voter education presentation “journey to may 2021”
TRANSCRIPT
![Page 1: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/1.jpg)
Voter Education Presentation“Journey to May 2021”
Rebuilding Rowlett Infrastructure One Step at a Time! The Journey to 2021
and Beyond…
![Page 2: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/2.jpg)
What is all the talk about this Bond Election in May 2021?
What is the COMMUNITY INVESTMENT ADVISORY BOARD (CIAB) and what were they tasked with doing?
What is the status of the projects approved in the 2015 & 2018 Community Investment Bond Program?
How much will this initiative cost us and how will we pay for it?
What are the Propositions being considered for this bond?
What are the projects being proposed and where can I get more information?
When is election day/early voting?
![Page 3: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/3.jpg)
Community Investment Advisory Board
Target $40-50MTimeline: 3-year implementation
plan
NO TAX RATE INCREASE using current capacity
GOAL
S
$40-50 Million
3-Year Implementation and Project Delivery
NO TAX RATE INCREASE
FOU
NDA
TIO
NFinancial StewardshipSound PlanningCitizen EngagementCommunicationsCommunity GoodwillBalanced PrioritiesInnovative SolutionsLeveraging OpportunitiesResults OrientedAccountability to the Community
PRIO
RITI
ES
Transportation & CirculationPublic Safety Existing InfrastructureExisting Facilities Revitalization & Balanced Growth Quality of Life Regulatory Compliance External Funding Sources Impact on Operational Budget Timing/Location Special Considerations
RESU
LTS
Proposition A Paving & Drainage -$19.499 Million
Proposition B Parks, Trails, & Recreational Facilities - $7.365 Million
Proposition C Public Safety - $2.286 Million
![Page 4: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/4.jpg)
CIAB Members & Staff• CIAB Members
– Brian Galuardi, Chair– Jeff Sheldon, Vice Chair– Michael Volz– Micah Rabalais– Noel Wardrope– Tiffany Batiste– Victor Cardoso– David Smith, Alternate– Yvonne Newkirk, Alternate– Ronald McCarty, Alternate
• Council Liaison– Whitney Laning
• Staff– Brian Funderburk, City Manager– Angie Smith, Deputy City Manager– Laura Hallmark, City Secretary– Wendy Badgett , Director of Finance– Gary Enna, Public Works Director– Aaron Cleaver, Director of Parks and Recreation– Neil Howard, Fire Chief
![Page 5: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/5.jpg)
The CIP Process is Ongoing• This is for projects that go beyond the
3-Year planThe City is developing an ongoing
5-Year CIP with a Long-Term Outlook
• This will be accomplished through the annual budget process
The CASH CIP will continue to fund smaller projects and repair
initiatives in the neighborhoods
• So, your input is valuable in the ongoing planning process
Any projects suggested by the public are being kept for the next
initiative
• Stay tuned and check the City’s website at www.Rowlett.com
In fact, you will be able to submit your project from the web portal
after the 2021 Bond Election5
![Page 6: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/6.jpg)
Balancing Priorities
Existing Infrastructure
Needs
Planning for Growth and
Capacity Needs
Quality of Life
Initiatives
![Page 7: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/7.jpg)
What about the funding from the last two bond elections?
7
![Page 8: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/8.jpg)
8
74%
16%
10%
2015 BOND ELECTION PROJECT BREAKDOWNPROPOSITION 1 - STREETS - $18,932,340PROPOSITION 2 - PARKS - $4,206,110PROPOSITION 3 - PUBLIC SAFETY - $2,631,050
TOTAL = $25,769,500
![Page 9: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/9.jpg)
2015 Community Investment Bond Program Status
• Thornhill/Faulker-Jones/Colonial/Powell/Persimmon Alleys –Design 90% complete
Proposition 1 –Streets
• Only outstanding project is restroom at Lakeside Park – construction to begin Summer 2021.
