water treatment plant selection by manitoba hydro for … · water quality source and the...
TRANSCRIPT
Manitoba Hydro Case Study January 2018
Water Treatment Plant Selection by Manitoba Hydro for the
Lower Nelson River Stations
Case Study
Dr. Lyle Henson Membrane Specialists
Isaac Deluna Manitoba Hydro
Manitoba Hydro Case Study January 2018
ABSTRACT
The old water treatment systems at the LNRS were not able to meet Manitoba Regulations and
Guidelines for Canadian Drinking Water Quality (GCDWQ) and a decision was made to seek viable
options as a replacement. Manitoba Hydro performed a series of pilots utilizing Microfiltration,
Ultrafiltration and Nanofiltration (Fyne Process) to evaluate the technologies for potential use at these
facilities to meet their potable water needs. In addition to these technologies water hauling was
evaluated as a potential means to meet their needs.
Microfiltration and Ultrafiltration were eliminated as the pilots produced water which did not meet the
Manitoba Regulation and Guidelines for Canadian Drinking Water Quality (GCDWQ). Additionally, both
technologies were shown to require excessive operations and maintenance due to the nature of the raw
water quality source and the pretreatment required with these technologies. The Nanofiltration (Fyne
Process) was successful as it exceeded the GCDWQ and was shown to be an essentially “hands off”
technology in terms of operation.
Nanofiltration (Fyne Process) was then evaluated against water hauling and it was determined it was the
preferred choice due to a higher NPV, no risk of cross contamination, low operator certification
requirement, no supply risk due to weather and the inability of the local municipality to meet current
regulatory requirements.
Manitoba Hydro Case Study January 2018
Water Treatment Systems at the Lower Nelson River Stations (LNRS)
Hydroelectric generating stations are typically remote in nature and operated by a small number of
operation and maintenance personnel. The current population of the Lower Nelson River Stations
(LNRS) fluctuates between 20 to 25 people during the day shift and 2 to 3 people during the night shift.
The population during heavy maintenance periods (spring and fall) have been estimated to be between
25-30 people during the day shift and 15-20 during the night shift.
The original water treatment systems at the LNRS were fed from the station service and cooling water
system carrying Nelson River water from the forebay through the turbine unit main strainer to a
hydropneumatic tank. Historically, prior to entering the hydropneumatic store tank raw water was
dosed with chlorine. From the hydropneumatic store tank, the “treated” water was then distributed
through the generating station.
For years this process was the water treatment system at Limestone Generating Station and Long Spruce
Generating Station for production of potable water. A multimedia filtration system was also in operation
at Kettle Generating Station during this time for potable water production. The old water treatment
systems at the three stations were not able to meet Manitoba Regulation and Guidelines for Canadian
Drinking Water Quality (GCDWQ) and a decision was made to seek viable options as a replacement.
Additionally, consideration for the remote nature of these facilities and the limited availability of
operations personnel had to be considered when choosing the appropriate technology for use.
Water Treatment Alternatives Considered
The water quality data gather by Manitoba Hydro indicates that the Nelson River contains high levels of
turbidity (up to 60 NTU) and dissolved components. Research indicates that turbidity levels at 30 NTU or
higher significantly decrease the effectiveness of chlorination in the treated water, which creates a high-
risk of microbiological contaminants in the drinking water. Surface water (Nelson River Water) typically
contains high levels of dissolved organic matter, and when mixed with chlorine, it creates by-products
such as Trihalomethanes (THMs) and Haloacetic Acids (HAA) which are considered carcinogenic. Typical
analytical results for the Nelson River are shown in Table 1 below.
Various water treatment technologies were considered for the upgrade of the water treatment systems
at the LNRS, with the following four alternatives being the most viable.
