vt report on foundation

Upload: manish-singh

Post on 04-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 vt report on foundation

    1/47

    1

    ACKNOWLEDGMENT

    Before we get to more important things, we would like to thank numerous people,

    without whom our summer training would have been very difficult.

    We would like to thank National Building Construction Corporation Limited for

    providing us with the necessary, whole-hearted guidance and valuable suggestions

    throughout our training period, without which this endeavor would not have been

    possible.

    We are very grateful to Mr. M. Manna, Regional Manager & Mr. P.Saha, Project In-

    charge, for their continuous support. We thank Mr Sagar Sahoo & Mr. Rajiv Rao,

    Planning, for guiding us right from the start.

    We profoundly express our gratitude to Mr. Kamal Bhattacharya, for being kind &

    helpful in getting us the summer training.

    Finally, We acknowledge each and every member of staff at the construction site , for

    their wholehearted co-operation, which made our summer training comfortable and

    successful.

  • 7/29/2019 vt report on foundation

    2/47

    2

    NATIONAL BUILDING CONSTRUCTION

    CORPORATION PROFILE

    YEAR OF INCORPORATION

    NBCC was incorporated in November 1960 as a wholly owned Government of India

    undertakingunder the erstwhile Ministry of Works, Housing & Supply ("MoWHS"), which is

    now known as the Ministry of Urban Development ("MoUD").

    AN ISO COMPANY

    ISO 9001:2008 Certification has been awarded to NBCC for its Project Management and

    Consultancy Divisions. ISO 9001:2008 certification issued by Bureau of Indian Standards is

    valid up to March 2014.

    AUTHORISED CAPITAL

    The authorized, issued and paid-up equity share capital is Rs. 120 crore. This includes Rs.

    30 crore of fully paid-up bonus shares to the existing share holder s as on 30-09-2011.

    PERFORMANCE RECOGNITION

    On October 14, 2008, the Government granted NBCCSchedule "A" PSU status. NBCC has

    also been awarded ISO 9001:2008 from the Bureau of Indian Standards in respect of our

    consultancy and project management division. NBCC has also received "Excellent" rating

    from MoUD for each of the Fiscal years from 2004 to 2010 and Ministry of Heavy Industries

    & Public Enterprises has awarded us with an "Excellence Award". MoUD grants us

    "Excellent" rating if all the targets set out in the MoU with MoUD for the respective Fiscal

    year are acheived. Further, in 2011, for one of our PMC projects, we were awarded an

    "Appreciation Shield" for quality and timely completion of NSEZ Noida Project by the

    Ministry of Commerce & Industry and the Development Commissioner, NSEZ.

  • 7/29/2019 vt report on foundation

    3/47

    3

    AREAS OF OPERATION

    NBCC is one of the few public sector companies engaged in the business of

    (i) project management consultancy services for civil construction projects ("PMC")

    (ii) civil infrastructure for power sector and real estate development.

    NBCC is headquartered in New Delhi and in addition has 10 regional / zonal offices across

    India. The projects undertaken by our Company are spread across 23 states and 1 union

    territory in India. In addition, NBCC has also have also undertaken projects overseas.

    NBCC's PMC business segment includes providing management and consultancy services

    for a range of civil construction projects including residential and commercial complexes,

    redevelopment of buildings and colonies, hospitals, educational institutions; infrastructure

    works for security personnel, border fencing as well as infrastructure projects such asroads, water supply systems, storm water systems and water storage solutions.

    NBCC's civil Infrastructure for power sector segment includes providing engineering and

    construction services for power projects, including design and execution of (i) civil and

    structural works for power projects (ii) Cooling towers (iii) Chimneys.

    NBCC's real estate development segment focuses on principally two types of projects,

    namely, (i) residential projects, such as apartments and townships and (ii) commercial

    projects, such as corporate office buildings and shopping malls.

    COMPUTERIZATION AND TRANSPARENCY

    NBCC makes extensive use of information and communication technologies for the

    execution and management of its projects. NBCC has implemented Enterprise Resource

    Planning ("ERP") system in some business processes related to accounting, salaries, HRM

    system and e-Bidding system. In addition, NBCC's team has access to domain controller and

    additional domain controller, cluster servers, IT security management, network

    management etc. IT security management is also utilized for the continuous upkeep of

    security products , solutions, products, tools. The online computer maintenance services

    ensures accurate management of the organizations hardware and software complaints

    electronically, including hardware management, complaint tracking, minimum problem

    rectification time, better reports management and optimal performance. NBCC also

    hascentralised its database and has begun digitising its records and has business continuity

    servers to protect the electronic data and ensure maximum uptime.

  • 7/29/2019 vt report on foundation

    4/47

    4

    PROJECT MANAGEMENT CONSULTANCYFOR CIVIL

    CONSTRUCTION PROJECTS ("PMC")

    Our PMC business segment includes providing management and consultancy services for a

    range of civil construction projects including residential and commercial complexes,

    redevelopment of buildings and colonies, hospitals, educational institutions; infrastructure

    works for security personnel, border fencing as well as infrastructure projects such as

    roads, water supply systems, storm water systems and water storage solutions. Some of

    our clients in this segment are or have been, ESIC, Ministry of Defence, Ministry of Home

    Affairs (including Security forces like CRPF, CISF, NSG, BSF), Ministry of External Affairs,

    MoUD, Ministry of Commerce and Industry, Ministry of Corporate Affairs, Ministry of

    Finance, Haryana Urban Infrastructure Development Board, IIT Roorkee, IIT Kharagpur, IITPatna, SVNIT, amongst others.

    Our key completed projects during the period April 01, 2006 tillSeptember 30, 2011, based

    on the total contract value, include road works at Agartala, construction of defence campus

    at Jaipur, Jodhpur, Ahemdabad, Ambala, Sulur, CBI headquarters at New Delhi, Extension of

    campus of MDU university and IIT Roorkee. Our key domestic PMC Ongoing Projects based

    on the total outstanding contract value, include Indo Bangladesh Border Fencing Works at

    Meghalaya, ESIC Hospital, Parel (Mumbai). We presently have one overseas PMC Ongoing

    Project at Male, Maldives for construction of India - Maldives Friendship Faculty of

    Hospitality & Tourism Studies.

    As of September 30, 2011PMC Projects

    Ongoing Projects Forthcoming Projects

    Number of Projects 130 59

    Contract Value (in million) 162,764.24 23,786.40*

    Outstanding Contract Value/ Order Book (in million)

    79,240.52 23,786.40*

  • 7/29/2019 vt report on foundation

    5/47

    5

    REAL ESTATE DEVELOPMENT

    Our real estate development segment focuses on principally two types of projects,

    namely, (i) residential projects, such as apartments and townships and (ii)

    commercial projects, such as corporate office buildings and shopping malls. OurCompany has undertaken real estate projects which are spread across 10 states in

    India. As ofJanuary 15, 2012, our Land Reserves aggregate approximately 127.918

    Acre. Our Land Reserves are located in Delhi, Uttar Pradesh, Patna, Gurgaon,

    Kolkata, Kochi, Alwar and Lucknow.