Proposition 2 –Parks
• ALL Projects Completed!Proposition 3 –Public Safety
9
![Page 10: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/10.jpg)
69%
15%
16%
2018 BOND ELECTION PROJECT BREAKDOWNPROPOSITION A - PAVING & DRAINAGE - $41,470,000PROPOSITION B - PARKS, TRAILS & RECREATIONAL FACILITIES - $8,955,000PROPOSITION C - PUBLIC SAFETY & FACILITIES - $9,485,000
TOTAL = $59,910,000 10
![Page 11: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/11.jpg)
2018 Community Investment Bond Program Status
•Majority of projects are complete. Alleys in Construction are Daisy/Thistle-Dandelion/Trumpet Alleys. Projects in design are Lakeshore/Windridge-Rice/Tulane Alleys, Chiesa Road from Dalrock to Miller, and Right Turn Lanes various locations. Design is complete on Miller Road widening from Dalrock to Glen Hill – currently purchasing easements to begin construction.
Proposition 1 – Paving & Drainage
•Majority of projects complete. Remaining projects are Herfurth Park Phase I construction, Lakefront at Pecan Grove construction, Lake Highland Trail construction, Sports field construction – all slated for Summer 2021.
Proposition 2 – Parks, Trails & Recreational
Facilities
•Fire Station #2 rebuild under construction – slated for June 2021 completion.Proposition 3 – Public
Safety & Facilities
11
![Page 12: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/12.jpg)
How much will the 2021 bonds cost us and how will we pay for it?
![Page 13: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/13.jpg)
Existing Debt Service Schedule
Up until 2015, it had been nearly 10 years since the last
measurable governmental bonds were issued.
As a result, the City has a large curve where bonded
indebtedness will significantly drop off over the next several
years.
13
$0
$2,000,000
$4,000,000
$6,000,000
$8,000,000
$10,000,000
$12,000,000
$14,000,000
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
2037
2038
2039
2040
2041
City of RowlettCurrent Tax Related Debt Service and Future Bonding Capacity
Current Tax Supported Debt New Issue Series 2021, 2022, 2023 Future Capacity
Future Capacity From Declining Debt
Existing Debt
![Page 14: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/14.jpg)
Future Bonding Capacity
Despite the 3-year bond election cycles approved in 2015 and
2018, bond capacity remains that could provide the ability to issue as much as $40 million over the three years without a tax rate
increase.
14
$0
$2,000,000
$4,000,000
$6,000,000
$8,000,000
$10,000,000
$12,000,000
$14,000,000
$16,000,000
$18,000,000
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
2037
2038
2039
2040
2041
City of RowlettCurrent Tax Related Debt Service and Future Bonding Capacity
Current Tax Supported Debt New Issue Series 2021, 2022, 2023 Future Capacity Growth Capacity
Future Capacity From Declining Debt
Future Capacity From Growth
![Page 15: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/15.jpg)
Leveraged Bond Packages
As we have done over the past 6 years, this bonding capacity can
be leveraged in three-year increments to maximize our
opportunities.
Again, this provides significant dollars for streets, alleys,
neighborhood and recreational improvements, public safety and
other needs.
15
$0
$2,000,000
$4,000,000
$6,000,000
$8,000,000
$10,000,000
$12,000,000
$14,000,000
$16,000,000
$18,000,000
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
2037
City of RowlettHypothetical Leveraged Bond Packages
Current Tax Supported Debt New Issue Series 2017
New¹ New²
New³ New⁴
![Page 16: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/16.jpg)
Current Forecasts
16
• The 2021 bond election capacity is projected at approximately $40M
• The amount of the 2021 bond election was set by Council at $29.15M with the potential to call an additional bond election in November 2021 for the remaining $10.85M capacity
• The 2024 bond election capacity is projected at approximately $60M
• This can be achieved with NO TAX INCREASE
SERIES 2021 SERIES 2022 SERIES 2023
$12,216,000 $7,215,000 $9,719,000
3.00% 4.00% 4.00%
Assume 8/1 delivery date in each year
![Page 17: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/17.jpg)
17
$29,150,000 $10,850,000 $60,845,000 No Tax Rate Increase
![Page 18: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/18.jpg)
If the Bond Election is successful, what projects will get built?
