vikramasingapuram
TRANSCRIPT
Directorate of Municipal Administration (DMA) Government of Tamil Nadu
DRAFT FINAL REPORT
on
Preparation of City Development Plan for Grade – III Municipal Towns
VIKRAMASINGAPURAM
April 2009
Prepared by:
Head Office: INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD, C - 2, Green Park Extension, New Delhi - 110016. Phone: +91 (011) 26568607/ 08/ 13, 26962636 Fax: +91 (011) 26969478 Email: [email protected] Website: http://www.ipeglobal.com
Branch Office: INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD, S-11, II Floor, K.G. Plaza, No 41-44, G.P. Road, Mount Road, Chennai – 600 002
Phone: 04432411001
CITY DEVELOPMENT PLAN
VIKRAMASINGAPURAM
AN EFFECTIVE CDP IS A READER FRIENDLY
DOCUMENT WITH FACTS STYLISED OR
GRAPHICALLY PRESENTED TO ENABLE ALL
STAKEHOLDERS TO UNDERSTAND THE CITY’S
DEVELOPMENT AGENDA.
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
1
TABLE OF CONTENT
CHAPTER 1 INTRODUCTION TO THE CITY DEVELOPMENT PLANNING PROCESS.2
1.1 BACK GROUND NOTE .................................................................................................................2 1.2 A RECAP .....................................................................................................................................3 1.3 CDP- THE APPROACH.................................................................................................................4 1.4 DATA SOURCES...........................................................................................................................7
CHAPTER 2 CITY VISION AND THE REGIONAL CONTEXT ...................................... 8
2.1 INTRODUCTION............................................................................................................................8 2.2 THE STATE CONTEXT ..................................................................................................................8 2.3 THE DISTRICT CONTEXT: TIRUNELVELI .......................................................................18
CHAPTER 3 TOWN PROFILE ................................................................................... 35
3.1 TOWN HISTORY AND GROWTH........................................................................................35 3.2 DEMOGRAPHIC PROFIILE ..................................................................................................35 3.3 URBAN ECONOMY.............................................................................................................. .38 3.4 LANDUSE AND SPATIAL GROWTH PATTERN ...............................................................................39 3.5 POPULATION FORECAST.............................................................................................................35
CHAPTER 4 URBAN INFRASTRUCTURE & SERVICE DELIVERY MECHANISM...... 43
4.1 WATER SUPPLY..........................................................................................................................43 4.2 SEWERAGE AND SANITATION SYSTEM .......................................................................................50 4.3 ROADS AND STORM WATER DRAINAGE ...................................................................... .53 4.4 TRAFFICE AND TRANSPORTATION..............................................................................................55 4.5 SOLID WASTE MANAGEMENT.....................................................................................................56 4.6 STREET LIGHTING ......................................................................................................................59 4.7 SOCIAL INFRASTRUCTURE .........................................................................................................60
CHAPTER 5 HOUSING, SLUMS AND THE URBAN POOR.......................................... 64
5.1 INTRODUCTION .........................................................................................................................64 5.2 HOUSING CONDITIONS ...............................................................................................................64 5.3 SLUMS AND BPL POPULATION ................................................................................................. .65 5.4 HOUSE CATEGORIES ..................................................................................................................66 5.5 INFRASTRUCTURE PROVISIONS IN SLUMS ..................................................................................66 5.6 SLUM IMPROVEMENT/ PROGRAMMES AND ISSUES .....................................................................68 5.7 STRATEGIES AND TIME FRAME...................................................................................................69
CHAPTER 6 HERITAGE............................................................................................ 71
6.1 HERITAGE COMPONENTS ...........................................................................................................71 6.2 HERITAGE SITES IN VIKRAMASINGAPURAM AND VICINITY.........................................................72 6.3 HERITAGE CONSERVATION ....................................................................................................... 73 6.4 STATE INTERVENTIONS .............................................................................................................74 6.5 ISSUES AND CONCERN ...............................................................................................................74
CHAPTER 7 URBAN ENVIRONMENT ....................................................................... 76
7.1 BROAD ENVIRONMENT CONCERNS.............................................................................................76 7.2 SITUATIONS IN VIKRAMASINGAPURAM......................................................................................76
CHAPTER 8 URBAN GOVERNANCE AND URABN REFORMS................................... 80
8.1 ORGANISATIONAL STRUCTURE ..................................................................................................80 8.2 FUNCTIONAL WINGS ..................................................................................................................82 8.3 LINE AGENCIES ..........................................................................................................................83 8.4 REFORMS FOR ULBS UNDER UIDSSMT ........................................................................................84
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
2
8.5 RECOMMENDED ORGANISATIONAL STRUCTURE ........................................................................83
CHAPTER 9 MUNICIPAL FINANCE .......................................................................... 88
9.1 INTRODUCTION..........................................................................................................................88 9.2 REVENUE ACCOUNT...................................................................................................................88 9.3 DEMAND COLLECTION BALANCE SCENARIO ..............................................................................93
9.4 RATIO ANALYSIS .......................................................................................................................96
CHAPTER 10 DEVELOPMENT OF PERSPECTIVE AND VISION OF THE CITY........... 97
10.1 SPATIAL PERSPECTIVE FOR VIKRAMASINGAPURAM 2041..........................................................97 10.2 SECTOR SPECIFIC OBJECTIVE AND PROJECTS..............................................................................97 10.3 PRIORITISATION OF PROJECTS....................................................................................................98 10.4 INFRASTRUCTURE PROJECTS......................................................................................................98 10.5 CONCURRENCE ON PRIORITIZED PROJECTS ..............................................................................106
CHAPTER 11 CITY INVESTMENT PLAN ...................................................................107
11.1 BACKDROP STUDY ...................................................................................................................107 11.2 CIP PROCESS FOR VIKRAMSINGAPURAM ..................................................................................108 11.3 WATER SUPPLY........................................................................................................................109 11.4 SEWERAGE AND SANITATION...................................................................................................111 11.5 STORM WATER DRAINAGE .......................................................................................................112 11.6 SOLID WASTE MANAGEMENT...................................................................................................113 11.7 TRAFFIC AND TRANSPORTATION..............................................................................................114 11.8 STREET LIGHTING ....................................................................................................................117 11.9 BASIC SERVICES TO URBAN POOR ............................................................................................118 11.10 LIST OF PROJECTS FOR VIKRAMSINGAPURAM UNDER DIFFERENT SECTORS ............................119
11.11 SECTORWISE CITY INVESTMENT PLAN .....................................................................................122
CHAPTER 12 ASSET MANAGEMENT ........................................................................125
12.1 INTRODUCTION........................................................................................................................125 12.2 BENEFITS OF ASSET MANAGEMENT..........................................................................................126 12.3 ASSET MANAGEMENT PLAN METHODOLOGY............................................................................126 12.4 REQUIREMENTS OF ASSET MANAGEMENT ................................................................................128 12.5 INFRASTRUCTURE ASSETS .......................................................................................................139 12.6 LAND BUILDINGS AND VEHICLE...............................................................................................140 12.7 STRATEGIES AND RECOMMENDATIONS....................................................................................141
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
3
Chapter 1 INTRODUCTION TO THE CITY DEVELOPMENT
PLANNING PROCESS
1.1 Back Ground Note
1. City planning has adopted a new format to move into the future. Conventional land use
planning methods had failed to recognize ground level realities and had frozen
development futures into rigid frameworks giving very little leeway for change. This
apparently created minor and major hurdles in recognizing issues which had emerged
from the larger nation, state, city, and even micro level consideration, and which disabled
efficient city planning.
2. The City Development Plans move through a different process. They involve formulating a
Vision which is a collective shared one to instill pride and identity of people in their city.
They involve partnering with civil society, businesses, and citizens to make way for
legitimate economic growth and development, they involve recognizing inner city cores
and the heritage wealth of centuries lying within, and renewing it so as to retain
connections with the past. Other missed issues brought into the ambit of the new planning
ethos is the integration of urban poor through slum renewal and socially as well as
economically integrated neighborhoods so as to enshrine our commitment to equity and
inclusiveness. One of the severest drawbacks of earlier planning were a lack and often
breakdown of essential basic services to most except to the elitist; the new process
emphasizes deeply the fast tracking of infrastructure availability to a set of justified
standards to promote not just economic development but also reduce environment health
risks, especially in dilapidated areas and poverty pockets in the city.
3. To nourish the new Planning process, there was need to have accountable governance in place,
decentralize city planning to local level institutions who have grass root connections,
ensure sustainable funds and responsible accounting procedures, in short, run it like a
socially responsible business house to achieve the desired effects of Reforming,
Enlarging, Sustaining, Profiting from and directing growth: becoming more a
Mission than an agenda under the new ideology, with philanthropy added to activate
integration of the socially disadvantaged groups.
4. Since this is a complex activity, it needed technology-driven systemizing, like Improved
Accounting, GIS based planning and Revenue collection, Budget earmarking for poor,
Basic services to Urban poor through special programmes, E-governance, levying user
charges, assigning responsibilities to partners, enacting public disclosure – information
based laws, and community participation laws / practices, Review and Performance
evaluation etc.
5. Initially special programmes have been introduced to build reform, investment and well
serviced sustainable city building exercises broadly through a routinized process:
• Analysis of current situation.
• Vision for Future development.
• Strategies for development.
• Financing plans.
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
4
The FIRE- D model (Financial Institutions Reform and Expansion project- Debt Infrastructure
component) initiated by World Bank for CDP preparation, followed by the JNNURM
(Jawahar Lal Nehru National Urban Renewal Mission) for CDPs for 63 cities has been an
exercise to actualize the above. Precursors to these planning reforms included the
“Millennium Development Goals” program and “Sustainable Cities Program” which
were introduced by international aid agencies.
The Tamil Nadu government has further innovated the same to apply similar conditions for the
CDP for newly transitted urban local bodies in an effort to “Catch them young” as well as
to ‘nip the evil in the bud,’ in short, put new urban centers through a drill of modern city
planning and ensure sustainable long term effects. It has chosen to do this through the
IUDSSMT program (Integrated Urban Development Schemes for Small and Medium
Towns) combining it with another one AUWSP (Accelerated Urban Water Supply
Program), both centre sponsored schemes, assuring 80% finance ( seed money) to put
into motion the new CDP process.
6. Some apprehensions expressed on the JNNURM CDP process figure around the continuation
of consultation with grass root institutions, lack of allocation for social sector, proportion
of total funds allocated to a particular city and the criteria adopted for that allocation
particularly with respect to its fiscal impact on the city. Also being questioned are the
definition of “renewal”, and the tenurial role of Technical Advisory Groups (TAGS) for
CDP under government schemes for their continuation for ensuring transparency as well
as the participatory mechanisms. Other fears which have been expressed are with respect
to cost limit of sub-missions IHSDP and BSUP projects, and the ways of operationalising
manpower efficiency with in the ULB’s.
In larger metropolises the slum free city is being perceived by pro-poor as an exploitive
opportunity for businesses to locate at slum cleared sites.
The issues and concerns of CDP formulation is graphically explained in Annexure – I.
7. A brief on CDP Plan Making Process is recapitulated as under:
1.2 A Recap
CDPs provide an integrated version of an urban community’s diverse perspectives through a
unified vision for a future development. The on ground realities, when compared to the
vision set the agenda for action and onward movement. This entails formulating and
sequencing policy initiatives, investment and development strategies, and, civil society
partnerships.
CDPs for Grade III municipalities in Tamil Nadu are an effort at developing them with city, state
and central government.
The UIDSSMT, a centrally sponsored project has objectives which are congruous with India’s
JNNURM and aim to create economically productive, efficient, equitable and responsive
cities. The project aims to enhance a) water, sanitation and other infrastructure services.
b) expand access to the poor, c) increase municipal finance sustainability, d) initiate
policy reform in the ULBs e) explore the abundant heritage and f) include people’s voice
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
5
in their development. Improved Urban governance with technical assistance in plan
making, policy and financial structuring are an expected outcome of the project.
In brief the CDP is expected to respond to the challenge of urban growth; poverty: under serviced
population with respect to infrastructure and public services, and inefficient city
management struggling with rapidly changing city profiles. The expected deliverables are
a fast tracked city development, efficient infrastructure delivery mechanism, community
participation and the ULBs accountability to the citizens.
The project involves FORMULATING A PLAN which incorporates implementable policies and
actions in line with the aforementioned objectives of the CDP.
(The scope of work is outlined in Annexure-II )
The CDP will suggest reforms aligned to the vision and strategic plan for sustainable planned
interventions by the state and ULB.
Fig 1.1: City Development Plan - Framework
1.3 CDP - The Approach
The plan will set out strategic thrust areas with their policy and investment options as well as base
line for future performance by the ULB. As a tool it comprises of projects and reforms to
ensure planned development and sustainable municipal operations. CDP Fraework is
shown in Fig. 1.1.
Fig. 1.2 & Fig. 1.3 outline the plan making process of the CDP, with inbuilt review facilitated by
performance indicators. The process is dynamic and assures that felt needs and
requirements are duly met.
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
6
Fig 1.2
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
8
The CDP approach, to ensure it is dynamic and satisfies the felt need, must be formulated in a
way, to position the cities in the most favourable way drawing all its inherent and
perceived opportunities. (Many cities facing decline have reinvented themselves to new
economic frontiers different from the past, to excel in, say, Tourism, Finance, Education,
Production, Entertainment, Management …).
There is enough learning from our early cities, which were traditionally productive, inclusive and
sustainable, even when governed by monarchs, who used the political and institutional
stability to produce large volumes of rich treasures of the built environment which forms
our heritage legacy. Good governance which is least intrusive in day to day affairs of
citizens, but enabling an effective in shoring up opportunities and capabilities which are
in the community’s interest, can be a great asset to city building from down up. For
example:
� Introducing Education for vocational training for high end services early in the city’s
development, ensures, that at times of crisis poverty can be kept in control by taking
advantage of deep social capital when the less successful members can be supported
� Permitting local economies, (even if dominated by the informal sectors) and the
institutions to evolve into leading roles if they constitute a large part of the city’s GDP.
� Providing signals to private sector players to share and invest in city’s development
efforts.
� Encouraging outsiders’ perceptions of the city by those who have exposure to larger
challenging environments, so as to guide City Development Strategies rather than
adopting internally driven strategies which often have limited utility.
� Take advantage of the speedy CDP process, (obviating need for policy change) to
undertake programmes and projects on pilot basis to ascertain their impact, OR, adopt
those which are time tested and give assured results. The ULBs drive an initiative will
determine how it deploys its actions to change its performance. There is freedom to do
this under the CDP approach.
1.4 Data Sources
a) Demographic data is made available from the Tamil Nadu Census (2001)
b) A number of Tamil Nadu websites have provided valuable data for the state, district, taluk
and for different aspects of development / other sectors as needed for the project.
c) Various state institutions and organizations, responsible for urban development, transport,
water and sewage disposal, other infrastructure aspects have provided DPRs for current
and proposed projects. Anna University’s library, Connemara library, NGOs private
organizations, the Town and Country Planning Department and other GIS oriented public
and private organizations have pitched in to provide / support data.
d) The ULB itself has provided all data within its jurisdiction.
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
9
Chapter 2 CITY VISION AND THE REGIONAL CONTEXT
2.1 Introduction
Formulating a CDP involves envisioning the city future through a SWOT analysis. At the same
time to provide perspective to this vision, references have to be drawn from the larger
context so as to demarcate aspects that will help in realizing the vision. The State, district
and taluk have accordingly been taken up for the study so as to strengthen the city vision
and are brought out as follows.
2.2 The State Context
2.2.1 Political and Historic
Politically and historically the State has undergone constant change and has used it to its
advantage. It has an ancient history representing Dravidian culture and has been ruled by
4 great kingdoms, Cholas, Cheras, Pandyas and the Pallavas, till the 10th century. There
was an intervening phase of unstable muslim rule with fragmented petty kingdoms all of
which ended with the arrival of East India Company in 1639 and the establishment of the
Madras Presidency under British rule. Soon, after 1947 Andhra Pradesh secured its
independent Statehood followed later (1956) by the formation of Karnataka and Kerala
States. In 1967 the State was renamed Tamil Nadu, is today the 4th largest, with 6 percent
of India’s population spread over 30 districts mostly rural, yet rapidly urbanizing with 44
percent urbanization level. The rapid fragmentation of the State into more districts has
been a continuous process. Fig 2.1 displays this process over time and which
accompanied several changes in the district boundaries.
Due to its historicity the State is rich in heritage resources, having more than 3000 temples and
sites of antiquity. It has two World Heritage Sites identified by UNESCO; the
Mahabalipuram group of Monuments and Brahadeeswar temple at Thanjavur. A
significant move has been made by state archeological department to identify and protect
‘Choultries” or “Chatirams” a tradition of old heritage buildings for pilgrims to stay in
the pilgrimage town. Conservation efforts are on and 38 towns identified for action on
conserving historical, cultural and ‘priceless’ monuments. The study area is a repository
of several heritage buildings and tourism based resources.
2.2.2 Urban Growth and Governance
Chennai is Tamil Nadu’s capital city and India’s fourth largest city with the Municipal
Corporation responsible for the development and governance. The State has added 363
urban units in the last decade. Other large cities having status of Municipal Corporations
are Coimbatore, Madurai, Tiruchirapalli, Salem, Tirunelveli and Tirupur.
The state governance is through 30 districts and 206 taluks and nearly 17,244 villages; 6 cities
have Corporations (mentioned above); there are 152 Municipalities, 385 Panchayats (out
of which 105 are in place in the six districts under study). Besides there are the village
panchayats. District headquarters are named after the district. Town panchayats are for
governance of areas transiting to urban from rural, Municipal Councils for smaller urban
areas and Municipal Corporations for larger urban areas.
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
10
Fig 2.1: Administrative Transformation in Tamil Nadu (1951-2001) Source: Administrative Atlas- Census of India 2001, Tamil Nadu
No. of Districts - 30
No. of Districts - 16
No. of Districts - 13
No. of Districts - 13
No. of Districts - 14
No. of Districts - 21
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
11
The 10 municipalities under reference, remain democratically elected bodies, requiring self
governance in matters listed on the Twelfth Schedule, (reserve seats for SC/ST/Backward
Classes/ Women in power sharing, levy taxes/ duties, assign proceeds given by the State
Governments and for making grants, review their finances by the State Finance
Commission and as of now, introduce e-governance/ reform/ improve accounting/ budget
and provide basic services for urban poor). The down top governance is defined through
urban wards politically represented, some wards mandated for women/ other
disadvantaged classes.
Source: Administrative Atlas of India, 2001
Note: Figure below districts indicates the number of towns.
Fig. 2.2: Proportion of Rural and Urban Population, Tamil Nadu
Figure 2.2 above shows highly urbanized districts against the highly rural districts in the State,
significantly five of the 6 reference districts have a high percentage of urban population.
Following the Nagar Palika Act of 1994 all the 611 town panchayats were brought under the
category of statutory towns. As evident from the Table 2.1, the inclusion of all the town
panchayats resulted in an increase from 1991-2001 of 57.94 lakh persons in that category
alone.
32 56
67
79
25
28
26
45
60 45
Urban Reference District
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
12
Fig 2.3: Urban Frame, Tamil Nadu
Table 2.1 : Urban Population of Tamil Nadu 1991-2001 (Category wise)
Category Number Population (Lakh) Decadal Growth
Rate (%)
1991 2001 1991 2001
Corporation 3 6 71.35 79.12 10.90
Municipalities /
Cantonme
nts
108 104 72.37 82.46 13.95
Town Panchayats 224 611 37.81 95.75 153.23
Census Towns 134 111 N.A. N.A.
Total 469 832 190.77 272.41 42.79
Source: Census of India, 2001
The population of town panchayat increased by 42.80 per cent in the decade 1991-2001. (Table
2.2) Urbanization levels slowed down between 1971-1991 but again increased in 2001.
Table 2.2: Urban Population of Tamil Nadu, 1961-2001
Year No. of
t
o
w
n
s
Urban
Po
pul
ati
on
Urban
Popula
tion
(%)
Decadal
gro
wth
(%)
Annual Growth
Rate (%)
1961 339 89.90 26.69 22.59 2.04
1971 439 124.64 30.26 38.64 3.27
1981 434 159.5 32.95 27.98 2.47
1991 469 190.77 34.15 19.59 1.79
2001 832 272.42 43.86 42.79 3.56
Source: Census of India, 2001
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
13
For bottoms up governance, the state is ideally organized through well defined urban wards, each
with one elected representatives.
Fig 2.3: Distributions of Towns by Size Class 2001, Tamil Nadu
Figure above shows most towns in the State are small sized but poised for future growth. It is
significant to address the urban issues early before they magnify into irresolvable
dimensions.
According to the 2001 Census, the State’s population is approximately 62 million as opposed to
55.9 million in 1991. The sex ratio works out to 986 in 2001 as compared to 974 in 1991
and 977 in 1981. The decadal (1991–2001) growth rate is 11.19 per cent. The density of
population in Tamil Nadu, a true indicator of population distribution, is 478 persons per
sq. km in 2001, as against 429 in 1991 and 372 in 1981. Tamil Nadu’s slum population
was estimated in 1993–94 to be 3.13 million which is 16.5 per cent of the total urban
population of the State.
The State is unique in some aspects as,
• Its high urbanization level as mentioned earlier
• An increasing sex ratio (974 in 1991 to 986 in 2001)
• A decadal growth rate of 11.19%
• It’s fairly distributed population density of 478 persons/sq.km
Slum population in Tamil Nadu is 16.5% with Chennai Corporation area showing a 30% slum
population, half of which lives in very dense areas. Slums have been recorded for towns
with more than 50,000 populations in Census 2001. Slum dwellers form a high
proportion of many town populations and are of serious concern in the agenda of the
Millennium Development Goals of World Bank, which desire that poverty be reduced to
zero level.
Globalization in early nineties has increased export opportunities, making Tamil Nadu the third
largest economy among the States of India. As regards education institutions, there has
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
14
been a tremendous increase in their numbers in Tamil Nadu, with the State containing the
largest number of vocational training institutions in the country.
Tamil Nadu is one of the leading states in the social, economic and other arenas. The State is
India's second biggest producer of rice, (next to Punjab where there is a perennial source
of irrigation). The town of ‘Namakkal’ in the State is also known as the poultry hub of
India. The state is first amongst all to have a formal bio-diesel policy using Jatropha
plant crops. Under this policy the State has distributed wasteland to the poor farmers for
planting Jatropha.
Tamil Nadu has a well established transportation system and networks connecting all parts of the
State. This has resulted in attracting huge external investments in recent years. There are
24 National Highways having total length of 2,002 km. The State has a total railway track
length of 6,693 km and has about 690 railway stations. There is one international airport
at Chennai. Air links to Chennai are spread across 19 countries having 169 direct flights.
It has three major seaports at Chennai, Ennore and Tuticorin. Other minor ports include
Nagapattinam, Rameswaram, Kanyakumari, Cuddalore, Colachel, Karaikal, Pamban and
Valinokkan.
2.2.3 Location and Geography
• Tamil Nadu, situated at the south eastern end of India has Karnataka to its north,
Andhra Pradesh on the east, Kerala to its west and the Indian Ocean on the south. Its
capital Chennai is the 4th largest Indian city. (see Map 1)
• There are two natural divisions in the State, Coastal plains and the hilly western
region. Plains further sub divide into the Coromandel plains (districts of Kancheepuram,
Thiruvallur, Cuddalore, Vellore); Cauvery delta (districts of Thanjavur and parts of
Tirucharapally); and the dry southern plains (districts of Madurai, Dindigul,
Ramnathapuram, Sivaganga, Virudhnagar, Tirunelveli and Tuticorin), the last group
being areas of this study.
• The state’s coastline is nearly a 1000 km long, There are 33 river basins, chief among
them being Cauvery, Palar, Vaigai and Tambraparni (Last two being relevant to this
study)
• Western ghat hills, nearly 1000 meters long ( and 3000’-8000’ height) consist of
several hill groups (Nilgris, Anaimalai, Palani, Varushannad, Andipatti) The
aforementioned rivers originate from here and are of importance to this study.
2.2.4 Demography & Economy
• The state has 31 districts, a total population of 62,110,839 (6% of India’s population)
high urbanization level (44%) and is densely populated, covering an area of 1,30,058
square kilometers.
• High literacy rates, reduction in poverty levels, improved life expectancy at birth, and
declining fertility rates have contributed to human development achievement. Efforts are
on for gender development. (Table 2.3 and Map 3 give comparison of the 6 study districts
)
• A disquieting factor is the large number of marginal workers in worker participation
rate (WPR); higher WPR in rural than urban; increase in female WPR and decline in
child labour are positive outcomes.
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
15
• Primary sector is the largest contributor to the economy (50% workers) secondary
workers being 23.6%, and tertiary sector 26.1% of the employment. Agriculture incomes
have declined from 25% to 18% (1994-2004) with rise in share of income in the other
two sectors which are located in urban areas. Diversifying agriculture (high value crops/
allied activities) for improving productivity per unit of capital would help avoid income
disparity in the rural and urban sector. The expanding literate work force need to be self
employed entrepreneurs (in food processing/ horticulture/animal husbandry or non farm
small scale industry)
• Poverty in some districts of the study is higher than others (See Table 2.4 and 2.5);
coastal districts appear to be better off. There is a co-relation between poverty and the
marginalized groups, who show higher poverty levels. These need to be addressed.
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
17
(v) Infrastructure and Industry
• There is a substantial road network of 2000 Kms of National Highway (NH 7; the
North South Corridor cuts midway through the districts of this study providing equal
access to the eastern and western parts); 6700 Kms of rail track and 690 railway stations;
an international airport at Chennai; two major ports, Chennai & Tuticorin achieve
sufficient export driven cargo handling, besides the nine small and intermediate ones
being considered for up gradation. (Map 2 compares 6 study districts for their road and
rail network)
• Infrastructure with future expansion and a sensible Industrial policy make it the third
largest economy amongst states in India.
• Industrial and Infrastructure development based on identified thrust areas is
underway (Electronics, Software/ Auto components/ Agro-food processing/Petroleum &
Chemicals/ Roads/ Power/ Port development/Mining/ Leather/ Textiles) Each activity has
well defined scenarios, policy initiatives and projects in place for all scales of industry,
proposed/ located in modern parks and complexes, with a host of state sponsored
institutions in place as DIC, TANSI, TANSIDCO, TALCO, SISI, SIDO, SENET, TBSI,
TANSTIAFNF etc.
Table
Key Map
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
18
Table 2.4
Table 2.5
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
20
2.3 The District Context: Tirunelveli
2.3.1 Political and Historic
Ever since Tamil Nadu came into being Tirunelveli district has been a constant. Changes that
took place were in naming it Tinnevelly (1951) which remained so till 1981. In 1991 it
was bifurcated to 2 districts and renamed Tirunelveli – Kattaboman, and
Chindambaranar. Between the decades 1991-2001 these districts have again been
renamed as Tirunelveli and Thoothikudi respectively.
Historically, the district is linked to the dynastic rule of the Pandyas as compiled in Sangam
literature which is a record of medieval times (300 BC to 300 AD), quite like Madurai
and Ramnathapuram. The Nayaks of Vijayanagar ruled in the 18th century, followed by
the Muslims. After Tipu Sultan’s defeat (1799), East India Company (later the British
Empire) took over control till India’s independence.
2.3.2 Urban Growth and Governance
Tirunelveli district is fairly urbanized (Table 2.6) containing 45 urban units within its jurisdiction.
The district headquarter is a Corporation (one amongst the six in the State). Urban areas
are clustered along either or near NH-7 the North-South axis, and SH-40 which is the
route to Kerala via Shencottai pass in the Western Ghats, besides NH-208 which meets
SH-40 at Tenkasi (Map 5). The district has 11 taluks, 481 villages and a total population
of 27,23,988 persons (nearly 4.4% of the State). The district has besides Tirunelveli
Corporation, 9 municipalities and 36 town panchayats. Map in Table 2.6 indicates the
urbanization levels which are of the 11 taluks of which 5 are urban and 6 rural. Urban
taluks are geographically aligned along the border with Kerala. Areawise, it is one of the
largest districts (6,824 sq. miles)
2.3.3 Location and Geography
• The name ‘Tirunelveli’ suggests a sacred place bounded by paddy fields. True to its
name, the district is green with paddy cultivation, irrigated by the waters of river
Tambraparni. Tirunelveli, the penultimate southern district of Tamil Nadu, is one of the
largest in the state (6824 sq.kms) with 11 taluks, a total population of 27,23,988 and
containing within its area all the five geographical divisions referred to in Tamil
literature, the Kurinji (mountains), the Mullai (forests), Marudham (cultivable lands),
Neithal (coastal) and Palai (deserts). (see Map 4)
• Locationally, this hill district forming part of the Western Ghats which separates it
from Kerala state on its western side, lies between 8ο
10’ and 9ο
40’ North latitude, and
77ο
21’ and 77ο
99’ East longitude. On its north is Virudhnagar district, on the east
Tuticorin, on the west the Travancore areas of Kerala and Kanyakumari district, and
towards the south is the Gulf of Mannar. (Map 4 - Tirunelveli district )
• Parts of the district in the western ghat region have vast forest resources, Notable
hills are Kallakadai Mottai (5721’), Kottaimalai (6335’), Kuliratti (5876’) and the
Pothigai hills where, at Agasthyamallai (6132’) is the source of Tambraparni, which
descends at Papanasam in Vikramasingapuram taluk journeying onwards creating
waterfalls at each descent (Kalyanateertham, Vanatheertham, Agasthyar, Panatheertha,
Manirruthur). Most natural places there are marked by ancient Temples. The ghats have
thick forest (often vulnerable trees as Teak, Rosewood and Ebony are found here) which
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
21
yield produce as honey, wax, cashew, cayenne pepper, tamarind and bamboo etc; nearly
1, 40,000 Ha. of land is under forests, and wild life sanctuaries have been created for
conserving the biological resources in their natural habitats. (Mundanthural Kalakkad
Tiger Reserve; Megamalai; Koonthakulam Bird Sanctuary). Several minerals as
limestone and garnet sand are mined and quarried (by 400 units) to the tune of 27,28,354
tons/ unit per year chiefly for the production of cement. Ghats are watershed for the main
rivers Tambrapani and Chittar. In the district 27 rivers and streams have been identified.
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
24
2.3.4 Demography, Economy and Human Resource
• Within the district, Tirunelveli taluk is the most urbanized (80%) whilst also being
the district headquater and, set singularly amidst other rural taluks. The urban taluks,
located in the Western Ghats run 160 Km in lengths in 3 adjoining taluks, Sankarankoil,
Tenkasi and Ambasamudram.
• Comparative assessment of the district growth and other demographic factors (Table
2.3) for six reference district show their relative position with respect to population,
growth rate, densities, sex ratio, literacy and its worker proportion. Tirunelveli has the
largest area, modest growth, high sex ratio and literacy and a fair share of workers (41%)
in the economy. Human resource indicators suggest adequate human development and
gender development (Table 2.4, 2.5, and Map 3)
• In literacy the district ranks third in the state with 79.5 percent literacy rate. With a
large number of educational institutes located here it is also called the ‘Oxford of South
India’. A major state ICT project TAMIL NILAM (Information System on Land
Administration and Management) has been fully implemented in all the 11 taluks making
e governance a reality here. GIS and Land Information System have made possible a data
inventory of 18 lakh land parcels and 16 lakh land owners with more than 1 lakh land
ownership certificates already issued as per their website.
• Regional variation amongst the 6 districts in the Madurai - Tirunelveli region
suggest that disparity and income inequality are on account of low industrialization, low
rice productivity, high population of socially backward classes.
• Low income is also associated with high infant mortality rate and low life
expectancy. In this respect slum population is a vulnerable segment.
• Average literacy rate of Tamilnadu Municipalities is 84.4% with very high
literacy recorded for districts of Kanyakumari (93%), Thoothukudi (89%) and Nilgiris
(89%). Ranked at bottom three are Tirunelveli (77%), Theni (81%) and Salem (75%).
(Table -2.7) gives comparative account of the slum profile in 6 reference districts.
Table 2.7: Comparative Profile of Slums in Reference Districts
S. DISTRICT SLUM
POPULATION
TOTAL, NOS
POPULATION
TOTAL,
NOS
SLUM/TOTAL
POPULATION
(%)
1 Madurai (MC) 175875 922913 19.06
2 Virudhnagar
(Sivakasi)
22841 72170 31.65
3 Thoothukudi
(Thoothukudi)
21370 216058 9.9
4 Tirunelveli
(Tirunelveli M.C)
56958 411298 13.85
5 Theni (Cumbum) 19798 58713 33.72
6 Ramanathapuram
(Ramanathapuram)
6763 61976 10.91
Source: Census of India, 2001
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
25
2.3.5 Infrastructure and Industry
• Tirunelveli rural taluks grow crops of paddy, pulses, groundnut, cotton, sugarcane,
palm as well as horticulture products like guava, mango, lemon, tomato, onion, banana,
drumstick, semai velerukkai, both offering scope for agro based industries (as palmgur,
tetra packed pathaneer, citrus and coconut based industries) other natural products as
flowers, herbs, aromatic plants (like lemon grass, curry leaves, chillies) offer scope for
perfumery and pharma products. Similarly forest produce as rubber, coir, jute or wood
offer scope for export based growth in self employment ventures.
