verification report for · ssrs* baseline: emissions from decomposition of biomass and methane...
TRANSCRIPT
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Verification Report for:
Sundre Forest Product THF Biomass Burner Project (3157-5491)
Proponent:
Sundre Forest Products Inc.
Prepared by:
Tetra Tech Canada Inc.
Prepared for:
West Fraser Mills Ltd.
Version:
Final
Date:
April 20, 2018
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 2 of 43
Table of Contents
1.0 Summary – Offset Project ............................................................................................. 4
2.0 Introduction ................................................................................................................ 7
2.1 Objective ............................................................................................................ 7
2.2 Scope ................................................................................................................. 8
2.3 Level of Assurance ............................................................................................... 9
2.4 Criteria ............................................................................................................... 9
2.5 Materiality ........................................................................................................... 9
3.0 Methodology ................................................................................................................ 9
3.1 Procedures ........................................................................................................ 10
3.1.1 Verification Procedures ............................................................................. 10
3.1.2 Verification Steps ..................................................................................... 11
3.1.3 Site Visit ................................................................................................. 12
3.1.4 Risk Assessment ...................................................................................... 12
3.1.5 Verification and Sampling Plan ................................................................... 13
3.2 Team ................................................................................................................ 13
3.3 Schedule ........................................................................................................... 15
4.0 Results ..................................................................................................................... 15
4.1 Assessment of Internal Data Management and Controls .......................................... 15
4.2 Assessment of GHG Data and Information ............................................................. 16
4.3 Assessment against Criteria ................................................................................. 17
4.4 Evaluation of the GHG Assertion ........................................................................... 18
4.5 Summary of Findings .......................................................................................... 18
4.6 Opportunity for Improvement .............................................................................. 20
5.0 Closure ..................................................................................................................... 20
5.1 Verification Statement ........................................................................................ 20
5.2 Limitation of Liability .......................................................................................... 20
5.3 Confirmations .................................................................................................... 21
6.0 References ................................................................................................................ 21
Appendix A: Final Verification Plan and Sampling Plan ............................................................ 22
Appendix B: Statement of Qualifications................................................................................ 30
Appendix C: Findings and Issues .......................................................................................... 33
Appendix D: Statement of Verification .................................................................................. 36
Appendix E: Conflict of Interest Checklist .............................................................................. 39
Appendix F: Limitation on Use of this Document..................................................................... 42
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 3 of 43
List of Tables
Table 1: Scope ..................................................................................................................... 8
Table 2: Verification Procedures ........................................................................................... 10
Table 3: Risk Assessment and Procedures ............................................................................. 13
Table 4: Schedule .............................................................................................................. 15
Table 5: Summary of Internal Controls ................................................................................. 16
Table 6: GHG Data and Informaiton...................................................................................... 17
Table 7: Offset Criteria Assessment ...................................................................................... 17
Table 8: Summary of Findings ............................................................................................. 19
Table 9: Detailed Findings and Issues Log ............................................................................. 34
List of Figures
Figure 1: Verification Steps ................................................................................................. 12
Figure 2: Data Management and Flow ................................................................................... 16
Instructions are in italics throughout and should not be deleted when report is complete. Some instructions
are specific to the verification of facilities and for offset projects. The document is not restricted but do not
alter the format, the layout, the headings or the overall ‘look and feel’ of the document. If if is more usefule
to paste information outside of the text box, use the empty line just below the text box to drop text or
tables int. This should not change the headings or the formats. There are several dropdown boxes in the
document that must be completed.
• Complete report in Verdana 10pt font (no italics).
• After the report is complete, right click the table of contents and ‘update field’ which will update page numbers in Table of Contents.
• If an instruction only applies to facilities or only applies to offsets indicate ‘not applicable’.
• Appendix F is available for additional tables, diagrams etc.
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 4 of 43
1.0 Summary – Offset Project
Item Description
Project Title
Enter project title (must match the registry
project title)
Sundre Forest Product THF Biomass Burner project
Project Description
Provide a brief description of the project and
baseline conditions.
The Project involves direct Greenhouse Gas (GHG)
emission reductions by reducing natural gas
consumption.
Project Location
Include the latitude and longitude for each
unique location or installation. Include legal
land location if applicable and other
information identifying the unique location.
Sundre Forest Products Inc. is located approximately
3 km West of Sundre, Alberta on highway 584. The
legal description of the site is 5541 Hwy 584, 5-05-
032-31 NW.
Latitude: 51.791258. Longitude: -114.705591
Project Start Date
Enter the project start date.
October 2007
Offset Start Date
Enter the start date for offset credit
generation.
January 1, 2008
Offset Crediting Period
Enter the offset crediting period, including the
offset start date. Include day, month year.
Initial project credit duration period: January 1, 2008
to December 31, 2015
Reporting Period
Enter the reporting period being verified.
January 1, 2014 – December 31, 2015
GHG Assertion (Actual Emission
Reductions/Sequestration Achieved)
Enter the actual emissions reductions /
sequestration for the reporting period. Enter
serial numbers if available.
2014: 10,378 t CO2e
2015: 10,340 t CO2e
Protocol
Indicate the relevant protocol (if
applicable)
Diversion of Biomass to Energy from Biomass
Combustion Facilities Quantification Protocol (Version
1.0, September 2007)
Ownership
Enter offset project owner.
Sundre Forest Products Inc.
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 5 of 43
Project Activity
State how the project activity meets the
eligibility requirements
Site visit confirmed the reduction occurs in Alberta
Combustion of biomass waste is not required by law
for energy generation.
Project started commercial operations October, 2007
The Project reductions/removals are real,
demonstrable, quantifiable and verifiable: The Project
is creating real reductions that are not a result of
shutdown, cessation of activity or drop in production
levels.
Activity data is measured and emissions are
quantified using the approved protocol.
The verification team meets the requirements set out
in the Standard for Verification (Version 1.0 Dec.
2017) Part 1 Section 3.
Project Contact
Enter contact name, company name, mailing
address, phone number and email address.
Veikko Paivinen, CPA
Financial Manager, Energy and Carbon
West Fraser Mills Ltd.
1250 Brownmiller Road, Quesnel, BC V2J 6P5
Tel: (250) 992-0804
Email: [email protected]
Verifier
Verifier name, verifier’s company name,
address, phone number email etc.
Min Si, M.N.R.M, GHG-V
Tetra Tech Canada Inc.
115, 200 Rivercrest Drive SE, Calgary, AB T2C 2X5
Tel: (403) 369 5254
Email: [email protected]
Verification Team Members
Include verification team members, roles,
training, training dates and qualifications.
