Audience Bidders
Confidentiality CONFIDENTIAL
Version Conformed
Date 30 November 2017
Wales and Borders Rail Service and
South Wales Metro
Invitation to Submit Final Tender
Volume 9: Core Valley Lines
Infrastructure Management Requirements
Issue Date 30 November 2017
Contents
1. INTRODUCTION 1
2. GENERAL REQUIREMENTS 2
3. RESPONSIBILITIES 7
4. RESOURCING AND EFFICIENCY
IMPROVEMENT 9
5. APPENDIX 9.A – ASSET MANAGEMENT
PLAN 12
6. APPENDIX 9.B – ASSET KNOWLEDGE
MANAGEMENT PLAN 13
7. APPENDIX 9.C – STANDARDS AND
DEROGATIONS MANAGEMENT
ARRANGEMENTS 15
8. APPENDIX 9.D – DISCOVERY PLAN 16
9. APPENDIX 9.E – IM MOBILISATION AND
CVL ASSET TRANSFER PLAN 17
10. APPENDIX 9.F – DAY TO DAY ASSET
MANAGEMENT EXECUTION PLAN 18
11. APPENDIX 9.G CVL ASSET STATEMENT 20
12. APPENDIX 9.H - TABLE OF INDICATIVE
CVL INFRASTRUCTURE MANAGER YEAR
ONE RENEWALS 34
13. APPENDIX 9.I SUMMARY METHOD
STATEMENT REQUIREMENTS FOR EACH
CVL INFRASTRUCTURE MANAGER YEAR
ONE RENEWAL EXAMPLE 38
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 1
1
1. Introduction
1.1 The Infrastructure Manager (“IM”) has a discrete set of responsibilities within
the wider responsibilities of the ODP. In this Volume 9, the term IM is used in
place of ODP, except where reference is being made to responsibilities that
are wider than those simply of the IM.
1.2 In this Volume 9 you are asked to explain:
a) How you will execute these IM responsibilities;
b) How you will discover new information on CVL Assets and
c) Your proposal for IM Mobilisation and CVL Asset Transfer at the
beginning of the ODP Grant Agreement.
1.3 The following table summarises the terminology used for IM responsibilities.
Full definitions of defined terms are in Schedule 3A to the ODP Grant
Agreement
Asset Operational
Management
Train and power control
Performance reporting
Regulatory and legal duties and responsibilities 1
Compliance and standards
Tota
l A
sset
Man
agem
ent
Day to Day
Asset
Management
Fault management
Weather and season related interventions
Inspection: routine and periodic
Maintenance
Asset Knowledge Management
Renewals Excludes renewals that are being undertaken for
CVL Transformation.
Future Enhancements All enhancements other than those delivered by
CVL Transformation
CVL Asset Statement
1.4 The Authority has released a CVL Asset Statement providing information on
the nature, condition and other characteristics of the CVL Assets which the
1 This includes capacity allocation and charging. At bid stage, the level of activity relating to this responsibility throughout
the term of the contract is unknown, therefore you should price for the level of Asset Operational Management effort
that will be needed to develop the capacity allocation and charging regime for access of third party freight operators
operating the services specified in the document ‘170224 - Future Freight on CVL V1.1 for bidders.pdf’. This pricing will
form the basis of any pricing for planning different levels of third party access
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 2
2
ODP will manage. The data, databases and Network Rail systems that
comprise the CVL Asset Statement are defined in Appendix 9.G of this
Volume 9. You should use this information to shape Responses in this Volume
9, referencing data in the CVL Asset Statement as appropriate.
2. General Requirements
Health, Safety and Environmental Management
2.1 You will be required to put in place health and safety management
arrangements to meet your statutory and regulatory obligations. Approval of
the railway safety management arrangements are the responsibility of the
ORR. The Authority seeks confidence that your plans for health and safety
will be mature and approved.
2.2 You will be required to put in place environmental and stakeholder
management arrangements to meet your statutory and regulatory obligations
and also to meet the additional Requirements set out in Schedule 13.3 of the
ODP Grant Agreement.
R9.1 Describe how your health and safety management arrangements will ensure
and exceed compliance with your statutory and regulatory obligations and
how your safety management arrangements will integrate with wider rail and
other industry safety initiatives, such as the Reporting Systems and Protocols
operated by the RSSB.
R9.2 Describe how you will act as a ‘good neighbour’ throughout the ODP Grant
Agreement Term, maintaining a clean environment and minimising
inconvenience for those adjacent to CVL Assets.
Asset Management Approach
2.3 Your Response to Questions R9.3 to R9.9 below should be linked to
resourcing described in Volume 11.
R9.3 Set out your asset management strategy, describing how it will:
a. Efficiently and economically deliver a safe and high-performing railway
within a live operational environment within the annually defined
budgetary ceiling;
b. Use a whole life cost approach in which the condition of CVL Assets
should not be allowed to decline inappropriately nor should premature
renewal occur solely to reduce maintenance;
c. Ensure that capital investment decisions taken for the implementation of
the CVL Transformation works take proper account of the whole asset
management cost consequences; and
d. Allow efficient handback at the end of the ODP Grant Agreement Term of
the CVL Assets in a condition that meets the condition requirements
detailed in the ODP Grant Agreement.
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 3
3
R9.4 Describe how your asset management approach will address the different
characteristics of each of the following classes of asset, describing the
expected balance of maintenance and renewals:
a. Track;
b. Signalling, Control Systems and Passenger Information Systems;
c. Power distribution, electricity and plant;
d. Earthworks;
e. Structures;
f. Buildings and property;
g. Off track;
h. Telecommunications, Overhead Line Equipment (“OLE”);
i. Level crossings; and
j. Other assets.
R9.5 Describe how you will exploit the benefits of vertical integration, taking full
advantage your control of both asset management and rail service delivery, to
improve operational performance and reliability and reduce cost for the
Authority. Your Response should include vehicle/infrastructure interface
management and how you will balance operational/infrastructure investment
decisions.
R9.6 Describe how you will use possessions and blockades for CVL Transformation
works (as described in your Volume 8 Responses) for Total Asset
Management activities (i.e. both Day to Day Asset Management and also
Renewals) to maximise the utilisation of those possessions and blockades.
R9.7 Define what asset condition monitoring systems you will implement, including
remote condition monitoring and other asset data collection systems e.g.
CCTV recording vehicles, and describe how you will use the information they
provide to enable continuous improvement of the asset systems and their
asset management over the ODP Grant Agreement Term.
R9.8 Explain how your spares and special tools strategy, including spares held
directly and relationships with spares suppliers, will avoid delays to asset
replacement that could affect operational railway performance.
R9.9 List all material2 Support Contracts, >£20,000 per annum which you plan to
establish for asset management by asset class, over the ODP Grant Agreement
Term. For each, demonstrate how you will ensure that;
a. each sub-contractor has the appropriate skills and competencies; and
2 Where ‘material’ means substantial
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 4
4
b. that appropriate commercial terms are included in your sub-contractors
to enable you to meet your commitments to the Authority and gain best
value.
Asset Management Plan
2.4 The rolling 5 year Asset Management Plan (AMP) will be renewed annually and
will set out how the IM will meet its asset management obligations.
R9.10 Provide a draft Asset Management Plan as defined in Appendix 9.A of this
Volume 9.
R9.11 Describe how you will proactively engage with the Authority and Independent
Reporter to achieve continuous improvement in best value for the Authority,
balancing capital, revenue and operational elements and working within the
constraints of the Authority’s annual priorities and spending objectives.
