virginia department of transportation · planworks case study route 29 corridor assessment,...

58
PlanWorks Case Study Route 29 Corridor Assessment, Campbell County Virginia Department of Transportation PlanWorks is a web resource that supports collaborative decisionmaking in transportation planning and project development. PlanWorks is built around key decision points in longrange planning, programming, corridor planning, and environmental review. PlanWorks suggests when and how to engage crossdisciplinary partners and stakeholder groups. Transportation decisionmaking phase(s): Corridor Planning Executive Summary Route 29 (Wards Road) in Campbell County, Virginia is a 6.6 mile corridor serving two sets of users: through travelers who value the corridor’s contribution to statewide mobility and the business community which values local access. The corridor has been well examined, with five separate studies conducted during the past two decades, however, a lack of funds for major capacity investments has forced the community to look toward lower‐cost solutions, such as establishment of a transportation corridor overlay district and consolidation of access points—but such solutions have not been identified, in a detailed manner, on a systematic basis. The single‐most greatest challenge, therefore, has been the lack of an authorizing environment in which to make progress toward improving this corridor which functions as both a VDOT route of statewide significance and a local main street. A key outcome includes the development of a $19.43 million set of improvements that collectively improve local vehicular access (e.g., the addition of turn lanes), local nonmotorized access (e.g., construction of a shared use path), and through mobility (e.g., the closure of medians). This outcome is supported by a public involvement process (supported by the local Board of Supervisors [BOS]) that demonstrated interest in specific corridor‐preservation techniques and the preparation of these projects for candidate funding sources available in Virginia: Smart Scale, the Highway Safety Improvement Program, and the MPO’s Constrained Long Range Plan. Project Snapshot A 6.6 mile corridor with ADT equal to about 20,376 (2015) and 365 crashes over a 5 year period (2011‐2015). The corridor is on Virginia’s Corridors of Statewide Significance (COSS), emphasizing its mobility function Yet, users must increase expected commuting time by about 45% if they cannot afford to be late more than twice per month. The corridor is the site of the county’s 2006 Transportation Corridor Overlay District. The corridor has been studied several times outside the traditional planning process: 1997, 2003, 2005, 2009, and 2011. Funds for large scale capacity improvements are not available: a 2016 planning‐level cost estimate for a bypass is $100 million. A new programming environment in Virginia (Smart Scale) emphasizes cost‐effective projects, where benefits must be quantified as much as possible. County BOS strongly emphasized the need for an open process allowing all to participate.

Upload: nguyendien

Post on 18-Apr-2018

217 views

Category:

Documents


3 download

TRANSCRIPT

PlanWorks Case Study Route 29 Corridor Assessment, Campbell County

Virginia Department of Transportation

PlanWorksisawebresourcethatsupportscollaborativedecision‐making intransportationplanningandprojectdevelopment.PlanWorksisbuiltaroundkeydecisionpointsinlong‐rangeplanning,programming,corridorplanning,andenvironmentalreview.PlanWorkssuggestswhenandhowtoengagecross‐disciplinarypartnersandstakeholdergroups.

Transportationdecision‐makingphase(s):CorridorPlanning

ExecutiveSummary

Route29(WardsRoad)inCampbellCounty,Virginiaisa6.6milecorridorservingtwosetsofusers:throughtravelerswhovaluethecorridor’scontributiontostatewidemobilityandthebusinesscommunitywhichvalueslocalaccess.Thecorridorhasbeenwellexamined,withfiveseparatestudiesconductedduringthepasttwodecades,however,alackoffundsformajorcapacityinvestmentshasforcedthecommunitytolooktowardlower‐costsolutions,suchasestablishmentofatransportationcorridoroverlaydistrictandconsolidationofaccesspoints—butsuchsolutionshavenotbeenidentified,inadetailedmanner,onasystematicbasis.Thesingle‐mostgreatestchallenge,therefore,hasbeenthelackofanauthorizingenvironmentinwhichtomakeprogresstowardimprovingthiscorridorwhichfunctionsasbothaVDOTrouteofstatewidesignificanceandalocalmainstreet.Akeyoutcomeincludesthedevelopmentofa$19.43millionsetofimprovementsthatcollectivelyimprovelocalvehicularaccess(e.g.,theadditionofturnlanes),localnonmotorizedaccess(e.g.,constructionofasharedusepath),andthroughmobility(e.g.,theclosureofmedians).Thisoutcomeissupportedbyapublicinvolvementprocess(supportedbythelocalBoardofSupervisors[BOS])thatdemonstratedinterestinspecificcorridor‐preservationtechniquesandthepreparationoftheseprojectsforcandidatefundingsourcesavailableinVirginia:SmartScale,theHighwaySafetyImprovementProgram,andtheMPO’sConstrainedLongRangePlan.

ProjectSnapshot

A6.6milecorridorwithADTequaltoabout20,376(2015)and365crashesovera5yearperiod(2011‐2015).

ThecorridorisonVirginia’sCorridorsofStatewideSignificance(COSS),emphasizingitsmobilityfunction

Yet,usersmustincreaseexpectedcommutingtimebyabout45%iftheycannotaffordtobelatemorethantwicepermonth.

Thecorridoristhesiteofthecounty’s2006TransportationCorridorOverlayDistrict.

Thecorridorhasbeenstudiedseveraltimesoutsidethetraditionalplanningprocess:1997,2003,2005,2009,and2011.

Fundsforlargescalecapacityimprovementsarenotavailable:a2016planning‐levelcostestimateforabypassis$100million.

AnewprogrammingenvironmentinVirginia(SmartScale)emphasizescost‐effectiveprojects,wherebenefitsmustbequantifiedasmuchaspossible.

CountyBOSstronglyemphasizedtheneedforanopenprocessallowingalltoparticipate.

2

Agency’sChallenge

ThechallengeVDOTfacedwhenseekingthisPlanWorksgrantwashowtoidentifyspecificprojectsthatboth(1)generatedlocalsupportand(2)couldbebuiltwithavailablefinancialresources.ThischallengewasexacerbatedbythefactthatWardsRoad(Route29)inCampbellCountysupportstwodistinctpurposes:localeconomicdevelopment(asthisareaincludesLynchburgRegionalAirport,anexpandingLibertyUniversity,andsignificantgrowthincommercialestablishments)andstatewidemobility(asUS‐29isamajornorth‐southconnectionprovidingpassengerandfreightserviceforVirginiaandadesignatedcorridorofstatewidesignificance).Theneedtoimproveinstitutionaldecision‐makingwhenacorridorservesbothmobilityandaccesshasbeendocumentedinVirginia(OhlmsandRoy,2016).

Forthiscorridor,theroleoflocalsupportandthelimitsoffinancialresourcesareclear,basedon20yearsofstudies:aphase1statewidestudy(1997),aphase2and3statewidestudy(2003),thedevelopmentofacorridoroverlaydistrictinCampbellCounty(2005),astatewideblueprint(2009),aroadwaysafetyaudit(2010/2011),andinclusionwithincomprehensiveplans.Theaforementioned2003studyclearlyarticulatestheneedtobothreducethenumberoffutureaccesspointsandtosecurefundingforimprovementsinaneraofscarcefiscalresources,concludingthat,giventhatthecompetitivenatureoftransportationfundinginVirginia,evenwithinnovativefinancingtechniquessuchasaretailsalestaxdedicatedtotransportation,thereexistsa“needtochangethepriorityofthisprojectinthecontextofoverallCommonwealthtransportationprojects.”(VDOT,2003).(Forexample,thatreportsuggestedthataretailsalestaxforthe100+milecorridor[e.g.,notjustCampbellCountyandtheadjacentCityofLynchburg,butfromthecityofCharlottesvilletothenorthtoDanvilleinthesouth]—couldgenerateapproximately$327million[inyear2000dollars]overa20yearperiod[about$361millionin2016dollarsintermsofpurchasingpowerforhighwayconstructionbasedonconstructioncostindicesavailableforthatperiod(FHWA,2015,2016)].A2016planningcostestimateisthatabypassinthiscountyalonewouldcostapproximately$100million—easilydwarfingthe$26millionprimaryallocationfortheentireten‐countyLynchburgDistrictin2004.)Thecorridorhistoryalsohighlightstheneedforthegenerationoflocalsupport:anaddendumtothe2009statewideblueprintstatedthataprofessionalfacilitatorshouldbeenlistedtobuildaconstituencyforimprovements,explainingthat“Localofficialscancollaboratewithotherstakeholdersandoneanotherinfacilitatedworkshopsand/orcharrettestocompareinterests,explorealternativesandextendcorridorvisions.”(VDOT,2011).Thus,achallengefacedatthebeginningofthisprocesswastheintegrationofsought‐afterneedsforthecorridorwithlocalandstatewideplanningprocesses.

Thepreviousplanningeffortsdonotsuggestintensedisagreementoverthebenefitofimprovingthecorridor,andthislackofdisagreementprovidesanimportantcontextforbetterunderstandinghowthesechallenges—theneedforlocalsupport,thecorridorhavingmultiplepurposes,andfundinglimits—underscorewhatnowappearstobeanoverarchingneedforgettingaprojectunstuck:solutionspecificity.Thatis,asummaryofstudiesoftheRoute29CorridordevelopedbyAECOM(2016)underscorestheneedforspecificsolutionstogetaprojectunstuck.Forexample,inanevaluationofthe2009Route29CorridorStudy,AECOMnotesthatastrengthofthestudyisthatitsrecommendationtocloseandconsolidatecrossoverscanhelpenact“accessmanagementprinciples”andimprovesafety.However,AECOM(2016)alsonotedthataweaknessofthestudywasthatsomecrossoversprovided“essentialaccess”totripgeneratorsinthecorridor,necessitatingamoredetailedevaluationofeachparticularcrossovertodetermineitsimpactoncrashriskandlocalaccess.ItisthisneedforspecificsolutionsthatPlanWorkssoughttoaddress.

3

ProductImplementation

Theprojectteam(CampbellCounty,Region2000,VDOTLynchburgDistrict,UVA’sInstituteforEnvironmentalNegotiation,AECOM,FHWAVirginiaDivision,andVTRC)appliedthePlanWorkscorridorplanningprocesstodevelopcorridorpreservationandaccessmanagementprojectsthatcanbefundedthroughavarietyofmechanisms.

CorridorPlanningDecisionGuideThedecisionguideinfluencedthemannerinwhichtaskswereundertaken.Table1showsthedecisionsthatresultedfromtheapplicationofeachPlanWorksmoduleandactionstakentoachieveeachdecision.

Forexample,considerCOR‐1,wherethePlanWorksdecisionpointistoagreeonthescopeoftheplanningprocess.Forthatparticularmodule,twooutcomeswereparticularlyrelevantasshowninthemiddlecolumnofTable1:membersofthepublicshouldbeabletodirectlyinfluencetheprocess(whichledtonotusingatechnicaladvisorycommitteebutratherhavingmultiplepublicmeetings)andtheprocessshouldfocusonshortertermprojectsthatcanbeimplemented,asfundsforlarge‐scalecapacityexpansionprojects,suchasabypass,arenotavailable.TherightcolumnofTable1showstheactionstakentoimplementCOR‐1,whichincludedaDecember2015meetingwithtwosupervisors(inwhosedistrictsthecorridorexists)andasubsequentJanuary2016meetingwheremembersofthepublicwereintroducedtothecorridorplanningprocess(seeFigure1).

Theteam’sexperiencewithapplyingthedecisionguidewasthatseveralofthemodulesareiterative.GenerallytheteamfoundthatCOR‐1andCOR‐2(scope,problemstatements,andopportunities)couldbeperformedintandem,thatCOR‐3throughCOR‐5(goalsandperformancemeasures)neededtobeperformedmultipletimessuchthattheresultsofCOR‐5[measures]modifiedCOR‐3[goals],andthatCOR‐7throughCOR‐9(blendedsolutionsetandprioritizationofprojects)neededtobeperformedintandem.Inparticular,COR‐6requiressubstantialeffortasastand‐aloneitemasitisthefirstinstancewhereattendeesbegintoseeadirectoutcomeoftheirparticipation.

Figure1.Attendeeslistentopresentations(left)andoffersolutions(middle);corridormap(right)

ImplementationSummary

DecisionGuide:Whileall9COR‐moduleswereused,keydecisionpointsincludedCOR‐2,COR‐3,COR‐5,COR‐7,andCOR‐9.

Assessments:(Forthegeneralpublic),asingleassessmentwasconductedbasedonquestionsfrompartnercollaborationandstakeholdercollaboration.

Application:IncorporatingReliabilityPerformanceMeasuresintotheTransportationPlanningandProgrammingProcesses.Library:SHRP2’sIncorporatingTravelTimeReliabilityintotheHCMandPerformanceMeasurementFrameworkforHighwayCapacityDecision‐Making.

4

Table1.SummaryofDecisionPointsfromthePlanWorksCorridorPlanningProcessCOR DecisionsResultingfromApplicationofPlanWorks Actions1 ApproveScopeofCorridorPlanningProcess

Everylandownerneedstobeinvitedtoeverymeeting.

Avoidatechnicaladvisorycommittee—rather,letparticipantsdirectlyinfluencetheprocess.

ThegeographicalscopeoftheplanningprocessistheRoute29CorridorwithinCampbellCountyfromtheCityofLynchburg(Route29/640interchange)toRoute24(theMPOboundary),andthefocusisonprojectsthatcanbeimplementedfairlysoon.

MetwithCampbellCountyBOSmembersandDirectorofEconomicDevelopment(December2016).

FirstpublicmeetingJanuary2016(42participantsand71commentsshownontheWebsite.)

Specificdeficienciesandopportunitiesareidentifiedatthepublicmeetingwhereattendeesaregivenlarge(6footby6foot)mapsofthecorridorandaskedtodrawcommentsdirectlyonthemaps.

DeficienciesarecategorizedbygoalandmadeavailabletothepublicviaaninteractiveGIS‐basedwebsite.Forexample,publiccomment37statesthata60mphspeedlimitis“murderous”ataparticularlocation.(Thewebsiteismosteasilyfoundbysearchingfor“Route29CorridorAssessment,CampbellCounty.”)

2 ApproveProblemStatementsandOpportunities Deficienciesincludecongestion,safety,andespeciallya

cumbersomedevelopmentreviewprocess. Opportunitiesincludesimplifyingthelanddevelopment

reviewprocess,improvingtransportationoperationsinthiscorridor,andeducatingthepubliconhowthecorridoroverlaydistrictapplies.

3 ApproveGoalsoftheCorridor Fourgoalsareinitiallyestablishedrelatingtosafety,

effectiveness,theenvironment,andtransportation/landusecoordination.

Additionalstakeholdersareinterviewedsuchasresidentialpropertyowners,largeemployers,aregionalairport,transitprovider,andahomeownersassociationrepresentative.

Basedontheinterviewsandpubliccomments,4goals

forthecorridorareestablished—andthenmatchedtospecificperformancemeasures,suchthatatotalof23performancemeasuresareidentified.

Dataforperformancemeasuresaredetermined.

4

ReachConsensusonScope Tentativeperformancemeasuresareproposedforeach

goal.Forexample,landusecoordinationcanberelatedtointersectiondelaybasedon2040projectedvolumes.

5 Approveevaluationcriteria,methods,andmeasures Numberofgoalsisreducedfrom4to3,andnumberof

performancemeasuresisreducedfrom23to13. Twopromisingwaysofdeterminingreliabilityare

observed:traveltimereliabilityindex[TTRI](forrecurringcongestion)andcrashrisk(fornon‐recurringcongestion)

AttendeesidentifyspecificsolutionsatsecondpublicmeetinginJune2016(53comments).

Stakeholderassessmentshowsthatmoreeffort

needstobedevotedtoexplainingtheprocessatfuturemeetings;henceflowchartisdeveloped.

Thetraveltimereliabilityindex(TTRI)inthecorridorisdetermined.

6 Approverangeofsolutionsets Fourcandidatesolutionsetsareidentified,whereeach

solutionsetidentifiesmultipleprojects.Eachsolutionsethasaparticulartheme:capacity,safety,economicdevelopment,andalternativemodessupportedbytechnology.

Numberofperformancemeasuresisreducedfrom13to

4.Year2040conditionsareused.TTRI,notcrashriskalone,ischosentomeasureimpactsonreliability.

Internaldiscussionssuggestthatadditionalconstraintsonhowlandisdevelopedwouldlikelygenerateoppositiontothisproject,thusnomodificationismadetotheTransportationCorridorOverlayDistrict.

Candidatesolutionsetsarepresentedatathird

publicmeetinginOctober2016(56comments).Attendeesbreakintosmallgroups;eachtablehasateammemberpresentwhocananswerquestions.

5

COR DecisionsResultingfromApplicationofPlanWorks Actions7 Adoptpreferredsolutionset

Blendedsolutionsetincludesroughly$19.43millionin

proposedprojects.Elementsaddresssafety(e.g.,rightinrightouts),capacity(e.g.,closingthemedian),businessaccess(e.g.,two‐wayleftturnlane)andmultiplemodes(e.g.,sharedbicycle/pedestrianpath)

Costsforeachprojectelementsintheblendedsetareestimated.

Performancemeasuresarecomputedforeachsolutionset,whereperformancemeasuresareEquivalentPropertyDamageOnly(EPDO)offatalandinjurycrashesexpectedtobereduced,mainlinedelay(2040conditions),TravelTimeReliabilityIndex,andmovementdelay(2040conditions).

Atthesamepublicmeeting,stakeholdersareasked

“whichelementscauseaconcern?Whichelementswouldyousupport?”

8 Approvecriteriaforprioritizationofprojects

Criteriaare:(1)costin2016dollars;(2)EPDOoffatalandinjurycrashesreduced;(3)impactonthetraveltimereliabilityindexascomputedfromSmartScale;(4)mainlinedelay;and(5)intersectiondelaybasedon2040conditions.

AllprojectswillbepursuedprovidedsupportremainsasperCOR‐9,recognizingthatsomefundingsources(e.g.,theHighwaySafetyImprovementProgram[HSIP])mayleadtoconstructionsoonerthanotherfundingsources(e.g.,thelongrangeplanningprocess).

Detailsofprojectsareidentifiedattheplanninglevelsuchascost,location,numberofsites,andwherepossible,criteriausedbyfundingsourcestoevaluateprojects.DatabaseprovidedbyAECOMcanbeusedasastartingpointtoprepareprojectsforsubmission.

Example:theprojectsfromthiscorridorwill

competewithotherprojectsthroughoutVirginiaforfundsmadeavailableunder“SmartScale.”OnesuchcriterionisaVirginia‐specificformulathatisusedtoestimatehowimprovementswillaffectthetraveltimereliabilityindex.AnothercriterionistheEPDOofcrashesreduced.Thesecriteriaarecomputedforeachproject.

DraftmemorandumpreparedfortheCountytouseasabasisforpresentingtheseprojectstotheBoardofSupervisors.

ProjectteammembersagreethattheCampbellCountyComprehensivePlanwillbeupdatedbasedontheresultsofthisstudy.

