village action plan for village bagla jal jeevan...
TRANSCRIPT
1
DISTRICT RAJOURI
Village Action Plan For Village Bagla Under
Jal Jeevan Mission
हरघरनलसेजल
DETAILED PROJECT REPORT OF WATER SUPPLY SCHEME BAGLA, PANCHAYAT BAGLA, BLOCK QILA DARHAL, RAJOURI UNDER JAL JEEVAN MISSION IN CONVERGENCE WITH MGNREGA
Superintendent Engineer District Development Commissioner
Hydraulic, Rajouri Rajouri
S.No Components No. of Schemes Proposed
Resources with Scheme
Proposed Project Cost (in lacs)
01 Water Supply Scheme Bagla 01 JJM 351.00
02 Construction of Cattle Trough @ Rs.0.28
Lacs per trough
10 MGNREGA 2.80
03 Construction of Water Harvesting
Structure @ Rs.1.22 Lacs
10 MGNREGA 12.20
Total
21 366.00
2
INDEX
S.No. Particulars Page No.
1 Basic Information of Village 3
2
Detailed summary of the scheme 8
3
Feasibility report cum population calculation 10
4
Certificates 20
5
Salient Features 11
6
Technical Report 13
7
Source Certificate 20
8
General Abstract of cost 20
9
Abstract of Cost for Procurement and Installation of Machinery 21
10
Detailed Estimate for construction of 10000 Glns GSR 22
11
Detailed Estimate for construction of 5000 Glns GSR 25
12
Detailed Estimate for construction of Pump Room Building 29
13
Detailed Estimate for construction of Spring Covering 33
14
Detailed Estimate for Providing and Laying of Distribution system
36
15
Detailed Estimate for Providing and Laying of Rising Main 37
16 Design of Rising Mains
38
17
Typical Estimate of Cattle trough 44
18
Typical Estimate of Water Harvesting Structure 45
3
Village Action Plan (VAP)
1
Date of preparation: 24.12.2019 Date of approval in Gram Sabha: 28 .12 .2019
Date submitted to DWSM: 06.01.2020
2
Village name: Bagla GP name: Bagla Block name: Qila Darhal District name: Rajouri
State name: UT of Jammu & Kashmir
Village census code:245461
(No. of habitations and habitation names, if applicable)
I. GP Resolution
3
Aspiration of village community: FHTC to 350 number of rural house holds by year June 2020 with water supply in adequate quantity of 55 lpcd of prescribed quality on a regular basis, i.e. 3 no. of hours every day along with water supply to 7 no. of cattle troughs and 5 no. of
washing/ bathing blocks.
We, the village community, take the responsibility to own, manage, operate and maintain our
in- village water supply infrastructure. We will respect and protect our water bodies and will not
contaminate them. We will manage our grey water and save our freshwater.
It is resolved to pay 5 % of capital cost, calculated share of O&M cost and contribute in
managing water supply system.
*water quality certificate to be issued by PHED/ RWS Dept.
II.Gram Panchayat and/or its sub-committee,i.e VWSC/Paani Samiti/User Group etc. details
4
Which committee will lead the planning, implementation, management, O&M of water
supply scheme in village? (GP and/ or its sub-committee)VWSC
What is the committee called: VWSC
Chairperson name: K H Firdous Gender: Male Age: 45 Years
5
Member name Gender Age
K H Firdous M 54
Zulfqar Ahmed M 38
Mohd Muzaffer M 32
Farooq Ahmed M 45
Rabina Kouser F 30
Maneer Hussain M 60
III. General details
6
As per 2011 Census:
population:2597
No.of HHs:432
No.of women:1130
No. of men:1467
No. of children:825
No.of FHTCs:153
As per current
Panchayat/ Anganwadi
records:
Current population 2965
No.of HHs:449
No.of women:1305
No. of men:1660
No. of children:915
No.of FHTCs:360
7
Population projection:
Intermediate stage-15 years from date(18%increase over present population):215.35 Kilo
Litre/ Day(KLD)
Ultimate stage - 30 years from date (32% increase over present population ): 615.82 Kilo Litre/ Day (KLD)
8 Current cattle population (Animal husbandry records):5050
9
Agricultural cropping pattern _________________
Major crops Kharif Rabi
Sugarcane □ □
Paddy □ □
Maize □ □
Cotton □ □
Wheat □ □
Other □ □
11 Topography (plain, slope, etc.):
Plain
IV. Situation Analysis
12 Is resource mapping done? (Y/N) No
(attach the map with VAP)
13 Is social mapping done? (Y/N)
No
14
S.No
Public
Institutions
Name
Is FHTC
available? (Y/ N)
Is Rain Water Harvesting
structure available? (Y/
N)
soak pits
available?
(Y/ N)
1 School N N N
2 Anganwadi N N N
3 Health Centre N N N
4 GP building Y N N
5 Other
Total daily requirement of water
15
Present requirement of water-popn X rate 215.35 KLD
present requirement of water for cattle 72.98 KLD
No.of cattle troughs required:7
Requirement of water for intermediate stage-popn X rate 337.34 KLD
Requirement of water for ultimate stage- popn X rate 805.90 KLD
History of water supply
16
History of water supply/availability in the village, drought/scarcity/cyclone/flood or any other
natural calamity pattern, general trend of water availability:
Natural Source
17
any history of emergency arrangements like water supply through tanks, trains, etc.:
Nil
18
history of part work related to water supply, source strengthening,
Nil
19
history of water-borne diseases:
Nil
Water quality
20 Name of person identified for WQ surveillance with community using FTKs / vials:
Krishan Lal Gender: Male Age:48 Years
21 Dates identified for sanitary inspection First week of the month
22
Water quality of existing/proposed drinking water source(s) used in the water
supply scheme: source name (location): S/s at Taryathi, Kotli
Parameter Method result
Turbidity visual comparison 1.68
pH strip colour comparison 7.20
Total Hardness titrimetric method 120
Total Alkalinity titrimetric method 150
Chloride titrimetric method 60
Ammonia visual colour comparison -
Phosphate visual colour comparison Nil
Residual Chlorine visual colour comparison 0.2
Iron visual colour comparison 0.03
Nitrate visual colour comparison 4.3
Fluoride visual colour comparison 0.04
Arsenic (in hotspots) visual colour comparison Nil
Washing/bathing blocks
23
Some poor areas in the village might not have sufficient space to have a washing space and
/or a tap connection. Number of such areas identified to have a washing/bathing block:
Nil
Location name No. of
Households
Population
Source Sustainability
24 In case of groundwater source, is there a borewell recharge structure? (Y/N)
25
List of existing water bodies in the village that need to be rejuvenated/ maintained:
Traditional Water bodies are being rejuvenated/maintained by utilizing the funds of MGNREGA.
Bowlies at W. No 1 and 6
Harvesting Tank at W. No 3
Ponds at W. No 2 and 7
Grey water management
Detailed Project Reports for Grey water management are being prepared in consultation with Director Rural Sanitation J&K as it is permissible activity under SBM-G.
7
26
Grey water generated (65%ofwatersupply):__ _ KLD
No. of HHs with individual soak pits: Nil
No. of HHs that need individual soak pits: 128
No. of community soak pits needed: 30
Is there a need for waste stabilization pond?(Y/N): N
V. Water Supply Scheme
27
FHTCs will be provided under which of the following category:
□ retrofitting of ongoing schemes taken up under erst while NRDWP for the last mile connectivity
□ retrofitting of completed RWS to make it JJM compliant
□ SVS in villages having adequate ground water/spring water/local or surface water
source of prescribed quality
□ SVS in villages having adequate ground water that needs treatment
□ MVS with water grids/regional water supply schemes
□ Mini solar power based PWS in isolated/tribal hamlets
28
Water source identified: Yes
Proposed water supply scheme based on techno-economic and socio-economic appraisal:
_ _ _
Land identified for the scheme: Yes
Date by when land will be handed over to PHED/RWS Dept.: _ __
Cost of scheme: 255.00 Lacs
GoI share: 218.02 lacs State share: 24.23 lacs
Community share: 12.75 Lacs
Individual house hold contribution: 12.75 lacs (It can be in shape of labour/material/cash)
Annual O&M charges: 2 % of the contributed cost to be raised through community share.
Individual house hold monthly water tariff/user charge: 80.00
If any remote habitations, PWS identified: Nil
8
DETAILED SUMMARY OF WATER SUPPLY SCHEME BAGLA
1.Name of Scheme :- WSS Bagla
i. i.District: - Rajouri
ii. Tehsil: - Rajouri
iii. Block: - Qila Darhal
iv. Panchayat:- Bagla
2. Funding, under which program implemented NRDWP/NABARD/LIC/Any other Specify: - Jal Jeevan Mission
3. Year of implementation: 2019-20
4. Population as per census 2011:
As per census 2011: 2797 Souls
Present population 2020: 3676 Souls
Population after 15 years 2035: 5797 Souls Population after 30 years 2050:
16577 Souls
5.Household served by the Scheme
Total No.of HH as per census 2011 =548 Total present No.of HH in 2020=710
Total No.of HH covered with piped water=350
Total No.of HH yet to be covered with piped water = 360Total No.of Schools
=5Total No. of Anganwardi Centres=4Total No. of health centre
=NilGP Building =1
6. Source of water.
a).Ground water
Spring = 10 No.
