TRANSCRIPT
China: HCFC Phase-out Project
Procurement Plan (P115561)
June 9, 2015
I. General
1. Bank’s approval Date of the procurement Plan [Original March 7, 2012; Revision 1: December 20, 2012; Revision 2: April 18, 2013; Revision 3: September 29, 2013; Revision 4: October 24, 2013; Revision 5: January 24, 2014; Revision 6: December 15, 2014; Revision 7: January 12, 2015; Revision 8: June 9, 2015]
2. Date of General Procurement Notice: August 9, 2013 (update) 3. Period covered by this procurement plan: 2012-2015
II. Goods, Works and Non-Consulting Services
1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement:
Thresholds for Procurement Methods and Bank Prior Review
Expenditure Category
Contract Value (US$) Procurement Method Bank Prior Review
Goods
>=10 million ICB All ICB contracts<10 million NCB First NCB contracts irrespective of
value and all contracts >= US$ 3 million<500k Shopping NoneNA DC All DC contracts
Works
>=40 million ICB All ICB contracts<40 million NCB First NCB contracts irrespective of
value and all contracts >= US$ 15 million
<500k Shopping NoneNA DC All DC contracts
Notes: ICB – International Competitive BiddingNCB – National Competitive BiddingDC – Direct ContractingNA – Not Applicable
2. Prequalification. Bidders for _______shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines: Not applicable.
3. Proposed Procedures for CDD Components (as per paragraph. 3.19 of the Guidelines: Not applicable.
1
97907
4. Reference to (if any) Project Implementation Manual (PIM): The National Implementing Agency (FECO) has prepared a project implementation manual including a procurement management manual for the project, which has been reviewed by the Bank.
5. Any Other Special Procurement Arrangements: (i) Retroactive financing and advance contracting may be used under this project. The proposed retroactive financing is subject to the payments being made within 12 months of the signing date of the legal agreement. In case of those contracts by using retroactive financing, all the advance contracts (including prior and post review contracts) shall be subject to the Bank’s prior review; (ii) Goods, works and non-consulting services under Components 1 will be procured by the beneficiary enterprises and follow the Bank procurement guidelines. The activities to be procured by the beneficiary enterprises shall be also packaged by contracts in this procurement plan and be approved by the Bank.
6. Procurement Packages with Methods and Time Schedule
2
Goods, Works and Non-consulting Services under Components 1Procured by Beneficiary Enterprises
1 2 3 4 5 6 7 8 9 10 11 12
Ref.
No.
Name of company
Contract (Description)
Date of Contract Signing
EstimatedCost (US Dollars)
Procurement
Method
Prequalification
(yes/no)
Domestic Preferenc
e(yes/no)
Reviewby
Bank(Prior / Post)
ExpectedBid-Opening
Date
Actual Contract
ValueContract Duration
PU-1
Qingdao CIMC Reefer
Container Manufacture
Co., Ltd.
Storage system and tanks
27 February
2014119,672 Shopping no no Post December
2013¥730,000$119,672
12 months
PU-2 Pre-mix system
February 2014 609,934 Shopping no no Post January 2014
¥3,180,000$521,311
12 months
PU-3
High pressure foam machines (14 units)
16 April 2014 3,645,659 ICB no no Prior March 2014 $3,645,659 12
monthsPU-4 Safety system 16 June
2014 400,000 Shopping no no Post May 2014 ¥2,432,000$398,688
6 months
PU-5
Qingdao CIMC Special
Reefer Co., Ltd.
