water minimization through pinch technology
TRANSCRIPT
-
8/2/2019 Water Minimization Through Pinch Technology
1/59
Water Minimizationthrough Pinch
technology
Ankara, September 13-15 2010
Jose R. AlvarezDepartment of Chemical and Environmental Engineering
UNIVERSITY OF OVIEDO
-
8/2/2019 Water Minimization Through Pinch Technology
2/59
Water Pinch Technology
Systematic technique for analyzing water networks andreducing water costs for processes. Aims to identify andselect the best water re-use, regeneration and effluenttreatment opportunities.
Avoid End-Of-Pipe solutions
May be applied to almost any industrial water systemwhere there are users of fresh water and producers ofwaste water. It can also analyze small systems.
More restrictions = less scope for water savings. Good solutions:
save water reduce capital investment recover valuable raw materials
-
8/2/2019 Water Minimization Through Pinch Technology
3/59
Applicability
The savings achieveddepend greatly on theproject objectives.
Capital cost savingsoften play a major role inthe deliverables of a waterpinch study.
Identifying and deployingthe best water re-usesystems is a challenge.
Industry Water
Reduction
Chemical &Fibers 25 %
Corn processing 25 %
Oil refining 30 %
Chemicals 40 %
Paper mill 20 %
Coal chemicals 50 %
Polymers (batch) 60 %
Military Base 40 %
-
8/2/2019 Water Minimization Through Pinch Technology
4/59
Water Uses in IndustryWaste Water Streams
RAW WATER
TREATMENT
RAW
WATER
FRESH
WATER
BFW
TREATMENT
WASTEWATER
TREATMENT
STEAM
SYSTEM
PROCESS 1
PROCESS 2
PROCESS 3
WASTE
WATER
CONTAMINATED
STORM WATER
Condensate
loss
Boiler blowdown
Cooling tower blowdown
Ion exchange regeneration
Discharge
Steam
-
8/2/2019 Water Minimization Through Pinch Technology
5/59
Principles for Saving Water
Re-use (no concentration changes)
Re-use (with changes to inletconcentration)
Regeneration and re-use
Distributed effluent treatment
-
8/2/2019 Water Minimization Through Pinch Technology
6/59
Re-Use (no concentration changes)
Begin with the assumption that the existingconcentrations are the maximum limits.
This normally identifies a few small re-useopportunities.
To achieve further savings we must challenge theassumptions made for concentration limits.
-
8/2/2019 Water Minimization Through Pinch Technology
7/59
Re-Use (with changes to inletconcentration)
Identify projects where large water savings are possible byincreasing the upper concentration limits to selected sinks.
This will normally identify a few large re-use opportunities.
-
8/2/2019 Water Minimization Through Pinch Technology
8/59
-
8/2/2019 Water Minimization Through Pinch Technology
9/59
Distributed Effluent Treatment(de-centralized effluent treatment systems)
Streams are segregated into categories and treated appropriatelybefore mixing with other streams.
Several small scale treatment units are used that operate onundiluted effluent streams rather than one large unit operating on
very dilute effluent. The resulting system can offer better removal efficiency at reduced
cost.
