volume 2 chapter 7 construction impact assessment

Upload: dramit-dutta

Post on 03-Apr-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Volume 2 Chapter 7 Construction Impact Assessment

    1/21

    7

    .0Constructionimpac

    tassessment

    7.0 Construction

    impact assessment

  • 7/28/2019 Volume 2 Chapter 7 Construction Impact Assessment

    2/21

    Chapter 7 Construction impact assessment 7-1

    7 Construction impact assessment

    This chapter discusses the Projects potential environmental effects on the

    marine environment that may occur during construction. The environmentalimpact assessment for construction is based on specialist findings from the

    following reports:

    Bassett (2008) Underwater Noise(Technical Appendix 22)

    Biosis Research (20082)Assessment of Marine Mammals, Birds, and

    Reptiles for the Desalination Project, Bass Coast, Victoria(Technical

    Appendix 13)

    Biosis Research (20087) Cultural Heritage Existing Conditions and Impact

    Assessment Report Plant site(Technical Appendix 45)

    Consulting Environmental Engineers (CEE) (2008) The Desalination ProjectMarine Biology (Technical Appendix 31)

    Essential Economics (20082) Victorian Desalination Project Impact

    Assessment(Technical Appendix 11)

    GHD (20084) Invasive Marine Species(Technical Appendix 27)

    Maunsell Australia (Maunsell) (20085) Victorian Desalination Project

    Environment Effects Statement-Social Impact Assessment Report(Technical

    Appendix 56).

    Volume 1Synthesis of

    environmentaleffects

    Volume 2Environmental

    effects ofMarine Structures

    Volume 3Environmental

    effects ofDesalination Plant

    Volume 4Environmental

    effects ofTransferPipeline

    Volume 5Environmental

    effects ofPower Supply

    TechnicalAppendix

    Chapter 7Construction

    impact assessment

  • 7/28/2019 Volume 2 Chapter 7 Construction Impact Assessment

    3/21

    Table 7-1 Construction risks assessed as medium or above

    Activity Impact pathway

    Consequence

    Likelihood

    k

    Seabed clearing Removal or damage of reef habitat Moderate Certain

    Ris

    High

    Removal or damage of sandy habitat Minor Likely Medium

    Destruction of or disturbance to significant reef species Moderate Likely Medium

    7-2 Chapter 7 Construction impact assessment

    Marine construction activities for the Reference Project, as detailed in Chapter 2

    of this Volume, would build the Marine Structures by tunnelling under the

    dunes, beach and seafloor and would install the intake and outlet structures.

    Self-elevating platforms (SEPs) would conduct marine drilling. These temporary

    structures may be serviced (with materials and people) from land by marine

    vessels and helicopters.

    7.1 Impact assessment

    This section discusses the potential impacts of construction activities of the

    Marine Structures on the marine environment. Both the risk assessment and the

    impact assessment recognise that, like the Reference Project, the Project must

    comply with the Performance Requirements set out in Chapter 11 of Volume 1.

    7.1.1 Risks assessed medium or above

    The risk assessment was conducted for the Variations as well as the Reference

    Project and impacts on the marine environment are applicable to these

    Variations. Construction risks and potential impacts for the Variations multiple

    smaller conduits, passive screens at the intake head, pipeline diffuser and

    alternate locations for the Marine Structures (low profile reef or sand in deeper

    water) are considered to be similar to the Reference Project and are discussed

    below where applicable.

    Table 7-1 sets out the risks associated with construction of the Marine

    Structures which were rated medium or above. The risks are discussed in order

    of activity and likelihood with those most likely to occur discussed first.

  • 7/28/2019 Volume 2 Chapter 7 Construction Impact Assessment

    4/21

    Table 7-1 Construction risks assessed as medium or above

    Activity Impact pathway

    Consequence

    Likelihood

    k

    Generation of noise Impact pile driving impacting on fish Moderate Likely Medium

    Ris

    and vibrationUse of air guns impacting on fish Moderate Likely Medium

    Use of air guns impacting on smaller toothed cetaceans, Minor Likely Medium

    mammals and sea birds

    Geophysical surveys other than air guns impacting on fish Minor Likely Medium

    Use of chemicals and Small chemical/hydrocarbon spill or incident impacting on Minor Almost Medium