Storage system and tanks
27 February
2014119,672 Shopping no no Post December
2013¥730,000$119,672
6 months
PU-6 Pre-mix system February
2014 609,934 Shopping no no Post January 2014 ¥3,180,000$521,311
6 months
PU-7
High pressure foam machines (14 units)
16 April 2014 1,414,566 ICB no no Prior March 2014 $1,414,566 6
monthsPU-8
Safety system and Nitrogen equipment
16 June 2014 386,230 Shopping no no Post May 2014 ¥2,356,000
$386,2306
monthsPU-9
Guangdong Xingxing
Refrigeration Equipment
Co., Ltd
Two High pressure foam machines (H22-
100)
30 December
2013241,000 Shopping no no Post November
2013¥2,260,000
$370,4929
months
PU-10
Three high pressure foam machines (2
units of H11-100 and a H1-40)
25 March 2014 291,478 Shopping no no Post December
2013¥1,790,000
$293,442 9 months
PU-11 Pre-mix system 6 March
2014 85,830 Shopping no no Post December 2013
¥520,000$85,246
9 months
PU-12
Storage system and tanks
25 December
2013138,300 Shopping no no Post November
2013¥858,000$140,656 9
monthsPU-13
Safety and ventilation system
13 March 2014 65,000 Shopping no no Post December
2013¥426,600
$69,8369
months3
PU-14
Guangzhou Suiling
Electrical Co., Ltd
Three high pressure foam machines
May 27th
2013382,800 Shopping no no Post May 6th 2013 ¥2,430,000
$398,3616
monthsPU-15
Storage system and tanks
June 6th
2013 87,100 Shopping no no Post May 6th2013
¥550,000$90,164
6 months
PU-16
Safety and ventilation system
June 6th
2013 329,153 Shopping no no Post May 6th 2013¥1,970,000
$322,951 6 months
PU-17
Retrofit three existing foam machines
May 27th
201379,000 Shopping no no Post May 6th 2013 ¥505,000
$82,7876
monthsPU-18
Jiangsu Gelin Electric Co.
Ltd.,
Two Hp-100 high pressure foam
machines
Aug 18th
2013 376500 Shopping no no Post August 2013¥2,250,000
$368,85210
months
PU-19
Five high pressure foam machines ( 4
units of KL-100H and a KL-40H)
Sep 30th
2013 380500 Shopping no no Post September 2013
¥2,420,000$396,721 10
months
PU-20
Safety, storage and ventilation system
Aug 31st
2013110000 Shopping no no Post August 2013 ¥820,000
$134,4269
months
PU-21
Hangzhou Kaili
Stainless Steel Kitchen
Equipment Co., Ltd
Procure 2 units of H100 and a H180
foam machines and retrofit a H100C foam
machines
July 16th
2013 346500 Shopping no no Post July 5th 2013
¥2,150,000$352,459 9
months
PU-22
Storage system and tanks
10 January 2014 71500 Shopping no no Post January 2014 ¥457,600
$75,0169
monthsPU-23
Safety and ventilation system
17 April 2014 100450 Shopping no no Post April 2014 ¥658,000
$107,8699
months
PU-24
Shandong Hongtai
Electrical Appliance
Co.,Ltd
Procure three high pressure foam
machines and retrofit two foam machines
June 16th
2013 382,000 Shopping no no Post June 4th 2013
¥2,350,000$385,246
6 months
PU-25
Pre-mix, safety, ventilation and
Storage systems
June 16th
2013 305,000 Shopping no no Post June 4th 2013¥
1,980,000$324,590
6 months
PU-26
Retrofit the foam production lines and
foam moulds
July 8th
2013 220,000 Shopping no no Post June 18th 2013
¥1,310,000$214,754
6 months
PU-27
Zhejiang Debao
Electrical Appliance
Co.,Ltd
A HP100 foam machine
April 28th 2013
120,000 Shopping no no Post March 26th 2013
¥755,000$123,770
5 months
PU-28
Retrofit 4 foam machines and procure
a storage system
Aug 3rd
2013 163,000 Shopping no no Post July 8th 2013¥1,028,000
$168,52510
monthsPU- Retrofit production 9 January 181,858 Shopping no no Post 18 November ¥1,253,000 10
4
29lines and procure
safety, and ventilation systems
20142013
$205,410months
PU-30 Zhejiang
Huamei Manufacture
Electric Appliances
Co.,Ltd
Three high pressure foam machines ( a
HP150 and 2 units of HP40)
July 10th
2013 326,000 Shopping no no Post May 23th2013
¥2,021,200$331,344 8
months
PU-31
Three high pressure foam machines
( HP100)
Aug 17th
2013 362,000 Shopping no no Post July 30th
2013¥2,253,000
$369,344 6 months
PU-32
Retrofit 4 foam machines and procure
supply system
July 10th
2013 226,300 Shopping no no Post May 23th
2013¥1,407,000
$230,656 10 months
PU-33
Shanghai CIMC Reefer
Containers Manufacture
Co., Ltd.and
Taicang CIMC reefer
logistics equipment Co., Ltd.
