verification report

Upload: ajaydeshpande

Post on 13-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 Verification report

    1/79

    Verification Report-1ST PERIODIC

    ORISSA POWER CONSORTIUM LTD.

    20MWSAMAL GRID-CONNECTED HYDROELECTRICPROJECT IN ORISSA,INDIA

    UNFCCCREF.NO.:0895

    Monitoring Period: 2009-05-31 to 2011-03-31(incl. both days)

    Report No: 8106772122 10/269

  • 7/27/2019 Verification report

    2/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No:8106772122 10/269

    Verification Report: Report No. Rev. No. Date of 1stissue: Date of this rev.

    8106772122 10/269 0 2011-12-13 2011-12-13Project: Title: Registration date: UNFCCC-No.:

    20MW Samal Grid-connected HydroelectricProject in Orissa, India

    2007-06-01 0895

    Host Country: Verification No.:

    India 1st periodic verification

    Crediting period: From: To.:

    Renewable (7y) Fixed (10y) 2009-05-31 2019-05-30

    Project Scale:

    Large Scale Small Scale

    Project Participant(s): Host Party: Other involved Parties:

    Orissa Power Consortium Ltd., India PTC India Financial Services

    Limited. - Switzerland Macquarie Bank Limited -

    United Kingdom of GreatBritain and Northern Ireland

    Client: Project Owner:Orissa Power Consortium Ltd. Orissa Power Consortium Ltd.

    Appliedmethodology/ies:

    Title: No.: Scope(s) / TA(s)

    Consolidated baseline methodology for grid-connected electricity generation fromrenewable sources

    ACM0002Version 6

    1/ 1.2

    Monitoring: Monitoring period (MP): No. of days: MP No.

    2009-05-31 to 2011-03-31

    (both days included)670 First

    Monitoring report: Title: Draft version: Final version:

    20MW Samal Grid-connected HydroelectricProject in Orissa, India

    01 03

    Verification team /

    Technical Review andFinal Approval

    Verification Team: Technical review: Final approval:

    Manojkumar Borekar(TL, TE),Dr. AtulTakarkhede (TM, TE)

    Swapnil Thanekar(TM, TE)

    Rainer WinterKatja Beyer

    Rainer Winter

    Emission reductions:[t CO2e]

    Verified amount As per draft MR: As per PDD:

    60,583 t 60929 106789(average) t /a

    O i P C ti Ltd h i i d th TV NORD JI/CDM

  • 7/27/2019 Verification report

    3/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No:8106772122 10/269

    a conservative and appropriate manner.

    TV NORD JI/CDM CP herewith confirms that the project has achieved emissionreductions in the above mentioned reporting period as follows:

    Emission reductions: 60,583 t CO2e

    Documentinformation: Filename: No. of pages:S01-VA050-A1.doc 79

  • 7/27/2019 Verification report

    4/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No:8106772122 10/269

    Abbreviations:

    CA Corrective Action / Clarification Action

    CAR Corrective Action Request

    CDM Clean Development Mechanism

    CEA Central Electricity Authority

    CER Certified Emission Reduction

    CO2 Carbon dioxide

    CO2eq Carbon dioxide equivalentCL Clarification Request

    DG Diesel Generator Set

    ER Emission Reduction

    FAR Forward Action Request

    GHG Greenhouse gas(es)

    GRIDCO Grid Corporation of Orissa Limited

    HT High Tension

    MP Monitoring Plan

    MR Monitoring Report

    OPCL Orissa Power Consortium Ltd.

    O & M Operation and Management

    OPTCL Orissa Power Transmission Corporation Limited

    PA Project Activity

    PDD Project Design Document

  • 7/27/2019 Verification report

    5/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Table of Contents Page

    1. INTRODUCTION ............................................................................................ 71.1. Objective 71.2. Scope 72. GHG PROJECT DESCRIPTION..................................................................... 92.1. Technical Project Description 92.2. Project Verification History 102.3. Involved Parties and Project Participants 102.4. Project Location 11

    3.

    METHODOLOGY AND VERIFICATION SEQUENCE .................................. 12

    3.1. Verification Steps 123.2. Contract review 123.3. Appointment of team members and technical reviewers 133.4. Publication of the Monitoring Report 143.5. Verification Planning 143.6. Desk review 163.7. On-site assessment 163.8. Draft verification reporting 183.9. Resolution of CARs, CLs and FARs 183.10. Final reporting 183.11. Technical review 193.12. Final approval 194. VERIFICATION FINDINGS ........................................................................... 205. SUMMARY OF VERIFICATION ASSESSMENTS ........................................ 345.1. Implementation of the project 345 2 Project history 35

  • 7/27/2019 Verification report

    6/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    5.12. Hints for next periodic Verification 416. VERIFICATION OPINION ............................................................................. 427. REFERENCES ............................................................................................. 43ANNEX 1: VERIFICATION PROTOCOL ................................................................... 50ANNEX 2: STATEMENTS OF COMPETENCE OF ALL INVOLVED PERSONNEL.......... 78

  • 7/27/2019 Verification report

    7/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    1. INTRODUCTION

    Orissa Power Consortium Ltd. has commissioned the TV NORD JI/CDMCertification Program (CP) to carry out the 1st periodic verification of the project

    20MW Samal Grid-connected Hydroelectric Project in Orissa, India

    with regard to the relevant requirements for CDM project activities. The verifiers havereviewed the implementation of the monitoring plan (MP) in the registered CDMproject.

    GHG data for the monitoring period was verified in detailed manner applying the setof requirements, audit practices and principles as required under the Validation and

    Verification Manual/VVM/

    of the UNFCCC.This report summarizes the findings and conclusions of this 1st periodic verificationof the above mentioned UNFCCC registered project activity.

    1.1. Objective

    The objective of the verification is the review and ex-post determination by an

    independent entity of the GHG emission reductions. It includes the verification of the:- implementation and operation of the project activity as given in the PDD,- compliance with applied approved methodology and the provisions of the

    monitoring plan,- data given in the monitoring report by checking the monitoring records, the

    emissions reduction calculation and supporting evidence,- accuracy of the monitoring equipment,

    - quality of evidence,- significance of reporting risks and risks of material misstatements.

    1.2. Scope

    The verification of this registered project is based on the validated project design

  • 7/27/2019 Verification report

    8/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    - other relevant rules, including the host country legislation,- CDM Validation and Verification Manual/VVM/,- monitoring plan as given in the registered PDD/PDD/,- Approved CDM Methodology ACM0002 version 6: Consolidated baseline

    methodology for grid-connected electricity generation from renewable sources.- Change in start date of crediting period/VAL-2/

  • 7/27/2019 Verification report

    9/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    2. GHG PROJECT DESCRIPTION

    2.1. Technical Project Description

    The project activity is generation of electricity for a grid system using the power

    generation potential available at Samal barrage in the state of Orissa. The projectwith an installed capacity of 20 MW (5x4000 kW) will rely on the water dischargesfrom Samal Barrage which had been constructed at Samal, 34 km downstream ofRengali Dam, across Brahmani river in Orissa. During the site visit (dated 2011-05-24and 2011-05-25) the verification team checked the physical installation, verified thetechnical details of installed equipments and compared the number platespecifications of the installed equipments with the technical description as providedunder the Supply contract facility performance data/TD/ and deems the projectimplementation as consistent with the description made during the validation.

    The key parameters of the project are given in Table 2-1:

    Table 2-1: Technical data of the project activity/TD/

    Equipment Parameter Unit Value1. Turbine Make - VA TECH, Faridabad

    Type -Horizontal S Type KaplanTurbine

    No. of generating units - 5Rated net head m 9.85Rated discharge m3/sec 52

    2. Generator Make TDPS, Bangalore

    No. of units 05

    Type - synchronous typeRated speed rpm 750

  • 7/27/2019 Verification report

    10/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    water resource thereby displacing, electricity generated by fossil fuel fired powerplants or future capacity additions in the NEWNE grid.

    Based on the assessment of the verification during the site visit and subsequentdocument review of submitted documents, it is confirmed that during this verification,covering the period 2009-05-31 to 2011-03-31 (inclusive of both days), there is no

    change of the capacity of turbines used under the project activity. The proposedproject activity has been implemented as described in the registered PDD. Also theproject complies with all relevant statutory requirements. The amount of emissionreductions over the monitoring period is 60,583 tCO2e.

