value for money review of the strategic non-national ... · final draft – july 2008 value for...

244
FINAL DRAFT July 2008 Value for Money Review of the Strategic Non-National (Regional and Local) Roads Programme

Upload: lydung

Post on 08-Apr-2018

216 views

Category:

Documents


2 download

TRANSCRIPT

FINAL DRAFT – July 2008

Value for Money Review of the Strategic Non-National (Regional and Local) Roads Programme

i

Table of Contents Chapter Title Page 1. Introduction 1

1.1 Background and Overview 1.2 Regional and Local Roads 1.3 The Value For Money and Policy Review Initiative 1.4 Steering Committee 1.5 Format of the Report Executive Summary 6

Terms of Reference Conclusions Recommendations

2. Scene Setting 18

2.0 Introduction 2.1 The Irish Housing Market 2.1.1 The Factors Driving Supply and Demand 2.1.2 Supply and Demand– Implications for the VFM Review 2.1.3 What Caused Irish House Prices to Rise? 2.1.4 Expanded Housing Supply 2.1.5 The UK Experience – The Barker Report 2.2 The Role of Roads in Promoting National and

Regional Development 2.2.1 General (but not Unanimous) Agreement

2.2.2 Ireland‟s Experience 2.2.3 Assessing the Social and Economic Outcomes of Non National Roads - The Appropriateness of Cost Benefit Analysis 2.2.4 CBA - Practical and Conceptual Issues for Non National Roads 2.2.5 Assessing Social and Economic Benefits – Conclusions 2.3 Reviewing Other Reviews 2.3.1 Efficiency and Effectiveness - Key „Value for Money‟ Concepts 2.3.2 The First VFM Report on Regional and Local Roads 2.3.3 The Use of Guidelines to Achieve Standardisation of Approach 2.3.4 Performance Indicators 2.3.5 Evidence of Progress and Improvement

3. Methodology 44

3.1 Introduction 3.2 The Programme Logic Model 3.3 Efficiency and Effectiveness 3.4 The Counterfactual – What Would Have Happened Without the Programme? 3.5 The Survey Questionnaires – Design and Technical Issues 3.6 Assessing Causality - The Role of Roads Infrastructure

in Delivering Housing and Development Lands 3.7 Assessing Social and Economic Outcomes 3.8 Quality Assessment 3.9 Concluding Comments

ii

4. Programme Objectives 58 4.0. Introduction 4.1. The Origins and Objectives of the Programme

4.1.1 The Primary Objective 4.1.2 First Bacon Report 4.1.3 The Second Bacon Report 4.1.4 The Third Bacon Report 4.1.5 Circular RW 13/00 „Non-National Road Grants to Support

Housing and Other Related Developments‟ 4.2 The Economic Rationale Behind the Programme

4.2.1 „Market Failure‟ and Non-National Roads 4.2.2 Non-National Roads as „Public Goods‟ 4.2.3 Housing Supply and Market Failure

4.3 Conclusions 5. Current Validity of Objectives 68

5.0 Introduction and Overview 5.1 Concerns about the Sustainability of Housing Development 5.2 The New Hierarchy of Planning Policy and Legislation

5.2.1 The Co-ordination of Housing, Transport and Planning Policy 5.2.2 Translating National Policy into Regional and Local Planning Guidelines 5.2.3 County and City Development Plans 5.2.4 The New Spatial Planning Hierarchy – Implications for the Programme

5.3 Housing Supply and Housing Policy –Current Policy Context 5.3.1 Housing Supply Projections 5.3.2 Land and Zoning 5.3.3 „Delivering Homes Sustaining Communities‟

5.4 Development Levies and their Role in Providing Public Infrastructure 5.5 Conclusions

6. Programme Outputs 81

6.1 Introduction – Identifying the Outputs 6.2.1 Aggregate Outputs – Housing and Development Land 6.2.2 Delivered and Potential Outputs

6.3. Performance of Individual Projects 6.4 Roads Outputs 6.5 Factors Affecting the Delivery of Outputs

6.5.1 Commencement and Completion of Projects 6.5.2 Public Consultation and Environmental Impact Statements 6.5.3 Delays in Land Acquisition 6.5.4 Other Delaying Factors

6.6. Conclusions and Recommendations 7. Effectiveness 102

7.1 Introduction 7.2 How the Roads Projects Linked With the Planning Process 7.3 Cases Where Output Data Was Not Available 7.4 Industrial and Commercial Sites 7.5 Case Study - Tramore, County Waterford 7.6 Case Study - Park West, Dublin 12 7.7 Case Study - Naas, Co. Kildare 7.8 The Counter-Factual - What Might Have Happened in the

Absence of the Programme? 7.8.1 Planned Rather than Piecemeal Development

7.9 Conclusions and Recommendations

iii

8. Costs and Efficiency 134 8.1 Introduction 8.2 The Level and Trend of Exchequer Funding Over the

Lifetime of the Programme 8.2.1 Why 75% Exchequer Funding? 8.2.2 Expansion of the Original Funding Commitment in December 2000 8.2.3 Project Changes 2000-2008 8.2.4 Increased Grant Allocations 2000-2008

8.3 The Level and Trend of Project Costs Over the Lifetime of the Programme 8.3.1 Headline Trends in Cost Data 8.3.2 What Factors Were Driving Cost Upwards 8.3.3 Land Prices

8.4 The Cost of Achieving Outputs 8.5 Contract or Direct Labour? - How the Works Were Carried Out 8.6 Administration

8.6.1 Departmental Administration 8.6.2 Local Authority Administration

8.7 Maintenance 8.8 Conclusions and Recommendations

9. Future Public Funding 173

9.1 Emerging Analysis on the Current Policy Position 9.2 The New Strategic Regional and Local Roads Programme 9.3 Assessing Benefits and Costs 9.4 Stages and Level of Appraisal 9.5 Contracts and Value for Money 9.6 Dealing with the Rising Cost of Land 9.7 Conclusions and Recommendations

10. Performance Indicators 192

10.1 Introduction 10.2 Performance Management and Current Performance Indicators 10.3 Identifying Gaps in Current Indicators 10.4 Recommendations

11. Concluding Comments and Next Steps 199

11.1 Issues for Further Consideration Not Addressed in the Review 11.2 Key Findings 11.3 The Next Steps

iv

Appendices

Appendix I - Bibliography

Appendix II – Steering Committee

Membership

Dates of Meetings

Appendix III - Questionnaires and Cover Letter

Self-Completion Questionnaire for all projects funded under the programme

Questionnaire for projects that were submitted but not funded

Cover Letter to Local Authorities

Appendix IV - Interviews

Participants and Dates

Appendix V - Original Circular Letters and Application Form

Circular RW 13/00 of 3.7.00, „Non-National Road Grants to Support Housing

and Other Related Development‟ (which invited applications from local

authorities under the programme)

Original Application Form, July 2000

Circular RW 25/00 of 14.12.00, „Non-National Road Grants to Support

Housing and Other Related Development‟ (which formally notified local

authorities of approved projects and grant amounts)

Appendix VI - Output Data

Housing Units, Housing Lands and Industrial / Commercial Lands -

Reported Outputs

Project Commencement and Completion

v

List of Tables and Figures

Table Reference

Title Page Number

1.1

All projects approved under the Strategic Non-national Roads Programme 2000-2008

5

1.2 Summary of Housing and Land Outputs 10

2.1 Annual House Completions 2001-2007 24

5.1 The Availability of Undeveloped Lands that Were Zoned and Serviced For Housing at 30 June 2006

75

6.1 Original Output Targets 82

6.2 Headline Outputs – Housing and Development Land 83

6.3 Housing Unit Outputs 85

6.4 Housing Land Outputs (Hectares) 85

6.5 Industrial / Commercial Land Outputs (Hectares) 85

6.6 Relative Performance of Projects - Reported Outputs Compared to Original Intended Outputs

89

6.7 Roads Outputs 90

6.8 Facilities for Cyclists and Pedestrians 91

6.9 Project Commencement Dates 92

6.10 Project Completion Dates 92

6.11 Length of Public Consultation 94

7.1 Summary Traffic Count Data for the R406 / R407 Kildare Projects

106

7.2 Tramore - Distance Traveled to Work 2006 113

7.3 Tramore - Distance Traveled to Work 2002 113

7.4 Naas - Distance Traveled to Work 2006 123

7.5 Naas - Distance Traveled to Work 2002 123

7.6 Naas - Distance Traveled to Work 1996 123

7.7 Naas - Labour Force by Social Class - Comparison with the Greater Dublin Area and the State.

124

7.8 Naas - Highest level of educational attainment, as a percentage of the Population aged 15 and over.

125

7.9 Naas – Population Classified by Socio Economic Group 1996 – 2006

125

7.10 Applications that were not Selected – Did the Projects Proceed? 127

8.1 Level and Trend of Total Project Costs and Exchequer Commitment 2000 to 2008

135

8.2 Level and Trend of Grant Allocations – 2000 to 2008 139

8.3 Project Cost Comparison, Original Estimates from 2000 versus Costs Reported in the Questionnaire Returns 2007/2008

147

8.4 Construction Inflation, 2000-2007 150

8.5 Cost of Land Acquisition, 2000 - 2008 and Unit Cost Per Hectare

153

8.6 Cost of Achieving Development-Related Outputs 161

8.7 Contract or Direct Labour – How Works Were Carried Out 163

8.8 Estimated Administration Costs 2008 165

Figure Reference

3.1 The Programme Logic Model 46

8.1 Breakdown of Grants by Amount Awarded - 2000 140

8.2 Breakdown of Grants by Amount Awarded - 2008 140

8.3 Projects Separated into Cost Bands - 2000 145

8.4 Projects Separated into Cost Bands - 2008 146

8.5 Proportion of projects affected by Land Cost Increases 152

vi

List of Abbreviations

AADT Annual Average Daily Traffic (measurement used for counting traffic)

CBA Cost Benefit Analysis

C & AG Comptroller and Auditor General

CPO Compulsory Purchase Order

CSO Central Statistics Office

DEHLG Department of the Environment, Heritage and Local Government

(also its predecessor, DELG – Department of the Environment and

Local Government)

DoT Department of Transport

D&MRA Dublin and Midland Regional Authority

ESRI Economic and Social Research Institute

HGV Heavy Goods Vehicle

Ha Hectare

IDA Ireland Industrial Development Authority Ireland

IAVI Irish Auctioneers and Valuers Institute

IMF International Monetary Fund

KPMG Consulting Firm (authors of efficiency review of non-national roads)

MIF Management Information Framework

NDP National Development Plan

NESC National Economic and Social Council

NRA National Roads Authority

NSS National Spatial Strategy

OECD Organisation for Economic Co-operation and Development

PI Performance Indicator

PPP Public Private Partnership

SDZ Strategic Development Zone

VFM Value for Money

1

Chapter 1

Introduction

1.1. Background and Overview

The Programme was framed in the immediate context of recommendations contained

in the three reports commissioned by the Department of the Environment and Local

Government1, and prepared by Peter Bacon and Associates, Economic Consultants

in 1998, 1999 and 2000. These examined the significant changes occurring in the

housing market in Ireland from the 1990s onwards. Each of the three reports

identified inadequate infrastructure (including roads), as barriers to the supply of

housing to cater for rising demand. Such constraints on housing supply were seen

as factors leading to a disparity between supply and demand, contributing to rising

house prices and affordability problems for certain sectors of the market. Each report

was accompanied by the publication of a Government-approved policy document.

These policy responses set out the specific measures to address the issues raised in

the respective Bacon reports.

When established in 2000, the Programme was known as „Non-National Roads

Grants to Support Housing and other Related Developments‟. Formal applications

were invited in July 2000 from 15 local authorities in and adjacent to main urban

centres. Allocations for 43 projects were announced in December 2000. The initial

exchequer commitment at this time was €247.6m. A number of alterations have

occurred since then with the addition, removal, subdivision and amalgamation of

individual projects. Upon completion, 44 schemes in total will have been supported.

Table 1.1 contains a full list of the projects selected under the Programme, with

notation to highlight those affected by the alterations described. The total

commitment of grant aid when all are completed is expected to be €317.334m.

However, in addition to this amount significant funding has been provided by local

authorities. This has been primarily generated through development levies. Based

on data provided by local authorities for this review, the total expenditure on all

projects upon completion is estimated at €584.917m, however this figure is likely to

be higher.

1 The Department of the Environment and Local Government was re-titled the Department of the Environment, Heritage and Local Government in 2002. Within the review both of these terms are used. For ease of reference a truncated version „the Department of the Environment‟ is also commonly used.

2

1.2. Regional and Local Roads

While the specific programme under review has its own definable objectives, it is also

part of a wider scheme of policy and expenditure on roads. Under „The Roads Act,

1993‟, Ireland‟s road system is split into three categories. These are „National‟,

„Regional‟ and „Local‟ roads. Regional and Local Roads have traditionally been

described collectively as „Non-National Roads‟. On the other hand, „National‟ Roads

consist of all national primary and national secondary routes (including motorways).

Until June 2007, the Department of the Environment, Heritage and Local

Government had overall policy responsibility for non-national roads. However, this

function and the related funding responsibilities were transferred to the Department

of Transport at this time. The term „Regional and Local Roads‟ is now used in

preference to „Non-National Roads‟. The unit responsible for coordinating policy and

administering the payment of grants in this area is now called the „Regional and

Local Roads Division‟ of the Department of Transport. Within the review, the terms

„Regional and Local Roads‟ and „Non-National Roads‟ are used interchangeably.

Approximately 91,000 kilometres, or 94% of the country‟s road network are in the

„regional and local‟ category. In 2008, state grants totalling €618.714m are being

distributed to local authorities by the Regional and Local Roads Division. The overall

budget of the Department of Transport in 2008 is estimated at €3,226m.

The allocation in 2008 to the strategic programme being reviewed here was

€40.324m, while €45.909m was committed to projects under a newer programme,

established in 2006 to fund strategic roads tied into the National Spatial Strategy.

The remainder is spread across different funding categories. The most significant is

the „Restoration Programme‟, with a budget in 2008 of €310m. It commenced in

1995 following public and political concern about the pot-holed state of the regional

and local roads network. A study carried out in 1995/1996 identified that some

47,000 kilometres of non-national road was in need of restoration (Ove Arup et

al.,1997). In 2005, that Programme was reviewed and a follow-up study concluded

that the Programme needed to take account of changed road use patterns and

refocus priorities to areas of greatest need (RPS et al., 2005). Up to the end of 2007,

over 46,000 km of roads have been improved under the Programme.

The „Specific Improvement‟ grants scheme, which generally funds smaller scale

projects to support local and regional development has a budget of €101m in 2008.

A further €55.5m is being committed to county council „Discretionary Grants‟, where

3

the local authority decides how the funds are expended. €16.1m in „Block Grants‟

are being given to urban local authorities under similar conditions. There is also a

€17.4m fund for carriageway and footpath repairs and a €15m allocation to the „Local

Improvement Scheme‟ for non-public roads. In addition there are a number of

allocations towards smaller programmes.

When the Strategic Non-National Roads Programme was established in 2000, the

main policy focus of regional and local roads expenditure was the conservation,

restoration and maintenance of the existing network. However rapid economic

development from the 1990s onward brought new pressures. A need began to

emerge, particularly around larger urban areas, for the provision of new roads to

serve housing, and industrial/commercial needs. By way of a policy response, a

separate targeted scheme of exchequer funding was therefore put in place through

the Programme which is now being reviewed.

1.3. The Value For Money and Policy Review Initiative

The „Value for Money and Policy Review Initiative‟ is a Government-wide framework

to achieve value for money in public expenditure. It commenced in 1997, and was

formerly known as the „Expenditure Review Initiative‟. It was expanded and renamed

in 2006. As a general rule each Department should carry out a series of reviews

covering 10-15% of its expenditure every three years. The most recent set of

reviews for the period 2006-2008 was announced in June 2006 by the Minister for

Finance. This VFM review is one of 90 being carried out across Government

Departments and Offices during that period.

At a Governmental level, the review initiative is co-ordinated by a Central Steering

Committee and Central Expenditure Evaluation Unit that operate through the

Department of Finance. Published guidelines set out the processes that should be

followed in undertaking a review. The final report from each VFM review is submitted

to the relevant Oireachtas Select Committee and published.

VFM reviews follow a particular structure, with requirements to examine expenditure,

and the outputs and outcomes that arise as a result. These requirements lend

themselves to certain analytical approaches which will be examined in detail in the

methodology chapter.

4

1.4. Steering Committee

The guidelines issued by the Department of Finance recommend that a „Steering

Committee‟ be established to direct each review. It has responsibility for the conduct

of the review and oversees the drafting of the final report. The Committee is seen as

an important element in assuring objectivity. The steering committee for this review

reflects the fact that the Programme‟s original objectives combined elements of roads

and housing policy, whilst being delivered by local authorities. Membership of the

committee therefore comprises officials from the Department of the Environment,

Heritage and Local Government, the Department of Transport, and an official from

one of the local authorities involved in the delivery of the Programme. Between July

2007 and April 2008, the Steering Committee met five times. The draft report was

circulated to the members of the committee and approved in June 2008. A list of

members of the committee, and schedule of meeting dates is set out in Appendix II.

All reviews undertaken as part of the Value for Money and Policy Review Initiative

must be based on „Terms of Reference‟. These are prepared at the outset. There is

also a requirement that they generally comply with a template issued by the

Department of Finance. The steering committee agreed the Terms of Reference in

July 2007. These were approved by the Secretary General of the Department of

Transport and agreed with the Department of Finance.

1.5. Format of the Report

Each of the seven individual terms of reference is addressed in a separate chapter,

but given the interrelated nature of the issues being examined, there is some overlap

between them. The review commences with a „Scene Setting‟ chapter, which

examines a number of earlier reports and studies. These crucially inform the

methodologies used to gather data (which are set out in Chapter 3). The next seven

chapters (4 to 10) address each of the individual terms of reference. The final

chapter describes the next steps to be taken to implement the recommendations in

the review. A summary of the Conclusions followed by a list of Recommendations

from each chapter is included at the outset in the form of an „Executive Summary‟.

5

Table 1.1. All projects approved under the Programme 2000-2008

Local Authority

Road Project Name

Commentary

#Cork County 1. Carrigaline Western Relief Road

#Cork County 2. Clarkes Hill / Moneygourney Road

#Cork County 3. Midleton Northern Relief Road [Phase 1]

#Dun Laog/ R‟down 4. Dundrum Main Street Bypass

#Fingal 5. Balbriggan Inner Relief Road [stage 2]: Dublin Road - Skerries Road

#Fingal 6. Lusk Bypass

#Fingal 7. Naul Road Improvement Scheme

#Fingal 8. Ongar Road

#Galway County 9. Oranhill Distributor Road

#Galway County 10. Parkmore Road [Phases I & II]

#Kildare County 11. Barberstown Cross - Maynooth [R407] north of Barberstown cross

#Kildare County 12. Barberstown Cross - Maynooth [R407] south of Taghadoe Cross

#Kildare County 13. Celbridge Interchange

#Kildare County 14. Clane - Kilcock [R407] south of M4

#Kildare County 15. Clane - Kilcock [R407] to a point 1500m north of Clane

#Kildare County Clane Inner Relief Road Decommitted Jan 2008

#Kildare County Enfield - Edenderry [R402] [Carbury to Kishawanny] Reallocated to Another Programme 2006

#Kildare County Enfield - Edenderry [R402] [ohnstownbridge to Carbury Reallocated to Another Programme 2006

#Kildare County Naas Inner Relief Road [Dublin Road to Tipper Road] Decommitted Jan 2008

#Kildare County 16. Naas Ring Road - Newbridge Road to Caragh Road

#Kildare County 17. Naas Ring Road - Newbridge Rd to Kilcullen Rd to Craddockstown Rd

#Kildare County 18. Naas Ring Road - Newbridge Road to Industrial Estate [Millennium Park]

#Kildare County 19. Sallins - Clane [R407} south of Blackhall junction

#Kildare County 20. Sallins - Clane [R407] Castlesize estate to Blackhall Stud

New - Kildare County 21. Roads Serving Intel Added February 2001

#Limerick County 22. Castletroy Distributor Roads: Monaleen - Kilbane - N7 Dublin Road

#Meath County 23. Duleek-Julianstown-Laytown

#Meath County Plattin-Colp [MCC part] Decommited 2002

#Meath County 24. R154 Trim Inner Relief Road, phase 2a

#Meath County R154 Trim - Dublin Improvement Scheme Subdivided into 3 projects

25. R154 Trim/Dublin [Iffernock]

26. R154 Trim/Dublin [Kiltale/ Scurlogstown]

27. R154 Trim Dublin [Tullaghmedan]

#Meath County R161 Athlumney Subdivided into 2 projects

28. R161 Athlumney Phase I (Connaughtons)

29. R161 Athlumney Phase II (Bridge N3)

#Meath County 30. Trim-Kilcock R158

#Meath County 31. Trim-Navan Improvement Scheme [R161]

#South Dublin 32. Outer Ring Road

#Waterford County 33. Tramore Ring Road [phase 4]

New - Waterford County

34. Tramore Ring Road [phase 5] Added July 2002

#Wicklow County 35. Wicklow Town Relief Road & Wicklow Port Access

The two projects originally selected were merged #Wicklow County

#Cork City 36. Improvement works at Old Whitechurch Road

#Dublin City 37. Jamestown Road, Inchicore

#Dublin City 38. Killeen Road, Ballyfermot

#Galway City 39. Parkmore Road Industrial Lands

#Galway City 40. Terryland Valley Access Road

#Limerick City Corbally Link Road Subdivided into two Projects

41. Corbally Link Road Phase I

42. Corbally Link Road Phase II

#Waterford City 43. Outer Ring Road

New - Waterford City 44. Ballybeg Road Added September 2002

Notes on Table 1.1

Projects marked in the first column with the hash symbol (#) denote the 43 originally selected in December 2000.

In the second column, the projects numbered 1 to 44 represent the full list of projects that currently comprise the Programme.

6

EXECUTIVE SUMMARY

1. TERMS OF REFERENCE

Title and Context

The Strategic Non-National Roads Grants Programme (formerly known as Non-

National Roads Grants to Support Housing and other Related Developments)

commenced in December 2000. It was framed in the context of recommendations

contained in the reports „The Housing Market: An Economic Review and

Assessment‟ (March 1999) and „The Housing Market in Ireland: An Economic

Evaluation of Trends and Prospects‟ (June 2000) prepared by Peter Bacon and

Associates, Economic Consultants. The Department, in its policy response, „Action

on Housing‟ (June 2000), recognised the need for targeted investment in non-

national roads schemes crucial to housing and other related development.

Scope

The scope of the review will cover the Programme from its commencement in

2000 to the present, 2007.

A new and separate programme was introduced in 2006, for „strategic non-

national roads that make a significant contribution to the implementation of

the National Spatial Strategy‟. While conclusions and recommendations

arising from the VFM review will be relevant, this new programme is at a very

early stage and does not form part of the immediate scope of the review.

As the implementation of the Programme is largely devolved to local authorities, the

efficiency and effectiveness of the local government system in meeting the objectives

of the Programme will be considered in the assessment.

Terms of Reference:

The VFM Review of the Strategic Non-National Roads Programme will:

1) Identify the Programme‟s objectives,

2) Examine the current validity of those objectives and their compatibility with

overall Government strategy,

3) Define the outputs associated with the Programme activity and identify the

level and trend of those outputs,

4) Examine the extent that the Programme‟s objectives have been achieved,

and comment on the effectiveness with which they have been achieved,

7

5) Identify the level and trend of costs associated with the Strategic Non-

National Roads Programme and thus comment on the efficiency with which it

has achieved its objectives,

6) Evaluate the degree to which the objectives warrant the allocation of public

funding on a current and ongoing basis and examine the scope for alternative

policy or organisational approaches to achieving these objectives on a more

efficient and/or effective basis.

7) Specify potential future performance indicators that might be used to better

monitor the performance of the Programme or other specific programmes

related to the grant support of roads infrastructure to facilitate social and

economic development.

2. CONCLUSIONS

Chapter 2 - Scene Setting

The major studies of the Irish housing market in recent years have drawn upon

economic models to estimate the key influences driving supply and demand.

These factors include rising incomes, demographics and interest rates. The use

of such models can inform the review, but are insufficient in their own right in

explaining all of the factors that influence housing supply.

Housing output has expanded hugely in the past decade, assisted by

Government policy measures put in place to stimulate supply. However, a

problem arises in attempting to disaggregate the influence of any one measure.

The UK experienced broadly similar problems to Ireland in relation to growing

demand, but restricted supply. It responded in a similar fashion (in 2004) with the

establishment of a dedicated transport infrastructure fund to assist in the supply

of housing. This offers a validation of the Irish approach. It also acts as a useful

source of information for the review.

There is a widespread view internationally that infrastructure investment in roads

is beneficial to economic growth. This view also informs investment policy in

roads infrastructure in Ireland. The mid-term review of the „National Development

Plan 2000-2006‟ noted that the rate of return on non-national roads, although

small was consistent and reliable. The review did however comment on the

difficulties in quantifying benefits.

The appropriateness of using a Cost Benefit Analysis methodology to assess the

Programme was considered. However for technical and conceptual reasons this

was ruled out. CBA can be unreliable when applied in urban areas, and on roads

that experience significant traffic growth.

8

A major study by KPMG in 1997, which examined the efficiency of delivery of

non-national roads, offers a useful building block to commence the review at

hand.

Chapter 3 – Methodology

The overarching methodological structure is built around the „Programme Logic

Model‟. It allows for the systematic analysis of the cause-effect relationships

between the Inputs, Activities, Outputs and Outcomes.

Policy documents, departmental files and interviews with Departmental staff are

used to establish the objectives of the Programme.

A self-completion questionnaire in respect of each project is the main instrument

used for gathering data from local authorities on inputs and outputs.

In examining „Effectiveness‟, comparisons are drawn between the stated

commitments contained on the original application forms, and the actual

performance of the projects.

„Efficiency‟ is assessed by examining the cost of achieving the declared outputs.

In order to attribute outcomes to the Programme it has to be established that the

roads have played a causal role in facilitating new housing and development

lands. A technique called „Contribution Analysis‟ (Mayne 1999) is used. Inherent

in this approach in the use of multiple lines of evidence, and an awareness of

external factors that may have contributed to outcomes. Qualitative interviews

were undertaken with senior officials in each of the 15 relevant local authorities.

These included staff from different areas (engineering, administration, policy and

planning).

To examine „Effectiveness‟ in more detail, three case study areas were selected.

In Tramore (Co. Waterford), two new sections of its ring road were funded in

order to assist housing development. To assess the relationship between the

roads and housing supply, interviews were conducted with two local housing

development companies. The Killeen Road in Ballyfermot, Dublin facilitated the

Park West Business Park. An interview was conducted with the developers of

the park. Economic outcomes are examined with reference to the companies

located there. Naas in County Kildare had three roads funded under the

Programme. These are examined in relation to their specific role in facilitating

development, and resulting socio-economic impacts on the town.

An important consideration in the effectiveness of a Programme is to examine

what might have happened in its absence. By its nature this can be speculative.

However, it is useful in assessing „deadweight‟, „displacement‟ and „additionality‟.

9

When applications were invited from local authorities under the Programme a

total of 117 were submitted. 43 were approved, leaving a total of 74 projects that

were not selected. These 74 projects are used as a type of „control group‟ to

compare with the projects that were funded under the Programme.

Chapter 4 - Programme Objectives

The immediate objective of the Programme was to enable roads to be built that

would facilitate the opening up of development lands and the construction of

housing. This reflected the rapid economic growth and development pressures

that were prevalent in the late 1990s. The Programme was also to contribute to a

wider goal of increasing housing output in order to stabilise house prices. These

objectives were in line with stated government policy.

There was a justification for the Programme on the grounds of „Market Failure‟,

particularly in relation to the performance of the housing market at the time.

Underinvestment in infrastructure can lead to an undersupply in the housing

market and a loss of benefits to society. There were also wider „market failure‟

grounds based on the position of local and regional roads as „public goods‟, and

in their role of stimulating economic and social development.

The decision to establish the Programme was therefore justified from a policy

perspective.

Chapter 5 - Current Validity of Objectives

Since the Programme commenced, housing output has peaked and since

contracted. Prices have also peaked, and since 2007 have been falling.

Particular „market failures‟ related to the housing market are no longer

significantly prevalent.

In the medium to long term, demographic projections indicate a requirement to

provide considerable housing output. This can be best achieved through the new

hierarchical planning framework that has been put in place in recent years. This

framework consists of the National Spatial Strategy, Regional Planning

Guidelines, County Development Plans, Strategic Development Zones and Local

Area Plans. Decisions on resource allocation are also now crucially informed by

considerations of sustainability.

While there is no longer a need for a housing-focused roads Programme, there is

still an identified role for regional and local roads in facilitating social and

economic development. This role is recognised in the National Development

Plan 2007-2013.

10

Chapter 6 – Programme Outputs

The Programme was set up to facilitate additional housing units, housing lands

and industrial and commercial lands. In comparison with its original projections,

under all of these headings, the Programme will exceed expectations.

Most projects had a combined focus on both housing and industrial outputs,

although some focused on just one area. Amongst the individual projects, most

either met or exceeded their projected outputs. 26 of the 34 projects with

housing outputs are meeting or exceeded their stated targets on housing lands.

27 are meeting or exceeding their projected outputs for housing units.

In the case of the 30 projects with industrial and commercial land outputs, 19 are

meeting or exceeding targets. 11 have under-delivered, although in a number of

cases this was offset through additional housing-related outputs. However eight

projects did not have quantified deliverables at the outset, or similar current data.

Table 1.2. Summary of Housing and Land Outputs2

At least one third of the housing units have not yet been submitted for planning

permission. However, most of housing development lands facilitated by the

Programme have been zoned and serviced. Upon completion of the Programme,

the combined anticipated length of all roads outputs will be 104 kilometres, which

is broadly in line with expectations. An additional bonus in terms of sustainability

is the widespread presence of cycle tracks and footpaths.

There was widespread underestimation by local authorities of the time take it

would take to commence and complete projects. Expectations of timescale were

also over-optimistic. Within its intended lifespan (2001-2004), 32 projects

commenced and 19 were completed. Coming into 2008, 3 projects had yet to

commence, and 13 awaited completion. Delays were caused by longer than

2 Full account is taken in the table of changes in the numbers of projects over the course of the Programme

Declared Outputs based on

Questionnaire Returns

Difference between Expected and Actual

Performance

Housing Units 65,436

19,412

(+42%)

Housing Hectares 2,281

+490

(+27.5%)

Industrial / Commercial Hectares

973.5 +14.5

(+1.5%)

11

expected statutory and planning procedures, land acquisition and localised

issues affecting individual projects. Cost increases also resulted in delays as

local authorities sourced additional funding. Delays and cost increases had a

mutually reinforcing effect.

Chapter 7 - Effectiveness

A key determinant of effectiveness involves identifying the causal relationship

between the roads and the development that took place. Based on the combined

data sources referenced in the methodology chapter, the Programme did fulfil this

role. The most compelling supporting evidence came when planning decisions

were predicated on the presence of the road, and were directly linked through

specific development plans in an area.

Some roads have experienced the equivalent of a full generation of traffic-growth

in the space of around four years. In these cases, it is possible to say that the

road upgrades were required with reference to demonstrated need. However the

growth in traffic has implications for sustainability.

The roads played a key role in opening up business park sites, and in attracting

companies to locate there. Economic benefits accrue through improved

accessibility. Business have better access to their workforce (current and

potential), customers and suppliers. Increased employment has occurred at the

sites facilitated by the Programme. While it would be inappropriate to attribute all

economic and employment benefits to the Programme, the roads did play a key

role.

The facilitation of housing and commercial development affects local

demographics and the socio-economic profile of areas.

There is also evidence in the case study areas of principles of sustainable

development being followed within local development plans, and in planning

decisions.

The review considered a „counter-factual‟ scenario on what might have happened

without the Programme. Some projects (particularly smaller ones) may have

proceeded, albeit in a more piecemeal fashion. „Additionality‟ is clearest in

relation to the larger projects, which may not have gone ahead had the

Programme not been in place. The number of other projects that local authorities

supported outside the Programme indicates that exchequer funding wasn‟t used

to „displace‟ local resources. Overall, in terms of outcomes, the Programme can

be considered effective.

12

Chapter 8 – Costs and Efficiency

While the Programme delivered more outputs than projected, costs were greater

than expected. Tackling this issue will be crucial to improving efficiency. There

was a widespread underestimation of costs by local authorities at the outset.

Sufficient attention wasn‟t paid to the potential of costs to increase. When cost

increases began to be felt, the Department was left in the difficult position of

either choosing to curtail the Programme or approve grant increases. In the

main, it chose the latter option. Changes in costs and the Exchequer

commitment between 2000 to 2008 are outlined below.

Year Total Estimated

Project Costs

Total Exchequer

Grant Commitment

December 2000

(Announcement of Projects)

€385.97m €247.6m

January 2008 €584.917m3 €317.334m

The Department‟s financial commitment increased by 28% over the lifetime of the

Programme. Overall, the estimated cost of delivering the projects increased by

61% (approx), which indicates that proportionately, local authorities took on

additional responsibilities to meet cost increases. Some projects were

disproportionately affected, 15 had cost increases in excess of 100%.

Increases were caused by a number of factors namely: construction inflation that

was particularly rampant between 2000 and 2002, significant land price rises,

changes in specifications of individual projects, and a range of localised factors.

Increases in land costs largely reflected prevailing market conditions. For 18

projects land now constitutes 20% or more of total costs, which is comparable to

what is seen in motorway construction. 5 now have land costs comprising 50%

or more of their budget, which is largely a reflection of their urban location where

land costs are higher.

Given the substantial number of variables affecting cost, the preparation of data

on the unit costs per square metre of road did not yield useful information that

would facilitate a Programme-wide comparison. The difficulties encountered are

consistent with prior experience of previous reviews.

The use of Competitive Tender for the procurement of design and construction

contracts was the norm across the Programme. This represents a shift from

earlier studies in 1997 and 2002.

3 Some of the individual figures that formed the basis for this aggregate amount are estimates. This figure is likely to be higher.

13

Administration costs are estimated at 0.2% (approx) of the Programme budget in

2008, and 0.25% over its entirety. This compares favourably with other VFM

reviews and with strategic roads programmes in England and Scotland.

Administration costs within local authorities proved difficult to calculate, but the

introduction of a new system of overhead apportionment should make this easier

in future.

Most of the roads were constructed to have a design-life of 20 years. At that

point, rehabilitation works will be required. As a rough indicative estimate, this

could cost up to €61m (in 2008 terms). These costs will, in the main, fall to be

met by local authorities.

Chapter 9 – Future Public Funding

Pressures on the housing market have significantly eased, and policy priorities

have shifted toward integrated and sustainable development. In line with this

change, the new strategic programme to support regional and local roads that

contribute to the implementation of the National Spatial Strategy was put in place

in 2006. This programme has been endorsed by the „National Development Plan

2007-2013‟, and in the Department of Transport‟s Statement of Strategy (2008).

Experience in relation to cost increases and delays supports the need for a more

formalised framework for project appraisal, approval and monitoring.

Chapter 10 - Performance Indicators

There is already quite a comprehensive system of performance indicators in

operation for regional and local roads. These cover the five different indicator

types as set out in the Department of Finance „Management Information

Framework‟ guidelines (Dept. Finance, 2001), namely: „Strategic‟, „Effectiveness‟,

„Quality‟, „Efficiency‟ and „Activity‟.

Any additional indicators should be informed by the criteria used to appraise

projects under the new programme. The twin factors of cost increases and

delays can be monitored by the Department through reporting procedures.

Chapter 11 – Concluding Comments and Next Steps

The strategic programmes (both current and new) constitute 14% of the regional

and local roads budget in 2008. It was beyond the scope of the review to say if

strategic roads are more deserving of Exchequer support than the other policy

priorities within the Regional and Local Roads Division.

14

The central conclusion from this review is that strategic roads are worthy of

investment, and the central recommendation is that a revised system of appraisal

is needed to assure value for money.

3. RECOMMENDATIONS

1. When the Programme was established some projects did not have measurable

outputs in the form of housing units and development lands. Notwithstanding the

case that existed for funding these roads, there is a need to have a more uniform

approach to output indicators, which allow a common basis for the comparative

appraisal and evaluation of projects.

2. For future reference, the key benefits and outputs that are anticipated to accrue

from roads programmes should be subject to an estimated timescale for delivery.

This is notwithstanding the fact that some factors affecting delivery may be

outside the direct control of the Department or the local authority.

3. Public consultation procedures for local authority roads, and requirements to

undertake Environmental Impact Assessments are a necessary and important

part of the planning process. While it is difficult to envisage every eventuality,

estimates of time taken to conclude these processes should be based on realistic

assessments.

4. Based on the widely expressed view of local authorities as part of this review,

seeking a Compulsory Purchase Order at an early stage brings greater clarity

and certainty in planning the likely time that land acquisition will take. However,

there are situations where negotiated agreement can be both quick and effective

in securing land from developers at preferential rates. These circumstances can

typically apply where there is a limited group of owners with a vested interest in

co-operating to see that the road project proceeds.

5. Overall, there is a need for greater rigour in the estimation of project timescales.

The probability of delays occurring and their potential impact should be assessed

at the outset in a risk analysis as part of the pre-approval project evaluation

process.

6. Where delays occur and become particularly serious, there is a need for a formal

framework within which their impact can be assessed by the Department.

7. The case study areas in particular identified the importance of good integrated

and sustainable planning. This manifests itself through linkages with local,

regional and national planning policy objectives. The extent to which project

proposals are consistent with other policies should be a key consideration in the

future appraisal of strategic roads projects.

15

8. The review has found that a good deal of localised traffic count data is generated

by local authorities. When this data is being gathered, it is important that it is

done in a manner that will facilitate its application and use in the future appraisal

of road projects (through multi-criteria and cost benefit analysis).

9. „Additionality‟ in the Programme particularly arose with the larger projects. There

is a case that the new Strategic Regional and Local Roads Programme

(established in 2006) should therefore focus on larger-scale projects that are

consistent with wider strategic development objectives.

10. The Department should not give full and irreversible approval to projects based

on initial cost estimates.

11. Problems related to cost increases and delays should be addressed through a

more formalised structure or framework for project appraisal, approval and

monitoring.

12. Where a proposed road project has the capacity to generate development levies,

there is a case for this to be reflected in the proportion of funding provided by the

Department.

13. Once the remaining €70m in commitments (including for 2008) to existing

projects under the Programme is met, the original Strategic Non-National Roads

Programme should be concluded. While the broader objectives of the original

programme to support residential and economic development are still valid, they

should be subsumed into the new programme to fund strategic regional and local

roads aimed at supporting the objectives of the National Spatial Strategy.

14. Any new system for the appraisal, approval and monitoring of projects should be

based on the Department of Transport‟s „Guidelines on a Common Appraisal

Framework for Transport Projects and Programmes‟ (2007) and Department of

Finance „Capital Appraisal Guidelines‟ (2005). These should be suitably adapted

to reflect the policy priorities of regional and local roads.

15. In the interests of administrative efficiency, an application form should be

developed for the Programme. The structure of the application should be

consistent with information requirements as set down in the Department of

Transport and Department of Finance appraisal guidelines. This would allow for

the assessment of costs and benefits through the use of a „Project Appraisal

Balance Sheet‟. By implementing a staged approach, as recommended in the

Department of Finance guidelines, the application form could be effectively used

as the basis for „Preliminary‟ appraisal in the case of projects costing more than

€5m. If these larger projects were found to have merit, they could then undertake

16

a more detailed appraisal. The application form could also be simultaneously

used for undertaking a „Single‟ appraisal for projects costing less than €5m.

16. Given the experience of the current programme, there should be a facility for the

Department to review the level of costs and the case for the proposal once full

planning, design and land acquisition issues become clear. In the case of land

acquisition in particular, a final estimate of costs should be provided to the

Department for approval before the „Notice to Treat‟ activating the Compulsory

Purchase Order is served on land owners.

17. Currently, contract documentation must be submitted to the Department for

approval in advance of advertising for tenders. This procedure should be

retained and incorporated into the new system of appraisal.

18. There is a need to re-state in more detail, the objectives of the new strategic

programme. These are currently set out in general terms. This will aid the

appraisal of proposed projects, and assist in their monitoring and evaluation.

19. The new strategic programme would benefit from having a defined time frame

within which it is expected to operate. A logical lifespan would be the duration of

the current NDP, up to 2013. In advance of this date, the Programme and its

objectives could be reviewed, before the successor plan to the NDP is agreed.

20. There should be an expectation that some of the „Betterment‟ arising from the

road development be captured, either through „General‟, „Special‟ or

Supplementary‟ development levies. The capacity of proposed road projects to

facilitate development should be assessed when the project is being appraised

by the Department.

21. In the application form, evaluation documentation and monitoring reports, all cost

estimates should be disaggregated under the four standardised headings of:

„Land‟, „Construction‟, „Design & Supervision‟ and „Other‟. This is already being

done on other regional and local roads programmes. The format enables

comparisons to be made on the key elements driving the costs of projects.

22. Given its particular significance, disaggregated data should be collected in a

manner that would allow comparative analysis to be regularly carried out on land

costs.

23. Additional output and outcome indicators will be dependent on the final format of

any new system of appraisal, and the relative weighting given to different criteria

in the assessment of projects. It is therefore difficult to be prescriptive at this

point. However, quantifiable indicators should relate to roads outputs, improved

accessibility through journey time savings (where relevant) and levels of

development.

17

24. Using the framework set out in Department of Finance Capital Appraisal

Guidelines (2005), the more complex social and economic outcomes may be

better examined during the „Evaluation‟ stage of the Programme.

18

Chapter 2 Scene Setting

2.0. Introduction

This chapter will consider the theoretical and policy background that informed the

creation of the Programme. While the commitment to establish the Programme was

contained in a specific policy document, it was underpinned by certain analytical

perspectives. In some cases these were explicitly stated while in others they were

implicitly understood. The chapter draws upon a range of source materials that

includes academic studies, Government policy documents, inter-governmental and

international studies, Departmental files, consultancy reviews and other policy

material.

This chapter is divided into three distinct sections. Section one looks specifically at

the „Irish Housing Market‟. A key objective of the Programme was to provide

infrastructure to facilitate the supply of housing. Such policy measures are designed

as a stimulus to trigger an anticipated response. Underpinning such interventions

are a series of assumptions about the behaviour of markets. This involves the use of

a variety of terms, some of which are widely understood, other less so. This

terminology is discussed and explained. The most significant studies of the Irish

Housing Market in the past decade have drawn upon econometric models that use

advanced statistical techniques. While these types of studies are beneficial in

giving an understanding of the housing market, they have limitations. This is

especially so when it comes to examining the role that infrastructure plays in the

supply of housing. These studies are reviewed and examined. Conclusions are

drawn that influence the methodological approach adopted later in the review.

The other main objective of the Programme was to facilitate the provision of lands for

industrial and commercial development. From an economic perspective, there is a

wide-ranging (but not unanimous) acceptance that the provision of public roads

infrastructure is a key element in promoting economic growth. The „Role of Roads in

Facilitating National and Regional Development‟ is then examined. . It considers a

number of international perspectives, as well as looking at experience here in Ireland.

The assessment of economic benefits associated with regional and local roads

expenditure poses particular challenges. The standard methodological approach in

the economic assessment of roads infrastructure is Cost Benefit Analysis. The

appropriateness of applying CBA in the current study is examined. This discussion

19

offers a further foundation in selecting the methodological approaches to assess the

social and economic impacts of the Programme.

The third section of this chapter is entitled „Reviewing Other Reviews‟. This

dissertation follows the template of a „Value For Money Review‟. At the core of such

reviews is the study of „Efficiency‟ and „Effectiveness‟. Since the mid-1990s, these

areas have been scrutinised in some detail in relation to non-national roads

programmes. This has in turn led to the strengthening of quality control regimes

locally and nationally. Developments in recent years are critically examined, and

issues of relevance to the current review are identified. These lessons will also feed

into the methodologies employed in the review, and are also of relevance when

potential future performance indicators are identified later.

2.1. The Irish Housing Market

2.1.1. The Factors Driving Supply and Demand

This section examines the major studies of the Irish housing market in recent years.

One purpose is to explain the key influences driving the market. An understanding of

these influences is crucial in explaining the pressures that necessitated a policy

response. However another reason is to consider the methodological limitations of

some of the techniques described. While many of these techniques explain „bigger-

picture‟ issues, they may not be appropriate to a more tightly-focused review like that

being conducted here.

In theory, demand (what buyers want) and supply (what sellers will make available)

determines the quantity of goods produced and the price charged in a market. The

„equilibrium price‟, is the price at which quantity supplied equals the quantity

demanded. Cases can arise where the quantity demanded exceeds the quantity

supplied, a situation described as „Excess Demand‟. When this happens the price

usually goes up and there is unmet demand. In a properly functioning market, supply

should expand to meet this demand and a new „equilibrium price‟ will be set. In fact,

the key question in most policy analyses of housing is whether the market responds

with more supply or higher prices (Malpezzi & Maclennan, 2001).

Demand and supply are influenced by certain factors. These are described as the

„conditions‟ of supply and demand. In the model used by Bacon et. al. (1998), the

principal factors contributing to demand in Ireland were identified as: real income, the

20

cost of finance (which incorporates the interest rate and the capital appreciation of

the asset), demographic patterns and other variables that could not be specified. On

the supply side, the principal factors identified were: price, costs (e.g. land and

construction) and demographics (1998, p.37, p.113). Changes in the „conditions‟ of

demand and supply have a knock on effect. For example, when real incomes

increase, housing demand increases (all else being equal).

An increase in demand should, in theory, result in an increase in supply. However

because of the time taken to acquire development land, seek planning permission

and undertake construction, there can be a significant time lag before the supply

response kicks in. Not surprisingly therefore, Bacon et al. found a substantial

difference between the short-run and long-run response of housing supply to

demand. In the short-run a 1% increase in house prices resulted in a 0.92% increase

in house completions (even taking account of a natural time lag of 1 year). However,

in the long-run, the supply response was estimated at 3% (ibid. p. 41). However, of

greater significance was the finding that the corresponding figure for Dublin region

was 1.8%. In other words it was less responsive. This indicated that there were

particular constraints on supply that required a policy response. Bacon concluded

that a shortage of infrastructure to support housing development was one of the main

causes. This informed the policy response that led to the Programme being

established.

This review is particularly interested in how supply responds to demand, and there

are different methodological models used in the housing market to estimate this. The

most prevalent is the method described above which is based on statistical

techniques. A more recent study by Girouard et. al. (2006) which considered various

studies on house price determination across OECD countries notes that such

econometric studies, although useful, can be unstable. They advise that they be

complimented by other approaches (ibid., p. 10). In the first Bacon report (1998), the

statistical analysis was supplemented by a qualitative survey of practitioners and

professionals active in the housing market. This involved the administration of a

survey to a relatively small group of eight people. For the purposes of the review at

hand, it suggests that the views of those involved in the supply of housing can make

a useful contribution.

21

2.1.2. Supply and Demand– Implications for the VFM Review

The decision to set up the Strategic Non-National Roads programme can be traced

directly from the economic logic of supply and demand. The Bacon reports

concluded that economic fundamentals had unleashed effective demand in the

market. The economic factors driving demand were principally: income and

employment growth, an increase in population and low interest rates. A relatively

limited supply response had helped drive up prices, particularly in the Dublin area.

While the availability of suitably serviced land with water services infrastructure was

pinpointed as a more serious constraint on supply, roads were also identified as a

factor.

The message flowing through the three Bacon reports, and the subsequent

Government policy responses was that supply-side constraints had to be tackled

through policy interventions, backed up where necessary with public expenditure.

The decision to provide specific funding for a new scheme to support roads

infrastructure was one of a number of policy measures. On the supply side, the

obvious intention was to increase the supply of suitable development land and

housing. In addition there were a range of demand-side policy measures to dampen

demand in certain segments of the market. The overall intention was “to maximise

and expedite housing supply, secure house price stabilisation, address affordability

and ensure balanced growth of the market in the future” (DELG, 1999, p.1)

This analysis has similarities to conclusions reached by the NESC in its seminal

2004 report entitled „Housing in Ireland‟ (2004). It noted that a key element in the

supply of housing is the availability of suitable land on which to build. Decisions on

planning and infrastructure were identified as major influences on the supply of this

land and its price, and the price of housing.

Looking across the three policy documents launched by the Government in

conjunction with the three Bacon reports, there are approximately 70 different policy

measures or submeasures. These included, for example, changes in stamp duty tax,

the expansion of college courses for planning professionals, changes in capital gains

tax for development lands, new planning guidelines, expanded housing densities and

an increase in staff for Board Pleanála, to mention just some. The approach adopted

by the Government was a broad one. It attempted to understand the dynamics of the

housing market from a wide range of perspectives and respond accordingly.

22

At an aggregate level, the success of policy measures to increase housing supply

can be measured in simple terms by counting the number of houses built. This is a

valid and useful exercise, even if it is difficult to disaggregate the affects of individual

policy measures on the supply of housing. Within this VFM review, the numbers of

housing completions and amount of land made available for development within the

specific areas benefiting from newly funded road infrastructure are treated as

relevant output indicators. However, a key issue here is causality, and assessing the

role played by infrastructure in the delivery of the Programme objectives.

There are also other issues that need to be considered. A core reason for having

policy interventions to increase supply was to help address affordability problems. In

evaluating a single supply-side policy measure (in this case roads investment), one

needs to ask if the house price increases that occurred were justified by prevailing

economic conditions, or if they were caused by supply failures in the market. This is

important in assessing if the policy response was appropriate. An important way of

answering this question is to assess if price increases reflected what are called

„economic fundamentals‟. Ireland was somewhat unusual in that both house prices

and housing supply were expanding simultaneously at rates never previously seen.

In order to understand why the Programme was put in place, it is also important to

consider why the Irish housing market behaved as it did.

2.1.3. What Caused Irish House Prices to Rise?

Between 1995 and 2005 house prices in Ireland roughly tripled in real terms. The

vast majority of developing countries have seen increases in house prices over that

decade. However, Ireland outstripped them all (Girouard et. al., 2006, Honjo et. al.,

2004).

In 2006, the OECD investigated the issue of Irish house prices (Rae & van den

Noord, 2006). They used a variety of different methods to make their assessment.

An econometric model was applied to estimate the „fundamental price‟ – or the price

that houses should be based on demand and supply factors. In theory, if the actual

market price is above this „fundamental‟ price or „long-term equilibrium level‟, then it

would be an indication that houses were overvalued and possibly driven by

unrealistic expectations of capital gains. Using this method, Rae & van den Noord

concluded that between 80% and 90% of house price increases were justified by

fundamentals, namely, rising incomes, lower interest rates and demographic factors.

The remainder, they said was „speculative froth‟ (ibid., p. 13).

23

While this research focused mainly on demand-related conditions, the supply side

response was commented upon favourably. The contribution of relaxed zoning rules

in fueling a major expansion of supply was noted (ibid. p. 9). However, the report

predicts continued long-term demand and cites the fact that the number of people per

dwelling in Ireland is significantly higher that in other OECD countries. If Ireland does

(as expected) converge towards the norm for other developed countries, this would

lead to continued demand for housing (even without taking account of an expected

increase in population). This is obviously an issue for future housing policy in Ireland

and is considered in more detail in Chapter 5.

On the supply side, the OECD analysis echoed that of the Bacon reports in

acknowledging that the sharp increase in prices in the mid-1990s may have reflected

in part relative particular constraints like land, infrastructure and planning (Girouard

et. al., 2006, p. 14). However, there also appears to be a consensus that the supply

side response has been significant. Studies by both the OECD and IMF use the

same language, describing it as “unprecedented by international standards” (Rae &

van den Noord, 2006, p.9, Honjo et. al., 2004, p.22). Similar language has also been

used by the NESC (2004, p. 34).

A reasonable conclusion to draw from all of this is that Irish house prices increases

largely reflected changes in the economic fundamentals, but with an element driven

by speculation. As the NESC noted in its report:

“Given the remarkable strength of demand – driven by unprecedented

growth in incomes and employment and a range of demographic

factors – a significant increase in prices was inevitable. Although the

supply response was delayed, Ireland has displayed a very large

increase by both historical and international standards” (2004, p.1)

The studies of the housing market were generally saying that most of the housing

demand was driven by factors that required a supply-side response. In other words,

more houses needed to be built. Given the established relationship between roads

infrastructure and housing supply, this needed to be a feature of any policy response.

There was therefore a clear justification for the Programme.

24

2.1.4. Expanded Housing Supply

Describing the expansion in Ireland‟s housing supply witnessed over the past decade

as „unprecedented‟, as both the OECD and the IMF have, is certainly not hyperbole.

Over 600,000 new homes and apartments were built between 1997 and 2006, which

represents approximately one third of all housing stock in the State (DEHLG, 2007a,

p.14). At the time of the launch of the Programme in 2000, annual housing

completions totaled 49,812. By 2006 this figure had risen to 93,019, although it fell

back to 78,027 in 2007 (DEHLG, 2001-2008). The table below sets out the number

of annual house completions in the intervening period. These completions include

private, local authority and voluntary and co-operative housing.

Table 2.1. Annual House Completions 2001-2007

Period

Completions

2000 49,812

2001 52,602

2002 57,695

2003 68,819

2004 76,954

2005 80,957

2006 93,419

2007 78,027

(DEHLG, 2001-2008)

The expansion of supply to meet growing demand can also be seen as a crucial

element in maintaining the affordability of housing. Increased supply exerts a

significant downward pressure on prices. Going back to the first Bacon report, it was

estimated that a 1 percent increase in housing stock would lead to a decrease in the

price of housing on 2.08% (1998). This figure is broadly consistent with those quoted

in the 2006 OECD Economic Review for Ireland, which estimated the elasticity of real

house prices relative to housing stock supply as –2.0 for new houses for the period

1977 to 20044. In other words, there is a direct and proven inverse correlation

between housing supply and house prices. The significance of such an observation

for the review is that it provides the conceptual link between policies to increase

supply and those to achieve greater affordability. This was an important objective

that informed the establishment of the Programme.