Pre-mix system28
February 2014
360,000 Shopping no no Post January 2014¥3,180,000
$521,31112
monthsPU-34 ventilation system 190,000 Shopping no no Post August 2014 ¥1,845,000
$302,45912
monthsPU-35
High pressure foam machines (11 units)
16 April 2014 3,670,000 ICB no no Prior March 2014 $2,834,375 12
monthsPU-36
Safety system25 July 2014
320,000 Shopping no no Post May 2014¥2,168,000
$355,410 12 months
PU-43
Yindu Kitchen
Equipment Co.,Ltd
High pressure foam machines (2 units)
25 November
2013227,900 Shopping no no Post August 2013
¥1,398,100$229,197 12
monthsPU-44 Retrofitting 4 foam
machines 25
November 2013
254,000 Shopping no no Post August 2013¥1,558,200
$255,44312
months
PU-45
Safety, ventilation and nitrogen system and
supply system
9 June 2014
363,300 Shopping no no Post 30 May2014
¥2,222,67
1$356,42
6
12 months
PU-46
Retrofitting production lines
29 December
2013113,200 Shopping no no Post May
2013¥692,557.6
$113,53412
monthsPU-47
Zhejiang Iceshare
Refrigeration Appliance Co., Ltd
High pressure foam machines (3 units)
21 January 2014 244,780 Shopping no no Post October 2013 ¥1,740,000
$285,2469
monthsPU-48
Raw material supply system
21 January 2014 72,600 Shopping no no Post October 2013 ¥390,000
$63,9349
monthsPU-49
Retrofit the foam moulds
27 February
20,000 Shopping no no Post December 2013
¥245,000 7 months
5
2014 $40,164PU-50
Safety and ventilation system
6 February 2014 100,000 Shopping no no Post October 2013 ¥520,000
$85,2467
monthsPU-51
Jiaxing Zhongyi Electric
Appliance Co., Ltd.
CP based foam machines (2 units)
13 June 2014 350,000 Shopping no no Post August 2013 $349,700 8
monthsPU-52
Retrofitting foam machine (ED02-05)
13 June 2014 65,000 Shopping no no Post September
2013$64,900 8
monthsPU-53
Storage and feeding system for MDI and CP
based polyol
10 June 2014 50,000 Shopping no no Post April 2014
¥380,000
$62,295 8
monthsPU-54 Safety and ventilation
system10 June 2014 253,258 Shopping no no Post April 2014
¥1,450,000$237,705 8
monthsPU-55
Storage tank, nitrogen system, pipes and other modifications
10 June 2014 66,400 Shopping no no Post April 2014
¥359,000$58,852 8
monthsPU-56 Zhejiang
Hailishi Electrical Appliance Co., Ltd
CP based foam machines (2 units)
13 June 2014 350,000 Shopping no no Post August 2013 $348,500 8
monthsPU-57
Storage and feeding system for MDI and CP
based Polyol
10 June 2014 45,000 Shopping no no Post April 2014
¥360,000$59,106
8 months
PU-58
Safety and ventilation system
10 June 2014 239,160 Shopping no no Post April 2014 ¥1,160,000
$190,1648
monthsPU-59
Hangzhou Chuangxin
Refrigeration Electric
Appliances Co., Ltd.