-
8/2/2019 Water Minimization Through Pinch Technology
10/59
Variants of Water Pinch
Method 1: UMIST
based on contaminant generation
and concentration limitationswhich give limiting profiles and targets
Method 2: LM (Linnhoff March)
based on known available sourcesand known demands
which give targets and water use
-
8/2/2019 Water Minimization Through Pinch Technology
11/59
C
m
CPROC, INCPROC, OUT
CW, OUT
CW, IN
C
m
CPROC, INCPROC, OUT
Water
Profiles
CPROC, IN CPROC, OUT
CW, OUT CW, IN
Process Stream
Water Stream
Mass Transfer
f
fW
C
m
Process(CW, OUT)max
(CW, IN) max
Limiting Water Profile
C
m
Process Limiting Water Profile
Water Supply Lines
-
8/2/2019 Water Minimization Through Pinch Technology
12/59
Concentration vs mass
transported diagram
T
DH
TPROC, INTPROC, OUT
TW, OUT
TW, IN
C
m
CPROC, IN
CPROC, OUT CW, OUT
CW, IN
DT = 1/CP DH DC = 1/Q Dm
-
8/2/2019 Water Minimization Through Pinch Technology
13/59
UMIST approach
Maximum use of water
Maximum water inlet concentration
Maximum water outlet concentration
Restrictions:
Minimum driving force for mass transfer
Solubility limits
Scaling and deposit formation Corrosion limits
Minimum flow to avoid sedimentation ofsuspended solids
-
8/2/2019 Water Minimization Through Pinch Technology
14/59
Example. One contaminant
after R. Smith, UMIST
PROCESS 2
PROCESS 3
PROCESS 4
PROCESS 1C
m
Process
(CW, OUT)max
(CW, IN) max
Limiting Water Profile
-
8/2/2019 Water Minimization Through Pinch Technology
15/59
Example : One contaminant
after R. Smith, UMIST
PROCESS 2
PROCESS 3
PROCESS 4
PROCESS 1C
m
CW, OUT
CW, IN
-
8/2/2019 Water Minimization Through Pinch Technology
16/59
Example: One contaminant
From Wang and Smith, ,-Wastewater Minimization,Chemical Engineering Science, 1994, 49(7):981-1006
ProcessingUnit
CIN, max(ppm)
COUT,max(ppm)
ContaminantGeneration (kg/h)
Limiting WaterFlowrate (t/h)
Process 1 0 100 2 20
Process 2 50 100 5 100
Process 3 50 800 30 40
Process 4 400 800 4 10
Sum: 41 kg/h From C:s
and Gener.
-
8/2/2019 Water Minimization Through Pinch Technology
17/59
Data AnalysisProcessingUnit
CIN, max(ppm)
COUT,max(ppm)
ContaminantGeneration (kg/h)
Limiting WaterFlowrate (t/h)
Process 1 0 100 2 20
Process 2 50 100 5 100
Process 3 50 800 30 40
Process 4 400 800 4 10
FRESH
WATER
112.5 t/h
PROCESS 1
PROCESS 2
PROCESS 3
WASTE
WATER
112.5 t/h
PROCESS 4
20 t/h
50 t/h
37.5 t/h
5 t/h
PROCESS 1
0
100
200
300
400
500
0 2 4 6 8 10
m (kg/h)
C
(ppm)
PROCESS 2
0
100
200
300
400
500
0 2 4 6 8 10
m (kg/h)
C
(ppm)
PROCESS 3
0
200
400
600
800
1000
0 10 20 30
m (kg/h)
C
(ppm)
PROCESS 4
0
200
400
600
800
1000
0 1 2 3 4 5
m (kg/h)
C
(ppm)
Process 1 Process 2
Process 3 Process 4