• Tirunelveli district presents a picture of Infrastructure inadequacy as follows:
a. 56% HHs do not have any type of toilet facility.
b. An average 55 Ipcd potable water supply is availed in the
district, with Tirunelveli Corporation drawing the largest amount
of water (nearly 500 lakh liters) against municipalities which
draw between 25-50 lakh liters each. Smaller municipalities and
town panchayats (Courtallam, Kalakedu, Melagram) are able to
meet 40-70% demand.
c. Sewage is mostly disposed into rivers as there is no
organized UGD system for the more than 700 lakh liters of liquid
waste generation in the districts urban areas.
d. Solid waste generation equivalent to 900 tonnes has a
collection efficiency of 65% only.
e. There are more than 200 Kms of National Highway, 150
Kms of State Highway, 900 Kms of major roads, about 600 Kms
of ghat roads, 88 bridges and 6000 minor bridges/ culverts. The
district is well endowed with roads and both broad gauge and
meter gauge railways.
f. The district’s rural profile overshadows its industrial
profile; Industries produce Cement, Paper, Textile, and Sugar in
the large industry sector. Small, medium and household industry
produces safety matches, Coir mats, beedis, handloom textiles.
Articles from palm fibre, are mostly located in Tenkasi,
Vikramasingapuram and Tirunelveli taluks. Articles from Palm
trees are produced in Nanguneri taluk. There are 2,300 small
scale units in the district, in descending order are the chemical
products, food products.
• It is important to consider all avenues for income equality. It is expected that
secondary and tertiary employment are likely to be the preferred futures for an expanding
qualified work force, and in either sector it is imperative to prepare for non-farm
occupations in a way that self employment ventures are linked to policy, training,
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
26
financing, institutions and finance. Farm occupation similarly will require diversification
for enhancing productivity per unit of capital.
• The District Urbanization Scenario whilst focusing on Indicators that have a direct
bearing on environmental concerns would also indicate trends in size and spatial
distribution of the population. Urban Population densities provided a record of not just
the concentration of people over urban space but also the towns structural condition, the
expected quality of life in its residential neighborhoods and even the spread and expected
level of infrastructure demand (Table 2.6).
2.3.6 Historic footprint and Heritage
• There are several heritage resources in the district; of the listed 3000 temples in the
state, 50% are located in the three taluks of Tirunelveli, Vikramasingapuram and Tenkasi.
Some are listed here :Vikramasingapuram- Kasinathar Kovil, Thirumalainathur Kovil,
Veeramarthandesar Kovil, Ammaiyappar Kovil, Agasthiyar Kovil; Deivacheyalpuram
(Rajarajes wari temple, Ramar temple); Tenkasi (Varanasi of South); Krishnapuram
(Krishna temple) Manapad (Holy church cross of St.Xavier) Kulasekarpattinam
(Mutharamman temple, Chidarambeswar temple, Katchiappar temple) Sankaram Kovil
(Lord Vishnu and Lord Shiva, Gomti Ambal ) Nanguneri (Vishnu temple) Mukkudal
(Muthumalai Amman temple) Tirunelveli (Nellaiappar temple, Pottalpudur Dargah,
Pulithevan palace. The inventory of temples includes village deities, Vinayakars, or the
Muruggan- Siva- Vishnu temples.
• The state is rich in heritage resources with the listing of 3,000 temples, half of which
are reputed to be in the three taluks of Tirunelveli, Ambasamudram and Tenkasi.
• Courtallam has 8 waterfalls and one tourist place of note.
• Tirunelveli town’s historic footprint goes to 3,000 years back, has mythological roots
for its establishment and was known for commerce during the period of Arcot Nawabs
and Nayaks. In 1801 the British acquired the town from the nawabs, and it served as
military headquarter during British period.
• Cultural effects on cuisines include ‘halwa’ (made of wheat & sugar) ‘Sothi’
(coconut milk with vegetables) ‘Kootan charu’ (spicy rice, vegetables and dal), and
‘Ulunthamparu Choru’ with ‘Yellu thovayal’ as well as the filter coffee.
• This quixotic mixture of natural places, temple heritage, forest, wildlife, local
handicrafts, food, cascades-waterfalls-lakes-rivers etc. accessibility make it ideal for
tourism promotion in particular eco tourism.
1. Relevant District Profile
The District being predominantly rural, has assured irrigated land for cultivation, particularly
paddy in Sankaramkoil, Tirunelveli, Tenkari, Senkottah, Vikramasingapuram and
Nanguneri taluk. Dry tracts of the district occur in Sivagiri and part of Sankarankoil,
where camby, cholam and Kudiraivali are cultivated. Forest covers 22% and cropped area
18% of total land; 50% land being fallow is not available for cultivation.
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
27
The district is also industrially active as mentioned earlier. District level accessibility through all
categories of roads for destined and through traffic is adequately disposed, as also for rail
traffic.
2. The Taluka Context: Ambasamudram
• Vikramsighpuram is within Ambasamudram taluk about 9 km away from the
headquater town forming almost an urban continuum with four other towns,
Ambasamudram, Kallakurichi, Manimatharu, and Sivanthipuram, the last two aligned
linearly along the Western Ghat foothills. There is perceived advantage in providing high
cost infrastructure serving a larger region. These five out of the 12 urban units in the
taluk are crisscrossed by rivers, the railway line and the state highway which are
thresholds in long term planning.
• After Tirunelveli, this is the second largest taluk in the district with an area of 1910
sq, km. and a population of 3,92,226 persons (28% and 14% respectively); a 57% urban
population component, with 12 towns and 65 villages contained within it. A large part of
the taluk (Map) consists of reserved forests along the western ghats region, of the
remaining nearly one third of the land is covered by urban areas of municipalities and
Town Panchayats (12 nos), two of which are Ambasamudram and Vikramsingapuram,
from the Reference Municipalities.
• The Municipalities Ambasamudram (Population 32,739; Area 17.89 sq, km.) and
Vikramsingapura (Population 48,309; Area 38.57 sq. km.) occupy 8.5% and 14% of the
taluk population respectively, as well as 1%and 2% of the land area respectively.
Together the 5 urban units occupy 6% of taluk land.
• Town densities of 18pph and 15pph reflect low town densities since a sizeable
population of urban area land is devoted to wet lands and paddy cultivation. The main
river Tambraparni’s source is located here with reserved forest as its watershed, SH-40,
as a main artery in the taluk, connects from Tenkasi and lead to Tirunelveli with the MG
Rly line running almost parallel to it while cutting across the taluk. The SH-40 cuts
through the Vikramasingapuram ULB creating congestion and laying grounds rerouting
by-passable traffic. There exists a ban on setting up industries within 1km. of the
embankments of the all water sources. Taluks adjoining Ambasamudram to its west are
smaller sized but with larger urban units (Tenkasi and Shenkottai)
• There is select building regulation regarding height restrictions in Heritage towns.
• Town planning regulation specify Agriculture use zone as a distinct land use thereby
its restrictive implication for urban expansion. Software training plus the list of permitted
uses for development can be established without restriction (except within CRZs,
Archeological / heritage sites/ Airports/ Quarry sites/ Railway properties/ Burial
grounds.)
• Multi-storied buildings are permitted on 18m wide roads.
3. Inputs for Promoting Vikramasingapuram Vision.
Vikramasingapuram, as an urban taluk has, other contiguous urban taluks to its East (Tirunelveli)
and (Tenkasi, Shenkottai & Sivagiri) to its North. Future planning would require
strengthing of the road networks so as to serve the objectives of tourism growth which
can logically be used to derive income and employment within an existing resource base
for heritage and natural areas, but which would also promote linear urban settlement and
avail the infrastructure advantage.
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
28
4. Promoting Vikramasingapuram for Growth
It has been established that Vikramasingapuram is in urgent need for catalyzing its growth.
Whilst providing focused development inputs to it, it will be natural that the effects will
be felt on the nearby (about 7km away) Ambasamudram (and neighboring towns) ULB,
both towns being aligned along or near the SH40, as also forming part of the reference
towns for CDP preparation.
The schematic map (Map 7 & 8) explains that with the introduction of 4 lane / high speed
transport corridor (dual carriageway), would help ease congestion on SH40 passing
through Vikramasingapuram acting as a By-pass. It would double the road capacity for a
faster goods movement to Kerala, hitherto restricted due to hilly region barrier and
intervening forest areas, (it is prudent not to poach on forest land for a quicker access to
Kerala, which was demanded by Vikramasingapuram stakeholders). It would also
synergize economic activity in Vikramsingapuram by twinning the 2 towns and
sandwiching future development zones for their mutual benefits.
Three distinct zones would then serve to kick start development;
(1) Institutional zone,
(2) the Mini – Enterprise zones explained earlier and
(3) the Tourism Nodes.
The Institutional zone shall be located near a proposed Ecological Park (a Regional level
Recreational green) as a perfect setting for education to serve service sector growth; the
enterprise zones for agro processing, food processing, wholesale / retail commercial
would be self sufficient with integrated fully serviced residential areas; the Tourism
Nodes would contain integrated Tourism infrastructure in modern well designed IT
managed environments containing Transport, Boarding , Hotels and Lodges, Restaurants,
and would be in adjacent locations to both Vikramasingapuram and Ambasamudram.
(See Map 9)
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
29
Map 7
Map 8
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
30
5. Inception Stage and the SWOT Analysis
The consultants visited Vikramasingapuram on September 21, 2007 for a reconnaissance of the
Municipality area and for a consultative meeting cum workshop with the Chairman,
Councilors and other major stakeholders. Another meeting cum workshop was held in
Madurai on October 16, 2007 for presenting the inception report, under the Chairmanship
of JCMA where ULB Chairman and state level concerned functionaries were apprised,
and views consolidated for the onward exercise of preparing the Draft CDP. A record of
these meetings is provided in Annex - 3.
The SWOT analysis and draft emerging vision for Vikramasingapuram ULB is derived from this
meeting and as incorporated in the inception report. The ULB’s regional perspective and
interconnections with the district helped sharpen the Vikramasingapuram Vision.
6. City Assessment, SWOT Analysis for Vikramasingapuram
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
31
STRENGTH • Is situated close to taluka headquater, aligned off but connected to SH–40 with a
metalled road going to Kerala (Kollam) passing through 2 urban taluk headquarters Tenkasi and Shenkottai.
• Forms a sizeable urban continuum with four other urban units (as mentioned earlier).
• Within reach of district headquarters Tirunelveli 42 km on SH-40.
• Located within western ghats forest, 600-900m above MSL., extremely pleasant scenic environment, with hill road passing through two large dam sites and a series of water falls (Agasthyar, Karaiyar, Panartheertham) in the Pothigai hills, also the site of a hydro power station.
• River Tambraparni flows through the town on SW side.
• Important tourist places, as Mundanthuri tiger reserve sanctuary located nearby.
• Several heritage temples (Papanasam, Sivanthiappan…) located nearby. The reservoir of tourist places in the district is listed in the tourism department circuits.
• Is larger both in population and area then the taluk headquarter.
• Have effective road linkages to other taluka and distrct town.
• Accessible to many educational institutions.
• Shares labour force with Ambasamudram for Madura Coats factory together contributing 12,000 labour (now fairly downsized). Indicates acculturation to industrial environment.
• High literacy effective for translating to skilled human resource.
• Harmonious co- sharing amongst caste / religious groups and a low slum population.
• Women SHG are engaged in micro enterprises in forest based activities.
Summarised, VICKRAMSINGAPURAM, WITH ITS LITERATE POPULATION, SCENIC AND
HERITAGE RICH ENVIRONMENT, SUFFICIENT TOURISM RESOURCES AS WELL AS
AGRO AND FOREST BASED RESOURCES NEED TO BE EFFECTIVELY USED THROUGH
AN ECOLOGICAL DEVELOPMENT MODE FOR DEVELOPING ITS ECONOMY. (THE REGION COULD BE GAZETTED AS A HERITAGE AND ENVIRONMENTALY SENSITIVE)
WEAKNESS
• Very weak town growth, negative population growth rate.
• Weak employment base in spite of resources.
• Proximity to Tirunelveli not fully exploited.
• Constraint of forward movement of goods/services due to geographical barrier of western ghat mountains, as well as the reserved forests.
• Support for mini enterprises for resource based/cottage/handloom/handicraft sector missing.
• Mining/ quarrying limited to labour intensive low return activity. Also degrade the environment.
• Weak Tourism infrastructure.
• Deficient economic base corroborated by the state conducted Industrial Potential Survey Report (2001-2002) which puts several blocks in Tirunelveli district on the Backward, and Most Backward blocks in Tamil Nadu.
• E-governance requires strengthening.
• City drainage poor
• ULB assets not inventoried.
• Community facilities insufficient.
Summarized, VICKRAMSINGAPURAM’S LACKS RAILWAY LINK, FORMAL INDUSTRY,
INFORMAL MARKETS-WAREHOUSING AND PROCESSING OF AGRO PRODUCTS OTHER
THAN PADDY. LOCAL ECONOMY NEEDS RESTRUCTURING TO CONTRIBUTE TO GDP.
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
32
THREAT
• New Forest Act 2007 and its implications to tribal welfare within the ULB/Taluka.
• Current out migration and lack of jobs
• Environmental deterioration due to ineffective SWM.
• Pollution of water bodies (rivers, lakes, reservoirs) by human activities, effluent discharge, other noxious discharge.
• Obstruction to surface drainage by urbanization
• Damage to ancient heritage buildings for lack of funds for restoration, preservation, and conservation and natural areas in the absence of monitoring.
• Heritage Management Measures, not in place at Tourism sites.
• Paddy cultivation and its export may mean giving up more carrying capacity embodied in its production (water) exceeding the regions natural surplus. In the long run this may be economically unsustainable; may require Ecological Footprint Analysis to determine sustainability.
Summarized, CONSCIOUSLY DESIGNED STRATEGIES FOR TOURISM, HERITAGE, MICRO INDUSTRY, RESOURCE BASED ACTIVITY IN COLLABORATIVE MODE SO AS NOT TO
ENVIRONMENTALLY DAMAGE AND PROMOTE POSITIVE EXPLORATION OF GROWTH.
OPPORTUNITY
• Tourism development as in riverfront development, road improvement and facilities upto perennial water-falls, temple improvement schemes, resorts - budget hotels - recreation and entertainment - picnic spots – zoo and safari rides – eco tourism within a large Bio-reserve within western ghats region – boating facilities in water bodies.
• Twinning urban units for developing synergies and collaborative programs for SWM, employment growth, tourism development, road development, ecologically based settlement planning.
• Granting special status of GREEN TOWNS and prescribing Green and Clean practices.
• Establishing Center for Environment and Ecology, promoting sustainability in development practice.
• High literacy including female literacy; need for strengthening state sponsored Self Help Groups (SHGs).
• Need for promoting service sector linked to available natural resources (Forest/mines/agriculture/horticulture) in specially tailored development hubs.
• Need for establishing educational institutions for Hospitality, Fashion & Design, Fine art and commercial art, IT, basic accounting, vocational training and enterprise development etc. for service sector growth in peri-urban areas of 2-3 adjoining towns.
• Need for Temple improvement measures and attaching a Heritage Information Kiosk to each temple; training centre for vernacular Architecture and building construction methods (skills for building, painting, carpentry, stone carving, drawing and draughtsman ship etc.) jointly with 2-3 ULB’s on their peri-urban areas by conjoining the two urban units.
• Need for establishing regional markets for Fruits, Vegetables, Flowers, Horticulture products, Pulses, Cereals & Food grains, Forest produce, Minerals etc. with permanent exhibition- display facility, Business Finance-Marketing Centre; Mini Agro processing zones
Summarised, DRIVING DEVELOPMENT THROUGH TOURISM., AGRO PRODUCTION,
GREEN PRACTICES AND SUSTAINED HUMAN RESOURCE DEVELOPMENT,
EMPHASIZING ON WOMEN SHGs.
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
33
7. Emerging Draft Vision for Vikramsingapuram
Vikramasingapuram and its adjoining urban units located within areas of unique environmental
quality, need to develop in collaborative mode helping to sustain the region’s ecology
through Green Practices; they need to develop centres for tourism/recreation, quality
education backed by knowledge goals as well as practical applications; Micro enterprise
development and services of non polluting nature using natural resources and viable
enough with value added through design/ marketing/ promotional work.
Innovative Strategies for Tourism and traditional skill enhancement showcased in ‘Haat’
environments…. all lead to more visibility and repeat visits endowing the town with
economic growth and helping the ULB to establish a productive base for governance.
8. Critical Inputs
Strengthening road networks is critical to urban, economic and tourism growth and is usefully
productive at a regional scale.
9. Emerging Vikramasingapuram Vision
Focused development inputs are required for delivering economic growth; Expressways can lead
to faster movement of goods and services trans state to Kerala so far hindered by forests
acting as dead ends. Similarly SWM operations require scale to become viable which is
achievable with a cluster of towns; peri urban areas are perceived as good options for
locating them for a mutual benefit.
Spatial perspective for Vikramasingapuram is provided with considerations as below:
Eco-Centric Activities
Eco- park; Eco- centre;Eco- resorts/ lodges; Eco- product Development centre; Organic foods and
processing centres; Eco- Education centres
Infrastructure- Centric Roads and expressways,Bridges and culverts;Halting and Maintenance Stations
Heritage Tourism and Growth Centric
Temple Improvement; Heritage trails; Parks, picnic areas; Rural Conservation Zones
Enterprise Zones; Micro to medium size units
Institutional Zones; Vocational centres; Knowledge centres
10. Emerging Spatial Perspective for Vikramasingapuram
The organization of Expressways and Development Nodes, Hubs or Zones are schematically
given at the taluk level but emphasized for Vikramasingapuram and its adjoining
settlements. The Development Hubs are:
� Regional tourism and ecological parks
� Tourism nodes
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
34
� Composite micro enterprise zones
� Bus stands
The proposals are diagrammatically explained in Map – 9.
11. The ULB Jurisdiction:
The present area of 3857 hectares in the ULB with its nearly 565 hectares as undeveloped is
sufficient for its future land needs.
PLATE – 1: Waterfalls and Hills in the Region
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
35
Chapter 3 TOWN PROFILE
PLATE – 2: Town Glimpses
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
36
3.1 Town History and Growth
Vikramasingapuram ULB is situated west of Ambasamudram ULB, within
Ambasamudram Taluk of Tirunelveli district, at a distance of 10 kms. and 45 kms away
from them respectively. Located at the foot of the western ghats (Pothigai hills) and on
the northern banks of River Tambrapani it is 8ο
67’ North latitude and 77ο
33’ East
longitude, about 300 m above MSL. The ULB is connected to Ambasamudram through
the Ambai-Papanasam main road connecting to the ancient temple at Papansam (the
name implying papam – sin and nasam – destroy). Another temple 4 km away is the
Agasthyar Koil whose waterfalls are a tourist draw. Several scenic places around
associated with mythological events related to Lord Shiva and Parvati, and the sage
Agasthya, are, the Kalyana theertham, the Agasthyar falls, the Panatheertham falls, the
Papanasam falls, the Karyar falls and the Tambraparni river. All these suggest the
ancient history of the town. The Courtalam falls are further down about 25 kms away and
are an amazing sight. On the way to Agasthayar falls, temple and Kalyanamtheertham is
located the Hydro electric power station. There are two large dams, the upper dam
(Servalar) built in the Pothgai hills, and the Karyar dam whose water is provided by
Panatheertham water falls; on the way to Karyar dam is another ancient temple known as
Sorimuthu Ayannar Kovil. All the above places fall within the Municipality’s jurisdiction
in 13 hamlets.
The Mundanthurai Tiger Sanctuary is situated on way to upper dam from Papanasam. The ULB
has 21 municipal wards covering an area of 38.57 sq km and a population of 48,309
(2001).
3.2 Demographic Profile 3.2.1 Population growth trends
Table 3.1: Population Growth Trends
YEAR POPULATION DECADAL GROWTH RATE
1961 32,978 -
1971 40,274 22.12
1981 49,319 22.46
1991 49,834 1.04
2001 48,309 (3.06)
Source: Census of India, 2001
Source: IPE Analysis
Fig 3.1: Population Growth Trends Fig 3.2: Population Growth Rate 3.2.2 Density
Population Growth
0
10000
20000
30000
40000
50000
60000
1961 1971 1981 1991 2001
Years
Popula
tion
Population Growth Rate
-5
0
5
10
15
20
25
1971 1981 1991 2001
Years
Perc
enta
ge
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
37
Table 3.2: Wardwise Population Distribution, Area and Density
POPULATION AREA WARD
NO. Persons % Sq.km % Total Area
DENSITY
PERSONS
PER HA
1 2860 5.92 2.80 7.2 10
2 1750 3.62 1.10 2.85 16
3 2412 4.99 0.85 2.20 28
4 1981 4.10 0.90 2.33 22
5 1817 3.76 0.75 1.94 24
6 1472 3.05 0.80 2.07 18
7 2579 5.34 0.89 2.30 29
8 2236 4.63 0.80 2.07 28
9 2071 4.29 12.65 32.80 2
10 3031 6.27 1.40 3.62 22
11 2794 5.78 2.10 5.44 13
12 2598 5.38 2.76 7.15 9
13 2708 5.61 2.20 5.70 12
14 2346 4.86 1.10 2.85 21
15 2480 5.13 1.65 4.27 15
16 2351 4.87 0.60 1.55 39
17 2149 4.45 0.70 1.81 31
18 2167 4.49 0.85 2.20 25
19 2285 4.73 1.10 2.85 21
20 2103 4.35 1.17 3.03 18
21 2119 4.39 1.40 1.40 15
Total 48309 100.00 38.57 100.00 Avg. 12
Source: Census of India, 2001 & IPE Analysis
The ULB comprises 21municipal wards within its jurisdiction. Overall town density is 12 pph
(Table 3.2) which is low. The developed area density is also very low 14pph indicating
spread development which is unfavorable for both infrastructure development and energy
use. A wardwise assessment of density shows there is moderate density in most wards
permitting room for future infill development.
3.2.3 Birth Rate and Death Rate
The data indicates a decline in the birth rate from 5 to 2/1000 population and a consistent death
rate
Table 3.3: Birth and Death Rate
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
38
YEAR LIVEBIRTHS DEATHS BIRTHRATE (PER 1000
POPULATION)
DEATH RATE ( PER
1000
POPULATION)
2004 220 345 5 7
2005 79 335 2 7
2006 91 401 2 8
Source: Vikramasingapuram Muncipality
Source: IPE Analysis
Fig. 3.3 Birth and Death Rate
3.2.4 Literacy and Sex Ratio
Table 3.4: Literacy Rate
YEAR LITERATES LITERACY RATE
1961 15,892 48
1971 22,720 56
1981 31,384 64
1991 35,183 71
2001 37,680 78
Source: Census of India, 2001
Fig 3.4: Literacy Rate
Table 3.5: Sex Ratio
Birth and Death Rate (%)
0
1
2
3
4
5
6
7
8
9
2004 2005 2006
Years
Perc
enta
ge
Birth Rate (per 1000 population) Death Rate ( per 1000 population)
Literacy Rate (%)
-
10
20
30
40
50
60
70
80
90
1961 1971 1981 1991 2001
Years
Perc
enta
ge
Literacy rate
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
39
YEAR MALES FEMALES SEX RATIO
1961 16,316 16,662 1,021
1971 20,378 19,896 976
1981 25,225 24,094 955
1991 24,661 25,173 1,021
2001 24,019 24,290 1,011
Source: Census of India, 2001
Literacy rate over the years has significantly increased to 78% (higher than the state average) Sex
ratio has been constantly good, and this appears to have a co-relation to general literacy
levels and specifically, to female literacy levels.
3.3 Urban Economy
Vikramasingapuram’s economy depended on Madura Coats textile Industry where raw cotton
was processed to make cloth, and whose labour was drawn from this town as well as
Ambasamudram. This now stands declined due to plant modernization and labour force
reduction from 12000 to 1000 workers. The Papanasam paper mill too has done similarly.
There are nearly 61 mining and quarrying units in some of the taluk’s Municiplaities /
development blocks, of which some -are located in this ULB. The town has about 12
Rice mills 20 Flour mills and other small scale beedi units as well as 5 mineral water
units within its jurisdiction, but none are large scale.
The town has around 472 shops and 75 retailing and workshop units, one vegetable market,
around 120 restaurants, besides the usual social infrastructure distributed over different
wards.
3.3.1 Occupational Structure
Table 3.6: Occupational Structure Sector Total
No
Persons
%
totto
No. of
Persons
%
to to
No.of
Persons
%
to to
No.of
Persons
%
to to
No.of
Persons
%
to to
Cultivators
Agriculture
Labourers
2,801 24 1,543 13 1,453 10 3,158 18 1,729 9.23
Household
Industry
7,009 61 6,412 56 1,754 12 8,449 49 4,887 26.09
Others 1,634 14 3,526 31 10,719 71 3,720 22 12,114 64.68
Maginal
Workers
- - - 1,267 8 1,962 11 - -
Total
Workers
11,444 100 11,481 100 15,193 100 17,289 100 18,730 100.00
Non workers 21,534 28,793 34,126 32,545 29,579
Total 32,978 40,274 49,319 49,834 48,309
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
40
Population
WPR 35 29 31 35 39
Source: Census of India, 2001 & IPE Analysis
The occupational structure has undergone change in the last decade, with Primary workers
decreasing to half (18% to 9% of total workers); similarly workers engaged in household
industry are also declining from 48% to 26% bringing about growth in the services
sector which has enlarged from 22% to 65%. It appears that the economic base both
from agriculture and micro industry is eroding and is being substituted by low paid jobs
in the service sector, probably one of the reasons for a negative growth rate of the town.
3.4 Land use and Spatial Growth Pattern
Land use surveys by the Town and Country Planning department, were conducted (2000) for
preparing the revised Master Plan for the 3857 hectares of land within the town’s
boundary.
Table 3.7: Land Use Distribution
LAND USE AREA (HEC) % OF DEVELOPED
AREA
% OF TOTAL
AREA
Residential 2551 77.50 66.15
Commercial 712 21.62 18.45
Industrial 29 0.98 0.75
Public/Semi
public/Institutional
Developed Area 3292 100.00 85.35
Agriculture/
Wet Lands
407 10.56
Circulation 59 1.52
Graveyards 99 2.57
Total 3857 100.00
Source: Vikramasingapuram Municipality
Land use distribution indicates that the developed area constitutes 85% of the ULB area with 15%
under Agriculture and other uses. The use distribution for developed area is as : 77%
under Residential use, 21% under commercial, less that half per cent under Industrial Use
and similar for public amenities. The distribution of uses is highly skewed towards
residential uses and is un usually a high proportion.
(a) Water Bodies
There are a large number of water bodies / ponds (16 nos) within the town besides the river
Tambraparni and the north Kodalmallagian channel; together they cover nearly 109 acres
(44 hectares) of land which is municipal owned. The Servalar dam and the upper / lower
dam too are within municipal limits.
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
41
The water bodies need safeguarding against effluents discharging, and, require networking
with green corridors to develop as recreational sites for the city- the number of
temples within the town and along water bodies need to be brought under walkable
and improved temple environment as part of the towns cultural plan. This needs
serious work to maintain cultural zones, in the town. The town needs libraries,
community halls, gardens, open and enclosed forums for performing arts.
(b) Transportation
The Ambasamudram Papanasam road, an off shot of SH-40, cuts through the town leading to
areas north and south of it. Another major city road in N.S. alignments intersects the
above road with most residential areas contained within grid iron streets.
3.4.1 Spatial Growth Pattern
The future growth in the town shall centre on Residential enclaves, medium density with proper
infrastructure and decentralized STPs for safe sanitation accessible to all, exploring new
technologies and recycling water for agriculture/ horticulture to retain the green
environment. New development hubs as in Map-9 would contain the new employment
centres for the city and its region.
3.4.2 Emerging Issues
• The town is close to taluk headquarters, linked by metalled roads and further linked
to Tirunelveli and Tuticorin through the Rail link at Ambasamudram. Another train
station between Vikramasingapuram and Alwarkuridchchi on the existing rail line would
held improve connectivity. Growth constraints include existing infrastructure inadequacy
and needs enhancement of both social and physical infrastructure both qualitatively and
quantitatively for the present and future population.
• Water bodies improvement, development of master plan for tourist places around
heritage areas, development of a Zoo as tourist attraction and taking advantage of forest
areas inclusion in town, lining of the canal, improving access to introduce pucca roads to
eliminate cases of snake bites prevalent here; introduction of tribal welfare schemes
(Papansam) ; improving drainage to avoid water logging/ flooding/ constructing culverts /
sufficient high mast lighting for improving illumination were some of the issues seen
with respect to the towns location amidst sylvan surroundings.
• For physical infrastructure, issues emerging out of the consultation process were the
need for more OHTs suitably located at elevated positions to facilitate gravity flow and
decrease energy cost; preventing discharge from septic tanks into water bodies;
rehabilitating old water supply scheme; improving community toilets through aided funds
for individual toilet improvement and constructing public conveniences at congested
sites; introducing sewerage; improving solid waste management.
• Other issues stated dwelt on jobs and their necessity in the town for introducing food
and agro based (especially sugarcane) industry, as well as creating jobs for women
through SHGs as per policy in Tamil Nadu.
3.4.3 Development Objectives
Promoting a spatial structure for Vikramasingapuram that preserves and enhances is natural and
heritage assets, explores forest and agro resources for creating employment and
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
42
improving the economic base, collaborates with other ULBs for effective regional
infrastructure of roads, SWM, water supply, sewerage and drainage, introduces
collaborative institutions for generating non polluting jobs within ‘Green Town’ formats,
and provides for an integrated land use - transport development by restructuring its
regional linkage.
Constraints
• Decreasing growth rate of the town
• Insanitation and environmental degradation
• Low grade basic infrastructure
• Non – adherence to development controls.
• Weak economy and limited employment.
• Urban poor and slum formation.
• Inadequate municipal resources.
• Leadership, guidance and management institutions.
3.5 Population Forecasts
Population Forecasts are important to any planning exercise, and accurate forecasting is an
important criteria. It is also a very difficult exercise. Literature on forecasting concludes
that though many methods are available, no single method is consistently more accurate
than the other methods. Research into forecast accuracy also concludes that forecast
accuracy generally increases with population size, or with areas with slow but steady
positive growth rate. The reverse being true for areas experiencing rapid population
increases or losses – A rule of thumb on base period is generally found to be true , ie.
Length of the base period should generally correspond to the length of the projection
horizon. (short horizon period, 1-5 yrs, short base period, long projection horizon,
20+years, longer base period) Projections can be improved by combining different
projection results, weighing and averaging them, and using a composite method. The
same is being done for Vikramasingapuram here.
As mentioned, the city has seen a decline of – 3.5 % in the last decade. This is common in cities
where the economy has not renewed, and could lead to a downward growth spiral.
However, development opportunities are required to reverse this trend. For assessing the
future growth of population, the following methods have been considered.
Table 3.8: Population Forecasting Methods
YEAR POPULATION SIZE INCREASE VARIATION
(%)
AVG.
INCREME
NT
1961 32978 - - -
1971 40274 7296 22.12 -
1981 49319 9045 22.40 1749
1991 49834 515 1.04 (8530)
2001 48309 (1525) (3.06) (1010)
Average 4595 12.15 2822
Table 3.8 A Table 3.8 B Table 3.8 C
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
43
Assuming est. population (2006) – 50800; Average Variation per annum – 1.215 % as per State
govt. estimates
Table 3.8 D Table 3.8 E
Table 3.9 Population Forecast by Methods
METHOD 2011 2021 2031 2041
A 52904 57499 62094 66689
B 54178 60761 68143 76423
C 5726 63143 70560 77977
D 53285 58773 64826 71503
E 66859 89854 120772 139999
Table 3.10 Population Forecast by Range
METHOD 2011 2021 2031 2041
A 66059 89854 120772 139999
B 54178 60761 68143 76423
C 52904 57499 62094 66689
Source: All tables source is Census of India, 2001 and IPE Analysis
It is suggested that the medium Forecast be accepted
Formula Used
Arithmetic Method r = average of decadal increment (1961-2001)
n = no. of decades
Population Projected = Population of base year + n * r
Population n = Population (2001) + n*r
Arithmetic Increase
Average Increase 4595
2011 52904
2021 57499
2031 62094
Forecast
2041 66689
Geometric Increase
Average Variation 12.15
2011 54178
2021 60761
2031 68143
Forecast
2041 76423
Incremental Increase
Average Increase 2822
Average Arithmetic Increase 4595
2011 55726
2021 63143
2031 70560
Forecast
2041 77977
Arithmetic Increase
Average Increase 4595
2011 53285
2021 58773
2031 64826
Forecast
2041 71503
Geometric Increase
Average Variation 12.15
2011 66859
2021 89854
2031 1,20,772
Forecast
2041 1,39,999
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
44
Incremental Increase
r = average of increment on decadal increment (1961-2001)
n = no. of decades
Population n = P (2001) + nr + n (n+1) r / 2
Geometric Increase X= decadal increment / previous decade population
Or
X = Rate of growth
n = no. of decades
r = (product of rate of growth)^1/no. of rate of growth
r = (product of rate of growth 1961-71, 1971-81, 1981-91, 1991-2001)^1/4
Population n = P (2001) * (1+ r)^n
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
45
Chapter 4 URBAN INFRASTRUCTURE & SERVICE DELIVERY
MECHANISM
The Infrastructure profile of a town makes a direct reference on the quality of life within it. It is
an important consideration for the town’s economic development and its investment
climate. Infrastructure services and its adequacy require an assessment be made of its
coverage, quantity and quality, as also the demand supply gap. The cost of delivering
services and recovering that cost is another matter for review.
