Energy Sector Reform in the Democratic Republic of Congo Energy Sector Reform in the Democratic Republic of Congo Energy Sector Reform in the Democratic Republic of Congo Energy Sector Reform in the Democratic Republic of Congo Energy Sector Reform in the Democratic Republic of Congo Energy Sector Reform in the Democratic Republic of Congo Energy Sector Reform in the Democratic Republic of Congo Energy Sector Reform in the Democratic Republic of Congo (DRC). Inga III and Grand Inga Hydro Projects Development (DRC). Inga III and Grand Inga Hydro Projects Development (DRC). Inga III and Grand Inga Hydro Projects Development (DRC). Inga III and Grand Inga Hydro Projects Development (DRC). Inga III and Grand Inga Hydro Projects Development (DRC). Inga III and Grand Inga Hydro Projects Development (DRC). Inga III and Grand Inga Hydro Projects Development (DRC). Inga III and Grand Inga Hydro Projects Development by by by by by by by by VIKA di PANZU VIKA di PANZU VIKA di PANZU VIKA di PANZU VIKA di PANZU VIKA di PANZU VIKA di PANZU VIKA di PANZU Cabinet Director Cabinet Director Cabinet Director Cabinet Director Cabinet Director Cabinet Director Cabinet Director Cabinet Director RD Congo 1 POWER POWER POWER POWER INDABA SUMMIT CAPETOWN, SOUTH AFRICA, 14 – 16 MARS 2011 March 2011 S S oci oci é é t t é é N N ationale ationale d d E E lectricit lectricit é é REGIDESO REGIE DE DISTRIBUTION D’EAU

Upload: others

Post on 30-Jun-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Vika di Panzu - ESI Africa · VIKA di PANZU Cabinet Director RD Congo 1 POWER POWER INDABA SUMMIT CAPETOWN, SOUTH AFRICA, 14 – 16 MARS 2011 March 2011 Société Nationale d’Electricité

Energy Sector Reform in the Democratic Republic of Congo Energy Sector Reform in the Democratic Republic of Congo Energy Sector Reform in the Democratic Republic of Congo Energy Sector Reform in the Democratic Republic of Congo Energy Sector Reform in the Democratic Republic of Congo Energy Sector Reform in the Democratic Republic of Congo Energy Sector Reform in the Democratic Republic of Congo Energy Sector Reform in the Democratic Republic of Congo

(DRC). Inga III and Grand Inga Hydro Projects Development(DRC). Inga III and Grand Inga Hydro Projects Development(DRC). Inga III and Grand Inga Hydro Projects Development(DRC). Inga III and Grand Inga Hydro Projects Development(DRC). Inga III and Grand Inga Hydro Projects Development(DRC). Inga III and Grand Inga Hydro Projects Development(DRC). Inga III and Grand Inga Hydro Projects Development(DRC). Inga III and Grand Inga Hydro Projects Development

bybybybybybybyby

VIKA di PANZUVIKA di PANZUVIKA di PANZUVIKA di PANZUVIKA di PANZUVIKA di PANZUVIKA di PANZUVIKA di PANZUCabinet DirectorCabinet DirectorCabinet DirectorCabinet DirectorCabinet DirectorCabinet DirectorCabinet DirectorCabinet Director

RD Congo 1

POWER POWER POWER POWER INDABA SUMMITCAPETOWN, SOUTH AFRICA, 14 – 16 MARS 2011

March 2011

SSociociééttéé

NNationaleationale

dd’’EElectricitlectricitéé

REGIDESO

REGIE DE

DISTRIBUTION

D’EAU

Page 2: Vika di Panzu - ESI Africa · VIKA di PANZU Cabinet Director RD Congo 1 POWER POWER INDABA SUMMIT CAPETOWN, SOUTH AFRICA, 14 – 16 MARS 2011 March 2011 Société Nationale d’Electricité

1. D R Congo backgrounda) D R Congo energy potential

b) Electricity and Water Access levels

c) Challenges and constraints

2. Reform of the Energy Sectora) Reform of the institutional framework

b) Reform of the public utilities SNEL(power) and REGIDESO(water)