R9.12 Describe how you will revise the Asset Management Plan annually to address
the Material Discoveries made since the last Asset Management Plan.
R9.13 Describe how, in the last three years of the ODP Grant Agreement Term, the
AMP will prepare for the smooth transfer for IM responsibilities to a
successor in satisfactory manner and condition as set out in the ODP Grant
Agreement.
R9.14 Set out the process you would go through to amend the AMP to align to a
significant change in the Authority’s spending priorities that results in a
hypothetical 10% cut in annual funding for Total Asset Management.
Risk Based Management Framework
2.5 You will adopt a Risk Based Management Framework for the execution of your
IM responsibilities. An example of good practice in risk based management is
Network Rail’s Business Critical Rules programme.
R9.15 Describe and illustrate with examples, how you will ensure a consistent and
proactive approach so that:
a) Roles, responsibilities and risk controls are transparent;
b) Derogation treatment of non-compliances properly balances consideration
of the local conditions and the applicable standards in order to maintain
safety and avoid unnecessary expenditure and disruption; and
c) There is a clear ‘line of sight’ from risks to the way in which they are
managed.
Asset Knowledge Management
2.6 The Authority requires that you adopt best practice in Asset Knowledge
Management (“AKM”). Schedule 3A of the ODP Grant Agreement sets out
minimum standards for AKM.
R9.16 Provide a draft Asset Knowledge Management Plan (“AKMP”) as set out in
Appendix 9.B of this Volume 9:
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 5
5
2.7 The rolling five-year AKMP will be renewed annually and will set out how the
IM will meet AKM obligations.
2.8 You are expected to use web-based collaborative IT platforms to maintain high
levels of ‘live’ transparency, providing the Authority with real-time access to all
asset data, data systems, decision support tools, the IM’s resources plans, the
standards derogations database and other relevant systems.
R9.17 Summarise key systems, and highlight how your AKMP will enable you to gain,
maintain and use accurate asset information to support economic and efficient
asset management.
Compliance, Standards and Derogation Management
2.9 You will be responsible for developing and implementing a standards and
derogations management process that will form part of the supporting
framework for attainment of your safety case and other regulatory approvals.
This will operate within the principles of your Risk Based Management
Framework to provide a long term framework for safe and efficient asset
management.
R9.18 Set out your standards and derogations management arrangements as
described in Appendix 9.C of this Volume 9.
R9.19 Set out the relationship between your proposed standards derogation
management arrangement and NR/L2/CSG/STP001, Module 04, ‘Managing
variations to Network Rail Standards and Control Documents and Railway
Group Standards’, explaining how the relationship changes during CVL
Transformation.
R9.20 Provide a schedule of the standards you anticipate changing to deliver cost
reductions or to improve the value delivered by the assets, including those
resulting from your CVL Concept Design. Detail the anticipated associated
cost reductions or improvements in the value delivered.
Temporary Operating Restrictions, track access, possessions
and blockades
2.10 The extent of blockades and possessions during CVL Transformation is set out
in your Responses to Volume 8. This section seeks information about the
planning and management of possessions and blockades.
2.11 Applying your Risk Based Management Framework you will be responsible for
identifying, planning, implementing and managing:
a) All possessions and blockades on the CVL; and
b) Any temporary operating restrictions, such as temporary speed
restrictions, needed whilst assets are operating in a state of reduced
capability, to ensure continued safe operation of the CVL whilst minimising
the operational impact on the CVL.
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 6
6
2.12 You will also be responsible for setting up commercial arrangements, and
managing those arrangements, for the safe access of third parties to maintain
and renew third party owned assets on the CVL.
2.13 The Rail Delivery Group’s report ‘Planning and Timing of Engineering Works
on the GB Rail Network’ sets out a number of examples of good practice in
possessions and blockade management.
R9.21 Outline your proposed process for planning and managing track access,
possessions and blockades for the access of the ODP, other parties delivering
the CVL Transformation, Renewals and Future Enhancements, those
maintaining or renewing third party owned assets on CVL land and other
parties that may legitimately require access from time to time such as
emergency services, RAIB, ORR and others with a statutory right to require
emergency access. Your Response should include:
a. How the planning of possessions and blockades will be integrated with
operational forward planning such as timetable alignment and amendment
and detail your proposed classes of possessions and their planning
horizons; and
b. How possessions or blockades will be managed including:
i. Management of route section handover and handback and of an OLE
isolation;
ii. Access management;
iii. Arrangements for control of engineering trains;
iv. Discharge of CDM and Safety file responsibilities;
v. Updating asset knowledge to reflect the changes during the
possession or blockade;
vi. Managing the impact on passengers (refer to Volume 8, Section 4)
and
vii. A description of your balanced approach to providing reasonable
access for the maintenance and renewal of third party owned assets
whilst avoiding disruption to CVL operations.
R9.22 Describe how your approach to possessions and blockade management takes
full advantage of the vertical integration of asset management and rail service
delivery to exceed the efficiency and effectiveness of Network Rail’s
possession and blockade arrangements.
R9.23 Detail your arrangements for managing Temporary and Emergency Operating
Restrictions, including:
a. The Temporary Operating Restrictions you anticipate may be required;
b. How you will effectively communicate restrictions to operational
personnel, including drivers and signallers/train controllers; and
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 7
7
c. Any supporting arrangements that may be required such as trackside
signage.
3. Responsibilities
Discovery
3.1 During the Preliminary Design and Discovery Phase, you will be responsible
for effective review and survey of the CVL Assets and reporting of
Discoveries. Network Rail will be the IM during this period.
3.2 Your Interim Asset Knowledge Management arrangement will be a key
facilitator of the success of the asset discovery process, capturing the
knowledge this provides.
R9.24 Provide a Discovery Plan as described in Appendix 9.D of this Volume 9.
R9.25 Summarise:
a. The key elements of your approach which maximise the Discoveries that
are made in the Preliminary Design and Discovery Phase and enable
effective revision of the Asset Management Plan and other required
responses to Discoveries; and
b. How you will work with Network Rail through this phase, including key
risks and contingency plans if Network Rail dependencies lead to delay or
other issues.
IM Mobilisation and CVL Asset Transfer
3.3 The Preliminary Design and Discovery Phase provides a valuable opportunity
to plan in detail IM Mobilisation and the CVL Asset Transfer. The Authority
expects the ODP to take full advantage of the opportunity so that risks are
minimised and the process is smooth.
3.4 Questions R8.36 and R8.37 cover the statutory approvals and third party
dependencies for IM Mobilisation, CVL Asset Transfer and CVL
Transformation.
R9.26 Provide an Initial IM Mobilisation and CVL Asset Transfer Plan that
demonstrates how you will achieve the required statutory approvals, will
address the third-party dependencies and also provides the detail set out in
Appendix 9.E of this Volume 9. You may cross refer to your Responses to
Questions R8.36 and R8.37.
Asset Operational Management
3.5 As IM, you will be responsible for:
a) Signalling and train control on the CVL, interfacing with Network Rail at
the system boundary; and
b) Operational management of the Train Power Systems on the CVL.
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 8
8
3.6 When setting out your arrangements for signalling and train control systems
and for train power systems you may cross refer to Volume 8 Responses.
R9.27 Set out your arrangements for operational management of railway control
systems immediately after the IM transfer from Network Rail.
R9.28 Set out ‘steady state’ arrangements for operational management of railway
control systems after CVL Transformation, clearly setting out the efficiencies
CVL Transformation will deliver.