![Page 19: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/19.jpg)
67%
25%
8%
2021 BOND ELECTION PROJECT BREAKDOWNPROPOSITION A - PAVING & DRAINAGE - $19,499,000PROPOSITION B - PARKS, TRAILS AND RECREATIONAL FACILITIES - $7,365,000PROPOSITION C - PUBLIC SAFETY - $2,286,000
TOTAL = $29,150,000 19
![Page 20: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/20.jpg)
What are the 2021 projects and how much will it cost us?
20
Paving & Drainage$19,499.000
• Lakeland Heights Phase 2 -construction
• Concrete Pavement Replacement
• Merritt Interconnector
• Long Branch Creek Erosion Control
• Toler Business Park Phase 1 & 2
• Country Aire Estates, Phase 1 & 2
• Alley Reconstruction
• East Industrial
Parks, Trails and Recreational Facilities$9,365,000
• Herfurth Park Phase 2 & 3
• Wet Zone• Trail Construction• Erosion Control at Lake
Ray Hubbard parks• Community Park –
Sports Field Improvements
Public Safety$2,286,000
• Replace Emergency Siren System
• Sapphire Bay Fire and Police Station Design
![Page 21: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/21.jpg)
2021 Project Details
21
![Page 22: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/22.jpg)
PROPOSITION A
• Shall the City Council of the City of Rowlett, Texas, be authorized to issue and sell the bonds of said City, in one or more series or issues, in the aggregate principal amount of $19,499,000, for the purpose of designing, constructing, reconstructing, improving, extending, expanding, upgrading and developing streets, roads, sidewalks, thoroughfares and related improvements in the City, including pedestrian rights-of-way, related drainage, utility relocation, signalization, landscaping, lighting, and signage, and the purchase of land, any necessary rights-of-way and other costs related to such street and road projects; with said bonds to be issued in one or more series or issues, to mature, bear interest at such rate or rates, not to exceed the respective limits prescribed by law at the time of issuance, and to be sold at such price or prices, as the City Council in its discretion shall determine; and shall there be levied and pledged, assessed and collected annually ad valorem taxes on all taxable property in said City in an amount sufficient, within the limits prescribed by law, to pay the annual interest on said bonds and provide a sinking fund to pay said bonds at maturity?
22
![Page 23: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/23.jpg)
Lakeland Heights Phase 2 – $1,634,000• Design Cost : Designed in 2018 Bond Program • Construction Cost*: $1,634,000 • Scope: The project includes installing a new
drainage system, pavement and sidewalks, street trees, and decorative street lighting on portions of Lisa Drive, Leanne Lane and Sandra Lane. Phase 1
Phase 2
* water/sewer revenue C.O. bond funds will also need to be issued for replacing water and sewer lines but not part of CIAB Bond Issuance
![Page 24: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/24.jpg)
Concrete Pavement Replacement - $3,000,000• Design Cost : None• Construction Cost*: $3,000,000 • Scope: The project includes removing and
installing failed street pavement panels throughout the City of Rowlett.
*Cost for each location and panel variesdepending on pavement thickness and location.$1,000,000 allocated per year.
![Page 25: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/25.jpg)
Merritt Interconnector - $2,000,000• Design Cost : Designed with 2015/2018 Bond
Program • Construction Cost: $2,000,000 • Scope: Funds required to secure future grant
dollars for constructing an interconnector for Liberty Grove to PGBT, including drainage system, pavement, bridge, sidewalks, street trees, and decorative street lighting.
![Page 26: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/26.jpg)
Long Branch Creek Erosion Control - $2,735,000• Design & Construction Cost: $2,735,000• Scope: The project includes removing failing
creek channel areas and stabilizing with gabion baskets, Turf Reinforcement Mat, and other methods of erosion protection. It is estimated that approximately 5 of the worst areas which are located east of Rowlett Road and south of Miller Road can be stabilized, based on the estimated cost for survey, design and construction.
