1VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
OFFICE OF THE AUDITOR GENERAL
T H E R E P U B L I C O F U G A N D A
M A R C H , 2 0 1 3
VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF
THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II)
A REPORT BY THE AUDITOR GENERAL
www.oag.go.ug | E-mail: [email protected]
T H E R E P U B L I C O F U G A N D A
VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE
OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT
PROGRAMME (CAIIP I &II)
A REPORT BY THE AUDITOR GENERAL
MARCH, 2013
OFFICE OF THE AUDITOR GENERAL
12th June, 2013
The Rt. Hon. Speaker of ParliamentParliament of UgandaKampala
VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I & II)
In accordance with Article 163 (3) of the Constitution, I have undertaken a value for money audit on the Performance of the Community Agricultural Infrastructure Improvement Programme (CAIIP I & II) and hereby submit this report.
My office intends to carry out a follow – up at an appropriate time regarding actions taken in relation to the recommendations in this report.
I would like to thank my staff: The Director, Mr Stephen Kateregga and Assistant Director Liz Nambuya; and team Bob Monday – Senior Principal Auditor, Paul Rwabutara Principal Auditor, Henry Mutegeki Senior Auditor, the two VFM auditors: Esther Akurut and Raphael Olowo and the five Engineering auditors: Arthur Kasozi, Roselyn Mawanda, Bruno Ruberwa, Robert Okee and Dennys Muhesi who undertook this audit. I would also like to thank the staff of Ministry of Local Government charged with the implementation of CAIIP Project for the assistance offered to my staff
during the period of the audit.
John F. S. MuwangaAUDITOR GENERAL
AUDITOR GENERALAUDITOR GENERAL’S MESSAGE
TABLE OF CONTENTS
i
List of Tables ....................................................................................................................................................... iiList of Pictures .................................................................................................................................................... iiList Of Abbreviations .......................................................................................................................................... iii
Executive Summary ………………………………………………………………………......................………………..................…….... iv
CHAPTER ONEINTRODUCTION ................................................................................................................................................... 21.1 Motivation .................................................................................................................................................. 21.2 Description of the Audit Area ................................................................................................................... 31.3 CAIIP Goal, Objectives and Outputs .......................................................................................................... 3 1.4 Funding ...................................................................................................................................................... 41.5 Audit Objective .......................................................................................................................................... 41.6 Scope ......................................................................................................................................................... 4
CHAPTER TWOMETHODOLOGY ................................................................................................................................................... 62.1 Sampling ................................................................................................................................................... 62.2. Document review ...................................................................................................................................... 62.3 Interviews .................................................................................................................................................. 62.4 Observation/Field Inspections .................................................................................................................. 6
CHAPTER THREESYSTEM AND PROCESS DESCRIPTION ........................................................................................................... 83.1 Roles and Responsibilities of Key Players ............................................................................................... 83.1.1 Development Partners (ADB and IFAD) ................................................................................................... 83.1.2 The Inter-ministerial Policy Committee (IPC) ......................................................................................... 83.1.3 Ministry of Finance Planning and Economic Development ..................................................................... 83.1.4 Ministry of Local Government .................................................................................................................. 83.1.5 The Programme Facilitation Team (PFT) ................................................................................................. 83.18 The Districts .............................................................................................................................................. 83.1.7 The Sub-counties ...................................................................................................................................... 93.1.8 The Community ......................................................................................................................................... 93.2 Process description .................................................................................................................................. 93.2.1 Planning .................................................................................................................................................... 93.2.2 Funds Disbursement ................................................................................................................................ 93.2.3 Funds Flow Process ................................................................................................................................. 103.2.4 Procurement process .............................................................................................................................. 113.2.5 Project Implementation .......................................................................................................................... 123.2.6 Monitoring and Evaluation ...................................................................................................................... 12
CHAPTER FOURFINDINGS, CONCLUSIONS AND RECOMMENDATIONS .................................................................................. 154.1 Road Conditional Surveys, Inventories And Designs ............................................................................. 154.1.1 Inadequate Roads Designs ..................................................................................................................... 154.1.2 Inconsistencies in the Bills of Quantities (BOQs) .................................................................................. 174.2 Establishment Of Infrastructure ............................................................................................................ 184.2.1 Establishment of Infrastructure on registered Public Land ................................................................. 184.2.2 Quality of works and workmanship ........................................................................................................ 194.2.3 Quantity Verification ................................................................................................................................ 234.3 Completion of Projects ........................................................................................................................... 244.4 Operation and maintenance of established infrastructure ................................................................... 274.4.1 Occupancy of Markets ............................................................................................................................ 274.4.2 Functionality of Agro Processing Facilities (APFs) ................................................................................ 294.4.3 Maintenance of infrastructure ................................................................................................................ 31GLOSSARY OF TERMS ....................................................................................................................................... 34
APPENDICES ..................................................................................................................................................... 35
VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERALii
Table 1: CAIIP Funding………………………………………...........................…………………………………...…………………4
Table 2: Occupancy Status of Markets visited………………...........………………………...............……………………28
Figure 1: Flow Diagram for Funds Flow Process – CAIIP…………..........................…………………………………11
Picture 1: Rock along the road route on Longot – Sobezi road ……………...............…............………………… 15
