Vietnam: Central Region UrbanEnvironmental Improvement
Project (CRUEIP)
Uzma Hoque
14 November 2011
The views expressed in this paper are the views of the author and do not necessarily reflect the views or policies of the Asian
Development Bank (ADB), or its Board of Governors, or the governments they represent. ADB does not guarantee the accuracy ofthe data included in this paper and accepts no responsibility for any consequence of their use. The countries listed in this paper donot imply any view on ADB's part as to sovereignty or independent status or necessarily conform to ADB's terminology.
-
8/3/2019 Vietnam: Central Region Urban Environmental Improvement Project (CRUEIP)
2/16
Overview of the Presentation
The CRUEIP project, objectives, genderaction plan and results
Challenges
Some key learning/ messages
-
8/3/2019 Vietnam: Central Region Urban Environmental Improvement Project (CRUEIP)
3/16
The Project
Objective: Improved urban environment in 6 towns Five Components
Gender analysis and action plan:
- Recognized womens roles in household and
community sanitation- Targets and strategies to facilitate womens
involvement.
EA: Ministry of Construction. Provincial PeoplesCommittee implement at province level.
-
8/3/2019 Vietnam: Central Region Urban Environmental Improvement Project (CRUEIP)
4/16
Gender Action Plan (GAP)
A: Awareness and Pro Poor Sanitation- VWU responsible for implementation (CMC)
- Training on environmental sanitation for men/women
- Training for (URENCO) workers
- 50% women in all training activities
- 30% women community and neighborhood groupmembers
- 75%women beneficiaries of HH sanitation program
- Participatory process for community contribution.
- Exemption consideration for FHHs
-
8/3/2019 Vietnam: Central Region Urban Environmental Improvement Project (CRUEIP)
5/16
GAP features
B. Drainage and flood protectionC. Wastewater and public sanitation
IEC targeted to men and women
Address different needs of men and women in the
design and operation and maintenance (O&M) ofwastewater and public sanitation.
D. Solid waste management
IEC to improve men and womens awareness and
practice, and payment of monthly sanitation fees. Womens concerns addressed in URENCOs
-
8/3/2019 Vietnam: Central Region Urban Environmental Improvement Project (CRUEIP)
6/16
GAP features
E. Implementation assistance and institutionalstrengthening
Gender awareness training for all staff/partners
Use of gender-sensitive indicators for implementation
and monitoring. Ensure the resettlement plan is gender responsive.
Leadership training for
female URENCO staff.
-
8/3/2019 Vietnam: Central Region Urban Environmental Improvement Project (CRUEIP)
7/16
The Project ResultsLoan Outputs Gender Equality Results
A. Awarenesson sanitation
High levels of womens participation ( 67%-90%)
75% women trained in management skills (24women and 8 men).
67% women trained in sanitation (30 womenand 15 men).
74% women trained on management and IECmethods .
12,000 students received school/communitybased training on sanitation.
90% women CMC members; participated in CBS
boards of management.
All directors of community managementcommittees were female
89% of urban motivators were women.
-
8/3/2019 Vietnam: Central Region Urban Environmental Improvement Project (CRUEIP)
8/16
The Project ResultsLoan Outputs Gender Equality Results
A. Awarenesson sanitation
Increased participation of women in decision-making at commune and ward levels.
Increased capacity of VWU in planning,management and monitoring.
More middle aged men participating in meetingsand training on sanitation.
Over 75% of credit recipients of HH sanitationimprovements were women. Women receivedloans to build toilets and septic tanks.
FHH exempted from cost recovery for O&M
-
8/3/2019 Vietnam: Central Region Urban Environmental Improvement Project (CRUEIP)
9/16
The Project ResultsLoan Outputs Gender Equality Results
B. Drainageand floodprotection
C. Wastewaterand publicsanitation
Women participated in consultations on wastewater,public sanitation and solid waste management.
VWU participated in monitoring the quality ofconstruction activities.
VWU involved in resettlement planning meetings andimplementation ensured special consideration for FHH
including extra compensation and land titles.
D. Solid wastemanagement
Gender training for ward leaders and communitymembers.
Re-design of hand-carts and garbage cans to makethem lighter for women. New technology so that
garbage cans do not require to be manually lifted bywomen garbage collectors.
Female waste pickers received gloves and protectivegear
Urban environmental company (URENCO), womengarbage collectors participated in gender, HIV and safetytraining.
-
8/3/2019 Vietnam: Central Region Urban Environmental Improvement Project (CRUEIP)
10/16
The Project Results
Loan Outputs Gender Equality Results
E.Implementationassistance and
institutionalstrengthening
Capacity of VWU increased; reinforcement ofVWUs role and profile in the community and ingovernment institutions.
URENCOs, community leaders, programmanagement unit (PMU) and CMCs trained ongender issues;
increased understanding by URENCOs,community leaders, PMUs and CMCs of genderissues in urban environmental, sanitation andhealth.
Data on womens participation collected andreported.
-
8/3/2019 Vietnam: Central Region Urban Environmental Improvement Project (CRUEIP)
11/16
Challenges
Delay and slow disbursement of funds delayedimplementation in some areas.
Increase of womens time burden- better balance
of men and women in community activities
-
8/3/2019 Vietnam: Central Region Urban Environmental Improvement Project (CRUEIP)
12/16
Key learning/ messages
Importance of gender analysis: ensuredstrategies were relevant and effective.
Quality GAP :well targeted, clearly linked to
outputs, practical for EAs and built on lessonslearnt from other WSS projects.
Targets for womens participation.
-
8/3/2019 Vietnam: Central Region Urban Environmental Improvement Project (CRUEIP)
13/16
Key learning/ messages
Capacity building ofimplementers and
ownership of GAP.
GAP updated using a
participatory approach: concrete targets,guidelines and step by step implementation plans.
Gender Specialists to supportimplementation.
-
8/3/2019 Vietnam: Central Region Urban Environmental Improvement Project (CRUEIP)
14/16
Key learning/ messages
Consistent Monitoring of the GAP: sexdisaggregated data.
GAP included as a loan covenant/assurance
-
8/3/2019 Vietnam: Central Region Urban Environmental Improvement Project (CRUEIP)
15/16
In Ha Tinh Mme Van, an elderly widow and mother of fourchildren received a loan to build a toilet and a drain was
constructed alongside her home. She received training from theWomens Union on sanitation and managing her loan.
She said the training improved her understanding of sanitationand how this contributes to good health. Her new toilet has
improved household sanitation and the drain prevents herbackyard from flooding which has improved her livingconditions. She is proud of her new toilet and her ability toborrow and successfully repay the loan.
-