4 The research notes that this time trend is relative to the population aged between 25 and 44.

25

There is little doubt that public policy has played a crucial role in facilitating the

expansion of supply. Relevant policy measures include, for example, increases in

housing densities, improvements in the processing of planning applications, the

implementation of regional planning guidelines, the preparation of local authority

„Housing Action Plans‟ and the instigation of active land management strategies to

assure sufficient quantities of zoned and serviced land. However the difficulty from

an evaluators perspective is trying to identify the effects of a single intervention like

roads infrastructure on complex housing-market behaviour.

In addition, DiPasquale notes that empirical evidence on the supply side of housing is

far less convincing than on the demand side (1997, p.2). In other words, we know

more about the factors driving demand than we do supply. This is evident in many of

the recent studies of the Irish housing market, where housing supply is seen mainly

as a function of the conditions of demand. Also, a key problem in assessing how

housing supply responds, is the lack of evidence on the behaviour of housing

suppliers. As Di Pasquale notes, “this remarkable lack of information on the major

actors in housing supply presents a significant obstacle to increasing our

understanding of housing supply” (ibid., p.3). What she had in mind was information

of a quantitative nature, but the same holds true for qualitative evidence as well. We

do know that if prices go up, so should supply. But as DiPasquale concluded, price

is not a sufficient statistic in its own right to explain the market response with new

supply, although other indicators are difficult to explain (ibid., p.23).

The VFM review at hand will set out to identify the contribution that roads

infrastructure makes in the supply of housing. The preferred approach in exploring

this relationship is to combine quantitative data on housing supply with qualitative

information using interview and case study techniques. The methodology chapter

provides a fuller explanation of the research instruments used. However, input from

those directly involved in the supply decision (builders, developers and planners) will

be a valuable source.

2.1.5. The UK Experience – The Barker Report

Ireland isn‟t the only country internationally to experience problems with rising house

prices. Many others have also faced recent policy challenges in attempting to match

the supply of housing with demand. In the vast majority of OECD countries, house

prices in real terms steadily increased from the mid 1990‟s up to 2005 (Girouard et.

al., 2006). However, Ireland, the UK, the Netherlands and Spain are identified as

26

having experienced a housing boom in recent years with significant real house price

gains (ibid, p.22). The UK in particular faced a similar situation to that in Ireland,

albeit with differences in specific causes and characteristics. In its case, complex

and inefficient zoning rules and a slow authorisation process were identified among

the reasons for the rigidity of supply (ibid.). These were compounded by widespread

failures to provide supporting infrastructure to enable new houses to be built.

In response, the British Government commissioned Kate Barker, a senior economist

at the Bank of England to undertake a study, which in many respects is similar to the

Bacon Reports in Ireland. An interim report and analysis published in 2003 noted

that between 1971 and 2001 real house price inflation in the UK was around 2.5%, in

comparison with a European average of 1.1%. Between 1996 and 2001 prices were

increasing by an estimated 9% per annum in real terms. While much of the rise was

attributable to factors such as interest rates and economic activity, the weak supply

response was a key factor. Demand was rising, but was being met with higher

prices, rather than increased supply (Barker, 2003, p.5). Kate Barker‟s final report

published in 2004 concluded that physical and social infrastructure shortcomings

constrain development and stated specifically that: “the Government should make

resources available for infrastructure provision to bring forward development”

(Barker, 2004, p.53).

The Government responded by establishing a new „Community Infrastructure Fund‟.

It was announced in July 2004 and earmarked £200m sterling in funding for use in

four „Growth‟ areas that had been identified in an earlier Government policy

document. The objective of the Fund was:

“to support transport infrastructure costs to enable faster housing

development in four growth areas in 2006/07 and 2007/2008. It will

complement not replace mainstream transport funding in these areas”

(ODPM, 2004)

The Barker Report and the decision to establish the „Community Infrastructure Fund‟

is of direct relevance to the review of the Programme on a number of counts. It

offers a validation of the economic analysis and policy approach adopted in Ireland,

specifically in setting up an earmarked transport infrastructure fund. In Ireland

however there was a narrower focus on roads. The Barker report in the UK

considered the deeper economic rationale behind government intervention to fund

transport infrastructure to support housing development and concluded that it had a

27

sound basis (2004, p.53). It adopted a targeted approach to focus on a limited

number of areas (similar to Ireland). The existence of such a programme can also

provide a useful basis to examine and compare elements of both schemes that are

similar in nature.

The focus of the scene setting chapter so far has been on the factors influencing the

housing market, and the role played by roads infrastructure. This emphasis now

shifts towards the second major purpose of the Programme.

2.2. The Role of Roads in Promoting National and Regional Development

2.2.1. General (but not Unanimous) Agreement

The Programme was set up to help boost the supply of housing. However, its other

main objective was to facilitate the provision of lands for industrial and commercial

development. This is generally in line with wider national policy objectives as set out

in successive National Development Plans. According to the current NDP which

covers the period 2007-2013, the promotion of regional and national development

through the provision of infrastructure (including roads) are key national priorities.

The importance of the road network to the economic well-being of the country is

specifically highlighted. It notes that currently, 98.3% of internal merchandise trade

is carried on the road network, both national and non-national, (NDP, 2007, p.130).

From an economic perspective, there is a wide-ranging (but not unanimous)

acceptance that public infrastructural provision is a key element in promoting

economic growth (Ter-Minassian & Allen, 2004). However, many of the published

studies focus on larger national-level projects in various countries. Economist

Andreas Kopp in a paper published as part of a discussion on productivity in Ireland

showed that an increase in road investment improves national productivity growth.

He proposes a more selective approach to projects based on their rate of return. He

suggests that local roads can have higher than expected rates of return, justifying

public investment (Forfás, 2007, p.291).

One of the most influential (and critical) voices in the study of the economic effects of

infrastructure, Edward Gramlich (1994) highlights the importance of distinguishing

between social and economic objectives. He uses roads infrastructure to highlight

how a new motorway might provide a high rate of return if subjected to economic

evaluation like cost benefit analysis. However a rural road might provide a low or

28

even negative rate of return. Its objectives might be more social than economic.

When it comes to evaluating the impact of infrastructure, Gramlich also offers an

important caution in saying that “it will always be difficult to relate infrastructure

investment to its goals or changes in them”. He cautions against overestimating the

economic benefits of public infrastructure in economic development. The need to

consider social as well as economic impacts is something that this review will take on

board.

2.2.2. Ireland‟s Experience

In Ireland, the justification for expenditure on roads is based on both economic and

social grounds. In the case of the larger national roads, their role in driving economic

development is given greater emphasis. However, regional and local roads make an

important contribution to economic and regional development. This was specifically

examined in the mid-term review of the last National Development Plan undertaken

by the ESRI. It noted that the social rate of return for non-national roads projects

may not be as high as other more risky projects, however they did have the

advantage of offering a more certain return (Fitzgerald et. al., 2003, p. 84). The

presence of this lower, but certain rate of return provided a basis for the evaluation‟s

recommendation that funding be increased. A further conclusion is relevant to the

choice of methodological approach for the present VFM review. The report stated

that while it is very difficult to calculate such returns in a formal way, it is important

that they are taken into account in a qualitative fashion (ibid.). This raises particular

questions about the choice of research instrument, and particularly whether or not a

quantitative approach like cost benefit analysis is either feasible or desirable in

assessing non-national roads programmes. These issues are considered further in

the next section.

Investment in roads would appear to confer a competitive advantage on regions in

attracting investment and boosting a local economy. Haughwout highlights the

importance of roads in regional development. He provides empirical evidence

showing that infrastructure investments affect the relative attractiveness of places,

potentially redirecting growth from infrastructure-poor areas to those that have

invested more heavily (2000, p.26). Regional development and the redistributive

qualities that are ascribed to road infrastructure in promoting economic growth are

explicitly recognised in Ireland‟s latest NDP (2007, p. 84).

29

A similar rationale underpins regional roads infrastructural investment in Scotland

(Page, 2005). Both countries have comparable population sizes, with a mixture of

dispersed and concentrated settlement patterns. However the Scottish Executive

publishes Transport Appraisal Guidelines, which are more specific than those

available in Ireland. In particular, detailed advice is given on the appraisal of the

„Economic Activity and Location Impacts‟ of transport infrastructure investment.

These recommend that information drawn from the business community, along with

employment and economic data, should be used when appraising the case for

specific project investment. Some useful pointers for the review can be drawn from

these guidelines.

The economic significance of roads investment for national and regional economic

development has informed roads expenditure going back to the 1970s and into the

1980s. Prior to the 1970s roads investment in Ireland lagged considerably behind

the European norm, and the link between economic development and public roads

infrastructure largely hadn‟t been made in public policy. Historically, the national

policy focus of road expenditure had more to do with alleviation of unemployment

through the creation of seasonal jobs, than on the provision of transport

infrastructure (Daly 1997). The idea that roads could play a key role in economic

development wasn‟t taken seriously. This was even the case after Ireland embarked

on its programme of economic expansion following the Whittaker report of the late

1950s (Barrett 1982, Daly 1997, Garvin 2004). This position has now completely

changed, and infrastructural provision linked to economic growth is a fundamental

principle upon which the current and recent National Development Plans have been

based. Given the Irish economy‟s strong focus on encouraging foreign direct

investment, the development of good quality roads is a justifiable economic

objective. The view of IDA Ireland is that investment in transport infrastructure is

particularly critical for success in attracting foreign direct investment (2007, p. 9).

Whilst investment in roads can encourage economic growth, there is also evidence

that economic growth can in turn lead to a demand for infrastructure, as a review of

research in this area by De Haan et. al. (2007) showed. This observation is relevant

to Ireland, which has seen unprecedented economic growth in recent years. The

accepted assumption on which Irish infrastructural planning is based, is that traffic

volumes tend to increase broadly in line with economic growth (in the absence of

demand reduction measures) (NDP, 2007, p.131). In the case of Ireland, the

economy has grown by approximately 6% per annum in the past decade (ibid.),

30

although future forecasts are more modest. The economy is expected to contract by

0.4% in 2008, while growth in 2009 forecast to be 2% (ESRI, 2008). Car ownership

rates in Ireland are below the EU average, and are likely to converge in the coming

years putting increasing pressure on roads infrastructure (ESRI, 2006, p.134).

These issues are highly relevant to future policy objectives and interventions to cater

for transport demand. Future traffic forecasts for non-national roads up to the year

2040 predict that volumes of heavy good vehicles will increase by 50% between

2002 and 2040. Car and light-goods vehicle traffic is expected to increase by 43%

(NRA, 2003, p. 3).

The rationale informing the Programme could be seen as a response to the double-

edged effect of infrastructural investment. The investment was intended to

encourage economic growth, which in turn is contributing to a further need for

infrastructure. A key justification for the Programme‟s establishment was that “rapid

economic development began generating a need for targeted investment in non-

national roads in certain areas” (DELG, 2000b). The investment in regional and local

roads infrastructure can be seen as both a response to economic growth, and a

means to further stimulate it.

2.2.3. Assessing the Social and Economic Outcomes of Non National Roads -

The Appropriateness of Cost Benefit Analysis

Difficulties in assessing benefits associated with non-national roads investment pose

a particular challenge. A key methodological decision for the review is whether to

apply a specific instrument like cost benefit analysis. The alternative approach would

be to use other quantitative social and economic data, supported by qualitative

sources. As has been noted already, qualitative assessment can offer important

insights that can sometimes be overlooked. However, cost benefit analysis also has

its advantages. A review of roads expenditure under the last NDP acknowledged

that the routine estimation of benefits was not possible on non-national roads

projects. However it did recommend “that a cut-down form of cost benefit analysis

might be applied to a sample of projects each year in order to gain some information

on, and reassurance about, the benefits of expenditure of the relatively large

amounts of money involved” (Fitzpatrick, 2002, p.15c). The threshold for undertaking

Cost Benefit Analysis at project appraisal stage is €30million. While most of the

projects under the Programme were of a much smaller scale, the next section of the

review with examine the feasibility of conducting Cost Benefit Analysis for individual

projects. CBA is widely applied in relation to roads projects in Ireland, albeit for

31

larger national and motorway routes. However it is not currently used as tool for

either ex-post appraisal or ex-ante evaluation of regional and local roads.

As an evaluation technique, CBA is rooted in the principles of „Welfare Economics‟.

It attempts “to evaluate on a common monetary scale the costs and benefits of all

marketed and unmarketed consequences of projects and to estimate the net social

benefits” (Mulreany, 2002, p.1). Where the benefits exceed the costs over the

lifetime of the project a „net present value‟ or economic surplus accruing to projects

and society can calculated. The form of cost benefit analysis currently applied to

roads projects in Ireland is an adapted version of the UK „COBA‟ computer-based

system5. Guidelines are published by the National Roads Authority (NRA, 2005).

In practice, calculating the costs associated with roads projects are fairly

straightforward. They consist of capital and maintenance expenditure. User benefits

however are calculated based on changes arising in travel times, the operating costs

of vehicles and accident costs (NRA, 2005, p.A4). Travel time changes generally

make up the majority of benefits in Ireland as they do in other countries. In the UK

for example, they represent approximately 75% of quantified benefits for road

schemes and up to 80% for European transport infrastructure projects. These are

broadly consistent with figures in Ireland which have recorded up to 90% of benefits

from travel time-savings (Keegan 1999, ECMT 2001, Wallace 2005). The principle in

valuing these benefits is that shorter journey times from road improvements result in

time-savings. These are translated into monetary values based on a notional

„willingness to pay‟ on the part of each user. Standardised national parameter values

for time-savings, operating costs and accident savings are applied. These are based

on market values. These parameter values were prepared by Goodbody Economic

Consultants on behalf of the Department of Transport (Goodbody, 2004).

Environmental and other impacts that can‟t be quantified monetarily are assessed

separately. Notwithstanding the criticism of CBA that it falls short of full social

analysis (something acknowledged in the NRA‟s guidelines), it is the standard tool

used in the assessment of roads projects. It also forms a central plank of the

Department of Finance‟s Appraisal Guidelines for Capital Projects (2005).

5 The version in current use is „Coba11 (Release 6)‟.

32

Changes in traffic flows form the core basis for assessing benefits through the

„COBA‟ method used in Ireland. However the traffic forecasting process is carried

out separately and input to the computer programme. A comparison is made

between traffic flows with and without the road development. Crucial issues surface

here in relation to the Programme. These arise at both a conceptual and practical

level. COBA calculations are based on what is called a „Fixed Trip Matrix‟ traffic

pattern. This rests on the assumption that the road improvements will not affect the

overall number of trips made. When road improvements take place, several changes

in trip pattern are possible in principle, and are referenced in the NRA guidelines

(2005, p.A6). These possible changes are summarised and synopsised below:

The re-assignment of traffic from an existing route to a new route,

Trips may be made at a different time of the day,

Traffic may change its origin or destination (going longer distances for

example),

There may be „modal shift‟ with people using a different mode of transport

(e.g. going by car instead of bus, or vice versa),

New trips may be generated. This would include the release of suppressed

demand for travel.

The COBA method operates on the assumption that only the first of the above

reactions occurs and that demand does not increase as a result of the scheme.

These assumptions, which are widely prevalent in cost benefit analyses have been

critiqued by, amongst others, Goodwin (1996), Noland and Lem (2001), and more

recently by Litman (2007). A synopsis of seven major studies on induced traffic

points to generated traffic effects ranging from 10% to 50% in the short term, and up

to 100% in the long term (Litman, 2007, p.7). The consequences when new journeys

are not fully considered in an appraisal were described succinctly in widely quoted

comment from a 1994 report on Trunk Roads for the UK‟s Department of Transport.

It states that: “the economic value of a scheme can be overestimated by the omission

of even a small amount of induced traffic. We consider this matter of profound

importance to the value for money assessment of the roads programme” (SACTRA,

1994).

There are also deeper social impacts that can be difficult to quantify or even monitise

through a cost benefit analysis. Litman argues for example, that induced traffic

creates car dependent transportation and land use patterns (2007, p.22). A similar

33

conclusion was also reached by Noland & Lem (2001, p.28). Consideration of these

issues is of obvious interest to Government policies on sustainable development and

there is some evidence of these trends emerging in Ireland. These are examined in

more detail in Chapters 4 and 5. Overall, there are a number of emerging issues of

practical and conceptual significance in the use of methodological instruments to

evaluate the outcomes of road infrastructure in general, and the Programme in

particular.

2.2.4. CBA - Practical and Conceptual Issues for Non National Roads

Clearly for the Programme here, a key objective in developing new road

infrastructure was to cater for additional housing. As a consequence it set out to

generate additional traffic and induce new demand. From a practical point of view, a

„Fixed Trip Matrix‟ and conventional CBA as normally applied to National roads

projects would therefore ignore a central purpose of the Programme, which was to

create and facilitate new journeys above and beyond increases that could be

expected. This was precisely the point made by Devlin and Feeney in their paper

„Developing an Economic Evaluation Procedure for Road Investments‟6. They

commented on the general usefulness of CBA as an important instrument in

economic evaluation and in guiding investment decisions. However they noted that:

“Its use in the urban context or for strategic road investment plans is

not advisable because, in such situations traffic levels may be

expected to increase as a result of the investment. For example, in

the urban context, road investments may cause existing road users to

change their journey destinations and may induce additional trip

making which was previously suppressed by road congestion”

(Feeney & Devlin, 1987, p. 248)

The problems associated with using CBA as a tool in making transport decisions that

affect housing development were alluded to in the NESC‟s report on Housing (2004).

It commented that “a narrow cost-benefit approach to public transport investment

decisions, which measured current demand and usage, would miss a fundamental

aspect of urban development: transport not only connects existing places, it makes

new places”, (ibid., p.134).

6John Devlin was formerly Principal Advisor on Non-National Roads in the Department of the Environment. He was also centrally involved in setting up the Strategic Non-National Roads Programme.

34

While there are limitations in its use to appraise certain types of road project,

conventional CBA could be used for investments where induced traffic is not a

significant issue. It is an important tool in assessing the wider economic and social

consequences of a roads project. Reduced journey times and other quantifiable

benefits are an important measure for assessing improvements in economic welfare.

However, initial inquiries suggest gaps in data and practical difficulties. In developing

a traffic model for use in carrying out a CBA, the following items of data are required:

Origin and destination surveys,

Traffic count data,

Journey time surveys. (NRA, 2005, p.B13).

Further data based on longer term surveys are also needed to estimate seasonal

traffic differences, vehicle mix proportions and other factors. Preliminary discussions

with Departmental and local authority personnel at the outset of the VFM review

suggested limitations in the quantity and quality of traffic data for non-national roads.

A national data-set of traffic counts for National Primary Routes is gathered and

published by the National Roads Authority. In contrast with the situation for national

roads, there is no systematic nationwide programme of data collection for non-

national roads. This is not surprising given the dispersed nature of the network and

the potential costs involved. Both electronic and manual traffic counting is expensive

to conduct. If cost benefit or other quantitative analysis based on traffic counts is to

be feasibly used on non-national roads programmes, reliable local data is needed.

The extent to which this might be available will be examined in the review.

Bearing in mind the limitations already outlined in relation to both conceptual and

practical issues, it is not proposed to subject individual projects or the Programme as

a whole a cost benefit analysis. CBA could contribute useful information in

conducting appraisals of regional and local roads investment in other circumstances.

Its feasibility for future use, and the availability of sufficiently comprehensive data

sources to make this possible will be examined. Where quantitative traffic count data

is available it will be used as an output measure in the review.

2.2.5. Assessing Social and Economic Benefits – Conclusions

At an aggregate level, a clear reason for investing public funds in roads infrastructure

(including regional and local roads) is the promotion of economic development. This

has been the case for many years now, and is a central objective within the latest

35

National Development Plan. This is broadly consistent with international thinking.

Within national-level policy in Ireland, there is a general consensus that investment in

infrastructure is a crucial strategic priority. However, it does not automatically follow

that all roads investment, per se, will have positive benefits. In deciding between

projects at a local level, it is important to consider their individual economic and

social impacts.

The social benefits are particularly difficult to identify and measure. This represents

something of a challenge for the VFM review in developing appropriate approaches

to consider benefits (and indeed disbenefits). Useful pointers have been offered by

the Scottish Transport Appraisal Guidelines, particularly in gathering data about the

impacts on businesses. The social and economic impacts can also be assessed

with reference to demographic, economic and social data drawn from Census figures

and other credible sources. Given that a key purpose of the Programme was to

facilitate housing supply in certain areas, the social and economic impacts caused by

such population increases are worth examining. These matters will be further

addressed in the methodology chapter.

So far the scene setting chapter has looked at policy and evaluation questions

concerning housing and economic development. These issues informed the main

specific objectives of the Programme. However when public funds are committed to

roads infrastructure, there is also a need to ensure that they deliver the maximum

benefit in terms of the efficiency and effectiveness. This is now explored.

2.3. Reviewing Other Reviews

2.3.1. Efficiency and Effectiveness - Key „Value for Money‟ Concepts

Two of the central questions in a Value for Money Review concern „Efficiency‟ and

„Effectiveness‟. Drawing upon the definitions used in the Department of Finance

Guidelines for carrying out VFM Reviews (2007, p. 33/34), „Efficiency‟ compares the

outcomes that were achieved, against the resources deployed. „Effectiveness‟

considers the extent to which the Programme‟s objectives are achieved and planned

benefits delivered. These are explained in further detail in Chapter 3, which outlines

the methodologies used to study these concepts.

This section looks at recent developments in assessing the efficiency and

effectiveness of regional and local roads expenditure. The lessons identified from

36

other studies will critically inform the techniques deployed in addressing the „Terms of

Reference‟. Understandably, when issues around efficiency or effectiveness

measurement are involved, there is some overlap into the area of Performance

Indicators. The discussion in this section will therefore inform the identification of

potential indicators for future use, which the review is also committed to doing.

Since the mid-1990s, regional and local roads programmes have been scrutinised in

some detail from the point of view of efficiency and effectiveness. This has in turn

led to the strengthening of quality control regimes locally and nationally. At a

practical level, this has manifested itself through the publication of a series of „best

practice‟ guides to achieve greater standardisation of approach across local

authorities. In addition, measurable performance indicators are now routinely applied

in the construction and maintenance of regional and local roads. The coming

paragraphs will examine general developments across wider non-national roads

expenditure, but with specific reference to the Programme. Assessing previous

reviews also conveys something of the complexity and diversity involved in the

physical delivery of these roads.

2.3.2. The First VFM Report on Regional and Local Roads

A key catalyst for much of the progress witnessed in recent years was a report

entitled „A Review of the Efficiency of County Council‟s Operations in the Non-

National Roads Area‟. It was commissioned by the Department of the Taoiseach as

part of the original Expenditure Review process set in train in 1997 under the

Strategic Management Initiative. The main terms of reference were:

“To examine the efficiency and effectiveness of county councils‟

operations on non-national roads with the aim of securing the best value

for money and maximum outputs from expenditure on public roads by

county councils” (KPMG et al.1997, p1)

In one of its main exercises, the review calculated the unit costs per square metre of

road for the more standardised and comparable works that each local authority

undertakes, namely:

Surface Dressing,

Surface Restoration,

Road Reconstruction.

37

These categories represent three different levels and standards of work, each with

differing cost implications. „Surface Dressing‟ as the name suggests, involves an

overlay of new material on an existing road. „Surface Restoration‟ includes surface

dressing and involves more comprehensive work. „Road Reconstruction‟ involves

the regulation or reconstruction of an existing road. However, some methodological

problems that were experienced are noteworthy. The consultants also gathered

information on a fourth category of works which are entitled „Road Improvements‟7.

These include, for example, the construction of new roads, the widening or

realignment of an existing road and the construction of roundabouts (DELG, 2001,

p.69). Because of the level of variation in these types of works, there were significant

differences in cost depending on the type of improvement carried out. The review

found that it wasn‟t possible to achieve valid unit cost comparisons under this

category (KPMG, 1997, p. x). This particular difficulty is relevant to the examination

of the Programme. Almost all of the projects contain elements that come within the

definition of these „Other Improvement Works‟. This poses a challenge in developing

appropriate, comparable and meaningful unit-cost indicators.

Based on their analysis of the data gathered, the consultants made a number of

recommendations. It was proposed that the Department should prepare national

standards and guidelines for local authorities in their work on non-national roads

(ibid. p.xvi). A greater strategic focus was also recommended. At local level this was

to be advanced by linking non-national roads programmes with the objectives set out

in local County Development Plans (ibid.).

In carrying out work on roads, local authorities use a combination of „Direct Labour‟

employed by the Councils, and contractors. The report recognised the difficulties in

assessing the optimal levels of direct labour employment. It recommended the use

of private sector practices work practices and competitive market rates in making this

determination (ibid.).

Following publication of the review, a Working Group consisting of representatives

from the Department of the Environment, County Managers and County Engineers

was set up in 1999. It agreed that a series of „Best Work Practices‟ guidelines

documents should be prepared. In drafting these guidelines, work practices across

7 A comprehensive list of improvement works is included in the „Memorandum on Grants for Non-National Roads‟ originally published by the Department of the Environment in 2001. This is the edition currently in use.

38

local authorities were surveyed. The Working Group was also charged with

examining the issue of Performance Indicators. Overall then, the various efficiency

and effectiveness reforms of the past decade provide an important context for the

present review. The methodological approaches used in previous evaluations also

offer some useful pointers.

2.3.3. The Use of Guidelines to Achieve Standardisation of Approach

Flowing directly from the 1997 Efficiency Review, seven „Best Practice‟ documents

have been published to date and are now in use by local authorities. These outline

the appropriate procedures and practices to be followed in order to comply with

standards in relation to both efficiency and effectiveness. The titles and order of

publication of the guidelines were as follows:

Guidelines on the Depth of Overlay to be used on Rural Non-National Roads

(May 1999);

Guidelines on the Rehabilitation of Roads over Peat (May 2000);

The Machinery Yard – A Value for Money Guide (May 2000);

Guidelines and Tender Documentation for Road Marking Materials (July

2000);

Guidelines for the Opening, Backfilling and Reinstatement of Trenches in

Public Roads (April 2002);

Traffic Management Guidelines (May 2003);

Work Methodologies (2004).

The report on „Work Methodologies‟ is illustrative. It sets out clear procedures to be

adopted in relation to tendering (in addition to statutory requirements). The main

objective here is to encourage transparency, greater competition and value for

money (DEHLG, 2004, p.4). This issue had been raised in the 1997 review. Correct

practices to be followed in the planning, design and preparation of works are

detailed. Appropriate levels of management and decision-making responsibilities for

different scales of project are set out.

A significant part of the guidelines concern quality control. The stated objective here

is to assure value for money and effectiveness of road materials through systematic

testing. Technical procedures, parameter values, and recommended frequencies for

testing are outlined. In particular, the recording of testing results is prioritised to

ensure reporting requirement on „effectiveness‟ performance indicators are met.

39

Recording of information also provides a baseline of data that can be consulted in

assessing the future performance of the roads (ibid. p.19). In other words, if the

grade of material used was expected to have a lifespan of 15 years, effectiveness

can be assessed in the future against the original baseline.

These guidelines are relevant to the review at hand insofar as their presence has

impacted on practices within local authorities. However a relevant observation

concerns their status. Some have clear mandatory effect. For example, all road

works must be carried out in accordance with the „Guidelines on the Depth of

Overlay‟ (DELG, 2001, p. 34). In other cases, elements of the guidelines have been

incorporated into Departmental circulars and are also mandatory. These would apply

to the most significant issues related to tendering, work standards and safety, for

example. Some of the guidelines also appear to act as a form of good practice,

without obligatory effect. While there may be a lack of clarity as to status of some of

the guidelines as a collective body of work, this doesn‟t mean that their effects

haven‟t been positive overall. The general consensus from Department and local

authority officials is that they have been. Where the effects of the Working Group are

particularly prevalent is in the area of Performance Indicators.

2.3.4. Performance Indicators

In advance of the 1997 efficiency review by KPMG, initiatives were already underway

to develop performance indicators within local authorities. The Department of the

Environment and Local Government document „Better Local Government‟ (1996)

included commitments to introduce measurable indicators across the range of local

authority activities (DELG, 1996, p.33). The KPMG report built upon this, and

recommended a number of actual indicators that should be used by local authorities

to report on progress in the non-national roads area. These reflected the

methodological approaches adopted in the review, and focused on the quantification

of inputs and outputs, with a particular emphasis on comparative unit costs. The

Working Group set up by the Department to oversee implementation of the review

was charged with putting a system of performance indicators into practice. It

concluded that a good deal of information already received by the Department could

be collated in a way to enable it to be used as a management tool.

The review of roads programmes undertaken by Fitzpatrick Associates in 2002 as

part of the mid term review of the NDP 2000-2006, also considered performance

indicators for non-national roads. It drew upon the recommendations already made

40

in the 1997 KPMG study. Progress in the implementation of these recommendations

was noted, and the 2002 review expressed agreement with the approach that had

been adopted by the Department‟s Working Group (Fitzpatrick, p.c.15). It went on to

propose a series of specific indicators to be used by local authorities in reporting on

progress in implementing NDP commitments. They proposed indicators were listed

in the report as follows:

1. Kilometres improved under „Specific Grants Scheme‟

2. Kms improved under „Restoration Improvement Grant‟

• Regional Roads-Surface Restoration in Kms

• Regional Roads-Roads Reconstruction in Kms

• Local Roads-Surface Restoration in Kms

• Local Roads-Road Reconstruction in Kms.

3. Kms maintained under „Restoration Maintenance Grant‟

• Regional Roads-Surface dressing in Kms

• Local Roads-Surface dressing in Kms.

4. Number of „Low-Cost Safety‟ and „Regional Traffic Management Grant

Schemes‟.

(ibid., p. c14)

All of the recommended indicators above were put in place and are now routinely

used in local authority reporting mechanisms to the Department of Transport and the

Regional Authorities. Progress is measured against specific targets that have been

put in place under the different categories of grant schemes. Of particular note is

the practice employed on the specific programme targeted at regional development

(this was until recently co-financed by the EU). The percentage volume of traffic

related to industrial development, tourism, fisheries, forestry, rural development and

agriculture arising from the road investment is estimated. This is used as a form of

outcome indicator to show that the objectives of this scheme are reflected in

estimated traffic usage figures.

Since 2005, performance information is also gathered on the number of schemes

where Environmental Impact Assessments were prepared. The numbers of projects

subject to consultation arrangements under the statutory planning and development

regulations are also assessed. Such processes provide important safeguards to

assure environmental protection, and public accountability. However, they also have

an important bearing on the speed with which projects are delivered. Issues

identified in the course of these procedures can also give rise to additional

41

expenditure. Remedial measures may be necessary to ameliorate particular

negative impacts highlighted in the environmental assessment. If such additional

expenditure was unanticipated, it will have value-for-money implications.

Environmental and consultative processes are therefore relevant to the current VFM

study.

Of overall significance to the current study is the fact that there is a routine

mechanism in place within local authorities and the Department of Transport for

gathering performance data on regional and local roads, albeit mainly related to

inputs and outputs. There is an existing solid basis on which to recommend future

performance indicators.

2.3.5. Evidence of Progress and Improvement

Non-national roads expenditure represented a major element of the National

Development Plan 2000-2006, accounting for €2.43 billion (based on the original

budget). The Programme having been announced in 2000 (with the first allocations

in 2001), came subsequent to the NDP. It did however feature in the review of roads

investment by Fitzpatrick Associates which covered the period 2000-2001. It

examined progress, programme management and financial and cost management of

the entire non-national roads programme. It offers a window on the impact of the

various reforms initiated as a result of the 1997 Efficiency study. The 2002 review

did note that significant progress had been made. It concluded that:

“the Non-National Roads Programme is being operated on a

reasonable and efficient basis. We do not see scope or reason for

major changes in how it is operated” (p.c.15)

However, an important issue that overlaps between 1997 KPMG efficiency study and

the 2002 Fitzpatrick review of NDP roads expenditure concerns the issue of „Direct‟

versus „Contract‟ Labour. The NDP review noted that:

“The share of direct labour is at least 50% in all cases. There is no

evidence that direct labour costs are more expensive than

contractors. However its dominance is not in accordance with

international practice where the trend is away from use of direct

labour by public bodies.” (ibid., p.c29).

42

The current role of Direct Labour, and the extent to which it was used by local

authorities in the delivery of projects under the Programme will be examined in this

review.

The review by Fitzpatrick Associates fed into the overall Mid-term Evaluation of the

NDP by the ESRI. The conclusions here were generally positive, and the comments

on the rate-of-return for regional and local roads projects were noted earlier. Overall,

the review stated that, “progress on non-national roads part of the NDP had been

excellent” (Fitzgerald et al., 2003, p.98). There is a further sub-text to the resulting

recommendation to increase funding for this area under the NDP. The review

proposed a re-direction of priorities in line with National Spatial Strategy (ibid., p.7).

This is one of many references across key policy documents expressing the

desirability of linking infrastructural expenditure with the National Spatial Strategy.

These issues are considered in more detail in Chapter 5. It is sufficient to note at this

point that there has been a key shift in national policy which has implications for the

future of the Programme.

While the 1997 KPMG review and 2002 Mid-Term NDP Evaluation dealt directly with

non-national roads, there are other reports that have general relevance. In 1996, the

Department of the Environment and Local Government published a series of „Value

for Money Studies on Local Authorities‟. The impetus here was the widening of the

Comptroller and Auditor General‟s remit in 1993 to include economy and efficiency in

the use of resources. At that time, the Department established a „Value For Money

Unit‟ within the Local Government Audit Service, which undertook a series of studies.

Many of the recommendations from these reviews were incorporated into the later

guidelines prepared by the Department, particularly in relation to tendering, contracts

and unit costing / overhead charging. These studies offer further evidence of a

general commitment to the promotion of what could be called a „value for money‟

culture in relation to regional and local roads.

This Scene Setting chapter has looked at the factors driving the housing boom in

Ireland, which commenced in the late 1990‟s and continued until 2006/2007.

Unprecedented demand led to pressures on supply not witnessed in the history of

the state. The Programme was part of the policy response to help meet this demand.

It was also designed as a means to promote economic and regional development.

Investment in roads as a means to promote this objective is a strong feature of

Government policy and planning. This VFM review also takes place in the context of

43

changes in procedures and practices in the management of public expenditure on

regional and local roads. These have been influenced by other evaluations

undertaken in the past decade. Those studies offer important guidance in how the

current review addresses its own terms of reference. This is now the focus of the

next chapter, which will describe the methodologies that are to be used.

44

Chapter 3

Methodology

3.1. Introduction

The review methodology provides a structured means to address each of the

individual terms of reference. This chapter considers what approaches can best yield

answers to the individual questions that have been set out. All research instruments

have their limitations, and these are acknowledged and discussed.

The review draws upon sources of data that are appropriate to the specific issues

being addressed. In general terms, the three distinct sources can be categorised as

Primary, Secondary and Tertiary. The main secondary sources are Governmental

and other research reports. Statistical data were used as indicators to assess the

operation of the Programme. Examples already used in the scene-setting chapter

include the housing output figures produced by the Department of the Environment,

and social and economic data from Central Statistical Office reports. Given the focus

of the study as a Value for Money Review, financial and administrative data is of

considerable importance. Departmental records were therefore vital sources.

Tertiary sources mainly comprise existing policy analysis from governmental and

non-governmental sources. Examples of tertiary sources already cited would include

NESC reports, other evaluations and various academic studies relevant to housing

and roads policy.

Given the focus of the review on a specific programme, there are unique questions.

This necessitated the generation of original primary data, particularly to provide

accurate and up-to-date information on inputs and outputs. The data here is of a

quantitative nature and a self-completion survey questionnaire was the preferred

choice of research instrument. The previous chapter has pointed to difficulties when

assessing the contribution made by regional and local roads infrastructure in the

supply of housing, and in the promotion of economic development. This mainly

concerns the effectiveness of the Programme. In other words - can any changes that

occurred in housing supply be attributed to the Programme? A combined qualitative

and quantitative approach was chosen, using semi-structured interviews triangulated

against quantitative data indicators on housing output.

To examine in greater detail the relationship between roads infrastructure, housing

supply and economic development, a case study approach was adopted. Three

45

projects were selected – one with a housing focus, one with a focus to deliver lands

for commercial development, and one where both objectives were combined. In

each of the three areas, interviews were conducted with private companies involved

in the supply of housing and the development of business parks. The influences

affecting their commercial decisions are identified. The social and economic impacts

of the roads infrastructure were assessed with reference to the most recent census

data. Data within the case study areas is compared against broader regional and

national trends to identify particular impacts. Further local information supplements

these sources. Informing this analysis were the normative policy ideals set down in

national and regional spatial policies.

For the two case-studies with a focus on the delivery of industrial lands, a key

indicator is the numbers of jobs created in the area. The influence of transport

infrastructure on the decisions of businesses to locate in those areas is also

examined. For the case-study area that had a combined focus, the inter-relationship

between the population increases arising from new housing developments and

objectives to promote economic progress are studied. Of interest here is the

question of synergies that may be present. The essence of the case-study approach

adopted in the review is to build a general and convincing picture of the impacts of

roads investment by drawing upon multiple inter-linking sources.

The overarching methodological framework guiding the research is the Programme

Logic Model. The official guidelines issued by the Department of Finance advise that

this model be used when carrying out VFM reviews (2007, p. 28). While the model

acts as a framework, specific techniques and instruments are deployed to gather and

analyse information. The chapter begins by introducing the Programme Logic Model,

and the central questions of efficiency and effectiveness. The main methodological

instruments used in the review are then examined in greater detail.

3.2. The Programme Logic Model

At its most basic, the model tracks the results arising from the resources made

available. It also asks how those resources were used and what activities were

undertaken. It divides the Programme into a logical sequence. According to the

official guidelines, the advantage of the Programme logic model is that it provides: “a

systematic and visual way to present and share understanding of the cause-effect

relationships between inputs, activities, outputs and outcomes (results and impacts)”

(ibid, p.28). Consequently it is sometimes referred to as the „Input-Output‟ Model.

46

Comparisons are drawn between what the Programme set out to do and the eventual

results. The diagram and descriptions of the various elements in the model (below)

are adapted from the VFM Guidelines (ibid. pp 28-31).

Fig 3.1 The Programme Logic Model

Inputs – In the case of the current review, inputs refer to the exchequer funding

provided through the Programme, as well as resources provided by local

authorities. Financial resources were also translated into physical inputs for

roads construction, as well as other human inputs to deliver individual projects.

Activities – In the Programme they include the engagement of contractors to

undertake projects, the deployment of staff and resources, as well as the systems

put in place to manage and deliver the projects.

Outputs - this describes what is produced by the Programme. Here, outputs

primarily comprise roads infrastructure and related engineering works. In this

review, there is some overlap between outputs and outcomes, although there is

an important distinction between these two terms. The facilitation of new housing

and other development lands can be seen as both an output and an outcome.

Outcomes (Results) – The key short-term outcome objective of the Programme

was the delivery of housing and facilitation of development lands. In the

terminology of the VFM Guildeines, these can be seen as the „Intermediate

Outcomes‟.

Outcomes (Impact) – An important issue is the overall impact that the

Programme had on housing supply. Social and economic outcomes are also

likely to result within their respective areas.

47

There is a basic challenge inherent in the model when it comes to conducting an

evaluation, and developing indicators to assess performance. As Schacter notes, the

further you move down the logic model from inputs to outcomes, the further you

move away from results that are within the control of the progamme (2002, p.18).

This is often referred to as the „Attribution Problem‟. As was noted earlier, factors

influencing the housing market are many and complex. The Programme under

review was one of a substantial number of policy measures introduced over a period

spanning a number of years. One approach proposed by Boyle in assessing

performance, is to distinguish between “Programme” indicators and “Context‟

indicators (2005). Programme indicators relate to direct effects and can be fairly

clearly attributed to the Programme itself. Context indicators on the other hand,

apply more widely with attribution being less clear. Boyle outlines the rationale

behind this thinking:

“Because many factors can affect final outcomes, it is often impossible to

directly attribute to a programme or policy the changes that are reflected

in final outcomes. But these changes need to be tracked as they provide

important contextual information for making judgments about the ultimate

success or otherwise of a programme or policy” (2005, p.8).

In the case of this review, the „Programme‟ indicators refer to the roads constructed

and the housing / lands directly facilitated. „Context‟ indicators describe the wider

changes in the housing market and in relevant social and economic indicators. In the

scene-setting chapter, statistics on increased levels of housing output since 2000

were referenced. This is an example of a „Context‟ indicator‟. Further context

indicators include changes in commuting patterns arising from local development.

Clearly, context indicators on their own would be of little value is evaluating the

Programme. However, when combined with programme indicators and supported by

a set of reasonable assumptions through the Programme Logic Model, a credible

sequence of cause-and-effect can be developed. This is the essence of the

approach adopted in Chapter 7, which deals with the question of „Effectiveness‟.

The review methodology draws upon the work of Mayne, who uses what is called

„Contribution Analysis‟ to address the problem of attributing results and impacts to a

programme (1999). Inherent in this approach in the use of multiple lines of evidence,

and an awareness of external factors that may have contributed to outcomes. Mayne

describes Contribution Analysis as attempting to demonstrate “plausible

associations” between activities and outcomes. He quotes Hendricks (1996) in

48

stating that the test when attributing outcomes is whether “a reasonable person,

knowing what has occurred in the program and that the intended outcomes actually

occurred, agrees that the program contributed to these outcomes” (Mayne, 1999,

p.7). He advocates building as complete a picture as possible using programme

files, expert opinion, literature reviews of secondary data sources, structured surveys,

as well as other available sources (ibid. p.14). This is the overall approach used

within the review to gather evidence in order to draw conclusions and make

recommendations.

3.3. Efficiency and Effectiveness

These concepts were introduced earlier are of central importance to review. Drawing

upon the official VFM guidelines (D/Finance, 2007) and Mulreany (2002), „Efficiency‟

can be seen as either getting the maximum output from available inputs, or using a

minimum level of inputs to achieve a given level of outputs. Issues of „Economy‟ are

closely related to „Efficiency‟ but focus specifically on securing appropriate quality

inputs at the best price.

„Effectiveness‟ on the other hand compares planned outputs and effects against what

is achieved in reality. In addition, there may be unplanned outcomes that need to be

taken into account. These can be either positive or negative. As Mulreany notes

(2002, p.15), measurement of economy and efficiency are more advanced than

measurements of effectiveness within the public service. A case in point is the

seminal 1997 KPMG efficiency review, which focused more on the former than the

latter. This observation is also evident in the widespread use of output rather than

outcome-based performance indicators in relation to roads (including regional and

local roads). Assessing effectiveness represents a particular methodological

challenge, and as has already been outlined, multiple sources and research

instruments are used.

When the Programme was established, local authorities were required to submit

project proposals on a standardised application form. For the purpose of conducting

the VFM Review, the information contained on these forms and their general format,

provided a useful basis to develop evaluation questions. Comparisons can be drawn

between the stated commitments contained on the application form, and the actual

performance of the projects. In other words, did the projects deliver the houses units

and development lands that they said they would? This is assessed at the level of

the individual project and also in aggregate form for the Programme as a whole. In a

49

number of cases, the application form data was incomplete and did not include

measurable outputs. Alternative indicators were therefore identified. This issue is

addressed in more detail in the main body of the analysis.

The original application forms also provide a benchmark to examine the level and

trend of costs, and questions of efficiency. Comparisons are drawn between

budgeted costs and the actual outturn, taking into account the somewhat volatile

economic and inflationary conditions that have prevailed in the construction industry

over the past decade. Comparisons across the projects examine questions of

„relative efficiency‟. In other words, were particular projects more efficient than others,

and what were their defining elements and characteristics. This is a „non-parametric‟

approach. However, it must be borne in mind that many of the projects are individual

and unique in character, making comparisons difficult. Some projects required more

costly or complex additional civil engineering works. Land values were also a key

element of costs and vary significantly across the country depending on specific and

often unique location characteristics. This has the potential to skew comparisons.

Some elements of a „Theory-Based‟ approach to evaluation are applied. Drawing

upon the methods advocated by evaluation theorist Ray Pawson (2006), the

particular factors that helped and hindered the success of individual projects are

analysed. The purpose here is to isolate „What Works‟ when it comes to strategic

roads projects, and just as importantly to identify „What Doesn‟t Work‟.

To gather relevant data to assess programme inputs, activities and outputs, a

questionnaire to be completed by local authorities in respect of all funded projects

was prepared. This is a key research instrument in the review. It provides data on

quantifiable inputs and outputs to assess certain aspects of efficiency and

effectiveness. In addition to the main questionnaire, a second shorter questionnaire

was also prepared. Its purpose was to gather data on projects that were submitted

but not selected under the Programme. The next section looks at the reasoning

behind this particular approach. The main survey questionnaire for projects that

were selected will then be described in greater detail.

3.4. The Counterfactual –

What Would Have Happened Without the Programme?

When evaluating a programme, it is important to consider alternative scenarios.

While outputs can be assessed against stated objectives, a „counterfactual‟ scenario

50

should also be referenced - in other words, what would have happened anyway, in

the absence of the Programme. In an ideal situation an „experimental design‟ form of

evaluation could be used. This would involve the implementation a programme in a

particular area or with a particular group. An evaluation would then compare results

against an alternative area or group with similar characteristics (a „control‟ group). In

social and economic research, isolating a control group in order to make

comparisons can prove difficult, with some arguing that it is impossible. In a proper

scientifically-based evaluation, the control group would be selected at random.

Evidentially this is not possible here given the ex-post nature of the review. Also, the

targeted nature of the Programme in local authority areas with specific characteristics

would make comparisons with other areas difficult.

Nevertheless, there are some lessons from the experimental design approach that

can be utilised. When applications were invited from local authorities under the

Programme a total of 117 were submitted. 43 were approved, leaving a total of 74

projects that were not selected. The VFM review examines what happened to these

other projects, treating them as a form of „control group‟. It establishes if the other

projects went ahead, and if so, when. This represents a form of „quasi-experimental‟

approach that is quite common in evaluation studies (Cook and Campbell, 1979). It

fulfils some of the criteria of experimental-based research, but with limitations. As

applied in this review, it helps identify if „Deadweight‟ and „Displacement‟ were

present. „Deadweight‟ describes projects that would have happened anyway

irrespective of the Programme. If unsuccessful projects did go ahead, it would

suggest that those selected might also have gone ahead. „Displacement‟, on the

other hand, occurs when benefits from new programme result in a loss of output

elsewhere.

There are limits to the extent of inferences that can be drawn from this exercise.

Demonstrably, the successful projects were selected on the basis of specific

characteristics and were deemed to satisfy the Programme‟s criteria better than the

unsuccessful ones. The successful and unsuccessful projects have significant

characteristics that differ. The latter could therefore not be described as a „control‟

group in a strict sense. This affects the „internal validity‟ of conclusions that can be

drawn. In other words there could be a number of reasons for differences in

outcomes between the two groups, and these could have been caused by other

factors. However there are enough similarities between the two groups to make

some inferences.

51

3.5. The Survey Questionnaires – Design and Technical Issues

Both the main questionnaire in respect of funded projects, and the second

questionnaire for unsuccessful projects were circulated to local authorities in October

2007. The choice of instrument was based on the type of information being

gathered. Much of it was project-specific, and financial and technical in nature.

Good practice was followed in the design of the survey questionnaire and in drafting

the individual questions (Bryman, 2004, pp 131-143, Wimmer & Dominic, 1997, pp.

136-166).

The questionnaires were accompanied by a cover letter from the Chairperson of the

VFM review Steering Committee. The questionnaire and cover letter were sent to

the „Director of Service‟ in charge of roads in each of the relevant local authorities,

and copied to the County Manager. The Director was advised to nominate a person

to co-ordinate completion of the questionnaire in their local authority.

The draft questionnaires were proof-read by the Engineering Inspectorate in the

Regional and Local Roads Division of the Department of Transport. This process

checked that the survey questions were properly constructed, and that the questions

would achieve the desired effect of gathering data appropriate to the requirements of

the review8. The questionnaires were then checked with one of the local authorities

involved in the Programme (Waterford County Council). Arising from these

exercises, alterations were made to the overall structure of the questionnaires, and

the wording of individual questions.

The main questionnaire was divided into six sections. Section one consisted of

technical details (road length, width, type of works). These are important details in

assessing output and preparing unit costs. Section two focused on statutory and

procedural matters – the acquisition of land, consultation processes and

environmental impact assessments. All of these issues have an impact on the

delivery of projects. They would fall into the category of „Activities‟ under the

Programme Logic Model. Section three establishes when the project commenced

and was completed in order to make comparisons with the original projected

timescales for delivery. Scope was given for respondents to include qualitative

comments explaining reasons for delays where these arose.

8 In research parlance this is known as „measurement validity ‟ and „internal validity‟.

52

Section four sought cost and expenditure details. A breakdown of funding sources

was also sought. The role of development levies in funding public infrastructure was

an issue of specific interest here. The Department of Finance VFM Guidelines

advise that administration costs be considered in undertaking a review (2007, p.64).

The questionnaire also addresses this issue.

Section five sought information on traffic volumes using the road. The extent of

usage of a given piece of road is an output measure. This was done in order to

assess levels of traffic growth, and development in given areas. The availability of

traffic count and survey data also has implications for the feasibility of undertaking

future cost benefit analysis on regional and local roads projects.

The final part of the questionnaire (section six) measures the key output and

outcome indicators, namely; the area of housing land facilitated by the Programme,

the numbers of houses, and the area of industrial and commercial land. A distinction

is drawn between lands that are at different of stages of development. Lands that

have been fully zoned, serviced and developed clearly represent a more significant

output than those that have not been.

To gather data on the projects not selected from the application process, a second

questionnaire was circulated to local authorities. The data sought here was quite

limited and consisted of three basic questions – if the project went ahead, if so when,

and how it was funded. There were two reasons for having such a shortened

questionnaire. The first was that the projects in question were obviously not funded

under the Programme, and details available to the local authority at a remove of

almost eight years may be limited. The second reason was to avoid placing

unrealistic demands on people who would have to complete two different

questionnaires. Copies of both questionnaires, and the cover letter are attached at

Appendix III.

3.6. Assessing Causality - The Role of Roads Infrastructure in Delivering

Housing and Development Lands

A key objective of the Programme was to facilitate new housing and development

lands. The extent to which this was achieved is a vital indicator of effectiveness.

While the main survey questionnaire makes it possible to identify programme outputs

in terms of roads built and housing and lands facilitated, the issue of causality

requires further investigation. Infrastructure plays a key role in the supply of housing

53

and industrial development. However, because of factors already discussed, a multi-

method approach is favoured which combines both qualitative and quantitative

techniques. A key methodological instrument used to assess causality is the semi-

structured interview. Here, the review examines whether the infrastructure was really

a crucial factor in development and zoning decisions.

Qualitative interviews were arranged with senior officials in the Roads section in all

15 local authorities with projects. As well as discussing the issue of causality, there

were other reasons for adopting this approach.

Although there was some scope for qualitative comment in the questionnaire,

this was relatively limited. The interviews allow for more detailed probing of

issues arising from individual questionnaire responses.

The local authorities are considered key stake-holders in the delivery of

regional and local roads programmes. A detailed level of consultation was

therefore considered important.

Typically, the implementation of projects involved input from engineering and

administrative staff. A conscious effort was made to involve multiple participants in

the interviews from these different backgrounds. The interviews were therefore

conducted as a hybrid form of focus group. Where there were multiple participants,

interaction between them was encouraged. A list of questions was prepared and

used as a discussion guide. In order to facilitate comparisons across the 15

sessions, common questions and themes were explored. In three particular cases

(Kildare, Dublin City and Dun Laoghaire Rathdown), arrangements were made to

have a member of staff from the Planning Department present9. These particular

groups had four participants each and included at least one engineer, a local

authority planner and an official with an administration and policy background. The

number of participants is at the lower end of the scale in comparison with other

studies that have used focus groups (Bryman, 2004, p.350). However, given the

nature of the topics being discussed, and the requirement to have specific expertise,

the numbers were considered not only sufficient, but optimal in the circumstances.

A further key element in assessing causality and programme effectiveness involved

detailed case-study examinations in a limited number of areas. The Programme

currently consists of 44 geographically dispersed projects spread across 15 local

9 It was originally intended that these would overlap with the three case study areas, but for practical reasons, this was not possible.

54

authorities. It would not be feasible to examine each in detail. Case studies are a

standard methodological approach used in the appraisal of infrastructural projects in

general, and roads in particular. They were used with some effect in the review of

roads expenditure under the NDP 2000-2006 (Fitzpatrick, 2002). The approach is

also in keeping with the Department of Transport guidelines which advise that post-

project appraisal be carried out on a representative sample of 5% of completed

projects (DoT, 2007, p.3). There is a similar recommendation in the Department of

Finance Capital Appraisal Guidelines (2005, p.29).

Three case study areas were selected to reflect geographic location and project

focus. One was selected from County Dublin (i.e. Dublin City, Fingal, Dun Laoghaire

Rathdown, South Dublin), one from Greater Dublin Area hinterland counties of

Kildare, Wicklow and Meath, and one from outside of the Greater Dublin Area (i.e.

Cork, Limerick, Waterford and Galway). The areas selected were neither typical nor

atypical. In other words specific „good‟ or „bad‟ projects were not particularly

favoured. While the case study areas are broadly representative, limitations do arise

in relation to „external validity‟. They have their own unique features and it does not

automatically follow that findings in one area would be replicated elsewhere.

However this shortcoming can be minimised by cross-referencing data sources from

other areas to check any observations.

Within the case study areas a decision was taken to interview companies involved in

building and development. The first Bacon report points to the usefulness of input

from those with direct experience in the housing market. Research by DiPasquale

(1997, p.3) suggests that information from builders and developers can offer

important insights into housing supply decisions. The case study area of Tramore

(Co. Waterford) looked in particular at housing development. Interviews were

conducted with the two private companies responsible for building most of the

housing outputs reported by the local authority along the new sections of the ring

road. The Killeen Road in Ballyfermot, Dublin was intended to facilitate the Park West

Business Park. This has since developed into a mixed commercial and residential

district. An interview was conducted with its owners. In Naas in County Kildare, the

developers of a new business park on the ring road funded by the Programme were

interviewed. The approach is also consistent with methods recommended in Scottish

Transport Appraisal Guidance documentation when assessing the impacts of

transport policy decisions on population change and the local economy. It advocates

interviewing those involved in the development and sale of housing (STAG, Ch.