    hydrocarbons marine biota and ecosystems certain

    Medium or significant chemical/hydrocarbon spill or incident Moderate Unlikely Medium

    impacting on water column, intertidal marine biota and marineecosystems

    Medium or significant chemical / hydrocarbon spill or incident Major Rare Medium

    impacting on the marine park

    Production of drilling Release of spoil at the drill site impacting on reef biota and Minor Likely Medium

    spoil ecosystems

    Disposal of spoil at a selected oceanic location impacting on Minor Likely Medium

    marine biota and ecosystems

    Movement of marine Increase in marine traffic impacting on fishing and recreational Minor Almost Medium

    vessels activities Certain

    Introduction of flora and fauna marine pests from marine Major Unlikely Medium

    vessels impacting on marine species

    Increase in marine traffic impacting on public safety Major Rare Medium

    Use of construction Introduction of abalone disease impacting on commercial Extreme Unlikely High

    divers viability of abalone diving industry in the Project area

    Introduction of abalone disease impacting on abalone Major Unlikely Medium

    communities

    Chapter 7 Construction impact assessment 7-3

  • 7/28/2019 Volume 2 Chapter 7 Construction Impact Assessment

    5/21

    Table 7-1 Construction risks assessed as medium or above

    Activity Impact pathway

    Consequence

    Likelihood

    k

    All construction Social impacts of construction of Marine Structures impacts Minor Certain Medium

    Ris

    activities on amenity

    Potential for reduced visitation and loss of business revenue Moderate Almost High

    due to perception that the Wonthaggi / Kilcunda coastline is

    becoming industrialised

    certain

    Construction Impacts on commercial fishing Minor Likely Medium

    exclusion zone

    Increased access to People accessing Williamsons Beach impacting on threatened Moderate Unlikely Medium

    Williamsons Beach fauna

    7-4 Chapter 7 Construction impact assessment

    The above risk assessment is based on accepted construction practices but does not take into account the mitigation measures

    embodied in the Performance Requirements. If the Performance Requirements are taken into account, both the likelihood and

    consequence of these risks may be significantly lower.

    7.2 Seabed clearing

    Some clearing of the seabed would occur to create a level platform for

    placement of equipment including SEP legs, anchors and cables that would be

    used to position and anchor the SEPs. This would likely disturb some biological

    habitats and affect the associated biological communities, although disturbance

    would likely be localised to around the SEPs. Benthic communities are mostlikely to be affected by seabed clearing. There may be localised damage to the

    seabed and the plants and animals that inhabit the affected areas. Generally,

    marine mammals are expected to avoid disturbed areas due to noise and

    vibration from construction activities, so it is unlikely that clearing activities

    would affect these species.

    Seabed clearing for the multiple smaller conduits and the pipeline diffuser

    Variations is expected to encompass a similar area as the clearing required for

    the Reference Project. Clearing for alternate Marine Structure locations (also a

    Variation in the Reference Project) would also be similar to the Reference

    Project as these locations would not be within marine sensitivity areas.

  • 7/28/2019 Volume 2 Chapter 7 Construction Impact Assessment

    6/21

    The consequence of these activities are not considered to be significant as SEPs

    and associated infrastructure would be removed from the marine environment

    upon completion of construction of the Marine Structures and it is expected that

    these communities would recover to their original state after construction

    activities are complete. Secondary effects due to clearing (such as dispersal of

    sand from the seabed) would also only occur for a short period of time.

    Disturbed areas in the marine environment tend to be rapidly colonised by a

    succession of marine biota, usually resulting in a marine biological assemblage

    similar to the community that existed prior to disturbance (CEE 2008, Technical

    Appendix 31).

    7.3 Generation of noise and vibration

    Many marine mammals rely on sound as their primary method of

    communication. Some species may even use echolocation to determine the

    physical features of their surroundings. These animals communicate underwater

    at varying frequencies. Therefore, artificial sources of underwater noise may

    impact marine mammals by masking biologically important sounds. This could

    induce a behavioural response causing a temporary threshold shift (TTS) or

    permanent threshold shift (PTS) in hearing.