• Water Hauling
• Microfiltration System
• Ultra filtration System (UF)
• Nanofiltration System (Tubular Membranes)
Manitoba Hydro Case Study January 2018
Water Hauling
The first option considered was hauling treated water by truck to the generating station. Depending on the water usage at the generating station, water could be delivered as required. There are advantages with this alternative regarding the permitting, operator classification and operation and maintenance requirements. Classification and permitting would only be required for the distribution system (level 1) and minimum chemicals would be required. On the other hand, there are huge disadvantages with this alternative. First, the potential of cross contamination when handling the water from the water plant to the point of use is a serious concern. Second, the cost of transporting water is high considering the purchased/leasing of trucks, maintenance, and garage. Finally, the process is vulnerable to delays in water delivery due to weather conditions,
Table 1 - Lab Results – RAW WATER (SUMMARY)
Sample Date Comments
Parameter Units Mar-27
2014
April-10
2014
May-01
2014
May-21
2014
Jun-11
2014
Jun-13
2014 Pass/fail
Dissolved Organic
Carbon (C)
mg/L 8.12 - 37.0 - - 8.03
Alkalinity (Total as
CaCO3)
mg/L 120 - 112 - - 90.0
Total Organic
Carbon (C)
mg/L 9.08 - 8.55 - - 8.58
pH pH 7.9 8.21 8.12 8.19 19 8.21
Total Inorganic
Carbon (C)
mg/L 28.8 - 28.5 - - 23.6
True Colour TCU 11 14 7 13 - 23
Total Dissolved
Solids
mg/L 192 - 184 - - 174
Turbidity NTU 10 9.7 8.9 9.8 16 18
Total Aluminum
(Al)
μg/L 464 403 414 438 435 547
Total Iron (Fe) μg/L 455 412 404 522 633 722
Total Lead (Pb) μg/L 0.27 0.29 0.24 0.29 0.27 0.31
Total
Trihalomethanes
μg/L <1.0 - 180 - - 450
Total Haloacetic
Acids
μg/L <5.0 - - - - -
THM Formation
Potential
μg/L - - - - - 460
E. coli (QT) MPN/100mL 11 - 0 - - 0
Total Coliforms
(QT)
MPN/100mL 48 - 0 - - 2
Manitoba Hydro Case Study January 2018
truck breakdowns, and truck operator availability. The Town of Gillam is a remote location where the closest city/town is 300 Km away and it is the only source of water when considering this option. Preliminary engineering draft assessment conducted by a consultant indicated that the Town of Gillam water treatment plant could not handle any additional load unless upgrades were made to the water treatment process and infrastructure. In addition, the pressure filters at the Town of Gillam water treatment plant are currently not meeting standards (turbidity).
Micro Filtration
This alternative produces higher levels of water quality than more traditional methods of coagulation and filtration (conventional treatment systems) and will typically meet or exceed current water quality regulations. One of the major drawbacks of this system is that the raw water requires pre-treatment (reduce dissolved organics) prior to being fed to the primary system (microfiltration). If the system is installed without pre-treatment there is a high chance that turbidity and particulate content of the raw water will cause membrane fouling, frequent cleaning cycles, higher operator involvement and increase pathogens. Because of the pre-treatment required, this alternative presented huge disadvantages such as high capital cost, a larger footprint because of the two-stage treatment, associated chemical costs and a higher operator classification level. As part of the Water Treatment Plant (WTP) upgrades at Lower Nelson River Stations a study was conducted at Henday Converter Station to prove the viability of installing a microfiltration water treatment system without pre-treatment. Two water quality tests were performed at Henday and in one of the tests, the treated water showed non-compliance with the Total Trihalomethanes parameter mandated by MR 41/2007. Also, it was determined that DOC removal was poor with this technology. Table 2A below contains the overview of the non-compliant results.
