victoria street transformation update 5/media/your-council/... · months while we upgrade this...

2
Artist’s impression of Volunteer Corner, at the corner of Dixon and Victoria Streets Memorial Park Alliance Please email us with your contact details so we can keep you up to date. [email protected] wellington.govt.nz/Victoria From 26 January, work will be in full swing on the Victoria Street Transformation project. We are currently clearing the three blocks south of Dixon Street in preparation for installing wider tree-lined footpaths, a new southbound cycle lane and new paved parks at Volunteer Corner and near the intersection of Vivian Street. NORTHBOUND LANE CLOSED TO THROUGH TRAFFIC FOR FIVE MONTHS The northbound through-route in Victoria Street between Ghuznee and Dixon Streets will be closed for five months while we upgrade this area. However, motorists can still turn from Ghuznee Street into this block to park at St Peter’s Carpark, Warehouse Stationery and businesses in Feltex Lane. (See map on P2.) The through-route closes from Monday 26 January and follows the earlier closure of the left turn from Vivian Street on 5 January. Motorists and cyclists, please plan ahead and use alternate routes. Victoria Street remains open to southbound traffic though lanes may narrow or close at times. Please watch out for cyclists. NEW WATERMAIN FOR EAST SIDE OF VICTORIA STREET A new watermain will upgrade the water supply system on east Victoria Street between Vivian and Ghuznee Streets. Property owners and occupiers will have their water briefly shut off at various times and will be contacted. Overnight work across the intersections will be required and is scheduled for Thursday 29 January (Ghuznee) and Wednesday 4 February (Vivian) – weather permitting (See map on P2.) Night work will be noisy at times and we will use sound barriers to minimise noise. Thank you for your patience while this work is underway. TREES AND PLANTS Most garden beds in the three blocks have now been removed to prepare for road and footpath works. Further garden bed removal in the north block takes place next week. The four elm trees will remain as the design for the project fits around them. Planting round the Volunteer Corner (Dixon Street) elm will remain until design for that urban park is finalised. Victoria Street Transformation November 2014 – June 2015 UPDATE 05 23 January 2015

Upload: others

Post on 24-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Victoria Street Transformation Update 5/media/your-council/... · months while we upgrade this area. However, motorists can still turn from Ghuznee Street into this block to park

Artist’s impression of Volunteer Corner, at

the corner of Dixon and Victoria Streets

Memorial Park Alliance

Please email us with your contact details so we can keep you up to date. [email protected]/Victoria

From 26 January, work will be in full swing on the Victoria Street Transformation project. We are currently clearing the three blocks south of Dixon Street in preparation for installing wider tree-lined footpaths, a new southbound cycle lane and new paved parks at Volunteer Corner and near the intersection of Vivian Street.

NORTHBOUND LANE CLOSED TO THROUGH TRAFFIC FOR FIVE MONTHS

The northbound through-route in Victoria Street between Ghuznee and Dixon Streets will be closed for five months while we upgrade this area.

However, motorists can still turn from Ghuznee Street into this block to park at St Peter’s Carpark, Warehouse Stationery and businesses in Feltex Lane. (See map on P2.)

The through-route closes from Monday 26 January and follows the earlier closure of the left turn from Vivian Street on 5 January.

Motorists and cyclists, please plan ahead and use alternate routes.

Victoria Street remains open to southbound traffic though lanes may narrow or close at times. Please watch out for cyclists.

NEW WATERMAIN FOR EAST SIDE OF VICTORIA STREET

A new watermain will upgrade the water supply system on east Victoria Street between Vivian and Ghuznee Streets. Property owners and occupiers will have their water briefly shut off at various times and will be contacted.

Overnight work across the intersections will be required and is scheduled for Thursday 29 January (Ghuznee) and Wednesday 4 February (Vivian) – weather permitting (See map on P2.)

Night work will be noisy at times and we will use sound barriers to minimise noise. Thank you for your patience while this work is underway.

TREES AND PLANTSMost garden beds in the three blocks have now been removed to prepare for road and footpath works. Further garden bed removal in the north block takes place next week.

The four elm trees will remain as the design for the project fits around them.

Planting round the Volunteer Corner (Dixon Street) elm will remain until design for that urban park is finalised.

Victoria Street TransformationNovember 2014 – June 2015

UPDATE 0523 January 2015

Page 2: Victoria Street Transformation Update 5/media/your-council/... · months while we upgrade this area. However, motorists can still turn from Ghuznee Street into this block to park

DIXON ST

GHUZNEE ST

VIVIAN ST

ABEL SMITH ST

WIL

LIS

ST

VIC

TORI

A S

T

KARO DR

FELTEX LANE

FELTEX LANE

Warehouse Stationery

Tommy’s Real

Estate

Crafters & Co

The Mill

Gordon Harris

Work sites – Jan–JuneWork site – starting 26 JanNorthbound lane closuresPedestrian pathStormwater drainsNew watermain

Bus Stops: May change position from time to time

Mobility parks: May change position from time to time

Vehicle access to properties: May change position from time to time

P10

OFF-STREET PARKING

OFF-STREET PARKING

OFF-STREET PARKING

OFF-STREET PARKING

OFF-STREET PARKING

23 JANUARY – 6 FEBRUARY General work hours

Mon to Fri 7.00am – 6.00pm Sat 8.00am – 2.00pmNight work will be advisedThank you for your patience while transformation works proceed.

PEDESTRIAN ACCESS TO PROPERTIES ONLY

NORTH BLOCKNorthbound lane closed to through traffic• From January 26 – June 2015• No on-street parking• Mobility parking maintained• Alternate northbound routes: Via Willis Street and Mercer Street Via Taranaki Street and Dixon StreetAccess maintained to properties• Vehicles can use the northbound lane to

St Peter’s (Care) Carpark, Warehouse Stationery and other westside properties via Feltex Lane.

CENTRAL BLOCKNorthbound lane closed to through traffic• To June 2015• No on-street parking• Access maintained to properties• Alternate northbound routes: Via Willis Street to Ghuznee Street Via Taranaki Street to Ghuznee StreetNew watermain • Installed 26 January – 6 February• East side of Victoria Street from Vivian

to Ghuznee Streets• Water shutdowns required for new

connections. Affected properties will be contacted.

• Night works when watermain installed across Vivian and Ghuznee Streets

Night works• Thursday 29 January, 7.00pm – 5.00am,

Ghuznee/Victoria Streets intersection• Wednesday 4 February, 7.00pm

– 5.00am, Vivian/Victoria Street intersection

• Weather permitting• Sound barriers used to minimise noise• One lane closed using traffic

management control.

SOUTH BLOCKNight worksStormwater drains being installed across the road.• Monday 26 January• 7.00pm – 5.00amOne lane closed using traffic management control.Sound barriers used to minimise noise.

LANE WIDTHS REDUCED; WATCH FOR CYCLISTS