w el c o m e t o a c o m e t 2 0 17 - cem
TRANSCRIPT
![Page 1: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/1.jpg)
1 C O M E T 2 0 1 7
C O M E T 2 0 1 7 W E L C O M E T O A
T E C H N I C A L P A P E R P R E S E N T A T I O N
![Page 2: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/2.jpg)
2 C O M E T 2 0 1 7
B y : J O S H C O N T R E R A S a n d L I S A M A R T I N
“ DISTRIBUTED GEN ERATION : IN TEGRATIN G
UTILITY- SCALE BATTERY STORAGE.”
![Page 3: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/3.jpg)
3 C O M E T 2 0 1 7
J O S H C O N T R E R A S S Y S T E M E N G I N E E R I N G
A U S T I N E N E R G Y
A B O U T T H E P R E S E N T E R
Josh Contreras is a Power System Engineer Senior at Austin Energy,
the City of Austin’s municipally-owned utility.
Josh currently works in the System Engineering workgroup that
supports integrating Distributed Generation into the AE system, and
previously worked in Transmission Relay for seven years. Josh is a
registered Professional Engineer in the State of Texas.
BRIEF B IO
![Page 4: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/4.jpg)
4 C O M E T 2 0 1 7
L I S A M A R T I N D E R I N T E G R A T I O N
A U S T I N E N E R G Y
A B O U T T H E P R E S E N T E R
Lisa Martin is a Program Manager of Advanced Technologies at
Austin Energy. Her focus is in the field of Distributed Energy
Resource (DER) Integration.
Lisa serves as the project manager for Austin SHINES, a federal and
state-funded project. Austin SHINES establishes an open standards-
based DER management platform to integrate and optimize DER at
several levels along the utility value chain. Lisa is a registered
Professional Engineer in the State of Texas.
BRIEF B IO
![Page 5: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/5.jpg)
5 C O M E T 2 0 1 7
A BSTRA CT SUM M A RY
O V E R V I E W &
S o l a r + S t o r a g e , M i c r o g r i d , D E R M S a n d S t a c k e d
Va l u e s a r e b u z z w o r d s t h a t c o n t i n u e t o g a i n i n
p o p u l a r i t y a s t h e u t i l i t y i n d u s t r y c o n t i n u e s t o
d r i v e t o w a r d b u i l d i n g a S m a r t G r i d . D i s t r i b u t e d
E n e r g y R e s o u r c e s o f f e r m a n y p r o m i s i n g b e n e f i t s
t o t h e u t i l i t y a n d t o t h e c u s t o m e r , b u t i n t e g r a t i n g
D E R i s o f t e n m o r e c h a l l e n g i n g a n d c o m p l e x t h a n
o n e m i g h t r e a l i z e .
T h i s s e m i n a r p r o v i d e s a d e e p - d i v e i n t o o n e
u t i l i t y ’ s j o u r n e y f o r i n t e g r a t i n g u t i l i t y - s c a l e
e n e r g y s t o r a g e i n t o i t s d i s t r i b u t i o n s y s t e m .
L E A R N M O R E
C r e d i t : D i s t r i b u T e c h 2 0 18
![Page 6: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/6.jpg)
6 C O M E T 2 0 1 7
I N TEGRA TI N G UTI LI TY-
SCA LE BA TTERY STORA GE
D I S T R I B U T E D G E N E R A T I O N
What is causing the industry to think
about deploying more and more
distributed energy resources?
S T R A T E G I C D R I V E R S
The very basics, just to ensure everyone
has a foundation
B A T T E R Y B A S I C S
Proper set-up (resources and tools) are
critical to successful operations and
maintenance
C O N T R O L S & M O N I T O R I N G
Design considerations and constraints,
planning and analysis … critical to
success of the project
I N T E R C O N N E C T I O N A N D P L A N N I N G
Field work, testing, troubleshooting, and
commissioning lead to an operational
project
I N S T A L L A T I O N
Lessons learned, workgroups involved,
Q&A
C O N C L U S I O N S
![Page 7: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/7.jpg)
7 C O M E T 2 0 1 7
STRATEGIC DRIVERS
![Page 8: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/8.jpg)
8 C O M E T 2 0 1 7
STRA TEGIC D RIVERS E N E R G Y S T O R A G E
Regulatory Mandate
Transmission/Distribution Deferral
Market Participation
Reliability Benefits
Renewables Integration
Available Capacity
U T I LI T Y- B A S E D Bill Offsets
Back-Up Power
Power Factor Support
Behind-the-Meter Control
Sustainability Leadership
C U S T O M E R - B A S E D
Th e b u s i n e ss c a se f o r e n e r g y s t o r a g e i s r e a l i z e d w h e n b o t h c u s t o m e r a n d u t i l i t y o b t a i n v a l u e
![Page 9: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/9.jpg)
9 C O M E T 2 0 1 7
A USTIN EN ERGY A B O U T
M I S S I O N : T O S A F E LY D E L I V E R C L E A N , A F F O R D A B L E , R E L I A B L E E N E R G Y A N D
E X C E L L E N T C U S T O M E R S E R V I C E
P U B L I C P O W E R 8th largest community-owned electric utility
Reports to the City Manager who execute the policy and
direction of the City Council
1700+ employees; Annual budget $1.5B
C O M P A C T , D E N S E S YS T E M 437 square miles of service area covering City of Austin and
beyond
480,000+ meters (65,000+ C&I)
V E R T I C A L L Y- I N T E G R A T E D • Vertically-integrated (NOIE) in a deregulated, energy only
market (ERCOT)
• System peak load 2755 MW (summer), 2377 MW (winter)
![Page 10: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/10.jpg)
10 C O M E T 2 0 1 7
STRA TEGIC D IRECTIO N A U S T I N E N E R G Y
M I S S I O N To safely deliver clean, affordable, reliable energy and excellent
customer service
V I S I O N Drive customer value in energy services with innovative
technology and environmental leadership
C U S T O M E R D R I V E N . C O M M U N I T Y F O C U S E D .
