vsc-hvdc technology for the connection of offshore windfarms
TRANSCRIPT
Factors Affecting the Reliability of VSC-HVDC
for the Connection of Offshore Windfarms
A thesis submitted to The University of Manchester for the degree of
Doctor of Philosophy
in the Faculty of Engineering and Physical Sciences
2014
Antony James Beddard
School of Electrical and Electronic Engineering
Table of Contents
2
Table of Contents
Table of Contents ................................................................................................................. 2
List of Figures ....................................................................................................................... 7
List of Tables ...................................................................................................................... 14
Nomenclature...................................................................................................................... 17
Abstract ............................................................................................................................... 22
Declaration .......................................................................................................................... 23
Copyright Statement .......................................................................................................... 23
Acknowledgements ............................................................................................................. 24
1 Introduction ................................................................................................................. 25
1.1 Background .............................................................................................................. 25
1.2 The Connection of Round 3 Windfarms ................................................................... 25
1.3 Impact Factors on the Connection’s Reliability ...................................................... 27
1.3.1 Availability Analysis ...................................................................................... 28
1.3.2 HVDC Circuit Breakers .................................................................................. 28
1.3.3 Accurate Electromagnetic Transient Models for Radial and MT VSC-HVDC
Connections ....................................................................................................... 28
1.4 Aims and Objectives ................................................................................................. 29
1.5 Main Thesis Contributions ....................................................................................... 30
1.6 Publications .............................................................................................................. 31
1.7 Thesis Structure ........................................................................................................ 32
2 Availability Analysis ................................................................................................... 35
2.1 Radial System ........................................................................................................... 36
2.2 Component Availability ............................................................................................ 38
2.2.1 Converter Reactor ........................................................................................... 41
2.2.2 MMC with Cooling System and Ventilation System ..................................... 42
2.2.3 Control System ............................................................................................... 43
2.2.4 GIS and Transformer ...................................................................................... 43
2.2.5 DC Switchyard ................................................................................................ 45
2.2.6 DC Cable ......................................................................................................... 46
2.3 Radial VSC-HVDC Scheme Availability Analysis ................................................... 47
2.3.1 Offshore System Availability Analysis (subsystem 1) ................................... 47
Table of Contents
3
2.3.2 Onshore System Availability Analysis (subsystem 3) .................................... 50
2.3.3 DC System Availability Analysis (subsystem 2) ............................................ 51
2.3.4 Radial VSC-HVDC Scheme Availability ....................................................... 52
2.4 MT HVDC Network Availability Analysis ................................................................ 54
2.5 Cost-benefit Analysis ................................................................................................ 60
2.6 Summary ................................................................................................................... 63
2.7 Conclusion ................................................................................................................ 63
3 HVDC Protection ........................................................................................................ 65
3.1 Basic Circuit Breaker Theory .................................................................................. 67
3.1.1 The Electric Arc .............................................................................................. 67
3.1.2 Arc Interruption .............................................................................................. 68
3.2 HVDC Circuit Breaker Topologies .......................................................................... 69
3.2.1 Review of HVDC Circuit Breaker Topologies ............................................... 69
3.2.2 Hybrid Commutation HVDC Breaker (New) ................................................. 74
3.2.3 Latest HVDC Circuit Breaker Designs ........................................................... 78
3.3 Comparison of HVDC Circuit Breakers .................................................................. 80
3.4 Protection Strategies ................................................................................................ 81
3.4.1 Protection System Requirements .................................................................... 81
3.4.2 Detection and Selection .................................................................................. 83
3.4.3 Back-up Protection ......................................................................................... 87
3.4.4 Seamless and Robust Protection System ........................................................ 89
3.5 Conclusion ................................................................................................................ 90
4 MMC-HVDC ............................................................................................................... 91
4.1 MMC Structure and Operation ................................................................................ 91
4.2 MMC Parameters ..................................................................................................... 94
4.2.1 Number of MMC Levels ................................................................................. 94
4.2.2 SM Capacitance .............................................................................................. 96
4.2.3 Limb Reactance .............................................................................................. 97
4.2.4 Arm Resistance ............................................................................................... 98
4.3 Onshore AC Network ............................................................................................... 99
4.4 DC system ............................................................................................................... 100
4.4.1 Cable ............................................................................................................. 100
4.4.2 DC Braking Resistor ..................................................................................... 100
Table of Contents
4
4.5 Offshore AC Network ............................................................................................. 101
4.6 Control Systems ...................................................................................................... 102
4.6.1 Control Systems for an MMC Connected to an Active Network ................. 102
4.6.2 dq Current Controller .................................................................................... 103
4.6.3 Outer Controllers .......................................................................................... 112
4.6.4 Tap-Changer Controller ................................................................................ 117
4.6.5 Control System for MMC Connected to a Windfarm ................................... 118
4.6.6 Inner MMC Controllers ................................................................................ 119
4.7 Windfarm Control .................................................................................................. 125
4.8 Conclusion .............................................................................................................. 126
5 MMC-HVDC Link Performance ............................................................................. 127
5.1 Radial MMC-HVDC Link for a Round 3 Windfarm .............................................. 127
5.1.1 Start-up .......................................................................................................... 127
5.1.2 Windfarm Power Variations ......................................................................... 128
5.1.3 MMC ............................................................................................................. 130
5.1.4 Onshore AC Fault Ride-through ................................................................... 133
5.1.5 DC Faults ...................................................................................................... 141
5.2 VSC-HVDC Interconnector .................................................................................... 146
5.2.1 Power Reversal ............................................................................................. 146
5.2.2 AC Faults ...................................................................................................... 146
5.2.3 DC Faults ...................................................................................................... 147
5.3 Variable Limit DC Voltage Controller ................................................................... 151
5.4 Conclusion .............................................................................................................. 152
6 Comparison of MMC Modelling Techniques ......................................................... 153
6.1 MMC Modelling Techniques .................................................................................. 154
6.1.1 Traditional Detailed Model ........................................................................... 154
6.1.2 Detailed Equivalent Model ........................................................................... 154
6.1.3 Accelerated Model ........................................................................................ 159
6.2 Simulation Models .................................................................................................. 160
6.3 Results .................................................................................................................... 160
6.3.1 Accuracy ....................................................................................................... 160
6.3.2 AM Simulation Limitation ............................................................................ 165
6.3.3 Simulation Speed .......................................................................................... 166
Table of Contents
5
6.3.4 Enhanced AM Model .................................................................................... 167
6.4 Analysis and Recommendations ............................................................................. 168
6.5 Conclusion .............................................................................................................. 170
7 HVDC Cable Modelling ........................................................................................... 171
7.1 The Cable ............................................................................................................... 171
7.2 Multi-conductor Analysis ....................................................................................... 174
7.3 HVDC Cable Models .............................................................................................. 176
7.4 System Model .......................................................................................................... 177
7.5 Results .................................................................................................................... 178
7.5.1 Accuracy ....................................................................................................... 178
7.5.2 Simulation Speed .......................................................................................... 180
7.6 Conclusion .............................................................................................................. 180
8 MTDC MMC Modelling ........................................................................................... 182
8.1 MTDC Test Topology ............................................................................................. 182
8.2 MTDC Control Methods ......................................................................................... 184
8.2.1 Centralised DC Slack Bus ............................................................................. 184
8.2.2 Voltage Margin Control ................................................................................ 184
8.2.3 Droop Control ............................................................................................... 185
8.2.4 Control Methods Investigated ....................................................................... 187
8.3 MTDC System Model ............................................................................................. 187
8.3.1 Windfarm Power Variations ......................................................................... 188
8.3.2 Three-phase Line-to-Ground Fault at PCC1 ................................................. 190
8.3.3 Converter Disconnection .............................................................................. 195
8.4 Conclusion .............................................................................................................. 199
9 Conclusion and Future Work .................................................................................. 200
9.1 Conclusion .............................................................................................................. 200
9.1.1 Availability Analysis .................................................................................... 200
9.1.2 HVDC Protection .......................................................................................... 201
9.1.3 VSC-HVDC System Modelling.................................................................... 202
9.2 Future Work ........................................................................................................... 204
9.2.1 Availability Analysis .................................................................................... 204
9.2.2 HVDC Breakers ............................................................................................ 205
Table of Contents
6
9.2.3 MMC Modelling ........................................................................................... 206
10 References .................................................................................................................. 207
APPENDIX 1A – HVDC TRANSMISSION SYSTEMS .............................................. 216
APPENDIX 2A – COMPONENT RELIABILITY INDICES ..................................... 237
APPENDIX 2B – RELIABILITY CONCEPTS AND DEFINITIONS ....................... 252
APPENDIX 2C – MTDC GRID ANALYSIS ................................................................ 256
APPENDIX 3A – HVDC CIRCUIT BREAKER REVIEW ......................................... 260
APPENDIX 4A – SUB-MODULE CAPACITANCE DERIVATION ........................ 268
APPENDIX 4B – ARM INDUCTANCE DERIVATION ............................................. 276
APPENDIX 4C – SHORT-CIRCUIT RATIO CALCULATION ............................... 285
APPENDIX 4D – ABC TO DQ TRANSFORMATION DERIVATION .................... 286
APPENDIX 4E – POWER CONTROLLER TRANSFER FUNCTION
DERIVATION .................................................................................................................. 288
APPENDIX 4F – DC VOLTAGE CONTROLLER TRANSFER FUNCTION
DERIVATION .................................................................................................................. 289
APPENDIX 4G – AC VOLTAGE CONTROL ............................................................. 291
APPENDIX 4H – KEY PARAMETERS FOR THE MMC-HVDC LINK ................. 292
APPENDIX 5A – DC POLE-TO-GROUND FAULT ................................................... 293
APPENDIX 6A – PARAMETERS FOR MMC COMPARISON MODEL ............... 295
APPENDIX 7A – HVDC CABLE PARAMETERS, BONDING AND SENSITIVITY
ANALYSIS ....................................................................................................................... 296
Word count: 53,083 (72,601 with appendix)
List of Figures
7
List of Figures
Figure 1.1: Connection diagram for the UK’s windfarms ................................................... 26
Figure 1.2: Accelerated growth 2030 transmission system scenario – potential connection
diagram, ............................................................................................................. 27
Figure 2.1: 1GW VSC-HVDC point-to-point offshore connection overview diagram ....... 36
Figure 2.2: 1GW point-to-point VSC-HVDC scheme ........................................................ 36
Figure 2.3: VSC-HVDC availability model for a point-to-point link .................................. 37
Figure 2.4: Image of a MMC sub-module ........................................................................... 39
Figure 2.5: Image of a 245kV GIS bay ................................................................................ 40
Figure 2.6: Image of a 150kV, 140MVA transformer and offshore platform ..................... 40
Figure 2.7: Offshore GIS and transformer configuration (Subsystem 4)............................ 44
Figure 2.8: Onshore GIS and transformer configuration (Subsystem 5) ............................. 44
Figure 2.9: Image of a MMC VSC DC Switchyard ............................................................. 46
Figure 2.10: Availability model for offshore system (Subsystem 1) ................................... 48
Figure 2.11: Simplified availability model for offshore system (Subsystem 1) .................. 48
Figure 2.12: Offshore transformers and GIS configuration (Subsystem 4) ......................... 48
Figure 2.13: Availability model of subsystem 2 .................................................................. 52
Figure 2.14: Availability model for the VSC-HVDC scheme ............................................. 52
Figure 2.15: Component importance for availability ........................................................... 53
Figure 2.16: MT HVDC system ........................................................................................... 55
Figure 2.17: Onshore and offshore nodes ............................................................................ 56
Figure 2.18: Block diagram of MTDC network................................................................... 56
Figure 2.19: Simplified two-state block diagram of a MTDC network ............................... 57
Figure 3.1: Single line diagram for a four-terminal HVDC system ..................................... 66
Figure 3.2: Passive resonance circuit breaker ...................................................................... 69
Figure 3.3: Conventional hybrid circuit breaker .................................................................. 71
Figure 3.4: Hybrid breaker with forced commutation circuit ............................................. 73
Figure 3.5: Solid-state circuit breaker .................................................................................. 73
Figure 3.6: Hybrid commutation HVDC circuit breaker ..................................................... 74
Figure 3.7: PSCAD schematic for the hybrid commutation HVDC circuit breaker ............ 77
Figure 3.8: Example simulation results for the hybrid commutation HVDC circuit breaker
........................................................................................................................... 77
Figure 3.9: Proactive hybrid DC breaker ............................................................................. 78
List of Figures
8
Figure 3.10: Hybrid circuit breaking device ........................................................................ 80
Figure 3.11: Single line diagram for a four-terminal HVDC system ................................... 83
Figure 3.12: Cable directional protection............................................................................. 84
Figure 3.13: STFT (left) and Wavelet (right) views of signal analysis ............................... 85
Figure 3.14: DC current direction before (left) and after (right) cable fault ........................ 87
Figure 3.15: Fault on cable C2 ............................................................................................. 87
Figure 3.16: Back-up protection strategies .......................................................................... 89
Figure 4.1: MMC VSC-HVDC link for Round 3 windfarm ................................................ 91
Figure 4.2: Three-phase MMC ............................................................................................. 92
Figure 4.3: SM conduction states ......................................................................................... 92
Figure 4.4: Equivalent circuit for phase A ........................................................................... 93
Figure 4.5: Onshore AC system ......................................................................................... 100
Figure 4.6: DC braking resistor .......................................................................................... 100
Figure 4.7: Simplified diagram of a full scale converter wind turbine .............................. 101
Figure 4.8: Representation of the offshore network........................................................... 102
Figure 4.9: MMC control system basic overview .............................................................. 103
Figure 4.10: MMC phase A connection to AC system ...................................................... 103
Figure 4.11: Equivalent dq circuit diagrams ...................................................................... 104
Figure 4.12: State-block diagram for system plant in dq reference frame ......................... 105
Figure 4.13: State-block diagram with feedback nulling ................................................... 105
Figure 4.14: Decoupled d and q current control loops ....................................................... 105
Figure 4.15: d-axis current loop without d-axis system voltage disturbance ..................... 106
Figure 4.16: Simplified d-axis current control loop ........................................................... 106
Figure 4.17: Current controller step response for a bandwidth of 80Hz ............................ 108
Figure 4.18: Current controller step response for a bandwidth of 160Hz .......................... 109
Figure 4.19: Current controller step response for a bandwidth of 320Hz .......................... 109
Figure 4.20: Current controller step response for a bandwidth of 320Hz with tap-changer
ratio increased ................................................................................................. 110
Figure 4.21: Current controller step response for a bandwidth of 320Hz with increased SM
capacitance ...................................................................................................... 111
Figure 4.22: dq current controller implementation ............................................................ 111
Figure 4.23: System response for a 10% change in active power ...................................... 113
Figure 4.24: System response for a 10% change in reactive power................................... 113
List of Figures
9
Figure 4.25: DC side plant ................................................................................................. 114
Figure 4.26: System response for a 1kV step change about the operating point, Kv=0.5 .. 115
Figure 4.27: System response for a ramped injected noise current of 1.6kA in 1 second . 115
Figure 4.28: MMC phase A connection to the AC network with the system resistances
neglected.......................................................................................................... 115
Figure 4.29: System response for weak AC network with reactive power set to zero ...... 117
Figure 4.30: System response for weak AC network with AC voltage control ................. 117
Figure 4.31: MMC output voltage THD when exporting 300MVAr with no tap-changer 118
Figure 4.32: MMC output voltage THD when exporting 300MVAr with tap-changer .... 118
Figure 4.33: Implementation of the AC voltage controller for the offshore network ........ 119
Figure 4.34: Equivalent circuit for a single phase of a MMC ............................................ 119
Figure 4.35: CCSC plant state-block diagram ................................................................... 121
Figure 4.36: CCSC response to active power ramped at 1GW/s for 1s starting at 2s with a
BW of 10Hz .................................................................................................... 122
Figure 4.37: CCSC response to active power ramped at 1GW/s for 1s starting at 2s with a
BW of 30Hz .................................................................................................... 122
Figure 4.38: Block diagram of CCSC implementation ...................................................... 122
Figure 4.39: Simplified diagram of the capacitor balancing controller ............................. 124
Figure 4.40: NLC block diagram ....................................................................................... 124
Figure 4.41: Block diagram for the windfarm power controller ........................................ 125
Figure 4.42: Implementation of the windfarm power controller ........................................ 125
Figure 5.1: MMC VSC-HVDC link for a Round 3 windfarm ........................................... 127
Figure 5.2: Start-up procedure; capacitor voltages are for the upper arm of phase A for
MMC1 ............................................................................................................. 128
Figure 5.3: Link response to variations in windfarm power .............................................. 129
Figure 5.4: Link response at steady-state for Pw =1GW .................................................... 130
Figure 5.5: THD for the line-to-line voltages at PCC1 for Pw = 1GW .............................. 130
Figure 5.6: Phase voltages, arm currents and difference currents for onshore MMC with Pw
=1GW .............................................................................................................. 131
Figure 5.7: Phase voltages, arm currents and difference currents for onshore MMC with Pw
=1GW and CCSC disabled .............................................................................. 131
Figure 5.8: Rms value of the upper arm current for phase A with Pw=1GW and CCSC
enabled ............................................................................................................ 132
List of Figures
10
Figure 5.9: Rms value of the upper arm current for phase A with Pw=1GW and CCSC
disabled............................................................................................................ 132
Figure 5.10: THD for the line-to-line voltages at PCC1 for Pw = 1GW and CCSC disabled
......................................................................................................................... 132
Figure 5.11: SM capacitor ripple voltages for the upper arm of phase A with Pw=1GW .. 133
Figure 5.12: SM capacitor ripple voltages for the upper arm of phase A with Pw=1GW and
CCSC disabled ................................................................................................ 133
Figure 5.13: Supergrid voltage dip to 0.3p.u. with no MMC reactive current support...... 137
Figure 5.14: Supergrid voltage dip to 0.3p.u. with MMC reactive current support........... 138
Figure 5.15: Phase A to ground fault at 3s and phase A to phase B fault at 4s ................. 139
Figure 5.16: Three-phase to ground fault at 3s .................................................................. 140
Figure 5.17: DC line-to-line fault at the terminals of MMC1 at 3s ................................... 143
Figure 5.18: Positive pole-to-ground fault at MMC1 ........................................................ 144
Figure 5.19: Positive pole-to-ground fault at MMC1 with under voltage protection ........ 145
Figure 5.20: MMC VSC-HVDC interconnector ................................................................ 146
Figure 5.21: System response for a wide range of active and reactive power orders ........ 148
Figure 5.22: Three-phase fault for 140ms at 3s ................................................................. 149
Figure 5.23: DC line-to-ground fault ................................................................................. 150
Figure 5.24: Comparison of active power response for a 140ms three-phase AC fault using
fixed and variable limits .................................................................................. 151
Figure 6.1: SM circuit (left) SM equivalent circuit (right) ................................................ 156
Figure 6.2: String of SM Thevenin equivalent circuits (left) Converter arm Thevenin
equivalent circuit (right) .................................................................................. 158
Figure 6.3: PSCAD half-bridge MMC arm component ..................................................... 158
Figure 6.4: Implementation steps for the accelerated model ............................................. 159
Figure 6.5: Basic simulation model structure .................................................................... 160
Figure 6.6: Steady-state simulation results for the three models ....................................... 161
Figure 6.7: DC line-to-line fault applied at 4.5s ................................................................ 163
Figure 6.8: Line-to-ground fault for phase A applied at 4.5s............................................. 164
Figure 6.9: Phase A output voltage for the three models when the converter is blocked at
3s. .................................................................................................................... 165
Figure 6.10: Blocked SM test circuit ................................................................................. 165
Figure 6.11: Implementation of blocked SM test circuit based on AM principles ............ 166
List of Figures
11
Figure 6.12: Simulation times of the three models for different MMC levels. .................. 167
Figure 6.13: Line-to-ground fault for phase A applied at 4.5s for the TDM, AM and AM30
models. ............................................................................................................ 168
Figure 7.1. Image of a submarine XLPE HVDC cable ...................................................... 171
Figure 7.2: MTDC test model ............................................................................................ 177
Figure 7.3: Onshore AC power response to windfarm power variations ........................... 179
Figure 7.4: DC voltage response at MMC2 for a DC line-to-line fault at the terminals of
MMC1 ............................................................................................................. 179
Figure 7.5: DC current response at MMC2 for a DC line-to-line fault at the terminals of
MMC1 ............................................................................................................. 179
Figure 7.6: AC power response at PCC1 for a three-phase line-to-ground fault at PCC1.180
Figure 7.7: DC voltage response at MMC1 for a three-phase line-to-ground fault at PCC1
......................................................................................................................... 180
Figure 8.1: Accelerated growth 2030 transmission system scenario – potential connection
diagram ............................................................................................................ 183
Figure 8.2: MTDC test topology ........................................................................................ 183
Figure 8.3: Standard Vdc-Idc characteristic; DC slack bus (Left) voltage margin control
(Right) ............................................................................................................. 185
Figure 8.4: Implementation of the voltage margin controller ............................................ 185
Figure 8.5: Standard Vdc-Idc characteristic for voltage droop control ................................ 186
Figure 8.6: Implementation of voltage droop controller .................................................... 186
Figure 8.7: Vdc-Idc characteristic for voltage droop control with dead band ...................... 187
Figure 8.8: MTDC test model ............................................................................................ 188
Figure 8.9: MTDC system response to windpower variations when employing a centralised
DC slack bus.................................................................................................... 189
Figure 8.10: MTDC system response to windpower variations when employing voltage
margin control bus ........................................................................................... 190
Figure 8.11: MTDC system response to windpower variations when employing standard
droop control bus ............................................................................................. 190
Figure 8.12: MTDC system response to a three-phase to ground fault when employing a
centralised DC slack bus ................................................................................. 192
Figure 8.13: MTDC system response to a three-phase to ground fault when employing
voltage margin control .................................................................................... 193
List of Figures
12
Figure 8.14: MTDC system response to a three-phase to ground fault when employing
standard droop control ..................................................................................... 194
Figure 8.15: Impact of MTDC control methods on the upper arm current for phase A of
MMC1 for a three-phase to ground fault ........................................................ 195
Figure 8.16: MTDC response for MMC3 disconnected at approximately 2s and for MMC1
disconnected at approximately 3s when employing a centralised DC slack bus
......................................................................................................................... 196
Figure 8.17: MTDC response for MMC3 disconnected at approximately 2s and for MMC1
disconnected at approximately 3s when employing voltage margin control .. 197
Figure 8.18: MTDC response for MMC3 disconnected at approximately 2s and for MMC1
disconnected at approximately 3s when employing standard droop control .. 198
Figure A.1: Overview of a HVDC connection and a HVAC connection .......................... 216
Figure A.2: CSC-HVDC monopole scheme with metallic return ..................................... 218
Figure A.3: Six-pulse converter ......................................................................................... 218
Figure A.4: PSCAD simulation of CSC converter switching waveforms for a firing angle
of 0° ................................................................................................................. 219
Figure A.5: PSCAD simulation of CSC converter switching waveforms for a firing angle
of 25° ............................................................................................................... 220
Figure A.6: PSCAD simulation of switching waveforms for CSC converter with AC side
reactance and firing angle of 0° ...................................................................... 222
Figure A.7: PSCAD simulation of phase current for six-pulse converter (left) and twelve-
pulse converter (right) ..................................................................................... 223
Figure A.8: VSC-HVDC scheme ....................................................................................... 224
Figure A.9: Three-phase two-level voltage source converter ............................................ 225
Figure A.10: Sinusoidal voltage synthesised from a two-level converter with PWM ....... 225
Figure A.11: Single phase of a diode neutral clamped voltage source converter .............. 227
Figure A.12: Sinusoidal voltage synthesised from a three-level converter with PWM ..... 227
Figure A.13: Single phase of an active neutral clamped voltage source converter ........... 229
Figure A.14: Three-phase MMC ........................................................................................ 230
Figure A.15: Sinusoidal voltage synthesised from a MMC ............................................... 230
Figure A.16: Sinusoidal voltage synthesised from a 400MW MMC with 200 modules per
arm ................................................................................................................... 230
List of Figures
13
Figure A.17: Single phase of a two-level cascaded converter ........................................... 232
Figure A.18: CTL Converter voltage for a fundamental frequency of 50Hz..................... 233
Figure A.19: Image of a MMC VSC DC switchyard ........................................................ 248
Figure A.20: Relationship between MTBF, MTTF and MTTR ........................................ 253
Figure A.21: Product lifecycle ........................................................................................... 254
Figure A.22: Mechanical breaker with turn-off snubber ................................................... 260
Figure A.23: DC/DC resonance converter ......................................................................... 261
Figure A.24: HVDC circuit breaker arrangement and method (ABB, Nov 2008) ............ 262
Figure A.25: Transformer arrangement ............................................................................. 263
Figure A.26: GTO thyristor circuit breaker ....................................................................... 266
Figure A.27: IGBT circuit breaker ..................................................................................... 267
Figure A.28: Single-phase equivalent circuit for MMC .................................................... 268
Figure A.29: DC side plant ................................................................................................ 289
Figure A.30: SFSB for DC voltage control loop ............................................................... 290
Figure A.31: MMC phase A connection to the AC network with the system resistances
neglected.......................................................................................................... 291
Figure A.32: Positive pole-to-ground fault at MMC1 with under voltage protection and a
star-point reactor ............................................................................................. 293
Figure A.33: Positive pole-to-ground fault at MMC1 with under voltage protection and DC
surge arresters (no star-point reactor) .............................................................. 294
Figure A.34: Cable parameter sensitivity test model ......................................................... 301
Figure A.35: Effect of semi-conductor screen thickness on the receiving end voltage ..... 302
Figure A.36: Effect of insulation design on the receiving end voltage .............................. 302
Figure A.37: Effect of sheath design on the receiving end voltage ................................... 303
Figure A.38: Effect of armour design on the receiving end voltage .................................. 303
Figure A.39: Effect of inner jacket design on the receiving end voltage ........................... 304
Figure A.40: Effect of outer jacket design on the receiving end voltage ........................... 304
Figure A.41: Effect of sea-return impedance on the receiving end voltage ....................... 304
List of Tables
14
List of Tables
Table 2.1: Mean time to access the offshore platform based on components/spare part size
........................................................................................................................... 39
Table 2.2: Estimated reliability indices for converter reactors ............................................ 42
Table 2.3: Estimated reliability indices for MMC with ventilation system and cooling
system ................................................................................................................ 43
Table 2.4: Estimated reliability indices for control system ................................................. 43
Table 2.5: Estimated reliability indices for GIS .................................................................. 45
Table 2.6: Estimated reliability indices for transformers ..................................................... 45
Table 2.7: Estimated reliability indices for DC switchyard ................................................. 46
Table 2.8: Estimated submarine cable reliability indices ..................................................... 47
Table 2.9: Availability of offshore components .................................................................. 48
Table 2.10: Example GIS failure modes and consequences ................................................ 49
Table 2.11: Available capacity table for subsystem 4.......................................................... 50
Table 2.12: Available capacity table for the offshore subsystem (Subsystem 1) ................ 50
Table 2.13: Availability of onshore components ................................................................. 51
Table 2.14: Available capacity table for subsystem 5.......................................................... 51
Table 2.15: Available capacity table for the onshore system (Subsystem 3)....................... 51
Table 2.16: Available capacity table for the DC system (Subsystem 2) .............................. 52
Table 2.17: Available capacity table of radial VSC-HVDC scheme ................................... 52
Table 2.18: Cable sensitivity analysis .................................................................................. 54
Table 2.19: Equivalent available capacity table for subsystem 1 ........................................ 57
Table 2.20: Two-state capacity availability tables ............................................................... 58
Table 2.21: Truth table for MTDC network......................................................................... 58
Table 2.22: Probability table for MTDC network ................................................................ 58
Table 2.23: Capacity table for MTDC network with Sub6=Sub7=900MW ........................ 58
Table 2.24: Capacity availability table for MTDC network with Sub6=Sub7=900MW ..... 59
Table 2.25: Capacity availability table for regional MTDC network with
Sub6=Sub7=1200MW ....................................................................................... 59
Table 2.26: Capacity availability table for MTDC network with Sub6=Sub7=1800MW ... 59
Table 2.27: VSC converter costs .......................................................................................... 60
Table 2.28: HVDC extruded cable costs .............................................................................. 60
Table 2.29: Cable installation costs ..................................................................................... 60
List of Tables
15
Table 2.30: HVDC transmission scheme costs excluding offshore nodes........................... 61
Table 2.31: Economic cost-benefit analysis......................................................................... 62
Table 3.1: Comparison of HVDC breaker types .................................................................. 80
Table 4.1: IEC 61000-3-6 harmonic voltage limits for high voltage systems ..................... 96
Table 4.2: IEEE519 harmonic voltage limits ....................................................................... 96
Table 4.3: Nominal transformer parameters ........................................................................ 99
Table 4.4: Calculated time constants for commercial wind turbines ................................. 125
Table 6.1: Normalised MAE for the DEM and AM waveforms when operating in steady-
state at 1GW .................................................................................................... 162
Table 6.2: Normalised MAE for the DEM and AM waveforms when operating in steady-
state at 500MW ............................................................................................... 162
Table 6.3: Normalised MAE for the DEM and AM waveforms when operating in steady-
state at 100MW ............................................................................................... 162
Table 6.4: Normalised mean absolute error for the DEM and AM waveforms for a DC line-
to-line fault. ..................................................................................................... 163
Table 6.5: Normalised mean absolute error for the DEM and AM waveforms for a line-to-
ground AC ....................................................................................................... 164
Table 6.6: Comparison of run times for the three models for a 5 second simulation ........ 166
Table 6.7: Comparison of run times for different AM models .......................................... 168
Table 6.8: Normalised mean absolute error for the AM and AM10 waveforms for a line-to-
ground AC fault. .............................................................................................. 168
Table 7.1: Physical data for a 300kV 1GW submarine HVDC cable ................................ 172
Table 8.1: Control methods investigated ........................................................................... 187
Table 8.2 : Maximum and rms values for Figure 8.15. ...................................................... 195
Table A.1: Evolution of VSC-HVDC technology ............................................................. 234
Table A.2: Circuit breaker MTTF and MTTR values given in sources 1 to 4 ................... 237
Table A.3: Cigre high voltage circuit breaker reliability data ........................................... 238
Table A.4: Failure statistics from the 1996 survey for GIS commissioned after 1985 ...... 238
Table A.5: Estimated reliability indices for GIS ................................................................ 240
Table A.6: Transformer failure statistics given in sources 1 to 4 ...................................... 240
Table A.7: Estimated reliability indices for transformer ................................................... 242
Table A.8: Converter reactor reliability values given in sources 1 to 4 ............................. 242
List of Tables
16
Table A.9: Murraylink energy availability ........................................................................ 242
Table A.10: Estimated converter reactor reliability indices............................................... 243
Table A.11: MMC failure statistics given in sources 1 to 4............................................... 243
Table A.12: Estimated MMC reliability indices ................................................................ 245
Table A.13: Control and protection failure statistics given in sources 1 to 4 .................... 245
Table A.14: Availability of DNV duplicated control system ............................................ 245
Table A.15: Estimated control system reliability indices .................................................. 247
Table A.16: DC equipment failure statistics given in sources 1 to 4 ................................. 247
Table A.17: Analysis of the DC equipment failure statistics from the World 2007-2008
HVDC survey .................................................................................................. 249
Table A.18: Estimated reliability indices for DC switchyard ............................................ 250
Table A.19: DC cable failure statistics given in sources 1 to 4 ......................................... 250
Table A.20: Estimated reliability indices for submarine cable .......................................... 251
Table A.21: Truth table for the simplified MTDC system ................................................ 257
Table A.22: Capacity probability tables for MTDC with 900MW paths back to shore .... 259
Table A.23: Key parameters for the MMC-HVDC link .................................................... 292
Table A.24: Parameters for MMC comparison model ....................................................... 295
Table A.25: Submarine HVDC Light 320kV cable with copper conductor in a moderate
climate with close laying ................................................................................. 296
Table A.26: XLPE land cable systems ............................................................................... 296
Nomenclature
17
Nomenclature
List of Acronyms
AC Alternating Current
AM Accelerated Model
CBC Capacitor Balancing Controller
CCSC Circulating Current Suppressing Controller
CEPIM Coupled Equivalent PI Model
COPT Capacity Outage Probability Table
CSC Current Source Converter
DC Direct Current
DCCB Direct Current Circuit Breaker
DC-XLPE Direct Current Cross-Linked Polyethylene
DEM Detailed Equivalent Model
DNV Det Norske Veritas
EAM Enhanced Accelerated Model
EMT Electromagnetic Transient
EMTDC Electromagnetic Transients Including DC
EMTP-RV Electromagnetic Transients Program – Restructured Version
FDMM Frequency Dependent Mode Model
FDPM Frequency Dependent Phase Model
FS Firing Signal
GIS Gas-insulated Switchgear
GTO Gate Turn-off Thyristor
HVAC High Voltage Alternating Current
HVDC High Voltage Direct Current
IGBT Insulated Gate Bipolar Transistor
LCC Line Commutated Converter
MAE Mean Absolute Error
MMC Modular Multi-level Converter
MOAT Mean Offshore Access Time
MRTB Metallic Return Transfer Breaker
MT Multi-terminal
MTDC Multi-terminal Direct Current
Nomenclature
18
MTTF Mean Time To Failure
MTTR Mean Time To Repair
NETS SQSS National Electricity Transmission System Security and Quality of Supply
Standard
NFSS Nested Fast and Simultaneous Solution
NLC Nearest Level Control
ODIS Offshore Development and Information Statement
PCC Point of Common Coupling
SCR Short-circuit Ratio
SM Sub-module
STFT Short-time Fourier Transform
TDM Traditional Detailed Model
THD Total Harmonic Distortion
TRV Transient Recovery Voltage
VSC Voltage Source Converter
XLPE Cross-Linked Polyethylene
List of Main Symbols
Symbol Definition S.I. Units
A Availability p.u./%
B DC Breaker -
BRK AC Breaker -
BWic Bandwidth of inner current controller rad/s
BWp Bandwidth of power controller rad/s
C Capacitance F
Ceq MMC equivalent capacitance F
CSM Sub-module capacitance F
G Conductance S
I Current A
I2f Circulating current (appendix) A
I(abc) Phase currents A
Iarm Arm current A
Nomenclature
19
Ib Current through breaker / phase b current A
Ic Current through commutation path / phase c current A
Icap Capacitor current A
Icirc Circulating current A
Idc DC current A
Idiff Difference current A
Idq dq current A
Ig DC current per phase leg A
IL Line current A
Il(abc) Lower arm phase currents A
Is Current through surge arrester A
Ism Sub-module current A
Isx(abc) Phase currents at PCC x where x = 1 to 4 A
Iu(abc) Upper arm phase currents A
Ki Integral gain -
Kp Proportional gain -
L Inductance H
Larm Arm inductance H
Ls System inductance H
LT Transformer inductance H
N Number of sub-modules -
NL Number of levels -
Np Number of turns on the primary winding -
Ns Number of turns on the secondary winding -
p d/dt -
P Active power W
Pd DC power W
Pdrated DC rated power W
Pi Input power W
Ptf Power transfer function W
Pw Windfarm active power W
Q Reactive power VAr
Qw Windfarm reactive power VAr
Nomenclature
20
R Resistance Ω
Rarm Arm resistance Ω
Rbrak Braking resistor Ω
Req Equivalent resistance Ω
Roff IGBT/diode off-state resistance Ω
Ron IGBT/diode on-state resistance Ω
RT Transformer resistance Ω
S Switch / Apparent power -/VA
s Laplace operator -
SA Surge arrester -
Sdq dq apparent power VA
τ time constant S
T Semi-conductor switch with turn-off capability -
Ti Integral time constant S
ν Wind speed m/s
V Voltage V
Vc(abc) Internal converter phase voltages V
Vcap Capacitor voltage V
Vc(dq) dq converter voltage V
Vdc DC voltage V
Vdcnom DC nominal voltage V
Vdiff Difference voltage V
Vdq dq voltage V
Veq Equivalent voltage V
Vl(abc) Lower arm phase voltages V
Vn(abc) Network phase voltages V
Vs(dq) dq voltages at PCC referred to primary converter winding V
VSM Sub-module voltage V
Vsx(abc) Phase voltages at PCC x where x = 1 to 4 V
VTp Transformer primary winding voltage V
VTs Transformer secondary winding voltage V
Vu(abc) Upper arm phase voltages V
Vw(dq) dq windfarm voltage V
Nomenclature
21
Vx(abc) Output phase voltages for converter x, where x = 1 to 4 V
W Energy J
*x Set-point -
x Error -
x Peak -
X Reactance Ω
XT Transformer leakage reactance Ω
Y Admittance S
Z Impedance Ω
Zn Network impedance Ω
δc Converter angle Rad
ΔWSM Variation in sub-module stored energy J
ζ Damping ratio -
ω System frequency rad/s
ωn Natural frequency rad/s
ε Capacitance ripple voltage factor -
θ Angle rad
Abstract
22
Abstract
Name of University: The University of Manchester
Candidate’s name: Antony James Beddard
Degree Title: Doctor of Philosophy
Thesis Title: Factors Affecting the Reliability of VSC-HVDC for the Connection of
Offshore Windfarms
Date: April 2014
The UK Government has identified that nearly 15% of the UK’s electricity generation
must come from offshore wind by 2020. The reliability of the offshore windfarms and their
electrical transmission systems is critical for their feasibility. Offshore windfarms located
more than 50-100km from shore, including most Round 3 offshore windfarms, are likely to
employ Voltage Source Converter (VSC) High Voltage Direct Current (HVDC)
transmission schemes. This thesis studies factors which affect the reliability of VSC-
HVDC transmission schemes, in respect to availability, protection, and system modelling.
The expected availability of VSC-HVDC systems is a key factor in determining if Round 3
offshore windfarms are technically and economically viable. Due to the lack of
publications in this area, this thesis analyses the energy availability of a radial and a Multi-
Terminal (MT) VSC-HVDC system, using component reliability indices derived from
academic and industrial documentation, and examining the influence of each component
on the system’s energy availability. An economic assessment of different VSC-HVDC
schemes is undertaken, highlighting the overall potential cost savings of HVDC grids.
The connection of offshore windfarms to a MT HVDC system offers other potential
benefits, in comparison to an equivalent radial system, including a reduction in the volume
of assets and enhanced operational flexibility. However, without suitable HVDC circuit
breakers, a large MT HVDC system would be unviable. In this thesis, a review of potential
HVDC circuit breaker topologies and HVDC protection strategies is conducted. A HVDC
circuit breaker topology, which addresses some of the limitations of the existing designs,
was developed in this thesis, for which a UK patent application was filed.
Accurate simulation models are required to give a high degree of confidence in the
expected system behaviour. Modular Multi-level Converters (MMCs) are the preferred
HVDC converter topology, however modelling MMCs in Electromagnetic Transient
(EMT) simulation programs has presented a number of challenges. This has resulted in the
development of new modelling techniques, for which the published validating literature is
limited. In this thesis these techniques are compared in terms of accuracy and simulation
speed and a set of modelling recommendations are presented. Cable models are the other
main DC component which, upon analysis, is found to have a significant impact on the
overall model’s simulation results and simulation time. A set of modelling
recommendations are also presented for the leading cable models.
Using the modelling recommendations to select suitable MMC models, radial and MT
EMT MMC-HVDC models for the connection of typical Round 3 windfarms are
developed in this thesis. These models are used to analyse the steady-state and transient
performance of the connections, including their compliance to the GB grid code for AC
disturbances and reactive power requirements. Furthermore, the MT model is used to
investigate the effect of MT control strategies on the internal MMC quantities.
Declaration and Copyright Statement
23
Declaration
No portion of the work referred to in the thesis has been submitted in support of an
application for another degree or qualification of this or any other university or other
institute of learning.
Copyright Statement
The author of this thesis (including any appendices and/or schedules to this thesis) owns
certain copyright or related rights in it (the “Copyright”) and s/he has given The University
of Manchester certain rights to use such Copyright, including for administrative purposes.
Copies of this thesis, either in full or in extracts and whether in hard or electronic copy,
may be made only in accordance with the Copyright, Designs and Patents Act 1988 (as
amended) and regulations issued under it or, where appropriate, in accordance with
licensing agreements which the University has from time to time. This page must form part
of any such copies made.
The ownership of certain Copyright, patents, designs, trade marks and other intellectual
property (the “Intellectual Property”) and any reproductions of copyright works in the
thesis, for example graphs and tables (“Reproductions”), which may be described in this
thesis, may not be owned by the author and may be owned by third parties. Such
Intellectual Property and Reproductions cannot and must not be made available for use
without the prior written permission of the owner(s) of the relevant Intellectual Property
and/or Reproductions.
Further information on the conditions under which disclosure, publication and
commercialisation of this thesis, the Copyright and any Intellectual Property and/or
Reproductions described in it may take place is available in the University IP Policy
(seehttp://documents.manchester.ac.uk/DocuInfo.aspx?DocID=487), in any relevant Thesis
restriction declarations deposited in the University Library, The University Library’s
regulations (see http://www.manchester.ac.uk/library/aboutus/regulations) and in The
University’s policy on Presentation of Theses.
Acknowledgements
24
Acknowledgements
First and foremost, I would like to express my gratitude to my supervisor, Professor Mike
Barnes. This PhD would not have been possible without his excellent guidance and
unparalleled support and it has been a privilege working with him over the past 3.5 years.
It would also not have been possible for me to undertake this research without financial
support and I therefore wish to acknowledge the UK Engineering Physical Sciences
Research Council and National Grid plc for their assistance in this area.
During this PhD I have had many fantastic opportunities to meet, work and discuss ideas
with some inspiring and knowledgeable engineers and I would like to recognise the
members of the “Supergen Wind Energy Consortium” and the “Cigre B4-57 Working
Group”, for aiding my professional development. In terms of inspiration, a special mention
must be made to my previous college tutor Mr Hubert Ward. His dedicated, enthusiastic
and exhaustive approach to teaching electrical engineering principles was invaluable and I
thank him for encouraging me to follow a career in this field.
For their kind support and humorous discussions during my time undertaking this research,
I would like to thank the members of the Power Conversion Group, Dr Robin Preece and
Dr Luke Livermore. A special thank you goes to Dr Steven Jordan, for taking time out
from his travels to review this thesis.
Finally, to family and friends, including those already mentioned, your encouragement has
made this PhD possible, and far more enjoyable than it may have otherwise been. I would
especially like to thank Angela for her time, effort and support throughout this research.
Chapter 1 Introduction
25
1 Introduction
1.1 Background
Offshore wind power generation is a critical component in the production of a clean,
secure and sustainable energy supply for the future. The amount of offshore generation is
increasing worldwide. In the UK alone, the Crown Estate has leased enough offshore wind
development sites to provide a potential capacity of 47GW [1]. Considering that the UK’s
current total power station capacity is approximately 80GW [2], it is clear that offshore
wind will become a major contributor to the UK’s generation mix.
The lease of the potential offshore wind development sites in the UK has been through a
series of allocation rounds, designed to increase in scale and technical complexity as the
industry has developed. Round 1 and Round 2 sites have a capacity of 8GW and are
already in operation, under construction or in development [1, 3] . The Round 3 windfarms
have a potential capacity of 32GW, and construction of these projects is expected to start
from 2015 [1, 3]. These windfarm sites are significantly larger than the Round 1 and
Round 2 sites and are located much further from the shore, as shown in Figure 1.1. The
connection of Round 3 windfarms therefore creates a number of new challenges.
The EPSRC Supergen Wind Project Consortium, which consists of a number of research
institutions and industrial partners, are undertaking research to help assist with these
challenges [4]. This PhD formed part of that research. The Consortium’s principle
objective is to undertake research to achieve an integrated, cost-effective, reliable and
available offshore wind power station. The research documented in this thesis was carried
out in alignment with the consortium’s principle objective.
1.2 The Connection of Round 3 Windfarms
The connection of a windfarm can be either via a High Voltage Alternating Current
(HVAC) or a High Voltage Direct Current (HVDC) transmission system. The choice of
transmission system is largely dependent upon how far the windfarm is located from shore.
HVDC technology is typically more favourable for windfarms located more than 50-
100km from shore [1, 5]. This is primarily because in a HVAC system a large proportion
of a cable’s current carrying capacity is required to charge and discharge the cable’s
capacitance every cycle. Whereas in a HVDC system, once the cable is charged almost its
entire current carrying capacity is available for active power transfer. National Grid’s
Chapter 1 Introduction
26
Offshore Development Information Statement (ODIS) has identified that the vast majority
of the Round 3 windfarm potential capacity is likely to employ HVDC systems due to the
sites’ location [1].
Current Source Converters (CSC) and Voltage Source Converters (VSC) are the two main
types of converter technology used in HVDC transmission systems. VSC-HVDC is more
suited for offshore windfarms because it does not require a strong AC system and has a
smaller footprint in comparison to CSC-HVDC [6].
Since its inception in 1997, and until 2010, all VSC-HVDC schemes employed two or
three-level VSCs [7]. In 2010, the Trans Bay Cable project became the first VSC-HVDC
scheme to use Modular Multi-level Converter (MMC) technology. The MMC has
numerous benefits in comparison to two or three-level VSCs; chief among these is reduced
converter losses [7]. Today, the three largest HVDC manufacturers offer a VSC-HVDC
solution which is based on multi-level converter technology [7]. This thesis therefore
focuses on MMC VSC-HVDC schemes. For further information, a comparative review of
HVAC and HVDC technologies, as well as the different HVDC converter configurations,
is given in Appendix 1A.
Figure 1.1: Connection diagram for the UK’s windfarms [8]
Chapter 1 Introduction
27
With the exception of the recently commissioned (December 2013) Nan’ao island project,
all operational windfarms employing VSC-HVDC connections are radial (point-to-point).
There have however been a number of proposals to interconnect offshore generation to a
common VSC-HVDC Multi-Terminal (MT) system such as the European Super Grid and
National Grid’s Integrated Network, as shown in Figure 1.2. The connection of offshore
windfarms to a common grid has the potential to reduce the volume of assets installed
offshore and improve operational flexibility and network security [1]. It should be noted
that the terms “HVDC grid”, “MT HVDC system” and “Integrated HVDC network” in this
thesis are all HVDC systems which contain three or more HVDC converters and share a
common HVDC connection.
Figure 1.2: Accelerated growth 2030 transmission system scenario – potential connection diagram,
modified from [9]
1.3 Impact Factors on the Connection’s Reliability
This section identifies factors which require further research to reduce the negative impact
they may have on the reliability of VSC-HVDC schemes and therefore the development of
Round 3 windfarms.
Chapter 1 Introduction
28
1.3.1 Availability Analysis
Availability in this work is defined as the probability of finding the component, device or
system in the operating state during its useful life. The expected availability of the VSC-
HVDC systems (radial and MT), which connect the Round 3 offshore windfarms is a key
factor in determining if these windfarms are technically and economically viable.
Availability figures affect the profitability of the system and therefore have a major impact
on potential investors as well as the operation of the onshore National Grid. Availability
analysis can also enable the key components which affect the reliability of the link to be
identified. Strategies can therefore be developed to improve the availability of these
components if required. At the time of investigation no publications existed in the public
domain which estimates the expected availability of the VSC-HVDC systems which may
be employed to connect a typical Round 3 windfarm. Further work is therefore required in
this area.
1.3.2 HVDC Circuit Breakers
A key problem for the development of large HVDC grids (>1.8GW) is the lack of
commercially available HVDC circuit breakers. In order for a large HVDC grid to be
technically and commercially viable, the ability to isolate parts of the grid due to a fault, or
to perform maintenance without de-energising the entire grid, must be achieved.
Currently, offshore windfarms connected to radial VSC-HVDC schemes deal with DC
faults by blocking the Insulated Gate Bipolar Transistor (IGBT) devices in the
converter and by tripping the AC circuit breakers, so that the converter’s anti-parallel
diodes do not conduct. Applying this approach to a DC grid would effectively mean de-
energising the entire DC grid to isolate the faulted section. This is generally considered an
unacceptable solution for relatively large HVDC grids. Further work is therefore required
to produce a HVDC breaker so that this stumbling block is removed from the path of
developing a HVDC grid.
1.3.3 Accurate Electromagnetic Transient Models for Radial and MT VSC-HVDC
Connections
Simulation models are a vital tool in the research and development of VSC-HVDC
systems. Highly accurate models are required in order to give a high degree of confidence
in the simulation results and therefore ensure that the system operates in the expected way.
Chapter 1 Introduction
29
The use of MMC converters in VSC-HVDC systems has presented a number of challenges.
Applying traditional modelling techniques to MMC VSC-HVDC systems is
computationally intensive and impractical in many cases. This has led to the development
of new modelling techniques for MMC converters [10, 11]. The published literature
validating these techniques are however, very limited in some areas, and non-existent in
others [12]. More research is therefore required in this area to give a higher degree of
confidence to these models and also to assess which models are suitable for which studies.
The potential development of HVDC grids has led to the need to produce highly accurate
EMT grid models which are valid for a range of studies. The issue of accuracy vs.
computational efficiency is of greater concern for grids than radial systems due to the
increased size of the model. In addition to the MMC models, cable models are the other
main DC component which may have a significant impact on the overall model’s
simulation results and simulation time. The fidelity of cable models is of particular
importance for HVDC grids due to the need to locate the faulty section of the grid within
approximately 1-2ms, which requires accurate representation of the DC quantities.
Publications regarding the impact of different cable models, in terms of their accuracy and
speed, for typical VSC-HVDC studies are however very limited. The opportunity therefore
exists for further research, so that recommendations can be made as to which cable models
are appropriate for particular studies.
1.4 Aims and Objectives
This thesis aims to address some of the issues raised in the previous section. In order to
achieve these aims the following objectives have been identified:
1. Conduct an availability study for a radial VSC-HVDC system and identify the key
components which affect the system’s overall availability.
2. Identify the key issues in the development of a HVDC breaker and present potential
solutions.
3. Develop a high fidelity EMT model of a radial VSC-HVDC system employed for
the connection of a typical Round 3 windfarm and compare the leading MMC
modelling techniques.
Chapter 1 Introduction
30
4. Develop a high fidelity EMT model of a MT VSC-HVDC system employed for the
connection of a typical Round 3 windfarm and compare the leading cable
modelling techniques.
1.5 Main Thesis Contributions
The work contained within this thesis has made a number of contributions. References with
the prefix ‘B’ ‘C’, ‘J’, ‘P’ and ‘S’ refer to books, conference publications, journal
publications, patents and Supergen reports respectively. A full list of publications is given
in Section 1.6. The main contributions can be summarised as follows:
An availability study of a radial VSC-HVDC scheme for the connection of a typical
Round 3 windfarm was conducted. This study involved the derivation of a new set
of reliability indices for MTTF and MTTR1, for the key components in a VSC-
HVDC scheme and the production of overall availability figures for the scheme.
The key components which have the greatest impact on the scheme’s overall
availability were also identified. Furthermore, this study analysed the overall
availability of a MT HVDC system which may be employed for the connection of
Round 3 windfarms and assessed the effect of varying the cable’s capacity on the
grid’s availability. In addition, an economic assessment of radial and selected grid
schemes was carried out to determine the impact of the scheme’s availability on the
profitability of the scheme. [B1, C1, J1, S1].
A review of existing HVDC circuit breaker topologies was conducted in order to
identify the limitations of each design. From this review a new type of HVDC
circuit breaker topology was designed which addressed some of the key limitations
of the previous designs. A UK patent application has been filed for this topology.
[J1, P1, S2].
An MMC VSC-HVDC test simulation model was developed in PSCAD and the
three leading detailed MMC modelling techniques were compared in terms of their
accuracy and simulation speed. This work identified limitations of the models and
presented an enhancement to one of the models to reduce the simulation time. The
findings of this were used to propose MMC modelling recommendations [J3].
1 MTTF – Mean Time To Failure, MTTR – Mean Time To Repair.
Chapter 1 Introduction
31
The test MMC VSC-HVDC simulation model was further developed using the
most suitable MMC modelling technique to produce a detailed EMT model for a
radial VSC-HVDC link for the connection of a typical Round 3 windfarm. Another
radial model was also developed for the interconnection of two active networks.
The AC fault ride-through performance of both radial models was assessed against
the UK grid code. This led to the standard DC voltage controller being modified in
order to improve the system’s fault recovery performance. Furthermore the radial
model for the interconnection of active networks was used in a collaborative effort
with another PhD student [J2] to investigate the key dynamics of active power
controllers for VSC-HVDC, regarding stability, performance and robustness. [C2,
J2, S3].
A four-terminal EMT VSC-HVDC model was developed based on a subsection of
a potential scenario outlined in National Grid’s 10 year statement. This model was
used to perform converter co-ordination studies and to compare different types of
cable model in terms of their accuracy and speed, for a range of typical VSC-
HVDC studies which has led to a set of modelling recommendations being
produced [C3, S4].
1.6 Publications
Books [B]:
1. Reliability indices for the VSC-HVDC components derived in this thesis have
been published in: G. Migliavacca “Advanced Technologies for Future
Transmission Grids”, Springer, 2012.
Cigre Working Groups:
1. Contribution to “Cigre WG B4-57 - Guide for the Development of Models for
HVDC Converters in a HVDC Grid”, as an observer.
2. Supergen report [S2] was used as a reference document for “Cigre WG B4-60 -
Designing HVDC Grids for Optimal Reliability and Availability Performance”.
Conference Papers [C]:
1. A. Beddard and M. Barnes, “Availability analysis of VSC-HVDC schemes for
offshore windfarms”, IET PEMD Conference, Bristol, UK, 2012.
Chapter 1 Introduction
32
2. A. Beddard and M. Barnes, “AC Fault Ride-through of MMC VSC-HVDC
Systems” IET PEMD Conference, Manchester, UK, 2014.
3. A. Beddard and M. Barnes, “HVDC Cable Modelling for VSC-HVDC Systems”
Accepted for publication in IEEE PES GM Conference, Washington DC, 2014.
Journal Papers [J]:
1. M. Barnes and A. Beddard, “Voltage Source Converter HVDC Links – The State
of the Art and Issues Going Forward” Energy Procedia, 2012.
2. W. Wang, A. Beddard, M. Barnes and O. Marjanovic, “Analysis of Active Power
Control for VSC-HVDC”, Accepted for publication in IEEE Transactions on
Power Delivery, 2014.
3. A. Beddard, M. Barnes and R. Preece, “Comparison of Detailed Modelling
Techniques for MMC Employed on VSC-HVDC Schemes”, Accepted for
publication in IEEE Transactions on Power Delivery, 2014.
4. Patents [P]:
1. A. Beddard and M. Barnes, “Conduction path of a DC breaker” Patent No.
GB2993911, 2011.
Supergen Reports [S]:
1. Supergen Report 3.3.1b entitled “Radial HVDC availability analysis”, 2011.
2. Supergen Report 3.3.2b entitled “DC circuit breaker technology”, 2012.
3. Supergen report 4.1.6 entitled “Detailed Modelling of MMC VSC-HVDC Links
for the Connection of Offshore Windfarms”, 2013.
4. Supergen report 4.1.5 entitled “Investigation of converter co-ordination”, 2013.
1.7 Thesis Structure
Chapter 2 – Availability Analysis
This chapter outlines the importance of availability analysis in determining the technical
and economic viability of the UK’s Round 3 windfarms. An availability model of a radial
VSC-HVDC system for the connection of a typical Round 3 windfarm is developed and
analysed using reliability indices derived from academic papers and industrial
documentation. This analysis determines the overall energy availability of the system and
identifies the key components which influence its value. An availability model for a MT
Chapter 1 Introduction
33
DC network is also developed and analysed for different levels of additional capacity in the
transmission paths back to shore. A cost-benefit availability analysis is performed to show
the relationship between the transmission scheme’s availability and its profitability.
Chapter 3 – HVDC Protection
In this chapter, the fundamental challenges associated with isolating faults in a HVDC grid
as opposed to a HVAC grid, are highlighted. A review of potential HVDC circuit breaker
topologies at the time of investigation is given and a new HVDC circuit breaker topology
is presented. In addition, the key requirements of a DC cable protection system for a
HVDC grid are outlined and a review of potential protection strategies is conducted.
Chapter 4 – MMC-HVDC
This chapter describes the modelling process for a MMC-HVDC link for a typical
Round 3 offshore windfarm, including the analysis to determine the value of key
parameters of the MMC and associated AC and DC networks, and the tuning and
implementation of the required control functions. It also describes the modelling process
for a MMC-HVDC link used to interconnect two AC networks. The MMCs are modelled
using the Detailed Equivalent Modelling (DEM) technique as a result of the work carried
out in Chapter 6.
Chapter 5 – MMC-HVDC Link Performance
This chapter assesses the steady-state and transient performance of the MMC-HVDC link
models developed in chapter 4 for the connection of a typical Round 3 windfarm and for
the interconnection of two active AC networks. The results are compared with those
derived from theory. The systems’ ability to comply with the GB grid code for AC
disturbances and reactive power requirements are investigated and a modification to the
standard DC voltage controller is proposed to improve the system’s active power recovery
response. The models’ response to DC faults are also investigated and the differences
between a MMC-HVDC link employed for the connection of a windfarm and a MMC-
HVDC link employed for the interconnection of two active networks are examined.
Chapter 6 – Comparison of MMC Modelling Techniques
The three leading detailed MMC modelling techniques are described and compared in
terms of their accuracy and simulation speed in this chapter. The findings of this study are
Chapter 1 Introduction
34
used to propose a set of modelling recommendations which offer technical guidance on the
state-of-the-art of detailed MMC modelling.
Chapter 7 – HVDC Cable Modelling
This chapter focuses on HVDC cable modelling for VSC-HVDC systems. The complex
structure of a submarine Cross-Linked Polyethylene (XLPE) HVDC cable is detailed and
parameters to represent a 1GW 300kV cable are derived from academic and commercial
documentation. Types of commercially available cable models are discussed and four of
these models are compared in terms of their accuracy and simulation speed for a range of
studies. The chapter concludes with a set of cable modelling recommendations.
Chapter 8 – Multi-terminal MMC Co-ordination
In this chapter a four-terminal high fidelity MTDC model for the connection of two 1GW
Round 3 offshore windfarms is developed and is used to investigate the performance of
selected MTDC control strategies for different scenarios. This chapter highlights the
importance of high fidelity MMC models when comparing MT control methods.
Chapter 9 – Conclusion and Future Work
The work contained in this thesis is summarised, and the main conclusions are discussed in
this chapter. A number of recommendations for further work are also presented.
Chapter 2 Availability Analysis
35
2 Availability Analysis
Availability can be defined as the probability of finding the component/device/system in
the required operating state at some point in the future [13]. The availability of a VSC-
HVDC system may therefore be defined as the percentage of time that the system is
expected to be operational. From a commercial point of view it is the scheme’s ‘energy
availability’ which is most important as this has the greatest impact on revenue. The
scheme’s energy availability is the measure of energy which could be transmitted through
the VSC-HVDC scheme except for limitations in capacity due to outages. Assessing the
expected energy availability of VSC-HVDC transmission systems used for the connection
of Round 3 windfarms is therefore essential in determining if these windfarms are
economically viable.
At the time of investigation there were a small number of publications which had assessed
the availability of VSC-HVDC transmission systems for different applications [2-4].
However, there were no publications which assessed the energy availability of VSC-
HVDC schemes for the connection of a typical Round 3 windfarm. Furthermore, the
justification for the component reliability indices, particularly the offshore components,
was very limited.
In this chapter, an availability model of a radial VSC-HVDC link and a MT VSC-HVDC
system for the connection of a Round 3 windfarm is developed. The availability model is
broken down into subsystems and then into components. Reliability data for each of these
components is gathered from academic papers, commercial documentation and
international surveys. Using this data, and engineering judgement, reliability indices for
each of the components are derived and justification for the indices is given along with
discussion of the assumptions used. Analytical availability techniques are then used to
assess the availability of each component and the energy availability of the scheme. Each
component’s influence on the scheme’s energy availability is also analysed.
An economic assessment of different VSC-HVDC schemes is carried out which calculates
the profitability of each of these schemes. This economic analysis demonstrates the link
between a scheme’s energy availability and profitability.
Chapter 2 Availability Analysis
36
2.1 Radial System
The most important aspect of evaluating the availability of a system is to understand the
way that the system operates and fails, and the consequence of a failure. Only through a
good understanding of the system can an availability model, which accurately represents
the system, be developed. The accuracy of the reliability data and the complexity of the
availability analysis techniques are irrelevant if a poor model is used.
National Grid has presented three different strategies for the connection of the UK’s Round
3 windfarms in their Offshore Development Information Statement (ODIS) [1, 14]. The
radial strategy requires more than twenty five 1GW VSC-HVDC point-to-point schemes.