The following sections relate to an analysis of the above mentioned factors for the various
services within the town. (See Annexure: 4 Maps 10 to 14 giving location of facilities)
4.1 Water Supply
4.1.1 Source and availability of water
Vikramasingapuram Municipality is required to provide water supply to its 21 wards and 13
hamlets, the latter being outgrowths to the core urban area; four of these hamlets (Lower
Camp, Upper Dam, Servalar and Kanikudiyiruppu] lie on the slopes of Western Ghats. In
general the town’s topography is rocky with several hillocks sloping towards
Tambraparani river; ground level variation (range 76m to 106m) in 30m. An abundance
of water is available for irrigation from the North Kodaimelalagian canal running south
of the town.
(i) The scheme in place was sanctioned 40 years back (1967) commissioned 6 years later
for an intervening population (1981 - 48,000) and ultimate population (1996-60,000) at a
standard of 90 lpcd through which, of the total 18,300 properties present, 42.7 percent
had availed HSCs. The water supply system entailed sourcing it from 80m upstream of
Kodamelalagian anicut in river Tambraparni (which is the first anicut after Agasthyar
falls) and had sufficient supply of surface water for subsequent improvement schemes.
The initial scheme, post treatment and transportation to clear water storage at Ground Level
Service Reservior (GLSR) Vambahnthanparai (15 LL) and SR at Tanna (3.15 LL)
provided water supply to Vikramasingapuram. Hamlets located on the slopes near the
Dams were provided water by the Electricity board, and one tribal hamlet
(Kanikudiyiuppu – ward 9) was provided water from upstream River Tambraparni stored
at GLSR (built by ULB) and distributed through 3 public stand points. This w. s. scheme
had a distribution network of 24.5 km with 24.1km for extension areas, totaling 49 kms in
its entirety.
(ii) The second extension to W.S.Scheme (1991) by TWAD was designed for interim
population of 85000- 2019 and for an ultimate requirement of 59.50 LL considering 22
hours of supply. This entailed boosting from Taana SR and storing 2 LL water at the SR
Agasthiapuram, and another boosting fromVambalanathan to store 2 LL at SR
Mettulhangammankoil. Yet another SR Pothigaryadi stored 30,000 litres pumped direct
from the treatment plant.
(iii) The third extension, again designed by TWAD, entails constructing additional SRs
North of river Tambraparni where bulk of the population resides and where ground level
variations aggravate water shortage problems. These are variously located as,
Meenakshipuram, Pasukidavilai, Mudaliarpatti, Ayyanarkulam, Ambalavanapuram/
Irudayakulam and Sankaranpandinpuram/ Kottavilaipatti (See Map 10, 11 and Annex - 4
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
46
for the entire existing and proposed w.s. scheme). The Vikramasingapuram ULB has on
its own been managing water supply distribution to stall problems, by boosting
arrangements at the mains and avoiding management delays. The present proposal
intends to systematically streamline and plan for long term supply, using population at
2001, 06 (Est. 50,800) and projections for (2021) 59200 and (2036) 69000. The design
population (after deducting for population in hamlet on slopes- dams etc) is 48885
(2006); 58969 (2021); 66396 (2036). The norm adopted is 90 lpcd, (10% additional for
commercial requirement and 10% for transmission losses.) A 16 hours supply
propositioned by TWAD implies 6463 lpm (2021), and 7531 lpm (2036). A 5 percent
loss for backwash, and 3 fillings per day for service reservoirs has been assumed. The
scheme continues to use surface water from the existing location upstream at
Kodalmelalagian anicut. Raw water @ 6.5 MLD – 2021 and 7.6 MLD- 2036 will off take
from same source. (The scheme is in operation and foresees a per capita cost of Rs.503
and the water cost @ Rs.2.53 per 1000 litres)
The projected demand for water by this perspective year 2038 @ 90 lpcd matches the demand of
this study and is acceptable.
Table 4.1: Existing Storage Capacity
S. NO. LOCATION STORAGE
CAPACITY
(IN LAKH
LITRES)
1 GLSR at Vambalanthanparai 14.62
2 SR at Pothigaiyadi 0.30
3 SR at Mettu Thangamman koil St. 2.00
4 SR at Taana 3.15
5 SR at Agasthiyarpuram 2.00
Total 22.15
Source: Vikramasingapuram Municipality
4.1.2 Storage Capacity and System Adequacy
(i) Gross supply to the town at present is 83lpcd. To bring it to the assigned 90lpcd, the
improvement works by TWAD board are in progress. The existing treatment plant
designed for treating 5.7 MLD needs to be augmented to 7.6 MLD (2036) with an
intermediate 6.5 MLD (2021) for the projected design population envisaged by TWAD.
As mentioned earlier, this would involve besides the existing 3 GLSRs, at Vamnalanthanparai
and Taana and the 40HTs, constructing a further new clear water sumps of 5 LL (1 hour
detention time), 4 LL (near existing) and 60,000 lit (Taana) and 7ESRs.
Thus the raw water tapped would increase by 33% (from 5.7MLD to 7.6MLD) by the TWAD
board exercise. As per our forecast population the situation would imply as below:
Table 4.2: Projected Population and Water Supply Demand
YEAR POPULATION WITH 15% @90 LPCD @135 LPCD
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
47
INCRE
ASE
2011 54178 62304 5607360 8411040
2021 60761 69875 6288750 9433125
2031 68143 78364 7052760 10579140
2041 76423 87886 7909740 11864610
Source: IPE Analysis.
The supply at 90 lpcd would be adequate with 7.6 MLD envisaged by TWAD but with the
increased supply (@135 lpcd) it would be short by nearly 3 MLD.
Table 4.3: Water Supply Demand (@90 LPCD)
Year Demand @90lpcd
2011 5.6 MLD
2021 6.2 MLD
2031 7 MLD
2041 7.9 MLD
Source: IPE Analysis
Fig 4.1: Water Demand
Source: IPE Anlaysis
Assumptions: 47% HHs. have HSCs @ 83 lpcd (2006)
(ii) The existing status is already known to the ULB for updating performance in water supply to
raise standards from:
• 83 lpcd at present to 90lpcd and ultimately to 135 lpcd.
• Reduce T & D losses to 2% from 5%.
• Improve distribution reach from 80% to 100%
• Enhance treatment of storage capacity from 39% to 100%
• Improve PT assessment with HSCs from 47% to 100%.
Presently HSCs are charged a flat rate of Rs.55/ month for residential connections and Rs. 105/
month for commercial connections, with a one time connection fee of Rs. 3000 and Rs.
6000 respectively.
4.1.3 Demand Supply Gap
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
48
For getting a realistic demand for Vikramasingapuram, it is prudent to add 15% population to the
projected population for achieving efficiency in service delivery. This has already been
done in Table 4.2
The water supply improvement scheme envisaged in the DPR for Vikramasingapuram was
necessary for addressing water supply (in Meenakshipuram, Pasukidavilai, Mudaliarpatti,
Ayyanarkulam, Ambalavanapuram and Sankaranpandinpuram) created due to ground
variations and which fall north of the Municipality. It entails a proposed treatment plant
(for water demand beyond the intermediate (2021/ 6.5MLD) for an ultimate additional
demand of 2.55 MLD (the intermediate is to be served by rehabilitating existing
treatment plants as suggested by the financing Institution TUFIDCO). New construction
in the scheme are besides the treatment plant, an additional 7 ESRs which obtains an
additional length of 25.5 kms, includes ancillary works as culvert/ drain crossing, road
cutting/ restoration, bifurcation valves, power and support RCC columns etc.
The additional components of the water supply scheme are sufficient for meeting the ultimate
requirements of the town and will close the demand supply gap.
Table 4.4: Total HHs forecasted with HSCs
YEAR % HHS WITH HSCS @ LPCD HHS
2011 75% 90 18059
2021 100% 108 20253
2031 100% 120 22714
2041 100% 135 25474
Source: IPE Analysis
Table 4.5: HH Forcast for Water Demand for HSCs : Non HSCs
YEAR HH WITH
HSCS: NON HSCS
POPULATIONWITH
HSCS : NON HSCS
WATER
DEMAND
@ 90 LPCD (2011)
@ 108 LPCD
(2021)
@ 120 LPCD
(2031)
@ 135 LPCD
(2041)
2011 13542 : 4516 40626 : 13548 4.86 MLD
2021 20253 : 0 60761 : 0 6.56 MLD
2031 22714 : 0 68143 : 0 8.17 MLD
2041 25475 : 0 76423 : 0 10.31 MLD
Source: IPE Analysis
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
49
Fig 4.2: Water Demand at Assumed Consumption Level
Source: IPE Analysis
Table 4.6: Water Supply Indicators
INDICATORS VALUE
• Gross lpcd 83
• % Storage Capacity 39%
• % HHs assessed with HSCs 47%
• Ratio of Distribution network length to
total Road Length
80%
• Cost / 1000 litres Rs.2.53
• Revenue /1000 litres Rs.1.99
• Current collection Performance 23%
Source: IPE Analysis
4.1.4 Designing the Services
(i) Distribution is best in a grid pattern with interconnected mains keeping dead ends to a
minimum; this way any point is fed at least from two different directions. Smaller water
supplies may resort to tree system when smaller mains branch off from single trunk main.
(ii) Distribution should ensure equalization of supply throughout the area. If adjoining zones
differ in elevation by 15m-25m, then each zone needs a separate system. Zoning of water
supplies takes into account population densities/locality type/topography and the ease
with which the system can be isolated when leaks occurs.
(iii) When water supply is fed through a single reservoir, it is economical to place it at a
central place. Difference in elevation should be used to advantage when locating
reservoirs at ground level. Difference in pressure between same zones/same system
Water Demand
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
50
should not exceed 3m to 5m. Tail end reservoirs are desirable for the more distant direct
locations, and are fed by supply either by boosting or during lean hours.
Storage provision, as recommended should be for 24 hours water requirement of command area
at the reservoir site. Since a number of sources are used, at least one day storage is
expected (for any eventuality). Storage volume for 2021 projected water demand is
suggested along with provision for future augmentation.
(iv) The different water zones for the city are given in table 4.8, demarcated to provide
coverage to the entire development in the town. As per practice, R.C.C construction is
used, proper protection ensured and unnecessary utility services, disinfection, ground and
security wall is provided.
(v) Water losses need to be minimized. Classified as physical (due to leakage, old damage
and corroded pipes, leaking joint connections, overflow at OH Tanks, poor plumbing at
consumer end) or administrative (as theft, illegal tapping, unregistered connections,
faculty meters, unrecorded supply, poor recording, faulty billing) water audits and leak
detection studies become necessary to curb such menaces. An information base of
reliable data (preferably GIS enabled) can ensure efficient delivery and conserve a scarce
resource.
The tariff for water is fixed by the Executive Officer through a consultation process with the
ULB. The last revision in tariff was in 2005. The Demand – Collection Balance statement
Table 4.7 through the years 2002-07 have shown variation in the collection efficiency
ranging from 100% to 23% averaging at 50%. The lowest was in FY 07 [23%] with
consistent decline between FY 04-07. This maybe due to poor service delivery,
unwillingness to pay, weak management, or even high collection cost. Reasons would
have to be pinpointed to improve service and enable the ULB to enhance its HSCs base,
both domestic and non-domestic. Bringing reforms as e-billing, incentives, penalties and
GIS based property registration would prove rewarding.
4.1.5 User Charges and Collection Efficiency
Table 4.7: Water Tax. Demand Collection Balance Statement
ITEMS FY FY FY FY FY
03 04 05 06 07
Demand (In Lakhs Rs.)
Arrears 0.00 0.00 0.00 64.41 81.43
Current 30.59 46.35 46.80 51.48 55.00
Total 30.60 46.36 46.80 115.89 136.43
Collection (In Lakhs Rs.)
Arrears 0.00 0.00 0.00 9.79 7.63
Current 30.59 23.99 20.66 24.68 24.02
Total 30.59 23.99 20.66 34.46 31.65
Collection Performance
Arrears 0% 0% 0% 15% 9%
Current 100% 52% 44% 48% 44%
Total 100% 52% 44% 30% 23%
Source: IPE Analysis
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
51
4.1.6 Key Issues
• Coverage of HSCs to 75% can enlarge the revenue base from water tax for which the
already prepared DPR should be urgently taken up for implementation. This will help
keep in step with the water demand.
• Future strategies for water recycling and adopting new technology is necessary
knowing that over use of water should be discouraged. Energy costs for pumping are an
environmental cost.
• Policy for locating ESRS on higher elevation naturally available in the town should be
explored. The trade offs for cost can be determined between longer hours for supply to
longer length of water mains.
• Distribution network reach needs to fill existing gap and ensure zero gaps in future.
• Roof rain water harvesting should be mandated in the building bye laws. Recharging
depleted water bodies and storing water during monsoon is recommended.
• All slum areas should be covered adequately for supply.
• Elevated reservoirs may combine other uses such as offices within a structure which
can handle both functions safely
4.1.7 Effective Practices
Certain practices, adopted across countries could serve to guide ULB water supply systems in
Tamil Nadu including in the reference ULBs.
• Water audits for ascertaining unaccounted for water (especially in underground pipes)
• O&M Plan. Adopting an O&M Plan with a schedule; with private participation (e.g.
Management contracts).
• Mapping & GIS is important in laying of services, detecting dilapidation and renewing
etc.
• Tariff Revision is essential to enlarging the coverage and recovering costs/debt
servicing/modernizing/installation of equipment etc.
• Performance Monitoring for better service delivery, consumer satisfaction and continued
service.
• Capacity Building and institutional strengthening Training needs for field staff is required
for operating, maintaining and servicing the water supply system.
4.1.8 Enhancement of Water Supply-2009
Water Supply System has been strategically enhanced in the town with water supply raising form
2.9MLD to 4.8MLD. The revised service levels and a comparison of desired service
levels for the town are provided in the table below:
Table Error! No text of specified style in document..9: Revised Service Level Compared with
desired Service level
S. NO HEADS 2007
2009 2011
2015 2021 2041 UNIT
1 Daily Supply 2.90 4.80 5.35 5.80 6.47 8.61 MLD
2 Per capita supply 88.00 146.00 135 135 135 135 LPCD
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
52
3 Treatment capacity 0.00 0.00 5.35 5.80 6.47 8.61 ML
4 Roads Covered with
Distribution Network
43.87 46.00 51.77 54.75 61.11 81.29 Km.
5 Elevated Storage
capacity w.r.t Supply
1.30 1.89 1.78 1.93 2.16 2.6 ML
6 Refurbishment of Old
Distribution Network
0.00 0.00 0.00 0.00 23 23 Km.
7 Metering System Not available Required Nos.
8 Development of
Monitoring System
Not available Required LS
9 LPCD with same
water supply-4.8
146 121 112 100 75 LPCD
Source: Ambasamudram Municipality, June 2009 and IPE Analysis
4.1.9 Strategies and Time Frame
The following strategies and time frame has been adopted to over come the identified gaps in
water supply sector.
Table 4.8: Strategies and Time Frame – Water Supply
Sl. No. Strategy 2009 2010 2011 2012 2013
1 Asset Management Plan
2 Leak detection plan
3 Mapping & GIS
4 Piloting 24/7 water supply
5 Source Augmentation
6 General Households
7 Households coverage for slum
Source: IPE
4.2 Sewerage and Sanitation Systems
4.2.1 Existing Sewerage System
Existence of a sewerage system in a town determines its environmental status; the development of
the system and its efficient treatment is a prerequisite for a quality of life. Issues of
covering large populations emerging in urban areas, augmenting the system, adopting
technologies for treating the liquid waste etc. have to be resolved, especially when water
is scarce, financial resources burdensome, and people unwilling to pay for improvement.
In the state of Tamilnadu, the TWAD Board is the planning agency for what is termed the
“Underground Drainage” (UGD), and ULB executes, operates and maintains it.
4.2.2 Current Disposal System
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
53
There is no standard sewerage system in Vikramasingapuram for disposing off sewage and
sullage. The present disposal system consists of a combination of septic tanks and
community toilets. Untreated sewage and liquid waste is transported through surface
drains (both Pucca and Kutcha) in all parts of the town to be let out raw into the canal or
accumulate in low lying stretches, creating unhealthy environments. Slum dwellers as
well as other low income population depend on community toilets or defecate in the
open.
Coverage of Sanitation
Table 4.9 ULB Sanitation
Item Unit
Town area 38.57 sq kms
Population (2001) 48307 persons
Septic tank Connected to 11425 HHs (62.4 %total
properties)
Low cost sanitation units nil
Community toilets Slums under VAMBAY scheme
3 toilets @7 seats each.. 21 seats
Non slums.. 4 toilets @ 10 seats each 40 seats
Source: Vikramasingapuram Municipality 2007
Nearly 62% HHs in the town have access to some safe form of sewerage with septic tanks; the
coverage is low and an aspect of concern, with the alternative of community toilets not
being satisfactorily maintained. The public conveniences provided have limited seats
which cover only the visitors to the city. Open defecation must be totally disapproved due
to its environmental risks.
Nearly 11,425 properties (62.43% of total) are assessed for property tax and have septic tank
connections; the remaining population depends on Community toilets or defecates in the
open. Community toilets are normally poorly maintained and have inadequate seats as
required by the standards. It appears that in Vikramasingapuram the provision for toilet
seats is nearly 140 persons/seat and would need to be upped three times for the present
population to be adequately served by this mode. Open defecation must be totally
disapproved due to the environmental health risks.
4.2.3 Putting a Sewerage System in Place
The Under ground sewerage system will be designed for zones compatible with the natural
topography and cater to populations in the different city zones including the core area and
the extended city. In the elementary stage, oxidation ponds are used for primary
treatment. The municipality has to use equipment like vacuum pumps and jetting
machines to clear choked lines, water logging and for clearing septic tanks. Sewage can
also be disposed off in sewage farms and on land.
4.2.4 Issues
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
54
1. Absence of sewerage facility and poor sanitation can often result in water borne diseases
in the town, especially when population densities are intense and neighbourhoods are
closely packed. Future population needs to be protected from health risks.
2. Mixing of sewage, storm water and solid waste can be hazardous; especially dumping night
soil into water bodies can have adverse ecological impacts.
3. As there is no sewerage facility the user charges cannot be imposed and municipal finance is
affected.
4. Uncontrolled solid waste dumping and encroachments results in silt formation; open SW
drains become easy dumping places of waste in the town and often block flow resulting
in overflows.
4.2.5 Demand and Supply Gaps
Planning for sewage treatment demands 80% of water consumption. Accordingly water
consumption @135 lpd has been assumed for the projected population of 87886 for the
year 2041. This produces sewage of 9.5 MLD (2041).
Table 4.10: Sewage System Proposed
YEAR POPULATION PER CAPITA
SEWAGE
GENERATION
(LITERS)
LENGTHUGD
NETWORK
(KMS)
TREATMENT
PLANTCAPACITY
%PROPERTIES
CONNECTEDBY
HSCS
2011 62304 108 74.5 6.7 100 %
2021 69875 -do -do 7.5
2031 78365 -do -do 8.4
2041 87886 108 -do 9.5
Source: IPE Analysis
Note: 1. Assuming there is no increase in road length network and future growth. Future growth will be
as infill re-densification
2. The length of the distribution network will depend on spread of future urban areas and the
associated network of roads. At a conservative estimate, by 2041 the length of
distribution network will be 100 kms.
4.2.6 Strategies and Time Frame.
Table 4.11: Strategies and Time Frame – Sewerage and Sanitation System
Sl. No. Strategy 2009 2010 2011 2012 2013
1 Asset Management Plan
2 Sewerage for unserved areas
3 Mapping & GIS
4 Network Coverage of Slum Households
Source: IPE Analysis
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
55
4.2.7 Designing the System
(a) Sewerage treatment is dependent on how the final product has to be utilized and who
will regulate it to ensure it is of unpolluted form. The by products of sewerage treatment
(manure, gas and liquid waste) can be used, as done in different cities in India.
(b) Treatment plants require to be decentralized to meet neighborhood needs for all the
end products. Large scale treatment plants should be designed and completed in not more
than 1-2 years and should normally meet the requirements of a 30 year period.
(c) Industrial waste, quantified as population equivalent, for suspended solids and BOD
(90 gm and 45 gm respectively) is used for levying charges for accepting industrial waste
into the sanitary sewers. They should however be within tolerance limits set by BIS codes
for discharge onto land or water bodies.
(d) Reduction of BOD, SS, and total coliforms are expected of the sewage treated for
primary, secondary and tertiary levels. Settled sewage or sludge should be mixed with
peat / manure, composted completely (ensuring dehelminthization) and then sold for use
on farms.
(e) Conventional systems require large amount of land for treating effluent before
discharging. Since the consultants are proposing that settlements in the western ghat
region be developed on “Green” principles, the sewerage system envisaged takes a
longer perspective and considers decentralized STPs as friendlier solutions, both in
facilitating compact thereby low energy) development and utilizing new technology
spread over smaller plots of land whilst eliminating the need for digging deep sewers
which have proved hazardous.
4.2.8 Suggestions
• Low income households should be taken up for sanitation on a priority: provision of eco
– toilets can be considered. Here the toilet is above ground, three outlets are provided for
excreta, urine and water to be used, which are collected in separate chambers (Elevated
toilets are practical where water table is high, water is short or the terrain is rocky). Later
this toilet can connect to the city sewerage system. Karnataka has adopted these forms of
toilets to great success.
• A regular sewerage and storm water system should be designed and laid in the town.
• Buffalo / cow dung and other objectionable material entry into sewers has to be
prevented.
• As far as possible sewers should be cleaned with modern suction and other jet washing
machines reducing manual labour to a minimum and only in dire circumstances.
• Unauthorized connections have to be detected / penalized and later regularized within
short time frames.
• People, especially slum dwellers have to be prepared to accept sanitary system and
understand how to maintain hygiene.
• O & M plans are important and private management contracts can be operationalzed.
• Assets created in the town need to be well managed.
• Mapping and GIS are important for detailing the sanitary system, repairing it, and
renewing it after it has outlived its life.
• Tariffs need to be determined based on upgrading, recovering costs, and servicing the
debts from invested capital.
• Needless to say that performance of the sewerage system has to be consistently
monitored.
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
56
• The 7 slums located in wards mentioned earlier have a population of 3,550 within 1,010
HHs some of whom are in the notified slum pockets. Often they are located near water
bodies, in ward interiors or along major roads. In all they occupy 4.22 sq.kms.46% of
slum population is BPL the largest concentration being in ward 11.The standard for toilet
seats in community toilets is far below recommended, is filthy and on very poorly
drained area with solid waste strewn around.
• Slums in Vikramasingapuram are not covered by the IHSDP or BSUP schemes.
• Slum communities need to be organized to involve in slum improvement programs for
ensuring their sustainability.
• It is important to have individual HH’s avail independent toilet facilities and HSC’s so as
to be part of the standard city population.
4.3 Roads and Storm Water Drainage
Drainage, an important element of physical infrastructure helps remove and dispose off surplus
rainwater from the land. Urban expansion, an inevitable process, would imply providing
new drains as well as supplementary drains and also remodeling of existing drains due to
the increased run off co- efficient.
4.3.1 Existing System and its Adequacy
The city does not have an underground system. The terrain slopes towards the river; the north
Kodamelalagian channel runs east-west through the ULB area with most habitation north
of the channel, its southern side devoted to wet lands/ paddy culvitation with the terrain
helping to log water in the area between the channel and the river.
Drains are open type, nearly 58 kms in length and lined. Roads not covered by drains are subject
to erosion by rain water. Effective drainage helps reduce stagnant water and pot holed
roads as well as repeated resurfacing which is often repeatedly practiced by most
municipalities.
4.3.2 Current Improvement Proposals
Road sections/wards poorly drained are to be attended by projects listed for road improvement
works as framed in the prepared DPR FY-08 for all the ward roads of the town. A brief
abstract of the project is given in Table 4.12.
Table 4.12: Proposed Projects for Roads and Drains
ROAD TYPE ROAD WIDTH
(IN METRE)
ROAD
LENGT
H
(KMS)
DRAIN TYPE
Up to 3m 3-5m Single
Double
Earthen to cc paved 10.4 2.54 12.94 9.4 2.6
WBM layer to
BT/CC road
0.12 0.10 0.22 --- --
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
57
Renewal of BT road 0.94 2.38 3.32 --- 0.52
Repair reconstruction
of CC road
0.24 -- 0.24 --- --
Road widening Nil
Total 16.72 kms 9.4 kms 3.12 kms
Estimated Cost 211.8 Lakhs 0.94 Lakhs 0.78 Lakhs
Source: DPR for Road and Drains – FY 08
For the total road length of 67 kms, 25% is being upgraded to pucca roads with drains added to
(10kms. single and 3 kms. double sided) the project.
Table 4.13: Existing Situation: Road Networks
ITEM LENGTH
(KMS)
PERCENTAGE
• Surfaced Road
Concrete
Tarred/BT
WBM
Total
22.99
29.89
0
52.88
34.40
44.8
0.00
79.2
• Unsurfaced Road
Earthen
Others
Total
15.24
0.00
15.24
20.8
0.00
20.8
Total 66.8 kms 100 %
Source: DPR for Road and Drains – FY 08
4.3.3 Issues
Roads are proposed to be improved but alongside the drains are not being considered for both
sideswhich would have been preferable. Drains not just remove storm water but also
sewage and sullage which is dumped in. Thus drains need to be designed for year long
flow with their width, depth and culettes conforming to GANTT charts and sewerage
manuals. Similarly roads have to conform to CBR values.
4.3.4 Gap Analysis
Drainage is not perceived as as a key issue on account of the large number of water bodies which
help draining (16 ponds, 1 canal and 1 river). Yet well designed drains ensure
environmental health.Ideally there should be 134 km, length of drains which implies a
gap of 77kms. The proposed DPR will cover 13kms leaving a gap of 64 kms.
4.3.5 Strategies and Time Frame
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
58
Table 4.14: Strategies and Time Frame – Storm Water Drainage
Sl. No. Strategy 2009 2010 2011 2012 2013
1 Constructions of Drains
2 Rejuvenation and
Rehabilitation works
for Water Bodies
3 Operation and Maintenance
Schedule
4.4 Traffic and Transportation
Urban economy is seen to improve with urban transport infrastructure. Roads and circulation
is an important city land use allowing efficient functioning of the city’s activities.
Conversely, it can drag down and prove detrimental to its GDP
4.4.1 Existing Situation and Adequacy
• The land use distribution of the city has a very meagre land under roads (2%). Main city
roads aligned EW are the Ayyanarkulam road, Ambai-Papanasam road,
Ambavalanapuram and the Papanasam; in the other direction are the Keelakottaram road,
The Kottaram main road, the Karaiyar Dam road, the Servalar dam road, the
Thiruvandapuram road, West car and East car street, Poonthottam street.
• The indicator for road density 1.74 sq. km. is short of the benchmark of 10-
15kms./sq.km. The per capita road length 1.23 m is also short of the standard of 1.75 m.
Surfaced roads (existing 77%) should be 100 percent surfaced. Project roads will increase
this length by 16.7 km adding 25 percent length.
• The development in scattered fashion is served by linear roads. Within is a system of grid
iron streets giving access to residential areas while the commercial areas and bus routes
are aligned along the main roads.The composition of roads by surface type is given in
Table 4.13.
• Interior road widths range from1.5 to 9 m. There is no strict road hierarchy. The plan on
future should engage on this.
• All roads are municipality maintained as the town does not have a state highway passing
through. Public transport is by auto and mini buses. The bus stand in ward 6 at an
important junction is conveniently located but fairly congested needing both upgradation
and as a revenue source.
4.4.2 Issues
• Absence of organized parking near bus stand
• Absence of parking areas near commercial and other public areas
• Carriageway widths need to be maintained
• Connection to regional roads needs to be strengthened
4.4.3 Suggestions
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
59
• Traffic surveys can provide causes of delays and its rectification
• Signals, crossings, sidewalks, road markings, intersection treatment, bus bays & shelter,
landscaping & street furniture are areas needing attention.
• Campaigns for road safety, driving behavior, road education are important for citizen
safety
• Essential road furniture includes
o Kilometers stones / signboards
o Road painting with reflectorised thermoplastic paint.
o Regulatory / cautionary sign boards
o Street lights of standard intensity and at standard distances.
o High mast lights at all major junctions.
o Other signs as required
o Policy on advertisements / hoardings.
• Review location of alternate bus stand
4.4.4 Railways
At a distance of 9 km there is need for for a line extension, or, frequent low cost to and fro bus
journey between this town and Ambasamudram to boost both city economies.
4.4.5 Strategies and Time frame
Table 4.15: Strategies and Time Frame
Sl. No. Strategy 2009 2010 2011 2012 2013
1 Up – gradation of Roads
2 Formation of New Roads
3 Pedestrianisation & Signages
4 Parking Management
5 Junction Improvement
6 Widening & Strengthening
4.5 Solid Waste Management
One of the most critical it is also one of the most poorly managed function of most municipalities.
It is important to address it by relooking at system technology, finance, and other
associated problems so that problems don’t get out of hand.
4.5.1 Existing System and Adequacy
Several kinds of wastes are generated in a city, as, commercial, household, bio medical,
construction, hotels etc. Increase in incomes also leads to more waste generation. Tourist
and visitor inflows add to the quantum of waste. Besides there is street sweeping and
occasions such as marriages, festivals all of which require quick off loading and disposal
before it putrifies. Other factors as birds, dogs and cats, pigs, flies and insects both living
and dead have to be taken care of. The municipality’s domain in this matter is very wide.
Table 4.16: SWM Status and Indicators
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
60
ITEM UNIT BENCHMARK GAP
Garbage generated /day/MT 12.00 _ _
Collection by municipality/day/MT 10.00
83.33%
100% 17%
Collection by private
contractor/day/MT
NIL _ _
Water generation gln/day 216 <350 nil
Area covered per collection
point(sq km)
1.8 0.16 90%
Moisture 5% _ _
Door to door collection efficiency 75% 100% _
Collection frequency daily daily _
Dustbins capacity (0.1 MT) Nos 142 _ _
Hand carts (0.3 MT) Nos 25 _ _
Waste treatment (secondary to
disposal site)
Tipper Lorry
Non Tipper Lorry
Tipper Auto
Mini lorry @ 3trips/ day
Power Tiller @10 trip /day
1 No.- 2.5 MT each
1 No.-1.5
MTeach
4 No.- 2.8
MT each
5.25 MT
Quantitytransported
4.75 MT quantity
transported
Source: Vikramasingapuram Municipalilty and IPE Analysis
Table 4.17: Quantity of Waste by Source
ITEM QUANTITY (MT) %
Domestic 5.8 48.5
Commercial 2.2 18.4
Institution/hospital / Ind /other 4.0 33.2
Total 12.00 100.00
Source: Vikramasingapuram Municipalilty, 2006 and IPE Analysis
Note: Waste generation by hospital - 0.18 MT
Waste generation by eating places - 0.5 MT
The municipality disposes the collected waste to a site of 6.4 acres located at
Kattaboman colony.
4.5.2 Composition of Waste
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
61
Majority of waste generated is by the domestic households and collected through street sweeping.
Per capita generation in Vikramasingapuram is 216 grams per day. Solid waste generated
in Vikramasingapuram is mainly organic in nature. The major contributors to the solid
waste generated in the town are households and commercial areas. The other major
components being inert material mixed with paper and plastic. Apart from these, bio-
medical waste also mixes with the domestic solid waste generated by the city.
• Domestic waste per household varies from area to area with an average as given, yielding
nearly 5.8 MT per day, the market waste (mostly decomposable) is around 2.2 MT
including paper, plastic, metal and other inorganic material.
• Biomedical waste (0.2 MT) is required to be destroyed by the Hospital authorities but the
prevalent practice is to bury it at the compost yard. It is required to be scientifically
handled as per the manual guidelines and SWM rules (2000) mandated by State Pollution
Control Boards.