    As on January 15, 2012, our completed commercial projects include commercial

    complex at Vadodara, Cuttack, Agartala, Ghaziabad (Uttar Pradesh) and at

    BhikajiCama Place, PragatiVihar and PushpVihar in New Delhi. Further, some of our

    key real estate development Ongoing Projects include residential complex at "NBCC

    Heights" at Sector-89, Gurgaon, Haryana; Khekra (Phase-I), Baghpat, Uttar Pradesh;residential-cum-commercial complex at Bahadurpur, Phase-I, Patna; New

    Delhi,Sukias Lane at Kolkata and Hemanta Basu Sarani Complex. The following table

    represents details for types of real estate projects, as of January 15, 2012:

    Type ofReal

    EstateDevelopm

    ent

    CompletedProjects

    Ongoing Projects Forthcoming Projects

    No. ofProjec

    ts

    Developable

    Area

    No. ofProjec

    ts

    Developable Area

    Saleable Area

    Leasable Area

    No. ofProjec

    ts

    Developable Area

    Saleable Area

    Leasable Area

    Residential

    Nil - 4 3,732,0533,410,4

    030 6 5,555,821

    4,878,882

    147,585

    Commercial

    8 1,076,65 3 407,633 239,560 66,624 6 2,323,9081,724,1

    01290,78

    6

    Total 8 1,076,65 7 4,139,6863,649,9

    6366,624 12 7,879,729

    6,602,983

    438,353

  • 7/29/2019 vt report on foundation

    6/47

    6

    CIVIL INFRASTRUCTURE FOR POWER SECTOR

    Our civil Infrastructure for power sector segment includes providing engineering

    and construction services for power projects, including design and execution of (i)

    civil and structural works for power projects (ii) Cooling towers (iii) Chimneys.Some of our clients in this segment include NTPC Limited, BHEL, APGENCO Limited,

    Uttar Pradesh RajyaVidyutUtpadan Nigam Limited, MAHAGENCO Limited and

    Karnataka Power Corporation Limited.

    Our completed key projects, during the period April 01, 2006 till September 30,

    2011based on the total contract value, include construction of civil, structural and

    architectural works for 2x250 MW at Korba, Chattisgarh;Rihand Main Plant , Civil

    Works in Uttar Pradesh our key On-going PMC Projects, based on the total

    outstanding contract value, include cooling tower, chimney at Farakka Super

    Thermal Power Project, West Bengal, ,Koderma Thermal Power Project atJharkhand, Durgapur, Thermal Power Project at West Bengal, Rihand Super Thermal

    Power Project, Uttar Pradesh, Barh Super Thermal Power Project, Patna, Mauda and

    Vindhyachal Super Thermal Projectat Maharashtra & Madhya Pradesh respectively.

    As of September 30, 2011 Civil Infrastructure for power projects(Ongoing Projects)

    Number of projects 14

    Contract Value(` in million) 7,875.43

    Outstanding Contract Value / Order Book(`in million)

    3,199.49

  • 7/29/2019 vt report on foundation

    7/47

    7

    SEQUENCE OF STRUCTURE WORK

    1)Site Clearance

    2)Demarcation of Site

    3)Positioning of Central coordinate ie (0,0,0) as per grid plan

    4)Surveying and layout

    5)Excavation

    6)Laying of PCC

    7)Bar Binding and placement of foundation steel

    8 )Shuttering and Scaffolding

    9)Concreting

    10)Electrical and Plumbing

    11)Deshuttering

    12)Brickwork

    13)Doors and windows frames along with lintels

    14)Wiring for electrical purposes

    15)Plastering

    16)Flooring and tiling work

    17)Painting

    18)Final Completion and handing over the project

  • 7/29/2019 vt report on foundation

    8/47

    8

    PROBLEMS FACED AT SITE

    There were numerous problems which were faced at site. Some of these were

    purely due to the human errors and poor workmanship but some were due to

    unseen factors.

    1. There was a problem in providing beams at one location as per the standarddrawings so the drawings were changed by consulting the structural designersand architect

    2. There was problem pouring concrete in one beam due to small area availablefor pouring and compacting. The solution to this problem was that the size ofsteel was increased but the number of steel bars was decreased so as toprovide the total area same.

    3. No window was there in staircases which lead to complete darkness, so it wasdecided to change the drawing by consulting the concerned authorities.

    4. The depth if beam above the door was 35 earlier but to keep the size of the

    door as per the standard it was changed to 3.

    5.Frequent power cuts lead to increase in the cost of construction as generatorswere used to meet the power requirements

    6.Laying of foundations was postponed by 1 month due to the rainy season.

  • 7/29/2019 vt report on foundation

    9/47

    9

    CONSTRUCTION PROCESS AND MATERIALS USED

    Site Clearance- The very first step is site clearance which involves removal of grass and

    vegetation along with any other objections which might be there in the site location.

    Demarcation of Site- The whole area on which construction is to be done is marked so as toidentify the construction zone. In our project, a plot of 450*350 sq ft was chosen and the

    respective marking was done.

    Positioning of Central coordinate and layout- The centre point was marked with the help of a

    thread and plumb bob as per the grid drawing. With respect to this center point, all the other

    points of columns were to be decided so its exact position is very critical.

    Excavation

    Excavation was carried out both manually as well as mechanically. Normally 1-2 earth

    excavators (JCBs) were used for excavating the soil. Adequate precautions are taken to see thatthe excavation operations do not damage the adjoining structures. Excavation is carried outproviding adequate side slopes and dressing of excavation bottom. The soil present beneath the

    surface was too clayey so it was dumped and was not used for back filling. The filling is done in

    layer not exceeding 20 cm layer and than its compacted. Depth of excavation was 54 from

    Ground Level.

  • 7/29/2019 vt report on foundation

    10/47

    10

    PCCPlain Cement Concrete

    After the process of excavation, laying of plain cement concrete that is PCC is done. A layer of 4

    inches was made in such a manner that it was not mixed with the soil. It provides a solid bas for

    the raft foundation and a mix of 1:5:10 that is, 1 part of cement to 5 parts of fine aggregates and

    10 parts of coarse aggregates by volume were used in it. Plain concrete is vibrated to achieve fullcompaction. Concrete placed below ground should be protected from falling earth during and

    after placing. Concrete placed in ground containing deleterious substances should be kept free

    from contact with such a ground and with water draining there from during placing and for aperiod of seven days. When joint in a layer of concrete are unavoidable, and end is sloped at an

    angle of 30 and junctions of different layers break joint in laying upper layer of concrete. The

    lower surface is made rough and clean watered before upper layer is laid.

    LAYING OF FOUNDATION

    At our site, Raft foundations are used to spread the load from a structure over a large area,

    normally the entire area of the structure. Normally raft foundation is used when large load is to

    be distributed and it is not possible to provide individual footings due to space constraints that is

    they would overlap on each other. Raft foundations have the advantage of reducing differentialsettlements as the concrete slab resists differential movements between loading positions. They

    are often needed on soft or loose soils with low bearing capacity as they can spread the loads

    over a larger area.

    In laying of raft foundation, special care is taken in the reinforcement and construction of plinth

    beams and columns. It is the main portion on which ultimately whole of the structure load is tocome. So a slightest error can cause huge problems and therefore all this is checked and passed

  • 7/29/2019 vt report on foundation

    11/47

    11

    by the engineer in charge of the site.