A u s t i n – T h e n a n d N o w
![Page 11: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/11.jpg)
11 C O M E T 2 0 1 7
RESO URCE GEN ERA TIO N PLA N
REN EW A B LE EN ERGY
65% renewable energy
by 2027
EN ERGY EFFI C I EN CY a n d
D EM A N D RESP O N SE
900 MW of savings from
energy efficiency and
demand response
by 2025
SO LA R a n d STO RA GE
950 MW solar (200 MW
local and 100 MW
customer-sited)
10 MW electrical storage
30 MW thermal storage
by 2025
GO I N G FO RW A RD
Net-Zero Community-Wide
Green House Gases
by 2050
S u b j e c t t o A f f o r d a b i l i t y G o a l s
![Page 12: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/12.jpg)
12 C O M E T 2 0 1 7
![Page 13: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/13.jpg)
13 C O M E T 2 0 1 7
BY TH E N UM BERS L O C A L S O L A R
![Page 14: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/14.jpg)
14 C O M E T 2 0 1 7
STRA TEGIC GO A LS A U S T I N E N E R G Y
F i n a n c i a l H e a l t h B u s i n e s s
E x c e l l e n c e E m p l o y e e
E n g a g e m e n t
E n v i r o n m e n t C u s t o m e r
C o l l a b o r a t i o n G r i d
M o d e r n i z a t i o n
![Page 15: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/15.jpg)
15 C O M E T 2 0 1 7
ROOTED IN CUSTOM ER SA TISFA CTION A N D RELIA BILITY IN DEX M ETRICS
G R I D M O D E R N I Z A T I O N
AE Strategic Goals
Grid Modernization
Advanced Metering Infrastructure
Grid Automation
Distributed Energy Resource Integration
Asset Management
![Page 16: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/16.jpg)
16 C O M E T 2 0 1 7
ST R A T EGY F U N D A M EN T A L S
Policy/ Stakeholder Inclusion
Customer and Application Driven
Leverage Funding Opportunities
Build on Project and Industry Learnings/ Share Openly
Open Standards/ Interoperability/ Scalability
Diversification of Application, Architecture, Partners
Stacking the Values
![Page 17: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/17.jpg)
17 C O M E T 2 0 1 7
The U.S. Department of Energy initiated a funding
opportunity for projects that would work to dramatically
increase solar-generated electricity that can be
dispatched at any time – day or night – to meet
consumer electricity needs while ensuring the reliability
of the nation’s electricity grid.
This opportunity is known as SHINES.
Austin Energy is a proud recipient of a SHINES award
for $4.3 million. Along with several project partners, AE
is in the process of implementing its Austin SHINES
project.
S U S T A I N A B L E A N D H O L I S T I C I N T E G R A T I O N O F E N E R G Y
S T O R A G E A N D S O L A R P V
![Page 18: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/18.jpg)
18 C O M E T 2 0 1 7
DER Management System
Utility Scale Energy Storage + PV
Commercial Energy Storage + PV
Residential Energy Storage + PV
![Page 19: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/19.jpg)
19 C O M E T 2 0 1 7
U T I L I T Y S C A L E
2.5 MW Community Solar Farm
1.5 MW / 3 MWh Li-Ion Battery Storage
1.5 MW / 2.5 MWh Li-Ion Battery Storage
C O M M E R C I A L S C A L E
Aggregated storage installations at four sites:
Two 18 kW / 36 kWh Li-Ion Battery Storage installations
Two 72 kW / 144 kWh Li-Ion Battery Storage installations
All sites have existing solar (300+ kW)
R E S I D E N T I A L S C A L E
Aggregated storage installations at six homes (10 kWh each)
Each with existing rooftop solar
Utility-Controlled Solar via Smart Inverters at twelve homes
Autonomously Controlled Smart Inverters at six homes
D E R M A N A G E M E N T S Y S T E M
Fleet-wide controller at utility control center and energy market desk
Circuit manager for certain applications like voltage control
Site-level controller for grid-scale installations
Inputs include grid data, market data and forecasts
![Page 20: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/20.jpg)
20 C O M E T 2 0 1 7
![Page 21: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/21.jpg)
21 C O M E T 2 0 1 7
D E P L O YM E N T U N D E R W A Y
4 5 m o n t h p r o j e c t
$ 11. 5 m i l l i o n
![Page 22: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/22.jpg)
22 C O M E T 2 0 1 7
BATTERY BASICS
C o u r t e s y o f S n o h o m i s h P U D
![Page 23: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/23.jpg)
23 C O M E T 2 0 1 7
Energy can be neither created
nor destroyed
However, energy can change
forms, and energy can flow from
one place to another
The total energy in an isolated
system does not change.