The main disadvantages of the water hauling option are:
• Lower NPV than nanofiltration Fyne Process® system
• No self-sustaining potable water source at each station in case of emergency
• The potential of cross contamination
• Possibility of delays in water delivery due to adverse weather and/or road conditions
• Truck breakdowns
• Truck operator availability
Manitoba Hydro Case Study January 2018
Table 2A – MF Pilot Study at Henday Converter Study Results
Pilot Plant (Ultra Filtration/Hollow Fiber) With this technology raw water is pumped through a coarse filter (50 & 100 micron), then the water coming out of the cartridge filter passes through a ultrafiltration (UF) membrane unit. The product water coming out of the UF membranes is directed to the post UF water storage tank. The Ultrafiltration membranes are back washed periodically to avoid differential pressure increase. A chlorination system is provided for injection into the back wash water entering the UF membranes. The back-wash water coming out of the membranes is collected in a wash water tank and then disposed of slowly. The filtered water is then injected with antiscalant solution for control of scale on the surface of the membranes. A booster pump feeds the water into two housings of Ultrafiltration membranes. While passing through the membranes water divides into three streams – product, reject and recycle water going back to the Ultrafiltration pump.
A pilot plant was installed at Limestone Generating Station in 2016 to determine if this technology was
suitable for use at the LNRS. The pilot plant resulted in the following findings:
• The 50-micron filters constantly plugged up (every second day), requiring operator intervention.
These filters were located downstream from the raw water supply. Note, new filters would need
to be purchased and installed. This negatively impacted the operation and maintenance cost of
the proposed system. Figure 1 and Figure 2 shows the condition of the 100-micron particle
filters plugged and requiring operator intervention.
• The UF system frequently stopped due to high differential pressure at the 50-micron filters. The
pilot plant could not run for more than 1/2 day without operator intervention.
Manitoba Hydro Case Study January 2018
• This technology required the use of antiscalant (chemical product) prior to UF. As water is
produced, this antiscalant need to be replenished which adds another cost to the operation.
This antiscalant has been approved by the Regulator, BUT it still has a negative impact to the
environment.
Figure 1 – Fouled 100 Micron Particulate Filters (UF Pilot Plant at Limestone)
Manitoba Hydro Case Study January 2018
Figure 2 – Fouled 100 Micron Particulate Filters (UF Pilot Plant at Limestone)
Pilot Plant (Nanofiltration/Fyne Process)
A small nanofiltration pilot plant was installed at Limestone Generating Station and Radisson Converter Station in 2014. A small Mini-Fyne Pilot Unit was used for the pilot tests fitted with three full scale 12 ft C10 modules each containing a different membrane to be tested (AFC30, AFC31 & ES404). The pilot plant is shown in the Figure 3 below.
Figure 3 – Fyne Tubular Nanofiltration Membrane Pilot at Limestone LNRS
Manitoba Hydro Case Study January 2018
The semi-permeable Nanofiltration membrane is coated on the inside of the membrane tubes. The membrane tubes are connected by “U”-shaped connectors in a series flow path within each module. Cut-Away photographs of the module follow showing the end connections and internal tube arrangement are shown in Figure 4 below.
Figure 4 – C10 Cutaway View
There is only one inlet and one outlet connection on each module for raw water. A ½” diameter foam ball is fitted in one of the raw water connections on each module. A screened “foam ball catcher” at each end of the flow path keeps the foam ball from leaving the system. During operation, flow reversal causes the foam ball to pass through all the tubes in the module before being caught in the foam ball catcher at the other end of the module providing cleaning of the inside wall of the membrane tube.
A pressurized feed of raw water was supplied to the unit for the pilot. The Mini-Fyne unit has a higher-p r e s s u r e recirculation pump, driven by a variable frequency drive, to provide the correct flow conditions at the membrane surface for process and foam ball clean.
When the unit is filtering, raw water is circulated at pressure by a recirculation pump through the inside of the membrane tubes. Additional raw water is drawn into the recirculation loop. Clean filtered water passes through the membrane tube wall and is collected in the module shroud.