9 Adoptprioritiesforimplementationa PendingtheresultofapresentationbytheCampbell

CountyDirectorofEconomicDevelopmenttotheCountyBoardofSupervisors,theelementsoftheblendedsolutionsetwillbepursuedthroughthreedistinctfundingsources:Virginia’sSmartScale,thedevelopmentoftheMPOConstrainedLongRangePlan,andtheHighwaySafetyImprovementProgram.

aThisreportisbasedoninformationcurrentasofFebruary2017.ItispossiblethatastheprojectsgiveninTable3andshowninAppendixCmovethroughthetransportationprogrammingprocess,theywillberevised

CorridorPlanningAssessmentsTheteamsolicitedquestionsfromtwoPlanWorksAssessments(PartnerCollaborationandStakeholderCollaboration).Themostpressingareaiswhethermembersofthepubliccouldfollowtheplanningprocessforthiscorridor.Additionally,theassessmentquestionscouldhelpgarnerparticipantagreementonthegoals,criteria,andperformancemeasures—thatis,towhatextentdoesthematerialinPlanWorksCOR‐5,asimplementedbytheprojectteam,resonatewithattendees?TheteammodifiedthewordingofthesequestionstomakethemsuitableforthespecificaudienceandthecontextofCampbellCounty.Forexample,wechangedthePlanWorks“Neutral”categoryto“NeitherAgreenorDisagree.”Asanotherexample,wechanged“Ihavebeenabletoengagewithothersofsimilarinterestthroughouttheprocess”towhatisshownasthelastquestioninTable2:“Atthismeeting,Ihavebeenabletosharemyviewswithothers.”

6

Table2.ResultofthePlanWorksStakeholderAssessment(June2016)

SurveyQuestion(1=StronglyDisagree,2=Disagree,3=Neutral,4=Agree,5=StronglyAgree) Score

Thedecision‐makingprocessisclear 2.9

Theprojectgoalsareclearlystated. 3.0Theprojectgoals(topromoteasafe,efficienttransportationsystemcompatiblewithexistingandfuturelanduses)reflectmypersonalgoalsforthecorridor. 3.1

Theperformancemeasures(forexample,crashespermileonthecorridor)directlyrelatetothegoals. 3.0

Myinputhasbeenincorporatedintotheprojectperformancemeasures. 3.0

Atthismeeting,Ihavebeenabletosharemyviewswithothers. 3.3

Thelowscoreforclarityofthedecision‐makingprocesssuggestedthatatthenextpublicmeetingattendeesshouldbeprovidedwithasinglepagehandoutthatcontainstwopiecesofinformation.(Inretrospect,thisscorewasnotsurprisinggiventhatsomestakeholdersatthesecondpublicmeetingindicatedtheyhadmissedthefirstpublicmeeting.)Thefrontofthehandoutshouldsummarizetheprocessusedtogeneratecandidatesolutions—e.g.,establishmentofgoals,performancemeasures,andcandidatesolutionsbasedonlimitedfunds.Thebackofthehandoutshouldsummarizeafewexamplesofhowpublicinputwasincorporateddirectlyintothesolutions.Thathandout(Figure2)wasusedatthethirdpublicmeeting.

Figure2.PlanWorksHandoutDevelopedinResponsetotheStakeholderAssessment

7

Applications

IntegrationofotherSHRP2ProductsandFHWAInitiatives

TheSHRP2reporttitledIncorporatingTravel

TimeReliabilityintotheHCMwasactivelyusedforthiseffort.Findingsfromthatreport,asappliedtothiscorridor,are:

Thebufferindexisonepromisingwayofassessingreliability.

Forexample,foramotoristtravelingtoworktoavoidarrivinglate90percentofthetime(thatisduringallbuttheworstpeakperiodtravelinagivenmonth),theestimatedplanningtimeindexindicatedthat,whentravelingnorthboundinthemorningpeakhourorsouthboundintheeveningpeakhour,theexpectedtraveltimeshouldbeincreasedbyafactorof1.4overthefree‐flowtraveltime(e.g.,usingthespeedlimit.)

Anotherinterpretationofthe90thpercentilevalueintheplanningtimeindexisthatassumingapproximately20workingdayspermonth,the1.4multipliershouldbeusedbycommuterswhocannotaffordtobelatemorethantwiceamonth.

Further,thebufferindex(90thpercentile)showsthat,ifacommutercannotaffordtobelatetoworkmorethantwicepermonth,heorsheshouldpresumethathisorhermediandailycommutetimewillneedtoincreasebyroughly25%andadjusthisorherdeparturetimeaccordingly.Acharacteristicofthesetwoindicesisthattheycanbedominatedbyrecurringcongestion.

Theaforementionedreportisaccessibleat:http://onlinepubs.trb.org/onlinepubs/shrp2/SHRP2_S2‐L08‐RW‐1.pdf)

Figure3.PlanningTimeIndex,TravelTimeIndex,andBufferIndexfortheCorridor.Theplanningtimeindexisthe90thpercentiletraveltimedividedbythefreeflowtraveltime.

Figure4.First‐timeattendeesatthesecondpublicmeetingtalkwiththefacilitatortounderstandtheprocessbeingusedinthecorridor,whichledtothedevelopmentoftheflowchart(Figure2)forthethirdpublicmeeting.

8

TheconceptsintheGuidetoIncorporatingReliabilityPerformanceMeasuresintotheTransportationPlanningandProgrammingProcesseswereusedtoconsiderreliabilityininthedevelopmentoftheneedfortheproject.TeammemberswerepreviouslyawareoftheseconceptssowedidnothavetousePlanWorkstolearnthemforthefirsttime,buttheyareusefulasareferencewhendetailsofhowthevariousindices,suchasplanningtimeindexandthebufferindex,areneeded.

Forexample,wefoundforthiscorridorthatthemiseryindex,asitsnameimplies,indicatesthetraveltimewhencongestionisworst.BasedonadifferentdatasetthanthatshowninFigure3(alldays,notjustweekdays,fortheperiodfromOctober1,2014throughSeptember30,2015),thisindexistheaverageoftheslowest5%ofalltraveltimesdividedbythetraveltimeatthespeedlimit.Whenappliedtotheentirecorridorandtotheeveningrushhour(4‐7pm),themiseryindexis1.57(northbound)and1.67(southbound).Alooseinterpretationis:aboutoneworkdaypermonth,whentrafficisunusuallybad,oneshouldassumethatcommutingtimewillbe57%(northbound)or67%(southbound)longerthanitwouldifonecouldtravelatthespeedlimit.Ultimately,however,wefocusedonthetraveltimereliabilityindex(seeFigure3)givenitsrelationshiptofundingsources.LibraryThePlanWorksLibraryshowshowothershavedemonstratedtrade‐offsassociatedwithaccessmanagementstandards.Forexample,thelibraryshowsonecase(NJRoute31IntegratedLandUseandTransportationPlan)whichappearstoevaluatethetradeoffbetweenaccessandmobility.Ultimately,theteamfoundthatonewaytomakethistradeoffwastoprovidetwosetsofperformancemeasures:oneforthroughdelayinthecorridor(suchasthroughtraveltime)andoneforaccessdelay(suchasturningleftintobusinesses.)Bothperformancemeasuresassessdelay,buttheformerisformobilityandthelatterisforlocalaccess.Oneinnovationthattheteamusedwastoincludetheinvolvementofprofessionalfacilitators(inthiscase,theUniversityofVirginiaInstituteforEnvironmentalNegotiation).Theprofessionalfacilitators’costwasapproximately$40,000forthedurationofthe14montheffort.Majorcontributionsincludedstakeholderinterviews(e.g.,truckingfirmsinCOR‐3/4),engagementwiththepublicatthreepublicmeetings(bothtosolicitcommentsandhelppresentinformationinaone‐on‐oneenvironmentwithindividualswhohadquestions),andorganizationofselectcorridorplanningmeetingsinvolvingstakeholders.Forexample,thefacilitatorplayedanactiveroleinelicitingpublicopinionthroughtheapplicationofCOR‐3throughfourmajorsteps:

1. HoldapublicmeetingatwhichasurveywasdistributedtoobtainearlyfeedbackforCOR‐1andCOR‐2.

2. Identifycandidateintervieweesinboththepublicandprivatesector.

3. DevelopquestionsforinterviewsofpartnersandadvisorsbasedonCOR‐3.and

4. Conductinterviewswithstakeholders.

Forexample,onepolicyquestionfromCOR‐3is“Aretheredifferencesorconflictsamongthestakeholderinterests?”Accordingly,differentstakeholderswereaskedhowtheywould“definesuccessforthisparticularsection”ofthecorridor.AsshownintheCampbellCountyRoute29PlanningEffortFindingsReport,anexampleofthesediverseresultsisthedifferentattitudestowardabypass:somestakeholdersarehopefulforabypass,althoughconcernsaboutabypassadverselyaffectinglocalbusinessesarealsonoted.TheCampbellCountyRoute29PlanningEffortFindingsReportalsoshowshowdifferenttrippurposesareconsidered.Forinstance,thedifficultyofmakingturnsoccursatseverallocations:LibertyMountainDrive(purposeistoaccessamajoremployer[LibertyUniversity]),CalohanRoad(purposeistoaccessaregionallandfill),andthevicinityofEnglishTavernRoad(purposesaretoaccessresidences[mobilehomeparks]andaplaceofworship[HylandHeights

9

BaptistChurch]).Thereportalsoexemplifiedthediversepurposesofthecorridor:forcongestion,individualsexpresslynotedthattheydidnotwanttoseespeedsdeterioratefurthersuchthattheareasuffereddelayscomparabletomoreurbanizedareasoftheCommonwealth.Safetyissuesarearguablyparamount:somecommentsdirectlyrelatetoincreasedtrafficvolumes(i.e.,onefirmhasadoptedapolicythattrucksmaynotchangelanes),andsomeconcernsaredrivenalsobygeometricconsiderations(i.e.,locationofcrossoversandneededturninglanestoseparateflows).Economicdevelopmentisviewedbothasbothdesirableandasituationthatmustbemitigated,withquestionsabouttheabilityoftheregiontoaccommodategrowthintraveldemand.

StakeholderCollaboration

ThisuseofPlanWorksinVirginiahasalwaysbeendescribedasamulti‐agencyeffortinvolvingCampbellCounty,Region2000whichstaffstheCentralVirginiaMPO,theVDOTLynchburgDistrict,FHWA’sVirginiaDivision,theUniversityofVirginiaInstituteforEnvironmentalNegotiation,AECOM,andtheVirginiaTransportationResearchCouncil.Thecollaborationamongstakeholdersfundamentallydrovetheprojectinseveralkeyways.

COR‐1askshowstakeholderswillbeinvolved.ThisexactquestionaroseinaDecember2015briefingwiththeCounty’sEconomicDevelopmentDirectorandalocalsupervisorwithauthorityoverthecorridor.Theresultwasthatalllandownersadjacenttothecorridorneededtohaveeveryopportunitytoinfluencetheprocess,whichdrovethedecisiontonotconveneasmallertechnicaladvisorygroupbutrathertoallowallinterestedindividualstoparticipateinthedevelopmentofsolutions.

COR‐2asksforagreementondeficienciesandopportunities,andalthoughthecorridorisastateDOTfacility,itwasthecounty’sdesirethat“althoughnoteveryonewillgeteverythingtheywant,wewantallvoicestobeheard”whichcontributedtoanactivepublicinvolvementprocessofgettingstakeholderagreementondeficienciesinthecorridor.

COR‐3andCOR‐4askforgoals,stakeholdercomments,objectives,andperformancemeasures.CollaborationwithprofessionalfacilitatorsledtothedevelopmentofaCampbellCountyRoute29PlanningEffortFindingsReportwherethosefacilitatorsinterviewedadditionalstakeholdersina

one‐oneoneformat(beyondthosewhocametothepublicmeeting)suchaspropertyowners,largeemployers,aregionalairport,transitprovider,andahomeownersassociationrepresentative.ThiswasfollowedbytheaforementionedAECOMmemorandumwhichcapturedtheresults—andnecessarymodifications—basedonpreviousstudies(andhencepreviousstakeholders).

COR‐6asksforthedevelopmentofsolutionsets,whichwasinspiredbymembersofthepublicwhoidentifiedvarioussolutionsatthesecondpublicmeeting.(Figure5showsanexampleofthe54commentsreceivedatthatmeeting).

Figure5.ExampleofSolutionsIdentifiedattheSecondPublicMeeting

COR‐8andCOR‐9requiretheprioritizationofprojects.ThisprioritizationinvolvedcollaborationbetweentheMPO,theCounty,andVDOT—andwasbuiltonhowprojectswerepreparedforrequirementsofcandidatefundingsourcesbyAECOM.(Anexampleisthecomputationsforhowthetraveltimereliabilityindexiscomputedformedianclosures.)

COR‐6andCOR‐9entailcompromise.Forexample,duringCOR‐6,thesecondpublicmeetinggeneratedcomplaintsofspeeding,and

10

COR‐7initiallyreducedspeedlimitsdramatically—insomeplacesto35mph.CommentsreceivedatthethirdpublicmeetingduringCOR‐7opposedanysuchreductions,leadingtothecompromiseinTable3.

KeyOutcomes

KeyoutcomesareobservedforboththisparticularprojectandfortheuseofPlanWorksgenerally.

Forthisparticularproject,roughly$19.43millioninimprovementshavebeenidentifiedatspecificlocationsinthecorridorasshowninTable3.

Table3.SummaryofBlendedSolutionSet

SolutionImprovement(NumberofSites)Cost in$millions

Closure/modificationofmedians(12) $0.27Lengthenleftturnlanestorage&taper(13) $1.30Installleftturnlane(8) $1.80Lengthenrightturnlanestorage&taper(5) $0.50Installrightturnlane(6) $1.35Varioussignalimprovements(1) $0.001Accessmodification(4) $1.50Installr‐cutmedianaccesspoints(3) $3.75Sidewalks(1) $2.75Sharedusepath(1) $6.20Speedlimitreduction(2)to55/45mph Minor

TherecommendationsforthisparticularprojectwillbepresentedtotheCampbellCountyBoardofSupervisorsbytheCampbellCountyDirectorofCommunityDevelopment.

BecausetwoBOSmemberswhosedistrictsincludethecorridorhavebeeninvolvedintheprocessandbecausethreepublicmeetingshavehelpedkeepcitizensinformed,therewillbestronginterestinthecommunity’sreactionasdocumentedbythepublicinvolvementprocessassociatedwithPlanWorks.Then,followingthemeetingwiththecounty,recommendationsforprojectsshowninthetop10rowsinTable3wouldbemovedintoapplicationsforvariousfundingsources,notablytheHighwaySafetyImprovementProgram(HSIP)andVirginia’sSmartScale.

ForthelastprojectinTable3(reducingspeedlimitsto55mphsouthofCalohanRoadand45mphnorthofCalohanRoad),iftheBOSmembersaresupportive,thenthenextstepwouldbeforVDOTTrafficEngineeringstafftoconductaspeedlimitstudyatthoselocations.

Anobservationthatisneitherpositivenornegativebutsimplyuniquetothecorridorplanningprocessisthatthetypesofprojectsthatarefeasiblefromafundingperspectivemustbeconsideredearlyintheprocess.Thatis,whenimplementingPlanWorks,onemusthaveanideaofthemethodsforprioritization(COR‐9)atthetimethatcandidatesolutionsetsaredeveloped(COR‐6).

PlanWorkscanpotentiallyserveasaresourceforperformingcorridorplanning,especiallycorridorpreservation.Thepassageof“SmartScale”inVirginiahasfundamentallyalteredthetransportationprogrammingprocesssuchthatprojectshavetoscorewellincertainperformancemeasuresinordertobefunded.Akeyimplicationisthatcorridorplansmustleadtoshort‐term,implementablesolutionsiftheyaretobeused,atleastinVirginia’scurrentfiscalenvironment.ThefactthatPlanWorkswashelpfulforensuringwekeptthecorridorplanningprocesstangiblehasbeensharedwithseveralentities(includingoneMPOthatwantedadditionalinformationonhowPlanWorksusedprofessionalfacilitators).

LessonsLearned

PlanWorksemphasizes“goingslowtogofast.”Asubstantialamountoftimeintheearlymodulesisspentgeneratingup‐frontagreement,whichbuildssupportfordevelopingsolutionsinthelaterCORmodules.

PlanWorksemphasizesperformance‐basedplanning.Thedecisionpointsteerstransportationpractitionerstomatchsolutions(inCOR‐7)totheperformancemeasures(COR‐5),whicharebasedongoals(COR‐1.)Thisencouragescreativity;forexample,it

11

encouragesonetoask“howmightwemeasureaproject’simpactoneconomicdevelopment?”

PlanWorksshouldbeappliedinaniterativefashion.Forexample,inorderforatransportationagencytodevelopfeasibleprojectsbasedonacorridorplanningprocess,thecriteriaforschedulingandprioritizinginvestments(COR‐9)mustbeexplicitlyconsideredintheselectionofthepreferredsolutionset(inCOR‐7).

Itmaybemoreproductivetoconductstakeholderassessmentsinthemiddleofcorridorplanningratherthanatthebeginning.Somestakeholdersmaynotevenattendtheinitialmeeting.Aseachcorridorprocessisunique,thevalueoftheassessmentistoask“whatneedsimprovement”—whichcanbeaskedonceparticipantsbetterunderstandhowtheplanningprocessmightunfold.

OftenPlanWorkspolicyquestionsmustbeshortenedforanin‐personmeetingwithstakeholders.Thequestionsareusefulasaninitialbrainstormingexercise,butwhenposingthequestionstostakeholdersormembersofthepublic,multi‐partquestionswillneedtobeabbreviated—partlybecausesomestakeholdersmaynotknowtransportationplanningdetails,andpartlytoenableaconversation.Forexample,onecanreplace“Areperformancemeasures,evaluationcriteriaandmethodologyforassessingbicycleandpedestriannetworkconnectivity,accessibility(tojobs,schools,essentialservices,recreation,etc.),equity,andsafetyincorporatedintotheprojectprioritizationprocess?”with“Whatfactorsinfluenceprioritization.”Then,additionalprobingquestionscanbeaskedofrespondents,asotherdescriptorsbesides“networkconnectivity”maybepreferable.

NextSteps

ForPlanWorksgenerally,theteamhasalreadymadefourpresentationsregardinghowPlanWorkscansupportcorridorplanning,especiallybetteraccessmanagement:

o ApresentationatVDOT’sTransportationandLandUseForumdescribingPlanWorksasacorridor

planningtoolforsupportingregionalandruralstrategies(June2,2017)

o ApresentationattheVirginiaAnnualPlanningandProgrammingMeetingregardinghowPlanWorkscansupporttheprogrammingprocessbasedoncorridorplanning(February1,2017).

o ApresentationtotheVDOTCorridorPreservationGroupandVDOTstafffromtheSalemandLynchburgVDOTconstructiondistrictsregardinghowPlanWorkscanencouragebetteraccessmanagement(February3,2017).

o AwebinarpresentedtoCaltransregardingthedetailsofhowPlanWorkscanbeimplementedusingthenineCORmodules(February15,2017).

ForPlanWorksgenerally,theteamwillcontinuetosharewithinterestedpartiesdetailsofhowtousePlanWorkscorridorplanning.

o Forexample,stafffromanotherVirginiaMPOmetwithafewteammembersinDecember2016todiscussrecommendationsforfuturePlanWorksapplications(AppendixAofthisreport)andhowPlanWorkswasappliedforthisparticularcorridor(seeAppendixB).

o SeveralmembersoftheteamhaveproducedvideotestimonialsofthestrengthsandweaknessesofusingPlanWorksasrequestedbyFHWA.