CP based foam machines (2 units)
Aug 25th
2013 200,000 Shopping no no Post July 2013¥1,187,000
$154,590 10 months
PU-60
Raw material supply system
30 April2014 41,000 Shopping no no Post June
2013¥300,000
$49,18010
monthsPU-61
Ventilation system and retrofitting production
lines and heating system
1 December
2013 146,172 Shopping no no Post July 2013¥890,000$145,902 12
months
PU-62 Safety system 30 April
2014 35,000 Shopping no no Post June2013
¥200,000$32,787
10 months
PU-63
Guangzhou Chengyun Kitchen
Refrigeration Equipments
Co.,Ltd
CP based foam machines (2 units) and
safety system
20 July2014
222,490 Shopping no no Post June2013
¥1,380,000$226,230
5 months
PU-64 Yangzhou
Tonglee CP based foam
machines (HP-2500)11
September 2014
290,000 Shopping no no Post May2013
$246,500 6 months
6
Reefer Container Co., Ltd
PU-65
CP based foam machines (HP-650)
17 October 2014 96,000 Shopping no no Post May
2013¥550,000
$90,1646
monthsPU-130
Cyclopentane tank20 October
2014 328,600 Shopping no no Post June 2014¥910,000$149,180
2 months
PU-66
Jiangsu Qiaoyi Kitchen
Equipment Co., Ltd
CP based foam machines (2 units of H100 and 2 units of
H40)
11 November
2014 370,000 Shopping no no Post September 2013
¥2,380,000$390,164 9
months
PU-67
Zhejiang Kangquan Electrical Appliance Co., Ltd
CP based foam machine (H40) and Storage and feeding system, and safety
and ventilation system
18 February
2014210,720 Shopping no no Post November
2013
Euro163,500
9 months
PU-69
Sidelong International
Electrical (China) Co.,Ltd
Retrofitting foam machine (H100) and
Safety and ventilation system
2 March 2014
86,675 Shopping no no Post May2013
¥490,000$80,328 6
months
PU-70
Solareast Solar Energy
Co., Ltd
Procurement of foam machines for plant one (H100 2 sets and H40
2 sets)
31 October 2014 383,500 Shopping no no Post March 2014
¥2,346,800$384,721 12
months
PU-71
Procurement of foam machines for plant two
( H40 4 sets)31 October
2014 373,000 Shopping no no Post October 2014
¥2,264,800$371,278
12 months
PU-72
Storage tank for polyol and MDI ( 35 M3 polyol tank, 2 sets, 35 M3 MDI
tank, 1 set)209,000 Shopping no no Post October 2014 12
months
PU-73
Retrofit existing foam machines ( H100, 3
sets)31 October
2014 181,500 Shopping no no Post March 2014¥1,086,600
$178,13112
monthsPU-74
Procurement of pre-mixing system
( capacity 40L/min, 2 sets) the transfer
pipes, 5000 meters
16 December
2014 368,000 Shopping no no Post 25 October 2014
¥2,360,000$384,790 12
months
PU-75
35 M3 Storage tank for CP, 2 sets; storage and transfer system of polyol and ISO, 2 sets
3 December
2014 399,000 Shopping no no Post 18 October 2014
¥2,180,000$355,442 12
months
PU- Safety and ventilation 16 396,000 Shopping no no Post 18 October ¥2,430,000 12
7
76 system, and equipment
modification
December 2014 2014
$396,204months
PU-77
Wuhu Midea Kitchen & Bathroom Electric
Appliances Manufacturin
g Co., Ltd.
CP storage tank and ventilation system, and nitrogen and
power system
16 June 2014 390000 Shopping no no Post February
2014¥1,795,000
$294,262 4 months
PU-78
Pre-mix machines (40kg/min) and safety
system
16 June 2014 350000 Shopping no no Post November,20
13¥210,000
$34,426 7 months
PU-79
Retrofit the existing foam machines
(ECOPLUS H100 4 sets, GMA-H100 2
sets)
December 2013
310000 Shopping no no Post December 2013
¥1,889,000$309,672
4 months
PU-80 Fire-fighting system 21 July
2014 80000 Shopping no no Post February 2014
¥89,500$14,672
3 months
PU-81
Retrofit the mould of 340mm diameter
12 June 2014 250000 Shopping no no Post June 2014 ¥1,252,000
$205,2467
monthsPU-82
Shandong Linuo-Ritter Solar Energy
Co., Ltd.
35 M3 CP storage tank and transfer
system
14 April 2014 162,800 Shopping no no Post 20 January
2015¥614,700
$99,18415
monthsPU-83
Pre-mixing system (≥36 kg/min) and retrofit the foam machines ( H100 2sets, H40 1 set)
11 November
2014 266,800 Shopping no no Post
24 October 2014
¥1,790,000$293,,501
15 months
PU-84
Retrofit the foam production lines ( 3
lines)133,500 Shopping no no Post
18 May 2015 15 months
PU-85 Safety system 125,900 Shopping no no Post 29 May 2015 15
monthsPU-86
Changzhou JingXue
Refrigeration Equipment Co., Ltd.