4.5.3 Solid Waste Collection, Treatment, Disposal
Primary Collection and Street Sweeping The ULB has 21 wards with 4 sanitation wards. The municipality has detailed wardwise
information on populations/ HHs from whom door to door collection is made through use
of push carts in two day trips (6.30 - 8.30 am and 8.30 -10.00 am) with a capacity to carry
80 kgs/ trip which average to 215 kgs/ ward. This sytem requires 3 bins to be placed from
secondary collection points. Norms suggest 250 HHs to be handled per sweeper, and
distance norms of 70 m. for unloading waste at the secondary collection point. Together
the system upto this point can have a capacity to handle 13.5 MT of waste (in actual
practice there are 142 dust bins of 0.1 MT capacity each giving total capacity of 14.2 MT
which is sufficient). 100 percent collection efficiency has been reported.
Secondary Collection The clearing of bins and transportation to disposal site (which is 5 km away on a 6.84 acre site
located at Kattaboman) is done daily; its weight /volume/estimated by visual inspection;
the activity is being performed by Tipper autos/ lorries.
4.5.4 Issues
• Biomedical and construction waste requires serious consideration for disposal.
• Waste not being scientifically treated and managed. Absence of covering the waste daily
with inert material.
• Waste not compacted on disposal site.
• Source segregation not ensured.
• No separate community bins for bio and non biodegradable waste.
• Absence of community composting of ward level.
• Absence of ragpickers organized for waste resource recovery.
• Very little private participation for public toilet maintenance; community
awareness/participation missing.
• Absence of information systems/ penalties/ periods campaign for ensuring clean town.
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
62
4.5.5 Suggestions
• Priority has to be accorded to segregation and storage of waste at source irrespective of
area of generation so as to adopt environmentally acceptable waste management
measures.
• The adoption of four R’s - Reuse, Recover, Recycle and Reduce can help ease pressure
on landfill sites and affords resource recovery.
• Varieties of waste have to be differently dealt with; construction waste should be stored
in proper skips at the premise and directly emptied by the generator at notified sites;
slaughter houses need to keep separate container for animal and other wastes;
Commercial – Hotel – Market waste should be privately collected and disposed.
• A number of campaigns / community awareness should be organized for introducing
source segregation.
• Waste handling operation should be minimized; non – biodegradable waste from
premises should have organized collection.
• Primary collection should cover all areas of the town with even innovative but safe
transporting arrangements.
• Street sweeping should be gradually privatized to include market and other areas /
desilting of drains / collection of green waste / hospital and hazardous waste / gardens
and other recreational areas / Religious and other public places etc.
• Recycling efforts by self employment SHGs should be encouraged
• For townships as Vikramasingapuram which are in close proximity to 4 other urban
areas, all within a 10 km, should adopt regional engineered land fill site for waste
disposal. This ensures scale and viability to the private participation mode.
4.6 Street Lighting
4.6.1 Existing Situation
The provision and maintenance of street lights is an obligatory function of Vikramasingapuram
Municipality. This includes their installations, replacement/ repair, operation and
maintenance. There are 1610 street light poles in the town with various types of
illumanaires given in the table below.
Table 4.18: Existing Status - Street Lighting
LUMINARY TYPE NOS. %
Tube lights (40w) 1400 87
Sodium vapor lamps
(150w)
210 13
Mercury vapor lamps
(125w)
0
Total 1610 100.00
Source: Vikramasingapuram Municipalilty
Table 4.19: Urban Indicators (Street Lights)
INDICATOR VALUE BENCHMARK
Spacing between 53m 30m
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
63
lights(m)
Ratio tube lights : low
Energy lights
9: 1 All lights should be
low energy
O&M Cast/ light. NA NA
Source: Vikramasingapuram Municipalilty
4.6.2 Coverage
Coverage of street lights is highly inadequate and needs to be doubled. High mast lights, though
of higher initial cost, serve to illuminate much larger areas, are low energy users, are less
damaged/ vandalized due to their height, and serve to effectively illuminate traffic
junctions/ high traffic zones thereby averting accidents/ thefts/ other mishaps. They need
to be introduced to serve at least 40 percent of illumination requirements.
4.6.3 Issues
• Standards for illumination have to be adhered.
• Timers to street lights ensure less wasteful culture.
• Energy audits and low energy adoption measures need to be undertaken for reducing
energy expenditure by municipality by at least half.
• Solar lamps (sponsored by business houses/ communities/ other active participants)
should be adopted.
• Residential area safety with adequate illumination should be ensured.
4.7 Social Infrastructure
4.7.1 Education
High literacy level in Ambasamudram taluk, Tirunelveli district has given this town an edge. A
number of educational institutions ensure adequate enrolment as shown in table below:
Table 4.20: Existing Status – Educational Institutes
INSTITUTION NOS ENROLLMENT
Primary school 8 2875
Middle 3 1850
High 4 2560
Art collage 1 960
Total 16 7245
Source: Vikramasingapuram Municipalilty
With 15% of town population engaged in education activity and 33% as workers gives an account
of nearly half the population engaged in meaningful activities. There is need to up
educational profiles of people enabling them to be entrepreneurs or skill fully employed
persons by equipping them with requisite education and training. This is important to
complete with others and upgrade this quality of life.
There is dearth of science, commerce, engineering, medicine, arts and graphics, agricultural
science, I.T. and other educational institutes relevant to today’s needs. Strengthening the
educational base of the town and further envisioning it as a concentrated node of
CDP - VIKRAMASINGAPURAM FINAL REPORT
DMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
64
educational activities could help deliver economic growth and its renewal. This study
considers the presence and propagation of educational institutes as having tremendous
influence in the town’s future growth, whose impacts can be far reaching and also help
enriching the human resource base and thereby ensuring positive developmental
outcomes.
Though no gap is perceived in this particular social infrastructure but its enhancement is seen as a
strategic move. It is suggested that institutes relating to IT, fashion, traditional art,
architecture and design, hospitality, enterprise and management development, commerce,
basic accounting, law, tourism & environmental studies etc. be located in special
Educational Zones in the town or as adjunct to the town. Establishing institutes ensures
regenerating the town’s ethnicity, economy and sustainability
CDP - VIKRAMASINGAPURAM INTERIM REPORT
CMA, GoTN INFRASTRUCTURE PROFESSIONALS ENTERPRISES (P) LTD
65
Plate 3: The Town’s Physical Infrastructure - Vikramasingapuram
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 66
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
4.7.2 Health
The town’s - both public and private health facility constitute of one government hospital, 2
private hospitals and 7 nursing homes sharing between them about 30 beds and 21
qualified doctors.
Table 4.21: Existing Status – Health Facilities
FACILITY TYPE NO.S. BEDS
Government hospitals 1 NA
Private hospitals 2 NA
Nursing homes 7 NA
Total 10 30
Source: Vikramasingapuram Municipalilty
4.7.3 Socio-Cultural
The city enjoys harmonious relation amongst different communities, castes, religious groups
and other socio cultural factors. Fairs and festivals are enjoyed by all and there have
been no recorded incidents of any violence, dissidence or other forms of revolt.
Conversely people of all denominations desire unity in tackling city issues and
peaceful resolutions to all issues. This is a very positive aspect and should be
constructively used in community participation and awareness programs.
Table 4.22: Religious Buildings
BUILDING TYPE NOS
Temples 6
Mosques 4
Churches 7
Source: Vikramasingapuram Municipalilty
4.7.4 Public Places
The numbers of tourist places/ pilgrim centres in and around the town are sufficient for
tourism projects to take off. The town being an entry town to the natural areas can
capture tourists if tourist infrastructure is in place. All water bodies in the area can be
made into picnic spots for citizen’s enjoyment. The town has one library, three
cinema houses, one auditorium and one organized park in the city.
The office complexes have Fire Station, Post and Telegraph Office, Police Station, Ranks and
other city amenities.The town has Burial grounds and a Crematorium.
Greens can be developed into picturesque area along the two water channel and riverside,
integrating them through shaded avenues with the other 16 water bodies in the town.
There is need to culturally keep the town activated by providing opportunities for
song/ dance/ drama/ art exhibitions/ other cultural activities for the enjoyment of
citizens.
4.7.5 Issues
Social Infrastructure in a town is contributory to its development and growth as well as
fulfillment of non-material goals. Infrastructure standards should be such to be
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 67
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
availed by all, and, inadequate infrastructure especially to the urban poor should be
avoided at all costs.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 68
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Chapter 5 HOUSING, SLUMS and THE URBAN POOR
5.1 Introduction
Housing is a crucial requirement in a city no matter what the size. It is also the largest
Land use constituting nearly half of all Land uses in the city. It can be available
in many forms as:
• Government and Municipal Housing
• Rental Housing
• Co. operative housing in lots or apartments.
• Privately developed colonies
• Unauthorized occupation of government or other private lands
• Squatting and temporary hutments
• Core area dilapidated housing etc.
Several variations of these types exist in almost all small, medium or large towns, the
commonest being self occupied self owned, or rental housing, with the rest being
driven to marginal options as slums, squatting or pavement dwelling. Towns in Tamil
Nadu, as the ones in our reference study have very little speculative housing because
of a poorly organized real estate market.
Most housing plans have no provision for housing for the poor, thus depriving them of
adequate housing. State intervention is necessary in this matter and for enjoying a
dignity of life; the vulnerable population has to be covered for housing. Currently,
central programs are specially committed to resolve this dilemma and special funds
devised to execute the schemes for housing the poor.
5.2 Housing Conditions
Vikramsinghpuram town has grown around the aforementioned 13 villages of which 4 are
located on the eastern slopes of the Western Ghats at foot of the Pothigai hills in
picturesque surroundings and containing within them the reserve forests, three dam
sites (Upper, Lower and the Servalar dams) the River Tambraparni and plant of the
Kodamelalagian channel from where the towns water supply is sourced. It proximity
to the taluka headquarter Ambasuamudram (about 9 kms), various waterfalls in the
region namely, Agasthyar, Papanasam, Courtallam, Manimuthar, Wildlife and bird
sanctuary as Kalakad Mundanthurai and Kunthankulam, make it ideal for capturing
tourism especially religious, adventure and eco-tourism considering natural resources
and several temples, myths and legends associated with the belt which are now being
substantiated by the Archological Survey’s findings in this region. Thus, the towns
historicity is fairly established and further inquiry into documented and other
information sources can yield further evidence; its location off the SH-40 but
connected to it through the Papanasam Road is both an advantage and disadvantage
depending on how the town is economically positioned, but explains why with the
downsizing of Madura Coats factory has adversely affected the town’s growth.
Core areas have G+1 or G+ 2 developments and mixed landuses and pucca construction.
Housing condition is brifly described below:-
Table 5. 1 Housing Condition (for Roof, Floor, Walls)
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 69
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
BUILDING TYPE HOUSES(NO
S)
%
Kutcha 350 2.1
Semi pucca 9625 57.9
Pucca 6650 40.0
Total 16625 100
Source: Census of India, 2001
Affordabilities for a permanent durable house vary as shown by the figures, with less than
half of the houses being of permanent type.
5.3 Slums and BPL Population
Nearly 422 Ha of land is occupied by slum housing covering 3,550 persons. The BPL
population, as percentage of slum population is shown in Table 5.2.
Table 5.2: Ward-wise Slum Population
S. NO. WARD NO. SLUM NAME ARE SLUM
POPU
LATI
ON
(2001)
(PERS
ONS
& % AGE)
SLUM
H/HS
SLUM WARD
POPULATION
1 3 Meenakshipuram,
Arunthathiyar
Colony
92 380
(10.70%)
110 2412
2 9 Pothigaiyadi 43 220
(6.20%)
30 2071
3 11 Anavankudiyiruppu 112 1100
(30.99%)
290 2794
4 13 Kamaraj Nagar 90 300
(8.45%)
90 2708
5 19 Gandhipuram,
Maruthuvar colony
85 550
(15.49%)
160 2285
6 20 Harijan colony &
Kamaraj Nagar
- 600
(16.90%)
180 2103
7 21 Georgepuram - 400
(11.27%)
150 2119
Total 422 1548
(100%)
1010 16,492
Source: Vikramasingapuram Municipality& IPE Analysis
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 70
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Observations: BPL: Slum Population = 46.0%
Slum Population: Town Population = 7.40%
BPL Population: Town Population = 3.40%
The profile of the urban poor is explained in the above table and its observations indicating
that the problem is of manageable scale. Measures to prevent slums may be adopted
in urgency.
Another comparision is made in the above table between the wards to show concentration of
the urban poor population. This would show where action is required within the town.
Wards which have slum population, i.e. wards 3, 9, 11, 13, 14, 19, 20, 21 require
handling sensitively the needs of the urban poor.
5.4 House Categories; Definitions
National Sample Survey Organization (NSSO) of India had categorized houses into three
types i.e. Pucca, Semi-Pucca and Kutcha. Census data on housing conditions in urban
area especially for district and taluk is available in Census of India 2001, only
through typologies of houses with various types of roof, walls and floors.
(a) Houses with Various Types of Roofs
Housing roof made up of Grass, Thatch, Bamboo, Wood, Mud, Plastic and Polythene are in
Kutcha category. Roofs made of Tiles, Slate, GI, Metal and Asbestos sheets are in
Semi-Pucca category and Brick, Stone, Concrete are in Pucca category.
(b) Houses with Various Types of Walls Housing walls made up of Grass, Thatch, Bamboo, Plastic and Polythene are in Kutcha
category. Walls made of Timber, Iron, GI, Metal and Asbestos sheets are in Semi-
Pucca category and Brunt Brick, Stone, Concrete are in Pucca category.
(c) Houses with Various Types of Floor Floors made up of Mud and Wood are in Kutcha category. Floors made of Brick and stone are
in Semi-Pucca category and Cement, Mosaic is in Pucca category.
5.5 Infrastructure Provision in Slums
(a) Water Supply Slums have piped water provided though public stand points in addition to which hand pumps
too are provided. There are 25 public stand posts and 15 hand pumps with a
distribution network running into about 14 kms within the slums.
(b) Sanitation Of the 1010 HHs in slums, 350 HHs (35%) have septic tank connections, the remaining being
served by 3 community toilets with a total of 21 seats, nearly 100 persons per seat
which is much less than the benchmark, good sanitary conditions are as important
goal.
(c) Roods & Street lights Nearly 8 km of bituminous roads are available to slum residents. These having pucca storm
water drains on one side measuring of total length 4 km.
Table 5.3: Details of Infrastructure Facilities in the Town
WATER SUPPLY STREE
LIGHT
S
NAME OF SLUMS WAR LENGTH
O
F
BT
R
O
LENGT
H
OF
S
W
D
PIPED PSP HP
PUBLIC
TOI
LET
S
WITH
SEP
TL
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 71
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
A
D
S
TIC
TANKS
KMS KMS KMS NO NOS NOS.
Meenakshipuram,
Arunthathiya
colony
3 1.18 0.75 3.10 3 2 - 10
Pothigaiyadi 9 0.9 0.40 1.75 3 3 - 5
Anavankudiyiruppu 11 1.97 0.17 1.90 4 1 - 13
Kamaraj Nagar 13 1.63 1.12 1.65 5 2 1 4
Gandhipuram,
Maruthuvar colony
19 0.71 0.92 1.80 3 3 1 20
Harijan colony &
Kamaraj Nagar
20 0.82 0.41 1.92 4 2 1 22
Georgepuram 21 0.52 0.26 1.52 3 2 0 27
Total 7.73 4.03 13.64 25 15 3 101
Source: Vikramasingapuram Municipality
Plate
4
&
5
:
S
lum Housing - Vikramasingapuram
(d) Indicators, Basic Services Availibity & Gaps
• 94 persons per toilet seat.
• 142 persons per public stand point
• Road density : 1.9kms/sq. km. against 10-15km/sq. km
• Road length/ Capita – 2.2 m/ km against 3-8 m/ km
• Distance of streetlights 154m against 30m
(e) Slum Housing demand and Housing Shortage
Table 5.4: Housing Gap
Year Gap
2011 1425
2021 3618
2031 6079
2041 8839
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 72
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Source: IPE Analysis
Housing of all types (16,625 units) and all tax paying properties (17,400 units) are indicative
of the units demanded in future. An assessment of housing gap is made in Table 5.4.
The non-residential properties for the same period is provided in Table 5.5 and slum
housing estimates demand are given in Table 5.6.
Table 5.5: Demand for Non-Residential Units
Year Gap
2001 753
2011 900
2021 911
2031 1020
2041 1146
Source: IPE analysis
Table 5.6: Demand for Slum Housing
Year Gap
2001 350
2011 1252
2021 1362
2031 1485
2041 1625
Source: IPE analysis
Note: assumed that with measures adopted Slum housing units will not exceed for 5% of all
population.
5.6 Slum Improvement/ Programmes and Issues.
The town is fortunate in not having a large population of urban poor living in slums and the
problem is a manageable one. However, some improvement measures suggested are:
� Improving toilet facilities in the slum and allow for environmentally safe areas,
providing each household with at least one toilet seat, preferably individual toilets
and ascertain if it is feasible on their present locations.
� Several options for low cost sanitation exist, and, it will be encouraging to adopt
a few of those in selected slum pockets.
� Ensure community participation in matters relating to their welfare and where
situations are likely to transform in the near future as a result of improvement efforts.
� Prevent slum formation near water bodies by safeguarding them and proposing
recreational facilities around them.
� While proposing economic growth in the town it will be impertive to stall any
further growth of slums by adequate arrangements in housing and informal jobs in the
town.
� Employment, housing and infrastructure needs of existing slums should be
satisfied within a short time frame.
Slum improvement programmes in the town include:
A review of slum improvement programmes indicate that by improving basic infrastructure
and access to municipal services, there is a significant impact on the quality of life of
slum residents, both poor and non-poor. The Municipality is regularly taking up
gradation of infrastructures works in slum pockets from various programmes.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 73
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Recently the municipality had taken all the slum area into IHSDP programme at the
estimated cost of Rs. 198.73 lakhs.
Swarna Jayanthi Sahari Roghar Yojana and Self Help Group: This program is to provide
employment to the urban poor through provision of self employment. There are about
1684 families living below the poverty line within this Municipal limit. 20 Self Help
Groups have been formed in the Town.
Self Employment Training: This is one of the main components of SJSRY and the
municipality has been conducting training programmes fro the below poverty line
population on options of self employment. This programme is decided by the
selection of beneficiaries who are finalised by the task force on the recommendation
of the community structure and the UPE cell. In this programme the council is not
involved because of the non involvement of the urban local body funds. A sum of Rs.
20,000 /- has been sanctioned as grant to this Municipality. Under this component 9
persons selected for learning Driving and are now under going training.
Wage Employment Programme: An amount of Rs. 47,000 /- has been received for this
scheme. Under this scheme one drainage work is taken up at the 19th ward Kattapulli
Street and the drainage work is completed.
DWCUA: This scheme is distinguished by special incentive extended to urban poor women
who decide to setup self employment ventures as a group as opposed to individual
effort. Groups of poor women shall take up and economic activity suited to their skill
training aptitude and local conditions. Besides generation of income their group shall
strive to empower urban poor women by making them independent as also providing
a facilitation atmosphere for self employment. A sum of Rs. 60,750 /- has been
sanctioned as grant to this Municipality in the above component, the above mentioned
amount has disbursed to 2 self help group.
Thrift and Credit Society: The development of women and children in urban area group sets
itself as a Thrift and Credit society, in addition to this other entrepreneurial activity.
The group is entitled to a lump sum grant of Rs. 27,000 /- has been sanctioned as
grant to this Municipality and it was resolved to sanction to 9 groups.
Community Structure: A sum of Rs. 24,000 /- has been sanctioned as grant to this
Municipality and it was resolved to conduct “Siddha Medical Camp”.
5.7 Strategies and Time Frame
As per National Slum Policy the objective to formulate strategy needs to be;
• To integrate slum settlements and communities residing within them into the urban
areas as a whole by creating awareness amongst the public and in Governance of
underlying principles that guide process of slum development and improvement and
the options that are available for bringing about the integration;
• To strengthen the legal and policy framework to facilitate the process of slum
development and improvement on a sustainable basis and,
• To establish a framework for involving all stakeholders for the efficient and smooth
implementation of policy objectives.
Table 5.7: Strategies and Time Frame
Sl. No. Strategy 2009 2010 2011 2012 2013
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 74
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
1 Better Access Road
2 Storm Water Drains
3 Sewer Network
4 Sanitation facilities
5 Provision of Housing
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 75
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Chapter 6 HERITAGE
Heritage, an aspect neglected so far in urban plans, is now an integral part of city
development. The country with its ancient history is dotted with architectural, cultural
and archological remains that impart pride and are worthy of conservation. Tamil
Nadu, with its 2000 years of continuous cultural history, has a vast repertoire of
magnificent temples, hills, forests and wildlife, beaches, a coastline and typical
settlements abutting it. That these manmade and natural resources need to be
conserved is without a doubt. Thankfully, legislation that helps heritage conservation
to be an integral part of development plans, is now in place. The JNNURM has a
toolkit to ensure that this component has credence in its framework, has made it
doubly sure that its neglect is now passé.
6.1 Heritage Components
These include sites and buildings of archeological, historical, architectural, cultural, religious
and ecological value. The incorporated sites and buildings shall be those listed by the
Archeological Survey of India; State Archeological departments and their acts;
Ministry of Forest and Environment/ supporting state departments under this acts;
listing done under the State Town Planning Acts, and lists approved, supported and
mandated by Trusts city Heritage groups/ registered societies for Heritage/ other
concerned individuals. Since listing is a prerequisite to conservation and perceived as
an obstructive mechanism for realizing a property’s real estate worth, it has a hesitant
acceptance. Heritage properties are also mired in ownership issues/ multiple
tenancies, and are not easily subject to any Heritage based projects. Several Heritage
houses, monuments and sites have been lost as a result of weak intervention in policy,
objectives and serious action.
It is important to map the entire (a) immovable natural heritage sites and (b) immovable
manmade heritage sites.
Plate 6: Evidence of Town Historicity
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 76
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
6.2 Heritage Sites in Vikramasingapuram and Vicinity
Vikramasingapuram is located within an environmentally scenic area with hills, forests,
waterfalls and cascades, ancient temples (associated with mythological events), wild
life and an abundance of nature’s bounty. It is a significant resource waiting to be
sensitively used before it is vandalised by vested interests. A movement to prevent
such an eventually is proposing it as a “Green Town” taking care that all development
follows ecologically sustainable patterns and is confined to its ecological footprint.
Branding a town as “Green” ensures that all buildings will follow the ‘Green Building
Council’ or similar requirements which hava a rating system, be of any scale or type
and are expected to see that the waste outputs of the consumed resouces are
recoverable on the same site if possible, low energy used, solar radiation used for
energy production, building climatically controlled using indigenous methods, city be
kept plastic free, waste segregated, rain water harvested… the listing can be done of
suitable measures. Eco-tourism is one such measure.
The town is expected to successfully use its heritage resource base and enlarge tourism
possibility by sharing opportunities with Ambasamudram for tourism based
employment which will be mutually beneficial. The priceless heritage in the area,
needs recognition in the second order heritage policy and development plans engage
in future on tourism growth including eco-tourism.
Eco tourism is defined as a purposeful travel to natural areas to understand the cultural and
natural history of environment, taking care not to alter the integrity of the eco system,
while producing economic opportunities that make conservation of natural resources
beneficial to local people. In short eco tourism can be conceptualized as ‘any tourism
program that is:
• Nature based
• Ecologically sustainable
• Where education and interpretation is a major component
• Where local populations benefit.
The noteworthy temple and natural heritage, in and near the town (besides the 9 local temples
which have their own customary ritual traditions) are:
(1) Papanasam Temple : 7 centuries old located on River Tambraparni; active
during Chithirai month), devoted to Lord Shiva
and Goddess Ulagambal.
(2) Agasthyar Koil : Associated with Sage Agasthya who is belived to have
Education & Interpretation
Economically beneficial to
locals
Ecologically
Sustainable
Nature Based
ECOTOURISM
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 77
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
bathed in the waterfalls here is very scenic
surroundings.
(3) Kalyana Theertham : Mythological associations with the marriage of Shiva and
Goddess Parvati witnessed by Saga Agasthya.
(4) Sorimuthu Ayyanar
Kovil
: On way to Karyar dam it is under a trust (Zameen
Singampatti Samasthanam) and the festival of
Adi-Amavasai is celebrated here.
(5) Panatheertham : A large waterfall as backdrop to the Karyar Dam is very
attractive spot.
(6)
Mundandurai wild life
sanctuary
: A tiger sanctuary in the afforested hills on way to upper
dam from Papanasam is popular with tourists and
their arrivals upto 2007 were numbered 15,000-
20,000.
(7) Town Waterbodies : 16 tanks, river Tambraparmi and the canal.
(8) The Heritage Wealth
in Tirunuleveli
District
: The heritage wealth at Tirunelveli, Tenkasi,
Ambasamudram Manapad, Coutallam,
Monimuthar, hydel power project paponasam,
Kallidaikurichi, Koonthakulam bird Sanctuary
and several other placess of interest quality for
improvement under a master plan for heritage
areas in Tirunelveli district.
6.3 Heritage Conservation
Temple precincts need to be demarcated under a heritage renewal plan for improvement and
conservation. Besides these noted sites, quite a few water bodies exist within and near
the town. The river is also a prominent water body and several canals in the area help
irrigate paddy fields.
The district has 5 rivers crossing it (Tambraparni, Karuppanathi, Chittar, Servalar,
Manimuthar); 9 Tanks and reservoirs (Manimuthar, Karuppanathi, Ramanathi,
Gatana, Papanasam, Kodama tank, Vijanarayar, Periyakulam, Tenkasi); 14 canals of
varying lengths (N.Koodamelagian, Nathiyni, Kannadian, Kodayan, Palayam,
Tirunelveli, Tenkasi, Vadakkd, Manimuthat, Main Gatana, Arasapattu, Vadakuruvai
pattu, Gatana reservoir, Radhapuram) Some of these fall within the taluka, town or
nearby areas.
These water bodies have to be safeguarded from untreated water being discharges into them,
besides ensuring sustainable sources of water supply highly valued for tourism
growth.
Water bodies have the option to introduce boating and other recreational activities as resorts
etc to activate some of the scenic sites.
Most temples could do with improvement works for pilgrims and visitors and could contain
within their premise, a small information kiosk, historic/records centre, picture
post cards, “know your temples”, a research and documentation centre, a
training school for understanding religious texts, their recording studios,
accompanying musical verses, musical instruments, the making of traditional
prasadams, an interpretation centre for allowing visitors a glimpse into
traditions and culture, building construction manuals of traditional wisdom now
available only to shilpakars and sthapatis etc. A whole new service sector industry
for job creation could build around temples, historic places, natural sites etc including
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 78
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
rural tourism/exotic location & camping sites which are well publicized on web
sites of Tourism department, so that they are marketed well and have drawing
power.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 79
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
6.4 State Interventions
There are several agencies/ institution of the state incharge of heritage aspects, as,
Government Museums; Archeology department; Deptt. of archives and historical
research; Governmental Oriental Manuscript Library; a directorate of art and
culture; regional cultural centres; government music colleges and music schools;
government college of architecture and sculpture; Tamil Nadu archieves; the TN Iyal Isa; Nadaga Mandram; the TM Ovia Nunkalai Kuzhu. In various ways they
are required to keep alive and grow in the realm of fine arts, music, sculpture,
architecture, dance and other forms of cultural expression. The department of
government museums is entrusted the function of restoring old heritage buildings.
There are a number of museum on the anvil, the Rock art gallery, consolidation and
modernization of 8 Archeological sites, conserving monuments and temples etc.
Tirunelveli district and the heritage sites within it should be earmarked for funds and
development activities in highly professional ways to give boost to tourism aiming to
generate jobs and incomes.
The Tourism and Culture department are aware of the economic benefits of Tourism and
consider that domestic tourists show keen interest in beaches, waterfalls, temples,
temple festivals etc. preferring a weekend for the purpose; the national tourist spends
around a week by combining two weekends whilst the foreign tourists are interested
in exploring historical monuments and heritage sites and can spend larger (15-30
days) time with almost a week devoted to Tamil Nadu.
Table 6.1: Tourist Arrivals in Tamil Nadu
YEAR DOMESTIC FOREIGN TOTAL (IN
LAKHS)
2002 246.61 8.05 254.66
2003 270.59 9.02 279.61
2004 300.77 10.58 311.35
2005 323.39 11.79 335.18
2006 392.14 13.35 405.50
Source: Department of Tourism, Tamil Nadu 2007.
Evidently the growth is good but can be improved to cover other less explored areas of Tamil
Nadu, for the various types of tourism that can be on offer, as, Leisure Tourism;
Pilgrim Tourism; Heritage Tourism; Adventure-Cruise-Rural Tourism etc.; Again, in the plans reflected by them there is no allocation of funds for the
Tirunelveli region, though Contallam and Tirunelveli do figure on their list of
Heritage Towns.
6.5 Issues and Concerns
Heritage conservation is a total concept and particularly for this town, it is being seen as a
driving force within a matrix of interconnected drivers explained earlier in the SWOT
analysis. Thus it is intended to have significant impact and would require larger
resource allocations for addressing the physical, social, economic, environmental and
cultural factors integrated into urban development and planning, and thereby release
vast energy while revitalizing the heritage town and its linked issues of developing
traditional skills.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 80
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
• Need to develop natural areas for their scenic worth into eco tourism development
activities.
• Integrate Leisure – Pilgrim- Heritage Tourism with urban development by twinning
the two towns Ambasamudram and Vikramasingapuram.
• Involve community into conservation of heritage areas.
• Involve industry as partners to Tourism growth.
• Special care to safeguard natural water bodies and develop recreational zones.
• Need for introducing one major project in the vicinity as a high end Tourist
destination, (complete with unique resorts, golf course, crafts centre, convention
centre) to trigger mega investment into Tourism sector in the region.
• Making improvements to local temples, sites and areas of heritage importance,
instituting a “Heritage Trail” for increasing visitor exposure to smaller heritage areas
often obscured by the larger temple sites, and also serve to make improvements in the
livelihoods of several poor communities with active support from city, industry and
temple authorities. This will help serve addressing poverty through enhancing local
economic performance.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 81
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Chapter 7 URBAN ENVIRONMENT
7.1 Broad Environmental Concerns
Environment, in its broadest sense, is a sum of the social, physical or chemical factors
surrounding man. Most urban environmental concerns causing harm to the existence
of communities centre around:
• High population densities and the accompanying pressure on resources, structural
condition of towns/ cities, new areas taken up for habitation etc.
• Growth of slums and the associated strains on sanitation, health, housing etc.
• Gap between demand and supply of water and access to safe drinking water.
• Sanitation, especially for underground sewerage facilities and its total absence in
many towns (though schemes such as the National River Conservation Plan are in the
process and have put into operation underground sewerage systems for towns located
along the Cauvery as well as for Tirunlveli Corporation in the district )
• Underground Storm Water drainage.
• Solid Waste Disposal is particularly a concern due to the range of associated
activities, as, collection, transportation and refuse disposal under existing
unsatisfactory conditions. Most Municipalities have been directed to prepare Action
Plans for this activity.
• Industrial pollution causing air, land and water pollution.
• Vehicular emission and congestion, produced by a high density of motor vehicles
per sq. km. which is getting enlarged with each passing year and releasing toxic air
pollutants into the atmosphere.
7.2 Situation in Vikramasingapuram
Vikramsigpuram does not have any concentration of industries. The nearby Modern Coats has
modernized and has little impact on the town. Absence of industries, presence of
water bodies and open green areas adds positively to the towns environmental quality.
Of some concern is the poorly managed garbage disposal, presence of slums, low
lying areas and places where growing ground water extraction.
Control of pollution is resorted to by categorising industries as Red, Orange or Green
depending on their pollution markers. No industry can be set up within 1 km from the
embankment of rivers, streams, dams etc.
7.2.1 Air Quality
Table 7.1: Ambient Air Quality
PARAMETERS PERMISSIBLE EXITING
SPM 100 622
SOZ 30 20
NOX 30 13
RSPM 75 Not available
SPM 100 622
Source: Vikramasingapuram Municipality 2007
There is no air quality monitoring stations. But suspension due to earthen roads is why SPM
level is high.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 82
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
7.2.2 Noise
Table 7.2 Norms for Noise Pollution
AREA CATEGORY CODE DAY TIME NIGHT TIME
Industries 75 70
Commercial 65 55
Residential 55 45
Silence Zone 50 40
Source: CPCB Norms
7.2.3 Water Quality
Table 7.3 Water Quality in Town
PARAMETERS PERMISSIBLE EXISTING STATUS IN
TOWN
PH 6.5-8.5 7.4
Nitrates/ Nitrites 4.5 1.27
Dissolved Oxygen(DO) 8(Fresh water) 5.27
Chemical Oxygen Demand
(COD)
300-600 7
Source: Vikramasingapuram Municipality 2007
There is low DO; oxygen deficiency can be attributed to organic matter being dumped into
the canal from where surface water is drawn.
7.2.4 Flora and Fauna
The Kalakkadu and Mundanathari Sanctuaries contain wild life in their 233 sq. km. area
reserve including foothills of the Western Ghats and its adjoining areas.
The Flora constitutes forests of tropical wet evergreen to tropical dry deciduous and thorny
forests on the lower hills.