    2.2. Project Verification History

    Essential events since the registration of the project are presented in the followingTable 2-2.Table 2-2: Project verification history

    # Item Time Status1 Date of registration 2007-06-01 Registered2 Start of crediting period 2009-05-31 Approved by

    UNFCCC /VAL-2/3 1stMonitoring period 2009-05-31 to

    2011-03-31(inclusive both

    days)

    Ongoing

    2.3. Involved Parties and Project Participants

    The following parties to the Kyoto Protocol and project participants are involved in

    this project activity (Table 2-3).Table 2-3: Project Parties and project participants

    Characteristic Party Project ParticipantHost party India Orissa Power Consortium Ltd.1

  • 7/27/2019 Verification report

    11/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    2.4. Project Location

    The details of the project location are given in Table 2-4:

    Table 2-4: Project Location4

    No. Project Location

    Host Country IndiaRegion: OrissaProject location address: Samal Village, Angul DistrictLatitude: 2104'44NLongitude: 8507'45 E

    The verification team undertook the site visit and document review of the geographical

    coordinates and confirms that the above mentioned project location is correct. Please referclosure of finding A1 for more details.

  • 7/27/2019 Verification report

    12/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    3. METHODOLOGY AND VERIFICATION SEQUENCE

    3.1. Verification Steps

    The verification consisted of the following steps: Contract review

    Appointment of team members and technical reviewers

    Publication of the monitoring report

    A desk review of the Monitoring Report/MR/ submitted by the client andadditional supporting documents with the use of customised verification

    protocol /CPM/according to the Validation and Verification Manual/VVM/, Verification planning,

    On-Site assessment,

    Background investigation and follow-up interviews with personnel of theproject developer and its contractors,

    Draft verification reporting Resolution of corrective actions (if any)

    Final verification reporting

    Technical review

    Final approval of the verification.

    The sequence of the verification is given in the Table 3-1 below:

    Table 3-1: Verification sequenceTable

    Topic Time

    Assignment of verification 2010-04-26/CON/P bli i f M i i R

  • 7/27/2019 Verification report

    13/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    the necessary competences to carry out the verification can be provided,

    Impartiality issues are clear and in line with the CDM accreditationrequirements

    a contract review was carried out before the contract was signed.

    3.3. Appointment of team members and technical reviewers

    On the basis of a competence analysis and individual availabilities a verificationteam, consisting of one team leader and 2 additional team members, was appointed.

    The list of involved personnel, the tasks assigned and the qualification status aresummarized in the Table 3-2 below.

    Table 3-2: Involved Personnel

    Name Company

    Function

    1)

    Qualification

    Status

    2)

    Scheme

    competence

    3)

    Technical

    competence

    4)

    Verification

    competence

    5)

    Hostcountry

    Competence

    On-sitevisit

    Mr.Ms.

    ManojkumarBorekar

    TUV IndiaPvt. Ltd.

    TL, TE SA 1.2

    Mr.Ms.

    SwapnilThanekar

    TUV IndiaPvt. Ltd.

    TM,TE LA 1.2

    Mr.Ms. AtulTakarkhede

    TUV IndiaPvt. Ltd.

    TM A 1.2

    Mr.Ms.

    Katja Beyer

    TUVNORDCert TR

    3) LA

  • 7/27/2019 Verification report

    14/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    B) No team member

    All team members contributed to the review of documents, the assessment of theproject activity and to the preparation of this report under the leadership of the teamleader.

    Technical experts contributed to the assessment of special aspects of the project

    activity, e.g. technical or host country aspects.In order to qualify further personnel the project team was accompanied by observersand/or trainees as indicated in the table above. They are usually not considered asteam members.

    Statements of competence for the above mentioned team members are enclosed inannex 6 of this report.

    3.4. Publication of the Monitoring Report

    In accordance with the CDM M&P ( 62) the draft monitoring report, as received fromthe project participants, has been made publicly available on the dedicated UNFCCCCDM website prior to the verification activity commenced. Comments received aretaken into account in the course of the verification, if applicable.

    3.5. Verification Planning

    In order to ensure a complete, transparent and timely execution of the verificationtask the team leader has planned the complete sequence of events necessary toarrive at a substantiated final verification opinion.

    Various tools have been established in order to ensure an effective verificationplanning.

    Risk analysis and detailed audit testing planning

    For the identification of potential reporting risks and the necessary detailed audittesting procedures for residual risk areas table A-1 is used. The structure and contentof this table is given in Table 3-3 below.

    T bl 3 3 T bl A 1 Id tifi ti f ifi ti i k

  • 7/27/2019 Verification report

    15/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Table A-1: GHG calculation procedures and management control testing / Detailed audittesting of residual risk areas and random testing

    Identificationof potential

    reporting risk

    Identification,assessment and

    testing ofmanagement

    controls

    Areas ofresidual

    risks

    Additionalverification testing

    performed

    Conclusions andAreas Requiring

    Improvement(including

    Forward ActionRequests)

    The followingpotential riskswere identifiedand divided andstructuredaccording tothe possible

    areas ofoccurance.

    The potential risksof raw datageneration havebeen identified inthe course of themonitoring systemimplementation.

    The followingmeasures weretaken in order tominimize thecorrespondingrisks.

    The followingmeasures areimplemented:

    Despite themeasuresimplementedin order toreduce theoccurrenceprobability the

    followingresidual risksremain andhave to beaddressed inthe course ofeveryverification.

    The additionalverification testingperformed isdescribed. Testingmay include:- Sample cross

    checking of

    manual transfers ofdata

    - Recalculation- Spreadsheet walk

    throughs to checklinks and equations

    - Inspection ofcalibration andmaintenance

    records for keyequipment

    - Check samplinganalysis results

    Discussions withprocess engineerswho have detailedknowledge ofprocess

    uncertainty/errorbands.

    Having investigatedthe residual risks,the conclusionsshould be notedhere. Errors anduncertainties arehighlighted.

    The completed table A-1 is enclosed in the Annex 1 (table A-1) to this report.

  • 7/27/2019 Verification report

    16/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Table 3-4: Structure of the project specific periodic verification checklist

    Table A-2: Periodic verification checklist

    Checklist Item Reference Verification TeamComments

    DraftConclusion

    FinalConclusion

    The checklist items in

    Table A-2 are linked tothe various require-ments the monitoringof the project shouldmeet. The checklist isorganised in varioussections as per therequirements of thetopic and the individualproject activity. Itfurther includesguidance for theverification team.

    Gives

    reference totheinformationsource onwhich theassessmentis based on.

    The section is used to

    elaborate and discuss thechecklist item in detail. Itincludes the assessmentof the verification teamand how the assessmentwas carried out. Thereporting requirements ofthe VVM shall be coveredin this section.

    Assessment

    based onevidenceprovided if thecriterion isfulfilled (OK), ora CAR, CL orFAR (seebelow)israised. Theassessmentrefers to thedraft verifi-cation stage.

    In case of a

    correctiveaction or aclarificationthe finalassessmentat the finalverificationstage isgiven.

    The periodic verification checklist (verification protocol) is the backbone of thecomplete verification starting from the desk review until final assessment. Detailedassessments and findings are discussed within this checklist and not necessarilyrepeated in the main text of this report.

    The completed verification protocol is enclosed in the annex (table A-2) to this report.

    3.6. Desk review

    During the desk review all documents initially provided by the client and publiclyavailable documents relevant for the verification were reviewed. The main documents

    are listed below: the last revision of the PDD including the monitoring plan/PDD/, the last revision of the validation report/VAL/, documentation of previous verifications/VER/ the monitoring report, including the claimed emission reductions for the

    j t/MR/

  • 7/27/2019 Verification report

    17/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    The on-site assessment included an investigation of whether all relevantequipment is installed and works as anticipated.

    The operating staff was interviewed and observed in order to check therisks of inappropriate operation and data collection procedures.

    Information processes for generating, aggregating and reporting theselected monitored parameters were reviewed.

    The duly calibration of all metering equipment was checked. The monitoring processes, routines and documentations were audited to

    check their proper application. The monitoring data were checked completely. The data aggregation trails were checked via spot sample down to the level

    of the meter recordings.Before and during the on-site visit the verification team performed interviews with the

    project participants to confirm selected information and to resolve issues identified inthe document review.

    Representatives of Orissa Power Consortium Ltd. and Zenith Energy Services Pvt.Ltd. (project consultant) including the operational staff of the plant were interviewed.The main topics of the interviews are summarised in Table 3-5.

    Table 3-5: Interviewed persons and interview topics

    Interviewed Persons /Entities

    Interview topics

    1. Projects & OperationsPersonnel, OrissaPower Consortium Ltd.;India /IM 01/, /IM 02/;

    2. Zenith Energy ServicesPvt. Ltd, /IM 03/

    - General aspects of the project- Technical equipment and operation- Changes since validation / previous verification- Monitoring and measurement equipment- Remaining issues from validation/ previous

    verification- Calibration procedures- Quality management system- Involved personnel and responsibilities- Training and practice of the operational personnel- Implementation of the monitoring plan

  • 7/27/2019 Verification report

    18/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    3.8. Draft verification reporting

    On the basis of the desk review, the on-site visit, follow-up interviews and furtherbackground investigation the verification protocol is completed. This protocol togetherwith a general project and procedural description of the verification and a detailed listof the verification findings form the draft verification report. This report is sent to the

    client for resolution of raised CARs, CLs and FARs.