R9.29 Describe clearly the ‘steady state’ (after CVL Transformation) interface
between railway control systems in CVL where you are IM and the wider
network which Network Rail will manage, with responsibilities clearly
identified, your reasons for confidence that Network Rail will be willing to
accept these arrangements and contingency plans for delay/issues.
R9.30 Set out key transitional arrangements for railway control systems during CVL
Transformation to provide confidence that transition is achievable as planned.
Include any proposed arrangements and agreements for subcontracting to
Network Rail, and highlight confidence and contingency plans for Network Rail
arrangements.
R9.31 Describe how you will provide signalling and other Asset Operational
Management Duties on a day-to-day basis to support the Rail Service
requirements during maintenance and any major planned refurbishment or
modification periods.
R9.32 Describe your disaster management and recovery arrangements to ensure
that Rail Services can continue to operate in failure scenarios, including:
a. Where the command and control centre is unavailable due to incident;
and
b. Where there is a major power failure.
R9.33 Set out your arrangements for operational management of train power
systems and the interface with DNOs and other sub-contractors.
Day to Day Asset Management
3.7 Day to Day Asset Management comprises the following activities and
responsibilities; fault management, weather and season related interventions,
inspections (routine, periodic and arising) and maintenance. Asset Knowledge
Management, also part of Day to Day Asset Management, is considered
separately in this Volume 9.
R9.34 Provide a Day-to-Day Asset Management Execution Plan as described in
Appendix 9.F.
3.8 You should base your Day-to-Day Asset Management Plan on:
a) The CVL Asset Statement;
b) Other information provided by Network Rail and the Authority during the
procurement; and
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 9
9
c) The Indicative CVL Infrastructure Manager Year One Renewals Volumes
in Appendix 9.H of this Volume 9.
Renewals
3.9 Appendix 9.H sets out indicative CVL Infrastructure Manager Year One
Renewals for which a summary method statement is required.
R9.35 Provide a Summary Method Statement for each of the CVL Infrastructure
Manager Year One Renewals as set out in Appendix 9.I of this Volume 9.
4. Resourcing and Efficiency Improvement
Discovery and IM Transfer Resourcing
R9.36 Summarise the resources you propose to deliver the Discovery Plan and effect
IM Transfer and demonstrate how this is consistent with the relevant financial
model information you have provided in response to Volume 12 and the CVL
Concept Design.
Asset Operational Management Resourcing
4.1 In the Questions below, you should set out your assumptions for the CVL
Transformation works to a level of detail that clearly justifies the decisions you
have made about the approach to Asset Operational Management, and which
provides a basis for adjusting the Asset Operational Management cost, should
the Authority chooses to change any aspect of the CVL Transformation works
from your stated assumptions. If no assumption is stated about an aspect of
the CVL Transformation, it will be assumed that all possible CVL
Transformation solutions can be accommodated by your Asset Operational
Management solution and pricing.
4.2 Resource information you provide below should have a similar level of
granularity as the Day to Day Asset Management schedule, but be structured
to reflect your Asset Operational Management solution, including;
a) The organisational structure that you will adopt, the numbers of personnel
their competencies and CVs for key personnel, noting where these are to
be subcontracted, and using the grade descriptions set out in Appendix
12.B in Volume 12 where not;
b) Responsibilities of Asset Operational Management for example Crowd
Management, Security, CCTV, Fault Management;
c) Working patterns and shift arrangements that dictate the numbers of
personnel;
d) Location of control centers and the effect of this on resourcing; and
e) All other requirements, other than personnel, that are attributable to
Asset Operational Management, such as vehicles.
4.3 In Responses to the Questions following, resourcing should be consistent with
your Volume 11 Responses. Highlight and justify any differences.
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 1
0
10
R9.37 Provide resource information for each year below in respect of Asset
Operational Management duties, for:
a. Each of Infrastructure Manager Years One, Two, Three, Four and Five,
reflecting the completed and under construction CVL Transformation
works (see next full paragraph) in each of those years;
b. Infrastructure Manager Year Six when the CVL Transformation works are
complete.
R9.38 Relate the resourcing for Asset Operational Management duties to the
relevant financial model templates provided in response to Volume 12 for
your Asset Operational Management responsibilities for each of Years One to
Six.
Day to Day Asset Management Resourcing
4.4 You should set out your resourcing assumptions for the CVL Transformation
works to a level of detail that clearly justifies the decisions you have made
about the approach to Day to Day Asset Management, and which provides a
basis for adjusting the Day to Day Asset Management cost, should the
Authority chooses to change any aspect of the CVL Transformation works
from your stated assumptions. If no assumption is stated about an aspect of
the CVL Transformation, it will be assumed that all possible CVL
Transformation solutions can be accommodated by your Day to Day Asset
Management solution and pricing. Resourcing information you provide below
should include:
a) Organisation structure and staff numbers, noting where responsibilities
are to be subcontracted, and where not, referencing the grade
descriptions set out in Appendix 12.B in Volume 12
b) Working patterns and shift arrangements that dictate the numbers of
personnel;
c) Details of plant and equipment, including on track plant
d) Infrastructure Depots and material and plant storage
R9.39 Set out the resources you require to undertake Day to Day Asset
Management, for:
a. Each of IM Years One, two, three, four and five, reflecting the completed
and under construction Transformation works (see next full paragraph) in
each of those years;
b. IM Year Six when the Transformation works are complete.
R9.40 Relate the resourcing for Day to Day Asset Management duties to the
relevant financial model templates provided in response to Volume 12 for
your Day to Day Asset Management responsibilities for each of Years One to
Six.
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 1
1
11
Renewals Resourcing
R9.41 For each of the eight Renewals highlighted in Appendix 9.H set out the
resourcing you require to undertake:
a. The design of renewals to TfW Plan of work Stage C;
b. The implementation management of the Renewals; and
c. Relate this resourcing to the relevant financial model templates provided in
response to Volume 12.
Efficiency Improvement
4.5 By the end of CVL Transformation, the CVL will be a stable system which is
well understood and on which any change is likely to be small and incremental.
In this stable environment, you will be able to apply good operational and asset
management practice to achieve annual efficiency improvements.
4.6 Candidate areas for delivering efficiency improvement include:
a) Continuous Improvement through techniques as ‘lean management’;
a) Improved supply chain management;
b) Adoption of more flexible working practices, including multiskilling;
c) Adoption of new technologies; and
d) Adoption of advancements in best practice.
R9.42 Explain how you will deliver the efficiency improvement commitments for
Asset Operational Management for each of years 7 through to 15 that you
have set out in the financial model templates in response to Volume 12.
R9.43 Explain how you will deliver the cumulative efficiency improvement
commitment for Day to Day Asset Management for each of years 7 through to
15 that you have set out in the financial model templates in response to
Volume 12.
DRAFT – CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 12
5. Appendix 9.A – Asset Management Plan
5.1 This appendix sets out key items which the Authority expects to see in your Draft Asset Management Plan
(AMP).
5.2 Your Asset Management Plan should address years one to five of the CVL Transformation Stage, setting
out all periodic and discrete Total Asset Management activities that the IM will undertake in each year (this
should set out clearly how your CVL works, both completed and under construction, are reflected in each
year’s plan)3. It should:
1. Set out policies for the principal asset classes;
2. Detail the reliability requirements for asset sub-systems;
3. Set out how the sub-system reliability and availability requirements combine to provide the whole
system reliability and availability needed to deliver the operational performance outputs;
4. Set out how decision support tools and analysis of asset trends will help you to meet the Authority’s
Asset Management requirements;
5. Link to Risk Based Management Framework and Asset Knowledge Management Plan, described
elsewhere;
6. How you will scan and assess the emerging technology landscape so if new or improved technology
emerges that can be deployed to deliver a whole life asset management cost savings, this is identified
and considered as part of Asset Management Planning process;
7. Set out your IM Acceptance process for new infrastructure delivered by CVL Transformation,
Renewal and other Enhancements; and
8. Set out how the effects of the introduction of the new Train Fleet on the existing assets will be
planned for, monitored and understood; so that strategies to manage these affects can be developed
in a proactive timely way.
