vermont lake champlain phosphorus tmdl phase i ... › sites › dec › files › wsm › erp ›...
TRANSCRIPT
1
Vermont Lake Champlain Phosphorus TMDL Phase I Implementation Plan
The Vermont Department of Environmental Conservation (VDEC) staff prepared the slides contained in this presentation to describe the policy commitments contained in the Lake Champlain Phosphorus TMDL Phase I Implementation Plan. The Plan was submitted to the U.S. Environmental Protection Agency on May 29, 2014. Data contained in this presentation came from a variety of sources and agencies. Some of the data are preliminary, undergoing review, and thus, are subject to possible change.
Expected Outcomes from the TMDL Phase I Plan
Summary of Phase I Plan • Plan expected to reduce
phosphorus loading by 36% over 20 years to meet State Water Quality Standards • Plan targets major source areas
using cost-effective actions 0%
20%
40%
60%
80%
100%
120%
Current Phosphorus Loads Expected Phosphorus Loads
Anticipated Improvements Over Time (Phosphorus load at Phase I completion,
as a percent of current level)
EPA, 2013
Phosphorus Sources in the Vermont Portion of the Lake Champlain Basin
3
Unpaved Roads
6%
Agricultural Lands 40%
Stream Instability
22%
Forest Lands 15%
Developed Lands Including Paved Roads
14%
Wastewater Treatment Facilities 3%
0
500
1,000
1,500
Missisquoi River Watershed
Land
Are
a (k
m2 )
4
Watershed Land Area of Land Use Categories
0.0
1.0
2.0
3.0
4.0
5.0
6.0
Missisquoi River Watershed
Phos
phor
us lo
adin
g ra
te (k
g/ha
/yr)
TMDL Plan’s Strategic Focus is based on Relative Ranking of Critical Sources of Phosphorus
(per unit of land area)
EPA, 2013 5
EPA, 2014; VTDEC, 2014 6
Relative Cost-Effectiveness of Actions by Source
Range of Annualized Cost (per kilogram of Phosphorus Reduced)
$0 $4,000 $8,000 $12,000
Agricultural Land Practices
Backroad Practices
Additional Wastewater Treatment
Developed Land Practices
$/kg
$0 $5,000 $10,000 $15,000
Agricultural Land Practices
Backroad Practices
Additional Wastewater Treatment
Developed Land Practices
7
Relative Cost-Effectiveness of Actions by Source
Annualized Cost (per kilogram of Phosphorus Removed)
Developed Land Practices ($/kg)
Agricultural Land Practices ($/kg)
Range of Cost per Kilogram
Strategic Investment
Critical Source Area Targeting Critical Source Area Study in Missisquoi Bay Basin found that program effectiveness increases 1.5 to 3 times with targeting
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
Random
Targeted
Total P Reduction
kilo
gram
/yea
r
8 LCBP, 2011
Strategic Investment
Tactical Basin Planning
• Targets priority stressors to restore and protect water quality • Informed by assessment data
Deerfield and Lower Connecticut Rivers
9
Program Area
Agricultural Programs Stormwater Management Rivers Management Wetlands Management
Lakes Management Forest Management
Lake Champlain Phosphorus TMDL Draft Phase I Implementation Plan
10
Agricultural Programs Proposed Rule Update: State Accepted Agricultural Practices (AAPs) and Technical Assistance Example: Increase buffer size and crop rotation
• Achieves 40%-80% reduction in Total Phosphorus • Estimated project cost = $6,000 (100 acres treated)
BEFORE AFTER
0%
20%
40%
60%
80%
100%
120%
Pre-Treatment Post-Treatment
Treatment Effectiveness (Phosphorus load as a percent of
pre-treatment level)
11
Corn crop showing bare soil & no buffer, increasing erosion and phosphorus loading
Hay crop & buffer reduce erosion and phosphorus delivery to streams
Agricultural Programs Proposed Rule Update: State Accepted Agricultural Practices Example: Grassed waterway to stabilize field gully • Achieves 35%-90% reduction in Total Phosphorus • Estimated project cost = $24,000 (2 acres treated)
BEFORE AFTER
0%
20%
40%
60%
80%
100%
120%
Pre-Treatment Post-Treatment
Treatment Effectiveness (Phosphorus load as a percent of
pre-treatment level)
12 Gully erosion from concentrated water Grassed waterway to prevent gully formation
Agricultural Programs
Proposed Rule Update: State Accepted Agricultural Practices Example: Livestock Exclusion and Vegetated Buffer • Achieves 40%-80% reduction in Total Phosphorus • Estimated project cost = $20,000 (fencing, stream crossing, 1 acre of buffer)