b.)Water Treatment
Chlorination
c).Discharge of 10 No. Spring Spring 1 =870 GPH Spring 2 =490 GPH Spring 3 =225 GPH Spring 4 =235 GPH Spring 5 =255 GPH Spring 6 =250 GPH Spring 7 =250 GPH Spring 8 =240 GPH Spring 9 =245 GPH Spring 10 =270 GPH
9
7. Storage:-
i. Sump Tank =2 Nos. Capacity =10000 Glns eachii.Sump Tank cum Service
Reservoir=1 No. =10000 Glns at stage 1st
ii.GLSR =2 Nos.=10000 Glns each & 1 No.= 5000 Glns
8.Rising Main:-
Material = GI Pipe
G.I.Pipe 80 mm Ф = 5000 mtrs
9.Gravity Main:-
Nil
10.Distribution System:-
Material = GI Pipe(Light)
G.I pipes 65 mm Ф = 2500m
G.I pipes 50 mm Ф = 5000m
G.I pipes 40 mm Ф = 6500m
G.I pipes 32 mm Ф = 7000m
G.I pipes 25 mm Ф = 6500m
G.I pipes 20 mm Ф = 5000m
G.I pipes 15 mm Ф = 5000m
11.No.of Public Stand Post = 07 for 7 Cattle Troughs
12.No.of Household Connection to be made = 360 Nos
13.Total No. of households = 710
14.Detail of Pumping Machinery and equipment under the Scheme:-
i. Horizontal Centrifugal Pumps:-3 Nos. of Capacity 4000 GPH by 200 mtrs each
ii. Electric Sub-Station:-3 Nos. of Capacity 100 KVA each
iii. Dedicated feeder:- Yes
iv. Voltage Stabilizer:- 3 Nos. of Capacity 100 KVA each
(Er.Zulfqar Ahmed) (Er.Ghulam Nabi) (Er.Mushtaq Ahmed) Jr.Engineer Asstt.Executive Engineer Executive Engineer PHE Sub Division West PHE Division Rajouri
WATER SUPPLY SCHEME BAGLA UNDER JJM
10
FEASIBILITY REPORT
Percentage decadal growth rate of District Rajouri1971-2011 =30.82%
Total No. of Households =710
No. of Households covered with FHTCs = 350
Anganwardi Centers Covered with FHTCs =04
Govt schools Covered with FHTCs = 05
No.of Householdsuncoveredwith FHTCs =360
No. of persons per Households = 06 (Average)
Population uncovered as on January 2020 (360 x 6)= 2160 Souls
Geometric mean of Decadal Growth rate from 1971-2011 = 3.082% per Annum
Design population as on 2035 AD = x (1+r/100)n
= 2160 (1+3.082/100)15
= 3406 Souls
Add Floating population as 15% of Designed population = 511 Souls
Total = 3917Souls
Requirement of water
Total Projected population of 2035 AD = 3917 Souls
Proposed rate of water supply/capita/day =12.11 GPD
Total requirement of water per day = 47435 GPD
Water requirement for cattleCow/Buffalo(2450 X 5.50) =13475GPD
Water requirement for sheep/goat (2600 x 1.00) = 2600 GPD
Total water requirement per day =63510 GPD
Add 17% losses for transmission & distribution losses = 10796 GPD
Total water requirement per day =74306 GPD
Storage Required Total ultimatum demand of water = 74306 GPD
11
Storage required for half day demand 74306/2= 37153 GPDSay= 40000 Gallons Therefore storage required (1x5000)=5000 Gallons (3 x10000) = 30000 Gallons Already Available Storage (1x5000) =5000 Gallons Therefore Net required Storage = 40000 Gallons
Design Population for 30 years period Design population as on 2050 AD = x (1+r/100)n
= 3917 (1+3.083/100)30 = 9740 Souls
Add Floating population as 15% of Designed population = 1461 Souls Total= 11201 Souls
Requirement of water for 30 Years Design period Total Projected population of 2050 AD = 11201 Souls
Proposed rate of water supply/capita/day =12.11 GPD
Total requirement of water per day = 135644 GPD
Water requirement for cattle Cow/Buffalo (2450 X 5.50) =13475 GPD
Water requirement for Sheep/Goat (2600 x 1.0) = 2600 GPD
Add 17% losses for transmission & distribution losses = 25792 GPD
Total water requirement per day =177511 GPD
WATER SUPPLY SCHEME BAGLA UNDER JJM
SALIENT FEATURES
1) Name of the Scheme : WSS Bagla
2) Authority : Govt. of Jammu & Kashmir
3) Name of District : Rajouri
4) Name of Tehsil : Rajouri
5) Name of Block : Qila darhal
12
6) Name of Constituency : Rajouri
7) Scope of the scheme
: 1.Bagla 2.Parran 3.Sandargala 4.Mau
8) Population in year 2011as per cencus 2011
: 2797souls
9)
Present population in year 2020 With growth ratio 30.83% per annumn.
:
3696 souls
10) Designed population for next 15 year upto 2035 @ 30.83% per decade
: 5797 souls
11) Designed population for next 30 year upto 2050 @ 30.83% per decade
: 16577 souls
12) Household served by the Scheme Total No.of HH as per census 2011 Total present No.of HH in 2019 Total No.of HH covered with piped water Total No.of Schools
Total No. Of Anganwardi centre
Total No. Of health centre GP Building Total No.of HH yet to be covered with piped water.
: 548 710 350 05 04 NIL 01 360
13) Household uncovered Population uncovered @ 6 Persons/HH
: 360 3406 Souls
14) Designed population for next 15 year up to 2035 @ 3.082% increase
: 3917Souls
15) Designed population for next 15 year up to 2050 @ 3.082% increase
11201Souls
16) Source of scheme : Springs
17) Rate of water supply : 55 LPCD
18) Type of treatment : Chlorination
19) Method of distribution : Through PSPs and PCs
13
20) Estimated cost : Rs.351.00Lacs
21) Cost per capita:-
:
a)On present population(2020)
: Rs.10305.00
b) On designed population(2035)
: Rs. 8960.00
c) On designed population(2050)
Rs.3133.00
22)
Peak factor adopted : 3
23) Status of land
: Available
24) Time of completion : The work shall be completed in a period of 06 months subject to the availability of funds and key construction materials.
WATER SUPPLY SCHEME BAGLA UNDER JJM
TECHNICAL REPORT
1 Name of
the scheme
: WSS Bagla under JJM
2 Authority : Govt. Of Jammu & Kashmir
3 Tehsil : Rajouri
4 Distt : Rajouri
5 Block : Qila Darhal
6 Type of Scheme
: Gravity /Lift
7 Type of Source
: Spring
8 Planning : The objective of a public protected water supply system is to
supply safe and clean water in adequate quantity,
conveniently and as economically as possible. The planning
may be required at national Level, state level or for region or
community level. Though the responsibility of the Department
incharge of planning of water supply system in each of these
cases is different, they still have to function within the
priorities fixed by the National and State Governments taking
into consideration, the areas to be provided with water supply
and the most economical way of doing it, keeping in view the
overall requirements of the entire area.
14
9 Location : The Village Bagla is located in foothills of Pir Panchal range
330–15’–7.56’’ N and 740–12’–43.56’’ E at a distance of 130
Kms toward North-West of Jammu near India-Pakistan
Border (Actual Line of Control). The village Bagla and its
adjoining mohras fall under the jurisdiction of Tehsil Rajouri
block Qila Darhal and is about 30 km from District Head
Quarter Rajouri.
10 History &
Necessity
: The part of the habitations falling under the proposed WSS
are presently getting partial water supply from existing spring
sources. The population of the area is very scattered, so
there are some left out pockets which are uncovered. The
discharge of existing in use natural sources available on hill
slopes have depleted. The existing water supply scheme has
already out-lived its design period due to increase in
population, so the water requirement has also increased.
Village Bagla is being covered presently by way of an existing
water facility through which 350 households are being
covered with FHTCs and 360 households are yet to be
covered with piped water system by way of minimum
extension @ 55 LPCD as per guidelines ofJal Jeevan
Mission.
Government of India has been launched an ambitious
programme namely Jal Jeevan Mission (JJM) to achieve the
above target in the country by 2024 with an aim to “HAR
GHAR NAL SE JAL” by installing 100% Functional
Household Tap Connection (FHTC) in every rural household.
Subsequently, the Government of Jammu and Kashmir has
decided to connect each and every household of the Union
Territory with piped water supply by December 2021 for
ensuring water security to its population. This shall be
achieved by providing 100% household portable water supply
@ 55 LPCD in rural areas. In this connection, BIS standards
quality compliant, sustainable sources are to be identified /
created with provision for piped water supply to the each
household of the village and its adjoining Mohras located at
higher contours.Hence necessity of preparation of this
scheme has arised.
11 Scope of
the scheme
: The Water Supply Scheme Bagla has been framed to cover
the cost for providing BIS standards quality compliant
portable water to each household at the rate of minimum
15
55LPCD through functional household tap connection in
Panchayat Bagla, Distt Rajouri, J&K.
12 Design
criteria
Introduction
There are two distinct aspects to the planning of water
supplies. The estimation of the future population, water
demand in the supply area & choosing the appropriate design
period. This chapter contains the basic design criteria for
various components of water supply systems, quality
standards. This chapter is organized in the following sections:
1.Population Forecast
2.Per Capita Water Supply
3.Design Period for different elements of Water Supply
system
4.Water Quality Standards
5.Power Supply
Population Forecast
The design population will be estimated with due regard to all
factors governing future growth and development of the
project area in the industrial, commercial, educational, social
and administrative spheres. The impact of some important
extraneous factors such as in-migration from other areas on
total population shall be considered. A judgment based on
these factors would help in selecting the most suitable
method of deriving the probable trend of the population
growth in the areas of the project area from out of the
following mathematical methods.
i.Arithmetical Increase Method
ii.Incremental Increase Method
iii.Geometric Increase Method
iv.Decrease growth method
Per Capita Water Supply
Piped water supplies for communities should provide
adequately for the following as applicable:
i) Domestic needs such as drinking, cooking, bathing,
washing, flushing of toilets, gardening etc.
ii) Institutional needs.
iii) Minimum possible UFW
16
In view of the requirements of JJM/recommendations of
CPHEEO water demand for design purpose shall be
considered as 55 LPCD minimum, at consumer end,with
institutional demand and losses in the system upto 20%.