3 Should you be unable to give the same level detail for years two to five as you have provided for year one, the level
should still be of sufficient detail for pricing.
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 13
6. Appendix 9.B – Asset Knowledge Management Plan
6.1 This appendix sets out key items which the Authority expects to see in your Draft AKMP. It should
include:
1. Your Interim Asset Knowledge Plan setting out how you will manage Asset Knowledge during the
Discovery Stage;
2. Arrangements for the control and management of the asset data, stating for each key class of data
whether it will be:
a. Retained and managed in whole or in large part by Network Rail;
b. A full migration into the IM’s own systems; or
c. A combination of retention and management of some data by Network Rail with the remaining
data to be migrated to, and managed in, the IM’s own systems.
3. Description of systems which you will implement to hold asset knowledge, and the decision support
applications that will utilise the data:
a. Explaining how they will support economic and efficient asset management;
b. Setting out the suppliers and anticipated hosting/maintenance arrangements;
4. Description of summary processes to ensure that asset data is maintained intact, complete and
current throughout the life of the ODP Grant Agreement, including:
a. Summary arrangements for secure and successful migration of any data that is to transferred
from Network Rail’s systems to the IM’s systems;
b. Summary arrangements for system and data security that comply with the principles set out in
the ISO/IEC 27000 standards series;
c. The data architecture solution, including systems into which each data set that is to be migrated,
will be migrated;
d. Metadata and data dictionary management arrangements;
e. How data duplication will be avoided where practical and where it does exist how it will be
rigorously managed to avoid deterioration in asset quality and ambiguity of asset currency;
f. The use of all Total Asset Management, CVL Transformation and Future Enhancement
transactions (inspection observation or change through fault response, maintenance, renewal and
enhancement) to maintain and improve the currency of the data; and
g. The arrangements that will ensure transfer of the data back to the Authority’s own system, or
the successor IM’s system, in a way that the data remains intact and complete.
5. How the Bidder will make good Asset Knowledge Management a core part of its IM culture, its wider
ODP culture and the culture of the IDPs;
6. How the IM will ensure that new innovations in asset data management will be adopted over the life
of the ODP Grant Agreement to improve efficiency and effectiveness of asset data management and
asset management;
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 14
7. A description of how it will allow the Authority real-time access to all the IM’s asset data and data
systems and platforms;
8. A description of how AKM will play a part in, and support, the maintenance of contemporaneous
records to support:
a. The management of change resulting from Discoveries;
b. Agreement of such change and all other contractual matters with the Authority and the
Independent Reporter.
9. Details of the annual reporting arrangements for data accuracy and system reliability using the grading
systems set out on page 290 to 293 of Network Rail’s 2016 Annual Return4.
4 Available here: https://www.networkrail.co.uk/wp-content/uploads/2016/11/Network-Rail-Infrastructure-Limited_Annual-
Return-2016.pdf
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 15
7. Appendix 9.C – Standards and derogations management arrangements
7.1 This appendix sets out key items which the Authority expects to see in your standards and derogations
arrangements. You should summarise:
1. A high level programme plan to set up compliance, standards and derogations management
arrangements;
2. Your proposed engineering authorities for each core asset category and supporting evidence for their
selection;
3. The process for considering changes to standards;
4. The process for issuing and controlling agreed standards;
5. The process for considering, agreeing, managing mitigation and communicating a derogation to a
standard; and
6. The process for transferring existing Network Rail derogations, actual or implied, to your
management and control.
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 16
8. Appendix 9.D – Discovery Plan
8.1 Describe discovery activities you will undertake during the Preliminary Design and Discovery Phase such
as:
1. A desk top analysis of the CVL Asset Statement;
a. Inspections and walkthroughs;
b. Non-intrusive surveys;
c. Intrusive surveys; and
d. Analysis of Network Rail’s asset knowledge management and wider asset management systems.
e. Provide a high level programme plan (Gantt chart) showing key elements of implementation of
your Discovery activities;
2. Explain how you will apply your derogations process to Material Discoveries and to existing Network
Rail derogations, actual or implied;
3. Explain how you will develop, maintain and communicate to the Authority; an assessment of the
cumulative impact of Discoveries, including derogations, Temporary Operational Restrictions, changes
to Day to Day Asset Management activities and changes to the identified Renewals;
4. Set out the support needed from on Network Rail to enable you to undertake these activities, how
you will procure this support from Network Rail and contingency plans for delay/non co-operation.
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 17
9. Appendix 9.E – IM Mobilisation and CVL Asset Transfer Plan
9.1 This appendix sets out key items which the Authority expects to see in your IM Mobilisation and CVL
Asset Transfer Plan:
1. Key milestones
2. Activities of both the ODP and other parties to the process
3. Assumptions made about durations for both activities and approvals by others and explain why those
assumptions are considered to be reasonable
4. Authority Dependencies
5. Other Third Party Dependencies
6. Key IT activities
7. HR, TUPE and IR activities and milestones
8. Dependencies on other Preliminary Design and Discovery Phase activities such as Asset
Characteristic discovery activities and derogation development
9. Other activities that the Bidder considers key to the successful delivery of their Solution.
10. Network Rail issues including;
a. Agreements
b. Plant and materials transfer; and
c. TUPE, IR and other personnel matter
11. Regulatory approvals
12. Stakeholder management plan
13. Safety and Risk Management Transition
14. Proposals for progress reporting
9.2 Include your ODP CVL Asset Assumptions. These are to be provided as a separate annexed document
to the Draft Asset Management Plan. The annexed document will not count as part of the page limit
guidance for the Draft Asset Management Plan.
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 18
10. Appendix 9.F – Day to Day Asset Management Execution Plan
10.1 This appendix sets out key items that the Authority expects to see in your Day to Day Asset Management
Execution Plan for years one to six inclusive.
1. You are to develop this plan on the basis of the following assumptions:
a. The CVL asset system and its Asset characteristics, including age and condition, being as defined
by the combination of:
i. The CVL Asset Statement (CAS); and
ii. Additional information to that given in the CAS, which has been provided by Network Rail
and the Authority in the dialogue and bid periods.
b. The year one Known Renewals should be assumed for year one; and
c. A volume of renewals equal to the volume of year one Known Renewals, should be assumed for
subsequent years for pricing ITSFT Day to Day Asset Management Planning purposes;
2. Each year’s execution plan is to reflect the then:
a. CVL system configuration, which changes through the CVL Transformation stage;
b. CVL operational arrangements, which change through the CVL Transformation stage; and
c. IM arrangements which your Solution may change during CVL Transformation.