ForthisprojectandotherVDOTprojectsinparticular

o VDOTiscontinuingtouseprofessionalfacilitatorsonotherprojects,basedontheexperienceofthisuseofPlanWorksandarelated(separate)researcheffortregardingcollaborationandconsensusbuilding(OhlmsandRoy,2016).

o ForRoute29,adatabasehasbeendevelopedthatshowshowtheblendedsolutionsetinTable3scoresagainstsomeoftheSmartScaleprogrammingcriteria.Thisdatabase,alongwiththe

12

recordofpublicinputgiveninthisreportwill(iftheCountyBOSconcurs)serveasastartingpointtoimplement

theprojectsshowninTable3.ThespecificprojectsareshowninAppendixCofthisreport.

For More Information

Contacts Resources AmyO’Leary,VDOTAssociateDirectorVirginiaTransportationResearchCouncil434‐293‐1995,[email protected],VDOTTransportationPlanningDirectorVDOTLynchburgDistrict434‐856‐8331,[email protected],FHWAPlanning/EnvironmentalSpecialist202‐366‐9206,[email protected]

Route29CorridorAssessment,CampbellCounty.http://www.virginiadot.org/projects/lynchburg/route_29__corridor.asp

UsingPlanWorkstoSupportTransportationProgramming:theCampbellCountyExperience,http://www.virginiadot.org/projects/resources/SYIP/2016/fall/Plan_Works.pdf

UsingPlanWorkstoSupportCorridorPlanning(TheFebruary15,2017webinarwillbepostedathttp://smartmobilityca.org/webinars/)

ReferencesCitedintheReport

AECOM.Memorandum(forTasks1,2,and3).July8,2016.

FHWA.NationalHighwayConstructionCostIndex(NHCCI),Washington,D.C.,2016.https://www.fhwa.dot.gov/policyinformation/nhcci/pt1.cfm.

FHWA.PriceTrendsforFederal‐AidHighwayConstruction‐FourthQuarter2003,Washington,D.C.,2015.https://www.fhwa.dot.gov/programadmin/pt2003q4.cfm.

Ohlms,P.B.andRoy,K.M.WhenMainStreetIsaHighway:AddressingConflictsBetweenLandUseandTransportation,VTRC,2016.http://www.virginiadot.org/vtrc/main/online_reports/pdf/17‐r13.pdf

UniversityofVirginiaInstituteforEnvironmentalNegotiation.CampbellCountyRoute29PlanningEffortFindingsReport,2016.http://www.virginiadot.org/projects/resources/Lynchburg/Rt_29_Campbell_Co_Corridor_Assessment/Findings_Summary.pdf

VirginiaDepartmentofTransportation.PhasesIIandIII,Route29CorridorStudy,TechnicalReport,Richmond,2003.http://www.virginiadot.org/projects/lynchburg/phases_ii_and_iii,_route_29_corridor_study.asp.

VirginiaDepartmentofTransportation.AddendumtotheRoute29CorridorStudy,Richmond,2011.http://www.virginiadot.org/projects/resources/Culpeper/Route_29/Addendum‐Route_29_Corridor_Study1.pdf

TeamMembers

AECOM(BillCashman,ChrisLawrence,ShelleyBogue),CampbellCounty(PaulHarvey),FHWAVirginiaDivision(ChengYan),Region2000LocalGovernmentCouncil/CentralVirginiaMPO(BobWhite),UniversityofVirginiaInstituteforEnvironmentalNegotiation(JudieTalbot,TanyaDenckla‐Cobb,LeahBrumfeld),VDOTLynchburgDistrict(RickYoungblood,DavidCook),VirginiaTransportationResearchCouncil(AmyO'LearyandJohnMiller)

13

AppendixA.SummaryofRecommendationsforFutureUsesofPlanWorks

AppendixAshowsrecommendationsforpersonswhowillusethecorridorplanningelementofPlanWorksinthefuture,basedontheexperienceofusingPlanWorksinCampbellCounty.ForconsistencywithPlanWorks,the15recommendationsareorganizedbyeachofthenineCORsteps,withtherecommendationsforusingthestakeholderassessmentpresentedlast.Thatsaid,thesomewhatnon‐linearnatureoftheplanningprocessmeansthatsomerecommendationsmayapplytootherstepsasfollows:COR‐1andCOR‐2maybeappliedsimultaneously(thus,recommendationsfromeachCOR‐1mayberelevanttoCOR‐2andvice‐versa);COR‐3,COR‐4,andCOR‐5maybeappliediteratively;andCOR‐7,COR‐8,andCOR‐9mayalsobeappliediteratively.COR‐1:ScopeoftheCorridorPlanningProcess

1. WhenusingPlanWorks,focusfirstontheoutcomeintheOverviewsectionofCOR‐1.

ThedetailinPlanWorksisquitehelpfulbutcaninitiallybedaunting;forexample,the44policyquestionsinCOR‐1helponeconsiderthebreadthoftheplanningprocessbutcanalsoleaveoneconfusedregardingwhichquestionsshouldbeposedfirst.Itwashelpfultoexamineeachdesiredoutcomeandthenworkbackwardsfromtheoutcometospecificquestions.Forinstance,theoutcomeofCOR‐1(aclearlydefinedscopetoguidethecorridorplanningprocess)helpedtheteamrealizetheimportanceofencouragingcompromiseinthecorridor,betweenlocalaccessandthroughmovements.Then,withthatoutcomeinmind,theteamcouldstudythesamplequestionsingreaterdetail.

2. Orderthepolicyquestionssuchthateasierquestionsprecedeharderones.

Ininteractionswiththegeneralpublic,itwaseasiertogetinputwhenstartingwithquestionsthatattendeescouldimmediatelyaddress,regardlessoftheirknowledgeofthecorridor.(Forexample,whilesomeindividualswerereadytoprovidedesignsolutions,otherswhohadcomelatetothefirstpublicmeetingwerenotimmediatelycertainwhattheywerebeingaskedtodo.)Accordingly,oneshouldaskeasierquestionsinitially(e.g.,whatstakeholderslikeordonotlikeaboutthecorridor),withthehardestquestions,suchas“Howcanthecorridorbestservethelongertermneedsofthecounty/theregionforthenext20years?”beingposedlater.Forexample,thisordermightbeasfollows:

Easyquestionsdesignedtointroducerespondentstotheprocess

Inwhatwaysdoyouusethispartofthecorridor? Whataresomeofthekeyfunctionsandrolesofthecorridor–nowandinthefuture? Whatdoyoulikeaboutwhatcurrentlyexists?(Usebluestickynotestodescribethisandputitonthe

map.) Whatdon’tyoulikeaboutwhatcurrentlyexists?(Usepinkstickynotestodescribethisandputon

map.)

Harderquestionsdesignedtoelicitlongertermideas

Howcanthiscorridorbestservethelonger‐termneedsofCampbellCounty,forthenext20years? Howcanthecorridorbestservethelong‐termsneedsofthelargerregion,forthenext20years?

QuestionDesignedtoElicitSpecificSolutions

Whatspecificideaswouldyouliketobeconsideredinthedevelopmentofthiscorridor?

14

COR‐2:ApproveProblemStatementsandOpportunities

3. ThequestionsinCOR‐2areagoodstartingpointforbrainstorming.Ratherthanposingallofthestakeholderquestions,teamsmaywishtouseasmallersubset,withlongerormorecomplexquestionsbrokenintosmallerones

Forexample,considerthestakeholderquestionfromCOR‐2“Whatisimportanttoyou,toyourneighborhood,tothelocalarea,totheregion(transportation,community,environment)inthecorridor?”Theintentofthequestionisappropriatebecauseitillustrateshowdifferentrespondentsmayhavedifferentusesforacorridor.However,thequestionincludesmultiplesub‐questions—whichcangenerateconfusioninapublicmeeting.Accordingly,itwasmoreappropriatefortheteamtofirstaskjustfromthepointofviewoftheattendee,withthe“largerregion”beingaseparateconcept.

4. Providephysicalmapsforattendees’reference.

Useoftwo‐partlarge‐scaleaerialmaps(6feetby6feet)showntotherightofFigure1inthebodyofthisreportprovidedaperspectivethatwasnotimmediatelyapparentfromexaminationofthematerialontheweb:attendeescouldpointoutparcels(whichweredelineated)andgeometryinhigherdetail.Forexample,theimportanceoftheLynchburgAirport—itssizedominatesmuchofthefrontagesectionofRoute29—becomesclearerwhenonecanseetheairportonaphysicalmap(asopposedtoasmallercomputerscreen).

COR‐3:ApproveGoalsfortheCorridor5. Considerintegratingthefactorsrelatingtocontextsensitivesolutions(CSS)directlyintothescopeofthe

corridoranalysisratherthanasseparate,stand‐alonegoals.Forsomecorridors,itwillbemoreproductivenottoapplythisrecommendationbutinsteadtohavespecific,measurableobjectivesrelatedexclusivelytoCSS.ItappearsthattheMinnesota“CompleteStreets”Plan(see“HowdoesPlanWorksworkintherealworld?”)mayhavefollowedthisapproachforCSS,andareviewofthePlanWorksexampleforCOR‐3showedthatforarelatedtopic(environmentaljustice)aspecificgoalofoutreachtotheSpanish‐speakingcommunityfortheAsheboroBypassledtobothgreatercommunityparticipationandtheadditionofabridgethatleftakeycommunityintact.Insuchinstances,aseparatelineitemmeasuringprogresstowardCSSorenvironmentaljusticeisappropriate.However,forthisparticularstudy,theteamfoundithelpfultoviewCSSasemphasizingaccommodationofallmodesoftransportation—apointthathadbeennotedthroughoutmeetingswithelectedofficialsandthecommunitysincetheproject’sinception.Accordingly,ratherthanhavingaseparatelineitemforCSS,theprojectteamensuredthattheapplicationofthegoalsinthecounty’stransportationplan(e.g.,improvesafetyandaccommodatefuturelanduses)couldbeappliedtoalltransportationmodesthatused,orsoughttouse,thecorridor.

6. Wheninterviewingexternalstakeholderswhohavelimitedtimetoparticipateintheplanningprocess,

considercombiningquestionsfromCOR‐1,COR‐2,andCOR‐3andtailorthequestionstotheaudience. Conceptually,itisappropriatetoposequestionsinCOR‐1andCOR‐2regardinggoalsandscope,digest

answers,andthenmoveontoCOR‐3andexaminewhetherthecandidategoalsaresufficientlybroad.However,“intervieweefatigue”canresultifindividuals(forwhomplanningisnotthefocusoftheirjob)areconsultedtoofrequently.Therefore,itcanbehelpfultoconductdetailedinterviewswithadvisorsandobserversonceinanattempttocapturekeyinformationforCOR‐1throughCOR‐3andlet

15

thoseinsightsguidethescope.(Thisconcerndidnotapplyasmuchtotheplanningpartners,whereinsightscouldbeobtainedinamorefrequentmannergiventheirfullinvolvementintheproject.)

Interviewquestionsshouldbetailoredtointendedaudiences.Indevelopingtheinterviewquestions,theprojectteamfounditeasiertoaskthesamequestionsoftheFHWAobserverasthelocal,regional,andstatedecisionmakers—largelybecausetheseentitieswereintimatelyfamiliarwiththedetailsoftheplanningprocess.Bycontrast,itwasappropriatetosegmenttheadvisorsintotwodistinctgroups:advisorswithalargeamountoflanddevelopmentinfluence(e.g.,singlelargeemployers)andadvisorswhorepresentedacollectionofdispersedinterests(suchasahomeownersassociation).

7. Bepatient,beflexible,andbeagoodlistener.Theprofessionalfacilitatorswhowerepartofthisteamstronglyemphasizedthisrecommendation:inbringingtogetherdifferentpartnersandadvisors,anycollaborativeprocesswillevolve.Goals,playersandconditionsmayallchange.Thus,projectteammembersmustbepatientandadaptive–allowingthemselvesandeachothertobeopentonewideasandperspectives.Thus,projectelementsthatteammembersdonotindividuallyenvisionatthestartoftheeffort,suchasthreedifferentsetsofinterviewquestions,canresult.Similarly,projectelementsthatwereenvisionedwerealsomoved—forexample,thestakeholderassessment(seerecommendation15)wasmovedfromCOR‐3toCOR‐6,inordertogivestakeholdersmoreexperiencewiththeplanningprocessthattheyweresubsequentlyaskedtoevaluate.

COR‐4:ReachConsensusonScopeofEnvironmentalReviewandAnalysis

8. ConsiderpursuingCOR‐3,COR‐4,andCOR‐5simultaneouslysuchthattwoiterationsofCOR‐4(andlater,COR‐5)areperformed.TwochallengescompoundthetransitionfromhighlevelgoalsinCOR‐3tothelevelofdataneedsandanalysisinCOR‐4andthentheuseofperformancemetricsinCOR‐5.Thefirstchallengeistodifferentiatebetweenhigh‐levelgoalsthatresultfromCOR‐3(e.g.,improvecorridorsafety)andmeaningfulmetricsforassessingprogresstowardthesegoalsinCOR‐5(i.e.,crashespermile),andresultantdataneedsinCOR‐4(i.e.,rear‐endcrashesoverathreeyearperiod).ThesecondchallengeistodeterminewhichperformancemeasuresarefeasibletocomputeforcandidatesolutionsetsinCOR‐6(i.e.,crashespermileandnear‐missespermilearebothmeaningful,buttheextenttowhichonecancomputetheminadefensiblemannermayvary).Becauseaddressingthesetwochallengesatthesametimeisdifficult,agenciesusingPlanWorksmaywishtofirstdevelopaninitialresultofCOR‐5assumingallmeasuresaremeaningful.Then,agenciesmaywishtorevisetheirinitialversionbasedonaninformedapplicationofCOR‐5.

COR‐5:ApproveEvaluationCriteria,MethodsandMeasures

9. Considermeasuringreliabilitythroughsafetymetrics.Becauseprobe‐baseddatahavebecomeincreasinglycommon,itisnaturaltoquantifyreliabilitythroughmeasuresthatrequiresuchdata,suchasthebufferindex,planningtimeindex,oreventhemiseryindex.However,whenconsideringalternativescenarios,itmaynotbeeasytoforecastthosemeasures—andwhiletheycanintheoryrepresentbothrecurringandnonrecurringcongestion,theymaybeweightedmoretowardstheformer.Acomplementaryapproachistorecognizethatreliabilityisinfluencedbyunplannedincidents—crashes—andthuslookatwaystodeterminehowalternativescenarioswillinfluencecrashrisk.Forexample,thenumberofaccesspointspermile(ageometricmeasurethatcanbeestimatedforaccessmanagementalternatives)andthenumberofvehiclestops(availablethroughsomesimulationprograms)arecorrelatedwithcrashrisk.Thus,thesecanbeusedwithprojectalternativesto

16

determinehowsuchalternativesmayinfluencereliability.(Ultimately,theteamdidnotusecrashriskalonetomeasurereliabilitybutinsteadusedamoretraditionalmeasure—theTTRI—becausethatmeasurewasrequiredfortheSmartScalefundingsource).

10. Considertheuseofhandoutsifperformancemeasuresortechnicalconceptsarebeingpresented.Whiletheteamhadusedhandoutsextensivelytoshowcorridorproblemsandtogatherfeedback,arelativelylast‐minutedecisionwastoprovidehandoutsregardinghow“accessmanagement”affectstrafficflow.Inretrospect,thisappearstohavebeenhelpful,asattendeescouldrefertohandoutsasneededduringthepresentation.

11. WhenapplyingCOR‐5,presentatentativesolution.COR‐5callsfordevelopmentofperformancemeasures,whileCOR‐6callsforthedevelopmentofcandidatesolutionsets.Thismakescompletesenseintheory,however,thetimelineforpublicinvolvementmeansthatonemustbecarefulinhowthesestepsareapplied:ifonecompletelyfinishesCOR‐5first,onemayfrustrateparticipants(who,afterseeingseveralCORsteps,wishtobegintoseesolutions).IfonebeginsCOR‐6tooearly,however,onemayspendsubstantialresourcesdevelopingcandidatesolutionsthathavelittlelikelihoodofbeingimplemented.OneapproachistocompleteadraftofCOR‐5andthenatleastbeabletoofferideasofthetypesofsolutionsbeingconsidered.(Forthisparticularcase,thosesolutionswerefrontageroadmodificationsandlocalstreetconnectionstoimproveaccesstoadjacentdevelopment,alongwithsomegeometricchangestoreduceconflictpoints.)

COR‐6:ApproveRangeofSolutionSets

12. Considerbringingone‐ormoreprogramming‐relatedpolicyquestionsfromCOR‐8intoCOR‐7andCOR‐6.Suchquestionsinclude(1)“Docandidatesolutionsetshaveenoughdetailtoallowtheidentificationoffundingsources?”and(2)“Whataretheprioritizationcriteriaestablishedforprogramming?”

Rationalefortherecommendation

COR‐8showspolicyquestionsthatask,inrelationtootherPlanWorksphases,“Whataretheprioritizationcriteriaestablishedforprogramming?Areourcriteriacompatiblewiththat?Docandidatesolutionsetshaveenoughdetailtoallowtheidentificationoffundingsources?”Whileitisconceptuallylogicaltodrawadividinglinebetweenthedevelopmentandselectionofsolutions(COR‐6andCOR‐7)andtheprioritizationofprojects(COR‐8),thelimitedfundingopportunitiesforsomecorridorprojectsmeansthatthemannerinwhichprojectsareprogrammedmustbeconsideredthroughoutthedevelopmentofthepotentialsolutionsets.Itisespeciallycriticaltoconsiderhowprojectsareprogrammedifitisexpectedthatmultiplefundingsourceswillbeneededtoimplementthesolutionset.(Forexample,forthisparticularcorridor,someprojectsarebeingpursuedthroughHighwaySafetyImprovementProgram[HSIP]fundswhereasothersarecandidatesforVirginia’sstatewideprogrammingprocess,knownasSmartScale).Becauseeachofthesefundingsourceshastheirowndatarequirements,itwasessentialinthisefforttoconsiderthe“criteriaforprogramming”(posedinCOR‐8)atthetimethecandidatesolutionsetsweredeveloped—thatis,inCOR‐6.

Tobeclear,PlanWorksdoesconnecttheprogrammingprocess(the“PRO”steps)andthecorridorplanningprocess(the“COR”steps).Forexample,understepCOR‐8,the“linkstodecisions”boxontheleftofthescreenprovidesaconnectionfromCOR‐8toPRO‐2,whereoneconsiderscriteriaforallocatingrevenue,asshowninFigureA1.However,byaddingapolicyquestiondirectlytoCOR‐6and

17

COR‐7thatrelatestoprogramming,onemayincreasethelikelihoodthatprojectswillbedevelopedsuchthattheymeettheinformationrequirementsforavailablefundingsources.Forthiscorridorinparticular,becauseVirginia’sSmartScaleisalikelyfundingsourceforatleastsomeimprovements,keySmartScalecriteriamustbeconsideredearlyintheprocesssuchaspointsresultingfromthetraveltimereliabilityindex,equivalentpropertydamageonlyreductionoffatalandinjurycrashes,andthereductioninpersonhoursofdelay.Inparticular,becausetheoverallscoreiscalculatedasthetotalpointsdividedbytheprojectcost,the“bangforthebuck”highlyinfluenceswhetheraprojectwillbefunded.Realistically,plannersmustconsidertheseprogrammingcriteriaearlyintheprocess—whencandidatesolutionsetsarebeingdeveloped—iftheywanttoseeprojectsmovetoimplementationunderthisfundingsource.