Procurement of High pressure machines (H100 1 set, H10 1
set)195000 Shopping no no Post
12 June 20159
months
PU-87
Procurement of High pressure machines
(H200 2 sets)330000 Shopping no no Post
2 April 2015 9 months
PU-88 Safety system 280000 Shopping no no Post July 2015 9
monthsPU-89
Retrofit the foam machines for 275000 Shopping no no Post July 2015 9
months8
continuous panel (H40 1 set and H100 1 set)
PU-90
Retrofit the foam machines for
panel(H100 2 sets) 250000 Shopping no no PostJuly 2015 9
months
PU-91
Pre-mixing system (80L/min) and 35 M3
CP storage tank280000 Shopping no no Post
July 2015 9 months
PU-92 Shenyang
Guosheng Anticorrosion
& Thermal Insulation Co., Ltd.
Procurement of foam machines (H100 1
set, H200 1 set, H300 1 set) and safety
system
810,350 ICB no no Prior July, 2015 9 months
PU-93
Fire-fighting system, power and nitrogen
system, and ventilation system
171,150 Shopping no no Post 13 February 2015
9 months
PU-94
Liaocheng Sanli
Insulation Materials Co.,
Ltd.
Procurement of foam machines ( H160 2 sets, H80 1 set, and
H20 1 set)880,000 ICB no no Prior April 2015 9
months
PU-95
Storage system for Polyol and ISO 50,000 Shopping no no Post 5 September
20149
monthsPU-96 Safety system 150,000 Shopping no no Post 5 September
20149
monthsPU-97
Duowei Joint Light Steel
Panel ( Group) Co. ,
Ltd.
Retrofit of the high pressure foam
machine392000 Shopping no no Post June 2015 10
monthsPU-98
CP storage system, ventilation system, and safety alarm
system254500 Shopping no no Post
June 20159
months
PU-99
Retrofit of polyol storage system and
other systems of foam machine
118500 Shopping no no PostJune 2015
7 months
PU-100
Modification of safety system 139000 Shopping no no Post
June 2015 4 months
PU-101
Modification of heating system 110000 Shopping no no Post
June 2015 7 months
PU-10
YantaiTonghu Procurement of foam machines ( 4 sets of
678000 ICB no no Prior October 2015 10 months
9
2 a Waterproof & Thermal Insulation
Engineering Co., Ltd.
H40)PU-103
Procurement of CP storage system 90000 Shopping no no Post
18 March 2015 10
monthsPU-104
Retrofit of foam production lines
( heating system of 5 production lines)
70160 Shopping no no PostOctober 2015
10 months
PU-105
Procurement of pre-mixing system (1set of
80Kg/min) 200000 Shopping no no Post
October 2015 10 months
PU-106
Retrofit of foam machines (1 set of
H40)40000 Shopping no no Post
October 2015 10 months
PU-107
Procurement of safety system 345000 Shopping no no Post
October 2015 10 months
PU-108
Lvyuan New Material Co.,
Ltd.
Procurement of CP and polyol storage system 140000 Shopping no no Post August 2015 6
monthsPU-109
Procurement of foam machine (2 sets of L300 and 2 sets of
H40)1,449,984 ICB no no Prior August 2015 6
months
PU-111
Safety system 191,000 Shopping no no Post August 2015 6 months
PU-112
Langfang Huayu
Innovation Technology
Co., Ltd.
CP storage system 99000 Shopping no no Post 12 May 2015 6 months
PU-113
Procurement of foam machine (1 set of
H140 with two systems)
810000 ICB no no Post28 April 2015
9 months
PU-114
Safety system 187000 Shopping no no Post12 May 2015 6
monthsPU-115
Foshan Shunde
Chencun Zhongbao
kitchen equipment
plant
Procurement of foam machine ( 1 set of
H100)
3 July 2014143754 Shopping no no Post 10 June 2014
¥910,000$149,180
12 months
PU-116
Retrofit of foam machines ( 2 sets of
H100)
3 July 201499889 Shopping no no Post
10 June 2014 ¥630,000$103,279
12 months
PU-117
Polyol storage tank 2 July 2014 21000 Shopping no no Post 10 June 2014 ¥145200$28,302
12 months
10
PU-118
Safety system2 July 2014
66557 Shopping no no Post10 June 2014 ¥431,470
$70,73312
monthsPU-119
Binzhou Tianhong Electric
Appliance Co. , Ltd
Procurement of foam machines ( 2 sets of
H100)
22 July 2014 330600 Shopping no no Post 25 June 2014
¥2,090,000$342,623
12 months
PU-120
Retrofit of foam machines ( 1 set of
H40, 2 sets of H100)
22 July 2014 144000 Shopping no no Post
25 June 2014 ¥910,000$149,180
12 months
PU-121
Safety system22 July 2014 95000 Shopping no no Post
25 June 2014 ¥600,000$98,361
9 months
PU-122
Ningbo Shuaikang
water heaters Co., Ltd.