Nelson Lee, M.A.Sc, P. Eng., GHG-V, Designated
Signing Authority. Mr. Lee has completed ISO 14064-
3 training in March 2006.
Min Si, M.N.R.M, GHG-V, Lead Verifier. Mr. Si
completed ISO 14064 – 3 training in December 2015.
Nancy Wellhausen, Peer Reviewer. Ms.Wellhausen
completed ISO14064 -3 training in June 2017.
Kathleen Dunnett, P.Eng., Verifier
Designated Signing Authority
Enter the designated signing authority for this
verification.
Nelson Lee, M.A.Sc, P. Eng., GHG-V
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 6 of 43
Verification Strategy
Describe the verification strategy used for the
verification, including rationale for the
approach. Note, if a controls reliance is used,
provide justification for how the project is
able to support this approach.
The strategy used in this verification approach relies
on substantive procedures. Tetra Tech applies
predominantly substantive procedures during the
verification process, with a focus on source data and
evidence gathered during site visits and sampling
procedures. Tetra Tech has developed the following
steps to substantiate the GHG assertion:
• Conducted a site visit to confirm the boundary, physical sources, sinks and reservoirs (SSRs) at the facility.
• Observed, interviewed personnel, and verified various processes, instrumentation and data management procedures during the site visit.
• Conducted sampling on primary documentation to confirm the processes resulting in the GHG assertions.
• Reviewed original data sources and calculations.
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 7 of 43
2.0 Introduction
Provide an introduction to the facility or project, the verification, and the background.
For Offset Project: summary of offset project baseline, changes to the baseline since project start date and
summary of changes at the project since the offset project start date or baseline period.
For Facilities: Description of compliance or baseline report, facility/project boundary, facility identification
information, GHG historical performance, summary of changes since the baseline or since the last
compliance report.
Tetra Tech Canada Inc. (Tetra Tech) was contracted by Sundre Forest Products Inc. (Sundre), a
division of West Fraser Mills Ltd.(West Fraser) to conduct verifications of greenhouse gas (GHG)
emission reductions for its Sundre Forest Product Lumber Thermally Heated Fluid (THF) Biomass
Burner Project (Project) for the period of January 1, 2014 to December 31, 2015.
Revision 1 to the Verification Report
The verification report was original issued on October 6, 2016 (Tetra Tech File Number 704-
ENVIND03938-01.002). The project developer – West Fraser submitted the verification report to
the CSA Registry for serialization in 2018.
As required by Alberta Environment and Parks - Climate Change Office (ACCO), offset project
verification reports submitted after January 1, 2018 must use the updated template (dated
December 2017). This revision is to update the verification report using the new template.
Summary of Offset Project Baseline
The Project is a biomass to energy carbon offset project at the Sundre facility. Prior to the Project,
lumber was dried in a kiln by a natural gas – fired forced hot air system. The offset project involved
the design and installation of a dual biomass furnace to produce thermal energy from the wood
waste generated by the facility. The thermal energy heats a hot oil system, and heated thermal oil
is circulated through the kilns to dry dimensioned lumber.
Summary of Changes to Baseline or at the Project Condition
There are no changes or modifications to the project operations and data collection. Quantification
changes are provided in the Offset Project Report.
2.1 Objective
Describe the objective of the verification (should include expressing an opinion).
The objective of this verification is to provide an independent assessment of the offset project to
identify any material and immaterial errors, omissions or misrepresentations, and to provide our
opinion on the GHG assertion in the Offset Project Report.
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 8 of 43
2.2 Scope
Define the scope in terms of: geographical, organizational, activities and processes, sources, sinks,
categories and greenhouse gases included (considering the completeness of the inventory), GHG assertion
time period.
For offset verifications: include the serial range (i.e. XXXX-XXXX-XXX-XXX-XXX-XXX to XXXX-XXXX-XXX-
XXX-XXX-XXX) if assigned (i.e. in the case of government verification a serial range will be available,
otherwise not applicable).
For Facilities: ensure all specified gases and source categories are evaluated. Include list of negligible
emission sources and justification for Emission Performance Credits (EPCs). Include listing of end products.
The scope of this Project level emission reduction verification includes the project boundaries,
physical infrastructure, activities, technologies, and processes of the project, GHG sources, sinks,
and/or reservoirs (SSRs), types of GHGs, and time periods covered.
The scope of the verification is listed in Table 1
Table 1: Scope
Item Sundre Forest Product THF Biomass Burner project
Geography Sundre Forest Products Inc. is located approximately 3 km West of
Sundre, Alberta on highway 584. The legal description of the site is
5541 Hwy 584, 5-05-032-31-NW.
Latitude: 51.791258. Longitude: -114.705591
Organization Sundre Forest Products Inc.
Activities and Processes Thermal energy generation from biomass combustion.
SSRs* Baseline: Emissions from decomposition of Biomass and Methane
collection and destruction (B9 and B10), Electricity production (B11),
Thermal energy produced (B12), Fuel extraction and processing
(B13)
Project: Emissions from facility operation P6, P8 to P11, P13, P14 and
P16, Combustion of biomass (P12), Fuel extraction and processing
(P22)
GHG Carbon dioxide (CO2), Methane (CH4), Nitrous oxide (N2O)
GHG Assertion 2014: 10,378 t CO2e
2015: 10,340 t CO2e
Time Period January 1, 2014 to December 31, 2015
*included sources as specified in the Protocol.
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 9 of 43
2.3 Level of Assurance
The verification was conducted to a reasonable level of assurance.
Choose type of verification from the dropdown box above.
Provide explanation on level of assurance.
The level of assurance is used to determine the depth of detail that a verifier designs into their
verification plan to determine if there are any material errors, omissions, or misrepresentations.
Reasonable level of assurance is conducted to evaluate whether the GHG assertion is deemed to be
presented fairly and substantiated by sufficient and appropriate evidence. As such, the goal of
verification is to provide positive, but not absolute assurance regarding the GHG assertions.
2.4 Criteria
Outline the program criteria used and relevant supporting documentation (acts, regulations, protocols,
standards, guidance documents, project documentation etc).
The verification assesses the Project against Alberta Offset program eligibility criteria, including
• Alberta Carbon Competitiveness Incentive Regulation (CCIR), December 18, 2017;
• Standard for Greenhouse Gas Emission Offset Project Developer (Version 1.0, December 2017);
• Standard for Verification (Version 1.0 December 2017);
• Quantification Protocol for Quantification Protocol for Diversion of Biomass to Energy from Biomass Combustion Facilities (Version 1.0, September 2007);
• Offset Project Plan for Sundre Forest Product THF Biomass Burner Project; and
• Offset Project Report for Sundre Forest Product THF Biomass Burner Project.
2.5 Materiality
Define the materiality of the verification.