FigureA1.ExampleofaLinkBetweenCorridorPlanning(COR‐8)andProgramming(PRO‐2).

TounderstandwhythisrecommendationmaybeneededfortheCORsteps,contrastcorridorstudies(e.g.,theCORsteps)withlongrangeplanningstudies(e.g.,theLRPsteps).Forthelatter,theMPOroutinelyconsidersalargevarietyofprojectsinthedevelopmentofthelongrangeplanandthen,throughcarefulconsiderationofavailablefunds,placesprojectsintheshorterrangeTransportationImprovementProgram.Theselongrangeplanningprocessesandprogrammingprocessesareinstitutionalizedandperformedonalargescale:thereisanexpectationeveryyearthatsubstantialagencyresourceswillbedevotedtoupdatingprojectsintheTIP,and(everyfiveyears)updatingthelongrangeplan.Forthatreason,havingalongplanningprocess(LRPsteps)andaprogrammingprocess(PROsteps)thatareseparateprocessesinPlanWorksmakessense—withinastateDOTorlargeMPO,thesetwoprocessesmaybeperformedbytwoseparategroupsofstaff.Theseprocessesarethenconnectedatformaldecisionpoints:forexample,LRP‐10,whichiswheretheMPOadoptsthelongrangetransportationplan,showsunder“LinkstoDecisions”aconnectionbetweentheLRPandthreemajorprogrammingsteps:projectprioritization,approvetheTIP,andincorporatetheTIPintotheSTIP.However,corridorprojects—especiallythosethatmaybe“stuck”—arenotinstitutionalizedanddonotnecessarilyhaveaspecificpointatwhichadecisionmustbemade.WhereasalongrangetransportationplaniseventuallytranslatedintoasetofprojectsforaTIP,thereisnorequirementthatthisbeperformedforacorridorplan.Thus,forcorridorprojectstomoveforward—especiallyinaneraoflimitedfunds—plannersneedtobecognizantofpotentialfundingsourcesandtheirassociatedrequirements.Thisrecognitionneedstobeperformedearly:plannersmustbeprovidingenoughdatainthedevelopmentofcandidatesolutionsets(COR‐6)suchthattheseprojectsatleasthavetheopportunitytobefunded.

18

COR‐7:AdoptPreferredSolutionSet

13. AddafeedbackloopbetweenCOR‐9andCOR‐7.Inorderforatransportationagencytodevelopfeasibleprojectsbasedonacorridorplanningprocess,thecriteriaforschedulingandprioritizinginvestments(e.g.,theresultsofCOR‐9)mustbeexplicitlyconsideredintheselectionofthepreferredsolutionset(inCOR‐7).FailuretodothiscouldresultinasetofimprovementsemanatingfromCOR‐7thatultimatelyareinfeasible.Thus,asshowninFigureA2,afeedbackloopthatemphasizestheimportanceofconsideringCOR‐7throughCOR‐9simultaneouslyshouldbeadded.

FigureA2.SuggestedFeedbackLoopbetweenCOR‐7andCOR‐9.AdaptedfromFHWA.PlanWorksDecisionGuide,Washington,D.C.https://fhwaapps.fhwa.dot.gov/planworks/DecisionGuide.AccessedFebruary2,2017.

COR‐8:ApproveEvaluationCriteria,MethodsandMeasuresforPrioritizationofProjects

14. Considerseparatingmajorquestionsfromthedetailsthatcanbeprovided.FuturedeploymentsofPlanWorksmightbenefitfromashorterquestionstem(suchasthoseshownintherightcolumnsofTableA1)andthenaseparatesectionthatlistsoptionaldetailforeachquestion.Forexample,whenworkingwithdiversepartnersinperson,itwaseasiertoaskashort,generalquestion(suchas“Whatfactorsinfluenceprioritization”)andthentobepreparedtospecifythat“factors”mightmeanspecificperformancemeasures(whichinthisprojectincludedmeasurableitemssuchastheamountofdelayatvariousintersectionsbasedon2040volumes).Tobeclear,thedetailinthePlanWorksquestionscanbequitehelpfulintermsofprovidingabreadthofconsiderations(e.g.,accessibilitytojobs,equity,andbicyclenetworkconnectivitycanallberelevantindifferentcorridors).ByseparatingthedetailfromthecorequestionsinCOR‐8andCOR‐9,thegeneralintentofthequestionscanbeclarified.TableA1.RevisedPlanWorksQuestions

No. OriginalPlanWorksQuestion QuestionUsedbytheTeam1 Areperformancemeasures,evaluationcriteriaandmethodologyfor

assessingbicycleandpedestriannetworkconnectivity,accessibility(tojobs,schools,essentialservices,recreation,etc.),equity,andsafetyincorporatedintotheprojectprioritizationprocess?

Whatfactorsinfluenceprioritization?

2 Whodevelopedtheprioritizationevaluationcriteriaandmethodology?[COR‐8]andHowwerestakeholders,includingmodalandoperationalpartners,engagedinprovidinginputandrecommendations?[COR‐9]

Howdoesthisprioritizationprocessreflectstakeholders’input?

Revisesolutionsetbasedonadditionalinformationfrom

settingpriorities

19

COR‐9:AdoptprioritiesforimplementationTherearenoadditionalrecommendationsforthissectionexceptrecommendation13asdiscussedpreviously(afeedbackloopbetweenCOR‐7andCOR‐9).Withthisfeedbackloop,thequestionscommontoCOR‐7,COR‐8,andCOR‐9canbeconsideredjointlythroughouttheprocess.

UsingthePlanWorksAssessment

15. WhenusingtheresultsoftheCorridorAssessment,itmaybeeasiertoentertheworst‐casescenariosoneatatimeandthenidentifythePlanWorksrecommendationsratherthanenteringthesurveyresponsesallatonce.Intheory,thePlanWorksassessmentsareintendedtobecompletedonline,wherestakeholdersorpartnersreceiveimmediatefeedbackfromtheprocess.However,theprojectteamusedtheassessmentquestionsinaslightlydifferentway:publicparticipantsweregiventhequestionsbutthentheassessmentwasusedtoidentifywherethegreatestamountofimprovementwasneeded.Forexample,considertheresponseto“Thedecision‐makingprocessisclear”whichgavethelowestaveragescore(2.9receivedinthesurvey).Tousetheassessmentresults,onecangotothetwoPlanWorkselementswhichwerethesourceofthatquestionandsimplyentera“StronglyDisagree”forbothofthose(FigureA3)andthenusetheappropriatefeedbackfromPlanWorks(FigureA4).NotethattomakefulluseofthePlanWorksAssessment,oneneedstokeeptrackoftheoriginalPlanWorkselement(e.g.,thetwolinesshowninFigureA3)andthemodifiedquestiongiventothepublic(e.g.,thefirstquestioninFigureA5).

FigureA3.PlanWorksElementsinSupportofQuestion1(“Thedecision‐makingprocessisclear.”)

FigureA4.ExcerptofPlanWorksRecommendationstoClarifytheDecision‐MakingProcess

Theprocessstepsareclearlystated/documented

Thecollectivegoalsareclearlystatedanddocumented

Clickingonthelinksattheleftleadstotextsuggestingan“organizationaloutcomemap”whichledtheprojectteamtoconsiderahandoutatthe3rdpublicmeetingshownasFigure2inthebodyofthisreport.

PlanWorksElement

20

FigureA5.PlanWorksAssessmentUsedDuringCOR‐6

21

AppendixB.SummaryofHowPlanWorksWasImplementedfortheRoute29CorridorAssessment

AppendixBshowshowthenineCORmoduleswereappliedfortheRoute29Assessment.AsisthecasewithAppendixA,materialispresentedbymoduleforconsistencywithPlanWorks,althoughinpracticetherewereseveralcaseswheremoduleswerepursuedintandem.ForeachCOR,therearetwosubsections:theoutcomesofapplyingtheCORandthestepstakenaspartoftheCOR.(Additionaldetails,ifneeded,areavailablefromtheauthorsintheformofindividualtaskreportsprovidedtoFHWA.)COR‐1:ScopeoftheCorridorPlanningProcessOutcomesofCOR‐1

ThegeographicalscopeoftheplanningprocessistheRoute29CorridorwithinCampbellCountyfrom

theCityofLynchburg(Route29/640interchange)toRoute24(theMPOboundary).

Thetemporalscopeisaninemonthstudy,withthegoalbeingtohaveaplanofactionbytheendof2016thattheCountyBoardofSupervisorscanusetoidentifylocalprioritiesforfundingwhichwouldsubmittedtoVDOT.

Thetechnicalscoperemainsopenbutwilldrawheavilyuponexistingwork:notablyfivepreviousstudiesinthecorridor,withthenewercontributionsfromthiseffortbeinggearedtowardreducingconflictpointsandsupportivelandusestrategies.

Theplanningprocessscopeisthattherewillnotbeacitizens’technicaladvisorycommitteewhichcouldinadvertentlyrestrictparticipation;rather,everycitizenwillbeabletoparticipateintheplanningprocessthroughattendingpublicmeetings.Mailings,messageboardsadvertisingthemeeting,andsocialmediawillbeusedtocommunicatetheplanningprocessandmaximizepublicinvolvement.

StepsTakeninCOR‐1

MeetwithakeymemberoftheBoardofSupervisorsonDecember15,2016ThetwoBOSmemberswithsupervisoryauthoritywithinthescopeoftheproject—Dr.JamesBorlandandMr.EricZehr—wereinvitedtoattendanin‐personmeetingfortheproject.(Mr.Zehrwasunabletoattend,however,Dr.Borlandandthecounty’sEconomicDevelopmentDirector,Mr.MikeDavidson,wereabletoattendandwerebriefedabouttheprojectthroughapresentationbyRickYoungblood[districtplannerforVDOT]andJudieTalbot[UniversityofVirginiaInstituteforEnvironmentalNegotiation]).SlideswerenotusedforthepresentationbutratherpresentershighlightedkeypointsoftheprojectastheyrelatetoCOR‐1andCOR‐2.Forexample,underCOR‐1,akeypolicyquestionis“Howwillstakeholders,includingmodalandoperationalpartners,andthepublicbeinvolved?”Thisparticularpointwasofinteresttothetwoboardmembers,whohighlightedtheneedforlandownerstohaveeveryopportunitytoattendpublicmeetingsfortheproject,andwasafactorintheplanningpartners’decisiontonotconveneasmallertechnicaladvisorygroupimmediatelybutratherallowallindividualstoparticipate.

Agreeinternallyonthescopeoftheproject.

22

In‐personmeetingsoftheinternalpartnersheldonDecember7and14(2015),andJanuary4(2016alongwithaconferencecallonJanuary11,(2016),helpeddevelopagreementontheenvironmentfortheproject.Forexample,considerthetwopolicyquestionsfromCOR‐1andCOR‐2,whicharerespectively:“Whoaretheproponentsandopponents?”and“Arethereidentifiedperformancemeasureanddatasourcesforevaluationofstrategies?”Regardingthefirstquestion,planningstaffwithCampbellCountywereabletonotethatthereweretwolikelyviewpointsthatwouldshapethediscussion:businesseswhowanttoshiptheirproductsoutofthearea,andbusinessesthatwanttousethecorridorforlocalaccess.Staffalsorecognizedthatanyrestrictionsplacedonwhatapropertyownercandowillbescrutinized,placingimportanceongettingagreementearlyonintheprocess.Regardingthesecondquestion,theVDOTdistrictplannernotedthatmuchofthetechnicalworkmayhavealreadybeenaccomplishedinpreviousstudies,includingthosedonefortherecentconstrainedlongrangeplan(CLRP).Whilesomeupdatesofthesestudyrecommendationsmaybenecessary,akeypartofthestrategywillbetothinkabouthowtouselandusetoolssuchaswaiversandexceptionrequests(andtheselectedconsultanthasexpertiseinthisarea.)

COR‐2:ApproveProblemStatementsandOpportunitiesOutcomesofCOR‐2

Keydeficienciesinthecorridorincludethefollowing(notlistedinpriorityorder).First,thereisnoticeablecongestionduringthepeakhour.ThiscongestioncontributestoatleasttwodifferentnegativeimpactscitedbyattendeesattheJanuary28,2016publicmeeting:(1)itcanbedifficulttoaccessbusinesses,suchashotels,duringthepeakhour;and(2)thecongestionslowsdownthroughmovementsbothforcommutersandthroughtravelersSecond,therearepotentialsafetyhazards.Someofthesehazardsmaybeinresponsetocongestion;oneattendeereferredtoaportionofthecorridoras“murderous”wherethereareseveralaccesspointsincloseproximitytooneanother.However,inresponsetothiscomment,anotherattendeenotedapotentialsafetyhazardthatcouldresultwhenthereisnotcongestion:largetrucksoftenneedtoturnaroundinaportionofthecorridor,andthiscreatesahazardgiventhatsomevehiclesaretravelingat60mph.Atanothertable,anattendeecitedafatalcrashintheportionofthecorridorwherethereisaschoolentrance.Third,someturnlanesaretooshort.Fourth,thedevelopmentreviewprocesscanbetimeconsumingforlandownersinthecorridor.Thisisalsoanopportunity:duringthemeeting,itwasnotedthat“timeismoney”andthataclearervisionofhowthecorridorshouldbedevelopedcouldexpeditereviews,savingboththeprivateandpublicsectortime.

Potentialopportunitiesincludethefollowing(notlistedinpriorityorder).Severalpotentialtransportationopportunitieshavebeennoted:improvedaccessmanagementthroughtheconsolidationofcommercialdriveways,additionoffrontageroads,andsomeattendeesexpressedaninterestinalternativeroutes.

23

Theremaybeopportunitiesforpubliceducation.Forexample,onecommentmadepriortothemeetingwastheregulationsonestablishmentofsignswithinthecorridor.Whilearestrictionexistsintermsofsignsizewithinthesetbackarea,itrecentlychangedandmanypeoplemaybeunaware(e.g.,themaximumsignsizeisnow100squarefeetwithamaximumheightof20feetforafree‐standingsign–thisisanincreasefrom32squarefeetand15feetinheight).Also,oneindividualthoughtthatsignsizeappliedtosignsplacedonthebuildingsthemselves.(Thisisnotthecase:thereisnoadditionallimitonthesignsizeassociatedwiththeTCOwhenthesignisattachedtothebuilding;seethecounty’smemorandumofMay15,2007.)Theremaybeopportunitiestoobtainfundingforimprovements.Underthecurrentenvironment,Virginia’sdecision‐makingprocessforselectingtransportationprojects—knownasHB2[whichwaslaterrenamedtoSmartScale]—tendstofavorprojectsthatboth(1)havestatewideramificationsand(2)strongcommunitysupport.GiventhatRoute29isacorridorofstatewidesignificance,andgiventheBoard’sinvolvementatthisstage(includingtheBoardandthecommunityinthedevelopmentofalistofrecommendedprojects),thelikelihoodoffundingmaybeincreased.Theremaybeopportunitiestoimprovetransportationinotherlocationsinthearea.AkeypointwasmadethatbyinvestingintheRoute29Corridor(inCampbellCounty)onecanreduceheavytrucktrafficinotherlocations(e.g.,MadisonHeights).

StepsTakeninCOR‐2

MeetwithkeypublicstakeholdersonJanuary28,2016

Atwohourmeetingwithanestimated42stakeholders(whosignedin)washeldonJanuary28thatHylandHeightsBaptistChurch,whichislocatedwithinthestudycorridor.Anadditional13staffwerepresent.Themeetingwasadvertisedinthelocalpaper,lettersweresentto140stakeholderswholiveinthecorridor,variablemessageboardssignswerereservedtodisplaymeetinginformation(howeveranimpendingseverewinterstormoneweekbeforethemeetingpreventedtheirdeployment),andawebsitewithprojectinformationwasdeveloped;thewebaddressishttp://www.virginiadot.org/projects/lynchburg/route_29__corridor.asp.Atthemeeting,theprojectwasintroducedasonewhereattendeeswouldbebriefedratherthan“talkedat”fortwohours—toprovideopportunitiesforthem,thestakeholderstoprovideinput(Figure1inthebodyofthereport).Attendeesweregivenabusinesscardwiththewebaddressandadrawingofthecorridor(FigureB1,left),toencouragefollow‐upafterthemeeting.Duringthemeeting,attendeeswereaskedtoprovideinputbyidentifying,onlargescalemaps,deficienciesinthecorridorbyusingpost‐itnotesandplacingthemonthemap(seeFigureB2foranexampleofresultsofthatexercise).Duringthepresentationthetransportationroleofthecorridor(wherethecorridorisofstatewideimportanceforthroughmovements)andtheeconomicroleofthecorridor(asalocalaccesspointforbusinesses)werenoted,andattendeeswerebriefedthatmultiplestudiesofthecorridorpointedtotheneedforacollaborativeapproachgivenlimitedfundsavailableforcorridorimprovements.Then,75chairsand8tableswerearrangedforattendees,alongwithlarge‐scalemapsonwhichindividualscouldplacepost‐itnotesof3differentcolorswiththeirwrittencommentsonwhattheylikedaboutthecorridor,whattheydidn’tlikeaboutthecorridor,orotherideas/commentsaboutthecorridor..Inpractice,manycasesattendeeschosetomaketheircommentsaloudandthenhavestaff(internalpartnersandtheirassociates)writethemdownandplacethemataspecificlocationonthemap.AkeypointofthepresentationwastheSHRP2PlanWorksplanningprocessbeingused,withanemphasisthattherewouldbeatleastthreepublicmeetings:January28th(todevelopavision);a

24

secondmeeting(todiscusspossiblesolutionsets—e.g.,prosandcons,arethereotherideastheinternalpartnersdidnotconsider?)andathirdmeetingwheretheinternalpartnerswoulddescribeaproposalforapreferredsolutionset(terminologyusedinCOR‐7ofPlanWorks).Insumtheinitialpublicmeetingwasaimedtobeatwo‐wayconversation.Forexample,considertheroleofaccessmanagement.Attendeesweregivensomeexamplesofrecentsuccessinthecorridor:thepresentationshowedhowtwosignalizedentrances—onetoaWalmartandonetoanadjacentSam’sClub—wereconvertedtoright‐inright‐outmovementsonly,withanew(single)accesspointreplacingthesetwoaccesspoints(FigureB1,right).Then,attendeesprovidedcommentsrelatingtohowbetteraccessneededtobeprovidedforcertainbusinesses.

FigureB1.(Left).DrawingoftheCorridoronaBusinessCardGiventoAttendeesattheFirstPublicMeeting.(Thereversesideofthecardhasthewebaddressthroughwhichpubliccommentsmaybedistributed.Theactualcorridorwillonlybethenorthernportion,fromLynchburgtotheMPOboundary).(Right).Exampleofaccessmanagement,wherethenorthandsouthentrances(square)wereconvertedtoright‐in/right‐out,withleftturnsconsolidatedtothesinglemiddleentrance(circle).

25

FigureB2.ExamplesofDeficienciesIdentifiedattheFirstPublicMeeting(January28,2016)

COR‐3:ApproveGoalsfortheCorridorOutcomesofCOR‐3

Publicinputindicatesthattherearethreekeyareasofconcernforthecorridor:safety,economic

development,andcongestion.