Polyol storage system21 October
2014 41500 Shopping no no Post 19 April 2014¥254,000
$416398
monthsPU-123
Procurement of foam machine ( 1 set of
H40)
21 October2014 129400 Shopping no no Post 19 April 2014
$130,728 9 months
PU-124
Safety system21 October
2014 124200 Shopping no no Post 19 April 2014$122,293 9month
sPU-125
Shandong Sang Le Solar Energy Co.,
Ltd.
Retrofit of foam machines ( 5 sets of
H100)575000 NCB no no Post September
20158
monthsPU-126
Retrofit of foam production lines ( 3
production lines)78000 Shopping no no Post
September 2015 6
monthsPU-127
CP and polyol storage system 50000 Shopping no no Post
September 2015 6month
sPU-128
Safety system 216000 Shopping no no PostSeptember 2015 6
monthsPU-129
Jiaxing Comely Electric
Appliance Co., Ltd.
Procurement of foam machine ( 1 set of
H100), retrofit of foam machine ( 1 set of
H100), supply system and safety system
1 September
2014 286475 Shopping no no Post 18 March 2014
¥1,538,700$252,246
10 months
PU-131
Shandong INOV New
Material Co., Ltd.
Static mixer 49,180¥300,000 Shopping no no Post June 2015 2 months
PU-132
CP storage tank and transfer system
81,967¥500,000 Shopping no no Post June 2015 3 months
PU- Polyol pre-mix and mix 113,115 Shopping no no Post June 2015 2
11
133 system ¥690,000 months
PU-134
Testing equipment 59,016¥360,000 Shopping no no Post August 2015 3 months
PU-135
Shandong Lecron Energy-
Saving New Material Co.,
Ltd.
CP storage tank and stainless steel mixer
245,902¥1,500,000
Shopping no no Post August 2015 6 months
PU-136
Automatic filling machine
68,852¥420,000 Shopping no no Post August 2015 1 month
PU-137
Safety systems 37,705¥230,000 Shopping no no Post August 2015 6 months
PU-138
Shaoxing Hengfeng
Polyurethane Industry Co.,
Ltd.
CP and polyol storage and mixer
340,328¥2,076,000
Shopping no no Post August 2015 6 months
PU-139
Semi-auto filling machine
47,213¥288,000 Shopping no no Post August 2015 6 months
PU-140
Safety systems 39,344¥240,000 Shopping no no Post August 2015 6 months
PU-141
Shanghai Dongda
Polyurethane Co., Ltd.
Automatic filling system
24,590¥150,000 Shopping no no Post October 2015 3 months
PU-142
Pre-mix system 24,590¥150,000 Shopping no no Post October 2015 5 months
PU-143
Storage and mixer 132,787¥810,000 Shopping no no Post October 2015 4 months
PU-144
Instruments and alarm system
45,902¥280,000 Shopping no no Post October 2015 4 months
PU-145
Zhengzhou Guangyang Industries Co., Ltd.
Automatic filling machine
40,984¥250,000 Shopping no no Post October 2015 5 months
PU-146
CP storage tank and pre-mix system
198,361¥1,210,000
Shopping no no Post October 2015 5 months
PU-147
Nitrogen, testing and safety systems
106,557¥650,000 Shopping no no Post October 2015 5 months
12
PU-148
Guangzhou Langtang
Polyurethane Co., Ltd.
CP storage tank and pre-mix system
160,328¥978,000 Shopping no no Post 23 April 2015 6 months
PU-149
Foam machine and automatic filling
machine111,803¥682,000 Shopping no no Post 23 April 2015 3
monthsPU-150
Safety system 35,377¥215,800 Shopping no no Post 23 April 2015 9 months
PU-151
Guangdong Weber
Electrical Appliances Co., Ltd.