3. Inga III and Grand Inga projects developmenta) The Inga hydro site

b) Inga site development

c) Inga III hydro project

d) Grand Inga hydro project

4. Conclusion- opportunities for investors

RD Congo 2

Page 3: Vika di Panzu - ESI Africa · VIKA di PANZU Cabinet Director RD Congo 1 POWER POWER INDABA SUMMIT CAPETOWN, SOUTH AFRICA, 14 – 16 MARS 2011 March 2011 Société Nationale d’Electricité

•Geographical position: located between Geographical position: located between Geographical position: located between Geographical position: located between longitudes 5longitudes 5longitudes 5longitudes 5°°°°20202020’’’’ north and 13north and 13north and 13north and 13°°°°27272727’’’’ southsouthsouthsouth•Area: 2 345 441 sq kmArea: 2 345 441 sq kmArea: 2 345 441 sq kmArea: 2 345 441 sq km• Country Organisation: 11Provinces Country Organisation: 11Provinces Country Organisation: 11Provinces Country Organisation: 11Provinces •Hydroelectric potential: 100 000 MW Hydroelectric potential: 100 000 MW Hydroelectric potential: 100 000 MW Hydroelectric potential: 100 000 MW (with 44 000 MW located at Inga)(with 44 000 MW located at Inga)(with 44 000 MW located at Inga)(with 44 000 MW located at Inga)•Post conflict countryPost conflict countryPost conflict countryPost conflict country

•Population: 72 millions peoplePopulation: 72 millions peoplePopulation: 72 millions peoplePopulation: 72 millions people• Population growth rate: 3 %Population growth rate: 3 %Population growth rate: 3 %Population growth rate: 3 %• Abundant water ressources( on and Abundant water ressources( on and Abundant water ressources( on and Abundant water ressources( on and under ground)under ground)under ground)under ground)

RD Congo 3

Page 4: Vika di Panzu - ESI Africa · VIKA di PANZU Cabinet Director RD Congo 1 POWER POWER INDABA SUMMIT CAPETOWN, SOUTH AFRICA, 14 – 16 MARS 2011 March 2011 Société Nationale d’Electricité

RD Congo 4

Hydro : 70 MW

Eolien : <5 m/sSolaire : 5,6 kWh/m2 j

Hydro : 100 MW

Eolien : <5 m/sSolaire : 5,5 kWh/m2 j

Hydro : 64.000 MW

Eolien : <5 m/sSolaire : 4,9 kWh/m2 j

Hydro : 75 MW

Eolien : <5,6 m/s

Solaire : 5 à 6 kWh/m2 j

Hydro : 210 MW

Eolien : 5 à 5,4 m/s

Solaire : 5,1 kWh/m2 j

Hydro : 1.600 MW

Eolien : 5 à 6 m/s

Solaire : 5,6 kWh/m2 j

Hydro : 1.050 MW

Eolien : <5 m/sSolaire : 4,9 kWh/m2 j

Hydro : 100 MW

Eolien : <5 m/sSolaire : 4,9 kWh/m2 j

Hydro : 300 MW

Eolien : <5 m/sSolaire : 4,9 kWh/m2 j

Hydro : 3.000 MW

Eolien : <5 m/s

Solaire : 5,5 kWh/m2 j

Superficie : 2.345.441 km2

Population : 72 millions habitants

Taux de croissance population : 3,0%<5 m/s

100.000 MW hydropower potential, 44 000 MW at Inga site. 56 000 MW 44 000 MW at Inga site. 56 000 MW

throughout the countrythroughout the country. Renewable energies include: solar, biomass, wind, . Renewable energies include: solar, biomass, wind,

methane gas, geothermal. Installed hydro capacity: 2 498,45 MW methane gas, geothermal. Installed hydro capacity: 2 498,45 MW (2,5% of the (2,5% of the country potential). Abundant water ressources.country potential). Abundant water ressources.