    Apart from raft foundation, individual footings were used in the mess area which was extended

    beyond the C and D blocks.

  • 7/29/2019 vt report on foundation

    12/47

    12

    ADVANTAGES OF USING PORTLAND POZZOLANA CEMENT OVEROPC

    Pozzolana combines with lime and alkali in cement when water is added and forms compounds

    which contribute to strength, impermeability and sulphate resistance. It also contributes to

    workability, reduced bleeding and controls destructive expansion from alkali-aggregate reaction.

    It reduces heat of hydration thereby controlling temperature differentials, which causes thermalstrain and resultant cracking n mass concrete structures like dams. The colour of PPC comes

    from the colour of the pozzolanic material used. PPC containing fly ash as a pozzolana will

    invariably be slightly different colour than the OPC.One thing should be kept in mind that is thequality of cement depends upon the raw materials used and the quality control measures adopted

    during its manufacture, and not on the shade of the cement. The cement gets its colour from the

    nature and colour of raw materials used, which will be different from factory to factory, and mayeven differ in the different batches of cement produced in a factory. Further, the colour of the

    finished concrete is affected also by the colour of the aggregates, and to a lesser extent by the

    colour of the cement. Preference for any cement on the basis of colour alone is technically

    misplaced.

    SETTLING OF CEMENT

    When water is mixed with cement, the paste so formed remains pliable and plastic for a short

    time. During this period it is possible to disturb the paste and remit it without any deleteriouseffects. As the reaction between water and cement continues, the paste loses its plasticity. This

    early period in the hardening of cement is referred to as setting of cement.

    INITIAL AND FINAL SETTING TIME OF CEMENT

    Initial set is when the cement paste loses its plasticity and stiffens considerably. Final set is the

    point when the paste hardens and can sustain some minor load. Both are arbitrary points andthese are determined by Vicat needle penetration resistance

    Slow or fast setting normally depends on the nature of cement. It could also be due to extraneous

    factors not related to the cement. The ambient conditions play an important role. In hot weather,

    the setting is faster, in cold weather, setting is delayed Some types of salts, chemicals, clay, etc ifinadvertently get mixed with the sand, aggregate and water could accelerate or delay the setting

    of concrete.

    STORAGE OF CEMENT

    It needs extra care or else can lead to loss not only in terms of financial loss but also in terms ofloss in the quality. Following are the dont that should be followed -

    (i) Do not store bags in a building or a godown in which the walls, roof and floor are notcompletely weatherproof.

    (ii) Do not store bags in a new warehouse until the interior has thoroughly dried out

  • 7/29/2019 vt report on foundation

    13/47

    13

    (iii) Do not be content with badly fitting windows and doors, make sure they fit properly and

    ensure that they are kept shut.

    (iv) Do not stack bags against the wall. Similarly, dont pile them on the floor unless it is a dry

    concrete floor. If not, bags should be stacked on wooden planks or sleepers.

    (v) Do not forget to pile the bags close together

    (vi) Do not pile more than 15 bags high and arrange the bags in a header-and-stretcher fashion.

    (vii) Do not disturb the stored cement until it is to be taken out for use.

    (viii) Do not take out bags from one tier only. Step back two or three tiers.

    (ix) Do not keep dead storage. The principle of first-in first-out should be followed in removing

    bags.

    (x) Do not stack bags on the ground for temporary storage at work site. Pile them on a raised, dry

    platform and cover with tarpaulin or polythene sheet.

  • 7/29/2019 vt report on foundation

    14/47

    14

    COARSE AGGREGATE

    Coarse aggregate for the works should be river gravel or crushed stone .It should be hard, strong,

    dense, durable, clean, and free from clay or loamy admixtures or quarry refuse or vegetable

    matter. The pieces of aggregates should be cubical, or rounded shaped and should have granular

    or crystalline or smooth (but not glossy) non-powdery surfaces.Aggregates should be properlyscreened and if necessary washed clean before use.

    Coarse aggregates containing flat, elongated or flaky pieces or mica should be rejected. The

    grading of coarse aggregates should be as per specifications of IS-383.

    After 24-hrs immersion in water, a previously dried sample of the coarse aggregate should not gain in

    weight more than 5%.

    Aggregates should be stored in such a way as to prevent segregation of sizes and avoid

    contamination with fines.

    Depending upon the coarse aggregate color, there quality can be determined as:

    Black => very good quality

    Blue => good

    Whitish =>bad quality

    FINE AGGREGATE

    Aggregate which is passed through 4.75 IS Sieve is termed as fine aggregate. Fine aggregate is

    added to concrete to assist workability and to bring uniformity in mixture. Usually, the natural

    river sand is used as fine aggregate. Important thing to be considered is that fine aggregatesshould be free from coagulated lumps.

    Grading of natural sand or crushed stone i.e. fine aggregates shall be such that not more than 5percent shall exceed 5 mm in size, not more than 10% shall IS sieve No. 150 not less than 45%

    or more than 85% shall pass IS sieve No. 1.18 mm and not less than 25% or more than 60% shall

    pass IS sieve No. 600 micron.

  • 7/29/2019 vt report on foundation

    15/47

    15

    Unit Weight of Materials Used at ConstructionSite

    Following table shows unit weight of materials used at construction site. Please note

    this is for reference purpose only and may vary from place and type of material.

    We are thankful to Engineer Prince Saha for submitting this very useful information

    to us.

    S.No Material Theoretical

    Weight

    in(KG/M)

    Approx Weight at Site

    in

    Remarks

    Kg Per

    1 Cement 1440 50 Bag

    2 Steel 7850 d/162 d -dia in mm

    3 Sand-

    Dry 1600 50 to 55 farma 1 farma=1.25cft

    River 1840 57 to 63 farma 1 farma=1.25cft

    4 Stone(basalt) 2850 to 2960 48 to 52 farma metal 12mm to 20mm

    5 Water 1000 1 liter

    6 PCC 2240 8.24 to 8.5 Cubemould

    cube mouldsize=15x15x15cm

    7 RCC 2% Steel 2420

    8 Bricks 1600 to 1920 1.9 to 2 no 9x4x2 3/4

    4.8 to 4.9 no 9x6x3 3/4

    9 Brick Masonry 1920

    10 Soil(damp) 1760 50 to 55 cft Black cotton

    11 Cement concrete

    block(solid)

    1800 18 to 20 cft 30x15x20 cm

    10 to 11 no 30x10x20 cm

    12 Cement Mortar 2080 57 to 62 cft

    13 Lime Mortar 1760 48 to 52 cft14 Lime 640 30 bag

    15 Glass 2530 0.9 to 0.95 sft 4mm tk plain

    16 Teak Wood 670 to 830 18 to 20 cft

    17 Sal Wood 990 22 to 24 cft

    18 Marble mosaic tile 2.8 to 3.2 no 25x25x22mm

    4.8 to 5.2 no 30x30x25mm

  • 7/29/2019 vt report on foundation

    16/47

    16

    19 Chequered tile 2.5 to 2.8 no 25x25x22mm

    20 Glazed tile15x15cm 0.20 to 0.25 no 5mm tk

    21 Marble Stone 2620 5.1 sft 3/4tk

    22 Granite Stone 2460-2800 5.35 sft 3/4tk

    23 Coddappa 2720 6.4 sft 1 1/4tk

    24 A.C.sheet corrugated 16 1.2 sft

    25 Bitumen 1040 220 Drum 200liter drum

    26 Window frame (simpledesign)

    1.9 to2.1 sft

    27 Door Frame

    a)30070 25 to 27 no section 4x2 1/2

    b)26x70 24 to 26 no section 4x2 1/2

    BRICKWORK

    Brickwork is masonry done with bricks and mortar and is generally used to build partition walls.