Ein = Eout + Lossesheat
C O N S E R VA TIO N O F E N E R G Y
F I R S T L A W O F T H E R M O D Y N A M I C S
1 Joule = Energy applied by a
force of one newton through a
distance of one meter
1 Joule [J] = 1 watt-second
1 kWh = 3,600,000 Joules
1 AA battery (alkaline) = 12,960 J
KB ESS = 833,334 AA batteries
E N E R G Y M E A S U R E M E N T
![Page 24: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/24.jpg)
24 C O M E T 2 0 1 7
Fast e st -g r o w i n g t y p e o f e n e r g y st o r ag e d u e t o sc a l ab i l i t y an d f l e x i b i l i t y
B A T T E R Y E N E R G Y S T O R A G E
Best for standby power because batteries degrade through multiple charge-discharge cycles
L E A D A C I D
Better at charge-discharge than lead-acid, but batteries degrade
N I - C A D
New technology, great for long-duration applications with frequent charge-discharge, about 70% efficient
V A N A D I U M F L O W
More expensive, but good for many charge-discharge cycles and efficient. Best for short-duration applications
L I T H I U M - I O N
Fair efficiency, about a 15-year life, best for high capacity installations
S O D I U M - S U L F U R
Most often used with batteries when a high discharge rate is needed
U L T R A - C A P A C I T O R
![Page 25: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/25.jpg)
25 C O M E T 2 0 1 7
Source: DOE’s Sandia National Laboratory, Energy Storage Systems Program
http://www.sandia.gov/ess/wp-content/uploads/2015/04/EsPositioningHandbook.png
B A TTERY SELECTI O N I S D EP EN D EN T O N D ESI RED
U SE
Lithium-ion is a versatile but costly selection, though prices are dropping
every year
However, battery modules are only one component of cost
Balance of system costs are often approximately equal to the battery
module costs
![Page 26: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/26.jpg)
26 C O M E T 2 0 1 7
BA LA N CE O F SYSTEM B A T T E R Y S T O R A G E S Y S T E M
O N E
P o w e r C o n v e r s i o n S y s t e m
c o n v e r t s e l e c t r i c i t y b e t w e e n
D C a n d A C a s n e e d e d
T W O
T H R E E
E S S C o n t r o l S y s t e m
p r o v i d e s a b i l i t y t o d i s p a t c h
a n d m o n i t o r b a t t e r y s t o r a g e ,
r e a l a n d r e a c t i v e p o w e r
F O U R
A n c i l l a r i e s : H VA C , f i r e
s u p p r e s s i o n s y s t e m ,
i s o l a t i o n p o i n t s , p r o t e c t i o n
r e l a y s a n d m o r e
A l t h o u g h t h e r e a r e m a n y, t h e f o u r m a i n c o m p o n e n t s a r e
B A T T E R Y E N E R G Y S T O R A G E
A battery energy storage system is made of more than just batteries. The rest of the
system is often referred to as “Balance of System” or “BOS”
B a t t e r y M a n a g e m e n t
S y s t e m s e n s u r e p r o p e r
c o n t r o l a n d p r o v i d e s a f e t y
![Page 27: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/27.jpg)
27 C O M E T 2 0 1 7
IN TERCON N ECTION AN D PLAN N IN G
![Page 28: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/28.jpg)
28 C O M E T 2 0 1 7
K i n g sb e r y En e r g y St o r ag e Sy st e m (KB ESS)
D e s i g n i n g t h e U t i l i t y - S c a l e
A r e v i e w o f t h e i n t e r c o n n e c t i o n p r o c e s s a n d t h e t y p e s o f i n t e r c o n n e c t i o n e q u i p m e n t u s e d t o d e s i g n a
s a f e , r e l i a b l e , a n d e c o n o m i c a l d i s t r i b u t e d g e n e r a t i o n f a c i l i t y o n a n A u s t i n E n e r g y d i s t r i b u t i o n c i r c u i t .
K e y G o a l s
E n e r g y S t o r a g e S y s t e m
C o n c l u s i o n s
I n t e r c o n n e c t i o n R e q u i r e m e n t s
D e s i g n O p t i o n s
F i n a l D e s i g n
![Page 29: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/29.jpg)
29 C O M E T 2 0 1 7
Ke y Go a l s E n e r g y S t o r a g e S y s t e m
Safely install, operate, and maintain a utility-scale energy storage system within Austin Energy’s operational and information technology ecosystem
A E E c o s y s t e m
Demonstrate and evaluate the benefits of the Modular Energy Storage Architecture (MESA) open standard.
M E S A B e n e f i t s
Identify and demonstrate distributed energy storage use cases that support power quality and reliability on a feeder with a high penetration of solar generation, energy arbitrage, distribution system efficiency, etc.
U s e C a s e s
Enhance Austin Energy’s ability to design and model the appropriate capacity of energy storage to address distribution system issues caused by solar penetration.