A simplified diagram for the offshore connection design of a Round 3 windfarm
employing a 1GW VSC-HVDC point-to-point scheme is shown in Figure 2.1. Figure 2.2
shows the key components of the VSC-HVDC system.
Wind Farm
500MW AC
Substation
500MW AC
Substation
1000MW VSC-
HVDC Scheme
400kV AC Grid
220kV AC
33kV AC
Figure 2.1: 1GW VSC-HVDC point-to-point offshore connection overview diagram
Figure 2.2: 1GW point-to-point VSC-HVDC scheme
According to National Grid a typical VSC-HVDC link for the connection of a Round 3
windfarm has a power rating of 1GW at ± 300kV. The VSC-HVDC link is connected to
the two 500MW AC substations via a 220kV busbar. The configuration of the link is based
on the use of MMCs as it is expected that any VSC-HVDC link employed for the
connection of a Round 3 windfarm will be based on a form of MMC, due to their superior
efficiency in comparison to other VSC topologies. MMC-HVDC schemes require
165km ±300kV DC Cable
165km ±300kV DC Cable
Idc
Idc
400kV AC Grid220kV AC
Convertor
Reactor
MMCTransformer
GIS
Subsystem 1 – Offshore System
Subsystem 2 – DC System
Subsystem 3 – Onshore System
Offshore
Cooling
System
Control
System
Offshore
Cooling
System
Control
System
Subsystem 4 Subsystem 5
Ventilation
System
Ventilation
System
DC
Switchyard
DC
Switchyard
Chapter 2 Availability Analysis
37
limb/converter/arm reactors that are connected in series to each arm of the converter but
which are normally located outside the valve hall. The length of the HVDC cables are
taken as 165km, as this is the average straight line connection distance to shore of the
Round 3 windfarms which are likely to require HVDC transmission schemes. The onshore
MMC is connected to the 400kV onshore grid via two 500MW transformers and Gas-
insulated Switchgear (GIS).
The VSC-HVDC transmission scheme is broken down into three subsystems as shown in
Figure 2.2 and Figure 2.3. The scheme can only facilitate power transmission if all of the
three subsystems are in service. The complete failure of any one of the series-connected
subsystems results in an outage. This is the concept of series dependent systems.
Subsystems 1 and 3 are able to operate at 50% of their capacity due to the parallel
transformer configuration. The capacity of the VSC-HVDC link is therefore reduced to
50% of its rating if one or both of these subsystems are operating at 50% of their capacity.
The effect that the failure of each component has on its subsystem, and hence the overall
scheme, is discussed in Sections 2.2 and 2.3.
Figure 2.3: VSC-HVDC availability model for a point-to-point link
Analytical and Monte Carlo simulation are the two main categories of availability
evaluation techniques [13]. Analytical techniques represent the system by a mathematical
model and use mathematical solutions to evaluate the availability indices, whereas Monte
Carlo simulation techniques estimate the availability indices by simulating the process and
random behaviour of the system. Both analytical and Monte Carlo simulation techniques
have been used to determine the availability of the VSC-HVDC systems [15-17]. There
are advantages and disadvantages to each method and neither approach can be considered
superior to the other [13]; however, simulation techniques are typically employed in cases
where the required availability indices cannot be readily obtained using suitable analytical
techniques.
The energy availability of the system in this work can be evaluated in a relatively
straightforward manner by employing a widely used analytical technique which is referred
to as Capacity Outage Probability Tables (COPT) [15, 18]. The COPT-based technique is
Subsystem 2 –
DC System
Subsystem 3 -
Onshore System
Subsystem 1 –
Offshore System
Chapter 2 Availability Analysis
38
therefore used to evaluate the energy availability of the VSC-HVDC scheme. This
technique is implemented for the system in Section 2.3.
2.2 Component Availability
A brief explanation of each component and their reliability indices is given here. A
thorough explanation for the derivation of the Mean Time To Failure (MTTF) and Mean
Time To Repair (MTTR) indices of each component is contained in Appendix 2A and 2B.
The availability, A, of each component can be calculated directly from equation (2.1).
MTTF
AMTTF MTTR
(2.1)
The components in the offshore system are very similar to the components in the onshore
system. The key difference is that the onshore transformers and GIS bays are connected to
the 400kV grid whereas the offshore transformer and GIS bays are connected at 220kV, as
shown in Figure 2.2. The voltage rating of equipment could affect their likelihood to fail
and the time it takes to repair the component in the event of a failure. This is taken into
consideration in this availability analysis.
The crucial difference between a component being located offshore and a component being
located onshore, is the time it takes to repair the component. This is because it takes longer
to access the offshore platform. The time it takes varies significantly depending on the
following factors:
Method of transport (small vessel/large vessel/helicopter)
Availability of transport
Weather conditions
Location of offshore platform
Location of air field/port/offshore maintenance platform
Availability of required personnel
The access time could be as little as one day, based on travel via a helicopter in good
weather conditions with the correct administration procedures in place to enable rapid
deployment of personnel and equipment. However, it could also be as long as three months
[19] or more due to very bad weather conditions and unavailability of a suitably large
vessel.
Chapter 2 Availability Analysis
39
The mean time to access the offshore platform with different sized components or spare
parts has been estimated, as shown in Table 2.1. Pictures of the example components/spare
parts in Table 2.1 are shown in Figure 2.4, Figure 2.5 and Figure 2.6 to give an indication
of their size.
Component Size
Example Component Mean Offshore Access
Time (hr) Transportation
Method
Small MMC Sub-module 48 Helicopter/Small
Vessel Medium Gas-insulated Switchgear 168 Medium Vessel
Large Transformer 504 Large Vessel
Table 2.1: Mean time to access the offshore platform based on components/spare part size
Figure 2.4: Image of a MMC sub-module from [20]
The MMC Sub-module (SM), depicted in Figure 2.4, is approximately 0.6x1.5x0.3m
(HxWxD) and weighs approximately 165kg [20].
Chapter 2 Availability Analysis
40
Figure 2.5: Image of a 245kV GIS bay from [21]
The 245kV GIS bay, depicted in Figure 2.5, has a footprint of about 12m2 and weighs
approximately 5-6 tonnes [22].
Figure 2.6: Image of a 150kV, 140MVA transformer and offshore platform modified from [23]
Chapter 2 Availability Analysis
41
A 150kV, 140MVA transformer, as shown in Figure 2.6, is a relatively small transformer
in terms of its rating, but still weighs approximately 90 tonnes [22]. Larger transformers
are significantly heavier.
In order to accurately estimate the MTTR for an offshore component, the size of the spare
part that the component would require in the event of a failure must be estimated. From
this estimation, the Mean Offshore Access Time (MOAT) for the component can be
calculated. Calculating the MTTR for a component located offshore is not as simple as
adding the MTTR for the component located onshore to the MOAT for that component.
This is because some tasks, which affect the MOAT, may be performed in parallel with
tasks included in the MTTR for the onshore component. To give greater clarity to these
two aspects consider the following example:
In this availability analysis it is estimated that 70% of GIS failures require a small sized
spare part and that 30% require a medium sized spare part. From Table 2.1 the MOAT to
repair a GIS bay would be 84 hours (70% helicopter/small vessel and 30% medium
vessel). The MTTR for a GIS bay located onshore is estimated to be 120 hours. It is also
estimated that 20 hours of the offshore access time is spent performing administration
related tasks, which could be done concurrently with the time spent obtaining spare parts
(included in the onshore MTTR). Therefore the MTTR of an offshore GIS bay is the
MTTR of an onshore GIS bay, plus the MOAT, minus the mean time spent performing
concurrent tasks (i.e. 120+84-20=184hrs). Further information on this topic is contained in
Appendix 2A.
2.2.1 Converter Reactor
The converter reactors, also known as limb reactors or arm reactors, are connected in series
with each arm of the MMC. At the time of investigation, there was only one commercial
MMC in operation (commissioned 2010) [24] and therefore, published reliability indices
for MMC converter reactors are non-existent. Det Norske Veritas (DNV) is the only
known source to have published reliability indices for a VSC-HVDC converter reactor.
These reliability indices are likely to be for the converter reactors employed on a two-level
VSC scheme. Nonetheless the reliability indices for these reactors are taken to be similar to
the converter reactors used in MMC-HVDC schemes. The reliability indices published by
Chapter 2 Availability Analysis
42
DNV were used to estimate the reliability indices for a converter reactor, as given in Table
2.2.
Table 2.2: Estimated reliability indices for converter reactors
2.2.2 MMC with Cooling System and Ventilation System
The cooling system is required to ensure that the components within the MMC, such as the
IGBTs, do not exceed their rated temperature. The ventilation system is needed amongst
other functions to ensure that the valve hall temperature and moisture does not exceed set
limits. Failure of either the cooling system or ventilation system is likely to result in the
converter being tripped. It is for these reasons that critical parts in the cooling system are
duplicated [25].
As discussed in Section 2.2.1, failure statistics for MMCs are non-existent. The first two-
level VSC-HVDC scheme was commissioned in 1997 and since then many more schemes
have been commissioned. That said, no VSC-HVDC schemes have been included in the
Cigre World survey of HVDC schemes which is published biannually [26]. There are a
small number of sources which have published reliability indices for HVDC VSCs2. One
of these sources estimated the VSC’s reliability indices based on data from the Cigre
survey of Line Commutated Converter (LCC)-HVDC schemes. This survey publishes
reliability indices for the HVDC converter with the cooling system and the ventilation
system included. It is expected, although not explicitly stated, that reliability indices for the
converter from the other sources (see appendix) also include the cooling system and the
ventilation system. Estimating the reliability indices for the MMC from these sources
would therefore also include the cooling system and the ventilation system. The
disadvantage of this would be that the individual effect of the cooling system and
ventilation system on the scheme’s availability would be obscured.
The converter, cooling system and ventilation system were analysed as individual
components in [17]. However, the components used in the offshore cooling system and
onshore cooling system were inconsistent with each other. As an example, the offshore
2 Although it is not stated explicitly, it appears that the reliability indices are for two-level VSCs.
Component MTTF (yr) MTTR (hr) Availability
Onshore Converter Reactor 7 24 0.99961
Offshore Converter Reactor 7 192 0.99688
Chapter 2 Availability Analysis
43
cooling system did not account for instrumentation, whereas the onshore cooling system
did and neither accounted for the failure rates of the cooling system’s control system. The
same inconsistency seems to apply to the ventilation systems. There may well be very
good reasons to explain these inconsistencies, however without this knowledge it would be
unwise to use the data from this paper for the cooling system and ventilation system as the
resultant availability could be very inaccurate. It is believed, therefore, that more accurate
reliability indices would be obtained by estimating the MTTF and MTTR for the MMC
from the sources which have factored in the cooling system and ventilation system3. The
reliability indices for the MMC including the cooling system and ventilation system are
given in Table 2.3.
Table 2.3: Estimated reliability indices for MMC with ventilation system and cooling system
2.2.3 Control System
The HVDC control system is fully duplicated to ensure a high level of reliability. The
reliability indices for HVDC control systems used in academic and industry publications
are for two-level VSC-HVDC schemes and LCC-HVDC schemes. The control algorithms
for MCC-HVDC schemes are more complex than other HVDC schemes. The hardware,
with the exception of the valve based electronics, is similar. These were two of the factors
which were taken into consideration when estimating the MTTF and MTTR for the control
system. The reliability indices for this component are given in Table 2.4.
Table 2.4: Estimated reliability indices for control system
2.2.4 GIS and Transformer
The reliability indices for the GIS have been mainly estimated from the GIS failure
statistics contained in the 1996 Cigre GIS survey [27]. Cigre surveys for AC circuit
breakers, and reliability indices for AC circuit breakers from other sources, were also used.
3 Sources one and two (see appendix) have not explicitly stated that they have included the cooling and
ventilation system, however the data suggest that this was the case.
Component MTTF (yr) MTTR (hr) Availability
Onshore MMC 1.9 12 0.99928
Offshore MMC 1.9 60 0.99641
Component MTTF (yr) MTTR (hr) Availability
Onshore Control System 1.6 3 0.99979
Offshore Control System 1.6 17 0.99879
Chapter 2 Availability Analysis
44
GIS failure statistics are categorised based on the voltage rating of the equipment. The GIS
voltage ratings are determined by the rating of the busbar to which they are connected. The
offshore GIS connected to the windfarm side (Busbar 1) as shown in Figure 2.7, would
need to be rated at 220kV, whereas the GIS connected to the converter side (Busbar 2)
would need to be rated at about 275kV4. This places the offshore GIS within the Cigre
survey’s 200-300kV voltage category.
Figure 2.7: Offshore GIS and transformer configuration (Subsystem 4)
The onshore GIS connected to the converter side (Busbar 3) as shown in Figure 2.8 would
need to be rated at approximately 275kV5, whereas the GIS connected to the AC grid
(Busbar 4) would need to be rated at 400kV. Therefore, the GIS connected to Busbar 3
would be within the 200-300kV category and the GIS connected to Busbar 4 would be
within the 300-500kV category. The reliability indices for the offshore and onshore GIS
are given in Table 2.5
Figure 2.8: Onshore GIS and transformer configuration (Subsystem 5)
4 This value is based on the peak AC converter voltage being 0.75 times half of the DC voltage (0.75*300kV)
which gives a converter side line-to-line voltage of 275.57kV rms. The 0.75 is based on simulation results from the Trans Bay Cable project which has a peak AC converter voltage of 150kV and a DC voltage of ±200kV [28] It should be noted, that based on information which was not known at the time of investigation, the converter side voltage may be as high as 367.42kVrms, due to the MMC utilising the full DC link voltage. The potential impact this may have on the availability results is discussed in Section 2.3.4. 5 Based on information which was not known at the time of investigation, the converter side GIS would
most likely need to be rated for 367.42kV rms. The potential impact this may have on the availability results is discussed in Section 2.3.4.
GIS
Switchbay
500MW
500MW
1000MW
T1
T2
GIS 1
GIS 3
GIS 2
GIS 4
Busbar 1
Busbar 2
GIS
Switchbay
1000MW1000MW
T1
T2
GIS 1
GIS 3
GIS 2
GIS 4
Busbar 3
Busbar 4
Chapter 2 Availability Analysis
45
Table 2.5: Estimated reliability indices for GIS
The reliability indices for the power transformer have been estimated from a number of
sources including Cigre surveys, academic papers and industry publications. The failure
statistics are categorised based on the transformer’s highest winding voltage. The highest
winding voltage for the offshore transformers is within the 100-300kV category,
irrespective of whether a delta or star connected transformer is employed. However, a delta
connected onshore transformer would have a winding voltage of 400kV, whereas a star
connected transformer would be approximately 230kV. This availability analysis assumes
that the onshore transformer is connected to the grid via a star winding, placing the onshore
transformers in the 100-300kV6 category. The reliability indices for the offshore and
onshore transformers are given in Table 2.6.
Table 2.6: Estimated reliability indices for transformers
2.2.5 DC Switchyard
The major equipment in a DC VSC switchyard consists of HV capacitor banks, line
reactors, measurement transducers and switchgear [29]7. The major equipment in a LCC
DC switchyard consists of DC harmonic filters, smoothing reactors, measurement
transducers and switchgear [30]. Figure 2.9 shows images of a MMC DC switchyard (left)
and a LCC DC switchyard (right).
6 Based on information which was not known at the time of investigation, the onshore transformer and
possibly the offshore transformer would most likely need to be rated for 367.42kV rms. The potential impact this may have on the availability results is discussed in Section 2.3.4. 7 HV capacitor banks are not necessarily required for MMCs.
Component MTTF (yr) MTTR(hr) Availability
Offshore switchbay 250 184 0.99992
400kV onshore switchbay 100 120 0.99986
275kV onshore switchbay 250 120 0.99995
Component MTTF(yr) MTTR(hr) Availability
Offshore Transformer 95 1512 0.99819
Onshore Transformer 95 1008 0.99879
Chapter 2 Availability Analysis
46
Figure 2.9: Image of a MMC VSC DC Switchyard (left, modified from [29]), Image of a LCC DC
Switchyard (right modified from [31])
Since there is significant similarity between the DC switchyards, the failure statistics from
the World HVDC survey (LCC) is used to estimate the reliability indices for the MMC
VSC-HVDC DC switchyard. The latest World HVDC survey was published in 2010,
which at the time of the study contained data collected on LCC-HVDC schemes during
2007-2008 [26]. Back-to-back HVDC schemes do not normally require smoothing reactors
or DC filters [30], therefore only the data from transmission schemes is considered. The
reliability indices for a DC switchyard are given in Table 2.7.
Table 2.7: Estimated reliability indices for DC switchyard
2.2.6 DC Cable
Submarine cable failure rates are very subjective. They are heavily influenced by many
factors including: fishing activity, installation protection method, awareness of cable
routes, water depth, and hardness of the sea-bed. Reliability indices for submarine cables
should therefore be used with a high level of caution and ideally estimated on a case by
case basis.
The latest survey for failures of submarine cables, at the time of the study, was published
in 2009 by Cigre for data collected between 1990 and 2005 [32]. Unfortunately failure
rates for the most common type of submarine cable used in VSC-HVDC schemes (DC-
XLPE) were not given in the report. The majority of known cable failures were due to
Component MTTF(yr) MTTR(hr) Availability
Onshore DC Switchyard 4.02 26.06 0.99926
Offshore DC Switchyard 4.02 98.06 0.99722
Line Reactor
Chapter 2 Availability Analysis
47
external damage, which is likely to be independent of cable type and voltage rating8. The
average failure rate of all cable types and voltages was therefore used to estimate failure
for DC-XLPE submarine cable. The average failure rate of submarine cables with some
form of installation protection was calculated to be approximately 0.1. Based on this figure
and the value given by DNV, it was estimated that the annual failure of a submarine cable
is 0.07 failures per 100km. The circuit length in this work is defined as the distance
between the onshore and offshore converter (i.e. 165km not 330km).
The average repair time for submarine cables in the Cigre survey was approximately 60
days, which is the same as the MTTR used by DNV in their availability analysis. Therefore
a MTTR of 60 days will be assumed in this chapter. The reliability indices and calculated
availability for this component are given in Table 2.8.
Table 2.8: Estimated submarine cable reliability indices
2.3 Radial VSC-HVDC Scheme Availability Analysis
The availability for the radial VSC-HVDC scheme as shown in Figure 2.3 will be
calculated in this section. First, the availability of subsystems 1, 2 and 3 are calculated and
then the availability of the overall system can be calculated.
2.3.1 Offshore System Availability Analysis (subsystem 1)
The offshore system is broken down into subsystems and components. The offshore
system has series dependency as shown in Figure 2.10. The failure of any one component
from subsystem 4 to the control system will result in the failure of the offshore system and
therefore the failure of the transmission scheme. Subsystem 4 (transformers and GIS) can
operate at 100% or 50% capacity. Due to the series dependency, if subsystem 4 is
operating at 50% capacity then the offshore subsystem, and consequently the transmission
scheme, can only operate at 50% capacity.
8 Only 4 of the 49 reported failures were classed as internal failures which were all for self-contained oil
filled cables.
Component Failure rate (occ/yr/100km) Circuit Length (km) MTTF (yr) MTTR (hr) Availability
DC Cable 0.07 165 8.493625 1440 0.98101
Chapter 2 Availability Analysis
48
Subsystem 4
(100%,50%)
Converter Reactor
(100%)
MMC
(100%)
Offshore Cooling
System
(100%)
Control System
(100%)
Ventilation System
(100%)
Simplified to a single component (MMC)
Figure 2.10: Availability model for offshore system (Subsystem 1)
The calculated availability of all the components in the offshore subsystem is given in
Table 2.9.
Table 2.9: Availability of offshore components
The simplified offshore subsystem availability diagram is shown in Figure 2.11.
Subsystem 4
(100%,50%)
Converter Reactor
(100%)
MMC
(100%)
Control System
(100%)
Figure 2.11: Simplified availability model for offshore system (Subsystem 1)
Subsystem 4 contains two parallel branches as shown in Figure 2.2, and repeated here in
Figure 2.12 . If both branches are in service subsystem 4 operates at full capacity. If only
one branch is in service subsystem 4 operates at 50% capacity.
Figure 2.12: Offshore transformers and GIS configuration (Subsystem 4)
The protection of the equipment before, and including, Busbar 1 is assumed to be the
responsibility of the AC substation manufacturer. As a result, the failure of this equipment
Component MTTF(yr) MTTR(hr) Availability
Offshore GIS Switchbay 250 184 0.99992
Offshore Transformer 95 1512 0.99819
Offshore Converter Reactor 7 192 0.99688
Offshore MMC 1.9 60 0.99641
Offshore Control System 1.6 17 0.99879
GIS
Switchbay
500MW
500MW
1000MW
T1
T2
GIS 1
GIS 3
GIS 2
GIS 4
Busbar 1
Busbar 2
Chapter 2 Availability Analysis
49
will not be included in this availability analysis. It is also assumed that permanent faults on
Busbar 2 are very rare and can therefore be neglected.
There are many components which make up a GIS switchbay including circuit breakers,
disconnectors and instrumentation. The component which fails and the mode in which that
component has failed determines the available capacity of the system. To demonstrate this,
three example GIS failure modes and consequences are shown in Table 2.10.
Failure Mode Immediate Effect Number of Branches Affected
Capacity Outage (MW)
Disconnector opens inadvertently Isolates the connected
branch 1 500
Circuit fails to open on command Cannot clear transformer
fault 2 1000
Insulation breakdown to earth Short-circuit connected
busbar 2 1000
Table 2.10: Example GIS failure modes and consequences
There are many different failure modes of a GIS switchbay. In order to take into account
each failure mode, and its effect on the capacity of the system, complex analysis could be
conducted. However, without accurate failure mode input data even the most sophisticated
availability analysis method will produce inaccurate results.
Data to determine the failure rate of a GIS switchbay as a single unit is limited; data to
estimate with any real degree of accuracy what component within a modern GIS switchbay
will fail, and how that component will fail, is near enough non-existent. It is worth noting
that in [27] there is some data from the Cigre 1996 GIS survey for the symptoms of GIS
failures. This includes symptoms such as “loss of mechanical function” and “failure to
operate switching device”. Such symptoms however, do not indicate the failure mode of
the GIS. The biggest single failure symptom (>30%) was an insulation breakdown to earth,
which indicates the third failure mode in Table 2.10.
From the research conducted into failure mode statistics for GIS, it has been established
that the biggest single failure symptom for GIS was a “breakdown to earth”. It is therefore
assumed that the failure of any GIS bay results in full capacity outage, which is the worst
case scenario. There are 64 possible combinations of component states in Figure 2.12,
when considering each component as either being available or unavailable. Only the
combinations that result in some available capacity are calculated, since the majority of
Chapter 2 Availability Analysis
50
combinations result in no available capacity, due to assumption that any GIS failure results
in full capacity outage.
In order for subsystem 4 to operate at full capacity, all of the components (GIS1-4 and T1-
2) must be available. The failure of any one transformer, providing that all of the GIS bays
are available, would result in an available capacity of 500MW. All other component
combinations result in full capacity outage.
Table 2.11: Available capacity table for subsystem 4
From equation (2.2) the available capacity of the offshore system (subsystem 1) can be
calculated. The results are given in Table 2.12.
1(100%) 4(100%) Re (100%) (100%) (100%)
1(50%) 4(50%) Re (100%) (100%) (100%)
1(0%) 1(100%) 1(50%)1
Sub Sub actor MMC Control
Sub Sub actor MMC Control
Sub Sub Sub
A A A A A
A A A A A
A A A
(2.2)
Table 2.12: Available capacity table for the offshore subsystem (Subsystem 1)
Table 2.12 shows that the offshore subsystem is operating at full capacity approximately
98.8%, half capacity 0.4% and is completely out of service 0.8% of the time.
2.3.2 Onshore System Availability Analysis (subsystem 3)
The analysis of the onshore system, subsystem 3, is the same as for the offshore system.
The availability of all of the components in the onshore system is given in Table 2.13.
Available Capacity GIS1 GIS2 GIS3 GIS4 T1 T2 Probability Availability
100% 1 1 1 1 1 1 0.99604 0.99604
1 1 1 1 1 0 0.00181
1 1 1 1 0 1 0.00181
0 0.00034 0.00034
50% 0.00362
All other combinations
1= available, 0= unavailable
Capacity Availability
100% 0.98817
50% 0.00359
0% 0.00824
Subsystem 1
0%
Chapter 2 Availability Analysis
51
Table 2.13: Availability of onshore components
The available capacity of subsystem 5 is given in Table 2.14.
Table 2.14: Available capacity table for subsystem 5
From equation (2.3) the available capacity of subsystem 3 can be calculated. The results
are given in Table 2.15.
3(100%) 5(100%) Re (100%) (100%) (100%)
3(50%) 5(50%) Re (100%) (100%) (100%)
3(0%) 3(100%) 3(50%)1
Sub Sub actor MMC Control
Sub Sub actor MMC Control
Sub Sub Sub
A A A A A
A A A A A
A A A
(2.3)
Table 2.15: Available capacity table for the onshore system (Subsystem 3)
Table 2.15 shows that the onshore system is operating at full capacity approximately
99.6%, half capacity 0.2% and is completely out of service 0.2% of the time.
2.3.3 DC System Availability Analysis (subsystem 2)
The DC system is broken down into three series dependent components as shown in Figure
2.13.
Component MTTF(yr) MTTR(hr) Availability
400kV Onshore GIS Switchbay 100 120 0.99986
275kV Onshore GIS Switchbay 250 120 0.99995
Onshore Transformer 95 1008 0.99879
Onshore Converter Reactor 7 24 0.99961
Onshore MMC 1.9 12 0.99928
Onshore Control System 1.6 3 0.99979
Available Capacity GIS1 GIS2 GIS3 GIS4 T1 T2 Probability Availability
100% 1 1 1 1 1 1 0.99720 0.99720
1 1 1 1 1 0 0.00121
1 1 1 1 0 1 0.00121
0% 0.00038 0.00038
50% 0.00242
All other combinations
1= available, 0= unavailable
Capacity Availability
100% 0.99588
50% 0.00241
0% 0.00171
Subsystem 3
Chapter 2 Availability Analysis
52
Figure 2.13: Availability model of subsystem 2
Subsystem 2 operates at full capacity if all three series dependent components are in
service. If any one component is out of service, then subsystem 2 is completely
unavailable. The same approach which was used for subsystems 1 and 3 is used to analyse
this subsystem. The results are given in Table 2.16.
Table 2.16: Available capacity table for the DC system (Subsystem 2)
2.3.4 Radial VSC-HVDC Scheme Availability
The availability diagram of the VSC-HVDC scheme is shown in Figure 2.14. The available
capacity of the overall VSC-HVDC scheme is calculated in Table 2.17.
Subsystem 2 - DC
System (100%)
Subsystem 3 -
Onshore System
(100%,50%)
Subsystem 1 –
Offshore System
(100%,50%)
Figure 2.14: Availability model for the VSC-HVDC scheme
Table 2.17: Available capacity table of radial VSC-HVDC scheme
The radial VSC-HVDC scheme operates at full capacity approximately 96.2% of the time,
half capacity 0.6% of the time and zero capacity 3.2% of the time. The scheme’s energy
availability is therefore approximately 96.5%9. The target annual scheduled outage for
9 Energy availability (EA) is defined in this chapter as “the maximum amount of energy which could have
been transmitted except for forced outages”.
Offshore DC
Switchyard
(100%)
DC Cable (100%)
Onshore DC
Switchyard
(100%)
Capacity Availability
100% 0.97757
0% 0.02243
Subsystem 2
Capacity (%) Subsystem1 Subsystem 2 Subsystem 3 Probability Availability
100 1 1 1 0.96202 0.96202
0.5 1 1 0.00350
1 1 0.5 0.00233
0.5 1 0.5 0.00001
0 0.03215 0.03215Any Other Combination
50 0.00583
Chapter 2 Availability Analysis
53
maintenance is typically 0.82% (72 hours) for a VSC-HVDC scheme10
. The overall energy
availability for the VSC-HVDC scheme analysed in this work would therefore be
approximately 95.7%11
. The only known availability statistics for VSC-HVDC schemes
are for the Murraylink and the Cross Sound Cable project. The average overall energy
availability for the Murraylink and the Cross Sound Cable project are 96.5% and 96.9%
respectively [33]. These figures include forced and scheduled outages. Considering that the
VSC-HVDC scheme in this work is for an offshore windfarm, and therefore one converter
station is based offshore, an overall energy availability of 95.7% seems to be within
reasonably expected limits.
A component’s influence on the availability of the scheme can be assessed by setting that
component’s failure rate to zero and noting the change in the scheme’s availability. Figure
2.15 shows that the DC cable has the greatest effect on the availability of the VSC-HVDC
link.
Figure 2.15: Component importance for availability
As mentioned previously the failure rate of submarine cables is dependent upon many
factors. The annual failure rate used in this availability analysis was 0.07 failures per
100km circuit. The effect of the submarine cable failure rate on the energy availability of
the VSC-HVDC scheme excluding scheduled maintenance is shown in Table 2.18.
10
The manufacturer’s target scheduled outage rate for the VSC-HVDC Cross Sound Cable project was 0.82% [33] 11
Overall energy availability (OEA) is defined in this chapter as “the maximum amount of energy which could have been transmitted except for forced and scheduled outages”.
DC Cable 54%
Offshore MMC 10%
Offshore Reactor
9%
Offshore DC Switchyard
8%
Other Offshore Equipment
9%
Onshore Equipment
10%
Chapter 2 Availability Analysis
54
Table 2.18: Cable sensitivity analysis
Table 2.18 indicates that if the true annual failure rate of submarine VSC-HVDC cables is
in the vicinity of 0.7 failures per 100km of circuit then VSC-HVDC schemes for the
connection of the UK’s Round 3 offshore windfarms are unlikely to be commercially
viable. This would in fact make the Round 3 windfarms altogether unviable as any
technology which requires submarine cables would have a similar availability.
The results presented in this chapter are based on the GIS and the transformer windings
connected to the converter being rated for a phase-to-phase voltage of approximately
275kVrms. Based on information which was not known at the time of investigation, the
converter side GIS and transformers with delta windings would most likely need to be
rated for 367kVrms. A decrease in energy availability of 0.2% is calculated when adjusting
the reliability data for the scheme’s four transformers to the 300-700kV voltage class and
the data for the converter side GIS to the 300-500kV class. Taking into account that a
voltage rating of 367kV for the GIS and the transformers is at the lower end of the 300-
500kV and the 300-700kV voltage classes respectively, and that the difference in the
energy availability is 0.2%, the results presented in this chapter are still considered to be
representative of a typical VSC-HVDC link for a Round 3 windfarm.
2.4 MT HVDC Network Availability Analysis
Many potential benefits have been identified from interconnecting offshore windfarms via
a MTDC network. These benefits include a reduction in the volume of assets installed
offshore, improved operational flexibility and network security [1]. A simplified diagram
of the MTDC network, which will be analysed in this chapter, is shown in Figure 2.16.
Cable Failure Rate (occ/yr/100km) Energy Availability (%)
0.007 98.2
0.07 96.5
0.7 79.7
Chapter 2 Availability Analysis
55
Figure 2.16: MT HVDC system
The three offshore nodes are rated at 600MW each, giving a total grid capacity of 1.8GW,
which is the maximum in-feed loss permitted by the National Electricity Transmission
System Security and Quality of Supply Standard (NETS SQSS) [14]. A fault on the DC
grid could temporarily cause the entire 1.8GW to be disconnected from the AC grid, while
the faulty section of the grid is isolated. The installation of HVDC circuit breakers with a
suitable protection system would enable DC faults to be cleared without de-energising the
entire DC grid and therefore the grid’s maximum capacity could be greater than 1.8GW.
However, there are currently no HVDC circuit breakers commercially available. The MT
network analysed in this chapter does not contain HVDC circuit breakers and hence its
maximum capacity is limited to 1.8GW.
The DC cables connected between the onshore and offshore converters have a length of
165km. This length of cable is approximately the average straight line connection distance
for the radial HVDC schemes outlined in ODIS. The offshore converters are connected
together via 60km of DC cable. This length of DC cable was chosen as it may be more
suitable to connect the windfarms together using HVAC for connection distances less than
60km. This analysis neglects the grid’s downtime due to isolating a DC side fault, as this
time is insignificant for the calculation of the grid’s availability.
Wind
Farm 3
165km DC Cable
AC Grid
Wind
Farm 1
DC
Shore
Wind
Farm 2
165km DC Cable
600MW Offshore
AC Substation
600MW Offshore
AC Substation
600MW Offshore
AC Substation
600MW Offshore
Node C (OFNC)
600MW Offshore
Node B (OFNB)
600MW Offshore
Node A (OFNA)
Onshore Node A
(ONNA)
Onshore Node B
(ONNB)
60km DC Cable
60km DC Cable
Chapter 2 Availability Analysis
56
Each offshore node consists of an offshore DC switchyard connected in series with
subsystem 1 and each onshore node contains an onshore DC switchyard connected in
series with subsystem 3, as shown in Figure 2.17.
Subsystem 1 –
Offshore System
(100%,50%)
Offshore DC
Switchyard
(100%)
Offshore Node (OFN)
Subsystem 3 –
Onshore System
(100%,50%)
Onshore DC
Switchyard
(100%)
Onshore Node (ONN)
Figure 2.17: Onshore and offshore nodes
600MW Offshore
Node A – OFNA
(100%,50%)
600MW Offshore
Node B - OFNB
(100%,50%)
600MW Offshore
Node C – OFNC
(100%,50%)
Onshore Node A-
ONNA
(100%,50%)
Onshore Node B –
ONNB
(100%,50%)
165km DC Cable -
C3 (100%)
60km 1200MW
DC Cable – C1
(100%)
60km 1200MW
DC Cable – C2
(100%)
165km DC Cable–
C4 (100%)
Subsystem 6 Subsystem 7
Figure 2.18: Block diagram of MTDC network
The onshore nodes and their series-connected DC cable can be combined into a single
subsystem as shown in Figure 2.18 and Figure 2.19. The offshore nodes, as well as
subsystem 6 and subsystem 7, can be in one of three states (100%, 50% or 0%), due to the
dual transformers in subsystems 1 and 3. The DC cables (C1 and C2) can be in one of two
states (100% or 0%). The HVDC grid as shown in Figure 2.18 therefore has 972 ( 5 23 2 )
possible states. Simplifying these nodes/subsystems to two states would reduce the number
of possible HVDC grid states to 128 (27). The probability that subsystem 1 or subsystem 3
is operating at 50% capacity is negligible, as shown in Table 2.12 and Table 2.15. In this
case, the 50% state may therefore be eliminated without introducing any significant error
in the overall availability analysis of the HVDC grid. The probability of the subsystem
Chapter 2 Availability Analysis
57
operating at 100% capacity is increased accordingly to account for the exclusion of the
50% state. As an example, subsystem 1 which has three states, can be simplified to two
states of equivalent available capacity as shown in Table 2.19.
Table 2.19: Equivalent available capacity table for subsystem 1
Subsystem 1 in the MTDC grid is rated at 600MW. The equivalent capacity of subsystem 1
can therefore be calculated as follows:
3
2
1 600 0.988167 300 0.003591 593.978
1 600 0.98996 593.978
Cap State
Cap State
Sub MW MW MW
Sub MW MW
(2.4)
Equation (2.4) shows that there is no difference between the three-state model and the
simplified two-state model in terms of the overall capacity of subsystem 1. The energy
transmitted through subsystem 1 when considered as a standalone system is therefore the
same whether it is represented by a three-state model or a two-state model. The calculated
availability of a system containing several three-state models is not strictly equal to the
calculated availability of a system with equivalent simplified two-state models, however
since the probability of the node/subsystem operating in the eliminated state is very small,
the error is insignificant for the cases analysed.
600MW Offshore
Node A – OFNA
(100%)
600MW Offshore
Node B - OFNB
(100%)
600MW Offshore
Node C – OFNC
(100%)
Subsystem 6
(100%)
Subsystem 7
(100%)
60km 1200MW
DC Cable – C1
(100%)
60km 1200MW
DC Cable – C2
(100%)
Figure 2.19: Simplified two-state block diagram of a MTDC network
The simplified two-state capacity availability tables for the onshore and offshore nodes as
well as subsystem 6 and subsystem 7 are shown in Table 2.20.
Capacity Availability Equivalent Availability
100% 0.988167 0.989963
50% 0.003591
0% 0.008242 0.010037
Subsystem 1
Chapter 2 Availability Analysis
58
Table 2.20: Two-state capacity availability tables
The seven components/nodes/subsystems in Figure 2.19 operate in one of two states giving
a possible 128 grid states. VBA code was written in Excel to produce a 7x128 truth table.
Only the first four states are shown here in Table 2.21. The full table is contained in
Appendix 2C.
Table 2.21: Truth table for MTDC network
Each ‘1’ and ‘0’ in the truth table is replaced with the probability of that subsystem/node
being available and unavailable respectively. The probability of each state is then
calculated by multiplying the seven columns together as shown in Table 2.22.
Table 2.22: Probability table for MTDC network
In order to calculate the HVDC grid’s overall availability, the grid’s capacity associated
with each of the 128 states must be deduced. VBA code was written to calculate the grid’s
capacity for each of the 128 states. Table 2.23 shows the available capacity for the first 4
states with subsystem 6 and subsystem 7 having a capacity rating of 900MW each.
Table 2.23: Capacity table for MTDC network with Sub6=Sub7=900MW
Summing the probabilities of each state for each grid capacity level gives the grid’s
available capacity as shown in Table 2.24.
Capacity Availability
100% 0.98721
0% 0.01279
Offshore Node
Capacity Availability
100% 0.99635
0% 0.00365
Onshore Node
Capacity Availability
100% 0.97743
0% 0.02257
Subsystem 6 and7
State OFNA OFNB OFNC C1 C2 Sub 6 Sub 7
1 1 1 1 1 1 1 1
2 1 1 1 1 1 1 0
3 1 1 1 1 1 0 1
4 1 1 1 1 1 0 0
State OFNA OFNB OFNC C1 C2 Sub 6 Sub 7 Probability
1 0.98721 0.98721 0.98721 0.99310 0.99310 0.97743 0.97743 0.90654
2 0.98721 0.98721 0.98721 0.99310 0.99310 0.97743 0.02257 0.02093
3 0.98721 0.98721 0.98721 0.99310 0.99310 0.02257 0.97743 0.02093
4 0.98721 0.98721 0.98721 0.99310 0.99310 0.02257 0.02257 0.00048
State OFNA OFNB OFNC C1 C2 Sub 6 Sub 7 Capacity (MW)
1 1 1 1 1 1 1 1 1800
2 1 1 1 1 1 1 0 900
3 1 1 1 1 1 0 1 900
4 1 1 1 1 1 0 0 0
Chapter 2 Availability Analysis
59
Table 2.24: Capacity availability table for MTDC network with Sub6=Sub7=900MW
The MTDC network shown in Figure 2.19, with each path to shore (sub6 & sub7) rated at
900MW, has an energy availability of 0.963. The energy availability was 0.965 for a radial
HVDC link as shown in Section 2.3. This indicates that three 600MW radial links would
have a higher energy availability than an 1800MW HVDC grid with each path to shore
rated at 900MW. Upgrading subsystems 6 and 7 to 1200MW increases the grid’s
availability as shown in Table 2.25.
Table 2.25: Capacity availability table for regional MTDC network with Sub6=Sub7=1200MW
The grid’s availability can be increased further by rating each path to shore equal to the
grid’s maximum capacity, as shown in Table 2.26.
Table 2.26: Capacity availability table for MTDC network with Sub6=Sub7=1800MW
It should be noted that the availability figures given in Table 2.26 are calculated from
component reliability indices for a DC voltage of ±300kV, however it is likely that any
1800MW VSC-HVDC scheme would be built at a voltage greater than this. Data on such
systems are even sparser than for ±300kV systems, and so this study has focused on
±300kV.
Capacity (MW) Availability Energy Availability
1800 0.90654
1500 0.01260
1200 0.03560
900 0.04395
600 0.00079
0 0.00052
Sub 6&7 =900MW
0.96302
Capacity (MW) Availability Energy Availability
1800 0.91915
1200 0.07954
600 0.00079
0 0.00052
Sub 6 & Sub 7 = 1200MW
0.97244
Capacity (MW) Availability Energy Availability
1800 0.96101
1200 0.03768
600 0.00079
0 0.00052
Sub 6 & Sub 7=1800MW
0.98640
Chapter 2 Availability Analysis
60
2.5 Cost-benefit Analysis
This section compares the required capital investment against the calculated availability of
each of the following schemes:
1. 1800MW MTDC network with each path to shore rated at 900MW
2. Three 600MW radial HVDC links
3. 1800MW MTDC network with each path to shore rated at 1200MW
Since the schemes are being compared with one another, the components which are
common to all schemes can be ignored as the cost of these components would be the same
regardless. All of the schemes require three 600MW offshore nodes; hence the cost of
these items has been neglected. The costs of components used in this cost-benefit analysis
are from the ODIS 2011 annex and are for indicative purposes only [22].
Table 2.27: VSC converter costs12
Table 2.28: HVDC extruded cable costs13
Table 2.29: Cable installation costs
12
It is assumed that the VSC converter cost is for a single converter including AC and DC switchyard. 13
It is assumed the cost is per km of cable not per km of route (i.e one radial link requires 2x165km of cable).
Rating Min Max Average
300kV 500MW 65 80 72.5
320kV 850MW 85 105 95
500kV 1250MW 105 130 117.5
500kV 2000MW 125 175 150
VSC Converter Costs (£m)
Extruded HVDC Cable
Cross sec area Min Max Average Min Max Average
mm2 £k/km £k/km £k/km £k/km £k/km £k/km
1200 200 400 300 300 450 375
1500 250 400 325 300 450 375
1800 300 450 375 300 500 400
2000 300 500 400 350 550 450
±150kV ±320kV
Cable Installation Type Min Max Average
Twin Cable in Single Trench 0.5 0.9 0.7
Cable Installation Costs (£m/km)
Chapter 2 Availability Analysis
61
From Table 2.27, Table 2.28 and Table 2.29, the cost of the three transmission schemes
(excluding the offshore nodes) can be estimated. The required cross sectional area for
HVDC submarine cables of different power ratings was estimated from data given in [34].
It is estimated that the 600MW, 900MW and 1200MW cables would require cross
sectional areas of approximately 630mm2, 1400mm
2 and 2200mm
2 respectively
14. The
costs of each scheme excluding the offshore nodes are given in Table 2.30.
Table 2.30: HVDC transmission scheme costs excluding offshore nodes
The HVDC grid with each path back to shore rated at 900MW (scheme 1) is the least
expensive scheme, but also has the lowest energy availability. The radial scheme (scheme
2) and the HVDC grid with each path back to shore rated at 1200MW (scheme 3) are more
expensive than scheme 1, but their energy availability is higher. Since higher availability
equates to greater revenue, it may make more economic sense to invest a greater amount of
capital to obtain a scheme with a higher availability.
The revenue lost each year due to a transmission scheme being unavailable can be
calculated using equation (2.5).
8760( )R F pLoss U P C hrs S (2.5)
£ /
R
F p
U Unavailability P Rated power in MW
C Capacity factor S Electricty sale pricein MW
14
Figures are based on a ±300kV submarine cable with a copper conductor in a moderate climate spaced closely together. These figures are indicative only.
Scheme Item Cost £m Total Cost £m
900km ±300kV 900MW Cable 337.5
Cable Installation 315
2 x 900MW Onshore Converter 200
990km ±300kV 600MW Cable 321.75
Cable Installation 346.5
3 x 600MW Onshore Converter 240
900km ±300kV 1200MW Cable 427.5
Cable Installation 315
2 X1200MW Onshore Converter 240
1. 900MW 852.50
2. Radial 908.25
3. 1200MW 982.5
Chapter 2 Availability Analysis
62
The capacity factor for the three schemes is assumed to be 0.415
. This means that over the
course of the year the transmission scheme is only required to operate at 40% of its rated
power. The electricity sale price is assumed to be £150/MWh16
.
The annual savings for scheme 2 and scheme 3 compared with scheme 1 is calculated by
subtracting the annual loss of each scheme from the annual loss of scheme 1.
Table 2.31: Economic cost-benefit analysis
Dividing the additional capital investment of a scheme by that scheme’s additional annual
revenue is one way to calculate the number of years it takes to repay the additional
investment. If the number of years to repay the investment is less than the life expectancy
of the scheme, then it would suggest that it is worth investing the additional capital.
HVDC schemes can have a life expectancy in excess of 40 years [40]. This cost-benefit
availability analysis indicates that scheme 3 offers the best potential return for the investor.
Variations in capital costs, capacity factor and electricity price could significantly impact
on these results. This type of economic cost-benefit analysis is simplistic and should only
be used as an indication. An extensive cost-benefit analysis would need to consider the
projected inflation rates, interest rates, and electricity prices over the next 40 years as well
as taxation, exchange rates and commodity prices such as copper. This type of economic
forecasting is outside the scope of this work.
The purpose of this cost-benefit availability analysis is to clearly show the strong link
between the transmission scheme’s availability and its economic feasibility. Other factors,
such as system losses, must be taken into consideration when evaluating which
transmission scheme configuration offers the greatest financial reward.
15
Capacity factors of 0.35-0.45 are typical for offshore windfarms [35]. 16
This figure is based on 1MWh of energy generated by an offshore windfarm being equal to the electricity wholesale price plus two renewable obligations certificates (ROC) plus one levy exemption certificate (LEC). The electricity wholesale price is approximately £60/MWh [36] Accredited offshore windfarms are currently awarded two ROC’s per MWh [37] , where each ROC is worth £38.69 plus 10% for headroom [38] . One LEC has a value of £4.85 [39] .
Scheme Capital Cost
£m
Availability Loss
£m/yr
Saving
£m /yr
Additional Capital
Cost £m
Payback
(yr)
1 852.5 0.963 34.990 0 0 0
2 908.25 0.965 33.174 1.816 55.75 31
3 982.5 0.972 26.073 8.917 130 15
Chapter 2 Availability Analysis
63
2.6 Summary
The most suitable transmission technology for the connection of large offshore windfarms
located more than approximately 50km from shore is VSC-HVDC. The technical and
commercial viability of connecting vast amounts of the UK’s generating capacity long
distances from shore is dependent upon the availability of VSC-HVDC schemes.
A radial VSC-HVDC scheme has been constructed for the purpose of performing
availability analysis. The scheme was based on the potential radial VSC-HVDC designs
outlined in National Grid’s ODIS, to ensure that the scheme represents a typical VSC-
HVDC link. Availability analysis, independent of methodology, can only ever be as good
as the input data. Unfortunately there are no true failure statistics for VSC-HVDC
components available in the public domain. The reliability indices for each component
within the scheme have therefore been estimated based on the most credible information
available.
The availability analysis for the radial VSC-HVDC scheme has shown the energy
availability due to forced outages to be approximately 96.5%. The DC submarine cable
was identified to be the key component which affects the availability of the transmission
scheme. Every effort must therefore be made to ensure failures of submarine cables are
minimised.
Availability analysis was carried out on a MTDC network with each of its two paths back
to shore rated at 900MW, 1200MW and 1800MW. This analysis showed that the
availability of the MTDC network is highly dependent upon the rating of the network’s
paths back to shore and that the grid with paths rated at 1200MW and 1800MW had a
higher availability than an equivalent radial system.
The strong link between a HVDC transmission scheme’s availability and economic
feasibility has also been established.
2.7 Conclusion
Connecting large amounts of offshore wind far from the shore is a clear way to increase
renewable energy generation. However, if the availability of the transmission systems
which facilitate the power transfer back to shore is poor, then the cost of energy to the
consumer will increase and will have a negative impact on the economy. Work to ensure a
Chapter 2 Availability Analysis
64
high availability of these transmission schemes is therefore of paramount importance.
Availability analysis is a good tool to calculate the availability of these schemes and to
identify key components which have the greatest impact on this value. This would allow
mitigation strategies, which would improve the scheme’s availability, to be put in place
before the schemes are built. With the current lack of reliability data for VSC-HVDC
components, conclusive availability analysis cannot be performed, although the key
importance of the cable’s availability is highlighted. Furthermore, HVDC grids with
additional capacity have been shown to have a higher availability than an equivalent radial
HVDC scheme and consequently could provide a more cost-effective solution for the
connection of offshore windfarms.
Chapter 3 HVDC Protection
65
3 HVDC Protection
The interconnection of HVDC links has numerous potential benefits, including: a reduction
in the volume of assets, enhanced operational flexibility and improved network security
[1]. However, there is only one large scale (2000MW) commercial HVDC MT scheme
(LCC) currently in operation (Quebec) [41]. This is primarily because there are technical
difficulties with reversing power flow with LCCs, since DC current can only flow through
the converter in one direction. VSCs do not have this limitation and as such are more
suitable for MT systems. As the power rating of VSCs has risen, so has the interest in MT
HVDC systems [42, 43]. The UK National Grid has released cost estimates that show that
the connection of the UK windfarms using an integrated VSC-HVDC approach, as
opposed to a radial VSC-HVDC design, could result in a saving of around 25% [44].
A key challenge for the development of HVDC grids is the protection of the grid from DC
faults. At present, all commercial VSC-HVDC links are radial. In the event of a DC fault
the converters at each end of the link are blocked and the AC circuit breakers are tripped so
that the converter’s anti-parallel diodes do not conduct. Applying this approach to a HVDC
grid would require all VSCs connected to the grid to be blocked, and their respective AC
circuit breakers to be tripped, for a DC fault occurring anywhere on the grid. The faulty
section of the grid could then be isolated and the remaining healthy sections could be re-
energised.
The consequence of de-energising the entire grid due to single DC fault, however, becomes
increasingly severe as the power rating of the grid increases. As discussed in section 2.4,
the maximum in-feed loss permitted by NETS SQSS is 1.8GW [45]. This means that the
maximum amount of power a HVDC grid could in-feed to the UK grid would be limited to
1.8GW. Therefore in order for a relatively large MT HVDC grid to be technically and
commercially viable, the ability to isolate parts of the grid due to a fault, or to perform
maintenance without de-energising the entire grid, must be achieved.
A “HVDC circuit breaker” is a device which can be connected to a high potential
conductor and is able to interrupt and isolate a fault on a HVDC grid. A simple single line
diagram of a four-terminal HVDC system, with HVDC circuit breakers installed at both
ends of each HVDC cable, is shown in
Chapter 3 HVDC Protection
66
Figure 3.117
. In this scenario, a fault occurring along cable 1 will trip the HVDC circuit
breakers at each end of the cable, isolating the faulty section of the grid and enabling the
healthy sections of the grid to remain in service. In this case, providing that the grid is
designed so that the disconnection of cable 1 does not result in a power in-feed loss to the
AC grid of more than 1.8GW, then there is no limit on the grid’s power capacity from a
protection point of view. At the time of writing, HVDC circuit breakers are however not
yet commercially available.
Windfarm1
Windfarm2
Converter1Converter2
Converter3Converter4
= AC circuit breaker
= HVDC Breaker
Cable1
Cable3
Cable2Cable4AC Grid
Figure 3.1: Single line diagram for a four-terminal HVDC system
In this chapter the fundamental challenges associated with isolating faults in a HVDC grid,
as opposed to a HVAC grid, are highlighted. A review of potential HVDC circuit breaker
topologies at the time of investigation is given and a new HVDC circuit breaker topology
is presented. The new topology referred to as the “hybrid commutation circuit breaker” is
shown to be able to improve on some of the limitations of the existing designs and has led
to a UK patent application. Furthermore, selected HVDC circuit breaker topologies, which
have been published since the design of the hybrid commutation circuit breaker, are also
discussed, and the current state of HVDC circuit breaker development is summarised.
The production of a commercial HVDC circuit breaker will be a significant step forward
for the development of HVDC grids. However without a suitable protection strategy,
which is capable of tripping the correct HVDC circuit breakers within the necessary time
frame, the potential of HVDC grids will not be realised. A section of this chapter is
therefore dedicated to reviewing the challenges of developing a suitable protection
strategy.
17
It should be noted that in practice the converters are interconnected by two cables (positive and negative) and that each cable requires a circuit breaker at each end of the cable.
Chapter 3 HVDC Protection
67
3.1 Basic Circuit Breaker Theory
In order to appreciate the challenge of interrupting DC current, it is first necessary to
understand basic circuit breaker theory. For completeness this basic theory has therefore
been included and more detail can be found in [46-48].
A circuit breaker is characterised by its ability to make load currents and interrupt both
load and fault currents, unlike other forms of switchgear which are not designed to
interrupt fault current. In the closed position, circuit breakers provide a passage for load
current, whereas in the open position they provide electrical isolation. In the event of a
fault, the circuit breaker must be capable of interrupting current that is well in excess of the
load current.
3.1.1 The Electric Arc
The separation of the circuit breaker’s contacts when current is flowing will result in the
production of an electric arc. The electric arc is a self-sustained electrical discharge that is
capable of sustaining large currents, behaves like a non-linear resistor, and has a voltage
drop [47]. The reader should be aware that the actual behaviour of an electric arc is more
complex than is discussed in this document, but for the discussion presented this simplified
model is sufficient. Generally speaking, electric arcs can be categorised into high pressure
and low pressure arcs. High pressure arcs occur in switchgear at or above atmospheric
pressure, such as in air blast or SF6 circuit breakers. In contrast, low pressure arcs exist in
switchgear below atmospheric pressure, for example in a vacuum circuit breaker.
A high pressure arc is a highly visible bright column consisting of ionised gases that permit
the flow of electric current. The total arc voltage is made up of voltage drops across the
anode, cathode and main body of the arc. The anode and cathode voltage drops exist in
very small regions of the arc, near the electrodes, and are mainly dependent upon the
electrode material. The voltage drop across the main body of the arc is dependent upon a
number of factors, including: the arc length, type of gas, gas pressure and current
magnitude. The electric arc’s conductivity increases in a non-linear fashion with a rise in
current magnitude. The arc voltage, therefore, decreases in a non-linear fashion as the
current magnitude increases, all other things being equal.
The conductivity for the main body of the low pressure arc is dependent upon the
electrodes, since it is composed of metal vapours which have been boiled off the
Chapter 3 HVDC Protection
68
electrodes, not ionised gases [46, 47]. The arc voltage of a low pressure arc is, therefore,
significantly less than for a high pressure arc. The vacuum electric arc can exist in the form
of a diffuse or a constricted arc. For current values between a few hundred and a few
thousand amperes, the arc consists of a number of parallel arc channels between the two
electrodes, which is known as a diffuse arc [48]. When the current value increases beyond
a certain limit, which is dependent upon the electrode material and size, the arc channels
come closer together to form a single tight column. This is known as a constricted arc.
3.1.2 Arc Interruption
A useful way to describe the behaviour of an arc, and the requirements for arc interruption,
is by the black box model [46]. If we consider an arc of conductance, G, per unit length
and with a current, I, the input power per unit length, Pi, and the voltage gradient, Vg, can
be given by the equations (3.1) and (3.2).
g
IV
G (3.1)
2
i
IP
G (3.2)
The arc column has an amount of stored energy in the form of heat. The arc’s conductance
is a function of this energy, with conductance increasing with temperature. The amount of
stored energy, Ws, is therefore given by equation (3.3).
0
t
s i LossW W W dt (3.3)
This equation shows that the amount of stored energy in the arc is the integral of the input
energy, Wi, minus the losses, WLoss, due to convection, conduction and radiation. The arc’s
conductance varies with time which can be described by equations (3.4) and (3.5).
. s
s
dWdG dG
dt dW dt (3.4)
.( )i Loss
s
dG dGW W
dt dW (3.5)
Equation (3.5) shows that if the input energy is greater than the losses then the arc
conductance will increase. Ideally the arc’s conductance would be zero and therefore the
input energy needs to be less than the losses. At or near a current zero the input power to
Chapter 3 HVDC Protection
69
the arc will be at or very close to zero. This means that the arc must be cooling, and so the
conductance will decrease. This is, therefore, an appropriate point to try and regain
sufficient dielectric strength between the contacts to extinguish and prevent the arc from
re-igniting. If not enough energy can be removed from the arc at or near zero current then
the arc will re-ignite. An arc itself may force interruption if the arc voltage is equal to or
greater than the system voltage. However, this is not possible in a HVDC system as the
system voltage will be significantly greater than the arc voltage.
In an AC system the circuit current is forced through zero twice per cycle, presenting an
opportune moment for an AC circuit breaker to interrupt the current. However, this is not
the case in a DC system and therefore interrupting current in a HVDC system is more
arduous. Furthermore, the fault current in an AC system is limited by the system’s
reactance which is not the case in a DC system.
3.2 HVDC Circuit Breaker Topologies
3.2.1 Review of HVDC Circuit Breaker Topologies
At the time of investigation a review of candidate HVDC circuit breakers from academic
papers, published patents and commercially available documentation was conducted. In
this section selected topologies are presented; additional topologies are presented in
Appendix 3A.
3.2.1.1 Passive/Active Resonance DC Circuit Breaker
The resonance DC circuit breaker consists of an AC breaker, BRK, in parallel with two
branches; one containing a series inductor, L, and capacitor, C, the other a surge arrester,
SA, as shown in Figure 3.2 [49-51].
BRKLs
SA
I Ib
Ic
Is
CL
Figure 3.2: Passive resonance circuit breaker
Under normal operation the line current, I, flows through the AC breaker, BRK. The
breaker will open its contacts upon receiving a trip order, which will cause a voltage arc to
Chapter 3 HVDC Protection
70
be produced between its contacts. The line current will virtually remain the same and will
continue to flow through the breaker via the arc. As the arc length increases, the arc
voltage will increase and will begin to interact with the LC branch. The natural fluctuations
in arc voltage produce current oscillations in the LC circuit. These oscillations grow until
the current, Ic, is equal to or greater than the line current, I, producing a zero crossing in the
current flowing through the breaker, Ib.
At this point the breaker is able to extinguish the arc in the same way as it would for an AC
current. The line current then commutates through the LC branch and continues to charge-
up the capacitor. The capacitor voltage grows and opposes the circuit voltage, reducing the
line current until it ceases. The surge arrester will begin to conduct if the capacitor voltage
exceeds the surge arrester knee-point, limiting the voltage across the capacitor.
In 1984, field tests were carried out on a prototype circuit breaker of this type at the Pacific
HVDC Intertie. The breaker consisted of four devices, similar to the one shown in Figure
3.2, connected in series. The breaker successfully interrupted current up to 2kA at 400kV
[51]. Further development and tests of this type of breaker in 1988 showed an interrupting
capability of more than 4kA [52].
This topology is used in LCC HVDC schemes to interrupt and commutate current into
another path. An example of this is the Metallic Return Transfer Breaker (MRTB), which
is used to interrupt current flowing through the ground return path and to commutate it into
the metallic return. DC switches such as the MRTBs are connected at near earth potential
and as such have lower Transient Recovery Voltage (TRV) requirements than the system
voltage [53]. In addition, they are only required to interrupt and commutate the line
current, not to reduce the line current to zero, which reduces TRV requirements and the
energy which must be absorbed by the surge arrester [54].
The passive resonance circuit breaker can be modified to an active resonance breaker by
pre-charging the capacitor and connecting a mechanical switch in series with the LC
branch. Under normal operation the mechanical switch is in the open position. Once the
interrupter, BRK, is opened, the mechanical switch is closed at the appropriate time,
allowing the capacitor to discharge creating an oscillatory current. The remaining sequence
of events for current interruption is very similar to that of a passive resonance breaker. This
Chapter 3 HVDC Protection
71
method allows higher current interruption in comparison to the passive resonance circuit
breaker, with tests showing successful interruption for currents up to 5 kA [50].
The time between fault inception and interruption for a resonance circuit breaker topology
is typically 30-100ms, in which time the DC current in a VSC scheme could reach in
excess of 20p.u. [55]. The interruption time is too long and the fault current is too high,
hence this circuit breaker topology is currently unlikely to be suitable for the protection of
HVDC grids.
3.2.1.2 Conventional Hybrid Solution
A hybrid circuit breaker is one that incorporates a minimum of two types of switching
technology, such as a mechanical and a semi-conductor switch. Figure 3.3 shows the
circuit diagram of a conventional hybrid circuit breaker [56]. This DC circuit breaker
consists of a fast mechanical switch, S, connected in parallel with two branches. One
branch contains a string of anti-parallel semi-conductor devices with turn-off capability,
connected in series with an inductor, L, and the other branch consists of a surge arrester,
SA.