    In our site, all the external walls were of concrete and most of the internal walls were made ofbricks. English bond was used and a ration of 1:4 (1 cement: 4 coarse sand) and 1:6 were used

    depending upon whether the wall is 4.5 inches or 9 inches. The reinforcement shall be 2 nos.

    M.S. round bars or as indicated. The diameter of bars was 8mm. The first layer of reinforcement

    was used at second course and then at every fourth course of brick work. The bars were properlyanchored at their ends where the portions and or where these walls join with other walls. The in

    laid steel reinforcement was completely embedded in mortar.

    STRENGTH OF BRICK MASONRY

    The permissible compressive stress in brick masonry depends upon the following factors:

    1. Type and strength of brick.

    2. Mix of motor.

    3. Size and shape of masonry construction.

    The strength of brick masonry depends upon the strength of bricks used in the masonry

    construction. The strength of bricks depends upon the nature of soil used for making and the

    method adopted for molding and burning of bricks .since the nature of soil varies from region toregion ,the average strength of bricks varies from as low as 30kg/sq cm to 150 kg /sq cm the

    basic compressive stress are different crushing strength.

    There are many checks that can be applied to see the quality of bricks used on the site.Normally

    the bricks are tested for Compressive strength, water absorption, dimensional tolerances and

  • 7/29/2019 vt report on foundation

    17/47

    17

    efflorescence. However at small construction sites the quality of bricks can be assessed based on

    following, which is prevalent in many sites.

    Visual check Bricks should be well burnt and of uniform size and color.

    Striking of two bricks together should produce a metallic ringing sound.

    It should have surface so hard that cant be scratched by the fingernails.

    A good brick should not break if dropped in standing position from one metre above ground

    level.

    A good brick shouldnt absorb moisture of more than 15-20% by weight, when soaked in water

    For example; a good brick of 2 kg shouldnt weigh more than 2.3 to 2.4 kg if immersed inwater for 24 hours.

    PRECAUTIONS TO BE TAKEN IN BRICK MASONRY WORK

    Bricks should be soaked in water for adequate period so that the water penetrates

    to its full thickness. Normally 6 to 8 hours of wetting is sufficient.

    A systematic bond must be maintained throughout the b rickwork. Vertical joints

    shouldnt be continuous but staggered.

    The joint thickness shouldnt exceed 1 cm. It should be thoroughly filled with the

  • 7/29/2019 vt report on foundation

    18/47

    18

    cement mortar 1:4 to 1:6 (Cement: Sand by volume)

    All bricks should be placed on their bed with frogs on top (depression on top of the

    brick for providing bond with mortar).

    Thread, plumb bob and spirit level should be used for alignment, verticality and

    horizontality of construction.

    Joints should be raked and properly finished with trowel or float, toprovide good bond.

    A maximum of one metre wall height should be constructed in a day.

    Brickwork should be properly cured for at least 10 days

    REINFORCEMENT

    Steel reinforcements are used, generally, in the form of bars of circular cross section in concrete

    structure. They are like a skeleton in human body. Plain concrete without steel or any otherreinforcement is strong in compression but weak in tension. Steel is one of the best forms of

    reinforcements, to take care of those stresses and to strengthen concrete to bear all kinds of loads

    Mild steel bars conforming to IS: 432 (Part I) and Cold-worked steel high strength deformed bars

    conforming to IS: 1786 (grade Fe 415 and grade Fe 500, where 415 and 500 indicate yield

    stresses 415 N/mm2 and 500 N/mm2 respectively) are commonly used. Grade Fe 415 is beingused most commonly nowadays. This has limited the use of plain mild steel bars because of

    higher yield stress and bond strength resulting in saving of steel quantity. Some companies havebrought thermo mechanically treated (TMT) and corrosion resistant steel (CRS) bars with added

    features.

    Bars range in diameter from 6 to 50 mm. Cold-worked steel high strength deformed bars start

    from 8 mm diameter. For general house constructions, bars of diameter 6 to 20 mm are used

    Transverse reinforcements are very important. They not only take care of structural requirementsbut also help main reinforcements to remain in desired position. They play a very significant role

    while abrupt changes or reversal of stresses like earthquake etc.

    They should be closely spaced as per the drawing and properly tied to the main/longitudinalreinforcement

    TERMS USED IN REINFORCEMENT

    BAR-BENDING-SCHEDULE

    Bar-bending-schedule is the schedule of reinforcement bars prepared in advance before cutting

  • 7/29/2019 vt report on foundation

    19/47

    19

    and bending of rebars. This schedule contains all details of size, shape and dimension of rebars to

    be cut.

    LAP LENGTH

    Lap length is the length overlap of bars tied to extend the reinforcement length.. Lap length about50 times the diameter of the bar is considered safe. Laps of neighboring bar lengths should be

    staggered and should not be provided at one level/line. At one cross section, a maximum of 50%

    bars should be lapped. In case, required lap length is not available at junction because of spaceand other constraints, bars can be joined with couplers or welded (with correct choice of method

    of welding).

    ANCHORAGE LENGTH

    This is the additional length of steel of one structure required to be inserted in other at thejunction. For example, main bars of beam in column at beam column junction, column bars infooting etc. The length requirement is similar to the lap length mentioned in previous question or

    as per the design instructions

    COVER BLOCK

    Cover blocks are placed to prevent the steel rods from touching the shuttering plates and there by

    providing a minimum cover and fix the reinforcements as per the design drawings. Sometimes it

    is commonly seen that the cover gets misplaced during the concreting activity. To prevent this,tying of cover with steel bars using thin steel wires called binding wires (projected from cover

    surface and placed during making or casting of cover blocks) is recommended. Covers should bemade of cement sand mortar (1:3). Ideally, cover should have strength similar to the surroundingconcrete, with the least perimeter so that chances of water to penetrate through periphery will be

    minimized. Provision of minimum covers as per the Indian standards for durability of the whole

    structure should be ensured.

    Shape of the cover blocks could be cubical or cylindrical. However, cover indicates thickness of

    the cover block. Normally, cubical cover blocks are used. As a thumb rule, minimum cover of 2in footings, 1.5 in columns and 1 for other structures may be ensured.

    Structural element Cover to reinforcement (mm)

    Footings 40Columns 40

    Slabs 15

    Beams 25

    Retaining wall 25 for earth face

    20 for other face

  • 7/29/2019 vt report on foundation

    20/47

    20

    THINGS TO NOTE

    Reinforcement should be free from loose rust, oil paints, mud etc. it should be cut, bent and fixedproperly. The reinforcement shall be placed and maintained in position by providing proper

    cover blocks, spacers, supporting bars, laps etc. Reinforcements shall be placed and tied such

    that concrete placement is possible without segregation, and compaction possible by animmersion vibrator.