Picture 2: Ntunda Market in Mukono District…………………………………..............................………………………. 20
Picture 3: Lwebitakuli Market in Sembabule District……………………………….............................……………… 20
Picture 4: Showing dissimilar iron sheet material for the same roof…………........................……………..… 20
Picture 5: Cracking of slab for Mityoru Market in KaptanyaKaphorwa District………….……..................... 20
Picture 6: Damaged latrine slab that has failed at Katosi market……………………………….......................... 20
Picture 7: Failed tank platform at Maanyi market……………………………………………………..........................… 20
Picture 8: Showing good road surface condition………………………………………………………............................. 21
Picture 9: Showing bad road surface condition………………………………………………………............................… 21
Picture 10: Damaged culvert that has given way due to inadequate back filling at Ch 2+600
on Lwengo – Kyawagonya road...................…………………………………………….............................… 22
Picture 11: Cracked culverts on Akopor-Kamuli road in Tororo District……………………….......................... 22
Picture 12: Broken Culvert End Structures on Kakule-kameruka road in Budaka District .................... 22
Picture 13: Chebukat – Kaptokwoi road…………………………………………………………………..............................… 25
Picture 14: Kashabul – Mokotu road surface conditions……………………………………………............................. 25
Picture 15: Molok – Toiwo road…………………………………………………………………………….................................… 25
Picture 16: Kaplak – Water source road surface conditions………………………………………............................. 25
Picture 17: Unoccupied market structures in Katosi Market in Mukono District……………....................... 27
Picture 18: Bukulula Market in Masaka District………………………………………………………...........................…. 27
Picture 19: Informal market operational in the neighbourhood…………………………………............................ 27
Picture 20: New market facilities abandoned by the vendors……………………………………..........................… 27
Picture 21: Vandalised transformer at Bukulula Market …………………………………………........................... 28
Picture 22: Kids playing and Animals grazing in Kapuyansi market……………………………........................... 28
Picture 23: Milk cooler in the compound of Kiganda Subcounty headquarters……………........................… 30
Picture 24: Silted culvert along Nsambya – Lugusulu Road in Sembabule……………………........................ 32
Picture 25: Section with overgrown vegetation along Radio Uganda – Nasuleta Road
In Pallisa District …………………………………………………………………………………………………….............. 32
Picture 26: Overgrowth of vegetation at Katosi Market in Mukono …………………………..........................….. 32
Picture 27: Peeling off of paint at Kapunyas market in Petete……………………………………............................ 32
LIST OF TABLES
LIST OF FIGURES
LIST OF PICTURES
VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
LIST OF ABBREVIATIONS
iii
AAMP Area based Agricultural Modernization Program
ADB African Development Bank
ADF African Development Fund
AWPB Annual Work Plan and Budget
BoU Bank of Uganda
CAIIP Community Agricultural Infrastructure Improvement Programme
CAO Chief Administrative Officer
CBOs Community Based Organizations
CDA Community Development Advisor
CDO Community Development Officer
DEO District Environment Officer
DFID Department For International Development
DLSP District Livelihoods Support Programme
DTPC District Technical and Planning Committee
DUCARIP District Urban Community Access Roads Investment Plans
EIA Environmental Impact Assessment
GDP Gross Domestic Product
GoU Government of Uganda
ICB International Competitive Bidding
IFAD International Fund for Agricultural Development
IPC Inter-Ministerial Policy Committee
LGSIP Local Government Sector Investment Plan
M & E Monitoring and Evaluation
MoFPED Ministry of Finance, Planning and Economic Development
MoLG Ministry of Local Government
NAADS National Agricultural Advisory Services
NARO National Agriculture Research Organization
NCB National Competitive Bidding
NEMA National Environmental Management Authority
NGOs Non-governmental Organizations
NUSAF Northern Uganda Social Action Fund
PA Programme Accountant
PC Programme Coordinator
PEAP Poverty Eradication Action Plan
PFT Programme Facilitation Team
PMA Plan for Modernization of Agriculture
POM Program Operational Manual
PPDA Public Procurement and Disposal of Public Assets Authority
PSO Program Support Officer
PY Project Year
SDR Special Drawing Rights
UA Unit of Account
VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
BACKGROUNDThe Auditor General is required under Article 163 (3) (b) of The Constitution of the Republic of
Uganda to conduct financial and value for money audits in respect of any project involving public
funds. This mandate is amplified by Section 21(1) of the National Audit Act 2008 which requires
the Auditor General to carry out value for money audits for purposes of establishing economy,
efficiency and effectiveness in the operations of any department or ministry.
The Community Agricultural Infrastructure Improvement Programme (CAIIP) was formulated in
2006. The programme is geared towards enhancing rural development through increased market
access, improved agricultural productivity and growth across the country.
Agriculture has for a long time been a core sector of Uganda’s economy in terms of its contribution
to Gross Domestic Product (GDP) and employment. The sector’s performance has not been
impressive in recent years. The real growth rate in agriculture output declined from 7.9% in the FY
2000/01 to 0.1% in the FY 2006/071.
This has mainly been due to constraints, such as: inadequate physical infrastructure, limited
extension support, high risks and cost of investment, inadequate meteorological services, among
others.
Government, in a bid to address the inadequate physical infrastructure challenges in the agricultural
sector, formulated the Community Agricultural Infrastructure Improvement Programme (CAIIP) in
the year 2006. The project is funded by a loan from the African Development Bank (ADB) and the
International Fund for Agricultural Development (IFAD), to a tune of USD 77.0 million (CAIIP 1) and
USD 70.0 million (CAIIP 2).2
Despite the heavy investment in the project by Government, there are reports of abandoned market
and road construction sites, substandard road works, unutilized market and agro-processing
facilities, among others3.
The Office of the Auditor General deemed it necessary to conduct a value for money audit to assess
the implementation of the Community Agricultural Infrastructure Improvement Program.
1 UBOS 2008 Statistical Abstracts.2 Project Loan Agreements.3 OAG Financial Audit Report Dec. 2011
EXECUTIVE SUMMARY
iv
VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
KEY ISSUES AND RECOMMENDATIONS
a) Inadequate Roads Designs:
A review of the designs/working drawings revealed that the designs for the roads were prepared
in accordance with the Ministry of Works and Transport guidelines for district roads based on
the classes required. However, the audit revealed that some roads were under designed in that
they left out key road features like bridges. For example, in Kabei sub county, Bukwo district, the
initial plan as per designs by the consultants was to construct five (5) roads (21.5km) at a cost
of Shs.989,682,703 without bridge works. However, during project implementation, bridge works
were found to be necessary on 2 roads (Lorok – Kapses -3no bridges and Makutano – Kapkoros
-1no bridge) hence re-scoping the works.
b) Completion of Projects:
It was established that most of the contractors for markets, roads and Agro Processing Facility
shelters had delayed to complete works. Analysis of 12 selected contracts for construction of
markets in 7 districts revealed that 17% of the contracts were completed within the stipulated
time. However, 75% experienced an average delay of 8 months while 8% of the sites had been
abandoned. Site inspection further revealed that some projects had been abandoned for more than
28 days without the authorization of the responsible officer/Project Manager, yet the works had not
been completed.
c) Establishment of Infrastructure on registered Public Land:
The audit established that all the 12 market sites valued at Shs.1,318,402,547 visited in the
districts of Iganga, Mukono, Mityana, Masaka, Sembabule, Pallisa, Kapchorwa were established
on land without proper ownership (untitled land) contrary to the programme operations manual
and market guidelines.
d) Quality of works and workmanship:
Although the completed works should have met the quality specifications in the contract
(Conditions of Contract, Clause 16), the physical inspection of the infrastructural works revealed
that the quality of works varied from good to bad.
e) Quantity Verification:
A review of the Bills of Quantities (BOQs) and Interim payment certificates (IPCs) revealed that
payments worth Shs.307,627,262 were made in respect of quantities over and above the actual
works executed. Further scrutiny of IPCs and subsequent physical inspections revealed that on
four (4) road contracts, payments amounting to Shs.63,471,015 had been made for works not
executed at all.
v
VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
Recommendations
Inadequate Roads Designs:
Management should ensure that contractors are strictly supervised during the design period and
designs should be reviewed for appropriateness before approval.
