volume: 1 part-2 works requirements to bidding document · insulation co-ordination iec 60071-1, -2...

88
2-1 Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT THE REPUBLIC OF THE UNION OF MYANMAR NATIONAL ELECTRIFICATION PROJECT National Competitive Bidding Installation for Distribution Lines and Transformers for Sagaing (1) NCB No. MOEE-NEP/C1-W1/18

Upload: ledung

Post on 03-Nov-2018

342 views

Category:

Documents


9 download

TRANSCRIPT

Page 1: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-1

V o l u m e : 1

P a r t - 2 Works Requirements

T o B I D D I N G D O C U M E N T

THE REPUBLIC OF THE UNION OF MYANMAR

NATIONAL ELECTRIFICATION PROJECT

National Competitive Bidding

Installation for Distribution Lines and Transformers for Sagaing (1)

NCB No. MOEE-NEP/C1-W1/18

Page 2: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-2

PART 2 – Works Requirements

Page 3: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-3

Section VII - Works Requirements

Contents(inpart1)7. CHARACTERISTICS OF INSTALLATION WORKS………………………………………………………..…………….……………5 7.1 LOCATION AND INSTALLATION WORKS PURPOSES………………………………………………...…………...…………………5 7.1 SIZE OF INSTALLATION

WORKS………………………….....…………………………….……………………5 7.3.1The Detailed Installation Schedule …………………………….…….5 7.3.2The Scope and Nature of Work……………………………………………….6

Table 2. SYSTEM PARAMETERS AND DESIGN DATA ...........................................................7 Table 3. CLIMATIC CONDITIONS ..............................................................................................7 Table 4. MINIMUM CLEARENCES ACCORDING TO ELECTRICAL REGULATION ..........3

7.3. INSTRUCTIONS FOR INSTALLATION WORKS WORKS ............................. 3

7.3.1 Applicable Law ........................................................................................................3 7.3.2 Mobilization of Equipment and Manpower ...........................................................3 7.4 ITEMS USED IN OVERHEAD MV INSTALLATION WORKS ..........................4

7.4.1 Concrete Poles .................................................................................................. 4 7.4.2 Stay Wire ........................................................................................................... 4 7.4.3 Stay Rod and Bow ........................................................................................... 5 7.4.4 Stay Insulator ................................................................................................... 5 7.4.5 Earthing Accessories ........................................................................................ 5 7.4.6 Bare Conductor ................................................................................................ 5 7.4.7 Preformed Binding for Pin Insulator................................................................ 7 7.4.8 Danger Board ................................................................................................... 7

7.5. Technical and Safety Instructions for installation of 33 kV,11 kV Line and 33/0.4kV, 11/0.4kV Transformers .................................................................................... 8

7.5.1 11kV and 33kV line Installation Works ....................................................................8 7.5.1.1 Details of Line Route and Terrain ............................................................ 8 7.5.1.2 Selection of the Line Route and Check Survey of Optimization Pole Location ....................................................................................................................... 8 7.5.1.3 Line Route Maps ......................................................................................... 8 7.5.1.4 Topographical Maps ................................................................................... 9 7.5.1.5 Route Marking ............................................................................................ 9 7.5.1.6 Pole Locations ............................................................................................. 9 7.5.1.7 Clearance from Ground, Building, Trees etc. ........................................... 10 7.5.1.8 Site Clearing.............................................................................................. 10 7.5.1.9 11kV and 33kV Final Line Route Maps ................................................... 11 7.5.1.10 Excavation & Erection of Poles ........................................................... 12 7.5.1.11 Pole Foundation ................................................................................... 12 7.5.1.12 Back Filling and compaction ................................................................ 13

Page 4: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-4

7.5.1.13 Instructions for fixing Cross Arms ....................................................... 13 7.5.1.14 Erection of Stay Sets ............................................................................ 13 7.5.1.15 Pole Design ........................................................................................... 14 (i) 2 Pole Structure ..................................................................................................... 14 7.5.1.16 Installation of Stays............................................................................... 14 7.5.1.17 Line Earthing ....................................................................................... 15

7.5.2 Handling and Stringing of Conductor and Ground Wire: .....................................15 7.5.3 Sagging in Operation ...............................................................................................17

7.5.3.1 Tensioning and Sagging of Conductor and Earth Wire: ................................ 17 7.5.4. Instructions for Installation of Transformers .......................................................................17

7.5.4.1 H pole structure for transformer installation. ................................................. 18 7.5.4.2 Earthing Installation .................................................................................. 18 7.5.4.3 400 V Cable and Panel Installation ........................................................... 18

7.5.4.4 Connection of Power Lines into Transformer and Pulling Lines Crossing Existing Lines ................................................................................................................................19 7.6. Final Checking, Testing and Commissioning .........................................................................19 7.7 Hauling and storing material, device, apparatus and equipment at Contractor’s warehouse 20 7.8. STEEL WORKS .....................................................................................................................21

7.8.1 General requirements ........................................................................................ 21 7.8.2 Transport and installation of reinforced steel ................................................... 21

7.9. Contents of Work Item ............................................................................................................22 7.10 Work Safety .............................................................................................................22

The Contractor shall ensure that emissions, surface discharges and effluent from the Contractor’s activities shall not exceed the values stated in the Specification or prescribed by applicable Laws. .................................................................................. 24 7.10.5 Fossil ............................................................................................................... 24 The Contractor shall send, to the Employer, details of any accident as soon as practicable after its occurrence. The Contractor shall maintain records and make reports concerning health, safety and welfare of persons, and damage to property, as the Engineer may reasonably require. ........................................................................ 25

7.11. Supplementary Informations ...................................................................................26 7.13 Checking-Taking Over, Trial Testing, Handing-Over ...........................................................27 7.14 Installation Works Schedule ..................................................................................................27 7.15 As-Built Drawings .................................................................................................................27 7.16 Others for the Attention .......................................................................................................27

7.16.1 Sag-tension Calculations ........................................................................... 28 7.17 Accounting of Material issued to Contractor ……………………………………34 7.18 Payment …………………………………………………………………………36 7.19 Design and Drawings ……………………………………………………………..37

Page 5: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-5

7. CHARACTERISTICS OF INSTALLATION WORKS

7.1 LOCATION AND INSTALLATION WORKS PURPOSES

The Government is committed to achieve universal electricity access by 2030.

The National Electrification Project 2015-2021 includes $400 million of World Bank funds for investment, technical assistance and capacity building to help implement the Project.

The Project is to connect the households which are not electrified with grid and permanent off-grid electricity solutions.

7.2 SPECIFICATIONS FOR INSTALLATION WORKS

7.2.1 The Detailed Installation Schedule

This schedule covers the detailed survey, site clearing, transportation of material, spotting of location of poles, excavation of pole pits, foundation works and erection of 10m and 12m concrete poles and tubular steel poles in single pole/double pole/tri poles/square pole arrangement with complete 11kV and 33kV line materials such as disc insulators, pin insulators with pins, suspension and tension fittings, pole top bracket, straight cross-arms, earthing material, stay sets with bolts & nuts and washers, pole bracings and all other required lines accessories etc., ACSR conductors, fixing of insulators , stringing of conductor and earth wire, fixing of stays, installation of 33/0.4kV and 11/0.4kV distribution transformers and associated equipment and testing and commissioning of the erected 11kV and 33kV lines and distribution transformers and handing over to Employee after issuing the acceptance certificate.

All works shall be completed in accordance with the present designated Specification by the Employer and the Employer’s distribution standard. The quantities of supplies and works are given in the relevant schedules.

