 16

SYNTHETIC GRASS SURFACING SYSTEM – PLAY AREAS 1

SECTION 32 18 16

SYNTHETIC GRASS SURFACING SYSTEM – PLAY AREAS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Division 01 Specification Sections apply to this Section.

1.2 SUMMARY

A. Section includes synthetic grass surfacing for installation as a play area with accessories as

indicated on the Drawings and specified herein.

1.3 SYSTEM DESIGN

A. The synthetic grass surfacing system shall be specifically designed and recommended by

the manufacturer for installation as a play area.

B. The synthetic grass surfacing system shall be constructed to maximize dimensional stability, to

resist damage during normal use, and to minimize UV degradation, including fading.

C. The synthetic grass surfacing system shall be resistant to staining, weather, insects, rot,

mildew, and fungus growth, and shall be non-allergenic and non-toxic.

1.4 ACTION SUBMITTALS

A. Product Data: Submit manufacturer's product data, specifications and installation instructions

for each product specified.

1. Include sources for component materials.

B. Material Certificates: Signed by manufacturer, certifying the materials and system proposed for

the project comply with the specified performance criteria.

C. Shop Drawings: Submit shop drawings that include scaled plans, sections, and large-scale

details showing the installation and attachment of the synthetic grass surfacing system.

1. Include locations of all seams in fabric surfacing.

D. Samples:

1. 18 inch by 18 inch samples showing details of finished installation. Include an example

of a field joined seam between adjacent rolls and outside edge attachment.

1.5 INFORMATIONAL SUBMITTALS

A. Qualifications for Installer.

B. Qualifications for Manufacturer.

C. Maintenance Data: For synthetic grass surfacing system and maintenance equipment, to be

included in maintenance manuals. Include the following:

Page 41: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 32 18 16

SYNTHETIC GRASS SURFACING SYSTEM – PLAY AREAS 2

1. Manufacturer's written instructions manual for routine cleaning, adjustment,

grooming, and other maintenance procedures. Include activities and procedures that

could be detrimental to the synthetic grass surfacing system and should be avoided.

2. Owner's manuals for field grooming and sweeping equipment.

3. Warranty information for field grooming and sweeping equipment.

D. Project Record Drawings: Record actual locations of seams and drains on the Record

drawings.

E. Warranty: 3 signed copies of signed warranty.

1.6 QUALITY ASSURANCE

A. Manufacturer Qualifications: Firm specializing in the manufacturing of synthetic grass

surfacing for a minimum of five years and who has completed work similar in design and

extent to that required for the project, in not less than 15 synthetic grass installations in the last

three years and whose work has resulted in construction with a record of successful in-service

performance.

B. Installer Qualifications: Firm experienced in the installation of synthetic grass installations, who

is certified by the synthetic grass manufacturer to install their materials, who has successfully

installed work similar in design and extent to that required for the project, in not less than 10

projects of similar scope, to the satisfaction of the Architect, in the last three years, who employs

trained workmen that are experienced in the installation of the synthetic grass system proposed

for the project, and whose work has resulted in construction with a record of successful in-service

performance.

C. Single-Source Responsibility: Obtain synthetic grass surfacing system materials, including

drainage mat, adhesives, and seaming materials, from a single manufacturer regularly engaged

in manufacturing the materials.

D. Pre-installation Conference: Prior to the start of the synthetic grass surface system work,

coordinate a conference, to be held at the Site, to review the construction schedule, availability of

materials, installer’s personnel qualifications and experience, equipment and facilities needed to

make progress and avoid delays, installation procedures, testing, inspection, and certification

procedures, and coordination with other work.

1.7 DELIVERY, STORAGE AND HANDLING

A. Deliver materials to the site in original, unopened containers, wrapping, or packaging, with

manufacturer's labels intact, identifying project, material, and production run or lot number for

fabric roll.

B. Immediately following delivery, inspect materials and components for damaged or defective

items, including materials that are not uniform in color, out of tolerance regarding edge alignment

and minimum pile height. Materials that are found to be damaged or defective shall be replaced

at no additional cost to the Owner.

Page 42: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 32 18 16

SYNTHETIC GRASS SURFACING SYSTEM – PLAY AREAS 3

C. Store materials in a secure, dry, well-ventilated location where protected from weather,

exposure to UV, soil, dust, moisture and other contaminants. Store fabric rolls horizontally, on a

flat surface.

D. Handle according to manufacturer's recommendations to prevent damage, deterioration,

distortion, or soiling.