55

8.12.9). There is some overlap here into the area of social and economic effects and

the discussions with local authority personnel were also used to identify and examine

these issues. To explore further the relationship between roads and the facilitation of

industrial development, a meeting was arranged with a senior manager from IDA

Ireland.

The number of interviews in the case study areas was considered sufficient for the

purposes of the review. The first Bacon report included a qualitative survey based on

views from eight professionals with expertise in different aspects of the housing

market. Given the qualitative nature of this part of the VFM review, there would be

no real advantage to increasing the number of interviewees in terms of achieving

external validity or improving a confidence interval (which doesn‟t apply here). The

number and range of interviewees was considered sufficient to provide information in

assessing the impact of the Programme. Details of all interviews and focus group

meetings, with the names of participants and dates on which they were conducted, is

included as Appendix IV.

In undertaking the meetings with the local authorities, a discussion guide with

questions and topics was prepared, tested and refined. The sessions were tape

recorded and transcribed. Common themes were identified through an iterative

process of comparison between transcripts. This is similar to a „coding‟ process

undertaken in studies involving large numbers of qualitative interviews. „Coding‟

involves the use of quantitative techniques to analyse qualitative data. While

recurring themes were sought, individual unique responses were also both

interesting and instructive. Particularly illustrative quotes are used to highlight issues

and supplement other data in the review.

While formal semi-structured interviews were arranged with the four development

companies in the three case study areas, these were not tape-recorded.

Contemporaneous notes were taken instead, and a record of the interviews written

up afterwards.

A second type of qualitative interview technique was also used in the study. When

the review commenced, „Informal Unstructured‟ interviews were used to assist in

establishing the original objectives of the Programme, to gather background

information and identify potential data sources. These typically took the form of

56

extended conversations lasting between half-an-hour and three hours with staff

involved in setting up the Programme.

3.7. Assessing Social and Economic Outcomes

The scene-setting chapter referred to the challenges posed in assessing the social

and economic benefits of non-national roads infrastructure. The mid-term review of

the National Development Plan 2000-2006, noted that while regional and local roads

projects provide a low but fairly consistent rate of return, this was difficult to measure.

The report recommended that in such circumstances, benefits should be considered

in a qualitative manner. The specific evaluation of roads investment undertaken as

part of the NDP mid-term evaluation also acknowledged that that it was not possible

to have any routine estimate of user benefits. However its suggestion of using a form

of cost benefit analysis was considered, and not deemed appropriate in the case of

the Programme.

There were two distinct objectives associated with the Programme – to assist

housing supply and to facilitate the development of industrial and commercial lands.

In the two case-study areas where the facilitation of development lands was an

objective, data on the nature and types of business setting up there was gathered.

This was informed by the Scottish approach to assessing the „Economic Activity and

Location Impacts‟ associated with transport infrastructure investment (STAG, Ch. 8).

However, it should be borne in mind that these guidance papers acknowledge that

such assessment tools are not as well developed as more conventional ones like

cost benefit analysis. In the case study areas the relationship between business

location choices and infrastructural provision is specifically examined.

Direct social and economic impacts are likely to arise as a result of demographic

change. The additional housing provided on foot of individual projects will have

resulted in altered settlement patterns and an increased population in the areas

affected. Changes in levels and types of employment in the case study areas are

also important. A specific possibility is that some occupants of the new housing

facilitated under the Programme may not necessarily work in the area. This has

implications for the wider issue of sustainable development and transport use.

Key data sources in examining these impacts are Census reports from 1996, 2002

and particularly 2006. Changes in the socio-economic profile of areas, drawn from

these reports give important indicators of the nature of the local workforce. This has

57

important implications for the potential of an area to attract industrial development.

The qualitative interviews also provide information for this part of the review. Census

data, when combined with other sources, enables a wider picture to be constructed.

This forms the basis for assessing short and longer-term outcomes arising from the

Programme.

Issues of sustainable development are assessed by comparing planning decisions

and settlement patterns against the normative ideals set down in local, regional and

national spatial planning guidelines. Most of the new framework for spatial planning

now in operation was put in place after the Programme commenced in 2000. This is

the main focus of chapter 5 of the review.

3.8 Quality Assessment

In undertaking a VFM review, there is a requirement that the draft report be assessed

by an independent consultant. Following a tendering process, a Quality Assessor

was selected from the panel of independent evaluation experts established by the

Department of Finance Central Steering Committee, which oversee the Value for

Money and Policy Review Initiative. Following receipt of the assessors report in June

2008, further amendments were made to review.

3.9. Concluding Comments

Earlier, the Scene-Setting chapter examined and discussed the different

methodological approaches used in the study of the housing market and the role of

infrastructure in facilitating industrial development. Previous studies to assess the

efficiency and effectiveness of non-national roads were also considered. Learning

from these various sources, the methodology chapter has sought to identify a series

of techniques best suited to the research questions being posed. A combination of

quantitative and qualitative methods are applied to generate original data from

different sources. Existing secondary and tertiary sources are also used. These

combine into a coherent body of evidence to assess if value for money was

achieved, and if the Programme can be considered effective. The review will now go

on to address each of the individual terms of reference.

58

Chapter 4

“Identify the Programme‟s Objectives”

4.0. Introduction

This chapter is split into two sections. The first identifies the background to the

Programme and its specific objectives. After identifying its main objective, an historic

narrative describes the origins of the Programme. This provides a vital context in

later chapters when assessing why public funding was expended and, if the stated

objectives have been achieved. The second section of Chapter 4 looks at the

„Rationale‟ behind the Programme. It draws upon the concept of „Market Failure‟ in

seeking to establish the economic justification for a public policy intervention, and if it

was warranted in this case. The analysis also provides an important foundation in

addressing if the original objectives were valid, and whether they continue to be.

4.1. The Origins and Objectives of the Programme

4.1.1. The Primary Objective

The core policy objective of the Programme is contained in Circular letter RW 13/00

of 3 July 2000, issued by the Department of the Environment and Local Government.

This circular invited 15 selected local authorities to submit proposals for funding

under the Programme:

“The Government recognises that rapid economic development is

generating a need for targeted investment in the non-national roads

area. The key objective of this scheme is to provide grant assistance

to relevant local authorities, particularly in the Greater Dublin Area, for

certain strategic non-national roads to support housing,

industrial/commercial and other developments.”

(DELG, 2000b)

This can be seen as the the primary purpose for which the Programme was

established. This objective was translated into quantified deliverables in the form of

lands and housing units to be facilitated by the projects. While the Programme had

its own distinct focus, it was put in place as part of a wider package of measures to

boost housing supply, stabilise house prices and address housing needs. These can

be seen as the more general goals to which the Programme was to contribute.

While the Programme was put in place in 2000, its genesis can be traced through

each of the three Bacon reports published in 1998, 1999 and 2000.

59

4.1.2. First Bacon Report

The first Bacon report entitled „An Economic Assessment of Recent House Price

Developments‟ was commissioned by the Department of the Environment in

November 1997 on foot of a Government Decision, and published in April 1998.

Some of its wider analysis of supply and demand conditions has already been

considered in the Scene Setting chapter. Concerning specific infrastructural issues,

the report made the following observations and recommendations:

“A number of key constraints on the realisation of housing supply in

Dublin, in terms of water/sewerage and road infrastructure, have been

identified. It is considered that, if the potential of housing land is to be

realised effectively there will have to be a considerable investment

undertaken in the improvement and development of infrastructure”

(1998, p. xiv)

“Where action needs to be taken and cannot be funded within the

current non-national roads programme additional resources should be

made available to local authorities on a similar basis to the existing

Serviced Land Initiative10

. ” (ibid, p. xv).

The direct Government policy response was a commitment to provide an additional

IR£5m to help local authorities to target areas where roads infrastructure was a key

constraint to housing development (DELG, 1998, p.1). This was the forerunner to the

Programme under review, and its objectives were carried into the current scheme.

The first Bacon report pointed to examples of infrastructural bottlenecks in the three

Dublin County Council areas. After analysing the situation, the Department

concluded that infrastructural problems also existed in the wider eastern region

around the greater Dublin area, and around other provincial cities. On this basis, the

scheme was targeted at the 15 local authorities areas located in and around the five

major cities. A key point here is that the 15 local authorities selected for the 1998

scheme were also those selected for the subsequent programme that is being

reviewed.

A point of significance from the 1998 programme was that direct Exchequer funding

was used through a separately voted Exchequer budget subhead. At that time, road

improvements were generally financed through three particular sources:

10 The exchequer would fund 40% of the cost, with the balance provided by local authorities.

60

Earmarked local government roads funding provided by the exchequer;

EU grants;

Local authorities‟ own resources.

There were particular contextual factors that explain why new and separate

exchequer funding was committed. There was considerable public criticism

throughout the early 1990s about the poor state of non-national roads. „Potholes‟

had a particularly high profile in the public consciousness. A 10-year „Restoration

Programme‟ was launched in 1995. This was a key Departmental and Government

policy priority. As part of this programme, a study undertaken by Ove Arup &

Partners Ireland identified that some 47,000 kilometres of non-national road was in

need of restoration at an estimated cost of IR£950m (KPMG et al., 1997, p.5). In

effect there were two significant national policy priorities affecting non-national roads

at the same time. The issue of diverting existing resources towards the proposed

new scheme was considered. However, it was felt that a stream of new funding

would be required, and it was on this basis that the Minister decided to establish the

new programme. The same logic informed the decision to fund the subsequent

programme in 2000 that is being reviewed here.

4.1.3. The Second Bacon Report

A second Bacon report was commissioned in November 1998 and published in

March 1999. It recommended that the Department of the Environment and local

authorities identify the road and transport constraints preventing the development of

existing zoned residential lands (Bacon et. al., p. 63) The Government‟s direct policy

response was launched by the Taoiseach and Minister for the Environment in March

1999. It included the following policy measure:

“Arrangements to identify infrastructural constraints in major growth

centres will be put in place in the near future. The Government is

committed to provide additional resources to remove any significant

constraints to housing development with minimum delay.” (DELG,

1999, p.4)

A survey exercise was undertaken by the Department in 2000 to identify roads that

were potentially acting as a constraint to housing and other development. The

information gathered formed the basis of the decision to set the current programme.

This commitment was then included in the Government‟s policy response to the third

Bacon Report.

61

4.1.4. The Third Bacon Report

The third and final Bacon report was published in June 2000. It reiterated that roads

infrastructure was needed to provide for a major expansion for housing supply

(Bacon et al., 2000, p.83). The Government‟s policy response, entitled „Action on

Housing‟ committed itself to setting up the Programme now under review. It stated:

“The Government recognise the need for targeted investment in non-

national road schemes crucial to housing development, and are

urgently assessing a number of schemes, which will support

development of a significant number of additional housing sites and

other related developments. The overall additional roads investment

involved is some £200 million over the NDP period of which £150

million will be provided by the Exchequer in particular for housing

related roads investment.” (DELG, 2000a, p. 3)11

.

4.1.5. Circular RW 13/00 „Non-National Road Grants to Support Housing and

Other Related Developments‟

In July 2000, the Department of the Environment issued Circular RW 13/00 inviting

formal applications from the 15 eligible local authorities. This set out the purpose of

the scheme, based on the Government policy statement. A copy of the circular and

application form is included at Appendix V. While the main objective of the

Programme was to support the provision of housing and industrial lands, the timely

commencement of schemes and their delivery of housing and development lands

were also considered important. The central premise of the scheme was:

“that a number of roads projects having the ability to support significant

housing and other development could be mobilised quickly if necessary

funding were provided” (DELG, 2000b).

The local authorities were required to submit project proposals on a standardised

application form. A formal weighting or scoring system did not apply in relation to the

specific criteria for the scheme. However, discussions with officials involved in

reviewing the applications suggest that an important consideration was the speed at

which work could commence. A further important factor was the type and amount of

development served by each scheme.

11 The eventual expenditure committed to the Programme was greater than the figure originally envisaged (above). These issues are addressed in Chapter 8.

62

Following the assessment of the project proposals submitted, 43 were selected and

approved by the Minister. Based on the estimates contained in the grant

applications, the 43 projects were to facilitate the provision of 43,659 housing units

and benefit 932 hectares of industrial land (DELG, 2000c). These figures in effect

translated the stated objectives into measurable quantities. An important

consideration for this review is the extent to which these are being delivered, and the

role played by the roads in their delivery.

4.2. The Economic Rationale Behind the Programme

4.2.1. „Market Failure‟ and Non-National Roads

The Department of Finance guidelines for carrying out Value for Money Reviews

advise that the rationale be established to explain why a public policy intervention is

necessary (2007, p.32). This involves consideration of the economic concept of

„Market Failure‟. Ordinarily, the market is assumed to be in the best position to

respond to demand in the most efficient manner. However, situations and

circumstances can arise where the market does not produce the optimal level of a

good or service from a societal perspective. „Market Failure‟ describes activities,

goods or services that would not be sufficiently provided in the absence of

government intervention. The ESRI has identified four rationales for public sector

intervention, based on types of Market Failure (ibid, p.40). It notes that this is not an

exhaustive list:

„Public Goods‟ – These are goods or services for which it is not possible or

convenient to charge all beneficiaries. Notably, the typical example cited in the

VFM Guidelines is that of public roads.

„Externalities‟ – These arise when the action of an individual or firm affects

others without appropriate compensation being paid. A common example is

that of pollution.

„Redistribution‟ – This type of spending is intended to deliver what society

considers as being a “fair” distribution of wealth and income among its

members. Typical examples cited in the Guidelines are welfare spending and

regional development programmes.

63

„Merit Goods‟ – Individuals or firms underestimate the personal or private

benefits derived from consuming a good or service. One example mentioned is

compulsory education, which has personal and wider societal benefits.

The „Indecon Review of Local Government Funding‟ published by the Department of

the Environment, also identified the same four headings as providing the justification

for local government expenditure and policy intervention (Indecon, 2005, p.136). In

examining non-national roads in general, and the specific programme that is subject

to this review, it is possible to identify elements of the first three „market failure‟

rationales. However some are more prevalent than others, most notably that of

„Public Goods‟.

Roads also give rise to pollution and congestion, which can be considered as

„Externalities‟. These factors are increasingly incorporated into transport policy

decisions. Roads and other infrastructure are also ascribed a crucial role in

promoting national economic development objectives as well as achieving

redistributive regional goals. In other words, they stimulate economic development,

but also attempt to distribute that growth to achieve balanced spatial development

objectives. In the case of the Programme, it could accurately be described as

providing a „Public Good‟, with the aim of achieving wider economic and social

objectives. This is consistent with stated Government policy. The National

Development Plan 2007-2013 sums up the core rationale underpinning public

spending on non-national roads when it states that:

“Regional and local roads serve an important economic role in the

Irish context and also have valuable social and community

functions. The network of non-national roads provides mobility

within and between local economies and are vital links to the

strategic national road network, ports and airports which are our

links with the wider international economy. Indeed, 94% of the

country‟s roads are non-national, carrying around 60% of all road

traffic. These roads are often the sole means of access for the local

economy”. (NDP, 2007, p.85)

4.2.2. Non-National Roads as „Public Goods‟

„Public Goods‟ are not just any goods provided for the public or by government

agencies. They have a specific meaning and economic definition that sets them

apart. „Public‟ goods have two particular characteristics:

64

They are „non-excludable‟. In other words, if provided to one person, it is

either very expensive or technically impossible to exclude others.

They are „non-rival‟. Consumption by one person does not affect the quantity

available for consumption by others.

Regional and local roads are a fairly clear example of a public good. As a result, the

2005 Indecon review noted that local authorities in most developed countries

(including Ireland) play a critical role in their provision (2005, p.136). If these roads

were not provided through state intervention, they would not be supplied at optimal

levels (or even at all) by the market.

Regional and local roads have particular characteristics that mark them out as „non-

excludable‟. At the moment, these roads are not subject to any direct charge or toll.

Notwithstanding this, the ESRI in its Ex-ante evaluation of the latest National

Development Plan has advocated a national pay-as-you-go system of charging that

would cover all roads, including non-national roads (2006, p.150). In economic

terms, such systems are referred to as „Road Pricing‟ where a charge is levied on

drivers based on their level of road usage. Currently there are no plans to introduce

such direct user charges, so in their absence paying for „public goods‟ like regional

and local roads falls on the local authorities and central government.

In theory local roads are also „non-rival‟. One person‟s use of a road has a limited

immediate effect on its use by others. However, the term „non rival‟ only applies up

to the point where congestion occurs. The issue of „induced traffic‟ was examined in

the Scene Setting chapter. When a road reaches capacity, further small increases in

traffic can result in significant and disproportionate disbenefits (Litman 2007, ESRI

2006). This is particularly felt through increased journey times.

Increased road use also places road surfaces under greater pressure, and can

cause significant damage if not addressed. Clear examples are provided by the

„Pavement Condition Studies‟ carried out on the non-national roads network in 1997

and 2005. The 2005 study in particular found that increasing traffic volumes were

having a severely damaging impact. It pinpointed the increased loading of vehicles

as being a significant factor (RPS et. al. 2005). Congestion and other negative

impacts can be considered as „Externalities‟. This is another form of market failure,

and is discussed further in the next section.

65

Regional and local roads are therefore not a „pure‟ public good. They are not fully

„non-excludable‟ or „non-rival‟. This trait is of significance. Because there aren‟t

direct price mechanisms in the supply of public goods, an increase in traffic volumes

or congestion can be seen as a signal of demand, requiring a response through

increased investment in roads. This has been the traditional and instinctive

response, which in policy terms is described as a „Predict and Provide‟ approach.

However the policy environment has shifted considerably in recent years with a

realisation that there is more than one way to address demand. The national

strategy set out in „Transport 21‟ (2005), takes a more integrated approach to

investment across different public and private transport modes. Balancing the

demand for roads against the minimisation of negative side effects, whether in the

form of congestion or pollution is in essence what the principle of „Sustainability‟ is all

about. This concept has come very much to the fore in public policy. It is now a

central concern that informs the „National Spatial Strategy‟ (2002), „Transport 21‟

(2005), the national partnership agreement „Towards 2016‟ (2006), the „National

Development Plan‟ (2007), and the recent draft plan on „Sustainable Travel and

Transport‟ (2008), amongst other significant national policy documents.

Within the recently revised „Statements of Strategy‟ for both government

Departments centrally concerned with the goals of the Programme, sustainability has

central prominence. It is therefore an important question in examining the present

policy context, and wider priorities in the provision of transport infrastructure. This

will be considered in greater detail in Chapter 5.

4.2.3. Housing Supply and Market Failure

The housing market, particularly on the supply side, can be subject to market

failures. The „Barker Report‟ on Housing in the UK examined the implications of

these failures. In a general sense it found that local authorities when assessing

housing development in their areas may not take full account of the full social costs

and benefits of their actions (Barker, 2004 p.53). The costs arising from increased

pressure on local services or disruption during construction tend to be borne locally.

The benefits tend to be spread more widely and felt at a macroeconomic level.

Greater benefits also accrue to incoming homeowners rather than the existing

community. Fears of unsustainable pressure on existing infrastructure and services

can have a powerful disincentive effect for local authorities and communities to

facilitate and encourage development. However in economic terms, there is a net

loss to society when development is hindered. This provides a „market failure‟ basis

66

for offering incentives to local authorities to provide infrastructure to facilitate

development.

Externalities can arise when the social costs and benefits of a housing project

diverge from private costs and benefits. A developer might be reluctant to build

housing where their private benefit does not justify the risk of investment, even

though there may be wider social benefits (ibid, p57). This particularly affects

brownfield sites and less attractive locations.

Barker also identifies „Co-ordination Failures‟ as being significant. These happen

where “individual private and public sector organisations may not be able to co-

ordinate their actions effectively, giving rise to sub-optimal outcomes” (ibid.). If

effective co-ordination can‟t be achieved in providing necessary complementary

infrastructure to facilitate development, then the potential benefits to society are lost.

In summary, Barker concluded in her recommendations that “numerous market

failures affecting land assembly, land servicing and infrastructure provision make a

compelling case for government intervention” (2004, p. 53). The same could also be

said in an Irish context. Each of the specific failures mentioned in the Barker report

were also identified in the Bacon reports, and more recently in the NESC analysis of

housing in Ireland. The first Bacon report identified problems with shortages of

serviced land, lengthy planning processes, and infrastructural deficits, particularly in

the Dublin area (1998, p. iv). Interestingly though, an economic study of housing

land supply could find no evidence of „land banking‟ in Ireland that would result in its

slow release for development use (Goodbody, 2003, p.2). This was in marked

contrast to the situation in the UK. However, the NESC report particularly identified a

problem with co-ordination between housing supply, and the provision of water and

transport infrastructure (2004, p.79). It also stated that local authorities were

constrained in granting planning permission for suitable housing densities because of

a lack of such infrastructure. This highlights the importance of co-ordination between

local authorities, developers and the relevant government departments and agencies.

4.3. Conclusions

A major reason for setting up the Programme was that local authorities were not in a

position to bear the full costs of the required roads infrastructure. This view was

confirmed in interviews with officials who were involved in decision-making at that

time. There is a proven link between infrastructural provision and the ability of the

67

housing market to function effectively. At a theoretical level, there is a case for

government intervention to provide infrastructure to support housing development.

At a practical level, the evidence in policy documents and from interviews with

officials point to „market failure‟ conditions that justified public expenditure. There

was an undersupply of suitably serviced development lands in areas of significant

housing demand. If this situation wasn‟t rectified with government intervention, there

would be a sub-optimal supply from an economic perspective. In a situation where

demand was outstripping supply, the consequences were being felt through unmet

demand and increased prices. It can be concluded that the social benefits (at a

macroeconomic level) from increasing housing supply were therefore being

hampered. At a programme level, public investment was therefore justified on

grounds of „market failure‟. This is notwithstanding the more general and mainstream

rationale for providing funding for local roads based on the widely accepted position

that they are „Public Goods‟ that also contribute to regional development. It is

increasingly accepted that roads and housing development should be planned in a

way that minimises externalities and that complies with principles of sustainability.

This is where the next chapter commences.

68

Chapter 5

“Examine the current validity of the objectives and

their compatibility with overall Government strategy.”

5.0. Introduction and Overview

The Programme can be seen as an infrastructural policy response designed to link

housing and planning objectives in order to achieve mutually compatible ends. It was

a one-off policy measure, albeit in the context of a larger drive to bring stability to the

housing market, and to facilitate economic development. Since the Programme was

announced in 2000 it is evident that the policy context has shifted considerably. The

housing market has moved on, and supply has expanded hugely. Even since work

on this particular review commenced in 2007, the level of housing supply has

peaked, and subsequently contracted. Prices have stabilised and fallen. There is

currently a wide variety of opinion about housing output forecasts in the short term.

Whatever about the fluidity of the current position, there is an acceptance that a

significant additional supply of housing will be needed in the long term. This is based

on demographic projections and other contributory factors. Current policy is built

around an estimation of need up to the year 2021. There is also an understanding

that future transport and housing needs should be met in a way that affords people a

good quality of life. Concerns about issues of „sustainability‟, the location of housing,

and the social consequences of development have become important considerations.

These have amplified as housing supply has dramatically expanded.

This chapter looks at some of the criticisms raised over the past decade in relation to

patterns of housing development and transport use. It then examines the

frameworks and policy mechanisms that have been established to link planning,

infrastructure and development decisions. The original objectives of the Programme

were centrally concerned with the housing market. Policy advances in this area are

therefore relevant to the current validity of the original objectives. Housing

development creates its own need for related infrastructure. A significant policy

initiative in recent years has been the formal establishment of a system of

development levies at local government level. Development levies and their role in

funding roads are a recurring issue throughout the review.

69

This chapter concludes by analysing the practical implications arising from significant

changes in the policy environment. It looks at the current strategic objectives of the

two Government Departments centrally concerned with the Programme.

Observations are made that will particularly inform Chapter 9, which considers the

degree to which the Programme‟s objectives warrant the continued allocation of

public funding.

5.1. Concerns about the Sustainability of Housing Development

While housing output has grown dramatically over the past decade, some questions

have been raised about the environmental sustainability of development patterns,

particularly those in and around Dublin. These concerns have had a major influence,

leading to key policy changes. Williams et. al. (2007) in their most recent

assessment of the growth of the Greater Dublin Area note that recent housing

demand has been largely absorbed by the outward growth of the commuter belt

which now stretches over 100 kilometres from Dublin. This, they say, “has created a

major sprawl-type settlement trend with new mono-functional housing areas and

transportation patterns with a near-total dependency on the private motorcar” (ibid.,

p.4). In one of his earlier papers, Williams had identified such patterns of

development as „Leapfrogging‟, where new settlements spring up on the outer

suburbs, and continue this process outwards. This phenomenon is also described

as a „doughnut‟ pattern of development. As the term suggests, development tends to

occur on the periphery, creating a vacuum or a hole in the centre. Concerns about

so-called urban sprawl have also been raised by the European Environment Agency

(EEA) in relation to Dublin, Cork City and other urban areas (2006). It has even

identified urban-sprawl growth in what were more traditional rural parts of Ireland.

Worry about patterns of urban development and indeed urban sprawl are nothing

new. Public policy was grappling with these issues throughout the 1970s and into

the 1980s (Barrett, 1982, p.181). Arguably, the housing boom of the last ten years

may have exacerbated a situation that was already in existence, particularly in

relation to spatial settlement patterns. The long held preference of Irish people

towards owner-occupation of their home could also be seen as a key contributory

factor here.

The NESC in its analysis concluded that demographic and economic factors since

the mid 1990s had fuelled an enormous increase in the demand for housing. In such

circumstances not only were significant price increases inevitable but so too “was a

70

significant spread of housing development beyond existing urban areas” (NESC,

2004, p. 76). It came to the view that while better planning could have yielded a

more balanced outcome, there would still have been development on green-field

sites (ibid. p.77). Evidently there are a series of crucial interrelationships between

housing, transport and planning policies, with each influencing and pressurising the

other. This is increasingly reflected in Government policy, with the strategic

emphasis now on sustainable and co-ordinated development. This has been the

central shift in policy focus at local, regional and national level in the past ten years

and has implications for the current programme.

5.2. The New Hierarchy of Planning Policy and Legislation

5.2.1. The Co-ordination of Housing, Transport and Planning Policy

The key policy document to achieve greater integration of major planning-related

objectives is the National Spatial Strategy (NSS). It was published in 2002 and

operates within a twenty year framework. The NSS sets a national context for spatial

planning which then informs „Regional Planning Guidelines‟ and „County and City

Development Plans‟ (DEHLG, 2002, p.12). These Guidelines and Plans operate on

a statutory basis and direct planning decisions. The NSS envisages the emergence

of spatial clusters “particularly focused around the city regions and other strategic

locations”, with easy access to transport and key infrastructure, (ibid., p.97). The

larger of these strategic locations were titled „Gateways‟, with the smaller clusters

being described as „Hubs‟. The overriding emphasis is on sustainability, which it

defines as matching where people live with where they work in order to be able to:

“sustain a better quality of life for people, a strong competitive economic position and

an environment of the highest quality” (ibid. p.10). The NSS is directly relevant to the

roads programme being reviewed here. The two aims of the Programme were to

facilitate lands for economic use, and housing development. Both of these issues

are addressed. The NSS advocates the continued development of strategic reserves

of lands for enterprise development, stating that this should be linked to the spatial

structure of hubs and gateways (ibid. p.98). In relation to housing, the Strategy

emphasises:

“the importance, particularly in urban areas, of combining the location of

housing with good transport facilities: and the need to ensure that housing

requirements are matched by the supply of zoned and serviced land”

(ibid. p.94)

71

The NSS is only one piece of the jigsaw however. To get a fuller picture it needs to

be placed in its proper context as one of a number of recent inter-linked changes.

The period since the turn of the new millennium has seen the prolific publication of

policies and guidelines across the fields of housing, transport and spatial planning.

There is now considerable overlap between these areas, which in turn has brought

greater clarity to overall national goals. These policy goals have also been backed

up by major public investment in infrastructure, particularly through the National

Development Plan 2000-2006 and its successor covering the period 2007 to 2013.

The impact of these new and co-ordinated policy initiatives in spatial planning has

been assessed positively. The NESC described what it calls “an evolution of

thinking” since the late 1990s with the adoption of what it refers to as “a new

hierarchy of strategies and plans for spatial development and new instruments to

support the provision of infrastructure” (2004, p.41). The key piece of legislation that

underpins all of this is the „Planning and Development Act 2000‟. It provides the legal

basis under which these reformed planning arrangements operate, particularly at

local and regional level.

5.2.2. Translating National Policy into Regional and Local Planning Guidelines

The „Planning and Development Act 2000‟ required all Regional Authorities12

to

make Regional Planning Guidelines to provide a long-term strategic planning

framework for the sustainable development of their region. These are intended to act

as a bridge between national and regional planning policy to guide local authority

decision-making. In the Dublin area, the new guidelines replaced earlier ones, which

had been in place since 1999. At that time these were the first such guidelines in

Ireland, which should give an idea of how new such approaches are in Irish planning

policy. The new guidelines were agreed by each of the regions in 2004, and are in

now effect for a twelve-year period. By way of an example, the Greater Dublin

Regional Planning Guidelines envisage the concentration of development into

identified and sustainable towns separated from each other. The stated long-term

objective is:

“to create self sufficient towns, with only limited commuting to the

Metropolitan Area” (D&MRA, 2004, p.71)

12 The eight Regional Authorities are Dublin, Mid-East, Midlands, South-East, South-West, Mid-West, West and Border.

72

Later in the review, progress towards the achievement of this objective in the Naas

case study area will be examined. To achieve an appropriate balance between

development in towns, villages and the rural countryside, different scales of

settlement-type are set out. In the case of Naas, it is defined as a „Primary Dynamic

Cluster‟ or location for major development. In the South East Regional Planning

Guidelines, Tramore (which is also a case study area), it is identified as a large town,

which is to be developed and strengthened. Regional and local roads are specifically

identified as having a role in facilitating development. All local authorities are legally

obliged to reflect the regional planning guidelines in their County and City

Development plans. This is the next step in the hierarchy.

5.2.3. County and City Development Plans

The County / City Development Plan for each of the 34 main local authority areas is

the primary strategic statement on land-use planning at city, town and county level.

In practice, it forms the basis upon which planning applications are assessed by a

local authority. At a strategic level it is the blueprint for the economic and social

development for each area. In June 2007, the Minister for the Environment issued

new guidelines in the preparation of Development Plans. These represent a further

progression towards the co-ordination of policy objectives between housing supply,

the location of development and the provision of transport infrastructure. They

stipulate that Development Plans should reflect key national policies dealing with

sustainability and infrastructure provision (DEHLG, 2007b, p.3).

Each local authority must now produce “a statement of supporting policies to ensure

that transport and settlement patterns will mutually support each other” (ibid. p.24).

Local authorities are advised to consult with industrial and business development

agencies to achieve the co-ordination of industrial land provision with other essential

infrastructure such as roads and public transport, water services, and energy

communications (ibid, p.26).

The guidelines advocate a „Sequential Approach‟ to development (ibid. p.35). This

means that the zoning of lands would progressively extend outwards from the centre

of the urban areas with “under-developed lands closest to the core and public

transport routes being given preference” (ibid. p.36). This can be seen as a

response to the problem of „leapfrogging‟ and the „doughnut‟ pattern of development.

73

In the hierarchy of policy there is also a facility for sub-county level planning. The

legislation allows local authorities to prepare „Local Area Plans‟ for areas within their

jurisdiction. In the case of towns and other settlements with a population of over

2,000 people, the preparation of a Local Area Plan is mandatory. The main County

Development Plan acts as the parent document and provides the strategic framework

for these local plans. In the case study areas for the review, the local area plans for

the respective areas offer a key normative template against which patterns of

development facilitated under the Programme can be assessed.

5.2.4. The New Spatial Planning Hierarchy – Implications for the Programme

Significant changes in planning legislation and policy have occurred since 2000.

There is a role for regional and local roads (along with other transport modes) in

providing links between settlements, and facilitating access to services and

employment opportunities. Strategic investment therefore needs to be guided by the

National Spatial Strategy and be compatible with regional as well as local planning

and development objectives. The planning framework as it now exists, provides a

means to do this in a structured fashion.

5.3. Housing Supply and Housing Policy – Current Policy Context

5.3.1. Housing Supply Projections

The Programme was put in place in 2000. Quite obviously the circumstances that

prevailed then are different now. As has already been established, housing demand

and supply are crucially linked to changes in population, incomes and other

economic factors like interest rates. Housing supply is also affected by house prices,

planning regulation, land zoning and government policy, amongst others things. The

provision of roads and water services also has an impact on supply. The housing

market is constantly changing and any current observations represent a snapshot in

time that will undoubtedly alter. Notwithstanding this caveat it is possible to consider

current trends.

The Department of the Environment is now basing its policies on future housing

requirements on a projected population of 5.3m by 2021 (2007c, p.20). In the 2006

Census, the population was recorded as 4.24 million people. The Department

estimates that up to one million new homes may be required up to 2021,

necessitating considerable investment in transport, economic and social

infrastructure (ibid). In fact the most recent detailed projections from the Central

74

Statistics Office now forecast that the population of the state could increase to

5.687m million people by the year 2021 (CSO, 2008, p.2), which suggests an even

greater housing need. Ireland also has significantly more adults per dwelling than

other OECD countries, but is expected to move towards the international norm in the

coming years (Rae & van den Noord, 2006, p. 9). This trend is already being felt,

and as it continues we will see an increase in household formation relative to

population. For example, in 1991 Irish households had an average of 3.34

occupants. By 2006 this was 2.81 (CSO, 2006, Vol. 6). This will contribute to

housing demand in the long run.

The forecast that up to 1 million homes may be needed by 2021 is consistent with

ESRI estimates that suggest housing demand for the period 2007 to 2015 of over

600,000 units (2006, p. 157). However it should be noted that these forecasts pre-

dated the serious decline in the housing market witnessed in late 2007 and

throughout 2008. Iin the short-term the housing market is experiencing some

volatility. Housing output peaked in 2006 with over 93,000 completions and fell back

to around 78,000 units in 2007. Official forecasts for 2008 estimate 43,000

completions (DKM, 2008, p.10), however this figure could be lower.

Whatever the long-term implications of these trends, they indicate that short-term

pressures on the housing supply have significantly eased. Demand for housing may

still be significant in the long-term, but the urgency which existed when the

Programme was established is no longer a factor.

5.3.2. Land and Zoning

An important factor in the supply of housing is the availability of zoned land. A

shortage of zoned land can create a „scarcity value‟ and drive up prices. Planning

controls, although necessary can also have the effect of increasing this scarcity

value. There was some criticism in the earlier years of the housing boom about

insufficient supplies of suitable zoned lands. Current circumstances are substantially

different. Under Section 95 (1) of the „Planning and Development Act 2000‟, local

authorities are obliged to ensure that sufficient and suitable land is zoned to meet

residential requirements and to ensure that a scarcity of land does not occur.

According to the most recent data, there were a total of 15,877 hectares of

undeveloped zoned serviced land available at June 30th 2006 (DEHLG, 2007a, p.44).

This means land that has the necessary water, sewage, transport or other services

75

required to bring it into development. Based on current density guidelines, this land

has the capacity to deliver 492,219 housing units. This equates to sufficient capacity

nationally for residential development for six years, based on average output (ibid.).

The level of serviced land, and capacity to deliver housing in respect of each of the

local authority areas that were covered by the Programme is set out below.

Table 5.1. The Availability of Undeveloped Lands that Were Zoned and Serviced For Housing at 30 June 2006

County / City Council Area

Hectares

No. of Housing Units

Greater Dublin

Dublin City Council 479 58,227

Fingal County Council 1,161 43,863

South Dublin County Council 814 39,660

Dun Laoghaire Rathdown County Council

342 20,604

Kildare County Council 755 19,381

Meath County Council 270 8,735

Wicklow County Council 225 7,621

Cork

Cork City Council 143 10,158

Cork County Council 1,389 29,686

Limerick

Limerick City Council 113 4,382

Limerick County Council 315 7,269

Galway

Galway City Council 123 2,983

Galway County Council 582 15,004

Waterford

Waterford City Council 173 5,661

Waterford County Council 78 1,612

(DEHLG, 2007a, p.44)

Providing sufficient zoned and serviced land whist important, will not ensure that

these lands are developed in a manner that is socially optimal. This calls for a more

proactive policy on land use management. The NESC in its „Housing in Ireland‟

report highlighted the importance of active land management in responding to

housing demand. This involves a more strategic and longer-term approach to land-

use policies (2004, p.9). Following publication of the report, all local authorities

reviewed their approaches in this area and incorporated the results of these reviews

into their statutory local Housing Strategies.

However, it is in the nature of housing supply that the owners of lands zoned for

development can‟t be compelled to actually build upon them. While the 2003 study

by Goodbody Economic Consultants found no evidence that land hoarding was a

76

widespread problem (2003, p.2), it can nevertheless arise. As a policy response

there is now a commitment to introduce legislation “to ensure lands zoned and

serviced for housing purposes are used in a timely fashion” (DEHLG, 2007c, p. 36).

Taken together, the changes on active land management and the zoning and

servicing of land mean that there should be adequate quantities of land available for

housing development in the coming years. The availability of zoned and serviced

land was a constraint on housing supply in the late 1990s. This was a crucial factor

that contributed to the setting up of the Programme. As a key constraint to housing

supply, this is no longer an urgent and pressing issue.

5.3.3. „Delivering Homes Sustaining Communities‟

In February 2007, the Minister for the Environment, Heritage and Local Government

published „Delivering Homes Sustaining Communities‟. This can be seen as the

most current and definitive national policy document on housing. It sees the key

instruments to deliver housing supply as being “Planning, Urban Design,

Infrastructure Investment, Land Management and Public Service Delivery” (DEHLG,

2007c, p.9). There is also consensus on the need to provide significantly expanded

provision for social and affordable housing.

The framework within which housing supply is to be delivered revolves around the

various policy initiatives, systems and mechanisms that have been implemented in

recent years, particularly the National Spatial Strategy and Regional Planning

Guidelines. What „Delivering Homes Sustaining Communities‟ is effectively saying is

that there is a continued role for Government investment in infrastructure to facilitate

housing development. However, infrastructure should be delivered within the

strategic planning hierarchy that is now in place. A further crucial question of

relevance to the review concerns how this infrastructure should be funded. The most

significant recent policy change in this area has been the establishment of a new

system of local development levies.

5.4. Development Levies and their Role in Providing Public Infrastructure

Housing development gives rise to greater pressures on existing roads, and can

result in the need to significantly improve infrastructure. In economic terms, this

represents a cost. Unless the cost is met by the developer or house purchaser, it is

transferred onto existing residents in a community. This can be in the form of a

„negative externality‟ manifest through increased congestion and worsening road

77

conditions, or as direct cost when local government has to provide infrastructure from

its own resources. The way that Irish public policy has sought to deal with this is

through a system of development levies. These arrangements evolved since 1963.

Current provisions are set out in Sections 48 and 49 of the „Planning and

Development Act 2000‟. They were brought into force in March 2002, with a

requirement that local authorities put a new scheme of levies in place by March 2004.

The NESC has suggested that limited forms of development contributions prior to this

legislation resulted in significant costs being imposed on local authorities as a result

of house construction (2004, p.119).

What makes development contributions relevant to the Programme is that they were

an important source of funding in meeting the local authorities‟ required contribution

to individual projects. The legislation now in place provides for three types of

development contributions, as follows:

General development contributions,

Special development contributions, and

Supplementary development contributions.

Payment is required as part of the planning process and is attached as a condition to

planning permission. Development contributions schemes attempt to strike a difficult

balance. On the one hand there is a clearly a case for ensuring that levies represent

the full additional costs of providing infrastructure. On the other hand, if levies are

too high they could act as a disincentive towards development. This would tally with

Barker‟s identification of a potential market failure when the costs imposed on

development can discourage housing construction and a potential welfare gain for

society. Higher-than-justified development levies could also result in a form of „free

riding‟ on the part of existing residents who may expect developers (and new home

owners) to provide infrastructure that benefits everyone. Whilst not explicitly using

the „market failure‟ terminology, the Guidelines issued by the Department warn of

“negative social and economic costs” that may be caused by unreasonably high

contributions (DEHLG, 2003, p.4)

For the purposes of reviewing programme, the system of levies is of significance

from both a theoretical and practical perspective. The contributions offer a formal

framework to address a specific market failure that was raised by Barker. They can

be seen as a means for the exchequer and local authorities to ensure that the

78

additional cost of infrastructure resulting from development is internalised by

developers. From a practical perspective, the Programme had an expressed aim to

facilitate the zoning of lands and development of housing and other commercial

buildings. This provided a source of revenue. The extent to which exchequer

funding was supplemented through development levies is therefore of interest. In

other words, did the developments benefiting from the roads infrastructure pay their

fair share of the costs? Development levies also offer an important future source of

funding for roads infrastructure, particularly in areas that are experiencing

considerable development.

5.5. Conclusions

The purpose of this chapter was to look at the Programme‟s original objectives and

compare them with current Government strategy. This examination of policy and

legislative changes is important in conveying the extent to which Government

strategies has developed since 2000. When the Programme was conceived,

particular exceptional circumstances prevailed in the housing market. There were

also strong development pressures to provide industrial and commercial lands.

There were specific market failures, particularly with the undersupply of housing.

However, these conditions generally no longer prevail. The supply of zoned and

serviced land is now sufficient to meet needs in the medium term. The urgency to

meet growing housing demand in the short-term is no longer a factor, with output

actually falling in 2007 and expected to fall further in 2008. An entire hierarchy of

planning strategies, guidelines and policies have been put in place to achieve spatial

planning goals, and co-ordination between various policy objectives in the fields of

housing, transport and economic development. In meeting future housing needs,

policy will be crucially informed by the principles of sustainable development.

Nothwithstanding the fall in housing construction output experienced in 2007 and

2008, and the differing forecasts about future output, the underlying social and

demographic factors point to significant housing demand that will need to be met up

to the year 2021. The manner in which this will be achieved is set out in the DEHLG

policy document „Delivering Homes Sustaining Communities‟. There is a role for

regional and local roads in facilitating the provision of development lands and

housing supply. Whatever policy instruments are used to deliver roads, the new

system of development levies offers an important source of additional funding.

79

There is a stated commitment on the part of the Department of Transport to support

the development and maintenance of the regional and local roads network. This re-

iterates a commitment in the National Development Plan 2007-2013. The

Department‟s „Statement of Strategy‟ published in April 2008 states that:

“Significant investment in the network of regional and local roads is

important to complement the investment in the national roads

network….these roads are vital to local enterprise agriculture, forestry

and tourism as well as having a valuable social and economic

function.” (DoT, 2008, p.40)

This entails a commitment to support the economic and social development role

played by regional and local roads. However, it does not automatically follow that

the Programme being reviewed here, which had a dedicated focus on opening-up

development lands, should continue. A core principle underpinning the entire „Value

for Money Policy & Review Initiative‟ is that investment decisions should be guided

by policy priorities as they now stand. Roads policy has substantially shifted its

focus in the direction the National Spatial Strategy, and this is now the guiding

framework.

In 2006 a new and separate funding programme was established to support roads

that make a significant contribution to achieving the objectives of the NSS. This is

described as the „New‟ Strategic Regional and Local Roads Programme. The

characteristics of the Programme, and the implications for future public expenditure

commitments are examined further in Chapter 9. In policy terms however, this shift

is in line with Governmental strategic priorities, and those of the two Departments

that are directly concerned with roads and spatial planning policy. The new

programme has been endorsed by the National Development Plan (2007, p.85), and

the recently revised Department of Transport Statement of Strategy (DOT, 2008,

p.40). This is a vital contextual factor influencing the overall recommendations that

can be made about future funding decisions. While the objectives of the Programme

under review are generally compatible with current Government policy, the shift in

strategic priorities calls into question the need for dedicated programme with such a

specific focus on the facilitation of housing and industrial land.

A further development of note was the publication by the Department of Transport in

2007 of „Guidelines on a Common Appraisal Framework for Transport Projects and

Programmes‟ (DoT, 2007). These effectively set down the procedures and rules to

80

be followed when making investment decisions on transport projects. Their

relevance to any future arrangements for providing regional and local roads will also

be examined in Chapter 9. Before this can be done, the performance of the current

programme must be assessed. The next three chapters constitute the core of the

review. They will evaluate the Programme in terms of its outputs, effectiveness and

efficiency.

81

Chapter 6

“Define the outputs associated with the Programme

activity and identify the level and trend of those

outputs.”

6.1. Introduction – Identifying the Outputs

The significant outputs of the Programme are the roads themselves. However, the

roads were intended as a means to facilitate lands for housing, industrial and

commercial development. These can be seen as both outputs and outcomes. For the

purposes of the review, these are treated as „secondary‟ outputs, or in the standard

terminology used to describe performance indicators, they can be also viewed as

„intermediate‟ outcomes. To avoid confusion, all of the physical roads infrastructure

and the resulting housing and development lands that were facilitated, are simply

referred to as „outputs‟. It was the view of the Quality Assessor who examined the

review, that the lands for housing, industrial and commercial development are more

accurately described as „impacts‟ rather than „outputs‟.

This chapter will provide quantitative details of these deliverables, as reported by the

local authorities in their questionnaire responses. The complexities surrounding the

causal relationship between the roads, the zoning of development land and the supply

of housing, are examined in Chapter 7, which deals in more detail with the question of

„Effectiveness‟. However, when outputs are measured and compared, it is natural that

some preliminary conclusions of programme effectiveness can be drawn.

The approach adopted here for assessing the level and trend of outputs is to use the

commitments in the original project applications as a baseline to make relative

comparisons with what has been delivered. In order to achieve valid comparisons,

appropriate adjustments have been made to take account of data that was not

available in the original application forms back in 2000, and to reflect changes in the

composition of the Programme since then. This quantitative data is augmented with

qualitative contextual detail drawn from the interviews with the local authority

personnel, and from the case study areas.

82

The circular letter and publicity materials which announced projects supported under

the Programme quantified the intended outputs. These are set out in table 6.1,

overleaf.

Table 6.1. Original Output Targets

Main Projected Deliverables

(per circular 25/00)

Quantities

Number of Houses

43,659 Houses

Length of Road (in kilometres)

123.545 km

Hectares of Housing Land

1,659 Hectares

Hectares of Industrial Land

932 Hectares

The kilometers of road were based on the combined total length of all 43 of the original

selected projects. However, the housing units and development land figures were

based on the 29 application forms that included figures for such quantifiable

deliverables. 14 did not, and were selected on the basis of a general commitment to

the facilitation of development, and their location in areas of Kildare and Meath which

were facing major development pressures. In the case of the Meath projects,

estimates of the quantified deliverables were subsequently provided. Of the 44

projects now being examined, 8 do not have original estimates of quantified outputs in

the form of housing units etc. from 2000, or similar current questionnaire data to use

for comparative purposes. These are the six projects involving improvement works

along the R406/ R407 regional roads in County Kildare13

, plus the Celbridge

Interchange and the „Roads Serving Intel‟. This lack of comparable data has

implications for the assessment of effectiveness in Chapter 7, and alternative

indicators are identified for this purpose. Notwithstanding the validity of the case that

existed for funding these projects, the lack of indicators is something from which

lessons should be learned. It would benefit future programmes if the same types of

indicator were used to appraise all projects at the outset, and to evaluate their

effectiveness upon implementation.

The individual projects are also units of output in their own right, which can be

assessed in terms of commencement and completion against their original intended

timescales. The impact of delays, as well as their causes, will be described and

13 Barberstown to Maynooth (both sections), Clane to Kilcock (both sections) and Sallins to Clane (both sections).

83

analysed. These delaying factors also have implications for other regional and local

roads programmes.

6.2.1. Aggregate Outputs – Housing and Development Land

Table 6.2, below sets out in aggregate terms the quantitative outputs being delivered

by the Programme, as reported in the questionnaire returns. Column 1 details the

original intended deliverables that have already been given in Table 6.1. Column 2

makes adjustments to this data to account for changes in the Programme and the

submission of output targets for some projects which weren‟t available at the outset.

Direct comparisons can therefore be drawn between columns 2 and 3. Respectively,

these two columns represent the original intended outputs, and the reported outputs

for 36 projects. The eight that have already been mentioned in County Kildare are not

included. The notation underneath explains the origins of the data and any noteworthy

issues to assist in understanding the figures.

Based on the questionnaire returns, it is possible to say that upon completion, the

Programme will have delivered upon, and exceeded its stated commitments in terms

of housing units and development lands for both housing and industrial purposes. The

extent to which this has happened can be gauged from column 4.

Table 6.2. Headline Outputs – Housing and Development Land

1 Expected Outputs based on Original 2000 Applications

(see note 1)

2 Original Expected Outputs – Revised

(see note 2)

3 Declared Outputs

based on 2007 Questionnaire

Returns (see note 3)

4 Difference between

Expected and Actual

Performance

Housing Units 43,659 46,024

65,436

19,412

(+42%)

Housing Hectares

1,659 1,791 2,281

+490

(+27.5%)

Industrial / Commercial Hectares

932 959 973.5 +14.5

(+1.5%)

Notes on the Data in Table 6.2

Note 1

Projected outputs in first column were quoted in Circular 25/2000 notifying local authorities of

the selected projects, and in publicity material for the Programme. Quantifiable deliverables

were not originally provided in respect of 14 projects

84

Note 2

Column 2 is a revised version of Column 1. It reflects changes in the make-up of the

Programme caused by the addition and discontinuation of projects, and the receipt of

outstanding data, as follows:

Two projects were added (Ballybeg Road in Waterford City, and the Tramore Ring

Road Phase 5 in Waterford County). The original deliverables for these projects have

been added.

Deliverables were subsequently submitted in respect of four of the five Meath projects.

The remaining Meath project (Plattin-Colp) was discontinued, and it was therefore not

necessary to include data.

Two Kildare projects were reallocated from the Programme (Enfield-Edenderry), and

one added (Roads Serving Intel). However, these did not have quantifiable housing

and development land outputs.

Two further Kildare projects were discontinued (Naas Inner Relief Road and Clane

Inner Relief Road). Appropriate adjustments have been made.

Parkmore Road crosses the local authority boundary in the Galway city suburbs. It

was undertaken as two separate schemes by Galway City Council and Galway County

Council. The data for columns 2 and 3 have been presented in a way that avoids

double counting of the same outputs.

The subdivision and amalgamation of projects also resulted in a net increase in the

number of projects with quantified outputs, but this had no net impact on the overall

quantity of outputs.

Note 3

A valid comparison can be drawn between columns 2 and 3. These are effectively the before-

and-after output data for 36 projects.

6.2.2. Delivered and Potential Outputs

The aggregate figures, although useful, do not give the full picture. In the case of

housing units and development lands, there is a need to differentiate between outputs

that have been delivered, and those that are projected to be provided in the future.

The local authorities were asked to provide this data through the main questionnaire.

While not all of them did (or could) provide this breakdown, the available figures give a

good indication of the extent of delivery of the key outputs to date.

These are set out in Tables 6.3, 6.4 and 6.5 (overleaf) and deal respectively with

Housing Units, Housing Lands and Commercial Lands.

85

Table 6.3. Housing Unit Outputs

Housing Units constructed, under construction or in the planning process

27,379

Potential housing units on zoned land that are not yet submitted for planning permission

20,061

„Other‟ - Housing Units where aggregate data did not differentiate between the two categories above

17,996

Total

65,436

Table 6.4. Housing Land Outputs (Hectares)

Land that has been zoned, serviced and built upon (including construction currently underway)

959 ha

Land that has been zoned and serviced but not developed

583 ha

Land that has been zoned but not serviced or developed

191 ha

„Other‟ - Land where the data provided did not differentiate between the three categories above

548 ha

Total

2,281 ha

Table 6.5. Industrial / Commercial Land Outputs (Hectares)

Land that has been zoned and developed upon (including construction currently underway)

295.5 ha

Land that has been zoned and serviced but not yet developed.

445.5 ha

Land zoned but not serviced or developed

18 ha

„Other‟ - Land where the data provided did not differentiate between the three categories above

214.5 ha

Total

973.5 ha

Before analysing these table, some caveats must be sounded. Differentiated data in

the categories requested was not provided for relatively large quantums of the output

data. Up to 17,996 housing units and 548 hectares of housing land fall into the „Other‟

category. It was not specified whether they had been delivered. This limits the

inferences that can be drawn.

A general message that can be read from the tables is that a reasonable proportion of

the anticipated outputs have not yet been fully realised. Given that an objective of the

Programme was to respond quickly to housing supply pressures and development

land shortages, this is a criticism. However, the original application process did not

require delivery within a set period.

86

In the case of the Housing Units, nearly one third fall into the category of „potential‟

outputs, but this may not be as significant an issue as it appears. Given the forecasts

for future housing demand as set out in the previous chapter, these are likely to be

required to meet future housing needs, albeit in the medium to long term. It is also

clear from the interviews that the local authorities are anticipating significant need for

housing development going forward. This is also evident from the detailed

examination of the most recent statutory Development Plans adopted by the local

authorities in the case study areas of Naas (Co. Kildare), Tramore (Co. Waterford).

They are basing their infrastructural planning around the assumption of future

population growth and housing needs, whatever the current situation affecting the

housing market in the short term.

It is noteworthy also that the majority of the housing land outputs declared in the

questionnaires are either developed, or have been serviced for development.

„Serviced‟ lands are those that have access to roads, water, and sewage services.

When required to meet housing demand, these can productively be used within a

relatively short timescale.