A 5% materiality threshold is set to assess errors, omissions, and misrepresentations in the GHG
assertion as required by the CCIR. Quantitative discrepancies are aggregated and assessed on the
basis of net and absolute values. Qualitative discrepancies are evaluated by professional judgement
of the verification body, and assessed to determine if the discrepancies could be deemed to be
material errors.
3.0 Methodology
Statement that the verification is performed according to ISO 14064-3.
Summary of the assessments/tests/reviews/evaluations that were conducted during the verification.
The verification is performed according to ISO 14064-3: Specification with Guidance for the
Validation and Verification of GHG Assertions.
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 10 of 43
Tetra Tech applies predominantly substantive procedures during the verification process, with a
focus on source data and evidence gathered during site visits and sampling procedures. Tetra Tech
has developed the following steps to substantiate the GHG assertion:
• Conducted a site visit to confirm the boundary, physical sources, sinks and reservoirs (SSRs) at the facility.
• Observed, interviewed personnel, and verified various processes, instrumentation and data management procedures during the site visit.
• Conducted sampling on primary documentation to confirm the processes resulting in the GHG assertions.
• Reviewed original data sources and calculations.
The assessments, tests, reviews, and/ or evaluations that were conducted during the verification
include inspection, observation, inquiry, confirmation, recalculation, and analytics test. The detailed
verification procedures are provided in below Section.
3.1 Procedures
Description of how the verification was conducted including: description of the nature, scale and complexity
of the verification activity, confidence and completeness of the responsible party’s GHG information and
assertion, assessment of GHG information system and its controls, assessment of GHG data and
information, assessment of GHG information system and controls, assessment against criteria, evaluation of
the GHG assertion.
Describe steps of the verification including planning, assessment, site visit, off-site verification, and report
preparation.
Describe how the risk based approach was implemented in the sampling plan. Identify categories of risk
including inherent risk, and detection risk (organization and verifier). Include the Verification Plan with the
Sampling Plan in Appendix A. Paste the risk assessment table in this section.
3.1.1 Verification Procedures
Verification procedures for the key components are provided in Table 2.
Table 2: Verification Procedures
Verification Component Procedures
Description of the nature, scale
and complexity of the verification
activity
The verification is conducted for Sundre THF Biomass Burner
project. The project is a biomass to energy generation
project, replacing natural gas consumption at the Sundre
facility to dry lumber.
The quantification of the offset project is assessed against
Quantification Protocol Diversion of Biomass to Energy from
Biomass Combustion Facilities (Version 1.0, September
2007).
The offset project generated approximately 12,000 tonnes of
CO2e emission reductions annually in 2008 – 2015.
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 11 of 43
The complexity of the verification is deemed to be low, as
there are limited emission sources, including:
• Baseline: Emissions from Thermal energy produced (B12), Fuel extraction and processing (B13)
• Project: Emissions from Facility operation (P6, P8 to P11, P13, P14 & P16), Combustion of biomass (P12), Fuel extraction and processing (P22)
Comparability with the baseline • Review the baseline calculations and supporting documents.
• Review Project Plan and Report.
• Interview facility operators.
Confidence and completeness of
the responsible party’s GHG
information and assertion
• Conduct a site tour to determine GHG sources and compare with the Protocol and calculation tool for completeness.
• Check the quantification against the Protocol.
• Interview personnel for completing GHG quantification.
Assessment of GHG information
system and its controls
• Review data collection and transfer processes.
• Interview personnel for internal control procedures.
• Inquiry data verification procedures for double entries.
• Examine natural gas and biomass records reconciliation.
Assessment of GHG data and
information
• Compare sources and sinks inspected through site visit to the GHG identified in the Project Report and calculator.
• Review raw data, including metering data and 3rd party records.
• Review emission factors used.
Assessment against criteria • Review and check against related criteria.
• Conduct site visit for physical boundary.
Evaluation of the GHG assertion • Recalculate GHG assertions.
• Evaluate supporting documents.
3.1.2 Verification Steps
The verification follows the steps outlined in the following diagram (Figure 1).
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 12 of 43
Figure 1: Verification Steps
3.1.3 Site Visit
Mr. Min Si of Tetra Tech visited the facility on June 9, 2015. The purpose of the site visit was to
gain an understanding of the offset project’s operation, equipment, and control processes for
assessment of the Project’s conformance with the Criteria. During the site visit, the emission
sources, various processes, data acquisition and onsite records handling processes were observed.
The control devices that were used to collect and monitor activity data for emission calculations
were also observed.
3.1.4 Risk Assessment
As part of the verification process, a risk-based verification and sampling plan must be developed
that outlines:
• The amount and type of evidence necessary to achieve the agreed level of assurances;
• Methodologies for determining representative samples; and
• Risks of potential errors, omissions, or misrepresentation
Tetra Tech’s verification team utilizes the risk assessment process to develop a compliant
verification and sampling plan. The risk assessment includes considerations associated with
regulatory requirements, GHG program requirements, industry/sector specific factors, and other
non-technical risks.
Acceptance
•Client and verification evaluation• Independence and team evaluation
Planning
•Gain an understanding - data and process flow, historical analysis•Risk assessment, planining analytics, contribution analysis and materiality analysis•Verification strategy, verification plan, sampling plan
Execution
•Conduct verification procedures and collect evidence•Review evidence against program criteria•Document findings log and unadjusted differences
Completion
•Conclusion: senior review, Issue for Review verification report•Peer review: approval and sign off• Issuance: Issue for Use verification report
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 13 of 43
The risk assessment considers inherent risk, control risk and detection risk. Inherent risk is the
Responsible Party’s risk of material error, omission, or discrepancy due to the complexity of the
facility or lack of capacity by staff at the facility. Control risk is the risk that the Responsible Party’s
control system will not detect and rectify a material error, omission or discrepancy. Detection risk
is the risk that the Tetra Tech verification team will not identify a material discrepancy. The method
to determine the risk is provided in Appendix A – Verification Plan.
The risk assessment for the applicable reporting elements are provided in Table 3.
Table 3: Risk Assessment and Procedures
Line Item Risk Procedures
GHG Assertions • Incomplete inventory
• Inappropriate data and emission factors used
• Incorrect GHG assertions
• Conduct site visit to inspect boundary and SSRs.