0%
20%
40%
60%
80%
100%
120%
Pre-Treatment Post-Treatment
Treatment Effectiveness (Phosphorus load as a percent of
pre-treatment level)
13
BEFORE AFTER
Uncontrolled livestock access to stream Installation of livestock fencing & buffer
Agricultural Programs
Proposed Rule Update: State Accepted Agricultural Practices Example: Vegetated buffer on Field and Roadside Ditches • Achieves 40%-80% reduction in
Total Phosphorus • Estimated project cost = $1,350 (3 acres treated)
0%
20%
40%
60%
80%
100%
120%
Pre-Treatment Post-Treatment
Treatment Effectiveness (Phosphorus load as a percent of
pre-treatment level)
14
BEFORE AFTER
Runoff draining into ditch Vegetated buffer along ditch
Agricultural Programs Technical Assistance: Nutrient Management Example: Manure Injection • Achieves 71%-94% reduction in
Total Phosphorus • Equipment price = $250,000 • Estimated project cost = $6,000 (100 acres treated)
BEFORE AFTER
15
0%
20%
40%
60%
80%
100%
120%
Pre-Treatment Post-Treatment
Treatment Effectiveness (Phosphorus load as a percent of
pre-treatment level)
Land-applied manure is subject to runoff Manure injection reduces runoff
Agricultural Programs Technical Assistance: Nutrient Management Example: Cover Cropping • Achieves 40%-90% reduction in
Total Phosphorus • Estimated project cost = $8,000 (100 acres treated)
BEFORE AFTER
16 Gully formation & runoff on bare soils Cover crop protecting soils from weathering
0%20%40%60%80%
100%120%
Pre-Treatment Post-Treatment
Treatment Effectiveness (Phosphorus load as a percent of
pre-treatment level)
Agricultural Programs
Increase Inspections Barnyard Runoff Management • Achieves 35%-70% reduction
in Total Phosphorus • Estimated project cost =
$35,000-$50,000
UNMANAGED MANAGED
17 Phosphorus-laden silage leachate discharging to stream
Silage leachate treatment
0%
20%
40%
60%
80%
100%
120%
Pre-Treatment Post-Treatment
Treatment Effectiveness (Phosphorus load as a percent of
pre-treatment level)
Agricultural Programs
Water Quality Permitting Example: Animal Waste Systems Crystal Brook, Orleans County • Replaced failed manure pit with
larger, sealed lagoon • Over 80% reduction in Phosphorus • Estimated project cost = $70,000-$150,000
0%
20%
40%
60%
80%
100%
120%
2006 2009 2010
Phosphorus in Stream (as a percent of 2006 level)
0%
20%
40%
60%
80%
100%
120%
2006 2009 2010
Stream Biological Health (as a percent of current level)
18
Improved manure storage
Agricultural Programs
Summary: Agricultural Practices Reduce Phosphorus Pollution
Con
serv
atio
n til
lage
Filte
r stri
ps
Barn
yard
runo
ff m
anag
emen
t
Nut
rient
man
agem
ent p
lan
Con
tour
stri
p cr
op
Rip
aria
n fo
rest
buf
fers
Anim
al w
aste
sys
tem
s
Cro
p ro
tata
tion
Per
cent
Red
uctio
n
0
20
40
60
80
100
Gitau, Gburek, Jarrett, 2005
19
Stormwater Management
Stormwater Runoff from Existing Developed Lands Englesby Brook, Blanchard Beach Burlington & South Burlington • Stormwater treatment achieved over 80% reduction in Phosphorus • Estimated cost for stormwater treatment for land already developed =
$30,000 per acre of impervious surface
0%
20%
40%
60%
80%
100%
120%
Pre-Treatment Post-Treatment
Effectiveness of Stormwater Treatment (Phosphorus load as a percent of pre-treatment level)
20 Expanded stormwater treatment pond
Stormwater Management
Stormwater Runoff from Existing Developed Lands Rice Brook, Sugarbush Ski Resort • Reduced annual phosphorus and
sediment concentrations by nearly 30% • Restored Water Quality Standards
0%
20%
40%
60%
80%
100%
120%
1996 1998 2000 2002 2004 2006 2008
Stream Biological Health (as a percent of 2009 levels)
21
Stormwater Treatment Pond
0%
20%
40%
60%
80%
100%
120%
Pre-Treatment Post-Treatment
Effectiveness of Stormwater Treatment (Phosphorus load as a percent of pre-treatment level)
Stormwater Management
Stormwater Runoff from Existing Developed Lands Potash Brook tributary, So. Burlington • Runoff causing water quality
degradation, stream instability • Reduced phosphorus load by 45% • Reduced sediment load by 70%
Figure 11. An actively eroding stream bank in Potash Brook Trib. 7 as it traverses the BF/OCV neighborhoods.