One of the purposes in setting up the Programme was to improve the situation being

faced by those seeking social and affordable housing. The questionnaire sought

details on the proportion of housing units that fell into the „Social and Affordable‟

category. However only 9 valid returns were received, which curtailed the use of this

data. However, almost all of the roads projects have come on stream after the

enactment of Part 5 of the „Planning and Development Act 2000‟, which requires

developers to set aside up to 20% of housing developments for social and affordable

purposes. It is therefore likely that a significant proportion of the housing outputs will

fall into this category, and that the Programme will assist in the delivery of social and

affordable housing. The case study area of Tramore Town would bear this out. The

proportion of social and affordable housing units delivered by phase 4 of the ring road

was 33% (which also includes direct local authority provision). For phase 5, the social

and affordable element is reckoned by the local authority to be 20%. This is in line

with the legislation. The local authority also appears to be vigorous in forcing

developers to meet their obligations. The company that developed most of the

housing along the Tramore Ring Road (R. McDonald & Son) raised this issue in their

interview (albeit as a cause of concern to them and a criticism of the local authority).

87

In the Naas case study area, it is interesting that the Town Council and Kildare County

Council are actively pursuing a policy to require developers to provide housing units,

rather than „payments-in-kind‟. The legislation allows developers to meet their

obligations by way of a payment, and this facility is widely used across the country.

The policy in relation to Naas is set down in the Kildare County Housing Strategy

2005-2007, and in the Naas Town Development Plan 2005-2011, where it states that

“compliance with Part 5 through a financial contribution will only be acceptable in

exceptional circumstances” (NTC, 2005, p.56). There is some evidence therefore that

the Programme is assisting in the delivery of social and affordable housing, although

this is based on the case study areas rather than a full set of programme-wide data.

In relation to the industrial and commercial lands, most of the deliverables are

differentiated. A high proportion, over 76%, are either developed or serviced for

development. This indicated that they are currently in use, or are immediately

available for use. A relative small portion (less than 2%), have neither been serviced

nor developed. The remaining 22% were not subcategorised within the questionnaire

returns.

In summary, based on the questionnaire data, the Programme will exceed its expected

outputs for delivering housing units, housing lands and industrial / commercial lands.

However, some of these deliverables are not yet realised, but are likely to be in the

medium term.

6.3. Performance of Individual Projects

The output data for each of the 44 individual projects is included in a spreadsheet table

at Appendix VI, „Output Data‟. This allows for a direct individual comparison to be

made between the stated expected outputs when the projects commenced, and the

outputs as reported by local authorities in their questionnaire returns. Some projects

had either housing or commercial outputs as their focus, while others combined both.

At aggregate level, 34 of the projects reported output data for housing lands. Of these

over half (18 projects) exceeded their original projected outputs. A further 8 are

delivering less housing lands than was originally anticipated, while another 8 report

outputs in line with original projections.

88

In the case of housing units, 32 projects provided output data14

. 18 of the 32 exceed

original projections while 5 are delivering less housing units than were originally

expected. A further 9 have outputs in line with original expectations. Interestingly, in

the case of the Waterford City Outer Ring Road, Tramore Ring Road (Phase 5), Naul

Road and Lusk Bypass, while a smaller area of land is being facilitated, a greater

number of houses than forecast is being provided. This was explored in the interviews

with the respective local authorities, and can be partly explained with reference to

increased densities that are promoted under revised planning policies. In fact, higher

density development is something that is prevalent right across the Programme in

other projects. It is noticeable that a significantly greater number of housing units than

expected is being delivered (almost 20,000 in total). While this can be partly explained

by the greater overall quantum of land being facilitated, increased housing densities

have been crucial in the Programme exceeding expectations. The Old Whitechurch

Road in Cork City can be cited by way of an example. It had originally been expected

to deliver 400 units on 22.6 hectares of land. It is now delivering 1,100 within the

same area. Proximity of access to public transport routes has facilitated the increased

density. This is relevant from a policy perspective, because there is greater emphasis

on integrated planning that allows for higher density housing to be developed where

sustainable modes of transport can be accessed. In this case, the road upgrade is

allowing development to take place, while public transport is facilitating the higher

densities.

From the 30 projects reporting outputs of industrial and commercial lands, exactly half

(15) exceeded original projections, while 4 are meeting their original targets. Notably,

11 projects did not meet their original projections. While outputs are being exceeded

at an overall programme level, the fact that such a significant number of projects did

not meet expectations needs further examination. The Oranhill Distributor Road in

County Galway did not report any of its expected 20 hectares of commercial land.

However this was offset by the delivery of 56 extra hectares of housing land. The

Naas Ring Road at Craddockstown which opened in March 2008, reported that none

of its anticipated 95.5 hectares have been facilitated. However, planning maps for the

area that were examined during the case study work would suggest that substantial

tracts will be opened up in future.

14 Two of the projects that had housing land outputs did not provide additional data on housing units Parkmore Road (Galway County Council) and Naas Ring Road Millennium Park (Kildare County Council).

89

Of particular note has been the tendency for certain roads originally intended solely to

open up industrial lands, to have also facilitated housing. This particularly applies to

the Kileen Road in Dublin City, the Millenium Business Park section of the Naas Ring

Road (Kildare) and the Parkmore Road (both Galway City and County sections). For

example, Kileen Road was originally intended to open up 80 hectares of industrial

land, but has facilitated 43 hectares, along with a further 43 of housing land (86ha in

total). This trend has not been accidental. The developers of all three industrial /

commercial sites were interviewed as part of the qualitative element of the study.

There has been a conscious shift towards combining commercial facilities with

residential development and related amenities. Heretofore these types of

development would have been separated. Principles of sustainable development have

shifted this policy. There is a conscious decision on the part of developers and

planners to facilitate mixed developments.

While some of the projects that did not meet original targets appear to have simply

underperformed, there are valid explanations and underlying policy shifts that explain

others. The table below presents the aggregated performance data at programme-

level that has already been outlined above.

Table 6.6. Relative Performance of Projects - Reported Outputs Compared to Original Intended Outputs

Housing Lands (No. of Projects)

Housing Units (No. of Projects)

Industrial / Commercial Lands

(No. of Projects)

Greater than Originally Expected

18 18 15

Same as Originally Expected

8 9 4

Less than Originally Expected

8 5 11

Total Projects 34 32 30

6.4. Roads Outputs

Upon completion of the Programme, the combined anticipated length of all roads

outputs will be 103,985 metres. This varies by almost 20 kilometres from the original

projected length. Almost all of the difference can be attributed to the reclassification

and removal of some of the original projects. When adjustments are made to take

account of these changes, the difference is 820 metres. There were some variations

within the individual projects, but this largely evened out at a programme level.

Obviously for the projects where the length of road changed, this would have cost

implications that will be examined later in the review. The length of road delivered in

90

line-metres offers a useful headline indicator for outputs. However, it has limitations

for other forms of analysis. For example, when the relative cost is considered, the

width of the road and particular design features (including structures like bridges etc.)

then become crucially important factors. Nevertheless, for the purpose of establishing

the level and trend of outputs, the length of road is informative.

In a manner similar to the earlier tables for the housing and development land outputs,

Table 6.7, provides a breakdown of the length of road delivered since the inception of

the Programme. The first column contains the original anticipated outputs from 2000.

Unlike the housing and development land data, this data is drawn from a complete set

of all 43 original projects. The second column is a revised version of column 1 and

represents the original projected output data for the 44 projects that current comprise

the Programme. Column 3 contains data on roads outputs as reported in the

questionnaire returns. Columns 4 and 5 differentiate between outputs delivered up to

the end of 2008, and those expected to come on stream after that date. Significantly

12,660 metres remain to be delivered in 2009 and beyond.

Table 6.7. Roads Outputs

1 Original

Expected Road Outputs – per Circular RW

25/00

2 Revised Original

Outputs (see note 1 below)

3 Total expected outputs for the

Programme (already

delivered and projected)

4 Outputs

Delivered by end of 2008 (see note 2)

5 Outputs

projected for delivery post

2008

123,545 metres

104,805 meters

103,985 metres

91,325 metres

12,660 metres

Note 1 - The two Enfield to Edenderry schemes (Kildare) were reallocated from the Programme.

Plattin Colp (Meath), Naas Inner Relief Road (Dublin Road to Tipper Road) and Clane Inner Relief

Road were taken out of the Programme. New projects were added (Waterford Outer Ring and

Ballybeg). „Roads Serving Intel‟ was added to facilitate access and egress from the Intel plant at

Leixlip. It did not have a measurable length of surface.

Note 2 – 640m of the Balbriggan Inner Relief Road was completed in 2005 and is included in

column 4. The remaining 1,160m are due for completion in 2009 and are included in column 5.

The roads also incorporate associated physical infrastructure. Of particular interest

here has been an emerging tendency to include additional features to accommodate

cyclists and pedestrians. These were not seen as particularly crucial elements when

the projects were initially selected. However, they have become significant aspects as

transportation policy has shifted emphasis, with sustainability becoming increasingly

important. Based on the questionnaire returns, 26 of the 44 projects have included

cycle tracks as part of their roads outputs. In almost all cases, these are separated

91

from the main road carriageway, which has added benefits from a safety point of view.

35 of the 44 projects include footpaths to facilitate pedestrians. The projects that didn‟t

include cycle tracks and footpaths are the longer stretches of road passing through

predominantly rural areas.

Table 6.8. Facilities for Cyclists and Pedestrians

Cycle Tracks Footpaths

Number of Projects (from a total of 44)

26

35

Accessibility and mobility for pedestrians and cyclists is an important aspect of

sustainable planning and development. These principles are set out in the planning

guidelines issued by the Department of the Environment, and since 2007 are also

factors when transport projects are appraised under the Department of Transport‟s

guidelines for capital expenditure. The extensive provision of such facilities through

this programme can therefore be seen in a positive light. As well as providing mobility

and accessibility, there are also health benefits that accrue. Waterford City Council,

for example, reported that the cycle tracks and footpaths on new Outer Ring Road

(which is 6.8km in length) have become a route used for training and exercise by

walkers, runners and cyclists.

By and large then, the Programme is delivering what it set out to do in terms of the

roads being constructed. The outputs are broadly in line with what was projected.

However, the 12,660 line-metres scheduled to be delivered after 2008 represents over

12% of the total road length. Eight years after the commencement of a programme

that was supposed to last four years, the fact that such a large proportion of outputs

have yet to be delivered is a cause for concern. Delays affecting the projects and their

impact will now be considered in more detail.

6.5. Factors Affecting The Delivery of Outputs

6.5.1 Commencement and Completion of Projects

At the outset, a sense of urgency pervaded the Programme. It should be recalled from

Chapter 4, which identified the objectives of the Programme, that the timely

commencement and completion of projects was seen as important. It should also be

recalled that the Programme was originally intended to run from 2001 to 2004. As a

result of a variety of factors, the projects have taken much longer to complete than was

originally anticipated. In examining this whole area three key questions in particular

arise:

92

What were the extent of the delays?

What caused them?

What lessons can be learned for the future?

Data to address these questions is drawn from the questionnaire responses and

interviews. A significant number of projects neither commenced, nor were completed

within the original planned timescale. Within the intended lifespan of the Programme

(2001-2004), 32 projects commenced and 19 were completed. Coming into 2008, 3

projects had yet to commence, and 13 awaited completion. Summary tables (below)

set out in aggregate, the dates of commencement and completion for projects. The

information is based on data drawn from the questionnaires. The individual

commencement and completion dates for all 44 projects is included at Appendix VI.

Table 6.9. Project Commencement Dates

Year of Commencement

Number of Projects

2001 11

2002 8

2003 8

2004 5

2005 2

2006 3

2007 4

2008 1

2009 1

Post-2008 (with no date specified)

1

Total 44

Table 6.10. Project Completion Dates

Year of Completion

Number of Projects

2001 1

2002 4

2003 5

2004 9

2005 4

2006 6

2007 2

2008 7

2009 4

2010 1

2011 1

Total 44

In a majority of cases, the local authorities were overoptimistic in their estimation of the

time taken to commence and conclude their projects. At programme level, the

93

Department‟s expectations for commencement and completion deadlines turned out to

be unrealistic and unattainable in practice. The data still only tells part of the story.

When evaluating a programme, it is also important to consider prevailing conditions

that impact upon delivery. The projects were being implemented within a changing

and volatile economic and policy environment. Construction and land costs were

increasing and putting pressure on local authorities. Other localised influences

associated with individual projects also need to be considered.

There is considerable overlap between the issue of delays and increased costs, with

the former contributing to the latter. For example, delays in the planning process and

land acquisition led to delays in works commencing. This caused exposure to

consequent inflationary increases in construction costs. In the year 2000 road

construction inflation was running at 12%. In 2001 it was 9% and in 2002, 5% (C&AG,

2004, p.56). Increased costs, particularly land costs, also created difficulties for some

local authorities in meeting their funding commitments on projects. This in turn led to

delays, which were again compounded through further inflationary cost increases. The

level and trend of costs will be examined in Chapter 8.

Apart from describing the delays, and suggesting ways in which they can be

overcome, it is also worthwhile to look beneath the statistical data, and explore

particular trends where they are present. Evaluation theorist Ray Pawson

recommends a method that seeks to identify “what works, for whom, in what

circumstance and in what respects”, (Pawson, 2006, p18). This is described as a

„Theory-Based‟ approach to evaluation. In drawing conclusions for this section of the

review, it is proposed to invert Pawson‟s method. The review will identify what didn‟t

work, for whom, and what circumstances prevailed in those instances. In doing this,

the purpose is to identify the common factors that were present when delays arose,

and to recommend measures to anticipate and deal with them in future.

6.5.2. Public Consultation and Environmental Impact Statements

Part 8 of the „Planning and Development Regulations, 2001‟ sets down statutory

obligations on local authorities when seeking planning consent for certain public

infrastructure works. Local authorities are required to undertake a process of public

advertisement and consultation for the construction of a new road, or the widening or

94

realignment of an existing road15

. The predecessor to this provision was Part 10 of the

„Local Government (Planning Regulations), 1994‟. Within the questionnaires and

interviews, the processes themselves did not come in for criticism, and were seen a

necessary and democratic element of the planning process. However, the public

consultation processes did take time to complete, and in a number of cases, delayed

commencement. This applied in particular to controversial projects, especially those

affecting residential areas where considerable local opposition arose.

Returns for 36 projects stated that they had been subject to a public consultation

process. The length of time taken to complete the process was indicated in 35 cases,

with one consultation process still ongoing at the time. One fifth of the projects

concluded their public consultation process within the minimum period possible, which

is 3 months.

Table 6.11. Length of Public Consultation

Length of Time to Complete

Public Consultation

Number of Projects

23/ 24 months 2

18 months 3

12 months 5

9 -11 months 3

7- 8 months 3

6 months 10

4-5 months 2

Within 3 months 7

Currently Ongoing 1

36

Just over half of the projects that engaged in a statutory public consultation concluded

it within 6 months. However, a considerable number took longer, with over one quarter

taking a year or longer. Projects where public consultation processes were particularly

cited as contributing to delays were two of the Cork County Council projects

(Carrigaline Western Relief Road and Clarkes Hill/Moneygourney Road), the South

Dublin Outer Ring Road, the Duleek to Julianstown Road (Meath), and the Newbridge

15 Part 8 (80.1.b). The provision applies to roads of 100 metres or more in an urban area, or 1 kilometer or more in a rural area.

95

Road to Caragh Road section of the Naas Ring Road (Kildare). All of these projects

also experienced cost increases to varying degrees.

Environmental Impact Assessments / Statements did not feature extensively, with

three in total. Where they were undertaken, they tended to be on larger and more

complex projects, again affecting residential areas (the Dundrum Bypass, South Dublin

Outer Ring Road and the Wicklow Port Access / Inner Relief Road). In the case of the

Outer Ring Road, it was originally intended that an EIS would be prepared for two

separate sections of the road. Following an oral hearing by An Bord Pleanála (the

independent planning appeals board), an additional (and third) EIS had to be

prepared. Recommendations from An Bord Pleanála also required that the design of

the road be modified. According to the County Council, the scheme originally

proposed in 2001 did not complete all of its statutory processes for 3 years. This is

something of an extreme example, but it does demonstrate the potential for difficulties

to arise, especially when developing strategic roads in urban or suburban areas.

Public consultation, planning consent and environmental impact assessment are

necessary and desirable aspects of the planning process. However, it is unrealistic to

expect these to be concluded within the minimum possible statutory period. Some

good advice here was given by a local authority engineer who recommended that

realistic timescales should be allowed for:

“Give yourself a realistic window, and I suppose you have to be a bit

more realistic with regards to the timeframes. I think sometimes looking

at schemes, we‟re all very optimistic….and the next thing someone puts

an obstacle in front of us, and all of a sudden our three month timetable

to get through this process is now six months…”

6.5.3. Delays in Land Acquisition

The acquisition of lands was a significant delaying factor on a number of schemes.

Ten questionnaire responses cited delays caused by land purchase. However, it

emerged as an even bigger issue during the interviews with the local authority

personnel. At the outset, a number tried unsuccessfully to conclude land deals by

negotiation and eventually had to use a Compulsory Purchase Order.

Ireland, in common with other jurisdictions has a market economy based on the private

ownership of assets. This includes lands and buildings. Article 43 of the Irish

Constitution guarantees the right to private property, although this right is regulated by

96

principals of social justice16

. Land for roads and other public infrastructure projects

can be acquired by local authorities by agreement with the owner at market value.

Where agreement is not possible, statutory powers can be invoked allowing for

compulsory acquisition. When this happens, the current basis for assessing

compensation to be paid to a landowner is the market value of the land, plus

allowances for what are described as „severance‟, „injurious affection‟ and

„disturbance‟. Allowances can also be made for „betterment‟, or improvements arising

as a result of the provision of local authority infrastructure like water services, roads

and public lighting. Where a dispute arises about compensation, the matter can be

referred to an independent property arbitrator for decision. The level of payments

made to landowners has implications for the cost of roads projects, and is addressed

further in the Chapter 8 of the review.

The way the procedure currently operates, is that an application is submitted to An

Bord Pleanála. Once a Compulsory Purchase Order is approved, a local authority is

then entitled to serve a „Notice to Treat‟ on persons holding an interest in the land in

question. In effect, it allows the local authority acquire the right to use the land upon

payment of compensation. The figure to be paid is either agreed by the parties, or by

the binding decision an arbitrator. An important consequence of the „Notice to Treat‟ is

that the market value of the land is (generally) assessed as its value when the notice

was served. Where there is a dispute about compensation, the local authority can still

take possession of the land, pending the determination of the sum to be paid.

Local authorities have traditionally relied upon a mixture of negotiation and compulsory

purchase to acquire the lands needed for public works. However, this may be

changing. There is an emerging view that even if negotiation is required in land

acquisition, it is best to serve the CPO at the outset, and negotiate within the context of

the CPO. This approach can have a crucial benefit in bringing greater certainty to the

time taken to complete a project. This point was specifically made by nine local

authorities in interviews – Dublin, Limerick and Waterford City Councils, and Fingal,

Meath, Kildare, South Dublin, Limerick and Waterford County Councils. By way of an

example, in the case of the two Dublin City Council projects, a negotiated approach

was first adopted, but it subsequently became necessary to use a CPO. In the case of

16 This paragraph relies heavily upon information, definitions and descriptions contained in the Report on „Private Property‟ prepared by the „All Party Oireachtas Committee on the Constitution‟ (APOCC, 2005), and a briefing paper on compulsory purchase prepared by the Department of the Environment, Heritage and Local Government.

97

the Kileen Road, the City Council reckoned a 12 months delay was incurred while

unsuccessful negotiations were undertaken.

In the interviews, the phenomenon of „Ransom Strips‟ cropped up frequently. This

term has not yet entered wider public discourse, but is used among local government

officials. It describes the practice whereby a landowner may retain a key piece of land

vital to the construction of a road, and use that leverage to gain a price greater than

market value. This effectively holds the local authority and the project „to ransom‟.

This practice invariably results in delays, and cost increases. A key point from the

interviews is that using a CPO at an early stage can obviate this. In one of the

interviews an official who was centrally involved in land negotiations explained the

benefits of this approach:

“We prefer to go with CPO because it basically means that we get the lands.

Once the scheme is actually approved we take possession of the lands. If

there‟s an argument with value, that goes to arbitration where they can set

the value. But it means that we can progress fairly quickly. With negotiation

we find that we are tied up with the detail and every time you try to close out

the deal there‟s always something else that comes into the equation…so it‟s

very hard to get negotiated land, particularly on the big schemes and they

know that you need it.”

There may be exceptions where going for an early CPO may not necessarily be

required. There are situations where negotiation can facilitate the speedy conclusion

of a deal. In addition, negotiated arrangements can yield land from developers at

preferential rates. These circumstances particularly apply where there may be a

single owner (or group of owners) with a vested interest in co-operating to see that the

road project proceeds. As one official explained:

“The CPO is much cleaner, even where we are engaged in negotiations,

I‟d prefer to have a CPO sitting in my back pocket if things go wrong.

Now again, notwithstanding that, we are doing a couple of schemes at the

moment where we are doing it by agreement, but that‟s only because we

have 3 or 4 landowners where the developers would have a vested

interest in getting the road done”

Similarly, in the case of the R161 (Athlumney), Meath County Council negotiated an

agreement for land on Phase 1 where there was effectively one landowner. They

went with CPO in Phase 2, which was more complex and involved multiple

98

landowners. The Oranhill Road was a project in County Galway that combined both

negotiation and CPO. Agreement with developers enabled sections of the road to be

built, effectively at no direct cost to the local authority. A CPO was needed on

additional lands required by the local authority to construct roundabouts. While this

approach has had financial benefits, it should be noted that elements of the project are

not yet complete and work is still ongoing. Nevertheless, even where arrangements

are being negotiated with landowners and developers, it can still be advisable to use a

CPO, especially where certainty of delivery is a factor. As one senior official advised:

“the lesson would be that even with agreement that you are receiving the

land at no cost, or receiving the land at a defined cost, that you proceed

with a CPO, particularly if you have to go to the Board anyway with the

scheme for approval….You should actually put the CPO in place, from

the point of view of ensuring that you have a defined timescale”

It should be noted that applying for a Compulsory Purchase Order is a statutory

process governed by legal rules and requirements. The preparation of documentation

for CPO also places an administrative burden on the local authorities, and can take up

a lot of time. This was also cited as a factor that caused delays in some instances. By

way of countering this, sufficient allowances should be made for the time it takes to

prepare CPO documentation. In the case of the Wicklow Town Relief Road and Port

Access failure to comply with the statutory requirement to serve the „Notice to Treat‟

within 18 months of the approval of the CPO Order led to the CPO being invalidated.

This necessitated a recommencement of the whole process, with resulting delays.

Where an application for a CPO is made, it is within the rights of those affected to

lodge an objection and this can proceed to a full oral hearing of An Bord Pleanála.

This was a delaying factor in at least six projects. In one case (albeit an exceptional

one), the CPO was appealed to the Supreme Court. This happened on the R161 Trim

to Navan Improvement Scheme. Where a CPO is involved, there is no way to predict

with certainty if objections will be lodged, and a full public hearing set up. However,

this eventuality should be considered at the outset, possibly as part of a risk analysis.

Sufficient contingency time should be built in, especially if the road is generating local

controversy or impacts upon residential dwellings. Based on the questionnaires and

interviews, these are two common contributory factors where appeals and objections

frequently occur, in both CPOs and also in statutory planning consent procedures.

99

6.5.4. Other Delaying Factors

Problems that arose in contracting and tendering were cited as causing delays in a

number of instances. In the case of phase 2 of the Corbally Link Road in Limerick

City, the two lowest companies that tendered for the job withdrew having been offered

the contract, and this resulted in delays. The Balbriggan Inner Relief Road was

undertaken by a PPP arrangement, and the resolution of a development agreement

took longer than expected. Environmental constraints were cited as a factor on the

Oranhill project in Galway, Clarke‟s Hill / Moneygourney Road in County Cork and

again on phase 2 of the Corbally Link Road. Specific localised staffing issues were

particularly highlighted in Kildare County Council. For two years at the

commencement of the Programme the local authority was without a Senior Engineer.

In examining the projects that experienced the most serious delays in commencement,

some common trends begin to emerge. These projects were generally affected by

multiple delaying factors that compounded themselves. In the case of the three Cork

County Council projects, changes in the projects specification to incorporate

alterations and additional features have had an impact (especially in Midleton). These

were compounded by land acquisition issues. Two of three Cork projects also had

complex planning and approval procedures. Similar factors were prevalent in the case

of the Wicklow Town Port Access and Relief Road. The local authority noted that

restarting the CPO process took 10 months, the pre-qualification of contractors caused

a 12-month delay. Getting an agreement with Irish Rail to build a bridge over the rail

line took 18 months, while the negotiations with landowners took 24 months. It is

scheduled for completion in late 2009.

6.6. Conclusions and Recommendations

After making allowances for changes in the overall composition of the Programme and

output data that was unavailable when it commenced, the Programme will have

exceeded its stated commitments under each of the three output headings of housing

units, housing lands and industrial/ commercial lands. These can be seen as both

„secondary outputs‟ and „intermediate outcomes‟, given that their presence derived

from the road construction. While somewhat pre-empting the next chapter, this can be

taken as an important indicator of effectiveness. It should be noted though, that some

of these outputs haven‟t been fully delivered. At least one third of the housing units

have not yet been submitted for planning permission. However, it should be borne in

mind that original terms of the Programme did not specify or require a timescale for the

delivery of the housing and land outputs. Most of the housing lands have been zoned

100

and serviced. Given the medium to long term forecasts of housing needs, these units

are likely to be required to cater for projected demand.

A significant outcome in terms of policies towards sustainable transport is the strong

prevalence of cycle tracks and footpaths adjoining the roads. At the outset these

weren‟t seen as particularly important factors, and their presence can now be seen as

something of a bonus benefit. A timescale for the commencement and completion of

projects was specified by local authorities at the outset, and problems have occurred

here. Delays have had a major impact on the Programme. A distinction can be drawn

between general delaying factors that occurred, and the more project-specific

problems. The more widespread delays were caused as a result of underestimating

the time required to complete public consultation processes, land acquisition and a

general over-optimism that projects could be concluded quickly. The more specific

ones related to the appointment of contractors, environmental constraints,

modifications in projects specifications and staffing, amongst others.

Rising costs were both a cause and a contributing factor in delays. Chapter 8 will look

in more detail at the process by which cost increases put pressure on local authorities.

In particular, problems arose with them meeting their obligation to provide 25% of the

budgeted costs. This led the local authorities in turn to lobby the Department for

increased grants. All of this caused further delays, and there was something of a

spiral effect. Delays contributed to cost increases, and as additional funding was

sought, further delays occurred. Fuelling this whole process was land and

construction cost inflation during the biggest construction boom that Ireland has ever

experienced. Construction inflation was particularly acute between 2000 and 2002,

when many of these delays occurred. This combination of factors was particularly

prevalent in the larger projects in Kildare and Meath County Councils. However, they

didn‟t exclusively affect those areas.

This chapter has pinpointed the extent of the delivery of outputs. In doing so, some

issues have been identified where modifications could improve the performance of

future programmes. The following points are therefore put forward as

recommendations:

1. When the Programme was established some projects did not have measurable

outputs in the form of housing units and development lands. Notwithstanding the

case that existed for funding these roads, there is a need to have a more uniform

101

approach to output indicators, which allow a common basis for the comparative

appraisal and evaluation of projects.

2. For future reference, the key benefits and outputs that are anticipated to accrue

from roads programmes should be subject to an estimated timescale for delivery.

This is notwithstanding the fact that some factors affecting delivery may be

outside the direct control of the Department or the local authority.

3. Public consultation procedures for local authority roads, and requirements to

undertake Environmental Impact Assessments are a necessary and important

part of the planning process. While it is difficult to envisage every eventuality,

estimates of time taken to conclude these processes should be based on realistic

assessments.

4. Based on the widely expressed view of local authorities as part of this review,

seeking a Compulsory Purchase Order at an early stage brings greater clarity

and certainty in planning the likely time that land acquisition will take. However,

there are situations where negotiated agreement can be both quick and effective

in securing land from developers at preferential rates. These circumstances can

typically apply where there is a limited group of owners with a vested interest in

co-operating to see that the road project proceeds.

5. Overall, there is a need for greater rigour in the estimation of project timescales.

The probability of delays occurring and their potential impact should be assessed

at the outset in a risk analysis as part of the pre-approval project evaluation

process.

6. Where delays occur and become particularly serious, there is a need for a formal

framework within which their impact can be assessed by the Department.

102

Chapter 7

“Examine the extent that the Programme’s objectives

have been achieved, and comment on the

effectiveness with which they have been achieved.”

7.1. Introduction

It should be recalled that the immediate objective of the Programme was to support

the building of roads in order to facilitate the construction of housing and the opening

up of development land. Progress in the delivery of the physical outputs (i.e. metres

of road), was outlined in the previous chapter. So too were details of the housing

and development lands facilitated. The extent of the delivery of these outputs is an

indicator of effectiveness. Based on an assessment of outputs it is possible to say

that the Programme has been effective, although this is tempered to an extent by

delays in both the completion of projects and the delivery of outputs. Cost increases

were a further factor affecting the Programme and their impact on effectiveness will

be examined in Chapter 8.

The overall approach in establishing „effectiveness‟ was discussed earlier in the

Methodology chapter. It is based upon the Programme Logic Model, which makes

direct links between inputs, outputs and effects. The technique proposed by Mayne

which is described as „Contribution Analysis‟, is adopted. This involves the use of

multiple lines of evidence to build plausible associations between activities and

outcomes. The outcomes in the case of this programme are varied. These range

from the impact on the supply of housing, to the social and economic effects that

have resulted from development. By combining different lines of evidence, drawn

from data generated by original research, and wider existing information in the form

of what Boyle calls „Context Indicators‟, a comprehensive picture can be painted.

This is somewhat similar to the approach adopted by Morgenroth in his wide-ranging

economic and social analysis of the Greater Dublin Region (2001). He used source

material drawn extensively from existing statistical data.

A fundamental question to be answered in the review concerns the causal

relationship between the roads and the delivery of the development outputs. We

know that certain roads were built. We also know that certain housing and

development lands have come on stream. However, the „effectiveness‟ of the roads

103

crucially hinges on the role they played in enabling development to proceed. For

example, it is possible that the development might have gone ahead anyway, in the

absence of the roads being built. The earlier chapters introduced the complexities

surrounding the relationship between infrastructure and development, and housing

supply in particular. Through interviews with local authorities a plausible picture of

the relationship between roads construction and development is established in this

chapter. The discussions involving local planners were particularly insightful.

Based on the comments of the local authority officials, the general consensus was

that roads funded under the Programme were indeed crucial in the development of

the housing and in the facilitation of the lands. The most compelling supporting

evidence came when planning decisions were predicated on the presence of the

roads. There were also a difference between the roads which facilitated housing and

those with an emphasis on commercial lands, in terms of how effects were felt. The

particular dynamics involved in opening up industrial and commercial lands are

examined. This chapter will then look at effects of the Programme in the three case

study areas described earlier. The review also establishes what might have

happened in the absence of the Programme. It explores what is called the „counter-

factual‟ scenario. The final section of this chapter draws all of the evidence together,

using the multiple indicators already described to assess the effectiveness of the

Programme. It applies the „Hendricks‟ test of whether “a reasonable person,

knowing what has occurred in the program, and that the intended outcomes actually

occurred, agrees that the program contributed to these outcomes” (Mayne, 1999,

p.7). Recommendations are then made.

7.2. How the Roads Projects Linked With the Planning Process

Typically, across the Programme, the existing roads infrastructure was insufficient to

facilitate additional development on any scale. This necessitated investment in new

and upgraded roads. For example, in the interview with Galway City Council it was

explained how the new Terryland Valley Access Road facilitated 37 hectares of lands

for housing. The existing narrow and rural road would not have been capable of

accommodating the development.

Similar comments were made by local authority officials in relation to the two Phases

of the Tramore Ring Road (Waterford County Council) and the Waterford City

Council Outer Ring Road. For most of the projects, it is fairly clear that the

developments could not have happened without the road. In the case of the

104

improvement works on Old Whitechurch Road in Cork City, the planning applications

for the housing had to await completion of the road. Similarly, with the Kileen Road

project undertaken by Dublin City Council, the officials were of the view that planning

permission would not have been granted for the scale of development had the road

not been upgraded. On the Wicklow Town Port Access and Relief Road, an

example was cited of a major residential, commercial and office development that

applied for planning permission, but was refused initially on the basis of poor roads

infrastructure. Kildare County Council were able to cite examples of planning

applications for housing around the Naas Ring Road, where conditions requiring

improved roads were included in the planning permissions. There was a similar

situation in relation to the road widening and improvement works at Clarke‟s Hill in

the Cork County Council area. The granting of the planning permission was

contingent on the County Council giving a commitment to upgrading the road.

In the case of the Carrigaline Western Relief Road (also in Cork), the developers are

awaiting completion of the road, and at that point they will be able to apply for

planning permission. With the Oranhill Road in County Galway, the improved roads

were part of the planning permission for the housing being developed there. The

relationship between development and the provision of roads was commonly felt

through the County / City Development Plan or through more localised town or area

plans. These plans generally set down planning requirements for the provision of the

specific roads to allow development to proceed. In the case of Dun Laoghaire

Rathdown County Council, the Dundrum Bypass was one of two crucial pieces of

infrastructure that allowed a major shopping centre and range of residential

development to proceed. The other infrastructural project was Luas. The officials

described the symbiotic relationship between public transport and roads

infrastructural that allowed for significant planned and sustainable development to

happen in and around Dundrum.

The Midleton Northern Relief Road in Cork County is the subject of a special local

area plan, which ties the future development of the town with the improved road

infrastructure and the re-opening of the rail line into Cork City. In the case of the

road improvement projects in County Meath (Trim-Kilcock, Trim-Navan, Dublin-Trim)

the local authority stated that these were linked in with the County Development

Plan, and that decisions locally to grant planning permissions hinged on the delivery

of these roads. However, it was suggested that in the absence of the roads, some

105

development may have gone ahead and placed pressure on the existing (and largely

overburdened) road networks.

Two of the roads projects funded under the Programme played a crucial role in

opening up „Strategic Development Zones‟. These zones are a major recent

planning innovation that are designed to achieve the integrated planning of large-

scale housing developments. They are designated by the Government under

Section 169 of the „Planning and Development Act 2000‟ and are deemed to be of

importance to the social and economic development of the State. Three were initially

established. Provision of Outer Ring Road by South Dublin County County Council

(which was funded under the Programme) was linked to the development of the

Adamstown SDZ. In the Fingal County Council area, the Ongar Road (which was

also funded) was crucial to the development of the Hansfield SDZ. Given the

Government‟s endorsement of the Strategic Development Zones as a means to meet

housing needs and in delivering sustainable development, the role of roads funded

under the Programme in facilitating two of the first SDZ‟s in the country can be

assessed positively.

One of the most significant issues to emerge from the interviews was the extent to

which the roads have linked in with local development plans. This issue was raised

with all 15 local authorities. Each was able to relate their respective projects back

into their county development plan or a specific local area plan. This points to

integration between transport and land use planning, which is inherent in the

hierarchy of planning policy that has come on stream since the year 2000. Evidence

from the interviews suggests that the influence of these policies is being felt locally.

While this was the stated position in the interviews, such claims will be further tested

with reference to the three case study areas.

7.3. Cases Where Output Data Was Not Available

There were projects where there was a general rather than a specific direct causal

link between new development and the presence of the roads. These tended to be

the longer road upgrade works, particularly in County Kildare for the R406 / R407

Regional Road improvements linking Kilcock, Maynooth, Barberstown Cross, Clane

and Sallins. These roads did not have quantified deliverables in the form of housing

units or land hectares when selected at the outset. Rather, they were chosen on the

basis that they would facilitate general development in the main towns along the

106

route. During the interview, the Kildare local authority officials noted that these roads

contributed in a general sense to the development of the county.

Based on the most recently available census data, between 2002 and 2006 the

population of Clane increased by 12.5%, Kilcock by 49.6% and Sallins by 30.3%, so

development has occurred. The local authority also cited significant increases in

traffic volumes as an indicator that development in these areas had taken place, and

that the roads were necessary to facilitate access to the occupants of new residential

developments. The available traffic count statistics collated as part of this review

point to a huge growth in traffic in a relatively short period of time. This was most

likely caused by major development in towns along the R406 / R407 Regional

Roads. The data is set out below.

Table 7.1. Summary Traffic Count Data for the R406 / R407 Kildare Projects (6 in total)

Project Title Daily Traffic* (Year of Count)

Daily Traffic* (Year of Count)

% Change

Sallins to Clane (Blackhall Junction)

12,923 (2007)

8,844 (2003)

+ 46%

Sallins to Clane (Blackhall Stud) 17,000 (2007)

Figure

extrapolated from traffic data

12,786 (2005)

+33%

Clane to Kilcock (South)

Clane to Kilcock (North) Counts apply to both projects.

6,821 (2007)

4,930 (2005)

+38%

Barberstown Cross to Maynooth

Barberstown (south of Taghadoe Cross)

Counts apply to both projects

13,987 (2007)

7,623 (2003)

+83%

*Based on AADT – Average Annual Daily Traffic figures.

To put these figures into perspective, the National Roads Authority‟s long term traffic

forecasts for the period 2002 to 2040, estimate that future traffic growth on the

State‟s non-national routes will be 43% for cars and light goods vehicles over that

entire 38-year period (NRA, 2003, p.3). What effectively has happened on some

parts of the network in Kildare, is that a full generation of traffic growth has occurred

in less than four years. The traffic volume figures convey something of the

unprecedented development pressures facing County Kildare. Similar pressures

were prevalent in County Meath. Had the R406/R407 roads not been upgraded as

107

part of the Programme, it is unlikely that they would be able to cope with increasing

traffic volumes. The consequences would likely have been felt through a

deterioration of the surface, worsening safety performance and increased journey

times. The traffic volumes being carried on these roads are well in excess of what is

seen on many of the major national routes17, although they do not have access to the

more substantial funding streams that support the national network. This was a key

reason why the Programme funded these roads, in spite of them not having

measurable deliverables in the form of housing and development lands. In other

words, the roads needed to be upgraded, but local funding sources were insufficient

and other national exchequer sources were unavailable.

Based on the traffic volume data, it is possible to say that expenditure was justified

and necessary with reference to demonstrated needs. However, questions can be

raised about levels of car-dependency and the implications for sustainability.

7.4. Industrial and Commercial Sites

Through the interviews with local authority staff it became apparent that there was a

different dynamic at play in the development of the industrial and commercial sites

when compared to the housing-focused projects. Local authorities can‟t in their own

right directly influence decisions on industrial and commercial jobs. However, they

do have an important role, particularly in the facilitation of zoned lands, and in the

provision of services and infrastructure. These are a prerequisite if industrial

development sites are to be provided in sufficient numbers and at appropriate

locations. This role is specifically recognised in the National Spatial Strategy. To

help explore these issues, the owners of two industrial parks developed on foot of

the Programme were interviewed. A meeting was also arranged with a senior

manager from IDA Ireland.

Based on the views of local authority staff, there appeared to be a strong level of

interaction between the developers of the industrial sites and the local authority.

This applies in the case of relationships with public bodies (IDA Ireland), and private

companies in the development of business parks (Park West in Dublin and

Millennium Park in Naas). Such an interactive approach is recommended in the

2007 guidelines issued by the Department of the Environment (DEHLG, 2007b,

p.26). As an example, in the case of the Parkmore Road, which facilitated the

17 Full year-by-year NRA traffic count data on the National Roads network is contained on: www.nra.ie/NetworkManagement/TrafficCounts/

108

extension of an IDA business park, Galway City Council described how both they

and the County Council met with IDA Ireland and were being encouraged to upgrade

the roads in the area in order to facilitate existing companies and to allow for an

extension of the business park to attract new companies. The local authority noted

that when they moved ahead with the road upgrade, the IDA announced additional

jobs for the site.

The manner in which business and industrial sites are selected and developed is

also relevant to the review. It has implications for the provision of roads

infrastructure. Key local factors informing the choice of location are the accessibility

of the site, the availability of local authority services and the availability of sufficient

lands for development. The IDA official noted that key requirements in selecting

sites are: roads, water, waste, electricity and gas.

The role of roads is crucial to the site selection process in two distinct, but

interrelated, ways. The roads provide access to the site and make it viable as a

location in the first place. In addition, the roads are a crucial element in the decision

of a company to locate there. This manifests itself through the improved accessibility

to suppliers and customers. Increasingly, the ability to recruit from a sufficiently large

and accessible workforce is a vital factor in location decisions. A key determinant

here is the quality of the transport infrastructure. How such factors influence the

marketing strategies of business parks and the location decisions of companies are

examined in more detail later in the case study areas. A further noteworthy point

raised by IDA Ireland is that ease of access for key overseas parent-company staff

visiting their sites in Ireland is a significant and growing issue, particularly in the high

tech and services sectors.

The centrality of roads funded under the Programme in facilitating industrial lands

was most clearly demonstrated with Phase 1 of the South Dublin Outer Ring Road,

which opened up the Grange Castle Business Park. This is a facility run by IDA

Ireland and South Dublin County Council. One of the major companies located at

the site (with more than 1,000 employees) is the international biotechnology

company, Wyeth. According to the local authority, one of the requirements set down

by the company in selecting that location was that the Outer Ring Road be put in

place. They viewed the access provided by the road as being crucial to their

operation.

109

In the case of the Millennium Business Park in Naas, the developer part-funded one

section of the ring road in order to open up the site. In the absence of the

commitment from the Department and local authority to fund the remaining sections

of the road, the owners of the site (Osberstown Developments), were of the view that

the park would have been curtailed. Accessibility via the new ring road is cited by

the company as a key attraction of the site, and in the decision by companies to

locate there. Again in this case, the road was needed to open up the site, and the

presence of the roads is cited as a key factor in making the site accessible and

therefore attractive to client companies. In March 2008, there were 757 people

working in the business park. With further companies in the process of taking up

vacant units, this was expected to rise to 1,000 by mid-2008. The Masterplan for the

area which links in to the local authority Development Plan sets out a long term goal

of having 12,000 jobs based at the site, with 8,000 residential units. The developers

estimate that within 7 years, 6,000 jobs will be located on the site and 3,000 of the

residential units will be occupied.

One way of assessing the economic benefits flowing from these new industrial and

commercial parks would be through the impact on job creation in an area. However,

it should be recognised that there are a number of inter-related factors that go into

decisions on the location of business parks and subsequent uptake of units by

companies. In the case of infrastructure, roads are only one element. In attracting

foreign direct investment, location decisions are also influenced by the presence of

incentives, not to mention macro-economic tax policies, amongst a range of other

factors. In the case of the Programme under review, it would inappropriate to

ascribe all employment flowing from the development or extension of business parks

to the presence of the new roads. However, roads have played a crucial role in

opening up sites. In the case of Grange Castle (South Dublin), Park West (Dublin

City) and the Millenium Park (Naas), had the roads not been built or upgraded,

additional employment accruing to the areas would have been severely curtailed or

would not have happened. These roads can therefore be seen as effective in

meeting the objectives of the Programme.

One of the larger projects funded was the Celbridge Interchange with the M4

motorway in County Kildare. Over €22m was provided against a total cost of almost

€45m. The basis for its inclusion in the Programme was to support development in

Celbridge and Leixlip, and specifically to facilitate the expansion of two of the major

multi-national companies in the State; Intel and Hewlett Packard. A specific stated

110

intention of the local authority in developing the project was to facilitate a motorway

access for these two companies. The needs of both companies were articulated in

meetings with the local authority. The project consisted of a full interchange and 3.8

kilometres of associated roads serving Celbridge, Leixlip, Intel and Hewlett-Packard.

A further €496k was expended under the Programme to part-fund separate road

improvements around Intel. These were to facilitate access and egress from the

Intel facility at Collinstown. Both Intel and Hewlett Packard contributed to the

Celbridge Interchange by way of direct contributions. Special Development

Contributions totaled €2.69m with a further €8.55m coming from General

Development Contributions. Given that a link was being provided to the National

road network, the NRA provided €11.63m.

Since completion of the interchange, the planned expansion of Intel did go ahead,

with the announcement in 2004 of a new fabrication plant to manufacture its „Fab24-

2 Wafer‟. The cost of the plant was estimated at the time to be €1.6billion. It opened

in 2006. The company now employs over 5,000 people directly and indirectly in

engineering, technical and operational activities In the case of Hewlett Packard, in

2004 it established a Strategic Research and Development Centre at its site in

Leixlip, with a €21.4m investment in its Inkjet Manufacturing Operation, which

employs 1,800 people (DETE, 2004). In March 2006, Hewlett-Packard Financial

Services announced the expansion of its headquarters in Leixlip, with the creation of

110 high value financial services jobs. The jobs were in addition to the 250 people

already employed by HP Financial Services in Leixlip. Hewlett Packard as a whole

employs more than 4,000 people in Ireland (IDA, 2006). Although the Celbridge

Interchange and the smaller project to support the additional Intel roads did not

included measurable deliverables either at the outset or in the questionnaire

submitted for the review, there is evidence that the roads have been effective. The

main reason the roads were funded under the Programme was to facilitate the

expansion of Intel and Hewlett Packard. This has happened. While the upgraded

roads were a factor, they were one of a number of contributing influences. While

there were more significant reasons guiding investment decisions and the expansion

of the companies, the roads infrastructure funded under the Programme played a

role.

This chapter has so far looked at the wider effectiveness of the Programme, with

reference to the experience of individual projects. This is now taken a step further by

111

looking at the three case study areas. This allows for a more in-depth analysis of

how the effects of the road infrastructure are being felt on the ground.

7.5. Case Study - Tramore, County Waterford

Tramore is located 13km (8 miles) to the south of Waterford City. It is a traditional

seaside resort that in recent years has been attempting to diversify its commercial

base from an over-reliance on tourism. Phases 4 and 5 of the Tramore ring road

were funded under the Programme. Its deliverables were focused mainly on

housing. To explore the relationship between the roads infrastructure and the

construction of housing, interviews were conducted with two of the building

companies responsible for almost all of the housing development along the new

parts of the ring road. One reason for adopting this approach was to provide

independent corroboration of the claims made by the local authority that the roads

were indeed crucial to facilitating development in the area. A further consideration,

as noted earlier, was that there is a lack of information on how developers operate

and how they make decisions on housing supply.

One interview was conducted with John and Pat McDonald, Directors of „R

McDonald & Sons Ltd.‟, Building Contractors. Their company was responsible for

around 85% of housing construction along the new ring road. The second interview

was with William Bolster, Managing Director of Bolster Construction. His company is

currently constructing 18 housing units at a site on the Tramore ring road. Bolster

Construction is also completing 180 housing units adjacent to the Waterford City

Outer Ring Road, which was also funded under the Programme. These

developments form part of the quantifiable outputs for the two projects. Both

interviews were held in the offices of the respective companies and lasted around 1

hour each.

Based on the interviews, the roads entered the supply decision on the part of the

builders in two distinct ways. The first was through the planning requirement to have

the roads in situ (or under construction) before development could proceed. The

presence of roads infrastructure is also important in conferring a comparative

advantage on one location over another when it comes to selling houses. The

likelihood that housing units will sell is a crucial determining factor in the housing

supply decision, a point on which both sets of interviewees were in agreement. To

illustrate the point, one interviewee said that when developing a site, he would be

willing to pay more for lands that were serviced by roads and that were accessible.

112

In such circumstances he is more likely to be able to recoup the costs and turn a

profit, because potential purchasers would also be willing to pay for the location. In

economic terms the effects of roads infrastructure are ultimately felt in the property

market through accessibility. The quicker one can get to work or other locations, the

more attractive the site. At a more basic level what the interviews show is that the

claims of the local authority about the central role played by the roads in facilitating

housing development are substantiated by the developers.

The extent to which the development of Tramore is being properly planned was

examined with reference to the Local Area Plans for the town. The two most recent

plans cover the respective periods from 2003 to 2009 and 2008 to 2013. Both plans

were framed in the context of the National Spatial Strategy and the Regional

Planning Guidelines for the South East. These are set out as overarching principles

in the opening paragraphs. Under section 4.6 of the National Spatial Strategy,

Tramore is identified as a town that can provide a good base for population and

services which will attract investment and employment activities additional to those of

Waterford (DEHLG, 2002, p.83). In the Regional Planning Guidelines it is seen as a

larger town which is to be strengthened (SERA, 2004, p. 30). In fact, the presence of

Waterford City nearby is seen as both an advantage and something of a hindrance.

Tramore has traditionally been a dormitory town of Waterford City, although the 2003

plan states clearly that this is unsustainable (WCC, 2003, p.6). The main challenge

flowing through the two successive Plans is to facilitate the long-term development of

the town, and to move it towards self-sustainability.

There is evidence in the development plans of principles of good planning being

adopted. Lands are being zoned and developed in a logical sequential fashion

moving outwards, as sites closer to the town centre are developed. This can be

seen as a means to address the phenomena of „doughnut development‟ and

„leapfrogging‟. In fact „leapfrogging‟ is identified as something that is to be

particularly avoided (WCC, 2007, p.34). The interviews with the developers

confirmed that this is what is happening in the implementation of planning policy and

decisions. This overall approach is in line with Guidelines issued by the Department

of the Environment (2007b, p.35).

The provision of services for water is preceding new development. The view of the

two developers was that there is good co-ordination in the provision of roads and

water services to facilitate development. In the case of Bolster Construction, the

113

situation in Tramore was contrasted with that at the Outer Ring Road site. The view

was expressed that that the provision of some services was delayed here, and this

caused problems. Both development companies stressed the importance of co-

ordination in the delivery of local authority services to allow development to proceed

in a timely and planned fashion. This supports the idea that a lack of co-ordination

can lead in extreme cases to a form of market failure. This was an issue identified in

the Barker Report in the UK.

The challenge facing Tramore in achieving self-sustainability should not be

underestimated. Based on the most recent Census, its population increased from

8,305 in 2002 to 9,634 in 2006. Given that most of the housing development in the

town in that period was based around the ring road, it played a key role in facilitating

the rise in population. The Census also confirms the current position of Tramore as

being predominantly a dormitory town. By using the „distance travelled to work‟ as a

proxy, the census data shows a fairly consistent commuting pattern between 2002

and 2006. Around 45% of workers travel a distance of between 10 to 14 kilometres,

which accords with the journey in to Waterford City. The 2002 distances were

measured in miles, but tell the same story.

Table 7.2. Tramore - Distance Traveled to Work 2006

Year Total

Number of

Persons

0 km 1 km 2 to 4

km

5 to 9

km

10 to

14 km

15 to

24 km

Over

25 km

Not

Stated

2006

3,797 0.7% 8.7% 8.2% 6.8% 45.1% 13.5% 6.4% 10.6%

(CSO, 2006, Vol. 12)

Table 7.3. Tramore - Distance Traveled to Work 200218

Year Total

Number of

Persons

0

miles

1 mile 2

miles

3 to 4

miles

5 to 9

miles

10 to

14

miles

Over

15

miles

Not

Stated

2002

3,178 2.3% 14.3% 3.5% 2% 44.5% 17.4% 7.6% 8.4%

(CSO, 2002, Vol. 9)

18 Based on the working population aged 15 years and over usually resident in the state and present in their usual residence on census night.

114

Other proxy indicators like the „time taken to travel to work‟ confirm the picture set

out above. Likewise, the predominant mode of travel is the private car, a further

indicator of unsustainable work and travel patterns. However, from a more

favourable perspective, the relative proportion of commuters has remained around

the same in recent years, in spite of a significant population increase. This is in

contrast with some parts of the commuter belt around Dublin which has seen a rise

in absolute and proportional terms. Given the long-term and pre-existing status of

Tramore as a dormitory town, it may be too much to expect that this trend would be

turned around in a few years.

There has been some progress in creating conditions conducive to attracting industry

to the town. The Local Area Plan sets out to achieve this objective through zoning,

infrastructure provision and promoting Tramore as a viable location (WCC, 2007,

p.33). The ring road is identified as a key element in providing accessibility to

potential companies locating in Tramore. An example is the Riverstown Industrial

Park at one end of the ring road. A new major access road to open up lands at the

site is currently under way (2008). According to the County Council, the rapid uptake

of sites in the business park is indicative of considerable demand for commercial and

light industrial units in the town. A visit to the area was undertaken as part of the

review and confirms that significant light industrial and warehouse development is

taking place. In addition, two major retail sites are also being developed, one in the

town centre and the other feeding off the ring road. According to the County Council,

both of the developments would not have been possible without the ring road. R

McDonald Ltd. is developing the site near the ring road, and this was discussed. The

development will include commercial retail outlets, ancillary infrastructure, and a

major new school to cater for the town‟s growing population. The 2006 Waterford

County Retail Strategy had noted that Tramore was underserved by retail outlets,

and that retail activity had declined by 3.6% between 2003 and 2006, in spite of an

increased population (ibid., p.34). Essentially, local residents were doing their

shopping in Waterford City. This trend is now expected to substantially reverse once

the new retail outlets open.

Whether all of this will be sufficient to achieve the stated objective of reversing the

commuting patterns remains to be seen. What is important from a sustainability

perspective in evaluating the impact of residential development on the Tramore Ring

Road, is that it didn‟t happen in a piecemeal fashion. The new houses were

accompanied in tandem by a strategy to create sustainable employment and

115

transport patterns, although the full impacts have not yet been felt. What can be said

is that the strategies are there for it to happen. This is indicative of a fairly standard

problem that arises in trying to evaluate the effectiveness of programmes. It is

difficult to assess the social and economic impacts after a relatively short period of

time. Based on the available evidence, the ring road has certainly facilitated

residential development. This was its primary objective, so from that point of view it

has been effective. The road is also contributing to the economic development of the

town. While it is too early to say what the long-term outcomes will be, there are

some positive indications that the stated objectives of the town development plans

have the potential to be delivered.

7.6. Case Study - Park West, Dublin 12

The realignment of the Kileen Road in Ballyfermot was funded under the Programme

in order to facilitate access to a major brownfield site, part of which was occupied by

the old Semperit tyre factory (which closed down in the 1990s). The whole site

measures 230 acres (93 hectares approx.). The Kileen Road is one of two access

points. When approved under the Programme the lands to be facilitated were

intended to be used for industrial and commercial purposes. However, they are now

also being used for residential development. This issue was examined already and

is notable from a sustainable development perspective. The role played by the roads

infrastructure in opening up the lands was discussed with the group of City Council

personnel. A meeting was then held with the developers of the Park West site,

Harcourt Developments Ltd., which was attended by the Manager of Park West and

two other representatives of the company. Two officials from Dublin City Council

also participated. The initial discussion with the City Council staff examined the role

of the road in facilitating development. The officials stated that the planning

permission for the development of Park West was contingent on the upgrade of the

Kileen Road (and the other access point at Cloverhill Road). Development at the site

was capped until the infrastructure was improved. The existing road was of

insufficient scale and there were serious safety issues.