The detailed installation schedule includes:

i) Conducting of Check Survey

ii) Site Clearing/Preparation

iii) Mobilization and Transportation of material to site

iv) Excavation of Earth and Pole Erection

v) Foundation Work

vi) Fitting and Dressing of Cross Arms/ Insulators/Auxiliaries

vii) Laying and Stringing of Conductor

viii) Transformer with related accessories installation including Fencing

ix) Testing /acceptance /putting into operation

Page 6: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-6

7.2.2 The Scope and Nature of Work

The NEP project sites include 11kV power lines, 33kV power lines, 11/0.4 kV transformers and 33/0.4 kV transformers Installation Works. The Employer is responsible for providing required transformer and line materials as well as for transportation of Transformers, Concrete Poles, Steel Poles and ACSR conductor to the delievery point and Insulators, Steel Parts and Accessories and other related accessories to the delievery point of ESE, YESC and MESC. The detailed delivery points are complete furnished in Delivery Point for Materials, Annex III, and Volume 2.

The required transformer and line materials (except capacitor banks) shall be provided by the Employer at each designated delivery point. It is the duty of the Contractor to ensure that goods received from the Employer are in good order and also the Contractor will provide any other accessories other than Volume 2, Annex II-A and II-B, necessary to make the installation complete and functional or indicate that the Employer will provide any material that is required and not included in the list of materials provided by the Employer.

The delievery Points for Materials to be provided by Employer, are at ANNEX III,Volume 2 Price Schedules and Annex, The contractor shall be responsible for installation of distribution lines and transformers in accordance with the guidelines and drawing provided by Employer and also the transportation of materials from respective stores to the project sites, foundation for poles and fencing for transformers as per drawings. Table 1 .THE COMPLETION TIME FOR EACH LOT IN PACKAGE 1 IN NATIONAL ELECTRICATION PROJECT

Sr. No

Number of Villages

to be Electrified

Line Length to

be Installed

(Mile)

Transformerto be

Installed (Nos)

Works completion

(Month)

Lot-1 18 15.1896 18 9

Lot-2 24 31.8883 23 9

Lot-3 52 51.9858 52 9

Lot-4 49 47.9827 49 9

Lot-5 56 37.0203 60 9

Lot-6 46 30.9848 44 9

Lot-7 128 97.3670 131 12

Lot-8 51 37.3388 52 9

Page 7: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-7

Lot-9 58 44.0467 57 9

Total 482 393.8040 486

Table 2. SYSTEM PARAMETERS AND DESIGN DATA

Parameter 33kV System 11kV System LV System

Nominal voltage Un 33kV 11kV 400/230 V

Maximum Voltage Variation ±10% ±10% ±10%

Highest Voltage of the Equipment Umax as per IEC at Sea level and for equipment with internal insulation, e.g. in oil.

36kV 12kV 440/253 V

Highest Voltage of the Equipment 36kV 12kV 0.6/1 kV

Rated frequency 50 Hz 50 Hz 50 Hz

System configuration 3 phase, 3 wire 3 phase, 3 wire 3 phase, 4 wire

1 phase, 2 wire

Earthing Insulated /Isolated neutral

Neutral Solidly earthed at transformers

Neutral Solidly earthed, PME(protective multiple earthing) system

Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2

Standard power frequency short duration voltage 1 min at 1000M for equipment exposed to air.

70kV 28 kV 3 kV

Standard Lightning Impulse Withstand voltage (peak) at 1000M for equipment exposed to air.

170kV 75 kV 6 kV

Rated Short Circuit Current 25kA/1 sec 20kA/1 sec 12.5 kA/1 sec

Table 3. CLIMATIC CONDITIONS

Altitude Maximum for all equipment 3000 m

Page 8: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-8

Annual Rainfall

Delta Region

Dry Zone

Coastal Region

2500 mm

1000 mm

5000 mm

Period of Exceptional Raining June to September

Ambient Temperature

Average +280C

Minimum +100C

Maximum +450C

Relative Humidity 97%

Wind Velocity 30 m/h with return of 50years

Isokeraunic Level Up to 65 thunderstorms days/year

Max. Lightening 100 kA

Seismic Level Design shall be consider earthquakes of magnitude 9 M

Pollution Level Light, Dust

Page 9: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-3

Table 4. MINIMUM CLEARENCES ACCORDING TO ELECTRICAL REGULATION

(a) The Electrical Regulations for Minimum Clearence between Overhead Line and the Building under Article 78,79 and 80 Mandated in 1985

Sr. Description Voltage (kV)

0.4 6.6/3.3 11 33 66 132 230 ft m ft m ft m ft m ft m ft m ft m

1 Horizontally 4 1.22 6 1.83 8 2.44 10 3.05 15 4.57 50 15.24 50 15.24 2 Vertically 8 2.44 8 2.44 8 2.44 12 3.66 13 3.96 14 4.27 16 4.88

(b) The Electrical Regulations for Minimum Clearence - Distance Between Line to Line under Article 80 Mandated in 1985

Sr. Description Voltage(kV)

230 132 66 33 11 6.6/3.3 0.4 ft m ft m ft m ft m ft m ft m ft m

1 Telephone line 12 3.66 10 3.05 8 2.44 8 2.44 6 1.83 4 1.22 4 1.22 2 0.4 kV 8 2.44 8 2.44 8 2.44 6 1.83 4 1.22 4 1.22 3 6.6/3.3 kV 8 2.44 8 2.44 8 2.44 6 1.83 4 1.22 4 11 kV 8 2.44 8 2.44 6 1.83 4 1.22 5 33 kV 8 2.44 8 2.44 6 1.83 6 66 kV 8 2.44 6 1.83 7 132 kV 6 1.83

Page 10: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-4

(c)The Electrical Regulations for Minimum Clearence between Overhead Line and the Building under Article 76 and 80 Mandated in 1985

Sr. Description

Voltage(kV)

0.4 6.6/3.3 11 33 66 132 230

ft m ft m ft m ft m ft m ft m ft m

1

Height of overhead line (Traffic not accessible)

15 4.57 17 5.18 17 5.18 18 5.49 19 1.67 21 6.40 22 6.71

2

Height of overhead line in Parallel with any access road

18 5.49 19 5.79 19 5.79 20 6.10 20 1.86 20 6.10 24 7.32

3 Height of overhead line cross-over any access road

19 5.79 20 6.10 20 6.10 20 6.10 22 1.86 23 7.01 23 7.01

4 Height of overhead line cross-over railway

24 7.32 24 7.32 24 7.32 24 7.32 24 2.23 24 7.32 25 7.62

(a)At the cross-over railway, the maximun span of section is 120 ft (36.58 m).

(b)At the cross-over railway, the angle of deviation shall be right angle (90 degree) .

( c)Crossing-over of medium voltage overhead line must be only flat ground. (must not cross-over in the railway yard)

(d)Pole must be erected one and half of their length from the Railway.

Page 11: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-3

7.3. INSTRUCTIONS FOR INSTALLATION WORKS WORKS

7.3.1 Applicable Law The Contractor need to commit doing the works in accordance all legal provisions and regulations that are related to works listed in the contract. The following laws and regulations are obliged to adopt:

- Labor Laws of the Republic of the Union of Myanmar.

- Construction Laws of the Republic of the Union of Myanmar.

- Electricity Laws of the Republic of the Union of Myanmar.

- All related standards and practice codes issued by the Ministry of Construction, Ministry of Industry, Ministry of Home Affairs, Ministry of Communication and Transporting, Ministry of Agriculture, Livestock’s and Irrigation and Ministry of Resources and Environmental Conservation.

- The Contractors is responsible to study all documents supplied by the Employer to be ensure those are sufficient to complete all works in the project.