![Page 27: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/27.jpg)
Toler Business Park PH1 - PH2 Eng. - $2,157,000• Design & Phase 1 Const. Cost*: $2,157,000• Scope: The project includes designing both
PH1 and PH2 and constructing PH1. Project includes new pavement, drainage, sidewalks and street lighting.– Phase 1 – Century Dr., Vaughn Dr. to
Rowlett Rd.– Phase 2 –Lawing Ln, Vaughn Dr. and
Singleton St.
*water/sewer revenue C.O. bond funds will also need to be issued for replacingany water and sewer lines but not part of CIAB Bond Issuance
Phase 1Phase 2
RO
WLE
TT R
D.
LAWING DR.
SINGLETON ST.
VAU
GH
AND
R.
![Page 28: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/28.jpg)
Country Aire Estates PH1 - PH2 Eng. - $1,144,000• Design & Phase 1 Const. Cost*: $1,144,000 • Scope: The project includes designing both PH1
and PH2 and constructing PH1. Project includes new pavement, drainage, sidewalks and street lighting.– Phase 1 – Salzburg Dr. from Chiesa Rd.to
Acapulco Dr.– Phase 2 – Swiss Way from Acapulco Dr. &
Salzburg Dr. from Acapulco Dr. to Richmond Ct.
*water/sewer revenue C.O. bond funds will also need to be issued for replacingany water and sewer lines but not part of CIAB Bond Issuance
Phase 1Phase 2
RIC
HM
ON
D C
T.
SALZBURG DR.
SWISS WAY
ACAP
ULC
O D
R.
CH
IESA
RD
.
SALZBURG DR.
MUNICH DR.
![Page 29: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/29.jpg)
Alley Reconstruction Program $2,000,000
• Design & Construction Cost: $2,000,000• Scope: The project includes designing and
reconstructing approximately six alleys to City’s current standards. Drainage improvements may be required for certain alleys.
*water/sewer revenue C.O. bond funds will also need to be issued for replacingany water and sewer lines but not part of CIAB Bond Issuance
![Page 30: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/30.jpg)
East Industrial - $4,829,000• Design & Const. Cost*: $4,829,000• Scope: The project includes designing and
constructing Industrial from PGBT to the DART Station Parking Lot. The project will add boulevard style sidewalks, landscaping and street lighting.
*water/sewer revenue C.O. bond funds will also need to be issued for replacingany water and sewer lines but not part of CIAB Bond Issuance
INDUSTRIAL DR.
LAKEVIEW PKWY
MAR
TIN
DR
.
MAIN ST.
![Page 31: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/31.jpg)
PROPOSITION B
• Shall the City Council of the City of Rowlett, Texas, be authorized to issue and sell the bonds of said City, in one or more series or issues, in the aggregate principal amount of $7,365,000, for the purpose of designing, constructing, improving and equipping municipal parks and recreational facilities, including trails, sport fields, recreational parks, aquatic facilities, parking and related infrastructure, and the acquisition of land and interests in land necessary therefore; with said bonds to be issued in one or more series or issues, to mature, bear interest at such rate or rates, not to exceed the respective limits prescribed by law at the time of issuance, and to be sold at such price or prices, as the City Council in its discretion shall determine; and shall there be levied and pledged, assessed and collected annually ad valorem taxes on all taxable property in said City in an amount sufficient, within the limits prescribed by law, to pay the annual interest on said bonds and provide a sinking fund to pay said bonds at maturity?
31
![Page 32: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/32.jpg)
Herfurth Park Phase 2 & 3 - $3,600,000
• Design & Const. Cost: $3,600,000• Scope: Design and construct Herfurth
Park renovations, which will include the Active Play Zone and Main Street Zone. This funding, along with funding from 2018, will complete the renovation of Herfurth Park.