Park West has been a huge success story. According to the developers, there are

currently 270 companies located there employing some 8,000 workers. However, in

assessing the effectiveness of the Killeen Road project it is important to recall that

when the site was being originally developed, the lands were considered marginal

from an economic perspective. The area wasn‟t seen as an attractive proposition,

being the site of an old heavy industrial plant and located in a disadvantaged area.

116

The provision of new roads infrastructure was seen as a means to open up the

potential of the lands. While hindsight has shown it to be a good investment, at the

time back in 2000 there was considerable risk involved. This point was made by

both the developers and the City Council. The contribution of the Department in

funding the road was seen as a form of risk sharing, and was key to the road going

ahead. From the perspective of economic theory, Barker notes that brownfield sites

in particular can suffer from market failures and that public investment in

infrastructure can be justified on the grounds that it unlocks wider social and

economic benefits (Barker, 2004 p.57). In the case of the Kileen Road there is

evidence that this was the case. The developers paid for 50% of the costs of the

Killeen Road works, with the Programme funding the other 50%. The developers

also contributed 60% of the costs of the Cloverhill Road improvements (which were

not part of the Programme). The local authority met the remainder of the costs. In

the early days of the development, tax incentives were also offered to businesses

locating in Park West. This reiterates the view that the site was considered as a

marginal location. It also justifies the reluctance within this review to attribute the

success of the site solely to the infrastructural development. Other factors also had

an impact.

Clearly, benefits have flowed from the development of the site. One way of

assessing them is in reference to the companies located there. In promoting Park

West as a business location, Harcourt Developments have created a series of

information and publicity publications. Within one of these, a series of three „case

study‟ companies were used as examples to demonstrate the advantages of the

location. While these materials are used for promotional purposes, they do offer

some useful information to show how benefits accrue to the companies and the staff

employed there.

„Hostings 365‟ is a technology company which provides internet infrastructure. It

states that the location allows the company to recruit from a wider range of areas

and pool of people. The Managing Director of this company also mentioned benefits

from shorter commuting times for employees and access to public transport

(Harcourt, 2007, p.27). What is interesting here is the fact that locational benefits are

felt through time-savings to employees, and through improved access for the

company to a wider workforce. These are seen as typical economic benefits which

are assessed in UK transport projects, especially ones affecting marginal and

brownfield sites (DfT, 2003, 3.5.8). Reduced journey times and improved

117

accessibility were also cited by the insurance company Allianz in its testimonial. In

the UK‟s transport appraisal guidelines, further economic benefits are assessed with

reference to improvements accruing to businesses in accessing their clients and

customers. This was specifically cited as a benefit by the third case-study company,

the Park West Clinic. It also mentioned the ability to expand its operation as being

important. This is also regarded as an economic benefit, in that it allows for the

expansion of economic activity and the creation of employment.

Transport infrastructure was highlighted in the discussion with the developers, and

seen as crucial in making the site both accessible and attractive. This infrastructure

includes both the roads network and public transport. The Kileen Road was and still

is a key artery allowing access to the site. In recent years there has been a strong

emphasis on public transport. Work is currently nearing completion on a new train

station serving Park West. The level of planned, co-ordinated and integrated

development which is taking place can be seen as a positive outcome. The

development of the area is based on the „Park West / Cherry Orchard Urban

Framework Plan‟ (McDermott Norton, 2002). It sets out structuring principles

detailing how different parts of the site should develop. There is a strong level of

integration with public transport provision. In setting the planning context for the

framework plan, a number of key policy documents are identified. These are the

National Sustainable Development Strategy, the Strategic Planning Guidelines for

the Greater Dublin area and the Department of the Environment‟s Residential

Density Guidelines.

Based on the different information sources, it is possible to identify in overall terms

how economic benefits have arisen from the Kileen Road project and the

development of Park West. The roads played a key role in opening up the site. Park

West has generated considerable employment and led to the construction of

integrated residential and commercial development. It would be an inaccurate over

simplification to state that all of the employment generated in Park West flowed from

the roads investment. However, the funding provided under the Programme was

crucial in what was then a risky decision affecting a marginal site. For those

companies now located in Park West, the economic benefits are particularly felt

through locational impacts, which are also dependent on transport infrastructure.

These benefits accrue to companies through improved access to its workforce and

customers, and by providing the scope for future expansion. These benefits were

also identified in the next case study area of Naas. These are standard economic

118

benefits used in the appraisal of transport projects. While limitations on time and the

scope of the review precluded the systematic calculation of these benefits, their

presence can be seen as an indicator of effectiveness in the assessment of the road

investment.

7.7. Case Study - Naas, Co. Kildare

Three separate sections of the Naas Ring Road were funded under the Programme:

Newbridge Road to Kilcullen Road to Craddockstown Road (1,850 metres)

Newbridge Road to Caragh Road (450 metres)

Industrial Estate - Millennium Park (1,800 metres).

These were intended to facilitate residential, as well as industrial and commercial

development. Rather than looking at these roads individually, the review will look at

the overall social and economic impact on Naas. While measurable outputs were

provided in the questionnaire returns for the projects, the three new roads are having

a significant impact on the entire town and not just in the areas where the roads are

directly located. This point was specifically mentioned during the group discussion

involving local authority officials. The Naas Town boundary extends to a radius of

1.5 miles (2.4km) from the centre and covers some 1,831 hectares (NTC, 2005, p.2).

The social and economic impacts can be examined with reference to Census data

and changes in the characteristics of the town. Two of the three projects were

completed in 2006, while the third was finished in March 2008. While it would be too

early to assess longer-term impacts, it should be possible to detect some emerging

trends. Most of the current and planned major development in Naas is taking place

around the ring road, or is predicated on its presence. For example, in addition to

the development on the ring road, the diversion of traffic has allowed a major 43-unit

commercial development at Corbin‟s Lane in the town centre to proceed. However, it

must also be recognised that the new roads, although crucial to the town‟s

development, are one of a number of contributing influences. At an infrastructural

level, the presence of the M7 motorway and the nearby rail link from Sallins to Dublin

are key factors.

The relevant local authority Development Plans for the town were used as an

important reference point. The two most recent development plans for Naas cover

the periods 1999 to 2004, and 2005 to 2011, respectively. Under the Regional

Planning Guidelines for the Greater Dublin Area, Naas (along with Newbridge and

Kilcullen) is classified as being a ‟Primary Dynamic Cluster‟. It is envisaged that the

119

cluster will attract employment and be economically self-sustaining. Naas is seen as

„Large Growth Town – Category 1‟ (D&MRA, 2004, p.70).

In a manner similar to the Tramore case study area, Naas has traditionally been a

dormitory town, albeit on a far larger scale given its proximity to the capital city. It too

is attempting to establish itself as a self-sustaining entity. While improved transport

infrastructure was seen as contributing to the position of Naas as a commuter town,

it was also seen as a means to develop the town in its own right based on its location

and transport links. As the 1999 development plan stated:

“Naas has tended in recent decades to develop as a dormitory town for the

greater Dublin Metropolitan Area - a trend that is continuing as a result of

improved transportation links, - it is important that it also develops as an

independent integrated community with necessary support services located

at the strategic intersection of the N7 and N9” (NUDC, 1999, p.8)

Of particular relevance to the review is that the 1999 Development Plan set out plans

for the future residential and economic growth of the town, including a system of

distributor ring-roads linking the main radial arteries coming into Naas. These roads

were submitted as applications under the Programme. The roads therefore were

part of an overall plan to facilitate economic development. In order to improve the

economic position of the town, the Plan identified the need for three distinct types of

industrial development:

Manufacturing and warehousing / distribution.

Specialist Manufacturing of a high-Tech type.

Tertiary services. (ibid., p.12)

The 2005 plan built upon this objective. As part of its strategic contribution to

attracting industry and employment the local authority placed its emphasis on the

provision of infrastructure. As the Plan states:

“Emerging policies favour the switch from subsidies and grants to

investment in infrastructure because it is considered to be more

effective and offers better value for money over the long term” (NTC,

2005, p.18)

This is in line with the overall economic policy for the region contained in the

Regional Planning Guidelines, which is to relieve supply constraints in relation to

120

infrastructure and some categories of labour (ibid. p.21). It is within this context that

the local authority has sought to invest money in roads. There was a twin objective

to facilitate the anticipated population growth of the town in a planned fashion, and to

create conditions conducive to attracting business and industry.

The first part of the ring road to commence under the Programme was the section to

open up the Millenium Business Park at Osberstown. It started in June 2004 and

was completed in November 2006. Based on the questionnaire returns, it has

opened up almost 103 hectares of commercial lands and 7.5 hectares of residential

lands. A site visit to examine the extent of the development was undertaken in

January 2008 as part of the review. A meeting was also arranged with the owners of

the site, Osberstown Developments Ltd. Considerable development has taken place

there, and it is now the location of an expanding business park. There are currently

14 companies and organisations based there. In March 2008 there were 757 people

working there. These include companies providing IT and engineering services,

financial and business services as well as public sector organisations. These are the

types of companies that the 1999 and 2005 Naas Town Development plan set out to

attract. The owners of the business park are also developing a separate part of the

site which is being termed the „Gateway‟. This has a particular target to attract

technology companies.

Based on the discussions with Osberstown Developments, the land and housing unit

outputs reported by the local authority may have erred on the side of conservatism.

The developers of the park envisage that up to 3,000 residential units will be in place

at the site within 7 years, with a longer term aim of 8,000 units. For the time being,

the estimates from the local authority are still used as the baseline in the review.

The attractiveness of the location and its comparative advantage over other sites

hinges on the presence of transport infrastructure. The developers cite accessibility

as a crucial selling point. Economic theory in the area of transport posits that

benefits flowing from the infrastructure are felt through improved access by

companies to suppliers, customers and its workforce. In the case of the workforce,

the owners of the park have carried out research to measure the effects. The

businesses that have relocated to the park from other sites have reported that the

per annum turnover rate of staff has fallen from between 33% and 35% to

approximately 10%. The location is more accessible for staff who would previously

have commuted longer distances. The easier access to their place of employment

121

makes it less likely that they will change jobs. This has resulted in direct monetary

savings for the companies involved. The companies have also reported to the

owners of the park, that the salary packages needed to attract staff do not need to be

as high as those for Dublin City locations. For the workforce, the cost of travel to

their place of work is reduced (both in terms of time savings and direct costs). On a

more intangible level, the site developers also claim that the lower turnover of staff is

indicative of improved job satisfaction. Based on the information provided by the

business park developers it is possible to say that substantial economic benefits

have arisen from the business park. The road was crucial in allowing the park to be

developed, and in making it attractive as a location for companies. However, it is not

possible to say if the benefits outweighed the costs.

Ideally the economic benefits of the new roads would be measured by way of a cost

benefit analysis. The original 1983 motorway bypass around Naas was assessed in

this way (Barrett & Mooney, 1984). The 1999 Naas Development Plan noted that

many of the benefits from improved traffic flows through Naas arising from the

opening of the first bypass in 1983 were eroded through traffic growth in the town.

The new ring road funded under the Programme has again helped alleviate

congestion problems. However, in order to quantify and monetise these benefits,

certain types of data are essential.

The availability of traffic count and origin-destination surveys was discussed with the

local authority. A major data gathering exercise is currently under way to map traffic

patterns around Naas. Some of this data is available. What is lacking is an earlier

body of data for these specific roads against which the current data can be

compared. We know that current AADT traffic figure for the Newbridge Road to

Caragh Road section is 5,538 vehicles, with HGVs accounting for 6.2%. On the

Millennium Business Park section of the ring road the AADT is 12,098 vehicles,

comprising 4.7% HGVs. These are based on traffic counts from January 2008.

Origin, destination and travel time surveys are also being carried out. These are the

essential data sources in calculating time saving for cost benefit analysis. Time-

savings constitute the vast majority of benefits in transport CBA. However, the local

authority has said that a comparable body of data from before the road was built is

not available. It is therefore not currently possible undertake a cost benefit analysis

as part of this review. What is becoming clear is that with some additional forward

planning, it should be possible in future to have full data sets available that would

allow for the ex-post and ex-ante calculation of costs and benefits. For example,

122

there is currently a proposal to build a new interchange onto the M7 motorway to

allow access to the Millennium Park / Osberstown development. This is being

subject to a full cost benefit analysis, and original data is being gathered for this

purpose.

Where the scale of future projects is sufficient to justify the expense and effort,

modifications in how data is gathered should make it possible to carry out a

quantitative assessment of cost and benefits for local and regional roads. This is

notwithstanding the problems arising in the case of urban projects with more

complex traffic patterns, and situations where there is substantial induced traffic.

These issues were discussed earlier. In any event, if the 2007 Department of

Transport capital appraisal guidelines are adapted for local and regional roads (as

this review proposes), Multi-Criteria Analysis will require the quantification of

benefits. The practical application of these guidelines is a major focus in Chapter 9.

Based on the evidence provided by the owners of the Millennium Business Park, the

Naas Ring Road specifically facilitated sites that have allowed new companies to

locate there. The ring road is also facilitating the construction of new housing units.

This is in line with the overall planning and development objectives for the town,

which were restated most recently in 2005 Naas Development Plan. It describes its

Strategic Goal as being:

“To improve the access of the existing and future labour force resident

in Naas to employment, and to make Naas a first choice location for

indigenous and foreign direct investment by developing, through the

effective and efficient deployment of resources, a location that will

attract and sustain indigenous and foreign direct job-creating

investment” (NTC, 2005, p.23)

According to the 2006 Census, the current population of Naas (including suburbs or

environs) is 20,044. This has risen from 18,288 in 2002, (an increase of 9.6%). The

population in 1996 was 14,074. The overall increase in 1996 to 2006 period was

almost 30%. While this appears to be quite high, it is in line with planning projections

contained in the recent town Development Plans, which were respectively planning

for a population of 23,000 by 2003 (NUDC, 1999, p.7), and 27,000 by 2011 (NTC,

2005, p.15). The population growth therefore could not be described as „unplanned‟,

which was an original criticism leveled at a lot of development in the Greater Dublin

Region. Given the town‟s role as envisaged under the National Spatial Strategy, its

population is likely to grow even further.

123

An indicator of sustainability is the extent to which those living in Naas actually work

there. The distance traveled to work can be used as a proxy for assessing level of

commuting. Trends between 1996 and 2006 are detailed in tables 7.5, 7.6 and 7.7,

below. Given the changeover from miles to kilometers, there are difficulties in

drawing precise comparisons, however some observations can be made.

Table 7.4. Naas - Distance Traveled to Work 2006

19

0 km 1 km 2 to 4 km

5 to 9 km

10 to 14 km

15 to 24 km

Over 25 km

Not Stated

Number of Persons

10,086 54 892 1,831 771 751 1,348 2,770 1,669

Percentage 100% 0.5% 8.8% 18.2% 7.6% 7.5% 13.4% 27.5% 16.5%

(CSO, 2006, Vol. 12) Table 7.5. Naas - Distance Traveled to Work 2002

0 miles

1 mile 2 miles 3 to 4 miles

5 to 9 miles

10 to 14 miles

Over 15 miles

Not Stated

Number of Persons

8,602 166 1,427 778 441 798 828 3,586 578

Percentage 100% 1.9% 16.6% 9.1% 5.1% 9.3% 9.6% 41.7% 6.7%

(CSO, 2002, Vol. 9)

Table 7.6. Naas - Distance Traveled to Work 1996

0 miles

1 mile 2 miles 3 to 4 miles

5 to 9 miles

10 to 14 miles

Over 15 miles

Not Stated

Number of Persons

6,162 308 1,188 593 294 512 486 2,285 496

Percentage 100 5% 19.3% 9.6% 4.8% 8.3% 7.9% 37.1% 8%

(CSO, 1996, Vol. 6)

Between 1996 and 2002 there was a big increase in the number of commuters

traveling a distance greater than 10 miles to work every day. The most significant

figure from the 2006 data is the apparent decline in both the number and percentage

of people traveling longer distances. In 2002, 51.3% of workers were traveling 10

miles or more to work. In 2006, 40.9% were traveling a roughly equivalent 15

kilometres or more. However in the 2006 data there was also a significant rise in

persons who did not state a distance traveled to work. This could be a confounding

factor. The proportion of those traveling shorter distances remained broadly the

same, with 27.5% traveling a distance of less that 4km in 2006, and 27.6% traveling

2 miles or less in 2002. This broadly matches the extent of Naas and its suburbs.

Between 2002 and 2006, there was an increase in the numbers traveling medium-

length journeys.

19 Based on the working population aged 15 years and over usually resident in the state and present in their usual residence on census night.

124

Taking a longer-term perspective, between 1996 and 2006, the numbers of people

working in and around Naas (within a the distance threshold of 4km or 2 miles),

increased in absolute terms from 2,089 in 1996 to 2,371 in 2002 and to 2,777 in

2006. The data indicates that jobs are being created in Naas, and are being filled by

people living in, or moving to the area. While these jobs are keeping pace with the

population growth of the town, they are not exceeding it to any great extent.

The significant numbers who in 2006 did not state their distance traveled to work limit

any definitive observations on the available data. Notwithstanding this, the trends

between 2002 and 2006 indicate that, at worst, levels of commuting and distances

traveled have proportionately remained fairly static. However, Naas is still very much

a commuter town. If the analysis of Osberstown Developments is correct, there is

scope to encourage these people to work closer to home. However, as Morgenroth

noted in his analysis of the Greater Dublin Region, a crucially important determinant

in the attractiveness of a location to industry is socio-economic profile of the

workforce in an area (2001, p.64). Table 7.7. profiles the Labour Force in Naas,

making comparisons with the Greater Dublin area and the State.

Table 7.7. Naas - Labour Force by Social Class - Comparison with the Greater Dublin Area and the State. Professional

Workers Managerial

and Technical

Non Manual

Skilled Manual

Semi Skilled

Un- skilled

Others

Naas 858 3,354 2,079 1,759 1,656 458 1,130

Naas (%)

7.6% 29.7% 18.4% 15.6% 14.7% 4% 10%

Greater Dublin Area (%)

9.3% 28.9% 20.6% 15.1% 11.2% 3.9% 11%

State (%)

6.9% 26.3% 20.1% 19.4% 13.7% 4.8% 8.8%

(CSO, 2006, Vol 8)

In comparison with the Greater Dublin Area and the State as a whole, Naas has a

higher proportion of its workforce classified as „Managerial / Technical‟ and „Semi

Skilled‟. In comparison with the Greater Dublin, it has fewer „Professional Workers‟,

but has an advantage in the „Skilled Manual‟ category. These are key skill

categories in attracting and retaining industry. This data suggests that the town‟s

resident workforce is an asset in positioning Naas to take advantage of economic

opportunities. The level of educational attainment achieved by the population is a

further indicator here, and it detailed in the table below.

125

Table 7.8. Naas - Highest level of educational attainment, as a percentage of the population aged 15 and over.

3rd

Level (Non Degree)

3rd

Level (Degree of Higher)

Total Third Level

Naas (Persons) 1,650 3,389 5,039

Naas (%) 10.5% 21.6% 32.1%

Greater Dublin Area (%)

8% 21.5% 29.5%

State (%) 8.9% 15.6% 24.5%

(CSO, 2006, Vol.10)

Relative to the Greater Dublin Area and the State as a whole, Naas has a higher

proportion of third level graduates, which again make it attractive as a location for

business. This review is particularly interested in the extent to which the

development of the town in recent years has changed the socio-economic profile of

the population. Table 7.9 is also based on Census data and compares data from

1996 and 2006.

Table 7.9. Naas – Population Classified by Socio Economic Group 1996 – 2006

Employers

Managers

Higher

Profess.

Lower

Profess.

Non

Manual

Manual

Skilled

Semi

Skilled

Un

skilled

Own

Account

Workers

Farmers Agri

Workers

Others Total

2006 2,797 1,107 1,887 3,169 1,544 1,505 491 524 49 69 2,563 15,705

1996 1,912 754 1,252 2,586 1,248 735 467 446 72 90 901 10,463

(CSO, 2006, Vol. 8), (CSO, 1996, Vol. 7).

The most significant change was in the category described as „others‟, which has

skewed the table and limited the use of percentage-based data to make comparisons

between the two data sets. What is clear is that there has been a shift away from

unskilled and manual towards more skilled and professional categories. In absolute

terms the numbers of people in the six categories of Employer/Manager, Higher

Professional, Lower Professional, Non Manual, Manual Skilled and Semi Skilled

recorded large increases over the ten year period. This indicates that the economic

profile of the town, as reflected in its socio-economic composition of its population

has improved between 1996 and 2006.

This examination of certain socio-economic indicators has of necessity been limited.

As Morgenroth has demonstrated, a far broader analysis is possible. The indicators

used were also confined to limited geographical area covering Naas town and its

environs. Given the position of Naas within a „Primary Dynamic Cluster‟ that

incorporates Newbridge and Kilcullen, a wider perspective could easily be taken.

126

There are also growing urban areas in nearby Sallins and Clane, which would exert

some social and economic influences on Naas. However, the focus of the review is

on the effects of the 4.1 kilometres of new ring road that have opened up large tracts

of lands around the town and its immediate suburbs for development. Taking the

information provided by Osberstown Developments, significant employment is being

created in the area. With future plans for expansion, this is projected to increase.

The types of development being facilitated are in line with the objectives in the Naas

Development Plan and wider Regional Planning Guidelines. Population growth is

also consistent with stated planning objectives and the National Spatial Strategy.

The socio-economic profile of labour force in Naas compares well with the Greater

Dublin Area and the State as a whole. This provides tangible evidence to support

claims made by the developers about the potential of the location. The socio-

economic profile of the town has also been changing for the better in recent years.

The commuting patterns of the workforce may be stabilising to some extent, but are

still significant in overall terms. Based on views of Osberstown Developments, the

roads have been crucial making the Millennium Business Park viable in the first

instance, and then in attracting companies to locate there. The roads are also

facilitating additional housing, which in turn is a factor in the socio-economic changes

being experienced as the population expands. The roads have played a direct role

in opening up the development lands which have resulted in employment and

population increases. The roads can be said to have contributed to the resulting

socio-economic changes that are taking place among the population. However,

these are just indications. The real longer-term impacts will only become apparent

after some time.

The three case study areas have allowed for a more in-dept examination of issues

that were identified more generally in the earlier parts of this chapter. By their nature

many of the conclusions from the individual areas are unique and can not be

generalised. Their external validity is therefore limited. The case studies are

valuable nonetheless and have enabled the question of „effectiveness‟ to be

explored at project-level using a range of additional local data sources.

In order to be considered fully effective, the Programme should have contributed

something extra. It should have enabled roads and related development to proceed

that wouldn‟t have otherwise. The final section in this chapter will assess

effectiveness from this perspective.

127

7.8. The Counter-Factual

What Might Have Happened in the Absence of the Programme?

An important consideration in assessing the effectiveness of a programme is to

examine what might have happened in its absence. This provides what is known as

a „counterfactual‟ scenario. It is useful in assessing if „Deadweight‟ is present in the

form of projects that would have proceeded in any event. „Deadweight‟ is also

closely allied to concept of „Additionality‟, which describes outputs that would not

have occurred without the intervention. To complete a trilogy of related terms,

„Displacement‟ occurs when a programme output in one area leads to a loss of

output in another20. Effectiveness is enhanced when a programme can be shown

provide outputs and outcomes that would not have occurred.

Two different approaches were employed to deal with these questions. When

applications under the Programme were invited from local authorities in 2000, a total

of 117 projects were submitted, with 43 being approved. A self-completion survey

was undertaken with local authorities in respect of the 74 projects that were not

selected for funding, with a 100% response rate. During the interviews involving the

local authority officials, they were also invited to speculate on what might have

happened had the Programme not happened. They were asked if the selected

projects might have fully or partially gone ahead anyway.

In the questionnaire, local authorities were asked if the non-selected projects went

ahead. The results indicate that a significant number of projects drew upon

alternative sources of funding and did proceed. From the 74 questionnaire returns, it

can be ascertained that 38 projects went ahead, while a further 9 projects partially

proceeded. Therefore, based on the returns, a total of 47 went ahead in some shape

or form. 27 projects did not proceed. However from amongst this number a subset

of 9 can be identified where there is a stated intention to proceed at some point.

Table 7.10. Applications that were not Selected – Did the Projects Proceed?

Did Subsequently Proceed 38

Proceeded in Part 9

Did not Proceed 27

Total 74

20 The formal definitions of „Deadweight‟, „Displacement‟ and „Additionality‟, as they relate to Value for Money Reviews are contained in the Department of Finance Guidance Document (2007, p. 107-108)

128

A further issue of relevance here is the source of funding for the 47 projects that

proceeded in full or in part. The questionnaire asked: “What were the sources of

funding (i.e. own resources, development contributions, a different non-national

roads grant scheme etc.)”. The majority of the 47 projects that did proceed (26 in

total) went ahead with locally procured funds. 7 were funded from national-level

sources, while a further 14 had some combination of local and national funding. The

Department‟s Regional and Local Roads Division provided funding in some shape or

form for 16 schemes.

This data can be interpreted in different ways. At one level, it demonstrates a

considerable commitment on the part of the local authorities in funding important

regional and local roads projects. It has been a policy objective at Departmental

level for some time that exchequer funding should be augmented with locally

generated funds to the maximum degree possible. It also indicates that exchequer

funds weren‟t used to displace locally provided funds, and shift the burden of

responsibility for infrastructural provision to national government.

However, the data and interviews point to some deadweight within the Programme.

Clearly a considerable number of projects proceeded in any event, in spite of not

being chosen. It is reasonable to extrapolate that a number of the projects actually

selected under the Programme may also have similarly proceeded had they not been

approved.

The „counter-factual‟ scenario was discussed in each of the 15 interviews and group

discussions with local authority officials. When asked to speculate on what might

have happened in the absence of the Programme, their responses fell into three

categories:

1. The road could not have proceeded as the local authority was not in a

position to fund the costs involved.

2. It would have gone ahead at some point, but would have been delayed

for a number of years while alternative funding sources were found.

3. The road would have proceeded in a piecemeal fashion, based on

funding as it became available from development levies, or as developers

were prevailed upon through the planning process to upgrade stretches of

road.

129

Some of the discussions made specific reference to individual projects, while others

addressed the issue at a general level. However, the most commonly held view was

that in the absence of the Programme, a combination of responses number 2 and 3

(above) would have prevailed. Response number 3 was the most prevalent.

Nevertheless, a near unanimous view of those interviewed was that the larger of the

projects would have been severely curtailed and may not have proceeded at all.

These views are broadly consistent with the data drawn from the survey. For

example, Cork County Council in their interview speculated that some projects or

elements of them might have gone ahead within particular areas subject to the most

severe development pressures. However, they were also of the view that the larger

schemes would not have proceeded, or if they did, the County Council would have

had to apply to the Department for funding from another of its budget headings. This

view tallies with its returns from the survey. Cork County had 18 unsuccessful

applications, 11 of which subsequently proceeded in whole or in part. Of the 11,

each had an estimated cost of €2m or less (7 were under €1 million). The

experience of Meath County Council also supports this analysis. It had 13

unsuccessful applications, 4 of which proceeded. The 7 that did not proceed were

generally on a larger scale with estimated costs ranging from €1.3m to €26m (4

exceeded €13m). In its interview, Meath County Council said that if the Programme

was not in place, it‟s larger-scale projects that were selected, similarly would not

have proceeded. Making a related point, Waterford City Council noted that the final

cost of their Outer Ring Road project is the equivalent of two-thirds of the City

Council‟s entire annual budget, and could not have been met through local sources.

The identification of these examples of projects that are unlikely to have gone ahead

in the absence of the Programme offers evidence of „Additionality‟.

Dun Laoghaire Rathdown County Council had four unsuccessful applications that did

subsequently proceed. These had original estimated costs of €3.6m, €7.7m, €8.8m

and €29m respectively. However the four were either fully or part funded by national

exchequer sources. Although not selected under the Programme, they were

deemed to be important enough to be supported under other exchequer funding

mechanisms. From the 47 projects that did proceed, 21 in total ended up being fully

or part-funded through an alternative Departmental or other exchequer budget

heading. This suggests that the original programme may have been too limited.

Projects that were needed, but that could not be funded locally were delayed while

alternative exchequer sources were found.

130

The fact that a large number of initially unsuccessful projects went ahead along with

the successful projects suggests that „Displacement‟ wasn‟t a major issue. This

interpretation posits that in making exchequer funding available for the successful

projects, this freed up other local funds to enable more projects to be undertaken. In

other words, the Programme in some instances got „two for the price of one‟.

7.8.1 Planned Rather than Piecemeal Development

Based on the interviews and focus groups, a key benefit of having the Programme

was that it allowed for roads that were identified as strategically important in the

delivery of development to proceed as planned, rather than in a piecemeal fashion.

This was a common view expressed across the interviews. Essentially, without the

Programme the delivery of relevant sections of planned roads would have been

dependent on developers, rather the wider infrastructural needs as identified in local

county development plans. The Castletroy Distributor Road in the Limerick County

Council Area, for example provided a key component that links together other

sections of road that were provided by developers. It allowed the network to be

joined up, and to achieve improved overall traffic management benefits. In the

absence of the Programme, developer-provided sections may have been built, but

not the crucially important other parts that released the full benefit of the entire

network.

From amongst the projects actually selected under the Programme, one that is

amenable to speculation on the likely counterfactual scenario is the Corbally Link

Road in Limerick City. The view of the local authority was that in the absence of

exchequer funding, Phase I might have gone ahead, albeit on a more limited scale

and specification. An existing developer was keen to develop lands there. A cul-de-

sac road could have been built, with the sole beneficiary of the infrastructure being

the development in question. However, the project, as approved, involved two

phases. Phase II continued the link road with a canal bridge to open up further tracts

of land, and create a new access point into the city from the Limerick City suburbs

and County Clare. What this is saying, in effect, is that part of Phase I may

represent „Deadweight‟. However, without the Programme, significant additional

traffic management and development benefits would not have been achieved.

There are some further substantial points that were commonly expressed across the

interviews. Development levies were crucial in providing funds to enable many of the

originally unsuccessful infrastructural projects to proceed. The questionnaire data

131

supports this view. It should be noted that development levies in their current form

did not exist when the Programme was established in 2000. While the levies have

had a positive impact, the local authorities were at pains to point out that they are

insufficient in their own right. Each local authority had no difficulty listing current

priority projects that required exchequer funding to proceed.

Of its nature, seeking to establish a counterfactual scenario is speculative. There is

no way of knowing what might have happened in reality. Some observations can be

made however. Of the unsuccessful projects, two in five did not subsequently

proceed. The remainder did proceed in some form, but relied heavily on

contributions from developers. The Department acted as a key source in providing

funding. Other exchequer sources also contributed.

At the time of the announcement of the Programme the system of development

levies allowed for a far more limited scope to fund roads projects than is currently the

case. Development levies and other local funding sources on their own would not

been sufficient to fund larger-scale strategic roads projects. These can be seen as

„Additional‟. They wouldn‟t have gone ahead at all or to the same extent without the

Programme. Some may have proceeded in a limited and piecemeal fashion.

However, referring back to the earlier section which examined „Causality‟, the

delivery of development lands would have been curtailed. Based on the interviews,

the piecemeal development of projects would have impacted adversely on wider

development objectives, traffic management, and the provision of integrated road

networks.

Conclusions and recommendations arising from this analysis, and from earlier parts

of the chapter are now outlined.

7.9. Conclusions and Recommendations

This chapter has followed an approach consistent with the Programme Logic Model

in establishing links between the primary outputs in the form of roads, the secondary

outputs that comprise the housing units and development lands, and then the

outcomes in the form of the social and economic effects. Multiple indicators and

data sources have been used to describe outcomes that can be attributed to the

Programme. This is consistent with the „Contribution Analysis‟ approach advocated

by Mayne. Establishing the contribution of the roads in enabling development to

proceed is a vital element in assessing „Effectiveness‟. In the majority of cases, this

132

relationship can be identified with reference to data drawn from the local authorities

and the case studies. The role of roads is crucial in the development of industrial

and commercial parks in two distinct, but interrelated, ways. The roads provided

access to sites and made them viable as locations. They also make sites accessible

and attractive to potential companies who are seeking a good business location.

From the Tramore case study, which had a particular research focus on housing, the

roads entered the housing supply decision in two distinct ways. The first was

through the planning requirement to have the roads in situ (or under construction)

before development could proceed. The presence of roads infrastructure is also

important in conferring an advantage on one location over another when it comes to

selling houses. For the case study areas that examined the Park West and

Millennium business parks, economic benefits arising from the roads are felt in

improved accessibility. This manifests itself in a practical sense through reduced

journey times leading to time-savings for employees, and in improved staff retention

and salary savings on the part of the businesses. The ability to expand operations at

the new locations was also cited as a benefit by companies. While the roads are

contributing to the location-decisions of businesses, it would be inappropriate to

ascribe all of the benefits that arise. The contribution of the roads, although

important is one of a number of interrelated factors.

In Naas, the increased population and additional employment is impacting on the

social and economic profile of the town, however the long term effects won‟t be

evident for some time. From the three case studies there is evidence of sustainable

planning. This is based on interviews with the local authorities and developers, as

well as an examination of their local development plans.

At the outset of this chapter it was proposed to apply the „Hendricks‟ test. The

Programme set out to facilitate housing and development lands, and at aggregate

level has done this. Based on the available evidence, it is possible to conclude that

the Programme did indeed contribute to the key outcomes, and that these were

consistent with the original objectives. There are also credible indications that

additional social and economic benefits have occurred. There are two issues that

temper this generally positive assessment. The first concerns the delays that were

experienced in the delivery of projects. The second is the trend towards escalating

cost. This is the core focus of the next chapter. Before concluding the analysis of

programme „effectiveness‟, some recommendations can be made:

133

7. The case study areas in particular identified the importance of good integrated

and sustainable planning. This manifests itself through linkages with local,

regional and national planning policy objectives. The extent to which project

proposals are consistent with other policies should be a key consideration in

the future appraisal of strategic roads projects.

8. The review has found that a good deal of localised traffic count data is

generated by local authorities. When this data is being gathered, it is important

that it is done in a manner that will facilitate its application and use in the future

appraisal of road projects (through multi-criteria and cost benefit analysis).

9. „Additionality‟ in the Programme particularly arose with the larger projects.

There is a case that the newer Strategic Regional and Local Roads programme

should therefore focus on larger-scale projects that are consistent with wider

strategic development objectives.

134

Chapter 8

“Identify the level and trend of costs associated with

the Strategic Non-National Roads Programme and

thus comment on the efficiency with which it has

achieved its objectives.”

8.1. Introduction

Having considered the outputs and outcomes of the Programme in the two previous

chapters, this chapter will now look at the costs that were incurred in their delivery.

When evaluated against its original objectives, it is possible to say that at an

aggregate level, the Programme was effective when assessed in terms of its

outcomes. This is notwithstanding the variance in performance between individual

projects, and the key issue of time delays, which hampered delivery of outputs and

outcomes. The cost of delivering those outputs and outcomes is also a factor in

assessing effectiveness. The overall efficiency of the Programme will be examined.

Costs associated with the Programme arise in a number of different forms. At one

level, they can be assessed in terms of the exchequer commitment. Exchequer

funds were augmented by other sources, principally from the local authorities‟ own

resources. Development levies in particular have taken on increased significance in

funding roads infrastructure since 2000. Within the original application form, local

authorities were asked to break down estimated expenditure, making a distinction

between land costs and all other costs. Some comparisons can therefore be made

between projected and actual expenditure under these two main headings.

At the outset the Department committed itself to funding a maximum of 75% of the

original costs, with the local authority having responsibility for the remainder. This

figure could have been higher or lower and the reasoning behind the decision will be

examined. When the announcement of the Programme was made in June 2000,

there was an initial commitment of €190.46m (IR£150m). By December 2000 when

the projects were selected and announced, sanction was given to spend €247.6m.

Between 2001 and 2003 there were cost increases affecting a significant number of

projects, which put their completion in jeopardy. Following a review in late 2003, the

exchequer commitment was increased to almost €301m in early 2004. Since then, a

more limited number of projects have seen changes in their level of grant funding.

135

When all outstanding commitments are met the total grant expenditure is forecast at

€317.334m.

The increased grant commitments are a reflection of the increased costs that have

faced projects in the lifetime of the Programme. When the policy measure was

announced in June 2000, it was estimated that total project costs would be

€253.95m (including grant funding), although this was based on a fairly limited

indicative estimate. When the 43 projects were selected in December 2000, their

total estimated costs were reckoned to be €385.97m. By early 2004, total project

costs had been revised upwards and were estimated at €464.35m. When all 44

projects that currently comprise the Programme are complete, the total outturn costs

are estimated to be €584.917m, although this figure is likely to be higher. Some of

the individual project costs are based on estimates.

Table 8.1. Level and Trend of Total Project Costs and Exchequer Commitment 2000 to 2008

Year Total Estimated Project

Costs

Total Exchequer

Grant Commitment

June 2000 €253.95m €190.46m

December 2000 €385.97m €247.6m

April 2004 €464.35m €301m

January 2008 €584.917m*

(see notes below)

€317.334m

*Notes on Table 8.1

The Total Estimate Project Costs for January 2008 are based on total costs for the 44 projects that currently form part of the Programme.

Figures for the following projects are based on estimates: Carrigaline Western Relief Road (Cork County Council), Balbriggan Inner Relief Road and Naul Road Improvement Scheme (Fingal), Clane to Kilcock-South, Naas Ring Road to Craddockstown Road (both Kildare County Council), Duleek-Julianstown, Trim-Navan, R158 Trim-Kilcock (all Meath), Corbally Link Road - Phase II (Limerick County Council), Jamestown Road and Killeen Road (both Dublin City), Wicklow Town Port Access and Inner Relief Road.

The estimate for Clarkes Hill / Moneygourney Road (Cork County Council) is for construction costs only.

For the Midleton Northern Relief Road (also Cork), phase 1(a) was funded by the Programme. It was subsumed into a far larger project and an estimate is used.

The costs for the Oranhill Distributor Road (Galway) do not include works carried out by developers as part of a local agreement.

For the South Dublin Outer Ring Road Phase 1, aggregate cost data for the entire project was submitted. It was not possible to disaggregate the costs for individual phases, so the figure used here for phase I is an estimate, based on 2004 data. The actual cost is likely to be higher.

In addition, given that 13 projects are being completed in 2008 and beyond, there may be some further change in this total.

136

The Programme has also given rise to administration costs. These occur at a both

Departmental and local authority level and will be analysed. The construction and

upgrade of roads results in maintenance requirements, particularly the need to

rehabilitate the road at some future point. The review will calculate a cost estimate

for this work.

However, before examining the individual project costs in detail, the review takes a

step back in time. Decisions made in 2000 when the Programme commenced had

an important bearing on the level of exchequer funding commitment. This is the

focus of the first part of the chapter. This section then goes on to chart the level and

trend of exchequer commitments as the Programme proceeded.

8.2. - The Level and Trend of Exchequer Funding Over the Lifetime of the

Programme

8.2.1. Why 75% Exchequer Funding?

The amount of exchequer funding provided for individual projects was set at a

maximum of 75% of the original submitted costs (or 75% of the eventual expenditure,

depending upon which was lower). The balance was to be provided through the

local authorities‟ own resources, including from development levies, other private

sector contributions or contributions in kind (e.g. land). The decision to fund 75% of

costs represented a shift from the terms of the first (and smaller) grants scheme to

support housing, established in 1998 on foot of the first Bacon report. It had allowed

for a maximum of 40% of exchequer funding for individual projects, with 60% being

provided locally. Based on interviews with Departmental staff involved in setting up

the Programme, the reason for the shift to 75% was based on a concern that local

authorities would not be in a position to provide any more than 25%. Compared to

its predecessor, the current scheme involves projects of a larger scale, and it was felt

that a 60% local contribution would have been untenable. The first scheme provided

a relatively modest £5m (€6.35m) for 18 projects.

Local authorities were already contributing significant amounts of funding to the

„Pavement Restoration Programme‟ and other non-national roads works at that time,

so they were somewhat stretched financially. Departmental records indicate that

local authority contributions to these other programmes in 1999 and 2000 were

€108.6m and €123.3m respectively.

137

The obligation to provide a minimum 25% local contribution set the scheme apart

from another of the non-national roads programmes entitled the „Specific

Improvement Works Grants‟ Scheme which allowed for up to 100% funding of

approved projects. Its purpose was to support road infrastructure contributing to

balanced regional development and was co-financed by the EU as part of the

National Development Plan 2000-2006. However, it was decided not to provide

100% funding for the Strategic Programme. These roads projects were intended to

facilitate development, which in turn had the capacity to generate local levies to

contribute to costs.

An additional reason for having the 25% local contribution was to make local

authorities partly responsibility for costs. It was felt that this would encourage

stronger cost control and project management on the part of the local authority. This

would allow the Department to be less active in the micro-management of projects, a

function that it would have had difficulty fulfilling in any event because of limited

administrative resources21

. The choice of 75% as the threshold was not based on

any specific formula. Rather it was an estimate of the level of expense local

authorities could be reasonably expected to bear, whilst also ensuring that projects

would actually proceed. It should again be recalled that when the Programme was

announced, a less structured system of development levies was in operation.

A significant clause in the terms of the scheme was that grants were to be awarded

on a „fixed sum‟ basis. This condition placed the onus on the local authority to meet

any cost overruns, or additional work from their own resources. It effectively

transferred the risk from the Department. Given the prevailing economic and

inflationary conditions in the construction industry, there was a strong likelihood of

this risk being realised. There was something of a mixed outcome here. The

Department ended up breaching this rule in a number of cases, as can be seen in

Table 8.1 which details the overall increased grant commitments as the Programme

progressed. There was also a significant trend towards the local authorities meeting

additional expenditure requirements that arose. While the grant amounts did

increase in a number of cases, the percentage of costs covered by the exchequer

was not allowed to exceed 75%. The local authority was still held responsible for

meeting at least 25% of any revised costs. In many cases they exceeded this figure.

21 This point was raised in two of the interviews with Departmental staff, and is corroborated by a conclusion in the 2002 mid-term review of roads expenditure under the NDP carried out by Fitzpatrick Associates.

138

A detailed examination of the level and trend of costs will be undertaken later in the

chapter. For the time being, it can be concluded that the original decision to set the

level of exchequer funding at 75% was soundly based, when one considers the

circumstances as they prevailed in 2000. Whether such a fixed figure should now be

used is another issue and is addressed later. However, for the moment the review

will continue by chronologically outlining the series of events that led to the increased

levels of exchequer funding commitment.

8.2.2. Expansion of the Original Funding Commitment in December 2000

The combined total of the grants announced under circular RW 25/00 on December

14th 2000 was €241.34m. This amount was almost €40m greater than the original

projection of €190.46m (IR£150m22

) when the policy announcement was made in

June 2000. This original figure of €190.46m was based on a series of indicative

estimates in respect of 44 potential projects that were submitted by local authorities

as part of the survey exercise arising from the second Bacon Report. The formal

application process when Circular 13/00 was issued to the 15 local authorities in July

2000 resulted in a greater number of projects being submitted, with different cost

implications than those from the original survey. A total of 117 submissions were

received from the local authorities, with a combined total cost of over €776m.

Exchequer resources would not have permitted all of these to be selected.

When formal Exchequer sanction was sought, the grant requirement was given as

€247.598m. Final modifications before the December announcement reduced the

overall total amount of the allocations to €241.34m, a difference of €6.258m.

However the sanction for €247.598m remained the baseline against which future

spending adjustments were made. In the event, the full €247.598m was expended

with the €6.258m leeway being used to approve three additional projects, and to

allow for increased allocations on a limited number of existing projects in 2001 and

2002. A full list of the grants allocated to the 43 individual projects in December

2000, is included in the Table 8.3 (overleaf). This table also contains headline

information for each project on changes in the level of grant commitment over the

course of the Programme, from 2000 to 2004 and on to 2008.

22 Note on Currency Figures - Allocations under the Programme were announced in 2000 and at that time were given in Irish Pounds (IR£). From January 1

st 2002, the Euro became

Ireland‟s currency. Throughout this chapter the official exchange rate (IR£1 = €0.787564) is used in all conversions. For purposes of clarity, some figures are rounded.

139

Table 8.2. Level and Trend of Grant Allocations – 2000 to 2008

Local Authority

Road Project Name

Grant Approved

2000

Grant at 2004

Grant at 2008

Change 2000

to 2008

#Cork County 1. Carrigaline Western Relief Road €1,866,515 €1,866,515 €1,866,515 €0

#Cork County 2. Clarkes Hill / Moneygourney Road €3,371,155 €6,000,000 €6,000,000 €2,628,845

#Cork County 3. Midleton Northern Relief Road [Phase 1] €1,333,225 €1,333,225 €1,333,225 €0

#Dun Laog/ R‟down 4. Dundrum Main Street Bypass €29,203,976 €29,203,976 €23,537,944 -€5,666,032

#Fingal 5. Balbriggan Inner Relief Road [stage 2]: Dublin Road - Skerries Road

€7,047,046 €7,047,046 €7,047,046 €0

#Fingal 6. Lusk Bypass €4,025,069 €4,025,069 €3,954,491 -€70,578

#Fingal 7. Naul Road Improvement Scheme €2,523,604 €2,523,604 €2,523,604 €0

#Fingal 8. Ongar Road €3,809,214 €3,809,214 €3,809,214 €0

#Galway County 9. Oranhill Distributor Road €2,218,868 €2,218,868 €2,218,868 €0

#Galway County 10. Parkmore Road [Phases I & II] €1,428,455 €1,783,500 €1,584,948 €156,493

#Kildare 11. Barberstown Cross - Maynooth [R407] north of Barberstown cross

€428,537 €1,428,700 €1,428,700 €1,000,163

#Kildare 12. Barberstown Cross - Maynooth [R407] south of Taghadoe Cross €1,257,041 €1,290,481 €1,290,481 €33,440

#Kildare 13. Celbridge Interchange €12,062,512 €22,062,512 €22,062,512 €10,000,000

#Kildare 14. Clane - Kilcock [R407] south of M4 €2,523,604 €4,027,650 €4,027,650 €1,504,046

#Kildare 15. Clane - Kilcock [R407] to a point 1500m north of Clane €1,571,301 €1,602,840 €1,602,840 €31,539

#Kildare Clane Inner Relief Road €952,303 €1,219,875 €321,776 -€630,527

Kildare Enfield - Edenderry [R402] [Carbury to Kishawanny] €4,094,905 €5,788,112 €249,722 -€3,845,183

#Kildare Enfield - Edenderry [R402] [Johnstownbridge to Carbury €11,427,642 €12,883,219 €662,841 -€10,764,801

#Kildare Naas Inner Relief Road [Dublin Road to Tipper Road] €1,428,455 €4,315,193 €359,890 -€1,068,565

#Kildare 16. Naas Ring Road - Newbridge Road to Caragh Road €857,073 €2,689,125 €2,689,125 €1,832,052

#Kildare 17. Naas Ring Road - Newbridge Rd to Kilcullen Rd to Craddockstown Rd

€2,666,452 €7,840,661 €21,520,844 €18,854,392

#Kildare 18. Naas Ring Road - Newbridge Road to Industrial Estate [Millennium Park]

€1,904,607 €6,462,375 €6,462,375 €4,557,768

#Kildare 19. Sallins - Clane [R407} south of Blackhall junction €285,691 €343,220 €343,220 €57,529

#Kildare 20. Sallins - Clane [R407] Castlesize estate to Blackhall Stud €1,142,764 €1,609,875 €1,609,875 €467,111

New - Kildare 21. Roads Serving Intel (Approved 2001) €496,591 €496,591 €496,591 €0

#Limerick County 22. Castletroy Distributor Roads: Monaleen - Kilbane - N7 Dublin Road

€3,656,846 €3,656,846 €3,656,846 €0

#Meath 23. Duleek-Julianstown-Laytown €8,951,653 €12,386,529 €12,686,529 €3,734,876

#Meath Plattin-Colp [MCC part] €1,999,837 €87,684 €87,684 -€1,912,153

#Meath 24. R154 Trim Inner Relief Road, phase 2a €2,428,374 €4,654,069 €4,654,069 €2,225,695

#Meath R154 Trim - Dublin Improvement Scheme (Subsequently Divided) €5,856,667 €6,033,723 €6,033,723 €177,056

25. R154 Trim/Dublin [Iffernock] €600,000 €600,000

26. R154 Trim/Dublin [Kiltale/ Scurlogstown] €3,571,398 €3,571,398

27. R154 Trim Dublin [Tullaghmedan] €1,862,325 €1,862,325

#Meath R161 Athlumney (Subsequently Divided) €4,951,979 €5,068,152 €5,177,119 €225,140

28. R161 Athlumney Phase I [Connaughtons] €653,568 €653,568

29. R161 Athlumney Phase II (Bridge N3) €4,414,584 €4,523,551

#Meath 30. Trim-Kilcock R158 €21,426,830 €28,851,149 €43,500,000 €22,073,170

#Meath 31. Trim-Navan Improvement Scheme [R161] €5,856,667 €7,825,424 €9,000,000 €3,143,333

#South Dublin 32. Outer Ring Road €46,662,874 €46,662,874 €46,662,874 €0

#Waterford County 33. Tramore Ring Road [phase 4] €1,468,578 €1,468,578 €1,468,578 €0

New - Waterford County

34. Tramore Ring Road [phase 5] (Approved 2002) €1,500,000 €2,139,353 €2,139,353 €639,353

#Wicklow County 35. Wicklow Town Relief Road & Wicklow Port Access (Amalgamated)

€7,491,455

€7,783,177

#Wicklow County €15,274,632 €28,283,274 €13,008,642

#Cork City 36. Improvement works at Old Whitechurch Road €476,152 €476,152 €476,152 €0

#Dublin City 37. Jamestown Road, Inchicore €1,761,761 €1,761,761 €1,761,761 €0

#Dublin City 38. Killeen Road, Ballyfermot €3,352,108 €3,352,108 €3,352,108 €0

#Galway City 39. Parkmore Road Industrial Lands €885,643 €885,643 €885,643 €0

#Galway City 40. Terryland Valley Access Road €1,532,733 €1,532,733 €1,532,733 €0

#Limerick City Corbally Link Road €3,466,385 €3,458,997 €5,462,652 €1,996,267

41. Corbally Link Road Phase I €1,426,763 €1,426,763

42. Corbally Link Road Phase II €2,032,234 €4,035,889

#Waterford City 43. Outer Ring Road €11,903,794 €20,445,750 €20,445,750 €8,541,956

New - Waterford City

44. Ballybeg Road (Approved 2002) €1,063,000 €1,063,000 €1,063,000 €0

TOTAL (All Projects) €244,403,118 €300,956,603 €317,334,145 €72,931,027

TOTAL (Original 43 Projects Only – per Circular 25/00) €241,343,527

TOTAL (44 current projects) €224,499,976 €315,652,232 €91,152,256

ORIGINAL EXCHEQUER GRANT COMMITMENT €247.598m

The 43 Original projects announced December 2000 are marked with an with the hash symbol (#)

The three projects added subsequent to the Programme launch are marked „New‟.

The projects that are shaded were discontinued or reclassified from the Programme.

Following the same format as earlier, all of the current projects are numbered 1 to 44.

140

Of the projects announced in 2000, the largest single grant amount was for the South

Dublin Outer Ring Road (€46m). The smallest was the €285,691 allocated to for

work on the Sallins to Clane road (south of Blackhall Junction). The majority of

projects were awarded amounts up to €5million, with 31 of the 43 in this category.

Nine were to receive between €5m and €15m. The remaining three were awarded

amounts of €15m or higher. This data is presented in the chart below.

Fig 8.1. Breakdown of Grants by Amount Awarded - 2000

Up to €5m

€5m-€15m

€15m +

Throughout this chapter, the process that led to increased grant allocations for A

number of individual projects is explained and analysed. Of the 44 projects that

currently comprise the Programme, 32 are receiving amounts up to €5million, with

five projects in the €5m to €15 bracket. The remaining nine are receiving grants in

excess of €15m each.

Fig 8.2. Breakdown of Grants by Amount Awarded - 2008

Up to €5m

€5m -€15m

€15m +

While there was a net addition of 1 project (from 43 to 44) over its lifespan, there

were a considerable number of other changes. These included the addition of new

projects, and the de-committal of others, as well as subdivisions and amalgamations.

All of these changes are now described.

141

8.2.3. Project Changes 2000-2008

From its commencement in 2000 to the present time (2008), the composition of the

Programme changed. These changes had obvious financial implications on the level

of exchequer commitment and their background is now described.

1. Additions - Three new projects were added, as follows:

Kildare County Council: „Roads serving Intel‟ (February 2001). A grant of

€496,591 was provided.

Waterford County Council: „Tramore Ring Road Phase 5‟ (July 2002). An

allocation of €1.5m was made.

Waterford City Council: „Ballybeg Road‟ (September 2002). €1.063m was

allocated.

2. Subdivisions - Three of the approved projects were subdivided. This was done for

ease of management and to allow projects to proceed on a phased basis.

Limerick City: the Corbally scheme was split in two;

County Meath: the R154 (Trim-Dublin) was split into 3;

County Meath: the R161 (Athlumney) was split into 2.

3. Amalgamations - The Wicklow Town Relief Road and Port Access were originally

approved as individual projects but were amalgamated.

4. Reclassifications - In 2006, two of the Kildare projects were taken out of the

Programme:

Carbury to Kishawanny, [R404] Enfield – Edenderry Road

Johnstownbridge to Carbury, [R404] Enfield – Edenderry Road

It was decided that these two roads schemes were of national importance in

supporting the National Spatial Strategy, and consequently were reclassified as part

of the new strategic roads programme announced in 2006. Over €900k had already

been expended on design, leaving €17,758,768 in unallocated funding.