Completion of Projects:
Management should invoke the relevant contract clauses for timely execution of contracts, such
as, charging liquidated damages and termination of contracts in extreme cases.
Establishment of Infrastructure on registered Public Land:
CAIIP management should ensure that all programme implementing sub counties secure land
titles for the land on which project infrastructure was established.
Quality of works and workmanship:
The project managers should always ensure that the contractors adhere to the required
specifications. Works that do not meet the required technical specifications should not be paid for.
Quantity Verification:
Management should enforce recovery of the funds from the contractors in respect of works not
executed at all and for quantities above the actual.
Management should also ensure that Interim Payment Certificates (IPCs) are always accompanied
by measurement sheets, which should be checked for all contract works executed.
vi
1VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
CHA
PTER
ON
EC
HA
PTE
R O
NE
1
2VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
INTRODUCTION
1.0 BackgroundThe Community Agricultural Infrastructure Improvement Programme (CAIIP) was formulated in
2006.The programme is geared towards enhancing rural development through increased market
access, improved agricultural productivity and growth across the country. The programme is being
implemented in phases/projects (CAIIP I and CAIIP II: CAIIP I in 34 districts in central and eastern
Uganda covering 78 sub-counties (3 sub- counties per the original 26 districts) and the implementation
period is 2008 to 2013. CAIIP II, whose implementation period is 2009 to 2014, covers 65 sub-counties
in 15 districts in northern Uganda and Teso sub-region and also undertakes further deepening of the
programme interventions in 32 new sub-counties within the 26 districts of CAIIP I.
1.1 MotivationAgriculture has for a long time been a core sector of Uganda’s economy in terms of its contribution to
GDP and employment. By 2005, it employed 73 percent of the labour force (UBOS, 2005) and currently,
the sector employs over 80 percent of Uganda’s working population4. The sector’s performance has
not been impressive in recent years. The real growth rate in agriculture output declined from 7.9% in
2000/01 to 0.1% in 2006/075 (UBOS, 2008)
This has mainly been due to constraints, such as: inadequate physical infrastructure, limited extension
support, high risks and cost of investment, inadequate meteorological services, among others.
Government in a bid to address the inadequate physical infrastructure challenges in the agricultural
sector, formulated the Community Agricultural Infrastructure Improvement Programme (CAIIP) in
the year 2006. The programme is geared towards enhancing rural development. It seeks to improve
rural agricultural infrastructure through rehabilitation of district feeder and community access roads
which link farmers to functional markets, equipped with adequate facilities, including stalls, slabs,
stores, agro-processing facilities, water and sanitation and rural energy6.
The project is funded by a loan from the African Development Bank (ADB) and the International Fund
for Agricultural Development (IFAD) to a tune of USD 77.0 million (CAIIP I) and USD 70.0 million (CAIIP
II).7
4 National Development Plan (2010/11 – 2014/15)5 UBOS 2008 Statistical Abstracts.6 CAIIP I & II Appraisal Reports.7 Project Loan Agreements.
CHAPTER ONE
3VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
Uganda covering 78 sub-counties (3 sub-
counties per the original 26 districts) and its
implementation period is 2008 to 2013.
CAIIP II covers 65 sub-counties in 15 districts
in northern Uganda and Teso sub-region
and also undertakes ‘further deepening of
the programme interventions in 32 new sub-
counties within the 26 districts of CAIIP I and
its implementation period is 2009 to 2014.
1.2.2 Legal FrameworkCAIIP derives its mandate from the approval
of the programme by Parliament and the
loan agreements between the Development
Partners (ADB and IFAD) and the Government
of Uganda.
1.3 CAIIP Goal, Objectives and OutputsOverall programme goal:
The overall goal of CAIIP is to contribute to
poverty reduction and economic growth in
Uganda through enhanced commercialization
of agriculture.
Specific Objectives:-
• To enhance farmers’ access to markets.
• To attract competitive prices of farmers’
produce.
Project Outputs
• Improvement of existing community access
roads and rehabilitation of district roads.
• Improvement of sub county market place
infrastructures.
• Promotion of agro-processing by procuring
and installing grain mills, rice hullers, coffee
hullers and milk coolers.
Despite the heavy investment in the project by
Government, there are reports of abandoned
market and road construction sites,
substandard road works; un utilized market
and agro-processing facilities, among others8.
The Office of the Auditor General deemed
it necessary to conduct a study to ascertain
the challenges in the management of the
Community Agricultural Infrastructure
Improvement Program, analyse
their underlying causes and suggest
recommendations for improvement..
1.2 Description of the Audit Area General Description
The Community Agricultural Infrastructure
Improvement Programme (CAIIP) was
formulated in 2006.The programme is geared
towards enhancing rural development
through increased market access, improved
agricultural productivity and growth across
the country.
CAIIP is geared towards enhancing rural
development. The project seeks to improve
rural agricultural infrastructure through
rehabilitation of district feeder and community
access roads which will link farmers to
functional markets, equipped with adequate
facilities, including: stalls, slabs, stores, agro-
processing facilities, water and sanitation and
rural energy9.
The programme is being implemented
in phases/projects (CAIIP I and CAIIP II:
CAIIP I in 34 districts in central and eastern
8 OAG Financial Audit reports Dec. 20119 CAIIP -1 & 2 Project Appraisal Reports
4VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
• Rural electrification of the market places.
• Mobilisations of communities in order to create awareness about the programme and enable
the communities to participate actively in the inventorization, prioritization, selection and
implementation of their local area infrastructure interventions.
1.4 FundingThe programme (CAIIP I & II) is financed by the African Development Bank (ADB) and the
International Fund for Agricultural Development (IFAD) loans and Government of Uganda (GoU)
contribution. During the period under review, CAIIP I was funded to the tune of Shs.102.4 billion,
whereas CAAIP II attracted funding of Shs.42.3 billion, mainly from ADB, as shown in Table 1 below.
Table 1: CAIIP Funding for the period 2009/10 to 2011/12
CAIIP IFinancialYear
ADB IFAD GoU Total
Amount Shs. (BILLIONS)
2009/10 38.772 4.911 0.288 43.971
2010/11 21.155 21.079 0.109 42.343
2011/12 10.076 5.840 0.168 16.084
TOTAL 70.003 31.83 0.565 102.398
CAIIP II Amount Shs.(BILLIONS)
2009/10 2.199 00 00 2.199
2010/11 12.064 00 0.208 12.272
2011/12 27.737 00 0.095 27.832
TOTAL 42.000 0 0.303 42.303
Source: CAIIP Audited Accounts FY 2009/10, 2010/11 and 2011/12
1.5 Audit ObjectiveThe overall audit objective was to assess the performance of Community Agricultural Infrastructure
Improvement Programme projects (CAIIP I and II); and the specific audit objectives were:
• To establish whether the planned agricultural infrastructure was put in place in accordance with
the desired standard specifications/guidelines.