Wild life consists of species of Lion tailed macaue, Nilgiri thar, Sambars, sloth bear, boars,
elephants, tigers, flying squirrel, panther, wild dog, and pangolin eat, besides the
birds and reptiles.
The Mundanthari Sanctuary, 567 sq. km, does not have elephants and the gaur, and its forest
also consists of dry deciduous to tropical wet evergreen, with some patches of reeds.
7.2.5 Disaster Proneness
Natural disasters take a toll on life, property, infrastructure, and disruptance to social and
economic well being. Vikramasingapuram may face droughts, floods or earthquake
for which guidelines issued may be referred.
Floods need to be averted by specifically improving the storm water drainage system as well
as improving low lying areas in the town.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 83
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Suggestion:
Environment Related:
• Constant monitoring of environment performance.
• Creating Environmental Upgrading Grants through creation of environmental
trusts.
• Enforcing peak hour traffic constraint
• Fostering improvements in Agriculture, horticulture, fisheries while minimizing
environmental conflicts.
• Exercising control over mineral developments.
• Undertaking surveys of degraded landscapes and potential protected areas.
• Ensuring there is no nuisance of smell and noise.
• Protecting water catchments areas.
• Designating sites for improved management of waste generation and disposal.
• Inventorising disused quarries, establishing a Reclamation Fund (using taxes on
mineral production).
• Providing incentives for relocating polluting industries.
• Incentivising low energy, low water use practices, green buildings, plus use of solar
cookers, solar panels etc.
• Effectively managing solid waste by inbuilding capacities of local bodies.
• Formulating a set of “good practices guidelines”
Conservation Related:
• Designating Urban Conservation areas where policies for environmental upgrading
are applied.
• Upgrading Tourism areas (country parks, network of picnic areas, Heritage trails)
• Designating rural conservation areas to cover non urban areas
• Ensuring new developments permitted in rural areas enhances areas of scenic value.
• Managing wild life sanctuaries/ designating Heritage sites.
• Encouraging tree plantation @ 1 tree per unit of population in the town, and also
Inventorising them.
• Ensuring water reservoirs are underground. If not, ensuring they blend with the
landscape.
• Developing and implementing a policy for wildlife protection.
• Enforce soil conservation measures.
• Improving access to disabled on footpath, buildings, facilities and even transport.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 84
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Chapter 8 URBAN GOVERNANCE AND URBAN REFORMS
The institution of Municipal governance has been in existence in Tamil Nadu since long
(District Municipalities Act. 1886). The Twelfth Schedule (73rd
and 74th Amendment)
Act. 1992 has restated the relation of the state to the ULB in matters of their
executive functions, taxation arrangements, revenue sharing with state, and
representation of women and weaker section of society.
8.1 Organisational Structure
Post 1992 and the amendment in the Twelfth Schedule (73rd
and 74th Amendment) Act,
changes were brought in the Municipal functioning to clarify relation of state to ULB
for the functions of taxation arrangement and revenue sharing as well as affording
adequate representation of weaker section in power sharing. A host of new
arrangements ensured that the ULB be professionally equipped to handle
development and governance issues, and a listing of the 18 functions that were
required to be operated by them.
Vikramasingapuram Municipality was upgraded in 2004 as Grade-III Municipality from a
selection grade Town Panchayat regulated by the TN District Municipal Act,
1920. The town has 21 wards with adequate representation of women and SC/ST
persons.
The Act specifies three types of Municipalities
(a) Nagar and Town Panchayat,
(b) Municipal Councils for smaller urban areas and
(c) Municipal Corporations for larger urban areas.
The set up of ULB comprises of the Administrative Wing and the Elected Wing, the latter
consisting of elected councillors from different wards of the city, and headed by a
Chairman. The Executive Wing is headed by the Executive Officer helps in the
functioning of the ULB by supporting the elected wing in the decision making
process.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 85
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Fig. 8.1: Exisiting Organisational Structure
Source: Vikramasingapuram Municipality 2007
Against the total of 77 posts, 62 are in place. Most of the posts are occupied, barring 15 lower
level posts. The proportionate divisions of higher to lower jobs are as
Manager : 1
Assistance to Top job : 8
Lower skilled jobs : 28
Lowest unskilled jobs : 40
Though not very vertical in structure, the lower level jobs tend towards a larger base due to
several manually performed operations.
Chairman ULB Executive Officer
Vice Chairman
Accounts &
Revenue
Manager, Jr. Asst., Office
Assistants, Watchman
Asst. Head Clerks
Electrician
Metre Reader
Health
Department
Sanitary Inspectors
Water Supply
Department
21 Councillors
Sanitary workers
Conservancy staff
Pump Fitter
Fitters
HP Operators
Pipeline Inspectors
Cleaners, Watchman
General
Administration,
Bill collectors
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 86
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
8.2 Functional Wings
(a) Elected Wing
The elected wing of the Municipality consists of 21 councilors from each of the 21 wards one
of them elected as Chairman. Councilors are responsible for raising development
issues and concerns of their respective wards. The elected wing provides an overall
direction to the Municipality in performing its various functions, through a set of
committees constituted for different purposes. There is no wards committee in the
local body.
(b) Executive Wing
The executive/administrative wing is responsible for day to day operations of the
Municipality, and is headed by the executive officer. The Executive Officer is the
administrative head of the Municipality and is supported mainly by three main
departments which include General Administration, Health and Engineering. The
usual roles and responsibilities of the various departments are as mentioned below:
Table 8.1: Roles and Responsibilities of Various Departments
S. DEPARTMENT RESPONSIBILITIES
1 General Administration,
Revenue and Accounts
This includes responsibility of taxation, accounts and
records. It deals with bill raising, collection
of property tax, deals with accounts, debit
etc. Conserves past records of properties,
staff etc.
2 Water Supply Department Engineering works for water supply, also street lights,
roads, drains etc.
3 Health and Sanitation It deals in implementation of government sponsored
health programmes, Solid Waste
Management, Street sweeping and clearing of
drains etc.
Source: IPE Assessment
8.3 Line Agencies
Several line agencies support ULB functions, these are:
(1) TWAD Board Creating water and sewerage infrastructure, handing over completed
projects to ULB for O&M purposes.
(2) TCPD Town Planning Functions. Preparing Master/ Development Plans.
Implementation by ULBs. Process to be duly revised due to
CDP preparation.
(3) PWD Roads and
Highway
s
State Highways, District and Other main metalled roads. Municipal
roads with ULBs.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 87
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
(4) TNPCB Environmental protection and pollution control functions.
Enforcement of rules.
(5) TNSCB Improvement schemes for notified slums for loans from HUDCO and
GOI, GoTN. Process revised with JnNURM. UIDSSMT
promoted IHSDP and BSUP
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 88
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
8.4 Reforms for ULB under UIDSSMT
Some mandatory reforms are foreseen to enable efficient ULB management and delivering
reliable services, which entails restructuring reorganization so that to routine /other
functions are performed in a streamlined way, speedily and with transparency. The
mandated reforms are:
• Adopting Modern Accounting procedures (double entry accrual based)
• Introducing e-governance with IT applications of GIS and MIS for services
provided by the ULB
• Property tax reforms, using GIS, and improving collection efficiency to 85
percent in next 7 years.
• Levying user charges to recover O & M costs fully within next 7 years.
• Introducing budgetary provisions for the urban poor.
• Providing housing, basic services, secure tenure and other social services by the
Government to the urban poor.
The optional reforms revolve around:
• Speeding and revising approval process for building activity.
• Simplifying process for conversion of land to Urban Land uses.
• Introducing property tax certification.
• Earmarking 25 percent land to EWS/LIG and arranging cross subsidy for their living.
• Introduce water harvesting.
• Use recycled water.
• Reduce administrative costs by cost cutting measures on non essential staff
• Encourage PPP.
8.5 Recommended Organisational Structure
Overseeing the list of functions, it is observed that the functions relating to urban planning,
land use, regulating the construction of building, are not yet being performed by the
municipal authority. Very little is being done by the municipalities in relation to basic
service to urban poor.
The present organizational structure of municipal authority is designed only to meet the
present needs and is not adequate to perform all the functions envisaged in the 12th
Schedule of the Constitution.
The present organizational structure represents a lean administrative staff where a further
possibility of outsourcing activities to the private sector can be envisaged in the solid
waste management side and thereby cut costs in a high cost activity if performed
internally.
Reforms will be needed in governance by
• Clearing identifying the tasks and sub tasks that Vikramasingapuram is required to
perform
• An information module which is accessible electronically and otherwise to the
citizens of the town as an interface between them and the Municipality
• It is prudent to agglomerate ULBs for infrastructure requirements water, sewerage,
solid waste management, transportation and other infrastructure so as to create scale
and facilitate development in a holistic way. There should be more external oriented
rather than inward based.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 89
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
• There should be forums for continuing dialogue between people and councilors on a
regular periodic basis, preferably as calendar events which should be well publicized.
The Municipality needs to undertake more functions under the 74th CAA for which the
organizational structure must modify and accommodate. A suggested structure is
provided in Table 8.2
• The structure envisages 6 functional heads which are coded as
Code 1: GENERAL ADMINISTRATION
Code 2: ENGINEERING & PHYSICAL INFRASTRUCTURE
Code 3: SOCIAL INFRASTRUCTURE
Code 4: POVERTY SLUMS & HOUSING
Code 5: URBAN PLANNING, DESING AND HERITAGE
Code 6: BUDGET AND ACCOUNTS
• These functional heads are further split into SEGMENTED FUNCTIONAL CODES
as
Eg.: 1A & 1B; 2A to 2 F; 3A to 3B; 4A to 4 F; 5A to 5B; 6A to 6C. (For details see Table
8.2)
• Under each Segmented functional code are the delivery TASKS. (For details see
Table 8.2)
Table 8.2: Proposed Organization Structure for Vikramsingapuram
CODE FUNCTIONAL HEAD SUB
C
O
DE
WINGS/ TASKS
1A General Administration matters
1A.1 Establishment matters
1A.2 Personal policy, Career growth, Training
1A.3
Appointments, Promotions, vigilance
matters
1B IT
1B.1 IT Networking
1B.2 IT support, IT training
1B.3 Website management
1B.4 Trouble shooting, general maintenance
1B.5 Archival,
1 Central Administration
1B.6 IT upgrade
2A Water Supply
2A.1 Interal network design
2A.2 O&M Asset management
2A.3 Water testing
2A.4 Complaints redressal
2A.5 Repair and renewal
2A.6 Any other
2B Sewerage
2B.1 Interal network design
2B.2 O&M Asset management
2B.3 Waste water treatment & disposal
2B.4 Waste water recycling
2B.5 Testing
2 Engineering
2B.6 Regulating discharge
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 90
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
CODE FUNCTIONAL HEAD SUB
C
O
DE
WINGS/ TASKS
2B.7 Composting / gasplant / any other
2C Roads and Drains
2C.1 Design and civil works for roads and drains
2C.2 Storm water disposal
2C.3 Maintenance of roads / drains
2C.4 Road furniture
2C.5
Road junctions, sidewalks, markings and
signage
2C.6 Bus bays
2C.7 Traffic related trouble shooting
2C.8 Parking lots, selecting sites
2D Street lighting
2D.1 Procurement
2D.2 Design & laying of UG cables
2D.3 O&M Asset management
2D.4 Sub-station / others
2E Parks / playgrounds
2E.1 TOI lots
2E.2 Parks and plagrounds
2E.3 Recreational sites
2E.4
Horticulture, water bodies, water
catchment area protection
2E.5 Roadside plantation and avenues
2E.6 Urban vegetable / fruit gardens
2E.7 Forest protection
2E.8 Wet area conservation
2E.9 Quarry sites improvement / renewal
2E.10 Degraded areas improvement
2E.11 Nurseries, fisheries, zoos, agro area, other
2E.12 Ecological safeguards
2F Solid Waste Management
2F.1 Primary collecation
2F.2 Storage and collection
2F.3 Disposal site
2F.4
Engineered landfill / O&M management
construction
2F.5 Vehicle asset management
2F.6
Recycling, composting, segregating, on site
recycling, on site composting,
community group
ogranisation SHGS, waste
involvement, NGOs
2F.7 Any other
3A Education 3 Social Infrastructure
3A.1
Monitoring / site selection for primary,
secondary,
Higher secondary
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 91
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
CODE FUNCTIONAL HEAD SUB
C
O
DE
WINGS/ TASKS
3A.2 Colleges / Institutions
3A.3 Any other
3B Health
3B.1
Monitoring / site selection for establishing
Hospitals/ Clinics /Nursing homes
3B.2 Ensuring Hazard free environments
3B.3 Any other
4A In situ slum improvement
4B Slum relocating / replanning
4C Poor Services Provision
4D Livelihoods and Community,
4E
Poverty assessment, Program, design,
executing
monitoring, evaluation
4 Poverty, Slums and
Housing
4F General Planning
5A
Urban plan making, Environmental
considerations
5A.1
Plan monitoring, regulation, encrochment
prevention
5A.2
Ward area plans, ward area need
assessment ,
monitoring
5B Building and Design
5B.1 Building rules, structural safety, Green
building,
guidelines, architectural elements
and componets,
vernacular architecture guidelines,
environment
guidelines
5B.2
Plan enforcements, Building law
enforcement
5B.3 Conservation guidelines and enforcement
5 Urban Planning Design
and Heritage
5B.4 Heritage section,
Heritage improvement
Heritage conservation and
regeneration
Heritage based promotional
activities
Heritage-tourism promotional
activities
Marketing section
6A Taxation and Revenue ralated activities
6B Finance and accounts related activities
6 Budget and Accounts
6C Any other
8.6
8.7 Suggestions
• Speeding up e-governance in the taluk and improving the tax collection system.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 92
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
• Capacity building to the ULB staff on performance efficiency and benchmarking it
with use of performance indicators.
• It is feasible that ward level plans be prepared for effective community participation.
• Local governance strengthening is important, especially having a separate tax
domain.
• Community participation as an ongoing process, should be facilitated by the ULB as
a periodic calendar event, with a monitoring cell in place to ensure that participation
results in community supported actions (It is not necessary to always have laws to tell
people how to do what). As city scales enlarge, participation may be segmented to go
upto neighborhood level.
• Rent control Laws, if any, have to be reviewed.
• Water supply, user charges, leaking systems, billing systems, illegal connections,
discretionary supply are matters where reforms have to be ensured, so that O & M
costs are recoverable.
• Documenting and disclosing published information by the ULB on decisions taken,
including financial statements, projects details and other information of common
interest to the citizens, will ensure the accountability of ULB.
• Most municipalities have proportionately high wage bills and pension payouts; the
reforms underway suggest that 35% of revenue expenditure only should go to salary
bills. This entails cost cutting on wages for unnecessary personnel and reducing the
number of employees.
• New Municipal Accounting systems have already been suggested elsewhere.
• Making room for PPP signifies sharing of risks, opportunities, responsibilities and
rewards and paves the way for a smoother and more satisfactory development culture.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 93
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Chapter 9 MUNICIPAL FINANCE 9.1 Introduction
Vikramasingapuram municipality used to maintain accounts on a single entry cash basis till
the financial year 2001-02. The ULB was upgraded from Town Panchayat to Grade
III in the financial year 2004. In the financial year 2002-03 & 2003-04, the ULB
maintained accounts as per Town Panchayat Accounting Manual. i.e. Double entry
accrual based accounting (non-fund based).
The ULB is supposed to maintain Fund Based double entry accrual accounting as per Tamil
Nadu Municipal Accounting Manual from FY 2004-05. However, this switchover has
not been initiated. Under the present system the ULB prepares Income & Expenditure
and Balance sheet at the financial year end. The account of this ULB has been audited
up to FY 2006-07.
9.2 Revenue Account
The revenue account comprises of recurring items of receipts (taxes, fees, grants etc.) and
payment account essentially transactions related to the ULBs operations. The table
below summarizes the status of the ULBs revenue account.
Table 9.1: Revenue Account (in lakhs)
FY03 FY04 FY05 FY06
Revenue Income 134.57 157.67 184.93 222.50
Revenue Expenditure 150.56 185.68 219.16 235.43
Surplus/Deficit -15.98 -28.01 -34.23 -12.93
Source: Vikramasingapuram Municipality
Fig 9.1 Trends in Revenue Income and Expenditure
The CAGR for the Revenue Income is 18.25 percent while the CAGR for Revenue
Expenditure 16.07 percent. The revenue income and expenditure have shown an
increasing trend. The Municipality has shown a deficit during the years taken into
consideration, which kept on fluctuating from 2003 to 2006, however was lowest in
2005.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 94
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
9.2.1 Revenue Receipts / Income
Receipts under this head include taxes, fees, grants, income from properties and special
services.
i. Taxes - own sources – This is includes property tax and professional tax and other
taxes collected by the Municipality. In 2006, the tax receipts accounted for Rs.25.9
Lakhs.
ii. Taxes - Assigned Revenue - Taxes collected by other agencies include entertainment
tax, duty on transfer of property, taxes on carts and animals etc this accounted for Rs.
10.21 lakhs in 2006.
iii. Non-tax Revenue - This head includes Income from Fees, Properties, Special
services & Miscellaneous. This head amounts to Rs.63.56lakhs in the year 2006.
iv. Grants & Contributions – The ULB could attract the Grants only from the Financial
Year 2006. There was no grants and contributions in years under considerations.
Table 9.2: Revenue Receipts, Vikramasingapuram (Rs. In Lakhs)
S. NO. PARTICULAR FY03 FY04 FY05 FY06
Rs. in lakhs
1 Property Tax 15.33 15.96 16.17 16.84
2 Other Taxes 5.98 6.97 7.97 9.06
3 Service Charges & Fees 43.52 54.38 99.90 63.56
4 Sale & Hire Charges 0.15 0.00 0.15 0.45
5 Other Income 8.10 7.19 5.85 7.36
6 Assigned Revenue 17.78 12.94 12.93 10.21
7 Devolution Fund 43.72 60.23 41.95 115.03
8 Grants & Contributions 0.00 0.00 0.00 0.00
Total 134.57 157.67 184.93 222.50
Source: Vikramasingapuram Municipality
Note: The excess expenditure over income has not been considered
Table 9.3 Revenue Receipts as Percentages of Total Revenue Receipts (value in %)
S. NO. PARTICULARS FY03 FY04 FY05 FY06
1 Property Tax 11.39 10.12 8.74 7.57
2 Other Taxes 4.45 4.42 4.31 4.07
3 Service Charges & Fees 32.34 34.49 54.02 28.56
4 Sale & Hire Charges 0.11 0.00 0.08 0.20
5 Other Income 6.02 4.56 3.16 3.31
6 Assigned Revenue 13.21 8.21 6.99 4.59
7 Devolution Fund 32.49 38.20 22.69 51.70
8 Grants & Contributions 0.00 0.00 0.00 0.00
Total 100.00 100.00 100.00 100.00
Source: Vikramasingapuram Municipality
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 95
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Fig 9.2 Source wise Revenue Income (%)
• The amount under most of the heads is growing however their share to the
revenue receipts in the respective years is varying. Revenue receipts have increased
from Rs.134.57 lakhs in 2002-03 to Rs.222.50 lakhs in 2005-06. It has shown
increasing growth trend over past 4 years.
• Property Tax is showing a varying trend over the years, while the other taxes
have shown a promising upward trend.
• The devolution funds occupy a significant share of the revenue income with the
highest in FY06.
Fig 9.3 Average Share of Revenue Income (%)
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 96
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
The overall average of the major sources of income is as presented above. Devolution Funds
are the largest source of income, with an average share of 37 percent to total revenue
and it is followed by service charges and fees which is around 32 percent.
9.2.2 Revenue Expenditure
Vikramasingapuram municipality uses the resources for general administration, operation and
maintenance of services and public works. Revenue expenditure during FY03 was Rs.
150.56 lakhs and in FY07 it accounts to Rs. 235.43 lakhs.
i. Personnel Cost - This constitutes one of the major components of expenditure. It has
increased from Rs. 60.28 lakhs in 2002-03 to Rs. 7.24 in 2005-05.
ii. Operating Expenses - This includes the O&M of core services and it accounts to Rs
54.20 lakhs in 2005-06. The O & M expense has shown an oscillating trend over the
years.
iii. Finance Expenses - This is an important component and amounts to Rs. 32.06 lakhs
money in 2006-07.
Table 9.4: Break – Up of Revenue Expenditure (Rs. In Lakhs)
S. NO. PARTICULARS FY03 FY04 FY05 FY06
1 Personnel Cost 60.28 61.74 70.44 77.24
2 Operating Expenses 29.38 59.45 56.44 54.20
3 Programme Expenses 0.01 0.00 0.28 0.39
4 Administration expenses 28.15 11.15 14.78 21.62
5 Finance expenses 2.40 5.10 28.86 32.06
6 Depreciation 30.35 48.25 48.37 49.91
Total 150.56 185.68 219.16 235.43
Source: Vikramasingapuram Municipality
Table 9.5 Revenue Expenditure as Percentage of Total Revenue Expenses (value in %)
S. NO. PARTICULARS FY03 FY04 FY05 FY06
1 Personnel Cost 40.04 33.25 32.14 32.81
2 Operating Expenses 19.51 32.02 25.75 23.02
3 Programme Expenses 0.00 0.00 0.13 0.17
4 Administration expenses 18.70 6.00 6.74 9.18
5 Finance expenses 1.59 2.74 13.17 13.62
6 Depreciation 20.16 25.98 22.07 21.20
Total 100.00 100.00 100.00 100.00
Source: Vikramasingapuram Municipality
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 97
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Fig 9.4 Component wise share of Revenue Expenditure (%)
As seen from the graph above, personnel cost shares a significant portion of the revenue
expenditure, followed by depreciation and operating expenses.
Fig 9.5: Average Share of Revenue Expenses (%)
As seen from the graph, on the expenditure side the ULB spends almost 34.56 percent on
personnel costs and a significant 22.35 percent on depreciation, followed by operating
expenses with about 25.08 percent.
9.2.3 Trend of Income & Expenditure – Vikramasingapuram Municipality
Income increased at an average of 18.80% over past few years on the other hand expenses
have increased at an average of 16.26% over the years. All the revenue income heads
shows a positive trend except assigned revenue. Income & Expenditure trend of the
municipality is shown in the following table and figure.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 98
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Table 9.6: Growth Rate in Revenue Income and Expenditure (%)
S. NO. INCOME FY04 FY05 FY06 AVERAGE
1 Property Tax 4.15 1.30 4.13 2.72
2 Other Taxes 16.45 14.44 13.68 14.06
3 Service Charges & Fees 24.95 83.70 -36.38 23.66
4 Sale & Hire Charges -100.00 188.52
5 Other Income -11.23 -18.59 25.72 3.56
6 Assigned Revenue -27.20 -0.07 -21.04 -10.55
7 Devolution Fund 37.77 -30.35 174.20 71.93
8 Grants & Contributions
Total 17.16 17.29 20.32 18.80
S. No. Expenditure FY04 FY05 FY06 Average
1 Personnel Cost 2.42 14.09 9.66 8.73
2 Operating Expenses 102.36 -5.06 -3.98 31.11
3 Programme Expenses -100.00 #DIV/0! 41.34 #DIV/0!
4 Administration expenses -60.39 32.55 46.31 6.16
5 Finance expenses 112.40 466.22 11.12 196.58
6 Depreciation 58.97 0.26 3.19 20.81
Total 23.33 18.03 7.43 16.26
Sorce: Vikramasingapuram Municipality
Fig 9.6 Growth Rate in Revenue Income and Expenditure
9.3 Demand Collection Balance Scenario
It is seen from the Income and Expenditure statement that the one of the major source of
income for the municipality is through the taxes. The DCB of major sources of
incomes are from:
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 99
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
(i) Property Taxes (ii) Professional Taxes and (iii) Water Taxes.
9.3.1 DCB for Property Tax
In FY06, the total demand for property tax (including arrears and current) stood at Rs.25.12
lakhs of which Rs.16.35lakhs has been collected. The overall collection performance
was 65% and, on an average around 68% of property tax has been collected yearly.
Coming to arrears and current demand collection, 11% and 89% has been collected
on an average in last five years. The arrears and current demand in 2005-06 was
Rs.8.28lakhs and Rs.16.84 lakhs respectively, out of which Rs. 2.19lakhs and
Rs.16.35lakhs has been collected.
Table 9.7. Demand Collection Balance for Property Tax (Rs. In Lakhs)
S. NO. PARTICULARS 2002-03 2003-04 2004-05 2005-06
Rs. In lakhs
A. Demand
1. Arrears 4.76 5.37 6.04 8.28
2. Current 15.30 15.60 16.17 16.84
3. Total 20.06 20.97 22.21 25.12
B. Collection
1. Arrears 0.22 0.11 0.62 2.19
2. Current 14.30 14.73 13.31 14.16
3. Total 14.52 14.85 13.93 16.35
D. Collection Analysis
Arrears (%) 5% 2% 10% 26%
Current (%) 93% 94% 82% 84%
Total (%) 72% 71% 63% 65%
Source: Vikramasingapuram Municipality
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 100
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Fig 9.7 Collection Efficiency for Property Tax (%)
9.3.2 DCB for Profession Tax
Table 9.8. DCB for Professional Tax of (Rs. in Lakhs)
S. NO. PARTICULARS 2002-03 2003-04 2004-05 2005-06
Rs. In lakhs
A. Demand
1. Arrears 0.28 0.14 0.03 0.00
2. Current 5.98 6.97 7.97 9.06
3. Total 6.26 7.11 8.01 9.06
B. Collection
1. Arrears 0.28 0.19 0.03 0.00
2. Current 5.84 6.94 7.97 9.06
3. Total 6.12 7.12 8.01 9.06
C. Collection Analysis
1. Arrears (%) 100% 136% 100%
2. Current (%) 98% 100% 100% 100%
Total 98% 100% 100% 100%
Source: Vikramasingapuram Municipality
The arrear demand in 2005-06 was Rs.0.00 lakhs, while the current demand was Rs.9.06
lakhs and the same has been collected indicating 100% efficiency. On an average, the
overall collection performance including both arrears and current demand is 100%.
Fig 9.8: Collection Efficiency for Professional Tax (%)
9.3.3 DCB for Water Charges
The total demand in 2005-06 was Rs.101.00 lakhs and only Rs.34.46 lakhs have been
collected. The collection performance was at 43% and 26% for arrears and current
demand respectively.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 101
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Table 9.9. DCB of Water Charges (Rs in lakhs)
WATER CHARGES 2002-03 2003-04 2004-05 2005-06
A. Demand
1. Arrears 0.00 0.00 22.37 48.50
2. Current 30.59 46.35 46.80 52.50
3. Total 30.60 46.36 69.17 101.00
B. Collection
1. Arrears 0.00 0.00 1.75 20.68
2. Current 30.59 23.99 18.91 13.78
3. Total 30.59 23.99 20.66 34.46
C. Collection Analysis
1. Arrears (%) 0% 0% 8% 43%
2. Current (%) 100% 52% 40% 26%
100% 52% 30% 34%
Source: Vikramasingapuram Municipality
Fig 9.9 Collection Efficiency for Water Charges (%)
9.4 Ratio Analysis (OR)
Ratio of revenue expenditure to revenue income has been mentioned below.
FY 03 –1.12
FY 04 – 1.18
FY 05 – 1.19
FY 06 – 1.06
The OR for all financial year, under consideration, was more than 1, indicating instability in
the efficiency of revenue management, or, a high dependency on state devolved funds
for revenue income.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 102
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Chapter 10 Development of Perspective and Vision of the city
10.1 Spatial Perspective For Vikramasingapuram 2041
A comprehensive view of Vikramasingapuram was derived and several fronts explored for
preparing a draft vision for the ULB. These included a SWOT analysis, stakeholders
meeting, interviewing citizens, officials and key stakeholders, and consolidating their
views, as well as a detailed analytical assessment of the state and district potential to
contribute to the USB’s growth. On the basis of these datasets, a spatial perspective
plan for Vikramasingapuram 2041 was prepared (see Map 9) The plan, indicative of
the new focal developments and its sustaining infrastructure, on approval, with or
without adjustments, would help generate a City Development Plan (CDP) along with
a five year project profile in a draft suggestive form, as incorporated later in this
chapter.
To mandate the CDP into an implementable document would need preparation of schemes
and ward plans. for actualizing listed projects and covering deficient development in
the city. This would require fast tracking approval by the ULB/ State for a healthy
development process.
10.2 Sector Specific Objectives and Projects
(i) A Spatial Growth
The neighbouring ULBs in close proximity to each other and almost contiguous formed the
basis to validate road infrastructure and bypass construction so that the economy is
provided an impetus in the form of planned development hubs in peri-urban sites of
2-3 contiguous ULBs. These are expected to be on ecological principles respecting
the existing environmental profiles (slopes/ topography/ catchments/ forest data) as
well as regulations determined for GREEN TOWNS wherein the new development
zones planned integrate with the existing landscapes of hills and foothills.
This co-sharing is extended to also siting regional landfills for SWM, demarcating water
supply zones regionally as well as road infrastructure which will help economic
growth.
(ii) Strategies
• Use tourism for improving incomes in the service sector by promoting TEMPLE
HERITAGE AND OTHER NATURAL AREAS.
• Use development modes and road bypass to site tourist infrastructure.
• Develop local initiatives and partnerships for tourism projects for their marketing,
transportation, accommodation and services.
• Campaign for GREEN PRACTICES.
• Develop local and regional skills, talent and entrepreneurship.
• Develop INSTITUTIONAL ZONES integrated within ECOPARKS and GREEN
SETTINGS
• Make selective use of forests and mineral resources for value added products which
are produced in MINI-ENTERPRISE ZONES. (In small village like communities
which have integrated housing – production – warehousing and commerce –
recreation – cohesive neighbourhoods) within natural surroundings.
• Re-densify existing town with infill development also improve physical – social
infrastructure and create aesthetic environment for enhancing Quality of Life (QOL).
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 103
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
(iii) Short Term Projects (2008 - 2013)
• Initiate site selection, conduct feasibility studies for new development hubs in the
peri-urban zones.
• Develop Municipal Park and tree plantation campaign.
• Develop Agasthyar Fall as attractive picnic spots.
• Recreational areas in townships near all water bodies integrating them with green
corridors.
• Develop mini-zoo.
• Line the canals.
• Improve roads – drains – footpaths – road markings – signage – road furniture.
• Set-up information centres for registering skilled persons, SHGs, informal sector
groups. Use best practices of ‘Reddy’s LABS’ for organising informal sector
activities.
• Fill gaps in community toilets, public conveniences.
• Plan and execute bus stand project (with 30 year perspective for traffic growth).
• Substitute all street lights with low energy luminaries; cover gaps in illumination.
• Improve garbage removal by composting – segregation – exploring recycling
possibilities.
• Build community halls at appropriate locations.
• Improve temple surroundings
• Establish Heritage Resource Centres.
• Establish Tourism Information & Promotion Centre
• Establish task force and design teams for Master plan for Conservation.
• Establish Ecological Resource & Eco-Tourism Centre.
• Create website for religious/ ethnic/ nature/ eco-tourism
• Prepare ward plans for re-densifying residential areas.
• Establishing/ Outsourcing GIS Mapping Centre.
10.3 Prioritisation of Projects
Projects have been prioritized to ensure that;
• They represent projects across sectors,
• Are short term, implementable in five years
• Preferably executed in public private partnership mode,
• Okayed by stakeholders,
• Have innovative elements for achieving ‘newness’/ demonstration effect.
On the basis of the detailed discussion with the Stakeholders of the town and analysis of the
existing situation prioritized project list for the ULB was prepared, as below:
1. Urban Roads
2. Street Ligths
3. Slum Improvement-Urban Poor with Social infrastructure like marriage Halll/
Community Hall
4. Heritage and Conservation
5. Sanitary Complex
6. E. Gov and Other Projects
The wish list which was presented by the ULB was very limited and was not in compliance
with the sustainability of the town. Therefore a comprehensive proposal was
developed by the consultant in conformity with the standards set in UIDSSMT
scheme and CPHEEO manual which is presented in the chapter 11.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 104
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
10.4 Infrastructure Projects
10.4.1 Traffic and Transportation
(i) Objective:
To achieve efficient transport network and improve traffic management in city and its
peri urban areas.
(ii) Short Term Strategy:
- Improve access to core area through core city improvement;
- Improve access to peri-urban areas by introducing land use conversions, developing
multi functional Nuclei, introduce by pass to link regional economy and facilitate
local economy within new development hubs, avoid haphazard sprawl by integrating
land use and transport.
- Remove all road encroachments on internal roads as a pre requisite to road
improvement.
- Organize parking lots with demarcated pitching spaces and ensuring definite no. of
car spaces.
- Provide street lights, signage, road markings on roads and intersections.
- Widen roads in core area to house entry level with demarcated foot paths on both
sides.
- Pave all roads in slum clusters; provide drains to engineering designs.
- Fix road levels permanently and adopt re-carpeting in a way as not to change levels
affecting drainage and other parameters.
- Traffic regulation and scientific guidelines should be adopted from IRC standards.
iii) Long Term Strategy
- A proper Transport Development Plan be prepared.