1.8 PROJECT CONDITIONS

A. Environmental Limitations:

1. Do not install synthetic grass surfacing materials when:

a. Substrate surfaces/materials are wet, excessively damp, or have standing

water.

b. Rain is imminent or forecast within 48 hours following proposed time of

installation.

c. Weather conditions, or forecasted conditions, in the opinion of the installer or

manufacturer's representative, will have an adverse effect on the installation.

d. Humidity levels are outside of the limits recommended by adhesive

manufacturer.

2. Install synthetic grass surfacing materials only when:

a. Material surface temperatures, including aggregate base materials, are above

45 degrees F, and anticipated to remain above 45 degrees F for not less than 48

hours following installation.

b. Ambient air temperature is 50 degrees F and rising, but not more than 95

degrees F, and forecast to remain above 50 degrees F for not less than 48 hours

following installation.

1) Ambient air temperatures shall be taken in the shade, away from

artificial heat sources, such as exposed pavement and stone aggregate

fill.

1.9 EXTRA MATERIALS

A. Furnish extra materials described below that match products installed and that are packaged

with protective covering for storage and identified with labels describing contents.

1. Synthetic Grass Surfacing System Fabric: For repairs and/or replacement of areas

displaying excessive wear.

a. 100 sq ft of fabric, 15 ft wide roll.

2. Cleaning Solution: One gallon of industrial-strength cleaning solution, recommended in

writing by fabric manufacturer, and fabric manufacturer's written cleaning instructions.

1.10 WARRANTY

A. Warranty: Submit a written warranty for the synthetic grass surfacing system agreeing to repair

or replace materials and components of the synthetic grass surfacing system that develop defects

in materials or workmanship within the specified warranty period and any other deterioration of

the surfacing system or evidence of failure to meet performance requirements. Defects include

the following:

Page 43: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 32 18 16

SYNTHETIC GRASS SURFACING SYSTEM – PLAY AREAS 4

1. Excessive Fading: Defined as the synthetic grass surfacing system shall remain a

uniform color, without a change in appearance that is perceptible and objectionable, as

determined by the Architect, when viewed visually in comparison with the original

samples.

2. Ultraviolet (UV) and heat degradation.

3. Excessive Wear: Defined as the synthetic grass surfacing system pile height shall not

decrease by more than 10 percent each year, or more than 50 percent within the

specified warranty period beyond that attributable to normal use.

4. Tuft bind loss.

5. Fabric delamination.

6. Loss of backing integrity.

7. Seam and edge raveling.

8. Perimeter attachments.

9. Distortion, either vertically or horizontally, due to dimensional instability.

B. Warranty Period: 15 years from the date of Owner acceptance.

C. The warranty shall include that if the synthetic grass surfacing system is determined to no

longer be serviceable within the specified warranty period, the manufacturer and installer shall, at

no cost to the Owner, remove and replace those areas of the surfacing system not meeting the

specified performance criteria for pile height and impact/shock absorption.

D. The warranty shall not be limited by the amount of use and shall not be prorated.

E. Provide warranty signed by the Contractor, surfacing system manufacturer, and installer.

F. The above warranties are in addition to, and not a limitation of, other rights the Owner may

under the Contract Documents.

PART 2 – PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers and Systems: Subject to compliance with requirements, provide one of the

following:

1. SYNLawn Play Premium, SYNLAWN, 2680 Abutment Road, SE, Dalton, GA 30721.

Phone: (866) 796-5296.

2. Synthetic Play Turf AS APPROVED EQUAL by Owner Representative

2.2 PERFORMANCE REQUIREMENTS

B. The synthetic grass surfacing system shall comply with the following:

1. Linear Density: Not less than 5,040 Denier; ASTM D 1557.

2. Pile Weight: Total pile weight 80 oz/sq yd; ASTM D 5848.

3. Primary Backing Weight: 8 oz/sq yd; ASTM D 5848.

4. Secondary Backing Weight: Average 20 oz/sq yd; ASTM D 5848.

5. Total Weight: 104 oz/sq yd; ASTM D 5848.

6. Tuft Bind: Not less than 8 lbs; ASTM D 1335.

Page 44: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 32 18 16

SYNTHETIC GRASS SURFACING SYSTEM – PLAY AREAS 5

7. Flame Resistance: Pass; ASTM D 2859.

8. Drainage Through Fabric: Not less than 30 inches per hour; ASTM F 1551.

9. Lead Content: Comply with ASTM F 2765 for maximum lead content. Meet all federal

and state heavy metal compliance standards.