7.3.2 Mobilization of Equipment and Manpower

a) The Contractor is responsible to provide the Installation Works equipment, tools as well as on-the-job protection clothing and safety measures for Installation Works.

b) The Contractor shall submit within three weeks of contract signing , adequate and detailed Installation Works program, plan including the manpower, mobilization schedule, on-site organization chart, number and categories of equipment to be used for the project Installation Works, to the representative of the Employer (attention should be paid to the ability and experiences of the key personnel, skill of workmen, the specialized equipment to be used for Installation Works and installation such as stringing equipment, etc.).

c) The Contractor shall be responsible to negotiate with the related agencies

for permission of using the existing transportation way. The toll for using such existing roads, bridges and ferry-boat, etc. shall be included in quoted bid price.

d) The Employer can make decision to reject or replace any equipment or

workmen unit, which deem to be unsatisfactorily to the Installation Works.

Page 12: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-4

e) Working by safety methods and those to be ensuring health condition of

workers shall be followed according to the Employer’s instructions. f) The Contractor shall compensate for any damages caused during

Installation Works period to the affected objects.

7.4 ITEMS USED IN OVERHEAD MV INSTALLATION WORKS

7.4.1 Concrete Poles

10 m and 12 m Poles shall be used for all new MV overhead line Installation Works and their working parameters are given in the following chart.

Pole positions are classified as, Terminal, Shackle and Intermediate, and are defending below;

Terminal Pole -Here the line is terminated with MV Tension Insulators

on one side of the pole. This is also called dead end poles. Tension Pole - Here the line is terminated with MV Tension Insulators on

both sides of the same pole. Intermediate Pole - Here the line is continuous and is supported on MV Pin

Insulators or Post Insulators as necessary. Note: Self supported poles may be used in urban and densely populated areas where Strays and Struts cannot be erected.

The chart given below is a simple guidance for a Installation Works Engineer and is called as working parameters for a MV Line.

WORKING PARAMETERS OF CONCRETE POLES

7.4.2 Stay Wire

7/10 Galvanized Steel Wire shall be used for 33kV Line Installation Works,7/12 Galvanized Steel Wire shallbe used for 11kV Line .

Pole Height(m)/ Type

Working Load (kN)

Drawing No. Purpose Buried Length

10m 2.5

WB/MYR-NEP/11kV/02/17

For MV Lines 1.67m

12m 3.5

WB/MYR-NEP/33kV/03/17

For MV Lines 2m

Page 13: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-5

7.4.3 Stay Rod and Bow

They are made of iron and after cutting and drilling are hot dipped galvanized to prevent corrosion. Dimensions of the stay and strut brackets are as shown in the Drawing No. ESE-LV-DL-408

7.4.4 Stay Insulator

The stay insulator is made of good commercial grade wet process porcelain. The entire glazed surface is relatively free from imperfection.There are two types of stay insulator.The 120mm length stay insulator shall be used for 11kV Line and the 220mm length stay insulator shall be used for 33kV line.Dimension and specification of stay insulator are as shown in Drawing No. ESE-LV-DL-405 and 406.

7.4.5 Earthing Accessories

7/16 GI Wire shall be used for 33kV Over Head Earth Wire.Copper Coated Earth Rod and 7/16 GI Wire is used for earthing of 33kV Over Head Earth Wire Installation. HDBC N0 4 and Copper Coated Earth Rod is used for 11/0.4kV transformer and 33/0.4kV transformer installation. Dimension of Copper Coated Earth Rod are given in the Drawing ESE-LV -DL-407.

7.4.6 Bare Conductor

Three types of bare conductors are used by the MOEE, for the Installation Works Medium Voltage Overhead Lines. They are;

i) 95/15 mm2 ACSR for 11kV Distribution Line ii) 150/25 mm2 ACSR for 33kV Distribution Line.

7.4.6.1 Steel Parts and Accessories

Cross Arms, bracing, tension bar, full clamp, half clamp and mounting structure are fabricated using channel iron section (50x100x50x5t)mm, (65x125x65x6t)mm and Angle iron section (65x65x6t)mm. The dimensions of the cross arms are given in: steel parts drawing. All components of these Cross Arms are hot dipped galvanized after cutting welding and drilling.

Page 14: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-6

7.4.6.2 Bolts and Nuts

The assorted sizes of hot dipped galvanized bolts and nuts are used for 11kV line, 33kV line, 11/0.4kV transformer and 33/0.4kV transformer.

7.4.6.3 Insulators

Two types of Insulators are used in the Installation Works of MV lines. They are : Pin and Tension type insulators. The Insulators are made of good commercial grade wet process porcelain .

7.4.6.4 Pin Insulators Pin Insulators are made of glazed porcelain. Dimensions of 11kV and 33kV Pin Insulators are given in Drawing ESE-LV-DL-107,108,115 and 116.These Pin insulators incorporate a hot dipped galvanized steel spindle, nut ,spring washers’ two flat washers as indicated in the above drawing. Threaded portion of the spindle is long enough to fix it on a channel iron cross arm.

7.4.6.5 Tension Insulators Tension Insulators are disc type, and are made out of either porcelain . The hardware part of the disc insulator is cap and pin type assembly with a 16mm & 22mm ball & socket coupling, incorporating a locking device as indicated in the following Drawing Two types of tension insulator sets available as indicated in (a) and (b) over leaf. In both types tension clamp is made out of an aluminium or aluminium alloy.

a) The 11kV tension insulator set is complete with Ball and Socket Eye Anchor Shackle, Cotter Pins, Bolted type conductor tension clamps etc. These are given in Drawing ESE-LV-DL-101,102,103,104,105,106

b) The 33kV tension insulator set is complete with Ball and Socket

Eye Anchor Shackle, Cotter Pin, Crimp Type Conductor Tension Clamp etc. These are given in Drawing ESE-LV-DL-109,110,111,112,113,114

7.4.6.6 Connector used in Bare Conductor, ACSR Lines

The Aluminium/Aluminium Alloy Connectors and terminations are made out of high strength, high conductivity Aluminium/Aluminium Alloy.

Page 15: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-7

The inside of each Aluminium/Aluminium Alloy tube and the internal faces of other connectors are coated with oxide inhibiting grease to improve the electrical contacts. The compression connectors and terminations have markings are also available indicating the size of conductors and sizes for easy identification. Markings are also available on the surface of the connector to show the location and sequence of the crimping.

7.4.6.7 Non Tension Joints (Jumper Connectors)

Non-Tension Jumper Connectors (PG Clamp Type) - Non-Tension Jumper Connectors (PG Clamp type) are for the jointing two ends of the jumper conductors in a main line. A PG Clampconnector is shown in the Drawing No. ESE-LV-DL-402.

7.4.6.8 Full Tension Compression Connectors (Torsion Sleeve joints)

Torsion sleeve joints are suitable for jointing two conductors of same size. It is provided with a central stop meant for correct positioning of connectors. Torsion sleeve used for ACSR Conductor is a 2 part fitting, with one for Aluminium and the other for steel wire.Torsion sleeve joint is shown in Drawing No ESE-LV-DL-403 and 404.

7.4.7 Preformed Binding for Pin Insulator There are two types of pre-formed bindings to bind the conductor to the insulator at an straight point and at a small angle point where angles of deviations are less than 30o. It also varies with the size of conductor

7.4.8 Danger Board

The contractor need to set up the danger sign board at the fencing of transformer.

Page 16: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-8

7.5. Technical and Safety Instructions for installation of 33 kV,11 kV Line and 33/0.4kV, 11/0.4kV Transformers

7.5.1 11kV and 33kV line Installation Works

7.5.1.1 Details of Line Route and Terrain

The medium voltage Power Lines, LT lines etc. will be running almost through plain and cultivated areas. Line route maps of Power lines covered under this package giving the general topography are provided in this document.

7.5.1.2 Selection of the Line Route and Check Survey of Optimization Pole Location Following factors should be considered when selecting the line routes:

a) One side of the road is used as far as possible b) Length of way to be cleared shall be minimized c) Inconvenience caused to the other services shall be minimized d) Swampy ground and areas liable to flood shall be avoided e) Routes which would involve excavation in rock shall be avoided f) The use of taller poles at up lifts shall be avoided and Installation Works of

tension points at up lifts also be avoided. g) The pole should not be in the boundary of the road where was assigned by

the department of the road under the Ministry of Construction. h) Archeological area and zone shall be avoided.