    Pile driving may be required during construction (based on geological

    conditions), depending on final siting of the Marine Structures. Pile driving, if

    required, would emit noise and vibration. The noise from pile driving is generally

    high level, low frequency and impulsive. The noise level from pile driving would

    depend on the pile diameter, local geology and bathymetry. Intense, impulsive

    signals such as those produced from pile drivers can affect fish, and noise levelsof a smaller magnitude can cause behavioural changes. Damage to hearing by

    intense sound depends on the auditory threshold of the receiving species and

    would therefore vary from species to species (Bassett 2008, Technical Appendix

    22). Noise from pile driving is expected to affect individual fish but not

    significantly affect species at the population level.

    Geophysical surveys (including the use of air guns) used to characterise the

    marine geology prior to construction have the potential to generate periodic

    underwater noise and vibration.

    Chapter 7 Construction impact assessment 7-5

  • 7/28/2019 Volume 2 Chapter 7 Construction Impact Assessment

    7/21

    Noise modelling was undertaken by Bassett (2008, Technical Appendix 22) using

    a software implementation of the Range-dependent Acoustic Model (RAM) to

    estimate geophysical survey construction noise and evaluate the consequence to

    marine biota. Modelling was undertaken for boomers and sparkers (used in

    geophysical surveys), which are mid-frequency sources used in seismic and

    hydrographic survey. These devices would likely be used for geophysical surveys

    for the Marine Structure tunnels.

    Figure 7-1 presents the noise modelling results for geophysical surveys. Results

    are presented between 16 hertz and 1 kilohertz. In order to provide a three-

    dimensional picture of the noise, each individual figure shows the modelled

    noise propagation along a transect radiating from the noise source. The noise

    source can be seen at the left of each of the bathymetric tracks with red

    indicating high noise levels. The variable line indicates the seabed. The colour

    gradient shows the sound pressure level (SPL) expressed in decibels. The

    modelling estimates the potential for some species of fish to be impacted within

    two kilometres of geophysical surveys operating at a typical source level of 230decibels (Bassett 2008, Technical Appendix 22).

    The impact on cetaceans, sea birds, mammals and reptiles is considered lower

    than the potential impact on fish. The soft start management procedure in the

    EPBC Act Policy Statement 2.1, which regulates seismic testing activities as they

    affect cetaceans, recommends a gradual increase of the geophysical source over

    a 30-minute period. This is expected to alert animals and enable them to move

    away from the disturbed area. Since this method would be required by the

    Performance Requirements, cetaceans, fish, sea birds, mammals and reptiles

    are not expected to be significantly affected by geophysical surveys including

    the use of air guns (Bassett 2008, Technical Appendix 22).

    7-6 Chapter 7 Construction impact assessment

  • 7/28/2019 Volume 2 Chapter 7 Construction Impact Assessment

    8/21

    Figure 7-1 Noise modelling results for geophysical survey at the intake location

    Bassett 2008

    7.4 Use of chemicals and hydrocarbons

    Chemicals and hydrocarbons would be used for marine construction, largely for

    vessel and equipment fuelling. These chemicals would not be placed in the

    marine environment, but accidental spills could occur. Accidental spills of

    hydrocarbons may affect:

    marine biota and ecosystems

    water column

    Chapter 7 Construction impact assessment 7-7

  • 7/28/2019 Volume 2 Chapter 7 Construction Impact Assessment

    9/21

    the intertidal community

    the marine parks in the region.

    The level of impact is dependent on the types of chemical used and their

    toxicity. The risk process identified that accidental small chemical orhydrocarbon spills would be almost certain to occur during the construction

    phase, but are likely to have only minor effects on any communities or

    ecosystems because quantities of chemicals stored and used would generally be

    small. Medium or significant spills are considered unlikely to occur. The PRs

    require development and implementation of methods and management systems

    to limit on-vessel storage and/or use of hazardous substances and dangerous

    goods, which would reduce the risk of spills.

    If a spill were to occur, it is expected to only affect individual marine biota,

    rather than entire populations and any effects, though moderate, are likely to be

    temporary and localised.

    The risk of an accidental spill affecting the neighbouring marine park was rated

    as low because the quantity of any spill is likely to be small and the marine

    parks are located at a sufficient distance from the Project area to minimise the

    impact. Accidental spills are not likely to have any significant or long-term

    effects on any population of marine mammal, sea birds or reptiles (Biosis

    Research 20082, Technical Appendix 13).