D e s i g n a n d M o d e l i n g
![Page 30: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/30.jpg)
30 C O M E T 2 0 1 7
KB ESS D e t a i l s U t i l i t y - S c a l e
Doosan, serving as the System Integrator, selected the following equipment during the conceptual design phase of the project:
B a t t e r y B a n k Lithium Ion
1.5MW
3.0 MWh
I n v e r t e r MESA compliant
Can act as a voltage source
D i s c o n n e c t E n c l o s u r e Houses the manual disconnect, 480V protection,
network switches, AC distribution panel, and the
auxiliary power meter
![Page 31: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/31.jpg)
31 C O M E T 2 0 1 7
K B- 1 Ci r c u i t Ch a r ac t e r i s t i c s
K i n g s b e r y F e e d e r
Substation with 69kV and 138kV
transmission voltages.
K i n g s b e r y S u b s t a t i o n
Primarily residential customers
C u s t o m e r s
Subject to the elements
Reliable circuit
O v e r h e a d F e e d e r
12.47kV primary;
four-wire multigrounded system
D i s t r i b u t i o n S y s t e m
Approximately 2.5 miles long
# m i l e s l o n g
2.5 MW community PV solar farm
installation adjacent to the Kingsbery
Substation
C o m m u n i t y S o l a r
![Page 32: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/32.jpg)
32 C O M E T 2 0 1 7
I n t e r c o n n e c t i o n Re q u i r e m e n t s
A u s t i n E n e r g y
For this project, we chose to follow the same guidelines that we would give any other customer looking to interconnect onto our distribution system. To begin, we started with the AE Distribution Interconnection Guide. The purpose of this guide is to make sure the design takes the following into account: 1. Safety: The DG must not pose a safety risk
to the general public or to our field crews working on the system
2. Reliability: The interconnection must not compromise the reliability and/ or the service quality of other AE customers
3. Economics: The interconnection must designed in a cost effective manner.
F o r D G S i t e s
![Page 33: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/33.jpg)
33 C O M E T 2 0 1 7
Use of certified DR equipment Potential for unintended islands System protection, fault conditions, and Arc Flash rating
Sy st e m En g i n e e r i n g
I m p a c t S t u d y , P a r t 1
Impacts on voltage regulation using quasi-steady state analysis Impact on AE equipment loading (steady state) Flicker Criteria
D i st r i b u t i o n Pl an n i n g
I m p a c t S t u d y , P a r t 2
![Page 34: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/34.jpg)
34 C O M E T 2 0 1 7
D e si g n Co n st r a i n t s S y s t e m I n t e g r a t o r
U n g r o u n d e d 4 8 0 V S y s t e m Required by inverter manufacturer as the common mode
noise filter would not work with a grounded system
D e l t a t r a n s f o r m e r c o n n e c t i o n Recommended by manufacturer for triplen harmonics
mitigation
A u x i l i a r y P o w e r 480V auxiliary power required to keep the batteries cooled
for warranty purposes
![Page 35: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/35.jpg)
35 C O M E T 2 0 1 7
D e si g n Co n si d e r a t i o n s A u s t i n E n e r g y
I m p e r v i o u s C o v e r Keep site under 1080 square feet to avoid major
development permitting within the Kingsbery Substation.
O p e r a t i n g G u i d e l i n e s Preferred to keep the operating guidelines for this DG facility the
same as the other DG facilities within the AE service area.
A E / S y s t e m I n t e g r a t o r C o n t r a c t Contract did not cover all aspects of the design
P r o j e c t S c h e d u l e / D O E I m p a c t s Funding for the project was tied to meeting milestones set
out in the project schedule
![Page 36: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/36.jpg)
36 C O M E T 2 0 1 7
Sy st e m Co m p o n e n t s M a j o r
O N E
D i r e c t Tr a n s f e r Tr i p
T W O
E R C O T M e t e r i n g
T H R E E
D G i n t e r c o n n e c t
Tr a n s f o r m e r
F O U R
U t i l i t y E x t e r n a l
D i s c o n n e c t s
A m i x t u r e o f e l e m e n t s a r e r e q u i r e d i n t h e d e s i g n o f a
D G i n t e r c o n n e c t i o n
D G I n t e r c o n n e c t i o n “ B i g P i c t u r e ”
While the types of DG facilities may vary, there are basic functions the interconnection
equipment need to perform for a safe, reliable, and economical system. The big picture
is that ERCOT requires EPS metering for systems that generate more than 1MW, a
direct transfer trip will be sent from the feeder breaker to prevent unintentional islanding,
disconnects are necessary in order to keep our field crews safe, and the DG
interconnect transformer plays a crucial role in the stability of the distribution system.
![Page 37: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/37.jpg)
37 C O M E T 2 0 1 7
AE System Engineering
-Protection One-Line -Specify equipment
AE Consultant
-Recloser Settings -Arc Flash analysis -Interconnection Transformer Study
12 .47k V D e si g n
A u s t i n E n e r g y
Doosan
-Battery (LG Chem) -Inverter (Parker) -Disconnect Encl. (Consultant)
AE Consultant
-480V relay settings -Maintenance Settings
48 0 V D e si g n
S y s t e m I n t e g r a t o r
![Page 38: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/38.jpg)
38 C O M E T 2 0 1 7
D e si g n D e c i si o n s 1 2 . 4 7 k V
W i t h a l l o f t h e r e q u i r e m e n t s a n d c o n s t r a i n t s a c c o u n t e d f o r , i t w a s t i m e t o b e g i n t h e d e c i s i o n
m a k i n g p r o c e s s f o r t h e t y p e s o f i n t e r c o n n e c t e q u i p m e n t t o b e u s e d f o r t h i s p r o j e c t
U t i l i t y E x t e r n a l D i s c o n n e c t s
12.47kV: Switchgear fault interrupter vs.