170 t/h
-
8/2/2019 Water Minimization Through Pinch Technology
18/59
Pinch AnalysisComposite Curves
0
100
200
300
400
500
600
700
800
0 10 20 30 40
m (kg/h)
C
(ppm)
0
100
200
300
400
500
600
700
800
0 10 20 30 40
m (kg/h)
C
(ppm)
0
100
200
300
400
500
600
700
800
0 10 20 30 40
m (kg/h)
ppm)
PINCH
2 5 20 4
-
8/2/2019 Water Minimization Through Pinch Technology
19/59
Pinch AnalysisComposite Curves
Concentration
interval, ppm
Process 1,
kg/h
Process 2,
kg/h
Process 3,
kg/h
Process 4,
kg/h
Total ,
kg/h
Accumulated,
kg/h
0 - 50 1 1 1
50 - 100 1 5 2 8 9
100 - 400 12 12 21
400 - 800 16 4 20 41
Total 2 5 30 4 41
-
8/2/2019 Water Minimization Through Pinch Technology
20/59
Pinch AnalysisComposite Curves
0
100
200
300
400
500
600
700
800
0 10 20 30 40
m (kg/h)
C
(ppm)
0
100
200
300
400
500
600
700
800
0 10 20 30 40
m (kg/h)
C
(ppm)
0
100
200
300
400
500
600
700
800
0 10 20 30 40
m (kg/h)
ppm)
PINCH
2 5 20 4 1 8 12 20
-
8/2/2019 Water Minimization Through Pinch Technology
21/59
Pinch AnalysisComposite Curves
0
100
200
300
400
500
600
700
800
0 10 20 30 40
m (kg/h)
C
(ppm)
1 8 12 20
C
m
(CW, OUT)max
(CW, IN) max
Limiting Water Profile
-
8/2/2019 Water Minimization Through Pinch Technology
22/59
Pinch AnalysisComposite Curves
0
100
200
300
400
500
600
700
800
0 10 20 30 40
m (kg/h)
C
(ppm)
0
100
200
300
400
500
600
700
800
0 10 20 30 40
m (kg/h)
C
(ppm)
0
100
200
300
400
500
600
700
800
0 10 20 30 40
m (kg/h)
ppm)
PINCH
2 5 20 4 1 8 12 20
90 t/h
-
8/2/2019 Water Minimization Through Pinch Technology
23/59
Water distribution
-
8/2/2019 Water Minimization Through Pinch Technology
24/59
Water distribution
90 ton/h0 ppm
P120 ton/h0 ppm
70 ton/h
0 ppm
20 ton/h100 ppm
50 ton/h
0 ppm
20 ton/h0 ppm
P2
2 kg/h
5 kg/h50 ton/h
100 ppm
P320 ton/h
800 ppm
16 kg/h
20 ton/h800 ppm
14 kg/h
45.7 ton/h
800 ppm
5.7 ton/h100 ppm
44.3 ton/h
100 ppm
P4 5.7 ton/h800 ppm
4 kg/h
-
8/2/2019 Water Minimization Through Pinch Technology
25/59
Water distribution
Concentration
interval, ppm
Process 1,
kg/h
Process 2,
kg/h
Process 3,
kg/h
Process 4,
kg/h
Total ,
kg/h
Accumulated,
kg/h
0 - 50 1 (1) 1 1
50 - 100 1 (1) 5 (5) 2 (2) 8 9
100 - 400 12 (6) (6) 12 21
400 - 800 16 (8) (8) 4 (4) 20 41
Total 2 (2) 5 (5) 30(16)(14) 4 (4) 41
-
8/2/2019 Water Minimization Through Pinch Technology
26/59
Example: One contaminant
From Wang and Smith, ,-Wastewater Minimization,Chemical Engineering Science, 1994, 49(7):981-1006
ProcessingUnit
CIN, max(ppm)
COUT,max(ppm)
ContaminantGeneration (kg/h)
Limiting WaterFlowrate (t/h)
Process 1 0 100 2 20
Process 2 50 100 5 100
Process 3 50 800 30 40
Process 4 400 800 4 10
Sum: 41 kg/h From C:s
and Gener.