    3.9. Resolution of CARs, CLs and FARs

    Nonconformities raised during the verification can either be seen as a non-fulfilmentof criteria ensuring the proper implementation of a project or where a risk to deliverhigh quality emission reductions is identified.

    Corrective Action Requests (CARs) are issued, if: Non-conformities with the monitoring plan or methodology are found in

    monitoring and reporting, or if the evidence provided to prove conformity isinsufficient;

    Mistakes have been made in applying assumptions, data or calculations ofemission reductions which will impair the estimate of emission reductions;

    Issues identified in a FAR during validation or previous verifications requiring

    actions by the project participants to be verified during verification have notbeen resolved.

    The verification team uses the term Clarification Request (CL), which is be issued if:

    information is insufficient or not clear enough to determine whether theapplicable CDM requirements have been met.

    Forward Action Requests (FAR) indicate essential risks for further periodic

    verifications. Forward Action Requests are issued, if: the monitoring and reporting require attention and / or adjustment for the next

    verification period.

    For a detailed list of all CARs, CLs and FARs raised in the course of the verificationpl refer to chapter 4

  • 7/27/2019 Verification report

    19/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    3.11. Technical review

    Before submission of the final verification report a technical review of the wholeverification procedure is carried out. The technical reviewer is a competent GHGauditor being appointed for the scope this project falls under. The technical revieweris not considered to be part of the verification team and thus not involved in the

    decision making process up to the technical review.As a result of the technical review process the verification opinion and the topicspecific assessments as prepared by the verification team leader may be confirmedor revised. Furthermore reporting improvements might be achieved.

    3.12. Final approval

    After successful technical review an overall (esp. procedural) assessment of thecomplete verification will be carried out by a senior assessor located in the accreditedpremises of TV NORD.

    After this step the request for issuance can be started.

  • 7/27/2019 Verification report

    20/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    4. VERIFICATION FINDINGS

    In the following paragraphs the findings from the desk review of the monitoringreport/MR/, the calculation spreadsheet/XLS/, PDD/PDD/, the Validation Report/VAL/ and

    other supporting documents, as well as from the on-site assessment and theinterviews are summarised.

    The summary of CAR, CL and FAR issued are shown in Table 4-1:

    Table 4-1: Summary of CAR, CL and FAR

    Verification topic No. of

    CAR

    No. of CL No. of FAR

    A General description of the project activity 0 1 0

    B Implementation of the project activity 1 0 0

    C Description of the monitoring system 3 0 0

    D Data and parameters monitored 0 0 0

    E - Emission Reductions Calculation 4 0 0

    SUM 8 1 0

    The following tables include all raised CARs, CLs and FARs and the assessments ofthe same by the verification team. For an in depth evaluation of all verification items itshould be referred to the verification protocols (see Annex).

  • 7/27/2019 Verification report

    21/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Finding: A1

    Corrective Action #1This section shall be filled bythe PP. It shall address the cor-rective action taken in details.

    The Geographical coordinates mentioned in the MR version01 are based on Project Design Document which is sourcedfrom DPR (which provided the coordinates till minuteresolution). Consequent to verification site visit finding by

    DOE, the exact geographical coordinates up to accuracy ofsecond is incorporated under section A.3 the MR Ver 02.DOE Assessment #1The assessment shall encom-pass all open issues in annex A-2. In case of non-closure,additional corrective action andDOE assessments (#2, #3, etc.)shall be added.

    Reference : Revised MR, version 2 dated 2011-07-28

    The verification team checked section A.3 of the monitoringreport and confirms that the PP has appropriately updated thecoordinates up to the resolution till seconds. The coordinatesconsistent with and are substantiated by publicly available

    traceable link(http://wikimapia.org/#lat=21.0786338&lon=85.1291084&z=16&l=0&m=b&v=1). The verification team confirms thecorrectness of the updated geographical coordinatessubstantiated by publically traceable link.

    Section A.7 of the monitoring report is deficient.

    The clarification request raised under finding A1 has beenkept OPEN.Corrective Action #2

    This section shall be filled by

    the PP. It shall address the cor-

    rective action taken in details.

    The section A.7 is updated to include the clarity on thechange of the start date of the crediting period postregistration under submitted MR Ver 03.

    DOE Assessment #2

    The assessment shall encom-

    pass all open issues in annex A-

    2. In case of non-closure,

    additional corrective action and

    DOE assessments (#2, #3, etc.)

    shall be added.

    Reference : Revised MR, version 3 dated 2011-12-08

    The MR is updated with respect to the details on the changein the start date of the crediting period/VAL-2/.

    The corrections are found traceable and appropriate, thus theclarification request raised under finding A1 has beenCLOSED

  • 7/27/2019 Verification report

    22/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Finding: B1

    Classification CAR CL FARDescription of findingDescribe the finding in unam-biguous style; address thecontext (e.g. section)

    Below findings are raised by the Verification Team:

    1. The sentence accept delay in project .applicabilityof the methodology under section B.1 of monitoring

    report needs correction as it is correlating twoindependent issues.

    2. The note provided under section B.1 is mis-leading forthe reader, as the description mentions Shutdown dueto less water in river and TRC river bed linings.Furthermore, the details of the shutdowns due to

    Insufficient water flows are missing.Corrective Action #1This section shall be filled bythe PP. It shall address the cor-rective action taken in details.

    1. The sentence is now corrected. The revised sentenceis as follows No other significant events occurredduring the monitored period, which may impact theapplicability of the methodology. Thus, the issues areno more mixed with each other.

    2. MR revised suitably and shut down details due to

    insufficient water are furnished. Log sheet is attachedfor your reference. The PP also clarified that there wasno down times of the installed metering equipmentresponsible for monitoring the project activity inline withmonitoring plan.

  • 7/27/2019 Verification report

    23/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Finding: B1

    DOE Assessment #1The assessment shall encom-pass all open issues in annex A-2. In case of non-closure,additional corrective action andDOE assessments (#2, #3, etc.)

    shall be added.

    Reference : Revised MR, version 2 dated 2011-07-28

    1. The verification team checked and confirms that thesentence under section B.1 of monitoring report is nowcorrected (refer corrected sentence: No othersignificant events occurred during the monitored period,which may impact the applicability of the methodology).The delay in implementation of project is appropriatelyseparated from the applicability condition.

    2. Revision under section B.1 of monitoring report isaccepted; supportive log of shut down is reviewed andfound consistent with the reporting under monitoring

    report. The Annex-2 of the monitoring report is alsoreviewed and the details of major shut downs andreasons are verified based on the log sheetrecords/LOG/. The corrections are thus deemedappropriate. The Verification team also reviewed theJMR issued by the GRIDCO, LOG of real-time mainmeter readings captured by the 132 kV meterauthenticated with covering letter issued by GRIDCOLimited, dated 2011-07-11 issued by AGM (Electrical),Grid Corporation of Orissa Limited as supportive toJMR and the submitted calibration reports and deemsthat there was no downtime/ malfunction of installedmetering system.

    The CAR raised under finding B1 has been CLOSED.ConclusionTick the appropriate checkbox

    To be checked during the next periodic verificationAppropriate action was takenProject documentation was corrected correspondinglyAdditional action should be takenThe project complies with the requirements

  • 7/27/2019 Verification report

    24/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Finding: C1

    Description of findingDescribe the finding in unam-biguous style; address thecontext (e.g. section)

    1. The metering diagram under section C of monitoringreport is inconsistent with single line diagram/site visitof the verification team. Appropriate corrections alongwith metering locations are missing.

    2. The following sentence under section C of MR thecalibration of theis as per the monitoring plan isnot unambiguous. Furthermore, the role of shift incharge mentions maintaining reading on daily basiswhich is inconsistent with monitoring plan andmethodology.

    Corrective Action #1This section shall be filled bythe PP. It shall address the cor-rective action taken in details.

    a. Suitable correction made under section C ofmonitoring report. The line diagram is updated byproviding metering location for gross and auxiliarymeters which are in control of PP and the main andcheck meter at 132 kV substation which are sealedand in control of OPTCL.

    b. Appropriate changes have been incorporated undersection C of revised MR.

  • 7/27/2019 Verification report

    25/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Finding: C1

    DOE Assessment #1The assessment shall encom-pass all open issues in annex A-2. In case of non-closure,additional corrective action andDOE assessments (#2, #3, etc.)

    shall be added.

