Wake County Transit PlanChoose how you move!

December 7, 2011Capital Area Friends of Transit

1

Page 2: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

What We Said We Would Do…

• Prepare a Bus Plan

• Prepare a Rail Plan

• Obtain Municipal Input

Wake County Transit Plan2

Wake County Transit Plan

Page 3: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 3

The Wake County Transit Plan is…• Derived from the Bus Plan and Rail Analysis

prepared by many stakeholders• Based on a conservative set of financial and

growth rate assumptions• Connecting all municipalities, employment

centers, universities/colleges, and the airport

Wake County Transit Plan

Page 4: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 4

Wake County Population

Jurisdiction 1980

1985

2000

2010

2020

2035

2040

Apex 2,847 3,710 20,212 37,476 58,690 98,638 114,227

Cary 21,763 35,520 94,536 133,812 160,512 189,419 196,457

Fuquay-Varina 3,110 3,746 7,898 17,937 33,590 65,463 78,376

Garner 10,073 12,372 17,787 25,745 46,278 87,543 104,160

Holly Springs 688 746 9,192 24,661 34,875 52,478 59,024

Knightdale 985 1,267 5,958 11,401 27,922 63,422 78,145

Morrisville 251 580 5,208 18,576 22,615 27,400 28,707

Raleigh 150,255 194,228 276,094 402,825 490,982 596,038 624,939

Rolesville 381 586 907 3,786 8,560 18,696 22,879

Wake Forest 3,780 4,379 12,588 29,218 42,450 65,927 74,802

Wendell 2,222 2,663 4,247 5,845 12,908 27,845 33,998

Zebulon 2,055 2,794 4,046 4,433 9,444 19,970 24,294

Total Wake County 301,429 360,387 627,846 900,993 1,160,823 1,541,088 1,667,841

Page 5: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 5

Wake County Transit Plan

Page 6: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 6

The Bus Plan

Page 7: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 7

Creating the Bus Plan• Stakeholders included

o Bus service providers o All Wake County municipalitieso CAMPO

• Identified common goals and service standards• Balanced trade-offs county-wide

Wake County Transit Plan

Page 8: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 8

Bus Plan - Overview• More frequent service• Enhanced existing transit corridors• Links population and employment centers• Circulator service connecting key destinations• Expanded service to unserved towns• Coordination with rail service• Incorporates new technology

Wake County Transit Plan

Page 9: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 9

Bus Plan – Capital Improvements• New transit centers• New park and ride lots• Additional shelters, benches, sidewalks• New buses• Operational improvements• Additional maintenance facility capacity

Wake County Transit Plan

Page 10: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 10

Bus Plan – Service Hour Expansion

Wake County Transit Plan

Page 11: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 11

Page 12: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 12

*Projection

Page 13: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 13Presentation Title13

Connecting the County

Page 14: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 14

The Rail Plan

Page 15: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 15

Rail – Alternatives Analysis• A focused look at the alternative corridors for

commuter rail and light rail• A means of reaching investment strategy for a

particular corridor• A requirement for federally funded transit

projects• Solicited feedback through a series of public

workshops across the region

Wake County Transit Plan

Page 16: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Presentation Title 16

Rail Corridor Study Areas

Page 17: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 17

Wake County Transit Plan

Commuter Rail Overview (Wake County Portion)

• Greenfield Parkway in Garner to Triangle Metro Center in RTP

• 9 stations – service every 30 minutes during peak hours and 60 minutes off-peak

• New park-and-ride lots• Can implement with locally generated funds

Page 18: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Presentation Title 18

Commuter Rail Corridor– Locally Preferred Alternative (LPA)

Page 19: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 19

Wake County Transit Plan

Light Rail Overview• Requires federal and state funding• Downtown Cary to Millbrook Road (13.9 miles)• 16 stations – service every 10 minutes during peak

hours and 20 minutes off-peak• New park-and-ride lots• Coordination with bus service

Page 20: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Presentation Title 20

Light Rail Corridor– Locally Preferred Alternative (LPA) & Minimum Operable Segment (MOS)

Page 21: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 21

The Wake County Transit Plan

Page 22: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 22

A Practical Approach for Implementation

Page 23: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 23

Core Transit Plan – Bus Costs

Wake County Transit Plan

Bus Plan Cost: First Five Years

Total Non-Local Local

Capital Costs $262,929,000 $197,197,000 $65,732,000

Operating Costs $80,663,000 $8,066,000 $72,597,000

Total $343,592,000 $205,263,000 $138,329,000Note: 1) All amounts are in FY 2011 dollars (not inflated) 2) Total Bus Plan cost FY2013-2040 is $1.9 billion 3) Includes existing federal & state capital assistance formula funding (75%)

Page 24: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 24

Core Transit Plan – Commuter Rail Costs

Wake County Transit Plan

Commuter Rail Cost

Total Wake County Share

Durham County Share

Capital Costs $650,000,000 $330,000,000 $320,000,000Note: 1) All amounts are in FY 2011 dollars (not inflated) 2) Annual operating cost is estimated at $7.5 Million in FY 2011 dollars

Page 25: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 25

Enhanced Transit Plan – Light Rail Costs

Wake County Transit Plan

Light Rail Cost

Total

Capital Costs $1.1 billion

Operational Costs $14 million/yr.Note: All amounts are in FY 2011 dollars (not inflated)

Page 26: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 26

Wake County Transit Plan

Local Revenue• Half-cent Local Sales Tax

o Revenue estimated at $53.47 million in FY 2011o Growth assumption:

o 1.0%.....FY 2012o 1.5%.....FY 2013o 2.0%.....FY 2014o 2.5%.....future years

Page 27: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 27

Wake County Transit Plan

Local Revenue• New $7 county vehicle registration fee• Increase from $5 to $8 regional vehicle registration fee• Existing 5% vehicle rental tax• Fare box revenue

Page 28: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 28

Page 29: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 29

Page 30: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 30

Wake County Transit Plan

Page 31: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 31

Interlocal Agreements (ILA)• County / Municipal ILA and County / Triangle

Transit / CAMPO ILAo Parties agree to the process for plan updates and

amendmentso Municipalities approve the Wake County Transit Plano Municipalities support placing a referendum for the ½

cent sales tax on the ballot

Wake County Transit Plan

Page 32: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Where We Are Now…• Draft Wake County Transit Plan is complete• Finalize the Wake County Transit Plan• Begin moving forward with municipal approval

Wake County Transit Plan32

Wake County Transit Plan

Page 33: Wake County Transit Plan Choose how you move! December 7, 2011 Capital Area Friends of Transit 1

Wake County Transit Plan 33

Wake County Transit Plan

Task/Milestone Date•Finalize Wake County Transit Plan November 2011•Municipalities Consider/Approve Transit Plan & ILA Nov. – Feb. 2012•CAMPO Consider/Approve Transit Plan Feb. – March 2012•Triangle Transit Consider/Approve Transit Plan Feb. – March 2012•Wake BOC Consider/Approve Transit Plan & ILA April 2012•Wake BOC Authorize the Referendum April 2012•Referendum November 2012