MINNESOTA MULTI-PURPOSE STADIUM CONSTRUCTION UPDATE Dear Neighbor, The Minnesota Sports Facilities Authority (MSFA) in partnership with the Minnesota Vikings is building a new Multi-Purpose Stadium on the site of the Metrodome. Mortenson/Thor is overseeing construction and is providing neighborhood construction updates on a regular basis. The plan for the stadium site is to close 5th street and make 6th street a wider, two way street. This letter is to inform you that 5th Street will close beginning Monday, March 30, 2015. Notification signs are posted at 5th and 11th streets to alert commuters. The detour route is 11th Avenue to 7th Street to Park Avenue (see attached map), until 6th Street has been constructed into a two way road later this year. Please be prepared to make alternate travel plans. We will continue to update the neighborhood on the construction of the Minnesota Multi-Purpose Stadium. If you have any questions, please do not hesitate to contact me directly. Regards, Lynn R. Littlejohn Director of Community Affairs Mortenson/Thor [email protected] 763.287.5649 MARCH 16, 2015

Upload: mill-city-times

Post on 23-Dec-2015

1.757 views

Category:

Documents


1 download

DESCRIPTION

Vikings Stadium Construction Update 03-16-15

TRANSCRIPT

M I N N E S O TA M U LT I - P U R P O S E S TA D I U M

CONSTRUCTION UPDATE

Dear Neighbor,

The Minnesota Sports Facilities Authority (MSFA) in partnership with the Minnesota Vikings is building a new Multi-Purpose Stadium on the site of the Metrodome. Mortenson/Thor is overseeing construction and is providing neighborhood construction updates on a regular basis.

The plan for the stadium site is to close 5th street and make 6th street a wider, two way street. This letter is to inform you that 5th Street will close beginning Monday, March 30, 2015. Notification signs are posted at 5th and 11th streets to alert commuters. The detour route is 11th Avenue to 7th Street to Park Avenue (see attached map), until 6th Street has been constructed into a two way road later this year. Please be prepared to make alternate travel plans.

We will continue to update the neighborhood on the construction of the Minnesota Multi-Purpose Stadium. If you have any questions, please do not hesitate to contact me directly.

Regards,

Lynn R. LittlejohnDirector of Community AffairsMortenson/[email protected]

MARCH 16, 2015

M I N N E S O TA M U LT I - P U R P O S E S TA D I U M

CONSTRUCTION UPDATE

DATE BY CKDNO DRAWN BY

DESIGNED BY

CHECKED BY

DATE:

PRINT NAME:

REVISION I HEREBY CERTIFY THAT THIS PLAN SHEET WAS PREPARED BY ME OR UNDER MYDIRECT SUPERVISION AND THAT I AM A DULY LICENSED PROFESSIONALENGINEER UNDER THE LAWS OF THE STATE OF MINNESOTA.

SHEETTITLE

XXXXXXX

DAN E. BOWAR

LIC. NO:XX XXX 2014 45018

6TH STREET PUBLIC INFRASTRUCTURE IMPROVEMENTS

Minneapolis

OF

NO

T FO

R C

ON

STR

UC

TIO

N

C. TA

S. PARK

D. BOWAR

4 OCT 14 SP DEBCCD-144 CITY SUBMITTAL

24 NOV 14 SP DEB1 BID DOCS DETOUR PLAN

SCALE IN FEET

2000

TC1

TC6

NOTES:1 PLACE SIGN 7 DAYS IN ADVANCE OF START OF

PROJECT AND OR CLOSURES

DETOUR ROUTE

ROAD CLOSED

ALL TRAFFIC CONTROL DEVICES AND SIGNING SHALL CONFORMTO AND BE PLACED OR CONSTRUCTED IN ACCORDANCE WITH THE"MINNESOTA MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES"(MN MUTCD) INCLUDING THE FIELD MANUAL FOR TEMPORARYTRAFFIC CONTROL ZONE LAYOUTS, DATED JANUARY, 2014.

POSTEDSPEED LIMIT

PRIOR TOWORK

STARTING

SPACING OFADVANCEWARNING

SIGNS(A)

TAPERLENGTH

(L)

SPACING OFCHANNELIZING

DEVICES(G)

BUFFERSPACE

(B)

(mph) FEET FEET FEET FEET

0 - 30 250 200 25 200

35 - 40 325 325 25 305

45 - 50 600 600 50 425

55 750 700 50 500

60 - 65 1000 800 50 650