vattenfall peter olsson transient studies
DESCRIPTION
Vattenfall Peter Olsson Transient StudiesTRANSCRIPT
-
1 | Transient studies | Peter Olsson | 2011.12.06
Transient studiesPresentation
2011-12-06
-
Confidentiality -2 | Transient studies | Peter Olsson | 2011.12.06
Peter Olsson
Staffanstorps Energi ABElectrician
Lund Technical UniversityElectrical engineering
Vattenfall Eldistribution ABProtection, control room, calculations and analysis and transformers
Vattenfall Research and Development ABSimulation and analysis of power systems
-
Confidentiality -3 | Transient studies | Peter Olsson | 2011.12.06
Agenda
Why transient studies
Methods
Some examples
-
Confidentiality -4 | Transient studies | Peter Olsson | 2011.12.06
Need for transient studies
Insulation coordination- Resonance- Switching surges- Fault initiating or clearing- Induction between systems- Lightning induced voltages
Power quality- Transformer or reactor energising- Cable or over head line energising- Harmonics
New configurations of grid layout- Extreme values of RLC- Wind power towers and lightning
-
Confidentiality -5 | Transient studies | Peter Olsson | 2011.12.06
Method
Mainly PSCAD/EMTDC but also Matlab - SimPowerSystems
Using models - In the PSCAD/EMTDC library- From PSCAD/EMTDC support- Developed by Vattenfall- Developed by suppliers- Developed by Universities
Using theory described in- Literature- Papers- PhD and Master thesis
Simulating frequencies in the range from 50 Hz up to MHz - high frequency models are needed.
Simulation time steps of 10 ns can sometimes be necessary.
PSCAD/EMTDC is a simulation tool for electromagnetic transients.
PSCAD/EMTDC is a flexible tool that gives the user large freedom to implement that of interest.
EMTP Theory book (from 1970-th)Papers
-
Confidentiality -6 | Transient studies | Peter Olsson | 2011.12.06
Method
Cable model in PSCAD/EMTDC Mathematical model of
the cable by using the physical parameters
The user defines the physical layout of the conductors.
Only one phase cables can be modelled.
Frequency dependant cable impedance.
Cable models are validated in others work
0.009 [m]
Cable # 1
0.017 [m]0.01735 [m]
0.023 [m]
1 [m]
0.3 [m]
ConductorInsulator 1
SheathInsulator 2
0.003 [m]
Cable # 4
0.3 [m]
0.82 [m]
0.6 [m]
ConductorInsulator 1
0.009 [m]
Cable # 2
0.017 [m]0.01735 [m]
0.023 [m]
0.948 [m]
0.33 [m]
ConductorInsulator 1
SheathInsulator 2
0.009 [m]
Cable # 3
0.017 [m]0.01735 [m]
0.023 [m]
1 [m]
0.36 [m]
ConductorInsulator 1
SheathInsulator 2
0.003 [m]
Cable # 5
0.3 [m]
0.82 [m]
0 [m]
ConductorInsulator 1
-
Confidentiality -7 | Transient studies | Peter Olsson | 2011.12.06
Method
Transformer model in PSCAD/EMTDC
0.001 [uF]
0.001
[uF]
0.001
[uF]
#2umec
#1
Mathematical model of the transformer using electrical design parameters
Saturation is available in the model
Remaining flux is not internally modelled but can be added by an external DC current source
At higher frequencies the transformer capacitances has to be added externally
-
Confidentiality -8 | Transient studies | Peter Olsson | 2011.12.06
Examples of transient studies made by Vattenfall
Resonant over voltages during faults
Lightning currents in cable and earthing system
-
Confidentiality -9 | Transient studies | Peter Olsson | 2011.12.06
Resonance model and simulation
-
Confidentiality -10 | Transient studies | Peter Olsson | 2011.12.06
Resonance
Simulation study made in PSCAD/EMTDC with a 130 kV feeding grid connected to a 30 kV wind power cable grid
Changing the capacitance by adding and removing cables.