Design Period for different elements of Water Supply
system
Based on the recommendations in the CPHEEO Manual on
water supply, following design periods have been adopted for
different components of water supply system:
1.Intake well,inspection well and jack well – 30 years
2.Raw water pumping main --15 years
3.Water Treatment Plant --15 years
4.Clear water main pipe line --30 years
5.Clear water ground/overhead tank --15 years
6.Pump house building --30 years
7.Pumping equipments(electric notes pumps --15 years
8.Distribution network --30 years
Effort has been made to adhere to the above CPHEEO
guidelines.
Water Quality Standards
The water quality standards specified in the CPHEEO
Manual on water supply for Physical, chemical and
Bacteriological quality will be followed is given below in Table
1.
Table 1: Treated Water Quality Guarantees
Parameters Units Required
Output
Standard Turbidity of the Effluent
from the Clarifiers
NTU ≤ 10
Treated Water Quality
Parameters
Turbidity of filtered
water
NTU < 1.0
Color (Units on
Platinum Cobalt Scale)
TCU ≤ 5
Taste and Odor SU Unobjectionable
pH SU 7- 8.5
Fecal Coliforms No. per 100
ml
0
17
Total Coliform
Organisms
No. per 100
ml
0
Total Iron as Fe mg/l ≤ 0.1
Residual Aluminum as
Al
mg/l ≤ 0.03
Manganese as Mn mg/l ≤ 0.05
Chlorides as (Cl) mg/l 200
Sulphates as (SO4) mg/l 200
Fluorides as (F) mg/l 1.00
Nitrates (NO3) mg/l 45.00
Alkalinity mg/l 200
Losses in the System
Treatment loss (WTP) - 3% maximum (with
recirculation)
Transmission losses - 2%
Distribution loss - 15%
Zonal (Nodal) reservoirs
Design Parameter for Overhead Tank/GLSR
1 Type of reservoir GLSR
2 Type of structure RCC
3 Minimum staging height 3.0 Mt. from Ground Level
4 Shape of tank Circular –Flat Slab OR
Dome OR Rectangular
type
5 Capacity of tank One hour for ultimate
demand
Pumping Main
Design Hours – The pipeline is designed for a daily run of 12
hours to supply the designed flow. G.I.Pipe is proposed.
Economical size – Most economic pipe size to be analyzed
as per the procedure specified in the Central Public Health
18
and Environmental Engineering Organization (CPHEEO)
Manual on Water Supply and Treatment.
Velocity in pipeline – The design velocity in the transmission
mains and feeder mains should preferably be not less than
0.8m/s and in no case greater than 3m/s.
Terminal pressure – The terminal pressure in the
transmission mains at the point of discharge into various OHT
reservoirs will be 1 to 1.5 m.
Internal Pressure – The operating pressure on the pipe
would be equal to the static pressure plus the frictional head.
The frictional head loss through the pumping main is to be
calculated with the Hazen Williams formula. The pipes are
internally lined and hence the roughness coefficient value (C
value) will be considered as 140 for analyzing the frictional
head loss. Head loss on account of fixtures and bends is to
be considered at 10% of the total frictional head loss.
Valves – The test pressure of the valve bodies should not be
less than (i) 1.5 times of the operating pressure or (ii)
operating plus water hammer pressure; whichever is more.
All types of valves including butterfly valves, sluice valves,
washout valves, pressure reducing valves and air valves
provided on the pumping main including the pump delivery
main, are proposed to have a pressure rating of PN 1.0-1.6.
13 Design
norms and
guidelines
: The present population in year 2020 has been worked out at
growth rate of 3.082% per annum.
ThePipe network has been designed for 30 years design
period w.e.f. Year 2020 (Base Year) up to year 2050 (design
year) but the Storage has been designed for 15 years design
period w.e.f. Year 2020 (Base Year) up to year 2035 (design
year) as per guidelines of CPHEEO manual.
Pipe lines have been designed using modified
Hazen William formula.
Hf = L (Q/CR)1.84
994.62 x D4.84
Cost of civil structures has been worked out at SSR of 2012
with 30% appreciation keeping in view the prevailing market
appreciation.
14 Population
projection
Population projections and requirement of water is worked out
as under:
19
and
requirement
of water
Present uncovered population works out to be 3406 souls up
to 2020. The designed population including average 3.082%
per annum increase on present population for the next 15
years works out to 3917 souls. Accordingly the requirement
of water for the designed population works out to 74306 GPD
@ 12.11 Gallon/capita/day.
15 Proposal : After thorough investigation and survey work, It is proposed
to tap 10 No.Spring sources at different location. The
discharge of these 10 No. springs is about 55 Gallon/min i.e;
3300 GPH or 79200GPD.The discharge of exiting 3 No.
tapped spring is1550 GPH or 35200GPD. These sources are
24X7 available for supply of portable drinking water to the
area. It is also proposed to install flow meters,level
transmitters and GPRS/GSM modem on every storage tank
for real time monitoring of the supply system.
16 Service
Reservoir/
Sump
Tanks
: It is proposed to construct two No.10000 Glns capacity sump
tank at different location for storage of water and then lift. It is
also proposed to construct Two No. Reservoirs of capacity
10,000 Glnseach at Bagla Top and at Parran Top for
providing drinking water to the public. It is also proposed to
construct one No. GSR of 5000 Glns capacity each at
Sangargala and Lower Parran for supply of water. It is also
proposed to construct one No.10000 Glns Sump Tank cum
service reservoir at central Parran for storage and supply of
water to the area.
17 Rising
Mains /
Gravity
mains
: It is proposed to lay 03 No.Independent 80 mm dia Rising
main from sources to existing Ground Service Reservoirs at
Bagla Top, Central Parran and Parran Top.
18 Pumping
machinery
: It is proposed to install Three Nos. HC pump sets with
specification 4000 GPH x 200mtr head and at base stage,
Stage 1st for pumping.
19 Electric Sub
Station
: Three Nos. 100 KV Electric Sub stations shall be erected at
base stage, stage 1st including extension of H.T / L.T Lines.
A provision for installation of three Nos. 100 KVA voltage
Stabilizers at base stage, stage 1st has also been kept in the
project report.
20 Distribution
system
: A well designed distribution system shall be laid from the
reservoirs to each and every household.
21 Other civil
structures
: It is proposed to construct Three No. Pump rooms at base
stage, Stage 1st for install pumping machinery.
20
22 Status of
Land
: Part land is available for construction of civil structures and
other allied work of the scheme. For remaining required land,
effort shall be made to utilise the State Land, if available,
otherwise proprietary land shall be acquired after following
the due land acquisition process.
23 Estimated
cost
: The work is estimated to cost Rs 351.00Lacsat rates of SSR
of 2012 with 30% appreciation, keeping in view the prevailing
market appreciation
24 Time of
completion
: The work shall be completed in a period of 6 months subject
to the availability of funds and key construction materials.
WATER SUPPLY SCHEME BAGLA UNDER JJM
SOURCE CERTIFICATE
Certified that:
1. The proposed source of scheme is free from any dispute.
2. Discharge available is adequate and will cater the need of designed population proposed to be covered under the scheme.
3. The source taped will not adversely affect the water supply scheme (in case the same has been tapped from the existing scheme).
4. The scheme has been properly investigated and proposals are viable from the Techno – economic consideration.
WATER SUPPLY SCHEME BAGLA UNDER JJM
GENERAL ABSTRACT OF COST
S.No.
Particulars Amount ( In lacs)
1 Cost A/c of Const. of 10000 glns Sump tank/GSR’s 5 Nos. @ 5.84 lacs/each.
29.20
2 Cost A/c of Const. of 5000 glns Sump tank/GSR’s 2 Nos. @ 3.58 lacs/each.
7.16
Cost A/c of Const. of Pump Room 3 Nos. @ 6.37 lacs/each. 19.11
3 Cost A/c of Const. of spring covering 10 Nos. springs @ Rs. 0.54 lacs/each
5.40
21
4 Cost A/c of Providing and laying of Distribution network 131.31
5 Cost A/c of Providing and laying of Rising Main 47.26
6 Cost on A/c of installation of pumping machinery, installation of 100 KVA stabilizers, and errection of electric substation.
64.57
7 Provision for installation of Flow metersfor 5 stations @ 2.00Lacs/No. 10.00
8 Provision for installation of level transmitters for 5 stations @ 1.00Lacs/No
5.00
9 Provision for installation of GPRS/GSM modem with UPS @ 1.00Lacs/No
1.00
10 Provision for construction of fencing around civil structure 3.00
11 Provision for Survey work and expenses on account of preparation of DPR (LS)
2.00
12 Provision for land compensation 10.00
Total 335.01
Add on account of work charge and contingencies @2.50% except item No. 6,7,8,9,10,11 & 12
5.98
Add on account of Consultancy charges @ 3.00%, except item Nos. 11 & 12
9.69
Grand Total
350.68
Say Rs. 351.00 Lacs
WATER SUPPLY SCHEME BAGLA UNDER JJM
ABSTRACT OF COST FOR PROCUREMENT AND INSTALLATION OF PUMPING MACHINERY
S.No.