• Check emission factors, raw data, and quantification methodologies
• Check calculations
Biomass Combustion • Incorrect measurement
• Incorrect emission factors
• Inspect raw data records
• Review the method used to estimate biomass volume and moisture content
• Check the emission factors
Natural Gas
Consumption
• Incorrect fuel consumption
• Inaccurate calculation
• Review raw data records
• Recalculation
Thermal Energy
Produced
Inaccurate calculation Recalculation
Electricity consumption incorrect calculation Review the method used to estimate
electricity consumption
3.1.5 Verification and Sampling Plan
Convenience sampling methods are used for the verification. The sample plan is developed based
on the risk assessment to achieve an overall low detection risk. The sample size is based on the
Guidance Document for GHG verification sampling by the European Commission with verifier’s
professional judgement. The sample size varies based on the number of evidence records. The type
and amount of evidence reviewed for each emission source is provided in the Final Verification Plan
(Appendix A).
3.2 Team
List verification team members including peer reviewer(s).
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 14 of 43
Describe the qualifications and training of the team members and peer reviewer(s) including dates of
training and certifications.
For Offsets: fill in the sample Statement of Qualification provided and included in Appendix B.
For Facilities: include the Statement of Qualifications from the facility compliance form in Appendix B.
The verification team meets the requirements under the Carbon Competitiveness Incentive
Regulation (CCIR) and have the technical knowledge of GHG emission quantification methodologies
required by Standard for Verification (ACCO Version 1.0 December 2017) Part 1 Section 3. The
team members have experience in completing third party GHG verifications, reviews and audits
related to emission inventories, including verifications in Alberta. Verification team members have
been trained under ISO 14064-3.
Nelson Lee, M.A.Sc., P.Eng., GHG-V is the Designated Signing Authority and Lead Verifier for
this verification. Mr. Lee has a B.Sc. in Chemical Engineering from the University of Alberta, and a
M.A.Sc. in environmental engineering from the University of British Columbia. He has 20 years of
experience in the oil and gas industry, and has completed over 100 GHG verifications in Alberta
and BC. Mr. Lee completed ISO 14064 – 3 training with Environment Canada in March 2006. Mr.
Lee is a CSA certified GHG verifier, and a California Air Resources Board (ARB) registered offset
project lead verifier.
Mr. Lee is responsible for ensuring:
• the verification acceptance requirement have been met as outlined in the Technical Guidance;
• the verification was conducted in accordance with ISO 14064-3 standard, and the Tetra Tech’s management system for quality assurance and control and independence has been applied during the verification;
• the verification was conducted in a professional manner; and
• the verification report was presented appropriately.
Nancy Wellhausen is the Peer Reviewer for this audit. Ms. Wellhausen is a Senior Air Quality
Scientist specializing in emission inventory development, dispersion modeling, air quality impact
analysis and assessments, and regulatory reporting. Ms. Wellhausen had GHG verification training
with California ARB, and is a ARB registered lead verifier. Her responsibilities include independent
review of verification deliverables and supporting documentation to confirm all verification activities
have been completed, and conclude whether the GHG assertion is free of material discrepancy and
the verification activities conducted achieved a reasonable level of assurance.
Kathleen Dunnett, P.Eng. is a Verifier for this audit. Ms. Dunnett is a Professional Engineer with
a degree in Chemical and Petroleum Engineering and is an Environmental Auditor with over 20
years of experience in regulatory compliance auditing and environmental management systems.
Ms. Dunnett has training in ISO 9001 and 14001 auditing standards. She conducted data review for
this project.
Min Si, M.N.R.M., GHG-V is the Lead Verifier for this verification. Mr. Si is an Environmental
Scientist with Tetra Tech in Calgary. He has worked on GHG verification and quantification projects
for a wide range of sectors, including oil and gas, pulp and paper, agriculture, manufacturing, etc.
His emission experience includes GHG life cycle assessment, GHG quantification and verification for
carbon offset projects, compliance report verification, National Pollution Registry Inventory (NPRI)
and corporate GHG reporting. Mr. Si has completed CSA ISO 14064 3 training with CSA in
December 2015. Mr. Si is responsible for:
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 15 of 43
• managing the verification project;
• ensuring the team has appropriate competencies for the verification;
• communicating to key members of the responsible party regarding the verification objectives and results
The Statement of Qualifications is provided in Appendix B
3.3 Schedule
Provide a list or table of verification activities and dates. Indicate when the verification was completed.
The schedule for the verification is presented in Table 4.
Table 4: Schedule
Activity Date
Kick-off Meeting and Initial Information Request April 14, 2015
Site Visit June 9, 2015
Desktop Review April 14, 2015 – August 6, 2016
Submit “Issued for Review” Report September 9, 2016
“Issued for Use” Report Delivered October 6, 2016
Revision to the Issue for Use Report April 20, 2018
4.0 Results
Add introduction to results section here, if desired.
4.1 Assessment of Internal Data Management and Controls
Provide a summary the information system(s) and its controls for sources of potential errors. Include
information on the selection and management of data, process for collecting and consolidating data, data
accuracy systems, design and maintenance of the GHG system, the systems and processes that support the
GHG information system and results from previous assessments if applicable.
The data management and flow is presented in Figure 1.
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 16 of 43
Figure 2: Data Management and Flow
The internal control procedures are summarized in Table 5.
Table 5: Summary of Internal Controls
Reporting Element Controls
Natural Gas Consumption 3rd party invoices and internal accounting
Biomass Consumption Internal accounting and DCS operator
Electricity Engineering
GHG Quantification Quantifier and facility manager review
Conclusion
The internal data management and controls are assessed based on the review of the Offset Project
Plan, observations during the site visits, and interviews with key project personnel. The internal
data management and controls for the offset project are deemed to be adequate.
4.2 Assessment of GHG Data and Information
Provide a summary of the information found during the verification of the GHG data and a summary of the
GHG Assertion that was assessed.
Natural gas Biomass Quantity Electricity
3rd party invoice DCS, # of dumps Estimated
Accounting: Separate gas usage
of wood treating facility
from the invoice
Accounting: Compile natural gas and biomass data
into spreadsheet
Quantifier: Quantify the GHG reductions using the spreadsheet
Offset project report
Manual Auto
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 17 of 43
For Facilities: Confirm that the quantification methodologies that were used in the compliance report are the
same as those reported in the BEIA.
For Offset Projects: Confirm that the quantification methodologies that were used by the project proponent
are the same as those described in the project plan. Indicate which quantification methodologies were used
by the project proponent.
The GHG data and information provided to support the GHG assertion is deemed to be sufficient.
The quantification methodologies used are consistent with the Offset Project Plan and the
Quantification Protocol.
The GHG data and information used to support the Assertion are presented in Table 6.
Table 6: GHG Data and Informaiton
Project Component Data and Information
Natural gas consumption 3rd party invoices
Biomass quantity Production Accounting records
Electricty consumption Field measurement
4.3 Assessment against Criteria
Provide a description of how eligibility criteria is met or not met.