The Check survey for the line route and optimization of the pole location along with profiling shall be carried out by the awarded contractor. The provisional quantity has been indicated in the Bill of Material/Quantity for each package.

In the case the contractor shall have any moderation based on our line survey route map; we will determine the bill of quantity and bill of price as per actual installation works. The installation works of contractor shall not exceed the contract total value.

7.5.1.3 Line Route Maps The Check survey shall be carried out by the contractor with reference to the Line Route Map provided by the Employer. The contractor will examine the site

Page 17: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-9

of works and its surroundings and obtain himself, at his own responsibility and expenses, all information regarding general site characteristics, crossings accessibility, infrastructure details etc. The employer will, however, assist the interested contractor to see and inspect the site of work. For this purpose the contractors are requested to contact;Project Manager of NEP, MOEE. Single pole, 2 Pole, 3 pole & 4 Pole Structure as per site requirements shall be provided where the situation so demands. Drawings of single pole,2 pole,3 pole and 4 pole Structure is provided for guidance. Additional H Poles required for Pole Mounting Sub-Station under the existing 11 KV feeders are to be taken care of by the Contractor as per the requirement of Operation Organization.

7.5.1.4 Topographical Maps The contractor should note that the Employer will not furnish the topographical map prepared by Archaeological Survey of Myanmar but will make available any assistance that may be required for obtaining topographical map.

7.5.1.5 Route Marking

At the starting point of the commencement of route survey the peg marking shall be done with spikes, driven firmly into the ground. A Benchmark on top section of the angle iron shall be made to indicate the location of the survey instrument. Wood peg shall be driven at prominent Position at intervals of not more than 750 meters along the Power line to be surveyed up to the next angle point.

7.5.1.6 Pole Locations

The position of the pole hole is usually indicated by a peg. The pole hole must be excavated so that the pole is erected in its correct position. If the peg indicates the Centre of the hole it is advisable to place a temporary peg at a definite distance away so that it is not disturbed during digging operations. The pit can be excavated either manually, or by truck mounted augers. The depth of the pit is usually made equal to one-sixth of length of the pole.

With the help of pole spotting data, pole locations shall be marked on the profiles prepared to check the required ground clearances. While locating the poles on the profile sheets the following shall be borne in the mind.

a) Extension:

An individual span shall be as near to the normal design span as possible. In case an individual span becomes too short or long with normal supports on account of ground profile, one or both supports of the spans may be extended with standard design or provision of a special structure for the purpose according to technical

Page 18: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-10

specifications. The design of such extension shall be prepared & supplied by the Contractor and shall be got approved from the Employer.

b) Road Crossings:

At all the important road crossings, poles shall be fitted with normal tension insulators strings depending upon the location but the ground clearance at the roads at the maximum temperature and in the still air shall be such that even with the conductor broken at adjacent spans, the ground clearance of the conductor from the road surface will not be less than 6.1 meter. For road and line crossings, 12m/3.5kN pre-stressed spun pole/or double pole structure using 12m/3.5kN shall be provided to achieve required clearances. H-pole structure on 12m/3.5kN poles for road crossings and single 12m/350kg poles for line crossing shall be provided.

c) Railway Crossings:

The Contractor will make the survey to assess the requirement of Railway Crossing and take the same into account in his Bid. The work of Railway Crossings will be got executed by him as a deposit work with the Railways or otherwise as per rules of Railway Department. The Employer will arrange to get the approval from Railway Authorities expedited. The case for approval will be submitted by the Contractor on the behalf of the Employer well in time.

d) Power Line Crossings:

Wherever the line is to cross over / below the other line of the same voltage or higher or low voltage the requisite clearances will be ensured in accordance with the Myanmar Electricity Rules. The Contractor shall submit and get approved from the Employer any special design wherever required in order to achieve such clearances.

e) River Crossing:

The route of medium voltage new lines, if routed through a river must have concrete foundation for erection of poles and 12m/3.5kN double pole structure supported by a good number of stay-supports capable to withstand water / wind pressure and must be executed to the entire satisfaction of the Employer.

7.5.1.7 Clearance from Ground, Building, Trees etc. Clearance from Ground, Building, Trees and Telephone lines shall be provided in conformity with the information given under “Minimum Clearance” in the clause above.

7.5.1.8 Site Clearing

Page 19: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-11

a) The contactor is responsible for the site clearing to be ready for Installation Works. Land acquisition for Right of Way (ROW) shall be performed in conformity by the Government on amendment stipulating in details and guiding how to execute some provision of Power law on safety projection to high voltage power grid on safety protection to high voltage works.

b) Except the compensation to permanent occupied and acquired land area and ROW in accordance with the mentioned above .The Contractor shall be fully responsible for compensation against all damages caused by Installation Works of project components.

c) For tree having historical, cultural value or having special value exists inside and/or outside of the ROW shall be trim off to ensure safety distance, before being trim off, the Contractor shall come to an agreement with the related department directly managing the tree. In case if such agreement is failed, the Contractor shall send his official letter to Union PMO to continue for settlement.

d) Such Installation Works methods as using explosive, burning forest shall not be acceptable.

e) Besides the requirements set forth in bidding data sheet, the Contractor shall be responsible to major contents, as follows:

- Removing overburden according to design requirements and dump to disposed area approved by the local authority.

- The Contractor shall be responsible to clean up the Works site and remove partial equipment, facility during Installation Works and when completion of works, including un-necessary site camps, surplus materials, debris arisen during Installation Works.

- Site clearance shall be in accordance with requirements in sections: Preparation works, safety, hygiene and environment management in Installation Works site. During leveling, a temporary drainage system for Works site shall be created in order to avoid stagnant.

7.5.1.9 11kV and 33kV Final Line Route Maps

Final medium voltage Line Route Maps duly spotted along with Check survey indicating position of poles(stated in GPS points using QGIS), wind span, weight span, angle of deviation, river or road crossings and other details shall be submitted for the approval of the Employer within 21 days from the contract signing date for ALL LOTs. After approval the, Contractor shall submit six more sets of approved reports along with one set of reproducible final profile drawings to the Employer for record purpose.

Page 20: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-12

7.5.1.10 Excavation & Erection of Poles

a) The Pits for the Poles are to be excavated with the correct orentaiton and bisect (Strain Pole) or straight (Suspention) in the direction of the line, as this will facilitate the erection of pole and given internal stability. The depth of the foundations to be excavated for the poles shall be approximately 1/6th of the Pole’s length. No over excavation allowed. The alignment of the Poles are to be set right and the earth-filling will be done after checking the alignment vertically and backfilled earth will be rammed afterwards properly.

b) The contractor is responsible to remain excellent quality and those have no any crack during transportation to the site.

c) The pole should not be in contact with the ground and should be properly supported to prevent deformation and/or being soiled.

Foundation whole excavation and installation of pole foundation for the required pole locations

d) The ground level must be 1675 mm for 10 m pole and 2000 mm for 12 m, footing size of concrete pole must be truly concreted (610x610x915 mm) and (762x762x915mm).Foundation design and drawing and soil investigation reports for various soil conditions shall be completed by the contractor and submit for the project manager’s approval before 28 days of commencement of installation works.

e) The footing molded concrete mixture ratio shall be 1:3:6.

f) Pole erection and alignment, no pole shall be more than 100mm out of line.

7.5.1.11 Pole Foundation The foundation of poles shall be of the following types:-

a) The Type of foundation for individual poles shall be decided during detailed engineering. The contractor shall quote their rates as per the quantity of volume 2 part 1 (price schedule) foundations indicated in the Bidding Document.

b) No over excavation is allowed for pole foundation. In case of over excavation contractor needs fill the over excavated are with concrete or crushed stones to ensure the settlement of the pole foundation.

c) The curing of concrete during the dry season is required for seven (7) days

from the completion of the concrete pouring.