Particulars Amount (Rs. In lacs)
01. Procurement and installation of 4000GPH X 200mtrs
statical headHC pump set at Base Stage and stage1st
including standby for 3 Nos. Pumping station
6 Nos. @ Rs.6.00 lacs each
36.00
Procurement and installation of 3 Nos.100 KVA voltage
stabilizer
9.00
02 Errection of electric sub station
3 Nos.@ Rs.6.00 Lacs/No.
18.00
Total Rs.63.00
22
Add on account of work charge and contingencies
@2.50%
1.57
Total 64.57 Lacs
WATER SUPPLY SCHEME BAGLA UNDER JJM
DETAILED ESTIMATE FOR CONSTRUCTION OF 10000 GALLON CAPACITY SERVICE RESERVIOR
S.No
Particulars Unit QTY. Rate Amount
1 Clearing jungle including uprooting of rank vegetation bushes etc. 8.50x8.50 = 72.25 m2
Sqm
72.25
5.85
423.00
2 Earth work in excavation in 80% all kind of soil and 20% ordinary rock π/4(6.70+8.70)2 x1.0 = 46.54 m3
2 For Pipe 2 x 6.25 x 0.70 x 0.50 = 4.37 m3
Drain Π/4 x (9.102-7.502) x .30 = 6.25 m3 Total = 57.16 m3
Cum
57.16
292.55
16724.00
3 Providing and laying of cement concrete in 1:4:8 mix with 40mm nominal size of aggregate. π/4(6.10)2 x0.20 =5.84 m3
π/4(7.502- 5.102) x0.15 =3.56 m3 Drain bed Π/4 x (8.702-7.52) x 0.10 = 1.52 m3 Total = 10.92m3
Cum
10.92
3112.80
33992.00
4 Providing and laying of cement concrete in 1:2:4 mix Drain Π/4 x (8.702-8.302) x 0.30 = 1.60 m3
Π/4 x (7.92-7.502) x 0.30 = 1.45 m3
Π/4 x (8.702-7.502) x 0.10 = 1.52 m3
Total = 4.57 m3
Cum 4.57 4575.00 20935.00
5 Filling of excavated earth in to trench 40% of item no.(2) = 40% x 57.16 =22.86 m3
Cum
22.86
85.25
1949.00
6 Providing and laying reinforced cement concrete in 1:1.50:3 mix using 20 mm nominal size of aggregate. Bed = π/4(5.10)2 x0.15 = 3.06 m3 Gola= πx4.80x1/2x0.30x0.30 = 0.67 m3
Wall= π/4(5.102- 4.802) x2.85 = 6.64 m3 Total = 10.37 m3
Cum
10.37
6280.95
65133.00
23
7 Providing and laying reinforced cement concrete in 1:2:4 mix using 20 mm nominal size of aggregate. Dome=2π x 3.0 x 1.20 x 0.10= 2.26 m3
Beam= π/4(5.702- 4.802) x0.20 =1.48 m3
D/d M.H= 1x0.60x 0.60 x0.10= (-) 0.04 m3
Total = 3.70 m3
Cum
3.70
6033.05
22322.00
8 Centring and shuttering incl. strutting, propping etc. and removal of form for; Foundation footing=πx6.10x0.20=3.83 m2
Drain Π x 7.90 x .30 = 7.44 m2 Π x 8.30x .30 = 7.81 m2 Π x 8.70 x 0.40 = 10.92 m2
= 30.0 m2
Sqm
30.00
179.25
5377.00
9 Centring and shuttering incl. strutting, propping etc. and removal of form for; Wall outer side= πx5.10x 3.00 =48.04 m2
Wall inner side=πx4.80x2.85 = 42.95 m2
Total = 90.99 m2
Sqm
90.99
342.80
31193.00
10 Centring and shuttering incl. strutting, propping etc. and removal of form for Beam= 2 π x (5.70+5.10)/2 x 0.20
= 6.78 m2
Sqm
6.78
305.70
2073.00
11 Centring and shuttering incl. strutting, propping etc. and removal of form for Dome = 2 π x 3.0 x 1.20 = 22.60m2
Sqm
22.60
1425.70
32232.00
12 Extra for centring and shuttering in circular work (20% of respective centring and shuttering items) Qty.vide item No.7 = 3.70m2
Sqm
3.70
35.85
133.00
13 Extra for centring and shuttering in circular work (20% of respective centring and shuttering items) Qty.vide item No.9 = 90.99 m2
Sqm
90.99
68.56
6238.00
14 Extra for centring and shuttering in circular work (20% of respective centring and shuttering items) Qty.vide item No.10 = 6.78 m2
Sqm
6.78
61.14
415.00
15 15mm thick cement sand plaster in 1:3 mix. Wall outer side=πx5.10x3.00 = 48.04 m2
Wall inner side= π x 4.80 x 2.85 = 42.95 m2
Beam=2πx (5.70+5.10) x 0.20 = 6.78 m2
2 Dome= 2 x π x 3.0 x 1.20 = 22.60 m2
Total = 120.37 m2
Sqm
120.37
248.90
29960.00
16 Extra for plaster in case of circular work. Qty. vide item No. 15 = 120.37 m2
Sqm
120.37
19.90
2395.00
24
17 Reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete. Cold twisted bars Qty. vide item No.6&7 = 14.07 m3 @ 80 Kg/m3 = 1126 Kg = Say 1150 Kg
Kg
1150
71.00
81650.00
18 50 mm thick cement concrete flooring in 1:2:4 mix. π/4 x (7.502- 5.102) = 23.73 m2
Sqm
23.73
370.20
8785.00
19 Dry stone masonry. 15 x 0.60 + 0.80 x 0.90 =9.45 m3
2
Cum
9.45
1304.45
12327.00
20 Supply of manhole cover. One No.
No.
1
1800.00
1800.00
21 Supply of PVC air bend = 4 No. No 4 89.00 356.00
22 Providing and incorporating during concreting GP sheet strip water seal 1.25mm thick at joints so as to form a continuous barrier .
π x 3 x 4.95x0.25= 11.65 m2 @ 7kg/m2=82KG
Kg
82.00
52.00
4243.00
23 Steel work for ladder = 60 Kg Kg 60.00 83.85 5031.00
24 Finishing of wall with cement paint Wall inner side=πx 4.80x 3.05 = 45.96 m2
Dome= 2 x π x 3.0 x 1.20 = 22.60 m2
Total = 68.56 m2
Sqm
68.56
56.90
3902.00
25 Extra for water proofing material Kg 100 43.95 4396.00
26 Labour engaged for fixing of manhole cover and PVC air bend. 01 No.Mason for 01 day 02 No. Mazd. For 01 day
Day Day
1 2
450.00 300.00
450.00 600.00
MATERIAL CONSUMPTION CHART
ITEM No. QTY
CEMENT SAND AGGREGATE STEEL
Rate Qty.
03)C. Conc.
1:4:8
10.92 m3 3.40 37.12 5.15 10.31
04)C. Conc. 1:2:4
4.57 m3 6.40 29.24 2.03 4.06
06)R.C.C. 1:1.50:3
10.37 m3 8.00 82.96 4.32 8.64
07)R.C.C. 1:2:4
3.70 m3 6.40 23.68 1.64 3.28
15)15 mm plaster
1:3 Mix
120.37 m2
21.94% 26.40 2.00 -------------------
25
18)50mm thick
Flooring 1:2:4
19.15m2 0.404 7.73 0.42 0.84
TOTAL Say =
207.13 207Bags
15.56 m3
27.13 m3 1150 Kg
CARRIAGE OF MATERIAL
27 Cement/Steel 40 Km by M/T Cement = 10.35 MT Steel = 1.15MT Total = 11.50 MT
MT
11.50
268.61
3089.00
28 Sand 40 Km by M/T Qty. 15.56m3
cum
15.56
302.18
4701.00
29 Aggregate 40 Km by M/T Qty. 27.13 m3
cum
27.13
302.18
8198.00
30 Cement/Steel 2000 mtr. by H/L Cement = 10.35 MT Steel = 1.15 MT
MT MT
10.35 1.15
287.60 617.81
2968.00 710.00
31 Sand/Aggregate 2000 mtr. by H/L Sand = 15.56m3
Aggregate = 27.13 m3 Total= 42.69 m3
cum
42.69
691.33
29512.00
32 Stone/Boulders 1000 mtr. By H/L Qty. =9.45 m3
cum 9.45 571.17 5397.00
TOTAL 449609.00
Add 30% above on all items except item Nos.(26) i.e. on ₹ 448559.00
134567.00
GRAND TOTAL 584176.00
Say Rs.5.84 Lacs
WATER SUPPLY SCHEME BAGLA UNDER JJM
DETAILED ESTIMATE FOR CONSTRUCTION OF 5000 GALLON CAPACITY SERVICE RESERVIOR
S.No
Particulars Unit QTY. Rate Amount
1 Clearing jungle including uprooting of rank vegetation bushes etc. 8.00x8.00 = 64 m2
Sqm
64.00
5.85
374.00
2 Earth work in excavation in 80% all kind of soil and 20% ordinary rock π/4(4.20+7.20)2 x0.70 = 17.85 m3
2 For Pipe 2 x 6.25 x 0.70 x 0.50 = 4.37 m3
Drain π/4(6.62- 5.402) x0.50 =5.65 m3
26
Total = 27.87 m3 Cum 27.87 292.55 8153.00