• To ascertain whether the established infrastructure was put to the intended purpose.
1.6 ScopeThe study was carried out at the Ministry of Local Government (MoLG) Headquarters in Kampala
and selected CAIIP implementing districts of Butaleja, Iganga, Kamuli, Mbale, Pallisa, Tororo
and Kapchorwa in the East; Gulu, Amuru, Kitgum and Lira in the North; and Masaka, Mityana,
Mubende, Mukono and Sembabule in the central regions of the country.
5VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
CHA
PTER
TW
OC
HA
PTE
R T
WO
2
6VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
METHODOLOGY
The audit was conducted in accordance with International Organization of Supreme Audit
Institutions (INTOSAI) Auditing Standards and OAG VFM Audit Manual. Those Standards require
that a VFM Audit should be planned in a manner which ensures that an audit of high quality is
carried out in an economic, efficient and effective way and in a timely manner. In collecting data
from the field, the team reviewed documents, carried out interviews and physical inspection/
observation of the facilities.
CHAPTER TWO
2.1 SamplingStratified sampling was used to select the
regions: northern, central and eastern. From
these regions, simple random sampling was
used to select specific districts as follows:
Amuru, Gulu, Lira and Kitgum in northern
region; Masaka, Sembabule, Mityana,
Mubende and Mukono in central region;
Iganga, Namutumba, Budaka, Pallisa,
Butaleja, Tororo, Manafwa, Bududa, Sironko
and Kapchorwa in eastern region.
2.2. Document reviewThe team obtained and reviewed the
documents to obtain information relating
to financing, legal framework/mandate of
the Community Agricultural Infrastructure
Improvement Programme (CAIIP), key
processes, financial performance, and vision,
mission, objectives, and activities for the
period under review. A list of documents
reviewed is attached as Appendix i.
2.3 InterviewsThe audit team conducted interviews with five
(05) officers of the CAIIP project Facilitation
Team (PFT) at the Ministry headquarters. The
audit team also interviewed Program Support
Officers, sub county chiefs and IMC members
in Sixteen (16) of the CAIIP implementing
districts visited. Details of the interviews
conducted are in Appendix ii.
2.4 Observation/Field InspectionsField visits were carried out in the sampled
CAIIP implementing districts where project
activities, including market construction and
roads works were undertaken. The inspections
were undertaken to assess the quality and
progress of works and, during inspections,
photographs of CAIIP project sites were taken
to support the audit observations made in the
report.
7VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
CHA
PTER
TH
REE
CH
AP
TER
TH
RE
E
3
8VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
SYSTEM AND PROCESS DESCRIPTION
3.1 Roles and Responsibilities of Key Players
3.1.1 Development Partners (ADB and IFAD)These are the Development Partners from
which the Government of Uganda secured the
programme funding.
3.1.2 The Inter-ministerial Policy Committee (IPC)This is a committee comprising the
MoLG as the chair, Ministry of Works and
Transport (MoWT), Ministry of Agriculture
Animal Industry and Fisheries (MAAIF),
Ministry of Gender, Labour and Social
Development (MGL&SD) and Ministry of
Water and Environment (MWE); Ministry of
Tourism, Trade and Industry (MTTI), National
Environmental Management Authority
(NEMA), Rural Electrification Agency (REA)
and the Plan for Modernization of Agriculture
(PMA). It provides policy guidance to project
management and works to resolve problems
that might arise during implementation. The
line ministries render policy and technical
advice of their portfolios or sectors through
the IPC and PFT.
CHAPTER THREE 3.1.3 Ministry of Finance Planning and Economic DevelopmentThe Ministry of Finance Planning and
Economic Development (MoFPED) secured
the funding on behalf of the Government of
Uganda, signed the loan agreements and is
also responsible for the release of funds and
monitoring of the loan portfolio.
3.1.4 Ministry of Local GovernmentThe MoLG is the Executing Agency for
the programme. Actual programme
implementation is undertaken at the
district and sub-county levels within the
frame work established by the government
for decentralized administration and
development.
3.1.5 The Programme Facilitation Team (PFT)This team is responsible for the day-to-
day coordination and monitoring of the
programme activities. It is charged with the
overall administration and management
of the project, liaison with the ADF, IFAD,
districts and sub-counties, providing technical
support and guidance to the districts, sub-
counties and involved NGOs, to facilitate
setting up and compliance with appropriate
financial management, accounting, auditing
and reporting procedures at district and sub-
counties, consistent with the national system,
among other roles.
3.1.6 The DistrictsThe Implementation of programme activities
is carried out through existing structures
of the district. The district CAO assigns
a Programme Support Officer (PSO) at
the district level who coordinates the
9VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
implementation and technical supervision of
the programme in their respective areas; and
the District Technical Planning Committees
mainstream the implementation of CAIIP in
their normal work plans, annual budgets and
programmes.
3.1.7 The Sub-countiesEach CAIIP implementing sub-county, under
the control of the sub county chief, carries
out a programme of community mobilization
and participatory planning and prioritization
of the rural infrastructure investments,
thereby ensuring community ownership
and promoting sustainability throughout the
life of the programme. Community leaders,
leaders of interest groups and members of
group management committees are involved
in awareness creation and community
mobilization, participatory planning and
assessments of programme effectiveness.
3.1.8 The CommunityThe programme has established
Infrastructure Management Committees
(IMCs). The IMCs sensitize fellow community
members to ensure their full participation in
prioritization, selection and implementation
of the local area infrastructure interventions
by the programme. The community also
monitors the progress of implementation of
the prioritized infrastructure.
3.2 Process descriptionCAIIP activities are implemented as described
below:-
3.2.1 PlanningPlanning of rural infrastructure investments
follows a series of participatory steps aimed
at continual close consultation with the
beneficiaries. Agreements are reached on
matters, such as: design, cost and cost
sharing, task responsibilities and organization
during implementation and on completion,
thereby maintaining “ownership” of the entire
process by the beneficiary community.