The concentration of organics and other contaminants slowly builds up in the recirculation loop and periodically this water is discharged to waste in a flush cycle. In the flush cycle the recirculation pump was slowed down and the reject by-pass valve was opened. The frequency of opening of the valve controls the recovery (percentage for raw water converted to filtered water).
During the filtration process, the inside walls of the membrane tubes slowly become coated with contaminants from the raw water. To maintain cleanliness of the membrane surface and to discharge the concentrated raw water contained in the recirculation loop, the unit periodically and automatically performed a “foam ball clean”. During the foam ball clean, the direction of the flow of the raw water in the module is reversed. This causes the foam ball to pass through each of the 72 membrane tubes inside the module, cleaning the inside surface of the membrane tube, while at the same time the reject valve opens discharging the concentrated raw water and drawing fresh water into the recirculation loop. The foam ball clean occurred every six flush cycles.
For the pilots the C10 modules were fitted with PCI type AFC30, AFC31 & ES404 membranes. These membranes are manufactured from polyamide (AFC30 & AFC31 75% retention of CaCl2) and
Manitoba Hydro Case Study January 2018
polyethersulphone (ES404 4000 MWCO) material.
The unit is automatically controlled by a programmable relay controller to undergo automated foam ball cleaning cycles on a pre-set frequency. A VFD driven recirculation pump draws water into the recirculation loop and filtrate leaves the system through a permeate flow meters. The recirculation loop water becomes more concentrated over time and is purged to drain each foam ball cycle. The foam ball interval setting controls the operating recovery.
The pilot plant resulted in the following:
• High quality water that exceeds Manitoba Regulation and Guidelines for Canadian Drinking
Water Quality as indicated in Table 2B below
• Low operation and maintenance requirements, essentially “hands off” operation
• No chemical required for treatment
• Chemical cleaning extended to 3-4 months due to mechanical foam ball clean
• Superb color removal as shown in Figure 5 and Figure 6
• Outstanding turbidity removal as shown in Figure 7
• Smaller foot print
• Easy installation
Figure 5 – Raw Water at Radisson Converter Station
Manitoba Hydro Case Study January 2018
Figure 6 – Finished Water at Radisson
Figure 7 – Finished Water Turbidity Results at Limestone
Manitoba Hydro Case Study January 2018
PILOT PLANT @ LIMESTONE G.S - LAB RESULTS SUMMARY
TABLE 2
Lab Results – AFC-30 membrane (SUMMARY)
Sample Date Comments
Parameter Units Mar-27
2014
Apr-10
2014
May-01
2014
May-21
2014
Jun-11
2014
Jun-13
2014
Pass/fail
Dissolved Organic
Carbon (C)
mg/L 0.89 - 0.73 - - 0.68 Pass
Alkalinity (Total as
CaCO3)
mg/L 65 - 75.2 - - 81.9 Pass
Total Organic
Carbon (C)
mg/L <0.50 - 0.54 - - < 0.50 Pass
pH pH 7.7 8.03 8.01 8.15 8.0 8.19 Pass
Total Inorganic
Carbon (C)
mg/L 16.4 - 19.7 - - 19.2 Pass
True Colour TCU 7 < 5 < 5 < 5 < 5 12 Pass
Total Dissolved
Solids
mg/L 104 - 116 - - 106 Pass
Turbidity NTU 0.1 < 0.1 < 0.1 0.1 < 0.1 < 0.1 Pass
Total Aluminum
(Al)
μg/L 4.7 < 3.0 3.4 < 3.0 < 3.0 3.4 Pass
Total Iron (Fe) μg/L < 10 < 10 < 10 < 10 < 10 < 10 Pass
Total Lead (Pb) μg/L < 0.20 < 0.2 < 0.20 < 0.20 < 0.20 < 0.20 Pass
Total
Trihalomethanes
μg/L 16 - 44 - - 29 Pass
Total Haloacetic
Acids
μg/L 6.8 - - - - - Pass
THM Formation
Potential
μg/L _ - - - - 29 Pass
E. coli (QT) MPN/100mL 0 - 0 - - 0 Pass
Total Coliforms
(QT)
MPN/100mL 0 - 0 - - 0 Pass
Manitoba Hydro Case Study January 2018
The results conclusively showed that the AFC30 membrane exceeded the CDWS and would meet the needs of both the Limestone, Long Spruce, Kettle and Radisson facilities. Additionally, the unit proved to be largely hands off and require a minimum amount of manpower to operate. There was only a single clean performed during the pilot and this was prior to start-up at the Radisson facility. As anticipated the pilot confirmed the need to perform a chemical clean every 3 or 4 months due to the efficacy of the foam ball clean. The results of both pilots supported the use of the Fyne process for all of Manitoba Hydro’s Generating Stations and HVDC facilities due to performance, limited manpower requirements and cost.