For Offset Project: Complete Table 1 to indicate if the GHG Assertion conforms to the Regulation and
Standard for Greenhouse Gas Emission Offset Project Developers eligibility criteria.
For Facilities: Delete Table 1 and Indicate if verification criteria are met or not met and explain.
The assessment against program eligibility criteria is provided in Table 7. It is our opinion that the
eligibility criteria are met.
Table 7: Offset Criteria Assessment
Offset Eligibility Criteria Assessment
Reduction or sequestration occurs in
Alberta
Site visit confirmed the project’s physical location.
Result from actions not required by Law
at the time the action is taken
Combustion of biomass waste is not required by law
for energy generation.
Result from Actions taken on or after
January 1, 2002 and occur on or after
January 1, 2002
Project started commercial operations January 1,
2008.
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 18 of 43
Reduction or sequestrations is real and
demonstrable
The Project reductions/removals are real and
demonstrable. The Project is creating real reductions
that are not a result of shutdown, cessation of
activity or drop in production levels.
Quantifiable and measureable Activity data is measured and emissions are
quantified using the approved protocol.
Verified by a third party verifier that
meets the requirements in Part 1 for the
Standard for Verification.
The verification team meets the requirements set
out in the Standard for Verification (Version 1.0 Dec
2017) Part 1 Section 3.
4.4 Evaluation of the GHG Assertion
Provide an assessment of the evidence collected during the verification. Determine if the data and
information available support the GHG assertion. Provide a conclusion on whether the assertion meets the
materiality requirements and the level of assurance agreed to at the beginning of the verification process.
The verification assessment is that the GHG Assertion meets the requirements of the Carbon
Competitiveness Incentive Regulation
The GHG data and supporting documents are deemed to be sufficient and appropriate. The GHG
assertion is calculated in accordance with the approved quantification protocol.
It is our opinion that
• 10,378 t CO2e of the emission reductions for the period of Jan 1, 2014 to December 31, 2014 and
• 10,340 t CO2e of the emission reductions for the period of Jan 1, 2015 to December 31, 2015
meet the materiality requirements and the reasonable level assurance criteria.
4.5 Summary of Findings
Provide a summary of material and immaterial discrepancies expressed in tonnes and as net and absolute
error in Table 2. Include whether the discrepancy was an understatement or an overstatement.
Include a more detailed description and log of results in Appendix C the “Issues Log”. This log will include
both resolved and unresolved issues from the verification. Unresolved issues should be brought forward to
Table 2.
During the verification, no material misstatements were identified. There are no unresolved
immaterial findings remained. The detailed description of the findings is provided in Appendix C.
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 19 of 43
Table 8: Summary of Findings
Number the finding with the year and provide a unique # for each finding.
Note: A detailed description of all material and immaterial findings should be provided in Table 3 of Appendix C.
Provide only a summary statement (1-4 sentences) for each unresolved immaterial finding and each material finding (resolved or unresolved). If
the finding is a resolved material finding, then put the tonnes net and absolute in the summary description column and indicate n/a in the net and
absolute columns. Do not include the tonnes in the total error calculation.
Indicate the type of error (qualitative or quantitative).
Indicate the Source Category (for facilities) or the Source/Sink (for offsets).
Indicate if the finding is an understatement or overstatement.
Provide both net and absolute error in tonnes of CO2 eq and as a % of the assertion.
Provide the total net error and the total absolute error in tonnes of CO2 eq and as a % of the assertion.
Result # Type Summary Description of Finding Source
Category or Source/Sink
Understatement/
Overstatement
Tonnes CO2 eq
% net
Tonnes CO2 eq
% absolute
N/A N/A N/A N/A N/A N/A
Total Error
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 20 of 43
4.6 Opportunity for Improvement
Provide feedback on the data management system and controls, transparency, completeness of the
inventory, additions to the quantification methodology document or diagrams, etc. Include positive
considerations and observations also.
Identify strengths and weaknesses that may help to improve the report/s for the current facility, sector, and
compliance program. Identify ways in which the project/facility could be more easily verified.
The quantification is conducted using Excel. The calculator is transparent. The data management
and controls are described and the justification for excluding specified SSRs are provided in the
calculator to facilitate the verification.
5.0 Closure
5.1 Verification Statement
Include the signed verification statement in Appendix D.
Instructions to insert a pdf: 1. Click Insert>Object 2. In the Object dialog box click Create from File and
then click Browse. 3. Find the pdf you want to insert then click Insert. 4.Click OK.
For Offset Projects: fill in the sample Verification Statement provided, sign, scan and paste.
For Facilities: paste a signed version of the Verification Statement from the facility compliance form. Include
the conclusion on the GHG assertion and any qualification or limitations and the level of assurance.
Provide the verification conclusion in the drop down box below.
The verificaion conclusion is: Positive
Based on our review, it is our opinion that Emission Reductions, including
• 10,378 t CO2e of the emission reductions for the period of Jan 1, 2014 to December 31, 2014 and
• 10,340 t CO2e of the emission reductions for the period of Jan 1, 2015 to December 31, 2015
contained in the GHG assertion generated from the Sundre Forest Product THF Biomass Burner
project offset project are materially correct and presented fairly in accordance with the relevant
criteria.
The Statement of Verification is provided in Appendix D.
5.2 Limitation of Liability
Include signed Conflict of Interest Checklist in Appendix E.
For Offset Projects: fill in the sample Conflict of Interest Checklist provided, sign, scan and paste.
For Facilities: paste the signed Conflict of Interest Checklist from the facility compliance form.
Insert limitation of liability statement and include information in an Appendix F if applicable.
Tetra Tech has undertaken the verification of the asserted emission reductions associated with the
Project in accordance with related program criteria. Tetra Tech has assessed the offset project GHG
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 21 of 43
assertion using reasonably ascertainable information as defined by ISO 14064. The assessment
represents the condition in the subject area at the time of the assessment. Tetra Tech did not
conduct direct GHG emissions monitoring or other actual environmental data sampling or analysis
as part of this verification.
The purpose of this report is to identify noted exceptions and observations in the quantification of
emission reductions. This report is not intended to imply exhaustive compliance or non-compliance
by the verification team. The verification team has made diligent effort to sample applicable
information available regarding emission reductions by the Project during the verification. It should
be noted that the inherent limitation in verification sampling and review practices may result in the
verifier not identifying all potential aspects of the project. Observations, exceptions and conclusions
are based on the judgment of the verifier.
The Conflict of Interest Checklist is provided in Appendix E.
5.3 Confirmations
Document information confirmed, including any discrepancies or inconsistencies, as per the Confirmations
section in the Standard for Greenhouse Gas Verification.