Each eligible sub-county, under the control
of the sub-county chief, carries out a
programme of community mobilization
and participatory planning resulting in the
identification of infrastructure priorities
to be included in the sub county workplan
which is eventually submitted to the PSO
at the district. The PSO consolidates all the
sub county work plans and submits a report
to PFT to be integrated in the CAIIP Annual
work plan. PFT then communicates the CAIIP
activities to the implementing districts to have
them (activities) included in their annual work
plans and budgets.
3.2.2 Funds DisbursementFor both ADB and IFAD, after the initial
deposits, subsequent transfers from the
Loan Accounts to the Special Accounts is
achieved through regular replenishments
backed by supporting documents of previous
expenditure, submitted by PFT to donors.
Similarly, transfers of funds to the Programme
District Accounts by PFT, is on a quarterly
basis upon submission by districts and
approval by PFT; of accountability for at least
50% of the preceding deposit and district
activity plans for the subsequent quarter.
In order to ensure a prompt replenishment
process, timelines for submission of
accountabilities by both PFT (to donors) and
Districts (to PFT) are in place.
10VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
3.2.3 Funds Flow ProcessCAIIP loan funds are kept on the respective
loan accounts denominated in UA and SDR
for the ADB and IFAD loans, respectively.
Withdraws from the loan accounts to the
respective Special Accounts are done by way
of submitting withdrawal applications (WAs) by
PFT and signed by the Permanent Secretary/
Secretary to Treasury, MoFPED, who is the
authorised signatory.
Funds from the Loan Accounts will be deposited
by the donors to special accounts maintained
in US Dollars in the Bank of Uganda for ADB
and IFAD loan proceeds, respectively. The GoU
counterpart cash contributions to cover local
costs of its obligations under the programme
are also deposited in these accounts.
Funds are transferred from the Programme
Special Accounts to the Programme Shs.
Account in the Bank of Uganda against
Approved Work Plans and Budgets submitted
by PFT to the donors for review and approval.
The GoU counterpart contribution to cover
local costs of its programme obligations are
also deposited on this account.
Funds are transferred by PFT from the
Programme Account against Approved District
Quarterly Work Plans and Budgets to the
District Programme Account, maintained in an
approved branch of a commercial bank in the
district, to finance the approved programme
activities at the district and in the participating
Sub-Counties, excluding the planned activities
that will be directly paid for from the loan
accounts and or from the PFT Programme
account.
For both IFAD and ADB, the authorised
signatories to Special Accounts and
Programme Accounts, respectively are the
Permanent Secretary MoLG, the Programme
Facilitator and Financial Controller; and these
are responsible for effecting payments.
The authorised signatories to the District
Programme Accounts are the Chief
Administrative Officers (CAO), Chief Finance
Officers (CFO) and district Programme Support
Officer (PSO).
Payments to contractors carrying out civil
works (Feeders Roads), Agro-Processing
Facilities (APFs) and procurement of bulk
goods namely: programme vehicles, is effected
by the Direct Payment Method.
Payments to contractors for Community Access
Roads (CARs) and markets is done through the
special account method whereas payment for
expenditures related to items imported by the
Programme such as APFs is through letters of
credit for the IFAD loan.
11VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
Figure 1: Flow Diagram for Funds Flow Process – CAIIP
KEY:
UA: Units of Account
APFs: Agro-Processing Facilities
CARs: Community Access Roads
BOU: Bank of Uganda
SHS: Uganda Shillings
USD: United States Dollars
SDR: Special Drawing Rights
3.2.4 The Procurement ProcessAll procurement of goods, works and acquisition of consulting services financed by the ADB should
be undertaken in accordance with the Bank’s Rules of Procedure for Procurement of Goods and
Works or, as appropriate, Rules of Procedure for the Use of Consultants, using the relevant Bank
Standard Bidding Documents.
The procurement of goods financed by IFAD should follow the provisions of the “Procurement
Guidelines of the International Fund for Agricultural Development (IFAD)”.
Local shopping (procurements of office supplies and general costs) applies to relatively inexpensive
items, such as: office supplies and general expenses (less than US$ 20,000). The key feature of
this procurement procedure is invitation and comparing of at least three quotations from eligible
suppliers. The steps required under this procurement method are similar to Micro procurements
under the PPDA regulations. The local shopping method is appropriate in this case as there are
many suppliers to ensure a competitive procurement process and adequate supplies are available
in the local market.
All Programme Civil Works contractors are procured using the National Competitive Bidding (NCB)
LOAN ACCOUNTS(UA or SDR)
SPECIAL PROGRAMME SPECIAL ACCOUNT IN BOU (USD)
GOU COUNTER PART CONTRIBUTION
PROGRAMME ACCOUNTIN BOU (UGX)
SPECIAL A/C PAYMENT METHOD
(CARs, Markets)
DIRECT PAYMENT METHOD(APFs, Feeder Roads, Vehicles)
DISTRICT PROGRAM ACCOUNTS (UGX).
12VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
method and for the Technical assistance staff
(consultants) under the project are hired in
accordance with the Government procedures
acceptable to the Donors. The individuals to
be recruited should have qualifications, terms
of reference and conditions of employment
satisfactory to the Donors.
3.2.5 Project ImplementationThe PFT is charged with the overall
administration and management of the project
and is responsible for the following, among
others: Coordination at the national level with
the IPC members and any other development
partners, Liaison with the ADF, IFAD, Districts
and Sub-counties, providing technical support
and guidance to the districts, sub-counties
and involved NGO’s.
Much of the programme implementation
takes place simultaneously at the District
and Sub-county local Governments. The Chief
Administrative Officer (CAO) designates one
officer to undertake the role of coordinating
the programme implementation in the
district, ensuring that the programming is
integrated within the district development
plans, consolidating sub-county work plans,
district AWPB and presented to the District
Technical Planning Committee (DTPC) and
defended at the planning, budget meetings.
The plans are eventually submitted to the PFT,
which liaises with the departments whose
sectors are related and relevant to CAIIP,
for instance, Engineering, Production and
Marketing, Community Development, Natural
Resources, Information and Planning, among
others. A Finance officer is also identified
and assigned to handle the project financial
management, records, accountability and
AWPB under the close supervision of the CFO
and the PSO. The finance officer liaises with
the sub-county Accountant and Sub-county
Chiefs on financial matters of the programme.
The administration of the selected sub-
county has to plan and develop strategies
of ensuring that they tap effectively the
project activities. The Sub-county Technical
Planning Committee (SCTPC), under the
Chairmanship of the Sub-county Chief, has
to start by understanding and internalizing
the CAIIP objectives and targets. This will be
through participating in start-up workshops,
mobilization and sensitization programmes
and accessing the POM and any other
literature that may be issued from time to
time.