    Three types of bars were used in reinforcement of a slab. These include straight bars, crank barand an extra bar. The main steel is placed in which the straight steel is binded first, then the

    crank steel is placed and extra steel is placed in the end. The extra steel comes over the support

    while crank is encountered at distance of (1-distance between the supports) from thesurroundings supports.

    For providing nominal cover to the steel in beam, cover blocks were used which were made ofconcrete and were casted with a thin steel wire in the center which projects outward. These keep

    the reinforcement at a distance from bottom of shuttering. For maintaining the gap between themain steel and the distribution steel, steel chairs are placed between them

    SHUTTERING AND SCAFFOLDING

    DEFINITION

    The term SHUTTERING or FORMWORK includes all forms, moulds, sheeting, shuttering

    planks, walrus, poles, posts, standards, leizers, V-Heads, struts, and structure, ties, prights,

    walling steel rods, bolts, wedges, and all other temporary supports to the concrete during theprocess of sheeting.

  • 7/29/2019 vt report on foundation

    21/47

    21

    FORM WORK

    Forms or moulds or shutters are the receptacles in which concrete is placed, so that it will have

    the desired shape or outline when hardened. Once the concrete develops adequate strength, the

    forms are removed. Forms are generally made of the materials like timber, plywood, steel, etc.

    Generally camber is provided in the formwork for horizontal members to counteract the effect ofdeflection caused due to the weight of reinforcement and concrete placed over that. A proper

    lubrication of shuttering plates is also done before the placement of reinforcement. The oil film

    sandwiched between concrete and formwork surface not only helps in easy removal of shutteringbut also prevents loss of moisture from the concrete through absorption and evaporation.

    The steel form work was designed and constructed to the shapes, lines and dimensions shown on

    the drawings. All forms were sufficiently water tight to prevent leakage of mortar. Forms wereso constructed as to be removable in sections. One side of the column forms were left open and

    the open side filled in board by board successively as the concrete is placed and compacted

    except when vibrators are used. A key was made at the end of each casting in concrete columnsof appropriate size to give proper bondings to columns and walls as per relevant IS.

    CLEANING AND TREATMENT OF FORMS

    All rubbish, particularly chippings, shavings and saw dust, was removed from the interior of theforms (steel) before the concrete is placed. The form work in contact with the concrete was

    cleaned and thoroughly wetted or treated with an approved composition to prevent adhesion

    between form work and concrete. Care was taken that such approved composition is kept out ofcontact with the reinforcement.

  • 7/29/2019 vt report on foundation

    22/47

    22

    DESIGN

    The form-work should be designed and constructed such that the concrete can be properly placedand thoroughly compacted to obtain the required shape, position, and levels subject

    ERECTION OF FORMWORK

    The following applies to all formwork:

    a) Care should be taken that all formwork is set to plumb and true to line and level.

    b) When reinforcement passes through the formwork care should be taken to ensure close

    fitting joints against the steel bars so as to avoid loss of fines during the compaction of

    concrete.

    c) If formwork is held together by bolts or wires, these should be so fixed that no iron is

    exposed on surface against which concrete is to be laid.

    d) Provision is made in the shuttering for beams, columns and walls for a port hole of

    convenient size so that all extraneous materials that may be collected could be

    removed just prior to concreting.

    e) Formwork is so arranged as to permit removal of forms without jarring the concrete.

    Wedges, clamps, and bolts should be used where practicable instead of nails.

    f) Surfaces of forms in contact with concrete are oiled with a mould oil of approved

    quality. The use of oil, which darkens the surface of the concrete, is not allowed. Oiling

    is done before reinforcement is placed and care taken that no oil comes in contact with

    the reinforcement while it is placed in position. The formwork is kept thoroughly wet

    during concreting and the whole time that it is left in place.

    Immediately before concreting is commenced, the formwork is carefully examined to

    ensure the following:

    a) Removal of all dirt, shavings, sawdust and other refuse by brushing and washing.

  • 7/29/2019 vt report on foundation

    23/47

    23

    b) The tightness of joint between panels of sheathing and between these and any hardened core.

    c) The correct location of tie bars bracing and spacers, and especially connections of

    bracing.

    d) That all wedges are secured and firm in position.

    e) That provision is made for traffic on formwork not to bear directly on reinforcement

    steel.

    VERTICALITY OF THE STUCTURE

    All the outer columns of the frame were checked for plumb by plumb-bob as the work proceeds

    to upper floors. Internal columns were checked by taking measurements from outer row of

    columns for their exact position. Jack were used to lift the supporting rods called props

    STRIPPING TIME OR REMOVAL OF FORMWORK

    Forms were not struck until the concrete has attained a strength at least twice the stress to whichthe concrete may be subjected at the time of removal of form work. The strength referred is that

    of concrete using the same cement and aggregates with the same proportions and cured under

    conditions of temperature and moisture similar to those existing on the work. Where so required,

    form work was left longer in normal circumstances

    Form work was removed in such a manner as would not cause any shock or vibration that would

    damage the concrete. Before removal of props, concrete surface was exposed to ascertain that theconcrete has sufficiently hardened. Where the shape of element is such that form work has re-

    entrant angles, the form work was removed as soon as possible after the concrete has set, to

    avoid shrinkage cracking occurring due to the restraint imposed. As a guideline, withtemperature above 20 degree following time limits should be followed:

    Structural Component Age

    Footings 1 day

    Sides of beams, columns, lintels, wall 2 days

    Underside of beams spanning less than 6m 14 days

    Underside of beams spanning over 6m 21 days

    Underside of slabs spanning less than 4m 7 daysUnderside of slabs spanning more than 4m 14 days

    Flat slab bottom 21 days

  • 7/29/2019 vt report on foundation

    24/47

    24

    CONCRETE MAKING

    Just mix cement, aggregates and water, cast this mix in a mould, open the mould next

    day. A uniform hard mass will be found, which is known as concrete, any body can makeit. The simplecity in making concrete make this material to be look like very simple in its

    production, yet it as not so simple. Due to ignorance about concrete no other building

    materials ever mis-used as concrete in the construction. In India concrete is being used

    in the construction since the last 70 years. Yet 80% of the builders have no proper

    understanding of this materials. Go to any construction site (except big construction

    sites) you will find that sand and aggregates are being taken in iron tasla or cane baskets

    to charge the mixer without the consideration of site aggregates actual grindings,

    moisture content and bulking of sand. The water is poured in the mixer without any

    measured quantity. It could be well imagine what sort of concrete structure will be

    made with the concrete being produced in this crude method.

    Most of the contractors, builders, masons etc. still follow 1:2:4 or 1:1.5:3 mixes they are

    not aware of Design Mixes and Concrete Admixtures. This paper described how Design

    Mixes can be converted into volume with 1 Bag Cement, 2 Boxes of sand and 4 Boxes of

    Aggregate. The site practical problem is the dispersion of water and liquid admixtures

    into the mixer. For this the site should fabricate a plastic circular graduated measuring

    container of 30 lit capacity with a tap fitted at its bottom. This container is to be fitted

    on top of the mixer. From this container water and liquid admixtures can conveniently

    poured direct into the mixer in a measured quantity.