NPV Evaluation (Water Hauling vs Fyne Nanofiltration Process)
Of the four original choices to be considered only two were considered to be viable options based on
the technology assessments performed. An economic analysis comparing the two viable alternatives
(water hauling vs Fyne Nanofiltration Process®) was performed with the following results:
• Nanofiltration Fyne Process® NPV (-$4.5M) is higher than water hauling NPV (-$6.9M).
• The high capital cost of $2M for water hauling and annual operator cost of $360,000 (2-truck
drivers) makes this option not economically viable.
As a result, the Nanofiltration Fyne Process® was recommended over water hauling. A feasibility study
was developed and performed on the Fyne Nanofiltration system. Below are some of the key findings
from the study:
• Nanofiltration Fyne Process® system provides no-risk of cross-contamination; ensuring the
safety & health of the employees and the public.
• Low environmental impact and minimum operator involvement
• Lab results met Manitoba Regulation and Canadian Drinking Water Quality Guidelines.
• Low System Operator Classification (level II).
A summary of evaluation criteria used for final assessment of the technology can be found in Table 4
below.
Table 4 – Evaluation criteria used for the Fyne Pilot Plant and Final Assessment
Criteria Assessment
• Water quality to meet or exceed Manitoba Regulation
and Guidelines for Canadian Drinking Water Quality
(GCDWQ)
Lab results met Manitoba Regulation and Guidelines for
Canadian Drinking Water Quality.
• Operation and maintenance requirements Low
• Footprint requirements Small footprint required.
• Chemical usage (environment) None (only for membrane cleaning, typically every 3 months).
Low environmental impact
• Installation requirements Minimum. Plug-in type. Pilot plant was installed and
commissioned in 3 days.
• Complexity of the system Low complexity.
• System performance using Nelson River water during
the spring melt and summer months
Very good. Raw water turbidity spikes did not affect the
system performance.
Manitoba Hydro Case Study January 2018
Conclusion
The old water treatment systems at the LNRS were not able to meet Manitoba Regulations and
Guidelines for Canadian Drinking Water Quality (GCDWQ) and a decision was made to seek viable
options as a replacement. Manitoba Hydro performed a series of pilots utilizing Microfiltration,
Ultrafiltration and Nanofiltration (Fyne Process) to evaluate the technologies for potential use at these
facilities to meet their potable water needs. In addition to these technologies water hauling was
evaluated as a potential means to meet their needs.
Microfiltration and Ultrafiltration were eliminated as the pilots produced water which did not meet the
Manitoba Regulation and Guidelines for Canadian Drinking Water Quality (GCDWQ). Additionally, both
technologies were shown to require excessive operations and maintenance due to the nature of the raw
water quality source and the pretreatment required with these technologies. The Nanofiltration (Fyne
Process) was successful as it exceeded the GCDWQ and was shown to be an essentially “hands off”
technology in terms of operation.
Nanofiltration (Fyne Process) was then evaluated against water hauling and it was determined it was the
preferred choice due to a higher NPV, no risk of cross contamination, low operator certification
requirement, no supply risk due to weather and the inability of the local municipality to meet current
regulatory requirements.