5. De-Committed Projects

County Meath: Plattin-Colp (July 2002). Costs had also escalated and would

have been beyond the capability of Meath County Council to meet. Before

being discontinued, a total of €87,684 was paid (in 2001). This left a total of

€1,912,153 to be decommited.

142

County Kildare: Naas Inner Relief Road - Dublin Road to Tipper Road (January

2008). Cost increases made this project untenable. Estimated costs escalated

from €1,9m in 2000 to €30m in 2007. €359,890 had been paid, but the

outstanding balance of €3,955,303 was transferred to cover additional costs on

the Naas Southern Ring Road.

County Kildare: Clane Inner Relief Road (January 2008). Similarly, estimated

costs had risen from €1.27m in 2000 to €8m in 2007, making this project

untenable. €321,776 had been paid and the balance of €898,099 was also

transferred to the Naas Southern Ring Road.

Some observations arise from the changes that occurred. The fact that three

projects were effectively decommissioned because of rising costs is in line with the

current recommended approach in the Department of Finance Guidelines that there

should be a willingness to walk away from a project if costs become excessive. The

total amount clawed back from the reclassified and decommissioned projects was

€24.52m. However this did not accrue to the exchequer as a saving and was

channelled back into the Programme to fund cost increases on other projects.

8.2.4. Increased Grant Allocations 2000-2008

Between December 2000 when the Programme was announced, and 2004,

increases in the individual allocations for a number of projects were approved by the

Department. This was a response to substantial local increases in estimated project

costs. Some of the extra commitments were met from within the initial approved

programme budget. However, the main source was an increased exchequer funding

commitment, which went from €247.6m to almost €301m. Table 8.2 tracks the

changes in each project‟s allocation from 2000 to 2004, and then on to 2008. Later

in this chapter the particular factors driving costs within the projects will be examined

in greater detail.

From the outset, a number of local authorities experienced problems with escalating

costs, and put forward individual cases to the Department stating that they would not

be in a position to meet these increases from within their own resources. In July

2001 Meath County Council made representations in respect of the Trim Inner Relief

Road, citing increased land costs. A further case was put forward by Kildare County

Council in August 2001 for increased funding for the Barberstown Cross (north)

project. This arose from rising costs and a proposal to extend the road by 600

metres. Both projects were given increases, although the total exchequer grant still

143

had to be held at a maximum of 75% of costs. The Trim allocation increased by

€1.7m. Barberstown (north) increased by €0.9m. The increases were met from the

€6.258m leeway that existed from the outset in the Programme fund23

.

The approval of these increases in grants (albeit on a limited scale) was contrary to

the stated position as set out in Circular 25/00 when allocations were made. Of

further significance was the fact that cost escalations within individual projects

became apparent within 7 months of the announcement of the Programme. This

was a trend that continued across other local authorities and throughout the lifetime

of the Programme to date. In March 2002 additional funding of €10m was sought by

Kildare County Council to complete the Celbridge Interchange project. This

necessitated an additional sanction from the Department of Finance. The sanctioned

amount for the Programme therefore increased from €247.6m to €257.6m.

By 2003, difficulties with escalating project costs were being experienced within a

number of counties. There was also an acknowledgement that project completion

would be delayed beyond the originally anticipated target of 2004. Representations

were made separately by Kildare, Meath, Waterford, Galway and Cork County

Councils as well as Waterford City Council seeking increased allocations. Rising

land costs were a significant factor, although other factors cited were the increased

costs of construction and accommodation works. As projects moved into a detailed

planning phase, land and construction costs were estimated with greater accuracy,

with resulting increases in estimated costs in some instances. The increases were

particularly affecting Kildare and Meath, the counties with the greatest number of

projects. The local authorities set out their respective positions in submissions to the

Department. Essentially they said that they were not in a position to meet the

additional costs, and that this was putting the delivery of the projects in jeopardy. At

this point the Department reviewed expenditure on the Programme. It considered

two main options24

, as follows:

1. The deletion of certain schemes from the originally approved list and the

reduction of the length of other schemes with the resultant „savings‟ in Exchequer

grant aid being used to offset the effects of increased costs. (In effect this would

entail the prioritisation of a more limited number of projects and the redistribution

of funding from within the existing programme budget).

23 Both projects were also to receive further subsequent increases in their allocations. 24 Based on DEHLG Filenotes of 16.7.03, 22.9.03 and 25.9.03.

144

2. Seek sanction from the Department of Finance for an additional €43m in

Exchequer funding (over and above the €257.6m that had already been

sanctioned) to meet the revised estimates in respect of the projects affected by

cost escalations. However, the exchequer commitment would remain at a

maximum 75% of total costs, with the local authority required to meet 25%.

In the event, the second of the two options was agreed. Sanction was sought and

approval given for the €43m increase. Circular RLS 3/2004 of 4 April 2004 notified

local authorities of the revised allocations. Between 2000 and 2004, allocations in

respect of 23 of the original projects were increased. This does not include the 3

new projects that were added. Between 2004 and 2008 a more limited number of

grant increases were approved on a case-by-case basis. However, the scale of the

individual amounts is significant. This data is also contained in Table 8.2. For the

Naas Ring Road (to Cradockstown Road), the allocation increased by €13.68m

between 2004 and 2008. On the R158 Trim-Kilcock scheme the allocation increase

by €14.65m. The Wicklow Town Relief Road and Port Access grant went up by over

€13m, while phase II of the Corbally link Road increased by over €2m. These

increases were partly met through the reallocation funds from decommitted projects.

However, an additional €16m was also required. This brings the Department‟s total

commitment under the Programme in 2008 to €317.334m.

This section has tracked how the overall exchequer commitment to the individual

projects and the Programme as a whole increased between 2000 and 2008 and how

those decisions were taken. The various increases have been described rather than

analysed. The focus now shifts towards the projects themselves and becomes more

analytical in identifying why costs increased.

145

8.3. The Level and Trend of Project Costs Over the Lifetime of the Programme

8.3.1 Headline Trends in Cost Data

The introduction to this chapter outlined the overall trend towards increased project

costs from 2000 to 2008. In December 2000, the estimated cost of completing the

43 projects originally selected was €385.97m. Based on data collected for this

review, the total cost in 2008 of completing all 44 current projects is estimated at

€584.917m. To reiterate a caveat given earlier, some of the figures that formed the

basis for this calculation are estimated. The final total cost of completing all projects

may therefore be higher. The fact that a number of the cost figures are based on

estimates also limits the extent of their use in calculating the unit cost of certain

outputs.

Based on the cost estimates provided in 2000, most of the projects (27 of the 43)

had total costs of less than €5m, with 13 having estimates between €5m and €30m.

The remaining 3 had estimated costs in excess of €30m.

Fig 8.3 Projects Separated into Cost Bands - 2000

Up to €5m

€5m-€30m

€30m +

When the 2000 estimates are compared to the costs as reported in the survey

questionnaires, there has been some change. Of the 44 projects in the Programme,

19 have estimated costs of less than €5m, with 18 now estimated to cost between €5

and €30m. There are now 7 projects with estimated costs over €30m. The

significance of these bands is that they represent the threshold figures for different

levels of appraisal in the Department of Finance Capital Appraisal Guidelines. The

figure of €30m is the threshold for undertaking full cost benefit analysis. The

implications of this observation are examined in more detail in the next chapter.

Figure 8.4 (overleaf) presents the 2008 data in a pie chart.

146

Fig 8.4 Projects Separated into Cost Bands - 2008

Up to €5m

€5m-€30m

€30m +

An important aspect in assessing the level and trend of costs is the ability to match

the projected budget at the outset, against the final expenditure upon completion. To

facilitate these comparisons, some modifications are being made in the presentation

of data. Forty sets of comparative project data will therefore be examined25.

Based on the data returns in the questionnaires, 34 of the 40 projects had or will

have higher costs upon completion, when compared with their original expected

costs. Costs decreased in 4 cases. For the remaining 2, it was not possible to make

an assessment26

. This information is contained in Table 8.3. The largest cost

increases occurred on the following projects (with increases in brackets):

Wicklow Town Port Access and Inner Relief Road (+€39.97m)

Trim to Kilcock R158 (+€29.43m)

Naas Ring Road to Craddockstown Road (+€27.31m)

Waterford Outer Ring Road (+€21.278m)

Carrigaline Western Relief Road (+€18.66m)

Celbridge Interchange (+€14.456m)

Naas Ring Road to Millennium Park (+€12.712)

25 Projects that were initially subdivided have been recombined to provide a single set of figures in each case. This affects the R161 Athlumney (Meath), the R154 Trim to Dublin Road (Meath), Corbally Link Road (Limerick City). 26 For Oranhill Distributor Road (County Galway) sections of the road were built by the developer and an estimate of the cost of this contribution was not provided by the local authority. The original Midleton Northern Relief Road phase 1(a) was subsumed into a far larger project as part of the reopening of the Cork-Midleton Rail Line, and development of the northern part of the town. An estimated cost for the construction element of the original section was provided by the local authority (€1.1m). This doesn‟t include land or other costs. The substantial change in the scale and scope of the project limits comparisons. The figure used in table 8.4 is the original cost estimate of €1,777,633.

147

Table 8.3. Project Cost Comparison, Original Estimates from 2000 versus Costs Reported in the Questionnaire Returns 2007/2008

Local Authority

Road Project Name

Original

Estimated Cost in 2000

Reported Cost

2008

Difference

2000 - 2008

Difference % 2000 - 2008

Cork County 1. Carrigaline Western Relief Road €2,488,687 €21,150,000* €18,661,313* 749.8%*

Cork County 2. Clarkes Hill / Moneygourney Road €4,494,873 €12,000,000* €7,505,127* 167%*

Cork County 3. Midleton Northern Relief Road [Phase 1] €1,777,633 €1,777,633*

Dun Laog/ R‟down

4. Dundrum Main Street Bypass €57,138,214 €42,037,860 -€15,100,354 -26.4%

Fingal 5. Balbriggan Inner Relief Road [stage 2]: Dublin Road - Skerries Road

€9,396,062 €18,818,388* €9,422,326* 100.3%*

Fingal 6. Lusk Bypass €10,069,022 €17,612,324 €7,543,302 74.9%

Fingal 7. Naul Road Improvement Scheme €3,364,805 €6,839,686* €3,473,881* 103.3%*

Fingal 8. Ongar Road €21,852,192 €13,150,661 -€8,701,531 -39.8%

Galway County 9. Oranhill Distributor Road €2,958,490 €2,200,000*

Galway County 10. Parkmore Road [Phases I & II] €1,904,607 €2,113,264 €208,657 11%

Kildare 11. Barberstown Cross - Maynooth [R407] north of Barberstown cross

€571,382 €2,851,342 €2,279,960 399%

Kildare 12. Barberstown Cross - Maynooth [R407] south of Taghadoe Cross

€1,676,054 €5,464,466 €3,788,412 226%

Kildare 13. Celbridge Interchange €30,473,714 €44,930,407 €14,456,693 47.4%

Kildare 14. Clane - Kilcock [R407] south of M4 €3,364,807 €6,200,000* €2,835,193* 84.3%*

Kildare 15. Clane - Kilcock [R407] to a point 1500m north of Clane €2,095,068 €2,515,971 €420,903 20.1%

Kildare 16. Naas Ring Road - Newbridge Road to Caragh Road €1,142,764 €3,596,906 €2,454,142 214.8

Kildare 17. Naas Ring Road - Newbridge Rd to Kilcullen Rd to Craddockstown Rd

€3,555,267 €30,866,084* €27,310,817* 768.1%*

Kildare 18. Naas Ring Road - Newbridge Road to Industrial Estate [Millennium Park]

€2,539,476 €15,252,110 €12,712,634 500.6%

Kildare 19. Sallins - Clane [R407} south of Blackhall junction €380,921 €418,903 €37,982 10%

Kildare 20. Sallins - Clane [R407] Castlesize estate to Blackhall Stud

€1,523,686 €2,172,663 €648,977 42.6%

Kildare 21. Roads Serving Intel (New 2001) €761,842 €833,040 €71,198 9.3%

Limerick County

22. Castletroy Distributor Roads: Monaleen - Kilbane - N7 Dublin Road

€4,875,794 €5,754,816 €879,022 18%

Meath 23. Duleek-Julianstown-Laytown €11,935,538 €20,500,000* €8,564,462* 71.8%*

Meath 24. R154 Trim Inner Relief Road, phase 2a €3,237,832 €6,697,368 €3,459,536 106.8%

Meath R154 Trim - Dublin Improvement Scheme €7,808,889 €11,117,925 €3,309,036 42.4%

25. R154 Trim/Dublin [Iffernock]

26. R154 Trim/Dublin [Kiltale/ Scurlogstown]

27. R154 Trim Dublin [Tullaghmedan]

Meath R161 Athlumney €6,602,638 €7,313,746 €711,108 10.8%

28. R161 Athlumney Phase I (Connaughtons)

29. R161 Athlumney Phase II (Bridge N3)

Meath 30. Trim-Kilcock R158 €28,569,107 €58,000,000* €29,430,893* 103%*

Meath 31. Trim-Navan Improvement Scheme [R161] €7,808,889 €12,000,000* €4,191,111* 53.7%*

South Dublin 32. Outer Ring Road Phase I €67,296,118 €71,119,744*

Waterford County

33. Tramore Ring Road [phase 4] €1,958,104 €2,365,097 €406,993 20.8%

Waterford County

34. Tramore Ring Road [phase 5] (New 2002) €1,998,367 €2,442,373 €444,006 22.2%

Wicklow 35. Wicklow Town Relief Road & Wicklow Port Access

€15,027,350

Wicklow €10,377,569 €65,375,000* €39,970,081* 157.3%*

Cork City 36. Improvement works at Old Whitechurch Road €634,869 €601,992 -€32,877 -5.2%

Dublin City 37. Jamestown Road, Inchicore €2,349,015 €6,021,000* €3,671,985* 156.3%*

Dublin City 38. Killeen Road, Ballyfermot €4,469,478 €10,353,000* €5,883,522* 131.6%*

Galway City 39. Parkmore Road Industrial Lands €1,180,856 €1,401,180 €220,324 18.6%

Galway City 40. Terryland Valley Access Road €2,043,643 €2,172,327 €128,684 6.3%

Limerick City Corbally Link Road €4,621,847* €10,207,401* €5,585,554* 120.8%*

41. Corbally Link Road Phase I €2,761,675

42. Corbally Link Road Phase II €7,445,726*

Waterford City 43. Outer Ring Road €15,871,726 €37,149,906 €21,278,180 134%

Waterford City 44. Ballybeg Road (New 2002) €1,800,000 €1,522,429 -€277,571 -15.4%

TOTAL

€363,997,195

€584,917,012

Figures marked with the asterix symbol (*) are estimates

Original estimated costs for the three projects added after 2000 are from the year when they were approved.

The original estimated costs in the table are for the 44 current projects. The 5 projects that were removed from the Programme are not included here. The total estimated costs for the 43 original projects announced in December 2000 was €385,974,513

148

The cost increases set out in the table are clearly significant both in absolute and

relative terms. In the case of the Wicklow Town project, there was a 157% rise in

original estimated costs, while on the Trim to Kilcock Road it was 103%. On the

Naas Ring Road to Craddockstown it was 768%. Although this was the largest

percentage increase and is at the extreme end of the scale, it was by no means

unique. In the case of 15 of the 40 projects, the final declared or estimated cost is

over 100% greater than the original projected cost submitted to the Department in

the year 2000. However, at an aggregate programme level, the cost increases whilst

significant, weren‟t as severe. Taking the 44 projects that currently comprise the

Programme, the combined level of cost increases over the lifetime of the Programme

was 61%. Their costs increased from €364m to almost €585m. The knock-on

effects as they impacted on the exchequer grant allocations were already outlined.

Between 2000 and 2008, the grant commitment under the Programme went from

€247.598m to €317.334, an increase of 28%. The combined grants for the 44

projects that currently comprise the Programme went from an original figure of

€224.5m to a current amount totalling €315.65m, an increase of 40%.

There are some observations that can be made here. The first is that cost increases

affected some projects more than others. Where increases occurred, their impact

was profoundly felt. In response, the Department relaxed its original rule about not

awarding funding increases. However it did this in a way that required the local

authorities to take on greater responsibility for costs. At an aggregate level, the

Department is providing €317.334m, while €267.583m is coming from other sources.

This represents a ratio of 54% : 46%. When the allocations were announced in

December 2000, the ratio was 63% : 37% between the Programme grants and other

sources.

The funding provided by sources other than the Programme is mainly coming from

local development levies. In the questionnaire, local authorities were asked to

specify from what source their portion of project funding came from. A full set of data

is not available which limits conclusions that can be drawn. A breakdown of funding

was provided in respect of €159.7m of the €267.5m non-exchequer sources. All bar

€26m (approx) of this came from development levies in one form or another. It

should also be acknowledged that the financial data here under-represents local

contributions in the case of the Midleton Northern Relief Road and South Dublin

Outer Ring Road, where subsequent phases of these roads are largely being funded

from development levies.

149

What all of this indicates is that when costs increased, both the exchequer and local

authorities ended up footing the bill. The fact that the local authorities had recourse

to development levies enabled them to provide additional funding. Within the

interviews it was a widely held view that had development levies not been available,

the local authorities wouldn‟t have been in a position to meet their additional funding

obligations. This highlights again the significant impact that the new system of levies

has had since its relatively recent introduction.

Whether it was an aggregate 61% increase in costs, or the more significant

increases that occurred in a number of individual cases, two key questions arise

What were the factors that drove the costs upwards?

What measures can be put in place in future to control and manage costs?

The first of these questions will now be addressed. The second question is the main

focus of Chapter 9, which follows.

8.3.2. What Factors Were Driving Cost Upwards

Within the questionnaire, and during the interviews, local authorities were asked to

identify the factors that had the most significant effect on costs. Land was the

biggest common issue, and will now be examined in detail. Construction inflation

was also raised. At a more specific level, a number of the projects incorporated

additional works, had their length increased or were subject to changes. Of note

here are the following projects which cited these as issues: Carrigaline Western

Relief Road (Cork Coutny), Clarke‟s Hill / Moneygourney (Cork County), Duleek to

Julianstown Road (Meath), Trim to Kilcock R158 (Meath), Outer Ring Road (South

Dublin), Jamestown Road (Dublin City), Kileen Road (Dublin City), Corbally Road

Phase II (Limerick City), Wicklow Town Relief Road and Port Access (Wicklow), Trim

to Dublin Improvements Scheme (Meath), Clane to Kilcock south of M4 (Kildare) and

Barberstown Cross North (Kildare). For the Tramore Ring Phase 5, the Department

granted additional funding to enable simultaneous resurfacing work to be undertaken

on an earlier phase of the ring road. This list of projects may not be exhaustive and

is reliant on information from the questionnaires.

The need to undertake unforeseen accommodation works was cited as a factor in a

number of cases, as were problems with contract tendering. On the Trim to Kilcock

road, archaeological finds delayed work, and also required elements to be

redesigned with resulting cost implications. On the South Dublin Outer Ring Road,

the planning approval from An Bord Pleanala included conditions that required

150

additional works to be carried out. For the Corbally Link Road (Phase II), the two

lowest tenders refused the job, and the eventual tender selected was €1.4m higher

than the lowest. On both the R161 Athlumney (Meath) and the Lusk Bypass (Fingal)

the lowest tender was disallowed, and this also resulted in increased costs.

Inflation in construction costs between the approval of the projects and the

preparation of tender documents was widely cited as an issue. Delays experienced

between project approval and commencement compounded this problem. The issue

of delays was already addressed in Chapter 6. As local authorities tried to source

additional funding to cover rising costs, further delays were felt. With a few

exceptions, those that experienced the largest increases were affected by delays.

Construction inflation was particularly rampant around the time when the Programme

commenced. In 2003, the Department of the Environment produced a series of

inflation calculations for road construction in the years up to 2002 (C&AG, 2004).

These show road construction inflation running at 12% in 2000, 9% in 2001 and 5%

in 2002. Comparable figures for roads inflation are not available post-2003. Other

sources for construction and tender price inflation data are therefore referenced.

Table 8.4 contains construction inflation figures for the period 2000 to 2007. This is

drawn from the authoritative Bruce-Shaw „Construction Cost‟ and „Tender Price‟

indices, and the construction cost inflation index prepared by the Society of

Chartered Surveyors. The data in the table relates to the construction industry in

general, so the situation affecting local authority road construction is likely to differ.

There is also likely to be regional variation. However, the inflation figures do convey

a good sense of changes in wider construction costs during the period. For

comparative purposes, annual inflation figures from the Consumer Price Index are

also included.

Table 8.4. Construction Inflation, 2000-2007

2000

2001

2002

2003

2004

2005

2006

2007

Bruce Shaw Construction Cost Index

9% 9% 3% 3% 2% 3% 3% 3%

Bruce Shaw Tender Price Index

14% 6% -2% -4% 4% 4% 3% 0%

SCS Construction Cost Inflation

8.2% 14.8% 6.2% 2.8% 5.2% 4% 5.4% 5%*

CPI Consumer Price Inflation

5.6% 4.9% 4.6% 3.5% 2.2% 2.5% 4% 4.9%

*Year on year figure to July 2007

Sources: Bruce Shaw Partnership (2008), DKM (2006), DKM/DEHLG (2007), CSO (2008)

151

The table broadly confirms the trend between 2000 and 2002 towards rising costs,

although there are variations between the different indices. This is understandable,

given that they are measuring different things, and use different methodologies27

.

Post-2003, prices appear to have stabilised to some extent, but were running ahead

of the general Consumer Price Index in a number of years. When combined and

compounded, the inflation rate for roads (based on the Department of the

Environment data) in the period 2000 to 2002 was around 28%. This would explain

some of the increases in the early years of the Programme, particularly in the lead-

up to the review of grant allocations 2003. Taken across the entire period from 2000

to 2007, the SCS index shows cumulative increases of 64%. The Bruce Shaw

Tender Price Index and Construction Cost Index increased by 27% and 40%

respectively during that period. The Consumer Price Index rose by 37%.

What is apparent is that adequate contingency wasn‟t included to cope with

inflationary increases. Estimates were submitted in 2000. Some of these estimates

were based on pre-existing cost data that had been prepared at an even earlier

stage by local authorities. As they were being submitted, the estimates were

becoming dated and obsolete. The allocations had only been announced a few

months before local authorities began making claims for additional exchequer

funding arising from cost increases. There are really two issues here; the

underestimation of costs to begin with, and the insufficient attention that was paid to

the likely future impact of inflation.

While there were exceptional inflationary increases at points in the lifecycle of the

Programme, there is something that can be learned from the experience. There is a

need for more robust estimation of costs from the outset. A significant number of

projects experienced changes in their specifications post-approval. While there may

have been a justifiable case for many of these changes (in some instances they were

forced upon the local authority following statutory procedures) there are measures

that the Department can introduce to manage this situation better. These are

discussed in Chapter 9. The inflationary changes explain some, but not all of the

increases that occurred. It was noted earlier that the most commonly cited problem

raised by the local authorities was that of land price increases.

27 The methodologies are described in Appendix I of the „Review of the Construction Industry 2005 and Outlook 2006 to 2008‟, DKM Economic Consultants (2006).

152

8.3.3. Land Prices

Table 8.5 provides comprehensive details on land acquisition costs as they impacted

on each of the projects. The data confirms the overall trend towards rising land

prices, although the impact was not uniformly felt. From 40 individual sets of figures,

comparable before-and-after data on land was available for 25. Land costs

increased in real terms in 19 cases and decreased in 6 cases.

Fig 8.5. Proportion of projects affected by Land Cost Increases

Land as a proportion of the total cost increased in 11 of the 25 comparable cases.

Where increases occurred, the consequence for individual projects was dramatic.

On the final section of the Naas Ring Road the estimated land cost went from

€1.27m in 2000 to €15.2m in 2008. On the Millennium Park section of the Naas Ring

Road, land estimates increased from €380k to €5.37m. For the Carrigaline Relief

Road the initial estimate of €0.5m in the year 2000 is now €14m. Land estimates on

the Wicklow Town Port Access and Inner Relief Road have gone from €10.15m to

€18.26m, and this doesn‟t allow for the fact that some of these lands are being

provided at less than market value. In many instances the relative cost of land as

part of the total project costs is in excess of what is being experienced on National

Road and Motorway construction projects funded by the National Roads Authority.

Up until 2000, land traditionally accounted for around 11% of the cost of building

National roads. This increased to 14% by 2002/2003 (C&AG, 2004, p.36). In 2005,

land costs were 17% of the NRA‟s budget, and this went up to 22% in 2006. Within

the Programme, 18 projects will have final land costs in excess of 20% of total costs.

For five of these, land costs will account for 50% or more of costs. Table 8.5

contains comprehensive comparative data on land costs. It also includes a

calculation for the unit cost of land, where data was available. Explanatory notes to

assist in interpreting the figures are included on the following page. It should be

noted that the cost-per-hectare is based on an average price (i.e. the total number of

hectares acquired divided by the total cost for land). The actual amounts paid to

individual owners will differ widely depending on the size, location and type of

holding.

Increased Land Costs

Decreased Land Costs

153

Table 8.5. Cost of Land Acquisition, 2000 - 2008 and Unit Cost Per Hectare

Local Authority

Road Project Name

Project Start / Finish

Original

Estimated Land Cost in

2000

Original

Land Cost as % of Total

Land Cost

2008

Land Cost

as % of Total 2008

Average Cost per Hectare

Cork County 1. Carrigaline Western Relief Road 2008/ 2009 €457,105 18% €14m* 66.19%* €4,912,280*

Cork County 2. Clarkes Hill / Moneygourney Road 2009/ 2011 €685,658 15% To be determined

Cork County 3. Midleton Northern Relief Road [Phase 1] 2007/ 2008 €515,513 29% €16 - 21m (all

phases)* 56.5%-

63.06%* €1.66-2.44m*

Dun Laog/ R‟down

4. Dundrum Main Street Bypass 2001/ 2002 €44,440,832 78% €26,571,074 63.21% €2.2-€5.44m*

Fingal 5. Balbriggan Inner Relief Road [stage 2]: Dublin Road - Skerries Road

2003/ 2009 €3,301,319 35% €4,092,106 21.75% €1,461,466

Fingal 6. Lusk Bypass 2003/ 2004 €5,471,781 54% €4,031,207 22.89% €995,359

Fingal 7. Naul Road Improvement Scheme 2010 €952,303 54% Unavailable (UA)

Fingal 8. Ongar Road 2005/ 2006 UA UA €75,000 0.6% UA

Galway County 9. Oranhill Distributor Road 2003/2009 €380,921 13%* Incomplete data provided

Galway County 10. Parkmore Road [Phases I & II] 2002/ 2004 €380,921 20% Incomplete data provided

Kildare 11. Barberstown Cross - Maynooth [R407] north of Barberstown cross

2004/ 2005 €190,460 33% €400,150 14% €102,251

Kildare 12. Barberstown Cross - Maynooth [R407] south of Taghadoe Cross

2006/ 2006 €380,921 23% €609,140 11.2% €135,094

Kildare 13. Celbridge Interchange 2001/ 2003 €10,157,904 33% €10,141,943 22.6% €441,203

Kildare 14. Clane - Kilcock [R407] south of M4 2002/ 2008 €444,408 13% €512,150* 8.3%* €322,106*

Kildare 15. Clane - Kilcock [R407] to a point 1500m north of Clane 2006/ 2007 €253,947 12% €89,276 3.6% UA

Kildare 16. Naas Ring Road - Newbridge Road to Caragh Road 2005/ 2006 €380,921 33% €1,114,604 31% UA

Kildare 17. Naas Ring Road - Newbridge Rd to Kilcullen Rd to Craddockstown Rd

2007/ 2008 €1,269,738 36% €15,231,269* 50%* €1,650,549*

Kildare 18. Naas Ring Road - Newbridge Road to Industrial Estate [Millennium Park]

2004/ 2006 €380,921 15% €5,372,125 35.2% €611,093

Kildare 19. Sallins - Clane [R407} south of Blackhall junction 2003/ 2003 €63,486 17% €269,526 64.3% €1,052,835

Kildare 20. Sallins - Clane [R407] Castlesize estate to Blackhall Stud

2007/ 2008 €253,947 17% €475,358 21.9% €1,061,066

Kildare 21. Roads Serving Intel 2002/ 2004 UA UA €26,177 3.1% €77,218

Limerick County

22. Castletroy Distributor Roads: Monaleen - Kilbane - N7 Dublin Road

2002/ 2006 UA UA €100,423 1.8% €19,651

Meath 23. Duleek-Julianstown-Laytown 2004/ 2008 UA UA 3,300,000* 16.1%* €196,592*

Meath 24. R154 Trim Inner Relief Road, phase 2a 2001/ 2003 €761,842 24% €2,197,639 32.8% €364,571

Meath R154 Trim - Dublin Improvement Scheme UA UA €1,745,402 15.7% €118,654

25. R154 Trim/Dublin [Iffernock] 2001/ 2006

26. R154 Trim/Dublin [Kiltale/ Scurlogstown] / 2004

27. R154 Trim Dublin [Tullaghmedan] / 2002

Meath R161 Athlumney €952,303 14% €573,200 7.84% €130,272

28. R161 Athlumney Phase I (Connaughtons) 2001/ 2001

29. R161 Athlumney Phase II (Bridge N3) / 2005

Meath 30. Trim-Kilcock R158 2004/ 2008 UA UA 10,732,000* 18.5%* €228,729*

Meath 31. Trim-Navan Improvement Scheme [R161] 2004/ 2008 UA UA €1,578,485* 13.2%* €114,316*

South Dublin 32. Outer Ring Road Phase I 2002/ 2005 €6,348,690 [phase I]

9% €26,719,032* [all 3 phases]

19.9%* [all phases]

UA

Waterford County

33. Tramore Ring Road [phase 4] 2001/ 2002 €285,691 15% €600,575 25.4% €133,461

Waterford County

34. Tramore Ring Road [phase 5] 2003/ 2004 UA UA €512,062 21% €365,758

Wicklow 35. Wicklow Town Relief Road & Wicklow Port Access

2007/ 2009

Wicklow €10,151,556 40% €18,260,000* 27.9%* €561,846*

Cork City 36. Improvement works at Old Whitechurch Road 2002/ 2003 0 0 0 0 0

Dublin City 37. Jamestown Road, Inchicore 2003/ 2004 €1,269,738 54% €2.4m* 39.9%* €2m*

Dublin City 38. Killeen Road, Ballyfermot 2003/ 2004 €1,041,185 23% €3,850,000* 37.2%* €2,566,666*

Galway City 39. Parkmore Road Industrial Lands 2001/ 2003 €168,875 14% €42,946 3.1% €208,479

Galway City 40. Terryland Valley Access Road 2002/ 2004 UA UA €248,360 11.4% €1,403,168

Limerick City Corbally Link Road €304,737 7%

41. Corbally Link Road Phase I 2001/ 2002 0 0 0

42. Corbally Link Road Phase II 2006/ 2007 €435,501* 5.9%* €483,890*

Waterford City 43. Outer Ring Road 2003/ 2005 €2,158,554 14% 10,130,592 27.3% €239,267

Waterford City 44. Ballybeg Road 2003/ 2004 0 0 0 0 0

figures marked with the asterix symbol (*) are estimates

154

Notes on Table 8.5

For the Ongar Road (Fingal), 1.2ha was provided by developers as part of an

agreement and did not feature as a direct cost.

For the Lusk Bypass (Fingal), lands were acquired at approximately 75% of market

value through a local development agreement.

On the northern section of the Clane to Kilcock road (Kildare) no lands acquired

other than roadbed and wayleave.

The majority of lands for the Castleroy Distributor Road (County Limerick) were

provided by the developer at no direct cost to the local authority.

Current land estimates for the Wicklow Town Relief Road and Port Tunnel take

account of a local arrangement with landowners along the route to acquire lands at

less than market value. However full market value is likely to be paid for some

lands.

Local authorities were asked if any additional local authority lands were provided

over and above those directly acquired and reported in the main cost data in the

questionnaire. They were asked to give details of the size, and estimated price at

the time it was used. The following data was provided on these additional lands,

and was not included in the calculations in Table 8.5. The estimated price is

provided in brackets;

- Balbriggan Inner Relief Road (Fingal): 2.2ha (€6.2m)

- Duleek – Julianstown (Meath): 0.442 ha (€85,000)

- Trim Navan Improvement Scheme (Meath): 1.598 ha (€250,000)

- South Dublin Outer Ring Road: 50ha (€124m)

- Wicklow Port Access and Town Relief Route: 1.01 ha (€499,000)

- Corbally Link Road Phase I (Limerick City): 0.3ha (€100,000)

- Waterford Outer Ring: 3.45ha (€7.3m)

The trends identified in the questionnaire data are also borne out from the interviews.

The strong and consistent view among local authority officials is that land costs now

represent a growing constraint on the ability of local authorities to undertake work on

regional and local roads. This is being acutely felt close to towns, villages and in

suburban areas, where lands (including those zoned agricultural) have tended to

attract what is called a „hope‟ value commensurate with their location close to other

development. However the trend is also prevalent on longer schemes through rural

areas where the land zoning is largely agricultural. For example, this was particularly

evident on the Duleek to Julianstown road, and R158 Trim to Kilcock (both Meath).

Procedures for land acquisition, and rules governing the assessment of compensation

when land is compulsorily acquired for roads are set out in statute, and are well tested

155

and established. These were touched upon already in Chapter 6. Landowners are

entitled to the market value for their land, plus compensation.

Paradoxically, in the case of the Programme under review, as the strategic roads have

set about opening up lands for development, one reported effect has been to increase

land values in the relevant areas. The increased value is part of what is known as

„betterment‟. Betterment describes how the value of land can increase on foot of

rezoning, the provision of physical infrastructure (e.g. roads, sewage), or through the

provision of social infrastructure (schools, sports facilities etc.). The impact of

„betterment‟ in causing cost increases in land acquisition for infrastructural projects is

not unique to regional and local roads. It has also been highlighted as a cause of

concern by both the Dublin Transportation Office and National Roads Authority

(APOCC, 2004, p.90).

The consequence, in simple terms, is that the land required to build a road increases

in cost by virtue of the self-same road being built. The road is also made more

expensive by being proximate to other developments, which benefit from new roads

but do not have to bear any of the cost. This issue was consistently raised by local

authority interviewees. As one local official explained:

“land cost is an issue, and this is coming up on practically every scheme

that we‟re doing here at the moment. Particularly when you‟re working

in a city environment, one of the big factors on every roads job is the

ratio of land costs to overall project costs, because every piece of land

has a development potential by virtue of its zoning, or would have a

development hope potential in the future because of its proximity to

other development or to the city centre. And I mean every piece of land

that you go in to, like you start negotiations probably at a million an

acre, and go up from there.”

Some local authorities have been able to recoup part of the „betterment‟ value by way

of special agreements with developers to acquire lands at preferential rates, or at no

cost. Fingal County Council acquired lands for the Ongar Road at no cost through an

agreement with developers. Limerick County Council similarly acquired land. The

land costs for that project constituted less than 2% of the total budget. For the

Dundrum Bypass, agreements were also made with developers on land. As was

already noted, Wicklow County Council has made an arrangement with landowners

along the route of the Wicklow Port Access and Town Relief Road. However, this deal

156

took years to conclude. The number of owners involved and the difficulty is achieving

consensus was a factor in causing delays. In all of these instances, local

arrangements are involved. While there is scope under planning legislation to enter

into agreements with developers for the provision of infrastructure, there is no means

to oblige a developer or landowner to cede land at less than the market rate.

Where there is no scope to make localised arrangements on land acquisition, or where

there are too many owners to conclude a deal, the local authority is left with little option

but to pay the going rate through CPO. As has been noted, these rates are based on

statutory rules over which the local authority has little or no control. Where there is a

limited and finite budget available for road construction and an increasing proportion is

being taken up by land acquisition, a logical response would be to scale back the

outputs. This essentially was the choice facing local authorities and the Department

as the Programme progressed. There were two options: either pay the going rate for

land which was rapidly rising, or make cutbacks. Given that the roads were

considered strategic in nature, increased funding was provided (in the main). There

were some exceptions. The Naas Inner Relief Road (to Tipper Road), and the Clane

Inner Relief Road, were removed from the Programme in January 2008 largely

because of rising land costs. Their allocations were diverted to help pay for cost

increases on the Naas Southern Ring Road, which were again largely driven by land.

Under the rules as they stand, and as they are required to be applied by arbitrators

when deciding upon compensation, regard is had for the market value but also the

„hope‟ value based on the value of other lands in the area. One local authority official

stated:

“when it comes to arbitration and the arbitrator decides on the land value,

which is a not unusual process - if the land is zoned agricultural but is

within the frame of an urban setting….that they use the adjoining land

zoning, whatever it may be, whether it‟s residential or commercial or

whatever to colour their position with regards to the value of the land”

The general view of local authority personnel in the interviews was that short of major

legislative change, the land costs as they stand simply have to be paid. The question

then arises as to how some of the benefit that accrues to landowners by virtue of the

„betterment‟ caused by the road can be captured. The most obvious vehicle is through

the system of development levies. This is examined in more detail in the next Chapter.

157

There is then the issue of whether the local authorities achieved value for money in

their acquisition of land. Table 8.5 includes data on the cost per hectare of lands

purchased. A problem in trying to draw unit cost comparisons between different

projects is that the market for land varies significantly from county to county, and is

crucially dependent on location. From the table it can be seen that the cost per

hectare of land varies considerably and ranges from €20,000 to €5.44m. Even within

the same town, land prices can vary. In the case of the Tramore Ring Road, the cost

per hectare on the first section to commence (Phase 4) was €133k. For the Phase 5,

the cost was €365k. This can be partly accounted for by additional conditions attached

to the purchase agreement on Phase 5, and to some extent by inflation, but the

location was a key factor. The land required was part of (or adjacent to) the local golf

course, making it more expensive. Relative comparisons between projects while

interesting and somewhat informative are of limited use in assessing cost

effectiveness. Other benchmarks are needed.

Unfortunately there isn‟t an official-level source of data on all land transactions. The

nearest thing available that constitutes a comprehensive national analysis of land price

trends is the Irish Auctioneers and Valuers Institute (IAVI) Annual Property Survey.

This is based on information reported by its members on individual transactions.

Given that these lands are being commercially traded, rather than being acquired by

compulsory purchase order, the basis upon which prices are determined is different.

While land values per hectare paid under the Programme may seem large, they do not

appear to be out of step with the prices reported in the IAVI surveys. In its 2006

survey (IAVI, 2007), one sale along the Nangor Road, which connects to the Killeen

Road (a road funded under the Programme), is reported at €2.14m per hectare. Land

in south-west Dublin was achieving €3.75m per hectare and €4m in South East Dublin

/ North Wicklow. In Midleton, County Cork, prices of €2.4m per hectare are quoted in

the IAVI Survey. In comparison, the estimated land costs per hectare on the Midleton

Northern Relief Road Phase 1a range between €1.66m and €2.4m per hectare. In the

suburban areas of Waterford City a 4.4ha site with planning permission sold for €1.7m

per hectare. In Kildare there were reports of agriculture land not zoned, but with

potential selling for €1.25m per hectare. In another transaction in Kildare the price was

€2.5m per hectare for development lands. The price per hectare on the final section of

the Naas Ring Road completed in March 2008 averaged €1.65m. While these

comparisons are somewhat arbitrary, the quoted land costs incurred by local

authorities are within the ranges of figures referenced by the IAVI.

158

One thing that can be said is that land prices nationally have been increasing over the

lifetime of the Programme, and this is reflected in successive editions of the IAVI

Annual Survey, with year-on-year increases of around 15% on certain types of

development land over the early and middle parts of the decade (IAVI 2006, p.21).

Given the different scope of the IAVI data, and the basis upon which prices are

determined, such inflation figures can only be used only for indicative purposes. What

is relevant is that local authorities, like other participants in the market, have been

affected by these changes and had to pay market rates. Whether land price will

continue to rise in the long term is another matter. The most recently available IAVI

data points to a general reduction in the price of development land in 2007 (IAVI, 2008,

p.15). Whatever about the macroeconomic consequences, a downward trend in land

prices would reduce the cost of constructing roads infrastructure.

The increase in costs and the factors that contributed to them had implications for the

efficiency of the Programme. More resources than originally anticipated were required

to achieve outputs and outcomes. Spending more money than was budgeted raises

questions about possible inefficiencies. The next section considers the efficiency of the

Programme in more detail.

8.4. The Cost of Achieving Outputs

While there are different definitions available, Efficiency can essentially be understood

as getting the maximum output from available inputs. This section will bring together

the cost data outlined earlier and make comparisons with the levels of outputs, as

reported in Chapter 6. These outputs are the roads that were constructed and the

housing units and lands that were facilitated. Comparing the cost of achieving these

outputs is a necessarily limited exercise. It is confined to quantitative data and does

not take account of the other social and economic outcomes identified in Chapter 7. In

looking at the direct construction-related outputs, there are some challenges in

preparing comparative efficiency data, and these were briefly addressed already. The

1997 review by KPMG developed a series of unit costs for different types of road

works but was unable to calculate a uniform and comparable unit cost on „Road

Improvements‟ because of the variation in the type of works. These would include, for

example, the construction of new roads, the widening or realignment of an existing

road and the construction of roundabouts. These are precisely the types of activities

funded under the Programme. In the main questionnaire, data on the dimensions of

the road (length and width), as well as other particular design features was sought.

159

Based on these details it is possible to calculate the area of road constructed in square

metres, and then calculate a basic unit cost per square metre. Given the significant

variation in land costs and the effect that they have in skewing the figures, unit costs

with and without land costs were prepared. Some significant reservations must be

raised on the use of this data.

In examining the unit cost data, problems similar to those already identified in the

KPMG report were identified. Excluding land, values ranged from €1,719 per square

metre at the top end to €79 at the lower end. The most expensive was the Dundrum

Main Street Bypass, which included a new road bridge, pedestrian bridge, demolition

works, a series of junction realignments and some enabling works affecting the Luas.

Construction took place in a busy and populated area of Dublin City. The lowest unit

cost was reported on the 270-metre stretch of the R407 road at Blackhall Junction in

County Kildare, and involved an improvement in the sightline of the road. Little in the

way of valid comparison can be made between the two projects. These unit cost

figures were at the extreme ends of the scale, but for those in-between there was also

considerable variance depending on the types of works that were undertaken.

There are a number of variables that have an influence on the unit cost. One key

determinant is whether the road was being constructed new or being improved and

realigned. Some of the projects had a combination of different types of works. The

level and extent of particular features like Bridge Structures, Roundabouts, Junctions,

Cycle Lanes and Footpaths also affects cost. Typically the projects with the highest

unit costs are those involving bridge construction and other major engineering works.

The extent of requirements related to what are called „accommodation works‟ to

ameliorate the impact of construction work on properties adjacent to the road is a

further factor. Some roads were undertaken in conjunction with additional works to

provide ducting for power, sewerage and telecoms. This had cost implications.

Ground conditions are also a factor, as is the proximity to environmentally sensitive

sites. Safety and access are issues, especially if a road must be kept open to traffic as

improvement works are simultaneously ongoing.

So many qualifications and caveats have to be introduced to explain each case that it

severely limits the value of the data at a programme level. Where it is of use, is in

making comparisons between projects that have similarities. However some detailed

knowledge of engineering and design issues is required. A particular value in using

unit cost data in the Programme is not so much that it answers questions, but causes

160

them to be asked. For example, on Parkmore Road in Galway, which crosses the

boundary between Galway City and County Council, the road was substantially

improved, but the work was undertaken as two separate projects by the two local

authorities. The unit cost per square metre for the Galway City end was €208. It was

€297 on the County side. This issue was raised with the County Council, which

explained that ground conditions on their side were substantially different,

necessitating excavation and levelling works. The usefulness of the unit cost data

arises in drawing attention to apparent anomalies. Of course, a level of expertise is

required in assessing the validity of the explanations. The data can‟t be said to „speak

for itself‟. The unit cost per metre would therefore be of most use as an indicator

internally within the Department where the technical expertise is available to make a

balanced judgement based on all of the potential factors impinging on cost. As a

general performance indicator for publication it would likely be counterproductive.

What this exercise confirms is that the KPMG analysis from its 1997 Value for Money

Review still holds true. Units costs can‟t really be used for general comparative

purposes in these types of regional and local road works.

Apart from the roads themselves, the major outputs were the housing lands, housing

units and commercial development lands. Table 8.6 compares the outputs against

their cost of delivery. The Programme had two different emphases, on housing and

commercial development. A considerable number delivered combined outputs under

the two headings. To get a meaningful common measurement for use in calculating a

unit cost for these outputs would involve combining housing lands, housing units and

industrial lands into some hybrid form. Given that the three outputs are quite distinct

and different in character, it wasn‟t felt appropriate to undertake such an exercise. The

table therefore lists the cost of the individual projects and their respective outputs,

without performing any additional data processing exercises on the figures.

161

Table 8.6. Cost of Achieving Development-Related Outputs

Local Authority

Road Project Name

Total Cost

Housing Land (Ha)

Industrial Land (Ha)

Housing Units

Cork County 1. Carrigaline Western Relief Road €21,150,000* 54.5 7.36 1,000

Cork County 2. Clarkes Hill / Moneygourney Road €12,000,000* 100 1 2,000

Cork County 3. Midleton Northern Relief Road [Phase 1] €1,777,633* 133.8 37.6 2,500

Dun Laog/ R‟down

4. Dundrum Main Street Bypass €42,037,860 41.64 20.7 2,667

Fingal 5. Balbriggan Inner Relief Road [stage 2]: Dublin Road - Skerries Road

€18,818,388 67 2.600

Fingal 6. Lusk Bypass €17,612,324 70 2,849

Fingal 7. Naul Road Improvement Scheme €6,839,686 151 32 5,800

Fingal 8. Ongar Road €13,150,661 73 3,000

Galway County 9. Oranhill Distributor Road €2,200,000* 86.38 2,160

Galway County 10. Parkmore Road [Phases I & II] €2,113,264 85.11 96.28

Kildare 11. Barberstown Cross - Maynooth [R407] north of Barberstown cross

€2,851,342

Kildare 12. Barberstown Cross - Maynooth [R407] south of Taghadoe Cross

€5,464,466

Kildare 13. Celbridge Interchange €44,930,407

Kildare 14. Clane - Kilcock [R407] south of M4 €6,200,000*

Kildare 15. Clane - Kilcock [R407] to a point 1500m north of Clane

€2,515,971

Kildare 16. Naas Ring Road - Newbridge Road to Caragh Road

€3,596,906 11.5 336

Kildare 17. Naas Ring Road - Newbridge Rd to Kilcullen Rd to Craddockstown Rd

€30,866,084* 42.7 1,310

Kildare 18. Naas Ring Road - Newbridge Road to Industrial Estate [Millennium Park]

€15,252,110 7.48 102.69

Kildare 19. Sallins - Clane [R407} south of Blackhall junction

€418,903

Kildare 20. Sallins - Clane [R407] Castlesize estate to Blackhall Stud

€2,172,663

Kildare 21. Roads Serving Intel (New 2001) €833,040

Limerick County

22. Castletroy Distributor Roads: Monaleen - Kilbane - N7 Dublin Road

€5,754,816 96.4 87 2,410

Meath 23. Duleek-Julianstown-Laytown €20,500,000* 12 20 360

Meath 24. R154 Trim Inner Relief Road, phase 2a €6,697,368 56 51 1,700

Meath R154 Trim - Dublin Improvement Scheme €11,117,925 50 23 750

25. R154 Trim/Dublin [Iffernock]

26. R154 Trim/Dublin [Kiltale/ Scurlogstown]

27. R154 Trim Dublin [Tullaghmedan]

Meath R161 Athlumney €7,313,746 58 54 1,300

28. R161 Athlumney Phase I (Connaughtons)

29. R161 Athlumney Phase II (Bridge N3)

Meath 30. Trim-Kilcock R158 €58,000,000* 23 10 710

Meath 31. Trim-Navan Improvement Scheme [R161]

€12,000,000* 34 8 1000

South Dublin 32. Outer Ring Road Phase I €71,119,744* 478.9 200 16,000

Waterford County

33. Tramore Ring Road [phase 4] €2,365,097 102.9 10 1,044

Waterford County

34. Tramore Ring Road [phase 5] (New 2002)

€2,442,373 34 400

Wicklow 35. Wicklow Town Relief Road & Wicklow Port Access

Wicklow €65,375,000* 58.15 33.6 1,450

Cork City 36. Improvement works at Old Whitechurch Road

€601,992 22.6 0.405 1,100

Dublin City 37. Jamestown Road, Inchicore €6,021,000* 7

Dublin City 38. Killeen Road, Ballyfermot €10,353,000 42.75 42.9 2132

Galway City 39. Parkmore Road Industrial Lands €1,401,180 58.33

Galway City 40. Terryland Valley Access Road €2,172,327 37 520

Limerick City Corbally Link Road €10,207,401*

41. Corbally Link Road Phase I €2,761,675 0.5 0.5 200

42. Corbally Link Road Phase II €7,445,726* 4 3

Waterford City 43. Outer Ring Road €37,149,906 217 60 7,595

Waterford City 44. Ballybeg Road (New 2002) €1,522,429 29.66 7.06 543

TOTAL

€584,917,012

2,281

973.5

65,436

Figures marked with the asterix symbol (*) are estimates

162

Earlier in Chapter 6, comparisons were made between the original projected outputs of

the Programme, and the outputs as reported in the recent questionnaires. In a like-

with-like comparison between these two data sets, the Programme is expected to

deliver 19,412 (or 42%) more housing units than expected, along with 27.5% more

housing lands (490ha) and 1.5% more commercial development lands (14.5ha). More

outputs are being delivered, but balanced against this were increased costs. Taken at

an aggregate level, the combined cost of projects funded under the Programme

increased by 61% (approx.) from the period 2000 to 2008, although this figure is likely

to be higher. The cost to the Department as reflected in its grant funding, increased by

28%. From looking at this information it is clear that a key to enhancing efficiency in

future will be the ability to keep control of costs.

While efficiency is centrally concerned with the cost of achieving the objectives of a

programme, the pursuit of greater efficiency can also be affected by the manner in

which the work is undertaken. This relates back to the Programme Logic Model, and

the role that „Activities‟ play in transforming inputs into outputs and outcomes. The

focus of the review then shifts in this direction.

8.5. Contract or Direct Labour? - How the Works Were Carried Out

It should be recalled that the two previous studies undertaken to review non-national

roads highlighted this as a key issue. The 2002 review noted that the proportion of

works carried out by direct local authority labour was at least 50% in all cases, and

over 80% on certain grant schemes. While it found no evidence that direct labour

costs were more expensive than contractors, it concluded that its dominance was not

in accordance with international practice where the trend was moving away from use

of direct labour by public bodies (Fitzpatrick, p.c29). The 1997 KPMG review noted

that the vast majority of non-national road works were carried out by direct labour at

that time. In the current review, local authorities were asked to identify how the design

and construction works were undertaken.

By way of a caveat, the projects were generally larger in scale and more self-contained

than a lot of the routine road maintenance works undertaken by local authorities. It

could be expected that quite a number would be contracted out. However, the data

indicates that in a significant majority of cases, contracting (particularly by competitive

tender) was the preferred option. For the construction work, 33 projects (75%) were

undertaken by contract using competitive tender, with only 3 (7%) being undertaken by

direct labour. A further five were undertaken by contractors or developers through a

163

different appointment process, while 3 had not yet commenced. From the 44

schemes, in 30 cases (68%) the design work was contracted using competitive tender,

while in 8 cases (18%) the work was done by direct labour.

With only three projects having been constructed using direct labour it is difficult to

make any meaningful relative comparisons between the cost of undertaking projects

by the use of contract or direct labour.

The conclusion that can be drawn from this data is that there is a growing use of

contractors appointed by competitive tender. This particularly applies in the case of

larger self-contained schemes. This represents a shift from the 2002 report and brings

the Programme more in line with international practice in this area. It is reasonable to

assume that part of the reason for this change has been driven by EU co-financing

rules, which required projects over certain thresholds to be undertaken by contract28.

However, these practices are also becoming common on exchequer-funded schemes.

Table 8.7. Contract or Direct Labour – How Works Were Carried Out

Design Construction

Competitive Tender 30 33

In-house / Direct Labour 8 3

Negotiated Procedure 2

Restricted Tender 1 1

Public Private Partnership 1

Work undertaken by Developer 2 2

Not yet at Construction Phase 3

Project Managed by Local

Authority Using Contractors

2

Total 44 44

Overall, there are implications for the trends identified in the table. With more and

more road projects being undertaken using contractors, the manner in which tenders

are prepared and agreed becomes an issue of greater importance. This is probed in

more detail in Chapter 9.

28 Under these rules, at least 90% of the value of projects costing more than €3m (excluding land) must be undertaken by single or multiple contract. Earthworks costing more than €0.6m and bridgeworks costing more than €0.25m must be undertaken by contract (DoT Circular RLS 20/2007).

164

8.6. Administration

The Department of Finance Guidelines for carrying out VFM Reviews recommend that

consideration of efficiency and effectiveness requires an estimate of the administrative

costs (2007, p.64). In the case of this particular programme, costs arise in two

particular forms. There are the administration costs of the Department, and the costs

borne by the local authority.

8.6.1. Departmental Administration

These costs can be calculated using a template approved by the Department of

Finance (CEEU, 2007). This allows for total salary costs to be calculated based on the

direct gross salary, employers PRSI contributions, an imputed pension contribution

plus an additional allowance to cover office overheads. The first step in the process is

to ascertain what staff members are directly involved in the administration of the

Programme. The Regional and Local Roads Division currently has 14 staff, not all of

whom work on the Programme. The combined grants paid by the Regional and Local

Road Division in 2008 total €618.714m. Expenditure on the Programme under review

in 2008 is projected to be €40.324m.

The estimation of the administration commitment is based on the assessment of the

two senior line managers in the Division, which takes account of commitments set

down in PMDS Role Profile forms29

. The number and grades of staff, and the

proportion of their respective jobs that relate to the Programme, was reckoned. This

represents the best effort at calculating the extent of the administrative commitment.