0%
20%
40%
60%
80%
100%
120%
Pre-Treatment Post-Treatment
Stormwater Treatment Effectiveness (phosphorus load as a percent of
pre-treatment level)
IMPACT
TREATMENT
22 Streambank erosion from stormwater runoff Stormwater treatment ponds
Stormwater Management
Stormwater Runoff - Existing Developed Lands Municipal Stormwater Management
• 2 actions prevent 2,000-4,000 tons of sediment from reaching State waters annually
0
1,000
2,000
3,000
4,000
5,000
6,000
2003-2008 avg 2009 2010 2011 2012
Catch Basin Cleaning Street Sweeping
MS4 Communities Water Quality Accomplishments
(Sediment Removed Annually, tons)
23
Stormwater Management Stormwater Runoff - Municipal Roads Sediment and Erosion Control Washington County • UVM Controlled Study found a
dramatic reduction in polluted runoff from Best Practices such as rock-lining ditches on steep roads • Estimated project cost = $3,000 (1,000 linear feet treated)
Wemple, 2013
24 Eroding roadside ditch Ditch stabilization saves road and reduces erosion
IMPACT TREATMENT
050
100150200250300350400
1 2 3 4 5 6 7 8 9 10 11 12Sedi
men
t dr
y m
ass (
kg)
Sediment Production by Storm Event
Pre-Treatment Post-Treatment
Investments that Work Floodplain and River Corridor Restoration
Rivers Channel Stability Floodplain Restoration Lamoille River, Black Creek Franklin County • Reconnected 200 acres of floodplain • Monitored 3 of the 11 sites (21 acres) • 3 sites captured 1.3 metric tons of
total phosphorus • Estimated cost for levee removal =
$50,000/mile
25 Restored floodplain Black Creek, Fairfield
Removal of elevated railroad embankment
11 Floodplain Restoration Sites
Wetlands Management
RESTORED
0%
10%
20%
30%
40%
50%
Maryland Study Illinois Study
Wetland Performance in Other States (Percent Phosphorus Removal)
Perc
ent R
emov
al
Woltemade, 2000
Wetland Protection & Restoration • 2,700 acres of Champlain wetlands
have been restored or conserved over the past 10 years
• UVM study found that wetland protection helps to reduce phosphorus loading to the Lake
• Estimated project cost = $4,000/acre
DEGRADED
26 Flooded cornfield, former wetland Restored wetland, former farmland
Lake Shoreland Management
Shoreland Protection • 80% of VT lakes have shoreland in fair or poor condition
due to clearing • On a per-acre basis, developed land can contribute more
phosphorus loading than agricultural land
27
PREVENTION
IMPACT
Disturbed lake shoreland Preserved lake shoreland
Forest Management
Acceptable Management Practices (AMPs) • Can reduce phosphorus loading by 85% • 60% of VT forests are subject to AMP
compliance or equivalent, as required under Current Use Program and public land management practices
• Estimated project cost = $3,000 (per crossing)
0%20%40%60%80%
100%120%
No AMPs With AMPs
Edwards, Williard, 2010
Effectiveness of Forestry Practices (Phosphorus load as a percent of load from watersheds logged without AMPs applied)
28
TREATMENT
IMPACT Unmanaged stream crossing at logging site Temporary skidder bridge
Vermont: A Small State Facing Big Challenges to Implement Plan
29 U.S. Census, 2010
• Vermont’s small population makes paying for clean water particularly challenging due to its small revenue base, compared with southern New England and Chesapeake states
• However, Vermont’s rural landscape means that the State has more cost-effective opportunities to reduce phosphorus loads than urbanized regions
0
100
200
300
400
500
600
700
800
900
VT VA DE MD CT MA
Popu
latio
n/sq
uare
mile
Population Density
Vermont: A Small State Facing Big Challenges to Implement Plan
30
Federal
Private
Local State
State will need to tap into existing & new sources to implement plan