Page 5: Vika di Panzu - ESI Africa · VIKA di PANZU Cabinet Director RD Congo 1 POWER POWER INDABA SUMMIT CAPETOWN, SOUTH AFRICA, 14 – 16 MARS 2011 March 2011 Société Nationale d’Electricité

Capacity Capacity Capacity Capacity range in MWrange in MWrange in MWrange in MW

Number of Number of Number of Number of sitessitessitessites

Total capacity Total capacity Total capacity Total capacity in MWin MWin MWin MW

> 10 MW 62 69 304, 90

Between 1 and 9 MW

83 246, 88

Between 0,5 and 1 MW

70 29,12

Total 215 69 580,90

RD Congo 5

Page 6: Vika di Panzu - ESI Africa · VIKA di PANZU Cabinet Director RD Congo 1 POWER POWER INDABA SUMMIT CAPETOWN, SOUTH AFRICA, 14 – 16 MARS 2011 March 2011 Société Nationale d’Electricité

6

PROVINCESPROVINCESPOPULATIONPOPULATION Electricity Electricity

Access in %Access in %

11 BANDUNDUBANDUNDU 8 135 0008 135 000 0,5030,503

22 BASBAS--CONGOCONGO 4 684 0004 684 000 12,2412,24

33 EQUATEUREQUATEUR 7 401 0007 401 000 0,830,83

44 KASAI OCCIDENTALKASAI OCCIDENTAL 5 215 0005 215 000 0,480,48

55 KASAI ORIENTALKASAI ORIENTAL 6 448 0006 448 000 0,670,67

66 KATANGAKATANGA 10 834 000 10 834 000 5,645,64

77 KINSHASAKINSHASA 8 683 0008 683 000 51,9251,92

88 MANIEMAMANIEMA 1 970 0001 970 000 1,431,43

99 NORD KIVUNORD KIVU5 621 000 5 621 000 3,973,97

1010 ORIENTALEORIENTALE 7 939 0007 939 000 3,553,55

1111 SUD KIVUSUD KIVU 4 874 0004 874 000 10,1410,14

Average electrification rate Average electrification rate 71 804 00071 804 000 9,439,43

Page 7: Vika di Panzu - ESI Africa · VIKA di PANZU Cabinet Director RD Congo 1 POWER POWER INDABA SUMMIT CAPETOWN, SOUTH AFRICA, 14 – 16 MARS 2011 March 2011 Société Nationale d’Electricité

CONSTRAINTS� Poor electricity(9%) and water access(24%) rate� Imbalance in energy development among provinces� No studies available for identified projects� No funding available for projects development� Poor funds absorption and mobilization� Institutional framework unable to attract international investors

(The project of Electricity Act that should improve electricity sector environment has been tabled to Parliament, and very soon for Water)

CHALLENGES� Improve electricity access from 9% to 19% in 2015, 33% in 2020 Improve electricity access from 9% to 19% in 2015, 33% in 2020 Improve electricity access from 9% to 19% in 2015, 33% in 2020 Improve electricity access from 9% to 19% in 2015, 33% in 2020

and 60% in 2025;for water access from 24% to 34% in 2015,50% in and 60% in 2025;for water access from 24% to 34% in 2015,50% in and 60% in 2025;for water access from 24% to 34% in 2015,50% in and 60% in 2025;for water access from 24% to 34% in 2015,50% in 2020 2020 2020 2020

� Need to mobilise funding for electricity as follows:� 6,5 billion USD in 2015(1,5 billion USD for Water) ;� 12 billion USD in 2020 ;� 20 billion USD in 2025.

RD Congo 7

Page 8: Vika di Panzu - ESI Africa · VIKA di PANZU Cabinet Director RD Congo 1 POWER POWER INDABA SUMMIT CAPETOWN, SOUTH AFRICA, 14 – 16 MARS 2011 March 2011 Société Nationale d’Electricité

� Objective Objective Objective Objective : Improve the sector management and attract private investments by offering an attractive and secure institutional and legal framework.

� Current legal frameworkCurrent legal frameworkCurrent legal frameworkCurrent legal framework: liberalized sector lacking updated documentation

� Current institutional framework: • (1) Ministry of Energy, • (2) Public Power utility SNEL managing 95% of the country

electricity infrastructure;Public Water utility REGIDESO. • Independent Power Producers: 2 private companies: EDC

(Electricite du Congo, in generation and distribution) and Hydroforce (in generation and distribution)

• An independent Transmission Operator: SAF Energy

RD Congo 8

Page 9: Vika di Panzu - ESI Africa · VIKA di PANZU Cabinet Director RD Congo 1 POWER POWER INDABA SUMMIT CAPETOWN, SOUTH AFRICA, 14 – 16 MARS 2011 March 2011 Société Nationale d’Electricité

� Electricity Act Electricity Act Electricity Act Electricity Act � Adopted by the Government and submitted to

Parliament for approval before promulgation by the DRC Head of State

� Electricity Act contentElectricity Act contentElectricity Act contentElectricity Act content: : : : � An institutional framework includes the Ministry of

Energy, an Independant Regulator, a National Electrification Agency (mostly for rural electrification) and a National Electrification Fund.