Page 21: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-13

d) Type and dimension of the each pole foundation shall be strictly follow the

approved drawing.

e) It is envisaged that medium voltage line may be traversing marshy & low laying area for which type of foundation shall be required. In such a case, difference in excavation quantity, concreting & reinforcement between special foundation and normal foundation shall be part of the package.

f) Erection of Poles: The poles are to be erected in alignment with utmost care. The poles shall then be lifted to the pit or by the crane. The pole shall then be kept in the vertical position with the help of 25 mm (min.) manila ropes which shall act as the temporary anchor or by the crane. The verticality of the pole shall be checked by spirit level in both longitudinal & transverse directions. Once, this is done, the back filling / concreting shall be done in the pit. The temporary anchor shall be removed only when poles set properly in the foundation.

7.5.1.12 Back Filling and compaction

a) For all the failure containment structures, described earlier & repeated below, the pits shall be back filled with excavated / borrowed earth and broken bricks properly rammed to the satisfaction of site-in-charge.

At some the tapping points & dead end poles i) At all the points where DT is to be installed. ii) At all the points as drawing (for the diversion angle of 10-

60 degree). iii) At DP structures - Tapping points & roads where the

failure containment structures are to be erected shall be decided during detailed engineering.

b) The cost of backfilling including all material /borrowed earth etc. is deemed to be included in the quoted price.

7.5.1.13 Instructions for fixing Cross Arms

a) The cross arms shall be pushed to the tip of top of the pole and fittings shall be installed according to the Installation Works drawings provided in the bidding document.

7.5.1.14 Erection of Stay Sets

a) The Contractor shall install the stay set complete in all respect. This includes

excavation of pit size (610x610x915)mm in all kinds of soil including

Page 22: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-14

laterite/hard rocks. Stay plate and rod (leaving the top 10 cm) shall be embedded in the pit with Pre-Casted Concrete in the ratio 1:3:6 (the volume of Pre-Casted Concrete shall be (610x610x915)mm. The rest (upper half) of the pit shall be filled with excavated soil duly compacted layer by layer. An angle between 30 to 45 degrees shall be maintained between stay wire and the pole. The stay wire shall be used with a stay insulator at a height of 5 m above ground level with Galvanised Iron turn buckle.

7.5.1.15 Pole Design

(i) 2 Pole Structure H Poles are to be erected on almost 10th location when the line is going straight and it is also to be provided wherever there is an angle of deviation in the line. When the angle of deviation is less, 2 pole structures shall be provided. In case of angled H-Pole, the pits are to be excavated along the bi-section of the angle of deviation. It will be ensured that the poles are held in vertical position and earth is filled in the pits and proper ramming is done so that pole remains in proper position. On every H-Pole, 4 stays are to be provided along the line i.e. 2 on each direction and in addition two more stays along the bi-section of the angle of deviation are to be provided as required depending upon the site conditions as per the drawings attached with the specifications.

(ii) 3 Pole Structure

When the angle of deviation is between 30° and 90°, 3 pole structures shall be provided. Other instructions are in line with 2 pole .

(iii) 4 Pole Structure

When the angle of deviation is equal 90°, 4 pole structures shall be provided. Other instructions are in line with 2 pole. In case of deviation above parameters according to the site condition, the contractor need to submit to the employer for the variation approval.

7.5.1.16 Installation of Stays

Page 23: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-15

The stays will be provided at all dead end locations, angle locations and T-Off points and also on normal locations as wind stays to counter the pressure of the winds. Normally every fourth pole of the line shall be provided with two wind stays one on either side of the pole. The angle of the stays will be generally kept on 30 to 45 degrees depending upon the tension and the location of the line.

7.5.1.17 Line Earthing Earthing shall be provided on every tension pole as per the design attached hereto in addition to the continuous Earth Wire. H-pole structures will be provided with 2 No. earthings.

7.5.2 Handling and Stringing of Conductor and Ground Wire:

a) The contractor shall give complete details of the stringing method, which he proposes to follow. Before the commencement of stringing, the Contractor shall submit the stringing charts for the Conductor and Earth wire for various temperatures and spans along with equivalent spans to the Engineer for the approval of the Employer.(Sag Tension Calculations)

b) Stringing conductors, ground wires shall be performed after 28 days from the completion of concrete foundation, checked and accepted by the Employer.

c) Stringing conductors, ground wires and associated works must be done in the day time. The conductors, ground wires shall be strained at not too fast and not too slow speed.

d) The Contractor must pay attention all the time to be ensure that the conductors, ground wires not be folded or scratched. The conductor, ground wires shall not be dragged on the ground surface, in water, on rock, barbed wires or any object that causes damages to the lines. The scaffolds or pulleys or wooden roller, aluminums roller shall be used where impossible to keep the conductors, ground wires away from contact with objects causing damages to the conductors, ground wires

e) The damaged conductors, ground wires due to the Contractors fault shall be replaced at the Contractors own cost, if such damaged lines sections are forced to be replaced.

f) The Contractor shall be entirely responsible for any damage to the poles, insulators and conductors during transportation & stringing. While running out the conductors, care shall be taken that the conductors do not touch or rub against the ground or objects, which could cause scratches or damages to the strands. The conductors shall be run out of the drums from the top in order to avoid damage due to chaffing.

g) The stringing blocks shall be suspended in a manner to suit the design of the X arms. Proper T&P shall also be made available to the Employer by the Contractor for checking

Page 24: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-16

the tensions in the guy wires. The drums shall be provided with a suitable braking device to avoid damages, loose running out and kinking of the conductor. The conductor shall be continuously observed for loose or broken strands or any other damage. When approaching end of a drum length at least three coils shall be left when the stringing operations are to be stopped. These coils are to be removed carefully and if another length is required to be run, a joint shall be made as per the recommendations of the manufacturers.

h) Repairs to Conductors if necessary shall be carried out during the running out operations with repair sleeves. Repairing of Conductors surface shall be done only in case of minor damage scuff marks etc. keeping in view both electrical and mechanical safe requirements. The final conductors shall be cleaned smooth and without any projections, sharp points cuts, abrasions.

i) Conductors Splices shall be made so that they do not crack or get damaged in the stringing operations. The Contractor shall use only such equipment/methods during Conductor stringing which ensures complete compliance in this regard.

j) Derricks shall be used where roads, rivers, channels, telecommunications or overhead power line, railway lines, fences or walls have to be crossed during stringing operations. It shall be seen that normal services are not interrupted or damage caused to property. Shut down shall be obtained when working at crossing of overhead power lines. Contractor shall be responsible for proper handling of the Conductor. Earth wire and accessories in the field.

k) The Contractor must install all of ground wire suspension string onto the poles suitably with details indicated in drawings or instruction given by the Employer.

l) The proposed 11 kV and 33 kVpower lines may run parallel for certain distance with the existing power lines, which may remain energized during the stringing period. As a result there is a possibility of dangerous voltage build up due to electromagnetic and electrostatic coupling in the pulling wire, conductors and earth wires which although comparatively small during normal operations can be severe during switching. It shall be Contractor’s responsibility to take adequate safety precautions to protect his employees and others from this potential danger.

m) The Contractor shall inform the Township Engineer of MOEE whenever he wants to get the ‘Permit to Work’ from the local sub-division for erecting the new 11 KV line/medium voltage line. A minimum 72 hours advance notice in writing for availing the shutdown on any live 33kV /11 KV feeder/LT lines shall be given to the Engineer. The 33kV /11 KV LT line on which permit is taken should be made clear from all the temporary earth, men and material before cancellation of the ‘Permit to Work’. It is worth mentioning here that the ‘Permit to Work’ on existing line shall

Page 25: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-17

be arranged through the Engineer or his representative and the same shall also be got cancelled through the same agency only.