    EXAMPLE OF MIX DESIGN

    1. For a construction site M-25 Grade of concrete is required to be designed as per IS:

    456-2000. The mix will be taken by volume. Workability required is 50 mm slump.

    Normal Superplasticizer will be used in the mix. The materials will be mixed at site in atilting drum mixer of one cement bag capacity.

    2. For durability consideration, maximum free W/C ration = 0.50 minimum cement

    content 300 kg/m3

    including Fly ash.

    3. Test datas of aggregates are as given in table-1.

  • 7/29/2019 vt report on foundation

    25/47

    25

    4. Cement will be used PPC, having 7 days average compressive strength of 37.5 N/mm2

    5. Mean design target strength:

    25 + 1.65 x 5 = 33.3 N/mm2 at 28 days age

    Table-1 Test Data of Dehradun Aggregates:

    I.S. Sieve Size Percentage Passing

    River Sand 20 mm Crushed Aggregate

    40 mm 100 100

    20 mm 100 86

    10 mm 95 3

    4.75 mm 79 0

    2.36 mm 72

    1.18 mm 56

    600 micron 47

    300 micron 27

    150 micron 6

    Specific Gravity 2.65 2.65

    Water absorption % 0.80 0.50

    Bulk density kg/lit 1.78 1.40

    Note : The sand is not falling to any grading Zone of IS : 383-1970. The aggregate grading

    is 20 mm single sized as per IS: 383-1970.

    If 95% this sand passes on 4.75 mm sieve, then the sand will become of Zone-II as per IS

    : 383-1970. The following mix is worked out as per Zone-II sand. For detail calculations

    refer reference of No. 1.

    a) For the target strength and given cement and Aggregate W/C ration found to be =

  • 7/29/2019 vt report on foundation

    26/47

    26

    0.49

    b) Water for OPC 190 kg/m3. For PCC 5/100 x 190 = 9.5 , Say 10

    190 10 = 180 kg/m3

    to give 50 mm of Slump with the given aggregates. Normal

    Superplasticizer at a dosages of

    7 ml/kg cement will give 15% water reduction without loss of workability.

    Water = 180 27 = 153 kg/m3

    c) Cement = 153/0.49 = 312 kg/m3

    d) Density of OPC concrete = 2405 kg/m3

    Density for PPC Concrete = 2405 24 = Say 2380 kg/m3

    e) Aggregates = 2380 -153 312 = 1915 kg/m3

    f) Sand (Zone-II) = 1915 x 0.36 = 689 kg/m3

    g) 20 mm aggregate = 1915 689 = 1226 kg/m

    3

    Mix. No. 1 On the basis of saturated and surface dry aggregates-

    Water =153 kg/m3

    PCC=312 kg/m3

    Sand=689 kg/m3

    20 mm Aggregate=1226 ml/m3

    Mix No. 2

    95-79 = 16% oversized particles in the sand is to be adjusted in the above mix. The

    modified mix on the basis of saturated and surface dry aggregates is given below:

    Water=153 kg/m3

    PCC=312 kg/m3

    Sand=820 kg/m3

    20 mm Aggregate =1095 kg/m3

    Normal Superplasticizer=2184 kg/m3

    Accordingly mix ratio by weight on the basis of saturated and surface dry aggregates is

    given below:

    Cement : Sand : 20 mm Agg.

    1 : 2.63 : 3.51 W/C Ratio = 0.49

    Mix ratio by volume on the basis of room dry aggregates is given below:

    Cement : Sand : 20 mm Agg.

  • 7/29/2019 vt report on foundation

    27/47

    27

    1 : 2.14 : 3.63 Free W/C Ratio = 0.49

    MIX RATIO BY VOLUME FOR ONE BAG OF CEMENT

    1. Cement = One bag = 50 kg = 35 lit = 35000 cc

    2. Sand (room dry) = 2.14 x 35 = 74.9 lit = 74900 cc

    3. 20 mm Aggregate (room dry) = 3.63 x 35 = 127.05 lit = 127050 cc

    4. Free Water = 24.5 lit

    5. Normal Superplasticizer = 350 ml

    MEASURING BOXES TO BE MADE AT SITE

    1. Cement = One bag = 50 kg

    2. Sand (room dry) = 33 x 33 x 34.4 cm two boxes

    3. 20 mm Aggregate (room dry) = 33 x 33 x 29.2 cm .. four boxes

    4. Free Water = 24.5 lit5. Normal Superplasticizer = 350 ml

    In the above example M-25 Design mix is converted to the familiar 1 bag cement : 2

    boxes of sand and 4 boxes of aggregate. While making concrete at site the moisture

    content of site sand and aggregate must be taken into account in the mixing water and

    bulking of sand. In the field trial mixes are to be carried out to finalize the mix.

  • 7/29/2019 vt report on foundation

    28/47

    28

    FOUNDATION

    The building foundation or sub structure is that part of a structure which is placed below the surface of

    the ground and which transmits the superstructure load to the underlying soil ultimately. It is the part of

    a structural system that supports and anchors the superstructure of a building. Foundation is the most

    important part of a building. Building activity starts with the formation of foundation. Main activities of

    building foundation are:-

    To distribute building load to soil beneath

    To distribute the load uniformly

    To grapnel the structure to the ground to resist movement due to lateral force

    To prevent sinking of the structure.

    Any part of a structure that serves to transmit the load to the earth or rock can be called foundation.

    The higher and heavier the building is to be, the wider and deeper the supports of footings for the

    foundation have to be.

    PURPOSE OF FOUNDATION

    To pass out building weight to the soil beneath evenly;

    To prevent differential settlement of building;

    To provide a plane surface for the convenience of construction;

    To make building substantial and durable by continuing the structure in the soil.

    TYPES OF FOUNDATION:

    Depending on tthhee ddeepptthh oofftthhee llooaadd--ttrraannssffeerr mmeemmbbeerr bbeellooww tthhee ssuuppeerr--ssttrruuccttuurree and tthhee

    ttyyppee ooffttrraannssffeerr llooaadd mmeecchhaanniissmm foundation can be classified into two types:

    a) Shallow Foundation

    b) Deep Foundation.

  • 7/29/2019 vt report on foundation

    29/47

    29

    The classification on foundation has been provided in flow chart as follows:

    Classification of Foundation

    a) SSHHAALLLLOOWWFFOOUUNNDDAATTIIOONN:A shallow foundation is a type of foundation which transfers building loads to the earth

    very near the surface. The objective of shallow foundation is to distribute the structural

    concentrated load over a wide horizontal area at a little depth rather than a range of

    depths.

    Shallow foundation is often selected when the soil has a good bearing capacity and the

    structural load will not cause excessive settlement of the underlying soil layers. In

    general, shallow foundations are more simple and cost effective to construct than deep

    foundations because little soil is removed or disturbed.Shallow foundation construction

    is typically utilized for most residential and light commercial raised floor buildings.