- A registration base for vehicle be prepared for future demand management.
- Green policies be implemented to permit cycles/ rickshaw/ pedestrians to operate in
safe road environments.
- Drains be well designed for peak summer flow as well as monsoon discharge, along
with effective monitoring of storm water drainage system.
- For lining of storm water drains, use of halved coconut shells / coconut husk and
other porous environment friendly materials may be used in view of coconut shell
availability in large volumes in the region.
- Policies and strategies be prepared as Special provisions for enhancing economic
opportunities, for developing Institutional zones, Tourism Nodes, Eco-parks, and
Multi-functional Mini Enterprise Zones and their Integration with Transport
Development Plan.
- Improve all main arteries, Bus stands, develop a new Bus stand off the By-pass which
will form part of Transport Development Plan, and, several Bus shelters at suitable
locations.
(iv) PPP
- Overhead signage on major roads and highways to be erected to international
standards.
- All residential areas be provided with direction/ indication boards along with maps
well designed and executed by reputed art agencies.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 105
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
- All parks, public buildings, offices be similarly provided with name boards etc as
above.
- Advertisement rights to private agencies may be given for the same for a specified
period (say 3 years).
(v) Identified Projects
- Development of Traffic Management Plan.
- Development footpaths on all main roads
- Provide zebra crossings and other markings
- Provide proper illumination and drainage
- Improve road junctions/ intersections
- Modernize and improve bus stand circulation – parking areas – public conveniences –
shops –
- Provide parking in heritage areas; pedestrianize; use bollards and signage’s.
- Provide modern petrol filling stations
- Provide slum areas paving
Table 10.1: Transportation Projects : Prioritization and Time Frame
S.No. Identified Projects 2009 2010 2011 2012 2013
1 Traffic Management Plan
2
Developing street junctions /
Sidewalks / Landscape /
Road Markings
3 Developing parking lots
4
Siting/ Constructing of new Bus
stand
5 Junction / Intersection development
6
Providing Metalled access road to
slum and paving inner slum
streets
10.4.2 Urban Poor and Slums
(i) Objectives:
- To provide basic housing to poor with effective roof protection;
- Provide micro-credit for individual toilet construction and connection to septic
tank.
- Provide health care and literacy in slums.
(ii) Short Term Strategy:
• Allocating at least 20 percent of the budget in slum improvement measures.
• Deciding and implementing slum housing as either /or in-situ or replanned
slum location. Deciding on housing design, construction methods/ technology,
women’s workplaces, cost cutting frameworks.
• Toilet construction with innovative design - maintenance – management
methods.
• HSCs to 100 percent slum housing.
• Incentives to small real estate companies and business models for slum
rehousing with ULB partnership.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 106
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
(iii) Long Term Strategy:
• Reducing slums to not exceeding 5 percent of the total population.
• Providing transit housing for slum projects.
• Focus on non-formal skills for town building and construction activities for slum
dweller organisation against wage employment.
• Introduction of Vocational training courses for skill development/ enhancement for
relevant jobs. (masons, drivers, carpenters, accountants-book keeping, production on
machines/ mechanics, chefs-cooks-waiters….,)
• The need for a policy especially tailored to reduce poverty and its impacts in a non-
political, meaningful way is recommended.
(iv) Identified Projects:
• Networking Slum Communities for infrastucture - skills – employment –
participation.
• Preparing feasibility reports and DPRs for Pilot projects using IHSDP/ BSUP funds
to cover at least 50% slums.
• Organising community built and managed, eco-toilets for all slum areas.
• Establising micro-credit societies as well as Feasibility Funds to undertake financially
atractive projects that can attract Bank Finance. (Note in Annexure 5 on Feasibility
Funds)
Table 10.2: Urban Poor Projects: Prioritization and Time Frame
S.No. Identified Projects 2009 2010 2011 2012 2013
1 Preparation of DPR Pilot Project
2 Implementation of DPR
3 Construction of Community toilets
4 Landscaping / Greening Slum area
10.4.3 Solid Waste Management
(i) Objective
- To provide a waste management system with safe waste disposal in environmentally
sustainable ways to all residents.
(ii) Short Term Strategy
- Explore partnering neighbouring ULBs for cluster landfill for cost sharing and
scale of operation.
- Select suitable options for selection (both primary and secondary points) with
simple equipment, labour intensive and low energy methods.
- Strategise health care and hazardous waste disposal.
- Define collection routes, transit storage of recyclables, safe working conditions,
incentives for innovation and incentives for rationalizing operations.
- Establish monitoring systems for vehicles/ materials/ repair/ maintenance/
landfill.
- Establish vermi-composting within landfill and small recycling activities en-
route to landfill.
- Dedicate a fund for SWM for its treatment and disposal.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 107
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
(iii) Long Term Strategy
- SWM Plans be prepared for implementation
- Continuous awareness using and selecting an effective medium
- Hazardous waste collection, storage, disposal in scientific way.
- Building bye laws to tailor refuse collection notices.
(iv) PP Partnership
- Establish possibilities for PPP in the SWM chain.
- Select contracts – tasks – services for private participants.
- Deliver efficient SWM operation process within collaborative mode.
- Ensure that PPP engages in minimizing risks to either party, pays employees
regularly, bids transparently, benefits workers, is non-hazardous and has a stable
operation.
(v) Identified Projects
- Based on sustainable parameters select site for cluster engineered landfill.
- Adopt innovative arrangements for door-to-door collection and waste
segregation at source.
- Purchase equipment or arrange loans for vehicles and equipment.
- Set-up composting plants at negihbourhood/ ward level.
- Contracting privately, tipping the waste operation at a pre decided cost per ton
basis.
Table 10.3 : SWM Projects ; Prioritisation and Time Frame
S.No. Identified Projects 2009 2010 2011 2012 2013
1 Selecting and Construction of
Land Fill Site on co-
sharing basis
2 Private Contracting of waste
tipping
3 Hiring pvt. waste pickers for HH
garbage collection under
new arrangement
4 Setting up Composting Plant
5 Purchase of essential equipment
10.4.4 Tourism and Historical Sites
(i) Objective
Encourage economic growth in Vickramsingauram by enhancing tourism resources,
developing tourism infrastructure, promoting tourism information and establishing an
Institution for Local Initiative in Heritage Conservation, Regeneration, Urban Design
and Natural area Conservation.
(ii) Strategy
Develop a Master Plan, mapping tourist resources, devising development partnership
with Local development group/ trust, opening an area planning office (expert views/
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 108
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
consultation/ committees); put on offer investment opportunities to private sector for
projects in leisure, recreation, heritage and water body improvements, commerce;
establishing an Environment and Heritage shop; establishing an Art/crafts village for
display and sale or artisan produced goods.
(iii) Major Initiative / Projects
- Accommodation/ Resorts/ Restaurants/ Cafes/ eating places.
- Entertainment and Leisure facilities.
- Temple Improvements, Picnic spot development at scenic sites (even outside
ULB jurisdiction at nearby Tourism places)
- Transportation facilities.
- Information and Communication facilities.
(iv) Identified Projects (1st Phase 2007- 2012)
- Conservation of temple and other built heritage sites.
- Rehabilitation of all old buildings (>50 yrs old).
- Tourist Guest Houses and Tourist Information Centres
- Tourism Circuits
- Construction of Heritage hotels, mid and low budget hotels
Table 10.4 : Heritage / Tourism Projects ; Prioritisation and Time Frame
S.No. Identified Projects 2009 2010 2011 2012 2013
1 Conservation of temples and other built
heritage sites
2 Rehabilitation of old buildings
3 Construction of Tourist Guest houses &
Information centres
4 Developing tourist circuits
5 Construction of heritage hotesl, Mid +
Low budget hotels, Rural
Tourism Resorts / Houses
6 Conservation of Water bodies
10.4.5 Storm Water Drainage
(i) Objective:
To ensure that the town is protected from flooding, and that the drainage network performs
efficiently.
(ii) Identified Projects
- All roads should be properly designed with drains on both sides of the road. All
drains should be engineered to perform year round (dry weather/ heavy rains)
drainage.
- All water bodies be rejuvenated and no untreated sewage/sullage be discharged with
them.
- Alternate methods may be used for lining of drains.
- Rain harvesting structure (roof tops/ paved/ unpaved areas/ arresting run-offs and
infiltering water into ground/ storing water under controlled conditions; these may all
be introduced as practices.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 109
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Table 10.5: Storm Water Drainage Projects ; Prioritisation and Time Frame
S.No. Identified Projects 2009 2010 2011 2012 2013
1 Construction of drains along all primary
roads (both sides)
2 Adopting alternative lining methods for
secondary drains (pilot projects)
3 Water harvesting structures
4 Treatment of waste water before discharge
into water bodies
10.4.6 Sanitation
(i) Projects
- Constructing New Community toilets at specified standards for the entire existing
and projected population (till 2012)
- Upgrading existing community toilets.
- Creating a framework for their planning/ designing, executing and management.
- Constructing ‘pay and use’ toilets near large commuter flow areas (bus stand/
market/ pilgrim places.)
Table 10.6 : Sanitation Projects ; Prioritisation and Time Frame
S.No. Identified Projects 2009 2010 2011 2012 2013
1 Construction of new community toilets for
slum dwellers
2 Upgrading existing toilets
3 Devising framework for planning / Design /
Construction / Management /
Financing New Community Toilets
4 Constructing Pay & Use toilets at busy
locations
10.4.7 Sewerage/ under ground drainage.
(i) Objective
To prevent health risks due to poor sanitation, and create healthy communities by
covering the entire town, including slums, with sewerage network.
(ii) Short term strategy
- Introduce sewer lines, by first designing a network to cover existing HHs
through a system of STPs in decentralized way for micro zones and planning for
population projected to 2018
- Serialize the network construction for every 5 years prioritizing it as per local
demand
- Connecting community toilets to sewers
- Connecting septic tanks to network in phased way.
- Ensuring no blocking of sewer takes place.
- Ensuring re use of waste water after its primary treatment
- Moving animal population away from several areas.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 110
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
(iii) Long Term Strategy
- Providing sewer connection to 100% HHs by 2041.
- Recycling of all liquid waste for non drinking purpose.
- Ensuring non mixing of sewerage and storm water
- Ensuring storm water drains are unlittered and year round functional.
(iv) PPP
- Innovative community toilets must be explored/ constructed after pilot testing,
and by involving private sector in its construction.
- Innovative management should be practiced to attract investment into sewerage
projects (incentives…)
- Compost/ manure, as commercial output from STPs may be used for ULB
incomes (through contractual arrangements)
- Effluents, if discharged into water bodies or elsewhere used, must conform to
environmental guidelines for safety.
- All private commercial/ industrial units will install and recycle their waste
water independent of the sewerage system.
(v) Identified projects
- Capital assets are required to provide a sewerage system with safe disposal
facilities for the entire population existing in 2021, 2031 and 2041.
- Components
- Mapping and GIS, topography surveys.
- Designing sewerage network as decentralized STPs for specified population till
2021 and further for every 5 year increments of population growth.
- Constructing the STPs
- Connecting community toilets, septic tanks to the sewerage network.
Table 10.7 : Underground Dranage (Sewerage) Projects ; Prioritisation and Time Frame
S.No. Identified Projects 2009 2010 2011 2012 2013
1 Topography Surveys, Mapping & GIS.
2
Design of new sewerage network for
decentralised STPs for existing town
3 Construction of Sewer system with STPs
4
Connecting Community Toilets / Septic tanks
to sewers
10.4.8 Water Supply
(i) Objective
Increasing the coverage and service levels for piped water supply with assurance of its
potability.
(ii) Identified projects
- Ensuring that water supply to Vikramasingapuram ULB, required for 2012, 2021,
2031 and 2041 are available to the acceptable standard.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 111
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
- For timely augmentation, required feasibility studies and preparation of a DPR should
be taken up.
- Present deficiency would require an ESR/ UG sump of capacity MLD with a
pumping system of the same capacity to service the population till 2012.
- Mapping and GIS
- DPR preparation and implementation
- Long term water supply demand calculated over 5 year periods beyond 2012
- Treatment and storage facilities for above demand with pumping facilities.
Table 10.8 : Water Supply Projects ; Prioritisation and Time Frame
S.No. Identified Projects 2009 2010 2011 2012 2013
1
Feasibility study and DPR
preparation for augmenting
future water supply
2
Covering Deficient demand upto
2012, construction of
ESR/UG sump, supply
network
3 Mapping & GIS
4 DPR implementation
10.5 Concurrence on Prioritized Projects
It is necessary to involve stakeholders in concurring that projects have been conceptualized
and prioritized as per their crucial requirements, have cut across all sectors specified
under the program, entail partnership modes in their implementation and
management, and are implementable in the first few years of the program
Successful execution will not only embolden the ULB to accept and asset more challenging
projects amiably and in a conflict free development environment.
After concurrence on the identified projects, the capital investment Plans will be prepared.
The Capital Investment Plans for the sectors Road network and Transport projects; water
supply, sewerage storm water drains; solid waste management; slum improvement;
Heritage conservation; Environment and Governance, will cover Project summaries,
Cost Estimates, Project Implementation phasing and Institutional arrangements.
The implementing ULBs will decide the manner in which efficiencies can be achieved in
project cost, implementing and financing as well as in projects development and
management through PPP arrangements.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 112
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Chapter 11 City Investment Plan (CIP)
11.1 Backdrop Study
The long –term vision for Vikramsingapuram town has already been set out in the Interim
Report of its CDP. The long-term goals of the community are expected to be driven
by fiscal, financial and policy initiatives of the ULB for making informed investment
choices for preparing the city’s Capital Investment Plan.
A CIP provides the level of investment that will be needed to implement the CDP and is an
estimate and approximation for determining the cost of implementing the stipulated
projects under the reform agenda.
The Capital Investment Plan which is an operational plan to actualize the goals and
strategies of the CDP is a multi year scheduling of the short term [usually 4-6 years]
plan for identifying capital projects and equipment purchase as well as identifying the
options for financing the plan. In real terms the plan provides effective links between
the ULB and the various city departments/ other state level agencies for identifying as
well as balancing competing needs and consequently developing short[and later long]
term capital finance plan. This way the city’s capital investments, both new and
O&M, as well as technical capacity for construction and O&M, through the linked
strategic plans spelt out in the CDP, get reflected in the Municipality’s annual budget.
11.1.1 Benefits of CIP
The Benefits of a CIP are;
1 Potential projects can be systematically evaluated at the same time.
2 Debts can be stabilized and projects consolidated to reduce the costs of borrowing.
3 It can serve as an public relations and economic development tool.
It also ensures the efficient use of public funds for preserving the ULB’s infrastructure whilst
promoting cooperation between the ULB and other public service structures.
11.1.2 Features of CIP
The typical Features of a CIP include;
• A list of capital projects [or equipment] to be purchased.
• A ranking of the projects as prioritized.
• The plan for financing them.
• The timetable for constructing or completing the projects.
• Justification for the projects.
As understood, capital projects are tangible with a life expectancy beyond one year. As the
CIP includes financial issues, it involves reviewing the ULB’s current finances.
Subsequent to its adoption, it is required to take count of a series of tasks, as,
inventorying existing capital assets, evaluating incomplete projects, assessing
financial capacity, compiling/ evaluating new projects, prioritizing them,
developing the Financial Plan, adopting the CIP, monitoring / managing the
approved projects, and updating the existing and ongoing Capital Projects.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 113
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
As part of the preparation of a CIP, it is prudent to consider the prevailing norms/ standards of
infrastructure services, and options for their provision, e.g. high, medium, low or
mixed. The agreed option should match public expectations and the technical
capacities of the ULB. Needless to say that they should be rationally chosen.
11.2 CIP Process for Vikramsingapuram
The framework for the long –term vision has already been provided in the CDP in the
previous chapters. These centre on leveraging the connectivity to the adjoining Kerala
State through State Highway 40, the ambience of Western Ghats which translates to
waterfalls, rivers, forests and wild life reserves as well as temples and other
significant architectural heritage. They all point to developing Tourism for catalyzing
economic growth and also encashing forest resources for organic products/
handicrafts and handlooms. The effect of development can significantly enhance if
the efforts serve the two adjoining towns of Vikramsingapuram and Ambasamudram.
This chapter focuses on the Capital Investment Plan on the Infrastructure needs for the
following urban sectors
(i) Water Supply;
(ii) Sewerage and Sanitation;
(iii) Storm Water Drainage;
(iv) Solid Waste Management;
(v) Traffic &Transportation;
(vi) Slums &Basic Services for the Urban Poor;
(vii) Others such as Urban Renewal, Urban Governance
Sector wise projects as identified cover the following;
• Project Summary; A description of the projects is made and its requirements assessed
as per Norms in Manuals/ standard reference documents as well as other stated
guidelines
• Cost Estimation of Projects identified; Project costs are assessed on the basis of
PWD Schedule of Rates for Tamil Nadu for Roads & Buildings the Water Supply
project emerged during the consultation process as given in the interim report of the
CDP after a due evaluation of the service levels, growth trends and future needs of
the city. Vikramsingapuram needs up-gradation/ improvement of the service apart
from meeting the needs of incremental growth in population. The Vikramsingapuram
Municipality also needs to strengthen its financial capacity for an effective service
delivery.
The prepared list of projects intend to meet the ULB’s goals for efficiency, a prompt
service delivery, strategic growth in house service connections and consequently an
increase in its revenue, are environmentally sustainable, benefit the community, and
meet the growing demands and incorporate the O&M needs.
• Phasing Plan for Project Implementation; The Phasing Plan presents the Project
Implementation Schedule during the period 2009-2014.
• Institutional Arrangements; This presents the Institutions/ULB/ Others responsible
for undertaking projects under the different sectors.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 114
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
The implementing institutions for projects in Vikramsingapuram are the Vikramsingapuram
Municipality, the Tamil Nadu Water and Drainage Board (TWAD), the TN Public
Works Department (PWD) the TN Town Planning Department, the TN Tourism
Department, the TN Forest & Environment Department, the TN Fisheries Department
11.3 Water Supply
11.3.1 Overview
The Water Supply project emerged during the consultation process as given in the interim
report of the CDP after a due evaluation of the service levels, growth trends and
future needs of the city. Vikramsingapuram needs up gradation/ improvement of the
service apart from meeting the needs of incremental growth in population. The
Vikramsingapuram Municipality also needs to strengthen its financial capacity for an
effective service delivery.
The prepared list of projects intends meeting the ULB’s goals for efficiency, a prompt service
delivery, strategic growth in house service connections and consequently an increase
in its revenue, be environmentally sustainable, benefit the community, and meet the
growing demand whilst incorporating the O&M needs.
11.3.2 Project Summary
The identified projects on preparing their DPRs can be classified under:
1 Production System
2 Storage System
3 Distribution System
4 Monitoring System
Locations of these components need to be put on maps
The Production System
Presently Vikramsingapuram is wholly dependant on surface water drawn from Tambraparani
river’s Kodamelaian anicut ( first anicut after Agasthya falls). The scheme initiated
40 years ago has progressed through three extension schemes for covering the
perspective population of 2036 and is clearly serving its purpose over future needs.
As such the need for source creation, improvement in supply, construction, O & M of
new assets is obviated, including the need for the other components ( as mentioned
below) that make up the water supply system.
� Head works
� Transporting raw water from surface source/ infiltration well at existing source
� Treatment of water
� Water pumps
� Water transmission main
� Booster station at
� Feeder mains
� Service reservoirs
� Distribution system with energy savers
� Distribution mains in previous omitted areas
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 115
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
(i) Water Treatment plant of 6.5 MLD (2021): Water Treatment Plant of 6.5 MLD
(2021) is already in operation against the present requirement of 2006.
(ii) Proposed Tube wells and Pumps: The assessed number have already taken into
account on design period of 15 years. A complementary supply from rain fed
construction of open wells/ tanks/ponds/ water harvesting structures for at least 10%
of the total supply. There is no established need for drilling tubewells for water
supply.
(iii) The Storage System:
• The present storage system of 2.2 ML is 33% of the total supply estimated at 6.6 ML.
The storage system should support continuous water supply for the city. The locations
should ensure that a water head of 4m. is available at the tail end of the distribution
system.
• CWR of 2.94ML Capacity: In order to counter the problem of power failure, the
design should propose to store water in CWR of 2.94ML capacity at a specified
location preferably given in the map.
• Overhead Reservoirs: OHRs of specified capacity (in LL) will be constructed with
the minimum staging height for improving water head at the tail end of the supply
network. These are to be connected to rising main for water intake and appropriately
shown on maps.
(iv) The Distribution System
The Distribution System comprises of rising main, sub main and primary distribution
network. Vikramsingapuram has fair amount of losses which have to be monitored
and new network laid in the non serviced areas of the town. With assured supply of
water for future, the network efficiency and water supply norms need to be adhered
and monitored.
(v) The Monitoring System
This involves monitoring both quantity and quality as well as minimizing losses of water and
the installation of Metering system for Bulk and end user consumption. Essentially
these should be done using energy efficient methods in a regime which ensures water
quality which is free of bacteria /other physico-chemical contaminants. It is suggested
that reliance be placed on automated water generation rather than human intervention.
Initial high costs of technology are compensated by efficient and reliable service
delivery.
11.3.3 Cost Estimates of Water Supply Projects
Broad cost estimates proposed are based on the unit costs. Investments are required to be
scheduled through an iterative process, taking into account aspects such as;
� Developed areas taking precedence over future development areas;
� Considerations for complementary investment for sewerage & sanitation and the
linkages thereof;
� Considerations for project size, the duration for implementation;
� Linking house service provision with the geographical expansion of the project
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 116
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
These have been provided in the consolidated CIP at the end of this chapter and are followed
by a phasing plan. Cost estimates follow unit rates derived from the Schedule of rates
(SoR) for each component. The water supply schemes have to meet the phasewise
demands of the town as per the DPR.
The urban local body for the period of next five does not wish to expand its water
augmentation through source as a scheme for this has been implemented,
wherein the demand for a shorter period has been taken care off. However, as
and when there will be increase in population/as per the priority and financial
arrangements ULB would require to expand its augmentation, treatment,
storage, and distribution. Development of metering and monitoring system
cannot be neglected in developing the water supply system however can be taken
as the last priority.
11.4 Sewerage and Sanitation
11.4.1 Overview
Vikramsingapuram does not have a sewerage system. A new one has to be put in place by the
TWAD Board. For doing this it is important to know the general and flood levels in
the town as well as the general slope of the city. The ridge formation too should be
known. At present the major modes of disposal are through individual septic tanks
and low cost sanitation through community toilets which are required to be
periodically cleaned by the municipality. About 63% of the HH have septic tanks
and nearly 7% have access to low cost sanitation units, the remaining defecate in open which is environmental hazard. The general practice of letting out wastewater
into low lying area or nearby stream is adopted creating insanitation. While designing
a new system it is important to ensure that sewer and water lines do not intercede for
avoiding contamination. In no case should the water line be laid below the sewer line.
GIS mapping for utilities is important and a prerequisite for a well designed
system.
For executing the sewerage project the requirement of STP cannot be under estimated and for
which land allocation will have to be considered. It may be possible to design the
STP for the neighbouring townships also and in integrated way. Since the economy of
the town is fairly sufficient one can consider higher cost technology for the STP and
ones which are land intensive.
Projects for Sewerage would include;
• An Underground Drainage System with provision for (a) Collection and Disposal
network (b)Treatment System
• Individual Sanitation System operated by a network of Septic Tanks
• Low Cost Sanitation System
On account of violating its natural drainage several wards in the city are flooded during
monsoons making them dysfunctional. General lay of the land is north to south; the
wards north of the E-W running Kodamelagian canal drain into the river. Those on
the southern part are helped by the terrain to log water and cultivate paddy between
the channel and the river. The city’s existing drainage partially served by some pucca
and katcha drains along with the non-existence of a sewerage system further
exacerbates loading on roadside drains which receive in addition the sewage and
sullage of the city. The open katcha and pucca drains need to be upgraded and a
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 117
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
closed drainage system introduced, besides the construction of New Drains and
desilting the existing ones.
Whilst the Detailed Project Report for Drainage for the entire town would identify specifics
with regard to ward level, area level and city level design details, the projects for
Improvements in the Drainage system would comprise of (i) Construction of New
Drains, (ii) Upgrading open & katcha drains to closed drainage system, and
(iii)Desilting blocked drains
Where the topography flattens making difficult the draining of the area, there would be need
for Pumping Stations at pre decided locations after a proper topographic assessment
11.4.2 The Underground Drainage System
The Development of Disposal System would incorporate Laying of the Trunk Network of
the desired length of specified size diameter for coverage of the existing town and
future development area as per the design; Laying of the Sub-Main Sewer
Network; Laying of the Lateral Sewer; Household Connection Sewer as well as
construction of Public Toilet complexes to serve slums, bus stands, shopping centres
and other recreational or other public areas. Particular care would be taken at notable
tourist places in the town.
The Individual sanitation system presently operative in old city areas or the isolated
residential and commercial areas dependant on site septic tanks or soak pits will
gradually be phased out to make room for standard UGD system beyond 2015.
Similarly the Low Cost Sanitation system would similarly be phased out to be replaced by
the UGD system beyond 2012. Till then it may be necessary to provide for LCS
system of sewage disposal for low income communities living in degenerated areas,
preferring introduction of eco toilets
The Operation and Maintenance system would entail procurement of equipment for
ensuring an efficient function and zero blockage by using appropriate technology
(sewage Lifting Stations, Sewer Flushing machines, Sewer Jetting machines, CCTVs
etc.). Treatment plant of 5MLD would be required by 2015.
Treatment plant of 6.7 MLD capacity is required for 2015.
Related aspects of the sewerage system would require that an effective Monitoring
arrangement be instituted by networking of STPs, establishing Testing Labs.,
automation and computerization of the system at a Central Control Room. The
STP location and setting should ensure nuisance free environment by proper
afforestation. Personnel have to be trained for the new roles, and, people have to
be made aware about adopting the new system.
11.4.3 Cost Estimates of UGD Projects
The urban local body does not wish to undertake development of underground drainage
system. A resolution has been passed by the board that underground drainage
system cannot be developed in the town. However, as and when there will be
increase in population/as per the priority and financial arrangements ULB
would require to expand its treatment, pumping, and distribution system,
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 118
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
whatever cost it may incur. Moreover, it has been mandated in UIDSSMT to
establish under ground drainage system as these are delayed investments.
11.5 Storm Water Drainage
11.5.1 Overview
The present system of drainage in the town consists of natural as well as man made drains. In
fact, the man-made drains are linked to the natural drains for disposal. The storm
water drains carry mainly the waste water comprising the sullage and sewerage from
the houses. This has created enormous environmental problems.
The length of storm water drainage network in the town is 58 km. This is approximately
1.1 times the length of road in the town. A DPR for constructing 13 km of new
drains and repairing 6 kms of existing drain is approved and work in progress.
A new DPR would be required to cover gaps of 77 km additional requirement of
drains upto 2012.
It has been observed that nearly 30% of the town remains flooded during the rainy season
making this component a critical one for Vikramsingapuram.
Trapezoidal sections with cunette at the base for dry weather flow gives hydraulic efficiency
to drains and should be adopted discarding the rectangular sections
The Operation and Maintenance of the drainage system by Vikramsingapuram Municipality
staff should assign due importance to safety and disaster prevention plus
environmental hazards by use of a monitoring system and vigilant handling.
Flood prone wards should integrate their drainage network by remodeling and even
constructing new drains to enhance system efficiency.
It is a preferred option to design a drainage system with outfall into a receptive water
harvesting structure for enabling ground water recharge knowing that the area is
drought prone and water supply a critical issue.
Building bye laws/ rules should be made mandatory for Rain Water Harvesting.
11.5.2 SWD System & Design Considerations
Whilst the Detailed Project Report for Drainage would identify specifics with regard to ward
level, area level and city level design details, the projects for Improvements in the
Drainage system would comprise of:
(i) Construction of New Drains,
(ii) Upgrading open & katcha drains to closed drainage system, and
(iii) Desilting blocked drains
11.5.3 Cost Estimates of Storm Water Projects
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 119
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
These have been provided in the consolidated CIP at the end of the chapter followed by
Phasing Plan. Cost estimates follow SoR for each component.
11.6 Solid Waste Management
11.6.1 Overview
The projects in solid waste management were identified considering the diverse aspects of
waste management and prioritizing based on level of services, city growth, and
possible options in solid waste management.
Presently 83% (2 MT) of the 10.56MT of waste produced in Vikramsingapuram is disposed
primitively on a site of 6.4 acres located at Kattaboman Clonywithin the city. A
composting yard is proposed to be set up using wind rose method and approximate
systems. Preparing a DPR will give a correct position vis a vis solid waste disposal of
21.9 MT scientifically.
11.6.2 SWM System
The SWM Collection system comprises of
1. Primary collection system The system of primary collection followed is cleaning, sweeping and collection of MSW by
handcarts. In future it is proposed to be dustbin free city except in the commercial
areas. This is possible by means of having a systematic door to door collection.
Pilot Project for Ragpickers: A pilot project for primary collection of waste (door to door)
will act as towards employment generation for the urban poor whilst serving a
important city level function. Three wards geographically representing the different
areas of the Vikramsingapuram Municipality shall be selected for the purpose of the
pilot projects.
2. Secondary collection system
The secondary collection comprises of collection bins of 4.5 MT are required to be placed at
conveniently placed for efficiency and covers the entire municipal area.
3. Development of Transportation System For primary collection of waste energy efficient transports such as handcarts designed for
selected load and convenient loading shall be used whilst vehicular transport -
trucks/tractors for collecting waste from secondary collection points to disposal sites.
4. Development of Disposal System
No scientific methods of disposal are followed. The waste is dumped at the current disposal
site on a site of 6.4 acres in the town within the municipal limit. A site of 5 acres is
proposed to be purchased for compost yard, and there is a proposal to save cost on
land purchase by accepting donated land for the purpose.
The disposal systems need to take into account longer perspective and designed for atleast 30
years. Thereby, requiring a larger site effectively afforested (for nuisance free
environment) and integrating on site screening, composting and recycling activities as
well as sanitary landfill with arrangements of safe handling of hazardous wastes.
Alternatively scientific landfill at cluster level is an option exercised only through
concurrence and discussion by other ULBs.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 120
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
The prospect of disposal on scientific sanitary landfill site can work to advantage on a larger
dedicated disposal site for the long term plan upto 2041.
5. Miscellaneous Works/Activities: Organizing waste workers and citizens into action in the
activity a series of capacity building and public awareness campaigns will be
necessary. PPP, SHGs and other appropriate mechanisms can be used to advantage as
per the State Policy.
11.6.3 Cost estimates of projects
The various projects for solid waste management include waste collection, transportation,
disposal and monitoring facility. These have been provided in the consolidated CIP at
the end of the chapter followed by Phasing Plan. Cost estimates follow SoR for each
component.
11.7 Traffic &Transportation
11.7.1 Overview
Roads form the main component of transportation system of any towns along with public
transport system, parking, signage, bus stop / shelters, etc. They are like arteries of
any settlements having economics and society heavily depended on them. It has been
observed that with the growth of urban areas many of the larger cities starts facing the
problem of traffic congestions, jams, larger travel time encroachments, traffic
mismanagement, erupting the day to day life of urban people. On the similar track,
one day, smaller urban settlements will also move, where, if the problems are not
resolved at this stage, can amplify and lead to unplanned growth.
During our visit to Vikramsingapuram Municipality the towns development appeared
bifurcated on account of the Kodamelagian Canal running West to East, and further
down, again, by the River Tambraparani. Most roads north of the canal runs at right
angles to each other in grid iron fashion coupled with some organically developed
areas. Major roads in the town run parallel to the Ambavalanapuram Road (West to
East) which is the main artery and also leads to regional destinations.
The ULB has some parts of forests ad water bodies as well as part of the slopes of the
Western Ghats/reservoirs and dams which are accessed by a hill road.
The consultation process articulated the need to convert all roads to all weather ones and work
towards accessing Kerala through forest road considered key ingredient.
Generally the projects under this section can be divided into two groups (i) short-term
improvement measures and (iii) long term improvement measures. Short term
improvement measures are regulatory measures and immediate remedial measures on
low investment cost. These include converting roads with two-way traffic to one-way
traffic; restricting entry of goods vehicles in core area etc. The long-term measures
involve construction of bridges, flyovers and new roads respectively.
11.7.2 Interim Measures
The short-term measures should be taken up as an immediate priority and attempted within a
1-3 year framework they are likely to give results with immediate effect for a low
investment proposed. These involve civil works of minor nature or simple
rearrangements for better efficiency. These are:
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 121
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
1. Preparation of Traffic Management Plan
Current and anticipated traffic of both regional and local level impacting Vikramsingapuram
Municipality would require to be assessed and a Plan prepared for project to be taken
up un the short and long term.
2. Improvement of Traffic Corridors
Vikramsingapuram has 2-3 major corridors catering to the local and regional traffic which
need to be improved and upgraded to concrete roads. The remaining road length
needs widening so as to ease core area congestion. A detailed survey exercise is
required to get the desired lengths and Road Right of Ways. The entire 67 km of
existing roads would have to be upgraded to desired service levels.