![Page 33: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/33.jpg)
Wet Zone Waterpark – $765,000• Project Cost: $765,000• Scope: Project includes upgrades to Wet Zone Waterpark that includes
new thematic painting for facility, new features for Turtle Cove, new shade structures, and new fencing around the complex.
![Page 34: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/34.jpg)
Trail Construction - $2,000,000
• Design & Const. Cost*: $2,000,000• Scope: The project will focus on completing additional trails
on the trail priority list including Garner, Fuqua, Spinnaker Point and Schrade Road Trail.
![Page 35: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/35.jpg)
Erosion Control - $500,000• Design & Const. Cost: $500,000• Scope: The project will address lake erosion control
in Scenic Point Park, Lakeside Park South, and Paddle Point Park. All Lake Ray Hubbard erosion control methods need to be approved by the City of Dallas.
![Page 36: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/36.jpg)
Community Park - $500,000
• Project Cost: $500,000• Scope: The project includes sports field upgrades and
improvements to baseball, t-ball and softball fields located at Community Park.
![Page 37: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/37.jpg)
PROPOSITION C
• Shall the City Council of the City of Rowlett, Texas, be authorized to issue and sell the bonds of said City, in one or more series or issues, in the aggregate principal amount of $2,286,000, for the purpose of designing, constructing, improving and equipping public safety facilities, including fire and police facilities and an emergency warning system, and the acquisition of land and interests in land necessary therefor; with said bonds to be issued in one or more series or issues, to mature, bear interest at such rate or rates, not to exceed the respective limits prescribed by law at the time of issuance, and to be sold at such price or prices, as the City Council in its discretion shall determine; and shall there be levied and pledged, assessed and collected annually ad valorem taxes on all taxable property in said City in an amount sufficient, within the limits prescribed by law, to pay the annual interest on said bonds and provide a sinking fund to pay said bonds at maturity?
37
![Page 38: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/38.jpg)
Replace outdoor warning siren system - $1,336,000
• Design & Const. Cost: $1,336,000Scope:
• Purchase and install a new outdoor warning system, including Whelen 10-cell omni directional sirens, lightning detection in major parks, cameras, weather stations, and fiber connection.
![Page 39: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/39.jpg)
Design Fire/Police Station at Sapphire Bay - $950,000• Design Cost: $950,000
Scope: Project includes design of the joint fire/police station at Sapphire Bay. Construction will be included in a future bond election.
![Page 40: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/40.jpg)
So How Can You Get More Information?
![Page 41: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/41.jpg)
CIP Public Outreach
Something for
Everyone
Bond Election Information MeetingsMonday, April 12th @ 6:30pmCome find out all the details about the 3 Propositions and projects on the ballot. Watch it on Facebook LIVE!!
Interactive Map with Detailed Information on Every Project
Website with Informational
Links
Facebook LiveTown Hall Meeting
Informational Newsletter Mailed to Everyone
![Page 42: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/42.jpg)
Interactive Map – Rowlett.com/2021bondmap
42Clic
k he
re
![Page 43: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/43.jpg)
Rowlett.com/2021bond
43
Clic
k he
re
![Page 44: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/44.jpg)
Important Milestones and Dates
Community Education/Outreach Meetings – continue through March & April
Meetings planned with all Boards and Commissions – March 2021
Bond Election Information Meetings – April 12th– 6:30PM
Early Voting dates – April 19, 2021 through April 27, 2021
Election Day – Saturday, May 1, 2021
Issuance of FY21 Bonds – Late summer of 2021
Design, Planning & Construction of Projects - over next 3 years
44
![Page 45: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/45.jpg)
Other things you may need…
• Newsletter/Mailer– Summary of projects and
process• Email address
– If you have questions and want to contact us
[email protected]• Bond Election Information
– Monday, April 12th @ 6:30pm– Facebook Live
45
![Page 46: Voter Education Presentation “Journey to May 2021”](https://reader033.vdocuments.us/reader033/viewer/2022061016/629a41de29cebe063e6277ed/html5/thumbnails/46.jpg)
Questions?