RD Congo 9

Page 10: Vika di Panzu - ESI Africa · VIKA di PANZU Cabinet Director RD Congo 1 POWER POWER INDABA SUMMIT CAPETOWN, SOUTH AFRICA, 14 – 16 MARS 2011 March 2011 Société Nationale d’Electricité

� Legal documents for business activities:

• Concession(transmission and distribution)

• license(generation with capacity >1000 kW and/or power export),

• authorization (by provincial authorities, with capacity between 60 kW and 1000 kW),

• Declaration (generation capacity ≤ 60 kW)

• liberty ( electricity network in private concession)

RD Congo 10

Page 11: Vika di Panzu - ESI Africa · VIKA di PANZU Cabinet Director RD Congo 1 POWER POWER INDABA SUMMIT CAPETOWN, SOUTH AFRICA, 14 – 16 MARS 2011 March 2011 Société Nationale d’Electricité

� Legal aspect of Infrastructure:

� Private ownership of generation infrastructure is allowed with transfer of the ownership to the Congo government after the contract period.

RD Congo 11

Page 12: Vika di Panzu - ESI Africa · VIKA di PANZU Cabinet Director RD Congo 1 POWER POWER INDABA SUMMIT CAPETOWN, SOUTH AFRICA, 14 – 16 MARS 2011 March 2011 Société Nationale d’Electricité

� SNEL has been commercialised

� With capital of 3.1 billion USD. The legal documentation of the new company was published in the December 2010 issue of the Official Gazette.

� Performance contract with independant audit to revue performance indicators every 3 months during the company stabilisation phase.

� Unblundling along generation, transmission and distribution might follow in the long run.

� Successful PPP experience with private investors, namely mining operators who provide funding for projects and are paid back through a portion of their electricity bills, according to specific agreements.

RD Congo 12

Page 13: Vika di Panzu - ESI Africa · VIKA di PANZU Cabinet Director RD Congo 1 POWER POWER INDABA SUMMIT CAPETOWN, SOUTH AFRICA, 14 – 16 MARS 2011 March 2011 Société Nationale d’Electricité

RD Congo 13

a) The Inga site

Page 14: Vika di Panzu - ESI Africa · VIKA di PANZU Cabinet Director RD Congo 1 POWER POWER INDABA SUMMIT CAPETOWN, SOUTH AFRICA, 14 – 16 MARS 2011 March 2011 Société Nationale d’Electricité

R D Congo 14

Congo RiverCongo RiverCongo RiverCongo River:

� 42 000 m3/s average flow

� Exceptionally :

~ 95 000 m3/s

InInInInstalled capacitystalled capacitystalled capacitystalled capacity::::

� Inga IInga IInga IInga I: 351 MW (1972)

� IngaIngaIngaInga II:II:II:II:1424 MW (1982)

� Inga III: Inga III: Inga III: Inga III: ~ 3500 à 4 320 MW

(project)

� Grand Inga Grand Inga Grand Inga Grand Inga ~ 39 000 MW

(project)

Page 15: Vika di Panzu - ESI Africa · VIKA di PANZU Cabinet Director RD Congo 1 POWER POWER INDABA SUMMIT CAPETOWN, SOUTH AFRICA, 14 – 16 MARS 2011 March 2011 Société Nationale d’Electricité

� ObjectivesObjectivesObjectivesObjectives: (1) Reduce the country energy deficit (in Kinshasa and in the mining industry in Katanga Province), supply BHP BILLITON aluminum smelter and (2) export excess capacity to Southern African countries.

� Project approved in Kinshasa in June 2009

� Steering Committee in place since September 2010.

Project to develop through PPP arrangements

� Invitation to tender for the selection of a developer launched in nov-dec 2010 (for more information please visit

www.cate.cd and www.energie.gov.cd )

� Selection process of a developer ongoing.