3 Providing and laying of cement concrete in 1:4:8 mix with 40mm nominal size of aggregate. π/4(4.20)2 x0.20 =2.77 m3
π/4(5.402- 3.402) x0.15 =2.07 m3
drain π/4(6.62- 5.402) x0.100 =1.13m3 Total = 5.97m3
Cum
5.97
3112.80
18583.00
4 Filling of excavated earth in to trench 40% of item no.(2) = 40% x 27.87 =11.15 m3
Cum
11.15
85.25
950.00
5 Providing and laying of cement concrete in 1:2:4 mix with 20mm nominal size of aggregate. Drain π/4(6.62- 5.402) x0.100 =1.13m3 π/4(5.802- 5.402) x0.300 =1.05m3 π/4(6.62- 6.202) x0.300 =1.20m3 Total = 3.38 m3
Cum
3.38
4575.00
15463.00
6 Providing and laying reinforced cement concrete in 1:1.50:3 mix using 20 mm nominal size of aggregate. Bed = π/4(3.40)2 x0.15 = 1.36 m3
Gola= πx3.10x1/2x0.30x0.30 = 0.43 m3
Wall= π/4(3.402- 3.102) x3.00 = 4.59 m3 Beam= π/4(3.802- 3.402) x0.20 = 0.45 m3
Total =6.83 m3
Cum
6.83
6280.95
42898.00
7 Providing and laying reinforced cement concrete in 1:2:4 mix using 20 mm nominal size of aggregate. Dome=2π x 1.90 x 0.80 x 0.10 = 0.95 m3
D/d M.H= 1x0.60x 0.60 x0.10= (-) 0.04 m3
Total = 0.91 m3
Cum
0.91
6033.05
5490.00
8 Centring and shuttering incl. strutting, propping etc. and removal of form for; Foundation footing= π x 4.20 x 0.20 = 2.63 m2
Drain Π x 5.80 x .30 = 5.46 m2 Π x 6.20x .30 = 5.84 m2 Π x 6.60 x 0.40 = 8.28 m2
Total = 22.21 m2
Sqm
22.21
179.25
3981.00
9 Centring and shuttering incl. strutting, propping etc. and removal of form for; Wall outer side= π x 3.40 x 3.00
= 32.03 m2
Wall inner side= π x 3.10 x 3.00 = 29.20 m2
Total = 61.23 m2
Sqm
61.23
342.80
20990.00
27
10 Centring and shuttering incl. strutting, propping etc. and removal of form for Beam= 2 π x (3.80+3.40)/2 x 0.20 = 4.52 m2
Sqm
4.52
305.70
1381.00
11 Centring and shuttering incl. strutting, propping etc. and removal of form for Dome = 2 π x 1.90 x 0.80 = 9.54 m2
Sqm
9.54
1425.70
13601.00
12 Extra for centring and shuttering in circular work (20% of respective centring and shuttering items) Qty.vide item No.7 = 2.63 m2
Sqm
2.63
35.85
94.00
13 Extra for centring and shuttering in circular work (20% of respective centring and shuttering items) Qty.vide item No.8 = 61.23 m2
Sqm
61.23
68.56
4198.00
14 Extra for centring and shuttering in circular work (20% of respective centring and shuttering items) Qty.vide item No.9 = 4.52 m2
Sqm
4.52
61.14
276.00
15 15mm thick cement sand plaster in 1:3 mix. Wall outer side= π x 3.40 x 3.00
= 32.03 m2
Wall inner side= π x 3.10 x 3.00 = 29.20 m2
Beam= 2 π x (3.80+3.40) x 0.20 = 4.52 m2
2 Dome = 2 x π x 1.90 x 0.80 = 9.54 m2
Total = 79.29 m2
Sqm
79.29
248.90
19735.00
16 Extra for plaster in case of circular work. Qty. vide item No. 14 = 79.29 m2
Sqm
79.29
19.90
1577.00
17 Reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete. Cold twisted bars Qty. vide item No.5&6 = 7.74 m3 @ 90 Kg/m3 = 696.60 Kg = Say 700 Kg
Kg
700
71.00
49700.00
18 50 mm thick cement concrete flooring in 1:2:4 mix. π/4 x (5.402- 3.402) = 13.81 m2
Sqm
13.81
370.20
5112.00
19 Dry stone masonry. 15 x 0.60 + 0.80 x 0.90 =9.45 m3
2
Cum
9.45
1304.45
12327.00
20 Supply of manhole cover. One No.
No.
1
1800.00
1800.00
21 Supply of PVC air bend = 4 No. No 4 250.00 35600
22 Providing and incorporating during concreting GP sheet strip water seal 1.25mm thick at joints so as to form a continuous barrier .
28
π x 3 x 3.25x0.25 = 7.65 m2 @ 7kg/m2 =53.55Kg Say 55 Kg
Kg 55.00 52.00 2860.00
23 Steel work for ladder = 60 Kg Kg 60.00 98.15 5889.00
24 Finishing of wall with cement paint Wall outer side=πx3.40x1.50 = 16.01 m2
Beam=2 π x (3.80+3.40)x0.20 = 4.52 m2
2 Dome= 2 x π x 1.90 x 0.80 = 9.54 m2
Total = 30.00m2 .
Sqm
30.07
56.90
1710.00
25 Extra for water proofing material Kg 60 43.95 2637.00
26 Labour engaged for fixing of manhole cover and PVC air bend. 01 No.Mason for 01 day 02 No. Mazd. For 01 day
Day Day
1 2
450.00 300.00
450.00 600.00
MATERIAL CONSUMPTION CHART
ITEM QTY
CEMENT SAND AGGREGATE STEEL
Rate Qty.
C. Conc. 1:4:8
5.97 m3 3.40 20.29 2.81 5.62
C. Conc. 1:2:4
3.38 6.40 21.63 1.47 2.94
R.C.C. 1:1.50:3
6.83 m3 8.00 54.64 3.07 5.80
R.C.C. 1:2:4
0.91 m3 6.40 5.82 0.40 0.77
15 mm plaster 1:3 Mix
79.29 m2 21.94% 17.39 1.42 -------------------
50mm thick
Flooring 1:2:4
13.81m2 0.404 5.58 0.30 0.60
TOTAL Say =
125.35 125
Bags
9.47 m3 15.73 m3 700 Kg
CARRIAGE OF MATERIAL
27 Cement/Steel 40 Km by M/T Cement = 6.25 MT Steel = 0.70 MT Total = 6.95 MT
MT
6.95
268.61
1866.00
28 Sand 40 Km by M/T Qty. 9.47 m3
Cum
9.47
302.18
2861.00
29 Aggregate 40 Km by M/T Qty. 15.73 m3
Cum
15.73
302.18
4753.00
30 Cement/Steel 2000 mtr. by H/L Cement = 6.25 MT
MT
6.25
287.60
1797.00
29
Steel = 0.70 MT MT 0.70 617.81 432.00
31 Sand/Aggregate 2000 mtr. by H/L Sand = 9.47 m3
Aggregate= 15.73 m3 Total= 25.20 m3
Cum
25.20
691.33
17421.00
32 Stone/Boulders 1000 mtr. By H/L Qty. =9.45 m3
Cum 9.45 571.17 5397.00
TOTAL 275672.00
Add 30% above on all items except item Nos.25 i.e. on ₹ 274422.00
82386.00
GRAND TOTAL 358058.00
Say Rs.3.58 Lacs WATER SUPPLY SCHEME BAGLA UNDER JJM
DETAILED ESTIMATE FOR CONSTRUCTION OF PUMP ROOM CUM
OPERATER QUARTER
S.No
Particulars Unit QTY. Rate Amount
1 Clearing jungle including uprooting of rank vegetation bushes etc. 10.00x14.00 = 140.00 m2
sqm
140.00
5.85
819.00
2 Earth work in excavation in 80% all kind of soil and 20% ordinary rock L/W = 2 x27’-6” x3’ x3’-6” = 577.50 cft S/W = 3 x9’-9” x3’ x3’-6” = 307.12 cft
Total = 884.62 cft Or 25.04 m3
cum
25.04
292.55
7325.00
3 Providing and laying of cement concrete in 1:4:8 mix with 40mm nominal size of aggregate. L/W = 2 x27’-6” x3’ x0’- 6” = 82.50 cft S/W = 3 x9’-9” x3’ x0’- 6” = 43.87 cft
U/floor=(15’x12’+8.X12’)6” =69.00 cft
Total = 195.37 cft Or 5.53 m3
cum
5.53
3112.80
17213.00
4 Filling of excavated earth in to trench 40% of item no.(2)= 40% x 25 = 10 m3
cum
10.00
85.25
852.00
5 Providing and laying cement concrete in 1:3:6 mix using 20 mm nominal size of aggregate with 30% boulders. 1st Step L/W= 2 x27’ x2’-6” x1’- 6” = 202.50 cft S/W = 3 x10’-3” x2’-6” x 1’-6” =115.31 cft 2nd Step
L/W = 2 x26’-6” x2’-0” x1’- 6”= 159.00 cft S/W = 3 x10’-9” x2’-0” x1’- 6” = 96.75 cft 3rd Step
L/W = 2 x25’-9” x1’-3” x1’- 6” = 96.75 cft S/W = 3 x11’-6” x1’-3” x1’- 6” = 64.68 cft
30
Total = 734.80 cft Or 20.80 m3
C.concrete70%=14.56m3x70%=11.76 m3 Boulders 30% =6.24 m3x 30%=5.04 m3
cum cum
14.56 6.24
3707.40 327.05
53980.00 2040.00
6 40 mm D.P.C. in 1:2:4 mix using 20 mm nominal size of aggregate.