Under normal operation the line current, I, flows through the mechanical switch. The
mechanical switch opens its contacts upon receiving a trip command creating an arc
voltage. The semi-conductor switches are then fired, which causes the line current to
commutate through the semi-conductor switches. Once enough time has lapsed for the
mechanical breaker to regain its dielectric strength, the semi-conductor switches are
turned-off. Due to the stored energy in the system’s inductance, Ls, the voltage will
increase rapidly until the surge arrester begins to conduct and clamp the voltage. The surge
arrester knee-point voltage must be higher than the system voltage in order to de-magnetise
the system’s inductance. It is common that the maximum knee-point voltage is chosen to
be 50% higher than the system voltage [56].
SLs
SA
I Ib
Ic
Is
L
Figure 3.3: Conventional hybrid circuit breaker
Chapter 3 HVDC Protection
72
The speed of fault current interruption for this device is predominantly dependent upon the
speed of the fast mechanical switch. Fast mechanical switches for HVDC circuit breakers
are currently under development and hence very little information with regards to their
specification is available. However, based on available information it is expected that the
total opening time18
for the fast mechanical switch will be less than 2ms [57] and hence the
interruption speed of the conventional hybrid circuit breaker is significantly faster than the
resonance breakers. The fast mechanical switch must be rated appropriately to carry the
nominal load current and to block a specific maximum voltage, which is dependent on the
surge arrester’s rating. The semi-conductor switches must be able to interrupt the
maximum fault current and to block the specific maximum voltage. The surge arrester
must have an appropriate energy dissipation rating.
3.2.1.3 Hybrid Circuit Breaker with Forced Commutation Circuit
The plasma created by an electric arc affects the mechanical switch’s voltage withstand
slew rate. According to [56] the fast mechanical switch has a slew rate of 80V/μs, if there
is plasma between the two contacts, and 300V/μs, if no plasma has occurred. Therefore if
no electric arc occurs in the mechanical switch, it can regain its dielectric strength more
than three times faster resulting in a much shorter interruption time. This enables the
current to be interrupted faster, which reduces the maximum current magnitude. This can
be achieved by ensuring that no current is flowing through the mechanical switch when its
contacts are separated, which may be realised by using the circuit breaker topology in
Figure 3.4 [56].
During normal operation, the line current flows through the inductor, Lc, and the
mechanical switch, S. Upon detection of a fault, the commutation thyristors are fired and
the current commutates from the inductor to the pre-charged commutation capacitor, C1.
The current flowing through the mechanical switch will remain unchanged until the
capacitor voltage reverses polarity. This opposing voltage causes the line current to
commutate into the parallel branch, which consists of series-connected semi-conductor
devices with turn-off capability and an inductor, L. Once the current has transferred to path
Ic there is no current flowing through the mechanical switch and therefore the contacts can
18
The total opening time in this report is defined as the time it takes from the trip signal being received by the switch until its contacts are fully open.
Chapter 3 HVDC Protection
73
be separated without arcing. The remaining sequence of events is the same as explained for
a conventional hybrid circuit breaker.
The forced commutation circuit breaker is able to interrupt fault current quicker than a
conventional hybrid circuit breaker, resulting in a reduction in the maximum current
magnitude. This leads to a reduction in the current interrupting capability requirement of
the semi-conductor switches and the energy dissipation rating of the surge arrester. The
fault current capability requirement of other components in the system may also be
reduced. Generally speaking, lower rated components are less expensive. An additional
commutation capacitor with pre-charging circuit, an inductor and a number of thyristors,
are however required for this topology, in comparison to the conventional hybrid circuit
breaker. The economic viability of this topology will therefore be very much dependent
upon the system voltage.
SLs
SA
I I1
Ic
Is
L
Lc
C1
IC1
Ib
Figure 3.4: Hybrid breaker with forced commutation circuit
3.2.1.4 Solid-state Circuit Breaker
This DC circuit breaker consists of a string of anti-parallel semi-conductor devices which
have turn-off capability connected in parallel with a surge arrester [56]. This configuration
is shown in Figure 3.5.
SA
Ib
Is
Ls
Figure 3.5: Solid-state circuit breaker
Chapter 3 HVDC Protection
74
During normal operation the current flows through the semi-conductor devices. Upon
detection of a fault the semi-conductor devices are switched-off, resulting in a rapid
voltage increase until the surge arrester begins to conduct. The knee-point voltage for the
surge arrester is again set above the system voltage and therefore the surge arrester de-
magnetises the system’s inductance.
This topology requires no mechanical switch, and as such it is able to interrupt fault current
significantly faster than the other DC circuit breaker designs (≈0.2ms [58]). The semi-
conductor devices are therefore required to interrupt a much smaller fault current, and
hence lower rated devices may be used, or fewer devices connected in parallel. This design
may however require hundreds of series-connected semi-conductor devices to block the
TRV, resulting in very high on-state losses, which are about 30% of the losses of a VSC
station [57]. The breaker will also require a large cooling system. There is a pilot 10kV
solid-state circuit breaker in Hällsjön, Sweden [59].
3.2.2 Hybrid Commutation HVDC Breaker (New)
To improve on the key limitations of the existing HVDC circuit breaker topologies, a new
topology was developed as part of this PhD work, which has resulted in a UK patent
application [60]. The hybrid commutation HVDC circuit breaker contains three branches
connected in parallel and is shown in Figure 3.6. The first branch consists of a semi-
conductor switching device with turn-off capability, T, and a mechanical switch, S,
connected in series. The semi-conductor switch, T, has a surge arrester, SD, connected
across its terminals to ensure that the voltage rating of the device is not exceeded. The
second branch is made up of a semi-conductor switching device, Tc, connected in series
with a capacitor, C, whilst the third branch contains a surge arrester, SA.
S
Tc
T
SASD
Ls
C
I 1
3
2
Figure 3.6: Hybrid commutation HVDC circuit breaker
Chapter 3 HVDC Protection
75
During normal operation the line current, I, flows through the semi-conductor switch and
the mechanical switch. At the instance the fault current is detected, the semi-conductor
switch is turned-off and the commutation thyristor is turned-on. This switching action
causes the line current to rapidly commutate from branch one into branch two. The line
current is no longer flowing through the mechanical switch and, therefore, its contacts can
separate without creating an electric arc. The line current charges-up the capacitor until the
surge arrester’s knee-point voltage is reached, resulting in the line current commutating
into branch three. The surge arrester de-magnetises the system’s inductance and the line
current ceases.
3.2.2.1 Advantages
Vastly lower on-state losses in comparison to the solid-state circuit breaker
In contrast to the solid-state circuit breaker, the hybrid commutation circuit breaker
may only require one semi-conductor switch in the normal conduction path. This is
because the voltage across this branch is distributed between the semi-conductor switch
and the mechanical switch, where the voltage across the semi-conductor switches is
limited by the parallel surge arrester. This approach allows a single semi-conductor
switch connected in series with a low contact resistance mechanical switch to provide
the normal conduction path, resulting in significantly lower on-state losses than the
solid-state circuit breaker.
Shorter initial interruption speed in comparison to other known mechanical
HVDC circuit breaker topologies
The initial interruption speed refers to how quickly the fault current is diverted from
the primary conduction path. The majority of hybrid circuit breaker designs use the arc
voltage to commutate the fault current from the primary path into the secondary path.
The current commutation time is dependent upon how quickly the mechanical contacts
open, and the magnitude of the arc voltage, amongst other factors. From the instance
the mechanical switch receives the command to open, there will be a delay before its
contacts begin to separate, and the arc voltage is not likely to reach more than 1kV. The
hybrid circuit breaker with forced commutation (Section 3.2.1.3) uses a pre-charged
capacitor to perform the current commutation from the primary path. For this device,
Chapter 3 HVDC Protection
76
the pre-charged capacitor must fully discharge and then charge in the opposite direction
to provide the commutation voltage to force the fault current into the secondary path.
In contrast, the commutation voltage for the hybrid commutation circuit breaker
(Figure 3.6 - Section 3.2.2) is the voltage across the semi-conductor switch at the
instance it is turned-off. The voltage across the circuit will increase rapidly and is only
limited by the surge arrester, SD, which is likely to have a knee-point voltage in excess
of 4kV. Therefore the commutation voltage of the hybrid commutation circuit breaker
develops faster and has a greater magnitude than the other hybrid designs resulting in a
shorter commutation time.
Arc-less operation
Using a mechanical switch to provide the commutation voltage has a negative effect on
the interruption time. Since the hybrid commutation circuit breaker uses a semi-
conductor switch to perform the initial interruption, and to commutate the current into
the parallel branch, there is no current flowing through the mechanical switch when its
contacts are separated and, therefore, no electric arc. This increases the mechanical
switch’s blocking slew rate. Furthermore, the mechanical switch experiences no
electric arc stress, which is likely to improve the reliability and reduce the maintenance
requirement of this device.
At the time of developing the hybrid commutation circuit breaker, the only other
known hybrid HVDC circuit breaker which performed commutation without an arc
voltage was the hybrid breaker with a forced commutation circuit (Section 3.2.1.3).
The hybrid commutation circuit breaker does however, have several advantages in
comparison to the hybrid breaker with a forced commutation circuit:
1. Faster initial interruption speed, resulting in a lower fault current
2. Requires less components
3. The control strategy for the device is less complex
4. Successful operation is less sensitive to the circuit parameters
5. Less expensive due to lower fault current and less components
3.2.2.2 Initial Simulation
Initial simulations were used to demonstrate the hybrid commutation circuit breaker’s
principle of operation for fault current interruption, where the PSCAD schematic is shown
Chapter 3 HVDC Protection
77
in Figure 3.7. With reference to Figure 3.8, the simulation results can be described as
follows:
1. Nominal line current, IL, flows through the GTO thyristor and mechanical switch.
2. A short-circuit fault is applied at 0.1s and the line current rapidly begins to rise.
3. 0.6ms later the GTO thyristor is turned-off and the commutation thyristor is turned-
on, causing the line current to commutate from the mechanical switch into the
thyristor-capacitor branch, Ic. The mechanical switch (BRK) contacts are separated
without creating an electric arc.
4. Capacitor voltage increases until the surge arrester knee-point voltage is reached
and the surge arrester begins to conduct, Isurge.
5. Surge arrester de-magnetises the system inductance.
6. Line current ceases.
Figure 3.7: PSCAD schematic for the hybrid commutation HVDC circuit breaker
Figure 3.8: Example simulation results for the hybrid commutation HVDC circuit breaker
Chapter 3 HVDC Protection
78
These simulation results show that the hybrid commutation HVDC circuit breaker is viable
in principle.
3.2.3 Latest HVDC Circuit Breaker Designs
This section presents selected breaker topologies which were published after the hybrid
commutation HVDC circuit breaker was designed.
3.2.3.1 Proactive Hybrid Breaker
The proactive hybrid DC breaker is shown in Figure 3.9 and is currently being developed
by ABB [57]. The first branch comprises a disconnector (fast mechanical switch)
connected in series with an auxiliary DC breaker (semi-conductor switch) which is very
similar to the hybrid commutation HVDC circuit breaker shown in Figure 3.6. The second
branch contains the main DC breaker which is separated into several sections. Each section
contains a stack of IGBTs with anti-parallel diodes and a surge arrester connected in
parallel with the stack. The main DC breaker is rated for the full voltage and current
breaking capability. The auxiliary breaker contains a small number of series-connected
IGBTs as it is only required to block a few kV.
Figure 3.9: Proactive hybrid DC breaker
During normal operation, the fast disconnector, auxiliary DC circuit breaker and main DC
breaker are closed/on. The main DC breaker has a much higher resistance than the
auxiliary DC breaker, due to the vastly higher number of series-connected semi-conductor
switches. The load current therefore flows through the auxiliary breaker under normal
operation. The line current is commutated to the main breaker by switching-off the axillary
breaker, once the overcurrent threshold is reached. The fast disconnector can then open
without creating an electric arc. Once the disconnector is fully open, and therefore able to
block the recovery voltage, the main DC breaker can be switched-off. The breaker is said
to be able to limit the line current by operating the main breaker, so that the voltage across
the DC inductance is controlled to zero [57]. This allows the protection strategy further
Disconnector
Auxiliary DC Breaker
Main DC Breaker
Current
Limiting
Reactor
Residual
DC
Current
Breaker
Hybrid DC Breaker
Chapter 3 HVDC Protection
79
time to determine whether or not the breaker needs to be tripped. The main DC breaker is
switched-off once the breaker receives a trip signal or the breaker reaches its maximum
time limit for current limiting. The instance that the main DC breaker is switched-off, the
voltage across the breaker rapidly increases until it is clamped by the surge arresters. In the
event that the breaker is not required to interrupt the fault current (i.e. the fault is on a
different cable) the line current can be transferred back to the primary path by closing the
disconnector and turning-on the auxiliary switch.
The current limiting mode allows the protection strategy additional time to select the faulty
cable19
. Furthermore, if two such breakers are connected in series the back-up breaker
could also be instructed to commutate the line current into the main DC breaker, so that the
DC current can be interrupted very quickly (≈0.2ms) if the primary breaker fails [57].
ABB are currently building a prototype of this device for a 320kV system with a nominal
current of 2kA. The device is expected to achieve a current breaking capability of 9kA in
less than around 2ms from fault inception. Currently the main DC breaker has been shown
to be capable of breaking currents above 9kA at 120kV [57].
An international patent application for this breaker has been filed [61]. ABB have
subsequently filed two additional patent applications for HVDC circuit breakers which
have a similar primary conduction path to the hybrid commutation HVDC circuit breaker
(Section 3.2.2) [62, 63]. These patents were filed before the patent for the hybrid
commutation HVDC circuit breaker [60]. The patent claims for the hybrid commutation
HVDC circuit breaker, were likely to infringe on the claims made in these patents,
especially [62, 63] due to the use a surge arrester in the primary condition path. It is for
these reasons that an international patent for the hybrid commutation HVDC circuit
breaker was not pursued.
3.2.3.2 Hybrid DC circuit breaking device (Siemens)
The hybrid DC breaking device shown in Figure 3.10 is currently patent pending and was
submitted by Siemens [64]. This topology is very similar to the hybrid commutation
HVDC breaker shown in Figure 3.6. The main difference between the two topologies is
that the hybrid DC circuit breaking device does not contain a thyristor valve in the
secondary conduction path.
19
The protection strategy must still operate before the grid DC voltage falls below acceptable levels.
Chapter 3 HVDC Protection
80
Figure 3.10: Hybrid circuit breaking device
The principle of operation for the hybrid circuit breaking device is effectively the same as
the hybrid commutation HVDC breaker, which is described in Section 3.2.2. The key
difference is that the current flowing through the capacitor in this topology may oscillate,
whereas the inclusion of the thyristor valve in the hybrid commutation HVDC breaker
prevents the capacitor current from reversing direction. One embodiment of the hybrid
circuit breaking device described in the patent prevents the current in the capacitor from
oscillating by connecting a residual breaker in series with, Ls.
The international patent application for this device was filed after the UK patent
application for the hybrid commutation HVDC circuit breaker [60, 64].
3.3 Comparison of HVDC Circuit Breakers
The HVDC circuit breaker topologies presented in this chapter have been categorised into
5 types and each type has been rated in terms of their speed, on-state losses and complexity
as shown in Table 3.1. Each type of circuit breaker is rated out of 5 for each characteristic,
with 1 being the best.
Type of breaker Topologies Speed Losses Complexity
Resonance 3.2.1.1 5 1 2
Arc voltage hybrid 3.2.1.2 3 1 3
Arc-less hybrid without auxiliary breaker 3.2.1.3 2 1 4
Arc-less hybrid with auxiliary breaker 3.2.2, 3.2.3.1,
3.2.3.2 2 2 3
Solid-state 3.2.1.4 1 5 3
Table 3.1: Comparison of HVDC breaker types
The resonance breakers are generally not considered to be technically viable for the
protection of VSC-HVDC grids due to their slow interruption speed (>30ms). The solid-
state circuit breaker is significantly faster than the other HVDC circuit breakers (≈0.2ms).
S
SA
Ls
C
I
Chapter 3 HVDC Protection
81
However, the very high on-state losses, which are about 30% of the losses of a VSC station
[57], make this device unsuitable.
The arc-less hybrid breaker without auxiliary breaker, offers improved interruption speed
in comparison to the arc voltage hybrid breakers at the expense of increased complexity.
The arc-less hybrid breaker with auxiliary breaker, further improves on the interruption
speed of the arc-less hybrid breaker without auxiliary breaker, but at the cost of increased
losses. However these losses are insignificant in comparison with a VSC station. The arc-
less hybrid breakers with auxiliary breakers also give greater operational flexibility with
reduced cost and complexity. The interruption speed of the arc-less hybrid breakers with
auxiliary breaker is expected to be about 3ms [57, 58, 65]. ABB have built a prototype of
arc-less hybrid breakers with auxiliary breaker and Siemens has filed at least one patent for
this type of breaker. It is for these reasons that this type of HVDC circuit breaker is likely
to be the first generation of HVDC breakers to be installed in a VSC-HVDC grid. The use
of a fully rated solid-state circuit breaker in the secondary path of the proactive hybrid
breaker offers greater operational flexibility than the other two topologies, however it is
also likely to require a larger footprint and be more expensive. It is clear from Table 3.1
that all designs to date have disadvantages and that further research is required.
3.4 Protection Strategies
Protection strategies which can locate and isolate DC faults MTDC grids are discussed in
several sources [66-70]. Many of these strategies require the entire grid to be de-energised
in order to isolate the faulty section of cable, which is likely to be unacceptable for HVDC
grids with a capacity in excess of 1.8GW. Therefore only protection strategies which are
potentially capable of isolating the faulty section of grid without de-energising the entire
grid are discussed.
3.4.1 Protection System Requirements
Any protection system should have the following properties [58, 71]:
Sensitivity – detect every fault
Selectivity – only operate under fault conditions and only affect the faulty section
Speed – act before the fault could potentially cause damage to equipment or could
no longer be interrupted by the circuit breakers
Chapter 3 HVDC Protection
82
Reliability – be reliable and have a back-up system in the case of primary
protection system failure
Robustness – be able to act in a degraded mode as well as a normal mode and be
able to discriminate between faults and other operations such as set-point changes
Seamless – after the fault clearance the healthy part of the system should continue
to operate in a secure state
In a HVDC grid the DC cable protection system must be able to identify line-to-ground
faults and line-to-line faults. A line-to-ground fault can occur when one of the cables is
damaged and a line-to-line fault can occur when both cables are damaged simultaneously.
An example of this could be when both cables are buried in a single trench and are
damaged by a single anchor strike.
The primary protection system should be selective so that it only trips the HVDC circuit
breakers necessary to isolate the faulty section of the grid. This means that the circuit
breakers responsible for protecting a particular cable should not act for faults on a different
cable, and that faults in other protections zones, such as the converter, should not trigger
the protection relays in the DC cable protection zone.
Leading HVDC circuit breakers designs are expected to be able to interrupt a fault current
of approximately 10kA in around 3ms. Based on a nominal DC current of approximately
1.7kA and a fault current rate of rise of about 2kA/ms for the worst case fault condition,
the breakers current breaking limit would be reached in approximately 4ms from fault
inception. Limiting the fault current rate of rise to 2kA/ms would require significantly
larger cable/line reactors than installed on existing VSC-HVDC schemes [57]. This leaves
about 1ms for the protection system to detect and identify the faulty section of cable and to
then instruct the appropriate breakers to open, unless the HVDC breaking time or the fault
current rate of rise can be reduced further.
The protection system must have a back-up to give a high degree of reliability.
Furthermore, once the faulty section of the grid has been isolated, the control and
protection systems must interact appropriately to ensure that the healthy section of the grid
can operate in a secure manner.
Chapter 3 HVDC Protection
83
3.4.2 Detection and Selection
A simple diagram of a four-terminal HVDC grid is shown in Figure 3.11. The HVDC
circuit breakers at the end of each cable are responsible for clearing faults on their
respective cables. If a fault occurs on cable 1 the protection system is required to identify
that a fault has occurred on cable 1 and to instruct only the HVDC circuit breakers at each
end of this cable to trip. All other HVDC circuit breakers should remain closed.
Windfarm1
Windfarm2
Converter1Converter2
Converter3Converter4
= AC circuit breaker
= HVDC Breaker
Cable1
Cable3
Cable2Cable4AC Grid
Figure 3.11: Single line diagram for a four-terminal HVDC system
VSCs have large capacitor banks connected to the DC side of the converter, which
discharge in the event of a fault. Hence, DC cable faults are typically characterised by a
rapid increase in the DC fault current and a rapid decrease in the DC voltage20
.
Cable faults could therefore be detected by one or more of the following protection
methods:
Overcurrent: trip breaker if the DC current exceeds a set threshold for a set period
of time
Undervoltage: trip breaker if the DC voltage drops below a set limit for a set
period of time
di/dt: trip breaker if the rate of increase of current exceeds a set limit
dv/dt: trip breaker if the rate of decrease of DC voltage exceeds a set limit
The protection strategies described above are not individually particularly selective and it
is likely that employing these protection strategies would result in HVDC breakers on
nearby cables tripping. Distance protection relays, which measure the distance to the fault
20
The fault current due to line-to-line faults is more severe than line-to-ground faults, as the capacitor bank connected to the positive pole, and the capacitor bank connected to the negative pole discharge. The configuration (symmetrical monopole, bipole etc.) and the type of VSC (Two-level, MMC etc.) employed can affect the fault current and voltage characteristics.
Chapter 3 HVDC Protection
84
by dividing the voltage measurement by the current measurement, are widely used in AC
grids [71]. Distance protection is however, not considered appropriate for DC grids for a
number of reasons, including the cable’s low resistance, which results in large distance
errors due to small measurement errors.
There are other protection methods, such as differential cable protection and cable
directional protection, which offer cable selectivity [58]. Differential cable protection trips
the HVDC circuit breakers at each end of the cable if the difference between the current at
the sending and receiving ends of the cable is above a specified limit. Cable directional
protection trips the breakers if the current through each breaker is flowing in opposite
directions. However, these protection strategies require communication between breakers
at each end of the cable. Reliance upon communication between platforms is unlikely to be
acceptable, due to the inherent time delays and the possibility of the fibre optic cable
becoming damaged.
The following example, shown in Figure 3.12, demonstrates the effect of time delays, due
to travelling waves and communication delays, for the cable directional protection scheme.
Under normal operation, power flows from the sending end to the receiving end of the
cable. A fault is applied to the sending end of the cable and the current through breaker B1
begins to rise rapidly.
B1 B2
Sending Receiving
100km DC Cable
100km Fibre Optic Cable
Figure 3.12: Cable directional protection
The speed of an electromagnetic wave through XLPE is approximately 2x108 m/s, hence it
takes more than 0.5ms before the current flowing through the breaker at the receiving end
of the cable, B2, changes direction21
. The speed of light via a fibre optic cable is also
21
Based on an XLPE permittivity value of 2.3, the speed of an EM wave through the cable can be
approximately calculated as follows: - 8 63 10 / 2.3 197.814 10 /m s m s . Therefore the time it takes for
the current wave due to the fault to arrive at breaker B2, is 6100 197.814 10 505.525km s .
Chapter 3 HVDC Protection
85
roughly 2x108 m/s
22. It therefore takes a further 0.5ms for B2 to signal to B1 that the
current direction has changed. Hence it takes about 1ms from the instance the fault occurs
until the HVDC breaker, B1, is able to acknowledge that there is a fault. Note also that
longer cables compound this problem. The time delays and the reliability concerns make a
DC protection system requiring communications between offshore platforms an unlikely
solution.
The use of travelling wave detection or signal processing (Fourier or wavelet analysis) has
been identified as a potential tool to find the faulty cable in a DC grid [71]. In [73]
travelling waves were used to find a faulty line for a DC grid using overhead lines [71]. In
[66] a protection methodology was developed using wavelet analysis to analyse local
measurement signals to identify a faulty cable in a HVDC grid.
The wavelet transform is a mathematical tool, similar to the Fourier transform for signal
analysis [74]. Fourier analysis is not a particularly good technique for analysing non-
periodic signals such as transients, because when transforming the complete signal into the
frequency domain the time information is lost. This problem can be overcome to some
extent by using a technique called the Short-time Fourier Transform (STFT) which
analyses a small section of the signal at a time. However, the major drawback is that the
time window is the same for all frequencies. Wavelet analysis circumvents this problem
by using variable sized windows, which enables a long time window to be used for low
frequency information and a shorter time window to be used for high frequency
information. Each scale in Figure 3.13 (right) represents a band of frequencies.
Time
Fre
qu
en
cy
Time
Sca
le
Figure 3.13: STFT (left) and Wavelet (right) views of signal analysis
Each HVDC breaker could process the local voltage and current measurements, using
wavelet analysis to identify fault characteristics. The protection algorithm in [66, 75]
22
An optical fibre is a very thin wire of glass. The speed of light in glass is about two thirds of its value in free space [72]
Chapter 3 HVDC Protection
86
acknowledges that a fault has occurred if two of the following three detection modules
indicate that a fault has occurred:
1. M1: fault detection by using voltage wavelet coefficients
2. M2: fault detection by using current wavelet coefficients
3. M3: fault detection by using the voltage derivative and magnitude
The two out of three selection system is employed to improve the reliability of the signal
processing, by helping to prevent the protection system from tripping the HVDC breaker
when no fault has occurred. The thresholds used to determine if a fault has occurred or not
were set using simulations, with a particular focus on the worst case scenarios (fault at
sending end and fault at receiving end of cable). Faults on cables near to the DC bus where
other cables are connected, caused the thresholds in the non-faulty cable to be reached.
This selectivity problem was overcome by comparing the wavelet voltage coefficients of
all the breakers connected to the same DC bus and by tripping the breaker with the highest
coefficient. The protection methodology was shown to be able to determine which cable
was faulty within 1ms, without the use of communications.
The lack of experience using wavelet analysis in the protection of power systems may
make its use as the main protection method, a cause for concern. If this is the case then it is
more likely that a protection strategy based on a combination of more traditional protection
methods will be sought. The preferred choice could be a protection strategy which uses
voltage, current, dv/dt and di/dt measurements with wavelet analysis for optimum
detection and selection, but which is not solely reliant upon wavelet analysis.
In one of the worst scenarios for selecting the faulty cable was when a fault was applied on
a cable near to the DC bus. This issue was avoided by comparing wavelet voltage
coefficients. This selectivity problem could also be overcome without the use of wavelet
analysis by checking the magnitude and direction of the current flowing through each cable
connected to the DC bus. Only the current in the faulty cable will increase in the direction
from the DC bus towards the fault, as shown in Figure 3.14.
Chapter 3 HVDC Protection
87
VSCDC Bus
VSCDC Bus
Figure 3.14: DC current direction before (left) and after (right) cable fault6
The current direction selectivity could solve the issue of breakers connected to the same
DC bus (same platform) incorrectly tripping. This technique cannot however be used to
prevent breakers on nearby platforms from tripping. For example, in Figure 3.15 a fault is
applied to cable 2 very near to the VSC1 DC bus. If the protection thresholds are exceeded
in breakers B1 and B2, the DC cable protection system for VSC1 can identify that B3
needs to be tripped by checking the current magnitude and direction. However, if the
protection thresholds in breaker B5 are exceeded, the DC cable protection system for
VSC2 would check the current direction and as a result, would trip B5, incorrectly
assuming that there is a fault on cable C1. Hence, the thresholds in B5 must not be
exceeded for a fault on cable C2.
VSC 1DC Bus
VSC 2DC BusB1
B2
B3
B4
B5
B6
C1
C2
Figure 3.15: Fault on cable C2
3.4.3 Back-up Protection
The protection system must have a high degree of reliability. This means that if any
component in the protection system fails, the system must still operate. The failure of a
HVDC breaker is a key concern for the protection of a HVDC grid. This is a valid concern,
considering the fact that there are no HVDC breakers commercially available and therefore
there is no operational experience. At present, the best method is to ensure that the HVDC
circuit breakers are highly reliable in theory and that a back-up protection system is in
place in the event that a HVDC breaker fails. The reliability of HVDC breakers could be
improved by duplicating all critical components within technical and economic boundaries.
Chapter 3 HVDC Protection
88
The back-up protection system must not interfere with the primary protection system and it
must ensure that, based on present procedure, no more than 1.8GW is disconnected from
the UK AC grid. This section of the document outlines three possible back-up protection
strategies.
In Figure 3.16 (left) each DC cable is protected by two HVDC circuit breakers. In the
event that one breaker cannot clear the fault on its cable the other breakers connected to the
same DC bus could be tripped, isolating the DC bus from the rest of the HVDC grid. The
AC circuit breakers for the VSC connected to the corresponding DC bus would also need
to be tripped. The isolation switches installed at each end of the faulty cable (not shown in
Figure 3.16) could then be opened, allowing the VSC’s AC circuit breaker to be closed
energising the DC bus. The HVDC circuit breakers connected to the non-faulty cable could
then be closed. This method requires the DC bus to be completely isolated from the rest of
the DC grid for several hundred milliseconds [76]. This means that the loss of the DC bus
must not reduce the power injected into the AC grid by more than 1.8GW. Installing a
HVDC circuit breaker between the VSC and DC bus could reduce the amount of time that
the DC bus is disconnected to less than 100ms23
. Upgrading the standard half-bridge
converter to a full-bridge converter, capable of blocking fault current, could replace the
need to install a HVDC breaker between the VSC and the DC bus.
The above strategy requires that every HVDC breaker is capable of breaking fault current
in both directions. If each breaker is however, only required to break current in one
direction, the size and cost of the breaker could be reduced. Instead of operating the
breakers connected to the same DC bus as the faulty breaker, the breakers at the opposite
end of the cable could break the fault current as shown in Figure 3.16 (centre). The use of
uni-directional breakers could also lead to a more simplistic protection strategy.
23
The breaking time of a HVDC breaker is expected to be about 3ms and the opening time of a fast mechanical isolator is likely to be less than 40ms.
Chapter 3 HVDC Protection
89
VSC 2
VSC 3
VSC 1
VSC 2
VSC 3
VSC 1
VSC 2
VSC 1
AC breaker closed
HVDC breaker closed
AC breaker open
HVDC breaker open
VSC 3
C3
C4
Figure 3.16: Back-up protection strategies : Cable bi-directional breakers (left) Cable uni-directional
breakers (centre) Ring bus (right)
In both of the aforementioned protection strategies, the failure of any HVDC breaker leads
to the entire DC bus being temporarily disconnected from the rest of the HVDC grid. A
fault on the DC bus, or the connection between the VSC and the DC bus, also requires the
entire DC bus to be permanently disconnected until the fault is removed, or until the faulty
section can be isolated and bypassed using disconnectors. If this bus is used as a transit bus
(transfer energy from VSC1 to VSC3) problems may ensue. These issues can be solved to
an extent by using a ring bus as shown in Figure 3.16 (right). The failure of any HVDC
breaker in the ring bus leads to two connections (C3 and C4), as opposed to four
connections, being disconnected from the HVDC grid. Hence, disconnecting any two
adjacent connections must not exceed the maximum in-feed loss of 1.8GW to the AC grid.
The ring bus, however, requires four bi-directional HVDC breakers, and the primary
protection strategy must select and trip four breakers for a single cable fault. This indicates
that the ring bus would be more expensive than the other two strategies and that the
primary protection system would be less reliable.
There are other DC substation configurations that would be possible; each with advantages
and disadvantages. It may be the case that installing uni-directional breakers is the best
solution for a terminal with two DC cables and that the ring bus is better suited for three
cables. It is therefore important that different configurations can be used within the same
HVDC grid and that the different protection strategies are compatible.
3.4.4 Seamless and Robust Protection System
Upon fault clearance, current flowing through the healthy converters and cables must be
redistributed carefully to ensure that components are not overstressed and to prevent other
breakers from needlessly tripping. This requires control and protection interaction studies
Chapter 3 HVDC Protection
90
to be carried out for the worst case scenarios. The protection system must be able to protect
the grid for all foreseeable grid configurations, not just the nominal configuration. For
example, if a VSC is disconnected from the grid, due to a fault or for maintenance
purposes, the breaker protection settings must still be valid to provide adequate protection
for the grid. It is unlikely that it would be permissible to update breaker protection settings
for different grid configurations, as this would require communications.
3.5 Conclusion
In this chapter, the requirement for a HVDC circuit breaker has been identified and
selected breaker topologies have been described and compared. The comparative analysis
concludes that arc-less hybrid circuit breakers with an auxiliary circuit breaker are the most
suitable type of HVDC circuit breaker for the protection of a HVDC grid. This is
predominantly due to their ability to achieve the best balance between operation speed and
on-state losses. The chapter also outlined the key requirements of a DC cable protection
system for a HVDC grid and reviewed potential protection strategies to identify and locate
a faulty cable. It is likely that a protection strategy will be developed based on a
combination of traditional techniques (dv/dt, overcurrent etc.) used in conjunction with
modern techniques (wavelet analysis) for optimum detection and selection.
Chapter 4 MMC-HVDC
91
4 MMC-HVDC
A simplified diagram for the offshore connection design of a Round 3 windfarm
employing a 1GW VSC-HVDC point-to-point scheme is shown in Figure 2.1. In order to
assess the steady-state and transient performance of the VSC-HVDC links, high fidelity
EMT models are required. The aim of this chapter is to describe the development of a high
fidelity EMT model of a MMC-HVDC link employed for the connection of a typical
Round 3 windfarm.
At the time this modelling work was undertaken, VSC-HVDC transmission system models
were mainly based on two-level VSCs with PWM control [77-79]. There were a small
number of publications which had modelled VSC-HVDC transmission systems with
MMCs [10, 80, 81], however these publications were limited in scope and lacked key
information required to produce a detailed MMC-HVDC transmission system model. The
work in this thesis provides a more detailed and complete description of EMT modelling
for MMC-HVDC systems.
Figure 4.1 shows a diagram of the MMC VSC-HVDC link for a Round 3 windfarm. In this
chapter the structure, operation, controllers and parameters for each component are
discussed in detail. The control functions that are required for a MMC-HVDC
interconnector are also described.
Figure 4.1: MMC VSC-HVDC link for Round 3 windfarm
4.1 MMC Structure and Operation
The basic structure of a three-phase MMC is shown in Figure 4.2. Each leg of the
converter consists of two converter arms which contain a number of Sub-modules (SMs),
and a reactor, Larm, connected in series. Each SM contains a two-level half-bridge
converter with two IGBTs and a parallel capacitor. The module is also equipped with a
bypass switch to remove the module from the circuit in the event that an IGBT fails, and a
XT=15%
Yg/D
MMC2-Offshore
Vs2(abc)
220kV 370kV
D/Yg
MMC1-Onshore
Is1(abc)
PCC1XT=15%
370kV 410kV
Vs1(abc)
Idc2
Is2(abc)
AC voltage magnitude and
frequency control
1000MW
Windfarm
Active and reactive power
control
DC link voltage control and
AC voltage magnitude control
Rbrak
Vdc2=600kV
165km DC cablePCC2
Larm=45mH CSM=1150μF
Vn
SCR=3.5
Zn
400kV
Idc1
Chapter 4 MMC-HVDC
92
thyristor, to protect the lower diode from overcurrent in the case of a DC side fault. The
conduction states of a SM are displayed in Figure 4.3.
Figure 4.2: Three-phase MMC
The converter is placed into energisation mode when it is first powered-up. In order to
energise the SM capacitor the upper and lower IGBTs are switched-off. If the arm current
is positive then the capacitor charges and if the arm current is negative then the capacitor is
bypassed. This energisation state does not occur under normal operation.
Figure 4.3: SM conduction states
The SM terminal voltage, VSM, is effectively equal to the SM capacitor voltage, Vcap, when
the upper IGBT is switched-on and the lower IGBT is switched-off. The capacitor will
charge or discharge depending upon the arm current direction. With the upper IGBT
switched-off and the lower IGBT switched-on, the SM capacitor is bypassed and hence
Single
IGBT
Sub-module
+Vdc/2
Va
Vua Vla
Vcap
Iarm
VSM
ArmSM2
SMn
SM1
SM2
SMn
SM1
SM2
SMn
Larm
IuaSM1
Rarm
Idc
SM1
SM2
SMn
SM1
SM2
SMn
SM1
SM2
SMn
-Vdc/2Ila
Vb
Vc
Idc
Iarm
VSM
VCap
Iarm
VSM
Iarm
VSM
Iarm
VSM
Iarm
VSM
Iarm
VSM
Iarm>0
Iarm<0
Energisation mode - Upper IGBT
off and Lower IGBT offSM on - Upper IGBT on and Lower
IGBT off
SM off - Upper IGBT off and Lower
IGBT on
VCap
VCap
VCap
VCap
VCap
Chapter 4 MMC-HVDC
93
VSM is effectively at zero volts. Each arm in the converter therefore acts like a controllable
voltage source, with the smallest voltage change being equal to the SM capacitor voltage.
With reference to the equivalent circuit for phase A, as shown in Figure 4.4, the following
equation for the phase A converter voltage can be derived:
2
dc uaa ua arm arm ua
V dIV V L R I
dt (4.1)
2
dc laa la arm arm la
V dIV V L R I
dt (4.2)
The upper and lower converter arm currents, Iua and Ila, consist of three main components
as given by equations (4.3) and (4.4) [82]. The current component which is common to
both arms (3
dc
circ
II ) is commonly referred to as the difference current, Idiff.
3 2
dc aua circ
I II I (4.3)
3 2
dc ala circ
I II I (4.4)
Figure 4.4: Equivalent circuit for phase A
The circulating current, Icirc, is due to the unequal DC voltages generated by the three
converter legs. Substituting equations (4.3) and (4.4) into equations (4.1) and (4.2), and
then summing the resultant equations, gives equation (4.5).
2 2 2
la ua arm a arma a
V V L dI RV I
dt
(4.5)
Equation (4.5) shows that the converter phase voltages are effectively controlled by
varying the upper and lower arm voltages, Vua and Vla. Equation (4.5) may be re-written as
Vdc/2
Vua
Larm Rarm Larm Rarm
Vla
Vdc/2
Va ZL
0V
IlaIua
Ia
Chapter 4 MMC-HVDC
94
equation (4.6), where Vca is the internal converter voltage for phase A given by equation
(4.7) and p d dt [83].
2 2
arm arma ca a a
L RV V pI I (4.6)
2
la uaca
V VV
(4.7)
Each converter arm contains a number of SMs, n. The SM capacitor voltage, Vcap, can be
described by equation (4.8), assuming that the SM capacitance is sufficiently large enough
to neglect ripple voltage and that the capacitor voltages are well balanced.
dccap
VV
n (4.8)
The voltage produced by a converter arm is equal to the number of SMs in the arm which
are turned-on, nonua and nonla, multiplied by the SM capacitor voltage as given by equation
(4.9) and equation (4.10).
ua onua capV n V (4.9)
la onla capV n V (4.10)
Through appropriate control of the SMs the output voltage magnitude and phase can be
controlled independently. The number of voltage levels that a MMC can produce at its
output is equal to the number of SMs in a single arm plus one.
4.2 MMC Parameters
This section determines the value of the key parameters for the MMC through detailed
analysis. A typical radial link for the connection of a Round 3 offshore windfarm has a
power rating of 1GW at ± 300kV according to National Grid’s Offshore Development
Information Statement (ODIS) [1, 14]. Therefore the modelled MMC is rated for 1GW at ±
300kV.
4.2.1 Number of MMC Levels
A suitable starting point for designing/modelling an MMC is to determine the appropriate
number of converter levels required. The MMC used on the Trans Bay Cable project is a
201 level converter, and therefore each converter arm contains approximately 200 SMs.
Chapter 4 MMC-HVDC
95
This large number of SMs ensures that the synthesised output voltage is very close to an
ideal sinusoid and therefore removes the need for filters. The primary reason that such a
large number of SMs per converter arm is required is to reduce the voltage stress across
each SM to around 2kV24
, it is entirely possible to use significantly less than 200 SMs per
converter arm and still not require AC filters.
Each SM contains two IGBTs with anti-parallel diodes and a capacitor. In order to model a
single MMC from the Trans Bay Cable project, it would require more than 2400 IGBTs
with anti-parallel diodes to be modelled, which would be extremely computationally
intensive. Therefore it would be advantageous to be able to represent the MMC with the
fewest number of SMs possible. The purpose of this section of the document is to assess
the minimum number of voltage levels that a MMC is likely to require to ensure that the
AC harmonic content is within acceptable limits so that no AC filters are required.
There are several harmonic limit standards in existence. These standards are defined by
national and international bodies, as well as transmission and distribution network
operators. There is no set of common standards. The standards tend to be specific to a
particular network and for a particular system voltage level. Harmonic limits may be
defined for voltage waveform distortion, injected current, telephone-weighted voltage
distortion and telephone-weighted current. Voltage waveform distortion limits are defined
for the very high majority of networks, whereas the injected current limits are less widely
used. Telephone-weighted limits are normally only considered when there is long exposure
of telephone circuits to power circuits. The IEC 61000-3-6 and the IEEE 519 harmonic
voltage limits are given in Table 4.1 and Table 4.2, respectively, from [30]. The IEC
standard does not provide limitations for current injection or telephone-weighted values
whereas the IEEE standard does.
A custom built voltage step generator was used to produce a very similar waveform to that
of an MMC for a given number of voltage levels. This allowed the harmonic content of the
waveform to be analysed without modelling the actual converter. The output waveform
from the voltage output generator can be analysed, by the fast Fourier transform block in
24
The DC voltage for the Trans Bay Cable project is ±200kV; hence the voltage across each SM is roughly 2kV.
Chapter 4 MMC-HVDC
96
PSCAD, to determine the magnitude of the individual voltage harmonics as well as the
Total Harmonic Distortion (THD) value.
Odd harmonics non-multiple of 3
Odd harmonics multiple of 3 Even harmonics
Harmonic order
Harmonic voltage (%)
Harmonic order Harmonic
voltage (%) Harmonic
order Harmonic
voltage (%)
5 2 3 2 2 1.4
7 2 9 1 4 0.8
11 1.5 15 0.3 6 0.4
13 1.5 21 0.2 8 0.4
17-49 - 21-45 0.2 10-50 -
Table 4.1: IEC 61000-3-6 harmonic voltage limits for high voltage systems
Bus voltage Individual voltage distortion Total voltage distortion (THD) (%)
161kV+ 1 1.5
Table 4.2: IEEE519 harmonic voltage limits
For a 31-level MMC, the THD and the maximum individual harmonic distortion were
found to be 1.42% and 0.49% respectively. The simulated waveform complies with the
IEEE519 voltage limits; however it does not comply with the IEC standards for individual
harmonic distortion. For example, the harmonic distortion for the 33rd
harmonic is 0.43%
which exceeds the 0.2% limit. The harmonic content at the Point of Common Coupling
(PCC) in a real system is dependent upon many factors which are not taken into
consideration in this analysis. Satisfying the IEEE519 harmonic voltage limits is
considered sufficient for estimating the number of levels that the converter is likely to
require.
4.2.2 SM Capacitance
The choice of the SM capacitance value is the next important parameter, and it is a trade-
off between the SM capacitor ripple voltage and the size of the capacitor. A capacitance
value which gives a SM voltage ripple in the range of ±5% is considered to be a good
compromise [84].
An analytical approach proposed by Marquardt et al. in [85] can be used to calculate the
approximate SM capacitance required to give an acceptable ripple voltage for a given
converter rating. This method effectively calculates the value of SM capacitance required
for a given ripple voltage by determining the variation in the converter arm energy. This
approach assumes that the output voltage and current is sinusoidal, that the DC voltage is
Chapter 4 MMC-HVDC
97
smooth and split equally between the SMs, and that the converter is symmetrical.
Circulating currents, which will be explained in Section 4.2.3, are also assumed to be zero.
Only the resultant formula is presented here (4.11). The full derivation is given in
Appendix 4A.
22
SMSM
cap
WC
V
(4.11)
where:
SMW is the variation of stored energy per SM
is the SM capacitance ripple voltage factor 0 1
The SM capacitance value for a ripple voltage of 10% (±5%) was calculated to be 1150µF.
The working for this calculation is given in Appendix 4A. This approach, which was
proposed by Marquardt et al., is widely used [86, 87], it should however only be used as an
approximation, as it is based on the assumptions noted in the introduction of this section.
According to [84] 30-40kJ of stored energy per MVA of converter rating is sufficient to
give a ripple voltage of 10% (±5%). Using this approximation, the value of SM
capacitance was calculated and compared with the value given by equation (4.11). It was
found that a value of 40kJ of stored energy per MVA of converter rating gives a similar
value of capacitance (1110µF) to the method proposed by Marquardt et al. A SM
capacitance value of 1150µF is employed for the MMC.
4.2.3 Limb Reactance
The limb reactors, also known as converter reactors and arm reactors, which are labelled
Larm in Figure 4.2, have two functions. The first function is to suppress the circulating
currents between the legs of the converter, which exist because the DC voltages generated
by each converter leg are not exactly equal. The second function is to reduce the effects of
faults both internal and external to the converter. By appropriately dimensioning the limb
reactors, the circulating currents can be reduced to low levels and the fault current rate of
rise through the converter can be limited to an acceptable value.
The circulating current is a negative sequence (a-c-b) current at double the fundamental
frequency, which distorts the arm currents and increases converter losses [88]. The value
Chapter 4 MMC-HVDC
98
of arm reactance required to limit the peak circulating current, ˆcircI , can be calculated using
equation (4.12) [89]. The analysis of circulating currents and the derivation of equation
(4.12) is given in Appendix 4B.
2
1
ˆ8 3arm dc
SM cap circ
SL V
C V I
(4.12)
The second function of the arm reactor is to limit the fault current rate of rise to within
acceptable levels. According to [90], the Siemens HVDC Plus MMC convertor reactors
limit the fault current to tens of amps per microsecond even for the most critical fault
conditions, such as a short-circuit between the DC terminals of the converter. This allows
the IGBTs in the MMC to be turned-off at non critical current levels. Assuming that the
DC voltage remains relatively constant from fault inception until the IGBTs in the
converter are switched-off, the value of arm reactance required to limit the initial fault
current rate of rise ( )fdI dt can be described by equation (4.13)
2( )
dcarm
f
VL
dI dt (4.13)
The minimum value of limb reactance permissible is calculated assuming the worst case
scenario of 20A/µs for a line-to-line fault. According to equation (4.13), the arm reactor
should be no smaller than 15mH. A 15mH limb reactor results in very large circulating
currents, which increase converter losses and distort the arm currents. Ideally the
circulating current should be zero, however, according to equation (4.12), very large limb
reactors, and/or SM capacitors, would be required for this to be achieved. The size of the
limb reactor is therefore selected as a compromise between voltage drop across the limb
reactor and the cost of the limb reactor, against the magnitude of circulating current. The
circulating current can also be suppressed by converter control action or through filter
circuits. The model developed in this work includes a Circulating Current Suppressing
Controller (CCSC). A 45mH (0.1p.u.) limb reactor used in conjunction with the CCSC was
found to offer a good level of performance.
4.2.4 Arm Resistance
The SM IGBT’s and diode’s on-state resistances, Ron, are set to the default PSCAD value
of 0.01Ω. Only one IGBT or diode in each SM is conducting at any one time, therefore the
resistance in each arm due to the SMs is 0.3Ω. A 0.6Ω resistor is further connected in
Chapter 4 MMC-HVDC
99
series with the SMs in each arm, hence, the converter arm resistance, Rarm, is 0.9Ω. This
model does not attempt to include converter losses, however, an arm resistance of 0.9Ω
represents approximately 0.5% conduction losses for a MMC rated at 1GW25
. The losses
of an MMC converter is approximately 1% [28], which takes into account a number of
factors including conduction losses, switching losses and off-state losses.
4.3 Onshore AC Network
The strength of an AC system is often characterised by its Short-circuit Ratio (SCR),
which is defined by equation (4.14), where Vn is the network voltage, Zn is the network
impedance and Pdrated is the power rating of the HVDC system.
2
n n
drated
V ZSCR
P (4.14)
An AC system with a SCR greater than three is defined as strong [30]. The SCR of the AC
system in this model is selected to be relatively strong with an SCR of 3.5. The AC
network impedance is highly inductive and consequently the AC system impedance is
modelled using an X/R value of 20. The SCR is implemented in PSCAD using an ideal
voltage source connected in series with a resistor and an inductor. The values of resistance
and inductance are 2.28Ω and 0.145H (0.34p.u.) respectively. The calculation of these
values is given in Appendix 4C.
The winding configuration of the converter transformer in the model is delta/star, with the
delta winding on the converter side of the transformer as is the case for the Trans Bay
Cable project [91]. A tap-changer is employed on the star winding of the transformer to
assist with voltage regulation. The transformer leakage reactance is set to 0.15p.u. with
copper losses of 0.005p.u., which are typical values for a power transformer [92]. The
nominal transformer parameters are given in Table 4.3, and a simplified diagram of the
onshore system is shown in Figure 4.5.
Transformer parameters
S (MVA) VTp (kV) VTs (kV) LT (H) RT (Ω)
1000 370 410 0.065 0.68
Table 4.3: Nominal transformer parameters
25
The arm current is approximately 1kArms when operating at 1GW.
Chapter 4 MMC-HVDC
100
Figure 4.5: Onshore AC system
4.4 DC system
4.4.1 Cable
The MMCs are connected by two 165km HVDC cables with a nominal voltage and current
rating of 300kV and 1.7kA respectively, as per ODIS [1, 14]. Accurate models of the
cables are required in order for the DC link dynamics of the scheme to be represented. The
cables are modelled using the Frequency Dependent Phase Model (FDPM) in PSCAD.
Chapter 7 of this thesis is dedicated to HVDC cable modelling. The reader is therefore
referred to this chapter for further information.
4.4.2 DC Braking Resistor
DC braking resistors are normally required on VSC-HVDC schemes used for the
connection of windfarms [93]. There are situations, such as an onshore AC grid fault,
which diminish the onshore converter’s ability to export the energy from the windfarm.
The bulk of this excess energy is stored in the scheme’s SM capacitors leading to a rise in
the DC link voltage. The DC braking resistor’s function is to dissipate this excessive
energy and to therefore prevent unacceptable DC link voltages.
Figure 4.6: DC braking resistor
The worst case scenario is where the onshore MMC is unable to effectively export any
active power. This can occur for severe AC faults such as a solid three-phase to ground
fault at the PCC as shown in Figure 4.6. The braking resistor should therefore be rated to
dissipate power equal to the windfarm power rating, Pwrated. The braking resistor, Rbrak, is
D/Yg
Vn
SCR=3.5
MMC
Iabc
PCCXT=15%
370kV 410kV
Vs
Zn
Ceq
Idc
RbrakD/Yg
Vn
MMC
Iabc
PCC
Zn
Vdc
Chapter 4 MMC-HVDC
101
turned-on once the DC voltage exceeds a set limit (1.1p.u.) and is then turned-off once the
DC voltage has returned to its nominal value (1.0p.u.), Vdcnom [93]. These voltage
thresholds prevent the braking resistor from interfering under normal operating conditions.
In this work, the DC braking resistor is designed to prevent the DC link voltage from
exceeding 1.2p.u. and is calculated using equation (4.15).
2 21.2 720500
1000
dcnom
brak
wrated
V kVR
P MW (4.15)
The IGBT braking valve would therefore be required to conduct up to 1500A.
4.5 Offshore AC Network
A 1GW offshore windfarm would typically contain 200 wind turbines based on a 5MW
turbine design. A simplified diagram of a full scale converter wind turbine is shown in
Figure 4.7. The DC link voltage varies due to the generated power. The function of the grid
side converter is to maintain the DC link voltage and to supply/absorb reactive power if
required. The power generated by the wind turbines is transmitted at 33kV to two 500MW
AC substations which step-up the voltage to 220kV for transmission to the HVDC link.
Figure 4.7: Simplified diagram of a full scale converter wind turbine
The focus of this work is the HVDC scheme, and therefore a simplified representation of
the offshore AC system is employed as shown in Figure 4.8. The voltage sources, Vw,
which represent the windfarm generators, are controlled using a dq controller to inject
active power into the offshore HVDC converter. Further information on this control system
is contained in Section 4.6.
G
33kV
Chapter 4 MMC-HVDC
102
Figure 4.8: Representation of the offshore network
4.6 Control Systems
This section describes the numerous control functions which are required for a MMC-
HVDC point-to-point link. The required control system functions are dependent upon
whether the MMC is connected to an active AC network or a passive/weak AC network.
The internal MMC control system functions are, however, independent of the connected
AC network.
4.6.1 Control Systems for an MMC Connected to an Active Network
For a VSC-HVDC scheme which connects two active networks, one converter controls
active power or frequency and the other converter controls the DC link voltage. The
converters at each end of the link are capable of controlling reactive power or the AC
voltage at the PCC. For VSC-HVDC links which are employed for the connection of
offshore windfarms, the converter connected to the onshore AC grid controls the DC link
voltage and the reactive power or AC voltage. This section describes the control structure,
tuning process and implementation of the aforementioned control functions.
Active power, frequency and DC link voltage are effectively controlled by varying the
angle of the MMC output voltage with respect to the voltage angle of the connected AC
network. The reactive power and AC voltage are effectively controlled by varying the
magnitude of the MMC output voltage with respect to that of the AC network. The MMC
output voltage magnitude and angle can be controlled either directly using direct control,
or indirectly using dq current control. Dq control is employed for the MMC in this work
because it can limit the valve currents under balanced operating conditions and provide a
faster response than direct control. Figure 4.9 shows the basic control structure for an
MMC connected to an active network.
XT=15%
Yg/D
Vw
MMC
Yg/Y
XT=15%
Vso
PCC220kV33kV 220kV 370kV
Chapter 4 MMC-HVDC
103
Figure 4.9: MMC control system basic overview
The current controller is a fast feedback controller, which produces a voltage reference for
the MMC based upon the current set-point from the outer feedback controller. The inner
MMC control system, amongst other functions, translates the voltage set-points using a
Nearest Level Controller (NLC) into Firing Signals (FS) to the MMC to obtain the desired
output voltage magnitude and phase.
4.6.2 dq Current Controller
The impedance between the internal converter voltage, Vca, and the AC system voltage,
Vsa, for phase A is shown in Figure 4.10. The phase shift and change in voltage magnitude
introduced by the converter transformer, is accounted for in the implementation of the
controller as shown in Figure 4.22, and it is therefore not discussed in this analysis.
Figure 4.10: MMC phase A connection to AC system
Equation (4.16) describes the relationship between the internal converter voltage and the
AC system voltage for phase A.
2 2
arm a armca sa T T a
L dI RV V L R I
dt
(4.16)
Equation (4.16) can be reduced to (4.17).
acsa a
dIV L RI
dt (4.17)
where:
2 2
arm armcsa ca sa T T
L RV V V L L R R (4.18)
For the three-phases:
Outer
controller
dq current
controller
P*/V*dc/freq*I*dq V*dq
Q*/V*ac
Inner MMC
control
FSMMC
V
Vn
LT RT Zn
Va Vsa
Larm/2 Rarm/2
Vca
Ia
Chapter 4 MMC-HVDC
104
csc
csa a
csb b
c
V I
V R pL I
V I
(4.19)
In the dq synchronous reference frame equation (4.19) becomes equation (4.20). The
derivation from equation (4.19) to equation (4.20) is given in Appendix 4D.
0 1
1 0
d d d d
q q q q
V I I IR Lp L
V I I I
(4.20)
Where 0 1
1 0
is the matrix representation of the imaginary unit j.
Expanding equation (4.20) and noting that d cd sdV V V and q cq sqV V V , equations (4.21)
and (4.22) are produced.
cd sd d d qV V RI LpI LI (4.21)
cq sq q q dV V RI LpI LI (4.22)
The equivalent circuit diagrams for the plant in the dq reference frame are given in Figure
4.11.
Figure 4.11: Equivalent dq circuit diagrams
Applying the Laplace transform with zero initial conditions to equations (4.21) and (4.22)
gives equations (4.23) and (4.24).
( ) ( ) ( ) ( ) ( )cd sd d d qV s V s RI s LsI s LI s (4.23)
( ) ( ) ( ) ( ) ( )cq sq q q dV s V s RI s LsI s LI s (4.24)
The plant equations in the Laplace domain can be represented by state-block diagrams,
with the (s) notation neglected, as shown in Figure 4.12.
- +
Vcd
Id L R
Vsd
ωLIq
+ -
Vcq
Iq L R
Vsq
ω LId
Chapter 4 MMC-HVDC
105
Figure 4.12: State-block diagram for system plant in dq reference frame
The state-block diagram in Figure 4.12 clearly shows that there is cross-coupling between
the d and q components. The effect of the cross-coupling can be reduced by introducing
feedback nulling, which effectively decouples the d and q components as shown in Figure
4.13.
Figure 4.13: State-block diagram with feedback nulling
The d and q currents are controlled using a feedback PI controller as shown in Figure 4.14.
The d and q components of the system voltage (Vsd and Vsq) act as a disturbance to the
controller. The effect of this disturbance is mitigated through the use of feed-forward
nulling, highlighted in Figure 4.13. The MMC is represented as a unity gain block (i.e.
Vcd*=Vcd), which is representative of its operation providing that the converter has a high
level of accuracy with a significantly higher bandwidth than the current controller. The d-
axis current control loop in Figure 4.14 can be simplified to Figure 4.15, due to the
cancellation of the disturbance term. This is equally applicable to the q-axis.
Figure 4.14: Decoupled d and q current control loops
-
1
L
1
s
R
Vsd
Vcd+
- Id-
1
L
1
s
R
Vsq
Vcq+
- Iq
ωL
ωL
+ -
-
1
L
1
s
R
Vsd
Vcd+
- Id-
1
L
1
s
R
Vsq
Vcq+
- Iq
ωL
ωL
+ -
ωL
+
ωL
-
-
1
L
1
s
R
Vsd
Vcd
+- IdMMC
=1
Vcd*
Vsd
+PI+ +
-
*dIdI
-
1
L
1
s
R
Vsq
Vcq
+- IqMMC
=1
Vcq*
Vsq
+PI+ +
-
*qIqI
Chapter 4 MMC-HVDC
106
Figure 4.15: d-axis current loop without d-axis system voltage disturbance
Using Mason’s rule the plant representation is simplified to a single block as shown in
Figure 4.16.
Figure 4.16: Simplified d-axis current control loop
The transfer function for the control loop can be calculated as follows [94]:
1 1
1 1*1 1
i p
d
di p
K K sI s Ls R
IK K s
s Ls R
(4.25)
*
1
i p
d
i pd
K K s
s Ls RI
K K sI
s Ls R
(4.26)
2*
i p
d
pd i
K K s
I LR KI K
s sL L
(4.27)
Approximating the current loop transfer function to a classic 2nd
order transfer function
allows the PI controller to be tuned to give an approximate damping ratio , , and natural
frequency, n .The current loop transfer function, equation (4.27), can be reduced to a
classic 2nd
order transfer function, equation (4.28), by neglecting the fast transient
information, as given in equation (4.29).
2
2 22
n
n ns s
(4.28)
-
1
L
1
s
R
Vcd
+IdMMC
=1
Vcd*PI+
-
*dIdI
Vcd IdMMC
=1
Vcd*+
-
*dIdI
ip
KK
s
1
Ls R
Chapter 4 MMC-HVDC
107
2*
i
d
pd i
KI L
R KI Ks s
L L
(4.29)
The natural frequency and damping ratio of the 2nd
order system can therefore be
calculated using equation (4.30) and equation (4.31) respectively.
in
K
L (4.30)
2
P
n
R K
L
(4.31)
The natural frequency of the system is approximate to its bandwidth for a damping ratio of
0.7. Alternatively, the closed loop transfer function can be reduced to a first order transfer
function which allows the PI controller to be tuned for a specific bandwidth, BW, with a
critically damped response [94, 95]. Equation (4.25) can be reduced to a first order transfer
function as follows:
1
* 11
p i
p
d
d p i
p
K Ks
Rs KL s
I L
I K Ks
Rs KL s
L
(4.32)
By selecting i
p
K R
K L equation (4.32) is reduced to equation (4.33)
1
*11
p
pd
pd p
p
K
KI sLK LI sL K
sKsL
(4.33)
The full closed loop transfer function is therefore reduced to a first order transfer function
with a time constant ic pL K . The bandwidth in radians for a first order system is equal
to 1 ic . Hence equation (4.33) can be re-written as equation (4.34), where BWic is the
inner controller bandwidth.
1
1CL
ic
Gs
BW
(4.34)
Chapter 4 MMC-HVDC
108
The proportional gain,pK , and integral gain, iK , can be calculated for given values of L, R
and BW from equations (4.35) and (4.36) respectively.
p icK BW L (4.35)
i p ic
RK K BW R
L (4.36)
The advantage of this method is that the exact bandwidth for the control loop can be
selected through a very simple tuning process. Also a phase margin of 90° with an infinite
gain margin is assured. The disadvantage is that since only the bandwidth can be selected,
there is less flexibility when optimising the controller to meet set performance criteria.