    Foundation

    Shallow

    SpreadFootings

    WallFootings

    IsolatedColumnFootings

    GrillageFoundation

    CombinedFootings

    MatFoundation

    EccentrcallyLoaded

    Footings

    Deep

    PileFoundation

    Pre-castPiles

    Cast-in -situ Piles

    Cofferdams Caisson

  • 7/29/2019 vt report on foundation

    30/47

    30

    SPREAD FOOTINGS:

    Spread footing is a common term used to

    refer shallow foundations which transfers

    concentrated loads to a wide range area. Itincludes reinforced concrete footings, wall

    footings, isolated column footings. Spread

    footing provides a stable base or platform at a

    low depth and it prevents the structure from

    settling into the ground.

    Spread Footing

    ISOLATED COLUMN FOOTINGS:

    Isolated column footings are used to support single columns. Each individual isolated

    footing provides support for each individual column, pier, post or other single

    concentrated load. So, they act as a base for a column. They transfer the superimposed

    structural load to a wide range of soil. They are the most economical types of footings

    and are used when columns are spaced at relatively long distances. They can be square,

    rectangular or even circular in plan view.

    Isolated footings can be of brick masonry, stone masonry or of Reinforced Cement

    Concrete (R.C.C.) depending on amount of load, project expanses and materials

    available. The base of the footing depends on the load bearing capacity of soil and the

    superimposed load. They are also known as pad footing or individual column footing.

    Generally isolated footings are used in case of reinforced concrete structure buildings.

    WALL FOOTINGS:

    This type of shallow footing supports a wall by providing footing beneath the entire wall

    structure. This type of footing is used when columns are made of bricks.

  • 7/29/2019 vt report on foundation

    31/47

    31

    GRILLAGEFOOTINGS:In case of low bearing capacity of soil and avoiding deep excavation grillage

    foundation can be used. Grillage foundation can reduce the superimposed load

    of column within the safe bearing capacity of the soil. The grillage can be made

    of steel or timber.

    COMBINED FOOTINGS:A combined footing is nothing but a combination of pad footings having a

    common base. A combined footing is constructed when (i) a column lies very

    close to the property line and (ii) to prevent overlapping of footings when

    columns are very adjacent. They can be rectangular or trapezoidal in plan.

    Combined footing proves to be more cost effective than a single column footing.

    MATFOUNDATION:

    A mat is a slab that supports multiple columns. It is typically used when thebearing capacity of soil is very low. When required footings will cover more than

    half the area beneath a structure, it is often desirable to enlarge and combine

    the footings to cover the entire area. A mat foundation may be cheaper than

    individual footings because of reduced forming costs and simpler excavation

    procedures. Although mat foundations are more difficult and more costly to

    design but they prove to be more effective.

    ECCENTRICALLYLOADED FOOTINGS:

    It is a spread or wall footing that must resist a moment in addition to the axial

    column load.

    b) DDEEEEPPFFOOUUNNDDAATTIIOONN:A deep foundation is used when the bearing capacity of soil is low near ground. When a

    building structure transmits excessive loads to a soil with low bearing capacity near

    ground, settlement of the foundation takes place which endangers the stability of the

    structure. In that case deep foundation is used to ensure good bearing capacity of soil at

    a considerable amount of depth. A deep foundation requires considerable amount of

    materials and earthwork resulting increased cost and effort. Piles, cofferdams and

    caissons are some the familiar forms of deep foundations.

  • 7/29/2019 vt report on foundation

    32/47

    32

    IISSOOLLAATTEEDDCCOOLLUUMMNNFFOOOOTTIINNGG

    Dependingon structural load and soil isolated footing can be of following types:

    BBRRIICCKKPPIILLLLAARRFFOOOOTTIINNGG: When the structural columns are made of bricks this type ofisolated footing is often used. This is the most economic type of isolated columnfooting. The width and the depth of the footing depend on load to be carried and

    bearing capacity of the soil. The width is found by offsets running symmetrical round

    the column.

    SSttoonnee PPiillllaarr FFoooottiinngg: Stone pillar footings are stronger than brick pillars.Construction of this type of footing is similar to brick pillar footing. The width and the

    depth of this footing is a bit bigger because of the stone sizes. This type of footing is

    weak in resisting bending. So they are not used against long heavy structural loads.

    RR..CC..CC.. CCoolluummnn FFoooottiinngg: In case of column subjected to heavy loading and bendingthis type of column footing provides a superior solution in shallow foundation. Made

    with reinforcement and concrete this type of footing is high on strength and bending.

    The footing is reinforced cross ways by re-bar placed at right angles to one another.

    This type footing is capable of transmitting massive loads with a reduced footing

    depth. This type is used as a most effective form of isolated footing. Due to its strong

    structure this footing is used against high building structures provided that the soil

    has sufficient bearing capacity.

    INDEPENDENT COLUMN FOOTING REQUIREMENTS:The main requirements of an independent footing are as follows:

    i. Must distribute loads evenly to the soil;

    ii. Must be well drained to prevent wash-out;

    iii. Must bear on engineered soil.

  • 7/29/2019 vt report on foundation

    33/47

    33

    Foundation Alternatives and Cost Evaluation

    As noted earlier, the two major alternate foundation types are the shallow and

    deep foundations. Shallow foundations are discussed in this chapter. Deep

    foundation alternatives including piles and drilled shafts are discussed in the next

    chapter. Proprietary foundation systems should not be excluded as they may be the

    most economical alternative in a given set of conditions. Cost analyses ofall feasible

    alternatives may lead to the elimination of some foundations that were otherwise

    qualified under the engineering study.

    Other factors that must be considered in the final foundation selection are the

    availability of materials and equipment, the qualifications and experience of local

    contractors and construction companies, as well as environmental

    limitations/considerations on construction access or activities. Whether it is for

    shallow or deep foundations, it is recommended that foundation support cost be

    defined as the total cost of the foundation system divided by the load the foundation

    supports in tons. Thus, the cost of the foundation system should be expressed in

    terms of dollars per ton loadthat will be supported. For anequitable comparison, the

    total foundation cost should include all costs associated with a given foundation

    system including the need for excavation or retention systems,environmental

    restrictions on construction activities, e.g., vibrations, noise, disposal of

    contaminated excavated spoils, pile caps and cap size, etc. For major projects, if the

    estimated costs of alternative foundation systems during the design stage are within

    15 percent of each other, then alternate foundation designs should be considered

    for inclusion in contract documents. If alternate designs are included in the contract

    documents, both designs should be adequately detailed. For example, if two pile

    foundation alternatives are detailed, the bid quantity pile lengths should reflect the

    estimated pile lengths for each alternative. Otherwise,material costs and not the

    installed foundation cost will likely determine the low bid. Use of alternate

    foundation designs will generally provide the most cost effective foundation system.

    A conventional design alternate should generally be included with a proprietary

    design alternate in the final project documents to stimulate competition and to

    anticipate value engineered proposals from contractors.