As required by ACCO, the verifier has confirmed the following information:
• Consistency of offset project information across offset project documentation;
• Offset project location;
• Methodology document/Project Report exists;
• Offset project contact and the amount of GHG emission reductions; and
• Completeness and accuracy of process and data flow diagram.
6.0 References
Author. Year. Title. (no hyperlinks)
International Organization for Standardization. 2006, ISO 14064-3: Specification with Guidance for
the Validation and Verification of GHG assertions.
Alberta Environment and Parks. 2015. Carbon Offset Emission Factors Handbook (Version 1.0)
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 22 of 43
Appendix A: Final Verification Plan and Sampling Plan
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 23 of 43
Information to be included in the Verification Plan and Sampling Plan:
Revisions to the sampling plan
Date originally sent to Facility/project
Level of assurance agreed with the facility/project developer
Verification scope
Verification criteria
Amount and type of evidence (qualitative and quantitative) necessary to achieve the agreed level of
assurance
Methodologies for determining representative samples
Sampling Plan and Procedures
Risk Assessment: Risks of potential errors, omissions or misrepresentations that are identified throughout
the verification process including:
- Details of site visit
-offset/facility boundaries
- Methodologies, emissions factors and conversions used
- Comparability with the approved baseline
- Conformance to the program criteria
- Integrity for the responsible party’s data management system and control (organization chart, GHGH
management plan, personnel/consultant training, protocols used, control system documentation,
software/program documentation/certifications)
- Greenhouse gas data and information, including the type of evidence collected, verification testing and
crosschecking, inventory of emission sources
- Discussion of data management, (measurement, fuel sampling, calibration, consistent use
of standard conditions, data storage, procedures to fill missing data; procedures to repair inconsistent data,
adjustment of variables and factors)
- Other relevant information
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 24 of 43
April 20, 2018
Attention: Mr. Veikko Paivinen, CPA Financial Manager, Energy and Carbon
Subject: Verification Plan Edson Biomass Energy Generation Project October 1, 2013 to December 31, 2014
A1.0 Introduction
Tetra Tech Canada Inc. (Tetra Tech) was contracted by Sundre Forest Products Inc. to conduct
verifications of greenhouse gas (GHG) emission reductions for its Sundre Forest Product Lumber
Thermally Heated Fluid (THF) Biomass Burner Project (Project) for the period of January 1, 2014 to
December 31, 2015.
A1.1 Objective
The objective of this audit is to provide an independent assessment of the offset project to identify
any material and immaterial errors, omission or misrepresentations and to provide our opinion on
the GHG Assertion in the Offset Project Report.
A1.2 Assurance
The scope and level of effort of this verification is planned to achieve a reasonable level of assurance.
The level of assurance is used to determine the depth of detail that a verifier designs into their
verification plan to determine if there are any material errors, omissions, or misrepresentations.
Reasonable level of assurance is to evaluate whether the GHG assertion is deemed to be presented
fairly and substantiated by sufficient and appropriate evidence. As such, the verification is to provide
positive, but not absolute assurance regarding the GHG assertions.
A1.3 Scope
The scope of this Project level emission reduction verification includes the project boundaries,
physical infrastructure, activities, technologies, and processes of the project, GHG sources, sinks,
and/or reservoirs (SSRs), types of GHGs, and time periods covered.
The scope of the verification is listed in Table A1.
Table A1: Scope
Item Sundre Forest Product THF Biomass Burner project
Geography Sundre Forest Products Inc. is located approximately 3 km West of Sundre,
Alberta on highway 584. The legal description of the site is 5541 Hwy 584, 5-
05-032-31-NW.
Latitude: 51.791258. Longitude: -114.705591
Organization Sundre Forest Products Inc.
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 25 of 43
Activities and Processes Thermal energy generation from biomass combustion.
SSRs* Baseline: Emissions from decomposition of Biomass and Methane collection
and destruction (B9 and B10), Electricity production (B11), Thermal energy
produced (B12), Fuel extraction and processing (B13)
Project: Emissions from facility operation P6, P8 to P11, P13, P14 and P16,
Combustion of biomass (P12), Fuel extraction and processing (P22)
GHG Carbon dioxide (CO2), Methane (CH4), Nitrous oxide (N2O)
GHG Assertion 2014: 10,378 t CO2e
2015: 10,340 t CO2e
Time Period January 1, 2014 to December 31, 2015
*included sources as specified in the Protocol.
A1.4 Verification Standard
The verification is performed according to ISO 14064-3: Specification with Guidance for the Validation
and Verification of GHG Assertions.
A1.5 Verification Criteria
The verification assesses the Project against Alberta Offset program eligibility criteria, including:
• Alberta Carbon Competitiveness Incentive Regulation (CCIR), December 18, 2017;
• Standard for Greenhouse Gas Emission Offset Project Developer (Version 1.0, December 2017);
• Standard for Verification (Version 1.0 December 2017);
• Quantification Protocol for Quantification Protocol for Diversion of Biomass to Energy from Biomass Combustion Facilities (Version 1.0, September 2007);
• Offset Project Plan for Sundre Forest Product THF Biomass Burner Project; and
• Offset Project Report for Sundre Forest Product THF Biomass Burner Project.
A1.6 Materiality
A 5% materiality threshold is set to assess errors, omissions, and misrepresentations in the GHG
assertion as required by the SGER. Quantitative discrepancies are aggregated and assessed on the
basis of net and absolute values. Qualitative discrepancies are evaluated by professional judgement
of the verification body, and determined if the discrepancies could be deemed to be material errors.
A2.0 Data Management and Controls
The Responsible Party’s GHG data management and controls are provided in Section 4.1 in this report.
A3.0 Team
The verification team is presented in Table A2.
Table A2: Verification Team
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 26 of 43
Team Role
Nelson Lee, M.A.Sc., P.Eng. Designated Signing Authority
Min Si, M.N.R.M., GHG-V Lead Verifier
Kathleen Dunnett, P.Eng. Verifier
Nancy Wellhausen Independent Peer Reviewer
A4.0 Schedule
The schedule for the verification is presented in Table A3.
Table A3: Verification Schedule
Activity Date
Kick-off Meeting and Initial Information Request April 14, 2015
Site Visit June 9, 2015
Desktop Review April 14, 2015 – August 6, 2016
Submit “Issued for Review” Report September 9, 2016
“Issued for Use” Report Delivered October 6, 2016
Revision to the Issue ofr Use Report April 20, 2018
A5.0 Risk Assessment
As part of the verification process, a risked-based verification and sampling plan must be developed
that outlines:
The amount and type of evidence necessary to achieve the agreed level of assurances;
Methodologies for determining representative samples; and
Risks of potential errors, omissions, or misrepresentation.