Changing the inductance by adding and removing Over Head line
Simulations of wind power grid indicating that high over voltage occurs in the connected underlying 30 kV grid during fault initiation and fault clearing
Cable OH-lines
Cables
~
130/30 kVFeeders
Tower
~130 kV
LSC RSC
R130
C130
L30
R30
C30
Electrical equivalent
130 kV cables
130 kV short circuit impedance
130 kV fault 30 kV cables
130/30 kV transformer
-
Confidentiality -11 | Transient studies | Peter Olsson | 2011.12.06
Cable OH-lines
Cables
~
130/30 kVFeeders
Tower
Resonance
Simulation results of fault in 130 kV grid
0.0300 0.0310 0.0320 0.0330 0.0340 0.0350 0.0360 0.0370 0.0380 0.0390 0.0400 ... ...
...
-250
-200
-150
-100
-50
0
50
100
150
200
V
(
k
V
)
Ea130 Eb130 Ec130 E0130
Time ... 0.0300 0.0310 0.0320 0.0330 0.0340 0.0350 0.0360 0.0370 0.0380 0.0390 0.0400 ... ...
...
-150
-100
-50
0
50
100
150
V
(
k
V
)
Ea Eb Ec
30 kV phase to earth voltages130 kV phase to earth voltages
Frequency of the oscillations is ~800 Hz. The rise time of the voltage from zero to the maximum value is about 300 s.
130 kV voltage during the fault
Fault is cleared
130 kV voltage after fault clearance. Oscillating frequency is ~800 Hz
Max voltage is 130 kV, that is about 4.5 p.u.
-
Confidentiality -12 | Transient studies | Peter Olsson | 2011.12.06
Resonance
~130 kV
LSC RSC
R130
C130
L30
R30
C30
Impedance from 130 kV towards 30 kV grid.The series LC-circuit have a minimum at the resonant frequency
130 kV impedance without the 30 kV grid connected.The parallel LC-circuit have a maximum at a resonant frequency
1
10
100
1000
10000
100000
1000000
10000000
10 100 1000 10000f(Hz)
I
m
p
e
d
a
n
c
e
(
|
O
h
m
|
)
130 kV: |Z+|(Ohm)30 kV: |Z+|(Ohm)
The impedance at the resonant frequency is: Z=R+j(XL-XC)~R
Only the resistance limits the current, and voltage.
The resistance can be low in these cable networks
The 130/30 kV transformer and 30 kV grid acts like a consuming filter for this frequency.
Grid impedance at different frequencies
-
Confidentiality -13 | Transient studies | Peter Olsson | 2011.12.06
ResonanceFrequency components in the 130 kV voltage
~130 kV
LSC RSC
R130
C130
L30
R30
C30
30 kV connected30 kV not connected
A
m
p
l
i
t
u
d
e
(
k
V
)
Frequency (Hn)
Hn=16fn=800 Hz
Frequency component of the oscillating 130 kV voltage after the fault is cleared when the 30 kV grid is disconnected.
Frequency component of the oscillating 130 kV voltage after the fault is cleared when the 30 kV grid is connected.
0.0300 0.0310 0.0320 0.0330 0.0340 0.0350 0.0360 0.0370 0.0380 0.0390 0.0400 ... ...
...
-250
-200
-150
-100
-50
0
50
100
150
200
V
(
k
V
)
Ea130 Eb130 Ec130 E0130
-
Confidentiality -14 | Transient studies | Peter Olsson | 2011.12.06
Resonance
Insulation coordination
Mainly three tests are performed to verify the degree of insulation of equipment
- Nominal frequency tests, AC, to verify this frequency voltage withstand level. Test voltage level for 36 kV is 70 kV (IEC)
- Lightning Impulse tests, LI, to verify the withstand level against lightning induced voltages. Rise time of the test voltage is 1.2 s Test voltage level for 36 kV is 145 or 170 kV (IEC)
- Switching Impulse tests, SI, to verify the withstand level against switching induced voltages. Rise time of the test voltage is 250 s Not defined for 36 kV but the level is assumed to
be in the order of 80-85 % of the LI-level.
Frequency of the calculated over voltages in the example is ~800 Hz. The rise time of the voltage from zero to the maximum value is about 300 s. Voltage withstand test at this frequency may therefore be verified by SI test.
SI(36 kV) ~ 0.83*LI(36 kV) = 120/141 kVThis shall be compared with the calculated voltage of 130 kV
This can lead to that higher insulation level for the equipment is needed.