3. Fault Management including:
a. Integration of fault management with Asset Operational Management and Rail Services Delivery
Management
b. Arrangements for clear and timely fault reporting by both IM and wider ODP personnel
c. Protocols for prioritisation of fault response
d. Fault response team structure and management, including arrangements for
i. Location of personnel, travel arrangement and track access arrangements to facilitate rapid
response
ii. Spares arrangements – strategic spares carried by teams and access to centrally stored
spares
iii. Response to different asset classes
e. Management of faults in systems provided by others, for example NR telecoms
f. How your management of faults will ensure compliance with the asset knowledge capture
requirements of your Asset Knowledge Management Plan
g. How you will continuously improve fault management and reduce disruptive faults
4. Weather and season related interventions to manage the impact of:
a. Snow, ice and extreme cold
b. Extreme heat
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 19
c. Flooding
d. High wind
e. Leaf fall
5. Management of routine and periodic inspections including:
a. Inspection schedules for each asset class; noting
i. Any key standards and anticipated asset supplier’s that influence these schedules
ii. Any proposed variations (additions or reductions) to the above to improve efficiency
b. Inspection team structure and management;
c. How your management of routine and periodic inspections will ensure compliance with the asset
knowledge capture requirements of your Asset Knowledge Management Plan.
6. Management of Maintenance (the delineation of Maintenance and Renewals is defined in Annex 7 of
Schedule 3A of the ODP Grant Agreement including:
a. Schedule of planned Maintenance by asset class and geographical area
b. Commentary
c. Maintenance team structure and management;
d. How your management of Maintenance will ensure compliance with the asset knowledge capture
requirements of your Asset Knowledge Management Plan.
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 20
11. Appendix 9.G CVL Asset Statement
11.1 This appendix sets out the data that comprises the CVL Asset Statement. Volumes 1 and 9 set out how
this data is to be treated as a basis for the development of your Final Tender.
11.2 For the avoidance of doubt, should any other asset data in the ITSFT contradict the data set out in this
appendix, the data set out in this appendix shall take priority because it is the most up to date. If you have
any questions regarding data integrity you should submit a RFC to the Authority.
11.3 Access to the following data repositories is provided via access to live Network Rail systems
1. Linear Asset Decision Support (LADS), via the Network Rail laptop and Network Connect login that
has been issued to you;
2. Civil Asset Register and Reporting System (CARRS), via the browser based login with which you have
been provided;
3. GEO RINM for network survey and ‘network model’, via the Network Rail laptop and Network
Intranet login that has been issued to you; and
4. the 065 database, via the browser based login with which you have been provided
11.4 The data contained within the above live LADS, CARRS and 065 systems shall take priority over any
information contained within any other part of the asset statement. Where there is an inconsistency or
discrepancy between any data contained within the LADS, CARRS and 065 systems and any data forming
any other part of the asset statement, the data derived from the LADS, CARRS and 065 systems shall take
precedence.
11.5 The data contained within any part of CVL Asset Statement excluding the GEO RINM system shall take
priority over any information contained within the GEO RINM system.
11.6 For clarity, a discrepancy between the LADS, CARRS and 065 systems and any other part of the CVL
Asset Statement will not be a valid basis for a Discovery. If you have any questions regarding data integrity
you should submit a RFC to the Authority.
11.7 Except for the information provided in the live Network Rail systems noted above, all data repositories,
data sets or databases have been loaded onto the Award System.
11.8 The following tables:
1. Are organised by asset class;
2. State the name of each data repository, data set or database;
3. State whether the data repository, data set or database is in Award or is in one of the four data
repositories noted in paragraph 11.3 of this appendix and in the case of the former where in Award it
is located; and
4. Provide a brief description of the data in data repository, data set or database
11.9 The Authority may provide additional data, to the data provided on issue of the ITSFT in the repositories,
data sets or databases in Award, during the tender period in response to RFCs where it is available.
11.10 Except for additional information provided in accordance with the previous paragraph, all data in Award
will be frozen on the date of issue of the ITSFT.
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 21
11.11 The arrangements for treating the data in the live Network Rail data repository LADS is:
1. Access to the LADs will be provided for the full tender period;
2. The data in the LADS will be treated as frozen on the day of the 8-week anniversary of the issue of
the ITSFT and any data added after this day:
a. cannot be used as a basis for the preparation of your tender; and
b. may be treated as the basis for a Material Discovery.
3. On the day of the 8-week anniversary of the issue of the ITSFT, the Authority will have a PDF copy
printed of all CVL information in LADS;
4. The Authority will issue the record noted in the previous paragraph to Bidders no later than the day
of the 10-week anniversary of the issue of the ITSFT;
11.12 The arrangements for treating the data in the live Network Rail data repository CARRS is
1. Access to the CARRS database will be provided for the full tender period;
2. The data in the CARRS database will be treated as frozen on the day of the 8-week anniversary of the
issue of the ITSFT and any data added after this day:
a. cannot be used as a basis for the preparation of your tender; and
b. may be treated as the basis for a Material Discovery.
3. On the day of the 8-week anniversary of the issue of the ITSFT, the Authority will record the date of
the last minor and major inspection reports and any information on additional inspections or
comments for each of the structures on the Core Valley Lines in CARRS;
4. The Authority will issue the record noted in the previous paragraph to Bidders no later than the day
of the 10-week anniversary of the issue of the ITSFT.
11.13 The arrangements for treating the data in the live Network Rail data repository 065 is:
1. Access to the 065 database will be provided for the full tender period;
2. The data in the 065 database will be treated as frozen on the day of the 8-week anniversary of the
issue of the ITSFT and any data added after this day
a. cannot be used as a basis for the preparation of your tender; and
b. may be treated as the basis for a Material Discovery
3. On the day of the 8-week anniversary of the issue of the ITSFT, the authority will download a
spreadsheet from the 065-database recording the date of all the Earthworks Inspections, Flood
Warnings and Reports, Historic Unfinished Inspections and Recommendations in the 065 database on
that day;
4. The Authority will issue the record noted in the previous paragraph to Bidders no later than the day
of the 10-week anniversary of the issue of the ITSFT;
11.14 The arrangements for treating the data in the live GEO-RINM application is:
1. Access to the GEO-RINM application will be provided for the full tender period;
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 22
2. The nature of GEO-RINM application precludes date freezing of the information it provides;
3. GEO-RINM is provided to assist in the interpretation of data provided in the other CVL Asset
Statement systems and no reliance should be made on data in GEO-RINM unless confirmed by the
Authority as being allowing through a RFC.
4. If, because of referring to GEO-RINM, you have any questions regarding data integrity in other
systems you should submit a RFC to the Authority.
Structures
Tunnels
TfW Ref Name Location (in data room)
File Name Description
T1 CARRS Network Rail Structures
Dashboard
Master Network Rail
Database showing structures
location and inspections
T2 [redacted] [redacted] [redected]
T3 Structures Minor
Works
(7.001)
7.001 Structures Minor
Works.xlsx
Database showing minor
works carried out to
structures
T4 Structures PPM
Works
(7.001)
7.001 Structures PPM
Works.xlsx
Database showing work
carried out by the PPM Team
T5 Structures Cardiff
Valleys Data
(14.001)
Structures Cardiff Valleys
Data.xls
Contains the location of
structures along the Core
Valleys Route.