Pole-mounted recloser
480V: Manual disconnect for transformer maintenance
E R C O T - P o l l e d S e t t l e m e n t M e t e r s
Primary metered vs. Secondary metered
C o m m u n i c a t i o n s L o g i c P r o c e s s o r
Location: Substation control house vs. distribution circuit
I n t e r c o n n e c t i o n T r a n s f o r m e r
12.47kV to 480V DG Transformer
Wye-grounded to delta-ungrounded vs.
Delta to wye-ungrounded
![Page 39: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/39.jpg)
39 C O M E T 2 0 1 7
I s l and Mode
IEEE 1547 currently prohibits a DG facility from
controlling the voltage at the point of interconnection.
This may change in the future and AE was interested in
creating a design for the ESS that would also be
capable of islanding in the future.
The main obstacles to creating an island capable design
is having an inverter that could act as a voltage source,
a properly configured interconnect transformer, and a
way for protective relays to be able to detect a fault
when in island mode.
I s l a n d - C a p a b l e D e s i g n
![Page 40: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/40.jpg)
40 C O M E T 2 0 1 7
Primary, 12.47kV: Wye-grounded
Secondary, 480V: Delta (ungrounded)
Advantages:
• No overvoltage for ground faults on KB-1
• *Would provide zero sequence current source in
island mode
Disadvantages:
• Not on contract – long approval process
• Manufacturer lead time
• Unfamiliar equipment for field crews
• *Additional zero sequence current during KB
ground fault
• Could require a neutral impedance to ensure
proper operation of ground fault relaying
Y- D Tr a n s f o r m e r
C u s t o m E q u i p m e n t
Primary, 12.47kV: Delta
Secondary, 480V: Wye-ungrounded
Advantages:
• Spare transformers available
• Simply remove grounding strap to the XO
bushing
• *No source of zero sequence current to impact
the utility ground relay coordination.
Disadvantages:
During the clearing of a ground fault, it is possible
for the ESS to supply KB-1 in an ungrounded
configuration. This could cause overvoltage
conditions for our customers.
Prohibited from using for islanding for a four-wire,
multi-grounded neutral system (IEEE 1547.4)
D - Y Tr a n s f o r m e r
S t a n d a r d E q u i p m e n t
* I E E E I m p a c t o f D i s t r i b u t e d R e s o u r c e s o n D i s t r i b u t i o n
R e l a y P r o t e c t i o n
![Page 41: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/41.jpg)
41 C O M E T 2 0 1 7
I n i t i a l 12 .47k V D e si g n K B E S S
T h i s d e s i g n f e a t u r e d a s w i t c h g e a r t h a t i n c l u d e d a p r i m a r y m e t e r i n g c a b i n e t i n o r d e r t o r e d u c e t h e
e q u i p m e n t f o o t p r i n t . T h i s s w i t c h g e a r, a l o n g w i t h a p r o p e r i n t e r c o n n e c t t r a n s f o r m e r, w o u l d h a v e
a l l o w e d t h e s y s t e m t o b e i s l a n d c a p a b l e .
All components of the KB ESS would reside within the
KB substation.
W i t h i n K B S u b s t a t i o n
System VI switchgear with primary metering cabinet,
remote supervisory control, and a communications
logic processor to transfer trip all KB-1 DG devices.
S w i t c h g e a r
A wye-grounded to delta ungrounded 12.47kV to 480V
transformer was considered in order to act as a zero
sequence current source when in island mode.
D G T r a n s f o r m e r
![Page 42: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/42.jpg)
42 C O M E T 2 0 1 7
![Page 43: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/43.jpg)
43 C O M E T 2 0 1 7
Fi n a l 12 .47k V D e si g n K B E S S
T h i s d e s i g n u t i l i z e d s t a n d a r d d i s t r i b u t i o n e q u i p m e n t a n d k e p t p r o j e c t t i m e l i n e s / b u d g e t s w i t h i n
t h e i r l i m i t s . P l a c i n g t h e E S S i n i s l a n d m o d e w o u l d r e q u i r e a d d i n g e q u i p m e n t i n t h e f u t u r e .
ESS and interconnection equipment will not reside in
the same confined area.
I n s i d e / O u t s i d e o f K B S u b
12.5kA standard DG recloser with additional
communication equipment for transfer tripping.
P o l e - m o u n t e d R e c l o s e r
Standard distribution transformer used (delta to wye-
ungrounded).
D G T r a n s f o r m e r
![Page 44: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/44.jpg)
44 C O M E T 2 0 1 7 Kingsbery Energy Storage System Final Interconnection Design
![Page 45: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/45.jpg)
45 C O M E T 2 0 1 7
CLP
La Loma Community Solar Recloser
La Loma Community Solar Main Bkr
Kingsbery Energy Storage System Direct Transfer Tripping
![Page 46: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/46.jpg)
46 C O M E T 2 0 1 7
CLP
Kingsbery Energy Storage System 480V Direct Transfer Trip
when KB-PCS1 is open via SEL-751A (not shown)
Trip also helped to
dramatically reduce the arc flash incident energy.