TheseparateCampbellCountyRoute29PlanningEffortFindingsReportshowsthatstakeholdersidentifiedspecificareasofconcerninallthreeareas.Forcongestion,individualsexpresslynotedthattheydidnotwanttoseespeedsdeterioratefurthersuchthattheareasuffereddelayscomparabletomoreurbanizedareasoftheCommonwealth.Safetyissuesarearguablyparamount:somecommentsdirectlyrelatetoincreasedtrafficvolumes(i.e.,onefirmhasadoptedapolicythattrucksmaynotchangelanes),andsomeconcernsaredrivenalsobygeometricconsiderations(i.e.,locationofcrossoversandneededturninglanestoseparateflows).Economicdevelopmentisviewedbothasbothdesirableandasituationthatmustbemitigated,withquestionsabouttheabilityoftheregiontoaccommodategrowthintraveldemand.

Long turn lane is good, but fills up quickly in AM with 

students going to parking lots. 

Where businesses are built, consider requesting 

proffer of a turn lane on their property. 

More and more dangerous

2‐lanes on bridge hampers traffic.

Access to Liberty property is currently extremely difficult 

as there is no turn going S. and N. turns are prohibited. 

Could you use an overpass for a bypass (like 

Richmond did)? 

Longerturnlaneneeded

26

StepsTakeninCOR‐3

Asstatedinthebodyofthereport,COR‐3wasappliedthroughfourmajorsteps:holdapublicmeetingatwhichparticipantsprovidedearlyfeedbackbasedonCOR‐1andCOR‐2;identifycandidateintervieweesinboththepublicandprivatesector;developquestionsforinterviewsofpartnersandadvisorsbasedonCOR‐3;andconductinterviewswithstakeholders.

Inadditiontomembersoftheprojectteam,participantsintheseseparateinterviewsincludedBankerSteel,Boxley,FirstNationalBank,FosterFuels,GeorgiaPacific,GreaterLynchburgTransitCompany,HighlandHeightsBaptistChurch,LibertyUniversity,LynchburgRegionalAirport,LynchburgRegionalBusinessAlliance,Moore’sElectricalandMechanical,andNealbrookChips.TheCampbellCountyRoute29PlanningEffortFindingsReportlistscommentsbasedontheinterviews,aswellascommentsfromthefirstpublicmeeting,onasection‐by‐sectionbasisforthecorridor.Forexample,forthesectionbetweenCalohanRoadandRoute24,deficienciesincludeamediancrossingwheretherehavebeencollisions,conflictsatsomeunsignalizedintersectionsgiventhe60mphspeedlimit,andaccessviaanothermediancrossingtotwobusinessesinparticular.

Theresultsoftheinterviews(UVAIEN,2016)andthepublicmeetingunderscoredapointraisedinthereviewofpreviousstudiesbyAECOM(2016)inthatspecificsolutionswereneeded.Itwasatthisstageoftheprocessthattheteambegantoviewthecorridorasdiscretesections;asshowninFigureB3,thereweresixspecificsegmentsofthecorridorthatcouldbeanalyzed.(ThisfedCOR‐4directly.)

FigureB3.SixStudySegmentsoftheCorridor(VDOTGISIntegrator)

27

COR‐4:ReachConsensusonScopeofEnvironmentalReviewandAnalysis

OutcomesofCOR‐4

Aninitiallistofsixelements—goals,stakeholdercomments,objectives,performancemeasures,quantitativetools,andkeydatadetails—wasdevelopedasshowninTableB1.

Intheory,onlythegoals(whichcomefromCOR‐3andthefindingsintheCampbellCountyRoute29PlanningEffortFindingsReport)andthedataneeds(whichcomefromCOR‐4)arerequiredforthistask,withtheperformancemeasuresandquantitativetoolsforthcomingfromCOR‐5.However,developmentofthesesixelementsenabledtheteamtobetterunderstandwhichdataelementsforCOR‐4couldbethemostmeaningful.Severalcommentsfromthepublicinputmeetingsrelateexpresslytotransportationsafety—afindingnotnecessarilyexpectedatthetimetheteamsoughtthegrantfromFHWAandafindingwhichplacesmoreemphasisongeometricimprovementsthanoriginallyanticipated.Thus,onedataneedthathasbecomeapparentisafairlydetailedunderstandingofhowthephysicalandoperationalcharacteristicsofthecorridor(lanewidth,turningmovements,signaltimings,andpossiblysightdistance)changebycorridorsection.

Itmaybeappropriatetodividethecorridorintosixdiscretesegmentsforanalysis.

Thestakeholderinterviewssuggestthattheapplicationofperformancemeasures,quantitativetools,andsupportingdatasetsmay,insomecases,beperformedonsixdiscretesegmentsasshowninFigureB3:(1)LynchburgCityLimittoLibertyMountainDrive(Route1405);(2)LibertyMountainDrivetoRussellWoods(Route679);(3)RussellWoodstoLawyersRoad(Route683);(4)LawyersRoadtoEnglishTavernRoad’snorthernterminus(Route738),(5)EnglishTavernRoad’snorthernterminustoCalohanRoad(Route685),and(6)CalohanRoadtoColonialHighway(Route24).Examplesofspecificimprovementssuggestedbystakeholdersforeachsectionincludeaddingaccelerationlanes,closingmediancrossings,addingspeedlimits,lengtheningturnlanes,addingsignals,improvingsignaltimings,andaddingserviceroads.

StepsTakeninCOR‐4

Chapter9,titledTransportationSystemsandFacilities,fromtheCampbellCountyComprehensivePlanwaschosenasastartingpointforidentifyingcommunityvalues.ThePlanidentifiestwogoals:(1)“promoteasafe,effective,andenvironmentallysoundtransportationsystemthroughoutCampbellCounty”and(2)“promoteatransportationsystemcompatiblewithexistingandfutureplannedlanduses.”Thesetwogoalswereusedbytheprojectmanagementteamtoidentifypossiblegoals,objectives,performancemeasures,quantitativeapproaches,andrelevantkeydatadetailsasshowninTableB1.InformationgiveninthePlanofferedguidancefordevelopingtheseperformancemeasures.Forexample,theimportanceofaccommodatingtrucktraffic(giventhegeneralfreightcarriersinthearea)andconnectingRoute29tothegeneralfreightterminalusedbytheNorfolkSouthernrailway(whichoffersfreightservicefromrailtoroadatthatterminal)offereddetailforbetterunderstandingthesecondgoalinthePlan.Asanotherexample,oneofthepriorityprojectsfor(fromtheMPO’s2010bicycleplanwhichisreferencedinthePlan)wastohavesigningonRoute29withawideoutsidelane(whichcouldaccommodatebicyclists).Accordingly,aperformancemeasurebasedonbicyclelevelofservice(whichconsidersthewidthofthatcurblane)hasbeenincludedinTableB1.Asathirdexample,thePlanhighlightsthechallengeofcongestiononU.S.29betweenEnglishTavernRoadandtheborderwiththeCityofLynchburg,withtrafficvolumesapproaching44,000vehiclesperday.BecausethePlanemphasizesthemanagementofaccessasonetoolforaccommodatingthesevolumes,measuresrelatedtoaccessareincludedinTableB1.

28

TableB1.CandidatePerformanceMeasuresandDataNeeds(DevelopedinCOR‐3andCOR‐4,butRevisedinCOR‐5)

Goal StakeholderComments Objective PerformanceMeasure(s) QuantitativeTools Keydatadetails

Promoteasafetransportsystemthroughoutthecounty.

Roadworkcrewsafetymustbeconsideredaswellasmotorists.HighvolumeoftrucktrafficintheareathatcausessafetyconcernsSignalsareneededtoprovidesafegapsinthetrafficstream.VisibilitymayberestrictedbyguardrailoverthetraintracksandacrestintheintersectionatEnglishTavernRoadLackofaccelerationwhenturningoutofamediancausestravelproblems

Reducemotorvehiclecrashrisk

CrashespermileCrashesofacertaintype(rear‐endcrashes)CrashesinvolvingtrucksCrashesnearspotsofreducedvisibility

NCHRPReport420(relateaccesspointstocrashrisk)

Crashhistoryinthecorridor:229crashesfortheperiodJanuary1,2010‐October27,2015

Numberofstops(oranotherperformancemeasure)

SimTraffic/Synchrosoftware(evaluatenearmisses)

Crashesarenotalwayscomplete(hencesimulationresultsmaybeneeded)

Reducenon‐motorizedcrashrisk

BicycleCompatibilityIndexBicycleLevelofServiceQualityofpedestrianaccessfortransitstoplocationsNumberofcrashesinworkzones

StandardmethodsforapplyingBLOSandBCIareavailable(includingsomeonlinetools)TransitCapacityandQualityofServiceManualchapters4and5

VDOT’sStatewidePlanningSystem(SPS)providesBLOSasabaselinemeasurewhichcanhelpcalibratecalculatedvaluesItmaybemoremeaningfultosimplyindicate“yes/no”intermsofavailabilityofpedestrianfeatures;GISdatamaybeappropriate.

29

Goal StakeholderComments Objective PerformanceMeasure(s) QuantitativeTools Keydatadetails

Promoteaneffectivetransportsystemthroughoutthecounty.

TrafficsignalsimpedetheflowoftrafficTrafficsignaltimingdoesnotaccountforaccelerationoftrucksTurningtrucksimpedetrafficbecausetheyrequiremorethanonelaneTurningvehiclesatCalohanRdformaqueuethatextendstotheleftpassinglane

Reducedelay Numberoftimespeaktraveltimeinthecorridorisbelow20minutesasmeasuredfromAtoBTimespentattrafficsignalsDelaycausedbytrucksattrafficsignals

SimTraffic/Synchrosoftware(reportsdelayasafunctionofvolume)

ShouldthelimitsofthecorridorbeEnglishTavernRoadtoRoute460?

Improvereliability

Coefficientofvariationoftravelspeeds[VariousothermeasuresinTask4]PlanningTimeIndexBufferIndexMiseryIndexSkewStatistic

Varianceinspeedsfromsimulationrunsifthatisreasonable

Anycalibrationdatachallengeswouldbenotedhere.

Promoteanenvironmentallysoundtransportsystemthroughoutthecounty.

[Thetopicoftheenvironmentwasnotmentionedduringthestakeholderinterviews]

Improveairquality

Greenhousegasemissions(kgofCO2)

SumtotalfuelconsumptionfromSimTraffic/Synchro(foragivenvolume)andconverttoCO2emissions

ShouldwejustuseCO2orshouldweconsiderVOCsandNOx(whicharegivenbySynchro)Isasimpleconversion(say10kgofCO2pergallonoffuel)acceptable?

Promoteatransportationsystemcompatiblewithexistingandfuturelanduses

EwingDrivewilllikelyneedasignalduetoeconomicdevelopment(althoughthisis1.5milessouthofthecorridor)

Improvevehicularaccesstopointsinthecorridorforpassengertravel

Delayforturningleftandrightintocertainbusinesses

StoppeddelayatagivenintersectionforleftorrightturningvehiclesDelaytoreachthemainlinefromtheminorstreet

Atwhatpointsshoulddelaybecomputed(e.g.,eachintersectionorforkeybusinesses)?

30

Goal StakeholderComments Objective PerformanceMeasure(s) QuantitativeTools Keydatadetails

Improvepedestrianaccesstopointswithinthecorridor

Connectivityindex(orsomeothermeasureindicatingtheextenttowhichstreetsareinterconnected)Tabulatethenumberofparcelswhereconnectionpointsforpedestriansexist

PossiblyaGISlayeroflocallanddevelopment

Asthispertainstofuturelanduse,somedatadetailsmaybemissingfromanticipatedfuturedevelopment

Improvefreightaccesswithinthecorridor

TraveltimetotheNorfolkSoutherngeneralfreightfacility(whichofferspiggybackservicefortrucktorail

SimTraffic/Synchrosoftware(reportsdelayasafunctionofvolume)

Thefromwhichtravelshouldbemeasuredisrelevant

Provideanequallevelofimprovementstoallresidentsofthecorridor.

Impactsonhighandlowincomeareas:aretheythesame

Usecensusdatatoidentifyhighandlowincomeareas.Usethesimulationmodeltodetermineiftheseareasareimpactedequally.

IsCensusincomedataavailableattheblocklevel(orlevelsuitableforanalysis?)CanSynchro/SimTrafficbeusedtoidentifypositiveandnegativeimpactsinthecorridor

31

COR‐5:ApproveEvaluationCriteria,MethodsandMeasuresOutcomesofCOR‐5

Therearetwopromisingtraditionalwaysofassessingreliability:theplanningtimeindexandthebufferindex.Bothhavebeenappliedtothiscorridorandwillbeabaselineforfuturemeasures.Forexample,foramotoristtravelingtoworktoavoidarrivinglate90percentofthetime(thatisduringallbuttheworstpeakperiodtravelinagivenmonth),theestimatedplanningtimeindexindicatedthat,whentravelingnorthboundinthemorningpeakhourorsouthboundintheeveningpeakhour,theexpectedtraveltimeshouldbeincreasedbyafactorof1.4overthefree‐flowtraveltime(e.g.,usingthespeedlimit.)Anotherinterpretationofthe90thpercentilevalueintheplanningtimeindexisthatassumingapproximately20workingdayspermonth,the1.4multipliershouldbeusedbycommuterswhocannotaffordtobelatemorethantwiceamonth.Further,thebufferindex(90thpercentile)showsthat,ifacommutercannotaffordtobelatetoworkmorethantwicepermonth,heorsheshouldpresumethathisorhermediandailycommutetimewillneedtoincreasebyroughly25%andadjusthisorherdeparturetimeaccordingly.Acharacteristicofthesetwoindicesisthattheycanbedominatedbyrecurringcongestion.(Ifonlyoneofthesemetricscouldbechosen,thentherecommendationwouldbetochoosethebufferindex.)

Crashriskoffersapromisingnontraditionalwayofassessingreliability.

Whileanincreaseinrushhourtraveltimemaybeexpected,crashescanleadtounexpecteddecreasesinspeedsinthecorridor.TheStrategicHighwayResearchProgram(SHRP2)listssafetyasoneoftheimportantperformancemetricstostudyreliabilityonagivencorridor,asawayofdetectingnonrecurringcrashes.Asabaselineofcurrentconditions,thetotalnumberofcrashes(fatal,injury,andpropertydamageonly)andinjurycrashes,aswellastherateintermsofnumberofcrashespermillionvehiclemilestraveledshowshighercrashratesintheportionofthecorridorwithlessreliability,whichisthenorthernsegmentbetweenEnglishTavernRoadandRoute460.Surrogatemeasuresthatcanhelpquantifythiscrashriskincludethenumberofstops(fromtheSimTrafficsimulationpackage)andthenumberofaccesspointspermile.

Candidateperformancemeasuresare(inadditiontotheplanningtimeindex,thebufferindex,access

pointspermile,andnumberofstops)thedelayforturningleftandrightintocertainbusinesses,andthefeasibilityofconstructingtheproposedalternatives.WhilethepublicmeetingheldJune23,2016didnotpositivelyconfirmorrefutethesemeasures,informalcommentsfromparticipantssuggestedthatatthispointintime,itisprematuretoeliminatemetricsfromconsideration.Informalcommentsalsosuggestedthatparticipantsareinterestedinseeingactiononanalternativebetaken:aconcernvoicedbyseveralattendeeswasthatalternativeswhichhavebeendiscussedinyearspast(suchasconstructionofabypass)hadnotbeenimplementedasVDOThasexperiencedfundingshortfallsinsomeyears.Thus,implementationfeasibilityisameasuretobeconsideredwhensolutionsareprioritized(inCOR‐8)(andwhichultimatelydrovethedevelopmentofthedatabasenotedinCOR‐9).

Atthenextpublicmeetingattendeesshouldbeprovidedwithasinglepagehandoutthathastwopiecesofinformation.Thefrontofthehandoutshouldsummarizetheprocessusedtogeneratecandidatesolutions—e.g.,establishmentofgoals,performancemeasures,anddevelopmentofacandidatesolutionsunderthelimitationofavailablefunds.Thebackofthehandoutshouldsummarizeafewexamplesofhow

32

publicinputwasincorporateddirectlyintothesolutions.Thisrecommendationisbasedontheresultsofthecorridorassessment.

Attendeesexpressedastronginterestinsomeactionsthatmaybefeasible.

Somecommentssupportedrelativelyexpensiveinfrastructure:ofthe53commentsrecordedonthepinmapofimprovements(seeFigureB4),sevenreferredtoabypassandothers(e.g.,anewroadconnectionconsistingofaramptothebypassatRustburgor“removeamajority(ifnotall)trafficlightsleadingintoandoutofLynchburg”maynotbedoableinfull.Furtherafewothercomments(electronicspeedcamerasoraliquorlicenseforaparticularestablishment)areoutsidethestudyscope.However,manycommentssupportedspecific,tangiblespotimprovementsthatcanatleastinformcandidatesolutionsetsinCOR‐6suchasreroutingtrafficatRangoonStreet,revisitingthespeedlimitinthecorridor,removingsignals(althoughonecommentsuggestedtheneedforanadditionalsignalatPattersonRoad),allowingrightturnonredatCalohanRoad,makingthesouthernconnectionofEnglishTavernRoadandRoute29right‐in/right‐outonly,addingsidewalks,addingbikelanesnearLynbrookRoad,andimprovingoraddingdecelerationlanesatthemediannorthofAmyRoad/MoormanMillRoad.

FigureB4.ExampleofCommentsfromtheSecondPublicMeeting

StepsTakeninCOR‐5Asshowninthestand‐alonememorandum(AECOM,2016),avarietyofcandidateperformancemeasureswereconsidered.Somewereeliminatedfromconsiderationbecausetheydidnotmeetthecoregoalsofthecountycomprehensiveplan(forexample,thePlandoesnotexplicitlyconsidergreenhousegasemissions).Othermeasureswereeliminatedbecauseofimperfectdata—forexample,whilecoefficientofvariationoftravelspeedsdoesdirectlymeasurereliability,itmaybelessunderstandablethanthenumberofstops.TentativelyrecommendedmetricsareshowninTableB2basedonsynthesizingtheAECOMJune1memorandumandtheperformancemeasurespresentedatthepublicmeetingheldJune23.AtthetimeCOR‐

33

5wascompleted,theteamnotedthat“Itisstillprobablythecasethatnotallmeasureswillultimatelybeused,butthesegiveaframeworkforpresentingthealternativesfromCOR‐6.”Inretrospect,afterCOR‐5wascompleted,despitethediscussionofhowimprovedreliabilitycouldbemeasuredthroughareductionincrashrisk,theteamultimatelyassessedreliabilitythroughamoretraditionalperformancemeasure(atraveltimereliabilityindex[TTRI]).Thisresultedbecauseoftheneedtouseperformancemeasuresassociatedwithfundingsources,andTTRIisusedbyVirginia’sSmartScale.Thus,laterconsiderations(whichcamefromCOR‐7,COR‐8,andCOR‐9)ultimatelymodifiedthemetricsshowninTableB2.Thatsaid,Virginia’scomputationofTTRIdoesusedasurrogateforcrashrisk,asdiscussedinTableB3underCOR‐6.TableB2.TentativelyRecommendedPerformanceMeasuresb

Goal Objective PerformanceMeasure(s) QuantitativeTools

Promoteasafetransportsystemthroughoutthecounty.

Reducemotorvehiclecrashrisk

Crashespermile Numberofrear‐endcrashes

NCHRPReport420(relateaccesspointstocrashrisk)

Numberofstops SimTraffic/Synchrosoftware

(evaluatenumberofstops)

Promoteaneffectivetransportsystemthroughoutthecounty.