The performance criteria for the inner current loop are that it is fast, stable and has no
overshoot. Tuning the PI controller to provide sufficient bandwidth using the first order
transfer function is therefore a suitable approach. A bandwidth of 320Hz is employed for
the inner current loop. This bandwidth provides a very fast response with zero overshoot as
shown in Figure 4.19-Figure 4.21.
To verify the first order transfer function, a three-phase 31-level MMC with dq current
controller has been implemented in PSCAD. The expected d-axis current response for a
step input using the first order transfer function, Idtf, with the response from the PSCAD
model, Id, for different bandwidths are shown in Figure 4.17-Figure 4.19. The step change
in d-axis current, Idset (Id*), is equivalent to a change in active power of 100MW.
Figure 4.17: Current controller step response for a bandwidth of 80Hz ; x axis – time(s), y axis-current
(kA)
Chapter 4 MMC-HVDC
109
Figure 4.18: Current controller step response for a bandwidth of 160Hz ; x axis – time(s), y axis-
current (kA)
Figure 4.19: Current controller step response for a bandwidth of 320Hz ; x axis – time(s), y axis-
current (kA)
The plots show that the simulated response is similar to the expected response for the three
different bandwidths. These results demonstrate that the first order transfer function can
adequately describe the system behaviour. The small differences in the results are due to
assumptions and simplifications in the derivation of the transfer function.
The results show in general that the simulated current response is slower than expected,
particularly for higher bandwidths. This is because significant step changes in power can
easily force the MMC to enter the non-linear over-modulated region, which is not
accounted for by the transfer function. Increasing the converter transformer tap-changer
ratio so that the converter does not become over-modulated improves the simulated
response as shown Figure 4.20.
Chapter 4 MMC-HVDC
110
Figure 4.20: Current controller step response for a bandwidth of 320Hz with tap-changer ratio
increased ; x axis – time(s), y axis-current (kA)
The simulation results also show that the decoupling between the d and q-axis currents
improves as the bandwidth increases. This is likely to be because the control loop’s
disturbance rejection improves as the bandwidth increases.
Mathematically the d and q-axis should be completely decoupled due to the feedback
nulling terms ( dI and qI ). The derivation of the transfer function assumes that the
converter and associated components such as the abc/dq transform components are perfect
and can therefore be represented as unity gain blocks. The MMC implemented in PSCAD,
however, is not capable of perfectly reproducing the set-point d and q-axis voltages with
zero time delay.
The q-axis current peaks approximately 20ms (one fundamental cycle) after the step input
is applied, irrespective of controller bandwidth. The NLC employed by the MMC assumes
that the SM capacitor voltages are constant and equal, which is only true when there is no
current flowing through the converter arm or when the SM capacitance is infinite. During
normal operation, for finite capacitance, the SM capacitors exhibit a fundamental ripple
voltage. Employing very large SM capacitors ensures that the all SM capacitors are
virtually constant and equal which improves the accuracy of the NLC method. Figure 4.21
shows the converter response when the value of the SM capacitors is increased from
1150µF to 115000µF.
Chapter 4 MMC-HVDC
111
Figure 4.21: Current controller step response for a bandwidth of 320Hz with increased SM
capacitance ; x axis – time(s), y axis-current (kA)
Figure 4.21 shows that the decoupling has greatly improved, however, employing such
large capacitors is impractical and was only implemented to show that the transfer function
is able to describe the system behaviour very accurately when all assumptions are
considered. That said, the transfer function describes the system behaviour with sufficient
accuracy even when ideal converter behaviour is assumed.
The block diagram for the implementation of the current controller is shown in Figure
4.22. The phase voltages and currents, measured at the PCC are scaled, and the output
converter voltage set-points are advanced 30° to compensate for the transformer. The d-
axis and q-axis current orders from the outer controller have limits to prevent valve
overcurrents under balanced conditions.
Figure 4.22: dq current controller implementation
Vcd*
Vsd
++ +
-
dI*dI
dI
-
Vsq
++ +
- qI*qI
qI
+
ωL
ωL( ) *c abcV
( )s abcI
Vcq*
t t
PCCVc(abc)
I(abc) L R
t Vsq
Vs(abc)
PLL
dqabc
PI
PI
dqabcdq
abc
Np/Ns
Ns/Np +30°
Transformer
winding ratio Transformer
phase shift
Chapter 4 MMC-HVDC
112
4.6.3 Outer Controllers
4.6.3.1 Active and Reactive Power Controllers
In the magnitude invariant dq synchronous reference frame, the power flow at the PCC can
be described by equations (4.37) to (4.39).
3 3
* ( )( )2 2
dq dq dq sd sq d qS V I V jV I jI (4.37)
3
2sd d sq qP V I V I (4.38)
3
2sq d sd qQ V I V I (4.39)
The q-axis is aligned with Va such that 0sqV . Equations (4.38) and (4.39) are therefore
reduced to equations (4.40) and (4.41).
3
2sd dP V I (4.40)
3
2sd qQ V I (4.41)
Equations (4.40) and (4.41) show that the active power is controlled by Id and the reactive
power is controlled by Iq. The Id and Iq references to the current controller are set using
feedback PI controllers. The Kp and Ki values for the controllers can be calculated
according to equations (4.42) and (4.43), where BWp is the bandwidth of the power
controller. The derivation of the reduced first order transfer function and the resultant
equations for Kp and Ki is given in Appendix 4E.
1.5
p
p
sd ic
BWK
V BW (4.42)
i ic pK BW K (4.43)
Vsd is the value of d-axis voltage at the PCC, which has a nominal value in this model of
300kV. Providing that the AC system is relatively strong this value is effectively fixed, and
therefore the PI controller parameters can be calculated based on the nominal value for Vsd.
In any case, a variation in Vsd produces a proportional change in the power controller
bandwidth; hence a relatively large variation in Vsd of 10% produces only a 10% change in
pBW . Note that the relationship 1i
p ic
K
K is ensured irrespective of Vsd. Feedback PI
Chapter 4 MMC-HVDC
113
controllers are employed to give the Id and Iq set-points to the inner current controllers
based on the active and reactive power orders respectively.
The active and reactive power demands for a VSC-HVDC converter are typically ramped
at 1GW/min under normal operating conditions and at 1GW/s for emergency power
control26
. The outer power loop does not therefore require a large bandwidth and hence a
bandwidth of 30Hz is more than sufficient. The transfer function response and the
simulated response for a 100MW (10%) and -30MVAr (≈10%) step change are very
similar as shown in Figure 4.23 and Figure 4.24 respectively.
Figure 4.23: System response for a 10% change in active power ; x axis – time(s), y axis-active power
(MW)
Figure 4.24: System response for a 10% change in reactive power ; x axis – time(s), y axis-reactive
power (MVAr)
4.6.3.2 DC Link Voltage Controller
MMCs, unlike two-level VSCs, do not normally employ DC side capacitor banks and
therefore the MMC’s equivalent capacitance, Ceq, as calculated by equation (4.44), is used
26
Based on discussions with an HVDC controls expert from Alstom Grid.
Chapter 4 MMC-HVDC
114
in the DC side plant model shown in Figure 4.25. The plant equations and the derivation of
the 2nd
order transfer function are given in Appendix 4F.
Figure 4.25: DC side plant
The Ki and Kp values for a particular natural frequency and damping ratio can be
calculated using equation (4.45) and equation (4.46).
3 SM
eq
CC
n (4.44)
2
1.5
n eq
i
V
CK
K
(4.45)
2
1.5
n eq
p
V
CK
K
(4.46)
The primary function of the DC link voltage controller is to keep the DC link voltage
constant. The DC link voltage set-point is normally fixed at 1.0p.u. and therefore unlike
power controllers, following set-point variations is not a priority. Hence, the key
performance criteria for the DC voltage outer controller are that it is stable, with excellent
steady-state tracking and good disturbance rejection for a range of operating points
(Kv=0.5±10%).
The outer DC link voltage loop is tuned assuming that the inner current loop is a unity gain
block. This is a valid assumption providing that the outer loop is significantly slower than
the inner current loop. The maximum available bandwidth for the outer controller is
therefore limited to one order of magnitude smaller (≈30Hz) than the inner current loop
bandwidth (=320Hz). The controller’s ability to reject disturbances, particularly low
frequency disturbances, improves with bandwidth due to the increase in integral gain.
Tuning the outer loop controller for a bandwidth of 20Hz and a damping ratio of 0.7, using
equations (4.45) and (4.46) was found to offer a good level of performance. Figure 4.26
shows the systems response, Vdc, the full transfer function response, Vdctf, and the
Vn
MMC
CeqL R
Vs(abc)
In Idc
IcPCC
Vdc
Chapter 4 MMC-HVDC
115
approximate transfer function response, Vdctf2nd, for a 1kV step change about the nominal
operating point. This figure shows that the system response is similar to the expected
response, particularly the full transfer function. Figure 4.27 shows the system response for
an injected noise current ramped from 0 to 1.66kA in one second, which is equivalent to 0
to 1GW under emergency power conditions.
Figure 4.26: System response for a 1kV step change about the operating point, Kv=0.5 ; x axis –
time(s), y axis-voltage(kV)
Figure 4.27: System response for a ramped injected noise current of 1.6kA in 1 second ; x axis –
time(s), y axis-voltage (kV)
4.6.3.3 AC Voltage Control
With reference to Figure 4.28, the magnitude of the voltage at the PCC is given by
equation (4.47). The derivation of this equation is provided in Appendix 4G.
Figure 4.28: MMC phase A connection to the AC network with the system resistances neglected
X2
Vsa
X1
Vca
IaVna
PCC
Chapter 4 MMC-HVDC
116
2 2
(1 ) cos( ) sin( )sa na ca c ca cV V k V k V k (4.47)
where:
2Xk
X (4.48)
The network voltage, naV , and the system reactance values, X1 and X2, are fixed and
therefore the voltage at the PCC, Vsa, can be controlled by varying the internal converter
voltage magnitude, Vca, and angle, c . Variations in the converter angle have very little
influence on the voltage at the PCC and therefore the dominant variable in equation (4.47)
is the converter voltage magnitude. In the magnitude invariant dq reference frame the
magnitude of the converter voltage can be described by equation (4.49). The voltage at the
PCC is controlled using the q-axis converter voltage, Vcq.
2 2
( )c abc cd cqV V V (4.49)
For HVDC systems connected to weak AC grids, the AC voltage controller is required to
ensure that the AC system voltage does not fall outside permissible limits for the full
operating range of active power. Figure 4.29 shows the AC system voltage for the MMC
connected to a weak AC network (SCR=1.5) for an active power order of 1GW and a
reactive power order of 0MVAr. The AC system voltage, Vsa, falls to approximately 70%
of its nominal value and the MMC is only able to export 800MW due to the valve current
limit. With the AC voltage controller engaged, the AC voltage remains with ±2% of the
nominal value and the converter is able to export the maximum active power order, as
shown in Figure 4.30.
Chapter 4 MMC-HVDC
117
Figure 4.29: System response for weak AC network with reactive power set to zero ; x axis – time(s)
Figure 4.30: System response for weak AC network with AC voltage control ; x axis – time(s)
4.6.4 Tap-Changer Controller
The onshore converter transformer typically includes an on-load tap-changer to assist with
voltage regulation at the PCC. For a MMC operating in reactive power control, the
transformer tap ratio can be manipulated to help prevent the converter from becoming over
or under-modulated. Operating the converter in the over or under-modulated region could
have a negative impact in a number of areas such as harmonic performance. In this model
a slow PI controller is employed to set the tap ratio of the transformer to reduce the
magnitude of over and under-modulation. Figure 4.31 and Figure 4.32 show that the tap-
changer reduces the THD of the MMC output voltage.
Chapter 4 MMC-HVDC
118
Figure 4.31: MMC output voltage THD when exporting 300MVAr with no tap-changer ; x axis –
time(s), y axis – THD (%)
Figure 4.32: MMC output voltage THD when exporting 300MVAr with tap-changer ; x axis – time(s),
y axis – THD (%)
4.6.5 Control System for MMC Connected to a Windfarm
In situations where the MMC is connected to an islanded or very weak network the
MMC’s function is to regulate the AC network’s voltage and frequency [80]. In this mode
of operation, the MMC absorbs all of the power generated by the offshore windfarm. The
voltage magnitude at the PCC to the offshore network is equal to the d-axis voltage, Vsod,
providing that the q-axis voltage, Vsoq, is equal to 0. The voltage magnitude is therefore
regulated using PI controllers for the d and q-axis voltages. The voltage controlled
oscillator provides the reference angle from the ordered frequency. The implementation of
the controller is shown in Figure 4.33.
Chapter 4 MMC-HVDC
119
Figure 4.33: Implementation of the AC voltage controller for the offshore network
4.6.6 Inner MMC Controllers
4.6.6.1 Circulating Current Suppressing Control (CCSC)
The circulating currents distort the arm currents, which can increase converter losses and
may result in the requirement for higher rated components. The CCSC suppresses the
circulating current by controlling the voltage across the limb reactors. The development of
this controller is based on work carried out in [82, 88]. With reference to Figure 4.34, the
plant equations for the CCSC can be derived as follows.
Figure 4.34: Equivalent circuit for a single phase of a MMC
( ) ( )dc ua ua la laV V I R Lp I R Lp V (4.50)
The voltage drop across the upper and lower arm impedances, due to the / 2aI current
components in the upper and lower arm cancel each other out according to equation (4.50).
Vso(abc)
Vc(abc)LR
MMC
Iabc
Vdc
dqabc Vsod
PI+-
+-
Vsoq
0
Vsod*
PI
dqabc
Vc(abc)*
VCOf
Θ
PCC
Np/Ns
+30°
Vua(t)
Vdc/2
Ia(t)Vsa(t)
Iua(t)=Ig+Ia(t)/2
Vla(t)
Idc
Vdc/2
Larm
Rarm
Larm
Rarm
La Ra
Va(t)
Vu-g(t)
Vl-g(t)
Ila(t)=Ig-Ia(t)/2
Chapter 4 MMC-HVDC
120
uaI and laI can be replaced with diff g circI I I where 3g dcI I . Equation (4.50) can,
therefore, be reduced to equation (4.51).
2 ( )dc ua la diff arm armV V V I R L p (4.51)
( )2 2
dc ua ladiff arm arm
V V VI R L p
(4.52)
The right hand side of equation (4.52) is known as the difference voltage, diffV , which is the
voltage drop across one converter arm due to the difference current. If the circulating
current is zero then the difference voltage is essentially very small as it is the voltage drop
across the arm resistance due to the arm DC current, Ig. The presence of circulating current
increases the difference voltage, hence by reducing the difference voltage, the circulating
current can be suppressed.
The difference voltage can be controlled by varying the upper and lower arm voltages
equally. This does not affect the AC output voltage as described by equation (4.5) which is
repeated here in equation (4.53).
2 2 2
la ua arm a arma a
V V L dI RV I
dt
(4.53)
The circulating current is a negative sequence (a-c-b) current at double the fundamental
frequency. The plant equation in matrix form is given in equation (4.54).
diff a diff a diff a
diff c diff c diff c
diff b diff b diff b
V I I
V R I Lp I
V I I
(4.54)
Applying the acb to dq transform to equation (4.54) gives equation (4.55). The procedure
for going from equation (4.54) to equation (4.55) is very similar to that of the current
controller outlined in Section 4.6.2.
0 1
21 0
diff d circ d circ d circ d
arm arm arm
diff q circ q circ q circ q
V I I IR L p L
V I I I
(4.55)
The diffI component in equation (4.54) has changed to circI in equation (4.55), because the
DC component of diffI is a zero sequence component which has no effect on the dq values.
The dq components are therefore only affected by the circulating current. The state-block
diagram with feedback decoupling is given in Figure 4.35.
Chapter 4 MMC-HVDC
121
Figure 4.35: CCSC plant state-block diagram
The CCSC can be represented by a first order transfer function in the same manner as the
current controller in Section 4.6.2. Equations (4.56) and (4.57) can therefore be used to
calculate the PI controller parameters:
p armK BW L (4.56)
armi p arm
arm
RK K BW R
L (4.57)
The set-point for the CCSC is always zero in order to reduce the circulating current to the
smallest possible value. The circulating current increases as a function of power, which as
discussed in Section 4.2.3 is controlled using a ramped set-point. The circulating current
therefore also changes in a ramped manner. If however, the CCSC is enabled at a particular
power order then the input to the PI controller,circI , is a step input. The performance of the
CCSC is mainly assessed by its ability to suppress the circulating current under steady-
state and transient conditions.
The bandwidth of the controller has little effect on the circulating current under steady-
state conditions. A small controller bandwidth such as 10Hz is therefore suitable, Figure
4.36. However, higher bandwidths provide better performance during transient conditions.
A bandwidth of approximately 30Hz was found to give a good level of performance as
shown in Figure 4.37. The implementation of the controller is shown in Figure 4.38.
-
1
armL
1
s
Vdiff-d+
Icirc-d
-
1
s
Vdiff-q+
Icirc-q
+ -
2ωLarm
+-
Rarm Rarm
1
armL
2ωLarm
2ωLarm2ωLarm
Chapter 4 MMC-HVDC
122
Figure 4.36: CCSC response to active power ramped at 1GW/s for 1s starting at 2s with a BW of 10Hz
; x axis – time(s)
Figure 4.37: CCSC response to active power ramped at 1GW/s for 1s starting at 2s with a BW of 30Hz
; x axis – time(s)
Figure 4.38: Block diagram of CCSC implementation
4.6.6.2 MMC Driver
The MMC driver is a single component, built for this research in PSCAD, which
determines the correct number of SMs to fire to produce the voltage reference for each
arm, and which SMs to fire to ensure that the capacitor voltages are balanced. This has
been implemented in FORTRAN. To aid understanding, each function is represented by a
+ +-
* 0circ dI
circ dI
-
++ +
-
circ qI
dq
acb
* 0circ qI
( ) *diff abcV
dq
acb( )diff abcI
2 t 2 t
PI
PI
2 armL
2 armL
circ dI
circ qI
Chapter 4 MMC-HVDC
123
separate component, although in reality both functions are performed by a single
component.
The Capacitor Balancing Controller (CBC) ensures that the energy variation in each
converter arm is shared equally between the SMs within that arm. Without such a control
system the SM capacitors would exceed their tolerable voltage limits, which amongst other
things, would damage the SM IGBTs.
The CBC is based on the method outlined by Marquardt et al. in [85]. The CBC samples
the SM capacitor voltages and then sorts them into ascending or descending order based on
the direction of the arm current. If the arm current is positive then the SMs with the lowest
capacitor voltages are placed first. Conversely, if the arm current is negative then the CBC
orders the SMs with the highest capacitor voltage first. This ensures that for positive arm
current the capacitors with the lowest voltages are charged first and for negative arm
current the capacitors with the highest voltages are discharged first.
The CBC used here employs the bubble sort algorithm to order the capacitor voltages [96,
97]. The bubble sort algorithm is simple to implement, but is relatively inefficient for
sorting large lists in comparison to other sorting algorithms. However, the algorithm is
sufficient for this application because the list is relatively small.
The custom built CBC component is coded so that the user can select the number of times
the SM capacitor voltages are sorted per cycle. The sorting frequency is a trade-off
between how well the SM capacitor voltages are balanced, against the effective switching
frequency of the SMs, and the additional effort of sampling and sorting the SMs. A
common method is to sort the capacitor voltages each time the converter output voltage
transitions from one level to another. Employing this method for a 31-level MMC would
result in an approximate sorting frequency of 3kHz. A sorting frequency of 3kHz provides
excellent capacitor voltage balancing but at the expense of a high SM switching frequency.
A default sorting frequency of 1.5kHz was therefore chosen as it was found to offer good
performance without excessive switching. A simplified diagram of the CBC is shown in
Figure 4.39, where Vcapua and Vuao, are the SM capacitor voltages and their order in terms
of voltage, for the upper arm of phase A, respectively.
Chapter 4 MMC-HVDC
124
Figure 4.39: Simplified diagram of the capacitor balancing controller
A number of modulation methods have been proposed for MMCs. These include, but are
not limited to, space vector modulation [98], phase-disposition modulation [99], selective
harmonic elimination [100] and Nearest Level Control (NLC) [101]. The NLC method
produces waveforms with an acceptable harmonic content with a suitable number of levels,
and it is the least computationally complex method of the aforementioned techniques.
The controller block diagram for the NLC is shown in Figure 4.40. The NLC reads in the
reference voltage for the upper and lower arm of each phase (phase A is shown as an
example). Using the DC voltage measurement, it calculates the average SM capacitor
voltage and then calculates the Exact Number of SM Levels (ENL) required in the circuit
to obtain the reference voltage. Due to the finite number of SMs (30 in this case) the ENL
is however rounded to the Nearest Level (NL). The NLC then issues Firing Signals (FS) to
the correct SMs using the ordering information from the CBC. The NLC is coded so that
the SM FS can only update when a new NL is required. A simplified block diagram of the
NLC is shown in Figure 4.40.
Figure 4.40: NLC block diagram
If (Trig=1) then
If (Iua>0) then
Order Vcapua(1-30) lowest first
Else order Vcapua(1-30) highest
first
End If
If (Ila>0) then
Order Vcapla(1-30) lowest first
Else order Vcapla(1-30) highest first
End If
End if
Iua
Ila
Vuao(1-30)Vcapua(1-30)
Vcapla(1-30)
Vlao(1-30)
Trig
Vcap=Vdc/n
ENLU=Vua/Vc
NLU=round(ENLU)
ENLL=Vla/Vc
NLL=round(ENLL)
FSU=NLU
FSL=NLL
--
+
Vdiffa
++
-
Vdc/2
Vdc/2
Vca
VcaVua*
Vla*
FSU(1-30)
FSL(1-30)
NLC
Vuoa(1-30) Vlao(1-30)
Chapter 4 MMC-HVDC
125
4.7 Windfarm Control
A simplified diagram for the offshore windfarm control system is shown in Figure 4.41
and Figure 4.42.
Figure 4.41: Block diagram for the windfarm power controller
Figure 4.42: Implementation of the windfarm power controller
The wind turbine, generator and back-to-back converter are represented as a first order
transfer function with a time constant, w . The natural time constants, o , for three
commercial wind turbines have been calculated in [102] and are presented in Table 4.4.
Prated (MW) rated (m/s) o (s)τ
1.5 13 16.4
2.5 12.5 22.6
3.6 14 25.8
Table 4.4: Calculated time constants for commercial wind turbines modified from [102]
Extrapolating the data given in Table 4.4 for a 5MW wind turbine gives a natural time
constant of approximately 30s. Small signal analysis carried out in [102] has shown that
the actual wind turbine time constant, , varies with wind speed, v , and can be described
by equation (4.58).
ratedo
v
v (4.58)
The maximum cut out speed for a large commercial wind turbine is typical 25 m/s with a
rated wind speed of 12-14 m/s [103, 104]; hence the smallest time constant for a typical
5MW wind turbine is approximately 15s. Setting the windfarm first order transfer function
Power
controller
dq current
controller
Pw*
Idq* Vw(dq)*
Qw*
1
1 ws
d/dt
Vw
Lt
Vso(abc)
PCC
PLLΘdq
abc
Vw(dq)*
P,Q
Chapter 4 MMC-HVDC
126
time constant, w , to 15s would require very lengthy simulation times and therefore it is
reduced to 0.15s which is suitable for this model.
The windfarm reactive power order to the power controller is limited to a rate of change of
1MVAr/ms. The structure of the power controller and the current controller employed for
the windfarm are effectively the same as for the MMC and are therefore not repeated here.
The power controller and current controller are tuned using the first order transfer function
to give a bandwidth of 10Hz and 100Hz receptively. The power controller time constant is
therefore approximately one order of magnitude smaller than the reduced windfarm time
constant. The parameters for the controller are given in Appendix 4H.
4.8 Conclusion
This chapter has described the modelling process for a MMC-HVDC link for a
typical Round 3 offshore windfarm, including the analysis to determine the value of
key parameters of the MMC and associated AC and DC networks, as well as the
tuning and implementation of the numerous required control functions. Its key
contribution is that the main aspects of MMC-HVDC modelling have been brought
together and described in a comprehensive and integrated manner.
Chapter 5 MMC-HVDC Link Performance
127
5 MMC-HVDC Link Performance
This chapter assesses the steady-state and transient performance of the MMC-HVDC link
models developed in Chapter 4 for the connection of a typical Round 3 windfarm, and for
the interconnection of two active AC networks. The theory given in Chapter 4 is used to
verify the simulation results.
Considering that MMC VSC-HVDC systems are set to become a key component of the
UK’s power system, their ability to ride-through AC system faults is of great importance.
Publications in this area are however very sparse [105]. This chapter investigates the
systems’ ability to comply with the GB grid code for AC disturbances and reactive power
requirements. A modification to the standard DC voltage controller, to improve the
systems’ AC fault recovery response for different power operating points, is also proposed
in this work.
The models’ response to DC faults is investigated and the differences between a MMC-
HVDC link employed for the connection of a windfarm and a MMC-HVDC link employed
for the interconnection of two active networks are investigated.
5.1 Radial MMC-HVDC Link for a Round 3 Windfarm
The simplified system diagram for a MMC VSC-HVDC link for a typical Round 3
offshore windfarm is shown in Figure 5.1.
Figure 5.1: MMC VSC-HVDC link for a Round 3 windfarm
5.1.1 Start-up
The onshore converter’s SM capacitors are energised from the onshore AC system as
shown in Figure 5.2. The converter is initially in the blocked state, which effectively forms
a six-pulse bridge enabling each arm of the converter to charge-up to a value equal to the
rectified DC voltage. During this initial charging phase, resistors are inserted between the
AC system and the converter to prevent excessive in-rush current [6]. In this model, the
XT=15%
Yg/D
MMC2-Offshore
Vs2(abc)
220kV 370kV
D/Yg
MMC1-Onshore
Is1(abc)
PCC1XT=15%
370kV 410kV
Vs1(abc)
Idc2
Is2(abc)
AC voltage magnitude and
frequency control
1000MW
Windfarm
Active and reactive power
control
DC link voltage control and
AC voltage magnitude control
Rbrak
Vdc2=600kV
165km DC cablePCC2
Larm=45mH CSM=1150μF
Vn
SCR=3.5
Zn
400kV
Idc1
Chapter 5 MMC-HVDC Link Performance
128
rectified DC voltage is not equal to the nominal DC voltage (600kV), and therefore at 0.3s,
the converter is operated in DC voltage control to obtain the nominal DC voltage. During
the entire charging process the offshore converter’s circuit breakers are open and the SM
capacitors are charged from the DC voltage created by the onshore converter. Once the
charging process is complete the offshore AC circuit breakers are closed.
Figure 5.2: Start-up procedure; capacitor voltages are for the upper arm of phase A for MMC1 ; x axis
– time(s)
5.1.2 Windfarm Power Variations
To assess the link’s ability to respond to power demands, the windfarm is ordered to inject
1GW of active power at 1s; the order is then reduced to 500MW at approximately 3.1s and
again increased to 750MW at approximately 4s. The onshore converter is initially set to
supply 330MVAr to the onshore grid and then set to absorb 330MVAr at approximately
2.1s while operating at maximum active power. Figure 5.3 shows that the VSC-HVDC link
is capable of responding to the power demands of the windfarm and that the converter is
able to meet the required reactive power demands set out in the GB grid code (leading and
lagging power factor of 0.95) [106, 107].
The link’s steady-state response for the windfarm operating at maximum power is shown
in Figure 5.4. The phase voltages and phase currents at the PCC for the onshore network
(Vs1(abc) , Is1(abc)) and the offshore network (Vs2(abc), Is2(abc)) are shown to be almost
sinusoidal and as such have a small harmonic content. The DC voltages are smooth and
Vd*=600kV
Chapter 5 MMC-HVDC Link Performance
129
virtually ripple free, while the DC current exhibits a small ripple of approximately ±1.5%
of the nominal value. The DC current ripple can be reduced further by disabling the CCSC,
however, this would increase converter losses.
The THD of the line-to-line voltages at the onshore PCC is shown in Figure 5.5. This
analysis confirms that the harmonic content is very small and is within the 1.5% limit set
out in the IEEE519 standards.
Figure 5.3: Link response to variations in windfarm power ; x axis – time(s)
Q*=-330MVAr
P*=500MW P*=750MW
Chapter 5 MMC-HVDC Link Performance
130
Figure 5.4: Link response at steady-state for Pw =1GW ; x axis – time(s)
Figure 5.5: THD for the line-to-line voltages at PCC1 for Pw = 1GW ; x axis – time(s)
5.1.3 MMC
The output phase voltages (V1(abc)), arm currents (Iu(abc), Il(abc) ) and difference currents
(Idiff(abc)) for the onshore converter operating at 1GW are shown in Figure 5.6. The staircase
voltage waveform produced by the MMC is more evident than the voltages measured at the
PCC. The CCSC is able to suppress the circulating current to very small values as is
evident in the bottom graph of Figure 5.6 since there is virtually no AC component. The
absence of the circulating current component in the arm current ensures that there is little
Chapter 5 MMC-HVDC Link Performance
131
distortion and that losses are minimised. The effect of the CCSC on the waveforms can be
seen by comparing Figure 5.6 with Figure 5.7.
Figure 5.6: Phase voltages, arm currents and difference currents for onshore MMC with Pw =1GW ; x
axis – time(s)
Figure 5.7: Phase voltages, arm currents and difference currents for onshore MMC with Pw =1GW
and CCSC disabled ; x axis – time(s)
The effect of the CCSC on the converter losses can be assessed by measuring the rms value
of the arm current. Comparing Figure 5.8 with Figure 5.9 shows that disabling the CCSC
Chapter 5 MMC-HVDC Link Performance
132
increases the arm current by approximately 25%, indicating a significant increase in the
converter losses [108]. This increase in arm current may also require the valve components
to be designed for a higher current rating.
Figure 5.8: Rms value of the upper arm current for phase A with Pw=1GW and CCSC enabled ; x axis
– time(s)
Figure 5.9: Rms value of the upper arm current for phase A with Pw=1GW and CCSC disabled ; x axis
– time(s)
If the phase voltages in Figure 5.6 and Figure 5.7 are compared closely, particularly at the
peak of the waveform, it is noticeable that they are slightly different. This is because
circulating current increases the SM capacitor ripple voltage which increases the distortion
of the phase voltages. This can be shown by comparing Figure 5.5 and Figure 5.10.
Figure 5.10: THD for the line-to-line voltages at PCC1 for Pw = 1GW and CCSC disabled ; x axis –
time(s)
In Section 4.2.2, the SM capacitance was calculated to give a ±5% ripple voltage. Figure
5.11 shows that this calculation is accurate. Disabling the CCSC increases the ripple
Chapter 5 MMC-HVDC Link Performance
133
voltage to approximately ±10% as shown in Figure 5.12, which again indicates the benefit
of the CCSC.
Figure 5.11: SM capacitor ripple voltages for the upper arm of phase A with Pw=1GW ; x axis – time(s)
Figure 5.12: SM capacitor ripple voltages for the upper arm of phase A with Pw=1GW and CCSC
disabled ; x axis – time(s)
5.1.4 Onshore AC Fault Ride-through
VSC-HVDC links must be able to ride-through faults and disturbances on the AC network.
The exact requirements for the link will be dependent upon the grid code. The fault ride-
through criteria to meet the GB grid code is given in Section CC.6.3.15 of [106]. The
general criterion for HVDC systems is broadly the same as a power park module, however
there are some difference for faults in excess of 140ms. The active power recovery
response of the HVDC system for faults in excess of 140ms but less than 800ms is
determined through study work by the developer and the results are submitted to National
Grid. The key criteria for a power park module, for onshore AC short-circuit faults lasting
up to 140ms and Supergrid voltage dips greater than 140ms is summarised below:
1. The system must not be tripped for a close-up solid three-phase short-circuit fault
or any unbalanced short-circuit fault on the onshore transmission system for a total
fault clearance time of 140ms. It should be noted that the Supergrid voltage may
take longer than the 140ms clearance time to recover to 90% of its nominal value.
Chapter 5 MMC-HVDC Link Performance
134
2. It must deliver 90% of the pre-fault active power within 0.5s of the Supergrid
voltage returning to 90% of its nominal value. Oscillations in active power are
acceptable providing that the oscillations are adequately damped and that the active
energy is at least that which would have been delivered if the active power was
constant.
3. During the fault, for which the voltage at the interface point is outside the limits
specified in Section CC.6.1.4, the generating unit must supply maximum reactive
current without exceeding its thermal rating.
4. The system must remain transiently stable and connected to the system for balanced
Supergrid voltage dips and associated durations on the onshore transmission
system. The active power level during the dip should be retained at least in
proportion to the retained balanced voltage, and supply maximum reactive current
when the voltage is outside the limits specified by CC.6.1.4, without exceeding the
transient ratings.
5. The active power transfer capability following Supergrid voltages dips on the
onshore network should be restored to at least 90% of the level available before the
dip within 1 second. The oscillations criteria are the same as criterion two.
It is expected that the maximum instantaneous arm current for an MMC is approximately
1.5p.u. (≈3kA) and that the maximum instantaneous SM overvoltage is 1.3p.u.(≈27kV)27
.
Hence for each of the test cases simulated, the MMC arm current and SM capacitor
voltages must be within these limits in order to safely ride-through the disturbance.
During onshore AC disturbances, the onshore converter’s ability to export active power is
diminished. If the power generated by the windfarm is not curtailed to meet the demands of
the onshore converter, the DC link voltage will rise. Several methods have been proposed
for the curtailment of wind power during onshore AC faults. However, many of these
methods require telecommunications, are not applicable for all wind turbine topologies, or
require modifications to the offshore MMC and wind turbine controls. The use of a DC
braking resistor in the HVDC link enables the DC link voltage to be controlled very
effectively and does not impact on the windfarm. It is for these reasons that the use of a
DC braking resistor is employed for these studies.
27
Under normal operating conditions, the maximum instantaneous arm current and the maximum instantaneous SM capacitor voltage is approximately 2kA and 21kV respectively.
Chapter 5 MMC-HVDC Link Performance
135
5.1.4.1 Supergrid Voltage Dips
According to the GB grid code, for a Supergrid voltage dip to 30% the DC converter must
remain connected to the grid for at least 384ms. To test the link’s ability to ride-through
this disturbance the following simulation is conducted; the windfarm is set to operate at
maximum power, at approximately 2s the voltage at PCC1 is reduced to 0.3p.u. for 0.5s,
and is then increased to 90% of the nominal value. The simulation results are presented in
Figure 5.13.
At fault inception, the active power exported by the inverter, P1, decays in proportion to
the voltage dip, while the active power imported from the windfarm, P2, remains
unchanged. This leads to a rise in the DC link voltage. The DC braking resistor is
switched-on the moment that the DC link voltage exceeds the 1.1p.u. threshold and is
turned-off once the DC link voltage returns to 1.0.p.u. When the Supergrid voltage is
restored to 90% of the nominal value, the active power level recovers to its pre-disturbance
level with little oscillation and well within the allowable time. The converter’s SM
capacitor voltages and arm current values do not exceed tolerable values during this
simulation case. The simulation results therefore show that the system is capable of riding
through the disturbance for the required 384ms.
The MMC in the previous simulation case was set to inject no reactive power at the PCC1
and therefore criterion 4 would have not been fully met in this case. In the following case
the MMC operates in AC voltage control and the simulation results are shown in Figure
5.14. During the voltage dip the MMC injects maximum q-axis current. The reactive power
support increases the voltage at the PCC and subsequently enables the converter to supply
approximately 50% more active power than without the reactive power support. The active
power response upon fault clearance is more oscillatory when the AC voltage magnitude
control is employed. This is primarily because the AC voltage magnitude control is slower
than the reactive power controller, due to the rms measurements.
5.1.4.2 Unbalanced Short-circuit Faults
In order to meet criterion 1, the DC converter must remain connected to the onshore grid
for an unbalanced close-up short-circuit fault with a fault clearance time of 140ms. Figure
5.15 shows the converter’s performance for a 140ms line-to-ground fault occurring at 3s on
phase A, and for a 140ms line-to-line fault between phases A and B occurring at 4s. The
Chapter 5 MMC-HVDC Link Performance
136
simulation results show that the link is able to ride-through the two unbalanced AC
network faults and meet the necessary criterion.
5.1.4.3 Three-phase Line-to-Ground Fault at PCC1
A three-phase symmetrical fault is applied at PCC1 for 140ms starting at 3s. During such a
severe fault, the inverter is unable to export any significant quantity of active power,
leading to a rapid rise in the DC link voltage. In this scenario, the MMC converters are
effectively paralysed and the regulation of the DC link voltage is performed by the DC
braking resistor, which is designed to dissipate the maximum windfarm power at a DC link
voltage of 720kV (1.2p.u.).
Figure 5.16 shows that the DC link voltage does exceed 1.2p.u. This is due to power from
the onshore AC system being injected into the link when the fault is cleared. Upon fault
clearance, the converter is unable to effectively control the d-axis current for a short period
of time, which leads to power from the onshore AC system being injected into the link.
Increasing the bandwidth of the current controller and the Phase Locked Loop (PLL) can
improve the system’s response to this type of fault; however increasing controller
bandwidth may degrade system performance under different operating conditions. After
the fault is cleared, the active power level recovers to its pre-disturbance level well within
the allowable time and with acceptable oscillations.
The simulation results show that the peak voltage for the SM capacitor voltages for the
upper arm of phase A is approximately 26kV (<1.3p.u.), which is the worst of the cases
simulated. The maximum DC link voltage, the maximum arm current and the performance
of the CBC are the three main factors which determine the peak value of the capacitor
voltage. However, varying one of these three factors can limit the link’s performance in
other areas. For example, increasing the sorting frequency of the CBC can reduce the peak
capacitor voltage, but at the expense of increased switching losses. It is expected that the
SMs in a commercial MMC are rated to withstand 1.3p.u., a peak voltage of 26kV is
therefore considered to be acceptable. The peak arm current value does not exceed the 3kA
overcurrent protection limit.
The link’s ability to safely ride-through AC system faults is affected by a number of
factors which include, but are not limited to, AC system strength, fault impedance, control
system design, protection strategy and DC braking resistor design.
Chapter 5 MMC-HVDC Link Performance
137
Figure 5.13: Supergrid voltage dip to 0.3p.u. with no MMC reactive current support ; arm currents
are for MMC1 and capacitor voltages are for the upper arm of phase A for MMC1; x axis – time(s)
Chapter 5 MMC-HVDC Link Performance
138
Figure 5.14: Supergrid voltage dip to 0.3p.u. with MMC reactive current support ; arm currents are
for MMC1 and capacitor voltages are for the upper arm of phase A for MMC1; x axis – time(s)
Chapter 5 MMC-HVDC Link Performance
139
Figure 5.15: Phase A to ground fault at 3s and phase A to phase B fault at 4s ; arm currents are for
MMC1 and capacitor voltages are for the upper arm of phase A for MMC1; x axis – time(s)
Chapter 5 MMC-HVDC Link Performance
140
Figure 5.16: Three-phase to ground fault at 3s ; arm currents are for MMC1 and capacitor voltages
are for the upper arm of phase A for MMC1; x axis – time(s)
Chapter 5 MMC-HVDC Link Performance
141
5.1.5 DC Faults
The simulation results for a DC line-to-line fault applied to the terminals of MMC1 at 3s
are shown in Figure 5.17. The converters have an instantaneous overcurrent threshold of
3kA. Once the current magnitude in any arm of the converter reaches this threshold the
converter is blocked. It takes approximately 400µs from fault inception for MMC1 to reach
this limit. If the assumed maximum arm current rating of 3kA is impractical, then either
more inductance must be added to the fault current path, the converter must be capable of
blocking quicker, or a combination of the two must be employed. Upon blocking the
converter, the fault current flows from the AC system through the converter’s anti-parallel
diodes. In practice, protection thyristors are employed to conduct the DC fault current and
to therefore prevent the SM diodes from reaching their current rating. However, this does
not affect the overall simulation results. The results show that it takes approximately three
cycles for the AC breakers to open, after which the arm currents decay as the arm reactors
de-magnetise. The fast blocking action ensures that the converter is able to survive a severe
DC line-to-line fault.
A DC positive line-to-ground fault is applied to the terminals of MMC1 at 3s. As shown in
Figure 5.18 the faulted pole voltage collapses to zero whilst the healthy pole experiences a
voltage of 2p.u. (600kV). This causes the converter to synthesise voltages (Va1,Vb1,Vc1)
with a DC offset of 300kV. In a symmetrical monopole for a MMC-HVDC scheme, the
DC side is not normally earthed and therefore there is no low impedance path for the fault
current. The scheme can then theoretically continue to operate as stated in [109], however
this is unlikely to be possible in a commercial HVDC system due to the additional voltage
stress to the cable and transformer. The scheme is therefore tripped and the DC link
voltage is reduced as quickly as possible to protect the DC cables and transformer.
In Figure 5.19, the DC braking resistor is turned-on and the MMCs are blocked once the
local negative line-to-ground voltage magnitude exceeds 1.1p.u. (330kV) and 1.3p.u.
respectively. Once the offshore converter is blocked, active power is still injected into the
link from the windfarm through the MMC’s diodes, which is dissipated in the DC braking
resistor. Approximately three cycles after fault inception, the AC side breakers for both
converters are tripped and then the DC braking resistor rapidly discharges the DC cable.
The healthy DC cable voltage is reduced to less than 1p.u. within 80ms of fault inception
using this protection strategy.
Chapter 5 MMC-HVDC Link Performance
142
It should be noted that in commercial HVDC schemes a star-point reactor between the
transformer and the converter at one converter station is installed to provide DC voltage
grading [91] and that surge arresters are typically installed between the DC poles and
ground to limit overvoltages. These components were not modelled in the previous
simulation cases.
In the event of a DC line-to-ground fault, the star-point reactor provides a low impedance
path for DC current to flow and the surge arresters assist in limiting the magnitude and
duration of the DC voltage experienced by the healthy cable. Simulation results are
included in Appendix 5A to show the effects of the star-point reactor and surge arresters.
Chapter 5 MMC-HVDC Link Performance
143
Figure 5.17: DC line-to-line fault at the terminals of MMC1 at 3s ; arm currents are for MMC1 and
capacitor voltages are for the upper arm of phase A for MMC1; x axis – time(s)
Chapter 5 MMC-HVDC Link Performance
144
Figure 5.18: Positive pole-to-ground fault at MMC1 ; arm currents are for MMC1 and capacitor
voltages are for the upper arm of phase A for MMC1; x axis – time(s)
Chapter 5 MMC-HVDC Link Performance
145
Figure 5.19: Positive pole-to-ground fault at MMC1 with under voltage protection ; arm currents are
for MMC1 and capacitor voltages are for the upper arm of phase A for MMC1; x axis – time(s)
Chapter 5 MMC-HVDC Link Performance
146
5.2 VSC-HVDC Interconnector
The purpose of this section is to highlight the differences between a VSC-HVDC link
employed for the connection of a windfarm and a VSC-HVDC link employed for the
interconnection of two active networks. The structure of the model for the interconnector,
as shown in Figure 5.20, is similar to link for the offshore windfarm, shown in Figure 5.1,
except for the following distinctive differences:
The windfarm network is replaced with a relatively strong AC network
Each MMC must be able to operate as a rectifier and as an inverter
MMC2 is set to control active and reactive power, as opposed to AC voltage
magnitude and frequency
The interconnector has no DC braking resistor
Figure 5.20: MMC VSC-HVDC interconnector
5.2.1 Power Reversal
Figure 5.21 shows the link’s ability to operate under emergency power control for a range
of power orders including power reversal. The steady-state waveforms for a point-to-point
link are similar to a link employed for a windfarm (Section 5.1.3) and hence they are not
repeated here.
5.2.2 AC Faults
In terms of a link’s ability to ride-through AC faults, the key difference between an
interconnector and a link employed for the connection of a windfarm is that the
interconnector controls active power flow. Hence, if a fault occurs in the AC grid
connected to MMC 1, MMC 2 is able to control the power flow to regulate the DC link
voltage.
A method proposed in [77], varies the link’s power order in accordance with the AC
system voltage magnitude measured at each end of the link. This method is shown to work
XT=15%
Yg/D
MMC2
Vs2(abc)
410kV 370kV
D/Yg
MMC1
Is1(abc)
PCC1XT=15%
370kV 410kV
Vs1(abc)
Is2(abc)
Real and reactive power
control
DC link voltage control and
AC voltage magnitude control
Vdc2=600kV
165km DC cablePCC2
Larm=45mH
Vn
SCR=3.5
Zn
400kV
Vn
SCR=3.5
Zn
400kV
CSM=1150μF
Idc2 Idc1
Chapter 5 MMC-HVDC Link Performance
147
effectively in [77], however the reliance upon a telecommunications link between the two
converters is a drawback due to reliability concerns. An alternative method is to use
voltage margin control, which is discussed in detail in Section 8.2.2. The converter
effectively operates in constant power control, providing that its local DC link voltage is
within pre-set limits (Vdc-low<Vdc<Vdc-high), when employing this control method. If the DC
link voltage exceeds these limits then the converter operates in DC link voltage control
mode. Hence, applying voltage margin control to MMC 2 enables the DC link voltage to
be regulated for disturbances in AC grid 1 without a telecommunications link.
A three-phase symmetrical fault is applied at PCC1 for 140ms starting at 3s and the
simulation results are shown in Figure 5.22. The simulation results show that the link is
able to ride-through the three-phase AC network fault and meet the necessary criteria.
5.2.3 DC Faults
The link’s response to a DC line-to-line fault is similar to that of a link for a windfarm and
therefore will not be repeated. In the event of a DC line-to-ground fault for a HVDC link
interconnecting two active networks, the converters are blocked on line-to-ground
overvoltage protection, the AC circuit breakers are tripped after three cycles and the cable
then discharges without the aid of a DC braking resistor as shown in Figure 5.23. The
healthy DC cable voltage is reduced to less than 1p.u. within 200ms of fault inception
using this protection strategy. As mentioned in Section 5.1.5, surge arresters can be used to
limit the voltage on the healthy cable.
Chapter 5 MMC-HVDC Link Performance
148
Figure 5.21: System response for a wide range of active and reactive power orders ; x axis – time(s)
Chapter 5 MMC-HVDC Link Performance
149
Figure 5.22: Three-phase fault for 140ms at 3s ; arm currents are for MMC1 and capacitor voltages
are for the upper arm of phase A for MMC1; x axis – time(s)
Chapter 5 MMC-HVDC Link Performance
150
Figure 5.23: DC line-to-ground fault ; arm currents are for MMC1 and capacitor voltages are for the
upper arm of phase A for MMC1; x axis – time(s)
Chapter 5 MMC-HVDC Link Performance
151
5.3 Variable Limit DC Voltage Controller
During AC system disturbances, the DC link voltage controller increases the d-axis current
set-point. This is to compensate for the decrease in the AC system voltage in an attempt to
regulate the DC link voltage and hence maintain the pre-fault active power flow. Once the
fault is cleared, the AC system voltage recovers faster than the DC link voltage controller
is able to reduce the d-axis current set-point to achieve the desired active power, which
results in an overshoot. The d-axis current set-point has a fixed limit which is used to
prevent the converter from exceeding its current rating. In the event of a severe AC system
disturbance, such as an AC close-up three-phase fault, the DC voltage controller will reach
the d-axis current limit. This results in a large overshoot when the desired active power
flow is relatively low, as shown in Figure 5.24 (left) for the windfarm link model.
The system’s response can be improved by increasing the bandwidth of the DC link
voltage controller; however, this can degrade system performance under different
operating conditions. An alternative method is proposed here which varies the d-axis
current limits for the DC link voltage controller depending upon the pre-fault active power
flow. The controller continuously measures the active power, and calculates the required d-
axis current based on the AC system voltage to achieve the required active power. The
calculated d-axis current value is then increased by a safety margin (20%) and is used to
set the d-axis current limit. Once the measured AC system voltage decreases below a pre-
set level (0.85p.u.) the d-axis current value switches to variable limits until 100ms after the
AC system voltage increases above 0.85p.u. The threshold of 0.85p.u. is the minimum AC
system voltage value at which the system can supply maximum active power. This method
ensures that the d-axis current limit is set to a level appropriate for the pre-fault active
power flow and hence reduces the power overshoot as shown in Figure 5.24 (right). The
variable limits are only activated once the AC system voltage decreases below 0.85p.u. and
hence fixed limits are employed during normal operation.
Figure 5.24: Comparison of active power response for a 140ms three-phase AC fault using fixed and
variable limits Left) fixed limits, Right) variable limits
Chapter 5 MMC-HVDC Link Performance
152
5.4 Conclusion
This chapter has assessed the steady-state and transient performance of the MMC-HVDC
link models developed in Chapter 4 through conducting a range of typical studies. The
simulation results are shown to be in agreement with the theory outlined in Chapter 4.
These models thus provide a high fidelity version of a component level MMC model with
detailed parameters and control and can therefore act as a benchmark for lower fidelity
models. An example of this use was in the verification of an averaged value VSC-HVDC
model which enabled this lower fidelity model to be used for a comprehensive
investigation into the limitations imposed on active power controllers.
The models developed in this thesis were used to investigate the links’ ability to respond to
reactive power demands and to ride-through disturbances in the AC grid. The results show
that the models were able to meet the reactive power requirements and the AC fault ride-
through requirements set out in the GB grid code for the tests conducted, as well as
complying with the IEEE 519 THD voltage harmonic limits at the PCC. Furthermore, the
results show that the use of the proposed variable limit DC voltage controller, a
modification to the standard DC voltage controller, can improve the system’s fault
recovery response.
The differences between the control and protection of the interconnector, in comparison to
the link employed for the connection of a windfarm, were also highlighted. The key
difference is that the interconnector is able to maintain control of the DC link voltage in the
event of a severe AC fault, without a DC braking resistor, by controlling the active power
at the rectifier.
Chapter 6 MMC Modelling Techniques
153
6 Comparison of MMC Modelling Techniques
The 31-level MMC converters described in Chapter 4, and used for the MMC-HVDC link
models in Chapter 5, were represented using the PSCAD Detailed Equivalent Model
(DEM) which is based on the principles outlined in [10]. The DEM technique was
employed as a direct consequence of the comparative analysis of detailed MMC modelling
techniques described in this chapter.
Modelling MMCs in Electromagnetic Transient (EMT) simulation programs presents a
significant challenge in comparison to modelling a two or three-level VSC. The stack of
series-connected IGBTs in each arm of a two or three-level VSC are switched at the same
time. This simultaneous switching action enables the stack of IGBTs to be modelled as a
single IGBT for many studies. The MMC topology, however, does not contain stacks of
series-connected IGBTs which have identical firing signals and therefore a comparable
simplification in the model cannot be made.
The converter employed on the Trans Bay Cable project is an MMC with approximately
201 levels. A Traditional Detailed Model (TDM) of this converter would require more than
2400 IGBTs with anti-parallel diodes and more than 1200 capacitors, to be built and
electrically connected in the simulation package’s graphical user interface, resulting in a
large admittance matrix. The admittance matrix must be inverted each switching cycle,
which for MMCs can be hundreds of times per fundamental cycle and is therefore
extremely computationally intensive. This makes modelling MMCs for HVDC schemes
using traditional modelling techniques impracticable.
To address this problem an efficient model was proposed by Udana and Gole in [10],
which is referred to as the DEM in this work. In [10] the DEM was shown to significantly
reduce the simulation time in comparison with a TDM without compromising on accuracy.
A drawback of the DEM is that the individual converter components are invisible to the
user. This makes the model unsuitable for studies which require access to the individual
converter components and it makes it difficult to re-configure the converter SM for
different topologies. Only one publication has compared the DEM with the TDM, which
was performed in EMTP-RV [12].
A new model, referred to as the Accelerated Model (AM), was proposed by Xu et al. in
[11]. This model was found to offer greater computational efficiency than for a TDM
Chapter 6 MMC Modelling Techniques
154
without compromising on accuracy and it gives the user access to the individual converter
components. In [11], an attempt was made to compare the AM simulation time with the
DEM simulation time data from [10], however, a full and objective comparison could not
be completed because the models were built by different researchers on different
computers.
The objective of this chapter is to perform a much needed independent comparison of the
TDM, DEM and AM models, which will enable the reader to make a more informed
decision when selecting which type of detailed MMC model to use, and to have a greater
degree of confidence in the MMC model’s performance. In this work the TDM, DEM and
AM models are built in the same software environment and are simulated on the same
computer to evaluate their accuracy and simulation speed. This enables a fair comparison
between the DEM and the AM and it provides the first independent verification for the AM
against the TDM, and the first independent verification for the DEM against the TDM in
PSCAD. Having completed this verification, this work also highlights potential limitations
of the AM and proposes an enhanced accelerated model (EAM) with an improved
simulation speed.
6.1 MMC Modelling Techniques
This section describes the three leading detailed modelling techniques, TDM, DEM and
AM which represent the converter’s IGBTs and diodes using a simple two-state resistance.
6.1.1 Traditional Detailed Model
In a traditional detailed MMC model, each SM’s IGBTs, diodes and capacitors are built in
the simulation package’s graphical user interface and electrical connections are made
between the SMs in each arm, as shown in Figure 4.2. This is the standard way of building
a detailed MMC model and hence is why this type of model is referred to as the TDM.
This method of modelling is intuitive and gives the user access to the individual
components in each SM, however, for MMCs with a large number of SMs this method is
very computationally inefficient.
6.1.2 Detailed Equivalent Model
The DEM uses the method of Nested Fast and Simultaneous Solution (NFSS) [110]. The
NFSS approach partitions the network into small sub-networks, and solves the admittance
Chapter 6 MMC Modelling Techniques
155
matrix for each sub-network separately [10]. Although this increases the number of steps to
the solution, the size of admittance matrices are smaller, which can lead to a reduced
simulation time. A summary of the DEM is presented here, however, further information
can be found in [10].
6.1.2.1 Nested Fast and Simultaneous Solution
The NFSS approach is best explained with the aid of an example [10]. The equivalent
admittance matrix for a network, which is split into two subsystems is given by (6.1).
11 12 1 1
21 22 2 2
Y Y V J
Y Y V J
(6.1)
where:
11 22,Y Y admittance matrices for subsystem 1 and subsystem 2 respectively.
12 21,Y Y admittance matrices for the interconnections
1 2,V V unknown node voltage vectors
1 2,J J source current vectors
The number of nodes in subsystem 1 and subsystem 2 are N1 and N2 respectively. The
direct solution of (6.1) for the unknown vector voltages requires an admittance matrix of
size (N1+N2) (N1+N2) to be inverted.
Rearranging the 2nd
row of equation (6.1) for V2 gives (6.2). Substituting (6.2) into the first
row of (6.1) produces (6.3) which can be rearranged for V1, as given by (6.4).
1 1
2 22 21 1 22 2V Y Y V Y J (6.2)
1 1
1 11 1 12 22 2 22 21 1( )J Y V Y Y J Y Y V (6.3)
1 1 1
1 11 12 22 21 1 12 22 2( ) ( )V Y Y Y Y J Y Y J (6.4)
V1, calculated from (6.4), is then substituted into (6.2) to calculate V2. Once all unknown
voltages are calculated, all currents can then be calculated. This approach requires the
inversion of two matrices, 22Y , of size (N2N2) and 1 1
11 12 22 21( )Y Y Y Y of size (N1N1), instead
of a single matrix of size (N1+N2)(N1+N2). This example partitioned the original network
Chapter 6 MMC Modelling Techniques
156
into two subsystems, however the network can be split into many subsystems. In the DEM,
each converter arm is modelled as its own subsystem.
The size of the admittance matrices for each converter arm is related to the number of
SMs, hence, for MMCs with a high number of levels, the size of the admittance matrices to
be inverted are still relatively large. To further improve the simulation speed, the DEM
reduces each converter arm to a Norton equivalent circuit.
6.1.2.2 Norton Equivalent Circuit for the Converter Arm
This modelling method is based on converting a multi-node network into an exact, but
computationally simpler, equivalent electrical network using Thevenin’s theorem. The
IGBTs and antiparallel diodes employed in each SM form a bi-directional switch and can
therefore be represented as a resistor, with two values, Ron and Roff. The resistor value is
dependent upon the firing signal to the IGBT and the arm current direction, Iarm. The
converter is considered to be blocked when both IGBTs are switched-off and hence the
values of R1 and R2 are determined by the arm current direction. The SM capacitor can be
represented as an equivalent voltage source, Vcapeq, connected in series with a resistor, Rcap,
as shown in Figure 6.1.
Figure 6.1: SM circuit (left) SM equivalent circuit (right)
The Vcapeq and Rcap values are determined from the following analysis.
( )( )
cap
cap SM
dV tI t C
dt (6.5)
Solving equation (6.5) for ( )capV t using the trapezoidal integration method gives (6.6).
( ) ( ) ( )cap cap cap capeqV t R I t V t t (6.6)
R1
R2
Rcap
Icap
Vcap
Vcapeq
Vcap
Icap
Iarm Iarm
VSMVSM
Chapter 6 MMC Modelling Techniques
157
where:
2cap
SM
tR
C
(6.7)
( ) ( ) ( )2
capeq cap cap
SM
tV t T I t t V t t
C
(6.8)
The voltage at the terminals of the SM is given by (6.9):
( ) ( ) ( )SM arm SMeq SMeqV t I t R V t t (6.9)
where:
22
1 2
1SMeq
cap
RR R
R R R
(6.10)
2
1 2
( ) ( )SMeq capeq
cap
RV t t V t t
R R R
(6.11)
The SMs in each converter arm are connected in series. The Thevenin equivalent circuits
for each SM can therefore be combined to a single Thevenin equivalent circuit for each
converter arm, as shown in Figure 6.2, where:
1
n
eq SMeqi
i
R R
(6.12)
1
n
eq SMeqi
i
V V
(6.13)
The Thevenin equivalent circuit for the converter arm is converted to a Norton equivalent
circuit for use by the main EMT solver.
Chapter 6 MMC Modelling Techniques
158
Figure 6.2: String of SM Thevenin equivalent circuits (left) Converter arm Thevenin equivalent circuit
(right)
The process outlined in this section has reduced a multi-node network for each converter
arm and converted it into a two node Norton equivalent circuit in the main EMT solver.
This significantly reduces the size of the admittance matrix for the EMT solver which
improves the simulation speed. Since the main EMT solver only considers a two node
network for each converter arm, the individual identities of each SM are lost, however, the
Thevenin equivalent solver considers each SM separately and therefore the SM capacitor
voltages and currents are recorded.
PSCAD have developed a DEM model based on the work by Udana and Gole. The
component mask is shown in Figure 6.3. The development of the DEM has a clear
advantage over the TDM in terms of simulation speed, however there are some limitations.
The user it not able to access the SM components, which means that the model is not
suitable for studies which require internal converter access. Also re-configuring the
component for other SM topologies is not straightforward as it needs to be re-coded for the
specific topology, which can be complex and time consuming. Half-bridge and full-bridge
MMC equivalent arm components are currently available to PSCAD users.
Figure 6.3: PSCAD half-bridge MMC arm component
VSM1
VSMn
RSMeq1
VSMeq1
RSMeqn
VSMeqn
Iarm
Iarm
Iarm
Varm
Req
Veq
Ic
Vc
x10
Chapter 6 MMC Modelling Techniques
159
6.1.3 Accelerated Model
The Accelerated Model (AM) was proposed by Xu et al. in [11]. In many respects the AM
is a hybrid between the TDM and the DEM. The user is able to access the SM components,
as they can with the TDM, but the converter arm is modelled as a controllable voltage
source, which is similar to the DEM. An overview of the AM is presented here; the reader
is referred to [11] for further information. In the AM, the series-connected SMs are
removed from each converter arm, separated and driven by a current source with a value
equal to the arm current, Iarm. A controllable voltage source is installed in place of the SMs
as shown in Figure 6.4, where the value of the controllable voltage source is given by
(6.14).
1
n
arm SMi
i
V V
(6.14)
The AM reduces the size of the main network admittance matrix by solving the admittance
matrix for each SM separately. The AM has two key advantages in comparison to the
DEM. The first is that the AM allows the user access to the SM components. The second is
that because the AM is implemented using standard PSCAD components, the internal
structure of the SM can be easily modified; for example changing from a half-bridge SM to
a full-bridge SM.
