vattenfall peter olsson transient studies

Upload: adilson-leite-proenca

Post on 13-Jan-2016

220 views

Category:

Documents


0 download

DESCRIPTION

Vattenfall Peter Olsson Transient Studies

TRANSCRIPT

  • 1 | Transient studies | Peter Olsson | 2011.12.06

    Transient studiesPresentation

    2011-12-06

  • Confidentiality -2 | Transient studies | Peter Olsson | 2011.12.06

    Peter Olsson

    Staffanstorps Energi ABElectrician

    Lund Technical UniversityElectrical engineering

    Vattenfall Eldistribution ABProtection, control room, calculations and analysis and transformers

    Vattenfall Research and Development ABSimulation and analysis of power systems

  • Confidentiality -3 | Transient studies | Peter Olsson | 2011.12.06

    Agenda

    Why transient studies

    Methods

    Some examples

  • Confidentiality -4 | Transient studies | Peter Olsson | 2011.12.06

    Need for transient studies

    Insulation coordination- Resonance- Switching surges- Fault initiating or clearing- Induction between systems- Lightning induced voltages

    Power quality- Transformer or reactor energising- Cable or over head line energising- Harmonics

    New configurations of grid layout- Extreme values of RLC- Wind power towers and lightning

  • Confidentiality -5 | Transient studies | Peter Olsson | 2011.12.06

    Method

    Mainly PSCAD/EMTDC but also Matlab - SimPowerSystems

    Using models - In the PSCAD/EMTDC library- From PSCAD/EMTDC support- Developed by Vattenfall- Developed by suppliers- Developed by Universities

    Using theory described in- Literature- Papers- PhD and Master thesis

    Simulating frequencies in the range from 50 Hz up to MHz - high frequency models are needed.

    Simulation time steps of 10 ns can sometimes be necessary.

    PSCAD/EMTDC is a simulation tool for electromagnetic transients.

    PSCAD/EMTDC is a flexible tool that gives the user large freedom to implement that of interest.

    EMTP Theory book (from 1970-th)Papers

  • Confidentiality -6 | Transient studies | Peter Olsson | 2011.12.06

    Method

    Cable model in PSCAD/EMTDC Mathematical model of

    the cable by using the physical parameters

    The user defines the physical layout of the conductors.

    Only one phase cables can be modelled.

    Frequency dependant cable impedance.

    Cable models are validated in others work

    0.009 [m]

    Cable # 1

    0.017 [m]0.01735 [m]

    0.023 [m]

    1 [m]

    0.3 [m]

    ConductorInsulator 1

    SheathInsulator 2

    0.003 [m]

    Cable # 4

    0.3 [m]

    0.82 [m]

    0.6 [m]

    ConductorInsulator 1

    0.009 [m]

    Cable # 2

    0.017 [m]0.01735 [m]

    0.023 [m]

    0.948 [m]

    0.33 [m]

    ConductorInsulator 1

    SheathInsulator 2

    0.009 [m]

    Cable # 3

    0.017 [m]0.01735 [m]

    0.023 [m]

    1 [m]

    0.36 [m]

    ConductorInsulator 1

    SheathInsulator 2

    0.003 [m]

    Cable # 5

    0.3 [m]

    0.82 [m]

    0 [m]

    ConductorInsulator 1

  • Confidentiality -7 | Transient studies | Peter Olsson | 2011.12.06

    Method

    Transformer model in PSCAD/EMTDC

    0.001 [uF]

    0.001

    [uF]

    0.001

    [uF]

    #2umec

    #1

    Mathematical model of the transformer using electrical design parameters

    Saturation is available in the model

    Remaining flux is not internally modelled but can be added by an external DC current source

    At higher frequencies the transformer capacitances has to be added externally

  • Confidentiality -8 | Transient studies | Peter Olsson | 2011.12.06

    Examples of transient studies made by Vattenfall

    Resonant over voltages during faults

    Lightning currents in cable and earthing system

  • Confidentiality -9 | Transient studies | Peter Olsson | 2011.12.06

    Resonance model and simulation

  • Confidentiality -10 | Transient studies | Peter Olsson | 2011.12.06

    Resonance

    Simulation study made in PSCAD/EMTDC with a 130 kV feeding grid connected to a 30 kV wind power cable grid

    Changing the capacitance by adding and removing cables.

