VH-OJH INCIDENT

23 SEPTEMBER 1999PETER THOMAS

OJH PROJECT COORDINATOR

Page 2: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

THE FIRST DAY

• VH-OJH left the end of RWY 21L at BKK INTERNATIONAL AIRPORT on the night of 23 SEPTEMBER 1999. The A/C travelled a further 200 metres across the RWY run-off area.

• On its way the A/C collided with the RWY 03R Localiser Antenna before coming to rest in a RWL position.

Page 3: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

Localiser Antenna

pth13:

Localiser Antenna

Page 4: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

“The Day After”

pth13:

“The Day After”

Page 5: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR
Page 6: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR
Page 7: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

No.3 Pylon

pth13:

No.3 Pylon

pth13:

Note failure of Diagonal Brace “end fitting”

pth13:

Note failure of Diagonal Brace “end fitting”

Page 8: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

Golf Course Road

pth13:

Golf Course Road

Page 9: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

THE RECOVERY

• The importance of keeping the “Station Aircraft Recovery List” updated, including checking Emergency Contacts and Equipment Suppliers phone numbers.

• An assistant is required to keep notes during the initial Recovery planning period.

Page 10: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR
Page 11: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

Construction of a road to return to RWY 21L.

pth13:

Construction of a road to return to RWY 21L.

Page 12: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

Road constructed to allow unloading of aft cargo and parking of crane.

pth13:

Road constructed to allow unloading of aft cargo and parking of crane.

Page 13: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

Stabilising R/H wing to prevent A/C movement.

pth13:

Stabilising R/H wing to prevent A/C movement.

Page 14: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

Fuselage damage due to ingress of NLG Assy.

pth13:

Fuselage damage due to ingress of NLG Assy.

Page 15: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

“Classic” failure of R/H WLG.

pth13:

“Classic” failure of R/H WLG.

Page 16: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

ARRIVAL OF PARTS

• To ensure swift delivery of Parts, Materials and Tooling a Custom’s Agent must be engaged who has contacts at the HIGHEST LEVELS”. Arranging a “Custom’s Carnet” is of utmost importance to overcome “heavy” Customs Duties.

• To ensure these deliveries are completed with the utmost promptness, cooperation with all levels of the Airport Authority is required.

Page 17: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR
Page 18: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR
Page 19: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

INCIDENT SITE SCRAP

• All scrap had to be collected for documentation.

• To conform to “Customs” regulations all parts and raw materials movements had to be thoroughly documented and presented to the Authorities for approval so as not to incur large Customs duties. This procedure was also required for all scrap material.

Page 20: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR
Page 21: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

JANUARY 23 2000REPAIR BEGINS

• The Boeing Team begins the repair by first stabilising and “jigging” the Aircraft to prevent fuselage movement during the removal of the lower sections of Sections41 and 42.

Page 22: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

A/C was “tied” to the tail jack and the jack was cabled to the ground. Jack point was “drilled” to allow fitment of a rod between the jack adaptor and the jack point.

pth13:

A/C was “tied” to the tail jack and the jack was cabled to the ground. Jack point was “drilled” to allow fitment of a rod between the jack adaptor and the jack point.

Page 23: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

Installation of “Tower Jacks”

pth13:

Installation of “Tower Jacks”

Page 24: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

Fuselage “stabilisation” complete.

pth13:

Fuselage “stabilisation” complete.

Page 25: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

AIRCRAFT REPAIR BEGINS

• Removal of Section 41 and 42 begins.

• Replacement of the damaged “window-belt” has to be done before removal of the lower Section 41. This is to ensure the alignment of the Aircraft is maintained.

Page 26: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

“Window belt” repair.

pth13:

“Window belt” repair.

Page 27: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

No.3 Pylon repair.

pth13:

No.3 Pylon repair.