7.5.3 Sagging in Operation

a) The Conductor shall be pulled up to the desired sag and left in running blocks for at least one hour after which the sag shall be re-checked and adjusted if necessary before transferring the Conductor from the running blocks to the pin insulators. The conductor shall be clamped within 36 hours of sagging.

b) The sag will be checked in the first and the last span of the section in case of sections up to 8 spans and in one intermediate span also for sections with more than eight Spans. The sag shall also be checked when the Conductor have been drawn up and transferred from running blocks to the insulators.

c) The running blocks when suspended from the structures for sagging shall be so adjusted that the Conductors on running blocks will be on the same height as 11 KV Pin Insulators to which it is to be secured. At sharp vertical angle, the sag and tensions shall be checked on both sides of the angle, the conductor wire shall be checked from the running blocks for equality of tension on both sides.

d) Tensioning and sagging operations shall be carried out in calm weather when rapid changes in temperature are not likely to occur.

7.5.3.1 Tensioning and Sagging of Conductor and Earth Wire:

The Tensioning and Sagging Operations shall be done in accordance with the approved stringing chart before the Conductor and Earth wire are finally attached to the poles through the earth wire clamps and insulators for the Conductor. The relevant stringing charts for the Conductor and earth wire should be employed for this purpose.

7.5.4. Instructions for Installation of Transformers The Contractor shall comply with the Guidelines and drawings provided for the installation of Transformers and have prior approval from Project Manager for any modification that in his opinion improves the installation. Outdoor transformers shall be installed on an H pole structure with two 12 m, 3.5 kN poles for 33/0.4 kV transformer. Location of planned transformers shall be adhered to the load center of the village, whenever possible. Variations in location from that planned exceeding 10m for 11/0.4 kV transformer shall require the prior approval of the Project Manager of Project Management Office of MOEE.

Page 26: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-18

The following instructions for Transformer must be undertaken to satisfy installation of 11/0.4 kV and 33/0.4 kV Transformer.

7.5.4.1 H pole structure for transformer installation.

a) The ground level must be 1675mm for 10M and 2000mm for 12M.

b) Pole mounted type must be installed according to Design Drawing in the bidding.

c) The beneath of H pole structure must be concreted 610x610x915mm for 11/0.4 transformer and 762x762x915 mm with the ratio of 1:3:6 for 33/0.4 kV transformer.

d) Lightning Arrester and drop out fuse must be accorded with the design and drawing and connection must be installed correctly.

7.5.4.2 Earthing Installation

a) Body Earthing, Lightning Arrester Earthing and Neutral earthing must be installed separately and earth resistance must be less than 5 Ω.

b) Earth holes must be spaced at least 3 m from each other.

c) Earthing conductor (HDBC) must be installed without joint.

d) Earthing conductor (HDBC) and Earth Rod must be connected by exothermic welding (Cad weld Mold & Powder).The cad weld mold process provides HDBC and Earth Rod.The Contractor must be clean and remove the rest from surface of HDBC and Earth Rod by cable cleaning brush.The welded spot must not be watered for decrase the temperature of cause of welding.

e) If the earth resistance is more than 5 Ω based on the soil type, the bidder must installed to get required earth resistance by digging artesian well and earth spikes.

7.5.4.3 400 V Cable and Panel Installation

a) 400 V cable must be installed tightly. b) The stay must be the adjustable stay rod and stay footing must be concreted

according to the drawing design. c) After the 11/0.4 kV transformer installation, insulation test and earthing

resistance test must be carried out and test results must also be submitted.

Page 27: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-19

7.5.4.4 Connection of Power Lines into Transformer and Pulling Lines Crossing Existing Lines

The Contractor must have specific details for distribution lines connection, to ensure the implementation of connection according to design, safe and minimize the electricity shut-down time.

7.6. Final Checking, Testing and Commissioning

After completion of the works, final checking of the line and equipment shall be carried out by the Contractor to ensure that all the foundation works, pole erection and stringing has been done according to the specifications and as approved by the Employer. All the works shall be thoroughly inspected keeping in view the following main points:

a) All the structures are straight & erect and in proper alignment. Sufficient

back filled earth is lying over each pit and it is adequately rammed /

compacted.

b) All bolts are properly tightened and punched / tack welded.

c) Guys: To check whether the Guy wire is tight and whether the Guy

insulators are in-tact.

d) Erection of the Cross-arms with Proper alignment.

e) The stringing of the Conductors and Earth Wire has been done as per the

approved sag and tension charts and desired clearances are clearly

available.

f) All Conductors and Earth wire accessories are properly installed & fixed.

g) Binding, clamps and jumpers – To check whether these are in reach.

h) All other requirements to complete the work like fixing of danger plate,

phase plate, number plate etc. are properly installed.

i) The insulation of line as a whole is tested by the Contractor by providing

his own equipment, labor etc. to the satisfaction of the Employer.

j) Earthing System: To check whether the earthing connections of supports

and fittings are intact. Measure earth resistance with earth tester.

Page 28: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-20

k) After the visual inspection is over and satisfied, the conductor is tested for

continuity/ground, by means of megger. At the time of testing through

megger person should not climb on the pole or touch the guarding,

conductor, guy wire etc.

7.7 Hauling and storing material, device, apparatus and equipment at Contractor’s warehouse

a) The Contractor is responsible for the place where is temporary keeping

and storing material, apparatus, equipment supplied by the Employer in conformity with guidance by the manufacturer and requirement of Employer. Before handling material, apparatus and equipment to the Contractor, the Employer shall perform inspection, checking, and acceptance on method of material storing under criteria required for each types of material, apparatus and equipment.The contractor is responsible for accounting of materials provided by MOEE and filling out the Table .1 ,Balance of Material store issued from MOEE.

b) The Contractor is responsible for notify the Employer immediately of any damage, shortage, discrepancy etc. for the purpose of Employer’s information only. The Contractor shall submit to the Employer every week a report detailing all the receipts during the weeks. However, the Contractor shall be solely responsible for any shortages or damages in transit, handling and/or in storage and erection of the equipment at Site

c) The Contractor is responsible for making suitable indoor storage facilities, to store all equipment which require indoor storage

d) Any redundant material supplied by the Employer and material, apparatus and equipment recovered from the power system which is under Contractor’s responsibility shall be expected to be stored, hauled and returned by the Contractor to the Employer’s warehouse, or any other location stipulated by the Employer, right after the work has been accepted for connection.

e) The Contractor shall be fully responsible for any loss and/or damages to material, apparatus, device and equipment supplied by the Employer to him if such loss and/or damages caused by himself. In such a case, the Contractor shall compensate properly with the type, model, style, specification or he shall compensate by deducting from his due payment under requirement by the Employer .

Page 29: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-21

f) Within the period when material, apparatus, devices and equipment are stored at the site: the Employer shall send a team to inspect and check the storing condition at the site by Contractor.

7.8. STEEL WORKS 7.8.1 General requirements

The reinforced steel must be satisfied the following requirements:

- The surface of steel must be clean, free of mud, grease, paint, scale, peeled off.

- Flatten steel, reduced cross sectional area due to rust scrubbing, cleaning

surface or due to any other reasons shall not be over permissible limit 2% of diameter.

- The reinforced steel must be protected separately to each group and the

measures to prevent corrosion, rust must be available.

- The reinforced steel must be stored under the covered roof and stockpiled correspondent to its code, diameter, and length. The code must be marked clearly on steel stockpile for the purpose of convenient use. The rusted steel and non-rusted steel shall not be stockpiled together. In case the steel must be stockpiled outdoor, the steel shall be stored on wooden supports of sufficient height at least 30cm higher than the stable ground surface without grass growing. One end of steel stockpile must be supported on higher position than the other end. The height of steel stockpile should not be higher than 1.2m and the width of steel stockpile should not be greater than 2m.