3. Intersection Improvements
The 5-6 major roads including the major artery which passes through the centre of the city
require a signalized intersection, level crossings too have to be signalized. All
intersections need improvement for efficient movement of traffic after duly
examining them.
4. Removal of Encroachments and Provision of Sidewalks
The commercial encroachments on roads and sidewalks as well other encroachments such as
squatter and garbage dumps are common phenomenon in urban settlement in the
Municipal area. These encroachments are extension of built-up properties; parking of
vehicles of shopkeepers/ customers and informal vegetable and cloth market on major
roads. The carriage ways have to be kept free and sidewalks restored for pedestrian
movement and traffic efficiency.
5. On Street & Off Street Parking
All unauthorized on-street parking to be banned and designated locations (identified by
demand levels and feasibility) to be auctioned for private operation. The off street
parking is one of the important projects for the town. Around 30% of the roads are
encroached with the on street parking of private and commercial vehicles (Tempo,
Taxi, Auto Rickshaw etc).
6. Provision of appropriate street / traffic infrastructure (Street furniture, signage’s, hoardings, etc): Street furniture, signage, hoardings etc. also forms the part of short
term improvement measures. These components add quality to the overall traffic
management system.
7. Other Short Term Improvement Measures: The other measure for traffic improvement
involves Training of Traffic Police on Traffic Management; Public Awareness and
Traffic Enforcement Drives and Registration of vehicles.
8. O & M of Projects 2 to 6.
11.7.3 Long Term Measures
All medium term solutions are to be implemented in a 5-10 year time horizon. These will
involve some investment (high or average). These will require some redesigning, civil
construction works, organizational changes, etc.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 122
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
1. Construction of New Road
The per capita road length is 1.3 against the given standard of 1.75 mts. This can be done
when DPR of roads is prepared. By 2012 an additional 27 kms. of roads would be
necessary for meeting the standards.
2. Construction of ROBs
At all level crossings the construction of flyovers would be mandatory as they not just ease
traffic but also contribute to road safety.
3. Introduction of a Formal Public Transport (bus) System This requires development of bus stands and public/private operators to facilitate town level
as well as regional transportation.
4. Other Improvement Measures The other measure for traffic improvement involves Installation of CCTV, Speed Radar, and
Video Camera for traffic management.
Apart from the above three the other project which can be taken under consideration in
Traffic and Transportation section are construction of the flyover, construction of
pedestrian over bridge, widening of regional roads/by-pass roads, utilization of water
transport system etc. At present in Vikramsingapuram these projects are not required
till next 15 years, thereafter if the need will arise these can be taken into consideration
for improving traffic management.
11.8 Street Lighting
11.8.1 Overview
Street lights form an essential component of the infrastructure and is generally looked in
conjunction with the roads and transportation system of any towns. Provision and
maintenance of street lights is a mandatory function of any ULB. This includes their
installations, replacement/ repair, operation and maintenance. Street lighting is
important because it:
• Allows the safe movement of motorists or pedestrians;
• Enhances the amenity of an area
• Acts as a deterrent to crime
Minimum Street light spacing required between successive lampposts is dependent on the
road width, traffic volume and land use on a particular road. Ideally street lights have
to be placed at an interval of 30 m. The spacing between street lights in
Vikramsingapuram Municipality is at 53m, much lower than the standards, thereby
indicating a need for increasing the number of luminaries.
11.8.2 Strategies
In conventional street lighting energy wastage is due to:
• Irregular switching off and switching on
• Over design in selected areas
• Ad hoc installation of lighting systems as load patterns Increase
• Manual switching practices
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 123
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Road and street lighting is one of the largest single expenditure items for Corporations. As a
result, it is important for Corporations to keep up-to-date with developments in lamp
and light fitting technology. This will allow them to take advantage of opportunities
to reduce the cost, energy use and emissions associated with street lighting, while
providing a better service to road users. Savings measures include:
Use of Solar Lights
Solar lamps (sponsored by business houses/ communities/ other active participants) should be
adopted. Solar panels and Photovoltaic Cells are being marketed with government
subsidy, this should be fully utilized.
These systems should be provided with automatic ON/OFF time switch for dusk to down
operation and overcharge / deep discharge prevention cut-off with LED indicators.
Energy Audits and Energy efficiency opportunities Energy audits and low energy adoption measures need to be undertaken for reducing energy
expenditure by municipality.
� Timers to street lights ensure less wasteful culture.
� Replacing inefficient lamps
� Reducing the number of lights operating
� Reducing operating hours
� Replacing inefficient switching equipment
� Changing type of energy used
� Improving maintenance practices
� Improving data management
Automatic lighting controls Installing a device to automatically switch off one or more fittings should only be considered
after lighting density has been addressed, as lighting power density tends to be
cheaper to fix and the savings generated are more reliable.
Privatization Options Privatisation in the form of maintenance contract may be explored by the ULB.
11.8.3 Cost Estimates of Project
The various projects under street lights have been provided in the consolidated CIP at the end
of the chapter followed by Phasing Plan. Cost estimates follow SoR for each
component.
11.9 Basic Services to the Urban Poor
11.9.1 Overview
Vikramsingapuram Municipality has nearly 11,500 households. Out of these nearly 9% are
slum households concentrated in the wards 3,9,11,13,19, 20 and 21. In general it is
observed that the affordability for a pucca house is only 40% with permanent roofs,
remaining 60% live in kutcha houses. This takes to estimating the demand for
housing aggressively on a program of (i) slum related housing and (ii) non slum
related housing.
11.9.2 Strategies
The policy to deal with poverty is largely recommended through the following strategies:
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 124
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
• Facilitating house reconstruction as a permanent structure with regular provision for
HSCs for water supply and sewerage system whenever installed with interim
arrangement for septic tanks(for categoryii)
• In-situ upgradation & rehabilitation in permanent housing with regular provision for
HSCs to water supply and sewerage system whenever installed, and an interim
arrangement for PSPs and Community Toilets as per laid down norms (for category
ii)
• Making available night shelters rental units to new migrants and potential squatters/
slum tenants (@ 25% of all slum households) in single room / shared accommodation
for short or extended stay at affordable rental which is reviewed every 2 years for
change depending on the rental market in Vikramsingapuram Municipality. in
properly serviced and well maintained housing areas managed by PPP.
Preparation of a DPR will cover all slum pockets and, all katcha shelter units per ward, and
quantum of housing units needed as rental ones. Action plans maybe phased with the
first phase devoted to detailed surveys quantifying demand, and upgrading 50% of the
identified slums/ katcha houses/rental housing construction, with the 2nd
phase
covering the remainder.
11.9.3 Cost Estimates of Project
• Costs for in-situ upgradation includes paved paths, drainage, street lighting, piped water
supply, individual and community toilets, community facilities for health/
education/recreations. The cost per hectare of Rs1 crore is assumed to be spread over
3 years.
• Costs for 50% reconstruction and 50% in-situ upgradation assumed @ Rs. 3 crore per
hectare spread over 3 years
• Provision of rental units in pre determined sites within new/ existing housing areas/near
new employment nodes for which estimates have been assumed
The above have been reflected in the consolidated CIP at the end of the chapter followed by
Phasing Plan.
11.10 List of Projects for Vikramsingapuram under different Sectors
11.10.1 SECTOR: Water Supply
S. NO. PROJECT / INITIATIVES REMARKS
1 Streamlining House Service Connections into legalized
ones
In - house activity
2 Enhancing water supply infrastructure by source creation,
laying of pipes /pumps etc.
Preparation of DPR
3 Developing water storage(underground &overhead) for
present & future population up to 2015
Preparation of DPR
4 Pumping system in new developing adjoining areas for
present and future development up to 2015
Preparation of DPR
5 Piping work for present & future development up to 2015 Preparation of DPR
6 Awareness Programs NGO/SHG/In-house
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 125
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
7 O & M In-house
8 Reforms(PPP/ water tax/laws/strategies) State and ULB driven
11.10.2 SECTOR: Sewerage
S. NO. PROJECT / INITIATIVES REMARKS
1 Laying of sewer network for present municipal area
including connection of septic tanks, pumping
facility (present density @ 13pph, increased
density @ 16pph by 2021)
Preparation of DPR
2 Construction of STP (6.7 MLD )for 2021 Preparation of DPR
3 O & M In-house
4 Laying of sewer for adjoining future development areas Preparation of DPR
5 Construction of community toilets (seat & bath)
complexes
Preparation of DPR
11.10.3 SECTOR: Drainage
S. NO. PROJECT / INITIATIVES REMARKS
1 Reconstruction/ Remodeling of 50% pucca drains Preparation of DPR
2 Conversion of katcha to pucca drains Preparation of DPR
3 Construction of new drains Preparation of DPR
4 De silting existing drains In-house
5 O & M In-house
Developing new drainage infrastructure for new adjoining
developing areas.
Preparation of DPR
11.10.4 SECTOR: Urban Transport
S. NO. PROJECT / INITIATIVES REMARKS
1 Improvement of major corridors (total length 20 kms.) Preparation of DPR
2 Upgrading, remodeling of all other roads (total length
47kms.)
Preparation of DPR
3 Improvement of major & minor junctions/ intersections Preparation of DPR
4 Construction of sidewalks, bus bays and service roads for
transport stops ( at least 20 locations)
Preparation of DPR
5 O & M of listed projects In-house
6 Development of parking areas at least on 10 locations Preparation of DPR
7 Construction/ remodeling of bus stand, truck depot, and
warehousing
Preparation of DPR
8 Encroachment removal and decongestion measures In-house
9 Public Awareness program on traffic discipline In-house
10 Signage, Road markings, road furniture, provision of
automatic signals, Indication boards/ Road and
Area Maps
Preparation of DPR
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 126
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
11 Site development for petrol filling stations In-house/State Town
Planning
12 Adopting scientific guidelines for traffic regulation Based on
Consultancy
11.10.5 SECTOR: Solid Waste Management
S. NO. PROJECT / INITIATIVES REMARKS
1 Equipment for solid waste management for Y2015 Preparation of DPR
2 Sanitary Landfill (landfill development, construction &
equipment) for 2031
Preparation of DPR
3 Infrastructure Facilities at solid waste disposal site(roads/
green belt/land development)by 2031
Preparation of DPR
4 Incineration for biomedical waste Preparation of DPR
5 Awareness Campaign and Capacity Building In-house/NGO/SHG
6 O & M In-house
7 Increasing coverage to 100% through a PPP model In-house
8 Developing a Composting plant for 2031 (site
development/ construction and equipment
purchase)
Preparation of DPR
11.10.6 11.10.7 SECTOR: Heritage and Tourism
S. NO. PROJECT / INITIATIVES REMARKS
1 Conservation of historic temples, sites, landmarks in and
near town
Preparation of DPR
2 Conservation of water bodies, forest areas and their
surroundings in and near the town
Preparation of DPR
3 Development of green corridors, parks, recreation
sites/guest houses within Eco-parks
Preparation of DPR
4 Heritage and Culture Zone Preparation of DPR
5 Inner city development Preparation of DPR
6 Tourist nodes (3 no.s) at Regional State Level Preparation of DPR
7 Public sanitation facilities In-house
8 Public space with food courts and kiosks/tourist oriented
bazaar-flea market/ Other Bazaars in Commercial
Zone
Preparation of DPR
9 Ring road/ Regional Road network and Business Zone
Development
Preparation of DPR
10 Establishing a special cell for Heritage conservation and
Inner city Renewal
State and ULB
11 Establishing a special cell for mini enterprise development
and Institutional development State & ULB
State and ULB
Note: Projects from S.No 9 to 11 same as for adjoining ULB Ambasamudram
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 127
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
11.10.8 SECTOR: Basic Services for Urban Poor
S. NO. PROJECT / INITIATIVES REMARKS
1 Preparing DPR for Slum Development Preparation of DPR
2 Provision of housing Preparation of DPR
3 Provision of PSPs @ 1 PSP for 15 households (interim
measure)
Preparation of DPR
4 Laying the WS network for present and future
development up to 2015
In-house
5 House Service Connections to 100% slum households Preparation of DPR
6 Construction of Community Toilet complexes for present
and future population
Preparation of DPR
7 Construction of new drains Preparation of DPR
8 Remodeling/ reconstructing/de-silting katcha drains and
converting them to pucca ones
Preparation of DPR
9 Connecting drains to city wide network and improvement
works in flood prone wards
Preparation of DPR
10 Widening roads and paths Preparation of DPR
11 Converting katcha roads to pucca ones Preparation of DPR
12 Installing street lights In-house
13 Solid waste management Preparation of DPR
14 Constructing Community services centre In-house
15 Constructing primary school as per standard In-house
16 Constructing community level shopping centre In-house
17 Construction of interim rental units for independent/
shared stay at select sites near employment nodes
In-house
18 Construction of workshop spaces In-house
19 O & M In-house
11.10.9 SECTOR: Disaster Management
S. NO. PROJECT / INITIATIVES REMARKS
1 Preparation of Environmental base maps& Impact
Area Diagrams
Based on Consultancy
2 Preparation of Disaster Management Plan Based on Consultancy
3 Installation/ Equipment/Erection/ other accessories-
instruments as identified in the DMP
Preparation of DPR
4 Awareness and Implementation of regulations as
identified in the DMP
In-house
11.10.10 SECTOR: Environmental Aspects
S. NO. PROJECT / INITIATIVES REMARKS
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 128
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
1 Construction of Rain Water Harvesting structures
within green/ open spaces; harvesting rain
water in buildings; Implementing bye laws for
same
Preparation of DPR
2 Sea front Development Preparation of DPR
3 Development of Sewerage system Preparation of DPR
4 Development of Drainage system Preparation of DPR
5 Awareness Programs on Environmental Issues In-house/NGO
Campaigns
6 Shift towards reduction in carbon emissions/ adoption
of clean fuel
Based on Consultancy
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 129
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
11.11 Sector wise City Investment Plan
Investment
till
2013
-14
2009-10 2010-11 2011-12 2012-13 2013-14 2021 2041
Sector/ Component (Rs. Lakhs) (Rs. Lakhs)
Water supply
Total Investment 540.42 108.31 108.31 108.31 108.31 107.18 227.73 687.16
1 Source/ system capacity augmentation - 0.00 0.00 0.00 0.00 0.00 16.00 63.43
2 Treatment capacity augmentation - 0.00 0.00 0.00 0.00 0.00 13.33 52.86
3 Distribution network augmentation - 0.00 0.00 0.00 0.00 0.00 15.74 62.40
4 Elevated Storage capacity augmentation - 0.00 0.00 0.00 0.00 0.00 23.17 49.61
5 Refurbishment of old Distribution Network - 0.00 0.00 0.00 0.00 0.00 91.88 200.40
6 Metering and Monitoring System 540.42 108.31 108.31 108.31 108.31 107.18 67.61 258.46
Sewerage
Total Investment 315 \76.89 76.89 53.88 53.88 53.88 1,836.25 1,465.78
1 UGD - Network 266 53.26 53.26 53.26 53.26 53.26 1,438.83 1,215.69
2 UGD - STPs 46 23.01 23.01 - - - 248.63 210.07
3 UGD - Pumping Machinery 3 0.62 0.62 0.62 0.62 0.62 148.80 40.02
4 Refurbishment of Old Distribution Network
5
Procurement of sewer maintenance equipment
(CCTV, Sewer Jetting Machine, Septic Tank
Cleaner et.al)
Roads & Urban Transport
Total Investment 482 108.48 108.48 78.48 78.48 78.48 243.12 888.66
1 Roads Up-gradation
a) BT to CC - - - - - - - -
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 130
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
b) Earthen/WBM to BT 181 36.19 36.19 36.19 36.19 36.19 - 216.33
2 Roads New Formation 126 25.28 25.28 25.28 25.28 25.28 148.12 587.33
3 Imp. Road (Widening, beautification, ROBs, bridges,
utility shifting etc) 60 12.00 12.00 12.00 12.00 12.00 15.00 30.00
4 Public Transport/ Improvements 25 5.00 5.00 5.00 5.00 5.00 50.00 25.00
5 Traffic Management/ Junction Improvements 60 30.00 30.00 - - - 30.00 30.00
6 Parking 30 7.50 7.50 7.50 7.50
Drains
Total Investment 377 75 75 75 75 75 - 249
1 Drains Up-gradation
2 Drains New Formation 248.71
3 Desilting & Strengthening of Pucca Drains 377 75.40 75.40 75.40 75.40 75.40
Street Lights
Total Investment 79 16 16 16 16 16 12 46
1 Replacement - Tube Lights 26 5.12 5.12 5.12 5.12 5.12
2 New Installation - Tube Lights
3 New Installation - High power Lamps 53 10.57 10.57 10.57 10.57 10.57 11.52 45.68
4 New Installation - High Mast Lamps 0 0.16 0.16 0.11
Conservancy (SWM) & Sanitation
Total Investment 225 104.11 42.82 42.82 24.23 10.73 6.05 229.15
1 New Vehicles (Primary Collection) 3 0.66 0.66 0.66 0.66 0.66 0.49 0.31
2 New Vehicles (Secondary and Disposal) 40 40.00 40.00
3 Acquiring New Disposal Site 71 26.76 15.97 15.97 6.39 6.39 5.09 86.08
4 Infrastructure at Disposal Site and Composting Plant 8 1.68 1.68 1.68 1.68 1.68 0.46 1.25
5 DLDPs & Container Bins 102 35.00 24.50 24.50 15.50 2.00 - 101.50
6 Research, Training and Awareness
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 131
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Urban Poor/ Slums
Total Investment 1,140 228 228 228 228 228
1 Slum Improvement - Rehabilitation/ Housing 872 174.40 174.40 174.40 174.40 174.40
2 Slum Improvement - Infrastructure 218 43.60 43.60 43.60 43.60 43.60
3 Slum Improvement - Land acquisition 50 10.00 10.00 10.00 10.00 10.00
E gov./Land use/ Dev. Planning
Total Investment 117 117
1 E Governance 10 10.0
2 Survey and Mapping(GIS) 104 104.5
2 Capacity Building of ULB Staff 3 2.5
Others
Total Investment 245 95 50 50 50
1 Heritage and Conservation 45 45.00
2 Street Furniture 10 2.50 2.50 2.50 2.50
3 Tree Plantation & Gardens 15 3.75 3.75 3.75 3.75
4 Night Shelters/ Travellers Bungalows
5 Fire System
6 Water Body Conservation 100 25.00 25.00 25.00 25.00
7 Others (System Studies etc) 75 18.75 18.75 18.75 18.75
Grand Total 3,521 929 706 653 634 569 2,325 3565
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 132
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Chapter 12 ASSET MANAGEMENT PART I- INTRODUCTION TO ASSET MANAGEMENT
12.1 Introduction
Assets by definition include, but are not limited to information in all forms and media, networks,
systems, material, real property, financial resources, employee trust, public confidence and
international reputation which are the tangible or intangible things of the Urban Local Bodies
(ULBs).
These assets of the ULB whether in the form of water distribution networks, sewerage, roads, buildings,
equipments deteriorate over a period of time due to use, climatic and geological conditions.
Certain components of the infrastructure are neglected and proper maintenance/ remedial
measures are not undertaken due to lack of adequate funding and appropriate support
technologies.
ULBs are not in a position to take up repair, rehabilitate or reconstruct their assets on their own in the
absence of complete data base, inadequate funds. This leads to a reduction in the asset value
to an extent where excess costs have to be incurred in renewal of the assets and excess
expenditure in creating new ones. The deterioration of the assets also affects the existing
financial situation of the ULBs by ways of reduction in revenues.
For strategic, operational and financial reasons, asset management is becoming an increasingly
important area of decision making for municipal governments. New demands for better service
provision, trends towards decentralized systems of public sector management in emerging
economies, potential synergies and changing roles in the public and private sectors are creating
the need for better management and accountability of municipal resources. A management
information base on assets and their condition which can be regularly updated shall further help
the ULB.
Asset management has many definitions, as per the Federal Highway Administration (FHWA)
definition:
“Asset management is a systematic approach of maintaining, upgrading, and operating
physical assets cost effectively. It combines engineering principles with sound business
practices and economic theory, and it provides tools to facilitate a more organized,
logical approach to decision-making. Thus, asset management provides a framework
for handling both short- and long-range planning”
ULB should prepare an asset management plan, which will include an inventory on the existing assets,
prioritization of maintenance and repairs and help decision-makers in optimising investment
strategies which shall in turn improve the quality of services.
Past successful cases of municipal management indicates that effective use of the asset base is an
important factor contributing to increases in municipal revenues and successful performance,
with the value of fixed assets of a municipality increasing to more than four times its yearly
expenditures (400%).
Asset management planning provides optimal solutions which match assets to programs and service
delivery strategies. All decisions should be made keeping that in mind as part of the framework
for decision making in an organization.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 133
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
An attempt has been made to provide an inventory of the assets of the municipality in this chapter.
12.2 Benefits of Asset Management
Some of the benefits associated with developing an asset management plan are:
� improved service delivery based on municipal asset use;
� effective management of built assets and increase in revenue base;
� assistance in decision making for resource allocation and maintenance expenses;
� enhance the environment and improve quality of life Improve land valuation (for example,
through relocation of public properties, sale and leases, and improvements in infrastructure
such as better roads) that make land assets attractive for productive and real estate purposes;
� evaluation of the associated risks and impacts, reduction of risks and need of emergency
interventions;
� life cycle analysis of investment decisions
12.3 Asset Management Plan Methodology
Futuristic asset management plan is very necessary for strategy development. The process should
integrate current asset supply to match with the asset demand serving the utility for
infrastructure development. The process diagram (figure 8.1) and the steps have been detailed
below:
Level of Service
� The current assets are evaluated in terms of their functionality, physical condition, use, financial
performance.
� New assets – determine the asset needs for delivering the required level of programs and services.
� Gap analysis – at this level planning will provide a comparison between assets required to support
program/ services and currently available assets or in the process of acquisition. In this manner
the comparison aims to find out the gaps between the requirements and the capacity, the surplus
assets that are not required can be disposed off, and the requirements to be fulfilled.
Decision Making
� Risk assessment: Asses the financial risks and life cycle costs involved in each alternative
considered.
� Optimal cost – The option selected should be most economical based on a techno-economic
feasibility analysis done by the asset mangers or responsible officer in charge.
Implementation
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 134
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Assets
Current assets New assets
Inventory & condition analysis
Identification, evaluation & gap
analysis
Level of service
• Asset supply analysis
• Asset demand analysis
• Gaps
Decision making
• Risk assessment
• Optimal cost assessment
The implementation process includes many decisions as mentioned below:
� Maintenance incorporates carrying on routine maintenance, repair and rehabilitation works.
� Renewals and replacements assessment suggests assets which do not meet service levels and need
to be replaced by new assets or revived, refurbished.
� Creation of new assets based on the gap analysis to ensure satisfactory service delivery
considering the economics, timing and capital inflows required.
� Disposal of asset – surplus and obsolete assets can be disposed to create value addition to the total
asset bank.
� Non- asset solutions are like outsourced services, reduced demand for asset can be done by
o Re-designing the service system to maintain with existing assets;
o Employing outsourced equipment and services;
o Increasing the usage of existing assets.
Finally the decision process is performed through working out financial plans, and various plans for
acquisition, disposal etc.
Asset management plan
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 135
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
12.4 Requirements of Asset Management
There various important aspects for infrastructure assets are
� capital database (inventory);
� maintenance management, service life prediction;
� risk & reliability assessment and
� valuation
� life cycle costing
To accomplish the above, a varied number of techniques/tools are available which can help in
minimizing the maintenance costs and maximise the value of the assets for the municipality.
Some of the techniques/tools are listed below:
12.4.1 Capital database
Preparation of a capital database shall include data collection, usage of consistent terminology, a
consideration of betterment versus maintenance and integration of Geographical GIS and other
tools which have been further elaborated in the sections below.
12.4.2 Maintenance Management
A) Computerised Maintenance Management comprises of two main components: a relational
database containing the asset data, and a set of add-on analysis and decision-support modules.
There are many software available in the market which can help in this regard, a brief glimpse
of a popular model City Works is given below:
CityWorks (2005) is a GIS-based solution for operational and maintenance management of municipal
assets and supports functions including asset data management, work order management,
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 136
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
recording inspection and condition data, and report generation. It delivers various benefits to
organizations by delivering information to maintenance engineers and managers1.
Stage 1 : User Interface
Stage 2: Selection of Asset Module
1 Manual City Works
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 139
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Information provided in the asset module Asset module gives a detailed inventory of the asset with the following entries so that every asset is
recorded and maintained systematically.
Information Provided in the Asset Module
S. No Field Description
1 Asset No. A unique number assigned to an asset.
2 Asset
Descri
ption
Description of the asset.
3 Location Code assigned to a location and its description.
4 Department Code assigned to a department and its description.
5 Asset Category Different types of assets are grouped together under an asset
category. This enables easy management of asset data
and retrieval.
6 Asset Status The current asset status describes which operational state the
asset is in. A code assigned to an asset status and its
description.
Options are:
Active = an asset which is currently in service and on site
In-active = an asset which is not in service
Disposed = an asset which has been taken out of service
permanently.
Lost = an asset which cannot be accounted for in an audit,
therefore no disposable details.
In-storage = an asset which is currently in service but not kept
on site.
7 Criticality Defines the criticality depending on the usage of the
equipment.
8 Authorised
Emplo
yee
An employee who has been given the rights and
accountabilities for that particular asset.
9 Serial Number Enter the serial number of the asset which can be obtained
from the warranty card or on the asset nameplate
10 Manufacturer Enter the manufacturer of the asset in this field.
11 Contractor
Warranty Assets which are within the manufacturer warranty period
Contract Assets which are under service contracts
Warranty
Expiry
Date
Enter the date of the warranty expiry.
Enter additional notes on the warranty or contract, if
applicable
12 Supplier A supplier is a company which supplies the assets.
13 Purchase Current Value
Calculated field based on a linear depreciation rate.
Current Value = Purchase Price – [{(Today’s Date) – (Date
Acquired)}/ Estimated Life]
14 Date Disposed Enter the date when the asset was disposed (if applicable)
B) Engineered Management Systems
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 140
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Using hand held devices for field data entry is effective
and time saving. The case of City of Saco, Maine shows
that there was a 20% cost reduction due to usage of
hand held devices for information recoding regarding
the condition and characteristics of sewer, drains,
pavements, pipe size.
This assigns a Facility Condition Index (FCI) for an asset based on a number of factors including the
number of defects, physical condition and quality of materials or workmanship. With these data
it is possible to predict the FCI well into the future, given the degradation curve and the effect
of remedial action. FCI can be calculated using the formula mentioned below,
FCI = Deferred Maintenance Cost/ Capital Replacement value, If FCI is < 0.05 is good
FCI 0.05 – 0.1 is fair
FCI More than 0.1 is poor
C) Condition Assessment Survey
A Condition Assessment Survey (CAS) is a tool which helps in the decision making by establishing the
existing condition of the asset and aids in producing a benchmark between different types of
asset and also for the same asset at different times. CAS is a tool which records the deficiencies
in a system or component, the extent of the defect, as well as the urgency of the repair work; in
some cases the estimated cost of repair is provided, at the time of inspection, projected,
remaining life and future use. This type of systematic inspection is essential for asset
management as it provides data for the "maintenance management", "service life prediction"
and "risk analysis" enabling technologies, mentioned earlier2.
D) Geographical Information Systems with Asset Management
Software tools are used to support the tracking, analysis, and reporting of asset and related information.
Geographic Information System (GIS) integrates the technical information to geographical
information.
This helps in the efficient management of an asset inventory. GIS enables map-based views of the asset
helps in forming a database relationship between the spatial data in the GIS and details of the
assets and the work performed on these assets, extended graphical display and data analysis
functionality.
Asset-related information can be spatially analyzed to help identify trends or to determine impacts of
proposed operations. Analysis results and trends can be displayed on a map to further assist in
the decision making process.
High Resolution Imagery Quick Bird
Figure. Use of hand held devices for data entry
2 Technical Paper on Municipal Infrastructure Investment Planning: Asset management by D.J. Vanier and N.H.
Danylo
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 141
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Fig 12.3: CityWorks GIS based
Asset Management
System
An
example of application of GIS in India has been given below. Mirzapur Municipality in Uttar
Pradesh is one of the first to use GIS for municipal applications. It started with the purpose of
Property Assessment with the help of the Government of Netherlands and Government of India.
The spatial database has proved useful for many activities and later integrated with the utility
networks. Since its implementation, it had raised the increased the number of property tax
assessments by ten times and tripled its property tax revenue (1995-2000 bases). This was later
expanded to include water supply, street record, street drains, solid waste management (its
distribution network model, vehicle optimization, garbage bin location and staff deployment)
etc. The procedure adopted for the same has been mentioned below3.
• Existing infrastructure water distribution network, street network etc. is added to GIS and
existing paper records were transformed to layers on GIS map.
• Information on various infrastructure components (such as material, condition etc.) is collected
to represent physical proximity of assets so that strategies can be devised while considering
their management plans.
• Update conditions of recently built and mapped facilities
• Establish the mapped location and condition of the vast bulk of the municipal infrastructure
system.
• Considering the urban infrastructures as a single system with relationships between the
different elements.
Map depicting the water supply network
3 Ref: www.mirzapur.net
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 142
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Map depicting the water supply network on GIS
E) Global Positioning Systems
(GPS) technology assists in accurate data collection, precise identification of building or service
locations, calculations of areas and lengths, estimation of building height, and more importantly
the easy, clear and unambiguous documentation of physical location of identified defects and
potential problems.
These techniques represent valuable tools for the municipality to minimise their maintenance costs and
maximise the value of their assets. On the whole, the system will help the local body manage its
own assets in terms of location, land use, litigations, encroachments, property values, revenues
and expenditure.
12.4.3 Risk & Reliability Assessment
Condition assessment and risk and reliability analysis varies from the simple to the complex process
and is not a “one-size fits-all” process. Risk & Reliability analysis gives the probability of an
asset to failure. This can be carried out considering the trends in output of the assets, and life
cycle functioning. The Risk assessment considers various alternatives and risk involved in
ownership of an asset. Effective risk management requires as a first step an inventory of each
class of assets, standardized condition assessment, and a method to evaluate the reliability of
these assets and consequences of unsatisfactory performance.
The reliability assessment aids in decision making for whether the existing assets are in favourable
condition to provide desired or increased level of services and their accountability to the
services in future.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 143
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
12.4.4 Valuation
The various components which need to be considered for valuation are –
� present value of the asset;
� depreciation in the cost of assets;
� costs incurred in the betterment or having a new asset visa-a-vis maintenance of the existing
asset;
� documentation for the purpose of audit;
� capitalization of carrying costs are incurred in the acquisition, construction or development
activity of an asset;
� contributed assets include municipality’s assets contributed by others, including developer
contributed assets, even though these were acquired at no cost to the municipality;
� betterment (new ) vs. maintenance.
12.4.5 Life Cycle Costing
Asset life cycle comprises of different stages – procurement plan, acquisition, operation and disposal.
Life cycle cost assessment gives a holistic cost over these phases so as to integrate the
fragmented costs and give the total expenditure required for the asset’s life cycle and the
components included are:
1. Capital cost – Cost of acquiring an asset. This may also include costs for conducting feasibility
study, tendering etc.
2. Recurrent cost – This includes operating costs for energy, manpower, maintenance, cleaning,
etc.
3. Refurbishment cost – Planned refurbishment or improvement costs, or enhancement cost which
may be a non asset solution leading to reducing capital investment.
4. Disposal cost – It is the cost of disposal and could be significant in some cases like for example
the demolition cost of a building can be greater than its salvage value.
5. Environmental costs – the environmental considerations shall be made while evaluating the
costs of an asset. For example the public transport if not performing as per the environmental
standards they might incur pollution taxes or replaced in parts or as whole.
The relative significance of capital and recurrent costs as a proportion of total life cycle costs will
depend on the nature of the asset. The cost of operating and maintaining an asset over its useful
life often is greater than its acquisition cost. In such cases the use of full life cycle costing in
evaluating alternatives which are imperative to ensure overall program costs are recognized and
minimized.
A typical life cycle cost assessment is given in the diagram below. Year 1 depicts the capital cost, the O
& M expenses begin from Year 2 and drastically increase at Year n if replacement is not done
and the costs incurred are much more than the disposal costs. Environmental costs also added to
the O & M costs increasing the overall O&M costs.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 144
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
12.4.6 Contracting Asset Management
One of the most practiced methods of asset management is private sector participation. Another method
is organizing the framework of local bodies to involve asset management by means of
involvement of professionals or dedicated officers as asset managers while keeping the
municipal authorities in the loop. The two approaches have been described diagrammatically
below.
Approach 1 Approach 2
Municipality Municipality
Asset Management Cell
Physical Works Contract
Physical works Contract
Asset Manager / Executive
Professional Asset Management Consultant
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 145
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
PART II- ASSET MANAGEMENT IN VIKRAMSINGAPURAM
12.5 Infrastructure Assets
12.5.1 Water Supply
The water supply system in Vikramsingapuram municipality is in place since 1967. The municipal
water supply assets generally comprise of assets at the head works, treatment plant,
transmission mains, pump rooms, pumping mains, storage tanks, feeder mains, distribution
network including all valves, connections, meters, and quarters for watchmen and all related
facilities.