Tetra Tech’s verification team utilizes the risk assessment process to develop a compliant verification
and sampling plan. The risk assessment includes considerations associated with regulatory
requirements, GHG program requirements, industry/sector specific factors, and other non-technical
risks.
The risk assessment considers inherent risk, control risk and detection risk. Inherent risk is the
Responsible Party’s risk of material error, omission, or discrepancy due to the complexity of the
facility or lack of capacity by staff at the facility. Control risk is the risk that the Responsible Party’s
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 27 of 43
control system will not detect and rectify a material error, omission or discrepancy. Detection risk is
the risk that the Tetra Tech verification team will not identify a material discrepancy.
The inherent risk and control risk are rated by likelihood multiplied by consequence in accordance
with the matrix provided in Table A4. The detection risk is based on the combination of the inherent
and control risks.
Table A4: Rating Matrix for Inherent Risk and Control Risk
Risk Matrix
Consequence
Immaterial Minor Moderate Major Material
1 2 3 4 5
Lik
eli
hoo
d
5
5 10 15 20 25 Almost
Certain
4 4 8 12 16 20
Likely
3 3 6 9 12 15
Possible
2 2 4 6 8 10
Unlikely
1 1 2 3 4 5
Rare
The definition for the scoring is provided in Table A5, adapted from Intergovernmental Panel on
Climate Change (IPCC) 2007.
Table A5: Scoring Definition
Score Likelihood Consequence
5 possibility of misstatement >95% misstated GHG assertion (threshold) >5%
4 66% < possibility of misstatement <95% 4%<misstated GHG assertion <5%
3 33% < possibility of misstatement <66% 3%<misstated GHG assertion <4%
2 5% < possibility of misstatement <33% 1%<misstated GHG assertion <3%
1 possibility of misstatement <5% misstated GHG assertion<1%
Inherent risk is determined to be Medium based on the following:
• Natural gas consumption at the sawmill is determined by third party invoice minus Sundre
treating gas usage;
• Biomass quantify is determined estimated biomass volume per dump times numbers of the
dumps; and
• Quantifier is the first time to do this project.
Control risk is determined to be low - medium based on the following:
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 28 of 43
• Natural gas usage for sawmill is manually assigned by production accountant at the Sundre
treating facility; and
• Third party invoice data is manually entered into spreadsheet.
Detection risk is the risk that Tetra Tech’s procedures do not detect a misstatement in the GHG
Assertion. The detection risk is determined based on Table A6, as outlined in the Technical Guidance
for Greenhouse Gas Verification at Reasonable Level Assurance (V1, January 2013).
Table A6: Design of Detection Risk
Control Risk
High Medium Low
Inherent Risk Score from
Table A5
12-25 6-10 1-5
High 12-25 Lowest Lower Medium
Medium 6-10 Lower Medium Higher
Low 1-5 Medium Higher Highest
The verification procedures were designed and performed to achieve low detection risk so that the
overall verification risk is low for a reasonable level of assurance, as specified in the Verification
Technical Guidance.
A summary of risk assessment is provided in Table A7.
Table A7: Summary of Risk Assessment
Element Risk Assessment
Site Visit Low. Sundre facility is a relatively small facility, major
equipment were observed during the site visit.
Offset boundary Low. Site visit confirmed the offset boundary
Methodologies, emission factors and conversion
used
Medium. Quantification methodologies follow the
approved protocol and emission factors. Quantification is
conducted in the Excel spreadsheet. Emission factors and
conversions are transparent.
Comparability with the baseline Low. No operational changes since baseline.
Conformance to the program criteria Low. The project conforms to the program criteria.
Responsible Party’s data management system
and controls (e.g. organization chart, GHGH
management plan, personnel/consultant training,
protocols used, control system documentation,
software/program documentation/certifications)
Medium. The GHG data and information are mainly
supported by the 3rd party invoices. Majority of data is
transferred manually.
GHG data and information (e.g. including the type
of evidence collected, verification testing and
crosschecking, inventory of emission sources)
Medium. Suppliers’ invoices reviewed. The verification
tests conducted include vouching, recalculation, and
tracing.
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 29 of 43
Data management (e.g. measurement, fuel
sampling, calibration, consistent use
of standard conditions, data storage, procedures
to fill missing data; procedures to repair
inconsistent data, adjustment of variables and
factors)
Low. The GHG data and information are supported by
sufficient and appropriate evidence.
A6.0 Sampling Plan
The type and amount of evidence reviewed during the verification are summarized in Table A8.
Table A8: Sampling Plan
Reporting Element Type of Evidence Amount of Evidence Reviewed
Natural gas 3rd party invoices 2 years records
Electricity consumption Field tests
Engineering estimate Methodology reviewed
Biomass Production Records 2 years records
A7.0 Closure
If you have any questions or comments, please contact Min Si (403.723.1565,
Respectfully submitted,
Tetra Tech Canada Inc.
Prepared by: Reviewed by:
Min Si, M.N.R.M., GHG-V Nelson Lee, P.Eng.
Environmental Scientist Designated Signing Authority
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 30 of 43
Appendix B: Statement of Qualifications
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 31 of 43
Statement of Qualification
Offset Report
Project Name Sundre Forest Product THF Biomass Burner Project
Project ID 3157-5491
Project Developer Sundre Forest Products Inc.
Protocol Diversion of Biomass to Energy from Biomass Combustion
Facilities Quantification Protocol (Version 1.0, September 2014)
Report Period January 1, 2014 – December 31, 2015
Signature of Third Party Verifier
I, Nelson Lee (Third Party Verifier), meet or exceed the qualifications of Third-party verifiers
described in Section 29 of the Carbon Competitiveness Incentive Regulation.
Tetra Tech Canada Inc. Per:
Signature of Third Party Verifier Date
April 20, 2018
Training Received Under ISO 14064 Part 3
Nelson Lee received ISO 14064-3 training with Environment Canada, he has over 4 years of
experience in providing verification.
Name Nelson Lee
Professional Designation P.Eng.
Email [email protected]
Phone Number 778-317-7613
Lead Verifier
☐ Same as third party verifier?
Name Min Si, M.N.R.M., GHG-V
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 32 of 43
Professional Designation P. Ag.
Email [email protected]
Phone Number (403) 369 5254
Training Received Under ISO 14064 Part 3
Mr. Si is a CSA certified GHG verifier, and completed ISO 14064 – 3 with CSA.
Peer Reviewer
Name Nancy Wellhausen
Professional Designation
Email [email protected]
Phone Number 805.455.0604
Training Received Under ISO 14064 Part 3
Nancy Wellhausen received ISO14064 training from California Air Resources Board and State of
Washington Department of Ecology.