Reducedelay

Numberoftimespeaktraveltimeinthecorridorisbelow10minutes

Numberofdrivewayspermileb Numberofmediancrossoversper

mileb

SimTraffic/Synchrosoftware(reportsdelayasafunctionofvolume)

Improvereliability

TravelTimeIndex PlanningTimeIndex BufferTimeIndex

Thethreeindices(traveltime,planningtime,andbuffertime)maybeinfluencedmorebyrecurringcongestion.

Numberofdrivewayspermileb Numberofmediancrossoversper

mileb

Nonrecurringcongestioncanalsobecapturedbythesafetymeasures(e.g.,drivewayspermilenotedpreviously)

Promoteatransportationsystemcompatiblewithexistingandfuturelanduses

Improvevehicularaccesstopointsinthecorridorc

Stoppeddelayatagivenintersectionforleftorrightturningvehiclesintocertainbusinesses

Delaytoreachthemainlinefromtheminorstreet

Onecouldalsoconsiderdelaytoreachthemainlinefromtheminorstreet

aWhileitdoesnotfitintothegoalsandobjectivesperse,thefeasibilityofimplementingasolutionisitselfaperformancemeasure.Thiscanbeaddressedbydetermining,inCOR‐8,ifenoughinformationregardingthesolutionisavailablesothatitcanbepreparedforcandidatefundingsources.bItmaybethecasethatultimatelythesemeasuresarenotcarriedforwardiftheyduplicatetheothermetricsshown.cAnearlierversionofthistablehadtheobjective“improvenonmotorizedaccesstopointsinthecorridor”withaperformancemeasurebeingalevelofservicemeasureforpedestriansandbicyclists.However,becausenonmotorizedaccessimprovementsmaybepartofanypackageofprojects,suchaperformancemeasuremaynothelpdiscriminateamongprojectalternativesandthusisnotshowninTableB2.AnearlierversionoftheperformancemeasuresshowninTableB2werepresentedatthepublicmeetingheldJune23,2016.Thefirstportionofthemeetingconsistedoftwopresentations(FigureB5)withthelatterpart

34

ofthemeetinggivingattendeesachancetoprovidecomments—bothaloudandonhandwrittenmaps(FigureB6).Themeetingwasnotaswellattendedastheinitialpublicmeeting,however,onefactorsmayhavecontributedtothelower‐than‐expectedturnout:aseverestorm(withhail)hadbeenforecastandinfactthisstormstruckduringthemeeting.Becauseoftheloudnoisefromthehail,itwasnecessarytointerruptthepresentationafewtimesuntilthestormsoftenedsuchthatthespeakerscouldbeheard—whichdemonstratedthevalueofthehandouts.TableB2usesContextSensitiveSolutions(CSS)conceptsbutdoesnotshowaspecificCSSperformancemeasure.Rather,fourattributesofCSSareevidentintheperformancemeasures:(1)supportingallusersofthetransportationsystem;(2)reflectingcommunityvalues;(3)integratingsolutionsthroughoutthedesignofsolutionsinCOR‐6;and(4)jointconsiderationoflanduseandtransportationinvestments.Forexample,theapplicationofprinciples1and4isevidentinthatdiverseusers(freight,pedestrian,andbicycle)areconsideredinthegoalofintegratingtransportationandlanduseinvestments.ThegoalsshowninTableB2originatedfromthecountycomprehensiveplan,therebysupportingthesecondCSSprinciple.

FigureB5.(left)PresentationbyPaulHarvey,CampbellCounty;(middle)PresentationbyChrisLawrence,AECOM;(right)attendeeslisteningtothepresentationsattheSecondPublicMeeting.

FigureB6.AttendeesreviewplansafterthepresentationsattheSecondPublicMeeting

35

NotethatseveralcandidateperformancemeasuresnotedinCOR‐3(seeTableB1)wereultimatelynotselectedduetoeitherincompletedata,difficultywithcomputingthemeasure,orconcernsthatthemeasurewouldnotprovideinsightsintoprojectselection: Greenhousegasemissionsaredifficulttoevaluateastrafficcountswereonlytakenatsignalized

intersections,yetmanyoftheproposedchangeswillinvolveunsignalizedintersectionsforwhichwedon’thavetrafficdata.

Asthereislittleinterconnectivityofstreetsatpresent,andbecauseitisnotreasonabletodeterminefuturelandusesindetail,theconnectivityindexwaseliminated.

Nearlyalloftheparcelslackpedestrianfacilities,thustabulationofthenumberofparcelswithpedestrianaccommodationswaseliminated.

ThetraveltimetotheNorfolkSoutherngeneralfreightfacilityisnotknownandappearstoduplicatethereliabilitymetricsthathavebeenchosen.

ImpactsonhighandlowincomeareaswereeliminatedbecausealmosttheentirefrontageofRoute29iseitherzonedbusinessorindustrial;further,measuringtheimpactstotheadjacentresidentialareaswouldbedifficulttoclearlyquantify.

ThesechangesthusledtotheperformancemeasuresshowninTableB2.

COR‐6:ApproveRangeofSolutionSets

OutcomesofCOR‐6

Fourcandidatesolutionsetshavebeenidentified,whereeachsolutionsetidentifiesmultiplesolutions.Incontrasttosomecorridorstudieswhereonemightchooseasinglealternative,thesolutionsetsaredesignedsuchthatoneisnotrequiredtochooseoneparticularset;rather,itisexpectedthatstakeholdersmaychooseelementsfrommultiplesolutionsets.Eachsolutionsethasatheme:(throughput,safety,economicdevelopment,andinnovative[“smart”]approaches).Thefoursolutionsetscontaingeometricchangesrelatingtothespacingofaccesspoints,operationalchangessuchassignalretimingortheinstallationofaflashingyellowarrow,landaccessapproaches,accommodationofpedestrianandbicyclemodesthroughsidewalksandsharedusepaths,andnewtechnologiessuchasatrafficmanagementsystem.FigureB7showshowsomeofthesesolutionsetscompareatoneparticularlocation:Route29andRussellWoodsDrive,oneofseveralintersectionswithinthecorridor.Atthatintersection,solutionsetsoneandtwoshowaccess‐relatedimprovements,suchasclosingthemedian,extendingaleftturnlane,andmakingacommercialdrivewayright‐in/right‐outonly.Atthatsameintersection,solutionset3addsatwo‐wayleftturnlaneandacontinuousrightturnlane,therebyincreasingaccesstobusinesses.Atthatsameintersection,solutionset4addsasharedusebicycle/pedestrianpathforthelengthofthecorridor.Tobeclear,FigureB7onlyshowsthegeometricimprovements;forexample,whilesolutionsets1and2haveidenticalgeometricchangestothatintersection;solutionset2alsoincludesspeedlimitchangesandtheadditionofsignalstoimprovesafetyatotherlocationsinthecorridor,andsolutionset4alsoincludesaTrafficManagementSystem(TMS)fortheentirearea.ThesefoursolutionsetswerepresentedduringthethirdpublicmeetingheldOctober27,2016.

36

SolutionSets1and2Installwestboundleftturnlane

Extendeastboundleftturnlane

Installcommercialdriveway(right‐in,right‐out,limitedlefts)

Closemedian

SolutionSet3Installcontinuousrightturnlaneeastoftheintersection

Installtwo‐wayleftturnlanewestoftheintersection

SolutionSet4Addshareduse‐pathforbicyclistsandpedestrians(eastboundandwestbound)

FigureB7.ExamplesofImprovementsfromtheFourCandidateSolutionSetsattheIntersectionofRussellWoodsDriveandRoute29.

37

Thefoursolutionsetsaredesignedtobecomplementary,notmutuallyexclusive.Itisconceivablethattherewillnotbejustone“solutionset”whichisadopted.Rather,elementsofeachsolutionsetmaybeadoptedintoaproposed“blended”solutionset.Forexample,onemightchoosemedianclosures(fromsolutionset1),speedlimitchanges(fromsolutionset2),atwo‐wayleftturnlane(fromsolutionset3),andsignaloptimizationalongwithashared‐usepath(fromsolutionset4).

StepsTakeninCOR‐6(Iteration1)AdraftmemorandumdevelopedbyAECOMonAugust30,2016introducedbaselineandforecast(year2040)conditionsforthecorridor,intermsofintersectiondelayandcrashrisk.Thememorandumalsooutlinedfourcandidatesolutionsets,whereeachsolutionsetcontainedmultipleactions,suchasgeometricimprovements(e.g.,reducingthenumberofaccesspoints),operationalchanges(e.g.,changingsignaltimingsor,insomecases,thelocationsofthesignalsthemselves),andadministrativechanges(suchashowthetransportationcorridoroverlaydistrictisimplemented).Forexample,oneelementofthethirdsolutionsetwasacontinuoustwo‐wayleft‐turnlaneforthelengthofthecorridor.Forthatelement,thememorandumshowedthatsomedecreaseinfatalandinjurycrashescouldbeexpectedinyear2040;thememorandumexplainedthatthiscouldbequantifiedas155.60equivalentpropertydamageonly(EPDO)crashes,basedonapplicationofcrashmodificationfactorsfromtheFHWACrashModificationFactor(CMF)clearinghouseforatwo‐wayleft‐turnlane.Asanotherexample,oneelementinthefourthsolutionsetwassignaloptimization,whereareductionofthe62.24EPDOcrasheswasestimated.Inadditiontoimpactsonexpectedcrashes,thememorandumquantifiedtheexpecteddelayimpactsofsomeimprovements.Forexample,oneelementofsolutionset1(addingaflashingyellowarrowtotheintersectionofRoute29andCalohanRoadtoprovideapermittedleftturningphaseratherthanaprotectedonlyleftturningphase)wasexpectedtoreduce2040averageintersectiondelayfrom68secondsto41secondsduringthepeakhour.ThismemorandumwasreviewedataninternalteammeetingheldonSeptember2,2016.

TheimpactsoftheelementsofeachsolutionsetintermsofperformancemeasuressimilartothoseidentifiedinCOR‐5weredetermined.RecallthatCOR‐5identifiedthreegoals,abbreviatedhereaspromoteasafetransportsystem,promoteaneffectivetransportationsystem,andpromoteatransportationsystemcompatiblewithexistingandfuturelanduses.Foreachgoal,atleastoneperformancemeasureisgiven(reductioninequivalentpropertydamageonly(EPDOforfatalandinjurycrashesforthefirstgoal,reductioninvehiclehoursofdelayinthecorridorandimprovementinthetraveltimereliabilityindexforthesecondgoal,andreductioninmovementdelayforleftandrightturnsforthethirdgoal).Theimpactofeachelementfromeachofthefourcandidatesolutionsetsonthesemeasureshasbeendetermined.

Forexample,considerthefirstgoal(promoteasafetransportationsystem).Theperformancemeasureistheequivalentpropertydamageonly(EPDO)offatalandinjurycrashesexpectedtobereduced.(EPDOisawayofweightingcrashreductionsbyseveritylevel:theSmartScaleTechnicalGuide[VDOT,2016]indicatesfourweights:540points[forfatalcrashes],30points[forsevereinjurycrashes],10points[formoderateinjurycrashes],and5points[forminorinjurycrashes].Thussupposeahypotheticalimprovementwasbelievedtoreduceallcrashseveritiesby12%,anditwasappliedtoasitewherethenumberofcrashes(withouttreatment)was0fatal,1severeinjury,2moderateinjury,and5minorinjury.TheEPDOforfatalandinjurycrashesexpectedtobereducedforthishypotheticalimprovementwouldbecalculatedas(0fatalcrashes)(540points)(12%)+(1severeinjurycrash)(30points)(12%)+(2moderateinjurycrashes)(10points)(12%)+(5minorinjurycrashes)(5points)(12%)=9.Inpractice,theEPDOinfatalandinjurycrasheswillvaryforeachimprovementtypeandbylocation.Forexample,consideraT‐intersectionwithRoute29.TheexpectedEPDOreductioninfatalandinjurycrashesthatresultsfromeliminatingallleftturns(exceptfromRoute29)isestimatedtobe0.35foroneintersection(Route29andDennisRiddleDrive)but

38

morethantentimesthatamount(4.90)foranotherintersection(Route29andabusinesssouthofBakerRoad),asshowninFigureB8.

FigureB8.ExamplesofEliminatingLeftTurns(ExceptFromRoute29)atT‐intersections.(left:DennisRiddleDrive.right:accessforabusinesssouthofBakerRoad.)

39

Table 18 ‐ Performance Measures Applied to the Candidate Solution Sets 

Goal ObjectivePerformanceMeasure

Set1‐ArterialCapacityandThroughput Set2‐CorridorSafety Set3‐EconomicDevelopment

Set4‐ SmartandAlternative

TransportationSolutions

PromoteaSafeTransportation

System

Reducemotorvehiclecrashes

EquivalentProperty

DamageOnly(EPDO)offatalandinjury

crashesexpectedtobereduced

•31‐MedianCrossoverClosures•11‐TurnLaneExtensions•13‐NewTurnLanes•9‐RCUTIntersections

•190(FatalInjury)&72(SeriousInjury)‐SpeedLimitReduction•31‐MedianCrossoverClosures•11‐TurnLaneExtensions•13‐NewTurnLanes•9‐RCUTIntersections

•156‐InstallTWLTLinmedianspacealongRoute29

TrafficManagementSystem•252‐RedLightCamera•132‐SpeedEnforcementCameras•62‐SignalOptimization

PromoteanEfficient

TransportationSystem

ReducedelaySimTrafficdelay

‐2040conditions

•0.80min.decrease‐FlashingYellowArrow(FYA)InstallationatCalohanRd.andRoute29intersection

•4.91min.increase(twodirectionscombined)‐SpeedLimitReductionalongRoute29

N/A N/A

ImproveReliability

TravelTimeReliabilityIndex

•1.00‐MedianCrossoverClosures•0.50‐MedianLeft‐InOnlywithRight‐In/Right‐Out•2.75‐LeftTurnLaneExtensions•0.75‐RightTurnLaneExtensions•0.25‐LeftTurnLaneAddition•0.75‐RightTurnLaneAddition•0.25‐RCUTS•0.25‐InstallFYAatCalohanRd.Signal

•1.00‐MedianCrossoverClosures•0.50‐MedianLeft‐InOnlywithRight‐In/Right‐Out•2.75‐LeftTurnLaneExtensions•0.75‐RightTurnLaneExtensions•0.25‐LeftTurnLaneAddition•0.75‐RightTurnLaneAddition•0.25‐RCUTS•3.00‐ProposedSpeedLimitChanges

•0.25‐FutureSignalLocations:MoormanMillRoadPattersonRoadLynbrookRoadHylandDrive•2.75‐InstallTwo‐wayleft‐turnlanewithinthemedianspacealongRoute29

•1.50–TrafficManagementSystemtoincludered‐lightcamera,speedenforcementcameras,andsignaloptimization/adaptive

Promote a Transportation 

System Compatible with Existing and Future Land Use 

Improve vehicular access to 

points in the corridor for passenger travel 

Movement Delay for turning lefts and rights at existing and 

proposed solution conditions ‐ 2040 

conditions 

RCUTs (Movement Delay/Veh. (sec.)) with Existing Corridor Speed Limit  RCUTs (Movement Delay/Veh. (sec.)) with Speed Limit Changes along the Corridor 

Future Signalized Intersections 

N/A 

Intersection  NBL  SBL  EBR  WBR  NBU  SBU  Intersection  NBL  SBL  EBR  WBR  NBU  SBU 

MoormanMillRd

10.5(17.0)*

15.2(10.9)

15.3(34.7)

28.2(16.3)

12.8(86.8)

22.8(11.2)

MoormanMillRd

10.5(17.0)

15.2(10.9)

15.3(34.7)

28.2(16.3)

12.6(103.0)

23.0(14.8)

PattersonRd

10.5(17.0)

27.2(15.1)

15.3(34.7)

N/A10.6(50.7)

46.6(10.5)

PattersonRd10.5(17.0)

27.2(15.1)

15.3(34.70)

N/A10.3(51.2)

33.6(14.5)

ProposedSignalizedIntersection

AMOverallIntersectionDelay/Veh.

(sec)

PMOverallIntersectionDelay/Veh.

(sec)

LynbrookRd

9.9(16.5)

27.0(15.3)

14.0(32.8)

88.5(28.7)

52.8(81.8)

324.4(36.8)

LynbrookRd9.9

(16.5)27

(15.3)14.0(32.8)

88.5(28.7)

10.0(76.8)

160.7(33.9)

HylandDrive

9.9(16.5)

27.0(15.3)

14.0(32.8)

88.5(28.7)

56.8(42.6)

469.2(53.7)

HylandDrive 9.9(16.5)

28(15.3)

14.0(32.8)

88.5(28.7)

13.4(33.8)

385.5(33.9)

MedianCrossover(MovementDelay/Veh.(sec.))withExistingCorridorSpeedLimit

MedianCrossover(MovementDelay/Veh.(sec.))withExistingCorridorSpeedLimit

MoormanMillRd

22.2(LOSC)

29.6(LOSC)

MedianLocationsonRoute29Corridor

NBL SBL EBR WBRMedianLocationsonRoute29

CorridorNBL SBL EBR WBR

PattersonRd

14.4(LOSB)

50.1(LOSB)

NorthernEndofCorridor10.8(25.2)

26.1(15.1)

NorthernEndofCorridor10.8(25.2)

26.1(15.1)

LynbrookRd

29.9(LOSC)

22.8(LOSC)

SouthernEndofCorridor9.9

(15.6)14.0(10.3)

SouthernEndofCorridor9.9

(15.6)14.0(10.3)

HylandDr21.1(LOS

C)18.0(LOSB)

VDOT Planning Level Cost Estimates per Solution Set  $11,280,000 $10,420,000 $26,550,000 $11,445,000‐MovementDelayExceeds300seconds *XX(XX)‐AM(PM)PeakHour

FigureB9.PerformanceMeasureImpactsoftheFourCandidateSolutionSets,FinalVersion.(InitiallybasedonTable18ofAECOMTechnicalMemodatedOctober17,2016,however,EPDOforRCUTsandMedianCrossoverClosureswereupdatedfrom5to9andfrom34to31,respectively,asshown.OnFebruary27,thenumberofnewturnlanesprojectswasupdatedfrom11to13asshown,andtotalcostswerechangedfrom$11,155,000;$10,295,000;$26,350,000;and$11,445,000forsolutionsets1,2,3,and4,respectively,tothevaluesshowninFigureB9.

40

Thebenefitsresultingfromsuchindividualimprovements,suchasmedianclosures,extensionsoradditionsofturnlanes,changesinspeedlimits,andsoforth,maythenbeaggregatedforeachofthefoursolutionsets.FigureB9showsthat,forthefoursolutionsets,theexpectedEPDOreductionforfatalandinjurycrashesareasfollows:61(solutionset1‐arterialcapacityandthroughput);251(solutionset2‐corridorsafety);156(solutionset3—economicdevelopment);and446(solutionset4—smartandalternativetransportationsolutions).FigureB9,whichisanexcerptoftheattachedmemorandumfromAECOM,summarizestheseimpactsforeachcandidatesolutionset.Thesehavebeenprovidedtothepublic(clickhereforthewebsiteorgodirectlytohttp://www.virginiadot.org/projects/lynchburg/route_29__corridor.asp).