    Reference : Revised MR, version 2 dated 2011-07-28

    a. The section C of the monitoring report is appropriatelyupdated and includes the line diagram providing themetering points. The verification team checked the

    same with the help of submitted Single LineDiagram/SLD/ issued by Chief Engineer, OPTCL,Bhubaneswar. The verification team confirms that theline diagram providing the metering points is in line withthe Single Line Diagram/SLD/and deemed appropriate.

    b. OK, the section C of revised monitoring report is nowappropriately mentions that the Plant Manager will beresponsible to carry out the calibrations as perprovisions of the monitoring plan. Furthermore, themonitoring report now clearly states that the frequencyof monitoring electrical readings will be hourly (in placeof daily). In additional the PP has submitted the log ofthe real time meter readings captured by 132 kVsubstation main meter/LOG/ to the verification team inorder to establish the conformance to the monitoring

    frequency. Additionally the PP has also submittedElectrical Log Sheet to confirm hourly monitoring ofthe gross power generation. The shift engineer is alsonoting the net electricity exported to the grid on dailybasis and prepares the consolidated Daily/MonthlyGeneration/ Export details work sheet for crossverifying it with the JMR issued by the GRIDCO.

    The CAR raised under finding C1 has been CLOSED.ConclusionTick the appropriate checkbox

    To be checked during the next periodic verificationAppropriate action was takenProject documentation was corrected correspondingly

  • 7/27/2019 Verification report

    26/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Finding: C2

    Description of findingDescribe the finding in unam-biguous style; address thecontext (e.g. section)

    The PP needs to submit the following to the verification team:a. appointment of the Internal auditor

    b. audit report on monthly basis

    c. hourly monitoring records of 132 kV sub-station meter

    Corrective Action #1This section shall be filled bythe PP. It shall address the cor-rective action taken in details. a. Appointment letter of internal auditor is enclosed.

    b. Audit reports are enclosed. Furthermore, PP wishes toclarify that, the audit reports are prepared on every month

    and also half yearly. The monthly & half yearly reports areenclosed.c. The electronic data of Electricity Supplied to the grid

    received from GRIDCO Ltd., is provided to the DOE forverification.

    DOE Assessment #1The assessment shall encom-pass all open issues in annex A-2. In case of non-closure,

    additional corrective action andDOE assessments (#2, #3, etc.)shall be added.

    1. Appointment Letter of Mr. K. Yogeshwar Rao dated2009-10-03 is provided to the Verification Team. Theappointment letter clearly mentions the roles and

    responsibilities of the Internal Auditor. The VerificationTeam also studied the monthly reports issued by Mr. K.Yogeshwar Rao to the management. The Verificationteam during the site visit interviews noted that Mr. K.Yogeshwar Rao was involved during the entire cycle ofCDM validation, was responsible for CDM activitiesand thus possess the experience and knowledge of thesubject. Furthermore, external independent agencywas also appointed to support Mr. K. Yogeshwar Raofor the monthly as well as half yearly reporting andinternal audits.

    2. Audit reports on monthly basis are submitted to theVerification Team. The half yearly reports are also

  • 7/27/2019 Verification report

    27/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Finding: C2

    ConclusionTick the appropriate checkbox

    To be checked during the next periodic verificationAppropriate action was takenProject documentation was corrected correspondinglyAdditional action should be takenThe project complies with the requirements

    Finding: C3

    Classification CAR CL FARDescription of findingDescribe the finding in unam-biguous style; address thecontext (e.g. section)

    The PPs substantiation under section C of MR regardingTraining for Samal Personnel is insufficient to demonstrateappropriate steps undertaken by PP. Furthermore,

    clarification is requested regarding term designated personincharge.

    Corrective Action #1This section shall be filled bythe PP. It shall address the cor-rective action taken in details.

    The project proponent has executed O&M Agreement withM/s. Manihamsa Power Projects Ltd., on 2009-02-23 foroperation and maintenance of the plant. As per Clause 2.2.2of the O&M Agreement, the OPCL staff are trained andworking under the functional guidance and control of O&Mcontractor. The O&M contractor has provided training to thefollowing personnel of the project proponent.

    Name of the employee Designation

    1. Mr.G.P.Mahapatra, PPS2. Mr.S.K.Mishra, DGM (Site)3. Mr.Suryakanta Bisi Asst.Manager Elec.4. Mr.Bharat Relangi Jr.Manager Mech.5. Mr.Rath Babu Asst.Manager Tech

  • 7/27/2019 Verification report

    28/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Finding: C3

    DOE Assessment #1The assessment shall encom-pass all open issues in annex A-2. In case of non-closure,additional corrective action andDOE assessments (#2, #3, etc.)shall be added.

    Reference : Revised MR, version 2 dated 2011-07-28

    As per Clause 2.2.2 of the O&M Agreement//APR/, the OPCLstaff are trained and working under the functional guidanceand control of O&M contractor. This was also verified basedon the site visit interviews. The verification team alsoacknowledges that the appropriate corrections are includedunder section C of the monitoring report and hence clarity isincluded by correcting the term designated person inchargeto General Manager.

    The CAR raised under finding C3 has been CLOSED.ConclusionTick the appropriate checkbox

    To be checked during the next periodic verificationAppropriate action was takenProject documentation was corrected correspondinglyAdditional action should be takenThe project complies with the requirements

    Finding: E1

    Classification CAR CL FARDescription of findingDescribe the finding in unam-biguous style; address thecontext (e.g. section)

    Material mis-statement is observed in the ER sheet for theparameter Electricity Exported to grid for the month ofSeptember 2010, August 2010 and May 2010.

    Corrective Action #1

    This section shall be filled bythe PP. It shall address the cor-rective action taken in details.

    The appropriate corrections made on monthly export readings

    for the month of September 2010, August 2010 and May2010.DOE Assessment #1The assessment shall encom-pass all open issues in annex A-2. In case of non-closure,

    ddi i l i i d

    Reference : Revised MR, version 2 dated 2011-07-28 andcorresponding emission reduction worksheet:

    Th di f

  • 7/27/2019 Verification report

    29/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Finding: E1

    ConclusionTick the appropriate checkbox

    To be checked during the next periodic verificationAppropriate action was takenProject documentation was corrected correspondinglyAdditional action should be takenThe project complies with the requirements

    Finding: E2

    Classification CAR CL FARDescription of findingDescribe the finding in unam-biguous style; address thecontext (e.g. section)

    During site visit and document review the assessment teamfound that the monitoring parameter Electricity supplied tothe grid is recorded on daily basis the monitoring parameters

    are archived on paper (log books), which is not in linemonitoring plan under registered PDD. PP needs to clarify.

    Corrective Action #1This section shall be filled bythe PP. It shall address the cor-rective action taken in details.

    As per the monitoring plan in the registered PDD, theparameter Electricity supplied to the grid is to be measuredon hourly basis and to record every month. The energymeters (main and check) installed at sub-station are having afacility to measure the said parameter at 15 minute interval

    and the data records electronically. The electronic dataobtained from the GRIDCO Limited is furnished to the DOEfor verification. The hourly data maintained by the O&Mcontractor is also furnished to the DOE for verification.

    DOE Assessment #1The assessment shall encom-pass all open issues in annex A-2. In case of non-closure,additional corrective action andDOE assessments (#2, #3, etc.)shall be added.

    Reference : Revised MR, version 2 dated 2011-07-28

    The meter is accessible for taking readings (reference: Sitevisit observation of Assessment Team). The submitted

    supportive documents in form of real time log of the 132 kVmain meter readings/LOG/for hourly monitoring is reviewed bythe verification team.

    The CAR raised under finding E2 has been CLOSED.ConclusionTi k h i h kb

    To be checked during the next periodic verification

    1 t P i di V ifi ti R t 20MW S l G id t d

  • 7/27/2019 Verification report

    30/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Finding: E3

    Classification CAR CL FARDescription of findingDescribe the finding in unam-biguous style; address thecontext (e.g. section)

    1. Section E.1 of MR is lacks the baseline emissioncalculations and the stepwise approach adopted tocalculate the baseline emission factor. Furthermore, the

    monitoring approach adopted for parameter EF_OMy isinconsistent with monitoring plan.

    2. During the site visit verification team found DG installed atthe project site which acts as a backup to power plant,however same is not the part of registered monitoringplan. Clarification is requested why the same is not part of

    monitoring plan.

    Corrective Action #1This section shall be filled bythe PP. It shall address the cor-rective action taken in details.