![Page 47: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/47.jpg)
47 C O M E T 2 0 1 7
Kingsbery Energy Storage System Protection One-Line
![Page 48: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/48.jpg)
48 C O M E T 2 0 1 7
Syst em Im p ac t s I m p a c t S t u d y , P a r t 1
As expected, the equipment fault
ratings were not exceeded by the
limited fault contributions from an
inverter-based DG.
Fa u l t Ra t i n g s
Completed arc flash analysis on
both the 12.47kV system and the
480V system.
A r c F l a s h
All DER equipment was certified
and suitable for interconnecting.
UL 1741 devices removed the
potential for unintentional islanding.
D ER Eq u i p .
All devices coordinate from the 480V
system up through the KB-1 feeder
breaker.
Co o r d i n a t i o n
![Page 49: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/49.jpg)
49 C O M E T 2 0 1 7
48 0 V A rc Flash Valu es I m p a c t S t u d y , P a r t 1
![Page 50: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/50.jpg)
50 C O M E T 2 0 1 7
D ist r ib u t io n Plan n in g I m p a c t S t u d y , P a r t 2
Voltage changes, rises, and dips
were seen to be less than 1%.
The addition of the ESS did not
overload any distribution lines.
V o l t a g e / O L
KB-123 transformer tap changer
not impacted and remained at the
original tap position each time
the ESS connected to the grid.
T a p C h a n g e r
943.6kVAR will need to be added to
maintain KB-1’s original power factor
k V A R
Will be determined once we know
how often the ESS will connect and
disconnect within a typical one-hour
time frame of operation.
F l i c k e r
![Page 51: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/51.jpg)
51 C O M E T 2 0 1 7
IN STALLATION
![Page 52: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/52.jpg)
52 C O M E T 2 0 1 7
Clockwise, from upper left:
Battery module delivery on-site,
Battery module installation,
AE crews discuss BMS with battery
representative, Completed install,
Electrical connection of battery modules,
Inside the battery container
KB E S S IN S TA LLA TIO N
![Page 53: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/53.jpg)
53 C O M E T 2 0 1 7
Pole-Mounted Recloser
12.47kV/480V Transformer
Primary Metering Cabinet
Disconnect Enclosure
Power Conversion System
K i n g s b e r y En e r g y St o r a g e Sy s t e m
K i n g s b e r y E n e r g y S t o r a g e S y s t e m
Battery Container
![Page 54: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/54.jpg)
54 C O M E T 2 0 1 7
L a L o m a C o m m u n i t y So l a r
![Page 55: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/55.jpg)
55 C O M E T 2 0 1 7
K i n g s b e r y Su b s t a t i o n
K i n g s b e r y En e r g y St o r a g e Sy s t e m 1. 5 M W / 3 M W h
L a L o m a C o m m u n i t y So l a r
2 . 5 M W
![Page 56: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/56.jpg)
56 C O M E T 2 0 1 7
CON TROL & M ON ITORIN G
![Page 57: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/57.jpg)
57 C O M E T 2 0 1 7
IN TEGRA TED CO N TRO LLER K B E S S
S i t e l e v e l c o n t r o l o f f e r i n g 11 o p e r a t i n g m o d e s
R E A L P O W E R Limited Watts Charge/Discharge Peak Power Limiting Load/Generation Following Real Power Smoothing
R E A C T I V E P O W E R Fixed Power Factor Power Factor Correction Volt/VAR
V O L T A G E / F R E Q U E N C Y Dynamic Volt-Watt Automatic Generation Control (AGC) Spinning Reserves
![Page 58: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/58.jpg)
58 C O M E T 2 0 1 7 ARCHITECTURE
Utility-Scale Energy Storage
System
![Page 59: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/59.jpg)
59 C O M E T 2 0 1 7 CO N TRO L H IERA RCH Y
D E R O p t i m i z e r p r o v i d e s b u l k p o w e r s y s t e m c o n t r o l
C o n n e c t s d i r e c t l y t o A D M S a n d D a t a H i s t o r i a n
I n p u t s i n c l u d e m a r k e t s i g n a l s , f o r e c a s t s , g r i d d a t a
C i r c u i t M a n a g e r p r o v i d e s c o n t r o l a t d i s t r i b u t i o n c i r c u i t l e v e l
P r o v i d e s s u p p o r t f o r v o l t a g e c o n t r o l a l g o r i t h m
I n t e l l i g e n t C o n t r o l l e r p r o v i d e s l o c a l c o n t r o l f o r a s i n g l e e n e r g y s t o r a g e s i t e
D e s i g n e d t o t a l k t o o t h e r g r i d d e v i c e s
T r i e s t o m a k e a s m a n y d e c i s i o n s a s i t c a n l o c a l l y
DERO
DG- IC
DG- CM
![Page 60: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/60.jpg)
60 C O M E T 2 0 1 7