-
8/2/2019 Water Minimization Through Pinch Technology
27/59
Water distribution
-
8/2/2019 Water Minimization Through Pinch Technology
28/59
One Possible Solution
44.3 t/h
20 t/h
20 t/h 70 t/h
Water
90 t/h
Process 3
Process 4
Process 2
Process 1
-
8/2/2019 Water Minimization Through Pinch Technology
29/59
Possible designs
Choose e.g. from economical considerations
-
8/2/2019 Water Minimization Through Pinch Technology
30/59
Further possibilities: Minimumregeneration and minimum fresh
water use
F h ibili i Mi i
-
8/2/2019 Water Minimization Through Pinch Technology
31/59
Further possibilities: Minimumregeneration and minimum fresh
water use
0
100
200
300
400
500
600
700
800
0 10 20 30 40
m (kg/h)
C
(ppm)
-
8/2/2019 Water Minimization Through Pinch Technology
32/59
-
8/2/2019 Water Minimization Through Pinch Technology
33/59
Regeneration flowrate. At the pinch
Minimum regeneration
Minimum fresh water use
-
8/2/2019 Water Minimization Through Pinch Technology
34/59
Minimum Regeneration
-
8/2/2019 Water Minimization Through Pinch Technology
35/59
Water distribution
46.2ton/h0 ppm
P120 ton/h0 ppm
26.2 ton/h
0 ppm
20 ton/h100 ppm
P2
2 kg/h
2.62 kg/h26.2 ton/h
100 ppm
P3
16.7 kg/h
45.8 ton/h
800 ppm
P4 5.7 ton/h800 ppm
4 kg/h
46.2ton/h100 ppm
46.2ton/h5 ppm
REGENERATION
P225.1 ton/h5 ppm
21.1 ton/h
5 ppm
25.1 ton/h100 ppm
21.1 ton/h800 ppmP3
19 ton/h100 ppm
6.1 ton/h100 ppm
19 ton/h
800 ppm
5.7 ton/h100 ppm
0.4 ton/h
100 ppm
2.38 kg/h
13.3 kg/h
-
8/2/2019 Water Minimization Through Pinch Technology
36/59
Water distribution
Concentration Process 1, Process 2, Process 3, Process 4, Total , Accumulated,
interval, ppm kg/h kg/h kg/h kg/h kg/h kg/h
0 - 50 1 (1) 1 1
50 - 100 1 (1) 5 (2.62) 2 (2) 8 9
(2.38)
100 - 400 12 (6.3) 12 21
(5.7)
400 - 800 16 (8.4) 4 (4) 20 41
(7.6)
Total 2 (2) 5 (2.62) 30 (16.7) 4 (4) 41
(2.38) (13.8)
-
8/2/2019 Water Minimization Through Pinch Technology
37/59
Minimum Regeneration
-
8/2/2019 Water Minimization Through Pinch Technology
38/59
Minimum Fresh water
-
8/2/2019 Water Minimization Through Pinch Technology
39/59
-
8/2/2019 Water Minimization Through Pinch Technology
40/59
Minimum Fresh water
-
8/2/2019 Water Minimization Through Pinch Technology
41/59
Water distribution
P120 ton/h0 ppm
20 ton/h100 ppm
2 kg/h
P3
16.7 kg/h
P4 5.7 ton/h800 ppm
4 kg/h
46.2ton/h100 ppm
73.7 ton/h5 ppmREGENERATION
P2
52.6 ton/h
5 ppm
21.1 ton/h5 ppm
21.1 ton/h
800 ppm
P3
18.9 ton/h
100 ppm
33.7 ton/h100 ppm
18.9 ton/h
800 ppm
5.7 ton/h100 ppm
28 ton/h100 ppm
5 kg/h
13.3 kg/h
52.6 ton/h
100 ppm
REGENERATION
REGENERATION
REGENERATION
-
8/2/2019 Water Minimization Through Pinch Technology
42/59
Water use. Cost optimization
FRESH REGENERATED IMPLICATIONS
90 Ton/h0 Ton/h Minimum fresh water
46.2 Ton/h 46.2 Ton/h Reduce fresh waterReduce wastewater
20 Ton/h 73.7 Ton/h Increase watertreatment
-
8/2/2019 Water Minimization Through Pinch Technology
43/59
Linnhoff March approachBy Linnhoff March (now KBC)
List of available sources
flow rates and contaminant levels
List of demanded flows (sinks) flow rates and contaminant levels
cumulative chart gives pinch and
fresh water needed waste water produced
process flows and improvements
-
8/2/2019 Water Minimization Through Pinch Technology
44/59
Sources, Sinks and UnitOperations
Process. Water flow rates arefixed.
Utility. Water flow rates canbe changed (i.e., city water).May have minimum andmaximum flow limits together
with two cost terms: fixedcost and variable cost.
Sink: The point at which water is consumed.
Source: The point at which a supply of water isavailable.Unit Operation: A piece of equipment or processingunit that acts as both a sink and source for water(takes water in and sends water out).