    1. Baseline emission calculation and stepwise approachfor baseline emission factor furnished in revised MR.

    2. As per the methodology ACM0002 Ver. 06 monitoringof project emissions due to combustion of fossil fuel i.e.,diesel is not required. Further the expected emissions

    from operation of DG set during emergency (whileproject plant under shut down and also grid failure atthe same time which is very rare) are very negligibleand much less than 1%. Even if we apply requirementsof VVM footnote 78 of VVM version 01.2, inclusion ofthis parameter is not required though methodology alsodoes not specifically require it. Hence monitoring ofemissions due to operation of DG set is not part of the

    registered monitoring plan.The electricity generated by DG set during entiremonitoring period (i.e., from Oct 2009 to Mar 2011) is0.000071 GWh and percentage of emissions from DGset is 0 0001% as compared with actual emission

    1st Periodic Verification Report: 20MW Samal Grid connected

  • 7/27/2019 Verification report

    31/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Finding: E3

    DOE Assessment #1The assessment shall encom-pass all open issues in annex A-2. In case of non-closure,additional corrective action andDOE assessments (#2, #3, etc.)shall be added.

    Reference : Revised MR, version 2 dated 2011-07-28

    1. The calculation for the baseline emission factor isincorrect as parameter EF_OMy is not monitored in linewith the monitoring plan of registered PDD. The findingis KEPT OPEN.

    2. The PP has submitted the summary of the dieselconsumption to the verification team to confirm theHSD consumption, electricity generated by DG andhence confirmation on the emissions due to DG usage.To conform the unit generation from the DG the PP hassubmitted supportive of the Electricity Duty paid

    against the generation of power from the DG. Based onthe submitted evidence and review of above calculationthe verification team acknowledges that thecontribution of the emissions due to DG are negligibleand thus need not be part of the monitoring plan.Finding is CLOSED.

    The CAR raised under finding E3 has been KEPT OPEN.Corrective Action #2This section shall be filled by

    the PP. It shall address the cor-

    rective action taken in details.

    1. Appropriate corrections are included under the sectionE.1 of monitoring report and emission reductionworksheet.

    DOE Assessment #2

    The assessment shall encom-

    pass all open issues in annex A-

    2. In case of non-closure,

    additional corrective action andDOE assessments (#2, #3, etc.)

    shall be added.

    Reference : Revised MR, version 3 dated 2011-12-08

    1. The verification team noted that the PP hasappropriately calculated the operating margin in linewith registered PDD and appropriately includedbaseline emission calculation with stepwise approachfor calculating baseline emission factor under sectionE.1. Please refer section 5.6 of the report for detailedassessment on appropriateness of the operating

    1st Periodic Verification Report: 20MW Samal Grid-connected

  • 7/27/2019 Verification report

    32/79

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Finding: E4

    Description of findingDescribe the finding in unam-biguous style; address thecontext (e.g. section)

    The MR lacks information pertaining calibration scheduleobserved by the PP.

    Corrective Action #1This section shall be filled by

    the PP. It shall address the cor-rective action taken in details.

    The information regarding calibration of main and check

    meters were provided in detail under section- C of revisedMR.

    The PP requests the DOE to refer EB 52 Annex 60Guidelines for assessing compliance with the calibrationfrequency requirements. As per para 8 of the said guideline,in the cases where calibration frequency for measuring

    equipments is not specified either in the monitoringmethodology or the monitoring plan, the DOE shall ensurethat the equipments are calibrated either in accordance withthe specifications of the local/national standards, or as per themanufacturer specification. If local/national standards or themanufacturer specification is not available, internationalstandards may be used.

    Since neither the monitoring methodology nor the monitoringplan in the registered PDD specified the calibration frequencyfor measuring equipments, the PP has to follow thespecifications of the local / national standards or as per themanufacturer specification for calibration frequency, as perthe above guideline.

    As per the National Standard i.e., CEA Notificationdt.17.03.2006, Para 18 - Calibration and Periodical testing ofmeters all interface meters have to be tested at least once in

    1st Periodic Verification Report: 20MW Samal Grid-connected

  • 7/27/2019 Verification report

    33/79

    1st Periodic Verification Report: 20MW Samal Grid connected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Finding: E4

    DOE Assessment #1The assessment shall encom-pass all open issues in annex A-2. In case of non-closure,additional corrective action andDOE assessments (#2, #3, etc.)shall be added.

    Reference : Revised MR, version 2 dated 2011-07-28

    In line with the guidance EB52 Annex 60, the approachadopted by PP can be assessed and acceptable due tofollowing conclusions

    1. The assessment team verified the technical informationof the meters and the national metering guidelines/ceam/(and hence local/regional practices) as well as the setof PPA/PPA/.

    2. The PP at the time of registration of the project did notupdate the PDD with respect to frequency of

    calibration schedule as it could control the calibration ofthe electricity meters since it was under the purview ofOPTCL/PPA/ . As per PPA the calibration frequency istwo years.

    3. The calibration was performed within the aboveaccepted limit of Once in 2 years /PPA/ for appliedmonitoring period.

    4. The error detected during the calibration check was

    below the accuracy class of the meters/CAL/ so themeters were concluded to be working in line with thedesigned accuracy limits.

    The CAR raised under finding E4 has been CLOSED.ConclusionTick the appropriate checkbox

    To be checked during the next periodic verificationAppropriate action was takenProject documentation was corrected correspondingly

    Additional action should be takenThe project complies with the requirements

    1st Periodic Verification Report: 20MW Samal Grid-connected

  • 7/27/2019 Verification report

    34/79

    st e od c e cat o epo t 0 Sa a G d co ected

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    5. SUMMARY OF VERIFICATION ASSESSMENTS

    The following paragraphs include the summary of the final verification assessmentsafter all CARs and CRs are closed out. For details of the assessments pl. refer to thediscussion of the verification findings in chapter 4 and the verification protocol (Annex1).

    5.1. Implementation of the project

    During the current verification, a site visit was carried out on 2011-05-24 and 2011-05-25. The assessment team checked the installed TGs involved in the projectactivity during the site visit and found that the implementation of the project activity is

    in line with the registered PDD/PDD//IM01//IM02//TD/(please also refer section 2.1, Table 2-1: Technical data of the plant). None of the equipments involved in the project activityincluding the monitoring equipments i.e. energy meters have been reportedlyexchanged / replaced/CAL/.The equipments are subject to a well defined preventivemaintenance schedule/MMS-1,2/. The assessment team also verified the same bychecking the generation data during the site visit/JMR/. The project is currentlyoperational as per the submitted records/PDD//JMR//IM01//IM02/ and the same was also

    verified during the site visit assessment. On the basis of this site visit and thereviewed project documentation it can be confirmed that w.r.t. the realizedtechnology, the project equipments, as well as the monitoring and meteringequipment, the project has been implemented and operated as described in theregistered PDD. The verification team also identified change in the applied tariff ofthe project activity, therefore decided to access the impact of changed tariff onproject additionality. The candidate project was registered on 2007-06-01 based onthe input parameters that were available at that point of time, including tariff.

    However, consequent upon a steep increase in project cost, the tariff underwentrevision as shown in the following table:

    Year Original Tariff (INR/kWh) Revised tariff (INR/kWh)I 1.97

    1st Periodic Verification Report: 20MW Samal Grid-connected

  • 7/27/2019 Verification report

    35/79

    p

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    the project activity. Since in this instant case, the upward revision affect additionality,DOE reassessed the additionality of the project keeping in view the guidelines givenvide paragraph 8 of Annex 67, EB 48. Accordingly only the changed parametershave been modified in the original spread sheet calculations. Actual generation5 forthe first two completed years of operation has been taken, as the project could notachieve the projected generation due to lower discharge and since the project

    additionality is being reassessed, actual generation is more appropriate. Thereassessment reveals that the financial indicator will go up from 10.31% asenvisaged at the time of registration to 12.47% as against the benchmark of 15.53%considered at the time of registration. Thus, the project will continue to remainadditional.

    In this context, it is observed that though the tariff has undergone an upward revision(consequent upon the cost overrun in the project cost), it was not within the control of

    the Project Participant6. Moreover, DOE is also convinced that the PP could not havebeen aware of the impending revision in the tariff at the time of validation andregistration as the tariff was revised only vide Orissa Electricity RegulatoryCommission order dated 2011-01-14/ADD/based on the hearing conducted on 2011-01-07/ADD/, i.e., four years after registration of the project.

    Considering the facts that the tariff revision was not within the control of PP, PP couldnot have been aware of the impending revision of tariff and that even the applicationof revised tariff does not render the project non-additional, DOE concludes that theproject is additional and no additional measures are necessary as the project isimplemented in line with registered PDD.

    5.2. Project history

    During the validation the validating DOE DNV Certification, International ClimateChange Services has not raised issues that could not be closed or resolved duringthe validation stage and so no remaining issues are there in the validation report/VAL/.

    Furthermore as this is the 1st periodic verification, so no issues from former

    1st Periodic Verification Report: 20MW Samal Grid-connected

  • 7/27/2019 Verification report

    36/79

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    No special events with effect on the monitoring of the project have been observedduring the monitoring period. The verification team identified inconsistencies undersection B.1 of the monitoring report and raised CAR under finding B1, bullet 1,2 .