L/W = 2 x25’-9” x1’-3” = 64.38 sft S/W = 3 x11’-6” x1’-3” = 43.12 sft
Total = 107.50 cft Or 9.98 m2
sqm
9.20
227.50
2093.00
7 Brick masonry in cement mortar 1:6 mix. L/W = 2 x25’-6” x10’ x 9” = 382.50 cft S/W = 3 x12’-0” x10’ x 9” = 270.00 cft
Parapet L/W =2x 25’-6” x1’-6”x 4.5” = 28.69 cft S/W =3 x12’-0” x1’-6” x 4.5” = 20.25 cft
D/d opening Door = 1x 4’x8’-6”x9”=(-)25.50 cft Window=1x3’x8’-6”x9” =(-) 19.12 cft Window= 3x3’x6’x9” =(-) 40.50 cft Beam =1x25’-3”x9”x9” =(-)14.20 cft =2x6’x9”x9” =(-)6.75 cft Total Deduction =121.07 Cft Net total after D/d = 567.62 cft Or 16.31 m3
cum
16.31
4551.45
74234.00
8 Extra for brick masonry over plinth level Qty. vide item No.(7) =16.31 m3
cum
16.31
706.50
11523.00
9 Structural steel work including frame/ shutter Qty.(L.S) =350 Kg
Kg
350.00
80.60
28210.00
10 Providing and fixing MS steel for door/windows with frame 40 x 40 x 6 mm angle iron Qty. Vide item 7 D/d of door & windows= 100.12 cft Or 133.49 Sft Or 12.49 m2
sft
12.49
3171.40
39610.00
11 50 mm thick cement concrete flooring in 1:2:4 mix with 20 mm nominal size of aggregate. 15’ x12’+8’x12’ =276.00 sft Or 25.64 m2
sqm
25.64
370.20
9491.00
12 R.C.C. in1:2:4 mix with 20 mm nominal size of aggregate. Slab = 29’-3” x 17’-6” x 4.50”= 191.95 cft Beam = 25’x 9” x 9” =14.20 cft 2 x 6’ x 9” x 9” = 6.75 cft
Total = 212.90cft Or 6.00 m3
cum
6.00
5776.45
34658.00
13 Reinforcement for R.C.C works including straightening, cutting, bending, placing in
31
position and binding all complete. Cold twisted bars Qty.= 550 Kg
Kg
550
71.00
39050.00
14 Making plinth protection 50 mm thick in 1:3:6 mix 2 x (29’-3” +13’-6”) x 2’ =171.00 sft Or 15.88 m2
sqm
15.88
328.30
5213.00
15 Centring and shuttering incl. strutting, propping etc. and removal of form for; Foundation footing 1st Step L/W=2x2(27’ x1’-6”) = 162sft S/W=2x3(10’-3” x1’-6”) = 92.25 sft 2nd Step L/W=2x2(26’-6” x1’-6”) = 159.00sft S/W=2x3(10’-9” x1’-6”) = 96.75 sft 3rd Step L/W=2x2(25’-9” x1’-6”) = 154.50sft S/W=2x3(11’-6” x1’-6”) = 103.50 sft Total =768.00 sft Or = 71.34 m2
sqm
71.34
179.25
12787.00
16 Centring and shuttering incl. strutting, propping etc. and removal of form for; Slab Room= 15’ x12’ = 180 sft Kitchen=8’ x 12’ =96 sft Gallery= 74’-6” x 2’ =149 sft Beam = 2 x 25’-3”x9” = 37.87 sft
=2x2x6’x9” = 18.00 sft Total = 480.87 sft = 53.96 m2
sqm
53.96
372.40
20094.00
17 Centring and shuttering incl. strutting, propping etc. and removal of form for; Edges of slab=74’-6” =82 Rft =22.35 Rmt
Rmt
22.35
176.55
3945.00
18 15mm thick cement sand plaster in 1:4 mix . Outer side including parapet: L/W2x25’-3”x11’-6” = 568.12 sft-------(A) S/W=2x12’ x 11’-6”) = 684.75 sft-------(A) Room inner side = 2x(15’+12)x 10’ = 540.00 sft-------(B) Kitchen =2x (8’+12’)x 10 =400.00 sft------------(B) Parapet inner =2x(25’-3”+12’-”)x1’-6”=111.75Sft-----(A) Top= 74’-6” x 4.5”= 27.93 Sft ---------(A) Roof=(15’x12’+8’x12’)=276 sft--------(B) Gallery=74’-6” x 2’ =149.00sft---------(B) Total =2348.80 sft D/d Door/window Qty.vide itemNo.10=133.49x 2=267.00sft
32
Net Qty.=2348.80-267.00=2081.80 Sft Or = 193.40m2
sqm
193.40
184.65
35711.00
19 White washing. Qty. vide item No.(18-B)= 1365.00 sft D/d opening item. (10)= (-) 133.49 sft Total =1231.51 sft or 114.41 m2
sqm
114.41
15.90
1819.00
20 Finishing of wall with cement paint Qty. vide item No.(18-A) = 983.80 sft D/d opening item(10) =(-) 133.49 sft Total = 850.31 sft Or 79.00 m2
sqm
79.00
56.90
4495.00
21 Priming coat on steel work Qty vode item No.(10)
2 x 133.49sft or 24.80m2
sqm
24.80
27.80
689.00
22 Painting on steel work. Qty. vide item No. (21) = 24.80 m2
sqm
24.80
69.30
1718.00
23 Extra for water proofing material Kg 50 43.95 2197.00
24 Providing and fitting of electric fitting including supply of material.(To be paid as per actual) L.S.
LS
10000.00
Rs.419766.00 MATERIAL CONSUMPTION CHART
ITEM No. QTY
CEMENT SAND Bajri STEEL Bricks
Rate Qty.
C. Conc. 1:4:8
5.52 m3 3.40 18.77 2.60 4.62
C.Conc. 1:3:6
12.50 m3 4.40 52.80 5.88 11.12
40mm thick DPC 1:2:4
3.04 m3 6.40 19.45 1.30 2.58
50mm thick Flooring 1:2:4
25.64m2 0.404 10.35 0.56 1.12
R.C.C 1:2:4
6.00 m3 6.40 38.40 2.58 5.34 550
B. Mas. 1:6
16.31m3 1.20 20.38 4.34 -------------
8000
Plinth prot. 1:3:6
0.80 m3 4.40 3.52 0.38 0.71
15 mm plaster 1:4 Mix
193.40 m2
0.17 33.80 3.48 -------------
TOTAL Say=
197.47 198
Bags
20.94 m3
=21 m3
25.50 m3
550 Kg
8000 Nos.
CARRIAGE OF MATERIAL
25 Cement/Steel 30 Km by M/T Cement = 9.90 MT
33
Steel = 0.55 MT Total = 10.45 MT
MT
10.45
268.61
2806.00
26 Sand 30 Km by M/T Qty. 21.00 m3
cum
21.00
302.18
6345.00
27 Aggregate 30 Km by M/T Qty. 25.50 m3
cum
25.50
302.18
7705.00
28 Cement/Steel 1500 mtr. by H/L Cement = 9.90 MT Steel = 0.55 MT
MT MT
9.90 0.55
287.60 617.81
2847.00 339.00
29 Sand/Aggregate 1500 mtr. by H/L Sand = 21.00 m3
Aggregate = 25.50 m3 Total= 46.50 m3
cum
46.50
691.33
32146.00
30 Stone/Boulders 1000 mtr. By H/L Qty. = 6.24 m3
cum
6.24
571.17
3564.00
31 Bricks 30 Km by M/T and 1500 Mtr.by H/L Qty vide item No.(7) = 13.70 m3 @ 475/m3 = 8000 Nos
Nos.
8000
2095.75
1000
16766.00
TOTAL 492684.00
Add 30% above onS.S. 2012 all items except item No.24 i.e. on ₹
482684.00
144805.00
GRAND TOTAL 637489.00
Say ₹ 6.37 Lacs WATER SUPPLY SCHEME BAGLA UNDER JJM
DETAILED ESTIMATE FOR CONSTRUCTION OF SPRING COVERING
1.20X1.20X1.20 Mtr.
S.No
Particulars Unit QTY. Rate Amount
1 Clearing jungle including uprooting of rank vegetation bushes etc. 5.00 x 5.00 = 25.00 m2
Sqm
25.00
5.85
146.00
2 Earth work in excavation in 80% all kind of soil and 20% ordinary rock. L/Wall=2 x 1.95 x 0.60 x 0.60 = 1.40 m3
S/wall=2 x 0.75 x 0.60 x 0.60 = 0.54 m3
Total = 1.94 m3
Cum
1.94
292.55
567.00
3 Providing and laying of cement concrete in 1:4:8 mix with 40mm nominal size of aggregate. L/Wall=2 x 1.95 x 0.60 x 0.15 = 0.35 m3
S/wall=2 x 0.75 x 0.60 x 0.15 = 0.13 m3
Total = 0.48 m3
Cum
1.10
3112.80
1494.00
34
4 Providing and laying cement concrete in 1:3:6 mix with 20 mm nominal size if aggregate L/Wall=2 x 1.65 x 0.45 x 0.60 = 0.89 m3
S/wall=2 x 1.05 x 0.45 x 0.60 = 0.57 m3
Total = 1.46 m3
Cum
1.46
3707.40
5412.00
5 Providing and laying reinforced cement concrete in 1:2:4 mix using 20 mm nominal size of aggregate. L/Wall=2 x 1.50 x 0.15 x 1.20 = 0.54 m3
S/wall=2 x 1.20 x 0.15x 1.20 = 0.43 m3
Total = 0.97 m3
Cum
0.97
5587.45
5420.00
6 Providing and laying reinforced cement concrete in 1:2:4 mix using 20 mm nominal size of aggregate. Slab = 1.50 x 1.50 x 0.10 = 0.23 m3
D/d M.H=1x0.45x 0.45 x0.10 = (-) 0.02 m3
Total = 0.21 m3
Cum
0.21
5776.45
1213.00
7 Centring and shuttering incl. strutting, propping etc. and removal of form for; Foundation L/Wall = 2x2 x1.95 x 0.15 = 1.17 m2
S/Wall = 2x2 x 0.75 x 0.15 = 0.45 m2 L/Wall = 2x2 x1.65 x 0.45 = 2.97 m2
S/Wall = 2x2 x 1.05 x 0.45 = 1.89 m2 Total = 6.48 m2
Sqm
6.48
179.25
1161.00
8 Centring and shuttering incl. strutting, propping etc. and removal of form for; Walls L/Wall = 2x2 x1.50 x 1.20 = 7.20 m2
S/Wall = 2x2 x 1.20 x 1.20 = 5.76 m2
Total = 12.96 m2
Sqm
12.96
342.80
4442.00
9 Centring and shuttering incl. strutting, propping etc. and removal of form for Slab = 1.20 x 1.20 = 1.44 m2
Sqm
1.44
372.40
536.00
10 Centring and shuttering incl. strutting, propping etc. Edges of slab = 4 x 1.50 = 6.00 Rmt
Rmt
6.00
176.55
1059.00
11 15mm thick cement sand plaster in 1:3 mix . Wall outer= 4 x1.50 x 1.20 = 7.20 m2
Wall inner = 4 x 1.20 x 1.20 = 5.76 m2
Slab =1.20 x 1.20 = 1.44 m2
Total = 14.40 m2
Sqm
14.40
248.90
3584.00
12 Reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete. Cold twisted bars Qty. vide item No.5&6 = 1.18 m3 @ 100 Kg/m3 = = 118 Kg = Say 120 Kg