However it cannot be taken as an absolute measurement. The total administrative

costs for 2008 can be estimated at €76,400 (approx.). Intuitively this appears to be

relatively small and represents less than 0.2% of the annual projected expenditure for

2008. The Programme may be benefiting from certain economies of scale that arise as

a result of being located within the larger Regional and Local Roads Division. If the

Programme operated as a stand-alone entity, it would still require expert input from

engineers, and would also need dedicated administrative support. The Division

already has these resources in place and has been able to manage them in order to

simultaneously administer a number of different grants schemes, as well as other

responsibilities. The estimated staff commitments in 2008 are set out in table 8.8.

29 PMDS is the Performance Management and Development System which operates across the civil service. Each member of staff has a Role Profile form which sets out the individual responsibilities for that person.

165

Table 8.8. Estimated Administration Costs - 2008

Staff Grade Proportion of Job Attributable

Annual Salary (2008)

Amount Attributable

Employer PRSI

Pension Staff Overhead Costs

Total

Principal Advisor Higher (Pre-1995)

5% €106,616 €5,330.80 €107.15 €1,599.24 €3,307.48 €10,344.67

Principal Officer (Higher) (Pre-1995)

5% €101,675 €5,083.75 €102.18 €1,525.13 €3,154.20 €9,865.26

Roads Inspector (Engineer Grade I Civil) (Post 1995)

10% €74,438 €7,443.80 €800.21 €1,860.95 €4,749.33 €14,854.29

Roads Inspector (Engineer Grade I Civil) (Post-1995)

10% €74,438 €7,443.80 €800.21 €1,860.95 €4,749.33 €14,854.29

Assistant Principal Officer (Pre-1995)

5% €71,812 €3,590.60 €72.17 €1,077.18 €2,227.78 €6,967.73

Higher Executive Officer (Post 1995)

10% €53,614 €5,361.40 €576.35 €1,340.35 €3,420.71 €10,698.81

Clerical Officer (Post-1995)

10% €31,576 €3,157.60 €339.44 €789.40 €2,014.63 €6,301.07

TOTAL

€73,886.12

Travel and Subsistence Expenses

€2,500

Total

€76,386.12

Notes on Table 8.8

(a) The salaries are those effective from March 1 2008 and based on Department of

Finance Circular E107/22/06 of 20 February 2008.

(b) The annual salary attributed to each grade is taken as the mid-point on the scale.

(c) There are two rates for Employers PRSI. For staff who entered the civil service

before April 1995, the rate charged in 2.01%. For those that joined after April 1995, the

rate is 10.75%.

(d) The pension allowances are based on revised arrangements contained in Department

of Finance Circular E109/76/01 of 20 September 2005. For those in the civil service

before April 1995, 30% is added to gross salary. For post-1995 staff, 25% is added. The

pension is based on gross salary (excluding the PRSI charge).

(e) Additional staff costs and overheads related to the use of office space, telephones,

security, training, recruitment etc. are then added. The recommended convention is for

the addition of 47% to the total salary costs to cover such overheads. The „total salary‟

is defined as the combined direct salary, employer‟s PRSI and pension allowance.

(f) Disaggregated travel and subsistence expenses for individual roads programmes are

not recorded. The total budget for the Division in 2008 is €50,000. Taking account of

experience in previous years, it is estimated that proportion expended on the

Programme is approximately 5% of the total.

166

The administrative overheads, as calculated, represent an estimate of the cost in

2008. If these figures are extrapolated across the full life of the Programme, the

estimated proportion would still be approximately 0.25% of total expenditure. While at

first glance the level of administrative costs seem low, they may not be that surprising.

They confirm a finding in the NDP Mid-Term Review, which said that “the non-national

roads section of the Department has limited staff available for monitoring delivery of

the overall roads programme” (Fitzpatrick, 2002, p. c32).

By way of a comparative example, the Expenditure Review of the Local Authority

Swimming Pool Programme estimated departmental administrative costs at less than

2% of the overall programme (DAST, 2007, p.43). This programme is somewhat

similar to the one under review, in that it is run by a Government Department, but

delivered by local authorities. The Expenditure Review of the Sports Capital

Programme also estimated Departmental administrative costs as being less than 2%

of programme costs (DAST, 2005, p.8).

The level of administrative resources compares favourably with schemes operating in

England and Scotland, although direct like-with-like comparisons are difficult. The

„Community Infrastructure Fund‟ in England has similar aims. It allocated

£200m(sterling) to aid transport infrastructure to support housing development. The

background to this programme was examined earlier in the Chapter 2. Based on

discussions with an official involved in managing the Programme, the staff commitment

can be estimated as follows:

Executive Officer equivalent - 75% of job

Higher Executive Officer equivalent - 75% of job

Grade 7 (Assistant Principal Equivalent) – 10-15% of job

Divisional Manager Grade 5 (Principal Officer Equivalent) – supervisory role.

When this programme was set up, there was considerable input from economic

analysts. It wasn‟t possible to estimate in quantitative terms the extent of involvement

from these staff but it was particularly strong when applications were being assessed.

This is a reflection of the appraisal process, with its emphasis on techniques aimed at

measuring costs and benefits using a „Transport Economic Efficiency‟ model. This

system is more complex than the assessment procedure that was undertaken for the

scheme in Ireland. A point of note here is that if the Regional and Local Roads

Division moved towards such forms of appraisal, there would be administrative

167

implications. An overall observation on the Programme in England is that the level of

the commitment is comparable to that in Ireland.

In Scotland there is a form of specialised funding for „regionally important‟ local roads,

which is in addition to the more generalised roads funding provided from central

Government. In its latest round of funding, the Scottish Executive has set aside £35

million for this purpose. It is being provided to local authorities for projects identified

through the seven „Regional Transport Partnerships‟ that are spread across Scotland.

These partnerships are made up of local transport companies, local authorities, as well

as business and citizen interests. These roads could be considered „strategic‟ in

nature, although there are more differences than similarities when compared to

Ireland‟s programme, or indeed the „Community Infrastructure Fund‟ in England.

The Scottish initiative was discussed with an official who is responsible for the

Regional Transport Partnerships within the Scottish Executive (Transport Directorate).

Apart from certain legislative and policy aspects, responsibility for local roads is largely

devolved to local government. Funding is agreed as part of the general local

government allocation or „Settlement‟. The additional £35m is tied up in these

allocations. The unit that deals with the Regional Transport Partnerships has three

full-time liaison officers, which have an equivalence with the Higher Executive Officer

grade in the Irish civil service, along with one more senior official. Given the

substantial differences between the Programmes in Ireland and Scotland, direct

comparisons are not possible. However, at a more general level, it can be noted that

administration for the Programme in Ireland requires fewer resources.

This exercise in estimating the level of administrative costs and examining the

equivalent commitment in other programmes indicates that the Programme under

review compares favourably. The 2002 Fitzpatrick review (mentioned above),

concluded that “The Non-National Roads Programme is being operated on a

reasonable and efficient basis” (2002, p.c15). The evidence presented here supports

that assertion. The level of administrative resources committed at Departmental level

is reasonable, and is being employed efficiently. If anything, costs are the lower end of

the scale in comparison with other programmes.

8.6.2. Local Authority Administration

Apart from direct project overheads that arise in the form of construction contract

payments, materials, land etc., there are also administration costs. Under the terms

168

and conditions that govern the payment of roads grants by the Department, local

authorities are specifically disallowed from claiming administration overheads. A list of

items than can and cannot be recouped is contained in Part 3 of the „Memorandum on

Grants for Non National Roads‟ issued by the Regional and Local Roads Division

(DELG, 2001). Irrespective of who pays for the local administration of road works,

they do represent a cost. This was probed through the main questionnaire and in the

interviews with local authority personnel.

The manner in which project costs are calculated limited the ability to gather data.

Because the Department doesn‟t recoup administration costs, these overheads are not

apportioned to individual projects. Based on the interviews with local government

officials, this is the general practice. The data is not required for any official purpose at

the moment and is therefore not systematically gathered. A more general system of

overhead apportionment has operated with administration costs being allocated to

larger programme-based headings rather than on a project-by-project basis.

In the questionnaire completed by the local authorities, efforts were made to gather

data. Each was requested to estimate the level of administration resources committed

to their respective projects. This approach met with mixed success. For 16 of the

projects, no data could be provided. In the case of a three projects which had yet to

commence, „guesstimates‟ were submitted. For a further two, staff time commitment

couldn‟t be calculated, but a more generalised estimate of administrative costs was

submitted. For three projects, the estimates provided had already been included in the

main body of the survey.

What this means is that data for well over half the projects is either unavailable, or in a

format that curtails its usefulness. It is therefore not possible to develop any

programme-level estimate of administrative costs, or a framework that can yield

systematic and valid comparisons. For future reference, it is important that these

limitations be overcome. When the full cost of a roads project is calculated there is a

need to ensure that all costs, including local authority administrative overheads, are

included irrespective of whether or not they are recouped by the Department.

A development of some significance has been the introduction from 2008 of a new

„Costing Service Structure‟ for local authorities. This is being rolled out by the

Department of the Environment, Heritage and Local Government. A key reason is to

enable the “identification of the full cost of delivering services and the corresponding

169

unit cost” (DEHLG, 2007e). The main difference between the old and the new system

is that overheads were formerly apportioned on the basis of a Programme Group.

Under the new system, overheads are being charged against specific services. This

will make it easier to identify the full cost of providing the service.

The potential of the new system was discussed during the interviews with the local

government officials. The emerging consensus is that the new system will provide the

wherewithal to more fully assess the costs of providing roads infrastructure. This has

the potential to benefit both local authorities, and the Regional and Local Roads

Division of the Department. The local authorities are currently absorbing

administration costs, which are not being recouped by the Department, but are not

being routinely reported either. In effect, these costs are currently invisible.

8.7. Maintenance

The construction of roads gives rise to maintenance requirements and these have cost

implications. The official VFM Guidelines, and the Department of Finance Capital

Appraisal Guidelines advise that maintenance costs should be considered in the

evaluation and appraisal of projects. The future maintenance needs of the roads

funded under the Programme are the responsibility of the relevant local authorities.

Given that maintenance costs will, in the main, fall to be met by the local authority they

were not considered when projects were selected. Irrespective of who is responsible,

these costs will arise and will have to be met at some point in the future. Maintenance

is essential to ensure that the road does not deteriorate and continues to deliver

benefits. The most significant expense will be incurred when the road has to be

rehabilitated at the end of its design life. This is the focus of the review here. There

are also further expenses related to items like road makings, signalling and signage.

The level of maintenance is crucially dependent on the standard of design and

construction when the road is being built. Based on the questionnaire returns, and

responses given in the interviews, specifications drawn from the National Roads

Authority Design Manual were used across the Programme in almost all cases. These

allow for a design life of 20 years. Even with increases in traffic well above the norm,

the projected 20-year design life should hold true across the Programme and may

even prove to be conservative. By way of a recent example, the first bypass of Naas

in 1983 (the M7) was designed to a similar standard as the roads under the

Programme. It lasted 24 years before needing rehabilitation works. Incidentally, the

original Cost Benefit Analysis estimated a lifespan of 20 years.

170

At the end of their design-life this „rehabilitation‟ will involve works to restore the

strength of the road, and the quality of the surface. Based on current unit cost

estimates from 2008 (provided by the NRA), the cost of carrying out this work is

approximately €70 per square metre. This represents the cost of high quality works

carried out a heavily trafficked national route. If every square metre of the 103,985

metres of road funded under the Programme required rehabilitation to this standard,

the total cost would be approximately €61m in 2008 terms (without applying discount

rates to represent the real cost of future expenditure). This should be treated as a

general indicative estimate, given the substantial differences between projects.

Nonetheless, it is illustrative of the potential future costs that will need to be met, most

likely by local authorities.

8.8. Conclusions and Recommendations

Over the lifetime of the Programme a prevailing trend has been towards cost

increases. Based on a comparison between the financial information contained in the

original application forms and the final costs as reported in the questionnaire returns,

the original costs were underestimated. While some of the cost increases affecting

projects were exceptional, there are lessons that can be learned for the future. Cost

increases were caused by construction inflation, changes in the project specification

after initial approval, specific problems affecting individual projects (e.g. environmental

issues and contract disputes) and land cost increases. Delays were also a

contributory factor. When applications were submitted in 2000, they contained cost

estimates and some limited supporting information. They were approved on this basis,

and the Department was then fully committed to supporting them. As more detailed

plans were prepared and implemented the estimated costs increased. The

Department was faced with a difficult choice of cutting back on projects, or allowing

them to proceed by providing additional funding. In all but a few cases, it chose the

latter option. The following points arise from these conclusions:

There is a need for more robust cost estimation;

Time-scales for commencement should be based on a realistic assessment;

Contingency for inflation should be built in to estimates;

The risk of delays and cost increases should be assessed at the outset;

Given the dramatic impact that land prices can have on the total cost, the

Department should await a more definitive estimate before giving final approval

to proceed.

171

While, the Exchequer contribution to the Programme increased by 28%,

proportionately the local authorities took on additional responsibilities in meeting cost

increases. The new system of development levies provided important additional

funding. This supports a finding from the previous chapter where development levies

were also instrumental in supporting roads submitted but not selected under the

Programme. When established, it was decided that Department would provide a

maximum 75% of original costs, with the local authority funding at least 25%. Based

on circumstances as they prevailed at the time, this decision was soundly based.

Record levels of development in recent years have made substantial additional

resources available to local authorities. While this may not continue in the longer term,

development levies still represent an important source of funding for future roads

infrastructure.

From an efficiency perspective, the use of competitive tender for the procurement of

design and construction contracts was the norm across the Programme. This

represents a shift from earlier studies in 1997 and 2002.

The preparation of a unit cost per square metre of road constructed can facilitate

limited comparisons between similar projects. Given the substantial differences

between projects, and the number of variables affecting cost, a programme-wide unit

cost comparison is not possible. The difficulties encountered in preparing unit costs in

the review are consistent with prior experience in this area.

Outputs were greater than expected, but so too were costs. Controlling costs will be a

key issue in improving efficiency for the future. In the main, the Programme is being

efficiently administered. Administration costs compare favourably with those reported

in other VFM reviews. They also stand up well when compared with other roads

programmes in England and Scotland. Administration costs within local authorities

proved difficult to calculate, but the introduction of a new system of overhead

apportionment should improve matters. Most roads under the Programme have a

design-life of 20 years. At that point, rehabilitation works will be required. As an

indicative estimate, this could cost up to €61m (in 2008 terms).

Arising from these conclusions the following recommendations can be made:

10. The Department should not give full and irreversible approval to projects based

on initial cost estimates.

172

11. Problems related to cost increases and delays should be addressed through a

more formalised structure or framework for project appraisal, approval and

monitoring. This is the main focus of Chapter 9, which follows.

12. Where a proposed road project has the capacity to generate development levies,

there is a case for this to be reflected in the proportion of funding provided by the

Department.

173

Chapter 9

“Evaluate the degree to which the objectives warrant

the allocation of public funding on a current and

ongoing basis and examine the scope for alternative

policy or organisational approaches to achieving these

objectives on a more efficient and/or effective basis.”

9.1. Emerging Analysis on the Current Policy Position

The policy context for the provision of strategic regional and local roads, and the

planning of roads infrastructure has shifted considerably since the Programme was

established in 2000. This was already examined in some detail in Chapter 5. In

many ways the current policy objectives, and the means to address them have

already been mapped out in the review. As Ireland‟s population grows and as the

number of people occupying each dwelling falls, there will be considerable demand

for housing. The projections are set out in the Department of the Environment,

Heritage and Local Government‟s policy document „Delivering Homes Sustaining

Communities‟, and are consistent with other credible sources. There will also be a

need to provide infrastructure to support industrial and commercial sites. This is

recognised under the National Spatial Strategy and the National Development Plan.

The findings of the review confirm that roads infrastructure does play an important

role in facilitating housing and industrial development. However, the pressing and

immediate conditions that gave rise to the creation of the Programme no longer

prevail.

Housing supply peaked in 2006, and has since declined. The housing facilitated by

the Programme contributed to record levels of output. Given the established inverse

correlation in Ireland between housing supply and price (OECD 2006, Bacon 1998),

it can also be said that this increased output has contributed to a softening of the

serious house price inflation that was prevalent. When the Programme was

established in June 2000, year-on-year house price inflation were running at 21%,

having earlier reached record levels of 30% (Permanent TSB/ESRI). From mid-2001

to mid-2007 house price increases have fluctuated between 2% and 15%, but never

again reached the record levels experienced between 1998 and 2000. In July 2007,

the year-on-year price declined for the first time in over a decade and has continued

174

to fall since (ibid.). Apart from the impact of increased supply on price, there are

currently a number of other factors exerting downward pressures on house prices.

These include the slower rate of economic growth, higher interest rates, and current

problems in the international financial sector caused to a large extent by sub-prime

mortgage lending to high-risk customers.

Notwithstanding current difficulties in the market, the long term demand conditions

indicate the need for a significant future housing supply in Ireland. The developers

interviewed as part of this review confirmed that demand (and consequently supply)

in the short term has contracted, but were also of the view that in the long term it

should recover, although not at the same levels experienced at the height of the

housing boom up to 2006. Nevertheless, the market failures that particularly affect

the housing market that were acutely prevalent in Ireland in 2000 are not as evident

today.

The framework within which current and future development is taking place is a

hierarchy of planning policy, the most important element of which is the National

Spatial Strategy. Flowing downwards from the NSS are a series of other policy

documents that direct and guide planning decisions. Within the interviews with local

authority officials, the view was consistently expressed that these policy initiatives

are now driving planning and development policy at local level. These views were

corroborated in the three case studies areas of Tramore, Killeen Road / Park West

(Dublin City) and Naas. Evidence was identified that the principles of sustainable

development and planning as enunciated in the National Spatial Strategy are being

incorporated into local development plans. More importantly, there is evidence that

they are influencing planning decisions at a practical level.

In considering options to meet policy objectives, it is advisable that all possibilities be

considered, including a „Do Nothing / Do Minimum‟ scenario. In the case of the

current review, this option would effectively involve winding up the Programme when

the remaining funding commitments totalling €70m (including 2008) are met. Given

that the current programme was a dedicated policy response to a series of

exceptional circumstances that prevailed at the turn of the millennium, this is an

approach that can now be validly recommended. However there is an important

caveat. While this specific programme may no longer be required, there is still an

identified need to support the provision of strategic roads infrastructure. The

changed policy focus of recent years has already been reflected in the new

175

programme established in 2006 to provide exchequer funding for strategic regional

and local roads that support the implementation of the National Spatial Strategy.

The current National Development Plan includes a clear commitment to regional and

local roads, and explicitly recognised the role of the new programme:

“A key objective for the Plan will be to provide a non-national road

network which will support economic and social development at regional

and local levels. This will be achieved, inter alia, through the

acceleration of the Non-National Roads Restoration Improvement

Programme and the continuation of the scheme to assist Local

Authorities in progressing new major strategic non-national roads

projects” (NDP, 2007, p.85)

“NDP 2000-2006 saw major investment in key strategic non national

roads, especially in urban areas. This investment will be built upon in

the new plan with a particular focus on roads in the NSS Gateway

areas”. (ibid., p 133)

The Department of Transport‟s new Statement of Strategy reiterates this

commitment (2008, p40). It is against this background that the direction of current

policy can be interpreted. The objectives of the Programme under review revolved

around the delivery of housing and lands for economic development. Such needs

still remain, but are now more appropriately addressed within the context of the

National Spatial Strategy. There is no longer a need for a specific housing-focused

roads programme. However, there is still a need for strategically-targeted exchequer

expenditure on regional and local roads that support social and economic

development, particularly at regional level. Evidence from the review, and in

particular from the case study areas, indicates that investment in local roads is

important in assisting economic development. At a general level, it supports targeted

population growth and spatial development that is vital to regional economic growth.

Such investment is crucial in facilitating the establishment of industrial and

commercial sites to allow for the spatial distribution of indigenous economic

development. Regional and local roads are also one of the factors that influence the

location decisions of foreign direct investment.

While the broader objectives of the original programme to support residential and

economic development are still valid, they should be subsumed into the new

programme. Therefore, the key issue arising is not whether the current programme

176

should be re-established or extended. Policy-needs and the mechanisms to meet

them have moved on. Likewise, the question of whether or not there should be a

new programme with a different and broader focus has already been answered in the

NDP 2007-2013, and Department of Transport‟s Statement of Strategy.

The emphasis in this chapter is therefore on the organisational approaches that will

improve the efficiency and effectiveness of the newer programme established in

2006. The previous chapters highlighted some of the key issues that arose in the

current programme. Chief amongst them were delays and cost increases. When

these arose, the Department addressed them in an organised fashion. Options were

considered and decisions taken. However, there is a case for adopting a more

systematic approach to the appraisal, sanctioning and review of expenditure

commitments. The Programme did deliver more housing and development lands

than anticipated. It was also important in facilitating local development. Economic

benefits arising from development are identifiable. The roads were an important

factor in achieving these benefits. However, cost increases somewhat undermined

the more positive outcomes.

While there is a case for continued exchequer investment in strategic local roads, the

problems identified in this review need to be tackled if efficiency and effectiveness is

to be optimised. In essence, there is an identified policy need to support strategic

regional and local roads, but not at any price. The Department of Transport

„Guidelines on a Common Appraisal Framework for Transport Projects and

Programmes‟, published in 2007 offers a structure that can be applied. These

guidelines are compatible with the Department of Finance „Capital Appraisal

Guidelines‟ published in 2005. In many ways the DoT Guidelines are more relevant

to public transport projects, especially in their focus on certain benefits that are more

likely to arise in the case of rail and bus investment. But the template it offers is still

relevant and can be used for regional and local roads, and adapted if necessary.

Drawing upon the DoT and Department of Finance Guidelines, this chapter will

therefore recommend practical ways in which issues identified in the review can be

addressed. However, before this can be considered, it is important to examine the

origins and objectives of the newer strategic roads programme mentioned already.

177

9.2. The New Strategic Regional and Local Roads Programme

As has been outlined, the Programme was introduced in 2006 to assist with the

provision of major schemes that support the National Spatial Strategy. At that time

local authorities had identified a series of regionally important roads that required

significant investment which were beyond their ability to fund from their own

resources. These roads were needed in order to facilitate regional development

objectives. Many of these proposals were already submitted under the Department‟s

„Specific Improvement Grants‟ scheme. However, this tended to fund smaller scale

projects. The County and City Managers Association had also made a case to the

Department for a new strategic programme.

Initially, appropriate projects were selected from the major schemes that had already

been submitted to the Department. 12 projects were funded under the new

programme in 2006 and 24 funded in 2007 (of which 8 were specifically limited to

design stage only). In 2008 this has risen to 33 schemes. While project proposals

under this new programme were assessed in terms of their merit, there was no

formal call for applications or an application form for the submission of proposals.

This may be understandable, given that the projects originally selected were already

known to the Department, and their very presence contributed to the case for setting

up the new programme.

However, in the interests of transparency, and to facilitate the uniform and consistent

appraisal of projects going forward, there is a need to introduce a formal and

structured application process for the allocation of funding. Based on meetings with

Departmental staff, such a need has already been acknowledged. The DoT

Statement of Strategy also recognises the need for effective management and

monitoring arrangements for regional and local roads programmes (2008, p.43).

In the process of developing a formal application and appraisal mechanism there is

also a need to re-state in more detail, the objectives of the new programme. These

are currently set out in general terms. This harks back to a more fundamental

principle that has informed the review – in order for an appraisal or evaluation to be

effective, the objectives of the Programme should be clearly stated. It is already

clear that the primary objective of the Programme is to contribute to the fulfilment of

the National Spatial Strategy through balanced regional development, with a

particular focus on the NSS Gateway areas. In practice, this objective would benefit

from being fleshed out.

178

To help clarify the focus of the new programme, there is already a set of ready-made

criteria to assist in identifying projects that can contribute to regional development.

These are detailed in the Department of Transport Guidelines already mentioned

above. The following types of project are regarded as positive to regional balance:

Projects in Gateways or giving local access to Gateways in the peripheral

regions;

Between Gateways in the peripheral regions;

On routes accessing international ports and airports;

On radial routes to the East region, where such routes improve access to

international ports and airports (DoT, 2007, p.27).

In the interests of consistency in meeting the Department‟s policy objectives, it would

be appropriate if the Regional and Local Roads Division used the above list as

guidance to inform its selection of projects. Given the new programme‟s stated

objectives to support the National Spatial Strategy, there is a case for placing

particular emphasis on the first two bullet points.

The new strategic programme would also benefit from having some sort of defined

time frame within which it is expected to operate. A logical lifespan would be the

duration of the current NDP, up to 2013. In advance of this date, the Programme

and its objectives could be reviewed, before the successor to the present NDP is

agreed. While the current programme did encounter delays, the fact that it had a

limited and defined lifespan gave a focus for its delivery. It also provided a basis on

which assessments could be made as part of this VFM review. The design of the

original programme included elements of what is now considered to be good

practice. While the Programme predated the NESC‟s report on the „Management of

Public Expenditure‟, it reflects many of its subsequent recommendations. These

include; the Programme having strategic focus (2002, p.144), an emphasis on

measurable outputs (ibid., p.146) and a completion date in the form of a „sunset‟ or

termination clause (ibid., p152). That is not to say that improvements can‟t be made,

though.

9.3. Assessing Benefits and Costs

The original strategic roads programme was set up with a particular purpose in mind.

Quantified deliverables were measured in terms of housing and development lands.

179

This was understandable given the focus of the Programme and the prevailing policy

objectives of the time. A central theme running through this review is that the policy

focus has shifted and broadened. Although useful as a basis for this review, outputs

like residential housing units and hectares of lands are limited in the types of benefits

they capture. Such indicators do not, for example, identify the extent to which

development is compatible with the objectives of National Spatial Strategy, or other

key planning policy documents. They do not capture economic benefits like

improved accessibility that are key to facilitating access by companies to their

potential workforce, and which enables people to access employment more easily.

The review has identified these and other benefits that have arisen as a result of the

Programme. There is therefore a need for a more broadly focused set of headings

and indicators against which projects can be appraised.

The approach recommended in the Department of Transport Guidelines is described

as an “objectives led framework that employs both multi-criteria and cost benefit

analysis” (DoT, 2007, p.i). The policy goals and objectives are set by the political

and administrative process, and used as a basis for carrying out the appraisal. The

Guidelines recommend that a „Project Appraisal Balance Sheet‟ be used and that

potential projects be assessed against 5 separate headings as follows:

Economy,

Safety,

Environment,

Accessibility and Social Inclusion,

Integration [with other local and national policy objectives].

The „Balance Sheet‟ presents a summary of the appraisal results in three forms:

A Qualitative Statement summarising the impact of the project in qualitative

terms.

A Quantitative Statement that sets out quantified and monetised indicators of

impacts.

A scaling statement that ranks the project on a five-point scale in terms of

each criterion. The scale ranges from „highly negative‟ to „highly positive‟.

By way of an example, for the Economy criterion typical quantitative benefits would

arise through time-savings as described in the opening chapters of the review, where

the techniques associated with Cost Benefit Analysis were explained. While these

180

types of benefits are important and traditionally form the core of costs benefit

analysis, the „Balance Sheet‟ approach allows them to be combined in a more

measured and overall assessment. In situations where only limited monetisation of

certain economic benefits is possible (typically with strategic roads in urban areas),

there is scope to consider other types of quantitative and qualitative effects. The

„Qualitative Statement‟ can be particularly useful here. A significant advantage of the

Balance Sheet approach in appraising regional and local roads is that it would allow

a fairly clear and concise list of costs and benefits to be articulated in summary form.

The Guidelines note that multi-criteria analysis sometimes encompasses a ranking or

weighting system. However it leaves it open to policy makers within individual

transport sectors to adopt weightings that are appropriate to their own situation (ibid.

p.10). For the new programme, there is a case for a positive weighting towards the

„Integration‟ criteria, which appraises the degree to which the proposal is compatible

with other local and national policies. The benefits of integrated development were

particularly identified in the case study areas within the review, and a

recommendation to this end was made in Chapter 7. A particular emphasis here

should be on the National Spatial Strategy and the planning hierarchy that flows from

it. Under the „Economy‟ criterion, improved accessibility between locations is also an

important factor.

While the template provided by the DoT Guidelines provides a useful basis for

appraising potential investment in local and regional roads, it could be adapted to

reflect the particular requirements of policy in this area. In other words there is a

case for using the guidelines as a basis for developing a more specific structure that

could be used in the appraisal of strategic local and regional roads projects.

9.4. Stages and Level of Appraisal

Both the Department of Finance and Department of Transport Guidelines set out a

staged process whereby potential projects are appraised, and either progressively

sanctioned, or not approved. At any stage in this process, the guidelines advise that

the Sanctioning Authority (i.e. the Department) and Sponsoring Agency (i.e. the local

authority) should be prepared to abandon the project, if continuation would not

represent value for money. This is an important issue of relevance to the

Programme under review. The two most serious problems that arose related to

delays and increased costs. The staged appraisal process would allow for these

issues to be considered in a formal structured fashion. A valuable advantage of

181

linking this approach with the „Summary Appraisal Balance Sheet‟, is that it would

enable comparisons to be made between the relative costs and benefits when

changes occur in either. For example, if the cost of land was significantly

underestimated, or construction costs were subject to serious inflationary effects in

the course of the project‟s planning phase, these could be assessed against the

expected benefits and a decision taken as to whether the project was still justified.

An issue identified in the current programme was the position the Department found

itself in when costs began to increase. The Department had approved grants in

2000 based on information provided in an application form. The application was

supported in most cases by some very basic additional information like maps and

drawings. Cost estimates in a significant number of instances were less than robust

and timescales for delivery were over optimistic. The Department dealt with the

consequences of these issues, and considered a number of individual cases for

increased funding, particularly in 2001 and 2002. When cost increases became a

more serious programme-wide issue, the Department was faced with the difficult

choice - either provide more funding or shelve a number of the projects. These were

the options considered when the review of allocations took place in 2003 and an

additional €43m in funding was sanctioned. Based on the findings of this review,

future programmes would benefit from having a formal system in place to deal with

such issues when they arise.

The staged approach to the appraisal and management of projects in the

Department of Finance Capital Appraisal Guidelines can provide a basis for

developing a system to be used for local and regional roads. These Guidelines set

out the four different stages in making capital investment decisions;

(1) Appraisal

(i) Preliminary Appraisal - to assess whether the project has sufficient merit to

justify a full detailed appraisal.

(ii) Detailed Appraisal – which aims to provide a basis for a decision on whether

to drop or re-scope a project or approve it in principle.

(2) Planning / Approval

This involves detailed planning and costing of the project: no commitment to

finance a project should be taken until this stage is completed and a decision on

whether to proceed is taken.

182

(3) Implementation

This requires clear arrangements for monitoring progress and cost control,

securing standards and timely delivery.

(4) Post Project Review

This is an assessment of both the project outturn and the appraisal and

management procedures used.

(Dept. Finance, 2005, p.5/6)

What happened in the case of the current programme was that projects were

approved in full after the preliminary appraisal at Stage 1(i), rather than after Stage 2.

Some modifications to this approach have since been made. With the new strategic

roads programme, the Department has adopted a more incremental approach by

initially sanctioning funding for planning and design work in advance of making a full

commitment. There would be merit in formalising this system. Given the experience

of the current programme, there should be a facility for the Department to review the

level of costs and the case for the proposal once full planning, design and land

acquisition issues become clear.

An issue of some importance concerns the level of appraisal that should be carried

out. The ex-ante appraisal of project proposals can have significant resource

implications, both for the local authority and the Department. Depending on the

method adopted, and the level of detail required, project appraisal can be both

complex and relatively costly to undertake. The Department of Finance Guidelines

recommend that the appraisal should be commensurate with the costs of the project

and the degree of complexity involved. It sets out a series of cost thresholds, and

the appropriate methodologies to be employed within different expenditure bands.

These can be summarised as follows:

Less than €0.5m - simple assessment with a single appraisal,

Between €0.5m and €5m - single appraisal, incorporating elements of both

Preliminary and Detailed Appraisal (as described above),

€5m to €30m – „Multi Criteria Analysis‟,

Over €30m - full „Cost Benefit Analysis‟.30

30 The original guidelines published in 2005 stipulated that a full CBA was required for projects costing in excess of €50m. This was revised downwards in January 2006.

183

Had they been subjected to these requirements at the outset in 2000, only 3 of the

original 43 projects would have required a full cost benefit analysis. 27 had

estimated costs below the €5m threshold. The remaining 13 had estimated costs of

between €5m and €30m. Taking the actual expenditure as a benchmark (as

reported in the questionnaires), 7 of the 44 projects that currently comprise the

Programme had costs in excess of the €30m threshold that would have required a

CBA. 19 projects are under the €5m mark. The remaining 18 cost between €5m

and €30m, which would fulfil the requirement to undertake a multi-criteria analysis.

Based on this information, a challenge is to develop a systematic approach to

appraisal that can be commonly applied over the entirety of the new Strategic

programme, but that takes account of the varying levels of expenditure, and

consequentially, the need to have different levels of appraisal.

A potential solution can be found in the selection process for the „Specific

Improvements Grant‟ Scheme‟. To recap, this scheme provides grant funding for

roads that support local and regional economic development, in line with EU criteria

and objectives. The „Specific Improvements‟ programme uses a comprehensive

application form that combines both quantitative and qualitative elements in

assessing proposals. For example, it allows for statements and supporting evidence

to be provided on impacts related to the National Spatial Strategy. The level and

type of commercial traffic usage is taken as a proxy in determining the economic

importance of the road. The information requirements on cost estimates are quite

detailed, as are the data requirements dealing with technical, structural and

engineering issues. However, quantitative indicators covering areas like projected

time-savings, accident reduction data or an overall rate of return are not sought.

If this application form were restructured and expanded to take account of the policy

objectives of the new Strategic programme, and the requirements contained in the

Department of Transport Framework Guidelines, it could be effectively used as the

basis for of the „Single‟ appraisal in the case of projects costing less than €5m. It

could also be simultaneously used on projects costing more than €5m for the

„Preliminary‟ appraisal, as envisaged under the Capital Appraisal Guidelines. If

these larger projects were found to have merit, they could then undertake a more

detailed multi-criteria or cost benefit analysis, as is required. Both the application

form and any subsequent CBA or MCA could also be based around the stated

objectives of the Programme, and the relative importance attached to specific

assessment criteria.

184

Irrespective of whether or not an application form is used as the basis of the

preliminary appraisal, some form of structured approach is needed. The alternative

would be for the Department to issue more generalised guidelines on the submission

of proposals for funding under the Programme. These would set out the criteria

against which the proposal would be assessed, and list the information required from

the local authorities in order for the Department make decisions on the relative merits

of proposals. This is a viable option, although for a variety of reasons, using the

format of an application form has a number of potential advantages, namely:

It would minimise confusion on the part of local authorities in the information

requirements of the Department.

It is a format that local authorities are familiar with and currently use in

applying for regional and local roads grants.

It would allow comparisons to be made by the Department between projects

in terms of their costs and benefits.

It would allow cost data to be collected under uniform headings across the

Programme.

The issue of administrative resources is also important. In the previous chapter it

was noted that the Regional and Local Roads Division is administering a significant

budget, and is spreading its resources quite widely. Relatively speaking, the

administrative commitment to the Strategic Non-National Roads programme

compares favourably with other similar programmes. It can even be suggested (as it

has been previously in the 2002 Fitzpatrick review), that the staffing levels available

for the monitoring of the Programme are relatively limited, and that the Division may

even be under-resourced. Notwithstanding these issues, having a standardised

application format would enable proposals to be processed more efficiently. For

these reason it is recommended that an application form be developed, with

appropriate supporting information to assist local authorities in complying with any

new requirements.

A new system for the appraisal and approval of projects has the scope to provide a

consistent and structured approach. It would also provide a framework to deal with

the two key problems of delays and cost increases that were identified in the review.

In assuring value for money in the management of capital expenditure on roads,

185

there is also a further vital element that requires consideration. This relates to

tenders and contracts.

9.5. Contracts and Value for Money

Chapter 8 identified a growing trend towards the use of competitive tender contracts

in regional and local road works, particularly within the Programme under review.

This represents a shift in previous experience and is in line with international best

practice. In these circumstances the manner in which contractors are engaged and

works undertaken is becoming a more important element in project management.

Currently, there is a system within the Regional and Local Roads Division to monitor

and approve tender contracts31. Documentation must be submitted to the

Department for approval in advance of advertising for tenders. These include key

documents like the „Bill of Quantities‟, „Instruction to Tenderers‟, „Forms of Tender‟

and the Drawings. This requirement applies to all regional and road contracts with

an estimated tender value of €2m or more, and all bridges/structures contracts

valued at €0.5m or more. The examination of contract documents and tenders is an

important function undertaken by the Division in assuring both quality and cost

control in its administration of public funds. Within any new appraisal structure, it

would be important that this facility is incorporated, possibly as a central element of

the „Planning / Approval‟ stage. From the point of view of efficient administration, it is

equally important that the process is not replicated.

The Department‟s examination and approval of contract documents happens when

the tender is being finalised. However, issues can and have arisen after the

contractor has been selected and works commenced. This was discussed within the

interviews with local authority officials. In a number of cases, the view was

expressed that where circumstances allow, contractors will submit claims for extra

costs where any additional or unforeseen issues arise. Any modifications,

insignificant or otherwise, can and invariably have resulted in claims. The structure

of public works contracts as they have heretofore existed, allowed this to happen.

While the review did not quantify the extent of such impacts on the Programme, they

were identified as being a prevalent factor. This is a far wider issue that stretches

beyond local and regional roads and has been the subject of major reform over the

past two years. Since February 2007, new public works projects must be undertaken

using a „Fixed Price Lump Sum Contract‟. Similar conditions relating to the

31 As set down in the Department‟s „Memorandum on Roads Grants‟ (DELG, 2001), and subsequent Circular letters RLS 28/2005 and RLS 10/2007.

186

engagement of construction consultants are also in place. The arrangements for

giving effect to these changes are set down in Department of Finance Circular 33/06

„Construction Procurement Reform‟ (2006a), and in the detailed „Capital Works

Management Framework‟ (2006b)32. The Regional and Local Roads Division of DoT

has given effect to new procurement requirements in its own circulars and guidelines

issued to local authorities33.

What all of this means is that there is little the review can recommend in the way of

improvements that have not already been implemented. The element of „Risk‟

arising from unforeseen issues emerging in the course a project is now priced into

the tender. The new contract arrangements were discussed in some of the

interviews with local government officials. A common view (albeit based on a limited

number of opinions) was that inclusion of „risk‟ within the contract may make the

initial price higher, but brings benefits through greater certainty in cost estimation.

This was welcomed. Local authorities also reported that the new requirements

necessitate a more detailed and precise definition of works when tender documents

are being prepared. This is resulting in additional work for them at pre-tender stage.

Overall then, it can be noted that the use of fixed-price lump sum contracts as

standard, represents a further significant element in the assurance of value for

money. This particularly applies in the case of consultancy work at design and

planning stage, and in relation to construction contracts. The third major element in

the cost of providing regional and local roads is land. The previous chapter identified

the dramatic effects that rising land costs had on a large number of projects within

the Programme. It was a widely held view among local authorities that rising lands

prices are a factor that is putting potential future roads projects at risk. The scope for

making localised arrangements with developers to offset these costs was also

considered. The next section looks at recent proposals being discussed in the public

arena to address the consequences of rising land costs.

9.6. Dealing with the Rising Cost of Land

The balance between property rights, and the acquisition of land for public

development purposes was comprehensively addressed in the 2004 report on

32 Some additions to the original requirements were recently made through Department of Finance Circular 4/08, issued in February 2008. 33 Circular NNR 27/2007 and RLSD 09/2008, both of which are entitled „Procurement Procedures for Regional and Local Roads‟.

187

„Private Property‟ by the All-Party Oireachtas Committee on the Constitution. It has

already been noted that the Constitution guarantees the right to private property of its

citizens, and that these rights are regulated by the principles of social justice. A key

purpose of the Committee in undertaking its work was to assess whether proposals

on the acquisition of private lands by public bodies that were originally put forward in

the seminal 1973 „Kenny Report‟ would require constitutional change in order to be

implemented.

By way of background, in the early 1970‟s a committee chaired by Mr. Justice Kenny

was established by the Minister for the Environment and Local Government. Its

remit was essentially to put forward proposals to control the price of land required for

housing and other development, and for ensuring that some of the „betterment‟

arising from the zoning and servicing of lands be recouped by local authorities for

wider public benefit. The committee‟s recommendations were published in 1973 and

became known as „The Kenny Report‟. As the housing boom took hold in Ireland in

the late 1990‟s the report received something of a renaissance and began to be

widely quoted and advocated in public debates. It was against this setting that the

Oireachtas Committee undertook to examine whether there were constitutional

impediments to its implementation.

The central recommendation of the Kenny Report was that local authorities should

have the right to nominate „Designated Areas‟. Within these areas, land could be

acquired compulsorily, based on its „current use value‟, plus 25%. The land could

then be used by the local authority, or sold on at a higher price, thereby capturing a

portion of the „betterment‟. The proposal was never implemented, and disagreement

about its likely constitutionality continued in the 30 years following its publication. In

dealing with this core question, the Oireachtas Committee concluded that:

“it is very likely that the major elements of the Kenny Report

recommendations – namely that land required for development by

local authorities should be acquired at existing use value plus 25% -

would not be found to be unconstitutional….the committee is not,

therefore, persuaded that the existing constitutional provisions place

any unjustified impediment to infrastructural development.” (APOCC,

2004, p.137).

The Oireachtas Committee favoured the implementation of recommendations from

the original Kenny Report, with appropriate modifications to reflect changed

188

circumstances since it was published (ibid. p.142). Interestingly from the point of

view of transport and economic infrastructure, the National Roads Authority, Railway

Procurement Agency and Forfás (the state‟s enterprise promotion body) all argued in

favour of the implementation of the Kenny report recommendations, (APOCC, 2004,

p.95). They were concerned that rising land costs were making it increasingly

difficult to fulfill their respective functions. It is fair to speculate that if the Kenny

Report‟s main recommendation was implemented, the likely result would be a

reduction in the cost of land needed for works on strategic regional and local roads.

The Oireachtas Committee noted that there were alternative options available within

current policy parametres. It said that if the Kenny Report recommendations were

not implemented, there are mechanisms open to local authorities to recover

betterment. These they listed as follows:

Development Charges/Levies.

Planning Gain, whereby local authorities and developers enter into

agreements, as part of the grant of planning permission, which require the

provision of infrastructure and services, including social infrastructure such as

schools (Agreements under Part V of the 2000 Act are an example of

planning gain).

Taxation, this could vary from taxing the gains arising from increases in

value, to an annual site value tax.

Compulsory Acquisition of Land at existing use value in specified locations to

provide for social and affordable housing and other uses related to the public

good.

(ibid. p.143)

The tool in most common current usage by local authorities from the above list is the

development levy system. This probably represents the most realistic and practical

way of capturing betterment, and funding roads infrastructure. In the current

circumstances, development levies provide an avenue to systematically deal with the

issue of betterment. This is notwithstanding circumstances where local

arrangements can be made with developers.

The two previous chapters identified the key role played by levies in supporting

projects under the Programme, and in also allowing those that weren‟t selected to go

ahead. Based on the views expressed by local authority staff, many of the projects

189

wouldn‟t have happened had the new system of levies not been in place. On current

estimates, the Departmental grants under the Programme totalling €317m are being

supplemented by at least €267m from other sources, although this figure is likely to

be far higher. Development levies are the key source, with other local authority

revenues making an important contribution. It is a reasonable expectation on the

part of the exchequer that those benefiting from the provision of roads infrastructure

should provide some of the funding. It is clear that new and upgraded roads bring

economic benefits to the owners of lands in the relevant areas, particularly where

they are located in and around urban areas. Under the current programme, local

authorities were required to provide a minimum 25% of local funding, with the

Department providing up to 75%. Under the new Strategic Programme, there is

scope to provide up to 100% exchequer funding. The logic behind this provision is to

allow for the funding of roads between larger urban settlements where there is little

or no capacity to open up development lands along the route and generate levies.

Notwithstanding the validity of this view, there is still a case for requiring local

authorities to provide some contribution towards the provision of strategic roads.

The previous chapter recommended that where a proposed road project has the

capacity to generate development levies, this should to be reflected in the proportion

of funding provided by the Department. It is difficult to be prescriptive about a

precise figure, given the variation in local circumstances. However, the capacity of

roads to generate development levies should be reflected in the funding

arrangements for the roads, and the proportionate level of national / local

contributions.

9.7 Conclusions and Recommendations

The Programme was set up at a time of unprecedented supply and demand

pressures on the housing market. Those pressures have now significantly eased.

Since 2000, a new hierarchy of planning policies and structures have been put in

place. There is a now a greater focus on integrated and sustainable development.

As a reflection of this shift in policy, a new strategic programme to support roads that

contribute to the implementation of the National Spatial Strategy was put in place in

2006. A commitment to this programme is contained in the National Development

Plan 2007-2013, and the Department of Transport‟s Statement of Strategy. The

focus of this chapter has therefore been to recommend where improvements can be

made based on issues and problems identified in the review. The following

recommendations are therefore put forward:

190

13. Once the remaining €70m in commitments (including for 2008) to existing

projects under the Programme is met, the original Strategic Non-National

Roads Programme should be concluded. While the broader objectives of the

original programme to support residential and economic development are still

valid, they should be subsumed into the new programme to fund strategic

regional and local roads aimed at supporting the objectives of the National

Spatial Strategy.

14. Any new system for the appraisal, approval and monitoring of projects should

be based on the Department of Transport‟s „Guidelines on a Common

Appraisal Framework for Transport Projects and Programmes‟ (2007) and

Department of Finance „Capital Appraisal Guidelines‟ (2005). These should be

suitably adapted to reflect the policy priorities of regional and local roads.

15. In the interests of administrative efficiency, an application form should be

developed for the Programme. The structure of the application should be

consistent with information requirements as set down in the Department of

Transport and Department of Finance appraisal guidelines. This would allow

for the assessment of costs and benefits through the use of a „Project Appraisal

Balance Sheet‟. By implementing a staged approach, as recommended in the

Department of Finance guidelines, the application form could be effectively

used as the basis for „Preliminary‟ appraisal in the case of projects costing

more than €5m. If these larger projects were found to have merit, they could

then undertake a more detailed appraisal. The application form could also be

simultaneously used for undertaking a „Single‟ appraisal for projects costing

less than €5m.

16. Given the experience of the current programme, there should be a facility for

the Department to review the level of costs and the case for the proposal once

full planning, design and land acquisition issues become clear. In the case of

land acquisition in particular, a final estimate of costs should be provided to the

Department for approval before the „Notice to Treat‟ activating the Compulsory

Purchase Order is served on land owners.

17. Currently, contract documentation must be submitted to the Department for

approval in advance of advertising for tenders. This procedure should be

retained and incorporated into the new system of appraisal.

18. There is a need to re-state in more detail, the objectives of the new strategic

programme. These are currently set out in general terms. This will aid the

appraisal of proposed projects, and assist in monitoring and evaluation.

191

19. The new strategic programme would benefit from having a defined time frame

within which it is expected to operate. A logical lifespan would be the duration

of the current NDP, up to 2013. In advance of this date, the Programme and its

objectives could be reviewed, before the successor plan to the NDP is agreed.

20. There should be an expectation that some of the „Betterment‟ arising from the

road development be captured, either through „General‟, „Special‟ or

Supplementary‟ development levies. The capacity of proposed road projects to

facilitate development should be assessed when the project is being appraised

by the Department.

192

Chapter 10

“Specify potential future performance indicators that

might be used to better monitor the performance of

the Programme or other specific programmes related

to the grant support of roads infrastructure to

facilitate social and economic development”

10.1 Introduction

At the outset, the Scene Setting chapter considered the initial development and

adoption of performance indicators for regional and local roads. It has already been

noted that a good deal of progress has been made in their general application.

Consistent with widespread existing practice, especially in relation to the construction

of roads and other public infrastructure projects, there is a strong emphasis on inputs

and outputs. This chapter builds upon the earlier discussions, and brings them up to

date with an examination of more recent developments. The approach adopted is

consistent with good practice in the field. Boyle in his 2005 paper on civil service

performance indicators advises that a first step in developing indicators is “to

determine what existing performance indicators are in use, what aspects of

performance they cover, what gaps exist in coverage, and how these gaps might be

filled” (2005, p.8).

In analysing existing arrangements and considering the need for additional

indicators, this chapter also draws upon the guidance on performance indicators

issued by the Department of Finance „Management Information Framework‟ (MIF)

Project Management Group and Central Unit (MIF, 2001) (MIF, 2004). Their

recommended approach is based on the Programme Logic Model. The basic

principle is that indicators can be used to assess performance in relation to inputs,

activities, outputs and outcomes. When designing performance indicators, there is

always a danger that they become an end in themselves. At the outset it is important

to restate the benefits that good indicators bring to decision-making, whether in the

management of projects, in assessing performance across a programme, or in

determining higher-level resource allocation priorities between programmes. The

MIF „Users Guide‟ issued in 2001, contains a crucial piece of advice:

193

“Performance indicators are a means to an end. They are a key

component of the reporting structures to meet governance,

accountability and management requirements. The ultimate end is

achieving Government‟s policy objectives (outcomes) through the

delivery of efficiently and economically produced public services

(outputs)” (ibid., p.3)

This statement re-iterates something that is central to both good evaluation and the

effective application of indicators. The objectives of a programme must be clearly

specified. As Schacter has noted, it is difficult to gauge performance if it is unclear

what a programme is supposed to be doing in the first place (2002, p.3). Partly with

this in mind, the previous chapter noted the need to articulate more clearly and

concisely the objectives of the new Strategic Regional and Local Roads Programme.

The quoted extract above also points to important distinctions between different

levels and types of indicators. The MIF guidelines list five types of indicator (ibid,

p.7), which can be described as follows:

„Strategic‟ indicators – these are high-level indicators about performance on

policy objectives.

„Effectiveness‟ – these are used to assess if the Programme is doing what it set

out to do. Typically they would be used in high-level internal management

reports.

„Quality‟ measures. This can relate to the standards being achieved, and also

the level of customer satisfaction.

„Efficiency‟– these are predominantly quantitative with an emphasis on financial

data and the ratio between inputs / outputs. These would usually be used for

inhouse resource decisions.

„Activity‟ – these would typically look at throughput in an office.

The types of indicator employed and level of detail required are also dependent on

their intended use. For example, the indicators described in the Scene Setting

chapter covering resource inputs, roads outputs and activities are quite

comprehensive. These have mostly been developed in order to report on progress

in the implementation of successive National Development Plans. The Department

itself also gathers more detailed information on inputs and outputs for the purpose of

programme management and resource allocation. These allow for the determination

of unit costs per square metre on more standardised types of works.

194

10.2. Performance Management and Current Performance Indicators

Some elements of the Department‟s performance management system have already

been introduced. As a project moves from being a proposal into more detailed

design and tendering phases, the Department‟s Regional and Local Roads Division

is actively involved in reviewing and sanctioning progress through the different

phases. Approval of the key design and tendering documents is required in advance

of their operational use. As construction work commences and proceeds, the

Department monitors progress. Post-project spot checks are also undertaken. The

use of specific indicator data supports this work.

The scene-setting chapter at the outset also described the development of a

comprehensive range of guidelines manuals by the Department over the past ten

years. These cover the broad array of works involved in the maintenance and

construction of regional and local roads. The guidelines act as a key performance

management tool to assure compliance with standards that are set down by the

Department. Their objective is also to ensure the adoption of consistent approaches

across local authorities.

Clarity of purpose is an important factor in developing meaningful indicators.

Regional and Local Roads benefit from having their main priorities set out in the

Department of Transport‟s „Statement of Strategy‟:

“the main focus of the regional and local road investment programme is to

restore roads that have been identified as deficient in pavement condition

surveys, and to invest in strategic roads that support the implementation

of the National Spatial Strategy” (DoT, 2008, p.40)

The relevant „Key Performance Indicator‟ within the Statement of Strategy is

measured in terms of:

“schemes completed under the strategic regional roads programme” (ibid. p.43)

Using the MIF terminology, this can be seen as the main „Strategic‟ indicator.

„Effectiveness‟ indicators for roads have generally used outputs as proxies. For the

Programme under review, effectiveness has been assessed in terms of the roads

built, the number of houses provided, and area of lands facilitated for development.

For the „Specific Improvement Grants‟ scheme, the level of usage, particularly of

tourist and commercial traffic can be seen as an effectiveness indicator. That

195

programme has a particular objective to assist regional development and this

indicator is used in reports prepared for the Department and Regional Authorities.

„Quality‟ indicators are used to assure the standard of the road works undertaken,

and to assure compliance with technical requirements set out in Departmental

circulars and guidelines. „Efficiency‟ indicators are used within the Department in

comparing, for example, the cost per square metre, or linear kilometre of road

surfaced.

In 2006, the Minister for Finance announced a series of reforms affecting the Budget

and Estimates process. From 2007 all Departments were required to produce an

„Output Statement‟, in respect of their „Statement of Strategy‟. The Output Statement

is intended to set out the high level objectives for Departments, the strategies being

pursued to meet those objectives, and the actual outputs projected for the year. The

2007 Output Statement contained three sets of targets for regional and local roads.

For the strategic roads (the Programme being reviewed here, and the „new‟ strategic

schemes), the statement contains targets for the number of projects being brought to

planning stage during the year, those at construction stage and projects to be

completed. This has the potential to be an important indicator for the new

programme, especially in highlighting if the projects are not proceeding as planned

through their different phases. The other two indicators on the Output Statement

relate to the „Specific Improvement Grants‟ scheme and „Restoration Programme‟.

When funding decisions on Strategic roads are being considered, the technical

specification of the works must be submitted by the local authority. This includes, for

example, the types of materials used (concrete, asphalt, bitumen, macadam, etc.)

and the depth of the different layers (surface, base, and sub-base). Such data and

monitoring by the Department can be seen as a form of „quality‟ and „activity‟

indicator. Given its technical nature, interpretation of this data requires a level of

expertise. The data feeds into the Department‟s system of performance

management and is used as a monitoring and quality assurance tool.