Bridges
TfW Ref Name Location (in data room)
File Name Description
B1 CARRS Network Rail Structures
Dashboard
Master Network Rail
Database showing structures
location and inspections
B2 MA1 4 CAM
(17.006)
17.006 - MA1_4_CAM-02206T-
DK1_Redacted.pdf
Level 0 Inspection for Bridge
at CAM 22.0148
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 23
TfW Ref Name Location (in data room)
File Name Description
B3 MS1 ST3 (including
bridge strikes)
(17.006)
17.006 - MS1 ST3 (Inc Bridge
Strikes) UPDATED.xlsx
Incident database including
structure failure and bridge
strikes
B4 Reduced Interval
Inspections
(17.006)
17.006 - Reduced Interval
Examinations.xlsx
Databases showing
structures that are on a
reduced interval inspection
regime
B5 ST4 Scour 17.006
17.006 - ST4 - Scour.xlsx
Database of structures
considered to be at risk of
scour
B6 THT 01233 Asset Calcs
(17.006)
17.006 - THT 02133½ Asst
Calcs 19890806 001.pdf
17.006 - THT 02133½ Asst
Calcs 19890806 002.pdf
17.006 - THT 02133½ Asst
Notes 19960000 001.pdf
Inspection reports for Bridge
at THT 21.331/2
B7 UMB15 THT 02207
(17.006)
17.006 - UBM1_5_THT-
02207H-DK1-
REV2_Redacted.pdf
Level 0 Inspection for Bridge
at THT 22.0165
B8
UMB2 0 THT 02111
(17.006)
17.006 - UBM1_5_THT-02309-
DK1.REV4 TL1 Apr 2016.pdf
17.006 - UBM1_5_THT-02309-
DK1.REV4.pdf
17.006 - UBM2_0_THT-
02111T-DK2 -
Outputs_Redacted.pdf
Inspection Report for Bridge
at THT 21.0259
B9 ST5 LONG TIMBERS
(17.006)
17.006 - ST5 - LONG
TIMBERS.xlsx
List of long timber bridges
B10 Structures Cardiff
Valleys Data
(14.001)
Structures Cardiff Valleys
Data.xls
Contains the location of
structures along the Core
Valleys Route.
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 24
TfW Ref Name Location (in data room)
File Name Description
B11
Structures Minor
Works
(7.001)
7.001 Structures Minor
Works.xlsx
Database showing minor
works carried out to
structures
B12 Structures PPM Works
(7.001)
7.001 Structures PPM
Works.xlsx
Database showing work
carried out by the PPM
Team
B13 [redacted] [redacted] [redacted]
B14 [redacted] [redacted] [redacted]
B15 [redacted] [redacted] [redacted]
B16 [redacted] [redacted] [redacted]
B17 Off Track Asset
Download Ellipse
14.001
Off Track Asset Download
Ellipse.xls
Download from the
Network Rail Ellipse
database showing low value
off track structures assets
including any inspections or
maintenance.
B18 Structures – Wales
17.003
17.003 - Structures - Wales (10)
_redacted.pdf
Engineering Verification
Report on Structures
Buildings
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 25
TfW Ref Name Location (in data room)
File Name Description
BD1 CARRS Network Rail Structures
Dashboard
Master Network Rail
Database showing structures
location and inspections
BD2 Buildings Minor
Works Altrium
(7.001)
7.001 Buildings Minor Works
Atrium (reactive).xlsx
Spreadsheet showing minor
works instances for
Network Rail buildings
BD3 Buildings Property
Examinations
(7.001)
7.001 Buildings Property
Examinations.xlsx
Spreadsheet showing
stations along the route and
station cost codes.
BD4 Building Asset List
(14.001)
Buildings asset list.xls
A database showing the
buildings associated with the
Core Valleys Route.
Minor structures
TfW Ref Name Location (in data room)
File Name Description
MS1 CARRS Network Rail Structures
Dashboard
Master Network Rail Database
showing structures location
and inspections
MS2 Structures Minor
Works
(7.001)
7.001 Structures Minor
Works.xlsx
Database showing minor works
carried out to structures
MS3 Structures PPM
Works
(7.001)
7.001 Structures PPM
Works.xlsx
Database showing work carried
out by the PPM Team
MS4 Structures Cardiff
Valleys Data
(14.001)
Structures Cardiff Valleys
Data.xls
Contains the location of
structures along the Core
Valleys Route.
MS5 MS1 ST3 (including
bridge strikes)
(17.006)
17.006 - MS1 ST3 (Inc Bridge
Strikes) UPDATED.xlsx
Incident database including
structure failure and bridge
strikes
MS6 Reduced Interval
Inspections
(17.006)
17.006 - Reduced Interval
Examinations.xlsx
Databases showing structures
that are on a reduced interval
inspection regime
MS7 Structures – Wales
(17.003)
17.003 - Structures - Wales
(10)_redacted.pdf
Engineering Verification Report
on Structures
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 26
Track
TfW Ref Name Location (in data room)
File Name Description
T1 LADS (Linear Asset Data
Store)
Access provided via
Network Rail Laptop
LADS provides a rich data
on track age, condition and
defects.
T2 Metro Track Quality
(2.001)
2.001 - Metro Track
Quality.xlsx
A database showing WT35,
AL35, MT70 and AL70 data
T3 Steel Sleepers
(2.001)
Steel Sleepers- Metro Track
Assets Detailed Age of Road
April 2016.xlsx
A database showing the
location of Steel Sleepers
T4 Ellipse
(All asset types inc track)
(9.019)
9.019 CVL Ellipse data
cut.xlsx
Ellipse Data.zip
An asset database used to
raise and record
maintenance work
T5 GEOGIS
(9.030)
9.030 - GEOGIS Age of
Road Track Asset Wales
April 2017.xlsx
A database used to record
Network Rail Assets
T6 Age of Road
(14.001)
Detailed Age of Road April
2016.xlsx
A database showing the age
and specification of track
along the route
T7 Rail Defects Database
(17.008)
17.008 - TfW request
Defects and Breaks Cardiff
Valleys.xlsx
A database showing
recorded rail defects
T8 Broken Rails Register
(17.008)
17.008 - TfW request
Defects and Breaks Cardiff
Valleys.xlsx
A cut from the rail defect
management system showing
the location and status of
broken rails
T9 Broken Rail Incident
Reports (x5)
[redacted]
[redacted]
T10 Email
17.008 - T4&T9 -
BACKGOUND E-
MAIL.docx
Background email
concerning the provision of
broken rail information.
T11 Level 2 Exceedances
(17.008)
17.008 - Level 2
Exceedences.xlsx
A database showing
instances of Level 2
Exceedance
T12 Sidewear Records (17.008) Records of rail side wear
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 27
17.008 - Sidewear
Records.zip
T13 Switches and Crossing
Drawings
(17.008)
17.008 - Switches and
Crossing Drawings.zip
Digital drawings of switches
and crossings across the
route, where available.
Level Crossings
TfW Ref Name
Location (in
data room)
File Name
Description
LC1
Level Crossings Risk Detailed
Report
(9.003)
9.003 - Level
Crossings Risk
Details Report
22_05_17.xls
Spreadsheet showing all level
crossings across the Wales Route
with individual risk and collective
risk assessment grading
LC2 Level Crossing Strategy
(9.003)
9.003 Level
Crossings
strategy and
plans.zip
Contains three documents;
1, Planned Level Crossing closures
in CP5 (N.B. None of these are
within the CVL)
2, Network Rail Level Crossing risk
policy
3, Network Rail policy on reducing
risks at Level Crossings
LC3 List of all Level Crossings
(14.001)
List of Level
Crossings.xlsx
Contains a list of all the Level
Crossings on the Core Valley Lines
LC4 Level Crossing Risk
Assessments (17.002)
This folder contains all the detailed
assessments provided by Network
Rail (see note above)
Earthworks
TfW
Ref Name
Location (in data room)
File Name Description
E1 Specification for Invasive
Species Clearance
(2.001)
CAR-1103-B - TO011 -
Specification for Invasive Species
Clearance.pdf
Study conducted by Mott
MacDonald in 2016
concerning or otherwise
regulated species of plant
along the route
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 28
E2 Earthworks Breakdown (14.001)
Earthworks Breakdown.xlsx
A database showing location,
inspection status and risk
rating of earthworks
E3 065 Database (x10)
Not used as now accessible via
E4.