- The cold-rolled steel must be kept in weather-tight and dry warehouse.

7.8.2 Transport and installation of reinforced steel

Page 30: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-22

When transporting the reinforced steel and steel members, measures shall be taken for prevention of corrosion, collision and deformation of steel must be applied.

7.9. Contents of Work Item

The Contractor must ensure implementation of following work items:

Installation Works of items according to requirements specified in design documents. To ensure the source of power and water supply for Installation Works without causing impacts on surrounding environment.

The Contractor shall be responsible for all of safety measures as well as safety at works (if any) during the preparation and Installation Works stage until completion and handing over the project.

The Contractor must ensure the general organization on Installation schedule of project work items. The Contractor must inform the obstruction in time to the Employer for jointly solving. The access to the project site is shown in detailed drawings design. The Contractor shall be responsible to obtain the permission for access to work site, etc., and keep the access in safe and clean condition all the time.

Based on the detailed drawings design and take-over plan layout of project site, the Contractor shall be responsible to determine boundary land-marks and Installation Works area for each work item. The Contractor shall only start the Installation Works after having checked and approved by the Employer.

The Contractor shall be responsible to determine the location, elevation of foundation details, on the basic of the project site original data given by the representative of Employer and be responsible to the accuracy of this site setting out works.

The Contractor shall be responsible to submit adequate and detailed Installation Works program, plan including the equipment, manpower, investigation staff and required materials to be used for the project setting out works, to the representative of the Employer for checking without asking for any increased cost.

\

7.10 Work Safety

When Installation Works to make any provisions on labor safety and hygiene and the environment in accordance with current regulations.

Absolute safe for human and equipment is top-ranking Employer’s requirement to Contractor. The Contractor must appoint at least ONE safety person for project and arrange safety supervision for each group at the site.

Page 31: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-23

Safety person must be proficient all technical safety procedures as well as other means to avoid risks at the place to implement contract works.

All workers, groups implementing contract works must be trained, guided all procedures, regulations on Installation Works, safety, and checked, certified to ensure standards on safety of competent authority at current regulation.

7.10.1 Avoidance of Interference

The Contractor shall not interfere unnecessarily or improperly with:

(a) the convenience of the public, or

(b) the access to and use and occupation of all roads and footpaths, irrespective of whether they are public or in the possession of the Employer or of others.

The Contractor shall indemnify and hold the Employer harmless against and from all damages, losses and expenses (including legal fees and expenses) resulting from any such unnecessary or improper interference.

7.10.2 Access to Road

The Contractor shall be deemed to have been satisfied as to the suitability andaccess routes to the Site at Base Date. The Contractor shall use reasonable effortroad or bridge from being damaged by the Contractor’s traffic or by the ContracThese efforts shall include the proper use of appropriate vehicles and routes.

Except as otherwise stated in these Conditions:

(a) the Contractor shall (as between the Parties) be responsible for any maintenance which may be required for his use of access routes;

(b) the Contractor shall provide all necessary signs or directions along access routes, and shall obtain any permission which may be required from the relevant authorities for his use of routes, signs and directions;

(c) the Employer shall not be responsible for any claims which may arise from the use or otherwise of any access route;

(d) the Employer does not guarantee the suitability or availability of particular access routes; and

(e) Costs due to non-suitability or non-availability, for the use required by the Contractor, of access routes shall be borne by the Contractor.

Page 32: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-24

7.10.3 Protection of the Environment

The Contractor shall take all reasonable steps to protect the environment (both on and off the Site) and to limit damage and nuisance to people and property resulting from pollution, noise and other results of his operations.

The Contractor shall ensure that emissions, surface discharges and effluent from the Contractor’s activities shall not exceed the values stated in the Specification or prescribed by applicable Laws.

7.10.4 Security of the Site

Unless otherwise stated in the Particular Conditions:

(a) the Contractor shall be responsible for keeping unauthorised persons off the Site, and

(b) authorised persons shall be limited to the Contractor’s Personnel and the Employer’s Personnel; and to any other personnel notified to the Contractor, by the Employer or the Engineer, as authorised personnel of the Employer’s other contractors on the Site.

7.10.5 Fossil

All fossils, coins, articles of value or antiquity, and structures and other remains or items of geological or archaeological interest found on the Site shall be placed under the care and authority of the Employer. The Contractor shall take reasonable precautions to prevent Contractor’s Personnel or other persons from removing or damaging any of these findings.

The Contractor shall, upon discovery of any such finding, promptly give notice to the MOEE’s responsible person , who shall issue instructions for dealing with it.

Page 33: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-25

7.10.6 Health and Safety

The Contractor shall at all times take all reasonable precautions to maintain the health and safety of the Contractor’s Personnel. In collaboration with local health authorities, the Contractor shall ensure that medical staff, first aid facilities, sick bay and ambulance service are available at all times at the Site and at any accommodation for Contractor’s and Employer’s Personnel, and that suitable arrangements are made for all necessary welfare and hygiene requirements and for the prevention of epidemics.

The Contractor shall appoint an accident prevention person at the Site, responsible for maintaining safety and protection against accidents. This person shall be qualified for this responsibility, and shall have the authority to issue instructions and take protective measures to prevent accidents. Throughout the execution of the Works, the Contractor shall provide whatever is required by this person to exercise this responsibility and authority.

The Contractor shall send, to the Employer, details of any accident as soon as practicable after its occurrence. The Contractor shall maintain records and make reports concerning health, safety and welfare of persons, and damage to property, as the Engineer may reasonably require.

7.10.7 Supply of Water

The Contractor shall, having regard to local conditions, provide on the Site an adequate supply of drinking and other water for the use of the Contractor’s Personnel.

7.10.8 Prohibition of Harmful Child Labour

The Contractor shall not employ children in a manner that is economically exploitative, or is likely to be hazardous, or to interfere with, the child’s education, or to be harmful to the child’s health or physical, mental, spiritual, moral, or social development. Where the relevant labour laws of the Country have provisions for employment of minors, the Contractor shall follow those laws applicable to the Contractor. Children below the age of 18 years shall not be employed in dangerous work.

7.10.9 Employment Records of Workers

The Contractor shall keep complete and accurate records of the employment of labour at the Site. The records shall include the names, ages, genders, hours worked and wages paid to all workers. These records shall be summarized on a monthly basis and submitted to the Employer. These records shall be included in the details to be submitted by the Contractor.

Page 34: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-26

7.11. Supplementary Informations 7.11.1 Clearance of Site

Tidying and Cleaning Site after Completion of Installation Works

The site tidying and cleaning works must be done right after completion of the Installation Works. The Contractor must remove all trees, temporary site camps, Installation equipments, disposed materials, concrete formworks and other materials in adjacent area. The unusable materials must be fired or eliminated in place in such a manner not causing any unfavorable conditions or objection from the local inhabitants.

The Employer shall carry out site checking and accepting for works completion of the Contractor. The Contractor must carry out tidying and cleaning works according to the requirements given by the Employer. Upon receiving the Performance Certificate, the Contractor shall remove any remaining Contractor’s Equipment, surplus material, wreckage, rubbish and Temporary Works from the Site.

If all these items have not been removed within 28 days after receipt by the Contractor of the Performance Certificate

7.11.2 Progress Reports

Unless otherwise stated in the Particular Conditions, monthly progress reports shall be prepared by the Contractor and submitted to the relative Employer’s Engineer in six copies. The first report shall cover the period up to the end of the first calendar month following the Commencement Date. Reports shall be submitted monthly thereafter, each within 7 days after the last day of the period to which it relates.

Reporting shall continue until the Contractor has completed all work which is known to be outstanding at the completion date stated in the Taking-Over Certificate for the Works.