Figure 6.4: Implementation steps for the accelerated model
VSM1
VSM2
VSMn
VSM1
VSM2
VSMn
Iarm
Iarm
Iarm
Iarm
Iarm
Iarm
Icap1
Icap2
Icapn
Icap1
Icap2
Icapn
Vcap1
Vcapn
Vcap2
Vcap1
Vcapn
Vcap2
Iarm
Larm
Larm
Varm
Converter arm
Chapter 6 MMC Modelling Techniques
160
6.2 Simulation Models
A detailed MMC model for a typical VSC-HVDC scheme, employing the TDM converter
arm representation, has been developed. This model is used as the TDM simulation model
base case. The simulation models for the DEM and for the AM are identical to the TDM,
except that the TDM converter arms are replaced with the converter arms required for the
DEM and AM respectively. This approach ensures that fair comparisons between the
different modelling techniques can be made.
The basic structure of the simulation model and the key parameters are shown in Figure
6.5. This simulation model was built before the MMC-HVDC radial link models described
in Chapters 4 and 5 and is effectively one end of a MMC link with the other MMC
represented by a DC voltage source. The structure, controls and parameters for this model
are very similar to that of the model described in Chapter 4. The key differences are that
feed-forward active and reactive power controllers were used for this model and that this
model uses a larger value of arm reactance. The parameters for the model are given in
Appendix 6A.
Figure 6.5: Basic simulation model structure
6.3 Results
In this section the three models are compared in terms of their accuracy and simulation
speed.
6.3.1 Accuracy
The accuracy of each model is assessed for steady-state and transient events through
conducting a range of typical studies, and is evaluated graphically and numerically by
calculating the Mean Absolute Error (MAE) of the waveforms produced by the DEM and
AM with respect to the TDM. The MAE is normalised to the mean value of the TDM
waveform.
D/Yg
Vn
SCR=3.52
dcV
2
dcV
100km
FDPCM
31-Level MMC
Iabc
L-L Fault
PCC
L-G Fault
DCCB
Is(abc)
Vs(abc)
XT=15%
370kV 410kV
P=1GW Csm=1150µF Larm=85mHVdc=600k
400kV
Idc
Chapter 6 MMC Modelling Techniques
161
6.3.1.1 Steady-state
The steady-state waveforms produced by the models for the converter operating as an
inverter at 1GW are shown in Figure 6.6. The waveforms are virtually identical and this is
confirmed by the very small (<1%) normalised MAE values given in Table 6.1. The
models were re-simulated for the converter operating as an inverter at 500MW and
100MW, and their normalised MAE values are given in Table 6.2 and Table 6.3
respectively. The results generally show that the accuracy of the models decreases as the
operating point decreases. This is especially the case for the phase current and arm current.
At lower operating points, the magnitude of the arm and phase currents are smaller and the
switching noise is more noticeable. It appears to be the case that the effect of this switching
noise on the dominant signal and the models inability to replicate it, is impacting on the
normalised MAE values.
Figure 6.6: Steady-state simulation results for the three models . From top to bottom: (a) Phase A
output voltage, (b) Phase A output current, (c) Phase C upper arm current. (d) Phase A upper arm
mean capacitor voltage
TDM DEM AM
4.8 4.81 4.82 4.8 4.81 4.82 4.8 4.81 4.82
Time (s) Time (s) Time (s)
TDM DEM AM
4.8 4.85 4.9 4.8 4.85 4.9 4.8 4.85 4.9
Time (s) Time (s) Time (s)
Vca
p (
kV
) 21
18.5
Iuc
(kA
)Ia
(kA
)V
a(k
V)
2.2
-2.2
2.2
-2.2
300
-300
Chapter 6 MMC Modelling Techniques
162
1GW Steady-state
Signal DEM error (%) AM error (%)
Va 0.27 0.81
Ia 0.12 0.48
Iua 0.32 0.61
Vcap 0.11 0.21
Table 6.1: Normalised MAE for the DEM and AM waveforms when operating in steady-state at 1GW
500MW Steady-state
Signal DEM error (%) AM error (%)
Va 0.27 0.54
Ia 0.35 0.66
Iua 0.77 1.07
Vcap 0.03 0.07
Table 6.2: Normalised MAE for the DEM and AM waveforms when operating in steady-state at
500MW
100MW Steady-state
Signal DEM error (%) AM error (%)
Va 0.47 0.85
Ia 2.37 2.64
Iua 3.27 4.76
Vcap 0.04 0.05
Table 6.3: Normalised MAE for the DEM and AM waveforms when operating in steady-state at
100MW
6.3.1.2 DC Side Line-to-Line Fault
A DC line-to-line fault is applied at 4.5s to the MMC terminals as shown in Figure 6.5.
The DC circuit breakers (DCCBs) are opened 2ms after the fault is applied so that the DC
voltage sources do not continue to contribute to the fault current. The MMC converter is
blocked at 4.502s, and the AC side circuit breakers are opened at 4.56s. The waveforms
produced by the models are shown in Figure 6.7 and their normalised MAE values are
given in Table 6.4. The waveforms produced by the DEM and the AM are virtually
identical (<1%) and are very similar (<2.5%) to the TDM respectively. An error in the AM
model’s phase voltage is shown in Figure 6.7 at the instance the arm current goes through
zero. This issue occurs because the AM is not able to correctly determine the on/off status
of the SM diodes in a single time-step when the converter is blocked. This issue is
discussed further in Section 6.3.2.
Chapter 6 MMC Modelling Techniques
163
Figure 6.7: DC line-to-line fault applied at 4.5s . From top to bottom: (a) DC current (b) Phase A
output voltage, (c) Phase A upper arm current. (d) Phase A upper arm mean capacitor voltage.
DC Line-to-Line Fault
Signal DEM error (%) AM error (%)
Idc 0.41 2.29
Va 0.22 1.12
Iua 0.51 1.83
Vcap 0.07 0.07
Table 6.4: Normalised mean absolute error for the DEM and AM waveforms for a DC line-to-line
fault.
6.3.1.3 AC Line-to-Ground Fault
A line-to-ground fault is applied to phase A at the PCC for 60ms at 4.5s as shown in Figure
6.5. The waveforms produced by the models are shown in Figure 6.8 and their normalised
MAE values are given in Table 6.5.
TDM DEM AM
4.5 4.6 4.7 4.5 4.6 4.7 4.5 4.6 4.7
Time (s) Time (s) Time (s)
2
Idc
(kA
)V
a(k
V)
300
-300
Iua
(kA
)
4
-8
Vca
p (
kV
)
21
18
-18
Chapter 6 MMC Modelling Techniques
164
Figure 6.8: Line-to-ground fault for phase A applied at 4.5s . (a) Phase A output voltage, (b) Phase A
output current, (c) Phase A upper arm current. (d) Phase A arm current, zoomed.
AC Line-to-Ground Fault
Signal DEM error (%) AM error (%)
Va 0.96 1.76
Ia 0.51 1.37
Iua 3.01 4.34
Iua zoom 11.72 5.14
Table 6.5: Normalised mean absolute error for the DEM and AM waveforms for a line-to-ground AC
With the exception of the phase A upper arm current, the waveforms produced by the
DEM and the AM are virtually identical (<1%) and very similar (<2.5%) to the TDM
respectively. From all of the simulations conducted, the greatest difference between the
three models was found to be in the phase A upper arm current a few cycles after the fault
is cleared when the MMC becomes over-modulated, as highlighted in Figure 6.8d. This
difference lasts for a few cycles and there is no significant difference in the peak current
values for the three models.
TDM DEM AM
4.45 4.6 4.75 4.45 4.6 4.75 4.45 4.6 4.75
Time (s) Time (s) Time (s)
TDM DEM AM
4.6 4.62 4.64 4.6 4.62 4.64 4.6 4.62 4.64
Time (s) Time (s) Time (s)
Va
(kV
)
300
-300
Ia(k
A)
10
-10Iu
a(k
A)
4
-4
Iua
(kA
)
2
-2
Chapter 6 MMC Modelling Techniques
165
6.3.2 AM Simulation Limitation
The AM implemented in this work was found to be unable to fully manage the simulation
case when the converter is blocked, as shown in Figure 6.7. To further demonstrate this
issue, the converter is blocked at 3s when operating as an inverter at 1GW and the Phase A
output voltage for the three models are shown in Figure 6.9. Clearly the converter voltage
for phase A for the AM is different.
Figure 6.9: Phase A output voltage for the three models when the converter is blocked at 3s.
This is an inherent issue with the implementation of the AM and can be illustrated further
at the SM level. A circuit diagram for a blocked SM connected to a voltage through a
resistor is shown in Figure 6.10. A model of this circuit based on the principles of the AM
is shown in Figure 6.11.
The SM current, ISM, is measured in the primary circuit and is used as the current source
reference in the secondary circuit. The SM voltage, VSM, is measured in the secondary
circuit and is used as the voltage source reference in the primary circuit. Each network is
therefore solved at the present time-step based on information from the other network at
the previous time-step.
Figure 6.10: Blocked SM test circuit
TDM DEM AM
2.9 3 3.1 2.9 3 3.1 2.9 3 3.1
Time (s) Time (s) Time (s)
400
-400
Va
(kV
)
Icap
ISM
VSM
Vcap
VS
R
D1
D2
Chapter 6 MMC Modelling Techniques
166
Figure 6.11: Implementation of blocked SM test circuit based on AM principles
Upon model initialisation, VSM=0V, and therefore the SM current flows in the positive
direction causing the upper diode, D1, to conduct and the SM capacitor to charge. Once the
SM capacitor is fully charged, if the voltage source value is reduced, the upper SM diode,
D1, should become reverse biased. Assuming that the SM diodes are ideal, the SM
capacitor voltage should remain constant, Vs=Vsm and Ism=0. However, this is not the case
with the model implemented based on the AM principles. The arm current in the primary
circuit becomes negative because the value of VSM is equal to Vcap which is higher than Vs.
At the next time-step the negative arm current value causes the lower diode in the
secondary circuit to conduct and hence VSM=0. At the next time-step the arm current
becomes equal to /sV R causing the SM capacitor to charge. This behaviour continues for
the remaining simulation time. This limitation is understood to be have now been
addressed by Xu et al., but no details have yet been published.
6.3.3 Simulation Speed
A 5 second simulation was performed for a 16, 31 and 61 level MMC using the three
modelling techniques with a 20µs time-step. The simulations were conducted on a
Microsoft Windows 7 operating system with a 2.5GHz Intel core iq7-2860 processor and
8GB of RAM, running on PSCAD X4. The simulation times are compared in Table 6.6
and in Figure 6.12.
MMC
Levels
Indices TDM DEM AM
16 Time (s) 178 62 107
Ratio - 2.86 1.66
31 Time (s) 949 82 176
Ratio - 11.59 5.39
61 Time (s) 4570 107 329
Ratio - 42.57 13.88
Table 6.6: Comparison of run times for the three models for a 5 second simulation
Icap
ISM
VSMVSMVS
ISM R
Primary Secondary
D1
D2
Vcap
Chapter 6 MMC Modelling Techniques
167
The data shows that the DEM is the fastest and that the TDM is the slowest. It also shows
that as the number of converter levels increases the simulation time for the TDM increases
at a much faster rate than for the DEM and AM models.
It is worth noting that the results in [10] and [11] do appear, in general, to show that their
respective models simulate faster in comparison to the TDM than the results presented in
Table 6.6. The models simulated in this work are, however, more complex than the models
employed in [10] and [11] which may explain the difference.
Figure 6.12: Simulation times of the three models for different MMC levels.
6.3.4 Enhanced AM Model
The AM has the advantage that it is much faster than the TDM without noticeably
sacrificing accuracy for the majority of case studies. It does, however, need to be used with
care when the converter is blocked. In comparison with the DEM, the AM has the
advantage of allowing access to the SM components, but it is slower. This thesis proposes
an enhancement to the AM to improve its speed.
The procedure outlined in [11] to produce the AM, divides the series-connected SMs in
each arm into individual circuits, driven by a current source whose value is equal to the
arm current, as explained in Section 6.1.3. This approach effectively creates a subsystem
for each SM and solves the admittance matrix for each SM separately. Although this
increases the number of steps to the solution, the size of admittance matrices are smaller,
which can lead to a reduced simulation time [10, 11, 110] as shown in Table 6.6.
The simulation speed is affected by the number of steps to the solution and the size of the
admittance matrices. Hence it can be more efficient to group a number of SMs together in
1
10
100
1000
10000
16 31 61
Sim
ula
tio
n d
ura
tio
n (
s)
Number of MMC levels
TDM
DEM
AM
Chapter 6 MMC Modelling Techniques
168
order to reduce the number of steps to the solution, at the expense of larger admittance
matrices. A 5 second simulation was performed for a 31-level MMC with groups of 1
(AM), 5 (AM5), 10 (AM10) and 30 (AM30) SMs. The results given in Table 6.7 show that
it is more efficient to create a sub-network for 5, 10 or 30 SMs rather than to produce a
sub-network for each SM. This is an important result since splitting a simulation model
into a smaller number of sub-networks tends to be less time consuming for the user. It can
also improve the simulation speed and reduce the risk of application instability.
Model Time
(s)
Ratio
AM 176 -
AM5 138 1.28
AM10 139 1.27
AM30 147 1.20
Table 6.7: Comparison of run times for different AM models
The AC fault test scenario (Section 6.3.1.3) was performed using an AM30 model to assess
any change in the models accuracy. The arm current waveforms for the TDM, AM and
AM30 are compared in Figure 6.13 and the normalised MAE values for the AM and AM30
model with respect to the TDM are given in Table 6.8. The results show that there is very
little change.
Figure 6.13: Line-to-ground fault for phase A applied at 4.5s for the TDM, AM and AM30 models.
Signal AM error (%) AM 30 error (%)
Va 1.76 1.74
Iua 4.34 4.42
Table 6.8: Normalised mean absolute error for the AM and AM30 waveforms for a line-to-ground AC
fault.
6.4 Analysis and Recommendations
The three detailed EMT models compared represent the converter’s IGBTs and diodes
using a simple two-state resistance and are therefore not suitable for studies which require
a detailed representation of the power electronic devices, such as the assessment of
TDM AM AM30
4.45 4.6 4.75 4.45 4.6 4.75 4.45 4.6 4.75
Time (s) Time (s) Time (s)
-10
Iua
(kA
)
4
-4
Chapter 6 MMC Modelling Techniques
169
switching losses. The type of model compared is typically employed for control and
protection studies where the converter dynamics are important.
Although the three models compared in this work represent the power electronic devices in
the same way their implementation is different and this has an effect on the accuracy of
their results. A key difference between the TDM and DEM used in this chapter is that the
DEM does not use interpolation, and the key difference between the TDM and AM is that
the solution of the AM is dependent upon information from different sub-networks at the
previous time-step. These are the two most significant reasons why there is a small
difference between the results produced by each model, particularly under transient
conditions. The results in Table 6.8 have shown that even when two models are based on
the same modelling technique, but implemented slightly differently, the simulation results
are not identical. Using the TDM as the benchmark, the DEM was generally found to be
more accurate than the AM, and the AM was also found to produce numerical errors when
the converter is blocked and the arm current changes direction.
The different implementation methods for the three models have a significant impact on
their simulation speed. The results have shown that the DEM is the fastest and that the
TDM is the slowest. The simulation times for the TDM increases significantly more than
for the DEM and the AM as the number of converter levels increase and hence the DEM
and AM modelling techniques have great value when modelling MMCs with a relatively
large number of levels. The results have shown that a model of a 61-level MMC based on
DEM and AM techniques is 43 and 14 times faster than the TDM respectively.
In the DEM, the SM components are not visible to the user and therefore this model is not
suitable for studies which require direct access to the SM components. The TDM and AM
do allow the user access to the SM components and can therefore be easily modified for
the required study.
It is for these reasons that the DEM is considered to be the most suitable model for all
studies which do not require access to the SM components. The AM should be considered
for studies which require access to the SM components and where simulation speed is an
important factor, however great care should be taken if the study requires the converter to
be blocked. The user is also advised to create a sub-network for a number of SMs, rather
than for each SM, as this may reduce implementation time, simulation time and the
Chapter 6 MMC Modelling Techniques
170
possibility of application instability without decreasing accuracy. The TDM is
recommended for studies which require access to the SM components and for the converter
to be blocked. The TDM is also recommended when simulation speed is not an important
factor.
6.5 Conclusion
This chapter has presented the first independent comparison of two previously developed
MMC modelling techniques (AM and DEM). It is has also presented the first independent
verification of the AM, and the first independent verification of the DEM in PSCAD. An
improvement to the AM technique is also described. An MMC-HVDC test system was
developed and the AM and DEM modelling techniques were compared against the TDM
modelling technique in terms of accuracy and simulation speed. The accuracy of the AM
and DEM models was evaluated graphically and numerically for steady-state and transient
studies. These findings have shown that both the AM and DEM modelling techniques offer
a good level of accuracy but that the DEM is generally more accurate than the AM. The
AM and DEM models have been shown to simulate significantly faster than the TDM, and
the DEM is more computationally efficient than the AM. The AM model does however
provide access to SM components (which is not possible with the DEM) and so may be
considered when this is an important factor.
The AM model was found to have limited performance for certain conditions when the
converter is blocked. This finding highlights the importance of this comparative study as it
has highlighted previously unreported shortcomings of discussed modelling techniques. It
was also shown that by modifying the original AM by producing a sub-network for a
number of SMs rather than for a single SM, the simulation run time could be improved.
These results have been used to propose a set of modelling recommendations (Section 6.4)
which summarise the findings of this study and offer technical guidance on state-of-the-art
of detailed MMC modelling.
Chapter 7 HVDC Cable Modelling
171
7 HVDC Cable Modelling
The required fidelity of a VSC-HVDC transmission scheme model is dependent upon the
type of study being performed. Publications have a tendency to discuss the VSC converter
model in-depth whilst often overlooking the cable model. There are publications which
compare VSC models in terms of their accuracy and simulation speed [11, 12], however
there are no such publications for HVDC cable models employed on typical VSC-HVDC
transmission schemes. Furthermore, there is currently a lack of publically available HVDC
cable data which is required to represent the cable.
This chapter aims to address the aforementioned gaps in literature by focusing on the
modelling of HVDC cables for VSC-HVDC transmission schemes. The complex structure
of a submarine XLPE HVDC cable is detailed and parameters to represent a 1GW 300kV
cable are derived from academic and commercial documentation. Types of commercially
available cable models are discussed and four of these models are compared in terms of
their accuracy and simulation speed for a range of studies when employed to represent the
cables in a high fidelity MTDC model. The chapter concludes with a set of cable modelling
recommendations.
7.1 The Cable
A submarine HVDC cable is complex and consists of many concentric layers as shown in
Figure 7.1.
Figure 7.1. Image of a submarine XLPE HVDC cable , modified from [34].
The current carrying conductor may be made of copper or aluminium and the choice is
normally project specific. The insulation layer provides an effective potential barrier
between the conductor and the metallic screen/sheath. In VSC-HVDC schemes the
Chapter 7 HVDC Cable Modelling
172
insulation is typically XLPE because it is less expensive and more robust in comparison to
mass-impregnated cables [111]. The conductor screen and insulation screen are required to
protect the insulation from ridges/grooves which could be caused by extruding the
insulation directly onto the conductor [112]. Any ridges/grooves in the insulation could
result in an enhanced localised electric field stress which would reduce the dielectric
strength of the insulation. The metallic screen/sheath contains the electric field within the
cable as well as carrying fault current to earth [113]. Longitudinal water sealing is
achieved by applying swelling tape, which also absorbs humidity diffusing into the cable
[112, 114]. The inner jacket provides mechanical and corrosion protection and the armour
provides mechanical protection against impacts and abrasions [34]. The armour usually has
a zinc and bitumen coating to protect against corrosion. The outer cover is the final layer of
the cable and prevents the zinc and bitumen coating from scratches which damage their
anti-corrosion protection.
It is worth noting that there is no commercially available cable model which can represent
every individual layer of the cable and account for the stranded nature of the conductors.
In the absence of publically available data for a commercial HVDC cable model, the
geometric and material properties for the layers of the cable, which can be represented in
the cable model, have been estimated and are given in Table 7.1. Only a brief description
of the cable parameters is given here, the reader is referred to Appendix 7A for the full
derivation.
Layer Material Radial
Thickness (mm) Resistivity (Ω/m)
Relative Permittivity
Relative Permeability
Conductor Stranded Copper 24.9 2.2x10-8* 1 1
Conductor
screen
Semi-conductive
polymer
1 - - -
Insulation XLPE 18 - 2.5 [114] 1
Insulator screen Semi-conductive
polymer
1 - - -
Sheath Lead 3 [115] 2.2x10-7
[116]
1 1
Inner Jacket Polyethylene 5 [117] - 2.3 [118] 1
Armour Steel 5 [117] 1.8x10-7
[116]
1 10 [117]
Outer cover Polypropylene 4 [117] - 1.5 [118] 1
Sea-return Sea water/air - 1 - -
*Copper resistivity is typically given as 1.68*10-8Ω/m. It has been increased for the cable model in PSCAD due to the stranded nature of the cable which cannot be taken into account directly in PSCAD.
Table 7.1: Physical data for a 300kV 1GW submarine HVDC cable
Chapter 7 HVDC Cable Modelling
173
The conductor parameters are based on a stranded copper conductor installed in a moderate
climate with close spaced laying [34]. The PSCAD default value for the semi-conducting
screen’s thickness is employed in this work, which is 1mm. There is no official
documentation regarding the insulation thickness of HVDC cables, however a
representative from a leading cable manufacture has stated that a 320kV HVDC cable has
an insulation thickness of about 18mm. The representative also stated that using the
electrical parameters from an AC cable of similar thickness would yield similar results.
This indicates that the relative permittivity of XLPE and DC-XLPE is similar. The relative
permittivity of XLPE is given as 2.5 [114]. The relative permittivity of polypropylene
yarn, which is used for the outer cover, is assumed to be very similar to that of
polypropylene, which is 1.5 [118].
The calculation of the sea-return impedance is complex. In order to calculate the sea-return
impedance accurately, accurate values of sea resistivity, sea-bed resistivity, sea depth,
cable burial depth and frequency are required. A number of these parameters also vary
with the tide and the cable route. PSCAD can only consider the air/sea interface for a
submarine cable and therefore only the sea resistivity and cable depth below the sea
surface are required. The resistivity of sea water varies in the range of 0.25-2Ω/m due to
the temperature and the salinity of the water [119], which makes it difficult to obtain an
accurate value. The sea resistivity and cable depth are assumed to be 1Ω/m and 50m
respectively. Further information on the calculation of the sea-return impedance is given
in Appendix 7A.
The positive and negative cables may be installed in separate trenches, tens of meters apart,
to prevent a ship’s anchor from damaging both cables [111, 120]. This is however
approximately 40% more expensive than installing both cables in a single trench, [111] and
laying both cables close together means that their magnetic fields effectively cancel out.
Unless the cable route has a lot of fishing activity it is therefore more likely that the cables
will be buried in a common trench. It has been assumed that the horizontal distance
between the two cables would therefore be approximately two cable diameters (0.25m).
Sensitivity analysis to assess the impact of each of the cable’s parameters on its
electromagnetic characteristics was conducted, and the results are shown in Appendix 7A.
This sensitivity analysis has shown that small variations in the cable’s parameters do not
have a significant effect on the cable’s transient voltage response.
Chapter 7 HVDC Cable Modelling
174
7.2 Multi-conductor Analysis
The wave equation describes how the voltage and current vary along a transmission line
with time [121]. A submarine cable can be described as a multiphase system consisting of
three-phases (conductor, metallic sheath and armour), hence there are 6 conductors for two
submarine cables. The wave equations in the frequency domain for a transmission line are
given by equations(7.1) and (7.2) [117, 122]:
2
2' '
phase
phase phase phase
d VZ Y V
dx
(7.1)
2
2' '
phase
phase phase phase
d IY Z I
dx
(7.2)
phaseV and phaseI are n x 1 matrices for the voltage and current along the conductors within
the cable respectively, where n is equal to the number of conductors. 'phaseZ and 'phaseY
are n x n matrices for the series impedance per unit length and shunt admittance per unit
length respectively. These are calculated by the method of coaxial loops [123-125].
Equations (7.1) and (7.2) therefore each contain n coupled equations. These coupled
equations in the phase domain can be transformed to decoupled equations in the modal
domain. This allows each equation in the modal domain to be solved as a single-phase line.
The relationship between the phase domain and the modal domain for the voltages and
currents can be described by equations (7.3) and (7.4).
modphase v eV T V (7.3)
modphase i eI T I (7.4)
VT and iT are the voltage and current transformation matrices respectively. Inserting
equation (7.3) into equation (7.1) gives equation (7.5).
2
modmod2
ee
d VV
dx
(7.5)
where:
1
' 'v phase phase vT Z Y T (7.6)
Chapter 7 HVDC Cable Modelling
175
In order to obtain the diagonal matrix, , the values of the voltage transformation matrix,
vT , which diagonalises the ' 'phase phaseZ Y product, must be found. The voltage
transformation matrix is obtained by finding the eigenvectors of ' 'phase phaseZ Y . The
current transformation matrix is obtained by finding the eigenvectors of the product
' 'phase phaseY Z . The decoupled current wave equation in the modal domain is shown by
equation (7.7).
2
modmod2
ee
d II
dx
(7.7)
The wave equation for a single mode can be analysed in a similar manner to the wave
equation for a single-phase line as shown by equation (7.8), where m , is the eigenvalue
for mode m.
2
mod , 2
mod , mod , mod ,2
e m
m e m e m e m
d VV V
dx (7.8)
mod ,e m m m mj (7.9)
The propagation constant, , given by equation (7.9), is a complex quantity; the real part is
called the ‘attenuation constant’, , measured in nepers per unit length, and the imaginary
part is called the ‘phase constant’, , measured in radians per unit length of line. The
propagation constant describes how the voltage or current waveform is attenuated and
delayed travelling from one end to the other end of the line. The modal series impedance
matrix and modal shunt admittance matrix are diagonal matrices and can be obtained from
equations (7.10) and (7.11).
mod' 'T
e i phase iZ T Z T (7.10)
mod' 'T
e v phase vY T Y T (7.11)
The characteristic impedance, Zc, of a single mode can be obtained by equation (7.12).
mod ,
mod ,
mod ,
'
'
e m
e m
e m
ZZc
Y (7.12)
Chapter 7 HVDC Cable Modelling
176
Once the characteristic impedance and propagation constant for each mode have been
calculated, PSCAD can determine how the voltage and current waves will propagate
through the cable.
7.3 HVDC Cable Models
This section gives an overview of the most common types of HVDC cable models
commercially available.
Lumped parameter model - This model lumps the cable’s resistance, R, capacitance, C,
and inductance, L, together to typically form one or more PI-sections. In general lumped
parameter models are only considered appropriate when the wave propagation travel time
is smaller than the time-step. Based on a time-step of 50μs and the maximum velocity of
propagation in a typical XLPE cable, the travel time will only be less than the time-step if
the cable is shorter than about 10km. HVDC cables are normally greater than 50km in
length. However, for completeness a Coupled Equivalent PI-section Model (CEPIM) is
compared in this work.
Bergeron model - The Bergeron model is based on travelling wave theory and represents
the distributed nature of the cable’s LC parameters. The cable’s resistance is lumped
together and divided into three parts, 50% in the middle of the cable and 25% at each end.
This model is similar to the PI-section as it does not account for the frequency dependence
of the cable’s parameters and is therefore essentially a single frequency model.
Frequency-dependent models - Frequency dependent models represent the cable as a
distributed RLC model, which includes the frequency dependency of all parameters. This
type of model requires the cable’s geometry and material properties to be known. There are
two frequency dependent models available in PSCAD; the Frequency Dependent Mode
Model (FDMM) and the Frequency Dependent Phase Model (FDPM). The key difference
between the two models is that the mode model does not represent the frequency
dependent nature of the internal transformation matrix, vT , whereas the phase model does
through direct formulation in the phase domain.
Furthermore, the phase model has an additional feature which is referred to as DC
correction. This enables the model to produce the exact DC response rather than a best
Chapter 7 HVDC Cable Modelling
177
approximation, which is used by the mode model. The FDPM is the most advanced and
accurate time domain line model available [126].
7.4 System Model
To assess the impact of the cable model on typical studies a high fidelity model of a MT
VSC-HVDC system has been developed. A MT HVDC model is used for this study rather
than a radial model because it allows a wider range of cases to be conducted and it is more
appropriate for DC protection studies, which require very accurate representation of the
DC voltage and current. The test model which is shown in Figure 7.2 is described in
Sections 8.1 and 8.3. Based on the work carried out in Chapter 8, the onshore MMCs
employ standard droop control.
Figure 7.2: MTDC test model
The four cable models to be compared are the CEPIM, Bergeron model, FDMM and the
FDPM. The physical properties of the cable, cable positions and sea-return resistivity are
given in Table 7.1. The sheath and armour in the submarine cable are bonded to ground at
both ends of the cable [120] through a small resistor; further information on cable bonding
is given in Appendix 7A. The last metallic layer (armour in a submarine cable), is
eliminated from the impedance matrix. This is often a valid assumption for a submarine
cable, where the armour is a semi-wet construction which allows water to penetrate [117].
The steady-state frequency for the Bergeron model is set to 5 Hz as recommend for DC
studies for this type of model [126] and the CEPIM is created using PSCAD’s in-built
function. The starting frequency for the frequency dependent models is set to 0.1Hz and
XT=15%
Yg/D
MMC2
Vs2(abc)
220kV 370kV
D/Yg
MMC1
Is1(abc)
PCC1XT=15%
370kV 410kV
Vs1(abc)
Idc1
Is2(abc)
AC voltage magnitude and
frequency control
1000MW
Windfarm1
Active and reactive power
control
Rbrak
Vdc2
PCC2
Vn
SCR=3.5
Zn
XT=15%
Yg/D
MMC3
Vs3(abc)
220kV 370kV
D/Yg
MMC4
Is4(abc)
PCC4XT=15%
370kV 410kV
Vs4(abc)
Idc4
Is3(abc)
AC voltage magnitude and
frequency control
1000MW
Windfarm2
Active and reactive power
control
Rbrak
Vdc3
125km DC cable
PCC3
Vn
SCR=3.5
Zn
130km DC cable
200km DC cableIdc2
Idc3
Standard droop control
Standard droop control
Chapter 7 HVDC Cable Modelling
178
equal weighting is given to the entire frequency range. The DC correction function, which
is only available for the FDPM is enabled. All other settings are left at their default value.
7.5 Results
7.5.1 Accuracy
A series of tests were performed to assess the impact of the cable model on the simulation
results for common types of study ranging across a wide frequency range; the results of
which are presented in this section.
The active power generated by windfarm 1 increases from 500MW to 1GW at
approximately 2s and the windfarm power generated by windfarm 2 increases from
500MW to 1GW at 2.25s. At approximately 3s, the circuit breakers for windfarm 1 are
tripped. Figure 7.3 shows that the active power injected into the onshore AC network at
PCC1 is very similar for all the cable models. This plot also shows that greater accuracy
can be obtained for the FDMM by reducing the constant transformation matrix frequency
to 5Hz, as opposed to the default value of 2kHz.
A DC line-to-line fault is applied to the DC terminals of MMC1 at 2.5s. The DC voltage
and current response for the three cable models are shown in Figure 7.4 and Figure 7.5
respectively. The CEPIM shows virtually no propagation delay as expected, whilst the
propagation delay for the Bergeron model is approximately twice that of the frequency
dependent cable models due to the modal velocities for the cable being calculated at the
steady-state frequency. The attenuation for the two frequency domain models is different
due to the frequency dependent nature of the transformation matrix. MT protection
schemes are required to detect a DC fault, identify the faulty cable and issue the trip
command to the appropriate HVDC breakers within approximately 1-2ms, as described in
Chapter 3. MT protection strategies are therefore highly sensitive to the local DC voltage
and current measurements and hence very accurate cable models are required.
A three-phase line-to-ground fault is applied to PCC1 at 2s for 140ms. The active power
injected to the onshore network from MMC1 is shown in Figure 7.6. The responses
produced by the CEPIM, FDMM and the FDPM are very similar, whilst the Bergeron
model’s response is very different. This is because the Bergeron model is unable to
Chapter 7 HVDC Cable Modelling
179
accurately reproduce the DC voltage response and is adversely interacting with the DC
braking resistors as shown in Figure 7.7.
Figure 7.3: Onshore AC power response to windfarm power variations
Figure 7.4: DC voltage response at MMC2 for a DC line-to-line fault at the terminals of MMC1
Figure 7.5: DC current response at MMC2 for a DC line-to-line fault at the terminals of MMC1
0
100
200
300
400
500
600
700
800
900
1000
1.80 2.00 2.20 2.40 2.60 2.80 3.00 3.20 3.40
Po
we
r (M
W)
Time (s)
P1-CEPIM
P1-Bergeron
P1-FDMM
P1-FDPM
P1-FDMM T=5Hz
0
100
200
300
400
500
600
700
2.490 2.494 2.498 2.502 2.506 2.510
Vo
ltag
e (
kV)
Time (s)
Vdc2-CEPIM
Vdc2-Bergeron
Vdc2-FDMM
Vdc2-FDPM
0
2
4
6
8
10
12
14
16
2.490 2.494 2.498 2.502 2.506 2.510
Cu
rre
nt
(kA
)
Time (s)
Idc2-CEPIM
Idc2-Bergeron
Idc2-FDMM
Idc2-FDPM
P*WF1=1GW
P*WF2=1GW
Chapter 7 HVDC Cable Modelling
180
Figure 7.6: AC power response at PCC1 for a three-phase line-to-ground fault at PCC1.
Figure 7.7: DC voltage response at MMC1 for a three-phase line-to-ground fault at PCC1 (CEPIM
trace is behind FDMM and FDPM traces).
7.5.2 Simulation Speed
A three second simulation was performed for the four models using a 20µs time-step. The
simulations were conducted on a Microsoft Windows 7 operating system with a 2.5GHz
Intel core iq7-2860 processor and 8GB of RAM, running on PSCAD X4. The simulation
times for all three of the travelling wave models were approximately 260s, whilst the
simulation time for the CEPIM was approximately 375s. This is predominately because the
travelling wave models decouple the electric networks, which can result in reduced
simulation times.
7.6 Conclusion
The results presented in this chapter have shown that the choice of cable model can have a
significant impact on the overall model’s response for typical VSC-HVDC studies. The
results have also shown that the travelling wave cable model’s impact on the
computational simulation time is insignificant, particularly when the overall model is
-600
-400
-200
0
200
400
600
800
1000
1200
1.70 1.90 2.10 2.30 2.50
Po
we
r (M
W)
Time (s)
P1-CEPIM
P1-Bergeron
P1-FDMM
P1-FDPM
0
100
200
300
400
500
600
700
800
900
1.70 1.90 2.10 2.30 2.50
Vo
ltag
e (
kV)
Time (s)
Vdc2-CEPIM
Vdc2-Bergeron
Vdc2-FDMM
Vdc2-FDPM
Chapter 7 HVDC Cable Modelling
181
relatively complex. It is therefore recommended that the FDPM should be the default
model of choice for typical VSC-HVDC studies.
In the case of simple VSC-HVDC models, the choice of cable model may have a more
significant impact on the computational simulation time. The FDMM may therefore be
more suitable in this instance, providing that a very accurate representation of the DC cable
dynamics is not required. The Bergeron model or the CEPIM can also be employed when
computational simulation time is an issue and where accurate representation of the DC
cable outside of the steady-state frequency of the cable, is not required.
Chapter 8 MTDC MMC Modelling
182
8 MTDC MMC Modelling
At the time of writing almost all operational windfarms employing VSC-HVDC
connections are point-to-point (radial). Numerous potential benefits have however been
identified for interconnecting multiple offshore windfarms using HVDC cables (co-
ordinated design). These benefits include a reduction in the volume of assets installed
offshore and improved operational flexibility and network security [1]. The control of a
MT DC system does however require additional levels of complexity in comparison to the
control of a radial system.
Numerous studies have been carried out to assess the performance of MTDC control
strategies [127-129]. These studies have however employed simplified MTDC system
models, which cannot accurately represent the MMC dynamics and that may have an
impact on the MTDC system’s response to transient events, such as the loss of a converter.
The simple models are also unable to simulate the MMC arm currents and SM capacitor
voltages which are critical to ensuring that the converter is operating within safe limits
during transient events.
In this chapter a four-terminal high fidelity MTDC model for the connection of two 1GW
Round 3 offshore windfarms is developed. This model is based on a potential scenario
outlined in ODIS and it is used to investigate the performance of selected MTDC control
strategies for different scenarios.
8.1 MTDC Test Topology
National Grid has developed co-ordinated designs for large offshore windfarms, where a
benefit can be identified. The primary areas of where the co-ordinated approach has been
proposed are the Crown Estate Round 3 zones of the Firth of Forth, Dogger Bank,
Hornsea, East Anglia and the Irish Sea. Figure 8.1 shows the offshore HVDC cable
connections for Dogger Bank and Hornsea for one of the potential scenarios outlined by
National Grid [130].
Chapter 8 MTDC MMC Modelling
183
Figure 8.1: Accelerated growth 2030 transmission system scenario – potential connection diagram ,
modified from [9]
The MTDC system topology used in this work for the investigation of MTDC control
strategies is based upon a sub-section of this scenario. This topology represents a 1GW
radial VSC-HVDC link between Dogger Bank and the north east of England, and a 1GW
radial VSC-HVDC link between Hornsea and the east midlands, with a 1GW HVDC cable
connecting the two offshore converters as shown in Figure 8.2. The HVDC cable lengths
have been estimated from the information given in ODIS.
Figure 8.2: MTDC test topology
1 G W W in d fa rm -
D o g g e r B a n k
2 0 0 k m
V S C 2 V S C 1
N o rth E a s t
E n g la n d
1 G W W in d fa rm -
H o rn s e a
S h o re
V S C 3 V S C 4
1 3 0 k m
1 2 5 k m
E a s t M id la n d s
A C G r id
Chapter 8 MTDC MMC Modelling
184
8.2 MTDC Control Methods
In a point-to-point VSC-HVDC link employed for the connection of an offshore windfarm,
the offshore converter controls the connected windfarm’s AC voltage magnitude and
frequency, and the onshore converter controls the DC link voltage, as discussed in Chapter
5. The converter controlling the DC link voltage is often referred to as the DC slack bus. In
a MTDC network, such as the one shown in Figure 8.2, the offshore converters can be
controlled in the same way as they are in a point-to-point link. The regulation of the DC
link voltage for a MTDC system is however more complex than in a radial system.
A review of MTDC control methods is given in [131, 132]. Generally speaking these
methods can be categorised as centralised DC slack bus, voltage margin control, droop
control or a combination of the aforementioned control methods. In this chapter these
control methods are discussed with reference to the MTDC topology shown in Figure 8.2.
8.2.1 Centralised DC Slack Bus
Employing a centralised DC slack bus, one of the onshore converters operates in DC
voltage control (DC slack bus) whilst the other onshore converter operates in constant
power control. The DC slack bus converter must therefore supply/absorb the deficit/surplus
of active power to ensure that the DC voltage is regulated. If however, the required active
power is outside of the DC slack bus converter’s capability then it will no longer be able to
control the DC voltage. The converter and its connected AC network must therefore be
sufficiently rated to compensate for the total power variations of the other converters [127,
132]. Furthermore, in the event of a fault which diminishes the converter’s power
capability, the system may become unstable. It is for these reasons that a centralised DC
slack bus is generally not considered suitable, especially for large MTDC systems.
8.2.2 Voltage Margin Control
Applying the method of voltage margin control to the MTDC topology, one of the onshore
converters operates as a DC slack bus whilst the other operates in what is referred to as
voltage margin control. The voltage-current characteristics for the two converters are
shown in Figure 8.3 and the implementation of the voltage margin controller used in this
work is shown in Figure 8.4. The converter operating in voltage margin control effectively
operates in constant power control providing that its local DC link voltage is within pre-set
limits (Vdc-low<Vdc<Vdc-high). If the DC link voltage exceeds the pre-set limits then the
Chapter 8 MTDC MMC Modelling
185
converter operates in DC link voltage control mode. This means that if the converter
operating as the DC slack bus is unable to control the DC link voltage, the other onshore
converter will take control. Voltage margin control therefore improves the reliability of the
system in comparison to a centralised DC slack bus. There are however the following
limitations of employing voltage margin control [131, 132]:
Only one converter is responsible for regulating the DC voltage at a time.
The voltage margin must be carefully selected to avoid undesirable interaction
between the converters whilst minimising losses and maximising the systems VA
rating.
Transitions from one voltage level to another may occur abruptly leading to
additional system stress.
Figure 8.3: Standard Vdc-Idc characteristic; DC slack bus (Left) voltage margin control (Right)
Figure 8.4: Implementation of the voltage margin controller
8.2.3 Droop Control
Droop control can be employed to minimise some of the aforementioned limitations of
voltage margin control. In droop control more than one converter is able to participate in
regulating the DC voltage and therefore the burden of continuously balancing the system’s
power flow is not placed upon a single converter. A standard voltage-current droop
Vdc
Idc-maxIdc-min
Vdc
Idc-maxIdc-min
V
Vdc-High
Vdc-Low
Vdc*
Idc*Inv InvRec 0 0Rec
+-
P*
P
PI x(-1)
+-
Vdc-High*
Vdc
PI
+-
Vdc-Low*PI x(-1)
Idmax
Idmin
Id*
Vdc
d-axis current
controller
Chapter 8 MTDC MMC Modelling
186
characteristic is shown in Figure 8.5. The gradient of the droop slope determines the
converter’s current response to a change in the DC voltage; the steeper the gradient the
smaller the response. The converter operates in current limit mode when the DC voltage
thresholds are reached.
Figure 8.5: Standard Vdc-Idc characteristic for voltage droop control
The implementation of the droop controller used in this work is shown in Figure 8.6.
Ideally the upper and lower voltage limits (Vdc-High and Vdc-Low) are very similar to the no-
load voltage, Vdc-NL, however this requires large variations in the current controller’s set-
point, Id*, for relatively small deviations in the DC link voltage. This is an issue because
the high bandwidth current controller will respond abruptly to the switching noise in the
DC voltage measurement. The droop gain therefore needs to be selected with care.
Figure 8.6: Implementation of voltage droop controller
The standard droop characteristic can be modified, so that the converter acts as a DC slack
bus within pre-set voltage limits and then as a droop controller outside those voltage limits
as shown in Figure 8.7. This type of droop controller is effectively a hybrid between a
voltage margin controller and a standard droop controller. This type of characteristic is
sometimes referred to as a voltage droop with dead band [131].
Vdc
Idc-maxIdc-min
Vdc-NL
InvRec
Vdc-Low
Vdc-High
0
+-
Kdroop
Vdc-NL
Vdc
Id* d-axis current
controller
Idmax
Idmin
Chapter 8 MTDC MMC Modelling
187
Figure 8.7: Vdc-Idc characteristic for voltage droop control with dead band
8.2.4 Control Methods Investigated
The onshore converters could operate in various control modes, including DC voltage
control, constant power control, voltage margin control, standard DC droop control and
voltage droop control with dead band. The only limitation is that at least one converter
must regulate the DC voltage. A plethora of possible control options therefore exist. The
centralised DC slack bus control, voltage margin control and droop control methods are
investigated in this chapter with the control permutations shown in Table 8.1.
Control Method MMC1 control mode MMC4 control mode Comments
Centralised DC slack bus
DC voltage & AC voltage magnitude
Active power & reactive power
P*=500MW
Voltage margin control
DC voltage & AC voltage magnitude
Voltage margin & reactive power
Vdc-High=620kV, Vdc-
Low=580kV
Droop control Standard droop & AC
voltage magnitude Standard droop &
reactive power Droop gain =- 0.1
Table 8.1: Control methods investigated
8.3 MTDC System Model
The simplified system diagram for the MTDC model is shown in Figure 8.8. The structure,
parameters and controls for the four MMCs, onshore AC networks, offshore AC networks
and the DC cables are described in Chapter 4 and Chapter 7.
Vdc
Idc-maxIdc-min InvRec
Vdc-Low
Vdc-High
0
Chapter 8 MTDC MMC Modelling
188
Figure 8.8: MTDC test model
8.3.1 Windfarm Power Variations
At 1s both windfarms are each ordered to inject 500MW of active power. The power order
for windfarm 2 is increased to 1GW at 2s and the power order for windfarm 1 is increased
to 1GW at 3s.
Figure 8.9 shows the system’s response to the wind power variations when employing a
centralised DC bus. MMC4 is operated in constant power control, with a power order of
500MW, and MMC1 is operated as the DC slack bus. At approximately 2s, the DC slack
bus exports the increase in windfarm power to the onshore AC grid and therefore the DC
voltage is maintained to close to its nominal value. At 3s, however, the DC slack bus is
unable to export all of the additional increase in windfarm power due to the converter
reaching its valve current limit. This results in a rise in the DC link voltage to
approximately 1.1p.u. (660kV), at which point the DC braking resistors are activated to
dissipate the excess wind energy. In order for the DC slack bus to regain control of the DC
voltage, the power order for MMC4 must be increased or the windfarm power must be
curtailed.
The system’s response for operating MMC4 in voltage margin control and MMC1 as a DC
slack bus is shown in Figure 8.10. The system’s response to the increase in wind power at
2s is effectively the same as the system employing a centralised slack bus. This is because
the DC slack bus is able to export the increase in wind power from windfarm 2 and
therefore the upper voltage margin control limit is not reached. The upper voltage margin
limit is however reached at approximately 3.2s due to the increase in wind power from
XT=15%
Yg/D
MMC2
Vs2(abc)
220kV 370kV
D/Yg
MMC1
Is1(abc)
PCC1XT=15%
370kV 410kV
Vs1(abc)
Idc1
Is2(abc)
AC voltage magnitude and
frequency control
1000MW
Windfarm1
Active and reactive power
control
Rbrak
Vdc2
PCC2
Vn
SCR=3.5
Zn
XT=15%
Yg/D
MMC3
Vs3(abc)
220kV 370kV
D/Yg
MMC4
Is4(abc)
PCC4XT=15%
370kV 410kV
Vs4(abc)
Idc4
Is3(abc)
AC voltage magnitude and
frequency control
1000MW
Windfarm2
Active and reactive power
control
Rbrak
Vdc3
125km DC cable
PCC3
Vn
SCR=3.5
Zn
130km DC cable
200km DC cableIdc2
Idc3
Chapter 8 MTDC MMC Modelling
189
windfarm 1 and the inability of the DC slack bus to export it. This causes MMC4 to
operate in DC voltage control as opposed to constant power control. The DC voltage
control reference is equal to the upper voltage margin limit (620kV). This simulation result
shows that the use of voltage margin control enables the DC link voltage to be controlled
without the need for communications or the curtailment of wind power.
Figure 8.11 shows the system’s response to wind power variations when MMC1 and
MMC4 are operating in standard droop control with the same droop characteristic. This
figure shows that the onshore converters share the variations in wind power and therefore
the burden of continuously balancing the system’s power flow is placed on more than one
converter. The droop controller is a proportional only controller and therefore some steady-
state error is introduced in the DC voltage. This is a disadvantage in comparison to the
centralised DC slack bus control strategy and the voltage margin control strategy (when
operating within the pre-set voltage limits). The steady-state voltage error can however be
minimised via modifying the droop characteristic via a dispatch centre.
Figure 8.9: MTDC system response to windpower variations when employing a centralised DC slack
bus ; x axis – time(s)
P*WF2=1GW P*WF1=1GW
Chapter 8 MTDC MMC Modelling
190
Figure 8.10: MTDC system response to windpower variations when employing voltage margin control
bus ; x axis – time(s)
Figure 8.11: MTDC system response to windpower variations when employing standard droop control
bus ; x axis – time(s)
8.3.2 Three-phase Line-to-Ground Fault at PCC1
Windfarm 1 and windfarm 2 are ordered to inject 500MW and 1GW respectively. A three-
phase symmetrical fault is applied at PCC1 (Figure 8.8) for 140ms starting at 2s. MMC1 is
therefore unable to export any significant quantity of active power during the fault.
P*WF2=1GW
P*WF1=1GW
P*WF2=1GW P*WF1=1GW
Chapter 8 MTDC MMC Modelling
191
The system’s responses to this fault for centralised DC bus control, voltage margin control
and droop control are shown in Figure 8.12, Figure 8.13 and Figure 8.14 respectively.
These figures show that the three control strategies are able to ride-through the fault in
compliance with the GB grid code and without exceeding the maximum instantaneous arm
current limit of 3kA or the maximum SM overvoltage limit of 27kV. The system’s
response to the fault does however differ depending on the control strategy employed.
During the fault for the system employing the DC centralised bus, there is a surplus of
approximately 1GW which must be dissipated by the DC braking resistor to prevent
uncontrollable DC voltage rise. When employing voltage margin control or droop control,
MMC4 increases its exported power in response to the increase in DC link voltage. The
surplus of active power is therefore reduced to approximately 500MW, which again is
dissipated by the DC braking resistor. If the total windfarm power was within the power
capability of MMC4 (≈1GW), then the DC voltage could be controlled without the use of
the DC braking resistor when employing either voltage margin control or droop control.
Comparing Figure 8.13 and Figure 8.14, it is clear that the power response upon fault
clearance is more oscillatory for voltage margin control than for droop control.
Chapter 8 MTDC MMC Modelling
192
Figure 8.12: MTDC system response to a three-phase to ground fault when employing a centralised
DC slack bus ; arm currents are for MMC1 and capacitor voltages are for the upper arm of phase A
for MMC1; x axis – time(s)
Chapter 8 MTDC MMC Modelling
193
Figure 8.13: MTDC system response to a three-phase to ground fault when employing voltage margin
control ; arm currents are for MMC1 and capacitor voltages are for the upper arm of phase A for
MMC1; x axis – time(s)
Chapter 8 MTDC MMC Modelling
194
Figure 8.14: MTDC system response to a three-phase to ground fault when employing standard droop
control ; arm currents are for MMC1 and capacitor voltages are for the upper arm of phase A for
MMC1; x axis – time(s)
The phase A upper arm current waveforms from Figure 8.12-Figure 8.14 are plotted on the
same graph in Figure 8.15. This figure shows the significant impact that the MTDC control
methods can have on the converter’s arm currents. Table 8.2 shows that the maximum
current value experienced by the converter arm when employing DC slack bus control is
75% higher than for droop control. This result highlights the importance of modelling
MMC converters in detail when comparing MT control methods.
Chapter 8 MTDC MMC Modelling
195
Figure 8.15: Impact of MTDC control methods on the upper arm current for phase A of MMC1 for a
three-phase to ground fault
Indices Droop Margin Slack Iua max (kA) 1.41 2.14 2.47
Ratio - 1.52 1.75 Iua rms (kA) 0.71 0.99 1.04
Ratio - 1.41 1.47
Table 8.2: Maximum and rms values for Figure 8.15.
8.3.3 Converter Disconnection
In this section, the control strategies’ responses to the disconnection of an offshore
converter and an onshore converter are investigated. The power order for windfarm 1 and
windfarm 2 are 1GW and 500MW respectively. At 2s MMC3 is blocked and at 3s MMC1
is blocked. Their AC circuit breakers are tripped three cycles after their respective blocking
commands. The system’s response for a centralised DC bus, voltage margin control and
droop control are shown in Figure 8.16, Figure 8.17 and Figure 8.18 respectively.
-2
-1.5
-1
-0.5
0
0.5
1
1.5
2
2.5
2.24 2.26 2.28 2.30 2.32 2.34 2.36 2.38 2.40 2.42 2.44Cu
rre
nt
(kA
)
Time (s)
Droop
Margin
Slack
Chapter 8 MTDC MMC Modelling
196
Figure 8.16: MTDC response for MMC3 disconnected at approximately 2s and for MMC1
disconnected at approximately 3s when employing a centralised DC slack bus ; arm currents are for
MMC1 and capacitor voltages are for the upper arm of phase A for MMC1; x axis – time(s)
Chapter 8 MTDC MMC Modelling
197
Figure 8.17: MTDC response for MMC3 disconnected at approximately 2s and for MMC1
disconnected at approximately 3s when employing voltage margin control ; arm currents are for
MMC1 and capacitor voltages are for the upper arm of phase A for MMC1; x axis – time(s)
Chapter 8 MTDC MMC Modelling
198
Figure 8.18: MTDC response for MMC3 disconnected at approximately 2s and for MMC1
disconnected at approximately 3s when employing standard droop control ; arm currents are for
MMC1 and capacitor voltages are for the upper arm of phase A for MMC1; x axis – time(s)
The centralised DC slack bus is able to satisfactorily maintain control of the DC voltage
during the disconnection of the offshore converter (MMC3); however, the DC voltage
becomes uncontrollable when the onshore converter (MMC1), which is operating as the
DC slack bus, is disconnected. The voltage margin control method and the droop control
method maintain satisfactory control of the DC voltage for the disconnection of MMC3
and MMC1. The active power response and DC voltage response for the disconnection of
Chapter 8 MTDC MMC Modelling
199
MMC1 and MMC3 is more oscillatory for the voltage margin controller than for the droop
line controller.
8.4 Conclusion
In this chapter a MTDC topology based on a segment of a potential connection diagram for
the UK’s Round 3 windfarms, as outlined in National Grid’s 10 year statement, has been
developed. The performance of three MTDC control methods, namely, centralised DC
slack bus, voltage margin control and droop control, were investigated using a detailed
MTDC system model. The controllers’ response to wind power variations, onshore AC
faults and the disconnection of an offshore and an onshore converter were simulated.
The simulation results show that the use of a DC centralised bus is not suitable for MTDC
systems as the DC voltage becomes uncontrollable if the imbalance in active power is
outside of the power capability of the DC slack bus, or if the slack bus converter is
disconnected from the system. The voltage margin control method and the droop control
method were shown to be able to respond to variations in wind power, to ride-through
close-up three-phase AC faults in compliance with the GB grid code, and to maintain grid
stability after the disconnection of a converter without exceeding the converter ratings. The
droop controller shares power flow more evenly than the voltage margin controller and its
response to transient events was shown to be less oscillatory with lower arm currents. The
simulation results in this chapter therefore show that the droop controller offers the best
overall performance.
A key contribution of this chapter was to show that the MT control systems can have a
significant impact on the internal MMC quantities, which highlights the importance of high
fidelity MMC models when comparing MT control methods.
Chapter 9 Conclusion and Future Work
200
9 Conclusion and Future Work
9.1 Conclusion
This thesis identified factors which may have a negative impact on the reliability of VSC-
HVDC systems and which therefore required further research. These factors broadly fit
into three categories; availability analysis, HVDC protection and VSC-HVDC system
modelling. To address these factors, the following objectives were identified:
1. Conduct an availability study for a radial VSC-HVDC system and identify the key
components which affect the system’s overall availability.
2. Identify the key issues in the development of a HVDC breaker and present potential
solutions.
3. Develop a high fidelity EMT model of a radial VSC-HVDC system employed for
the connection of a typical Round 3 windfarm and compare the leading MMC
modelling techniques.
4. Develop a high fidelity EMT model of a MT VSC-HVDC system employed for the
connection of a typical Round 3 windfarm and compare the leading cable
modelling techniques.
All objectives have been met in this thesis, and in some areas further work has been
undertaken. The following sub-sections provide further details of the conclusions made in
the three main areas.
9.1.1 Availability Analysis
The expected availability of the VSC-HVDC systems which connect the Round 3 offshore
windfarms is a key factor in determining if the Round 3 windfarms are technically and
economically viable. However, at the time of investigation there were no publications
which estimated the expected availability of these systems.
In this thesis an availability model of a radial VSC-HVDC system for the connection of a
typical Round 3 windfarm was developed and analysed using reliability indices derived
from academic papers and industrial documentation. The analysis of this model showed
Chapter 9 Conclusion and Future Work
201
that the energy availability of the system due to forced outages was approximately 96.5%.
It also revealed that the DC submarine cable has the greatest impact on the availability of
the transmission scheme, which highlights the importance of protecting the DC cables.
An availability model for a MTDC network was also developed and analysed for different
levels of additional capacity in the transmission paths back to shore. This analysis showed
that the availability of the MTDC network is highly dependent upon the rating of the
network’s paths back to shore and that grids with additional capacity had a higher
availability than equivalent radial systems. Furthermore, a cost-benefit analysis was
conducted that showed that the HVDC grids with additional capacity could provide a more
cost-effective solution for the connection of offshore windfarms due to the improved
energy availability figures.
This work was published at an international conference and has contributed to Cigre
Working Group B4-60 “Designing HVDC Grids for Optimal Reliability and Availability
Performance”. The reliability indices for the VSC-HVDC components derived in this
thesis have also been published in: G. Migliavacca “Advanced Technologies for Future
Transmission Grids”, Springer, 2012.
9.1.2 HVDC Protection
In order for a large HVDC grid to be technically and commercially viable, the ability to
isolate parts of the grid due to a fault, or to perform maintenance without de-energising the
entire grid, must be achieved. This requires HVDC circuit breakers; however at the time of
investigation these were not commercially available.
In this thesis the requirements for a HVDC circuit breaker have been identified and
potential breaker topologies, including one developed as part of this thesis, have been
described and compared. The comparative analysis concluded that arc-less hybrid circuit
breakers with an auxiliary circuit breaker are the most suitable type of HVDC circuit
breaker for the protection of a HVDC grid. This is predominantly due to their ability to
achieve the best balance between operation speed and on-state losses. This type of circuit
breaker is being developed commercially and is expected to be available for order in the
next one to three years, with delivery in the next five years.
This thesis also outlined the key requirements of a DC cable protection system for a
HVDC grid and reviewed potential protection strategies to identify and locate a faulty
Chapter 9 Conclusion and Future Work
202
cable. The review concluded that a protection strategy will most likely be developed based
on a combination of traditional techniques used in conjunction with modern techniques for
optimum detection and selection.
This work resulted in a UK patent application being filed for a hybrid HVDC breaker and
has enabled contributions to be made to Cigre Working Group B4-57 ‘Guide for the
Development of Models for HVDC Converters in a HVDC Grid’. This work has also led to
further work being funded (two PhD students) by National Grid, “DC Circuit Breaker
Technologies” (2012-2016).
9.1.3 VSC-HVDC System Modelling
Simulation models are a vital tool in the research and development of VSC-HVDC
systems. Highly accurate models are required in order to give a high degree of confidence
in the simulation results and to therefore ensure that the system operates in the expected
way.
The use of MMC converters in VSC-HVDC systems has presented a number of modelling
challenges. Applying traditional modelling techniques to MMC VSC-HVDC systems is
computationally intensive and virtually unmanageable in many cases, which has led to the
development of new modelling techniques. The published literature validating these
techniques are, however, very limited in some areas, and non-existent in others.
In this thesis, the three leading detailed MMC modelling techniques, the TDM, the DEM
and the AM, were compared in terms of their accuracy and simulation speed. An MMC
VSC-HVDC test simulation model was developed in PSCAD for this study. The study
found that both the AM and DEM modelling techniques offer a good level of accuracy but
that the DEM is generally more accurate than the AM. The AM and DEM models were
also shown to simulate significantly faster than the TDM, and the DEM was found to be
more computationally efficient than the AM. Furthermore, the AM model was found to
have limited performance for certain conditions when the converter is blocked and it was
also shown that by modifying the original AM the simulation run time could be improved.
The findings of this study were used to propose a set of modelling recommendations which
offer technical guidance on the state-of-the-art of detailed MMC modelling.
The EMT simulation model for the comparison of MMC modelling techniques was
developed further using the DEM modelling technique to produce a detailed EMT model
Chapter 9 Conclusion and Future Work
203
for a radial VSC-HVDC link for the connection of a typical Round 3 windfarm. Another
radial model was also developed for the interconnection of two active networks. The
simulation results produced by these models were verified against the theory outlined in
the thesis. These models thus provide a high fidelity version of a component level MMC
model with detailed parameters and control and can therefore act as a benchmark for lower
fidelity models. As an example, the detailed MMC-HVDC model developed in this thesis
was used for the verification of an averaged value VSC-HVDC model, which enabled this
lower fidelity model to be used for a comprehensive investigation into the limitations
imposed on active power controllers.
MMC VSC-HVDC systems are set to become a key component of the UK’s power system
and their ability to ride-through AC system faults is therefore of great importance, however
publications in this area were found to be very limited. The models developed in this thesis
were used to investigate the links’ ability to meet the GB grid code requirements for
disturbances in the AC grid. The results show that for the tests conducted the models were
able to meet AC fault ride-through requirements and reactive power requirements, as well
as to comply with the IEEE 519 THD voltage harmonic limits. Furthermore, the results
showed that the use of a variable limit DC link voltage controller, proposed as part of this
thesis, can improve the system’s fault recovery response. The differences between the
control and protection of the interconnector, in comparison to the link employed for the
connection of a windfarm, were also highlighted.