-
Confidentiality -15 | Transient studies | Peter Olsson | 2011.12.06
Lightning model and simulation
-
Confidentiality -16 | Transient studies | Peter Olsson | 2011.12.06
Lightning
Wind power tower model developed by using a the frequency dependant phase cable model in PSCAD/EMTDC
Conductor
ScreenTower
Insulation
Injected current
Inner conductor, first insulation and second conductor represent a cable within the tower
Second insulation represent the air between the cable and steel tower
Third conductor represent the steel tower
Cable conductorScreen
Earth wire modelled as a distributed parameter line
-
Confidentiality -17 | Transient studies | Peter Olsson | 2011.12.06
Lightning
Voltage in the figure is calculated 90 m from A, in C. Blue curve is the voltage in the earth wire and green curve is the induced voltage in the cable screen.
Practical implication: Have large physical distance between parallel different earth systems?
0.100m 0.101m 0.102m 0.103m 0.104m 0.105m 0.106m 0.107m 0.108m 0.109m 0.110m ... ...
...
-200
-100
0
100
200
300
400
V
(
k
V
)
EE6 EE7
30 m 30 m 30 m 100 m 100 m0 m
300 m
A B
C
Conductor
ScreenTower
Insulation
Calculated voltage difference of 400 kV
Parallel earth wire and cable not connected at the same potential
-
Confidentiality -18 | Transient studies | Peter Olsson | 2011.12.06
Lightning
The red curve is the voltage in the earth wire and the green/blue curve is the voltage in the cable screen/phase.
The figures shows the calculated voltage at [0 100 1000] meters
The injected current in the screen and the earth wire is 50 kA with 1 s rise time
The soil resistivity is 1000 Ohm*m. At other soil resistivity the damping is different.
It seems like the positive influence of an earth wire is practically gone at a certain distance, determined by the soil resistivity!
0 .0 9 m 0.1 0 m 0 .11 m 0 .1 2m 0 .1 3 m 0.1 4 m 0 .15 m 0 .1 6 m 0.1 7 m 0 .18 m 0 .1 9m 0 .2 0 m ... ...
...
-0 .2 k
0 .0
0 .2 k
0 .4 k
0 .6 k
0 .8 k
1 .0 k
1 .2 k
V
(
k
V
)
EE4 EE3 EEC2
0 .0 9 m 0 .1 0 m 0 .1 1 m 0 .1 2 m 0 .1 3 m 0 .1 4 m 0 .1 5 m 0 .1 6 m 0 .1 7 m 0 .1 8 m 0 .1 9 m 0 .2 0 m . . . . . .
. . .
- 1 0 0
0
1 0 0
2 0 0
3 0 0
4 0 0
5 0 0
6 0 0
7 0 0
V
(
k
V
)
EE2 4 EE1 4 EE1 3
0 .0 9 m 0 .1 0 m 0 .1 1 m 0 .1 2 m 0 .1 3 m 0 .1 4 m 0 .1 5 m 0 .1 6 m 0 .1 7 m 0 .1 8 m 0 .1 9 m 0 .2 0 m ... . . .
. . .
-1 0 0
-5 0
0
5 0
1 0 0
1 5 0
V
(
k
V
)
EE3 0 EE3 1 EE3 2
100 m 100 m 100 m 100 m 100 m0 m
100 mAll voltages are the same at 0 m
Different damping gives different amplitude after some distance
10 s
-
Confidentiality -19 | Transient studies | Peter Olsson | 2011.12.06
Lightning
The figure is showing the voltage at the beginning of the wire as a function of total wire length, soil resistivity and rise time of the injected lightning current, of 100 kA
0
1
2
3
4
5
6
7
1 10 100 1000 10000
Length (m)
V
o
l
t
a
g
e
(
M
V
)
100 Ohm*m, 1/501000 Ohm*m, 1/5010000 Ohm*m, 1/5010000 Ohm*m, 2 // wires, 1/50100 Ohm*m 8/201000 Ohm*m 8/20100000 Ohm*m 8/20
Conductor
ScreenTower
Insulation
As expected, different soil resistivity gives different efficient length of the wire
Different rise time also gives different efficient length of the wire
Two earth wires are more efficient than increase length
-
Confidentiality -20 | Transient studies | Peter Olsson | 2011.12.06
Thank you for your attention
Questions?