    7.5 Production of drilling spoil

    Spoil will be generated from tunnelling and drilling for the Marine Structures.

    Based on the Reference Project, if a suitable marine spoil disposal site can not

    be identified, most of the drilling spoil will be collected on the jack-up barge and

    later taken to land for disposal. Any impact on the marine environment is

    expected to be minimal as the Performance Requirements specify disposal of

    any spoil from marine construction in accordance with EPA Best Practice

    Guidelines for Dredging and the National Ocean Disposal Guidelines.

    7-8 Chapter 7 Construction impact assessment

  • 7/28/2019 Volume 2 Chapter 7 Construction Impact Assessment

    10/21

    7.6 Movement of marine vessels

    Marine traffic would be largely from the movement of vessels to the SEPs from

    the shore.

    7.6.1 Increase in marine traffic

    It is possible that the movement of marine vessels could disturb recreational

    users in the Project area, especially fishing activities and affect public safety.

    Any disruption is expected to have a minor effect on recreational and fishing

    activities because the duration of the impact would be limited to the

    construction period. The construction exclusion zone would limit interactions

    between construction vessels and the public such that any impact would be

    from the exclusion zone rather than marine traffic. The exclusion zone is

    designed to protect public safety and would ensure that no public safety impacts

    arise from increases in marine traffic.

    7.6.2 Introduction of pests and disease

    Movement of construction and support vessels and discharge of ballast waters

    by vessels arriving from international and domestic locations have potential to

    spread marine pests if not properly managed. Marine pests and disease could

    also be transported via attachments to the hulls of ships (biofouling).

    The spatial and time scale over which the transplant of an introduced species

    may affect the marine environment is difficult to predict; however, the

    movement of introduced species into areas where there are no natural controls

    may have widespread ecological effects. The translocation of some pests can

    cause changes to biodiversity in the immediate affected area. Compliance with

    Commonwealth and State legislation requirements for ballast water would likely

    reduce the probability of pest species translocations and standard operating

    procedures have been developed in recognition of the risk that marine industries

    pose in translocating marine pests. The movement of vessels to and from the

    Project area poses no greater risk than any other marine industry in introducing

    marine pests. However, the Performance Requirements require development

    and implementation of a marine pest risk management process (including

    monitoring) to further reduce the risk of the introduction, spread andestablishment of marine pests (GHD 20084, Technical Appendix 27).

    Chapter 7 Construction impact assessment 7-9

  • 7/28/2019 Volume 2 Chapter 7 Construction Impact Assessment

    11/21

    7.7 Use of construction divers

    The disease of greatest concern is the ganglioneuritis virus that affects abalone.

    This disease appears to be spread by several vectors, including through the

    action of ocean currents, the use of abalone as fishing bait and by attaching to

    diving equipment and boats. Divers may be used to assist with sub-surface

    construction. This disease was detected in the wild in western Victoria in May

    2006 and has now currently spread approximately five kilometres from the

    Twelve Apostils Marine National Park eastern boundary (CEE 2008, Technical

    Appendix 31).

    Although it is considered unlikely that this disease would be introduced to the

    Project area, the consequence of this introduction would be serious as it may

    have significant implications for abalone commercial fishing and the areas

    abalone population. Additionally, experience from the infection site in western

    Victoria indicates that the disease can infect large areas after introduction (CEE

    2008, Technical Appendix 31). The PRs require specific risk managementprocesses to limit the risk of introduction of this abalone disease in the Project

    area (see section 7.11).

    7.8 Construction affecting social Amenity

    Collectively, construction activities are expected to affect the visual amenity of

    the local area, as the Project may interrupt the quality of coastal views in some

    areas. The coastal area is valued for its significant scenic landscape created by

    the intersection between the coast and the Strzelecki foothills. The community

    also values the views across to Phillip Island and east to Gippsland and thescenic quality of the undeveloped tourist route near Phillip Island. Any effect

    on amenity from construction is expected to be minor as construction activities

    would be restricted to a small section of the coast and would only extend for the

    temporary construction period (Maunsell 20085, Technical Appendix 56).

    7-10 Chapter 7 Construction impact assessment

  • 7/28/2019 Volume 2 Chapter 7 Construction Impact Assessment

    12/21

    The community consultation for the Project identified a concern that the Project

    would contribute to a general industrialisation of the Wonthaggi coastline,

    which could generally change the perception of the area and lower tourist visits.