    Changing the inductance by adding and removing Over Head line

    Simulations of wind power grid indicating that high over voltage occurs in the connected underlying 30 kV grid during fault initiation and fault clearing

    Cable OH-lines

    Cables

    ~

    130/30 kVFeeders

    Tower

    ~130 kV

    LSC RSC

    R130

    C130

    L30

    R30

    C30

    Electrical equivalent

    130 kV cables

    130 kV short circuit impedance

    130 kV fault 30 kV cables

    130/30 kV transformer

  • Confidentiality -11 | Transient studies | Peter Olsson | 2011.12.06

    Cable OH-lines

    Cables

    ~

    130/30 kVFeeders

    Tower

    Resonance

    Simulation results of fault in 130 kV grid

    0.0300 0.0310 0.0320 0.0330 0.0340 0.0350 0.0360 0.0370 0.0380 0.0390 0.0400 ... ...

    ...

    -250

    -200

    -150

    -100

    -50

    0

    50

    100

    150

    200

    V

    (

    k

    V

    )

    Ea130 Eb130 Ec130 E0130

    Time ... 0.0300 0.0310 0.0320 0.0330 0.0340 0.0350 0.0360 0.0370 0.0380 0.0390 0.0400 ... ...

    ...

    -150

    -100

    -50

    0

    50

    100

    150

    V

    (

    k

    V

    )

    Ea Eb Ec

    30 kV phase to earth voltages130 kV phase to earth voltages

    Frequency of the oscillations is ~800 Hz. The rise time of the voltage from zero to the maximum value is about 300 s.

    130 kV voltage during the fault

    Fault is cleared

    130 kV voltage after fault clearance. Oscillating frequency is ~800 Hz

    Max voltage is 130 kV, that is about 4.5 p.u.

  • Confidentiality -12 | Transient studies | Peter Olsson | 2011.12.06

    Resonance

    ~130 kV

    LSC RSC

    R130

    C130

    L30

    R30

    C30

    Impedance from 130 kV towards 30 kV grid.The series LC-circuit have a minimum at the resonant frequency

    130 kV impedance without the 30 kV grid connected.The parallel LC-circuit have a maximum at a resonant frequency

    1

    10

    100

    1000

    10000

    100000

    1000000

    10000000

    10 100 1000 10000f(Hz)

    I

    m

    p

    e

    d

    a

    n

    c

    e

    (

    |

    O

    h

    m

    |

    )

    130 kV: |Z+|(Ohm)30 kV: |Z+|(Ohm)

    The impedance at the resonant frequency is: Z=R+j(XL-XC)~R

    Only the resistance limits the current, and voltage.

    The resistance can be low in these cable networks

    The 130/30 kV transformer and 30 kV grid acts like a consuming filter for this frequency.

    Grid impedance at different frequencies

  • Confidentiality -13 | Transient studies | Peter Olsson | 2011.12.06

    ResonanceFrequency components in the 130 kV voltage

    ~130 kV

    LSC RSC

    R130

    C130

    L30

    R30

    C30

    30 kV connected30 kV not connected

    A

    m

    p

    l

    i

    t

    u

    d

    e

    (

    k

    V

    )

    Frequency (Hn)

    Hn=16fn=800 Hz

    Frequency component of the oscillating 130 kV voltage after the fault is cleared when the 30 kV grid is disconnected.

    Frequency component of the oscillating 130 kV voltage after the fault is cleared when the 30 kV grid is connected.

    0.0300 0.0310 0.0320 0.0330 0.0340 0.0350 0.0360 0.0370 0.0380 0.0390 0.0400 ... ...

    ...

    -250

    -200

    -150

    -100

    -50

    0

    50

    100

    150

    200

    V

    (

    k

    V

    )

    Ea130 Eb130 Ec130 E0130

  • Confidentiality -14 | Transient studies | Peter Olsson | 2011.12.06

    Resonance

    Insulation coordination

    Mainly three tests are performed to verify the degree of insulation of equipment

    - Nominal frequency tests, AC, to verify this frequency voltage withstand level. Test voltage level for 36 kV is 70 kV (IEC)

    - Lightning Impulse tests, LI, to verify the withstand level against lightning induced voltages. Rise time of the test voltage is 1.2 s Test voltage level for 36 kV is 145 or 170 kV (IEC)

    - Switching Impulse tests, SI, to verify the withstand level against switching induced voltages. Rise time of the test voltage is 250 s Not defined for 36 kV but the level is assumed to

    be in the order of 80-85 % of the LI-level.

    Frequency of the calculated over voltages in the example is ~800 Hz. The rise time of the voltage from zero to the maximum value is about 300 s. Voltage withstand test at this frequency may therefore be verified by SI test.

    SI(36 kV) ~ 0.83*LI(36 kV) = 120/141 kVThis shall be compared with the calculated voltage of 130 kV

    This can lead to that higher insulation level for the equipment is needed.