3.2.6 Monitoring and EvaluationThe purpose of Monitoring and Evaluation
(M&E) is to track performance and progress
of the various project components and
activities of the programme in comparison
with the set targets in the AWPs &Bs for that
year. CAIIP M&E system was designed to be
highly participatory; it places the monitoring
responsibilities to the different stakeholders
as described below.
Ministry of Local Government
The Ministry of local Government, supervised
by the Permanent Secretary, monitors the
overall operations for planning and facilitation
purposes for the rural infrastructure for
attainment of project objectives, while MOWT
monitors the implementation of the roads
infrastructure for the attainment of national
objectives.
Programme Facilitation Team
The PFT as the programme advisory body is
13VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
responsible for ensuring that the respective
departments across the CAIIP districts
adopt and follow appropriate monitoring
mechanisms, processes and procedures.
The PFT supports the districts to establish
meaningful and measurable indicators
during the start-up phase so that suitable
means of data collection can be built into
the programme activities. The PFT team also
monitors and evaluates the overall impact of
the project and compiles the projects quarterly
and annual reports for dissemination to
the following stakeholders: ADB and IFAD,
MOFPED and Districts.
District Level Monitoring
District authorities monitor the activities,
inputs and output achievements in their
respective areas. The program support
officers at the district monitor activities,
inputs and outputs achievements in their
respective areas, coordinate and develop
systems at the district and sub-county
levels, ensuring harmonization with other
district monitoring processes to improve
the efficiency of information collection while
avoiding the duplication of monitoring tasks.
The sub-county administrations monitor
projects against stated targets and, in addition,
coordinate M&E capacity building efforts for
the sub-county. The sub-counties also ensure
that data collection processes, procedures
and responsibilities are adhered to and
reporting is undertaken in accordance with
the design of the respective CAIIP activities.
Community Interest Groups monitor sub-
county activities and investigate performance,
supported by service providers.
14VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
CHA
PTER
FO
UR
CH
AP
TER
FO
UR
4
15VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
FINDINGS, CONCLUSIONS AND RECOMMENDATIONS
4.1 Road conditional surveys, inventories and designs
4.1.1 Inadequate Roads DesignsAccording to the Terms of Reference for the consultancy contract for the design of 3,120kms
of community access roads; and for the design and supervision of 560kms of feeder roads, the
consultant, M/S Arch Design Limited, was required to carry out road inventories and conditional
assessment surveys, design and preparation of tender documents for both community access
roads and feeder roads.
A review of the designs/working drawings revealed that the designs for the roads were prepared
in accordance with the Ministry of Works and Transport guidelines for district roads based on
the classes required. However, the audit revealed that some roads were underdesigned in that
they left out key road features like bridges. For example, in Kabei sub county, Bukwo District, the
initial plan, as per designs by the consultants, was to construct five (5) roads (21.5km) at a cost of
Shs.989,682,703 without bridge works. However, during project implementation, bridge works were
found to be necessary on 2 roads (Lorok – Kapses -3no bridges and Makutano – Kapkoros -1no
bridge), hence, re-scoping the works. This led to the cancellation of construction works on two
roads and reduction of the scope of the remaining three roads. The amount reallocated from the
planned works to cater for additional scope was Shs.566,000,000 but the contract price remained
constant.
In a related case, the item of rock blasting was not provided for during the design of Longot –Sobezi
road in Sisiyi Sub County in Sironko district and Molok – Toiwo road in Kapchorwa District. During
the implementation, the rock in Kapchorwa District became an obstruction to the contractor and
hence works were terminated at the point of the rock, whereas, in Sironko, the road was narrowed
to fit in the small space manually dug out on the rock sides by the local people as indicated in
Picture: 1 below:
Picture 1: Rock a long the road route on Longot – Sobezi road
16VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
Inadequate designs were caused by the
failure of the consultants to carry out
proper road inventories to establish detailed
road conditions. It was also noted that the
consultant, in some cases, did not engage the
district staff during the inventory and design
process and review.
Management attributed the inadequacy in
the designs to the fact that the consultant
was overwhelmed by the workload, which
had been anticipated to be carried out in
three lots. However, during the award of
the contract, one consultant (Arch Designs
Limited) bidded lowest in all the lots and
was awarded all the contracts. They further
explained that some roads were inaccessible
and therefore, no detailed inventory study
was done on them; and others required re-
alignment to avoid compensation costs that
had not been provided for.
Some communities which were meant
to receive infrastructure were denied the
opportunity as monies meant for such
development were diverted to address
omissions, such as, construction of bridges.
Although management explained that the
eliminated roads were catered for in the
subsequent plans, there was no evidence to
the effect.
Conclusion
Designs which do not represent the
actual condition of the road lead to project
cost escalations, diversion of resources,
substandard works, and project delays and
deprive the communities of the intended
benefits.
Management Response:
Inadequacies in designs were due to factors
which were exogenous to the consultant, viz:
a) Difficult terrain and weather conditions
The consulting firm faced challenges
associated with the terrain and harsh weather
conditions during the design process. This is
particularly the case with the Elgon Region
(Bududa, Manafwa, Mbale, Sironko and Bukwo
districts) and low lying areas of Butaleja and
Namutumba Districts. Most of the roads
were non-existent and, therefore, the design
teams had to carry out the condition surveys
on foot. Landslides /mud slides and heavy
rains significantly affected the assignment.
As a consequence, some of the design teams
made design estimates based on interviews
with the local communities, observations, and
experience because they could not traverse
through the difficult stretches.
To address this problem, management,
in liaison with the affected districts and
sub-counties, re-scoped the works and re-
prioritized the scoped-out works under Batch
C.
b) Cost control
In an effort to ensure that the costs are within
the loan amount, some trade-offs were
imposed on the consultant in terms of the
design of the roads. This was particularly
the case where widening of the road to the
standard width and/or gradient would involve
excessive ‘cut-to-spoil’ of hard material and/
or rock. As noted by the auditors, Longot –
Sobezi road in Sisiyi sub-county in Sironko
district and Molok- Toiwa road in Kapchorwa
District were affected by this factor of cost.
17VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
c) Limited design time given the workload
The design consultant was required to
traverse the entire project area, covering
54 feeder road sections, measuring 580Km,
and 534 community access road sections,
measuring 3,120Km, in a 2 year period of time.
In order to do a good design, it required the
consultants to carry out inventories spanning
over two seasons that is, the dry season and
the wet seasons. This time was not available.
In order to balance the work load with time,
management approached the design of
community access roads in a phased way i.e.
Batch B and Batch C. This strategy enabled
the consultant to focus on Batch B designs
and later Batch C while the civil works for
batch B were on-going.
The Project Engineers as well as the District
Engineers are involved in the review of the
consultant’s output.