    In reply to the finding B1, bullet 1, the PP has appropriately revised section B.1 ofmonitoring report and appropriately separated implementation of project activity andapplicability conditions.

    In reply to the finding B1, bullet 2, the PP has appropriately revised section B.1 andadded annex-2 to monitoring report to address details of downtimes of equipments &reasons.

    5.4. Compliance with the monitoring plan

    The monitoring system and all applied procedures are completely in compliance to

    the registered monitoring plan. All necessary monitoring instruments are installed.The measuring devices are well known and state of the art.

    The verification team found no inconsistencies in the MR with respect to approvedmonitoring plan/PDD/. During the verification process no significant lack of evidencewas detected.

    5.5. Compliance with the monitoring methodologyThe monitoring system is in compliance with the applied monitoring methodologyACM0002, Version 06: Consolidated Baseline Methodology for grid-connectedelectricity generation from renewable sources and thus reflect the requirements ofthe registered monitoring plan/PDD/.

    5.6. Monitoring parameters

    During the verification all relevant monitoring parameters (as listed in section B.7.1 ofregistered PDD/PDD/) have been verified with regard to the appropriateness of theapplied measurement / determination method, the correctness of the values appliedfor ER calculation, the accuracy, and applied QA/QC measures. The results as well

    1st Periodic Verification Report: 20MW Samal Grid-connected

  • 7/27/2019 Verification report

    37/79

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    post. The latest version of the CEA data base available during the monitoringperiod is utilized by the PP for determination of emission factor. Theverification team checked the monitored OM values following the belowmethod as indicated below:

    Period 31/05/2009 to 31/03/2010- The available version of CEA was version 5.

    Please refer below snapshot from CEA version05

    7

    .Simple Operating Margin (tCO2/MWh) (incl.Imports)

    2005-06 2006-07 2007-08 2008-09NEWNE 1.02 1.01 1.00 1.01South 1.01 1.00 0.99 0.97India 1.02 1.01 1.00 1.01

    Ex post option:If the ex post option is chosen, the emission factor is determined forthe year in which the project activity displaces grid electricity, requiring the emissionsfactor to be updated annually during monitoring. If the data required to calculate theemission factor for year y is usually only available later than six months after the endof year y, alternatively the emission factor of the previous year y-1 may be used.If the data is usually only available 18 months after the end of year y, the emission

    factor of the year proceeding the previous year y-2 may be used.The same data vintage (y, y-1 or y-2) should be used throughout all crediting periods.

    The PP has appropriately selected the data vintage y-1 i.e. value expressed for2008-09 i.e. OM = 1.006

    Now for the vintage period 01/04/2010 to 31/03/2011- the available version of CEA is

    Version 68, please refer below snapshot:

    Simple Operating Margin (tCO2/MWh) (incl.Imports)

    2004-05 2005-06 2006-07 2007-08 2008-09 2009-10

    1st Periodic Verification Report: 20MW Samal Grid-connected

  • 7/27/2019 Verification report

    38/79

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    If the data is usually only available 18 months after the end of year y, the emissionfactor of the year proceeding the previous year y-2 may be used.The same data vintage (y, y-1 or y-2) should be used throughout all crediting periods.

    The PP has appropriately selected the data vintage y-1 i.e. value expressed for i.e.OM =0.977

    The PP has appropriately considered the ex-ante value of the build margin(880.33tCO2/GWh )from the registered PDD.

    The combined margin emission factor (baseline emission factor) with thedefault values used for

    OMw (0.5) and

    BMw (0.5) are appropriately utilized

    EFy=EF_OMyx WOM+ EFBM, y x WBMWhere,WOM = Weighting of operating margin emissions factor (%)WBM = Weighting of build margin emissions factor (%)EFBM, y = Build margin CO2 emission factor in year y (tCO2/MWh)EF_OMy= Operating margin CO2 emission factor in year y (tCO2/MWh)

    For vintage: 31/05/2009 to 31/03/2010 (inclusive both days)

    EFy= 1.006 0.5 + 0.88033 0.5EFy= 0.943 t CO2/MWh

    For vintage: 01/04/2010 to 31/03/2011(inclusive both days)

    EFy= 0.9777 0.5 + 0.88033 0.5EFy= 0.929 t CO2/MWh

    Comparison of the monitored parameter with respect to the value determined attime of validation

    Vintage Value (t CO2/MWh) EFy EFy Assessment

    1st Periodic Verification Report: 20MW Samal Grid-connected

  • 7/27/2019 Verification report

    39/79

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    The monitoring report provides a list of all parameters that need to be monitoredwhich is in line with the monitoring plan provided in the PDD of the registered projectwhich was evaluated during the validation process.

    The reporting /MR2/ /XLS2/ is in line with the requirements of the validated monitoringplan as well as with the applied methodology ACM 0002, version 6/ACM0002/.

    The reporting procedures reflect the requirements of the monitoring plan /PDD/. Thenet electricity exported is recorded once every month by GRIDCO Limited. This dataform the basis of emission reduction calculation.

    All records needed for monitoring of net electricity exported to grid are available. Allvalues are available for purpose of monitoring reporting. There are no delays in thecalibration schedules undertaken by the PP (please refer closure of finding E4). TheVerification team also acknowledges that the monitoring parameters PlantIdentification for OM, GENj,k,l,y (Electricity imported to Grid.), GEN j,k,m,y (Electricitygeneration of the plant j,k,m.) are not separately monitored as the values of OM isdirectly obtained from the published CEA database.

    With appropriate closure of finding E1 and finding E4, it can be confirmed that allmonitoring parameters have been measured / determined without materialmisstatements and in line with monitoring plan.

    5.7. Monitoring reportA draft monitoring report was submitted to the verification team by the projectparticipants. The team has made this report publicly available prior to the start of theverification activities. No comments were received.

    During the verification, mistakes and needs for clarification were identified. The PPhas carried out the requested corrections so that it can be confirmed that theMonitoring report is complete and transparent and in accordance with the registeredPDD and other relevant requirements please refer section 4 of this report.

    5.8. ER Calculation

    During the verification mistakes in the draft ER calculation were identified This has

    1st Periodic Verification Report: 20MW Samal Grid-connected

    H d l t i P j t i O i I di

  • 7/27/2019 Verification report

    40/79

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    registered PDD/PDD/as well as covered in detail in the ER sheet/XLS2/.For the start andend of the crediting period, the approaches as defined under Annex 3 of thePDD/PDD/.The calculation approach was verified to be in line with the requirements.As a result the final emission reductions achieved during the monitoring period areequal to the baseline emissions 60,583tCO2e as the project emissions and leakageemissions are zero.

    5.9. Quality Management

    Quality Management procedures for measurements, collection and compilation ofdata, data storage and archiving/JMR/, calibration/CAL/, maintenance/IM01/, /IM02/, /MANT/andtraining of personnel in the framework of this CDM project activity have beenpredefined being a multiple party involvement in O & M and monitoring of the projectequipments. The procedures defined can be assessed as appropriate for thepurpose. No significant deviations thereof have been observed during the verification.The assessment team verified the monitoring arrangements referring to theregistered monitoring plan/PDD/as well as the applicable methodology.

    a. The assessment team verified the technical information of the meters and thenational metering guidelines/ceam/ (and hence local/regional practices) as well as theset of PPA/PPA/.

    b. The calibration frequency was not specified in PDD, thus the local practicesadopted by the regional SEB i.e. OPTCL under its PPA/PPA/ and the CEAguidelines/ceam/ which require the HT meters need to be re-calibrated once in every 5years.

    c. The calibration was performed within the above accepted limit of Once in 2 years

    d. The error detected during the calibration check was below the accuracy class ofthe meters/CAL/, so the meters were concluded to be working in line with the accuracy

    limits defined by the meter manufacturer. The assessment team, verified all thecalibration certificates/CAL/ available for the project activity since the last calibrationfrom the previous verification and observed it to be compliant and within two yearsi.e. calibration frequency.

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa India

  • 7/27/2019 Verification report

    41/79

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    5.10. Comparison with ex-ante estimated emission reductions

    The MR includes a comparison of the calculated actual emission reductions with theex-post calculated values in the registered PDD.

    The calculated value was found to be lower than the ex-post determined value, thusno further justification was required.

    5.11. Overall Aspects of the Verification

    All necessary and requested documentation was provided by the project participantsso that a complete verification of all relevant issues could be carried out.

    Access was granted to all installations of the plant which are relevant for the projectperformance and the monitoring activities.

    No issues have been identified indicating that the implementation of the projectactivity and the steps to claim emission reductions are not compliant with theUNFCCC criteria and relevant guidance provided by the COP/CMP and the CDM EB(clarifications and/or guidance).

    5.12. Hints for next periodic Verification

    No FARs have been raised during the course of First Periodic verification. Theverification team found all systems in place and no specific violation to applicableCDM requirements were observed.