Presently the water distribution network works through a system of OHTs, underground sump,
treatment plant, and distribution network pumps, hand pumps, open wells comes.
Transmission & Distribution Network
The existing storage system comprise of Ground Level Service Reservoirs (GLSR) at
Vambalanthanparai and Tana and four surface reservoirs with a total capacity of 22.15 lakh
litres.
Table 12.2: Details on Water Supply System
S. No Listing of Asset Nos. Age(years) Condition
1 Overhead Tanks (OHTs) 5 35 Good
2 Underground Sump 1 35 Good
3 Treatment Plant 1 35 Good
4 Distribution Network 2 35 Good
5 Power Pumps 9 30 Good
6 Hand Pumps 118 20 Good
7 Public Fountains 240 30 Good
8 Open Wells 10 25 Good
Source: Municipality, Vikramsingapuram
12.5.2 Solid Waste Management
The details on the various solid waste equipments have been given in the table below. In addition to the
equipments the municipality also has a waste disposal site of 6.84 acres.
Table 8.3 Details of Solid Waste Management
Particulars Description (nos.)
Temporary Waste Storage Points (Dustbins) 142 nos. (100Kg/ bin)
Trolleys (Tipper Auto) 4
Mini Lorries 3
Power Tiller 1
Source: Municipality, Vikramsingapuram
12.5.3 Road & Road Infrastructure
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 146
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Details on the various types of roads are given in the table below. Considering the road density and
other percentage of road length, the present network is highly inadequate for the town.
Table 8.4: Details on Roads
S. No Particulars Description (km)
1 Concrete 19.64
2 Asphalted / Black Top 31.70
3 WBM 0.22
4 Earthen 14.49
Source: Municipality, Vikramsingapuram
12.5.4 Street Lights
The details on the various types of street lights available with the ULB are given below. Automatic
timer fitted street lights instead of manual operation to save power, PPP services for
maintenance and cleaning of pavements can be adopted.
Table 8.5: Number of Lights by Type
S. No Particulars Description (nos.)
1 Incandescent Lamps Nil
2 Tube Lights (Fluorescent Lamps) 1106
3 Sodium Vapor Lamps 149
4 Mercury Lamps 9
Source: Municipality, Vikramsingapuram
12.6 Land, Buildings & Vehicles
Municipality does not maintain any computerized maintenance management system hence keeping a
track and updating of the assets is a problem. The buildings with the municipality can be
classified as remunerative and non-remunerative assets the latter are those which are either
acquired or purchased or gifted on which the municipality incurs considerable expenditure for
operation and maintenance.
The remunerative assets include commercial complexes, shops in the bus stand, markets, slaughter
house, pay & use toilets etc. Non-remunerative assets of the municipality include office
buildings, burial ground, compost yard, etc. A summary of these are presented in the table
below.
Table 8.6: Details on Land, Building and Vehicles
Listing of Asset Description (nos.) Age (years) Condition
Shops 54 10 Good
Markets 1 30 Good
1 10 Good
1 35 Good
1 35 Good
15 35 Good
2 35 Good
3 35 Good
Municipality Building
1 4 Good
Kalyana Mandapams - - -
Solid waste disposal site 6.84 acres 40 Good
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 147
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Community Hall 2 2 -
Movable Furniture 15 20 Good
Table 20 25 Good
Chair 35 30 Good
Telephone 5 25 Good
Source: Municipality, Vikramsingapuram
12.7 Strategies and Recommendations
Asset management is the tool in decision making and shall help in economising the costs. The various
recommendations under the different components have been detailed below:
Water Supply and Sewerage
� Inventory of all the components of water supply and sewerage (length, condition, age, no. of
valves, maintenance history, condition ratings etc.)
� Mapping the network on to GIS. It provides the graphical interface to view asset data directly,
w.r.t its location and corresponding asset related information.
� Validating the information by ground survey using GPS etc.
� This information should also be linked to the existing land use so as to facilitate the
maintenance and repair in a manner without interrupting the neighbourhood regular activities.
Solid Waste Management � Inventory on collection points, transfer station, equipments and schedules and integrating it
with GIS.
� Assessment of equipments based on the level of service and customer satisfaction.
� Assessment of shortest route to disposal site covering all collection points to economise on the
costs, assessing the maximum trips possible and procurement of vehicles accordingly.
� Continuous monitoring is effective in improving the management of assets and level of
services.
Street Lights � Inventory of the streetlights and assigning each of them a code, the code depicting various
attributes such as manufacturer’s name, year of purchase, warranty etc.
� This should be then mapped on GIS as layers which shall help in overall maintenance and
replacement of the street lights on a priority basis and assessment of the cost of shifting to solar
lamps in the longer run.
� Involving the resident welfare association in the maintenance and replacement charges.
� Franchising lighting and street furniture maintenance to private companies.
Roads
� Assign a link number to each road and attributes to every link and prepare digitized GIS maps.
� The attributes which shall be depicted as different layers would include age, material,
construction period, etc.
� Life cycle management plan - This section of road asset management plan identifies the process
required to effectively manage, maintain, renew and upgrade the road assets. It also highlights
the expected future expenditure required to effectively manage the road assets. Past
maintenance records and expenditure is required for life cycle management.
� Roads can further be rated in the ArcGIS database map on various factors such as tear and
shear, cracking, potholes, and tendency to degrade within two years or specified time frame and
preparing a logical and capacity supported strategic plan. This can also help in the financial
analysis of the roads which require repair or replacement on priority basis. This shall also
include the evaluating the cost options and preferred life span of the road, and considerations
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 148
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
overlapping with future investments for widening or new projects like diversions, grade
separators while making the allotments.
Land and Building Assets � A detailed inventory of the assets (lands and buildings) and mapping on a GIS map supported
by ground survey.
� Each plot/ building to cover various attributes such as number of floors, use, age, maintenance
charges, rent, revenue generated etc.
� Plotting and marking of vacant lands for the purpose of acquisition and creation of new assets
for public purpose. Involvement of the community or private sector can be considered in this
regard.
� Dilapidated and overburdening building assets should be leased out if the market value of the
structure is anticipated to go down. The economic life of the assets is an important factor in this
respect; when the land value is high and the asset becomes expensive to maintain it is better to
retain the ownership of the land and opt for PPP options to continue the services.
An ideal inventory for asset management is provided in the Part IV. Case Studies of best practices by
ULBs which have successfully implemented Asset Management have been enclosed in Part III.
A separate study is necessary for the purpose of preparing a detailed inventory of land and
infrastructure and land assets to minimise their maintenance costs and maximise the
value of their assets. Creation of maps for all assets will help cross check and update the
necessary information using GIS and GPS systems.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 149
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
PART III- CASE STUDIES
� Case – I
� Solid Waste Management, Park Development and Maintenance, Ahmedabad Municipal
Corporation
� The solid waste management in Bodakdev area of western Ahmedabad was a huge burden on
Bodakdev Nagar Panchayat with 8- 10 tons of waste being generated entailing an expenditure
of Rs. 40,000- 50,000 for collection and disposal. The privatization and PPP model being
adopted for collection changed with the assets being managed by the local body and a private
organization. The Local Govt. played the role of facilitator along with AUDA and other
stakeholders such as resident associations, and even Gram Panchayats. Together they
collaborated to make the city clean and green.
�
Another problem in Bokadev was scarce and ill maintained vacant lands. These reserved lands were
encroached upon or became dump yards. This created unhygienic situations at important
junctions and locations of the city. AUDA initiated partnership with private sector for
developing and maintaining the land parcels designated for open space/recreational and park
development as well as traffic islands.
Park development & Maintenance
Strategies Adopted
• In the new zoning plan, a virtual green belt was developed with private sector participation.
• Up to 5% of all land in the Town Planning Schemes is being earmarked for parks and open
spaces.
• AUDA has identified various pockets of land and traffic islands for development of
parks/gardens.
• Several leading organizations from private sector have been approached to carry out the
development and maintenance of these parks.
• These organizations are required to initially pay a fixed amount to AUDA as token money
based on the area of the plot.
• AUDA carries out the garden development, which has to be maintained by the organization on
yearly contract basis.
• All the maintenance charges including water charges, electricity bills, lighting repairs and
labour wages have to be borne by the private organization.
• In return, the private organizations are entitled to install their booths/stalls and advertising
hoardings at the particular park within the area permitted by AUDA.
• AUDA inspects the maintenance carried out by the private organizations on a regular basis and
the contract is renewed on yearly basis if it is found satisfactory.
� Achievements � Finances are generated to carry out works for improving the environmental conditions.
Dilapidated plots are developed and maintained as green spaces of the city.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 150
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
� Case – II
� Kodinar Municipality: Public Private Partnership Project – River Cleaning, Check Dam
construction, rain water harvesting.
� Situation before the Initiative
• The riverbed of Singoda River, which passes through the center of the city, was used as a
dumping site for the solid waste generated since the past 25 years. This waste formed almost
10-12’ ft deep layer over a stretch of 700m to 800 m lengths and 150m width. This comprised
of organic decomposed waste and silt.
• It created an unhygienic environment in the heart of the city. During monsoons as the sufficient
depth was not available for the river to carry the rainwater, it would overflow into the
surrounding areas, these led to difficulties in ground water recharge.
• The land abutting the riverbed was beginning to be encroached by shanties.
Strategies & Achievements
• The total cost estimated for the project
was Rs. 60 lakhs, of which the major
cost was of excavating the garbage up
to 10 to 12’ by excavators that were to
be rented.
• A retaining wall was built to support
the edges of the river stretch. The
existing wells on the riverbed were
protected during the excavation
activity and deepened later.
• Three percolation wells have been
constructed to increase the ground
water recharge.
• The encroachments (houses & shops) consisting of 32 families were relocated at the land
reserved for EWS housing and provided with houses/shops till the plinth level & provided with
water connection.
Table 8.7: Details on the Kodinar Project
Function Financing Agency Expenditure
Excavating the Garbage Ambuja Cement Foundation 6 lakhs
Protecting the existing wells
and building retaining
wall
Ambuja Cement Foundation 5 lakhs
Relocate 32 families and
provide them with
housing
Kodinar Municipality 10 lakhs
Relocate the shops Kodinar Municipality 10 lakhs
River Deepening Ambuja Cement foundation,
Bilashwar Sugar Mills co-
op society and Kodinar
Municipality
14 lakhs
Source: ICMA website
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 151
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Urban Poor
(20%)
Others
COMPOSITION OF
ECONOMIC CLASSES
BPL
WATER SANITATION ROADS SOCIAL
INFRASTRUCTURE
DRAINS
Non Poor
HERITAGE
CORE AREAS
Non Poor Non Poor Non Poor
Non Poor
Poor Poor
Poor Poor Poor
Non Poor Poor
CDP
VISION
STEPS TO TACKLE
DEVELOPMENT OPTIONS
INVESTMENTS
POLICY REFORM
TECHNICAL ASSISTANCE
ON GROUND
REALITIES
CIVIL SOCIETY
PARTNERSHIP A
C
B
D
ASPECTS AND ISSUES IN CDP PREPARATION Annexure-1
TECHNICAL ASSISTANCE
• Architectural & Engineering Design
• Service performance and Demand
Surveys
• Energy and Water Audits
• Shadow Credit Ratings and
Development Finance Services
• GIS
• e-governance
• Disaster Preparedness
• Project Costing
• Funds
• Maintenance
• Collections
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 152
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
? Property Tax? GIS? Info Kiosk?
User Charges? E-Governance?
Other
Core Infrastructure
Public Private
Partnership Municipality
? ?
OPTIONS
CDP
Interface
Government
G
CDP F
Govt. (Plan Making and Implementation)
dia
logue
Time START
CONTNUING DIALOGUE
RESETTLE ? FORM HOUSING
SLUM
COOPERATIVE?
BUILD
COMMUNITY
HALLS?
? INVEST IN
BUILD ROADS?
FORM AN EQUITY SHARE
HOLDING COMPANY?
ACQUIRE EQUIPMENTS?
OUTSOURCE TECHNICAL CONSTRUCTION
SERVICES?
H
EMOTIONALLY INVEST BY RICH RESIDENTS
VOLUNTARISM? FUNDS? CHARITIES? TECHNICALLY?.......................
E
I
J
K
MUNICIPALITY TASK
ENHANCING REVENUES
LEVERAGING FUNDS
Citizen
Annexure - 1 (Cont…d)
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 153
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
PERFORMANCE INDICATORS
Say Sanitation Program
Up to end of 1st decade
Up to end of 3rd
decade
Up to end of 2nd
decade
50 % Sanitation
75 % Sanitation
100 % Sanitation
From
From 0 Sanitation 33 % Septic Tank 66% Community
Toilet
30% septic 20% community
Toilets
25% septic 0% community
toilet
0% septic 0% community
Toilet
DEVELOPMENT MODELS ? GOVT
only
PPP PVT
only
CBO’s
only
ASSESSMENT STUDIES MUNICIPALITY STRUCTURAL AND
LEGAL
CLARITY OF VISION
AND MISSION
Funds
Functions
Functionaries
Laws
Schemes
Techniques
• Land
• Urban Development
• Infrastructure Development
• Business Development
• Transport/ Road network
• Sustainability / greens
• Urban Poor
Jobs
Houses
Services
• Culture and Heritage
N
Source: IPE
L
PERFORMANCE INDICATORS
Say Sanitation Program
Up to end of 1st decade
Up to end of 3rd
decade
Up to end of 2nd
decade
50 % Sanitation
75 % Sanitation
100 % Sanitation
From
From 0 Sanitation 33 % Septic Tank 66% Community
Toilet
30% septic 20% community
Toilets
25% septic 0% community
toilet
0% septic 0% community
Toilet
DEVELOPMENT MODELS ?
M
Annexure – 2
Scope of Work The
detailed scope of work as envisaged by Commissionerate of Municipal Administration is stated
as follows:
Annexure - 1 (Cont…d)
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 154
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
(a) Study of existing setup of ULB and an analysis of various projects executed or taken in hand to
formulate the background. The CDP should have future vision for the city in light of its
strengths and weaknesses.
(b) Situation analysis, with regard to demographic and economic trends in the ULB and their
implications for ULB governance and service delivery systems and structures referring to the
jurisdiction of town level agencies involved in provision and regulation of urban public services
(i.e. water supply, sewerage, sanitation, solid waste management, road network, urban
transport, street lighting, redevelopment of inner (old) city area of the town, basic services to
urban poor and other social infrastructure). The financial status of the municipality and
agencies concerned with service provision including an analysis of their credit worthiness and
efficiency of the institutional framework.
(c) A future perspective for the town area clearly showing the direction of change as well as
economic and basic services vision. (Sectoral agenda, reform agenda, quality of life, urban
services, social inclusion etc).
(d) Alternatives and development strategies for economic development, governance, landuse, urban
poor, core municipal infrastructure, urban environment and cultural heritage with proper
prioritization criteria and linkage with Reform Agendas. Preparation of a phased action plan
with targets for physical and financial investments, reforms, capacity building project
identification and prioritization.
(e) Assess the demand for the projects listed out by these Municipalities and anlayse demand for the
next 25-30 years.
(f) Financial Assessment of the ULBs an assessment of local finances (past 5 years) in terms of
sources and uses of funds, base and basis of levy, revision history and impacts. State
assignments and transfers base and basis of transfer and its predictability; uses of funds
outstanding liabilities (loans, power dues, pension etc.) and, a review of revenue and service
management arrangements. Levels of service, coverage and quality of municipal services in
both poor and non-poor localities. Staffing and management arrangements in delivery of
services.
(g) Outline the issues of revenue realization, quality of existing assets in relation to service levels and
coverage, and institutional constraints. Develop quick indicators of performance, based on –
• Current coverage and additional population in the medium term (10 years) and unit
costs, indicate town level investment requirement for upgradation of infrastructure.
• To improve service coverage and asset quality.
(h) Preparation of comprehensive Asset Management Plan and use fiscal notes policy analysis to
assist in making informed investment choices to achieve sector/ city goals.
(i) Define priority assets and indicative costs of rehabilitation.
(j) Conduct fiscal impact analysis of investments: life cycle O&M costs, revenues from project, and
costs/ impacts on finances and of not doing the project
(k) Explore funding options for rehabilitation of facilities.
(l) Prepare a Financial and Operating Plan (FOP). The FOP is a medium term framework of the
ULBs, and shall present the following.
(m) Assess the impact of upgrading these as municipalities from town panchayats.
� Additional data to be collected :
� Break-up of energy cost on water supply, street lighting and other EB charges etc.
� Salary for all the departments including staff and payments to private operators
� Finding out the benchmark cost i.e. at ideal condition what will be the cost of the
identified investments, a table indicating the investment plan for nest 5 years with identified
source of finance.
� Areas of reduction of expenditure:
� Energy audit resulting in savings in energy.
� Leak detection resulting either in connections or in the tariff (or) maintaining the same
supply and achieving a reduction in energy cost.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 155
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
� Privatizing the MSW collection and identifying a BoT operator for eliminating,
composting etc. items for revenue can be identified.
� Laying of cement concrete road/ fly ash and savings on maintenance cost resulting in
increasing operating surplus.
� Water recycling/ reuse.
� Rejuvenation of tanks and reduction of cost/ liters of water produced
� Privatisation and option for revenue rising.
� Options for increasing the revenues through non-traditional methods including land
development for raising revenue (not the traditional commercial complexes) and suggestions
for improvement of revenues.
(n) Initiate consultations with council and local stakeholders on the priorities; redefine priorities
(rerun FOP if required) and work with the Council to resolve on adoption of the City’s FOP and
CCP actions.
(o) Draft Report and Final Reports are proposed to be presented to the Council.
(p) Finalize Action Plan for the Town, with a resolution from the Council on the priorities and
commitment to implement revenue and management improvement measures.
(q) To prepare MoU between ULB and State Level Nodal Agency to implement UIDSSMT/ IHSDP.
(r) To assist and encourage full participation and formulate consensus within the town to arrive at an
adequate, appropriate and agreed strategy. The objective of this assistance is to ensure that the
process receives adequate and appropriate methodological and technical guidance in examining
the full range of environmental, social, economic and health issues in the city and through
communication, consultation and consensus building.
(s) To review all studies, plans and previous experience in the town, government, quasi- or non-
government, academic or private sector. This will include economic development, urban and
financial management, environmental protection, municipal service delivery, slum
improvement, social development and any other relevant initiatives or studies.
(t) To analyze findings and draw out useful lessons to inform the Action Plan. The process shall
primarily focus upon the areas of concern that emerge out of the CDP process. Indicative focus
areas are:
� Urban Economic Development
� Social Assessment
� Urban Infrastructure
� Human Resources and Institutional Issues
� Financial Management
� Urban Performance Indicator
� Environmental Management
At all stages, the consultants will have to encourage the institutionalization of the planning
methodologies and processes in the ULBs. This includes identifying and working alongside
counterparts, involving and supporting stakeholders in the working with new methodologies,
assisting the management of the process and building constructive relationships with key
stakeholders. This must be followed with proper documentation.
Annexure - 3
Minutes of the Multi-Stakeholder Workshop on CDP for Visioning Exercise for
Vikramasingapuram Municipality, Tirunelveli Region
A. Agenda of the
Meeting
: Formulation of Consensus on Vision for the Town of
Vikramasingapuram for preparation of CDP and Identification
of key areas of concern for sustainable development of the
town.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 156
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
B. Venue : AVSR Kalyana Mandapam, Vikramasingapuram
C. Date & Time : 21st September, 2007
D. Workshop
Participa
nts
: 1. Mr. Murugan, Executive Officer
2. Mr. S.P Mariyappan, Chairperson
3. Mr. K. Venkatachalam, Councilor
4. Mr. S.Rajendran, Councilor,
5. Mr. S.Papanasan, Councilor
6. Mr. G. sornamari, Councilor
7. Mrs. T. Gajalakshmi, Councilor
8. Mrs. A. Selvi, Councilor
9. Mrs. P. Chandra, Councilor.
10. Mrs. M. Meenakumari, Councilor.
11. Mrs. G. Sankari, President of Akashayaram Group.
12. Mrs. G. Uma, Secertary of Akashayaram Group
13. Mr. P. Kanagaraj, President of Vendors Association
14. Other Council Members and Citizens
E. IPE Project
Team
1. Dr. Veena Garella, Senior Urban Planner
2. Ms. Shilpi Raonka, Project Coordinator
3. Mr. Thomas Findo, Municipal Finance-Analyst
4. Ms. Kanmani, Associate Consultant
5. Mrs. Kavitha, Associate Consultant
F. Workshop Proceedings
The Multi-Stakeholder Workshop held at AVSR Kalyana Mandapam, Vikramasingapuram was
attended by the eminent citizens of the town including elected representatives, Municipality
Staff, Professors, Teachers, Government Officials etc.
The workshop started with the Welcome Address of the Chairperson of the municipality He introduced
IPE team and requested IPE officials to make a presentation before starting the discussions.
Giving an overview of CDP, IPE officials explained in detail the purpose and importance of
multi-stakeholders workshop in preparation of CDP. The workshop proceeded by seeking
valuable suggestions for improving infrastructure facilities, opinions for future development
and their proposed approach to accelerate local economic growth. Participants were also asked
to put forward their vision for the town in 30 years perspective.
Following data/ information summarized as below was provided by various town representatives during
the workshop.
1. General Vikramasingapuram Municipality was upgraded to Grade III Municipality in the year 2004.
Vikramasingapuram has 38.57 sq. kms area under its jurisprudence. It has 21 administrative
wards. The estimated present population of Vikramasingapuram is approx. 55 thousands as
against 48,309 persons as per 2001 census.
2. On Going Projects & Their Status
Following DPR have been prepared for the municipality:
• Prepared DPR for water supply scheme for the estimated cost of Rs. 1.96 crores.
• Prepared DPR for slum improvement under Integrated Housing Slum Development Programme
Scheme.
• Prepared DPR for Tourism development.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 157
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
3. Suggestions from Citizens & Officials of Vikramasingapuram Town
Following sectoral issues came forward during the discussions:
3.1 Water supply
� Water Supply scheme executed in 1972 is not adequate to meet the demand of growing population.
Andhence an additional water supply schemes should be designed and executed immediately.
� Additional requirement of OHTs, Hand pumps
� OHT has to be constructed near lower dam area which can supply water using gravity.
3.2 Under Ground Drainage � Demand for under ground drainage facilities.
3.3 Tourism � Tourism Development Fund has been rejected by the ULB and given back to the Forest
Department.
� Inadequacy of tourist infrastructure facilities includes lack of dressing room, recreation space etc.,
at Agasthiyar falls.
� Municipal boundary should be extended beyond the forest boundary and could be developed into
Zoological Park.
3.4 Industries
� Lack of industries in the area resulting in lack of employment opportunities due to the out migration
of people.
� Previously, Madura Coats had 12,000 labourers now; it has been downsized to 1,000 labourers only
due to advancement in technologies.
� Women should be empowered by providing income generating training that generates income like
embroidery work, tailoring classes, computer classes.
3.5 Roads � Road improvement works need to be taken up like all mud roads should be converted into surface
roads, roads in few wards need to be widened.
� Road leading to Trivandrum is just 40 km through Agasthiyar Falls but forest department, has
restricted the traffic beyond falls. Hence people have to travel 100 km for Trivandrum that
creates hindrance easy flow of business.
� Flood relief should be provided for citizens of Pappankulam and improve its road.
� Lack of railway network.
3.6 Recreation
� Development of Parks and Playgrounds around Agasthiyar falls which invites visitors 365 days a
year.
3.7 Sanitation and Water bodies � Water bodies should be preserved at any cost.
� Subsidy should be given for constructing individual septic tanks for low income groups.
� Construction of public conveniences for BPL population.
3.8 Streetlights � Some wards do not have proper streetlights resulting in frequent theft problems.
� Inadequacy of High mast lamps.
3.9 Social Infrastructure � Renovation of Primary Health Center.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 158
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
3.10 Others
� Lack of Electric Crematorium.
� Lack of Shopping Complexes
� Increase the Municipal Sanitary Workers.
# # #
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 159
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Annexure -3 Continued…
Minutes of the Review Committee Meeting on Inception Reports on CDP for Grade III
Municipal Towns in Madurai & Tirunelveli Regions held on 16th
October ,2007 at the
Conference Hall of Madurai Corporation.
The Review Committee Meeting on Inception Reports on CDP for Grade III Municipal Towns in
Madurai & Tirunelveli Regions was held on 16th October, 2007 at the Conference Hall of
Madurai Corporation, Madurai.
Thiru. Hitesh Kumar Makwana, I.A.S. Joint Commissioner of Municipal Administration (JCMA)
chaired the session. RDMAs of Madurai & Tirunelveli regions, Regional Executive Engineers,
Chairpersons and Executive Officers of Grade-III municipal towns, Overseers,
Representatives from DTCP, and TNUIFSL and IPE professionals attended the Review
meeting. The list of participants attended the Review Meeting is given Annexure.
Welcoming the Participants, the JCMA explained the significance of preparation of CDPs for the
municipalities as the Hon’ ble Minister for Local Administration during the Budget speech
for the year 2007-08 announced that CDPs would be prepared for all ULBs in a phased manner.
Further, the JCMA explained the key components of CDP including perspective plan,
Consultation with stake holders of development thro’ city opinion forms, regional workshop,
Demand Assessment of Infrastructure facilities for the towns, prioritization of identified
projects, 5-years capital invest programmes, funding mechanisms and a participatory
approach in preparation and implementation of CDPs and urban reforms.
Following this, IPE consultants made a presentation on the Inception report in four parts for the 10
Grade III municipal Towns (Anaiyur, Avaniapuram, Thiruparangkundram, Gudalur,
Rameshwaram and Keelakatalai Grade - III Municipal Towns in Madurai Region and
Vikramsinghapuram, Ambasamudhram, Kayalapattinam and Thiruthangal in Tirunelveli
Region) in as detailed below:
Part-I : Brief On the CDP Initiative
Part-II : City Images for 10 towns
Part III: Data Analysis –ULBs Comparative Picture
Part IV: Future Perspective & Vision
Following the presentation, the participants discussed various issues and sought clarification. The
JCMA and consultants clarified issues. The following are the record note of the discussion
during the Review Meeting:
• Regarding growth of population, the consultants should not project the population of the towns
for the plan period based on the existing trend. The urbanization trend in the region must be
taken into account.
• Stake holders’ meetings should be conducted in each municipality and regional workshop be
conducted at regional level for better participation of the stakeholders. At the regional
workshop, officers from PWD, TWAD, Highway & Rural works should be invited. It would be
better to hold the workshop under District Administration.
• The City opinion form must be collected from a cross-section of the society including NGOs,
residential association, Local Chamber of Commerce and Industry and economically weaker
section of the town.
• Study of Urban Performance Indicators should form part of the study report.
• At each stage the municipal council must be consulted and the Draft Final Report and Final
report must be approved by the Council.
• The employment opportunities, social infrastructure are to be assessed in each town not only
for the present and future population and provision of physical & social infrastructure should be
considered at the specific ULB level to meet the present and future demands.
• The revenue enhancement through new initiatives and also finding the new Remunerative
projects in these ULBs should be explored. The opportunities of optimum utilization of
municipal assets should be examined.
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 160
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
• Capacity building and Institutional Strengthening component for the ULBs need to be critically
considered in the next draft. The present strength of ULB staff and post vacant must be high
lighted in the next report. The three towns namely Anaiyur, Avaniyapuram &
Thiruparankundram report are under JNNURM. The CDPs for the three towns should take into
account the proposals contemplated in the CDP for Madurai City.
• The ULBs should take initiatives to achieve House Service Connections for 75% of the
Properties from the present level.
• The consultant may look into the cash flow statements adopted by TUFIDCO for appraising the
projects for financial evaluation.
• While formulating projects under ULBs, projects for integrated development of the region may
also be also considered.
• CDPs prepared for Grade-III municipalities by consultants, will be posed to multiple agencies
for funding various projects, and not necessarily under UIDSSMT Programme, so one should
not transfer the message to ULBs contribution being limited to 10 per cent only. In reality, the
contribution of ULB may be floating depending upon the scheme and funding agencies.
• With regard to lack of updated maps of the project towns, it was informed that GIS Maps of the
outgrowths of Madurai city like Anaiyur, Avaniyapuram Thirupparankundram has been given
to another consultant and that they are expected to start their work from 1st Nov, 2007. The
same would be available through O/o CMA after Nov 2007. For other towns, Local Planning
Area (LPA) maps could be collected from the Office of Local Planning Authorities / Regional
offices of Dept of Town & Country Planning and customised as per the requirement.
• A copy of approved CDP of Madurai was given to the consultant and IPE project team was
requested to take into consideration the proposal of CDP for Anaiyur, Avaniyapuram,
Thirupparankundram towns as they will be accessing funds primarily under JNNURM
Programme of Government of India, being the urban outgrowths of Corporation of Madurai.
• IPE was requested to recheck the authenticity of the infrastructure related data provided by
ULBs based on their past experiences.
• The project team to collect details of the land resources available with ULBs, especially the
unutilized and vacant land.
• Regarding the ULB financial positions, it was stated that the Grade-III municipalities might
show good share of revenue income but, in reality it may not be the case, as better figures
enable them to access the loan 4 times their revenue income.
• IPE project team was asked to include implementation framework, strategies for prioritized
project, institutional strengthening and capacity building measures for ULBs, and urban
reforms in the CDP.
• It was asked to collect data on existing staffing pattern and propose institutional framework in
light of 73rd
and 74th Constitutional Amendment Act. With regard to existing staffing pattern in
Grade-III municipalities copy of the past ‘Government Orders’ may be collected for reference.
• It was requested to enhance public participation in preparation of CDPs by holding intensive
Focused Group Discussions with various stakeholder groups in respective project towns.
• Rural/ Ethnic Tourism could be promoted in the towns which has good potential for the same.
• Realistic estimates could be made wherever data gaps exist in the municipalities based on
available urban standards.
• IPE project team was asked to hold a separate meeting with TNUIFSL to identify about the
projects/ proposals in the towns/taluks/ district under consideration and the projects should also
be taken into consideration, while preparation of City Investment Plan.
• The presentation made by IPE on classifications of towns on homogenous geographical
characteristics and asked to continue with matrix method for comparing various urban
indicators across the towns of same homogenous geographical characteristics.
The consultants should restrict the scope of the study as per the TOR. However they are free to indicate
the project for detailed study and preparation of DPR like
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 161
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
i. Improve Transport infrastructure, Core city improvement, main arteries, bus stand,
bus shelters, landscaping etc.
ii. Organize public-private land development entities at the town level which will operate as
real estate units for implementing development & renewal with participation of Local
community and private enterprise.
iii. Develop a system of Industrial Areas limited to medium size, clean and safe manufactures
iv. Develop Green areas, large and small as well as linear parks interconnecting neighborhoods
along selected streets, Community spaces which serve as focus of Residential areas.
v. Enhance Cultural / Heritage areas and promote tourism Develop on unique natural heritage
advantages.
The JCMA requested the DD Town & Country Planning, RDMAs and Executive Officers of the
municipalities to cooperate with the consultants in providing maps, data particularly the land
and building register and list of land and buildings owned by the local bodies and organising
the consultative meetings to make the CDP reports pragmatic and realistic.
The meeting was concluded thanking the participants for active participation.
The presentation made by IPE project team was appreciated. The inception report presented by
the Consultant is accepted with above remarks.
Sd./Hitesh Kumar Makwana, I.A.S.,
Joint Commissioner of Administration
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 162
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Annexure – 4 (Map 10 & 11)
Anne
x
u
r
e
–
4
(
M
a
p
1
2
&
1
3
)
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 163
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Annexure – 4 (Map 14)
CDP - VIKARAMSINGAPURAM FINAL REPORT
CMA, GoTN 164
INFRASTRUCTURE PROFESSIONALS ENTERPRISE (P) LTD
Annexure - 5
Note on Feasibility Fund
The term has been drawn from the “Community Planning Handbook”, authored by Nick Wates, (2000)
Earthscan Publications Ltd., and the book has been generously used in Action Planning
exercises in several countries including India.
“Feasibility Funds provide money to community organizations for paying experts to undertake
feasibility studies on possible projects. They are a highly effective way of kick starting local
initiatives by getting projects to a stage where they can attract capital funding and support”
Steps
• Fund is established by a suitable professional institute, local regional-or national organization.
Sponsors may include companies, local authorities, government departments or charities
• Scheme is advertised, community groups invited to apply for funding
• Grants are awarded. Feasibility studies undertaken. Study establishes if they are workable ideas,
best options and costs
• If projects succeed in attracting capital funding, the grant money is repaid to the organising body
- Funds as these, help communities to get involved and have a say in generating something
for themselves
- Projects undertaken : Community centres, Education facilities, Employment spaces,
Housing (new/improving) landscaping, leisure, (sports / youth clubs / cultural centres)