However, given the cost implication, the
time constraint and workload, the quality
assurance processes are on a sample basis.
The District Engineers are involved at 3
levels:
a. Prioritisation of the roads
b. Road inventory and design of the roads
c. Review of the bidding documents
However, given the fact that most of the roads
do not exist and given the time constraint, the
design process is very challenging.
Management has, however, noted the
recommendations of the Auditor General
and appropriate action will be undertaken
accordingly.
Auditor’s Comment:
The design exercise was not properly
managed. The challenges ought to have been
identified at an early stage and mitigation
factors devised.
Recommendations
• Management should ensure that contractors
are strictly supervised during the design
period and designs should be reviewed for
appropriateness before approval.
• Management should ensure that consultants
carry out detailed road inventories prior to
designing the road infrastructure.
• Design contracts should be spread
to a number of consultants to avoid
overstretching the consultants and delays in
the implementation of projects.
• The District Engineer should be adequately
engaged in the design and review process.
4.1.2 Inconsistencies in the Bills of Quantities (BOQs)According to the Terms of Reference for the
consultancy contract, the consultant was
required to carry out road inventories and
conditional assessment surveys, design and
preparation of tender documents for both
community access roads and feeder roads.
The audit established that for some projects,
there were inconsistencies between the
improvement plans and the bills of quantities.
For example, the quantities for reshaping and
road formation did not match the total road
length. In other cases, the quantity for gravel
in the bills of quantities did not match the
design quantity as shown in Appendix iii.
The inconsistencies in BOQs were caused by
inadequate quality control checks undertaken
by both the consultant and the MOLG.
Inconsistencies in BOQs lead to overpayments.
18VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
Conclusion:
There were inconsistencies in BOQs which lead to overall contract escalations.
Management Response
Management acknowledged that there were some inconsistencies in the BoQs and the improvement
plans had been put in place. In particular, there was overlap between the ‘Reshaping of Existing
Road Formation’ and ‘New Road Formation’. In contracts where this occurred, management
established that there was need for widening the roads to achieve the desired road width, hence,
creating two parts namely, a) partial reshaping of Existing Road Formation and b) opening up a
section of the road hence ‘New Road Formation’ bill item.
This was the design approach and the bidders submitted bids accordingly.
Auditor’s Comment:
The BOQs were not properly prepared. Management’s improvement plan is a matter of future
assessment.
Recommendation:
Both the Ministry and the consultants should put in place proper quality control measures to
enhance the accuracy and comprehensiveness of the BOQs.
4.2 Establishment of Infrastructure4.2.1 Establishment of Infrastructure on registered Public LandAccording to the CAIIP Programme Operational Manual, prior to improvement of any selected
market place, the Programme Facilitation Team (PFT) should be assured by the district/sub-
county of clear legal ownership by producing documentation/land lease. The market management
guideline, section 2.0 also required the Government of Uganda, represented by the sub-county
where the market is located, to own the land and all the facilities and structures therein.
The audit established that all the 12 market sites, valued at Shs.1,318,402,547, visited in the districts
of: Iganga, Mukono, Mityana, Masaka, Sembabule, Pallisa and Kapchorwa were established on
land without proper ownership (untitled land), contrary to the programme operations manual and
market guidelines. The sub county authorities informed the audit team that the land registration
process was underway in some of the sub counties. For Sub counties like Ntunda in Mukono that
had inadequate land, the sub county had purchased land from private land owners and the process
of transfer was underway. However, management explained that the land ownership requirements
were later relaxed and districts/sub counties were only required to sign a letter of undertaking and
provide a letter of comfort indicating that the land belonged to the entity. No evidence was provided
to support this explanation.
The sub county authorities interviewed attributed the failure to secure land titles to lack of funds
to facilitate the land registration process.
The establishment of markets on untitled land exposes the investment to a risk of loss should the
19VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
land on which they are established be claimed
by another party.
Conclusion
Establishment of permanent structures
on untitled land contravened the project
guidelines and criteria in the programme
operations manual and exposed the district/
sub county to loss of the infrastructure.
Management Response
Lack of land titles for public land is a nationwide
problem. During the loan negotiations of the
CAIIP, it was noted that most of the public
land in the country is not titled. It was further
noted that the process of securing land titles
takes long and in most cases delays the
implementation of projects. It was agreed
between the ADB and the Government, under
Article V, Section 5.01 (ii) of the Financing
Agreement that a Letter of Comfort stating
that the land where the market infrastructure
is to be constructed shall belong to the
Government or the community. The
Ministry of Finance, Planning and Economic
Development issued the Letter of Comfort in
fulfilment of Conditions Precedent to First
Disbursement. At implementation level, the
beneficiary sub-counties and District Local
Governments issued similar assurances prior
to the construction of the infrastructure.
Management stated that the process of
securing titles for these public lands was
on-going and also promised to follow up with
the districts and in liaison with the Ministry
of Lands, Housing and Urban Development
secure land titles accordingly.
Auditor’s Comment:
The letters of comfort were used as a stop-
gap measure, but in order to guarantee the
security of public land, land titles have to be
processed.
Recommendation
CAIIP management should ensure that all
programme implementing sub-counties
secure land titles for the land on which
project infrastructure was established.
4.2.2 Quality of works and workmanshipThe completed works should meet the quality
specifications in the contract (Conditions of
Contract, Clause 16).
However, a physical inspection of the works
revealed that the quality of works varied
from good to bad as some infrastructural
works were found not to be of the expected
standards.
Buildings works:
83% of the 12 constructed markets visited
had good visual finishes and the roofs were
provided with the recommended covering
material. Field measurements revealed
that there was compliance in setting the
dimensions of structures during construction.
Examples of such markets included:
Kyawagonya Market in Masaka District,
Ntunda market in Mukono District, Kapunyasi
market in Pallisa District and Lwebitakuli
market in Sembabule District as shown in
Pictures: 2 & 3 below:
20VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
Picture 2: Ntunda market in Mukono District Picture 3: Lwebitakuli market in Sembabule District
Mityoru market in Kaptanya sub-county, Kapchorwa District was not satisfactorily constructed.
This was reflected in the cracking of floors and slab tops, cracking in curtain walls, failed slabs for
VIP latrines, timber warping for roof truss members, dissimilar iron sheets on same roof and lower
quality iron sheet material than specified. The pictures below show some of the defects revealed.
Picture 4: showing dissimilar iron sheet material on the same roof
Picture 5: cracking of slab for Mityoru market in Kaptanya, Kapchorwa District
Picture 6: Damaged latrine slab that has failed at Katosi market
Picture 7: Failed tank platform at Maanyi market
21VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
Audit tested the strength of some market members, cattle loading points and bridges to determine
whether they corresponded with the specified strength. Audit established that most of the members
tested met the specified strength except a few that did not meet as shown in Appendix iv.