  • 7/29/2019 vt report on foundation

    34/47

    34

    STEPS OF ISOLATED FOOTING

    SOIL EXCAVATION

    LEVELLING & DRESSING OF SOIL SURFACE

    PLACEMENT OF BRICK FLAT SOLING LAYER

    GIVING A CEMENT CONCRETE LAYER ON IT

    PLACEMENT OF CEMENT CONCRETE BLOCK

    PLACING OF REINFORCEMENT

    SHUTTERING

    CONCRETE CASTING

    REMOVAL OF FORMWORK

    CURING

    BACKFILLING OF EXCAVATED AREA

  • 7/29/2019 vt report on foundation

    35/47

    35

    SOIL EXCAVATION

    To set a footing, the first step is to excavate the soil of respective area. At first the area should

    be located. The depth of excavation depends on the desired strength as strength increases with

    depth. We see the tools that are used in excavation below,

    PICS

    In most cases, baskets & spades are used for excavation. Deep excavation damages adjacent

    constructions. In this phase, shore piles or other preventive means are used. Soil sloping can also

    reduce this damage. The picture below shows how workers dig soil during excavation,

    Fig: Excavation

  • 7/29/2019 vt report on foundation

    36/47

    36

    The area of footings are chosen according to design. First the C.G of footings is located.

    The excavated soil is kept near the footing as later it can be used for backfilling.

    PIC: excavated soil nearby the footing

    LEVELLING & DRESSING OF SOIL SURFACE

    After excavation, the most important step is to level the soil surface. The load of the construction

    should be vertical & for this, leveling & dressing is must. Otherwise the construction might be

    subjected to tilting to one side. Sand layer & brick chips are often used for leveling & dressing.

    In our site LEVELLING & DRESSING were done by sand layer.

  • 7/29/2019 vt report on foundation

    37/47

    37

    PLACEMENT OF BRICK FLAT SOLING LAYER

    Now a hard & plane surface is needed. For this purpose we place a brick layer on previous layer.

    It is called BRICK FLAT SOLLING. In this layer bricks are arranged in a regular combination.

    The upper surface of the layer should be uniformly planed. Below we see a brick flat soling.

    CEMENT CONCRETE LAYER

    Generally a C.C (cement concrete) layer having 3 height is kept on the brick layer. It is named

    as CEMENT CONCRETE LAYER. It provides a smooth, uniform & strong surface for

    reinforcement frame. The mix ratio for C.C layer is cement:sand:aggregate=1:3:6.

    But sometimes it is avoided to reduce expenses.

    PLACING OF CEMENT CONCRETE BLOCK

    Usually some CC blocks are kept on the CC layer to maintain the clear cover between CC layer

    & reinforcement. It is also very important to prevent the reinforcement from corrosion. There is

    no standard size of blocks. It varies with size of footing & clear cover.

    Sometimes brick or half brick can be used instead of CC block. But bricks are not uniformly

    smooth plane. Its strength is also less than CC block. So, it is better to use CC blocs as clear

    cover. Generally its size is 3x3x3.

  • 7/29/2019 vt report on foundation

    38/47

    38

    PLACING OF REINFORCEMENT

    Now it is a very important step to place reinforcements. First we should maintain available clear

    cover by using CC blocks. We must tie rebars with G.I wires or welding. It is done so that

    rebars remains intact in all the time even during the casting. First a single frame of horizontal

    reinforcement is kept upon the CC block. The number & diameter of reinforcements depends

    upon the strength of construction. And it is determined by design engineer.

    The rebars are tied by hand at the outer place if the case is respectively small. But for large case,it is done on the brick flat soling. Because it is difficult to move & place a large case.

    Fig: Formation of a case Fig: Tied by G.I wire

  • 7/29/2019 vt report on foundation

    39/47

    39

    Fig: Preparing column

    The case must remain horizontal. It is done by plumb bob. The figure below we see how a case is

    being horizontal by plumb bob.

    Fig: Making horizontal

    After placing the case, the centre of case is marked as the column can be placed.

  • 7/29/2019 vt report on foundation

    40/47

    40

    Fig: Fixing the column position

    Now the column is placed upon the marking space. It must be vertical. Then it is also tied with

    case. After making vertical the column is supported to remain fixed.

    Fig: Placing of column

  • 7/29/2019 vt report on foundation

    41/47

    41

    Fig: making it vertical

    SHUTTERING

    Shuttering means the solid boundary around the concrete. It resists water flow. It also bears the

    load of concrete. So a shuttering should be enough water tight & strong. The amount of water

    should remain constant in order to get a proper hydration. There are two kinds of shuttering,

    1. Wooden shuttering &

    2. Steel shuttering

    Wooden shuttering is more chip than steel shuttering. But it is less water proof & less strong. It

    also lasts a short time. On the other hand steel shuttering is strong enough. It also can be used

  • 7/29/2019 vt report on foundation

    42/47

    42

    more times. But it is costly. Side shuttering can be removed after 3 days as after this time

    concrete get required strength.

    Fig: Wood shuttering

    The minimum requirements of a shuttering:

    *It should be enough strong to bear the load

    *It should be water tight

    *It should be economical

    *Its inner surface should be plane

    *Its joints should be made carefully

    *It should retain the concrete shape from all types of distortions.

  • 7/29/2019 vt report on foundation

    43/47

    43

    Problems in isolated footing

    1. Segregation: Separationof constituents of a heterogeneous mixture so that their distribution

    is no longer uniform is termed as segregation. In case of concrete casting when it is thrown

    from a large height

    Figure: segregation.

    Segregation occurs due to the difference in particles size (sometimes in the specific gravity of

    the mix ingredients) .There are two types of segregation. In the first, the coarser particles tend

    to separate out since travel further long distance. In the second, segregation is occurred by

    separation of grout (water &cement). Here in our project aggregates were thrown from a

    remarkable height. As a result the ingredients were separated as they hit the lower rebar layer.This segregation will ultimately decrease the strength of the concrete. So proper arrange should

    be taken to prevent segregation.

    Concrete is being thrown fro about 10 h

  • 7/29/2019 vt report on foundation

    44/47

    44

    2. Compaction: In our observed site, for compacting concrete they used both rodding &

    vibration procedure.

    In case of using vibrator, it should kept in mind that vibrator must be vertical. But in our project

    vibrator was used aligned.

    Roding

    withbamboo

  • 7/29/2019 vt report on foundation

    45/47

    45

    Figure:

    Aligned vibrating.

    3.Improper clear cover maintainance: Clear cover is a very important fact in structure. For the

    structure under the ground clear should be maintained at least 3. If clear cover is not

    maintained properly then the moisture content around the structure will penetrate into the

    structure & cause corrosion to the reinforcement . Finally collapse the structure.

    Figure: Improper clear cover maintainance

    Aligned

    vibrating

    Improperclear cover

  • 7/29/2019 vt report on foundation

    46/47

    46

    4. Water logging during casting: Mix proportion is very much important for the design strength.

    In our site during casting, water logged continuously. The source of water may be rain water or

    leakage from nearby pipes or drains.

    Figure: Water logging during casting

    5. Brick as C.C block & no C.C layer: In isolated footing we normally use BFS & C.C layer to

    provide a flat surface. But in our project BFS was used with no mortar. Here they also did not

    use C.C layer as well as C.C block. For maintenance of the clear cover between the BFS bricks

    were directly used as C.C block that is shown in the following figure.

    Loggedwater

  • 7/29/2019 vt report on foundation

    47/47

    Figure: Brick as C.C block & no C.C layer

    Bricks as

    C.C