Record version accessible on
Award is not to be used.
Not used as now accessible
via E4.
Record version accessible on
Award is not to be used.
E4 065 Database Logins provided to an online
based read-only version
Earthworks Examination
Database
E5 WERM2 (17.009)
All content of folder
Water Concentration
Database
E6 GEO-RINM Access provided via Network Rail
Laptop
Aerial Survey viewer with
Utilities and Boundaries
information
Signalling
Signalling Design
TfW
Ref Name
Location (in data room)
File Name Description
SD1 [redacted] [redacted] [redacted]
SD2 [redacted] [redacted] [redacted]
SD3 [redacted] [redacted] [redacted]
SD4 [redacted] [redacted] [redacted]
SD5 [redacted] [redacted] [redacted]
SD6 [redacted] [redacted] [redacted]
SD7 [redacted] [redacted] [redacted]
SD8 [redacted] [redacted] [redacted]
SD9 [redacted] [redacted] [redacted]
SD10 [redacted] [redacted] [redacted]
SD11 [redacted] [redacted] [redacted]
SD12 [redacted] [redacted] [redacted]
Signalling Condition and Maintenance
TfW
Ref
Name Location (in data room)
File Name
Description
SC1 CVL Ellipse Data (all asset
types)
(9.019)
9.019 CVL Ellipse data cut.xlsx
Ellipse Data.zip
Ellipse is the master asset
database for Network Rail for
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 29
storing and raising maintenance
reports
SC2 CVL SMTH INFO
(2015,2016,2017)
(9.037)
9.037 Cardiff Valleys SMTH
info 2015.xlsx
9.037 Cardiff Valleys SMTH
info 2016.xlsx
9.037 Cardiff Valleys SMTH
info 2017.xlsx
Data on signalling and related
(e.g. points) failures
SC3 S and T Metro Assets
30/03
(14.001)
SandT Metro Assets 30 03
106.xls
Database showing the signalling
and telecom assets
SC4 [redacted] [redacted] [redacted]
SC5 [redacted] [redacted] [redacted]
Telecoms
TfW
Ref Name
Location (in data room)
File Name Description
T1
CVL Ellipse Data Cut (All
Asset Types)
(9.019)
9.019 CVL Ellipse data cut.xlsx
Ellipse Data.zip
Ellipse is the master asset
database for Network Rail for
storing and raising maintenance
reports
T2
Extract from NR
Decision Support Tool
for Telecoms Assets
(9.021)
9.021 - Extract from NR
Decision Support Tool for
Telecoms Assets.pdf
Extract showing FTN assets in
the South Wales area (not
exclusively CVL)
T3 [redacted] [redacted] [redacted]
T4 [redacted] [redacted] [redacted]
T5
Core Valleys Telecom
Assets V2
(9.021)
9.021 Core Valleys Telecom
Assets V2.xlsx
Database showing the location
of telecoms assets
T6
Wales Metro Telecoms
Assets 190416
(9.021)
9.021 Wales Metro Telecoms
Assets 190416.xlsx
Database showing telecoms
maintenance
T7
Wales Metro Telecoms
Assets 110416
(14.001)
Wales Metro Telecoms Assets
110416.xlsx
Database showing the location
of telecoms assets
T8
Wales Metro Telecoms
Maintenance
(14.001)
Wales Metro Telecoms
Maintenance.xlsx
Database showing the location
of telecoms assets with some
maintenance information
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 30
Electricity and Power
TfW
Ref
Name Location (in data room)
File Name
Description
EP1 E and P asset list (9.023)
9.023 EandP asset list.xlsx
A list of the Electricity and
Power assets across the Core
Valleys
EP2 [redacted] [redacted] [redacted]
EP3 [redacted] [redacted] [redacted]
EP4 E and P asset list (14.001)
EandP asset list.xlsx
A list of the Electricity and
Power assets across the Core
Valleys
Stations
TfW Ref Name Location (in data room)
File Name
Description
S1 [redacted] [redacted] [redacted]
S2 Listed stations (9.023)
9.023 Listed stations.docx
A document showing listed
stations across the Wales
Route
S3 [redacted] [redacted] [redacted]
S4 [redacted] [redacted] [redacted]
S5 NR Station Ownership
Plans CVL
(11.002)
11.002 NR Station Ownership
Plans CVL.pdf
Document containing site plans
for each of the stations along
the Core Valley
S6
Station Boundaries
and agreements for
categories
(11.002)
11.002 Station Boundaries and
agreements for categories.zip
Contains more detailed
information on certain stations
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 31
TfW Ref Name Location (in data room)
File Name
Description
S7 [redacted] [redacted] [redacted]
S8 Station Maintenance
Plans
(11.008)
11.008 SFO Station
Maintenance Plan Reactive
Station Maintenance for
2016.xlsx
11.008 SFO Station
Maintenance Plan.doc
11.008 Stations Station
Maintenance Plans Part 2
Revised on 31 October
2016.xlsx
- SFO Station Maintenance Plan
Reactive Station Maintenance
for 2016
-SFO Station Maintenance Plan
-Stations Station Maintenance
Plans Part 2 Revised on 31
October 2016
- SFO Station Maintenance
Plan, Annual Water Testing
Cost Clarification
S9 Stations Database (11.013)
11.013 Stations Database.xls
A database of stations across
the Wales Route
S10 Stations Database
Revised March 2017
(11.013)
11.013 – Stations Database
Revised March 2017.xls
Revised version of the database
of stations across the Wales
Route
S11
List of Stations with
Accredited Secure
Station Status
(11.014)
11.014 – List of Stations with
Accredited Secure Station
Status.docx
Document showing all the
stations along the Wales Route
with accredited secure status
Non-compliances and Derogations
TfW Ref Name Location (in data room)
File Name
Description
NC1 Copy of NC’s and
TV’S National
(17.003)
17.003 - Copy of NCs
Derogations and
Spreadsheet showing non-
compliance derogations and
temporary variations nationally
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 32
TfW Ref Name Location (in data room)
File Name
Description
TVs_National_2017071
_Redacted.xls
NC2 Copy of NC’s and
TV’s Wales
(17.003)
17.003 - Copy of NCs
Derogations and TVs_ Wales
only_20170710_ Redacted.xls
Spreadsheet showing non-
compliance derogations and
temporary variations on the
Wales route
NC3 Engineering
Verification Tracker
(17.003)
17.003 - SSM Cardiff EV Report
final v2 0_Redacted.doc
Spreadsheet showing reported
non-compliances and remedial
actions
NC4 [redacted] [redacted] [redacted]
NC5 [redacted] [redacted] [redacted]
NC6 [redacted] [redacted] [redacted]
NC7 [redacted] [redacted] [redacted]
NC8 Structures – Wales
(17.003)
17.003 - Structures - Wales
(10)_redacted.pdf
Engineering Verification Report
on Structures
NC9 Telecoms Wales
(17.003)
17.003 - Telecoms Engineering
Verification Wales Period 3
Wales ROC-
signed_Redacted.pdf
17.003 - Telecoms Engineering
Verification Wales Period 7_
Redacted.pdf
Engineering Verification Report
on Telecoms
Renewals
TfW Ref Name Location (in data room)
File Name
Description
R1 Cost and Volumes
handbook
17.004 - Costs & Volumes
Handbook.zip
A handbook used by Network
Rail to define maintenance and
renewals volumes
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 33
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 34
12. Appendix 9.H - Table of Indicative CVL Infrastructure Manager Year One Renewals
12.1 This table sets out the Indicative CVL Infrastructure Manager Year One Renewals that are to act at the
basis of the pricing of Maintenance. It also sets out the eight Indicative Year One Renewals for:
1. Design of Renewals to TfW Plan of Works Stage E; and
2. Implementation Management of Renewals, either by the ODP or by an IDP.
12.2 Descriptions of categories are based on Network Rail’s Cost and Volumes Handbook located in Award in
the CVL Asset Statement directory. Routes are defined by Engineering Line References an index of which
is in Award.