H40 foam machines (single head, 3 units) 368,600 Shopping no no Post January 2015 4
monthsPU-152
H40 foam machines (dual head, 2 units) 300,600 Shopping no no Post
January 2015 4 months
PU-153
High pressure foam machine retrofit 125,000 Shopping no no Post
January 2015 5 months
PU-154
CP polyol storage and transfer system and
safety system253,051 Shopping no no Post January 2015 5
monthsPU-155
Guangzhou Zhuocheng
Weiye Foam machines 394,000 Shopping no no Post 25 March
201518
monthsPU-156
CP polyol storage and transfer system 96,948 Shopping no no Post 25 March
201518
monthsPU-157
Safety systems 128,000 Shopping no no Post 25 March 2015
18 months
Total 41,454,310
13
III. Selection of Consultants
1. Prior Review Threshold and Selection Method: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants:
Thresholds for Selection Methods and Bank Prior Review
Expenditure Category
Contract Value (US$) Procurement Method Bank Prior Review
Consultant Services
>=300k QCBS, QBS Firm: prior review first contract for each selection method, irrespective of the value and all contracts >= US$ 1 millionmillion;IC: Only in exceptional cases;; and all SSS contracts≥US$20k..
<300k QCBS, QBS, CQSNA SSSNA IC
Other All terms of reference for consultant contracts, regardless of contract value, will be subject to Bank prior review
Notes: QCBS – Quality- and Cost-Based SelectionQBS – Quality-Based SelectionCQS – Selection Based on the Consultants’ QualificationsSSS – Single (or Sole) -Source SelectionIC – Individual Consultant selection procedureNA – Not Applicable
2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines.
3. Any Other Special Selection Arrangements: NA.
4. Consultancy Assignments with Selection Methods and Time Schedule
4.1 HCFC production sector
Ref. No.
Description of Assignment EstimatedCost (US Dollars)
SelectionMethod
TOR preparati
on/clearance
Review (prior/p
ost)
ExpectedProposals
SubmissionDate
Comments
Pro.-CS-1
MIS: To develop a system for tracking HCFCs phase-out and implementation of annual Work Programs and other related project activities
200,000 QBS 2015-1 Post 2016-12
Pro.-CS-2
Monitoring and supervision on safeguard management: To hire individual consultant or
100,000 IC 2014-9 Post 2016-12
14
consulting firm to provide technical supports in overseeing and monitoring safeguards management in the project that the production facilities close-down or relocation, including but not limited to: provide day-to-day consultation to the enterprise, help the enterprise to prepare the RAP and/or DDR until it is satisfactory to the World Bank, and supervise the implementation of the plans.
Pro.-CS-3
Annual Financial Audit (FY 2014): To conduct the annual financial audit by CANO to verify whether the funding received are allocated and disbursed as per the requirement of the Bank.
100,000 SSS 2015-4 Prior 2015-10
Pro.-CS-4
Technical Support for verification and monitoring: to hire individual consultants to provide the technical comments, technical appraisal and necessary assistance to the PMO during the verification and monitoring, as well as the day-to-day project management and implementation.
50,000 IC 2014-3 Post 2016-6
Pro.-CS-5
Research and study on HCFC alternatives: to conduct a socio, economic and technical investigation and assessment on the alternatives for HCFC technology, so as to provide the advices and suggestions on standard development and modification, industry development, etc.
250,000 CQS 2014-6 Post 2015-12
Total 700,000
4.2 PU foam sector
Ref. No.
Description of Assignment EstimatedCost (US Dollars)
SelectionMethod
TOR preparati
on/clearance
Review (prior/p
ost)
ExpectedProposals
SubmissionDate
Comments
CS-1 Financial appraisal : To 170,000 CQS 2012-3 Prior 2012-6 The contract was signed
15
Ref. No.
