GRID Voltage Stability Assessment at the EMS Jay Giri i-PCGrid San Francisco, March 26 th , 2013

Upload: others

Post on 11-Mar-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Voltage Stability Assessment at the EMS...Strategic Team: PG&E, ALSTOM, GE, Mississippi State University, Quanta Academic & Testing GeorgiaTech, OMICRON / RTDS / Virginia Tech., Washington

GRID

Voltage Stability Assessment at the EMS

Jay Giri

i-PCGrid

San Francisco, March 26th, 2013

Page 2: Voltage Stability Assessment at the EMS...Strategic Team: PG&E, ALSTOM, GE, Mississippi State University, Quanta Academic & Testing GeorgiaTech, OMICRON / RTDS / Virginia Tech., Washington

EMS Overview – DSA Integration

Basecase

Division Load & Loss

Load (area) meas.

Status & Analog Data

Network Loss

Unit base point & transaction

schedules

Basecase Original or Rescheduled

Basecase

Harmful Contingencies

Load Forecast SCADA AGC

State Estimation

Contingency Analysis

Volt-Var Dispatch

Basecase Basecase

Short Circuit

Security Enhancement Constrained Dispatch

Contingency Planning

Preventive Action

DSATools CTG & RAS

e-terravision UI

VSAT TSAT SSAT

DSA UI DSA UI

Copyright Alstom Grid 2013

Page 3: Voltage Stability Assessment at the EMS...Strategic Team: PG&E, ALSTOM, GE, Mississippi State University, Quanta Academic & Testing GeorgiaTech, OMICRON / RTDS / Virginia Tech., Washington

EMS Integration with Powertech DSATools - VSAT

Copyright Alstom Grid 2013

• Fully automatic − Auto-run in real time network sequence − One-click to run in the study mode

• Archiving − Auto-archiving insecure cases for further investigation − Periodic Archiving

• Display the computation results on EMS side − Brings up VSAT result viewer from the EMS displays − Processes results to issue alarms, update statistics

Page 4: Voltage Stability Assessment at the EMS...Strategic Team: PG&E, ALSTOM, GE, Mississippi State University, Quanta Academic & Testing GeorgiaTech, OMICRON / RTDS / Virginia Tech., Washington

DSATools VSAT installations worldwide

Total: 36+

North America: 20+

Plus at utilities in:

Australia, China, Egypt , Ireland, South Africa, Korea, UK, Saudi, Malaysia, Norway, NZ, Vietnam, Colombia, etc

Copyright Alstom Grid 2013

Page 5: Voltage Stability Assessment at the EMS...Strategic Team: PG&E, ALSTOM, GE, Mississippi State University, Quanta Academic & Testing GeorgiaTech, OMICRON / RTDS / Virginia Tech., Washington

North American SynchroPhasor Initiative (NASPI) – DOE SGIG projects

“Better information supports better - and faster - decisions.”

DOE and NERC are working together closely with industry to enable wide area time-synchronized measurements that will enhance the reliability of the electric power grid through improved situational awareness and other applications

April 2007 March 2012

6 September 2012

Page 6: Voltage Stability Assessment at the EMS...Strategic Team: PG&E, ALSTOM, GE, Mississippi State University, Quanta Academic & Testing GeorgiaTech, OMICRON / RTDS / Virginia Tech., Washington

Emerging era of Holistic Grid Security Analysis

Page 7: Voltage Stability Assessment at the EMS...Strategic Team: PG&E, ALSTOM, GE, Mississippi State University, Quanta Academic & Testing GeorgiaTech, OMICRON / RTDS / Virginia Tech., Washington

Hybrid Approach to Voltage Stability Assessment

“Measurement-based” Voltage Stability identify potential problems: - Voltage Profile & Sensitivities - Reactive Reserves - Real-Time Voltage Instability Indicator (RVII):

Advanced indicators based on key properties associated with voltage collapse phenomenon

- “Model-based” Voltage Stability to evaluate: - MW/MVAR Margins - Weak network elements - Critical contingencies - Corrective Actions

Copyright Alstom Grid 2013

Page 8: Voltage Stability Assessment at the EMS...Strategic Team: PG&E, ALSTOM, GE, Mississippi State University, Quanta Academic & Testing GeorgiaTech, OMICRON / RTDS / Virginia Tech., Washington

EMS & Online-DSA Applications

VSAT

CA

RAS

A Hybrid Approach to Voltage Stability Assessment An integrated “measurement-based” and “model-based “ approach

Real-Time Voltage Instability Indicator (RVII) Detect WHEN in danger! PMU measurements

Estimate equivalent parameters in real-time

PMUs Real-Time Voltage Instability Indicator (RVII)

Determine HOW to respond!

Bus Voltage (V) Equivalent Impedance (Zeq) Reactive Margin (Qmargin)

Predict Qmargin changes under “worst case” contingency.

Provide recommendations on corrective actions.