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa India

  • 7/27/2019 Verification report

    42/79

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    6. VERIFICATION OPINION

    Orissa Power Consortium Ltd. has commissioned the TV NORD JI/CDMCertification Program to carry out the 1stperiodic verification of the project: 20MWSamal Grid-connected Hydroelectric Project in Orissa, India, with regard to the

    relevant requirements for CDM project activities. The project reduces GHG emissionsdue to electricity generation by making use of available hydro potential at the site tomeet the regional electricity demand. This verification covers the period from 2009-05-31 to 2011-03-31 (including both days).

    In the course of the verification 08 Corrective Action Requests (CAR) and 01Clarification Requests (CL) were raised. The verification is based on the monitoringreport, revised monitoring report, the monitoring plan as set out in the registered

    PDD, the validation report, emission reduction calculation spreadsheet andsupporting documents made available to the TV NORD JI/CDM CP by the projectparticipant.

    As a result of this verification, the verifier confirms that:

    all operations of the project are implemented and installed as planned anddescribed in the validated project design document.

    the monitoring plan is in accordance with the applied approved CDMmethodology, i.e., ACM0002 version 6.

    the installed equipment essential for measuring parameters required forcalculating emission reductions are calibrated appropriately.

    the monitoring system is in place and functional. The project has generatedGHG emission reductions.

    As the result of the 1st periodic verification, the verifier confirms that the GHGemission reductions are calculated without material misstatements in a conservativeand appropriate manner. TV NORD JI/CDM CP herewith confirms that the projecthas achieved emission reductions in the above mentioned reporting period asfollows:

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa India

  • 7/27/2019 Verification report

    43/79

    Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    7. REFERENCES

    Table 7-1: Documents provided by the project participant(s)

    Reference Document

    /APR/ Annual performance report from 2009-10-11 to 2011-03-31regarding the monitoring period mentioning the monthlygeneration, generation hours, down time hours and plant loadfactor.

    Monthly internal audit report for audit undertaken by PP andsupported by Third Party (Zenith Energy Services)

    Six monthly internal audit report for audit undertaken by PP andsupported by Third Party (Zenith Energy Services)

    Extract of O & M contract evidencing the provision for training ofPPs personnel

    /CAL/ Calibration requirements of all the equipments installed to monitor allthe data and parameter being measured in the project activity:

    1. Minutes of meeting for the testing of accuracy of Main Meter(APMO 2439) and check meter (APMO 2685) dated 2010-02-11jointly signed by representative of OPTCL, OPCL and SecuredMeter

    2. Installation, commissioning and testing of accuracy of Main Meter(APMO 2439) and check meter (APMO 2685) dated 2009-10-11jointly signed by representative of OPTCL, OPCL and SecuredMeter

    /ceam/ National Standard i.e., CEA Notification dated 2006-03-17, Para 18 -Calibration and Periodical testing of meters, all interface meters haveto be tested at least once in five years.

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

  • 7/27/2019 Verification report

    44/79

    y j ssa, a

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Reference Document

    7. Declaration of Commercial Operation of 20 MW Samal SHEPfrom GRIDCO Limited dated 30-01-2010.

    /ED/ Bio Data of Sri Gopal Prasad Mohapatra (B.Sc. Engg Electrical)designation Power Plant Superintendent.

    Bio Data of Suryakanta Bisi (Diploma in Electrical Engineering)designation Assistant Manager (Electrical).

    Bio Data of Appa Rao (Diploma Mechanical) designationMechanical Supervisor.

    Bio Data of Yuva Nagarjuna (B Tech E.E.E) designation ShiftIncharge.

    /JMR/ Joint meter reading from GRIDCO LIMITED for monitoringperiod 2009-10-11 to 2011-03-31(inclusive both days).

    Invoices raised by PP for period of 2009-10-11 to 2011-03-31

    /LOG/ LOG of real-time main meter readings captured by the 132 kVmeter authenticated with covering letter issued by GRIDCO

    Limited, dated 2011-07-11 issued by AGM (Electrical), GridCorporation of Orissa Limited as supportive to JMR. Machine LOG Sheet for monitoring turbine performance Log of downtime hours on daily basis in form of worksheet Proof of HSD consumption in form of electricity duty

    /MMS/ Maintenance schedule as per the O & M Contract Routine and Daily Check list of Electrical equipments Check list for Mechanical equipment

    /MR/ 1. Monitoring Report for project activity 20MW Samal Grid-connected Hydroelectric Project in Orissa, India dated 2011-05 04 (Version 01)

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

  • 7/27/2019 Verification report

    45/79

    y j

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Reference Document

    Orissa Power Consortium Limited dated 2004-10-21.

    /SC/ Consent to operate granted under section 25/26 of water(Prevention & Control of Pollution) Act, 1974 and under section 21

    of Air (Prevention & Control of Pollution) Act, 1981 dated 2010-11-29.

    /SLD/ Electrical Single Line Diagram of the power plant approved by theChief Engineer, OPTCL Bhubaneshwar

    /TD/ Technical details of turbines (S-Type, Kaplan) and generators (750

    RPM, 4000 kW at 11 kV, 3 Phase, 50 Hz, 0.8 PF) in line withSupply Contract Facility Performance Data or GuaranteedTechnical Particulars.

    /XLS/ 1. Emission reduction calculation sheet corresponding to monitoringreport version 01

    2. Emission reduction calculation sheet corresponding to monitoringreport version 02

    3. Emission reduction calculation sheet corresponding to monitoringreport version 03

    Table 7-2: Background investigation and assessment documents

    Reference Document

    /ACM0002/ CDM Methodology ACM0002, version 06: Consolidated baselinemethodology for grid-connected electricity generation from renewablesources

    /CBD/ CO B li D t b f I di P S t U G id

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

  • 7/27/2019 Verification report

    46/79

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Reference Document

    /KP/ Kyoto Protocol (1997)

    /MA/ Decision 3/CMP. 1 (Marrakesh Accords)

    /PDD/ Registered Project Design Document for CDM project: 20MW Samal Grid-connected Hydroelectric Project in Orissa, India, Version 03, dated 2007-01-17(http://cdm.unfccc.int/UserManagement/FileStorage/D59XRXL7J9SJ7UPJAA08XUA3U0Q694)

    /VAL/ 1. Validation Report for CDM project 20MW Samal Grid-connectedHydroelectric Project in Orissa, India version 02, dated 2007-01-24

    (http://cdm.unfccc.int/filestorage/1/U/G/1UGPJQ11EU971CLDSW86IR4NA0TCBB/Samal%20Validation%20report.pdf?t=Q0h8bHZ4ZjV4fDBJs3BCrMzPdMLMGb4nizq1)

    2. Validation Report for change in the crediting period of project activity

    /VVM/ UNFCCC Validation and Verification Manual (Version 01.2 as per EB 51)(http://cdm.unfccc.int/Reference/Standards/accr_man01.pdf)

    /VVS/ Clean Development Mechanism Validation and Verification Standard(Version 02.0, EB-65, Annex-4)(http://cdm.unfccc.int/Reference/Standards/accr_stan02.pdf)

    /TA/ Tool to calculate the emission factor for an electricity system, Version 02.2.1,EB-63, Annex-19.(http://cdm.unfccc.int/methodologies/PAmethodologies/tools/am-tool-07-v2.2.1.pdf)

    Table 7-3: Websites used

    Reference Link Organisation

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

  • 7/27/2019 Verification report

    47/79

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Reference Link Organisation

    of Power

    /GRIDCO/ http://www.gridco.co.in/ GRIDCO Limited

    /imd/

    http://www.imd.gov.in/section/hydro/dynamic/rfmaps/period/p30092009.jpg

    http://www.imd.gov.in/section/hydro/dynamic/rfmaps/period/p04112009.jpg

    India Meteorological Department,Government of India

    /eia/ http://www.envfor.nic.in/divisions/iass/notif/eia.htm

    Ministry of Environment and Forests

    /optcl/ http://www.optcl.co.in/ Orissa Power TransmissionCorporation Limited

    /unfccc/ http://cdm.unfccc.int UNFCCC

    Table 7-4: List of interviewed persons

    Reference MoI Name Organisation / Function

    /IM01/ V Mr.Ms K. Yogeshwar Rao GM,Orissa Power Consortium Ltd.

    /IM01/ VMr.Ms

    G.P. Mohapatra Power Plant Manager,Orissa Power Consortium Ltd.

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

  • 7/27/2019 Verification report

    48/79

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Reference MoI Name Organisation / Function

    Ms K.B.S Ele-cons (For Orissa PowerConsortium Ltd.)

    /IM02/ V

    Mr.Ms

    Bhanja Kishor Samal Helper,

    K.B.S Ele-cons (For Orissa PowerConsortium Ltd.)