The potential development of HVDC grids has led to the need to produce highly accurate
EMT grid models which are valid for a range of studies. The issue of accuracy vs.
computational efficiency is of greater concern for grids than radial systems, due to the
increased size of the model. In addition to the MMC models, cable models are the other
main DC component which may have a significant impact on the overall model’s
simulation results and simulation time. The fidelity of cable models is of particular
importance for HVDC grids due to the need to locate the faulty section of the grid within
approximately 1-2ms, which requires accurate representation of the DC quantities.
Publications regarding the impact of different cable models in terms of their accuracy and
speed for typical VSC-HVDC studies are however very limited.
In this thesis a four-terminal EMT VSC-HVDC model was developed based on a
subsection of a potential scenario outlined in National Grid’s 10 year statement. This
Chapter 9 Conclusion and Future Work
204
model was used to compare a coupled equivalent PI model, Bergeron model, frequency
dependent mode model and a frequency dependent phase model in terms of their accuracy
and simulation speed for a wide range of studies. The results showed that the choice of
cable model can have a significant impact on the overall model’s response for typical
VSC-HVDC studies and that the traveling wave cable model’s impact on the
computational simulation time is insignificant, particularly when the overall model is
relatively complex. The findings of this study were used to propose a set of modelling
recommendations which offer technical guidance on HVDC cable modelling.
Numerous studies have been carried out to assess the performance of MTDC control
strategies. These studies have however employed simplified MTDC system models, which
cannot accurately represent the MMC dynamics and which may have an impact on the
MTDC system’s response to transient events, such as the loss of a converter. The
simplified models are also unable to simulate the MMC arm currents and SM capacitor
voltages which are critical in ensuring that the converter is operating within safe limits
during transient events. The performance of three MTDC control methods, namely,
centralised DC slack bus, voltage margin control and droop control, were investigated
using the developed detailed MTDC system model for a range of studies. The key
contribution of this work was to show that the MT control systems can have a significant
impact on the internal MMC quantities, which highlights the importance of high fidelity
MMC models when comparing MT control methods.
This work resulted in two journal papers and the publication of two international
conference papers and has enabled contributions to be made to Cigre Working Group B4-
57 “Guide for the Development of Models for HVDC Converters in a HVDC Grid”.
9.2 Future Work
Recommendations for future work in the three main areas investigated in this thesis are
presented in the following subsections. This work could potentially improve the reliability
of VSC-HVDC systems.
9.2.1 Availability Analysis
Availability analysis, independent of methodology, can only ever be as good as the input
data. Unfortunately there are no true failure statistics for VSC-HVDC components
available in the public domain and therefore many of the reliability indices used for this
Chapter 9 Conclusion and Future Work
205
thesis were estimated based on data from LCC-HVDC schemes. However, the author
understands that the VSC-HVDC owners are now beginning to report failure statistics to
the Cigre World HVDC reliability survey. It would therefore be very useful to repeat these
studies using this data once it is available in the public domain.
Variations in wind energy were not taken into consideration for the availability analysis
contained in this thesis. The amount and location of the input energy for a HVDC grid is a
key factor in determining the actual amount of energy lost due to a system failure.
Incorporating the variations in wind farm energy into the availability analysis would be a
useful contribution to the field.
9.2.2 HVDC Breakers
In this thesis a review of HVDC circuit breakers was carried out and a patent application
for an arc-less hybrid breaker with auxiliary switch was filed. The review concluded that
arc-less hybrid circuit breakers with an auxiliary circuit breaker are currently the most
suitable type of HVDC circuit breaker for the protection of a HVDC grid and that this type
of breaker is likely to be commercially available for order in the next one to three years.
The key component which determines the breaking time for this type of breaker is the
opening speed of the fast mechanical switch. However, the performance of mechanical
switches received little attention in this thesis due to the lack of publications in this area.
Further research into the state-of-the-art of mechanical switches and their limitations is
therefore required.
One of the key parameters which determines how fast the circuit breaker is required to
open is the fault current rate of rise. Increasing the values of DC reactance and installing
other fault current limiting devices, such as superconducting fault current limiters, can
reduce the fault current rate of rise. However, the potential implications that the DC
reactance value and fault current limiting devices can have on system stability and breaker
footprint are not well documented and therefore further research is required.
This thesis reviewed potential protection strategies for the protection of a HVDC grid. It
concluded that although some good preliminary research has been carried out substantially
more is required before a HVDC protection strategy could demonstrate all of the necessary
requirements.
Chapter 9 Conclusion and Future Work
206
9.2.3 MMC Modelling
The focus of this thesis has been on the MMC-HVDC system and therefore high fidelity
models of the converters and the DC system have been developed. However for a more
complete model, the simplified models for the AC systems could be replaced with more
detailed models. Further work to incorporate more detailed models of the windfarm, AC
system and transformer would be a useful contribution. Incorporating such models is likely
to result in impractical simulation durations and therefore the use of variable rate and
hybrid simulation packages could be investigated.
Results presented in this thesis showed that the MT control methods can have a significant
influence on the internal MMC quantities and thus showed the importance of detailed
MMC models, even when comparing the performance of slower outer loop controllers.
However, producing high fidelity MMC models for every converter in a large HVDC grid
would result in lengthy simulation durations. Further work could be conducted to
investigate the necessary level of converter fidelity for each converter in the grid,
depending upon the converter location and the type of study. This work could lead to a set
of MTDC modelling recommendations being produced.
Chapter 10 References
207
10 References
[1] National Grid, "Offshore Development Information Statement " Company Report,
2010.
[2] Ofgem, "Electricity Capacity Assessment Report " Company Report, 2013.
[3] The Crown Estate. (April 2014). Leasing rounds. Available:
http://www.thecrownestate.co.uk/energy-infrastructure/offshore-wind-
energy/working-with-us/leasing-rounds/
[4] Supergen Wind. (April 2014). Supergen Wind Energy Technologies Consortium.
Available: http://www.supergen-wind.org.uk/
[5] C. Jones, "Wind Farm Connection and Design Issues," IET Round 3 Seminar,
Manchester, UK, Presentation slides, 2012.
[6] K. Friedrich, "Modern HVDC Plus application of VSC in Modular Multilevel
Converter Topology," IEEE International Symposium on Industrial Electronics,
Bari, pp. 3807 - 3810 2010.
[7] M. Barnes and A. Beddard, "Voltage Source Converter HVDC Links – The state of
the Art and Issues Going Forward," Energy Procedia, pp. 108-122, 2012.
[8] National Grid, "2011 Offshore Development Information Statement - Non
Technical Summary " Company report, 2011.
[9] National Grid, "Electricity Ten Year Statement 2012 - Appendix A4 " Company
Report, 2012.
[10] U. N. Gnanarathna, A. M. Gole, and R. P. Jayasinghe, "Efficient Modeling of
Modular Multilevel HVDC Converters (MMC) on Electromagnetic Transient
Simulation Programs," Power Delivery, IEEE Transactions on, vol. 26, pp. 316-
324, 2011.
[11] J. Xu, C. Zhao, W. Liu, and C. Guo, "Accelerated Model of Modular Multilevel
Converters in PSCAD/EMTDC," Power Delivery, IEEE Transactions on, vol. 28,
pp. 129-136, 2013.
[12] H. Saad, J. Peralta, S. Dennetiere, J. Mahseredjian, J. Jatskevich, J. A. Martinez, A.
Davoudi, M. Saeedifard, V. Sood, X. Wang, J. Cano, and A. Mehrizi-Sani,
"Dynamic Averaged and Simplified Models for MMC-Based HVDC Transmission
Systems," Power Delivery, IEEE Transactions on, vol. 28, pp. 1723-1730, 2013.
[13] R. Billinton and R. Allan, Reliability Evaluation of Engineering Systems - Concepts
and Techniques. New York: Plenum Press, 1992.
[14] National Grid, "Offshore Development Information Statement," Company Report,
2011.
[15] S. Zadkhast, M. Fotuhi-Firuzabad, F. Aminifar, R. Billinton, S. O. Faried, and A.-
A. A. Edris, "Reliability Evaluation of an HVDC Transmission System Tapped by
a VSC Station," Power Delivery, IEEE Transactions on, vol. 25, pp. 1962-1970,
2010.
[16] K. Linden, B. Jacobson, M. H. J. Bollen, and J.Lundquist, "Reliability study
methodology for HVDC grids," Cigre Paris Conference, 2010.
[17] O. Rui, C. Ohlen, J. Solvik, J. Thon, K. Karijord, and T. Gjengedal, "Design,
operation and availability analysis of a multi-terminal HVDC grid - A case study of
a possible Offshore Grid in the Norwegian Sea," in IEEE PowerTech Conference,
Trondheim, 2011, pp. 1-7.
[18] R. Billinton and R. Allan, Reliability Evaluation of Power Systems. New York,:
Plenum Press, 1996.
Chapter 10 References
208
[19] A. Sannino, H. Breder, and E. K. Nielsen, "Reliability of Collection Grids for
Large Offshore Wind Parks," in International Conference on Probabilistic Methods
Applied to Power Systems, Stockholm, 2006, pp. 1-6.
[20] N. MacLeod, "HVDC Max Sine : VSC Demonstrator," Alstom VSC Demonstrator
Visit, Stafford, Presentation slides, 2011.
[21] ABB, "Gas-insulated Switchgear ELK-14, 245kV," Product Brochure, 2011.
[22] National Grid, "2011 Offshore Development Information Statement Appendices,"
Company Report, 2011.
[23] ABB, "Liquid-filled power transformers," Product Brochure, 2009.
[24] Siemens, "Siemens Debuts HVDC PLUS with San Francisco’s Trans Bay Cable,"
Company Document, 2011.
[25] Alstom Grid, "Voltage Source Converter - Cooling Plant," Company Document,
2010.
[26] M. G. Bennett, N.S.Dhaliwal, and A. Leirbukt, "A survey of the reliability of
HVDC systems throughout the World during 2007-2008," Cigre Paris Conference,
2010.
[27] T. Chan, F. Heil, D. Kopejtkova, P. O’Connell, J.-P. Taillebois, and I. Welch,
"Report on the second International Survey on High Voltage Gas Insulated
Substations (GIS) Service Experience," Cigre Paris Conference, pp. 1-7, 1998.
[28] Siemens, "HVDC PLUS – Basics and Principle of Operation," Company Report,
2008.
[29] Alstom Grid, "Voltage Source Converter Switchyard," Company Document, 2011.
[30] Alstom Grid, HVDC - Connecting to the future: Published by Alstom Grid, 2010.
[31] Alstom Grid, "HVDC for beginners and beyond," Company Booklet, 2009.
[32] Cigre Working Group B1.10, "Update of Service Experience of HV Underground
and Submarine Cable Systems," Working Group Brochure, 2009.
[33] S. Dodds, B. Railing, K. Akman, B. Jacobson, T. Worzyk, and B. Nilsson, "HVDC
VSC (HVDC light) transmission – operating experiences," Cigre Paris Conference,
pp. 1-9, 2010.
[34] ABB, "Its time to connect," Company Report, 2008.
[35] Renewable UK, "Offshore Wind - Forecasts of future costs and benefits," Company
Report, 2011.
[36] Ofgem, "Electricity and Gas Supply Market Report," Company Report, 2011.
[37] Ofegm, "Renewables Obligation - Annual Report," Company Report, 2010-2011.
[38] Ofgem, "The Renewables Obligation Buy-Out price and Mutualisation Ceiling
2011-2012," Company Report, 2011.
[39] Combined Heat & Power Association, "Impacts of CPS on CHP - Briefing note,"
Association briefing note, 2011.
[40] J. E. Skog, "HVDC Transmission and Lifetime Expectancy," Company Memo, pp.
1-4, 2004.
[41] ABB. (April 2014). Québec - New England. Available: http://new.abb.com/
[42] Airtricty, "European Offshore Supergrid Proposal," Company Report, 2006.
[43] D. Jovcic and B. T. Ooi, "Tapping on HVDC lines using DC transformers,"
Electric Power Systems Research, Elsevier, vol. 81, pp. 561-569, 2010.
[44] P. Jones, "HVDC –Enabling the Transition to an Energy System based on
Renewables," IET ACDC, London, Presentation slides, 2010.
[45] National Electricity Transmission System Security and Quality of Supply Standard
(NETS SQSS), "Offshore Working Group (GSR011) Report," Company Report,
2012.
[46] D. I. Cotton, Switchgear: University of Manchester Lecture Notes, 2008.
Chapter 10 References
209
[47] R. Garzon, High Voltage Circuit Breakers, Second Edition: Marcel Dekker, 2002.
[48] A. T. Johns, Power circuit breaker theory and design: Peter Peregrinus, 1982.
[49] AREVA T&D, "DC circuit breakers: an important role in the continuity and quality
of service," Company Booklet, 2008.
[50] D. Andersson and A. Henriksson, "Passive and Active DC Breakers in the Three
Gorges-Changzhou HVDC Project," International Conference on Power Systems
2001.
[51] B. Bachmann, G. Mauthe, E. Ruoss, and H. P. Lips, "Development of a 500kV
Airblast HVDC Circuit Breaker," Power Apparatus and Systems, IEEE
Transactions on, pp. 2460-2466, 1985.
[52] B. Pauli, G. Mauthe, E. Ruoss, and G. Ecklin, "Development of a High Current
HVDC Circuit Breaker with Fast Fault Clearing Capability," Power Delivery, IEEE
Transactions on vol. 3, pp. 2072-2080, 1988.
[53] S. Henry, A. M. Denis, and P. Panciatici, "Feasibility study of off-shore HVDC
grids," Power and Energy Society General Meeting, 2010 IEEE pp. 1-5, 2010.
[54] W. Grieshaber, A. Fanget, B. Kayibabu, and J.-P. Dupraz, "MRTB for DC
applications: design and power tests," GridTech Conference, Delhi, 2009.
[55] D. Jovic and B. Wu, "Fast Fault Current Interruption on High-power DC
Networks," Power and Energy Society General Meeting, 2010 IEEE, pp. 1-6, 2010.
[56] C Meyer, M Kowal, and R. D. Doncker, "Circuit Breaker Concepts for Future
High-Power DC-Applications," IEEE Industry Applications Conference, vol. 2, pp.
860-866, 2005.
[57] J. Hafner and B. Jacobson, "Proactive Hybrid HVDC Breakers - A key innovation
for reliable HVDC grids," Cigre Bologna Conference, pp. 1-9, September 2011.
[58] D. Jovcic, D. v. Hertem, K. Linden, J.-P. Taisne, and W. Grieshaber, "Feasibility of
DC Transmission Networks," IEEE PES ISGT Europe, vol. Panel session 2e, pp. 1-
8, 2011.
[59] ABB and M. Callavik, "HVDC Grids for Integration of Renewable Power
Sources," presented at the EPRI’s HVDC & FACTS Conference, Palo Alto, 2009.
[60] A. Beddard and M. Barnes, "Circuit Breaker Conduction Path," Patent No:
P136908GB, Filed August 2011.
[61] J. Hafner and B. Jacobson, "Device and method to break the current of a power
transmission or distribution line and current limiting arrangement," Patent
publication No: WO2011/057675A1, Filed: Novemeber 2009, Published May 2011.
[62] P. Skarby, "A high voltage DC breaker apparatus," Patent publication No:
WO2011/141428A1, Filed May 2011, Published November 2011.
[63] P. Skarby, "A high voltage DC breaker apparatus," Patent publication No:
WO2011/141055A1, Filed: May 2011, Published: November 2011.
[64] M. Mohaddes, "Hybrid DC Circuit Breaking Device," Patent publication No: WO
2013/093066, Filed: December 2012, Published June 2013.
[65] Alstom Grid, "Alstom confirms research findings, done with RTE, in high-voltage
DC circuit-breaker technology," Press Release, 24/1/14.
[66] K. De Kerf, K. Srivastava, M. Reza, D. Bekaert, S. Cole, D. Van Hertem, and R.
Belmans, "Wavelet-based protection strategy for DC faults in multi-terminal VSC
HVDC systems," Generation, Transmission & Distribution, IET, vol. 5, pp. 496-
503, 2011.
[67] M. E. Baran and N. R. Mahajan, "Overcurrent Protection on Voltage-Source-
Converter-Based Multiterminal DC Distribution Systems," Power Delivery, IEEE
Transactions on, vol. 27, pp. 406-411, 2007.
Chapter 10 References
210
[68] J. Candelaria and P. Jae-Do, "VSC-HVDC system protection: A review of current
methods," in Power Systems Conference and Exposition (PSCE), 2011 IEEE/PES,
2011, pp. 1-7.
[69] T. Lianxiang and O. Boon-Teck, "Locating and Isolating DC Faults in Multi-
Terminal DC Systems," Power Delivery, IEEE Transactions on, vol. 22, pp. 1877-
1884, 2007.
[70] T. Lianxiang and O. Boon-Teck, "Protection of VSC-multi-terminal HVDC against
DC faults," in Power Electronics Specialists Conference, 2002. pesc 02. 2002 IEEE
33rd Annual, 2002, pp. 719-724 vol.2.
[71] D. V. Hertem, M. Ghandhari, J. B. Curis, O. Despouys, and A. Marzin, "Protection
requirements for a multi-terminal meshed DC grid," Cigre Bologna Conference, pp.
1-8, 2011.
[72] A. Rogers, Understanding Optical Fibre Communications: Artech House
Publishers, 2001.
[73] S. Mehmood, "Transient fault protection for HVDC grid," Masters Thesis, Royal
Institue of Technology Sweden, 2010.
[74] A. Ukil. and R. Zivanovic, "Abrupt change detection in power system fault analysis
using wavelet transform," International Conference on Power Systems Transients
pp. 1-5, 2005.
[75] K. D. Kerf, "Protection Strategies for DC Faults in Multi-Terminal VSC HVDC
Systems," Masters Thesis, K.U.Leuven, 2009.
[76] C. Barker, "HVDC as a bulk power transfer system," Supergen Offshore Wind
Training Seminar , Manchester, UK, Presentation slides, 2011.
[77] G. P. Adam, K. H. Ahmed, S. J. Finney, and B. W. Williams, "AC fault ride-
through capability of a VSC-HVDC transmission systems," in Energy Conversion
Congress and Exposition, Atlanta, 2010, pp. 3739-3745.
[78] S. K. Chaudhary, R. Teodorescu, P. Rodriguez, and P. C. Kjar, "Chopper controlled
resistors in VSC-HVDC transmission for WPP with full-scale converters," in
Conference on Sustainable Alternative Energy 2009, pp. 1-8.
[79] N. Flourentzou, V. G. Agelidis, and G. D. Demetriades, "VSC-Based HVDC Power
Transmission Systems: An Overview," Power Electronics, IEEE Transactions on,
vol. 24, pp. 592-602, 2009.
[80] U. N. Gnanarathna, S. K. Chaudhary, A. M. Gole, and R. Teodorescu, "Modular
multi-level converter based HVDC system for grid connection of offshore wind
power plant," in IET ACDC, London, 2010, pp. 1-5.
[81] G. P. Adam, O. Anaya-Lara, and G. Burt, "Steady-state and transient performance
of DC transmission systems based on HVDC technology," in AC and DC Power
Transmission, 2010. ACDC. 9th IET International Conference on, 2010, pp. 1-5.
[82] T. Qingrui, X. Zheng, and Z. Jing, "Circulating current suppressing controller in
modular multilevel converter," in IECON 2010 - 36th Annual Conference on IEEE
Industrial Electronics Society, 2010, pp. 3198-3202.
[83] A. Antonopoulos, L. Angquist, and H. P. Nee, "On dynamics and voltage control of
the Modular Multilevel Converter," in Power Electronics and Applications, 2009.
EPE '09. 13th European Conference on, 2009, pp. 1-10.
[84] B. Jacobson, P. Karlsson, G. Asplund, L. Harnefors, and T. Jonsson, "VSC-HVDC
Transmission with Cascaded Two-Level Converters," Cigre Paris Conference,
2010.
[85] R. Marquardt, A. Lesnicar, and J. Hildinger, "Modulares Stromrichterkonzept für
Netzkupplungsanwendung bei hohen Spannungen bei hohen Spannungen," ETG-
Fachbericht, vol. 88, pp. 155-161, 2002.
Chapter 10 References
211
[86] Y. Zhang, G. P. Adam, T. C. Lim, S. J. Finney, and B. W. Williams, "Analysis and
Experiment Validation of a Threelevel Modular Multilevel Converters,"
International Conference on Power Electronics, 2011.
[87] G. Ding, M. Ding, and G. Tang, "An Innovative Hybrid PWM Technology for VSC
in Application of VSC-HVDC Transmission System," IEEE Electrical Power &
Energy Conference, 2008.
[88] T. Qingrui, X. Zheng, and X. Lie, "Reduced Switching-Frequency Modulation and
Circulating Current Suppression for Modular Multilevel Converters," Power
Delivery, IEEE Transactions on, vol. 26, pp. 2009-2017, 2011.
[89] T. Qingrui, X. Zheng, H. Hongyang, and Z. Jing, "Parameter design principle of the
arm inductor in modular multilevel converter based HVDC," in International
Conference on Power System Technology 2010, pp. 1-6.
[90] J. Dorn, H. Huang, and D. Retzmann, "Novel Voltage-Sourced Converters for
HVDC and FACTS Applications," Cigre Osaka Conference, 2007.
[91] K. Friedrich, "Modern HVDC PLUS application of VSC in Modular Multilevel
Converter topology," in Industrial Electronics (ISIE), 2010 IEEE International
Symposium on, 2010, pp. 3807-3810.
[92] J. Grainger and W. Stevenson, Power Systems Analysis: McGraw-Hill, 1994.
[93] Y. Jiang-Häfner and R. Ottersten, "HVDC with Voltage Source Converters – A
Desirable Solution for Connecting Renewable Energies," Large scale integration of
wind power into power systems, 2010.
[94] M. Barnes, "Analysis and Modelling of Electrical Systems - Lecture Notes," MSc
Power conversion, The University of Manchester, 2009.
[95] S. Skogestad and I. Postlethwaite, Multivariable Feedback Control - Analysis and
Design. Sussex, UK: John Wiley and Sons, 2010.
[96] C. Taratoris, "Chain Link Converter Modelling," The University of Manchester,
MSc Thesis, 2011.
[97] M. Paul, "Voltage Source Converter High Voltage Direct Current Transmission,"
The University of Manchester, MEng Thesis, 2011.
[98] A. Lesnicar and R. Marquardt, "An innovative modular multilevel converter
topology suitable for a wide power range," in Power Tech Conference Proceedings,
2003 IEEE Bologna, 2003, p. 6 pp. Vol.3.
[99] M. Saeedifard and R. Iravani, "Dynamic Performance of a Modular Multilevel
Back-to-Back HVDC System," Power Delivery, IEEE Transactions on, vol. 25, pp.
2903-2912, 2010.
[100] D. Zhong, L. M. Tolbert, and J. N. Chiasson, "Active harmonic elimination for
multilevel converters," Power Electronics, IEEE Transactions on, vol. 21, pp. 459-
469, 2006.
[101] T. Qingrui and X. Zheng, "Impact of Sampling Frequency on Harmonic Distortion
for Modular Multilevel Converter," Power Delivery, IEEE Transactions on, vol.
26, pp. 298-306, 2011.
[102] C. Tang, M. Pathmanathan, W. L. Soong, and N. Ertugrul, "Effects of inertia on
dynamic performance of wind turbines," in Power Engineering Conference, 2008.
AUPEC '08. Australasian Universities, 2008, pp. 1-6.
[103] Vestas, "3MW Platform," Company Booklet, 2014.
[104] Siemens, "Siemens 6.0 MW Offshore Wind Turbine," Company Booklet, 2012.
[105] G. P. Adam, S. J. Finney, K. Bell, and B. W. Williams, "Transient capability
assessments of HVDC voltage source converters," in IEEE Power and Energy
Conference, Illinois 2012, pp. 1-8.
[106] National Grid, "The Grid Code - Issue 5 Rev 3," Company Report, 2013.
Chapter 10 References
212
[107] G. O. A. Kalcon, G. P. Adam, O. Anaya-Lara, G. Burt, and K. Lo, "Control
strategies of VSC-HVDC transmission system for wind power integration to meet
GB grid code requirements," Proceedings of the 2010 International Symposium on
Power Electronics Electrical Drives Automation and Motion 2010.
[108] P. Jones and C. Davidson, "Calculation of power losses for MMC-based VSC
HVDC stations," Power Electronics and Applications, 2013.
[109] C. Xiaofang, Z. Chengyong, and C. Chungang, "Research on the fault
characteristics of HVDC based on modular multilevel converter," in IEEE
Electrical Power and Energy Conference 2011, pp. 91-96.
[110] K. Strunz and E. Carlson, "Nested Fast and Simultaneous Solution for Time-
Domain Simulation of Integrative Power-Electric and Electronic Systems," Power
Delivery, IEEE Transactions on, vol. 22, pp. 277-287, 2007.
[111] National Grid, "2010 Offshore Development Information Statement Appendices,"
Company Report, 2010.
[112] T. Worzyk, Submarine Power Cables and Their Design Elements: Springer, 2009.
[113] G. J. Anders, Rating of Electric Power Cables: IEEE Press, 1997.
[114] ABB, "XLPE Land Cable Systems User's Guide Revision 5," Technical guide,
2010.
[115] ABB, "XLPE Submarine Cable Systems - Attachment to XLPE Land Cable
Systems - User´s Guide Revision 5," Technical guide, 2010.
[116] B. Gustavsen, J. A. Martinez, and D. Durbak, "Parameter Determination for
Modeling System Transients—Part II: Insulated Cables," Power Delivery, IEEE
Transactions on, 2005.
[117] F. Mura, C. Meyer, and R. W. D. Doncker, "Stability Analysis of High-Power DC
Grids," Industry Applications, IEEE Transactions on, vol. 46, 2010.
[118] HONEYWELL, "Dielectric Constant Table," Company Report, 2011.
[119] G. Lucca, "Evaluation of sea return impedance and mutual impedance between AC
power cables and pipelines," European Transactions on Electrical Power, 2010.
[120] R. Benato, M. Forzan, M. Marelli, A. Orini, and E. Zaccone, "Harmonic Behaviour
of HVDC cables," IEEE PES Transmission and Distribution Conference and
Exposition, New Orleans, 2010.
[121] G. Miner, Line and Electromagnetic Fields for Engineers. New York: Oxford
University Press, 1996.
[122] N. Watson and J. Arrillaga, Power systems electromagnetic transients simulation:
IET publishing, 2003.
[123] L. M. Wedepohl and D. J. Wilcox, "Transient analysis of underground power-
transmission systems. System-model and wave-propagation characteristics,"
Electrical Engineers, Proceedings of the Institution of, vol. 120, pp. 253-260, 1973.
[124] A. Ametani, "Wave Propagation Characterstics of Cables," Power Apparatus and
Systems, IEEE Transactions on 1980.
[125] S. A. Schelkunoff, "The Electromagnetic Theory of Coaxial Transmission Lines
and Cylindrical Shields," Bell System Technical Journal, Vol. 13, 1934.
[126] PSCAD, "PSCAD User's Guide," vol. 4.2.1, 2010.
[127] W. Wang, M. Barnes, and O. Marjanovic, "Droop control modelling and analysis
of multi-terminal VSC-HVDC for offshore wind farms," in AC and DC Power
Transmission (ACDC 2012), 10th IET International Conference on, 2012, pp. 1-6.
[128] M. M. T. M. Haileselassie, and T. Undeland, "Multi-terminal VSC-HVDC system
for integration of offshore wind farms and green electrification of platforms in the
North Sea," Nordic Workshop on Power and Industrial Electronics, Espoo,
Finland, 2008.
Chapter 10 References
213
[129] J. Beerten, S. Cole, and R. Belmans, "Modeling of Multi-Terminal VSC HVDC
Systems With Distributed DC Voltage Control," Power Systems, IEEE
Transactions on, vol. 29, pp. 34-42, 2014.
[130] National Grid, "Electricity Ten Year Statement," Company Report, 2012.
[131] Cigre WG B4-52, "HVDC Grid Feasibility Study," WG Brochure, 2013.
[132] W. Wang, "An Overview of Control Strategies of Multi-terminal VSC-HVDC
Systems," Internal Report, 2012.
[133] T. Burton, N. Jenkins, D. Sharpe, and E. Bossanyi, Wind Energy Handbook.
Sussex, UK: John Wiley and Sons, 2011.
[134] J. Arrillaga, Y. H. Liu, and N. R. Watson, Flexible Power Transmission - The
HVDC Options: Wiley, 2007.
[135] M. Fu and L. A. Dissado, "Space Charge Formation and its Modified Electric Field
under Applied Voltage Reversal and Temperature Gradient in XLPE Cable,"
Dielectrics and Electrical Insulation, IEEE Transactions on 2008.
[136] National Grid, "High Voltage Direct Current – technical information," Company
Report, 2011.
[137] T. Brückner, S. Bernet, and H. Güldner, "The Active NPC Converter and Its Loss-
Balancing Control," Industrial Electronics, IEEE Transactions on 2005.
[138] X. Yuan, H. Stemmler, and I. Barb, "Investigation on the Clamping Voltage Self-
Balancing of the Three-Level Capacitor Clamping Inverter," IEEE Power
Electronics Specialists Conference 1999.
[139] L. Ronström, M. L. Hoffstein, R. Pajo, and M. Lahtinen, "The Estlink HVDC
Light® Transmission System," CIGRÉ Regional Meeting, 2008.
[140] Siemens. (April 2014). Modular Multilevel Converter. Available:
http://www.energy.siemens.com/us/en/power-transmission/hvdc/hvdc-
plus/modular-multilevel-converter.htm
[141] Siemens, "Siemens receives order from transpower to connect offshore wind farms
via HVDC link," Press Release, 2010.
[142] Alstom Grid. (April 2014). Alstom Grid will provide Tres Amigas LLC in the USA
with first-of-its-kind Smart Grid “SuperStation”. Available:
http://www.alstom.com/press-centre/2011/4/Alstom-Grid-will-provide-Tres-
Amigas-LLC-in-the-USA-with-first-of-its-kind-Smart-Grid-SuperStation/
[143] ABB. (April 2014). Dolwin 2 Reference Project. Available:
http://new.abb.com/systems/hvdc/references/dolwin2
[144] C. Ö. Ø. Rui, J. Solvik, J. Thon, K. Karijord, T. Gjengedal, "Design, operation and
availability analysis of a multi-terminal HVDC grid - A case study of a possible
Offshore Grid in the Norwegian Sea " in IEEE Trondheim PowerTech, 2011.
[145] ABB. (September 2011). The evolution of GIS Available: http://www.abb.com
[146] ABB, "Extreme maintenance - No location too challenging for an on-site repair!,"
Company Booklet, 2004.
[147] ABB. (September 2011). ABB’s on-site transformer repair service provides rapid
return to full production for Corus’ Scunthorpe steelworks Available:
http://www.abb.co.uk
[148] R. V. Narinder S. Dhaliwal and M. H. Astrid Keste, Peter Kuffel, , "Nelson River
Pole 2 Mercury Arc Valve Replacement," Cigre Conference, 2004.
[149] Cigre Working Group B1.21, "Third-Party Damage to Underground and Submarine
Cables," Working Group Brochure, 2009.
[150] IMC Networks, "MTBF, MTTR, MTTF & FIT Explanation of Terms," Company
Report, 2011.
Chapter 10 References
214
[151] D. Jovcic. (April 2014). Research Council Sponsored Projects. Available:
http://homepages.abdn.ac.uk/d.jovcic/pages/index.html
[152] D. Jovcic and B. T. Ooi, "Theoretical aspects of fault isolation on high-power DC
lines using resonant DC/DC converters," IET Generation, Transmission and
Distribution, 2010.
[153] V. Lescale, "High Voltage Direct Current Circuit Breaker Arrangement and
Method," Patent publication No: WO2010060476 Filed: November 2008,
Published: June 2010.
[154] U. Astrom, L. Liljestrand, V. Lescale, and M. Man, "A DC Current Breaker,"
Patent publication No:WO2009149749, Filed: June 2008, Published: December
2010.
[155] G. Asplund, V. Lescale, and C. Solver, "Direct-Current Breaker for High Power for
Connection into a Direct-Current Carrying High-Voltage Line," Patent publication
No: 5517378, Filed: December 1994, Published: May 1996.
[156] Crown Estate. (May 2011). Round 3 offshore wind farms - Interactive map.
Available: http://www.thecrownestate.co.uk
[157] G. Bianchi and G. Luoni, "Induced Currents and Losses in Single-Core Submarine
Cables," Power Apparatus and Systems, IEEE Transactions on 1976.
[158] PSCAD, "Ground Plane," On-line help.
[159] PSCAD, "Frequency Dependent Line Models," On-line help.
Appendices
215
A. APPENDICES
Appendix 1A
216
APPENDIX 1A – HVDC TRANSMISSION SYSTEMS
1 HVAC vs. HVDC for Offshore Wind
Wind turbines typically generate power at a voltage of up to 1kV AC [133]. A transformer
located either in the nacelle, or at the bottom of the tower, steps the voltage up to either
11kV or 33kV [133]. The power from the wind turbines is transmitted to an offshore
substation which increases the voltage for transmission to shore. In a HVAC transmission
system a typical transmission voltage to shore is 132kV, which can be connected directly
to the electricity grid or stepped-up at an onshore substation if it is to be connected at
400kV. Alternatively the AC voltage can be converted to DC by a HVDC converter on the
offshore platform and then converted back to AC by a HVDC converter located onshore.
Figure A.1 shows a typical HVDC and HVAC connection.
Figure A.1: Overview of a HVDC connection and a HVAC connection
A HVDC transmission system typically has much higher investment costs in comparison to
a HVAC transmission system, due to the converters. However there are a number of
scenarios where HVDC is chosen for technical and/or financial reasons. These include,
connecting asynchronous grids, bulk power transmission through a long distance
transmission line, bulk power transmission via a submarine cable over a certain length and
for other technical advantages such as improved AC system stability.
Offshore windfarms are connected to the AC grid using a submarine cable, not a
transmission line. The capacitance of a cable is much greater than that of an equivalent
line, due to the proximity of the conductor to the grounded sheath and the insulating
medium. In an AC system the cable’s capacitance must be charged and discharged every
Wind
Farm 1
Wind
Farm 2
AC
DC
Rectifier R1 Inverter I1
AC
AC
Shore
AC
Appendix 1A
217
cycle, which constitutes a capacitive current flowing through the cable. This capacitive
current consumes a proportion of the cable’s overall current carrying capability and
therefore reduces the cable’s useful power transfer capability. However, in a HVDC
system once the cable’s capacitance is charged, almost the entire capacity is available for
active power transmission. Thus VSC-HVDC is typically employed for windfarms located
more than 50-100km from shore [5].
2 HVDC Converter Technology
A HVDC converter is capable of rectifying AC to DC and inverting DC to AC. The
converter must instantaneously match the AC and DC side voltages for stable operation
[134]. This is achieved by adding some impedance to the switching circuit to absorb the
instantaneous mismatch in AC and DC voltage levels. If this impedance is located
exclusively on the AC side, the instantaneous DC voltage is transferred to the AC side and
therefore the DC side acts as a voltage source. This type of converter is referred to as a
Voltage Source Converter (VSC). If a large smoothing reactor is located exclusively on the
DC side, the instantaneous AC voltage is transferred to the DC side, which results in
constant pulses of DC current and therefore the DC side acts as a current source. This type
of converter is referred to as a Current Source Converter (CSC).
CSC-HVDC is based on thyristor technology. Thyristors can be switched-on by issuing a
control signal, but can only be switched-off once the current flowing through the thyristors
ceases. It is for this reason CSC-HVDC requires a strong AC voltage source to commutate
the current between the valves (string of thyristors) in the converter. Therefore the CSC-
HVDC converter is also a Line Commuted Converter (LCC) and is sometimes referred to
as LCC-HVDC. VSC-HVDC can self-commutate current between the converter valves
because the valves consist of IGBTs, which have turn-off capability. Therefore the VSC-
HVDC converter is also classified as a Self-commutated Converter (SCC) and maybe
referred to as SCC-HVDC although this is not commonly used.
2.1 CSC-HVDC
There are several different CSC-HVDC transmission scheme configurations. One of the
most common schemes is the monopole HVDC scheme with metallic return as shown in
Figure A.2.
Appendix 1A
218
Figure A.2: CSC-HVDC monopole scheme with metallic return
The heart of the scheme is the six-pulse bridge, or Graetz bridge as it is sometimes known.
The six-pulse bridge consists of six valves. Each valve contains a number of series-
connected thyristors, as shown in Figure A.3. The number of thyristors in each valve is
dependent upon the voltage the valve is required to block.
Figure A.3: Six-pulse converter
AC Network 1 AC Network 2
6 - Pulse Bridge
DC Smoothing Reactor
Transmission Line
Metallic Return
3 - Winding Star / Star , Star / Delta
Transformer
V dcr V dci
I dc
I dc
V dc
I dc
I dc
L d
V a V b
V c
T 1 T 3 T 5
T 4 T 6 T 2
I 1 I 3 I 5
I 4 I 6 I 2
Anode
Cathode
V
Appendix 1A
219
A thyristor is turned-on by issuing a control signal to energise the thyristor’s gate terminal
when the thyristor is forward biased. The thyristor is turned-off when the external circuit
forces the current flowing in the thyristor through zero. The firing angle, also referred to as
alpha, is the delay measured in electrical degrees from when the thyristor is forward biased
until the gate terminal is energised. A thyristor is essentially a diode if the firing angle is
zero degrees.
Figure A.4: PSCAD simulation of CSC converter switching waveforms for a firing angle of 0° -
indicative waveforms shown, each valve conduction pulse is 120°.
The waveforms shown in Figure A.4 are for a six-pulse converter with a firing angle of 0°.
The anode voltage, Vdc-a, is the voltage transferred from the AC side, when valves T1, T3
and T5 conduct. Comparing Vdc-a, with the phase voltages in the second plot, it can be seen
that Vc is transferred to Vdc-a until Va exceeds Vc and then T1 conducts resulting in Va
being transferred to Vdc-a. The cathode voltage, Vdc-c, is the voltage transferred from the
AC side when valves T2, T4 and T6 conduct. In this case when the phase voltage is more
negative than Vdc-c, the valve connected to that phase will conduct. The voltage Vdc, is the
potential difference between Vdc-a and Vdc-c. Therefore Vdc has a mean voltage of twice Vdc-
a, with half the amplitude ripple, at six times the supply frequency. The two bottom plots in
Vdc-a (Blue),Vdc -c(Green) and Vdc (Red) against time
Va(Blue),Vb(Green) and Vc(Red) against time
Current
I1(Blue),I3(Green) and I5(Red) against time
I2(Blue),I4 (Green) and I6(Red) against time
Current
Time
Voltage
T1 T3 T5
T2 T4 T6
T1&T6 T1&T2 T3&T2 T3&T4 T5&T4 T5&T6
T1 T3 T5
T2 T4 T6T6
T1
Voltage
Appendix 1A
220
Figure A.4 show that when a valve conducts, a constant pulse of current flows due to the
large DC smoothing reactor. Each valve conducts for 120° per cycle.
The effect of increasing the firing angle is shown in Figure A.5. After a particular phase
voltage exceeds the anode voltage there is a delay, in this case 25° or 1.4ms for a 50Hz
system, before the valve is fired. This delay causes the DC voltage to decrease and the
fundamental phase current to lag the fundamental phase voltage, which results in the
converter absorbing reactive power.
Figure A.5: PSCAD simulation of CSC converter switching waveforms for a firing angle of 25° -
indicative waveforms shown, each valve conduction pulse is 120°.
The average DC voltage for the converter is calculated from equation (A.1).
3 2
( )LLdc
VV cos
(A.1)
Va(Blue),Vb(Green) and Vc(Red) against time
Time
VoltageT1 T3 T5
T2 T4 T6
T1&T6 T1&T2 T3&T2 T3&T4 T5&T4 T5&T6
T1 T3 T5 T1
T2 T4 T6T6
Voltage
α
Current
Current
Vdc-a (Blue),Vdc -c(Green) and Vdc (Red) against time
I1(Blue),I3(Green) and I5(Red) against time
I2(Blue),I4 (Green) and I6(Red) against time
Appendix 1A
221
where:
LLV - rms valve line-to-line voltage
α – firing angle
Increasing the firing angle decreases the DC voltage. A firing angle between 0° and 90°
results in a positive DC voltage and the converter operating as a rectifier. Increasing the
firing angle above 90° results in a negative DC voltage and the converter operating as an
inverter. Current can only flow in one direction in a CSC-HVDC scheme. At the rectifier,
power is being transferred from the AC side to the DC side (P=Vdcr.Idc) and at the inverter
power is transferred from the DC side to the AC side (P=-Vdci.Idc). Therefore power
reversal is achieved by changing the voltage polarity at each converter. XLPE cable is not
suitable for polarity reversal, due to space charge formation, and therefore mass-
impregnated cable is used. For more information on space charge formation see [135]
The bottom two plots in Figure A.4 and Figure A.5 show that the line current appears to be
able to commutate between valves instantaneously. This is because there is no reactance on
the AC side in this simulation, as shown in Figure A.3, however in reality there will be
some reactance on the AC side not least to limit the valve current during a fault. The most
common and predominate source of AC side reactance is leakage reactance from the
converter transformer. The leakage reactance reduces the rate of change for the current
commutating from one valve to the next, which in the absence of AC side reactance is
infinite. The time it takes for the current to commutate from one valve to the next is known
as the commutation overlap, µ, and is usually defined in degrees. The commutation overlap
reduces the DC voltage, as shown in Figure A.6 and described by the modified mean
voltage equation (A.2).
33 2
( ) c dcLLdc
X IVV cos
(A.2)
where:
cX - commutation reactance
Appendix 1A
222
Figure A.6: PSCAD simulation of switching waveforms for CSC converter with AC side reactance and
firing angle of 0° - indicative waveforms shown, each valve conduction pulse is 120°.
The relationship between the firing angle and commutation overlap on the amount of
reactive power the converter absorbs may be described by the Uhlmann approximation
given in [30, 134] and shown in equation (A.3).
cos 0.5 cos( ) cos( )P
S (A.3)
This approximation shows that increasing the firing angle, and/or increasing the
commutation overlap, results in the converter absorbing more reactive power.
A converter operating as an inverter has a large firing angle (>90°) and it is more common
to refer to the extinction angle or gamma, γ, which is mathematically expressed as
180 . Therefore the Uhlmann approximation can be re-written for an inverter as in
equation (A.4).
cos 0.5 cos( ) cos( )P
S (A.4)
The HVDC scheme controls the active power by essentially controlling the voltage drop
across the transmission line/cable. The firing angle affects the voltage drop across the
transmission cable and the amount of reactive power the converter absorbs. Therefore, the
converter cannot control active and reactive power independently. The reactive power the
converter typically absorbs is 60% of the active power [134]. Shunt capacitance, along
Voltage
Time
Current
µ
Vdc-a (Blue),Vdc -c(Green) and Vdc (Red) against time
I1(Blue),I3(Green) and I5(Red) against time
Appendix 1A
223
with AC harmonic filters, are normally required to supply the converter’s reactive power
requirements.
A CSC-HVDC converter, as shown in Figure A.2, contains two six-pulse bridges
connected in series on the DC side. The reason for doing this is to reduce the harmonics
which are generated by the converter. As shown in the previous section the six-pulse
bridge conducts rectangular pulses of current (no leakage reactance) which means the
phase current is very non-sinusoidal and therefore has a high harmonic content. In order to
reduce the harmonic content, two six-pulse bridges are typically connected in series on the
DC side, with one bridge connected to the AC source using a star/star transformer and the
other using a star/delta transformer. The effect of the star/delta transformer is that one six-
pulse bridge conducts current pulses which are shifted by 30° from the other six-pulse
bridge, resulting in phase currents which are more sinusoidal. This is shown in Figure A.7.
Figure A.7: PSCAD simulation of phase current for six-pulse converter (left) and twelve-pulse
converter (right)
Figure A.7 shows that a twelve-pulse converter produces a more sinusoidal phase current
in comparison to a six-pulse converter and therefore reduces AC side harmonics. A twelve-
pulse converter also reduces the DC side harmonics because the ripple voltage is twelve
times the fundamental frequency, in comparison to six times the fundamental frequency for
a six-pulse converter. Although a twelve-pulse converter improves harmonic content in
comparison to a six-pulse converter, it does not reduce the AC and DC side harmonic
content to within acceptable levels. Therefore harmonic filters are required. The AC side
harmonic filters are tuned at the 11th
and 13th
harmonic with an extra high-pass branch
added and typically tuned at the 24th
harmonic [134]. The AC side harmonic filters are
also designed to provide reactive power compensation for the converter. The DC side
generally has a high-pass filter tuned at the 12th
harmonic [134].
The AC harmonic filters, shunt capacitor bank and the associated AC switchyard account
for a large proportion (40-60%) of the overall space required for a CSC-HVDC scheme
Appendix 1A
224
[111]. The footprint for a typical 1000MW CSC station located onshore is 200m x 175m x
22m with an indicative cost of about £100m [111]28
.
Thus the disadvantages of a CSC-HVDC scheme are:
LCC requires a strong AC system for stable operation
Cannot control active and reactive power independently
Large footprint
Requires the more expensive and heavier mass-impregnated cable [111]
Multi-terminal operation is technically challenging due to the change of DC voltage
polarity for power reversal [134]
2.2 VSC-HVDC
ABB pioneered VSC-HVDC technology and introduced its 1st generation of VSC-HVDC
technology in 1997, known as HVDC Light. Currently the 3rd
and 4th
generation of HVDC
Light is available. Siemens have developed their VSC-HVDC technology under the trade
name of HVDC Plus, whilst Alstom Grid has developed its VSC-HVDC technology called
HVDC MaxSine. A single line diagram for a typical VSC-HVDC scheme is shown in
Figure A.8.
Figure A.8: VSC-HVDC scheme
As with CSC-HVDC, the converter is the heart of the scheme. There are several VSC
converter topologies available. The simplest VSC-HVDC converter is a two-level
converter, which is the converter topology used in the 1st and 3
rd generations of HVDC
Light. This converter topology will be used to explain the fundamental principles of VSC-
HVDC. A three-phase two-level VSC is shown in Figure A.9.
28
Cost is indicative for a 1000MW, 400kV converter station.
Transmission Line
Metallic Return
Vdcr Vdci
Idc
Idc
AC Network 1 AC Network 2
Appendix 1A
225
Figure A.9: Three-phase two-level voltage source converter
Each valve consists of a stack of series and parallel connected Insulated Gate Bipolar
Transistors (IGBT) with anti-parallel diodes. The number of devices connected in series
and parallel depends upon the voltage and current rating of the valve respectively.
Consider the phase A converter voltage, Va. This voltage has two possible values +Vdc/2
when the upper valve conducts and –Vdc/2 when the lower valve conducts. The same
applies for the phase converter voltage B, Vb, and phase converter voltage C, Vc. By
applying a Pulse Width Modulation (PWM) control scheme to the converter a sinusoidal
voltage of the desired magnitude and phase can be synthesized as shown in Figure A.10.
Figure A.10: Sinusoidal voltage synthesised from a two-level converter with PWM (modified from
[28]); Vd=Vdc.
The quality of the sinewave synthesised, and therefore the harmonic content as well as the
converter losses, is dependent upon the PWM switching frequency. Increasing the
switching frequency produces a better quality sinewave and therefore reduces the AC and
DC harmonic content but at the expense of increasing the converter losses. The first
generation of HVDC Light utilised a switching frequency of 1950Hz [134]. The high
switching frequency normally removes the low-order harmonics and therefore filters are
+Vdc/2
-Vdc/2
Vsa
Vsb
Vsc
Valve
XVa
Vb
Vc
Appendix 1A
226
only required to absorb the higher harmonics. This greatly reduces the VSC-HVDC
footprint in comparison to a CSC-HVDC scheme.
Power transfer between the inverter and the AC system for phase A can be described by
equations (A.5) and (A.6).
sinsa aV V
PX
(A.5)
( cos )sa a saV V V
QX
(A.6)
Active power flows from the inverter into the AC network when the inverter power angle,
is positive with respect to that of the AC system. Therefore active power flows from the
AC network when the inverter power angle is negative with respect to that of the AC
system. The inverter exports reactive power when its voltage magnitude is greater than the
AC system and absorbs reactive power when its magnitude if less than the AC system.
Since the VSC can control its voltage magnitude and phase independently, it is able to
control active and reactive power independently. This is a key advantage over CSC-
HVDC. A VSC-HVDC scheme can offer fast reactive power support for the connected AC
systems and does not require shunt capacitor banks which further reduces its footprint. The
typical footprint for an onshore 1000MW VSC is about 90m x54m x 24m [111].
Power flow reversal in a VSC-HVDC scheme is achieved by reversing the direction of
current, not the DC voltage polarity as is the case for CSC-HVDC. This means that the
cheaper, lighter and more robust XLPE cable is suitable for VSC-HVDC schemes. The
absence of DC voltage polarity reversal also makes MT operation much less challenging.
The VSC is a self-commutated converter and therefore does not require an AC voltage
source for commutation. It can therefore maintain stable operation when connected to a
weak AC system, such as an offshore windfarm. Also CSC converters are generally more
expensive than VSC due to their reactive power and harmonic filtering requirements [136].
However, at present VSC schemes have been installed at lower power ratings than CSC
and therefore have been more expensive in terms of capital costs per unit of power.
ABB modified its converter design from a two-level converter to a three-level diode
Neutral Point Clamped (NPC) VSC in their 2nd
generation, as shown in Figure A.11.
Appendix 1A
227
Figure A.11: Single phase of a diode neutral clamped voltage source converter
The output voltage from the converter is +Vdc/2 when the two upper valves (1 and 2)
conduct and -Vdc/2 when the lower two valves conduct (3 and 4). The NPC can also output
0V when the middle valves (2 and 3) conduct. Positive current flows through the additional
upper anti-parallel diode and the upper middle IGBT into the AC network; negative current
flows through the lower middle IGBT and the lower additional anti-parallel diode. The
sinewave synthesised by this type of converter is shown in Figure A.12.
Figure A.12: Sinusoidal voltage synthesised from a three-level converter with PWM (modified from
[28]); Vd=Vdc.
The NPC VSC switches between the positive or negative DC link voltage and zero, which
halves the dv/dt in comparison to a two-level converter. From the perspective of harmonic
content, the effective switching frequency has doubled in comparison to a two-level
converter. This allows the switching frequency to be reduced, which decreases converter
losses without adversely impacting on the converter output harmonics. The NPC converter
topology was used for a back-to back VSC-HVDC scheme in the year 2000 [33].
+Vdc/2
-Vdc/2
Va
Valve1
Valve2
Valve3
Valve4
Appendix 1A
228
The NPC converter suffers with unequal distribution of semi-conductor losses [137], due
to some of the valves being utilised more than others, leading to said valves experiencing
higher junction temperatures. The converter is switching its output voltage between 0V and
+Vdc/2 for the first half cycle. Providing the inverter is operating at unity power factor,
valve 2 will conduct the phase current for the entire half-cycle and valve 1 will conduct the
phase current for only a high majority of the half-cycle. Therefore valve 1 will have
slightly less conduction losses than valve 2. However, valve 1 also experiences switching
losses, which in [137] resulted in the overall losses for valve 1 being approximately double
that of valve 2. Since losses are related to switching frequency and phase current, the most
stressed valve will limit the permissible phase current and switching frequency for the
converter. The NPC VSC can also suffer from valve voltage imbalance, which under
certain conditions may cause valves 2 and 3 to experience higher voltages than valves 1
and 4 [138]. These issues may be overcome by using an Active Neutral Point Clamped
(ANPC) VSC [137, 138].
The ANPC VSC is a NPC VSC with the addition of an active switch connected in anti-
parallel with the NPC diodes, as shown in Figure A.13. The addition of the active switches
gives more switching states which allows the losses to be distributed more evenly. As an
example, for the NPC VSC to go from +Vdc/2 to 0V valve 1 must turn-off, whereas the
ANPC can switch between +Vdc/2 to 0V without switching valve 1 off. This could be
achieved by switching valve 2 off, valve 6 and valve 3 on and therefore leaving valve 1 on.
The additional switching states, in conjunction with an appropriate control strategy, can
more evenly distribute losses and reduce the maximum device junction temperature. This
results in a potential increase in converter output power or/and an increase in the switching
frequency. In [137] the converter output power rating increased by 20%, or the switching
could increase from 1050Hz to 1950Hz for an ANPC VSC compared to a NPC VSC.
In a NPC-VSC it is likely that all of the valves will be rated for the maximum stress of the
worst valve. It is unlikely that different valves will be designed and built depending on
their individual maximum stress rating due to the additional cost and time. HVDC schemes
are designed for two-way power transfer, although in many cases the power is
predominantly transferred in one direction. Therefore it is likely some valves will be
stressed more than others for the high majority of the time. Since the losses in an ANPC
Appendix 1A
229
VSC are distributed more evenly, the maximum stress that any valve experiences is
reduced. Therefore it is likely that the ANPC VSC is more reliable for the same rating.
Figure A.13: Single phase of an active neutral clamped voltage source converter
ABB utilised the ANPC VSC on the Murraylink and Cross Sound Cable projects in 2002
[33]. ABB’s HVDC Light technology then evolved again to its current 3rd
generation. The
third generation of HVDC Light reverts back to the two-level converter but employs a new
control strategy known as Optimum PWM (OPWM). OPWM can cancel selective
harmonics and therefore the switching frequency can be reduced [87]. The 350MW
±150kV VSC-HVDC scheme between Estonia and Finland, known as “Estlink”, employs
the OPWM at a switching frequency of 1050Hz [139]. This is a reduction of 900Hz in
comparison to the first generation of HVDC light used in the Tjaereborg VSC transmission
scheme [134].
Siemens VSC-HVDC technology, known as HVDC Plus, is based on a Modular Multi-
Level converter (MMC) approach. The MMC, as shown in Figure A.14, consists of six
converter arms. Each converter arm comprises a number of Sub-modules, SM, and a
reactor connected in series. The SM contains a two-level half-bridge converter with two
IGBT’s and a parallel capacitor. The SM is also equipped with a bypass switch, to remove
the SM from the circuit in the event that an IGBT fails, and a thyristor, to protect the lower
diode from overcurrent in the case of a DC side fault.
+Vdc/2
-Vdc/2
Va
Valve1
Valve2
Valve3
Valve4
Valve5
Valve6
Appendix 1A
230
Figure A.14: Three-phase MMC
Each SM in a MMC is switched at less than three times the fundamental frequency and
therefore the converter losses are less than the equivalent two-level and three-level
converters by about 1% per converter station [28, 140]. Figure A.15 shows the voltage
produced by the converter. The sinewave produced (orange) is very close to the desired
waveform, which means that the harmonic content is very low. Increasing the number of
voltage steps that are used to produce the desired waveform reduces the harmonic content.
The AC converter voltages for a 400MW MMC with 200 modules per arm is shown in
Figure A.16 (Trans Bay Cable project) [28]. This figure clearly shows that AC filtering is
not required with a high number of SMs per converter arm.
Figure A.15: Sinusoidal voltage synthesised from a MMC (modified from [28])
Figure A.16: Sinusoidal voltage synthesised from a 400MW MMC with 200 modules per arm (modified
from [28])
Single
IGBT
Sub-module
+Vdc/2
Va
Vua Vla
Vcap
Iarm
VSM
ArmSM2
SMn
SM1
SM2
SMn
SM1
SM2
SMn
Larm
IuaSM1
Rarm
Idc
SM1
SM2
SMn
SM1
SM2
SMn
SM1
SM2
SMn
-Vdc/2Ila
Vb
Vc
Idc
Appendix 1A
231
The MMC has a much lower voltage step (few kV) in comparison to a two-level and three-
level VSC-HVDC scheme which switches the entire DC voltage or half the DC voltage
respectively. This reduces the high frequency noise and component stresses. However, the
benefits of the MMC come at the expense of increased valve and control complexity.
Siemens have currently commissioned one HVDC Plus project (Trans Bay Cable), which
is a 400MW ± 200kV VSC-HVDC transmission scheme between Pittsburg and San
Francisco. Siemens have many more orders to use their HVDC Plus technology to connect
offshore windfarms such as Helwin1 and Borwin2 [141].
Alstom Grid have developed their VSC-HVDC technology under the trade name of
MaxSine, which also employs a MMC very similar to that of HVDC Plus. They have built
a 25MW VSC demonstrator in Stafford, UK, and have won a contract to supply a 750MW,
345kV VSC scheme for operation in 2014 [142].
ABB’s fourth generation converter is a Cascaded Two-level (CTL) converter topology
very similar to that of a MMC, as shown in Figure A.17. Each cell is a half-bridge two-
level converter with two valves and a parallel capacitor. The number of series and parallel
connected devices within the valve will depend upon the cell voltage and current
respectively. A phase leg consists of two phase arms which contain a number of cells. The
main difference between the CTL and MMC converter topologies is that the MMC SM
contains two IGBT’s whereas the CTL contains two valves (string of IGBTs).
The valves are initially blocked; the anti-parallel diodes conduct and the cell capacitance
charges-up providing the arm current is positive. The cell capacitor output voltage is
inserted into the circuit by switching the lower valve on and the upper valve off, the cell
capacitor charges for positive arm current and discharges for negative arm current. The cell
capacitor can be bypassed by turning the upper valve on and the lower valve off; hence the
cell output voltage is 0V.
Appendix 1A
232
Figure A.17: Single phase of a two-level cascaded converter (ABB 4th
Gen HVDC light)
Each cell is switched at a low frequency which is approximately three times the
fundamental frequency (150Hz for a 50Hz system). For a DC bus voltage of ± 320kV
about n=38 cells are required per arm, therefore the effective switching frequency of the
phase leg is 11.4 kHz. This is about 10 times greater than the third generation of HVDC
Light, which gives the converter a good dynamic response. The dynamic response for the
MMC is however likely to be better. A ±200kV MMC has approximately 200 SMs per
arm, which gives a dynamic response of 20kHz for a conservative switching frequency of
50Hz29
. An equivalent voltage rating (± 320kV) would result in more levels and therefore
an even better dynamic response.
According to [84] the nominal cell voltage for a CTL converter is approximately 18kV,
compared to a MMC SM voltage of approximately 2kV30
. The converter voltage for a CTL
converter is shown in Figure A.18.
29
The SM switching frequency is quoted as being less than three times the fundamental [140].Therefore the SM switching frequency equal to the fundamental switching is likely to represent the minimum dynamic performance for a converter. 30
Based on ±200kV MMC with 200 SMs per arm. Module voltage = DC voltage/ Number of SMs.
Appendix 1A
233
Figure A.18: CTL Converter voltage for a fundamental frequency of 50Hz with 17 cells per arm at a
nominal cell voltage of 17.6kV and cell switching frequency of 168.5Hz [84].
Due to the MMC having smaller voltage steps in comparison to the CTL converter, it is
able to produce a cleaner sinusoidal waveform as seen when comparing Figure A.16 with
Figure A.18. Therefore it is likely that the MMC generates a lower harmonic content than
the equivalent CTL converter. The MMC is also likely to have slightly lower losses than an
equivalent CTL converter due to its apparent lower module switching frequency. However
the CTL converter loss is quoted as being roughly 1% per converter [84] which is very
similar to the quoted losses of close to 1% per converter station for the MMC [28].
The MMC requires approximately nine times more modules than the equivalent CTL-
converter31
, which will result in a higher primary component count (capacitor, bypass
switch, thyristor, enclosure). The CTL converter on the other hand will require grading
circuits due the string of IGBTs connected within each valve. The MMC control system is
challenged with balancing nine times the number of capacitor voltages in comparison to
the CTL converter. However the CTL control system is likely to need to switch each cell in
and out of circuit at least three times per cycle, compared to possibly twice per cycle for
the MMC32
. Currently there is not enough information to conclude whether Siemens
HVDC Plus, Alstom Grid MaxSine or 4th
Generation HVDC Light will offer the greatest
performance. However with the current information, it is expected that the MMCs are
likely to offer the best performance in terms of harmonic content, dynamic response and
losses, but at the expense of a more costly and complex valve and control system.
There is little information on the size of the HVDC Plus and HVDC Light 4th
generation
converter stations. There are example layouts in [28, 44], but they are for very different
31
Based on 2kV SM voltage and an 18kV cell voltage. 32
The module switching frequency is only quoted as being less than three times the fundamental [140].
Appendix 1A
234
converter ratings which makes them difficult to compare. However since the MMC has
vastly more modules it is likely that the CTL converter will be more compact.