Page 28: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

“Wiring pull-back”

pth13:

“Wiring pull-back”

Page 29: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

“Wiring pull-back” completed.

pth13:

“Wiring pull-back” completed.

Page 30: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

Sections 41/42 removed.

pth13:

Sections 41/42 removed.

Page 31: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

“Aligning Sect.41.

pth13:

“Aligning Sect.41.

Page 32: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

Installation of Sect.42 “plug”.

pth13:

Installation of Sect.42 “plug”.

Page 33: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

“Final Alignment”

pth13:

“Final Alignment”

Page 34: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR
Page 35: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

Skin “finish” after repair.

pth13:

Skin “finish” after repair.

Page 36: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

STORES PERSONNEL

• A team of Stores Personnel was required to acquit all the Parts demands and to administer a Parts store to ensure a “smooth” production flow is maintained.

• Boeing were ordering “hundreds” of parts daily from Seattle and expecting 2 days delivery at the site.

Page 37: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

Mick Gledhill

pth13:

Mick Gledhill

Page 38: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

DOCUMENTING AND CERTIFICATION

• To lessen the impact of the “cost” of the repair to QANTAS a lot of rotable parts were supplied by QANTAS. The Insurance Company will only pay “Market Price” for these parts.

• A Team of LAME’s were needed to document and certify these parts as a lot of the Parts were delivered straight from the Vendor. This included all the Landing Gear assembly’s.

Page 39: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

Mark Coffey

pth13:

Mark Coffey

Page 40: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

First Engine installed by QANTAS LAME’s

pth13:

First Engine installed by QANTAS LAME’s

Page 41: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

Zones 1 & 2 rework by QANTAS.

pth13:

Zones 1 & 2 rework by QANTAS.

Page 42: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

A “few” of the 300+ F/G repairs to the L/E.

pth13:

A “few” of the 300+ F/G repairs to the L/E.

Page 43: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR
Page 44: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

HI - BLOW TEST

• “Seats” all the rivets and frame joints.

• Exposes any fuselage skin joints leakage.

• Fuselage blown to 12.5 psid.

Page 45: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR
Page 46: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

“Hi-Blow” relief vlv.

pth13:

“Hi-Blow” relief vlv.

Page 47: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

ROLL-OUT AFTER REPAIR

• Rollout from Hangar after approx. 6 months.

• Due to publicity sensitivity the A/C had to be similar in appearance to other B744’s prior to “rollout”.

• The repaint of the repaired areas was achieved by “paint rollers”.

Page 48: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR
Page 49: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR
Page 50: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR
Page 51: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

Thorough wash before “functional checks begin”.

pth13:

Thorough wash before “functional checks begin”.

Page 52: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR
Page 53: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR
Page 54: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

Second Test Flt. Return.

pth13:

Second Test Flt. Return.

Page 55: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

Taxi-In after 2nd Test Flt.return.

pth13:

Taxi-In after 2nd Test Flt.return.

Page 56: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR
Page 57: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

AFTER A/C DEPARTURE

• A/C Departs for Paint Facility in Xiamen.

• Final Clean-up underway.

Page 58: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

Signing of “Certificate of Completion”.

pth13:

Signing of “Certificate of Completion”.

Page 59: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

Departure for repaint at Xiamen, China.

pth13:

Departure for repaint at Xiamen, China.

Page 60: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

All scrap had to be disposed of so as to not arouse “Media” interest.

pth13:

All scrap had to be disposed of so as to not arouse “Media” interest.

Page 61: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

Last shipment of scrap is loaded before returning the Hangar to Thai Airways.

pth13:

Last shipment of scrap is loaded before returning the Hangar to Thai Airways.

Page 62: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

pth13:

The crash site 6 months later. Note: the addition of landing lights.

pth13:

The crash site 6 months later. Note: the addition of landing lights.

Page 63: VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

THE END

VH-OJH RETURNED TO SERVICE AFTER REPAIR AND REPAINT

ON

8 APRIL 2000.