Planninglevelcostsforeachofthesolutionsetshavebeenidentified.Forexample,thecostofaddingaleftturnlaneateachintersection($225,000)toeightintersectionsinthecorridor(foratotalof$1.8million)isshowninTable19oftheAECOMmemorandum.Thatmemorandumgivesaroughindicationofhowthecostmagnitudevariesbyelement;forinstance,thecostofaddingacontinuoustwo‐wayleft‐turnlanefromsolutionset3($12million)ismorethansixtimesthecostofaddingtheleftturnlaneatalleightintersections($1.8million)insolutionset1.Bycontrast,theproposedrealignmentofRangoonStreet(FigureB10)suchthatRangoonStreetintersectsTerminalDriveratherthanRoute29wouldcostonly$50,000—slightlylessthanaquarterofthecostofaddinganewturnlanetoanexistingintersection.TheproposedrestrictedcrossingU‐turnintersection(RCUT)—whicheliminatesleftturnsfromtheminorapproachesaswellasthroughmovementsfromtheminorapproaches—hasaconsiderablylargercost($1.25millionperintersection).

FigureB10.AnExampleofaLow‐Cost($50,000)Improvement(realigningRangoonStreettointersectTerminalDriveratherthanRoute29).

Projectshavebeenpartiallypreparedforusewithcandidatefundingsources.ThetwochieffundingsourcesforthesecandidatesolutionsetsarebelievedtobetheHighwaySafetyImprovementProgram(HSIP)andtheVirginiaSmartScale.ForaprojecttoreceivefundingunderSmartScale,theprojectmustbescoredbythesubmitteracrossadozencriteria(forprojectsthatareinareasofunder200,000people,suchasLynchburg).Theimpactsforthreeofthosecriteriahavebeencomputed:EPDOoffatalandinjurycrashesexpectedtobeeliminatedbytheproject,EPDOoffatalandinjurycrashesexpectedtobeeliminatedbytheprojectper100millionvehiclemilestraveled,andthetraveltimereliabilityindex(TTRI).Eachcriterionrequiresamixofdataandjudgmenttocompute.Forexample,considerthethirdcriterion(TTRI)andonesolutionfromcandidatesolutionset1:closureofmediancrossovers.TheTTRIiscomputedasshowninTableB3andfoundtobe1.0.

41

TableB3.ExampleofScoringaProject(ClosureofMedianCrossovers)basedonOneSmartScaleCriterion:TTRIaStep Value ExplanationComputebuffertimeindex 0.25 BTIwasestimatedusingINRIXspeeddataanditwasfoundtovary

between0.23and0.25.Thevalueof0.25wasadoptedforthiscorridor.

Determineimpactofincidents

2.0 TheSmartScaleTechnicalGuide (p.77)suggestsanimpactvalueof2forprojects“directlyimprovingincidentfrequency”andmedianclosureisbelievedtofalldirectlyinthiscategory.

Determinefrequencyofincidentsonthenetworkusinghistoricalcrashdata

1.0 TheSmartScaleTechnicalGuide (p.77‐78)suggestsusingEquivalentPropertyDamageOnly(EPDO)valueasasurrogatemeasuretodeterminefrequencyofincidents.TheestimatedEPDOvalueforclosureofmediancrossoverswasbetween25and75,whichcorrespondstoanincidentfrequencyscoreof1.0.

Determineimpactofweatherevents

2.0 TheSmartScaleTechnicalGuide (p.78)suggestsanimpactvalueof2.0forprojectsthat“directlymitigateweathereventsbygeometricimprovements”andmedianclosureisbelievedtofalldirectlyinthiscategory.

Determinefrequencyofweathereventsusinghistoricalweatherdata

1.0 Withlackofhistoricalweatherdataavailable,theteamassumes20‐40hoursofcombinedweathereventsperyear,whichwouldcorrespondtoavalueof1.0(SmartScaleTechnicalGuidep.78).

ComputeTTRI(TravelTimeReliabilityIndex)

1.0 TTRI =BufferTimeIndex*(ImpactofIncidents*Incidentfrequency)+(Impactofweather*Weatherfrequency)=0.25*(2*1+2*1)

aVirginiaDepartmentofTransportation.SmartScaleTechnicalGuide,Richmond,(September9)2016.http://vasmartscale.org/documents/201606/sstechnicalguide_final_9_8_2016.pdf.AccessedOctober12,2016.

StepsTakeninCOR‐6(Iteration2)Duringthereviewofthecandidatesolutionsets,projectteammembersconsideredthreequestionsthatareshownwithinthePlanWorksPolicyQuestionsforCOR‐7(butwhichwerechosenbecausetheyarerelevanttoevaluatingsolutionsetsinCOR‐6):

1. Areanysolutionsetsfatallyflawed?2. Istherangeofsolutionsetsbroadenoughtoaddresscorridorgoals?3. Aretherecertaincombinationsofsolutionsetsthatareessentialtoconsider

AdraftmemorandumprovidedbyAECOMonAugust30servedasabriefingtoolfortheprojectteamonSeptember2,2016.Theteam’sanswerstotheabovequestionsguidedrevisionstothecandidatesolutionsets.

1. Areanysolutionsetsfatallyflawed?

Thesecondcandidatesolutionsetincludedonesolutionwhichwastotightentheordinancegoverningthetransportationcorridoroverlaydistrict.TheTCODcurrentlyrequiresaminimumfrontageforanylotadjacenttoaprimaryhighway(suchasRoute29)of800feet(whichmaybereducedifaccesspointsareshared).Becausetheunderlyingzoningallowsafrontageof75feet,andbecausetheareacontainsnumerousnarrowlots,arecommendedchangewastoexpandtheminimumlotfrontagefrom75feetto200feet.However,acountystaffmembernotedthatinpractice,developerstendednottobuildcommercialinfrastructureonasinglesmalllot;rather,developerstendedtoacquiremultiplelotsandthencombinethem.Becausesuchaproposedchangecouldbeseenasaddingadditionalregulations,andgiventhattheconstituencyinthis

42

locationstronglyprefersnon‐regulatoryapproaches,makingtheTCODseemrestrictive(evenifthoserestrictionswouldnotmateriallyaffectactionstakenbypersonsinthecorridor)couldmakethesolutionsetdifficulttoimplement.

Thecandidatesolutionsetsalsoincludedlocationswheretrafficsignalsmightbeaddedandwherespeedlimitsmightbedecreased.Insomecasesitmightbepossibletojustifythesesolutionsonthebasisofsafety,however,itwasnotedthatingeneral,actionssuchasreducingtravelspeedsandaddingsignalswouldreceiveaveryhighlevelofscrutiny.

Therehavebeensomeminorchangesinthecorridorthateliminatedtheneedforafewofthespecificgeometricimprovementscited.Forexample,theabandonmentofaparticularroad(QuartzRoad)bythestateDOT,theadjacentreconstructionofacommercialentrance(tobecomearight‐in/right‐outentrance),andthechangeinthemedianopeningintheproximityofthisreconstruction(tohavealeft‐turnonly),eliminatedtheneedforoneofthefourrecommendedconversionsofmediancrossoverstomedianleft‐inonlymovementsforcandidatesolutionset1.

2. Istherangeofsolutionsetsbroadenoughtoaddresscorridorgoals?

Thesolutionsetswereindeedbroad—addressingsafety,congestion,economicdevelopment,andmultimodalsolutions.Further,theimpactofthesolutionsetsonsafety,throughestimatesofhow2040crasheswouldbeaffected,waspromising.ThusgiventhegoalestablishedinPlanWorksCOR‐5of“promoteasafetransportsystemthroughoutthecounty”itwaspossibletodeterminehoweachelementineachsolutionsetaffectedthatgoal.Forexample,theimpactofextendingaleftturnlaneatthesouthernconnectionofEnglishTavernRoadandRoute29—oneoftensuchextensionsproposedforcandidatesolutionset1—wasexpectedtoreduce7.35EPDOcrashes.

Followingtheexampleofhowthecrashimpactsofsolutionsetelementswerereported,arevisionwassuggested:providesimilarindicatorsofperformancefortheremainingtwoPlanWorksgoals:“promoteaneffectivetransportsystemthroughoutthecounty”and“promoteatransportationsystemcompatiblewithexistingandfuturelanduses.”Forexample,elementsofcandidatesolutionset4includingprovidingshared‐usepathsandbettersignalcoordination.ThelatterelementcanuseperformancemeasurespresentedinCOR‐5(suchasdelayinthecorridororstoppeddelayforcertainbusinesses)andwhileaperformancemeasureassociatedwiththeformerwasnotimmediatelyapparent,itseemedplausiblethatcandidatemeasuremightbenumberofpersonsservedbyalternativemodes.

3. Aretherecertaincombinationsofsolutionsetsthatareessentialtoconsider?

SeveralpubliccommentshadsuggestedthatabypassaroundRoute29shouldbeconsidered.ThisconcepthadarisenthroughsevenpubliccommentsmadeduringthefirstpublicmeetingheldJanuary28andthenthroughanothersevenpubliccommentsmadeduringthesecondpublicmeetingonJune23rd.Additionally,oneprojectteammemberobservednumerousresponsesonsocialmediaforthisproject,askingwhythestudyhadnotconsideredabypass.Althoughthestudyhadbeenfocusedonlowercostalternativesthatcouldbeimplementedwithinthecorridor(ratherthantheadditionalcostandexpenseofnewrightofwayacquisition),thereclearlywereindividualswhofeltthescopeshouldbeexpanded.Accordingly,inreviewingthecandidatesolutionsets,onemodificationwastoclarifythereasonsforhavingtoexcludeabypassfromthecandidatesolutionsets,withsuchreasonsincludingcost,environmentalimpacts,andfeasibilityofconstruction.

43

Thesolutionsetshadconsideredthe“SmartScale”fundingsource.(WhiletheacronymreferstoSystemfortheManagementandAllocationofResourcesforTransportation,thisisaprioritizationprocessforrankingtransportationprojectssubmittedbylocalgovernments[suchasCampbellCounty]andMPOs[suchastheCentralVirginiaMPO,whichisstaffedbytheRegional2000PlanningDistrictCommissionwhosestaffhavebeenactiveinthisstudy]).However,thereareotherfundingsourcesbesidesSmartScale,suchastheHighwaySafetyImprovementProgram(HSIP)(usedforat‐graderailcrossings,highwaysafety,andbicycleorpedestriansafety);theStateofGoodRepair(SGP)program(usedforpavementsandbridges);theRevenueSharingProgram(whereVDOTandthelocalitiesmaysharethecostsofprojects);andtheTransportationAlternativesProgram(TAP)(whichcanbeusedforfundingpedestrianandbicycletrails.)NotethatTAPnowencompassesprogramswhichhadpreviouslybeenseparate:SafeRoutestoSchool,TransportationEnhancement,andtheRecreationalTrailProgram.

ReviseSolutionSetsBasedonProjectPartnerInput

AECOMrevisedthesolutionsetsbasedonthesecomments.Keychangesincluded(1)theadditionofasummarytableshowinghoweachsolutionsetaffectedperformancemeasures(FigureB9presentedinthisAppendix),(2)computationofthecostsforthesolutionsandhowtheywouldaffectscoringacrossPlanWorks,(3)additionaldiscussionoftheprosandconsofthevarioussolutionpackages,and(4)anexplanationofwhythebypasswasnotpartofthecandidatesolutionsets.Asanexampleofthefirsttwochanges,thediscussionpointsoutthatthecostsofreducingcrasheswithatwo‐wayleft‐turnlane(estimatedcostof$12million)ismorethandoublethecostofprovidingturnlaneextensionsplusnewturnlanes(roughly$5million).Asanexampleofthethirdtypeofchange,thediscussionnotesthatmodificationofthecorridoroverlaydistrictcouldrequireextraeffortonbehalfoflandownerstocoordinateaccesspoints.Finally,thediscussionexplainsthatthebypasshasnotbeenconsideredforthepasttwodecadesbuthasatotalcostofroughly$100million,whereasthetotalfundingavailablefortheentireregion(CampbellCountywhichisthefocusofthestudyplustheadjacentjurisdictionsofLynchburg,Amherst,andBedford)is$137million.

NoticethatbecauseitisarequiredperformancemeasureforSmartScale,TTRI,ratherthancrashriskreduction,wasusedtoassessreliability.

COR‐7:AdoptPreferredSolutionSetOutcomeofCOR‐7Table3inthebodyofthereport(andasdetailedinTableB4inthisAppendix)summarizestheblendedsolutionsetforthecorridorimprovements.Atotalof$19.43millioninimprovementshavebeenidentified,andpendingtheresultofapresentationbytheCampbellCountyDirectorofEconomicDevelopmenttotheCountyBoardofSupervisors,theelementsoftheblendedsolutionsetwillbepursuedthroughthreedistinctfundingsources:Virginia’sSmartScale,thedevelopmentoftheMPOConstrainedLongRangePlan,andtheHighwaySafetyImprovementProgram.Approximatelyaquarterofthesefunds(26%)wouldbeusedtoimprovelocalvehicularaccesswithinthecorridor—thatis,waysfordriverstoenterandexitlocalbusinesses,suchasthroughtheadditionofturnlanes.Almosthalfthemonies—about46%‐‐wouldsupportlocalpedestrianandbicycleaccessalongthecorridor.About28%oftheinvestmentswouldsupportthroughmobility(e.g.,closingmedianopenings).Notethatnearlyalloftheimprovementsaddresssafety,especiallytheaccessmodificationswhichreducethenumberofconflictpoints.AsdiscussedCOR‐9andasinitiatedinCOR‐6,partoftheplanningefforthasbeentopreparetheseprojectsforsubmissiontothesefundingsources.

44

TableB4.ResultsofCOR‐7:PreferredSolutionSet(Knownasthe“Blended”SolutionSetwhenPresented)

SolutionElement Numberofsites Cost ImpactAreaClosureofMedianCrossoversLowCost 2 $20,000 MobilityaClosure/ModificationofMedianCrossoversHighCost 10 $250,000 MobilityaLengthenLeftTurnLaneStorage&Taper 13 $1,300,000 LocalaccessbInstallLeftTurnLane 8 $1,800,000 LocalaccessbLengthenRightTurnLaneStorage&Taper 5 $500,000 LocalaccessbInstallRightTurnLane 6 $1,350,000 LocalaccessbVariousSignalImprovements(CalohanRoad) 1 $10,000 LocalaccessbAccessModification‐AntseyRoad 1 $25,000 MobilityaAccessModification‐RealignmentofLynbrookRoad 1 $775,000 MobilityaAccessModification‐RealignmentofLawyersRoad 1 $650,000 MobilityaAccessModification‐RealignmentofRangoonStreet 1 $50,000 MobilityaInstallRCUTMedianAccessPoints 3 $3,750,000 MobilityaSidewalks‐CalohantoRt.460 1 $2,750,000 LocalaccessbSharedUsePath‐CalohantoRt.460 1 $6,200,000 LocalaccessbSpeedLimitReduction 2 MinorCosts LocalaccessbTotalcost $19,430,000StepsTakeninCOR‐7

COR‐7waslargelycompletedinitsinitialformatthethirdpublicmeetingheldOctober27butwasalsorevisedaspartofCOR‐8andCOR‐9.Basedontheresultsofthestakeholderassessment,attendeeswereprovidedwithhandoutsregardingtheoverallprocess,wheretheemphasisofthispublicmeetingwasgearedtowardidentifyingimplementablesolutions.Twomajordeliverableswereconsidered—first,thefourcandidatesolutionsetsintheareasofsafety,capacity,economicdevelopment,and“SMART”strategies(smartandalternativetransportationsolutions),andsecond,publicreactiontotheblendedsolutionsetwassought.Commentscamefromtwosources—aroundtablediscussionandcommentsplacedonthemaps.CommentsBasedonRoundtableDiscussionsAttendeeswerepresentedwiththefoursolutionsetsasdiscussedintheearlierreporttoFHWAregardingTasks6and7.Foreachofthesesolutionsetsattendeeswereaskedthreequestions.(ThesequestionswerechosenbasedonthepolicyquestionsshowninCOR‐7,COR‐8,andCOR‐9).Withonememberfromeachteamateachtable,itwaspossibletodirectlyanswerquestionsposedbystakeholders.

Isitclearwhatthesolutionsmean?Ifnot,whatquestionsdoyouhave? Isitclearhowdifferentsolutionsrelatetotheoutcomesofthrough‐travel,safety,economic

developmentand“SMART”transportation? Arethereanysurprisesorinsightsaboutthesolutions?

Attendeeswerethenpresentedwithablendedsolutionset(seeFigureB11),wheretheblendedsolutionsetwasahybridofcandidatesolutions.

45

FigureB11.Route29BlendedSolutionMatrix

Attendees’answerstothefollowingquestionswererecorded:

Doyouthinksomepeoplemightobjecttoaparticularsolution?Whatobjectionsdoyouthinktheymighthave?

Whatcouldbedonetoimproveorenhancethesolutionpackage? Arethereanysolutionsthatyoupersonallywouldbewillingtoactivelysupportandhelpimplement?

46

Theintentionwasthateachquestionwouldbeansweredseparately,however,generallythecommentsreceivedcouldbecategorizedaseithersupportingachange,beingconcernedaboutachange,orraisingasuggestion(oradditionalcomment).Forexample,considertheeightcommentsthatwerereceivedconcerningchangingthespeedlimits.Ofthoseeightcomments,threeclearlysupportedloweringspeedlimits,fourwereconcernedwithloweringspeedlimits,andonecontainedasuggestionabouthowspeedsshouldbemanaged.(TableB5alsoshowsthatthereissomeuncertaintywhencategorizingthesecomments;forexample,comment5mightbecategorizedasbothconcernaboutspeedlimitsaswellasprovidingasuggestion.Similarly,comment7couldbecategorizedasaconcern[giventheliteraluseoftheword“concern”]orasuggestion[minimizespeedlimitchanges,astheprofessionalfacilitatorwhowasatthattableexplainedthatthecommentwassupportforloweringthespeedlimitonastretchofroadtomatchthe“bookends”oflowerspeedlimitsateitherendofthatstretchofroad..)TableB5alsoshowsthattherecanbeareasofdisagreement,asshownbetweencomments2and4regardingthe35mphspeedlimit.TableB5.ExampleofCommentsReceivedattheThirdPublicMeetingPertainingtoSpeedLimits(BasedontheDiscussionattheTables)

No. Comment HowCategorized

1 Yestoa45mphspeedlimitnorthofCalohan Support2 OKwith45mphstep‐downto35mphbetweenEnglishTavernandendofsubsection3(north

end)Support

3 ForEnglishTavernsouth,thereiscompositionoflanduses‐ slowerspeedlimitsmakesensethere.

Support

4 35mphspeedlimitistotallyunacceptable. Concern5 45mphfromEnglishTavernRoadtoendofsubsection6(atsouthend),istoolow.Moveto55

mphafterEnglishTavernRoad,butmaintainexistingshort45mphzoneleadinguptoCalohanRoadintersection.