Thus-far all of the VSC-HVDC topologies which have been, or are likely to be, in
commercial operation in the near future have been discussed. The primary driver behind
each evolution of VSC-HVDC technology has been to reduce losses. The VSC losses have
been reduced from 3% to about 1%, but are still slightly higher than LCC at 0.8% per
converter [134].
Technology Year first scheme
commissioned Converter type
Typical losses per converter
(%)33
Switching frequency (Hz)34
Example project
HVDC Light 1st Gen
1997 Two-Level 3 1950 Gotland
HVDC Light 2nd Gen
2000 Three-level Diode
NPC 2.2 1500 Eagle Pass
2002 Three-level Active
NPC 1.8 1350 Murraylink
HVDC Light 3rd Gen
2006 Two-Level with
OPWM 1.4 1150 Estlink
HVDC Plus 2010 MMC 1 <150* Trans Bay Cable
HVDC MaxSine
2014 MMC 1 <150* SuperStation
HVDC Light 4th Gen
2015 CTL 1 ≈150* Dolwin 235
*switching frequency is for a single module/cell.
Table A.1: Evolution of VSC-HVDC technology
33
Losses are indicative of a particular converter type, not specific to a project. The HVDC Light losses are primarily estimated from a graph produced by ABB, which can be found in [44]. The figure for HVDC Plus losses is in [28]. HVDC MaxSine losses are based on the HVDC Plus losses since the converter designs are very similar. 34
Switching frequency for HVDC Light generations 1-3 are for the example projects and can be found in [134, 139]. Switching frequency for HVDC plus is based on [140]. The same value is also used for MaxSine. 35
Dolwin 2 is likely to be the first HVDC Light 4th
generation project based on correspondence with ABB and in [143] its states losses less than 1%, which implies 4
th generation technology will be used.
Appendix 1A
235
Table A.1 shows that the three main HVDC manufacturers are moving towards a multi-
level converter topology. The multi-level converter, as with the other VSCs, has the
following advantages in comparison to a CSC-HVDC scheme:
Can be connected to weak AC systems
Can control active and reactive power independently
Smaller footprint
Can use the cheaper, lighter and more robust XLPE cable
MT operation is less technically challenging
3 Conclusion
HVDC tends to be a more favourable transmission technology for offshore windfarms
located further than 50-100km from shore. This is due to the transmission cable’s
capacitance which requires charging and discharging every cycle in an AC system. The
charging current reduces the cable’s useful power transfer capacity. In a HVDC system,
once the cable’s capacitance is charged, nearly its entire current carrying capability can be
used for the transmission of active power.
LCC-HVDC is not a suitable technology for the connection of offshore windfarms. This is
primarily because LCC-HVDC requires a strong AC network at each end of the link and
the converter station is very large, which means the offshore platform is expensive. LCC-
HVDC cannot independently control active and reactive power and requires mass-
impregnated cable to handle the DC polarity reversal. Mass-impregnated cable is
expensive and time consuming to install and is not particular suitable for subsea
installation because it is heavy and inflexible.
The issues of LCC-HVDC can be mitigated, or partially overcome, with VSC-HVDC
technology. VSC-HVDC is a self-commutated converter and can therefore be connected to
a weak AC network such as an offshore windfarm. The VSC-HVDC footprint is about
40% smaller than the equivalent LCC-HVDC footprint36
, which results in a large cost
saving, particularly for offshore schemes. VSC-HVDC can control the output AC voltage
magnitude and phase independently which gives independent active and reactive power
capability. XLPE cable can be used on VSC-HVDC schemes because it does not change
36
Estimated from a space saving diagram comparing HVDC Plus with LCC-HVDC in [28].
Appendix 1A
236
the DC voltage polarity for power reversal. This type of cable is cheaper, lighter and more
flexible than mass-impregnated cable.
VSC-HVDC was pioneered by ABB in 1997. Since then there have been several
evolutions of VSC-HVDC technology with the main focus on reducing the losses to
similar levels of LCC-HVDC. The three leading manufacturers of HVDC technology have
all moved towards a form of multi-level converter topology, which has seen losses reduce
to about 1% per converter, which is comparable to the 0.8% per converter for LCC-HVDC.
Therefore it is fully expected that multi-level VSC-HVDC will facilitate the transmission
of power from the future offshore windfarms which require a HVDC link.
Appendix 2A
237
APPENDIX 2A – COMPONENT RELIABILITY INDICES
1 Introduction
Reliability statistics for the components in a VSC-HVDC scheme are extremely sparse.
The following papers/reports produced by academic institutions and industry are used as
the main basis for the derivation of reliability statistics for the VSC-HVDC scheme used in
this thesis:
1. LCC-HVDC data from academic paper [15] [Billinton et al., “Reliability
Evaluation of an HVDC Transmission System Tapped by a VSC Station"]
2. VSC-HVDC data from academic paper [15]
3. VSC-HVDC data from industrial paper report [144] [Statnett and DNV, “Design,
operation and availability analysis of a multi-terminal HVDC grid - A case study of
a possible Offshore Grid in the Norwegian Sea”]
4. VSC-HVDC data from Cigre paper [16] [ABB and STRI, “Reliability study
methodology for HVDC grids”]
Source 1 and 2 are from a recent IEEE transactions paper produced by respected authors in
the area of power systems reliability, including Roy Billinton. The third source is a report
produced by Statnett and Det Norske Veritas (DNV). The fourth source is a Cigre paper
written by authors from ABB and STRI. Therefore the data from these sources is expected
to be credible. Due to the limited data available some degree of estimation is unavoidable.
Where this has been done the rational used is explained.
2 Gas-insulated Switchgear (GIS) Failure Statistics
Unfortunately sources 1-4 only gave failure statistics for an AC circuit breaker. However
since the circuit breaker is the main component of a GIS switchbay, it is worth analysing
the failure statistics used in sources 1-4 to give an indication of the failure statistics for the
GIS. Table A.2 shows the reliability statistics for AC circuit breakers given in academic
and industrial papers.
Table A.2: Circuit breaker MTTF and MTTR values given in sources 1 to 4
Source MTTF(yr) MTTR(hr) Scheme
1 66.7 50 500kV
2 1000 40 500kV
3 405 190 132kV Offshore
4 50 200 >500kV
Appendix 2A
238
It is clear from Table A.2 that the circuit breaker reliability statistics used for reliability
studies in academic and industrial papers vary significantly. Source 3 and 4 reference Cigre
publications for their reliability statistics. At the time of investigation, the last known high
voltage circuit breaker survey was published by Cigre in 1994. This publication presented
results from two surveys, one conducted between 1974 and 1977 (all circuit breaker
technologies) and the other conducted between 1988 and 1991 (only SF6).
Table A.3: Cigre high voltage circuit breaker reliability data
The MTTF values for the survey conducted in 1988-1991 are more than three times higher
than the values from the 1974-1977 survey. This increase in MTTF for the circuit breakers
in the 1988-1991 survey is thought to be due to improvements in circuit breaker
technology and due to the utilities doing a better job of collecting statistics. The increase in
downtime for the MTTR for circuit breakers in the 1988-1991 survey was cited as being
primarily due to the time taken to obtain a specific spare part for the SF6 circuit breakers.
According to the ODIS 2011 document [14], Gas-insulated Switchgear (GIS) bays will be
installed on all offshore platforms, and on onshore platforms located less than 5km from
the sea. The final results for two surveys on the reliability of gas-insulated substations have
been published. The first international survey was circulated in 1991 and the second survey
was circulated in 1996 [27]. The major failure statistics from the 2nd
international survey
for GIS commissioned after 1985 are shown in Table A.4.
Table A.4: Failure statistics from the 1996 survey for GIS commissioned after 198537
Comparing the values from the Cigre 1988-1991 survey in Table A.3 with the values in
Table A.4, it is clear that a GIS bay tends to take longer to repair than an AC circuit
37
MTTF is calculated by taking the reciprocal of the failure rate. It is assumed that the failure rate is based on the number of circuit breaker bay-years in service. (I.e. the reciprocal of the failure rate is the MTTF not the MTBF). In any case the difference between MTTF and MTBF will be very small.
Survey Voltage(kV) MTTF (yr) MTTR(hr)
200-300 38.760 58.5
300-500 21.978 83.8
200-300 122.850 54.6
300-500 82.645 162.5
Cigre 1974-1977
Cigre 1988-1991
Component MTTF (yr) MTTR(hr)
200-300kV GIS 149 192
300-500kV GIS 39 192
Appendix 2A
239
breaker and that the higher voltage (300-500kV) GIS has a shorter MTTF than an AC
circuit breaker. This is not particularly surprising considering a GIS bay contains an AC
circuit breaker as well as other equipment such as disconnectors.
The data given in Table A.2, Table A.3 and Table A.4 can be used to estimate the failure
statistics for a 220/275kV GIS switchbay and a 400kV switchbay commissioned in 2011. It
is fair to assume that the MTTF of a GIS switchbay in 2011 would be much higher than a
GIS switchbay commissioned between 1985 and 1996. The MTTF from the 1996 survey
for 200-300kV GIS commissioned after 1985 was 45% higher than the GIS commissioned
after 1985 from the 1991 survey. The MTTF for AC circuit breakers 1988 survey was
more than 300% higher than the values given in the 1974 survey. Therefore, it is justifiable
to assume that the MTTF for a 220/275kV GIS switchbay and a 400kV switchbay
commissioned in 2011 would be 250 years and 100 years respectively. These figures lie
within reasonable ranges as shown by the figures used in academic and industrial papers in
Table A.2. It is also worth mentioning that ABB have quoted a Mean Time Between
Failure (MTBF) figure of up to 1000 bay-years for their gas-insulated switchgear [145].
Based on the assumption that GIS today would be somewhat easier to fix than 15-25 years
ago, and that the spare parts are more readily available, it is assumed that the MTTR values
will be reduced. Furthermore the supply chain is computerised with modern telecoms
which would help to improve service levels. Therefore the MTTR for modern GIS is
assumed to be 120 hours.
As mentioned in the main body access times for offshore platforms vary considerably
depending on a number of factors. The 1996 GIS survey stated that about 70% of repairs
could be carried out on-site and required a spare part and/or enclosure [27]. It is assumed
that the high majority of spare parts could be transported by helicopter. Therefore the time
to access the offshore platform to repair a GIS switchbay is taken as 84 hours (70%
helicopter, 30% medium vessel). It is estimated that about 20 hours of the offshore access
time is spent performing administration related tasks which could be done concurrently
with the time spent obtaining spare parts. Therefore the MTTR used for the offshore GIS
switchbay is 184 hours. Table A.5 shows the estimated reliability indices for GIS.
Appendix 2A
240
Table A.5: Estimated reliability indices for GIS
3 Transformer Failure Statistics
Table A.6 shows the reliability statistics for transformers given in sources 1 to 4.
Table A.6: Transformer failure statistics given in sources 1 to 4
The transformers used in LCC-HVDC schemes (source 1) are more complex and
experience greater stress than the transformers in the VSC-HVDC schemes (source 2).
This would explain the better reliability statistics for the transformer from source 2.
The reliability statistics provided by source 4 are from the latest transformer failure
statistics survey published by Cigre in 1983 for transformers between 300-700kV. After
analysing the 1983 report, it is clear that the statistics from source 4 are based on an
autotransformer with and without an On-Load Tap-changer (OLTC). Analysis of the 1983
report shows that for an autotransformer with an OLTC, the MTTF is 98.33 years and for
an autotransformer without OLTC the MTTF is 17.2 years38
. This is somewhat surprising
and the report noted that the abnormally high failure rate of autotransformers without
OLTC could be in part explained by the failure of the transformers belonging to a certain
network. In other words, the MTTF of 17.2 years for an autotransformer without OLTC
should be used with a degree of caution and therefore the figure with and without OLTC as
used in source 4 should also be used with a degree of caution. In any case, HVDC schemes
use transformers with an OLTC and tend not to use autotransformers, because they cannot
provide galvanic isolation between the AC and DC sides. Therefore, the statistic given in
source 4 may not be representative of a transformer used in a HVDC scheme.
38
MTTF is calculated by taking the reciprocal of the failure rate. According to the Cigre report the failure rate is calculated based on the number of transformer-years in service (i.e. the reciprocal of the failure rate is the MTTF not the MTBF).
Component MTTF (yr) MTTR(hr)
Offshore switchbay 250 184
400kV onshore switchbay 100 120
275kV onshore switchbay 250 120
Source MTTF (yr) MTTR (hr) Scheme
1 14.29 1200 500kV
2 20 1000 500kV
3 225 672 132kV Offshore
4 41.67 2160 >500kV
Appendix 2A
241
The 1983 Cigre report also gave statistics for substation station transformers. The MTTF
for a 100-300kV substation transformer with an OLTC and a 300-700kV transformer is
62.5 years and 50.85 years respectively. Considering the survey was conducted more than
30 years ago, it is reasonable to suggest that the MTTF for a modern transformer is much
improved. Therefore an estimated MTTF of 95 years for a 100-300kV transformer and 80
years for a 300-700kV transformer will be used in this availability analysis. These values
are still much less than the estimated values given by DNV in source 3.
Unfortunately, the 1983 Cigre report did not publish the mean downtime for non-
autotransformers in the 300-700kV range as it was deemed not significant. However, the
mean downtime with a 95% confidence level for a 100-300kV transformer with an OLTC
was reported as being between 46 and 76 days. The MTTR is taken as the mean, 61 days
(1464 hrs). Considering it is now more than 30 years since the survey was conducted, an
estimated MTTR value of 42 days (1008 hrs) will be assumed. This figure is based on the
assumption that technology today allows a quicker diagnosis and repair of the transformer
failure.
In the event a transformer fails it is normally shipped back to the factory for repair [146].
There have been situations where it is so difficult to send the transformer back to the
factory that a fully equipped workshop has been constructed on-site. It is difficult to send
an offshore transformer back to the factory, but due to the lack of space on an offshore
platform it would be extremely rare, if not impossible, to construct a workshop on the
platform. Therefore in the event a transformer fails it is expected it would need to be
shipped back to the factory for repair.
In this report, the time it takes to access an offshore platform with a transformer has been
estimated at three weeks (504 hours). This figure was based on the transportation of a large
item, such as a transformer, to the offshore platform. The offshore access time required for
repairing an offshore transformer would be split into two parts. The first part would be to
transport the transformer back to shore. The second part would occur once the transformer
is repaired and must be transported back to the offshore platform. Therefore the offshore
access time for repairing the transformer must at least be greater than three weeks. A
significant portion of the three weeks access time would be due to delays in acquiring the
large vessel at very short notice. However the vessel could be booked well in advance for
returning the transformer back to the offshore platform. Therefore, the access time to
Appendix 2A
242
transport the transformer to the offshore platform is estimated to be reduced to one week.
Therefore the total access time to repair the offshore transformer is estimated to be 4
weeks.
It is assumed that one week of the MTTR for the onshore transformer is spent sourcing
spare parts. It is feasible that the transformer could be diagnosed using non-invasive tests
on the offshore platform [147]. This would allow the spare part to be sourced while the
transformer is being transported back to the factory. Therefore the MTTR for the offshore
transformer is estimated to be three weeks longer than the MTTR for the onshore
transformer. For comparison DNV increased the MTTR for the offshore transformer by
three weeks in their availability analysis in source 3. Table A.7 shows the estimated
reliability indices for the transformers.
Table A.7: Estimated reliability indices for transformer
4 Converter Reactor Failure Statistics
Table A.8 shows the reliability statistics for phase reactors given in sources 1 to 4.
Table A.8: Converter reactor reliability values given in sources 1 to 4
Only source 3 has stated reliability values for the converter reactor. Unfortunately, there
are no other known author publications which have given reliability values for the
converter reactor. It is worth noting that availability statistics for the Murraylink VSC-
HVDC scheme have been published by ABB in a Cigre paper [33] as shown in Table A.9.
Table A.9: Murraylink energy availability
The very low availability of the scheme in 2007 was due to a fault in the phase reactor,
which was most likely caused by a fault in an external light fitting which led to a fire on
Component MTTF(yr) MTTR(hr)
Offshore Transformer 95.00 1512.00
Onshore Transformer 95.00 1008.00
Source MTTF (yr) MTTR (hr)
3 7 24
Energy 2003 2004 2005 2006 2007 2008 2009 Average
Total 95.18 97.08 95.39 98.92 90.56 99.17 99.37 96.52429
Scheduled 96.49 98.77 97.96 98.51 97.91 99.12 99.13 98.27000
Forced 98.21 98.04 97.11 99.33 90.98 99.86 100.00 97.64714
Murraylink
Appendix 2A
243
the reactor [33]. It was noted that one of the reasons the repair took so long was because
the building was not designed to accommodate an easy replacement. That said the
Murraylink went into service in 2003 and it is expected that new schemes would be
designed to allow easier replacement of components.
The values from DNV seem reasonable, after all DNV is a well-respected risk management
company and therefore their values are expected to be credible. The only slight concern is
that the MTTR values for both the onshore and offshore converters are the same. In the
event a converter reactor fails it is assumed it would need to be replaced rather than
repaired on-site because it is a single unit and has no moving parts. A converter reactor is
too large to be shipped via a helicopter, therefore a medium sized vessel would be
required. The offshore access time for the converter reactor is 168 hours. It is expected that
a converter reactor is readily available to allow replacement within 24 hours. Since there is
no time delay in sourcing the component, the offshore MTTR is equal to the onshore
MTTR plus the offshore access time. Table A.10 shows the estimated reliability indices for
the converter reactor.
Table A.10: Estimated converter reactor reliability indices
5 MMC Failure Statistics
Table A.11 shows the reliability statistics for MMCs given in sources 1 to 4.
Table A.11: MMC failure statistics given in sources 1 to 4
It is unclear if sources 1 and 2 have included the Control and Protection (C&P) systems, as
well as the cooling and ventilation systems, in the reliability values for the converter.
However, it is assumed that they have, since these systems are not considered separately in
the sources and the converter would be the most appropriate component in which to
Component MTTF (yr) MTTR (hr)
Onshore Converter Reactor 7 24
Offshore Converter Reactor 7 192
Source MTTF (yr) MTTR (hr) Comment 1 1 5 LCC
2 2 4 Two-level VSC
3 2 24 Two-level VSC
4 0.71 4.1 VSC*
*Value based on LCC and includes the C&P and the DC
Equipment
Appendix 2A
244
include these systems. Sources 2 and 3 do not explicitly state that their reliability statistics
are for a two-level VSC converter, however, since both systems include AC filters it is fair
to assume that they are for a two-level converter. Source 3 has considered the C&P as well
as the cooling and ventilation systems separately. Therefore the values given by source 3
are purely for the IGBT converter system.
The reliability statistics given for a VSC in source 4 are based on actual forced outage
statistics collected for LCC-HVDC schemes between 2005 and 2006 [16]. However the
value for source 4 given in Table A.11 is a combined value for the converter, C&P and DC
equipment. Based on the same analysis method used in source 4, the MTTF and MTTR for
the converter only are 2.1 years and three hours respectively. These values account for the
cooling and ventilation systems, but not the C&P and DC equipment.
There has been no actual reliability statistics published for converters used in VSC-HVDC
schemes. However based on the values given in Table A.11 it is assumed that the MTTF
and MTTR for a two-level VSC are 2 years and 12 hours respectively. The MMC has a
significantly higher component count than a two-level VSC, which is likely to reduce the
reliability of the converter. However, it does not suffer the high stress of switching all
IGBTs in the valve simultaneously. It is reasonable to assume that the MMC at this time
will be slightly less reliable than the two-level converter due to the lack of experience with
this type of converter in HVDC schemes and the higher component count. Therefore, the
MTTF will be reduced to 1.9 years as a placeholder to reflect the expected increase in
failure rates for MMC. The MTTR will be kept the same at 12 hours for an onshore
converter. The MMC reliability indices account for the cooling and ventilation systems.
The failure of a MMC is likely to require the replacement of a SM. It is justifiably assumed
that spare SMs would be readily available since they require minimum storage space and
are critical for converter operation. SMs are fairly small components and could be
transported by a helicopter with the engineer. Since the reliability indices for the MMC
includes the cooling and ventilation systems, the size of spare parts for these systems must
also be taken into account. The critical components which have high failure rates in a
cooling plant are electrical motors. It is expected that electrical motors could be transported
by helicopter/small vessel. The offshore access time for such a component has been
estimated at 48 hours and as such the MTTR for the offshore converter is 60 hours. Table
A.12 shows the estimated MMC reliability indices.
Appendix 2A
245
Table A.12: Estimated MMC reliability indices
6 Control System
Table A.13 shows the reliability statistics for the control system given in sources 1 to 4.
The reliability statistics from source 3 are a DNV internal estimate for a single VSC
control system. The C&P systems for HVDC schemes are normally duplicated [30].
Therefore the availability of the duplicated control system must be calculated, as shown in
Table A.14.
Table A.13: Control and protection failure statistics given in sources 1 to 4
Table A.14: Availability of DNV duplicated control system
Providing the repair time for the DNV duplicated C&P system is fixed at 9 hours the
MTTF for the duplicated control system would be approximately 930 years. This value has
been calculated in (A.11) by rearranging equation (A.7) for MTTF and substituting the
duplicated control system availability values.
MTTF
AMTTF MTTR
(A.7)
MTTF
MTTF MTTRA
(A.8)
(1 )MTTF A A MTTR (A.9)
(1 )
A MTTRMTTF
A
(A.10)
0.9999989 9
8181809 930(1 0.9999989)
hrsor yrs
(A.11)
Component MTTF (yr) MTTR (hr)
MMC Onshore 1.9 12
MMC Offshore 1.9 60
Source MTTF (yr) MTTR (hr)
3 1 9
4 1.60 3
Capacity Control 1 Control 2 Probability Availability
1 1 0.99795
1 0 0.00103
0 1 0.00103
0 0 0 0.00000 0.0000011
100% 0.9999989
Appendix 2A
246
The values given in source 4 are from the actual forced outage statistics collected for LCC-
HVDC schemes between 2005 and 2006. Therefore, the MTTF statistic is actually the
mean time to failure of both C&P systems, as the scheme could operate if only one of the
two C&P systems failed. Therefore, the availability of the duplicated C&P system is
0.99979, which is significantly less than the availability of the duplicated control system
from the DNV reliability data in source 3. This is further highlighted by the difference
between the calculated MTTF value from the DNV data and the MTTF value from source
4. It is expected that the reliability data given in source 4 is more realistic than source 3
since this is actual HVDC C&P failure data.
The hardware for the C&P system for a LCC-HVDC system is similar to a MMC VSC-
HVDC system. Therefore, the data given in source 4 would provide a good basis for
estimating the reliability indices for the MMC VSC-HVDC C&P system. The MMC Valve
Based Electronics (VBE), the interface between the C&P system and the converter, is
different from that of a LCC-HVDC scheme due to the higher number of levels. The
software is also more complex, because the control system must balance the capacitor
voltages in the MMC valve and turn each level on and off individually. However it is
expected that a modern C&P system would be more reliable than an older C&P system.
The World HVDC survey obtains data from many schemes using C&P systems of different
ages. Therefore all things considered, a MTTF and MTTR of 1.6 years and 3 hours will be
used in this availability analysis.
It is assumed that many control system faults could be solved without attending the site
(i.e. via remote access). In the event that the problem cannot be solved via remote access
an engineer would have to attend site. Spare parts for control systems, such as digital
signal processing cards, are very small and therefore access via helicopter is suitable. It is
assumed that 30% of faults on the offshore control system require an on-site visit.
Therefore the MTTR of the offshore control system is equal to MTTR for the onshore
control system plus 30% of the time required to access the offshore platform with a small
component (3+48x0.3=17hours). Table A.15 shows the estimated reliability indices for an
onshore and offshore control system.
Appendix 2A
247
Table A.15: Estimated control system reliability indices
7 DC Switchyard
Table A.16 contains the reliability indices for the DC equipment from sources 1 to 4.
Table A.16: DC equipment failure statistics given in sources 1 to 4
There is significant difference between the DC filter reliability indices between sources 1
and 2. The DC filters are for different schemes but it is unlikely that the VSC DC filter is
400 times more reliable than an LCC filter based on the MTTF. The DNV (source 3)
reliability indices for the VSC DC filter appear to be more realistic than source 2. Sources
1-3 appear to have included what they consider the key components for their analysis,
whereas source 4 has accounted for an entire DC switchyard. Source 4 has accounted for
all the VSC DC equipment by analysing the failure statistics for DC equipment in the
2006-2007 World HVDC survey (LCC) published in 2008.
The major equipment in a MMC DC VSC switchyard consists of HV capacitor banks (if
required), line reactors, measurement transducers and switchgear [29]. The major
equipment in a LCC DC switchyard consists of DC harmonic filters, smoothing reactors,
measurement transducers and switchgear [30].
Component MTTF (yr) MTTR (hr)
Onshore Control System 1.6 3
Offshore Control System 1.6 17
Source MTTF (yr) MTTR (hr) Scheme
20 300 Smoothing Reactor
2.5 12 LCC DC Filter
1 4 VSC HVDC Switch/breaker
1000 5 VSC DC Filter
7 24 HV DC Bus
6 24 VSC DC Filter
4 3.333 6.4 Based on Data from 2005-2006 LCC Survey
1
2
3
Appendix 2A
248
Figure A.19: Image of a MMC VSC DC switchyard (left, modified from [29]) , Image of a LCC DC
switchyard (right modified from [31])
Since there is significant similarity between the DC switchyards, the failure statistics from
the World HVDC survey (LCC) could be used to estimate the reliability indices for the
MMC VSC-HVDC DC switchyard. The latest World HVDC survey was published in 2010
for data collected on LCC-HVDC schemes during 2007-2008. Back-to-back HVDC
schemes do not normally require smoothing reactors or DC filters [30]. Therefore only the
data for transmission schemes should be considered. In the 2007-2008 HVDC survey, data
was collected from 18 transmission schemes (8 monopole and 10 bipole). Monopole
schemes have one DC switchyard at each end of the scheme, whereas bipole schemes have
the equivalent of two DC switchyards at each end of the scheme. The failure rate for a
single DC switchyard can be calculated by summing the number of failures for the 18
transmission schemes and dividing by the number of DC switchyards (56). The MTTR is
obtained by dividing the total number of outage hours by the number of failures. The
reciprocal of the failure rate is the Mean Time Between Failures (MTBF). The MTTF is
the MTBF minus the MTTR. The average MTTF and MTTR has been calculated and is
shown in Table A.17.
There is a significant difference between the MTTF and MTTR calculated in Table A.17
and the reliability indices from the 2005-2006 survey. However, source 4 calculated the
reliability indices for a DC switchyard from both back-to-back and transmission schemes.
Source 4 also assumed that 50% of the HVDC schemes in the 2005-2006 survey were
monopole and 50% were bipole. Since the 2007-2008 survey is the most recent, and the
analysis of the reliability indices is more accurate for a transmission scheme, these indices
will be used in this availability analysis.
Line Reactor
Appendix 2A
249
Table A.17: Analysis of the DC equipment failure statistics from the World 2007-2008 HVDC survey
It is worth noting that although there are 18 transmission schemes which would normally
equate to 56 converters (8x2+4x10) further analysis of the data shows that there are
actually 80 converters. This is because a number of schemes contain more than one
converter per pole. Nelson River BP 2 for example has 3 six-pulse converters connected in
series per pole, giving twelve converters for the bipole instead of the usual four [148]. This
is unlikely to affect the reliability indices for DC switchyards as there should still be about
the same amount of DC equipment for standard HVDC schemes with one converter per
pole. However calculating the reliability indices for the HVDC converters from the World
HVDC surveys should take the number of converters per pole into consideration to ensure
a high degree of accuracy.
In order to adjust the MTTR for the offshore DC switchyard, the most common types of
repair and size of spare parts would need to be known. Unfortunately, the HVDC surveys
do not give this level of detail. However, by analysing the outage statistics due to DC
equipment failures it may be possible to get an indication of the size of component
required for the most common failures. In 2007 there were twelve DC equipment failures
causing a total of 368 outage hours, of which a single failure accounted for 314 hours [26].
Therefore the MTTR excluding the single major failure was only 4.9 hours. Such a small
repair time is likely to indicate that only small parts which were readily available, if any,
were required. The 314 hour outage indicates the repair required a large component. The
314 hour outage was due to a smoothing reactor failure [26], which is a large component as
shown in Figure A.19. Only five of the 18 failures in 2008 required a repair time in excess
of 10 hours. This analysis indicates that the high majority of DC switchyard repairs require
a small spare part, if any, and that the spare part is readily available. Therefore it is
Parameters 2007 2008 Average
No of schemes 19 19
Number of monopoles 9 9
Number of bipoles 10 10
No of Failures 12 18
Failure per scheme year 0.63 0.95
Failures per Switchyard 0.21 0.31
MTBF (yr) 4.8333 3.22 4.03
Repair time (hr) 367.50 386.80
MTTR (hr) 30.63 21.49 26.06
MTTF (yr) 4.83 3.22 4.02
Appendix 2A
250
estimated that 80% of offshore DC switchyard repairs could be carried out via
helicopter/small vessel and the remaining 20% via a small vessel39
. Furthermore, since the
analysis indicates that the majority of spare parts are readily available it is assumed that
very little time could be saved performing parallel tasks and it is therefore neglected.
Hence the MTTR for the offshore DC switchyard is the MTTR for the onshore DC
switchyard plus the offshore access time for the DC switchyard. The offshore access time
to the DC switchyard is estimated to be 72 hours (0.8x48+0.2x168). Table A.18 shows the
estimated reliability indices for the DC switchyard.
Table A.18: Estimated reliability indices for DC switchyard
8 DC Cable
Only source 3 contained reliability indices for cables as shown in Table A.19.
Table A.19: DC cable failure statistics given in sources 1 to 4
The results from the latest reliability survey for cable systems were published by Cigre in
2009 [32]. The survey ended in 2005 and was for a 15 year period. At the end of 2005
approximately 7000 circuit km of submarine cable was identified as being in service.
DC-XLPE cable is the type of cable which is most likely to be used for VSC-HVDC
schemes. Unfortunately the failure rates for DC-XLPE cables were not given in the report.
The failure rate for all submarine cable types, with the exception of DC Self Contained Oil
Filled (SCOF) cables, due to internal faults, was zero. Therefore, the failure rate due to
internal faults for DC-XLPE cable will be assumed to be zero.
The average failure rate for all types of cable technology and voltage ratings due to
external/unknown damage gives a failure rate of 0.217 failures per year per 100km of
circuit. Approximately 55% of these submarine cable failures were reported to be at a
39
Based on the assumption that an outage time of less than 10 hours for a single fault indicates a small spare was required. In 2007, 2 of the 12 failures caused outages in excess of 10 hours while in 2008, 5 of the 18 failures caused outages in excess of 10 hours. Therefore approximately 80% of failures required a small part.
Component MTTF(yr) MTTR(hr)
Onshore DC Switchyard 4.02 26.06
Offshore DC Switchyard 4.02 98.06
Component Failure rate (occ/yr/100km) MTTR (hr)
DC Cable 0.05 1440
Appendix 2A
251
location where the cable was unprotected40
. Submarine HVDC cables are normally buried
at depths of 1m to offer protection [111]. For cable routes where direct burial is unsuitable
due to the sea-bed conditions (e.g. solid rock) other protection methods such as concrete
mattressing may be employed [111]. Considering that HVDC submarine cables will have
installation protection, the failure rate is calculated to be approximately 0.1 failures per
year per 100km circuit. This failure rate is nearly double the failure rate used in the DNV
report. It is important to note that submarine cable failure rates are very subjective. They
are heavily influenced by many factors including, fishing activity, installation protection
method, awareness of cable routes, water depth, and hardness of the sea-bed. In this
availability analysis it will be assumed that the annual failure rate is 0.07 failures per
100km of circuit. This is a reasonable assumption based on data from the DNV report and
the Cigre survey.
The offshore converter and onshore converter are located 165km apart. Therefore the total
cable length is 330km, but the circuit length/route length is assumed to be 165km41
. The
average repair time for submarine cables in the Cigre 2009 was 60 days [32] which is the
same as the DNV MTTR. Therefore this availability analysis will assume a MTTR of 60
days (1440hrs) for submarine cables. Table A.20 shows the estimated reliability indices for
the submarine cable.
Table A.20: Estimated reliability indices for submarine cable42
40
There were a total of 49 submarine cable failures recorded of which 4 were internal failures. 25 of the 45 external/unknown failures occurred at a location that the cable was unprotected. 17 faults occurred on cables that were protected. It is unclear if the remaining three faults (including two terminal faults) occurred on protected or unprotected cables. The vast majority of the cables surveyed (>80%) employed some form of protection [149]. Therefore by assuming that the smaller number of unprotected cables can be neglected and attributing the three unknown faults to the protected cables, the failure rate of a cable employing some form of protection can be approximately calculated by (20/45)*0.217=0.096≈0.1. 41
The questionnaire for the Cigre survey gives an example of how the circuit length is calculated. “A 5 km
long double-circuit connection with three phases and two cables per phase should be reported as 10 circuit km even though it has 60 km of cable core”. Therefore from this example 330km of core cable has a circuit length of 165km.
42 The reciprocal of the failure rate was assumed to be the MTBF. MTTF=MTBF-MTTR.
Component Failure rate (occ/yr/100km) Circuit Length (km) MTTF (yr) MTTR (hr)
DC Cable 0.07 165 8.493625 1440
Appendix 2B
252
APPENDIX 2B – RELIABILITY CONCEPTS AND DEFINITIONS
1 Reliability Concepts and Definitions
Reliability – is the probability of a device performing its purpose adequately for the period
of time intended under the operating conditions encountered [13].
Maintainability – is the probability that a component/device/system will be retained or
restored to specified working condition.
Mean Time To Failure (MTTF) – is the average time from the instance a
component/device/system enters a working state until a component/device/system enters a
failed state. This may also be defined as the component/device/system’s uptime.
Mean Time To Repair (MTTR) - is the average time it takes to restore a
component/device/system to a specified working condition from the instance the
component/device/system failed. This may also be defined at the
component/device/system’s downtime.
Mean Time Between Failures (MTBF) – is the average time elapsed between a
component/device/system entering a working state until the component/device/system re-
enters a working state. This may also be defined as the cycle time, which is the uptime plus
the downtime.
Availability – is the probability of finding the component/device/system in the operating
state at some time into the future [13]. The availability of a component with two states can
be calculated by equation (A.12).
Uptime MTTF MTTF
AUptime Downtime MTTF MTTR MTBF
(A.12)
Failure rate – is the number of times a component/device/system is expected to fail per
unit of time, or the number of times a component/device/system is expected to fail per unit
of time the component/device/system is in a working condition. The failure rate in this
report has two definitions because different reliability surveys determine the failure rate
from one of two methods. Some surveys record the number of failures for a sample of
components for a specified period time without suspending time for a component upon
failure, whereas other surveys suspend time when a component enters a failed state.
Appendix 2B
253
As an example, consider a fictitious reliability survey which collected failure statistics
from ten transformers for ten years during their useful life, giving 100 transformer-years of
data. The survey concluded that there were four failures in that time and that the average
time to repair each failure was three months. The number of times a transformer is
expected to fail per unit of time is calculated as follows:
4
0.04( / )10 10
occ yr
(A.13)
Equation (A.13) states that the failure rate for a transformer is 0.04 failures per year.
However this method for determining the failure rate did not suspend time when each
transformer was in a failed condition. The number of times the transformer is expected to
fail per unit of time when the transformer is in a working condition is calculated as
follows:
4
0.0404040( / )10 10 (4 3 )
occ yrmonth
(A.14)
Failure rates in this report are assumed to be constant, see Figure A.21. The reciprocal of
equation (A.13) is the MTBF, whereas the reciprocal of equation (A.14) is the MTTF.
Therefore the MTTF and MTBF can be calculated as follows and their relationship is
shown in Figure A.20:
1
24.750.0404040
MTTF years (A.15)
1
250.04
MTBF years (A.16)
24.75 3 25MTBF MTTF MTTR months years (A.17)
Figure A.20: Relationship between MTBF, MTTF and MTTR
MTBF
MTTR
MTTF time
1
0
Appendix 2B
254
Reliability surveys normally specify the failure rate and MTTR. Therefore if the reliability
survey has calculated the failure rate for a component without suspending time for failed
components, the MTTF may be obtained from equation (A.18).
1
MTTF MTTR
(A.18)
It is not always clear which method the reliability survey has used to calculate the failure
rate. However, in many cases this will not significantly impact on the calculated
availability of the component, since the MTTF is typically much greater than the MTTR.
The lifecycle of a product can be described by three distinct phases, as shown by the bath-
tub curve in Figure A.21. The infant mortality phase is characterised by a high failure rate
which decreases with time, and could be due to manufacturing errors or improper design.
Product failures in the second region (useful life) occur purely by chance and as such the
failure rate is constant. The third region (end of life) of the bath-tub curve shows the
product is wearing out.
Figure A.21: Product lifecycle from [150]
The failures rates in this report are assumed to be constant with time (i.e. phase one and
three are neglected). This is a fair assumption since components go through an extensive
testing process before they are installed at site and it is expected that the life of the product
has been designed to be equal to or less than the useful life of the product. In other words,
it is expected that manufacturing errors or improper design issues would be discovered in
the testing phase and that if a product is expected to be in operation for 25 years the
manufacture would have designed the product to have a useful life of at least 25 years.
Appendix 2B
255
Mean Time to Access Offshore Platform (MTTAOP) – is the average estimated time it
takes to reach an offshore platform with a component of a particular size.
Mean Offshore Access Time (MOAT) – is the average estimated offshore access time for
a particular component.
Mean Time Performing Concurrent Tasks (MTPCT) – is the average time spent
performing tasks associated with repairing a component located onshore which can be
conducted in parallel with tasks related to the MOAT for the component.
Example
A GIS switchbay located onshore has an estimated MTTR of 120 hours. It is estimated that
70% of GIS failures require a small sized spare part and 30% require a medium sized spare
part.
0.7 ( ) 0.3 ( )
0.7 48 0.3 168 84
MOAT MTTAOP small MTTAOP medium
MOAT hours
(A.19)
In addition it is estimated that 20 hours of the MOAT is spent on administration related
tasks which can be performed in parallel with the time spent obtaining spare parts
(accounted for in the onshore MTTR).
20MTPCT hours (A.20)
120 84 20 184offshore onshoreMTTR MTTR MOAT MTPCT hours (A.21)
Appendix 2C
256
APPENDIX 2C – MTDC GRID ANALYSIS
The full truth table for 7 variables is shown below:
State OFNA OFNB OFNC C1 C2 Sub 6 Sub 7
1 1 1 1 1 1 1 1
2 1 1 1 1 1 1 0
3 1 1 1 1 1 0 1
4 1 1 1 1 1 0 0
5 1 1 1 1 0 1 1
6 1 1 1 1 0 1 0
7 1 1 1 1 0 0 1
8 1 1 1 1 0 0 0
9 1 1 1 0 1 1 1
10 1 1 1 0 1 1 0
11 1 1 1 0 1 0 1
12 1 1 1 0 1 0 0
13 1 1 1 0 0 1 1
14 1 1 1 0 0 1 0
15 1 1 1 0 0 0 1
16 1 1 1 0 0 0 0
17 1 1 0 1 1 1 1
18 1 1 0 1 1 1 0
19 1 1 0 1 1 0 1
20 1 1 0 1 1 0 0
21 1 1 0 1 0 1 1
22 1 1 0 1 0 1 0
23 1 1 0 1 0 0 1
24 1 1 0 1 0 0 0
25 1 1 0 0 1 1 1
26 1 1 0 0 1 1 0
27 1 1 0 0 1 0 1
28 1 1 0 0 1 0 0
29 1 1 0 0 0 1 1
30 1 1 0 0 0 1 0
31 1 1 0 0 0 0 1
32 1 1 0 0 0 0 0
33 1 0 1 1 1 1 1
34 1 0 1 1 1 1 0
35 1 0 1 1 1 0 1
36 1 0 1 1 1 0 0
37 1 0 1 1 0 1 1
38 1 0 1 1 0 1 0
39 1 0 1 1 0 0 1
40 1 0 1 1 0 0 0
41 1 0 1 0 1 1 1
42 1 0 1 0 1 1 0
43 1 0 1 0 1 0 1
44 1 0 1 0 1 0 0
45 1 0 1 0 0 1 1
46 1 0 1 0 0 1 0
47 1 0 1 0 0 0 1
48 1 0 1 0 0 0 0
49 1 0 0 1 1 1 1
50 1 0 0 1 1 1 0
51 1 0 0 1 1 0 1
52 1 0 0 1 1 0 0
53 1 0 0 1 0 1 1
54 1 0 0 1 0 1 0
55 1 0 0 1 0 0 1
56 1 0 0 1 0 0 0
57 1 0 0 0 1 1 1
58 1 0 0 0 1 1 0
59 1 0 0 0 1 0 1
60 1 0 0 0 1 0 0
61 1 0 0 0 0 1 1
62 1 0 0 0 0 1 0
63 1 0 0 0 0 0 1
64 1 0 0 0 0 0 0
Appendix 2C
257
65 0 1 1 1 1 1 1
66 0 1 1 1 1 1 0
67 0 1 1 1 1 0 1
68 0 1 1 1 1 0 0
69 0 1 1 1 0 1 1
70 0 1 1 1 0 1 0
71 0 1 1 1 0 0 1
72 0 1 1 1 0 0 0
73 0 1 1 0 1 1 1
74 0 1 1 0 1 1 0
75 0 1 1 0 1 0 1
76 0 1 1 0 1 0 0
77 0 1 1 0 0 1 1
78 0 1 1 0 0 1 0
79 0 1 1 0 0 0 1
80 0 1 1 0 0 0 0
81 0 1 0 1 1 1 1
82 0 1 0 1 1 1 0
83 0 1 0 1 1 0 1
84 0 1 0 1 1 0 0
85 0 1 0 1 0 1 1
86 0 1 0 1 0 1 0
87 0 1 0 1 0 0 1
88 0 1 0 1 0 0 0
89 0 1 0 0 1 1 1
90 0 1 0 0 1 1 0
91 0 1 0 0 1 0 1
92 0 1 0 0 1 0 0
93 0 1 0 0 0 1 1
94 0 1 0 0 0 1 0
95 0 1 0 0 0 0 1
96 0 1 0 0 0 0 0
97 0 0 1 1 1 1 1
98 0 0 1 1 1 1 0
99 0 0 1 1 1 0 1
100 0 0 1 1 1 0 0
101 0 0 1 1 0 1 1
102 0 0 1 1 0 1 0
103 0 0 1 1 0 0 1
104 0 0 1 1 0 0 0
105 0 0 1 0 1 1 1
106 0 0 1 0 1 1 0
107 0 0 1 0 1 0 1
108 0 0 1 0 1 0 0
109 0 0 1 0 0 1 1
110 0 0 1 0 0 1 0
111 0 0 1 0 0 0 1
112 0 0 1 0 0 0 0
113 0 0 0 1 1 1 1
114 0 0 0 1 1 1 0
115 0 0 0 1 1 0 1
116 0 0 0 1 1 0 0
117 0 0 0 1 0 1 1
118 0 0 0 1 0 1 0
119 0 0 0 1 0 0 1
120 0 0 0 1 0 0 0
121 0 0 0 0 1 1 1
122 0 0 0 0 1 1 0
123 0 0 0 0 1 0 1
124 0 0 0 0 1 0 0
125 0 0 0 0 0 1 1
126 0 0 0 0 0 1 0
127 0 0 0 0 0 0 1
128 0 0 0 0 0 0 0
Table A.21: Truth table for the simplified MTDC system
Appendix 2C
258
The capacity probability table for the HVDC grid with each path to shore rated at 900MW
is shown below:
State OFNA OFNB OFNC C1 C2 Sub 6 Sub 7 Probability Capacity
1 0.98721 0.98721 0.98721 0.99310 0.99310 0.97743 0.97743 0.90654 1800
2 0.98721 0.98721 0.98721 0.99310 0.99310 0.97743 0.02257 0.02093 900
3 0.98721 0.98721 0.98721 0.99310 0.99310 0.02257 0.97743 0.02093 900
4 0.98721 0.98721 0.98721 0.99310 0.99310 0.02257 0.02257 0.00048 0
5 0.98721 0.98721 0.98721 0.99310 0.00690 0.97743 0.97743 0.00630 1500
6 0.98721 0.98721 0.98721 0.99310 0.00690 0.97743 0.02257 0.00015 900
7 0.98721 0.98721 0.98721 0.99310 0.00690 0.02257 0.97743 0.00015 600
8 0.98721 0.98721 0.98721 0.99310 0.00690 0.02257 0.02257 0.00000 0
9 0.98721 0.98721 0.98721 0.00690 0.99310 0.97743 0.97743 0.00630 1500
10 0.98721 0.98721 0.98721 0.00690 0.99310 0.97743 0.02257 0.00015 600
11 0.98721 0.98721 0.98721 0.00690 0.99310 0.02257 0.97743 0.00015 900
12 0.98721 0.98721 0.98721 0.00690 0.99310 0.02257 0.02257 0.00000 0
13 0.98721 0.98721 0.98721 0.00690 0.00690 0.97743 0.97743 0.00004 1200
14 0.98721 0.98721 0.98721 0.00690 0.00690 0.97743 0.02257 0.00000 600
15 0.98721 0.98721 0.98721 0.00690 0.00690 0.02257 0.97743 0.00000 600
16 0.98721 0.98721 0.98721 0.00690 0.00690 0.02257 0.02257 0.00000 0
17 0.98721 0.98721 0.01279 0.99310 0.99310 0.97743 0.97743 0.01174 1200
18 0.98721 0.98721 0.01279 0.99310 0.99310 0.97743 0.02257 0.00027 900
19 0.98721 0.98721 0.01279 0.99310 0.99310 0.02257 0.97743 0.00027 900
20 0.98721 0.98721 0.01279 0.99310 0.99310 0.02257 0.02257 0.00001 0
21 0.98721 0.98721 0.01279 0.99310 0.00690 0.97743 0.97743 0.00008 900
22 0.98721 0.98721 0.01279 0.99310 0.00690 0.97743 0.02257 0.00000 900
23 0.98721 0.98721 0.01279 0.99310 0.00690 0.02257 0.97743 0.00000 0
24 0.98721 0.98721 0.01279 0.99310 0.00690 0.02257 0.02257 0.00000 0
25 0.98721 0.98721 0.01279 0.00690 0.99310 0.97743 0.97743 0.00008 1200
26 0.98721 0.98721 0.01279 0.00690 0.99310 0.97743 0.02257 0.00000 600
27 0.98721 0.98721 0.01279 0.00690 0.99310 0.02257 0.97743 0.00000 600
28 0.98721 0.98721 0.01279 0.00690 0.99310 0.02257 0.02257 0.00000 0
29 0.98721 0.98721 0.01279 0.00690 0.00690 0.97743 0.97743 0.00000 600
30 0.98721 0.98721 0.01279 0.00690 0.00690 0.97743 0.02257 0.00000 600
31 0.98721 0.98721 0.01279 0.00690 0.00690 0.02257 0.97743 0.00000 0
32 0.98721 0.98721 0.01279 0.00690 0.00690 0.02257 0.02257 0.00000 0
33 0.98721 0.01279 0.98721 0.99310 0.99310 0.97743 0.97743 0.01174 1200
34 0.98721 0.01279 0.98721 0.99310 0.99310 0.97743 0.02257 0.00027 900
35 0.98721 0.01279 0.98721 0.99310 0.99310 0.02257 0.97743 0.00027 900
36 0.98721 0.01279 0.98721 0.99310 0.99310 0.02257 0.02257 0.00001 0
37 0.98721 0.01279 0.98721 0.99310 0.00690 0.97743 0.97743 0.00008 1200
38 0.98721 0.01279 0.98721 0.99310 0.00690 0.97743 0.02257 0.00000 600
39 0.98721 0.01279 0.98721 0.99310 0.00690 0.02257 0.97743 0.00000 600
40 0.98721 0.01279 0.98721 0.99310 0.00690 0.02257 0.02257 0.00000 0
41 0.98721 0.01279 0.98721 0.00690 0.99310 0.97743 0.97743 0.00008 1200
42 0.98721 0.01279 0.98721 0.00690 0.99310 0.97743 0.02257 0.00000 600
43 0.98721 0.01279 0.98721 0.00690 0.99310 0.02257 0.97743 0.00000 600
44 0.98721 0.01279 0.98721 0.00690 0.99310 0.02257 0.02257 0.00000 0
45 0.98721 0.01279 0.98721 0.00690 0.00690 0.97743 0.97743 0.00000 1200
46 0.98721 0.01279 0.98721 0.00690 0.00690 0.97743 0.02257 0.00000 600
47 0.98721 0.01279 0.98721 0.00690 0.00690 0.02257 0.97743 0.00000 600
48 0.98721 0.01279 0.98721 0.00690 0.00690 0.02257 0.02257 0.00000 0
49 0.98721 0.01279 0.01279 0.99310 0.99310 0.97743 0.97743 0.00015 600
50 0.98721 0.01279 0.01279 0.99310 0.99310 0.97743 0.02257 0.00000 600
51 0.98721 0.01279 0.01279 0.99310 0.99310 0.02257 0.97743 0.00000 600
52 0.98721 0.01279 0.01279 0.99310 0.99310 0.02257 0.02257 0.00000 0
53 0.98721 0.01279 0.01279 0.99310 0.00690 0.97743 0.97743 0.00000 600
54 0.98721 0.01279 0.01279 0.99310 0.00690 0.97743 0.02257 0.00000 600
55 0.98721 0.01279 0.01279 0.99310 0.00690 0.02257 0.97743 0.00000 0
56 0.98721 0.01279 0.01279 0.99310 0.00690 0.02257 0.02257 0.00000 0
57 0.98721 0.01279 0.01279 0.00690 0.99310 0.97743 0.97743 0.00000 600
58 0.98721 0.01279 0.01279 0.00690 0.99310 0.97743 0.02257 0.00000 600
59 0.98721 0.01279 0.01279 0.00690 0.99310 0.02257 0.97743 0.00000 0
60 0.98721 0.01279 0.01279 0.00690 0.99310 0.02257 0.02257 0.00000 0
61 0.98721 0.01279 0.01279 0.00690 0.00690 0.97743 0.97743 0.00000 600
62 0.98721 0.01279 0.01279 0.00690 0.00690 0.97743 0.02257 0.00000 600
63 0.98721 0.01279 0.01279 0.00690 0.00690 0.02257 0.97743 0.00000 0
64 0.98721 0.01279 0.01279 0.00690 0.00690 0.02257 0.02257 0.00000 0
Appendix 2C
259
Table A.22: Capacity probability tables for MTDC with 900MW paths back to shore
65 0.01279 0.98721 0.98721 0.99310 0.99310 0.97743 0.97743 0.01174 1200
66 0.01279 0.98721 0.98721 0.99310 0.99310 0.97743 0.02257 0.00027 900
67 0.01279 0.98721 0.98721 0.99310 0.99310 0.02257 0.97743 0.00027 900
68 0.01279 0.98721 0.98721 0.99310 0.99310 0.02257 0.02257 0.00001 0
69 0.01279 0.98721 0.98721 0.99310 0.00690 0.97743 0.97743 0.00008 1200
70 0.01279 0.98721 0.98721 0.99310 0.00690 0.97743 0.02257 0.00000 600
71 0.01279 0.98721 0.98721 0.99310 0.00690 0.02257 0.97743 0.00000 600
72 0.01279 0.98721 0.98721 0.99310 0.00690 0.02257 0.02257 0.00000 0
73 0.01279 0.98721 0.98721 0.00690 0.99310 0.97743 0.97743 0.00008 900
74 0.01279 0.98721 0.98721 0.00690 0.99310 0.97743 0.02257 0.00000 0
75 0.01279 0.98721 0.98721 0.00690 0.99310 0.02257 0.97743 0.00000 900
76 0.01279 0.98721 0.98721 0.00690 0.99310 0.02257 0.02257 0.00000 0
77 0.01279 0.98721 0.98721 0.00690 0.00690 0.97743 0.97743 0.00000 600
78 0.01279 0.98721 0.98721 0.00690 0.00690 0.97743 0.02257 0.00000 0
79 0.01279 0.98721 0.98721 0.00690 0.00690 0.02257 0.97743 0.00000 600
80 0.01279 0.98721 0.98721 0.00690 0.00690 0.02257 0.02257 0.00000 0
81 0.01279 0.98721 0.01279 0.99310 0.99310 0.97743 0.97743 0.00015 600
82 0.01279 0.98721 0.01279 0.99310 0.99310 0.97743 0.02257 0.00000 600
83 0.01279 0.98721 0.01279 0.99310 0.99310 0.02257 0.97743 0.00000 600
84 0.01279 0.98721 0.01279 0.99310 0.99310 0.02257 0.02257 0.00000 0
85 0.01279 0.98721 0.01279 0.99310 0.00690 0.97743 0.97743 0.00000 600
86 0.01279 0.98721 0.01279 0.99310 0.00690 0.97743 0.02257 0.00000 600
87 0.01279 0.98721 0.01279 0.99310 0.00690 0.02257 0.97743 0.00000 0
88 0.01279 0.98721 0.01279 0.99310 0.00690 0.02257 0.02257 0.00000 0
89 0.01279 0.98721 0.01279 0.00690 0.99310 0.97743 0.97743 0.00000 600
90 0.01279 0.98721 0.01279 0.00690 0.99310 0.97743 0.02257 0.00000 0
91 0.01279 0.98721 0.01279 0.00690 0.99310 0.02257 0.97743 0.00000 600
92 0.01279 0.98721 0.01279 0.00690 0.99310 0.02257 0.02257 0.00000 0
93 0.01279 0.98721 0.01279 0.00690 0.00690 0.97743 0.97743 0.00000 0
94 0.01279 0.98721 0.01279 0.00690 0.00690 0.97743 0.02257 0.00000 0
95 0.01279 0.98721 0.01279 0.00690 0.00690 0.02257 0.97743 0.00000 0
96 0.01279 0.98721 0.01279 0.00690 0.00690 0.02257 0.02257 0.00000 0
97 0.01279 0.01279 0.98721 0.99310 0.99310 0.97743 0.97743 0.00015 600
98 0.01279 0.01279 0.98721 0.99310 0.99310 0.97743 0.02257 0.00000 600
99 0.01279 0.01279 0.98721 0.99310 0.99310 0.02257 0.97743 0.00000 600
100 0.01279 0.01279 0.98721 0.99310 0.99310 0.02257 0.02257 0.00000 0
101 0.01279 0.01279 0.98721 0.99310 0.00690 0.97743 0.97743 0.00000 600
102 0.01279 0.01279 0.98721 0.99310 0.00690 0.97743 0.02257 0.00000 0
103 0.01279 0.01279 0.98721 0.99310 0.00690 0.02257 0.97743 0.00000 600
104 0.01279 0.01279 0.98721 0.99310 0.00690 0.02257 0.02257 0.00000 0
105 0.01279 0.01279 0.98721 0.00690 0.99310 0.97743 0.97743 0.00000 600
106 0.01279 0.01279 0.98721 0.00690 0.99310 0.97743 0.02257 0.00000 0
107 0.01279 0.01279 0.98721 0.00690 0.99310 0.02257 0.97743 0.00000 600
108 0.01279 0.01279 0.98721 0.00690 0.99310 0.02257 0.02257 0.00000 0
109 0.01279 0.01279 0.98721 0.00690 0.00690 0.97743 0.97743 0.00000 600
110 0.01279 0.01279 0.98721 0.00690 0.00690 0.97743 0.02257 0.00000 0
111 0.01279 0.01279 0.98721 0.00690 0.00690 0.02257 0.97743 0.00000 600
112 0.01279 0.01279 0.98721 0.00690 0.00690 0.02257 0.02257 0.00000 0
113 0.01279 0.01279 0.01279 0.99310 0.99310 0.97743 0.97743 0.00000 0
114 0.01279 0.01279 0.01279 0.99310 0.99310 0.97743 0.02257 0.00000 0
115 0.01279 0.01279 0.01279 0.99310 0.99310 0.02257 0.97743 0.00000 0
116 0.01279 0.01279 0.01279 0.99310 0.99310 0.02257 0.02257 0.00000 0
117 0.01279 0.01279 0.01279 0.99310 0.00690 0.97743 0.97743 0.00000 0
118 0.01279 0.01279 0.01279 0.99310 0.00690 0.97743 0.02257 0.00000 0
119 0.01279 0.01279 0.01279 0.99310 0.00690 0.02257 0.97743 0.00000 0
120 0.01279 0.01279 0.01279 0.99310 0.00690 0.02257 0.02257 0.00000 0
121 0.01279 0.01279 0.01279 0.00690 0.99310 0.97743 0.97743 0.00000 0
122 0.01279 0.01279 0.01279 0.00690 0.99310 0.97743 0.02257 0.00000 0
123 0.01279 0.01279 0.01279 0.00690 0.99310 0.02257 0.97743 0.00000 0
124 0.01279 0.01279 0.01279 0.00690 0.99310 0.02257 0.02257 0.00000 0
125 0.01279 0.01279 0.01279 0.00690 0.00690 0.97743 0.97743 0.00000 0
126 0.01279 0.01279 0.01279 0.00690 0.00690 0.97743 0.02257 0.00000 0
127 0.01279 0.01279 0.01279 0.00690 0.00690 0.02257 0.97743 0.00000 0
128 0.01279 0.01279 0.01279 0.00690 0.00690 0.02257 0.02257 0.00000 0
Appendix 3A
260
APPENDIX 3A – HVDC CIRCUIT BREAKER REVIEW
The HVDC circuit breaker topologies which were not presented in the main body are
described in this appendix.
1 Mechanical breaker with turn-off snubber
This DC circuit breaker consists of a fast mechanical switch connected in parallel with two
branches [56]. One branch contains a set of anti-parallel thyristors connected in series with
a snubber capacitor, and the other branch consists of a surge arrester. This device is shown
in Figure A.22.
SLs
SA
I Ib
Ic
Is
C
Figure A.22: Mechanical breaker with turn-off snubber
During normal operation, the current flows through the mechanical switch, S. Once the
fault is detected and the mechanical switch receives a trip order, it opens its contacts
causing the line current to begin to commutate into the thyristor-capacitor branch once the
thyristors are turned-on. The line current charges-up the capacitor creating a counter
voltage, resulting in a decrease in the rise of fault current. The surge arrester will become
highly conductive and de-magnetise the system’s inductance at the moment its knee-point
voltage is reached. The de-magnetisation of the system’s inductance reduces the voltage
across the surge arrester (i.e. it becomes less conductive). In the absence of a thyristor this
could cause the current to commutate back to the capacitor and ultimately result in
oscillations. The thyristor therefore prevents the current from oscillating and hence
successful interruption can be achieved.
The snubber capacitor must be designed to ensure that the rate of voltage rise across the
mechanical switch does not exceed its voltage blocking slew rate capability. This DC
breaker is able to reduce the maximum fault current, due to the capacitor gradually
reducing the voltage across the system’s inductance. It also uses thyristors, instead of semi-
conductor switches with turn-off capability, which is by far the most cost-efficient device
for very high power applications [134]. This may also increase the device’s reliability,
Appendix 3A
261
since no control equipment is required to turn-off the device. A suitable method of
discharging the capacitor once the current has been interrupted must however be
incorporated into the design.
2 Resonant DC/DC Converter
The prospect of incorporating DC/DC converters in MT HVDC grids is being investigated
[43, 151]. The proposed DC/DC resonant converters [55, 152] would allow the DC grid to
be operated at different voltages levels, which is claimed to optimise costs and losses. They
would also enable faulty sections of the grid to be isolated.
T1 T2T3 T4
T2 T1T4 T3
T7 T8T5 T6
T8 T7T6 T5
Rg
L1
L1L2u
L2u
L2d
L2d
V2+
V2-
V1+
V1-
C
CVc
I1 I2
Low Voltage Converter High Voltage converter
Figure A.23: DC/DC resonance converter
The proposed DC/DC resonance converter is also known as a high power bi-directional
DC transformer and is shown in Figure A.23. The converter creates two back-to-back LC
resonant circuits with a common capacitor, C. In step-up mode, (power transfer from V1 to
V2), thyristor pairs T1 and T2 are fired sequentially at a switching frequency with a duty
ratio of 50%. This creates a resonance with L1 and C, increasing voltage, Vc, and enabling
zero current switching of T1 and T2. The high voltage resonance circuit (L2u-C) allows the
thyristor pairs T5 and T6 to be switched at zero current. This operating principle is similar
for the converter operating in step-down mode with thyristor pairs T3 and T4 in the low
voltage converter, and thyristor pairs T7 and T8 in the high voltage converter, being
utilised.