    Most tourism in the area occurs in and around Philip Island and well away from

    the Project area. While a moderate impact on visitation and eco-tourism is

    expected in the immediate area of Wonthaggi during construction, the

    construction activities, as such, are of limited duration and are not expected to

    appear to industrialise the area.

    7.9 Exclusion zone

    A construction exclusion zone would be required to ensure health and safety of

    the general public. The temporary exclusion zone would preclude all marine

    activities including commercial fisheries and recreational uses within this zone in

    order to prevent the interaction between construction activities and other public

    and commercial activities.

    The construction area is frequently fished for rock lobster and abalone near-

    shore and less frequently for shark and squid offshore (CEE 2008, Technical

    Appendix 31). According to ABS census data (Essential Economics 20082,

    Technical Appendix 11), there are 30 to 40 jobs out of a population of around

    10 000 that are associated with the commercial fishing industry. The

    aquaculture and fishing industries are very small with respect to total business

    and employment (less than one per cent) in the area. Since the exclusion zone

    would only preclude commercial fishing from a small area (approximately two

    kilometres by two kilometres) and any reduction of commercial fishing would

    affect only a small percentage of the population for only the short constructionperiod, the exclusion zone would only have a minor effect on commercial fishing

    and it is not expected to have any long-term effects on commercial fishing in the

    local area.

    Chapter 7 Construction impact assessment 7-11

  • 7/28/2019 Volume 2 Chapter 7 Construction Impact Assessment

    13/21

  • 7/28/2019 Volume 2 Chapter 7 Construction Impact Assessment

    14/21

    Tunnel collapse

    It is highly unlikely that any tunnel collapse would affect the marine

    environment, as tunnelling would occur 15 metres below the seabed.

    However, if this did occur, only a small area of the seabed would likely be

    affected resulting in some disturbance or destruction to seabed habitat.

    Any disturbance would only be temporary and the seabed would likely fully

    recover (CEE 2008, Technical Appendix 31).

    Release of bentonite

    The tunnel-boring machine (TBM) that would create the tunnels for the Marine

    Structures could use bentonite as a drilling fluid to lubricate and cool the drill-

    cutting head. A malfunction of this machine may result in bentonite being

    released into the marine environment. However, only in rare circumstances

    would accidental release occur and any release of bentonite is expected to only

    have a moderate effect on marine biota. These water-based drilling fluids

    have low toxicity and any localised impact could be due to temporary

    seabed blanketing.

    Drilling noise affecting fish and marine mammals

    Underwater noise that would be generated from drilling for the intake and outlet

    risers has been assessed through noise modelling and this is considered to be a

    low risk to marine biota (Bassett, 2008 Technical Appendix 22). The rate of

    diminishing noise for drilling at the intake and outlet would be slightly less than

    for seismic activities (discussed above) and drilling noise is generally low level,

    low frequency and continuous with most energy concentrated below 1 kHz.

    Since this is a level in which most whales have reduced hearing sensitivity,

    only in rare circumstances would drilling affect cetaceans, and it is considered

    unlikely that drilling would affect and fish and other vertebrate species

    (Bassett 2008, Technical Appendix 22).

    Chapter 7 Construction impact assessment 7-13

  • 7/28/2019 Volume 2 Chapter 7 Construction Impact Assessment

    15/21

    Helicopter noise

    Helicopters may be used for transportation between the shore and the SEPs

    during the construction period. Noise impacts from helicopters may be a source

    of disturbance to birds, especially the beach-nesting species, the Hooded Plover.

    Helicopters could also affect other marine biota. It is likely that there would be

    some noise disturbance from this activity, but since helicopter movements are

    not likely to be frequent and would only occur during the construction period,

    the effect on Hooded Plovers and other biota is expected to be negligible

    (Biosis Research 20082, Technical Appendix 13).

    Lighting

    Artificial lights may also have deleterious effects on birds, especially on seabirds.

    Many seabirds fly or migrate at night. Artificial lighting can be disorienting and

    may trap large numbers of birds within a pool of light. Lighting impacts

    associated with construction activities are expected to only affect individual birds

    rather than an entire population. This impact would be contained in the local

    area, and would only occur during the period of construction (Biosis Research

    20082, Technical Appendix 13).