Kg
120
71.00
8520.00
13 Supply of manhole cover.
35
One No. No. 1 1800.00 1800.00
14 Finishing of wall with cement paint Wall outer = 4 x1.50 x 1.20 = 7.20 m2
Slab =1.20 x 1.20 = 1.44 m2
Total = 8.64 m2
sqm
8.64
56.90
492.00
15 Extra for water proofing material Kg 8 43.95 351.00
16 Labour engaged for fixing of manhole cover and PVC air bend. 01 No.Mason for 01 day 01 No. Mazd. For 01 day
Day Day
1 1
450.00 300.00
450.00 300.00
MATERIAL CONSUMPTION CHART
ITEM No. QTY
CEMENT SAND AGGREGATE STEEL
Rate Qty.
03)C. Conc. 1:4:8
0.48 m3 3.40 1.63 0.23 0.43
04)C.Conc. 1:3:6
1.46 m3 4.40 6.42 0.68 1.30
5,6)R.C.C. 1:2:4
1.18 m3 6.40 7.55 0.53 1.00
12)15 mm plaster1:3 Mix
14.40 m2
21.94% 3.16 0.26 -------------------
TOTAL Say=
18.76 19
Bags
3.06 m3 2.73 m3 120 Kg
CARRIAGE OF MATERIAL
19 Cement/Steel 30 Km by M/T Cement = 0.95 MT Steel = 0.12 MT Total = 1.07 MT
MT
1.07
268.61
287.00
20 Sand 30 Km by M/T Qty. 1.70 m3
Cum
1.70
302.18
513.00
21 Aggregate 30 Km by M/T Qty. 2.73 m3
Cum
2.73
302.18
824.00
22 Cement/Steel 1500 mtr. by H/L Cement = 0.95 MT Steel = 0.12 MT
MT MT
0.95 0.12
287.60 617.81
273.00 74.00
23 Sand/Aggregate 1500 mtr. by H/L Sand = 1.70 m3
Aggregate = 2.73 m3 Total= 4.43 m3
Cum
4.43
691.33
3062.00
TOTAL 41980.00
Add 20% above on all items except item Nos.(16) i.e. on ₹ 41230.00
12369.00
GRAND TOTAL 54349.00
Say ₹ 0.54 Lacs
36
WATER SUPPLY SCHEME BAGLA UNDER JJM
DETAILED ESTIMATE FOR PROVIDING AND LAYING OF DISTRIBUTION SYSTEM
Particulars of items Rate Amount
A. Material Cost:
G.I pipes 65 mm Ф = 2500m (Light)
G.I pipes 50 mm Ф = 5000m
G.I pipes 40 mm Ф = 6500m
G.I pipes 32 mm Ф = 7000m
G.I pipes 25 mm Ф = 6500m
G.I pipes 20 mm Ф = 5000m
G.I pipes 15 mm Ф = 5000m
Total
Add 5% as pipe special
Total
506/m
366/m
291/m
231/m
184m
132/m
96/m
1265000.00
1830000.00
1891500.00
1617000.00
1196000.00
660000.00
480000.00
8939500.00
446975.00
9386475.00
B Civil Work :
1. Carriage of pipe from divisional store to stacking
place avg. Distance 30km by MT and 2000 mtr. By
head load.
G.I pipes 65 mm Ф = 2500m x 5.80kg/m =14500.00
G.I pipes 50 mm Ф = 5000m x 4.11kg/m =20550.00
G.I pipes 40 mm Ф = 6500m x3.25kg/m =21125.00
G.I pipes 32 mm Ф = 7000m x 2.58 kg/m =18060.00
G.I pipes 25 mm Ф = 6500m x 2.01kg/m=13065.00
G.I pipes 20 mm Ф = 5000m x 1.41kg/m=7050.00
G.I pipes 15 mm Ф = 5000m x 0.96kg/m=4800.00
Total =99150.00 kg
Say 99.15MT
Add 200% above on carriage by M/T And H/L
732.68/MT
200%
72645.00
145290.00
2 General site clearance including cutting of runk
vegetation etc.
30000 X1.50 = 45000 Sqm Take 60% Qty
45000X 60% = 27000 Sqm.
5.85/m2
157950.00
37
3. Earthwork excavation in foundation for laying of
Pipes, Cables etc. in 80% all kind of soil and 20%
ordinary rock.
G.I pipe 65 mm Ф = 2500m x 0.60x 0.50 =750.00
G.I pipe 50 mm Ф = 4500m x 0.60x 0.50 =1350.00
G.I pipe 40 mm Ф=6000m x 0.50x 0.50 =1500.00
G.I pipe 32 mm Ф =5500m x 0.50x 0.45 = 1237.50
G.I pipe 25 mm Ф =5000m x 0.45x 0.45 = 1012.50
G.I pipe 20 mm Ф =1000m x 0.40x 0.40= 160.00
G.I pipe 15 mm Ф =1000m x 0.40x 0.30= 120.00
Total 6130.00 m3
292.55/m3
1793331.00
4. Laying& fitting of G.I Pipes.
G.I. pipe 65 mm Ф = 2500m
G.I.pipe 50 mm Ф = 5000m
G.I. pipe 40 mm Ф = 6500m
G.I.pipe 32 mm Ф= 7000m
G.I. pipe 25 mm Ф = 6500m
G.I. pipe 20 mm Ф = 5000m
G.I. pipe 15 mm Ф = 5000m
47.15/m
27.75/m
26.60/m
20.25/m
19.40/m
13.05/m
12.25/m
`117875.00
138750.00
172900.00
141750.00
126100.00
65250.00
61250.00
5.Refilling of excavated earth taking 90% of item (3).
6130.00 m3x 90% = 5517.00 m3.
85.25/m3
470324.00
6. Labour required for carriage of pipe from stacking
place to actual site of work along alignment, cutting &
rethreading of damaged end of pipes, bending to
required angle for PSP’s including carriage to bend site
and back, watch &ward of pipes and material including
testing and commissioning etc.
3% of cost of material i.e. on Rs.9386475.00
281594.00
Total(B) 3745009.00
Add cost of material 9386475.00
Grand Total 13131484.00
Say Rs.131.31 Lacs.
WATER SUPPLY SCHEME BAGLA UNDER JJM
DETAILED ESTIMATE FOR PROVIDING AND LAYING OF RISING MAINS
S.No
Particulars of items Rate Amount
A. Material Cost:
G.I pipes 80 mm Ф = 5000m (Medium)
Add 5% as pipe special
Total
661/m
3305000.00
165250.00
3470250.00
38
B Civil Work :
Carriage of pipe from divisional store to stacking place
av. Distance 30km by MT and 2000 mtr. By head load.
G.I pipes 80 mm Ф=5000m x 8.54kg/m =42700Kg
Say 42.70MT
Add 200% above on carriage by M/T And H/L
732.68/MT
200%
31285.00
62570.00
2 General site clearance including cutting of runk
vegetation etc.
5000 X1.50 = 7500 Sqm Take 60% Qty
7500X 60% = 4500 Sqm.
5.85/m2
26325.00
3. Earthwork excavation in foundation for laying of
Pipes, Cables etc. in 80% all kind of soil and 20%
ordinary rock.
G.I pipe 80 mm Ф =5000m x 0.70 x 0.60 = 2100m3
292.55/m3
614355.00
4. Laying & fitting of G.I Pipes
G.I pipe 80 mm Ф = 5000m
51.10/m
255500.00
5. Refilling of excavated earth taking 90% of item (3-A).
2100 m3x90% = 1890 m3.
85.25/m3
161122.00
6. Labour required for carriage of pipe from stacking
place to actual site of work along alignment, cutting &
rethreading of damaged end of pipes, bending to
required angle for PSP’s including carriage to bend site
and back,watch &ward of pipes and material including
testing and commissioning etc.
3% of cost of material i.e.on Rs.3470250.00
104107.00
Total(B) 1256264.00
Add cost of material
3470250.00
Grand Total : 4726514.00
Say Rs.47.26 Lacs
39
WATER SUPPLY SCHEME BAGLA UNDER JJM
Dsign of Rising Main from Stage 1st to 10000 Gln GSR at Parran Top
RL at Base Stage = 100.00 m RL at 10000 GLNS GSR = 265.00M Level Difference = 165.00 m Height of GSR = 3.00 m Length of rising main = 1500 Mtr. Design population = 2400 souls Water requirement @ 12 GPCD = 2400 x 12 = 28800 GPD Assumed 8 Hours per day pumping Design Discharge (Q) = 28800 x 4.54 = 4.54x10-3 = 0.00454cumec 1000x 3600x8 D. Max = 1.22 Q1/2 = 1.22(0.00454)1/2 = 0..82 m =82 mm D. Min = 0.969 Q1/2 = 0.969(0.00454)1/2
=0.065 m = 65 mm Let us proposed a Rising main of dia= 80 mm..