Description of Assignment EstimatedCost (US Dollars)
SelectionMethod
TOR preparati
on/clearance
Review (prior/p
ost)
ExpectedProposals
SubmissionDate
Comments
verify baseline HCFC-141b consumption and financial status of foam enterprises (30-50)
in July, 2012 and
the contract ceiling is
US$ 117,105
CS-3
Formulation and revision of safety standards: To formulate Safety management requirements for PU foam enterprises using Hydrocarbons as blowing agent
80,000 CQS 2014-11 Post 2015-2
CS-4
Formulation and revision of technical standards: To revise National standard of rigid PU foam used in reefer containers, freezers, small electric appliances
90,000 CQS 2014-10 Post 2015-8
CS-5
MIS: To develop a system for tracking HCFCs phase-out and implementation of annual Work Programs and other related project activities
90,000 CQS 2014-4 Post 2014-6
CS-6
Consultant services : To provide technical appraisal of subprojects and on-site supervision to assess the project progress and achieved milestones
30,800.18
IC (multiple contracts will be
awarded)
2012-3 Post 2012-4
The contract with four
independent consultants were signed
in July, 2012
CS-7
Implementation Support Agency (ISA-2012): to provide comprehensive day-to-day operational management support to Project Management Office on ODS phaseout activities in PU Foam sector and assistance for the implementation of PU foam sector plan and annual programs.
990,000
QBS (may be multiple
contracts)
2012-3 Prior 2012-7
The contract with ISA
(2012) was signed in
December, 2012 and
covered 37 beneficiaries
. The contract ceiling is
US$ 572,913
CS-8 Implementation Support Agency (ISA-2013): to provide comprehensive day-to-day operational management support to Project Management Office on ODS phaseout activities in PU Foam sector and
386,660 QBS 2013-3 Prior 2013-6 The contract with ISA
(2013) was signed in
September, 2013 and
covered 15 beneficiaries
. The contract
16
Ref. No.
Description of Assignment EstimatedCost (US Dollars)
SelectionMethod
TOR preparati
on/clearance
Review (prior/p
ost)
ExpectedProposals
SubmissionDate
Comments
assistance for the implementation of PU foam sector plan and annual programs.
ceiling is US$
299,464
CS-9
Baseline consumption verification : To hear the independent experts to provide the technical opinion during verification and to verify baseline HCFC-141b consumption of foam enterprises (less than 25 companies)
112,250 CQS 2013-5 Post 2013-5
The contract was signed
in June,2013 and the contract ceiling is
US$112,213,
one addendum was signed
in May 2014, the
amounts is no more
than ¥269,300
CS-10
Research on the Bans of use HCFC-141b as blowing agent in three target sub-sectors : to review the essential documents for issue the Bans , to evaluate the impact on three target sub-sectors after issuing the bans, and to proposal the issue of bans, if applicable
120,000 CQS 2014-1 Post 2014-2
The contract was signed
in July 2014, and
the amount is
US$95,000.
CS-11
On-site Disbursement Verification : To verify the project financial management and disbursement status of 31 beneficiary enterprises.
165,000 CQS 2013-11 Post 2014-1
The contract was signed in February 2014, and
the amount is US$
133,255.
CS-12
Implementation Support Agency (ISA-2014): to provide comprehensive day-to-day operational management support to Project Management Office on ODS phaseout activities in PU Foam sector and assistance for the implementation of PU foam sector plan and annual programs.
186,200Amendm
ent to CS-8
2015-4 Prior 2015-6
CS-13 Disbursement Verification : To verify the project financial
122,520 CQS 2015-1 Post 2015-3
17
Ref. No.
Description of Assignment EstimatedCost (US Dollars)
SelectionMethod
TOR preparati
on/clearance
Review (prior/p
ost)
ExpectedProposals
SubmissionDate
Comments
management and disbursement status of 29 beneficiary enterprises.
CS-14
Technical Support System: To provide technical support in the form of training, consulting and on-site guidance to enterprises
320,000 QBS 2015-5 Post 2015-6
CS-15
Local capacity building: Survey and monitor provincial level ODS and alternative use, preventing returning use of ODS
1,200,000 QBS 2015-6 Post 2015-8
CS-16
Comparison of alternative technologies in the spray sub-sector in the PU foam sector
254,950 CQS 2015-6 Post 2015-7
CS-17Research on cyclopentane application in panel production
299,500 CQS 2015-6 Post 2015-7
CS-18
Data collection and alternative evaluation for preparation of PU HPMP (Stage II)
110,000 SSS 2015-5 Prior 2015-6
CS-19 Preparation of PU HPMP (Stage II)
70,000 CQS 2015-5 Post 2015-6
TOTAL 4,793,880
Note: IC-Individual Consultant; CQS-Selection Based on Consultants’ Qualifications; QCBS-Quality and Cost-Based Selection; QBS-Quality-Based Selection.