  • Confidentiality -15 | Transient studies | Peter Olsson | 2011.12.06

    Lightning model and simulation

  • Confidentiality -16 | Transient studies | Peter Olsson | 2011.12.06

    Lightning

    Wind power tower model developed by using a the frequency dependant phase cable model in PSCAD/EMTDC

    Conductor

    ScreenTower

    Insulation

    Injected current

    Inner conductor, first insulation and second conductor represent a cable within the tower

    Second insulation represent the air between the cable and steel tower

    Third conductor represent the steel tower

    Cable conductorScreen

    Earth wire modelled as a distributed parameter line

  • Confidentiality -17 | Transient studies | Peter Olsson | 2011.12.06

    Lightning

    Voltage in the figure is calculated 90 m from A, in C. Blue curve is the voltage in the earth wire and green curve is the induced voltage in the cable screen.

    Practical implication: Have large physical distance between parallel different earth systems?

    0.100m 0.101m 0.102m 0.103m 0.104m 0.105m 0.106m 0.107m 0.108m 0.109m 0.110m ... ...

    ...

    -200

    -100

    0

    100

    200

    300

    400

    V

    (

    k

    V

    )

    EE6 EE7

    30 m 30 m 30 m 100 m 100 m0 m

    300 m

    A B

    C

    Conductor

    ScreenTower

    Insulation

    Calculated voltage difference of 400 kV

    Parallel earth wire and cable not connected at the same potential

  • Confidentiality -18 | Transient studies | Peter Olsson | 2011.12.06

    Lightning

    The red curve is the voltage in the earth wire and the green/blue curve is the voltage in the cable screen/phase.

    The figures shows the calculated voltage at [0 100 1000] meters

    The injected current in the screen and the earth wire is 50 kA with 1 s rise time

    The soil resistivity is 1000 Ohm*m. At other soil resistivity the damping is different.

    It seems like the positive influence of an earth wire is practically gone at a certain distance, determined by the soil resistivity!

    0 .0 9 m 0.1 0 m 0 .11 m 0 .1 2m 0 .1 3 m 0.1 4 m 0 .15 m 0 .1 6 m 0.1 7 m 0 .18 m 0 .1 9m 0 .2 0 m ... ...

    ...

    -0 .2 k

    0 .0

    0 .2 k

    0 .4 k

    0 .6 k

    0 .8 k

    1 .0 k

    1 .2 k

    V

    (

    k

    V

    )

    EE4 EE3 EEC2

    0 .0 9 m 0 .1 0 m 0 .1 1 m 0 .1 2 m 0 .1 3 m 0 .1 4 m 0 .1 5 m 0 .1 6 m 0 .1 7 m 0 .1 8 m 0 .1 9 m 0 .2 0 m . . . . . .

    . . .

    - 1 0 0

    0

    1 0 0

    2 0 0

    3 0 0

    4 0 0

    5 0 0

    6 0 0

    7 0 0

    V

    (

    k

    V

    )

    EE2 4 EE1 4 EE1 3

    0 .0 9 m 0 .1 0 m 0 .1 1 m 0 .1 2 m 0 .1 3 m 0 .1 4 m 0 .1 5 m 0 .1 6 m 0 .1 7 m 0 .1 8 m 0 .1 9 m 0 .2 0 m ... . . .

    . . .

    -1 0 0

    -5 0

    0

    5 0

    1 0 0

    1 5 0

    V

    (

    k

    V

    )

    EE3 0 EE3 1 EE3 2

    100 m 100 m 100 m 100 m 100 m0 m

    100 mAll voltages are the same at 0 m

    Different damping gives different amplitude after some distance

    10 s

  • Confidentiality -19 | Transient studies | Peter Olsson | 2011.12.06

    Lightning

    The figure is showing the voltage at the beginning of the wire as a function of total wire length, soil resistivity and rise time of the injected lightning current, of 100 kA

    0

    1

    2

    3

    4

    5

    6

    7

    1 10 100 1000 10000

    Length (m)

    V

    o

    l

    t

    a

    g

    e

    (

    M

    V

    )

    100 Ohm*m, 1/501000 Ohm*m, 1/5010000 Ohm*m, 1/5010000 Ohm*m, 2 // wires, 1/50100 Ohm*m 8/201000 Ohm*m 8/20100000 Ohm*m 8/20

    Conductor

    ScreenTower

    Insulation

    As expected, different soil resistivity gives different efficient length of the wire

    Different rise time also gives different efficient length of the wire

    Two earth wires are more efficient than increase length

  • Confidentiality -20 | Transient studies | Peter Olsson | 2011.12.06

    Thank you for your attention

    Questions?