MEAS

UREM

ENT-B

ASED

MO

DEL-B

ASDE

D

Copyright Alstom Grid 2013

Page 9: Voltage Stability Assessment at the EMS...Strategic Team: PG&E, ALSTOM, GE, Mississippi State University, Quanta Academic & Testing GeorgiaTech, OMICRON / RTDS / Virginia Tech., Washington

Dynamic limit

On-Line Voltage Stability Assessment Integrated “measurement-based” and “model-based” analysis

MW Margins are computed in real-time using “model-based” Voltage Stability Assessment Tools (VSAT). ⇒ identify proximity to voltage stability violation

Real-time P-V locus (and voltage sensitivities) based on PMU measurements. ⇒ monitor current operating condition

Copyright Alstom Grid 2013

Page 10: Voltage Stability Assessment at the EMS...Strategic Team: PG&E, ALSTOM, GE, Mississippi State University, Quanta Academic & Testing GeorgiaTech, OMICRON / RTDS / Virginia Tech., Washington

San Ramon - Proof of Concept Facility Strategic Team: PG&E, ALSTOM, GE, Mississippi State University, Quanta Academic & Testing GeorgiaTech, OMICRON / RTDS / Virginia Tech., Washington State Univ.

SynchroPhasor Applications for the Control Center Multi-host Redundancy (ISD Link)

Copyright Alstom Grid 2013

RVII VSAT

Page 11: Voltage Stability Assessment at the EMS...Strategic Team: PG&E, ALSTOM, GE, Mississippi State University, Quanta Academic & Testing GeorgiaTech, OMICRON / RTDS / Virginia Tech., Washington

DSA-EMS Integration with e-terravision

Copyright Alstom Grid 2013

Page 12: Voltage Stability Assessment at the EMS...Strategic Team: PG&E, ALSTOM, GE, Mississippi State University, Quanta Academic & Testing GeorgiaTech, OMICRON / RTDS / Virginia Tech., Washington

Situational Awareness VSAT and e-terravision

Copyright Alstom Grid 2013

Page 13: Voltage Stability Assessment at the EMS...Strategic Team: PG&E, ALSTOM, GE, Mississippi State University, Quanta Academic & Testing GeorgiaTech, OMICRON / RTDS / Virginia Tech., Washington

VSAT- PV Curves

Copyright Alstom Grid 2013

Page 14: Voltage Stability Assessment at the EMS...Strategic Team: PG&E, ALSTOM, GE, Mississippi State University, Quanta Academic & Testing GeorgiaTech, OMICRON / RTDS / Virginia Tech., Washington

Regional Reactive Reserves Where are the Vars ?

Select region of interest to identify available VAR resources

Detailed summary of existing resources within chosen region

Copyright Alstom Grid 2013

Page 15: Voltage Stability Assessment at the EMS...Strategic Team: PG&E, ALSTOM, GE, Mississippi State University, Quanta Academic & Testing GeorgiaTech, OMICRON / RTDS / Virginia Tech., Washington

Measurement-based voltage stability monitoring: - Bus

- Corridor

- Load Center

Real-Time Voltage Instability Indicator (RVII)

Copyright Alstom Grid 2013

Bus

Corridor

Load Center

Page 16: Voltage Stability Assessment at the EMS...Strategic Team: PG&E, ALSTOM, GE, Mississippi State University, Quanta Academic & Testing GeorgiaTech, OMICRON / RTDS / Virginia Tech., Washington

RVII Engineering User Interface (UI)

Real-Time Trends

P-Q-V Curves

Alarm messages

Monitored ‘Corridors’ & ‘Buses’.

Page 17: Voltage Stability Assessment at the EMS...Strategic Team: PG&E, ALSTOM, GE, Mississippi State University, Quanta Academic & Testing GeorgiaTech, OMICRON / RTDS / Virginia Tech., Washington

Comprehensive Voltage Stability Alarms Linking WAMS “Wide-Area” Low Voltage Alarms to Operator Guides in EMS

WAMS Composite Alarms

WAMS indicate the simultaneous occurrence of Low Voltage over a broad region. AND

Operator Guides in EMS

Reactive Reserve Monitoring in EMS Decision making: Operator Guides (e.g. “Switch On Capacitor Banks”). Arm Special Protection Schemes

Reactive Reserve (MVAR) monitoring for user-defined areas in EMS.

Detect WHEN to Take Action... and HOW to Respond!

Copyright Alstom Grid 2013

Page 18: Voltage Stability Assessment at the EMS...Strategic Team: PG&E, ALSTOM, GE, Mississippi State University, Quanta Academic & Testing GeorgiaTech, OMICRON / RTDS / Virginia Tech., Washington

WAMS: “Wide Area Monitoring System” The new heartbeat of the grid!

EMS

Dynamic Security Assessment - VSAT

State Estimation Contingency

Analysis

Offline Analysis

Modelling

Root Cause Analysis

Wide Area Controls

Post-Event

Generator & ISO Compliance

New Smart Grid Applications

Distribution

DMS Distributed Generation

Demand Response

Substation Automation

WAMS ‘the new heartbeat of the grid’

Local Controls

Synchrophasor Analytics - RVII

Copyright Alstom Grid 2013

Page 19: Voltage Stability Assessment at the EMS...Strategic Team: PG&E, ALSTOM, GE, Mississippi State University, Quanta Academic & Testing GeorgiaTech, OMICRON / RTDS / Virginia Tech., Washington

Thank you!