RD Congo 15

Page 16: Vika di Panzu - ESI Africa · VIKA di PANZU Cabinet Director RD Congo 1 POWER POWER INDABA SUMMIT CAPETOWN, SOUTH AFRICA, 14 – 16 MARS 2011 March 2011 Société Nationale d’Electricité

� Objective: Reduce the country energy deficit and export of excess of capacity to African Power Pools along the following axis: North, Centre-West, South-West and South-East.

� PPP Project

� Global study of the Inga site development and associated transmission lines recently launched in Kinshasa on March 9, 2011. Study funded by African Development Bank.Grant of 15 millions USD

� Study to be conducted in 17 months by Consultants EDF (France) and RSW Intl (Canada).

RD Congo 16

Page 17: Vika di Panzu - ESI Africa · VIKA di PANZU Cabinet Director RD Congo 1 POWER POWER INDABA SUMMIT CAPETOWN, SOUTH AFRICA, 14 – 16 MARS 2011 March 2011 Société Nationale d’Electricité

17R D Congo

Page 18: Vika di Panzu - ESI Africa · VIKA di PANZU Cabinet Director RD Congo 1 POWER POWER INDABA SUMMIT CAPETOWN, SOUTH AFRICA, 14 – 16 MARS 2011 March 2011 Société Nationale d’Electricité

RD Congo 18

DRC Egypt: 5 300 km

Alternative route RDC - Egypt

DRC – Zambia- RSA : 3 676 km

DRC –Angola – Namibia – RSA : 2 734 km

DRC - Nigeria: 1 400 km

LEGEND

Existing

Project

Interconnection Projects

Conversion stations

CO

NG

O

LIBYEALGERIE

MAROC TU

NIS

IE

NIGERMALI

MAURITANIE

SAH

ARA O

cc.

COTED’IVOIRE

GUINEE

GH

AN

A

TO

GO

BE

NIN

SENEGALGAMBIE

SIERRA LEONE LIBERIA

BURKINAFASO

GUINEE EQU.

LESOTHO

SWAZILAND

MO

ZAM

BIQUE

MA

DA

GA

SC

AR

MA

LA

WI

TANZANIA

KENYA

OU

GAN

DA

R.

B.

SOM

ALIE

ETHIOPIE

DJIBOUTI

ERITREE

GUINEE-BISSAU

COMORES

SAO TOME &PRINCIPE

TCHADSOUDAN

RCA

NIGERIA

ANGOLA

AFRIQUE DU SUD

BOTSWANA

INGAINGAINGAINGA

EGYPTE

CAMEROUN

GABON

NAMIBIE

ZIMBABWE

ZAMBIE

REP. DEM. CONGO

Page 19: Vika di Panzu - ESI Africa · VIKA di PANZU Cabinet Director RD Congo 1 POWER POWER INDABA SUMMIT CAPETOWN, SOUTH AFRICA, 14 – 16 MARS 2011 March 2011 Société Nationale d’Electricité

� Investors around the world are kindly invited to participate to the development of the Congo hydro resources including the Inga site, with the following advantages:

� Clean, abundant, low cost and environmentally friendly energy

� An important electricity market in Congo and other African countries with growing electricity needs. A cheaper alternative to very expensive generation options.

� A legal and institutional framework that will protect your investment.

� Profit expected as generation cost is very low at Inga (+/- 2 Usc/ kWh)

� A more and more peaceful environment within growing economic stability.

� Improved business climate as Congo has joined the OHADA treaty.

RD Congo 19

Page 20: Vika di Panzu - ESI Africa · VIKA di PANZU Cabinet Director RD Congo 1 POWER POWER INDABA SUMMIT CAPETOWN, SOUTH AFRICA, 14 – 16 MARS 2011 March 2011 Société Nationale d’Electricité

Inga = Affordable Answer to Energy Deficit in Africa.

RD Congo 20

Page 21: Vika di Panzu - ESI Africa · VIKA di PANZU Cabinet Director RD Congo 1 POWER POWER INDABA SUMMIT CAPETOWN, SOUTH AFRICA, 14 – 16 MARS 2011 March 2011 Société Nationale d’Electricité

THANK YOU

RD Congo 21