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 33 of 43
Appendix C: Findings and Issues
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 34 of 43
Table 9: Detailed Findings and Issues Log
Number the issue with the year and provide a unique # for the issue. If the issue resolved during the verification, indicate that in the resolution
column. If the issue is not resolved during the verification, or if the issue was material (whether resolved or not) record it as a finding in Table 2
and provide a cross reference to the finding # in the resolution column.
Describe the issues investigated. State the verification criteria that are not met. Provide a description of how it is not met and provide the
evidence. Indicate the Source Category (for facilities) or the Source/Sink (for offsets).
Indicate if the finding is an understatement or overstatement.
Summarize information between verifier and client.
Provide a conclusion including % discrepancy, if applicable.
Item
(YR-##)
Description of the Issues
Investigated During the
Verification
Summary of information exchanged
between verifier and client
Resolution Conclusion
(including %
discrepancy if
applicable)
16-01 Please provide explanation on how
the biomass quantify/volume is
determined in the calculator. Please
provide confirmation for the test
results
Our controller, Lee Dyer, was the one
who did this test to determine the
amount of biomass each dump count
holds. Here is the explanation of the
test:
We dropped 5 dumps of biomass and
collected into bins which had a volume
of 47lt (0.047 m3). What you see on C4
– C8 is the number of 47 lt bins that
were filled using each dump. Once we
know the number of bins and volume,
we can calculate how much biomass
was there in each dump. You see that
in D27. Hence the formula for wt of
biomass is as follows:
No.of bins/dump (C9) x Wt of each bins
(A26) / average volume per dump (D9)
Resolved No further
questions
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 35 of 43
17-02 Project condition, facility operation is excluded in the calculator. The convery system consumed electricity, and the offset project indicate the facility operation is included. Please explain the discrepancy.
Electiricty included Resolved No further
questions
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 36 of 43
Appendix D: Statement of Verification
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 37 of 43
Statement of Verification
Offset Report
Project Name Sundre Forest Product THF Biomass Burner Project
Project ID 3157-5491
Project Developer Sundre Forest Products Inc.
Protocol Diversion of Biomass to Energy from Biomass Combustion
Facilities Quantification Protocol (Version 1.0, September 2014)
Report Period January 1, 2014 – December 31, 2015
Statement of Verification
Total Baseline Emissions 2014: 14,761 t CO2e
2015: 14,761 t CO2e
Total Project Emissions 2014: 4,383 t CO2e
2015: 4,421 t CO2e
Other N/A
Net Reduction 2014: 10,378 t CO2e
2015: 10,340 t CO2e
Statement of Assertion In the period of January 1, 2014 – December 31, 2015, the net
reductions are 10,378 and 10,340 t CO2e respecitively.
Responsibilities of Project Developer and Third Party Verifier
West Fraser was responsible for the preparation and presentation of information within the
Project Report and GHG Assertion. Tetra Tech was responsible to provide a reasonable level of
assurance to ACCO on the GHG Assertion contained the Sundre Forest Product THF Biomass
Burner Project for the period of January 1, 2014 – December 31, 2015.
The objective of this verification is to provide an independent assessment of the offset project to
identify any material and immaterial errors, omission or misrepresentations, and to provide our
opinion on the GHG assertion in the Offset Project Report.
The verification was conducted to a reasonable level of assurance in accordance with ISO 14064-
3: Specification with Guidance for the Validation and Verification of GHG Assertions.
The evidence reviewed includes but not limited to production records, natural gas records, etc.
Conclusion
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 38 of 43
The verificaion conclusion is: Positive
Based on our review, it is our opinion that Emission Reductions, including
• 10,378 t CO2e of the emission reductions for the period of Jan 1, 2014 to December 31, 2014 and
• 10,340 t CO2e of the emission reductions for the period of Jan 1, 2015 to December 31, 2015
contained in the GHG assertion generated from the Sundre Forest Product THF Biomass Burner
project offset project are materially correct and presented fairly in accordance with the relevant
criteria.
Signature of Third Party Verifier
Tetra Tech Canada Inc. Per:
Signature of Third Party Verifier Date
April 20, 2018
Name Nelson Lee
Professional Designation P.Eng.
Email [email protected]
Phone Number 778-317-7613
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 39 of 43
Appendix E: Conflict of Interest Checklist
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 40 of 43
Conflict of Interest Checklist
Offset Report
Project Name Sundre Forest Product THF Biomass Burner Project
Project ID 3157-5491
Project Developer Sundre Forest Products Inc.
Protocol Diversion of Biomass to Energy from Biomass Combustion Facilities
Quantification Protocol (Version 1.0, September 2014)
Report Period January 1, 2014 – December 31, 2015
Conflict of Interest Checklist
1.The relationship between my firm and this reporting company poses
unacceptable threat to or compromises the impartiality of my firm. False
2.The finances and sources of income of my firm compromise the
impartiality of my firm. False
3.The personnel my firm has scheduled to participate in the verification
may have an actual or potential conflict of interest. False
4.
My firm participated in some manner in the development or
completion of the associated offset submission for this reporting
company.
False
5.My firm provided greenhouse gas consultancy services to this
reporting company. False
6.My firm will use personnel that have, are, or will be engaged or
previously employed by the reporting company. False
7.My firm will outsource the Statement of Verification for the associated
offset submission. False
8.My firm offers products or services that pose an unacceptable risk to
impartiality. False
Important: If you have checked "True" to any of the above, you may not fulfill the "independence"
requirement for third party verifiers. Please contact Alberta Environment and Parks for further instruction. If
the potential conflict of interest is a sufficient threat to impartiality (perceived or actual), or cannot be
effectively managed, you Third Party Verification Report will not be acceptable to Alberta Environment and
Parks.
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 41 of 43
Signature of Third Party Verifier
I, Nelson Lee (Third Party Verifier), have personally examined and am familiar with the
information contained in this Conflict-of Interest Checklist, and can demonstrate freedom from
any conflict of interest related to the reporting company for which the verification was
performed. I hereby warrant that the information submitted in this Conflict-of Interest Checklist
is true, accurate and complete to the best of my knowledge, and that all matters affecting the
validity of this Conflict-of-Interest Checklist have been fully disclosed. Impartiality shall be
monitored over the duration of the verification and any identified actual or potential conflict-of-
interest situations will be communicated to AEP directly.
Tetra Tech Canada Inc. Per:
Signature of Third Party Verifier Date
April 20, 2018
Name Nelson Lee
Professional Designation P.Eng.
Email [email protected]
Phone Number 778-317-7613
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 42 of 43
Appendix F: Limitation on Use of this Document
Sundre Forest Product THF Biomass Burner Project (3157-5491)
April 2018 | 704-ENW.EENW03301-01
Page 43 of 43