    Underwater noise affecting recreational activities

    Although it is possible that underwater noise generated by construction activities

    could affect recreational activities, any impact would be temporary with no

    lasting effect on recreational use of the area. Marine activities that generate

    noise and vibration that may affect recreational users (e.g. helicopters) would

    only occur during the construction phase during a short time period

    (approximately 24 months) and then would cease. Therefore, it is considered

    unlikely that noise and vibration from construction would affect the overall

    recreational use of this area (Maunsell 20085, Technical Appendix 56).

    Additionally, the PRs require minimising exposure of marine recreational users

    to underwater (continuous) noise levels greater than 145 dB re 1 PA.

    7-14 Chapter 7 Construction impact assessment

  • 7/28/2019 Volume 2 Chapter 7 Construction Impact Assessment

    16/21

    Exclusion zone affecting recreational activities

    It is also possible that the exclusion zone would preclude some recreational

    activities (such as diving). However, any impact on recreation would likely be

    minor because construction would only limit recreational activities in a small

    area for a short period of time.

    Tourism and visitation

    Penguin and seals are the main wildlife visitor attractions in Bass Coast Shire,

    although there is also some bird watching and occasional whale spotting.

    Although it is possible that adverse effects on the penguin population and other

    marine life from Project construction activities could affect long-term visitation

    and eco-tourism activities in the region, with adoption of the PRs, the Project is

    unlikely to have an impact on penguins, seals and other wildlife attractions

    (Biosis Research 20082, Technical Appendix 13). Therefore, it is unlikely that the

    eco-tourism industry would be adversely affected by the construction activities

    and eco-tourism operators are not likely to experience a downturn in business

    due to the Project. Any effects of the Project on eco-tourism would most likely

    be restricted to the Project area with no effect on operators on Philip Island who

    are responsible for the larger amount of employment and economic activity

    (Essential Economics 20082, Technical Appendix 11).

    Maritime heritage

    Construction activities are not expected to affect maritime heritage in the

    Project area. A systematic search of the Project area using the sidescan sonar

    and multibeam data did not detect any areas of heritage interest within the

    areas proposed for the Marine Structures. Therefore, any disturbance to the

    seabed in this area is unlikely to affect any maritime heritage assets (Biosis

    Research 20082, Technical Appendix 13).

    Marine vessel emissions

    Emissions generated from the movement of marine vessels during construction

    are unlikely to be sufficient to affect human health and interactions between the

    public and construction vessels would be restricted by the exclusion zone

    (Maunsell 20085, Technical Appendix 56).

    Chapter 7 Construction impact assessment 7-15

  • 7/28/2019 Volume 2 Chapter 7 Construction Impact Assessment

    17/21

    7.11 Performance Requirements during construction

    Performance Requirements (PRs) have been developed to provide an

    environmental framework for management of potential impacts during

    construction of Marine Structures. The PRs are focussed on the environmental

    outcomes that the State wishes to achieve through Project delivery. The PRs

    relevant to the management of construction impacts of the Marine Structures

    are set out below. The full suite of PRs for the Project is provided in Volume 1

    Chapter 11 as part of the overall Environmental Management Framework.

    As part of the environmental impact and risk assessment process relating to

    construction of Marine Structures, CEE (2008, Technical Appendix 31), Biosis

    Research (20082, Technical Appendix 13; 20087, Technical Appendix 45), GHD

    (20084, Technical Appendix 27) and Bassett (2008, Technical Appendix 22) have

    identified a range of suggested management measures that could be

    implemented to manage potential impacts. These suggested management

    measures have been formulated in response to the Reference Project andrelevant Variations for the Marine Structures. In effect, the suggested

    management measures demonstrate how the Reference Project and relevant

    Variations can achieve the PRs. These detailed management measures have

    formed an important input to the PRs for the Project.