V o l t a g e S u p p o r t f o r T r a n s m i s s i o n
P e a k L o s s A v o i d a n c e T r a n s m i s s i o n
C o n s t r a i n t A v o i d a n c e
S o l a r V a r i a n c e W i n d V a r i a n c e
P e a k L o a d R e d u c t i o n ( 4 - C P ) D a y - A h e a d E n e r g y A r b i t r a g e R e a l - T i m e P r i c e D i s p a t c h
F a s t F r e q u e n c y R e s p o n s e E m e r g e n c y R e s p o n s e S e r v i c e R e g u l a t i o n U p / D o w n
D E R C o n t r o l S y s t e m
R e n e w a b l e I n t e g r a t i o n
E n e r g y M a r k e t
O p e r a t i o n s
A n c i l l a r y S e r v i c e s
D i s t r i b u t i o n O p e r a t i o n s
S u p p o r t
T r a n s m i s s i o n O p e r a t i o n s
S u p p o r t
C u s t o m e r V a l u e
C o n g e s t i o n M a n a g e m e n t V o l t a g e S u p p o r t H a r m o n i c s L o s s A v o i d a n c e P o w e r F a c t o r C o r r e c t i o n
D e m a n d C h a r g e R e d u c t i o n
B a c k - u p P o w e r T i m e o f U s e
D E R VALU E AP P LIC ATIO N S
![Page 61: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/61.jpg)
61 C O M E T 2 0 1 7
V o l t a g e S u p p o r t f o r T r a n s m i s s i o n
P e a k L o s s A v o i d a n c e T r a n s m i s s i o n
C o n s t r a i n t A v o i d a n c e
S o l a r V a r i a n c e W i n d V a r i a n c e
P e a k L o a d R e d u c t i o n ( 4 - C P ) D a y - A h e a d E n e r g y A r b i t r a g e R e a l - T i m e P r i c e D i s p a t c h
F a s t F r e q u e n c y R e s p o n s e E m e r g e n c y R e s p o n s e S e r v i c e R e g u l a t i o n U p / D o w n
D E R C o n t r o l S y s t e m
R e n e w a b l e I n t e g r a t i o n
E n e r g y M a r k e t
O p e r a t i o n s
A n c i l l a r y S e r v i c e s
D i s t r i b u t i o n O p e r a t i o n s
S u p p o r t
T r a n s m i s s i o n O p e r a t i o n s
S u p p o r t
C u s t o m e r V a l u e
C o n g e s t i o n M a n a g e m e n t V o l t a g e S u p p o r t H a r m o n i c s L o s s A v o i d a n c e P o w e r F a c t o r C o r r e c t i o n
D e m a n d C h a r g e R e d u c t i o n
B a c k - u p P o w e r T i m e o f U s e
D E R VALU E AP P LIC ATIO N S
![Page 62: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/62.jpg)
62 C O M E T 2 0 1 7
D ER VA LUE STA CKIN G
A PPL I CA TI O N B EN EFI T
MA
RK
ET
U t i l i t y P e a k L o a d R e d u c t i o n
P o t e n t i a l f o r h i g h e c o n o m i c v a l u e
D a y - A h e a d E n e r g y A r b i t r a g e
I n c r e a s e f l e x i b i l i t y o f d a y - a h e a d p l a n n i n g
R e a l - T i m e P r i c e D i s p a t c h
H i g h v a l u e p e r e n e r g y t h r o u g h p u t
RE
LIA
BIL
ITY
V o l t a g e S u p p o r t R e d u c e l o s s e s a n d i n c r e a s e P V g e n e r a t i o n
D i s t r i b u t i o n C o n g e s t i o n
M a n a g e m e n t
I n c r e a s e l o c a l g r i d r e l i a b i l i t y
CU
ST
OM
ER
D e m a n d C h a r g e R e d u c t i o n
C u s t o m e r a n d s y s t e m b e n e f i t
M A R K E T V A L U E Economic dispatch based on market products and services
R E L I A B I L I T Y V A L U E Benefits to the grid in the form of real-time support or deferred
build
C U S T O M E R V A L U E Reduction in bill charges or increase in reliability support provided
directly to the customer
![Page 63: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/63.jpg)
63 C O M E T 2 0 1 7
D ERO A PPL I CA TI O N
KB
ES
S
MU
ES
S
Ag
g. P
V/E
SS
(c
om
me
rcia
l)
Ag
g. P
V/E
SS
(r
esi
den
tial
)
So
lar
PV
(r
esi
den
tial
)
MA
RK
ET
U t i l i t y P e a k Lo a d R e d u c t i o n
D a y - A h e a d E n e r g y A r b i t r a g e
R e a l - T i m e P r i c e D i s p a t c h
RE
LIA
BIL
ITY
V o l t a g e S u p p o r t
D i s t r i b u t i o n C o n g e s t i o n M a n a g e m e n t
CU
ST
D e m a n d C h a r g e R e d u c t i o n
![Page 64: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/64.jpg)
64 C O M E T 2 0 1 7
D ERO RESO URCE PA GE
![Page 65: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/65.jpg)
65 C O M E T 2 0 1 7
Illustrative
Discharging threshold
D A Y- A H EA D EN ERGY A RBITRA GE
![Page 66: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/66.jpg)
66 C O M E T 2 0 1 7 D A Y- A H EA D EN ERGY A RBITRA GE
![Page 67: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/67.jpg)
Interval Ending Deployed Energy Actual Energy SoC Scheduled SoC Actual
Deployed vs Actual
Value Generation
Interval Ending Energy Price Internal Revenue Accumulated Revenue
Ener
gy (M
Wh)
Pr
ice
($/M
Wh)
Reve
nue
($)
Stat
e of
Cha
rge
(%)
charging
discharging