Concern

6 Don'twanttoreducespeedlimits. Concern7 Thereareconcernsaboutraisingandloweringspeedlimitsonthecorridorandcreatingspeed

traps.Itisbettertohaveamoreconsistentspeedlimitthroughoutthecorridor.Concern

8 Ifanyspeedlimitsarereduced,stateshouldbecommittedtohiringatleastone newtroopertopatrolitregularly.

Suggestion

TableB6summarizesthe47commentsreceivedbasedonthediscussionsatthetablesasrecordedbyteammembers.Thefirstcolumnshowsthegeneralarea,suchasbuildingabypass,modifyingcrossoversorturnlanes,oraddingsidewalks.Thenexttwocolumnsshowexamplesofcommentsthat,intheteam’sopinion,exemplifiedeithersupportforimprovementsorconcernabouttheimprovements.Therightcolumnshowsexamplesofcommentsthatrelatedtoasuggestionorwhichposedaquestion.Thetotalnumberofcommentsineachcategoryisshowninparentheses.Forexample,forcrossoversandturnlanes,onecommentisshowninTableB6.Theotherthreecommentsthatwerecategorizedassupportinginthisregard(butwhicharenotgiveninTableB6)were“TheremaybetoomanycrossoversnorthofLawyersRoad,”“Noobjectiontoproposedmediancrossoverclosure,”and“Supportforclosureofsomemedians,providingrightturnonly.”

47

TableB6.SummaryofPublicCommentsfromtheThirdPublicMeeting(BasedonDiscussionsattheTables)

Area(totalcomments)

Exampleofasupportingcomment(totalcomments)

Exampleofaconcerncomment(totalcomments)

Exampleofacommentrelatedtoasuggestionoraquestion

Bypass(3) BypassfortheprojectareaandCharlottesvillewouldbringeconomicopportunityformNorthCarolina.(1)

Whileabypassincreasesflow,itmayadverselyaffectbusiness.(1)

Needtoaddresscostlylong‐rangeprojectsinaproductiveway,thatcapturespreferencebutallowsconversationforothersmaller‐scalepreferences.(1)

Crossoversandturnlanes(14)

Closureofcrossovers,andgoingsouthtogonorthon29,makessense.Itistooriskytocutacrosstwolanesoftraffictodirectlyaccessthecurrentcrossover,andmakealeftonto29north(4).

Closing medians will reduce access to businesses (2) 

Consideru‐turns,whichareeasierthantryingtocrosstraffic.

ClosethesoutherncrossoverfromEnglishTavernRoad.(8)

Extralaneorcongestionreduction(5)

SupportseffortstoreducecongestionatLawyersRoadfromwestsideofroad.(1)

None Addathirdlaneinthemostcongestedarea(Route460toEnglishTavern).(4)

RestrictedCrossingU‐Turns(RCUTs)(4)

None TheRCUTistoodangerouswiththespeed.DoRCUTscausepeopletospeeduporslowdown?(1)

ConsiderSuperstreetsatRCUTS Theconceptofthematrixwastoo

general,andthenrealizedthatthemapsprovidegreaterdetail.(3)

Sidewalks(3) Sidewalksmakesensethroughsubsections1and2,uptoLawyersRoad.Pedestrianareaswithinareaofairportmakesense.(1)

Donotsupporthighpricetagforsidewalksandmulti‐usepathsoutsideofsubsections1and2.(1)

Considerdeletingthesidewalkand/orthemulti‐usepath.Wouldbeunder‐utilizedunlessLibertyUniversityexpandssouth.BikeriderswillgototheParkway,etc.forasaferride(veryfew18‐wheeltrucks)andabetterview.(1)

SpeedLimits(8)

ForEnglishTavernsouth,thereiscompositionoflanduses‐slowerspeedlimitsmakesensethere.(3)

35mphspeedlimitistotallyunacceptable.(4)

Ifanyspeedlimitsarereduced,stateshouldbecommittedtohiringatleastonenewtroopertopatrolitregularly.(1)

Trafficsignals(4)

WouldliketoseeTrafficManagementSystemimplemented(fortrucksandout‐of‐areathroughtraffic.(1)

Morestoplightsandloweringspeedlimitwillnothelptrafficflow.(1)

Improvetimingoflights,sothattrafficdoesnothitmultipleredlights.(2)

Other(6) Mostinterestsinimprovingarterialcapacityandthroughput(speedandmobility).(1)

Thepresentationshouldhavespentabitmoretimeonexplainingthetradeoffsassociatedwithdifferentsolutions.(1)

Therearedifferentinterestsassociatedwithdifferentusers:Thosewholivewithintheprojectarea,andthoseusingasathroughroad.(4)

CommentsBasedonMapsoftheBlendedSolutionSet

Notethatthereweretwopotentiallyoverlappingsourcesofcommentsfromthethirdpublicmeeting.TheaforementionedcommentsreportedinTablesB5andB6werebasedonaspreadsheetof47comments

48

recordedonworksheetsbyoneteammemberwhosatateachtable(orcommentsmayhavebeenturnedinbyparticipants.)Thesecommentsarenotnecessarilytiedtoaspecificgeographiclocation.Another56commentswerewrittenbyattendeesonthemapoftheblendedsolutionset,andthesecommentsaretiedtoaspecificgeographiclocationandareavailableonthepublicwebsite(e.g.,http://www.virginiadot.org/projects/lynchburg/route_29__corridor.asp).Thereispotentialoverlapbetweenthesecommentsasitispossibleforanindividualtohavebothsaidacommentaloud(suchthatitwasrecordedinTableB6)andthenwrittenarelatedcommentonthemapoftheblendedsolutions(suchthatitisshownonthesectionofwebsitetitled“Route29AssessmentPublicMeeting3Comments.”

The56map‐basedcommentsshowsomedifferentareasofemphasisthanthoseshowninTableB6;forexample,therearethreecommentsthatindicateaparticularlocationisa“priority”andothercommentsareverylocation‐specific(e.g.,anoise‐relatedcommentisthat“Truckshavetobreakhardinthisarea.Loudandwindowsshake.”)Thatsaid,themap‐basedcommentsgenerallyshowareasofsupport,suggestions,andconcernforvarioustypesofimprovements,asisthecaseinTableB5.Forexample:

JustastherewereeightcommentsregardingspeedlimitsinTableB5(withsomeinfavorofmakingchangesandsomeopposed),therewerealsocommentsregardingspeedlimitsshownonthemapoftheblendedsolutionset.Atotalofsevensuchcommentswerereceived,withfourindicatingnottoreducespeedlimits(e.g.,“Donotcutspeedlimitsinthiscorridor”)andthreesupportingachangeinspeedlimits(e.g.,“CansupportlowerspeedlimitfromFNBDrnorthwardifwarranted.”)

ThereweretwocommentsshownonthemapthatrelatedtoRCUTs,withoneinsupport(“R‐cutsareagoodidea”)andonethatcouldbecategorizedassupportorconcern(“Don'tthinkR‐cutdesignwillworkatLynbrook.”)Thesevenaccess‐relatedcommentsalsoshowedareasofsupportformedianclosures(e.g.,“Isupportmedianclosuresalongthecorridor”andconcern(e.g.,“Businessowneratadjacentparcelhasanissuewithclosingthiscrossover.”)

Themap‐basedcommentsdoshowsomeareasofdisagreement,however:ofthesixcommentsthatarecategorizedasbicycle/pedestrian,twoareasuggestion“SidewalkshouldbeonnorthboundsidesouthofLawyersRdb/cmostattractionsonNBside”andfourareopposed(e.g.,“Can'tsupportsidewalks/sharedusepathinthisarea.Notenoughbenefitandhighcost.”)

ChangesintheBlendedSolutionSetBasedonComments

Thepubliccommentsalsoledtotwodemonstrablechangesintheblendedsolutionset:

Inresponsetotheseconcernsaboutthespeedlimit,theblendedsolutionsetwastoreducethespeedlimitto55MPHinthesouthernportionofthecorridor(southofCalohanRoad)andto45MPHinthenorthernportionofthecorridor(northofCalohanRoad).(Priortoimplementation,VDOTwillhavetoconductasafetyanalysisandaspeedstudy.)

Basedonthecomments,aswellasconsiderationofthecrashhistory,thesouthernEnglishTavernRoadintersectionshouldprovideonlyprovideright‐in/right‐outaccess.ThisimprovementmustbeinstalledincombinationwiththeLynbrookRoadextension(toEnglishTavernRoad)inordertoreplacethemovementsthatbecomerestricted.

49

COR‐8:ApproveEvaluationCriteria,MethodsandMeasuresforPrioritizationofProjects

OutcomesofCOR‐8

TherearetwosetsofoutcomesassociatedwithCOR‐8:themethodsforprioritizationandtheresultsofpublicopinion.

Regardingthefirstoutcome,allsourceswillbepursuedsimultaneously:HSIP,SmartScale,andtheMPO’sprioritizationprocess.

Regardingthesecondoutcome—anunderstandingofthepublic’sviewpointregardingtheseimprovements—thecommentsreceivedinthefinalpublicmeetingshow(seeCOR‐7)areasofbothsupportandconcernforthediversetypesofimprovementsproposed,withaboutaquarterofthecommentsshowingsupportforeachtypeofimprovement,aboutaquarterofthecommentsshowingaconcernabouttheimprovement,andabouthalfthecommentscontainingasuggestion,afollow‐upquestion,orsomeothertypeofstatement.Forexample,ofthe14commentsthatpertainedtoaccessmanagementimprovements(e.g.,closureofmediancrossoversortheadditionofturnlanes),fourgenerallysupportedtheconcept(e.g.,“TheremaybetoomanycrossoversnorthofLawyersRoad”),tworaisedaconcern(e.g.,“Closingmedianswillreduceaccesstobusinesses”),andeightwerecategorizedasOtherbecausetheycontainedasuggestionorquestionsuchas“FavorsnoleftturnsatLynbrookandMoormanMill;however,othersmayobjecttothisidea”[thiswasasinglequotefromoneperson]and“ClosethesoutherncrossoverfromEnglishTavernRoad.”(Theselasttwocommentscategorizedas“Other”showalsothatthereisnotalwaysafirmdelineationbetweensupportandasuggestion,asonecouldarguethattheyaregenerallysupportiveofaccessmanagement.)Thecommentstosomedegreereflectthediversenatureofthecorridorinthatitsupportsbothamobilityandalocalaccessfunction.Aspointedoutbyonerespondentatthisthirdpublicmeeting,“Therearedifferentinterestsassociatedwithdifferentusers:Thosewholivewithintheprojectarea,andthoseusingasathroughroad.”Thismatchesastatementmadebythecountyplannerattheoutsetofthestudy:noteveryonewillgeteverythingtheywantfromthisprocess,butwewantallvoicestobeheard.

StepsTakeninCOR‐8

AmeetingoftheprojectteamwasheldinLynchburgNovember14,2016wherefourquestions,eachfromCOR‐8andCOR‐9,appearedparticularlyrelevantfordetermininghowtoevaluateprojects(COR‐8)andthenhowtoprioritizecorridorimprovements(COR‐9).Generally,aswasnotedinearliermodules,itwasappropriatetoperformcertainmodulesintandem;theresultsarepresentedseparatelyhereinordertobeconsistentwiththeflowofPlanWorksmodules.Inthisparticularcase,theanswerstothequestionsfromCOR‐8andCOR‐9weredevelopedsimultaneously,andinfactoneofthequestionsfromCOR‐9(pertainingtomatchinggoalsandprioritization)waspursuedaspartofCOR‐8.Notealsothatquestionswhereshortenedinafewcasestofacilitateanin‐persondiscussion. Whatfactorsinfluenceprioritization?

Therearetwowaystoanswerthisquestion.Intermsofhowcapitalimprovementsareprioritizedwithintheformalplanningprocess,thisprocessfollowsthedevelopmentoftheMPO’sConstrainedLongRangePlan(CLRP)wherethreefactors—accessibility(20%),safety(25%),andeconomicdevelopment(25%)—playadominantroleinprioritizingprojectswithintheCLRP.However,amoreappropriateansweristhatthereareatleastthreedifferentfundingsourcesforcorridorprojects:Virginia’sSmartScale,the

50

developmentofprojectsbasedontheaforementionedMPO’sCLRP,andtheHighwaySafetyImprovementProgram(HSIP).ForHSIP,projectsareprioritizedbasedonbenefitcost,wheretheexpectedcrashesreducedaredividedbythecostoftheimprovement.

Howdoesthisprioritizationprocessreflectstakeholders’input?

Therearetwodistinctmechanisms.First,thecorridorprocessusedforPlanWorks(e.g.,thethreepublicmeetingsheldinJanuary,June,andOctober[2016]plustheearliermeetingwithselectBOSmembers[December2015]aswellasanycommentssubmittedthroughotherchannels)willgenerateprojectsofinterest.Forexample,theinterestinmultimodaltravelisevidentinthefactthatoftheslightlylessthanathirdofthe$19.43millionintotalimprovements(seeTable1)isattributedtothesharedbicycle/pedestrianusepath.Second,theMPOCLRPprocessitselfistheproductofpublicinvolvement.

Isthereaclearconnectionbetweentheprioritizationprocessandthecorridorgoals?

RecallthattheCampbellCountyComprehensivePlanidentifiedthreecorridorgoals:(1)promoteasafetransportsystemthroughoutthecounty;(2)promoteaneffectivetransportsystemthroughoutthecounty;and(3)promoteatransportationsystemcompatiblewithexistingandfuturelanduses.Wecanviewgoal(2)asrelatingtothestatewidemobilitypurposeofthecorridor,andgoal(3)asrelatingtothelocalaccessfunctionofthecorridor:goal(1)—safety—influencesbothmobilityandaccess.Table1showsthatsomeimprovements(8rows)reflectimprovedlocalaccess,andotherimprovements(7rows)reflectimprovedthroughmobility.Overall,atotalof$4.96millionisfocusedonsuchlocalaccessimprovements(forvehicles),$5.52millionisfocusedonthroughmobilityimprovements(forvehicles),andapproximately$8.95millionisfocusedonlocalaccessimprovementsforbicyclistsandpedestrians.

Aremorespecificevaluationcriterianeededtoprioritizeinvestments?

Generallytheanswerisno—giventhethreepublicmeetings,thedecisionprocessusedtoprioritizetheseprojectsrestswiththeCountyBoardofSupervisors.Thatsaid,thereisoneadditionalelementthatcouldbecomenecessaryonacase‐by‐casebasis:whennewbusinessesarebeingdeveloped,theymayrequireinformationregardingsiteplanreview.Thus,ifthereisaparticularproject(sayanintersectionimprovementandasiteplanadjacenttothatintersection),thenpossiblyadditionalconstructiondetails(suchastheexactlengthoftheturnlaneandhowthatwillinfluenceaccesstothebusiness)couldbeneeded.Thatsaid,thismorespecificevaluationcriteriawouldbecomepartofthelanddevelopmentreviewprocessastheneedarises.

COR‐9:Adoptprioritiesforimplementation

OutcomeofCOR‐9

TheCampbellCountyDirectorofCommunityDevelopmentwillbriefthecountyBOSregardingtheblendedsolutionset.ThereactionoftheBOSwillbeusedtoconfirmormodifytheblendedsolutionsetelements,andhelpdeterminetheoverallstrategyforpursuingfundingsources.AppendixCshowsthelocationsoftheseprojects(thedrawinghasbeenupdatedtoaddresschangesmadesinceOctober2016,whenaninitialversionofCOR‐7wasdeveloped).Adatabasethatcontainssome,butnotall,oftheinformationneededtosubmitprojectsforfundinghasbeenpreparedbyAECOMasofFebruary8,2017.ThatdatabaseshowshowprojectscanbepreparedforfundingthroughMPOprioritizationprocess,SmartScale,andtheHighwaySafety

51

ImprovementProgram.Whilethedatabasewillnotprovideallnecessarydataforthesethreeprocesses,itshouldprovideausefulstartingpoint.Thedatabasehasfourworksheets:(1)atableofeachimprovementandthesupportinginputdatainformation,(2)thecrashrecordsarrangedbycorridorintersection,(3)therelevantdataitemsforinputintotheMPOprocess,and(4)therelevantdataitemsforinputintoSmartScale(whichcanalsoprovidetheinputintoHSIP).Forexample,consideroneofthemedianclosures(fromAnsteyRoadtoRoute29andconversionofAnsteyRoadtoacul‐de‐sac.Thedatabaseshowsthefollowing:(1)thecostis$25,000persite;(2)theEPDOforfatalandinjurycrashes(whichisS.1underSmartScale)is80.63;(3)theEPDOrate(S.2underSmartScale)is94.97;(3)thetraveltimereliabilityindex(ED.3underSmartScale)is1.5;(4)additionaldataelementsareneededtopreparetheprojectsforSmartScale:A1‐A3,E1‐E3,ED1‐ED2,andL1,and(5)thecrashhistoryisavailableatthislocation. StepstakentoarriveattheoutcomesofCOR‐9

InNovember2016,theteamconsideredfourquestionsassociatedwithCOR‐9: Whatisthepriorityorderforimprovementstothecorridor?

TheMPOplanningmatrixwillprovideastartingpoint.However,someprojectswillriseinpriorityprimarilybecausetheassociatedfundingsourceiseasiertoobtain!Forexample,becauseHSIPhasafastertimelinethantheCLRPprocess,aprojectthatcanbefundedthroughHSIPwillbesteeredinthatdirection.Tobeclear,anyprojectsfromthelistinTable1thatareviewednegativelybytheBOSwillberemoved,buteasier‐to‐fund‐or‐buildprojectswillbepursuedfirstandtheremainingprojectswillbechosenbasedontheMPOPolicyBoard’svoting.

Whatarethenextstepsforeachidentifiedimprovement?Allprojectswillbepursuedsimultaneously,recognizingthatsomeprojectshavelongertimelines.

Howwillyouletstakeholdersknowtheresults?TheresultsofthepublicinvolvementprocesshavebeenpostedontheprojectwebsitetitledRoute29CorridorAssessment,CampbellCounty,whichisaccessibleatthisURL:http://www.virginiadot.org/projects/lynchburg/route_29__corridor.asp.Inaddition,thisinformationwillbesharedbytheBoardofSupervisorsandtheCampbellCountyPlanningCommissionasappropriate,throughstepssuchasputtingprojectsintotheprioritizationmatrixandthroughthestatewideSmartScaleprocess.

HowwilltheCampbellCountyComprehensivePlanbeupdatedbasedonthisstudy?

In2019therewillbeanupdatetothetransportationchapterbasedontheseimprovements.Atthispoint,itbelievedthattheoverlaydistrictwillnotchangebutwillberetained.Inaddition,theresultsoftwoactionswillbeincludedinthatchapter,anditisexpectedthatbothactionswilloccurbyJune2017.First,theCampbellCountyDirectorofCommunityDevelopmentwillbriefthecountyBOSregardingtheblendedsolutionset.Second,thereactionoftheBOSwillbeusedtoconfirmormodifytheblendedsolutionsetelements,andhelpdeterminetheoverallstrategyforpursuingfundingsources.

52

AppendixC.LocationofProjectsinTable1

Table1listsseveralsiteswhereimprovementsarebeingmade,suchastheadditionofleftturnlanes.FiguresC1‐C6showsthelocationoftheseimprovementsthroughoutthe6.6milecorridor.

FiguresC1andC2showthekeyforunderstandingthetypesofimprovementsmadeandthedivisionofthecorridorineightsections.FiguresC3,C4,C5,andC6showtheimprovementsineachoftheeightsections.

FigureC1.KeytoImprovementsShown(ThisdrawingwasrevisedinFebruary2017andtherevisedversionisshownhere)

54

FigureC2.OverviewofEightCorridorSections.(Section1isthenorthernmostsection;Section8isthesouthernmostsection.)

55

FigureC3.ImprovementsinSections1and3

56

FigureC4.ImprovementsinSections2and4

57

FigureC5.ImprovementsinSections5and7.

58

FigureC6.ImprovementsinSections6and8.