    The management measures suggested by CEE (2008), Biosis Research (20082,

    20087), GHD (20084) and Bassett (2008) for the mitigation of impacts associated

    with the construction of the Marine Structures address the following matters:

    managing the introduction of aquatic pests and diseases potentiallyintroduced by the transfer of equipment and construction vessels to theconstruction site by ensuring:

    - all international vessels comply with Australian Quarantine andInspection Service (AQIS) requirements

    - all interstate vessels comply with State requirements- a pre-entry risk assessment procedure is considered, determining the

    likelihood of any vessel associated with construction of the

    Desalination Plant introducing marine biofouling pests of concern to

    the Project bioregion

    7-16 Chapter 7 Construction impact assessment

  • 7/28/2019 Volume 2 Chapter 7 Construction Impact Assessment

    18/21

    minimising the effects of the self elevating platform (SEP) and associatedequipment on the marine environment by:

    - positioning the SEP, jack-up legs, anchors and cables to avoid areasof high relief reef

    minimising or avoiding the interaction between fishing operators, fishinggear and the marine construction site by:

    - consulting with the fishing operators and advising them of the natureof construction activities and timing, possible exclusion zones and the

    risks to their fishing gear and catches

    - taking particular care when construction vessels are moving throughfishing grounds between the construction site and home ports

    - limiting vessel movements to daylight hours to and from theconstruction sites

    managing potential impacts of seismic survey on cetaceans by:- ensuring compliance with the measures prescribed in the EPBC Act

    Policy Statement 2.1 Interaction between offshore seismic

    exploration and whales

    - minimising the generation and propagation of impulsive and/orrepetitive noise, such as from offshore impact pile driving underwater

    - ceasing drilling activities, where practicable, if a baleen whale, largertoothed whales such as the killer whale or false killer whale, or

    leatherback turtle is spotted within 50 m of activities

    managing the physical and ecological integrity of the Williamsons Beach,the dune systems and the intertidal zone by:

    - minimising project personnels access to these areas during Projectactivities

    - banning dogs from the construction site and consult with ParksVictoria to determine further measures in the protection of

    Williamsons Beach and Kilcunda-Harmers Haven Coastal Reserve

    - educating project personnel about conservation and exclusion zones- monitoring the locations and breeding success of resident Hooded

    Plovers along Williamsons Beach at least monthly until the plant is in

    routine operation

    - developing measures that manage injured sea birds if impacted byconstruction activities.

    Chapter 7 Construction impact assessment 7-17

  • 7/28/2019 Volume 2 Chapter 7 Construction Impact Assessment

    19/21

    7-18 Chapter 7 Construction impact assessment

    The PRs proposed for the marine environment are outlined in Table 7-2.

    Table 7-2 Performance Requirements

    Timing

    Subject

    D&C O&M

    Objective Performance Criteria Performance Requirements

    Coastal

    processes

    Protect coastal

    processes.

    Minimise impacts on sand

    movements, wave patterns

    and currents.

    Comply with the Performance Criteria.

    Demonstrate through modelling of hydrodynamic

    processes such as tides, currents, winds and sand

    movements, that the Project will have no adverse

    effect on coastal processes.

    Monitor and report the effect of Project Activities

    on coastal processes.

    Detail the measures proposed to address the

    results of the monitoring undertaken to achieve

    compliance with the Performance Criteria.

    Coastal

    integrity

    Protect the

    physical

    integrity of the

    dune system,

    beach and

    intertidal zone.

    No surface disturbance of

    the dune system, beach and

    intertidal zone.

    No measurable loss to the

    integrity of the coastal

    assets including the dune

    system, beach and intertidal

    zone.

    Comply with the Performance Criteria.

    Develop and implement methods and

    management systems designed to ensure no

    adverse effect on the dune system, beach and

    intertidal zone from Project Activities including:

    Induction programs for Project personnel

    Minimise access outside public access pathways

    Monitor and report the effect of Project Activities

    on the dune system, beach and intertidal zone.

    Coastal flora

    and fauna

    Protect the

    ecological

    values of coastal

    habitat.

    No reduction in habitat

    values for significant

    species.

    Minimise loss of significant

    species individuals.

    No removal of coastal

    vegetation.

    Comply with the Performance Criteria.