![Page 68: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/68.jpg)
68 C O M E T 2 0 1 7
L o a d s e r v e d b y l o c a l s o l a r ( % k W h )
Sy s t e m L C O E t o
s e r v e l o a d
( $ / k W h )
B A SE L I N E N o n e w S H I N E S a s s e t s i n s t a l l e d
B a s e l i n e + A l l A s s e t s + H o l i s t i c C o n t r o l s
B A SE L I N E + A L L A SSE T S N o c o n t r o l s
B A SE L I N E + A L L A SSE T S A u t o n o m o u s c o n t r o l s
SH I N E S So l u t i o n
+ SO L A R / ST O R A G E A SSE T N o c o n t r o l s
W i t h c o n t r o l s
Δ S y s t e m LC O E S H I N E S
Δ S y s t e m LC O E B A S E
H O LIS TIC VALU E o f D E R
![Page 69: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/69.jpg)
69 C O M E T 2 0 1 7
Init ial Capacit y YEAR 1 YEAR 2 YEAR 3 …
Warrantied Capacity [%] 100% 94% 89% 85%
Adjusted Warrantied Capacity [%] -- 94% 88% 82%
Average SOC Reduction -- -1% -- -2%
Average Temp Reduction -- -- -1.5% --
Annual Energy Reduction -- -- -- -1%
Annual DC Charge/Discharge
Reduction -- -- -0.5% --
Cumulative Reduction 0% -1% -3% -6%
Adjusted Warrantied Capacity [%] 100% 93% 86% 79%
W A RRA N TY B a t t e r y E n e r g y S t o r a g e
B a t t e r y m o d u l e s c o m e w i t h a e x p e c t e d d e g r a d a t i o n c u r v e , u s u a l l y u n d e r w a r r a n t y
A n i n n o v a t i v e a p p r o a c h p r o v i d e s a d d e d f l e x i b i l i t y, r e c o g n i z i n g m o r e t h a n o n e o p e r a t i o n a l u s e - c a s e
Capacity reduction if annual average state of charge
exceeds a predefined threshold
A V E R A G E S O C
Capacity reduction if average hourly ambient temperature
falls outside a tolerance band
Larger reduction as tolerance bands deviate further from
acceptable range
A V E R A G E T E M P E R A T U R E
Capacity reduction if cumulative annual discharge energy
exceeds a predefined threshold (varies by year)
Also includes limits on cycles/day and mandatory rest times
A N N U A L E N E R G Y
Capacity reduction if annual average DC charge/discharge
power exceeds a kW threshold per battery rack
A N N U A L D C C H A R G E / D I S C H A R G E
![Page 70: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/70.jpg)
70 C O M E T 2 0 1 7
CON CLUSION S
![Page 71: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/71.jpg)
71 C O M E T 2 0 1 7
O n g o i n g Su p p o r t K i n g s b e r y E S S
T h e f o l l o w i n g w o r k g r o u p s w i l l c o n t i n u e t o o p e r a t e a n d m a i n t a i n t h e e n e r g y s t o r a g e s y s t e m :
D i s t r i b u t i o n C o n s t r u c t i o n
T r o u b l e s h o o t e r s
S y s t e m E n g i n e e r i n g
E l e c t r i c a l M a i n t e n a n c e
C o n t r o l E n g i n e e r i n g
C o m p l e x M e t e r i n g
O & M S e r v i c e s
P r o g r a m S u p p o r t
E n e r g y M a r k e t O p e r a t i o n s
![Page 72: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/72.jpg)
72 C O M E T 2 0 1 7
P r o j e c t Tak e aw ay s K i n g s b e r y E n e r g y S t o r a g e S y s t e m
A u s t i n E n e r g y i s n o d i f f e r e n t f r o m o t h e r u t i l i t i e s t h a t l o o k t o s t a n d a r d i z e e q u i p m e n t a n d p r o c e s s e s a s
m u c h a s p o s s i b l e . H e r e a r e a f e w t h i n g s w e l e a r n e d a l o n g t h e w a y f r o m t h i s n o n - s t a n d a r d p r o j e c t :
Cu l t u r e M a t t e r s
Make a concerted effort to
educate the team about
DERs and how they help
both our customers and our
utilities. There must be buy
in for a successful project.
Ex p e r t i se D e p t h
Distribution engineering
does not typically require
the skillset required for a
project like SHINES. Get
the expertise and build a
“bench” to support.
P r o j e c t Sc r u t i n y Q A / Q C
Quality assurance and
quality control are
extremely difficult when
dealing with multiple
consultants and
workgroups.
I n t e r c o n n e c t Gu i d e
Spend the time to develop
and train your teams on the
interconnection guide.
Project schedules and
contracts require immense
scrutiny to avoid delays and
less than optimal designs.
![Page 73: W EL C O M E T O A C O M E T 2 0 17 - CEM](https://reader033.vdocuments.us/reader033/viewer/2022053104/6291b5439b37651c8a68e5db/html5/thumbnails/73.jpg)
73 C O M E T 2 0 1 7
GET IN TOUCH
J o s h . C o n t r e r a s @ a u s t i n e n e r g y. c o m
w w w. a u s t i n e n e r g y. c o m / g o / S H I N E S
L i s a . M a r t i n @ a u s t i n e n e r g y. c o m
JOSH CONTRERAS LISA MARTIN AUSTIN ENERGY
SMART GRID & SYSTEM OPERATIONS
.