Head Loss due to friction =Hf = L (Q/CR)1.84
994.62 x D4.84 = 1500 [ 0.00454] 1.84 0.805
994.62 x 0.0804.84 = 22.37 Mtr.
Add for losses on a/c of pipes special @ 10% = 10% x 22.37 = 2.23 Mtr. Total Head Loss = 22.37 + 2.23= 24.60 Mtr. Therefore total head against which pumping is to be done = = 165+ 3.00 + 24.60 = 192.60 Mtr.
Therefore it is recommended to install horizontal centrifugal pump of head 200 Mtr.
Taking efficiency of motor and pumps as 60% and 70%
HP = WQH 75 n = 1000 x 0.00454 x 200= 28.82 H.P 75 x 0.60 x 0.70 Say 30 H.P
40
Therefore it is recommended to install pumping machinery with specification as under:-
HC Pump with head = 200 Mtr. Discharge = 4000 GPH
HP = 30 H.P.
WATER SUPPLY SCHEME BAGLA UNDER JJM
Dsign of Rising Main from Base Stage to 10000 Gln GSR at BaglaTop
RL at Base Stage = 100.00 m RL at 10000 GLNS GSR = 265.00M Level Difference = 165.00 m Height of GSR = 3.00 m Length of rising main = 1700 Mtr. Design population = 2400 souls Water requirement @ 12 GPCD = 2400 x 12 = 28800 GPD Assumed 8 Hours per day pumping Design Discharge (Q) = 28800 x 4.54 = 4.54x10-3 = 0.00454cumec 1000x 3600x8 D. Max = 1.22 Q1/2 = 1.22(0.00454)1/2 = 0..82 m =82mm D. Min = 0.969 Q1/2 = 0.969(0.00454)1/2
=0.065 m = 65 mm Let us proposed a Rising main of dia= 80 mm..
Head Loss due to friction =Hf = L (Q/CR)1.84
994.63 x D4.84 = 1700 [ 0.00454] 1.84 0.805
994.62 x 0.0804.84 = 23.50 Mtr.
Add for losses on a/c of pipes special @ 10% = 10% x 23.50 = 2.35 Mtr. Total Head Loss = 23.50 + 2.35=25.85 Mtr. Therefore total head against which pumping is to be done = = 165+ 3.00 + 25.85 = 193.85 Mtr.
Therefore it is recommended to install horizontal centrifugal pump of head 200 Mtr.
41
Taking efficiency of motor and pumps as 60% and 70% HP = WQH 75 n = 1000 x 0.00454 x 200= 28.82 H.P 75 x 0.60 x 0.70 Say 30 H.P
Therefore it is recommended to install pumping machinery with specification as under:-
HC Pump with head = 200 Mtr. Discharge = 4000 GPH
HP = 30 H.P.
WATER SUPPLY SCHEME BAGLA UNDER JJM
Dsign of Rising Main from Base Stage to Stage 1st10000 Gln GSR at Central Parran
RL at Base Stage = 100.00 m RL at 10000 GLNS GSR = 265.00M Level Difference = 165.00 m Height of GSR = 3.00 m Length of rising main = 1800 Mtr. Design population = 2400 souls Water requirement @ 12 GPCD = 2400 x 12 = 28800 GPD Assumed 8 Hours per day pumping Design Discharge (Q) = 28800 x 4.54 = 4.54x10-3 = 0.00454cumec 1000x 3600x8 D. Max = 1.22 Q1/2 = 1.22(0.00454)1/2 = 0..82 m =82 mm D. Min = 0.969 Q1/2 = 0.969(0.00454)1/2
=0.065 m = 65 mm Let us proposed a Rising main of dia= 80 mm..
Head Loss due to friction =Hf = L (Q/CR)1.84
994.62 x D4.84 = 1800 [ 0.00454] 1.84 0.805
994.62 x 0.0804.84 = 24.89 Mtr.
Add for losses on a/c of pipes special @ 10% = 10% x 24.89 = 2.48 Mtr. Total Head Loss = 24.89 + 2.48= 27.37 Mtr.
42
Therefore total head against which pumping is to be done = = 165+ 3.00 + 27.37 = 195.37 Mtr.
Therefore it is recommended to install horizontal centrifugal pump of head 200 Mtr.
Taking efficiency of motor and pumps as 60% and 70% HP = WQH 75 n = 1000 x 0.00454 x 200= 28.82 H.P 75 x 0.60 x 0.70 Say 30 H.P
Therefore it is recommended to install pumping machinery with specification as under:-
HC Pump with head = 200 Mtr. Discharge = 4000 GPH
HP = 30 H.P.
WATER SUPPLY SCHEME BAGLA UNDER JJM
PIPE CHART OF DISTRIBUTION SYSTEM
S.No
Line 80 65 50 40 32 25 20 15
1 AA1 1700
2 AA2 500
3 A2A3 500
4 A1A5 600
5 A5A6 500
6 A1A7 650
7 A1A8 550
8 A8A9 600
9 A10A11 500
10 B2B3 500
11 B4B5 500
12 B5B6 500
13 B5B7 600
14 B7B8 500
15 CC1 500
16 DD1 500
17 D1D2 500
18 KK1 500
19 EE1 600
20 E1E2 500
21 FF1 500
43
22 F1F2 1200
23 GG1 600
24 G1G2 600
25 G1G3 900
26 HH1 600
27 JJ1 1800
28 J1J5 1500
29 J1J2 500
30 J1J3 500
31 J3J4 500
32 J5J6 600
33 J6J7 500
34 J5J8 600
35 J8J9 500
36 J5J10 500
37 J10J11 300
38 J10J12 1400
39 J5J13 500
40 J13J14 800
41 J14J15 1250
42 J14J16 1150
43 KK1 800
44 K1K2 900
45 K2K3 500
46 LL1 600
47 L1L2
48 For extension and Connections
6500 5000 5000
5000 2500 5000 6500 7000 6500 5000 5000
44
2. Detailed Estimate for the construction of Cattle
Trough
Say = 0.28 lacs.
S.N
o
Particulars Quantity Rate Amount
1. Earth work in bulk excavation in 100% AKS.
5.05 x 2.05 x 0.40 = 4.14 cum
4.14 m3
240/m3
993/-
2. P/L Cement Concrete in 1:4:8 mix .(6” thick) 5.05 x 2.05 x 0.15 = 1.55 cum
1.55 m3
3112/m3
4832/-
3. P/L Cement Concrete in 1:3:6 mix .
2 x 5.05 x 0.225 x 0.75 = 1.70 cum 2 x 1.55 x 0.225 x 0.75 = 0.52 cum = 2.22 cum
2.22 m3
3707/m3
8303/-
4. 12mm thick plaster in 1:4 mix with floating coat of neat cement.
2 x 2 x 5.05 x 0.75 = 15.15 sqm 2 x 2 x 1.55 x 0.75 = 4.65 sqm = 19.80 sqm
19.80 m2
182/m2
3603/-
5. Cement concrete flooring in 1:2:4 mix ,40 mm thick.
4.55 x 1.55 = 7.05 sqm
7.05 m2
320/m2
2256/-
6. Formwork required for Shuttering of ordinary timber planks
2 x 2 x 5.05 x 0.75 = 16.50 sqm 2 x 2 x 1.55 x 0.75 = 4.65 sqm = 21.15 sqm
21.15 m2
179.25
/m2
3791/-
7. Material Consumption :-
Item
no.
Qty. Cement Sand Bajree
2. 1.55 5.27 0.69 1.39
3. 2.22 9.76 0.99 1.99
5. 7.05 2.11 0.14 0.28
6. 19.80 1.76 0.31 ------
Total 18.90 2.13 3.04
a) Carriage of sand/Bajree 25km by MT & 500m HL.
5.17 m3
612/m3
3164/-
8. Add Diff in Cost of Cement 19 bags @ 90/bag(To be paid as per actual).
G.Total
1710/-
28665/-
45
3. Typical estimate for the construction of Water
Harvesting/Percolation Tank.
S.No Particulars Quantity Rate Amount
1. Earth work in bulk excavation in 30% OR and 70% AKS.
7.00 x 10.00 x 1.50 = 105 cum
105m3
300/m3
31500/-
2. P/R Dry Random rubble Masonary.
2 x 7.00 x (0.60 + 1.00 ) x 1.50 = 17.85 cum
2 2 x 9.15 x (0.60 + 1.00 ) x 1.50 = 23.32 cum
2
41.17 m3
1310/m3
53932/-
3. P/L 50 mm in 1:2:4 mix coping
2 x ( 7.00 + 9.70) x 0.30 = 10.02 sqm
10.02 m2
280/m2
2805/-
4. P/L hand packed stone pitching
5.00x8.00x0.15= 6 m3
6m3
377m3
2262/-
5. Material Consumption :-
Item
no.
Qty. Cemen
t
Sand Bajree Stone
2. 41.17 ---- ---- --- 34.99
3. 10.02 3.85 0.24 0.48 ----
4. 6 5.10
Total 3.85 0.24 0.48 40.09
a) Carriage of sand/Bajree 20km by MT & 800m
HL.
b) Carriage of stone 1km by HL.
0.78m3
40.09 m3
700/m3
571/m3
547/-
22891/-
6. Add Provision for steps and approach path ------------
-----------
G.Total
8,000/-
121937/-