-
8/2/2019 Water Minimization Through Pinch Technology
45/59
Example: One contaminant
From Wang and Smith, ,-Wastewater Minimization,Chemical Engineering Science, 1994, 49(7):981-1006
SINKS
ProcessingUnit
CIN, max(ppm)
COUT,max(ppm)
ContaminantGeneration (kg/h)
Limiting WaterFlowrate (t/h)
Process 1 0 100 2 20
Process 2 50 100 5 100
Process 3 50 800 30 40
Process 4 400 800 4 10
SOURCES
-
8/2/2019 Water Minimization Through Pinch Technology
46/59
Project Targets
Waste Minimization: Meeting new environmental regulations. Minimizing the cost of fresh material / waste disposal.
Site Expansion. Likely to need additional fresh water and wastewater capacity.
Avoiding new waste treatment or disposal facilities. Overcoming fresh water availability problems. Avoiding high fees for fresh water / waste disposal.
Debottlenecking. Water systems can be a bottleneck for theoverall production process: Cooling tower throughput. Batch vessel washing. Pump capacity.
P1
P2
S1
S2
P3RA
A
RB
B
P1
P2
S1
S2
P3RA
A
RB
B
P1
P2
S1
S2
P3RA
A
RB
B
P1
P2
S1
S2
P3RA
A
RB
B
P1
P2
S1
S2
P3RA
A
RB
B
P1
P2
S1
S2
P3RA
A
RB
BP1
P2
S1
S2
P3
RAA
RB
B
RC
C
P1
P2
S1
S2
P3
RAA
RB
B
RC
C
-
8/2/2019 Water Minimization Through Pinch Technology
47/59
Basic Data Required
Water flows. Key contaminant concentrations. Start with existing
concentration values. For sinks, if you can identify themaximum allowable concentrations, consider these.
Utility costs. For each utility to be considered: cost offresh water, cost of discharge, operating cost ofexisting treatments.
Environmental Limits.
Additional data: Geographical data. Physical location of sources and sinks within the system,
together with capital and operating cost terms based on distance and flow (to getsimpler network designs).
Cost data. Fixed cost and variable cost terms for utility items and connections Treatment and Regeneration specifications: performance characteristics for
the equipment together with cost information.
Bounds for selected variables.
-
8/2/2019 Water Minimization Through Pinch Technology
48/59
Selecting Key Contaminants
A key contaminant is "Any property that prevents the directre-use of a waste water stream.
color, temperature, suspended solids, and others.
often the plant operators have valuable contributions.
How many?
Anywhere between 3 and 15 contaminants simultaneouslyin a study.
Good results by considering only 2-5 contaminants forparticular sub-sections of a study.
Select 1, 2 or 3 contaminants to make the analysis easy(particularly if you are new to this technology). If you havetoo many contaminants defined you may make the analysisdifficult and your data collection will take longer and costmore.
-
8/2/2019 Water Minimization Through Pinch Technology
49/59
Key questions to ask whenselecting contaminants
Will re-use of water containing this contaminant cause aproblem with the process?
If it does not cause a problem, you do not need to consider it.
Can high levels of the contaminant go to waste?
If not, you will need to consider it when looking at the finaleffluent.
Is the contaminant a problem downstream?
Watch out for product quality issues downstream.
Is the contaminant a problem in just one part of the system?
If this is the case, you could exclude it from the selectedcontaminants, and use bounds to prevent reuse of thecontaminated water to that part of the system.
-
8/2/2019 Water Minimization Through Pinch Technology
50/59
Recommended Procedures
Group contaminants into types: Measurements that describegroups of contaminants:
COD (chemical oxygen demand), TOC (total organiccontent)
Suspended solids, Dissolved salts, conductivity.
Organics, Alcohols
and others!