    /IM03/ VMr.Ms

    V. Naresh Kumar Trainee Engineer,Zenith Energy Services Pvt. Ltd.

    1)Means of Interview: (Telephone, E-Mail, Visit)

    1st Periodic Verification Report: 20MW Samal Grid-connected

    Hydroelectric Project in Orissa, India

  • 7/27/2019 Verification report

    49/79

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    ANNEX

    A1: Verification Protocol

    A2: Appointment / Authorisation

    statements

    1st Periodic Verification Report: 20MW Samal Grid-connected Hydroelectric Project in Orissa, India

  • 7/27/2019 Verification report

    50/79

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Page 50 of 79

    ANNEX 1: VERIFICATION PROTOCOL

    Table A-1: GHG calculation procedures and management control testing / detailed audit testing of residual risk areas and random testing

    Identification of

    potential reporting risk

    Identification,assessment and testing

    of management controls

    Areas of residual risksAdditional verification

    testing

    Conclusions andAreas Requiring

    Improvement

    (including ForwardAction Requests)

    Raw data generation

    Installation ofmeasuring equipment

    Dysfunction ofinstalled equipment

    Maloperation byoperational personnel

    Downtimes ofequipment

    Exchange ofequipment

    Change of

    measurementequipmentcharacteristic

    Insufficient accuracy

    Change oftechnology

    Installation of modernand state of the artequipment

    Process controlautomation

    Internal data review

    Regular visual inspect-ions of installed equip-ment

    Only skilled and trainedpersonnel operates the

    relevant equipment Daily raw data checks

    Immediate exchange ofdysfunctionalequipment

    Stand-by duty is

    Inadequate installation /operation of the monitoringequipment

    Inadequate exchange ofequipment

    Change of personnel

    Undetected measurementerrors

    Inappropriateness ofManagement systemprocedures w.r.t. monitoring

    plan requirements (e.g.substitute value strategies)

    Non-application ofmanagement systemprocedures

    Insufficient accuracy

    Inappropriate QA/QC

    Site visit

    Check of equipment

    Check of technical data

    sheetsCheck of suppliers

    information / guarantees

    Check of calibrationrecords, if applicable

    Check of maintenancerecords

    Counter-check of rawdata and commercialdata

    Check of CDMmanagement system

    Check of CDM relatedprocedures

    See Table A-2

    1st Periodic Verification Report: 20MW Samal Grid-connected Hydroelectric Project in Orissa, India

  • 7/27/2019 Verification report

    51/79

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Page 51 of 79

    Identification ofpotential reporting risk

    Identification,assessment and testingof management controls

    Areas of residual risksAdditional verification

    testing

    Conclusions andAreas Requiring

    Improvement(including ForwardAction Requests)

    Accuracy of valuessupplied by ThirdParties

    organized

    Training Internal audit

    procedures

    Internal check ofQA/QC measures ofinvolved Third Parties

    measures of Third Parties Application of CDMmanagement systemprocedures

    Check of trainings

    Check of responsibilities

    Check of QA/QCdocumentation / eviden-ces of involved ThirdParties

    Raw data collection and data aggregation

    Wrong data transferfrom raw data to dailyand monthlyaggregated reportingforms

    IT Systems

    Spread sheetprogramming

    Manual datatransmission

    Data protection

    Responsibilities

    Cross-check of data

    Plausibility checks ofvarious parameters.

    Appropriate archivingsystem

    Clear allocation ofresponsibilities

    Application of CDMManagement systemprocedures

    Usage of standardsoftware solutions

    Unintended usage of olddata that has been revised

    Incomplete documentation

    Ex-post corrections ofrecords

    Ambiguous sources ofinformation

    Non-application ofmanagement systemprocedures

    Manual data transfermistakes

    Check of dataaggregation steps

    Counter-calculation

    Data integrity checks bymeans of graphical dataanalysis and calculationof specific performancefigures

    Check of managementsystem certification

    Check of data archivingsystem

    See Table A-2

    1st Periodic Verification Report: 20MW Samal Grid-connected Hydroelectric Project in Orissa, India

  • 7/27/2019 Verification report

    52/79

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Page 52 of 79

    Identification ofpotential reporting risk

    Identification,assessment and testingof management controls

    Areas of residual risksAdditional verification

    testing

    Conclusions andAreas Requiring

    Improvement(including ForwardAction Requests)

    (Spreadsheets)

    Limited access to ITsystems

    Data protectionprocedures

    Unintended change ofspread sheet programming

    or data base entriesProblems caused by

    updating/upgrading orchange of applied software

    Check of application ofManagement system

    procedures

    Other calculation parameters

    Emission factors,oxidation factors,coefficients

    The values and datasources applied aredefined in the PDD andmonitoring plan

    Unintended or intendedModification of calculationparameters

    Wrong application of values

    Misinterpretations of theapplied methodology and/or the PDD

    Missing update ofapplicable regulatory

    framework (e.g. IPCCvalues)

    Update-check ofregulatory framework

    Countercheck of theapplied MP in the MRagainst the methodologyand the PDD

    See Table A-2

    Calculation Methods

    1st Periodic Verification Report: 20MW Samal Grid-connected Hydroelectric Project in Orissa, India

  • 7/27/2019 Verification report

    53/79

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Page 53 of 79

    Identification ofpotential reporting risk

    Identification,assessment and testingof management controls

    Areas of residual risksAdditional verification

    testing

    Conclusions andAreas Requiring

    Improvement(including ForwardAction Requests)

    Applied formulae

    Miscalculation Mistakes in spread-

    sheet calculation

    Advanced calculationand reporting tools

    A CDM coordinator is incharge of the CDMrelated calculations

    Usage of tested /counterchecked Excelspreadsheets

    Involvement of external

    consultants

    The danger of miscal-culation can only be

    minimized.

    Countercheck on thebasis of own calculation.

    Spread sheet walk-trough.

    Plausibility checks

    Check of plots

    See Table A-2

    Monitoring reporting

    Data transfer to theauthor of themonitoring report

    Data transfer to themonitoring report

    Unintended use ofoutdated versions

    An experienced CDMconsultant isresponsible formonitoring reporting.

    CDM QMS procedures

    are defined

    The danger of data transfermistakes can only beminimized

    Inappropriate application ofQMS procedures

    Counter check withevidences provided.

    Audit of procedureapplication

    See Table A-2

    1st Periodic Verification Report: 20MW Samal Grid-connected Hydroelectric Project in Orissa, India

    TV NORD JI/CDM C ifi i P

  • 7/27/2019 Verification report

    54/79

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Page 54 of 79

    Table A-2: (Project specific) Periodic Verification Checklist

    Checklist Item(incl. guidance for the verification team)

    Refe-rence

    Verification Team Comments(Means and results of assessment)

    DraftConcl.

    FinalConcl.

    A. General Description of the project activity

    A.1. Brief description of the project activity(EB 54 Annex 34, A.1)

    Check if section A.1 of the MR includes the following:

    - Purpose of the PA and the measures taken toreduce GHG emissions

    - Brief description of the installed technology andequipments

    - Relevant dates for the project activity (e.g.construction, commissioning, continuedoperation periods etc.

    - Total emission reductions achieved in thismonitoring period

    /MR//PDD/

    The verification team has checked section A.1 of the MR and

    confirms that the information provided is complete and correctwith regards to the following:

    Purpose of the PA and the measures taken to reduceGHG emissions

    Brief description of the installed technology andequipments

    Relevant dates for the project activity (e.g. construction,

    commissioning, continued operation periods etcTotal emission reductions achieved in this monitoringperiod

    In this context the following findings have been identified:

    The Verification team checked section A.1 of the monitoringreport and confirms that the section included the purpose of theproject activity as renewable power generation and export of

    power to NEWNE grid of India. The brief description oftechnology is also appropriately stated under section A.1 ofmonitoring report. The relevant dates of commissioning andsynchronizing with grid are mentioned under section A.1 of themonitoring report. The section A.1 also mentions the emissionreductions achieved by the project activity.

    OK OK

    A.2. Project Participants /MR/The verification team has checked section A.2 of the MR andconfirms that the information provided is complete and correct

    OK OK

    1st Periodic Verification Report: 20MW Samal Grid-connected Hydroelectric Project in Orissa, India

    TV NORD JI/CDM Certification Program

  • 7/27/2019 Verification report

    55/79

    TV NORD JI/CDM Certification Program

    P-No: 8106772122 10/269

    Page 55 of 79

    Checklist Item(incl. guidance for the verification team)

    Refe-rence

    Verification Team Comments(Means and results of assessment)

    DraftConcl.

    FinalConcl.

    (EB 54 Annex 34, A.2)

    Check if section A.2 of the MR includes the following:

    - All PPs as displayed on the UNFCCC website

    /MoC/ with regards to