Each report shall include:

(a) charts and detailed descriptions of percentage progress, including each stage of design (if any), Contractor’s Documents, procurement and manufacture if any procure shall be done due to no provided material by the Employer, delivery to Site, Installation Works, erection and testing

(b) photographs showing the status of progress on the Site;

(c) safety statistics, including details of any hazardous incidents and activities relating to environmental aspects and public relations; and

Page 35: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-27

(d) comparisons of actual and planned progress, with details of any events or circumstances which may jeopardise the completion in accordance with the Contract, and the measures being (or to be) adopted to overcome delays.

7.13 Checking-Taking Over, Trial Testing, Handing-Over

The Contractor must prepare full documents before checking-taking over including as-constructed drawings, technical checking-taking over, project diary, and untreated minutes.

Contractor shall energize the 11kV and 33kV lines and Transformers under supervision of Employer’s Engineer and demonstrate safe operation for 72 hours before handing-over.

7.14 Installation Works Schedule

The Contractor is not permitted to start the Installation Works without written approval given by the Employer.

7.15 As-Built Drawings

After completion of project, the Contractor must submit the as-built drawings with sufficient contents as actual Completed situation acceptable by the Employer no later than 14(fourteen) days from the completion date.

7.16 Others for the Attention

The Contractor must strictly follow the detailed drawings and instruction given in the design, if there is any difficulties, the Contractor must notify the Employer to obtain solving measures.

The Contractor must have measures to construct each work item consecutively to ensure Installation Works schedule and quality of works.

The Contractor must have safety measures to avoid damages to equipment, not causing accident at work. The Contractor shall be fully responsible for such damages and accident occurred.

The Contractor must strictly follow the standards specified in technical requirements and current relevant standards.

Page 36: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-28

7.16.1 Sag-tension Calculations The Contractor shall carry out sag-tension calculations for respective line types and conductors prior to installation works. These calculations shall be based on the manufacturer’s data for respective conductor characteristics. The initial conditions for the calculation shall be such that maximum conductor tensions are achieved under cold + ice + wind conditions. This is necessary to ensure that maximum conductor tension forces are applied on the angle poles at above conditions. The Contractor shall prepare sag-tension charts based on the calculations approved by the Project Manager. These sag tension charts shall be used in stringing of the respective conductors. This aspect will be monitored by the Project Manager to ensure proper line Installation to suit the wide variation of temperature and climatic conditions in Myanmar.

7.17 Accounting of Material issued to Contractor

The contractor shall submit accountance of material supplied by MOEE.The excess material shall be returned to store of MOEE after the completion of installation with the filling of the balance form.

Page 37: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-29

Deliveried by Approved by Received by

Particulars Unit IssuedActual Used

Surplus

A

1

2

3

Form of Balance of Material Store Issued from MOEE

Sr . No

Page 38: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-30

7.19 Design and Drawings

The Contractor is responsible for providing full details of the equipment /tools and machinery used for Installation works. The following design and drawing must be undertaken to satisfy of installations.

Page 39: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-31

Page 40: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-32

Page 41: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-33

Page 42: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-34

Page 43: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-35

Page 44: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-36

Page 45: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-37

Page 46: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-38

Page 47: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-39

Page 48: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-40

Page 49: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-41

Page 50: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-42

Page 51: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-43

Page 52: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-44

Page 53: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-45

Page 54: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-46

33/0.4 kV Sub-station (Front Incoming)

No Description of Goods

1 33 kV Disc Insulator with Fitting for 150/25 mm2

2 Galvanized Full Clamp (192 mm Φ)

3 Galvanized Half Clamp (210 mm Φ)

4 Galvanized Channel Iron for Sub-station Incoming Bus Arm (65x125x65x6tx3600 mm L)

5 Galvanized Channel Iron for Sub-station Post Insulator Arm (65x125x65x6tx3600 mm L)

6 Galvanized Full Clamp (212 mm Φ)

7 Galvanized Channel Iron for Sub-station Post Insulator Arm (65x125x65x6tx200 mm L)(Short)

8 36 kV Disconnectiong Switch

9 Galvanized Channel Iron for Sub-station D/S Arm (65x125x65x6tx3600 mm L)

10 Galvanized Channel Iron for Sub-station Under D/S Arm (65x125x65x6tx800 mm L)

11 Galvanized Full Clamp (229 mm Φ)

12 Galvanized Channel Iron for Sub-station D.O.F/L.A Arm (65x125x65x6tx3600 mm L)

13 36 kV Lightning Arrestor

14 Galvanized Angle Iron for L.A Arm (65x65x6tx450 mm L)(Short)

15 Galvanized Full Clamp (248 mm Φ)

16 36 kV D.O.F

17 33/0.4 kV Transformer (For 50kVA, 100kVA, 200kVA & 315kVA)

18 600 V, 1C, Main Cable (28 M) & Feeder Cable (1 Feeder = 60 M) (For 50kVA, 100kVA, 200kVA & 315kVA)

19 Galvanized Channel Iron for Sub-station Transformer Arm (65x125x65x6tx3600 mm L)

20 Galvanized Full Clamp (292 mm Φ)

21 Galvanized Channel Iron for Sub-station D/S Handle Arm (65x125x65x6tx3600 mm L)

22 Galvanized Channel Iron for Sub-station Mounting Structure

23 Galvanized Full Clamp (308 mm Φ)

24 Galvanized Full Clamp (300 mm Φ)

25 400 V Dritribution Panel with 4 Pole 1 No ( No Fuse Breaker for Main ), 4 Pole 2 Nos ( No Fuse Breaker for 2 Feeder ) (For 50kVA, 100kVA, 200kVA &

Page 55: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-47

315kVA)

26 12 M Concrete Pole

27 Aluminium No.10 Binding Wire

28 Aluminium Tape

29 Galvanized Bolt & Nut with Washer M 16 Ø x 50 mm

30 Galvanized Bolt & Nut with Washer M 16 Ø x 75 mm

31 Galvanized Bolt & Nut with Washer M 16 Ø x 100 mm

32 Galvanized Bolt & Nut with Washer M 16 Ø x 300 mm

33 M.S Stay Rod (M18 x 1800 mmL)

34 Insulator Loop Strain for Stay (220 mm)

35 7/10 G.I Wire for Stay

36 1/4" Ø U Bolt & Nut for Stay

37 36 kV Insulated Cable 150 mm²

38 P.G Clamp 150/25 mm2 for Conductor

39 Bi-metal Clamp 150 mm2

40 Cu Cable Lug (For 50kVA, 100kVA, 200kVA & 315kVA)

41 Copper Earth Rod (1800 mmL)

42 HDBC No.4

43 Galvanized D-Iron (65x6tx400 mm L)

44 Cable Tie (Assorted Size)

45 36 kV H.T Tape

46 L.T Tape

47 Danger Sign Board

Page 56: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-48

Page 57: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-49

Page 58: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-50

Page 59: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-51

Page 60: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-52

Page 61: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-53

Page 62: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-54

Page 63: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-55

Page 64: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-56

Page 65: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-57

Page 66: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-58

Page 67: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-59

Page 68: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-60

Page 69: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-61

Page 70: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-62

Page 71: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-63

Page 72: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-64

Page 73: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-65

Page 74: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-66

Page 75: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-67

Page 76: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-68

Page 77: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-69

Page 78: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-70

Page 79: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-71

Page 80: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-72

Page 81: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-73

Page 82: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-74

Page 83: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-75

Page 84: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-76

Page 85: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-77

Page 86: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-78

Page 87: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-79

Page 88: Volume: 1 Part-2 Works Requirements To BIDDING DOCUMENT · Insulation co-ordination IEC 60071-1, -2 IEC 60071-1, -2 IEC 60071-1, -2 Standard power frequency short duration voltage

2-80