Check existing sources of data: Ideally, the concentrationlevels should not be difficult or expensive to obtain:
Existing material balances
Routine measurements
Previous studies
Laboratory archives
-
8/2/2019 Water Minimization Through Pinch Technology
51/59
Math-Derived Limitations
Contaminants do not react with each other whenstreams are blended. This limits the scope forrepresenting chemical reactions that increase orreduce contaminant load.
Contaminants blend linearly. Whenever two or morestreams are mixed, each contaminant is assumed toobey the standard rules of mass balance (conservationof mass, etc.), without interacting with othercontaminants.
Contaminants have linear units of measure. Non-linear measurements such as pH cannot be easilyrepresented.
-
8/2/2019 Water Minimization Through Pinch Technology
52/59
Identify Sources and Sinks
If you could change either the source or sink connection fora water stream and still make the same quality product,then the source and sink should be included in the analysis.
Select streams that are relevant for the project objectives Steams that contribute significantly to the contaminant load Streams with significant flow rates.
Steam and Condensate. There are two types of steam users toconsider: Steam users that return clean condensate to be re-used are often
excluded Steam users that do not return condensate for re-use are included
Streams to exclude: Aqueous "Process streams" that cannot be changed (example:
product from reactor A to reactor B) Atmospheric losses from cooling towers, vents, etc. Feed, product, or intermediate streams that contain water.
-
8/2/2019 Water Minimization Through Pinch Technology
53/59
Identify Utilities and Costs
Utility: source, sink or unit operation whose water flowrates can be changed during the water pinch analysis.
Typical utilities for a water pinch study include:
Utility Sources Utility Sinks Utility UnitOperations
Town / city water Final effluentdischarge
Filters
Demineralized water Road / rail / shipdisposal
Reverse osmosis
Well water Biological treatment
For each utility you should know realistic costs on aconsistent basis. For new treatment equipment, the costmight also be chosen to reflect the technological risk ofuntried or unproven technologies.
-
8/2/2019 Water Minimization Through Pinch Technology
54/59
Common Unit Operations
Reverse Osmosis
Backwash Filter
Precipitator Dissolved Air Flotation
Air Stripper
Steam Stripper Ion Exchange
Generic Treater
-
8/2/2019 Water Minimization Through Pinch Technology
55/59
Source/demand chart
-
8/2/2019 Water Minimization Through Pinch Technology
56/59
Design and Water Allocation
Graphical methods not always useful
especially if several contaminants
Problem solved with mathematicaloptimization algorithms (MILP-MINLP)
give ultimate optimum?
Commercial programs exist(WaterTargetTM)
-
8/2/2019 Water Minimization Through Pinch Technology
57/59
Optimization approachesMixed-integer Linear/Nonlinear Programming
},}1,0{|{
},,|{
,
0),(..
),(min
aAyyyY
bBxxxxRxxX
YyXx
yxgts
yxfZ
m
ULn
Objective function
Constraints
f(x,y) andg(x,y) linear =>
Branch and Bound Beale (1958), Balas (1962), Dakin (1965)
MILP Cutting planes Gomory (1959), Balas et al (1993)Branch and cut Johnson, Nemhauser & Savelsbergh (2000)
f(x,y) andg(x,y) nonlinear =>
Branch and Bound method
Ravindran and Gupta (1985) Tawarmalani,Sahinidis (2002)
MINLP Generalized Benders Decomposition Geoffrion (1972)Outer-Approximation
Duran & Grossmann (1986), Fletcher & Leyffer (1994)
-
8/2/2019 Water Minimization Through Pinch Technology
58/59
Summary
Water management demanded by:
environmental limits
water availability and price
reduced effluents (amount, concentrations)
energy consumption and price
Some reductions in fresh water consumptioncan be achieved by heuristics and pinchtechnology analysis
Bigger reductions / total closure demandsinternal cleaning
Water allocation and energy demand interactwith each other: analyze simultaneously?.
-
8/2/2019 Water Minimization Through Pinch Technology
59/59
Jose R. Alvarez
Water Managementthrough Pinch
technology
Department of Chemical and Environmental Engineering
UNIVERSITY OF OVIEDO