The high voltage converter’s switching frequency is synchronised to that of the low
voltage converter, but the firing angle is selected depending on the mode of operation
(step-up or step-down). The switching frequency is usually varied to control the DC
current (I1 or I2) using a Proportional-integral (PI) feedback controller.
Appendix 3A
262
The worst case zero-impedance faults, at both high voltage and low voltage converter
terminals, are considered. The moment the fault occurs there is an initial transient for one
to two cycles, in which the converter components experience peak fault values. Following
this the converter finds a new steady-state operating point, if possible, until the controller is
able to respond. The controller is assumed to be inactive from the instance that the fault
occurs until sometime later, due to the delays in transducers, in processing the data and in
firing the thyristors [152]. After this delay, the controller is able to act to reduce the
switching frequency or block the firing pulses (for a permanent fault), and to open the off-
load mechanical switches to provide fault isolation. The time period during which the
controller is inactive is said to be the converter’s natural response and is dealt with in
[152], which refers to the controller’s active response documented in [67].
The use of a DC/DC resonance converter as a HVDC breaker is relatively new and there is
ongoing work in this area [151]. The addition of DC/DC resonance converters in a DC grid
is likely to result in additional costs and losses.
3 Patent Filed by ABB Technology on 26th November 2008 titled
‘High Voltage Direct Current Circuit Breaker Arrangement and
Method’.
The novel part of this patent is how a number of DC breakers are arranged to enable a
larger current to be interrupted than is possible with a single device. The device consists of
an interrupter, BRK, connected in parallel with two branches, one containing a series
inductor and capacitor, the other a surge arrester [153].
BRKLs
SA
I Ib
Ic
Is
CL
Figure A.24: HVDC circuit breaker arrangement and method (ABB, Nov 2008)
The breaker is only able to interrupt DC circuits up to approximately 5kA, because above
this level the arc voltage/current characteristic becomes flat (i.e. for changes in arc current
the arc voltage remains constant).
Appendix 3A
263
Simplistically, connecting DC breakers in parallel will allow the current between the
breakers to be shared and therefore will, theoretically speaking, increase the total breaking
current capability. The issue, however, is that one breaker will interrupt the current first,
causing the current to commutate into the other breaker which will not be able to interrupt
the total current.
By introducing a single-phase two-winding transformer into the circuit, the problem may
be overcome. The first DC breaker is connected to the polarity end of one transformer
winding, whilst the second DC breaker is connected to the non-polarity end of the other
transformer winding. During steady-state operation, the core magnetic flux produced by
the current in one winding will therefore cancel out the core magnetic flux due to the
current in the other winding. As an example, if breaker 1, B1, interrupts its current first, its
parallel capacitor will begin charging up and will therefore produce an increasing voltage
across B1. This voltage will try to commutate the current into the other breaker, B2,
meaning that the total line current, I, will now be flowing through the second breaker. This
will however not happen due to the action of the transformer, allowing the second breaker
to only interrupt half of the line current. This arrangement is shown in Figure A.25.
B1
B2
I
I2
I1
W
W
Transformer
Figure A.25: Transformer arrangement
4 Patent Filed by ABB Technology on 10th June 2008 titled ‘A DC
Current Breaker’.
This invention is to improve the existing passive resonance circuit breaker design so that it
is capable of breaking DC current in excess of 2500A. The DC breaker design is an
interrupter, in parallel with an LC resonance circuit, in parallel with a surge arrester [154].
The acclaimed novel part of this design is the relationship between the values of
capacitance and inductance in the LC resonance circuit.
There is a known maximum frequency for which the interrupter is capable of extinguishing
the arc. Above this frequency the interrupter may no longer be able to cool the arc quickly
enough. The resonance frequency is given by equation (A.22).
Appendix 3A
264
1 1
2f
LC (A.22)
According to the patent, the resonance circuit up until now has been designed with a higher
value of inductance to reduce the cost of the capacitor. The typical relationship is for the
value of capacitance to be a third of the value of inductance. The inventors have however,
realised that increasing this relationship is more favourable. This is because the amplitude
of the oscillating current is proportional to (C/L)1/2
and the transient recovery voltage in the
interrupter is proportional to 1/C. Increasing the capacitance therefore results in a higher
oscillating current, which helps higher currents to be broken. The increased capacitance
also reduces the rate of rise of recovery voltage for a specific current.
The patent is for the capacitance to inductance value to be equal to or greater than one.
There are many embodiments of this invention mentioned in the patent, some of which are
outlined below:
According to the patent it is possible to break currents exceeding 2500A, for
example 5000A, if the said relationship is greater than two.
The use of the conductor’s self-inductance which therefore requires no separate
inductor.
Two interrupters connected in series and in parallel with the resonance circuit and
surge arrester. This arrangement is more costly but results in a higher total arc
voltage which has some benefits.
Connecting a switch in series with the resonance circuit. The switch is closed after
some delay from when the interrupter contacts open, meaning it is possible to
create a well-defined voltage step that efficiently initiates current oscillation. This
configuration makes it possible to break currents in the order of 7000A.
Application as a Metallic Return Transfer Breaker (MRTB) in a HVDC
transmission scheme.
5 Patent Filed by ABB Technology on 5th December 1994 titled
‘Direct-Current Breaker for High Power for Connection into a
Direct-Current Carrying High-Voltage Line’.
This patent focuses on two DC circuit breaker designs [155]. The first uses a GTO thyristor
to divert current from the breaker to allow arc extinction. The second uses an IGBT to
Appendix 3A
265
initiate current oscillations to create a zero-crossing to allow arc extinction. Considering
that this patent expires in 2014 and that these topologies are not known to be in operation
on any HVDC scheme it is unlikely that these solutions are cost-effective.
6 GTO Circuit Breaker
Figure A.26 shows the circuit diagram of the GTO circuit breaker. Prior to current
interruption, both sets of circuit breaker contacts, BC1 and BC2, are closed and the current,
Idc, is flowing through the HVDC line via the circuit breaker contacts. The circuit breaker
contacts open upon receiving the break command, producing arc voltages, V1 and V2.
The arc voltage, V2, charges-up capacitor, C2, whose voltage, VC2, is measured and
compared with a reference voltage, Vref, by the voltage level detector, VLD. Once VC2
exceeds Vref a Fire Now (FN) signal is issued to the Pulse Generating Circuit (PGC) and
the Time Delay Circuit (TDC). The PGC sends a Firing Signal (FS) to the Gate Turn-off
(GTO) thyristor to turn-on. The GTO thyristor enters a conducting state, causing the
current flowing through BC2 to commutate via the GTO thyristor, allowing the arc in BC2
to be extinguished. The TDC issues a turn-off signal to the GTO after a predetermined time
delay, which is determined to allow the current to commutate from BC2 to the GTO and
for BC2 to recover preventing arc re-ignition when the GTO thyristor is switched-off.
When the GTO thyristor is switched-off and BC2 is open, the voltage across the contacts,
and hence the voltage across the breaker, grows rapidly, causing the current to commutate
into C1. The voltage distribution between BC1 and BC2 is determined by the surge arrester
connected across BC2, which is used to limit the voltage across the GTO and related
control circuitry. This means that the majority of the voltage across the circuit breaker, Vt,
will be supported by BC1. The total voltage across the breaker, Vt, will ramp up due to the
capacitor and will oppose the external circuit voltage, causing the line current to decrease.
The surge arrester, SA1, will begin to conduct, if Vt exceeds the surge arrester knee
voltage, until the line current has ceased.
Appendix 3A
266
BC2L Idc Ibrk
C1
BC1
SA1
SA2C2
VLD PGC
TDC
Vref
VC2
FN
FS
V1 V2
Is1
Ic1
Vt
Figure A.26: GTO thyristor circuit breaker
The mechanical breaker with turn-off snubber described in Section 1 operates in a similar
way to this circuit breaker, by commutating the line current from the breaker to allow arc
extinction. This device is however more complex and requires an additional capacitor, C2,
surge arrester, SA2, and a breaker with two sets of contacts. The advantage of this
topology is that the voltage rating of the power electronics is determined by surge arrester
SA2, not SA1. The patent states that SA2 would have a knee-point voltage between 2 and
2.5kV for a system voltage of 500kV.
7 IGBT Circuit Breaker
This circuit breaker topology is shown in Figure A.27 and is very similar to the one
described in Section 6. This time however, when the contacts open, the arc voltage V2 acts
as the supply voltage to the oscillator, OSC, which is designed to generate a train of pulses
at the same natural frequency created by the inductor, L1, and capacitor, C1. The square
pulses are amplified and are used to control the switching of the IGBT. Controlling the
switching of the IGBT in this way causes an oscillation of natural frequency, with growing
amplitude, in the circuit consisting of the inductor, L1, capacitor, C1, and breaker contacts,
BC1 and BC2. The oscillations generate an alternating current, superimposed on the DC
current flowing through the breaker, which will produce a zero crossing. This zero crossing
allows the breaker contacts to extinguish the arc. The oscillations can now no longer
oscillate back to the breaker contacts and the oscillations cease. The current then
commutates into C1 as described in the above breaker topology. The inductor value is
chosen to be sufficiently low, to minimise the effect on the circuit.
Appendix 3A
267
BC2Ls Idc Ibrk
C1
BC1
SA1
SA2OSC AMP
V1 V2
Is1
Ic1
V2
L1
Figure A.27: IGBT circuit breaker
This circuit breaker topology is comparable to the passive resonance DC Circuit Breaker,
with the addition of power electronics to excite the oscillations. The additional components
in this topology are likely to increase the cost and to reduce the reliability of the device.
Appendix 4A
268
APPENDIX 4A – SUB-MODULE CAPACITANCE DERIVATION
An analytical approach proposed by Marquardt et al. in [85] can be used to calculate the
approximate SM capacitance required to give an acceptable ripple voltage for a given
converter rating. The converter arms are treated as controllable voltage sources as shown in
Figure A.28.
Figure A.28: Single-phase equivalent circuit for MMC
The current flowing through each converter arm contains a sinusoidal component, ( ) / 2aI t
and a DC component,gI as shown in Figure A.28 and described by equation (A.23).
1 1 ˆ( ) ( ) ( sin( ))2 2
ua g a g aI t I I t I I t (A.23)
where:
ˆ1
3 2
ag dc
g
II I m
I (A.24)
Substituting (A.24) into (A.23) gives Iua in terms of Idc, as given by equation(A.25).
1
( ) (1 sin( ))3
ua dcI t I m t (A.25)
Where is the phase angle between ( )aV t and ( )aI t .
Neglecting the voltage drop across the arm impedance, each arm of the converter is
represented as a controllable voltage source which can be described by equation (A.26).
Vua(t)
Vdc/2
Ia(t)Vsa(t)
Iua(t)=Ig+Ia(t)/2
Vla(t)
Idc
Vdc/2
Larm
Rarm
Larm
Rarm
La Ra
Va(t)
Vu-g(t)
Vl-g(t)
Ila(t)=Ig-Ia(t)/2
Appendix 4A
269
1 1 1ˆ ˆ( ) ( ) sin( ) (1 sin( ))2 2 2
ua dc a dc a dcV t V V t V V t V k t (A.26)
where:
ˆ2 a
dc
Vk
V (A.27)
The power flow of the upper phase arm, Pua, is given by equation (A.28), using equations
(A.25) and (A.26).
1 1
( ) ( ) ( ) (1 sin( )) (1 sin( ))2 3
ua ua ua dc dcP t V t I t V k t I m t (A.28)
Equation (A.28) can be simplified to give equation (A.29).
( ) (1 sin( ))(1 sin( ))6
dc dcua
V IP t k t m t (A.29)
The relationship between m and k can be obtained by equations (A.30) to (A.34).
ˆ ˆ
3 cos2 2
a ad dc dc
I VP V I (A.30)
Substituting Ig for Idc, using (A.24), gives equation (A.31).
ˆ ˆ
cos2 2
a adc g
I VV I (A.31)
Multiplying each side of equation (A.31) by two gives equation (A.32).
ˆ ˆ2 cosdc g a aV I I V (A.32)
Equation (A.32) can be rearranged to give equation (A.33).
ˆ
ˆ 2cos
dc a
ga
V I
IV
(A.33)
Substituting equations (A.24) and (A.27) into equation (A.33) gives equation (A.34).
2
cosm
k
(A.34)
The variation in stored energy from the upper arm over a half cycle can be found by
integrating the equation for Pua (equation (A.29)) between limits x1 and x2 (positive half
Appendix 4A
270
cycle). The first step of this approach is to put equation (A.29) into an easier format for
integration.
Multiplying out the brackets gives equation (A.35).
( ) 1 sin( ) sin( ) sin( )sin( )6
dua
PP t m t k t mk t t (A.35)
Equation (A.36) can be produced using trigonometric identities.
( ) 1 sin( ) sin( ) cos(2 ) cos( )6 2 2
dua
P mk mkP t m t k t t
(A.36)
This can be re-written as equation (A.37).
( ) sin( ) sin( ) cos(2 ) 1 cos( )6 2 6 2
d dua
P Pmk mkP t m t k t t
(A.37)
From equation (A.34), cos( ) 2mk . The following term therefore equals 0.
1 cos( ) 06 2
dP mk
(A.38)
Equation (A.37) can thus be reduced to equation (A.39).
( ) sin( ) sin( ) cos(2 )6 2
dua
P mkP t m t k t t
(A.39)
Each term in equation (A.39) can be separately integrated and then added together.
Equations (A.40) to (A.44) show the integration for the first term.
u t (A.40)
du
dt (A.41)
Using equations (A.40) and (A.41) the integral of the first term can be written as equation
(A.42).
sin( ) sin( )du
m t dt m u
(A.42)
Integrating the right hand side of equation (A.42) gives equation (A.43).
sin( ) cos( )du m
m u u
(A.43)
Appendix 4A
271
Substituting for u gives equation (A.44).
cos( )
sin( )m t
m t dt
(A.44)
Integrating each term of equation (A.39) in a similar way gives equation (A.45).
22
11
cos( ) cos( ) sin(2 )( )
6 4
xx
dua ua
xx
P m t k t mk tW P t
(A.45)
This can be re-written as equation (A.46).
22
11
( ) cos( ) cos( ) sin(2 )6 4
xx
dua ua
xx
P mkW P t m t k t t
(A.46)
The limits for the half cycle, x1 and x2, can be obtained by finding the zero crossings, as
shown by equations (A.47) to (A.50).
1 sin( ) 0m t (A.47)
1
1 1arcsin arcsinx t
m m
(A.48)
Since sin( ) sin( ) :
1 sin( ) 0m t (A.49)
2
1arcsinx t
m
(A.50)
Substituting limits into equation (A.46) gives equation (A.51).
2 2
2 2 2 2
1 1 1 1 1 1
cos( ) cos( )
6 sin( )cos( ) cos( )sin( )4
cos( ) cos( ) sin( )cos( ) cos( )sin( )6 4
dua
d
m x k xP
W mkx x x x
P mkm x k x x x x x
(A.51)
Equation (A.52) can be re-written as equation (A.52) by collecting like terms.
2 1 2 1
2 2 2 2
1 1 1 1
cos( ) cos( ) cos( ) cos( )
sin( )cos( ) cos( )sin( )6
sin( )cos( ) cos( )sin( )4
dua
m x x k x xP
W x x x xmk
x x x x
(A.52)
Substituting equations (A.53) to (A.56) into equation (A.52) gives equation (A.57).
Appendix 4A
272
1
1sin( )x
m
(A.53)
2
1sin( )x
m (A.54)
2
1 2
1 1cos( ) 1
mx
m m
(A.55)
2 2
1cos( ) 1x
m (A.56)
2 12 2
2 2 1 12 2
1 11 1 cos( ) cos( )
6 1 1 1 1cos( ) 1 sin( ) cos( ) 1 sin( )
4
dua
m k x xm mP
Wmk
x x x xm m m m
(A.57)
Simplifying equation (A.57) gives equation (A.58):
2 12
2 1 2 12
12 1 cos( ) cos( )
6 1 1cos( ) cos( ) 1 sin( ) sin( )
4 4
dua
m k x xmP
Wmk mk
x x x xm m
(A.58)
Substituting equations (A.61) and (A.64) into equation (A.58) gives equation (A.65).
2 2
1 1sin( ) 1 sin( ) cos( )x
m m (A.59)
1 2
1 1sin( ) cos( ) 1 sin( )x
m m (A.60)
1 2
2sin( ) sin( ) cos( )x x
m (A.61)
2 2
1 1cos( ) 1 cos( ) sin( )x
m m (A.62)
1 2
1 1cos( ) 1 cos( ) sin( )x
m m (A.63)
2 1 2
1cos( ) cos( ) 2 1 cos( )x x
m (A.64)
Appendix 4A
273
2 2
2 2
1 12 1 2 1 cos( )
6 1 1 1 22 1 cos( ) 1 cos( )
4 4
dua
m km mP
Wmk mk
m m m m
(A.65)
Equation (A.65) can be simplified to equation (A.69), shown by equations (A.66) to (A.69)
.
2 2
2 2
1 12 1 2 1 cos( )
6 2 1 2 11 cos( ) 1 cos( )
4 4
dua
m km mP
Wmk mk
m m m m
(A.66)
2 2 2
1 1 12 1 2 1 cos( ) 1 cos( )
6
dua
PW m k k
m m m
(A.67)
2
11 2 cos( )
6
dua
PW m k
m
(A.68)
2
11 1 cos( )
3 2
dua
P kW m
m m
(A.69)
Substituting2
cos( )km
from equation (A.34) into equation (A.69) gives equation (A.70).
2
1 2 /1 1
3 2
dua
P mW m
m m
(A.70)
This can be simplified to give equation (A.71), and further simplified to equation (A.72).
The variation in stored energy for the upper arm of the converter is obtained in terms of m.
2 2
1 11 1
3
dua
PW m
m m
(A.71)
3/2
2
11
3
dua
PW m
m
(A.72)
Equation (A.72) can be re-written in terms of k by substituting equation (A.34).
3/2
22 cos
( ) 13 cos 2
dua
P kW k
k
(A.73)
The variation in energy per SM can be calculated by dividing equation (A.73) by the
number SMs in the converter arm, n, as shown in equation (A.74).
Appendix 4A
274
3/2
22 cos
( ) 13 cos 2
dSM
P kW k
n k
(A.74)
The required capacitance per SM for a ripple voltage factor 0 1 can be determined as
follows:
20.54
SMCap SM cap
WW C V
(A.75)
22
SMSM
Cap
WC
V
(A.76)
This approach which was proposed by Marquardt et al. is widely used [86, 87]. The SM
capacitance calculation should only be used as an approximation as it is based on several
assumptions, as described in the main body. The control strategy implemented for
balancing the capacitor voltages will also have a very significant impact on the capacitor
ripple voltage. The SM’s capacitance should be calculated based on the converter’s
operating condition that causes the greatest variation in the capacitor’s stored energy. This
condition is likely to be when the converter is operating at maximum power.
Sub-module capacitance calculation
The SM capacitance required to give a 10% capacitor voltage ripple for a 1000MW,
±300kV, 31-level MMC is calculated below:
The average SM capacitor voltage can be calculated as follows:
600
2030
dccap
V kVV kV
n (A.77)
The DC current, AC phase voltage and current, and frequency are given in equations
(A.78) to (A.81).
1000
1670600
ddc
dc
P MWI A
V KV (A.78)
ˆ 300aV kV (A.79)
/ 3 333
1570212
da
a
P MWI A
V kV (A.80)
2 2 50 314f rads (A.81)
Appendix 4A
275
The values for Ig and m are calculated in equations (A.82) and (A.83) respectively.
1670
5573 3
dcg
I AI A (A.82)
ˆ 2 1570
22 2 557
a
g
Im
I
(A.83)
The variation in the upper arm’s stored energy is given in equation (A.84).
3/2
2
10001 12 1 1.38
314 3 2ua
MWW MJ
(A.84)
Based on the assumption that the energy variation is shared equally between all SMs in the
converter arm, the required SM capacitance for a voltage ripple of ±5% is calculated in
equation (A.85).
2
1.38 / 301150
2 0.05 20SM
MJC uF
kV
(A.85)
According to [84] 30-40kJ of stored energy per MVA of converter rating is sufficient to
give a ripple voltage of 10% (±5%). Using this approximation the value of SM capacitance
can be calculated and compared with the value calculated by equation (A.85). The value of
SM capacitance based on 30kJ/MVA is given in (A.87).
30 1000 30
1676 180
SM
KJ MJW kJ
n
(A.86)
2 2
167835
0.5 0.5 20
SMSM
sm
W kJC F
V kV
(A.87)
The value of SM capacitance based on 40kJ/MVA is given in (A.89).
40 1000 40
2226 180
SM
KJ MJW kJ
n
(A.88)
2
2221110
0.5 20SM
kJC F
kV
(A.89)
The analysis conducted here shows that a value of 40MJ of stored energy for a 1000MVA
converter gives a value of SM capacitance similar to the method proposed by Marquardt et
al.
Appendix 4B
276
APPENDIX 4B – ARM INDUCTANCE DERIVATION
This appendix document derives an expression to approximately calculate the value of arm
reactance required for a given value of peak circulating current. This derivation is given in
a more condensed form in [89]. In the main body of this thesis, circulating current is
denoted by Icirc, however in this appendix it is denoted by I2f. This notation is used as it is
in-keeping with the original literature and it has greater meaning for the analysis of
circulating currents.
Equation (A.90), which describes the instantaneous power of the upper converter arm,
( )uaP t , is derived in the appendix document entitled “Sub-module capacitance derivation”
(Appendix 4A).
( ) (1 sin( ))(1 sin( ))6
dua
PP t k t m t (A.90)
The equation which describes the instantaneous power of the lower converter arm ( )laP t is
derived in brief in equations (A.91) to (A.93).
1
( ) (1 sin( ))2
la dcV t V k t (A.91)
1
( ) (1 sin( ))3
la dcI t I m t (A.92)
( ) ( ) ( ) (1 sin( ))(1 sin( ))6
dla la la
PP t V t I t k t m t (A.93)
K, m and Pd are the same as stated in appendix 4A, and are restated in (A.94).
ˆ ˆ2 2
2 cos
a ad dc dc
d g
V Ik m P V I
V I k
(A.94)
Integrating ( )uaP t and ( )laP t with respect to time gives the fluctuations of stored energy in
the upper and lower converter arms respectively, as calculated in equations (A.95) and
(A.96).
sin(2 ) 2cos( )
( ) ( ) cos( )6 2cos( ) cos( )
dua ua
P t tW t P t m t
m
(A.95)
sin(2 ) 2cos( )( ) ( ) cos( )
6 2cos( ) cos( )
dla la
P t tW t P t m t
m
(A.96)
Appendix 4B
277
Summing uaW and laW gives the AC component of the total stored energy in the converter
leg, and is shown in equation (A.97). This derivation uses the phase A converter leg as an
example.
sin(2 )
( ) ( ) ( )6 cos( )
da ua la
P tW t W t W t
(A.97)
Equation (A.99) is written in terms of apparent power by substituting equation (A.98) into
equation (A.97).
cos( )dP S (A.98)
sin(2 )
( )6
a
S tW t
(A.99)
Equation (A.99) shows that the AC component of the stored energy in the converter phase
leg varies at twice the fundamental frequency. The energy stored in the converter leg is a
function of voltage. A component of the converter leg voltage (upper arm and lower arm)
must therefore also vary at twice the fundamental frequency. Equation (A.100) shows the
voltage for the phase A converter leg as an example.
_ _ 2ˆ( ) sin(2 )a a dc a ac dc fV t V V V V t (A.100)
The upper and lower arm voltages must be re-written to include the double frequency
component, as shown in equations (A.101) and (A.102).
2ˆ1
( ) (1 sin( )) sin(2 )2 2
f
ua dc
VV t V k t t (A.101)
2ˆ1
( ) (1 sin( )) sin(2 )2 2
f
la dc
VV t V k t t (A.102)
The double fundamental frequency voltage component excites circulating currents, as
described by equation (A.103).
2
2 2
ˆˆ( ) sin(2 ) cos(2 )
4 2
f
f f
N arm
VI t t I t
L
(A.103)
Re-writing the arm currents with respect to phase A gives equations (A.104) and (A.105)
2
1 ˆ( ) (1 sin( )) cos(2 )3
ua dc fI t I m t I t (A.104)
Appendix 4B
278
2
1 ˆ( ) (1 sin( )) cos(2 )3
la dc fI t I m t I t (A.105)
The instantaneous power of the upper converter arm ( )uaP t is now therefore written as
equation (A.106).
2
2
ˆ( ) sin( ) sin(2 )
2 2 2
ˆsin( ) cos(2 )3 3
fdc dcua
dc dcf
VV VP t k t t
I Im t I t
(A.106)
Multiplying out the brackets gives equation (A.107).
2
2 2
2 2 2
ˆ( ) sin( ) cos(2 )
6 6 2
sin( ) sin( )sin( )6 6
ˆ ˆsin( )cos(2 ) sin(2 )
2 6
ˆ ˆ ˆsin(2 )sin( ) sin(2 )cos(2 )
6 2
dc fd dua
d d
dc f f dc
f dc f f
V IP PP t m t t
P Pk t mk t t
V I V Ik t t t
V I V Im t t t t
(A.107)
This can be re-written as equation (A.108) by collecting like terms.
2
2
2 2
( ) 1 sin( ) sin( ) sin( )sin( )6
ˆcos(2 ) sin( )cos(2 )
2
ˆsin(2 ) sin(2 )sin( )
6
ˆ ˆsin(2 )cos(2 )
2
dua
dc f
f dc
f f
PP t m t k t mk t t
V It k t t
V It m t t
V It t
(A.108)
Equation (A.108) can be simplified to equation (A.109) by using trigonometric identities.
2
2
2 2
( ) 1 sin( ) sin( ) cos(2 ) cos( )6 2 2
ˆcos(2 ) sin(3 ) sin( )
2 2 2
ˆsin(2 ) cos( ) cos(3 2 )
6 2 2
ˆ ˆsin(4 2 )
4
dua
dc f
f dc
f f
P mk mkP t m t k t t
V I k kt t t
V I m mt t t
V It
(A.109)
Equations (A.110) to (A.113) repeats the same process but for the lower converter arm
( )laP t from equation (A.93).
Appendix 4B
279
2
2
ˆ( ) sin( ) sin(2 )
2 2 2
ˆsin( ) cos(2 )3 3
fdc dcla
dc dcf
VV VP t k t t
I Im t I t
(A.110)
Multiplying out the brackets gives equation (A.111).
2
2 2
2 2 2
ˆ( ) sin( ) cos(2 )
6 6 2
sin( ) sin( )sin( )6 6
ˆ ˆsin( )cos(2 ) sin(2 )
2 6
ˆ ˆ ˆsin(2 )sin( ) sin(2 )cos(2 )
6 2
dc fd dla
d d
dc f f dc
f dc f f
V IP PP t m t t
P Pk t mk t t
V I V Ik t t t
V I V Im t t t t
(A.111)
Equation (A.111) can be written as equation (A.112) by collecting like terms.
2
2
2 2
( ) 1 sin( ) sin( ) sin( )sin( )6
ˆcos(2 ) sin( )cos(2 )
2
ˆsin(2 ) sin(2 )sin( )
6
ˆ ˆsin(2 )cos(2 )
2
dla
dc f
f dc
f f
PP t m t k t mk t t
V It k t t
V It m t t
V It t
(A.112)
This can be simplified to equation (A.113) by using trigonometric identities.
2
2
2 2
( ) 1 sin( ) sin( ) cos(2 ) cos( )6 2 2
ˆcos(2 ) sin(3 ) sin( )
2 2 2
ˆsin(2 ) cos( ) cos(3 2 )
6 2 2
ˆ ˆsin(4 2 )
4
dla
dc f
f dc
f f
P mk mkP t m t k t t
V I k kt t t
V I m mt t t
V It
(A.113)
The instantaneous power of the converter leg is calculated using equation (A.114).
( ) ( ) ( )a ua laP t P t P t (A.114)
Substituting equations (A.109) and (A.113) into equation (A.114) gives (A.115).
Appendix 4B
280
2
2 2 2
ˆ( ) 1 cos(2 ) cos( ) cos(2 )3 2 2
ˆ ˆ ˆsin(2 ) sin(4 2 )
3 2
d
a dc f
f dc f f
P mk mkP t t V I t
V I V It t
(A.115)
Substituting cos( ) 2mk from (A.94) into equation (A.115) gives equation (A.116).
2
2 2 2
ˆ( ) cos(2 ) cos(2 )3 2
ˆ ˆ ˆsin(2 ) sin(4 2 )
3 2
d
a dc f
f dc f f
P mkP t t V I t
V I V It t
(A.116)
Substituting2
cos( )k
m from (A.94) into equation (A.116) gives equation (A.117).
2
2 2 2
cos(2 ) ˆ( ) cos(2 )3 cos( )
ˆ ˆ ˆsin(2 ) sin(4 2 )
3 2
d
a dc f
f dc f f
P tP t V I t
V I V It t
(A.117)
Equation (A.117) can be re-written in terms of apparent power by substituting cos( )dP S
from equation (A.98), as shown by equation (A.118).
2
2 2 2
ˆ( ) cos(2 ) cos(2 )6
ˆ ˆ ˆsin(2 ) sin(4 2 )
3 2
a dc f
f dc f f
SP t t V I t
V I V It t
(A.118)
Integrating equation (A.118) with respect to time produces equation (A.119).
2
2 2 2
ˆ( ) ( ) sin(2 ) sin(2 )
6 2
ˆ ˆ ˆcos(2 ) cos(4 2 )
6 8
dc f
a a
f dc f f
V ISW t P t dt t t
V I V It t
(A.119)
Substituting equation (A.120) into equation (A.119) produces equation (A.121).
2
2
ˆˆ
4
f
f
arm
VI
L (A.120)
2
2
2
2 2
2
ˆ( ) sin(2 ) sin(2 )
6 8
ˆ ˆcos(2 ) cos(4 2 )
6 32
dc f
a
arm
f dc f
arm
V VSW t t t
L
V I Vt t
L
(A.121)
Appendix 4B
281
It is shown in equations (A.122) to (A.129) that under normal operating conditions for a
typical HVDC scheme the third and fourth terms in equation (A.121) are at least one order
of magnitude smaller than the second term and that equation (A.121) can therefore be
approximated by neglecting the third and fourth terms.
According to [89], for a 50Hz system, providing Larm <0.2p.u., the third term in equation
(A.121) can be neglected since:
2 2 2
2
ˆ ˆ ˆ10
8 6 6
dc f f dc f dc
arm
V V V I V I
L (A.122)
The maximum value of limb reactor permissible for equation (A.122) to be true can be
determined by equations (A.123) to (A.126).
2
2
2
2
22
ˆ
ˆ8 6 3
ˆˆ 48
6
dc f
arm dc f dc
arm dcarm f dcf dc
V V
L V V V
L IL V IV I
(A.123)
Substituting L armX L into equation (A.123) produces equation (A.124)
2
2
2
ˆ
8 0.75
ˆ
6
dc f
arm dc
arm dcf dc
V V
L V
X IV I
(A.124)
Therefore to ensure 2
2
ˆ
8
dc f
arm
V V
L is at least one order of magnitude greater than 2
ˆ
6
f dcV I
Xarm and
Lmax must be defined by equations (A.125) and (A.126).
0.075 dcarm
dc
VX
I (A.125)
max
0.075
2
dc
dc
VL
fI (A.126)
Equation (A.127) compares the fourth term in equation (A.121) with the second term in
equation (A.121):
Appendix 4B
282
2
2 2
2
2 222 22
2
ˆ
ˆ8 32 4
ˆ ˆˆ 8
32
dc f
arm dc f arm dc
arm f ff
arm
V V
L V V L V
L V VV
L
(A.127)
Therefore to ensure 2
2
ˆ
8
dc f
arm
V V
L is at least one order of magnitude greater than
2
2
2
ˆ
32
f
arm
V
L, 2
ˆfV
must be defined by equation (A.128).
2ˆ 0.4f dcV V (A.128)
2ˆ
fV is significantly less than 0.4 dcV in any realistic MMC, hence the fourth term in equation
(A.121) can also be neglected. Equation (A.121) is therefore reduced to equation (A.129).
2
2
ˆ( ) sin(2 )
6 8
dc f
a
arm
V VSW t t
L
(A.129)
The double fundamental frequency voltage 2 ( )fV t , should distribute between all of the
SMs in the converter leg (2n) equally. Therefore the SM capacitor voltage can be described
by equation (A.130).
2ˆ
( ) sin(2 )2
f
cap cap
VV t V t
n (A.130)
capV is the DC component of the capacitor voltage. The total energy stored in the phase A
converter leg can be calculated by equation (A.131).
2 21( ) 2 ( ) ( )
2a SM cap SM capW t n C V t nC V t (A.131)
Substituting equation (A.130) into (A.131) produces equation (A.132).
2
2ˆ
( ) sin(2 )2
f
a SM cap
VW t nC V t
n
(A.132)
Multiplying out the brackets produces equation (A.133).
22
2
2 2 2
2
ˆsin(2 )
2( )
ˆ ˆsin(2 ) sin (2 )
2 4
cap f
cap
a SM
cap f f
V VV t
nW t nC
V V Vt t
n n
(A.133)
Appendix 4B
283
Equation (A.133) can be simplified to equation (A.134).
2
22 2
2
ˆˆ( ) sin(2 ) sin (2 )
4
SM f
a SM cap SM cap f
C VW t nC V C V V t t
n (A.134)
The second term in equation (A.134) is the double frequency component and can be
directly compared with equation (A.129), as shown by equation (A.135).
2
2 2
ˆˆ sin(2 ) sin(2 )
6 8
dc f
SM cap f
arm
V VSC V V t t
L
(A.135)
Equation (A.135) can be simplified to equation (A.136).
2
2 2
ˆˆ
6 8
dc f
SM cap f
arm
V VSC V V
L
(A.136)
Equation (A.136) can be rearranged for 2ˆ
fV as shown by equations (A.137) to (A.139).
2
2ˆ8 6
dcSM cap
arm f
V SC V
L V (A.137)
2
2
ˆ6 1
8
f
dcSM cap
arm
V
S VC V
L
(A.138)
2
2
6ˆ
8
f
dcSM cap
arm
SV
VC V
L
(A.139)
The double fundamental frequency current can be calculated by equation (A.140).
2
2
ˆˆ
4
f
f
arm
VI
L (A.140)
Substituting equation (A.139) into equation (A.140) produces equation (A.141).
2
2
6
8ˆ
4
dcSM cap
arm
f
arm
S
VC V
LI
L
(A.141)
Equation (A.141) can be simplified by equations (A.142) to (A.144).
Appendix 4B
284
2
2
1
6 4ˆ
8
armf
dcSM cap
arm
S
LI
VC V
L
(A.142)
2 2
2
1ˆ24
8
f
arm dcSM cap
arm
SI
L VC V
L
(A.143)
2 2
1ˆ3 8
f
arm SM cap dc
SI
L C V V
(A.144)
Equation (A.144) can be rearranged for Larm as shown by equations (A.145) to (A.147)
2
2ˆ3 (8 )f arm SM cap dcI L C V V S (A.145)
2
2
8ˆ3
dc arm SM cap
f
SV L C V
I (A.146)
2
2
1
ˆ8 3arm dc
SM cap f
SL V
C V I
(A.147)
Equation (A.147) allows the required value of arm reactor to be calculated to limit the
circulating current for a given system.
Appendix 4C
285
APPENDIX 4C – SHORT-CIRCUIT RATIO CALCULATION
The strength of an AC system is often characterised by its Short-Circuit Ratio (SCR),
which is defined by equation (A.148).
2
n n
drated drated
V ZSCLSCR
P P (A.148)
An AC system with a SCR greater than three is defined as strong [30]. The SCR of the
onshore AC system in the models is relatively strong with an SCR of 3.5, hence the AC
system impedance can be calculated by equation (A.149).
2 2400
45.713.5 1000
nn
drated
V kVZ
SCR P MVA
(A.149)
The AC network impedance is highly inductive and consequently the AC system
impedance is modelled using an X/R ratio of 20. The SCR is implemented in PSCAD
using an ideal voltage source connected in series with a resistor and an inductor. The
values of resistance and inductance are calculated from equations (A.151) and (A.152).
2 2(20 )n n nZ R R (A.150)
2
2.28401
nn
ZR (A.151)
20
0.145nn
RL H
(A.152)
Appendix 4D
286
APPENDIX 4D – ABC TO DQ TRANSFORMATION DERIVATION
In matrix form for the three phases:
csc
csa a
csb b
c
V I
V R pL I
V I
(A.153)
Applying the abc to (Clarke) transform as given by equation (A.154) to both sides of
equation (A.153) gives equation (A.155):
0
1 11
2 2
2 3 30
3 2 2
1 1 1
2 2 2
a
b
c
V V
V V
V V
(A.154)
0 0
V I
V R pL I
V I
(A.155)
Providing that the three-phase system (abc) is balanced, the three AC quantities are
transformed into two ac quantities of equal magnitude separated by 90°. The two ac
quantities can then be transformed into two dc quantities using the to dq (Park)
transform given in equation (A.156).
sin
sin cos
d
q
V Vcos
V V
(A.156)
Using Euler’s rule, as given in equation (A.157), and noting that V lags V by 90° (i.e.
V jV ), equation (A.156) may be re-written in vector form as in equation (A.158), with
its inverse given in equation (A.159).
cos sinjxe x j x (A.157)
j
dqV V e
(A.158)
j
dqV V e
(A.159)
Using equation (A.159), equation (A.155) can re-written in vector form as in equation
(A.160) and equation (A.161).
Appendix 4D
287
( )j j
dq dqV e R pL I e (A.160)
j j j
dq dq dqV e RI e Lp I e (A.161)
Using partial differentiation and noting that t , equation (A.162) is obtained.
j j j
dq dq dq
const I const
j j
dq dq
p I e e I I et t
e pI j I e
(A.162)
Substituting equation (A.162) into equation (A.161) gives
j j j j
dq dq dq dqV e RI e L e pI j I e (A.163)
Equation (A.163) can be simplified as follows:
j j j
dq dq dqV e RI e e Lp j L I (A.164)
dq dq dqV RI Lp j L I (A.165)
Or in matrix form:
0 1
1 0
d d d d
q q q q
V I I IR Lp L
V I I I
(A.166)
Where 0 1
1 0
is the matrix representation of the imaginary unit j.
Appendix 4E
288
APPENDIX 4E – POWER CONTROLLER TRANSFER FUNCTION
DERIVATION
Equations (A.167) and (A.168) show that the active power is controlled by Id and the
reactive power is controlled by Iq. The open loop transfer function, GOL, is given by
equation (A.169).
3
2sd dP V I (A.167)
3
2sd qQ V I (A.168)
1.51 3
1 2 1
p isd
piOL p sd
ic ic ic
K KV s
s KKG K V
s s s
(A.169)
Setting 1i p icK K equation (A.169) can be reduced to equation (A.170).
1.5 sd p
OL
ic
V KG
s (A.170)
The closed loop transfer function, GCL, is given by equation (A.171).
1.5
1.5 1
1.5 1.511
1.5
sd p
sd picCL
sd p icic sd p
sd pic
V K
V KsG
V K s V Ks
V Ks
(A.171)
The closed loop transfer function is therefore reduced to a first order transfer function with
a time constant 1.5
icp
sd pV K
.The bandwidth in radians for a first order system is equal to
1 rp . Hence equation (A.171) can be re-written as equation (A.172).
1
/ 1CL
p
Gs BW
(A.172)
The values of pK and iK can be calculated for given values of Vsd, BWp and BWic from
equations (A.173) and (A.174) respectively.
1.5 1.5
ic p p
p
sd sd ic
BW BWK
V V BW
(A.173)
i ic pK BW K (A.174)
Appendix 4F
289
APPENDIX 4F – DC VOLTAGE CONTROLLER TRANSFER FUNCTION
DERIVATION
Figure A.29: DC side plant
3 SM
eq
CC
n (A.175)
With reference to Figure A.29 the DC link voltage can be described by equation (A.176)
and the power balance between the AC and DC system can be described by equation
(A.177), assuming no converter losses.
dceq n dc
dVC I I
dt (A.176)
1.5dc dc sd sdI V V I (A.177)
Hence:
3
2
dc n sd sd
eq eq dc
dV I V I
dt C C V (A.178)
Taking partial derivatives gives equation (A.179), where the subscript ‘O’ denotes
operating point:
2
3 31
2 2
dc sdo sdo sdon dc sd
eq eq dco eq dco
d V V I VI V I
dt C C V C V
(A.179)
1.5 1.5dceq n V G dc V sd
d VC I K K V K I
dt
(A.180)
where:
sdo sdoV G
dco dco
V IK K
V V (A.181)
The state feedback system block diagram (SFSB) for the DC voltage control loop is shown
in Figure A.30.
Vn
MMC
CeqL R
Vs(abc)
In Idc
IcPCC
Vdc
Appendix 4F
290
Figure A.30: SFSB for DC voltage control loop
The transfer function for the control loop can be derived as follows:
1.5( )
1.5*1.5 ( )
Vp i
dc
Vdceq V G p i
KsK K
V sKV
C s K K sK Ks
(A.182)
2
1.5 ( )
* 1.5 ( ) 1.5
V p idc
dc eq V G p v i
K sK KV
V C s K K K s K K
(A.183)
Typically KG <<Kp and hence equation (A.183) can be reduced to equation (A.184):
2
1.5 ( )
* (1.5 ) 1.5
V p idc
dc eq V p v i
K sK KV
V C s K K s K K
(A.184)
Rearranging equation (A.184) and ignoring the psK term gives equation (A.185):
2
1.5
* 1.5 1.5
V i eqdc
dc V p eq v i eq
K K CV
V s K K C s K K C
(A.185)
The natural frequency and damping ratio is given by equations (A.186) and (A.187)
1.5 v i
n
eq
K K
C (A.186)
1.5
2
V p
n eq
K K
C
(A.187)
Hence the Ki and Kp values for a particular natural frequency and damping ratio can be
calculated by equations (A.188) and (A.189).
2
1.5
n eq
i
V
CK
K
(A.188)
2
1.5
n eq
p
V
CK
K
(A.189)
-
1
eqC
1
s
1.5KvKG
∆In
++∆Vdc* PI+
-
Inner
loop≈1
∆Isd* ∆Isd
1.5Kv
∆Vdc
Appendix 4G
291
APPENDIX 4G – AC VOLTAGE CONTROL
Figure A.31: MMC phase A connection to the AC network with the system resistances neglected
2sa na aV V I X (A.190)
where:
na caa
V VI
X
(A.191)
1 2X X X (A.192)
Substituting equation (A.191) into equation (A.190) and rearranging gives equation
(A.193)
(1 )sa na caV V k V k (A.193)
where:
2Xk
X (A.194)
Expanding equation (A.193) into its real and imaginary components gives equation
(A.195), noting that c is the power angle for the converter voltage and that the network
voltage is taken as the reference ( 0)n
(1 ) cos( ) sin( )sa na ca c ca cV V k V k jV k (A.195)
Hence, the magnitude of the voltage at the PCC is given by equation (A.196).
2 2
(1 ) cos( ) sin( )sa na ca c ca cV V k V k V k (A.196)
X2
Vsa
X1
Vca
IaVna
PCC
Appendix 4H
292
APPENDIX 4H – KEY PARAMETERS FOR THE MMC-HVDC LINK
Main circuit
Active power rating P 1000MW
Reactive power rating Q ±330MVAr
DC voltage Vdc 600kV
MMC
Number of levels NL 31
Number of SMs per arm n 30
SM capacitance CSM 1150µF
Arm resistance1 Rarm 0.9Ω
Arm inductance Larm 0.045H
Onshore MMC transformer
Leakage reactance XT 0.15p.u.
Star Primary winding voltage, L-L VTp 370kV
Delta Secondary winding voltage, L-L VTs 410kV
Apparent power base Sbase 1000MVA
Onshore AC system
Network voltage, L-L Vn 400kV
Network resistance Rn 2.28Ω
Network inductance Ln 0.145H
MMC power controllers Proportional gain Kp 0.000208
Integral time constant Ti 2.387
MMC DC voltage controller Proportional gain Kp 0.0269
Integral time constant Ti 0.413
AC voltage controllers Proportional gain Kp 0.000208
Integral time constant Ti 2.39
MMC current controller Proportional gain Kp 175
Integral time constant Ti 0.000442
MMC dq current limits Nominal d-axis current limit Idlim ±2.65
Nominal q-axis current limit Iqlim ±0.75
CCSC Proportional gain Kp 8.48
Integral time constant Ti 0.00589
Windfarm transformer
Leakage reactance XT 0.15p.u.
Star Primary winding voltage, L-L VTp 33kV
Star Secondary winding voltage, L-L VTs 220kV
Windfarm power controller
Proportional gain Kp 0.00246
Integral time constant Ti 0.645
Windfarm time constant τw 0.15s
Windfarm current controller Proportional gain Kp 0.327
Integral time constant Ti 0.29
Windfarm dq current limits Nominal d-axis current limit Idlim ±40
Nominal q-axis current limit Iqlim ±12
Offshore MMC voltage controller
Proportional gain Kp 0.5
Integral time constant Ti 0.005
Frequency freq 50Hz
Offshore MMC transformer
Leakage reactance XT 0.15p.u.
Star Primary winding voltage, L-L VTp 370kV
Delta Secondary winding voltage, L-L VTs 220kV
1. Value includes the on-state resistance of the semi-conductor devices in each arm.
Table A.23: Key parameters for the MMC-HVDC link
Appendix 5A
293
APPENDIX 5A – DC POLE-TO-GROUND FAULT
In Figure A.32, the system’s response to a DC pole-to-ground fault is shown when
employing a star-point reactor between the MMC1 and the transformer. The star-point
reactor has a per phase inductance of 50H and a mid-point resistance of 10Ω.
Figure A.32: Positive pole-to-ground fault at MMC1 with under voltage protection and a star-point
reactor ; arm currents are for MMC1 and capacitor voltages are for the upper arm of phase A for
MMC1; x axis – time(s)
Appendix 5A
294
The system’s response to a DC pole-to-ground fault with surge arresters installed between
the poles and ground at the terminals of each converter is shown in Figure A.33. The
PSCAD default surge arrester characteristic was used with a nominal voltage rating of
300kV.
Figure A.33: Positive pole-to-ground fault at MMC1 with under voltage protection and DC surge
arresters (no star-point reactor) ; arm currents are for MMC1 and capacitor voltages are for the
upper arm of phase A for MMC1; x axis – time(s)
Appendix 6A
295
APPENDIX 6A – PARAMETERS FOR MMC COMPARISON MODEL
MMC Comparison Model Parameters
Main Circuit Active power rating P 1000MW
Reactive power rating Q ±300MVAr DC voltage Vdc 600kV
MMC
Number of levels NL 31 Number of SMs per arm n 30
SM capacitance CSM 1150uF
Arm resistance1 Rarm 0.9Ω Arm inductance Larm 0.085H
Capacitor leakage resistance Rlc 10MΩ IGBT/diode on- state resistance Ron 0.01Ω IGBT/diode off-state resistance Roff 1MΩ
Transformer Leakage reactance XT 0.15pu
Primary winding voltage, L-L VTp 370kV Secondary winding voltage, L-L VTs 410kV
AC System Network voltage, L-L Vn 400kV Network resistance Rn 2.28Ω Network inductance Ln 0.145H
Inner Current loop control Proportional gain Kp 36
Integral time constant Ti 0.00015
CCSC Proportional gain Kp 150
Integral time constant Ti 0.00000745 CBC Sorting frequency Trig 30
1. Value includes the on-state resistance of the semi-conductor devices in each arm.
Table A.24: Parameters for MMC comparison model
Appendix 7A
296
APPENDIX 7A – HVDC CABLE PARAMETERS, BONDING AND
SENSITIVITY ANALYSIS
1 HVDC Cable Parameters
1.1 Core Conductor
The current ratings for ABB’s HVDC Light 320kV cable are given in Table A.25 and were
taken from [34]. The data is for a cable with a copper conductor installed in a moderate
climate with close spaced laying.
Table A.25: Submarine HVDC Light 320kV cable with copper conductor in a moderate climate with
close laying
The 1400mm2 cable has sufficient power rating at ±320kV for a typical connection of a
Round 3 windfarm, however, if the same cable was operated at ±300kV then the power
rating would be reduced to 956MW43
. The 1600mm2 cable is considered more appropriate.
The core conductor is typically made from strands of wire and therefore the conductor
radius, rc cannot be calculated in the normal manner using equation (A.197).
cc
Ar
(A.197)
The conductor radius of a 1600mm2 XLPE AC land cable is however given in Table A.26.
Table A.26: XLPE land cable systems
43
It is assumed that the design of a 300kV cable would be very similar to a 320kV cable and therefore the current capacity of both cables would also be very similar.
Conductor
Area
(mm²)
Voltage
rating
(kV)
Current
rating
(A)
Power
rating
(MW)
Resistance
(Ω/km)
Diameter over
cable (mm)
1400 320 1594 1020 0.0126 130
1600 320 1720 1101 0.0113 133
HVDC Light Cable Data
Conductor
Area
(mm²)
Radius of
conductor
(mm)
Insulation
thickness
(mm)
Capcitance
(uF/km)
1600 24.9 17 0.29
ABB XLPE Land Cable Systems Data
Appendix 7A
297
PSCAD assumes that the core conductors are solid and therefore the resistivity of the
copper needs to be modified to take into account the stranded nature of the conductor. This
is achieved using equation (A.198).
2
80.0113 0.0249
( / ) 2.2 10 /1 1000
R Am m
km
(A.198)
1.2 Lead Sheath
The thickness of the lead sheath for a typical single core XLPE submarine cable is
approximately 3mm according to ABB’s submarine user’s guide [115]. The electrical
resistivity of lead is given as 2.2x10-7
Ω/m [116].
1.3 Armour
The thickness of the steel armour for a typical submarine cable is assumed to be 5mm
[117]. The resistivity of the steel wire is given as 1.8x10-7
Ω/m [116] with a relative
permeability of 10 [117].
1.4 Semi-conducting layers
The latest version of PSCAD (X4) allows the conductor and insulator screens to be
represented in the cable model. In earlier versions of PSCAD the conductor and insulator
screens can be taken into account by modifying the relative permittivity of the insulator
[116]. The PSCAD default value for the screen thickness is employed in this work which is
1mm. The resistivity and relative permittivity for the semi-conducting layers cannot be set
by the user in PSCAD. It is therefore assumed that the cable parameters sub-routine is
using typical values.
1.5 Insulator
There is no official documentation regarding the insulation thickness of the HVDC Light
cables, however an ABB representative has stated that a 320kV HVDC Light cable has an
insulation thickness of about 18mm. The ABB representative also stated that using the
electrical parameters from an AC cable of similar thickness would yield similar results.
This indicates that the relative permittivity of XLPE and DC-XLPE is similar. The relative
permittivity of XLPE is given as 2.5 [114].
Appendix 7A
298
1.6 Polyethylene Inner Jacket
The inner jacket is assumed to have a thickness of 5mm [117]. The relative permittivity of
polyethylene is given as 2.3 [118].
1.7 Polypropylene Yarn Outer Cover
The outer cover thickness is assumed to be 4mm [117]. The relative permittivity of
polypropylene yarn is assumed to be very similar to that of polypropylene, which is 1.5
[118].
1.8 Horizontal Cable Distance
The positive and negative cables may be installed in separate trenches tens of meters apart
to prevent a ships anchor from damaging both cables [111, 120]. This is however
approximately 40% more expensive than installing both cables in a single trench. The use
of a single trench would result in a saving of about £40m for a 100km route [111] and by
laying both cables close together it means that their magnetic fields effectively cancel out.
Therefore, with the exception of cable routes which have lots of fishing activity, it is more
likely that the cables will be buried in a common trench. It has been assumed that the
horizontal distance between the two cables would be approximately two cable diameters
(0.25m).
1.9 Sea-return Impedance
The calculation of the sea-return impedance is complex. In order to calculate the sea-return
impedance accurately, accurate values of sea resistivity, sea-bed resistivity, sea depth,
cable burial depth and frequency are required.
The primary focus of this research is the connection of large offshore windfarms using
HVDC technology. Dogger Bank is a potential site for a Round 3 offshore windfarm which
has been leased by the Crown Estate to a consortium of developers. The site is situated
some 125-195km off shore [156], which makes HVDC transmission the only realistic
option. The sea depth of the site ranges from approximately 19 to 64 meters [156]. The sea
depth around the site is greater than the site and the sea depth will decrease closer to shore.
The sea depth along the cable route back to shore will therefore most definitely vary. In
addition the sea depth will fluctuate with the tide. The resistivity of sea water varies in the
range of 0.25-2Ω/m due to the temperature and the salinity of the water [119], which
Appendix 7A
299
makes it difficult to obtain an accurate value. Sea-bed resistivity logically speaking will
vary with the depth of the sea-bed and possibly along the cable route. Even if all the
different variables which affect the sea-return impedance for Dogger Bank could be
measured accurately, there is no known model which can factor all of them in to compute
the sea-return impedance.
Many studies which include submarine cables use the infinite sea model [117, 120], which
is based on [157] and assumes that the cable is surrounded by infinite sea in all directions.
This model therefore neglects the sea water/air interface and the sea water/seabed
interface. A new model proposed in [119] takes into account the sea water/air interface and
the sea water/seabed interface, however it assumes that the sea depth and soil resistivity are
constant and that the cable is laid on the surface of the seabed. In general this is not the
case and the cable will be buried 1-1.5 meters beneath the seabed to protect it from anchor
strikes [111, 120]. The new model is compared with the infinite sea model in [119], which
shows in general that there is little difference between the two models when the skin depth
of the sea is much less than the sea depth. If this condition is met, the results from [119]
show that the effect of soil resistivity is negligible. This indicates that the sea water/air
interface has a greater effect than the sea water/seabed interface.
The PSCAD models can only consider the sea water/air interface. PSCAD allows the user
to select whether the return impedance is solved using direct numerical integration
(Pollaczek) or an analytical approximation (Wedepohl or Saad). The approximation
method is normally accurate to within 5% of the exact solution and is much less time
consuming [158].
The effect that the sea-return impedance will have for the particular system model and
studies should also be considered. As an example, the sea-return impedance will have a
greater influence on a HVDC scheme employing a sea-return, than a HVDC scheme with a
metallic return. It is however more common to have a metallic return for environmental
reasons and due to the additional maintenance required for sea electrodes [30].
In summary the analytical approximation in PSCAD for the sea-return impedance will be
sufficient for the majority of simulation studies required for this research. The sea
resistivity and the vertical location of the cable are assumed to be of 1Ω/m and 50m below
the sea surface respectively.
Appendix 7A
300
1.10 Cable Bonding
For safety reasons cable sheaths must be bonded to ground. In the event that the cable
sheath is not bonded to ground, it could operate at a very large potential above ground.
This could make the cable sheath dangerous to touch and could cause damage to the layers
of the cable between the sheath and the ground.
In three-phase systems the main types of bonding arrangement are: single-point bonding,
solid bonding and cross bonding. Single-point bonding is where the sheath is bonded at
one end of the cable. This type of bonding removes the considerable heating effect from
circulating currents, but voltages will be induced along the length of cable, which increases
with the cable length and conductor current. Care must be taken to protect the free end of
the cable from excessive voltage, which is normally achieved using a surge voltage limiter.
The acceptable screen voltage potential normally limits the length of cable for which
single-point bonding can be used. Another disadvantage of single-point bonded systems is
that in the event of a phase to ground fault, the sheath is unable to carry the fault current.
Solid bonding is where the cable sheaths are bonded to ground at both ends of the cable.
This removes the problem of induced voltages but provides a path for circulating currents
to flow, which increases cable losses and therefore reduces the ampacity of the cable.
Cross-bonding avoids sheath circulating currents and excessive sheath voltages. This is
achieved by dividing the cable route into three equal lengths and cross-connecting the
sheaths of each phase. The voltage induced in the sheath of the cable within one section is
equal in magnitude but 120° out of phase. Therefore by cross-connecting the sheath, the
net voltage induced in each of the sheaths over the length of the cable is ideally zero.
Although cross-bonding increases the ampacity of the cable it can be expensive and is
impractical for submarine cables. For more information on bonding configurations see
[113].
In a HVDC system at steady-state there is no time-varying magnetic flux and therefore no
voltage induced in the sheath of the cable and no capacitive current. Therefore at steady-
state in a HVDC system the only current flowing in the sheath is due to the imperfections
in the cable’s insulation. A submarine HVDC cable could be single-point bonded, but this
makes little sense since there is no circulating current to affect the ampacity of the cable. In
addition for single-point bonded systems the sheath is unable to carry the fault current
Appendix 7A
301
during a phase-to-ground fault. Therefore solid-bonding is considered to be the ideal
bonding arrangement for submarine HVDC cables.
2 Cable Parameters Sensitivity
The effect of variations in the cable parameters on the cable’s transient voltage response
are assessed using the test model shown in Figure A.34.
Figure A.34: Cable parameter sensitivity test model
The cable is modelled using PSCAD’s frequency dependent phase cable model, which is
said to be the most accurate cable model commercially available [159]. The sheath and
armour in the submarine cable are usually bonded to ground at both ends of the cable
[120]. In this case the submarine cable’s sheath will be bonded to ground at both ends of
the cable through a small resistor. PSCAD gives the option to ground the last metallic layer
(armour in a submarine cable), which eliminates this layer from the impedance matrix.
Grounding the last metallic layer physically means that the layer is connected to ground
along its entire length. This is often a valid assumption for a submarine cable, where the
armour is a semi-wet construction which allows water to penetrate [117].
The sending end voltage source is initially set to 600kV and the load is modelled as a
350Ω resistor; hence the load is dissipating approximately 1GW. At 0.3s the sending end
voltage is increased to 605kV and the receiving end pole-to-pole voltage is measured. The
effect of varying the cable’s parameters on its transient voltage response is shown in the
following plots.
Increasing the thickness of the semi-conductor screen reduces the propagation velocity as
shown in Figure A.35. This is because increasing the screen thickness increases the
effective relative permittivity of the material between the core conductor and sheath.
Appendix 7A
302
Figure A.35: Effect of semi-conductor screen thickness on the receiving end voltage ; x axis – time(s)
Decreasing the relative permittivity of the insulation increases the propagation of velocity,
while variations in insulation thickness have virtually no effect as shown in Figure A.36.
Figure A.36: Effect of insulation design on the receiving end voltage ; x axis – time(s)
Increasing the effective resistance of the sheath, through decreasing the sheath thickness or
increasing the sheath resistivity, increases the attenuation of the cable as shown in Figure
A.37.
Appendix 7A
303
Figure A.37: Effect of sheath design on the receiving end voltage ; x axis – time(s)
Increasing the armour’s permeability or increasing its resistivity increases the cable’s
attenuation as displayed in Figure A.38. This is because increasing the amour’s
permeability reduces the skin depth of the armour and therefore effectively increases the
amour’s resistance for frequencies where skin depth is less than the armour thickness
[116].
Figure A.38: Effect of armour design on the receiving end voltage ; x axis – time(s)
The design of the inner jacket and outer jacket has virtually no effect on the receiving end
voltage as shown in Figure A.39 and Figure A.40 respectively.
Appendix 7A
304
Figure A.39: Effect of inner jacket design on the receiving end voltage ; x axis – time(s)
Figure A.40: Effect of outer jacket design on the receiving end voltage ; x axis – time(s)
Figure A.41 shows that the resistivity of the sea and the vertical location of the sea cable
has virtually no effect on the receiving end voltage.
Figure A.41: Effect of sea-return impedance on the receiving end voltage ; x axis – time(s)
Appendix 7A
305
The sensitivity analysis conducted in this appendix has shown that small variations in the
cable’s parameters do not have a significant effect on the cable’s transient voltage
response. It should be noted that the effect of the cable’s parameters on its electromagnetic
transient response may vary with the study. For example the effect of the sea-return
impedance has little effect for the test conducted in this chapter, but will have a greater
influence for line-to-ground faults.
3 Summary
Datasheets for physical and electrical properties of HVDC cables are not available in the
public domain. A set of parameters for a 1GW 300kV VSC-HVDC cable have therefore
been derived in this appendix based on available commercial documentation and reputable
academic papers. The estimated parameters may differ from a commercial cable and
therefore a sensitivity analysis on the cable’s parameters was conducted. The sensitivity
analysis has shown that small variations in the cable’s parameters do not have a significant
effect on the cables transient voltage response for the test conducted. This gives confidence
that the estimated parameters are sufficient to represent the dynamics of the cable for the
models in this thesis.