C. Provisions for Thermal Movement: The synthetic grass surfacing system, when installed, shall

accommodate expansion and contraction, to a maximum of 1.0 percent, over the average range

of temperature and humidity conditions experienced in Chicago.

D. Uplift Resistance: The synthetic grass surfacing system shall be capable of withstanding wind

loads in cladding wind load test report.

E. Drainage: The synthetic grass surfacing system shall allow for the free movement and

drainage of surface water through the surfacing system.

2.3 SYNTHETIC GRASS FABRIC

A. Yarn: Athletic quality polyethylene parallel-long slit fiber yarn engineered specifically for

outdoor use and stabilized to resist the effects of ultra-violet breakdown, heat, wear, water,

fungus attacks, and airborne pollution.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine area to receive synthetic grass surfacing system, with installer present, for

compliance with manufacturer's requirements and other conditions affecting performance.

1. Verify the finish elevations, slopes, and planarity of the base comply with

requirements of the Project and surfacing system manufacturer.

2. Record findings, prepare a written report, signed by Contractor and installer, and

submit copies of report to the Architect and the Owner.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

Commencement of installation shall indicate acceptance of existing conditions.

3.2 PREPARATION

A. Thoroughly clean the area to receive the synthetic grass system of foreign material and all

other substances and materials that may be detrimental to permeability and/or installation of the

synthetic grass system.

3.3 INSTALLATION

A. General: All work shall be performed by skilled workmen, who are experienced and trained by

the manufacturer in the installation of the synthetic grass system. Work shall be performed in

accordance with the Drawings, reviewed shop drawings, and manufacturer's written installation

instructions.

B. Synthetic grass surfacing fabric rolls shall be unrolled and allowed to relax prior to installation.

Page 45: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 32 18 16

SYNTHETIC GRASS SURFACING SYSTEM – PLAY AREAS 6

C. Fabric Roll Installation:

1. Install perimeter boards as recommended by the surfacing system manufacturer,

including board attachment fasteners.

2. Attach the foam pad to the perimeter boards with glue as recommended by the

surfacing system manufacturer.

3. Synthetic grass surfacing fabric rolls shall be installed across entire width of area,

parallel to long dimension, or as directed by the Architect.

a. Rolls shall extend from edge to edge. Cross seams are not allowed.

b. Rolls shall be rolled out in same direction and installed with uniform pile

direction of fibers.

c. Rolls shall be laid straight and true to line. Adjacent rolls, when laid together,

shall form a tight-fitting seam for the entire length of the fabric. Fitted pieces are

not allowed.

4. Spot glue the surfacing fabric to the foam pad as recommended by the surfacing

system manufacturer.

D. Seaming of Fabric:

1. Seams in the synthetic grass fabric rolls shall be glued together with seaming cloth,

utilizing the manufacturer’s standard seaming procedures and materials, ensuring that

each roll is properly attached to the next.

a. Seams shall be flat, tight, and permanent, with no separation or fraying.

b. Seams, when completed, shall display no visible signs of joining, with fibers

brushed to provide full coverage of fibers over the seam.

3.4 CLEANING AND PROTECTION

A. The installer shall keep the site clean and clear of debris throughout the project. Waste

materials, including excess materials remaining after completion of the Work, shall be removed,

and legally disposed of offsite.

B. Installer shall provide all labor, supplies, and equipment required to completely remove stains

and other blemishes from all finished surfaces.

C. Provide protection over installed synthetic grass surfacing systems, including closing the area

to traffic, as required to ensure installed system will be free of damage at time of Substantial

Completion.

3.5 INSPECTION

A. Inspection: After installation is complete, the synthetic grass surfacing system installer,

synthetic grass surfacing system manufacturer's representative, and Owner Representative shall

inspect the installation. Any corrections shall be noted in a written report and completed prior to

Substantial Completion.

3.6 DEMONSTRATION AND TRAINING

A. Train Owner’s staff regarding maintenance and repair/replacement of the synthetic grass

surfacing system, and maintenance. Training dates and times shall be coordinated by the Owner.

Page 46: WATSON TRAIL PARK PLAYGROUND IMPROVEMENTS GDS …

WATSON TRAIL PARK – PLAYGROUND IMPROVEMENTS GDS PROJECT #020-12

SECTION 32 18 16

SYNTHETIC GRASS SURFACING SYSTEM – PLAY AREAS 7

B. All training shall be completed prior to Substantial Completion of the project.

END OF SECTION