    Develop and implement methods and

    management systems designed to ensure no

    adverse effect on the dune system, beach and

    intertidal zone from Project Activities including:

    Induction programs for Project personnel

    Implement management measures to minimise

    access of construction personnel to Williamsons

    Beach and foreshore reserve, particularly during

    Hooded Plover breeding season (August to

    February)

    Collaborate with Parks Victoria and DSE to

    achieve additional protective measures such as

    fencing off portions of the beach used by

    nesting Hooded Plovers to exclude people,

    uncontrolled dogs and increased fox and cat

    control

    Ensure that external lights are kept to a

  • 7/28/2019 Volume 2 Chapter 7 Construction Impact Assessment

    20/21

    Timing

    Subject Objective Performance Criteria Performance Requirements

    D&C O&M

    minimum, that they are positioned as low to the

    ground as is practicable and that they are

    shielded to avoid light spill upward and toward

    the foreshore, beach and sea

    Implement a program of monitoring the

    locations and breeding success of resident

    Hooded Plovers along Williamsons Beach to

    measure the impact of Project Activities and

    inform opportunities for mitigation. This should

    continue at least monthly from prior to

    construction until the plant is in routine

    operation.

    Implement a program of monitoring for the

    Orange-bellied Parrot from March to September

    prior to and during construction activities and

    inform opportunities for mitigation.

    Marine flora Protect marine Minimise to the extent Develop, implement and maintain methods and

    and fauna flora and fauna. practicable the impacts on management systems to protect marine flora and

    general No significant marine flora and fauna from fauna.

    impact on Project Activities. No construction in the designated areas, which

    Bunurong Limit impacts on ecology of creates a long-term impact, presented in Figure

    Marine National continuous high relief reef. PR Sensitivity Area Marine Area, in Technical

    Park and on the Appendix 5.

    protected values Trenching is not permitted in the designated areasof marine parks. presented in Figure PR Sensitivity Area Marine

    Area, in Technical Appendix 5.

    Manage any geotechnical investigation program to

    avoid significant impacts on the high relief reef in

    the designated area and marine fauna in general.

    Any spoil from marine construction to be disposed

    of in accordance with EPA Best Practice Guidelines

    for Dredging and the National Ocean Disposal

    Guidelines for Dredged Material.

    Marine Minimise Outside any marine Comply with the Performance Criteria.

    amenity disruption to exclusion zone (for diving Develop and implement methods andrecreational marine safety) no significant impact management and systems to minimise disruption

    recreational on diving, surfing, to recreational activities.activities. recreational fishing or

    marine boating activities.Turbidity or colouration impacts from the outlet

    should not be visible from the shoreline.Limit disruption to divers

    outside construction

    exclusion zones.

    Chapter 7 Construction impact assessment 7-19

  • 7/28/2019 Volume 2 Chapter 7 Construction Impact Assessment

    21/21

    Timing

    Subject Objective Performance Criteria Performance Requirements

    D&C O&M

    Commercial Minimise Minimise restrictions on Comply with the Performance Criterion.

    fishing and disruption to the commercial fishing and Develop and implement methods andmarine commercial marine tourism activities. management systems that seek to achievetourism fishing industry

    effective consultation and communication with theand marine commercial fishing and marine tourism industry intourism. relation to potential restrictions and disruptions

    during construction.

    Marine pests Avoid the Compliance with the Comply with the Performance Criterion.

    introduction, Commonwealth and State Develop and implement a marine pest riskspread and legislative requirements for management and monitoring process (including aestablishment of Ballast Water. process directed to addressing the risks ofmarine pests. introducing pests by vessels and equipment).

    Develop and implement a risk management

    process specifically for limiting risk of abalone

    disease.

    Underwater Protect Compliance with EPBC Act Comply with the Performance Criterion.noise and cetaceans. Policy Statement 2.1 Conduct geophysical survey of Project Activities invibration Interaction between accordance with the procedures outlined underecological offshore seismic exploration the EPBC Act Policy Statement 2.1 - Interaction

    and whales. between offshore seismic exploration and whales.

    Underwater Protect marine No significant impact Comply with the Performance Criterion.

    noise and diving activities outside any marine Outside any exclusion zone, minimise exposure ofvibration from exclusion zone on marine marine recreational users to underwatermarine diving underwater diving activities. (continuous) noise levels greater than 145 dB reactivities noise and 1PA.

    vibration.Develop, implement and maintain methods and

    management systems that ensure effective

    consultation and communication with marinedivers in relation to marine noise and vibration.

    Marine Protect coastal Minimise impact on safe Comply with the Performance Criterion.

    navigation access on passage of non-Project Identify and implement any requirements formarine waters vessels along the coast. notifications for vessel movements by Marinefor vessels. Safety Victoria.