10.3. Identifying Gaps in Current Indicators

From reviewing the systems currently in place, it is apparent that under each of the

five types of indicator as set out in the MIF guidelines, there are measures in place.

At a strategic level, indicators are published in the Department‟s Statement of

Strategy, and the annual „Output Statement‟. These can also be seen as high-level

196

effectiveness measures. There are also medium-level effectiveness and efficiency

indicators that are collated in reports to the Department and Regional Authorities.

Internally within the Department, indicators of Effectiveness, Quality, Efficiency and

Quality are routinely collected and used. This includes unit cost data. In the main

then, local and regional roads have a well-developed system of indicators. In

recommending additions or changes, there is always the danger of placing too many

demands on the system. As Schacter has noted, overly complicated performance

frameworks inevitably leads to implementation problems (p.27). However, there are

some specific gaps that can be identified in relation to the strategic roads

programmes.

Two very prominent factors in the review that affected performance were costs and

delays. In any new system of project appraisal, it would be important that both costs

and progress against expected deadlines be monitored. There is already a

requirement in the Department of Finance Capital Appraisal Guidelines that the

Sanctioning Authority (i.e. the Department) be notified if there is a change in costs, or

if factors arise that affect project delivery. There would be merit in having a

formalised system of reporting by local authorities on progress towards the

completion of their projects an annual basis. The Department does report at

aggregate level on the progress of the Programme within its annual Output

Statement. This is a strategic level indicator. At a management and operational

level, it is important that the progress of each individual project be regularly and

systematically tracked and compared against their original planned timescales.

A particular issue of concern identified in the Programme was that of cost increases

in general and land costs in particular. Information on land costs was gathered as

part of this review and helped place the scale of the problem of price increases into

perspective. In gathering information from local authorities, disaggregated data

should be collected in a manner that would allow for comparative analysis to be

regularly carried out on land costs. This should include the relative proportion of

land costs within the total project costs.

In addition to making comparisons across individual projects in relation to land costs,

it would also be beneficial from a management point of view if the relative costs of

the other headline cost elements were also systematically compared. At the moment

four main aggregate headings are currently used to differentiate costs are:

„Land‟, „Construction‟, ‟Design and Supervision‟, „Other‟.

197

These headings are used, for example, on the application form for the „Specific

Improvement‟ grants scheme. The benefit of having financial information routinely

reported in this format is that it allows for the relative effect of the two key cost

drivers of construction and land acquisition to be separately assessed. It would also

allow for the routine calculation of the cost per square metre of road constructed

under the new programme. However, as the review has already noted, technical

expertise would be required in assessing this data. It could really only be used as a

management tool for carrying out limited non-parametric comparisons between

similar projects. The Regional and Local Roads Division is already planning to use

these headings to gather and assess cost data under the new strategic programme.

The recommendation to introduce a new structure for the appraisal of projects is also

highly relevant in the development of performance indicators. The objectives and

criteria against which proposals are appraised at the outset should be used as

benchmarks when assessing performance. At its most basic, this would involve

comparing the projected inputs, outputs and outcomes, against those actually being

delivered. These indicators will be somewhat dependent on the final format of any

new system of appraisal, and the relative weighting given to different criteria in the

assessment of projects. It is therefore difficult to be too prescriptive at this point.

While indicators like the construction of the roads, and certain quantifiable outputs

related to journey time savings and levels of development can be gathered,

assessing changes in wider social and economic indicators may be more

challenging. The distinction that Boyle draws between „Programme‟ and „Context‟

indicators is therefore relevant. The former are issues for which the roads projects

can be held directly accountable, whereas the latter represent wider factors over

which there may be limited control. In referring back to the Department of Finance

Capital Appraisal Guidelines and the approach it recommends, the „Evaluation‟ stage

may be particularly beneficial in assessing social and economic indicators that can

be difficult to systematically monitor on an ongoing basis. As Mayne acknowledges,

when it comes to more complex outcomes where measurement and attribution is an

issue, the use of evaluation rather than performance indications is the ideal option

(1999, p.3). The following recommendations can therefore be put forward:

198

10.4. Recommendations

21. In the application form, evaluation documentation and monitoring reports, all

cost estimates should be disaggregated under the four standardised headings

of: „Land‟, „Construction‟, „Design & Supervision‟ and „Other‟. This is already

being done on other regional and local roads programmes. The format enables

comparisons to be made on the key elements driving the costs of projects.

22. Given its particular significance, disaggregated data should be collected in a

manner that would allow comparative analysis to be regularly carried out on

land costs.

23. Additional output and outcome indicators will be dependent on the final format

of any new system of appraisal, and the relative weighting given to different

criteria in the assessment of projects. It is therefore difficult to be prescriptive

at this point. However, quantifiable indicators should relate to roads outputs,

improved accessibility through journey time savings (where relevant) and levels

of development.

24. Using the framework set out in Department of Finance Capital Appraisal

Guidelines (2005), the more complex social and economic outcomes may be

better examined during the „Evaluation‟ stage of the Programme.

199

Chapter 11

Concluding Comments and Next Steps

11.1. Issues for Further Consideration Not Addressed in the Review

The Programme established in 2000 has been reviewed in terms of its outputs,

efficiency and effectiveness. Broader issues associated with the value of investment

in strategic roads have been examined. The pre-existence of the new strategic

regional and local roads programme has led the review to follow a certain direction.

What the current review has not done is consider the relative merits of the

Programme in comparison with other regional and local roads policies and

programmes. This was beyond its scope.

It is nevertheless worth putting the strategic programmes (both old and new) into

some sort of wider context. In 2008, state grants totalling €618.714m are being

distributed to local authorities by the Regional and Local Roads Division of the

Department of Transport. €40.324m was allocated to the strategic programme being

reviewed, while €45.909m was committed to projects under the newer strategic

programme. The two programmes together constitute around 14% of the total

budget. The remainder is spread across different funding categories that were

outlined in the introductory chapter. This review has shown that the Programme was

effective in terms of outcomes. It also identified problems that hampered its

progress. Ways and means of addressing these problems have been identified.

Recommendations are put forward to improve the capacity of the new programme to

deliver value for money. However, it was beyond the scope of the review to say if

strategic roads are more deserving of exchequer support than the other policy

priorities within the Regional and Local Roads Division. That is a question which will

need to be considered elsewhere, most likely in the political sphere.

A further and more complex question concerns the funding arrangements for local

government. Regional and local roads are a core local government responsibility,

and as such are bound up in wider debates about local government funding. Central-

Government funding of these roads comes from two principal sources, the „Local

Government Fund‟, and direct exchequer provision via the vote of the Department of

Transport. The Local Government Fund was established under the „Local

Government Act, 1998‟. It was set up as a means to compensate local authorities for

the loss in direct revenue that they incurred when rates on domestic and agricultural

200

properties were effectively abolished in the late 1970s. The Fund is financed from

the proceeds of motor tax receipts, and from an exchequer contribution. Following

the transfer of responsibility for regional and local roads from the Department of the

Environment, Heritage and Local Government to the Department of Transport in

2007, a portion of the fund (34%) is now ringfenced and transferred into the

Department of Transport‟s Vote for allocation to roads. The amount being

transferred in 2008 is €564.9m. An additional €53.814m was approved from the

DoT‟s vote, bringing the total budget in 2008 for to €618.714m.

While the Local Government Fund represents a stable and coherent system of

funding for local authorities, many of the bigger questions and debates about who

should fund local government continue. Regional and local roads have featured

strongly. The most recent significant initiative was the establishment by the

Government in February 2008 of a new Commission on Taxation. One of its terms of

reference is to; ”consider options for the future financing of local government” (COT,

2008). It is due to report to the Minister for Finance with recommendations by the

end of September 2009.

At issue here are higher-level policy questions about taxation, and far broader

concerns associated with the financing of local government. Such issues date back

to the origins of local government and feature regularly in policy discussions. A

subset of this debate over the years has been the financing of road infrastructure,

and the respective responsibilities of local and national government. In fact these

matters have been on the policy agenda since the advent of motoring at the start of

the 20th century (Daly, 2007). Such fundamental questions are likely to continue to

be debated into the future and stretch well beyond the scope of this particular review.

The review now returns to its original remit and makes some final comments.

11.2. Key Findings

At the outset, a particular challenge was identified when assessing the value of

investment in regional and local roads. Earlier studies had concluded that these

roads play a role in social and economic development, but had difficulty specifying

the precise nature of the contribution. Taking up this challenge, the review set out to

identify the manner in which regional and local roads interact with local development

decisions. This exercise required the use of multiple methodological approaches and

sources of data. Quantitative data on development outputs was combined with the

qualitative views of local authority engineers, planners and senior policy makers.

201

Drawing upon the experiences of other studies, a key decision was taken to consult

with builders and developers to seek their views. Localised demographic and

economic data was used to build a wider picture of changing development patterns

within case study areas. Based on this range of data sources it can be concluded

that strategic regional and local roads do make an important contribution to social

and economic development within areas where investment is targeted.

The particular objectives of the Strategic Non-National Roads Programme were a

product of the unique circumstances that prevailed when it was set up. It was a

necessary policy response, particularly when one considers the unprecedented

pressures on the housing market at that time. However, there is still a need for

investment in strategic roads, albeit with an emphasis on different objectives that

reflect current policy priorities. There are certain projects which are vital in facilitating

the strategic social and economic development of towns and regions, but that are

beyond the abilities of local authorities to fully fund from their own resources (even

with development levies). Investment in roads and other transport infrastructure is

important in achieving spatially balanced development across the State. In making

investment decisions, it is crucial that structures to appraise the costs and benefits of

proposed projects are robust and lead to the best choices being made. The central

conclusion from this review is that strategic roads are worthy of investment, and the

central recommendation is that a revised system of appraisal is needed to assure

value for money.

11.3. The Next Steps

A series of recommendations have been set out in this report, and the next step in

the Value for Money Review process is to follow through with their adoption. As the

VFM review was being completed between April and July 2008, work had already

commenced on the implementation of the Review‟s draft recommendations. The

Regional and Local Roads Division is now at an advanced stage in adapting the

Department of Finance Capital Appraisal Guidelines for use on its new strategic

programme. The new structure being put in place identifies the different stages for

the appraisal and approval of proposed regional and local roads projects. An

application form is being developed that incorporates the five appraisal criteria, as set

out in the Department of Transport‟s appraisal framework. The new application form

will act as the „Preliminary Appraisal‟ for projects costing over €5m. Multi-criteria or

Cost-Benefit Analysis will also be required for projects costing more than €5m. Draft

guidance notes to assist local authorities in complying with the Department‟s new

202

requirements are also being prepared. The new appraisal structure is expected to be

rolled-out in September / October 2008. The work of the Department is developing

these new structure and the related supporting documentation has also been

informed by new project appraisal guidelines published by the National Roads

Authority in March 2008.

Considerable progress has already been made in implementing the review‟s key

recommendations. Carrying through the recommendations, and monitoring their

implementation, will now be the responsibility of the Regional and Local Roads

Division of the Department of Transport.

203

Appendix I – Bibliography APOCC (2004), All-Party Oireachtas Committee on the Constitution, „Ninth Progress Report – Private Property‟, Stationary Office, Dublin. Bacon P., MacCabe F. & Murphy A. (1998), „An Economic Assessment of Recent House Price Developments‟, Report Submitted to the Minister for Housing and Urban Renewal. Government Publications Office, Dublin. Bacon P., MacCabe F. & Murphy A. (1999), „The Housing Market: An Economic Review and Assessment‟. Report Submitted to the Minister for Housing and Urban Renewal. Government Publications Office, Dublin. Bacon P. & MacCabe F. (2000), „The Housing Market in Ireland: An Economic Evaluation of Trends and Prospects‟, Report Submitted to the Department of the Environment & Local Government. Government Publications Office, Dublin. Barker, Kate (2003), „Interim Report – Analysis, Review of Housing Supply, Delivering Stability: Securing our Future Housing Needs „, HM Treasury, London. Barker, Kate (2004), „Final Report – Recommendations, Review of Housing Supply, Delivering Stability: Securing our Future Housing Needs‟, HM Treasury, London. Barrett, Sean (1982), „Transport Policy in Ireland‟, Irish Management Institute, Dublin. Barrett, Sean & Mooney, David (1984), „The Naas Motorway Bypass – A Cost Benefit Analysis‟, in Mulreaney, Michael (ed.), „Cost Benefit Analysis Readings‟, IPA, (2002). Boyle, Richard, (2005), „Civil Service Performance Indicators‟, Centre for Public Management Research, Discussion Paper No. 29, Institute of Public Administration, Dublin. Bruce Shaw Handbook (2008), Bruce Shaw Partnership, www.bruceshaw.ie Bryman, Alan (2004), „Social Research Methods‟, Oxford University Press. C&AG (2004), „Special Report – National Roads Authority Primary Routes Improvement Programme‟, Comptroller and Auditor General, Dublin. CEEU (2007), „Costing of Civil Service Staff Time‟, Central Expenditure Evaluation Unit, Department of Finance. Cook TD, Campbell DT, (1979), „Quasi-Experimentation: Design and Analysis for Field Settings‟, Houghton Mifflin: Boston. CSO (2008), „Population and Labour Force Projections‟, Central Statistics Office. COT, Commission on Taxation (2008), „Terms of Reference‟, www.taxcommission.ie CSO (2008), Consumer Price Index, Central Statistics Office www.cso.ie/statistics/conpriceindex.htm

204

CSO (2006), „Census 2006 Preliminary Report‟, Central Statistics Office CSO (2006), Census 2006 Volume 1, „Population Classified by Area‟, Central Statistics Office CSO (2006), Census 2006 Volume 6, „Housing‟, Central Statistics Office. CSO (2006), Census 2006 Volume 8, „Occupations‟, Central Statistics Office. CSO (2006), Census 2006 Volume 10, „Education and Qualifications‟, Central Statistics Office. CSO (2006), Census 2006 Volume 12, „Travel to Work, School and College‟, Central Statistics Office. CSO (2002), Census 2002 Volume 9, „Travel to Work School and College‟. Central Statistics Office. CSO (1996) Census 1996 Volume 6, „Travel to Work School and College‟, Central Statistics Office CSO (1996), Census Volume 7, „Occupations, Social Class and Socio Economic Groups‟. Central Statistics Office. Daly, Mary E., (1995), „The Buffer State – the Historical Roots of the Department of the Environment‟, Institute of Public Administration, Dublin. DAST (2007), „Expenditure Review Local Authority Swimming Pool Programme‟, Department of Arts, Sports and Tourism, DAST (2005), „Sports Capital Programme 1999-2002 Expenditure Review‟, Department of Arts, Sports and Tourism. De Haan J., Romp W. & Sturm JE., (2007), „Public Capital and Economic Growth: Key Issues for Europe‟, Paper presented at the International Monetary Fund Seminar on Strengthening Public Investment and Managing Fiscal Risks from Public Private Partnerships: IMF. DELG (1996), „Better Local Government‟, Department of the Environment and Local Government. DELG, (1998), „Action on House Prices‟, Department of the Environment and Local Government. DELG (1999), „Action on the Housing Market‟, Department of the Environment and Local Government. DELG (2000a), „Action on Housing‟, Department of the Environment and Local Government. DELG (2000b), Circular Letter RW 13/00 of 3 July 2000, „Non-National Road Grants to Support Housing and Other Related Developments, Department of the Environment and Local Government.

205

DELG (2000c), Circular Letter RW 25/00 of 14 December 2000, „Non-National Road Grants to Support Housing and Other Related Developments‟, Department of the Environment and Local Government, DELG (2001), „Memorandum on Grants for Non-National Roads‟, Department of the Environment and Local Government. DEHLG (2002), „National Spatial Strategy for Ireland, 2002-2020, People, Places, Potential‟, Department of the Environment, Heritage and Local Government, Stationary Office, Dublin. DEHLG (2003), „Development Contribution‟, Circular Letter PD 4/2003 of 27 June 2003, Department of the Environment, Heritage and Local Government. DEHLG (2004), „Work Methodologies on Non-National Roads‟, Department of the Environment, Heritage and Local Government. DEHLG (2007a), „Annual Housing Statistics Bulletin 2006‟, Department of the Environment, Heritage and Local Government. DEHLG (2007b), „Development Plans – Guidelines for Planning Authorities‟. Department of the Environment, Heritage and Local Government. DEHLG (2007c), „Delivering Homes Sustaining Communities - Statement on Housing Policy‟, Department of the Environment, Heritage and Local Government. DEHLG (2007d) „Statement of Strategy‟, Department of the Environment, Heritage and Local Government. DEHLG (2007e), „Outline of Local Authority New Budget Format‟, Department of the Environment, Heritage and Local Government. DEHLG (2001-2008), Annual Housing Statistics, Department of the Environment, Heritage and Local Government. www.environ.ie. DETE (2004), „Hewlett-Packard Establishes Strategic R & D Centre for Ireland‟, press release 2/9/04, Department of Enterprise, Trade and Employment Department of Finance (2007), „Value for Money and Policy Review Initiative Guidance Manual‟, Central Expenditure Evaluation Unit, Department of Finance, Dublin. Department of Finance (2006a), „Circular 33/06, Construction Procurement Reform – revision of arrangements for the procurement of public works projects and the engagement and payment of construction consultants‟. Department of Finance (2006b), „Capital Works Management Framework‟, Guidance Note for Public Works Contracts. Department of Finance (2005), „Guidelines for the Appraisal and Management of Capital Expenditure Proposals in the Public Sector‟. DfT (2003), Department for Transport, WebTag Transport Analysis Guidance, Unit 3.5.8, „The Wider Economic Impacts Sub-Objective‟, www.webtag.org.uk

206

DiPasquale, Denise (1997), „Why we don‟t know more about housing supply‟, University of Chicago. DKM Economic Consultants (2006), „Review of the Construction Industry 2005 and Outlook 2006 to 2008‟: Dublin. DKM Economic Consultants (2008), „Preliminary Forecast for Construction in 2008‟, for the Department of the Environment, Heritage and Local Government. DKM / DEHLG (2007), „Construction Industry Indicators‟, Vols. 9, 10 & 11, 2007, DKM Economic Consultants / Department of the Environment, Heritage and Local Government. DoT (2007), „Guidelines on a Common Appraisal Framework for Transport Projects and Programmes‟, Department of Transport. DoT (2008), „Statement of Strategy 2008-2010‟, Department of Transport. D&MRA (2004), „Regional Planning Guidelines for the Greater Dublin Area‟, Dublin and Mid East Regional Authorities. Duffy, David (2005), „The Permanent TSB House Price Index, 1996-2005‟, Economic and Social Research Institute / Permanent TSB. ECMT (2001), „Assessing the Benefits of Transport‟, European Conference of Ministers of Transport: Paris. ESRI (2006), „Ex-Ante Evaluation of Investment Priorities for the National Development Plan 2007 – 2013‟, Morgenroth, E. & Fitzgerald, J. (eds.), Economic and Social Research Institute, Dublin. ESRI (2008), „Quarterly Economic Commentary Summer 2008‟, Barrett, A., Kearney, I. & O‟Brien, M. European Environment Agency (2006), „Urban Sprawl in Europe – The Ignored Challenge‟, EEA Report No. 10/2006. Feeney, B. & Devlin, J. (1987), „Developing an Economic Evaluation Procedure for Road Investments‟, in Mulreaney, Michael (ed.), „Cost Benefit Analysis Readings‟, IPA, (2002). Fitzgerald, J. et al. (2003), „The Mid-Term Evaluation of the National Development Plan and Community Support Framework for Ireland, 2000-2006‟, Policy Research, No. 50, Economic and Social Research Institute, Dublin. Fitzpatrick (2002), „Evaluation of Investment in the Road Network‟, Report prepared for the NDP / CSF Evaluation Unit by Fitzpatrick Associates Economic Consultants in conjunction with Africon Transport and Engineering Consultants and A&L Goodbody Consulting, Dublin. Forfás (2007) „Perspectives on Irish Productivity, A Selection of Essays by Irish and International Economists‟, Forfás, Dublin. Garvin, Tom (2004), „Preventing the Future – Why Was Ireland so Poor for so Long‟, Gill & McMillan, Dublin.

207

Girouard N., Kennedy M., van den Noord P. and André C., (2006), „Recent House Price Developments: the Role of Fundamentals‟, OECD, Paris. Goodbody Economic Consultants (2003), „Rationale for and Impact of a Use or Lose It Scheme‟, Department of the Environment, Heritage and Local Government. Goodbody Economic Consultants (2004), „Parameter Values in the Economic Appraisal of Transport Projects, Department of Transport. Goodwin, Phil, (1996), „Empirical Evidence on Induced Traffic‟, in „Transportation‟, Vol. 23, No. 1. Gramlich, E (1994), „Infrastructure Investment: A Review Essay‟, Journal of Economic Literature, Vol 32, pp 1176-1196. Harcourt (2007), „Park West Dublin - Dynamic New Quarter for Ireland‟s Leading City‟, Published by 3 Fox International for Harcourt Developments, Dublin. Haughwout, Andrew, (2000) „Public Infrastructure Investments, Productiity and Welfare in Fixed Geographic Areas‟, Federal Reserve Bank of New York. HM Treasury (2005), „The Government‟s Response to Kate Barker‟s Review of Housing Supply‟, London. Honjo, K., Hunt B., Koeva P. and Moreno-Badia M., (2004), „Adjustment in the Housing Market‟ in „Ireland, Selected Issues‟, International Monetary Fund IAVI (2008), „Annual Property Survey 2007‟, Irish Auctioneers and Valuers Institute IAVI (2007), „Annual Property Survey 2006‟, Irish Auctioneers and Valuers Institute IAVI (2006), „Annual Property Survey 2005‟, Irish Auctioneers and Valuers Institute IDA Ireland (2007), „Ireland, Knowledge is in our Nature – Annual Report 2006‟, Dublin. IDA Ireland (2006), „HP Financial Services Expands its Operations in Leixlip, Co. Kildare‟, press release 7/6/06, www.idaireland.com/ Indecon (2005), „Review of Local Government Financing‟, Report commissioned by the Minister for the Environment, Heritage and Local Government. Keegan, Owen P (1999)., „The Evaluation of Transport Projects‟, in Mulreaney, Michael (ed.), „Cost Benefit Analysis Readings‟, IPA, (2002). KCC (2005), „Kildare County Development Plan 2005-2011‟, Vol 1., Kildare County Council. KPMG, MC O‟Sullivan Consulting Engineers, Murphy Ryan Associates (1997), „A Review of the Efficiency of County Council Operations in the Non-National Roads Area‟, Department of the Taoiseach. Government Publications Office, Dublin. Litman, Todd (2007) „Generated Traffic and Induced Travel – Implications for Transport Planning‟, Victoria Transport Policy Institute (www.vtp.org)

208

Malpezzi Stephen & Maclennan Duncan (2001), Journal of Housing Economics, Volume 10, Issue 3, pages 278-306. Mayne, John (1999), „Addressing Attribution Through Contribution Analysis: Using Performance Measurement Sensibly”, Office of the Auditor General of Canada. McDermott Norton (2002), „Park West / Cherry Orchard Urban Framework Plan‟ commissioned by Dublin Corporation. MIF - Management Information Framework (2001), „Performance Indicators, A Users Guide‟, Department of Finance. MIF - Management Information Framework (2004), „Report on Performance Indicators‟, Department of Finance. Morgenroth, Edgar L W (2001), „Analysis of the Economic, Employment and Social Profile of the Greater Dublin Region (Dublin and Mid East), Economic and Social Research Institute, Dublin. Mulreany, Micheal (2002), „Cost Benefit Analysis Readings‟, IPA, Dublin NDP (2007), National Development Plan 2007-2013, „Transforming Ireland – a Better Quality of Life for All‟, Stationary Office, Dublin. NESC (2004), Report No. 112 „Housing in Ireland: Performance and Policy‟, National Economic and Social Council, Government Publications Office, Dublin. NESC (2002), „Achieving Quality Outcomes: The Management of Public Expenditure‟, National Economic and Social Council, Government Publications Office, Dublin. Noland Robert B. & Lem Lewison L. (2001), „A Review of the Evidence for Induced Travel and Changes in Transportation and Environmental Policy in the United States and the United Kingdom‟, Centre for Transportation Studies, Imperial College of Science, London. NRA (2003), „Future Traffic Forecasts 2002-2040‟, National Roads Authority, Dublin. NRA (2005), „Guidelines for Cost Benefit Analysis‟, National Roads Authority, Dublin. NTC (2005), „Naas Town Development Plan 2005-2011‟, Naas Town Council NUDC (1999), „Naas Town Development Plan 1999‟, Naas Urban District Council ODPM (2004), „Community Infrastructure Fund‟, Office of the Deputy Prime Minister. OECD (2006), „Economic Survey of Ireland‟, Organisation for Economic Co-operation and Development, Paris. Ove Arup & Partners, PMS Pavement Management Services Ltd., Jennings O‟Donovan & Partners, (1997), Pavement Study Conditions of Non-National Roads, Department of the Environment and Local Government.

209

Page, William (2005), „Infrastructure Investment and Economic Growth‟, Economist Group, Scottish Executive Edinburgh. Pawson, R. (2006), „Evidence-Based Policy: A Realist Perspective‟, Sage, London. Permanent TSB / ESRI (2008), „House Price Index‟, Quarter IV 2007, Quarter I, March 2008. Rae, David & Van den Noord, Paul (2006), „Ireland‟s Housing Boom: What has driven it and have prices overshot?‟, Economic Department Working Paper No. 492, OECD, Paris. REV – Revised Estimates Volume (February 2008), Government Publications Office. RPS / MCOS / PMS, (2005), „Non-National Roads Pavement Condition Study‟, the Department of the Environment, Heritage and Local Government, SACTRA (1994), „Trunk Roads and the Generation of Traffic‟, Standing Advisory Committee on Trunk Road Assessment, Department of Transport, UK. Schacter, M, (2002). „Not a Tool Kit: Practitioners Guide to Measuring the Performance of Public Programmes‟, Institute on Governance, Ottowa, Canada. SERA (2004), „Regional Planning Guidelines‟, South East Regional Authority. STAG - Scottish Transport Appraisal Guidance, „Chapter 8 – Economy‟, www.transportscotland.gov.uk Ter-Minassian, Teresa & Allen, Mark (2004), „Public Investment & Fiscal Policy‟, International Monetary Fund. Wallace, Monica (2005), „Ex-Ante Appriasal of Transport Investment: Lessons from the Dublin – Dundalk Corridor‟, Institute of Public Administration M.Econ.Sc. Dissertation. WCC (2003), „Tramore Local Area Plan 2003-2009‟, Waterford County Council. WCC (2007), „Tramore Local Area Plan 2007-2013‟, Waterford County Council. Williams, Dr. Brendan, Hughes, Brian & Shiels, Patrick, (2007), „Urban Sprawl and Market Fragmentation in the Greater Dublin Area‟, SCS Housing Study 2007, Chartered Surveyors of Ireland, Dublin. Wimmer, R. & Dominick J., (1997), „Mass Media Research‟, Thompson International, London.

210

Appendix II

Steering Committee

Membership

Mr. Kevin Ring, Principal Officer, Regional and Local Roads Division,

Department of Transport (Chairperson)

Mr. Dominic Mullaney, Principal Roads Advisor, Regional and Local Roads

Division, DoT

Mr. John O‟Flynn, County Engineer and Director of Service, Waterford County

Council

Ms. Mary Finnegan, Assistant Principal Officer, Housing Policy and Finance,

Department of the Environment, Heritage and Local Government

Ms. Elizabeth Munro, Assistant Principal Officer, Affordable Housing, DEHLG

(replaced Mary Finnegan in September 2007)

Mr. Barry Quinlan, Assistant Principal Officer, Finance Section, DEHLG

Mr. Derek McConnon, Assistant Principal Officer, Finance Division, DoT

Mr. Eamonn Waters (Policy Analyst)

Dates of Meetings

July 5th, 2007

October 5th, 2007

November 23rd 2007

February 8th, 2008

March 28th, 2008

211

Appendix III Questionnaires and Cover Letter

Main Self-Completion Questionnaire for all projects funded under the

programme.

Supplementary Questionnaire for projects that were submitted but not funded.

Cover Letter to Local Authorities - Circular NNR 25/07 of 24.10.07, „Value for

Money Review of the Strategic Non-National Roads Programme (formerly

known as „Non-National Roads Grants to Support Housing and other Related

Developments‟)‟.

212

QUESTIONNAIRE for FUNDED PROJECTS

Value for Money Review of the Strategic Non-National Roads Programme (formerly known as „Non-National Roads Grants to Support Housing and

other Related Developments‟)

Background To The Questionnaire

As part of the Government‟s „Value for Money and Policy Review Initiative‟, a

review is being undertaken of the „Strategic Non-National Roads Programme‟.

The decision to undertake this specific review was made by the Government,

and there is a requirement that it be carried out in accordance with

Department of Finance guidelines. Your co-operation would therefore be

greatly appreciated.

When established in 2000, the programme was known as „Non-National

Roads Grants to Support Housing and other Related Developments‟.

The programme arose from recommendations contained in the reports on the

Housing Market produced by Peter Bacon and Associates. The

Government‟s policy response „Action on Housing‟ (June 2000) recognised

the need for targeted investment in non-national roads schemes crucial to

housing and other development.

Formal applications were invited in July 2000 (Circular RW13/00), and

allocations announced in December 2000 (Circular RW 25/00). Information is

being sought on a total of 47 projects across 15 local authority areas.

Information on Completing the Questionnaire

An individual questionnaire must be completed in respect of each road project

funded under the programme.

The information being sought is wide-ranging (i.e. technical, financial and

administrative). Some consultation may be required between different offices

within the local authority.

Completed questionnaires should be returned to: Non-National Roads

Division, Department of Transport, Block 6, Irish Life Centre, Dublin 1, email:

[email protected], fax: 01-8882857. Please note that the deadline

for receipt of completed questionnaires is Wednesday November 14th 2007.

If you have any queries about the review or require clarification on any aspect

of the questionnaire, please contact Eamonn Waters at Tel:, 087-7592539

(mobile), 01-888 2747 (office), or email: [email protected].

213

QUESTIONNAIRE

Value for Money Review of the Strategic Non-National Roads Programme (formerly known as „Non-National Roads Grants to Support Housing and other

Related Developments‟) 1. Scheme Details

1.1. Name of Road Project

1.2 Name of Local Authority

1.3. Brief description of road works (Please note that details from the original application forms submitted under the scheme are attached and may assist you here)

1.4. Location of Works (start and end point)

1.5. Type of road (single/dual)

1.6 Type of works (new / widening)

1.7. Length of Road (m)

1.8. Carriageway width (m)

1.9. Total width of Footpaths (m)

1.10. Total width of cycle tracks (m)

1.11. Speed Limit (km / hour)

1.12 Technical Details (e.g. pavement structure)

1.13. Were the road works undertaken in conjunction with any other non-roads infrastructural works (e.g. pipe laying for water services, etc.).

If Yes, please specify the additional works undertaken.

214

2. Statutory and Procedural Issues

2.1 Land

Were all lands owned by the local authority (Yes / No)

If „No‟, how were they acquired (i.e. by Compulsory Purchase Order or by agreement)

Please specify the amount of land (in hectares), and number of landowners involved.

2.2 Consultation

Was a statutory public consultation process required for the road (i.e. under Part 8 of the Planning and Development Regulations, 2001 - or its predecessor) Yes / No

If Yes, how long did this take to complete (in months)

2.3 EIS

Was an Environmental Impact Statement Prepared? (Yes/No)

If yes, how long did this take to complete (in months)

2.4 How were the Design and Construction works undertaken:

Design

Construction

Competitive Tender

Restricted Tender

Direct Labour

Other (please specify)

2.5 Was a specific project management IT system used on the road project?

215

3. Construction Period

3.1. Date / Year of commencement of works (e.g. June 2001)

3.2. Is the project complete? Yes / No

3.3. If the project is complete, please indicate the date and year of completion (e.g. October 2004)

3.4. If the project is not yet complete, please indicated the expected date and year (e.g. September 2008)

3.5. Reasons for Delays (Where Applicable): Under the terms of the programme, work on projects was expected to commence in 2001. The programme was also originally intended to cover works undertaken during the period 2001 to 2004. If delays were experienced in the commencement or completion of the works, please indicate (briefly) the main reasons in the space provided below. This should include an estimate of the length of time caused by each of the individual delaying factors.

216

4. Cost / Expenditure Details

4.1. Total Final Expenditure of Road Project Including Design, Construction, Land, VAT, etc.) (in €).

Where road works were undertaken in conjunction with other non-roads infrastructural works (e.g. laying of water services pipes), please estimate the amount related to the road works here, and in the other relevant boxes below.

Where the works are not yet complete, estimates for the total expected outturn costs should be included.

4.2 Breakdown of Total Direct Expenditure (in €):

Design

Land Acquisition (i.e. land purchased directly)

Construction:

Labour Materials Plant Other (please specify)

Other Costs (Please Specify)

4.3 Total Amount provided by the Strategic Non-National Roads Programme

4.4. Total Amount Provided from Sources other than the Programme

4.5. Please provide a Breakdown of Funding from These Other Sources:

General Development Contributions

Special Development Contributions

Supplementary Development Contributions

Other Local Authority Funds

National Roads Authority

Other National Exchequer Funding (please specify)

Other Sources (e.g. loans)

217

4.6. Expenditure by Year Please indicate the total expenditure incurred by the project in respect of each of the years below. This includes all direct costs, as set out under 4.2 above). In the case of the period 2008 to 2010, the expected expenditure figure should be included.

2001 2002 2003 2004 2005

2006 2007 2008 2009 2010 (and after)

4.7. Lands Provided by the Local Authority

These are separate to lands directly purchased (under 4.2 above). Where local authority-owned lands were used, please provide details of: The amount of land (in hectares), and; An estimate of the value of these lands. The basis for this estimate should be the market value in the year of construction.

4.8. Administration Although the Department does not allow administrative salaries and costs to be included in grant claims, it is a requirement of the review that they be considered.

Staff Grade Amount of Time (estimated in hours over the lifetime of the

project)

Were these Administration Costs included in the Cost Estimates under 4.2,

above (Yes / No)

218

4.9. Factors Affecting Costs

Significant cost increases over the lifetime of projects have been identified as an issue that arose across the programme. If there were particular factors that caused an increase in costs on the project, please identify them (e.g. land, plant, materials, planning, consultation, EIS). Please also provide a brief summary of the relative impact they had on the overall costs.

219

5.1 Vehicular Traffic Using Road (Average Annual Daily Traffic) Where reliable information or accurate estimates are available, please include details below. If the project is not yet complete, future projections should be estimated (where this can be done reliably). Vehicular Traffic AFTER Completion of Road Project

AADT

HCV Content

Basis for Figures (Estimate / Actual)

Year when data was gathered / Year on which estimate is based

Vehicular Traffic BEFORE Commencement of Road Project

AADT

HCV Content

Basis for Figures (Estimate / Actual)

Year when data was gathered / Year on which estimate is based

Additional Traffic Attributable to new Development

AADT

HCV Content

Basis for Figures (Estimate / Actual)

Year when data was gathered / Year on which estimate is based

5.2. Additional Traffic Survey Information

If original traffic-count data or other traffic survey reports (e.g. Origin and Destination Surveys) are available for the road in question, please forward these as attachments.

220

6. Project Justification

The key objective of this scheme was to provide grant assistance to relevant local authorities for certain strategic non-national roads to support housing, industrial/commercial and other developments.

6.1 Type of Development supported by the proposed road (i.e. Housing / Industrial / Commercial / Other)

Housing 6.2. Overall Total area of new Housing Land facilitated by the road (in Hectares)

6.3 Breakdown of Housing - Please provide a breakdown of the above figure using the categories below:

Area of land that has been zoned, serviced and built upon (including construction currently underway)

Area of land that has been zoned and serviced but not developed.

Area of land that has been zoned but not serviced or developed.

6.4 Total Number of Housing Units Facilitated or To be Facilitated

6.5 Breakdown of Housing Units - Please provide a breakdown of the above figure using the categories below:

Housing Units constructed, under construction or in the planning process

Potential housing units on other zoned land not yet submitted for planning permission

Other (Please specify)

6.6. Of the Total number of housing units in 6.4 and 6.5 above, please indicate the numbers classified as Social & Affordable Units

221

Industrial / Commercial / Other 6.7 Overall Total area of New Industrial / Commercial land facilitated by the road (in Hectares)

6.8 Breakdown of new Industrial / Commercial Land - Please provide a breakdown of the above figure using the categories below:

Area of new land that has been zoned for industrial / commercial and developed upon (including construction currently underway)

Area of land that has been zoned and serviced for industrial / commercial but not yet developed.

Area of land zoned but not serviced or developed.

7. Contact Details and Further Information In the event of that of follow-up in relation to the survey questionnaire, please include the name and telephone of a contact person in the local authority:

Name:

Phone Number:

If you have any queries about the review or require clarification on any aspect of the questionnaire, please contact Eamonn Waters at Tel: 087-7592539 (mobile), 01-888 2747 (office), or email: [email protected].

Please note that the deadline for receipt of completed questionnaires is Wednesday November 14th 2007.

222

XXXXXXXX County Council

Supplementary Questionnaire for Projects That Were Not Funded

Value for Money Review of the Strategic Non-National Roads Programme (formerly known as „Non-National Roads Grants to Support Housing and other

Related Developments‟)

PLEASE NOTE THAT THIS IS THE SECOND OF TWO

QUESTIONNAIRES RELATED TO THE PROGRAMME. THIS

QUESTIONNAIRE SEEKS INFORMATION ON UNSUCCESSFUL

APPLICATIONS THAT WERE NOT FUNDED.

When projects were submitted for funding under the scheme in 2000, a

total of 117 applications were received. 47 were approved.

To get a wider picture of other roads schemes that may have assisted in

the provision of housing, we are trying to get a synopsis of what happened

with these other projects.

All of the information for all of these additional projects should be included

on the attached table.

Completed questionnaires should be returned to: Non-National Roads

Division, Department of Transport, Block 6, Irish Life Centre, Dublin 1,

email: [email protected], fax: 01-8882857. Please note that the

deadline for receipt of completed questionnaires is Wednesday

November 14th 2007

If you have any queries about the review or require clarification on any

aspect of the questionnaire, please contact Eamonn Waters at Tel: 01-888

2747, 087-7592539 or email: [email protected].

223

XXXXX County Council

Supplementary Questionnaire for Projects That Were NOT Funded

Value for Money Review of the Strategic Non-National Roads Programme (formerly known as „Non-National Roads Grants to Support Housing and other Related

Developments‟)

Name of Project Description

Did this project Go Ahead (or is it planned to go ahead) If „Yes‟, please indicate when it started.

What were the sources of funding (i.e. own resources, development contributions, a different non-national road grants scheme, etc.).

224

Director of Services, 24 October 2007 Circular NNR 25/07

Value for Money Review of the Strategic Non-National Roads Programme (formerly known as „Non-National

Roads Grants to Support Housing and other Related Developments‟) Dear Director,

As part of the Government‟s „Value for Money and Policy Review Initiative‟, the

Department has recently commenced work on a review of the „Strategic Non-National

Roads Programme‟. The decision to undertake this specific review was made by the

Government, and there is a requirement that it be carried out in accordance with

Department of Finance guidelines. Your co-operation would therefore be greatly

appreciated.

When established in 2000, the programme was known as „Non-National Roads

Grants to Support Housing and other Related Developments‟. The programme arose

from recommendations contained in reports on the Housing Market produced by

Peter Bacon and Associates. The Government‟s policy response „Action on Housing‟

(June 2000) recognised the need for targeted investment in non-national roads

schemes crucial to housing and other development. As a result, the programme was

put in place. Formal applications were invited in July 2000 (Circular RW13/00), and

allocations announced in December 2000 (Circular RW 25/00). Since its

commencement, 47 projects have been supported under the programme, with the

provision of grant aid totalling approximately €301m.

A list of the relevant projects in your area is attached. Feedback from the review

will inform national-level policy and will help improve other schemes operated by the

Department.

225

What is the „Value for Money and Policy Review Initiative‟

The initiative is a Government-wide programme. As a general rule each Department

must carry out a series of reviews covering 10-15% of its expenditure every three

years. The final report from each review is independently assessed, and then

published. It is also submitted to the Oireachtas Select Committee dealing with the

relevant policy area. A Steering Committee was established to oversee the review.

Membership comprises staff from the Department of the Environment, Heritage and

Local Government, the Department of Transport and a local authority representative.

Terms of Reference have been agreed in line with Government Guidelines.

What We are Asking You to Do:

1. Complete a Questionnaire in respect of EACH of the projects funded in your

local authority area. To assist you in this process, please find attached a table with

information in respect of each individual project. This is drawn from the original

application form submitted by your authority to the Department of the Environment. In

some cases the cost estimates will have been subsequently revised. The actual final

expenditure for many of the schemes will also be greater than initially forecast.

There is scope in the questionnaire for you to address these issues. The information

being sought is wide-ranging (i.e. technical, financial and administrative). Some

consultation may be required between different offices within the local authority. It

may be advisable to nominate an individual to co-ordinate these responses from

within your local authority.

2. Complete one additional single questionnaire. When projects were submitted

for funding under the scheme back in 2000, a total of 116 applications were received.

47 were approved. To get a wider picture of other roads schemes that may have

assisted in the provision of housing, we are aiming to get a general synopsis of what

happened with these other projects. The detail being sought here is very brief. All

of the information for all of these additional projects can be included on a

single sheet. On the questionnaire, the project title and details have already been

filled in for your area. The two additional questions being asked are:

Did these additional projects, not included in the programme, go ahead? (or

are they planned to?),

If so, how were they funded? (i.e. own resources, development contributions,

a different non-national road grants scheme, etc.).

226

3. Following completion and return of the questionnaires, it is proposed to

meet with you individually (or a senior member of staff involved in the construction

of the road schemes within your local authority). The purpose of this meeting will be

to discuss your overall view of how the scheme has operated, and any issues that

may have arisen. It is expected that these meetings will be arranged to take place in

December and January at a time and location convenient to you. Two or three

projects from the 47 that were funded will also be examined in greater detail as case

studies.

Further Queries and Return of Completed Survey Forms

Work on the review is being undertaken by Eamonn Waters from the Department‟s

Non-National Roads Division. If you have any queries or require clarification on any

aspect of the survey questionnaires, please contact him at 087-7592539 (mobile),

01-8882747 (office), or email: [email protected]. Completed

questionnaires should be returned to: Non-National Roads, Department of Transport,

Block 6, Irish Life Centre, Dublin 1, email: [email protected]. Please note

that the deadline for receipt of completed questionnaires is: Wednesday

November 14th 2007.

Yours sincerely,

Kevin Ring,

Principal Officer, Non-National Roads.

c.c. County / City Manager.

Attachments with this Circular:

1. List of Projects and Approved Grant Amounts in your local authority area.

2. A table of data from the original application forms submitted in 2000 (to assist in

completing the Main Questionnaire).

3. Main Questionnaire for Funded Projects (one to be returned for each project).

4. Additional single questionnaire with summary information on all projects that were

submitted but not funded.

227

Appendix IV

Interviews– Participants and Dates

Interviews / Focus Groups With Local Authority Staff

Local Authority Date Participants

Cork City Council 14.12.07 Tony Fleming (Senior Engineer)

Cork County Council 14.12.07 John Lapthorn (Senior Engineer) Pat O‟Mahony (Senior Engineer) Tom Coughlan (Senior Engineer)

Fingal County Council 17.1.08 Mick Lorrigan (Director of Service)

Galway City Council 16.1.08 Ciaran Hayes (Director of Service) Joe Tansey (Senior Engineer)

Galway County Council 16.1.08 John Morgan (Director of Service) Danny Barrett (Senior Executive Officer)

Limerick City Council 10.1.08 Pat Dromey (Director of Service) Vincent Murray (Senior Engineer)

Limerick County Council 10.1.08 Robert Gallagher (Senior Executive Engineer) Diarmuid O‟Dea (Assistant Engineer)

Meath County Council 29.1.08 Charlie McCarthy (Senior Engineer)

South Dublin County Council 18.1.08 John McLoughlin (Senior Engineer) Donna Lakes (Senior Executive Engineer)

Waterford City Council 31.1.08 Fergus Galvin (Acting Director of Service) Billy Duggan (Senior Executive Officer)

Waterford County Council 31.1.08 John O‟Flynn (Director of Service) Paul Daly (Senior Engineer) Ray Malone (Senior Executive Officer)

Wicklow County Council 11.1.08 Seamus Walker (Director of Service) Frank Clarke (Senior Engineer) Margaret Hartnett (Senior Resident Engineer)

Sessions Involving Planning Officials

Local Authority Date Participants Dublin City Council 15.1.08 Frank Fallon (Senior Executive Officer)

Rory Deegan (Deputy City Planning Officer) Eoghan Madden (Senior Engineer) Dermot Hanney (Senior Engineer)

Dun Laoghaire/ Rathdown County Council

17.1.08 Willie Horgan (Senior Engineer) Denise Doherty (Senior Planner) Jim Hayes (Senior Executive Engineer) Gerry Corcoran (Executive Technician)

Kildare County Council 22.1.08 Pat Whelan (Senior Executive Officer) Des O‟Connor (Senior Engineer) David Real (Senior Executive Engineer) Willie Joe Padden (Planner)

Interviews with Housing and Business Park Developers

Company Date Participants

Bolster Construction Ltd., Tramore

19.2.08 William Bolster (Managing Director)

R. McDonald & Sons Ltd. Tramore

19.2.08 John McDonald (Director) Pat McDonald (Director)

Harcourt Developments (Park West Business Park)

11.2.08 Mick Arthur (Business Park Manager) Donal Leahy, Dermot Arthur (Harcourt Developments)

Osberstown Developments (Millennium Business Park)

7.3.08 Gerry Prendergast (Executive Director) Sinead Murphy (Marketing Manager)

228

Informal Interviews With Departmental Staff

Date Name

23.10.07 John Devlin, Former Senior Inspector and Principal Advisor, Non-National Roads, Department of the Environment, Heritage and Local Government

26.10.07 Aeneas Langford, Former Principal Advisor, Non-National Roads, DEHLG

16.11.07 John Murphy, Former Principal Officer (Housing), DEHLG

Consultation Meetings / Discussions

Date Name

6.3.08 Brendan McDonagh (Manager, Policy and Planning Development, IDA Ireland)

24.1.08 Robert Fox, Department for Transport UK („Community Infrastructure Fund‟)

25.1.08 Alistair Mitchell, Transport Directorate, „Partnership and Local Authority Liaison‟, Scottish Executive.

229

Appendix V

Original Circular Letters and Application Form

Circular RW 13/00 of 3.7.00, „Non-National Road Grants to Support Housing

and Other Related Development‟ which invited applications from local

authorities under the programme.

Original Application Form from July 2000.

Circular RW 25/00 of 14.12.00, „Non-National Road Grants to Support

Housing and Other Related Development‟, which formally notified local

authorities of approved projects and grant amounts.

230

3 July, 2000. Circular RW 13/00

Non-National Road Grants to Support Housing

and other related developments

Dear Manager,

Background 1. I refer to the announcement in the “Action on Housing” programme in

relation to the provision of an additional £200 million for Non-National

Roads Schemes supporting residential and other developments. This

new budget line (which follows on a similar scheme of road grants in

support of housing operated in 1998 and 1999) was established, inter

alia, on the basis of indications to the Department from local authorities

that a number of roads projects, having the ability to support significant

housing and other development, could be mobilised quickly if

necessary funding were provided. Arising from this commitment, an

additional £74 million to the existing roads budget will be provided by

the Government for this purpose in the period 2000 – 2002, with the

balance of £76 million over the period 2003-2004; this will give a total

Exchequer contribution of £150m to this new roads programme.

2. The Government recognises that rapid economic development is

generating a need for targeted investment in the non-national roads

area. The key objective of this scheme is to provide grant assistance

to relevant local authorities, particularly in the Greater Dublin Area, for

certain strategic non-national roads to support housing,

industrial/commercial and other developments.

231

3. The purpose of this circular is to

(a) invite certain local authorities to confirm projects to be part-

financed under this scheme, and

(b) set out for local authorities how the scheme will operate.

Operation of the Scheme 4. Exchequer funding for qualifying road projects will be at a maximum

rate of 75%. The balance must be provided by local authorities from

their own resources, which may include the proceeds of development

levies, other private sector contributions or contributions in kind (e.g.

land).

5. Fixed sum grants will be allocated (up to a maximum of 75% of the cost

of the scheme). It will be a matter for local authorities to finance any

cost overruns or additions or unforeseen work from their own

resources.

6. Local authorities, in completing submissions to the Department, should

have regard to the following criteria:

(a) the impact of the development on the environment;

(b) planning status of the land in question e.g. zoning,

planning permissions, etc.

(c) the availability of serviced land, appropriately

zoned, in the area.

Submitting Applications

7. In submitting projects to the Department for consideration, local

authorities should bear in mind that the total Exchequer monies

232

available for all projects in the period 2000-2002 is £74 million with the

balance of £76 million in the period 2003-2004.

8. Proposals under this circular should relate to works which will

commence in 2000 or 2001. The position will be reviewed at the end of

2001. Local authorities should ensure that arrangements in relation to

planning, land acquisition, EIS‟s, Part X procedures etc., are either

completed or sufficiently well advanced to ensure that expenditure

targets can be met.

9. Subject to the foregoing paragraphs, local authorities should complete, as

a matter of urgency, proposals in respect of the construction of new

roads or the widening or realignment of existing roads which can be

considered for funding under this programme. In the case of the

counties of Cork, Galway, Limerick and Waterford, proposals should be

confined to the hinterland of the relevant county borough.

Format and timetable for submission of proposals

10. Local authorities should submit proposals to the Department on the

form attached as an Appendix to this circular by Wednesday 19 July,

2000

11. The Department will approve projects for funding having regard to the

level of funding available, the criteria set out above and the merits of

the projects submitted for consideration.

12. Grants will be notified to local authorities as soon as possible.

13. Full plans and documentation in respect of projects selected for funding

under this scheme will have to be submitted.

233

14. All queries regarding the contents of this circular letter should be

addressed to Ms. Sheila Power, Tel: 01 – 888 2274,

Fax: 01-888 2857; e-mail [email protected].

Yours sincerely,

______________________

Martin Condon, Principal Officer,

Road Works Section.

Phone: 8882146

To:

The county councils of Dun Laoghaire/Rathdown; Fingal; South Dublin; Kildare;

Meath; Wicklow; Cork; Galway; Limerick and Waterford

The county borough corporations of Cork; Dublin; Galway; Limerick and Waterford

234

14 December, 2000. Circular RW 25/2000.

Non-National Road Grants to Support Housing

and other related development.

Dear Manager,

1. I refer to this Department’s Circular RW 13/2000 of 3 July, 2000 which

sought applications from certain local authorities under the above new budget

line for non-national roads.

2. The applications received have now been considered in the Department and 43

projects costing £294m are now being approved. The maximum Exchequer

contribution will be £190m over the 2001 – 2004 period. These projects will

facilitate the provision of 43,659 housing units and benefit 932 hectares of

industrial land.

3. Exchequer funding for approved projects will be at a maximum rate of 75% of

the cost indicated in response to RW 13/2000 (see attached schedule) or 75%

of the completion cost if lower. This cost includes design, supervision,

construction, land, VAT etc. Some projects will receive grant aid which is

capped at less than 75% and this is indicated where appropriate. The grants

being notified now represent the maximum Exchequer grant which will be

forthcoming. Local authorities are reminded, in particular, that these grants

represent the maximum Exchequer contributions to these specific projects and

any cost overruns must be dealt with by the authorities themselves from their

own resources. Any application for increased funding over and above that

notified now for each scheme will not be entertained.

In all cases the balance of the funding must be provided by local authorities

from their own resources which may include proceeds of development levies,

or private sector contributions or contributions in kind (e.g. land), etc.

4. While total allocations for the 2001 – 2004 period are being notified now,

individual allocations for 2001 will be notified with the Non-National Road

Grant Allocations for 2001 early next year. These individual allocations

cannot be made until a response has been received to paragraphs 5 and 6

under.

/…

235

2

5. The grant(s) now notified to you in respect of the project(s) in the attached

schedule are subject to the following conditions:-

(a) Schemes should be frontage free insofar as is possible and the number

of road accesses should be minimised.

(b) Where appropriate schemes should be designed to the requirements of

the Design Manual for Roads and Bridges, as amended by the National

Roads Authority.

(c) The length to be completed and the cross section to be provided shall

be in accordance with the proposal which was submitted (see attached

schedule).

(d) Proposals regarding scheme programme and annual profile of

expenditure to be agreed with the Department by 10 January, 2001.

6. When expenditure profiles have been agreed with the Department and

individual allocations for 2001 have been notified to you, payment may be

claimed by using the normal payment claim form with the name of the project

inserted thereon. The normal requirements applicable to all non-national road

grant payments apply, dates for claims, unpaid bills etc.

7. This budget line is once-off and relates to the 2001 - 2004 period only. It will

not be extended beyond 2004. This targeted investment programme provides

a key opportunity to advance important projects. For this reason it is of the

utmost importance that the local authorities involved put in train now the

preparatory work which is necessary to ensure the timely drawing down of the

available funding. This budget line, over and above normal Non-National

Road Grant funding, was approved by the Department of Finance because of

the importance of the schemes involved and because they could be undertaken

in the timescale envisaged if there was funding available. There is an onus on

this Department and the local authorities involved to ensure that this budget

line is used effectively and efficiently and that it achieves its intended targets,

i.e. road length, total cost, housing and industrial lands facilitated etc.

/..

236

3

8. Any queries in relation to the contents of this circular should be addressed to

the undersigned.

Yours sincerely,

_____________________

Denis McDonald,

Assistant Principal,

Non-National Roads Section,

Tel: 01 888 2284.

To: City Managers of the County Borough Corporations of Dublin, Cork,

Limerick, Waterford and Galway and County Managers of the County Councils of

Cork, Dun Laoghaire-Rathdown, Fingal, Galway, Kildare, Limerick, Meath, South

Dublin, Waterford and Wicklow.

237

Appendix VI Output Data

Housing Units, Housing Lands and Industrial / Commercial Lands –

Reported Outputs

Project Commencement and Completion