Track Renewals
12.3 Renewal of both rails including re-padding and re-stressing at the following worksites.
1. CAM 13m 990 yards to CAM 13m 1430 yards on the UP line. (*Renewal example 1 of 8 for
which a Summary Method Statement, a Design Statement and an Implementation Management Price is
required)
2. CAR 302 Yards
3. CAR 208 Yards
12.4 Renewal of ballast including formation treatment (demonstrated at track bed investigation).
1. CAR 247 Yards
2. CAM 1,006 Yards
3. CAR 247 Yards
12.5 Renewal of ballast at the following worksites:
1. CAR 302 Yards
2. CAR 402 Yards
3. THT 137 Yards
4. CRY 119 Yards
12.6 Renewal of rail and sleepers and replacing existing sleeper types with concrete sleepers:
1. CAM 262 Yards
12.7 Contiguous Renewals on CAR (*Renewal example 2 of 8 for which a Summary Method Statement, a
Design Price and an Implementation Management Price is required), comprising
1. CAR 23m 732 yards to CAR 23m 1080 yards: Renewal of both rails including re-padding and re-
stressing; and
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 35
2. CAR 23m 1080 yards to CAR 23m 1215 yards: Complete renewal of Rail Sleepers and Ballast.
Additionally, formation treatment where this is demonstrated to be required through track bed
investigation
12.8 Contiguous Renewals on THT:
1. 398 Yards: Renewal of one rail including re-padding and re-stressing
2. 350 Yards: Renewal of both rails including re-padding and re-stressing
Structures Renewals
12.9 Repair and waterproofing of Tunnel (*Renewal example 3 of 8 for which a Summary Method Statement a
Design Price and an Implementation Management Price is required) comprising:
1. [redacted] repoint 25m2 of tunnel entrance; and
2. [redacted], Re-lining at 18 ¾ chains from the Lisvane Portal 175m2
12.10 Remediation of brick retaining wall including installation of tie bars;
12.11 THT: 575 m2
12.12 Timber Deck Replacement, steelwork repairs and paint of Mill [redacted]: 450m2 (Bridge at VON 23m 192
yards) (*Renewal example 4 of 8 for which a Summary Method Statement, a Design Price and an
Implementation Management Price is required)
12.13 Structural relining of culvert;
12.14 ABD, Unnamed Culvert: 20m2
12.15 Strengthen main girder and paint footbridge;
12.16 CAM, [redacted] Footbridge
12.17 Spot brick repairs and total repointing of retaining wall;
12.18 CAM, Feeder Canal Retaining Wall: 300m2
12.19 Strengthen and Repaint overbridge;
12.20 THT
12.21 Replace culvert;
12.22 ABD: 25m2
12.23 Replace retaining wall starting at CAM 18m 1540 yards for 158m2 in the up (Merthyr) direction. (*Renewal
example 5 of 8 for which a Summary Method Statement, a Design Price and an Implementation Management
Price is required)
Signalling and Control Systems and Passenger Information System Renewals
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 36
12.24 No signalling and control systems and passenger information system renewals will be funded during the first
ten years of the Grant Agreement Term. Where the OPD wishes to use the existing signalling system
functionality as part of its Transformation solution, but is unable to assure the Authority that parts of the
existing signalling system can be life extended to the end of the first ten years of the Grant Agreement
Term, the ODP is to renewal those parts in the Transformation.
12.25 Schedule 3A Definitions set out the arrangement for Renewals in years eleven to fifteen of the Grant
Agreement Term
Telecommunications Renewals
12.26 The Initial Telecommunications Plan required in accordance with Appendix 8.H of Volume 8 includes the
Requirement that your Solution for CVL Transformation must include all of the telecommunications
renewals and enhancements that are needed to deliver your Rail Services over the ODP Grant
Agreement Term. Accordingly, no renewals are included in Appendix 9.H for Telecommunications.
Earthworks Renewals
12.27 Contiguous Renewals, CAM 15m 880 yards to 5m 1650 yards (*Renewal example 6 of 8 for which a
Summary Method Statement, a Design Price and an Implementation Management Price is required),
comprising:
1. 5chs of Embankment Renewal
2. 20ch of Embankment Refurbish
3. 10ch of Soil Cutting Refurbish
12.28 Not used
12.29 Not used
Property and Buildings (Including Stations) Renewals
12.30 Platform re-construction;
[redacted]250 m2
12.31 Canopy Refurbishment at [redacted]of 657 m2 continuously from the Cardiff end of the station.
(*Renewal example 7 of 8 for which a Summary Method Statement, a Design Price and an Implementation
Management Price is required)
12.32 Footbridge Strengthening and Refurbishment;
[redacted] 111 m2
12.33 Footbridge Refurbishment
[redacted] 75 m2
CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 37
Power Distribution and Electricity and Plant Renewals
12.34 It has been assumed that there will be no renewals during the ODP Grant Agreement Term of any assets
forming part of the OLE system, including any existing assets forming part of the system. You are required
to strengthen or renew any such existing assets as part of the CVL Transformation works.
12.35 The following Infrastructure Manager Year one renewals are for E & P assets that are not directly
associated with the OLE system.
1. Signalling power renewal of 12km of 650kv cable relating to FSP upgrades. Bidders should assume that
the cable troughing has sufficient capacity for the cabling, but should also assume that cabling made
redundant by this renewal is to be removed, or, where this is not practical, clearly labelled as redundant.
(*Renewal example 8 of 8 for which a Summary Method Statement, a Design Price and an Implementation
Management Price is required)
2. UPS mid-life refurbishment: 1 UPS renewal
3. DNO renewal:1 DNO replacement
4. Generator renewal: 1 generator renewal
5. FSP renewals:6 FSP renewals
12.36 Not used
Level Crossing Renewals
12.37 It is assumed that works to level crossings to accommodate any changes needed to facilitate your Solution
for CVL Transformation will be undertaken as part of the CVL Transformation. No renewals work on
Level Crossings is anticipated for the first five Infrastructure Manager Years
Off Track Renewals
12.38 1000m of pipe
12.39 200m of Ditch/Channel
12.40 40 Catch Pits
12.41 11,938m of fencing
12.42 5 Access Points
DRAFT – CONFIDENTIAL
30/11/2017 Wales and Borders Rail Service and South Wales Metro 38
13. Appendix 9.I Summary Method Statement Requirements for each CVL Infrastructure Manager Year One Renewal Example
13.1 This appendix sets out key items which the Authority expects to see in your Methodology for each
Confirmed Known Renewal:
1. Programme and key milestones
2. Third Party dependencies
3. Site and access arrangements
4. Possession, Blockade and Temporary Operational Restriction requirements
5. Management of Neighbours and other Stakeholders
6. Plant and Materials
7. HSQE
8. Interdisciplinary and Systems integration issues
9. Handover, Testing and Commissioning and Handback
10. Risk Management including mitigation of possession and blockage overruns
11. Any additional information required