From the results of the Schmidt hummer test above, eight out of ten (80%) points tested met the
specifications in the bills of quantities. Stall slabs met the specifications whereas the concrete
strength of the 2 out 4 cattle loading points at Kawete cattle market failed.
Road works:
Road Surface Condition
Inspection of both feeder and community access roads sampled (47 roads) revealed that 39 (83%)
of the roads visited had good surface condition (Appendix v). However, it was also observed that on
some road sections, localised rutting and pot holes have started developing.
Picture 8: Good surface condition – Hasahya- Naboa Rd Picture 9: Bad surface condition-Magongolo-Railway Line Rd
Drainage condition
41 out of 47 inspected roads were provided with adequate drainage by formation of appropriate
cross falls, side drains and mitre drains and culvert lines (Appendix v).However, the long term
performance of the drainage structures was jeopardised by improper jointing of most culvert
pipes, lack of provision of culvert end structures and unsuitable embankment material.
Audit inspection further revealed that, culverts were not jointed as per specifications which required
that culvert joints be sealed with mortar. In addition, most of the culverts inspected had cracked or
broken head and wing wall structures. Some of the culverts were inadequately covered with gravel
and as such were exposed to damage by traffic.
22VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
Picture 10: Damaged culvert that has given way due to inadequate back filling at Ch 2+600 on Lwengo – Kyawagonya road.
Picture 11: Cracked culverts on Akopor-Kamuli road in Tororo DistrictPicture 12: Broken Culvert End Structures on Kakule-kameruka road in Budaka District
The work defects shown in the pictures above were caused by inadequate supervision by the
project managers, contractors’ non-adherence to the technical specifications and use of poor
quality working materials.
Poor quality works lead to quick deterioration of the infrastructure, increased maintenance costs,
reduction of the useful life of the infrastructure, loss of the invested amounts and endangering of
the lives of users.
Conclusion:
The quality of works on some of the roads, markets and APF shelters constructed was not up to
the expected standard. Works which do not conform to the required quality specifications lead to
quick deterioration of roads hence increasing the overall maintenance costs.
23VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
Management Response:
Management has taken adequate measures
to ensure that specifications are adhered to.
The defects on the roads are attributed to the
following:
Excessive traffic and overloading: the
community roads are now taking on too much
traffic beyond their design capacity. Trailers
and heavy trucks are now diverting off the
main roads to the community roads due
to their improved condition. Restriction of
traffic/axle loads could be the solution.
Movement of animals (cows) along the roads:
In the cattle keeping areas, animals are
moved along the road and get water around
the culvert outlets, hence damaging the
headwalls and the road beds.
Restriction is necessary but there is no
enforcement mechanism in place.
Auditor’s Comment
Management is explaining maintenance
challenges, but some of the defects happened
during construction as a result of not adhering
to specifications.
Recommendations:
• The project managers should always ensure
that the contractors adhere to the required
specifications.
• Works that do not meet the required
technical specifications should not be paid for.
4.2.3 Quantity VerificationOverpayment on worksPayments should be made for actual work
done and is arrived at by way of measurement
using measurement sheets. PPDA regulation
236(5) of the PPDA Regulations require the
measurement of work done to be undertaken
during the performance of the contract
and reconciliation of the measurements
upon completion of the contract. It is also a
requirement that the Client pays for works
that have been executed and before any
payment is effected measurement sheets
and supervision report have to be prepared
detailing the amount and quality of works
executed.
A review of the bills of quantities (BOQs) and
Interim payment certificates (IPCs) revealed
that payments worth Shs.307, 627,262 were
made for quantities over and above the actual
works executed. This includes overpayments
on Feeder and community access roads which
amounted to Shs.114,214,910 representing
37.1% (Appendix vi) and Shs.146,056,260
representing 47.5%, respectively(Appendix
vii) while those on markets were worth
Shs.47,356,092 or 15.4% (Appendix viii).
Further scrutiny of IPCs and subsequent
physical inspection revealed that on four(4)
road contracts, payments amounting to
Shs.63,471,015 had been made for works not
executed at all. (Appendix ix).
The overpayments on road works were
caused by incorrect measurement of gravel
quantities on all the roads, culvert length
and road length while the overpayments on
construction of markets were a result of over-
estimation of number of columns and steel
section quantities; ambiguous provision for
storm water and surface run-off; parking area
and access roads. Inadequate supervision
and absence of measurement sheets equally
contributed to overpayments and could have
also caused payment for unexecuted works.
Overpayments and payments for unexecuted
works are a loss to Government, as such,
funds would have been used to establish
more infrastructures in other sub counties.
24VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
Conclusion
The project paid for unexecuted works and
overpaid contractors who were engaged to
do road works and construction of markets.
This resulted into loss of funds, deprived
the communities of services and hampered
the major programme goal of improving
agricultural infrastructure.
Recommendations:
• Management should enforce the recovery of
the funds from the contractors in respect of
the irregular payments made to contractors.
• Management should ensure that Interim
payment certificates (IPCs) are always
accompanied by measurement sheets, which
should be checked for all the contract works
executed.
• Project managers should step up supervision
to ensure that all the work is done as per
BoQs and that payments are only effected for
quantities of works actually executed.
4.3 Completion of ProjectsAccording to the Special Condition of
Contract (SCC), the completion period for the
construction of rural markets, feeder roads
and community access roads was stated as
six (6) months, whereas for APF shelters it
was three (3) months.
It was established that most of contractors for
markets, roads and APF shelter had delayed
to complete works. An analysis of 12 selected
contracts for the construction of markets in
7 districts revealed that 17% of the contracts
were completed within the stipulated time.
However, 75% experienced an average delay
of 8 months. The details are indicated in
Appendix x.
Site inspection further revealed that some
projects had been abandoned for more than
28 days without the authorization of the
responsible officer/Project Manager, yet the
works had not been completed. In one road
construction contract,10 only setting out, site
clearing works and earth works had been
carried out on some sections of the roads.
These works had deteriorated to a level
that will require redoing the same activities
already paid for as shown in pictures 13 and
14.
10 Rehabilitation of 5 CARs contracted to Kapchorwa Broadway Agencies in Kaptanya Sub county Kapchorwa District.
25VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
Picture 13: Chebukat – Kaptokwoi road Picture 14: Kashabul – Mokotu road surface conditions
Picture 15: Molok – Toiwo road
Other abandoned sites include Lugusuulu cattle market in Lugusuulu Sub county Sembabule
District and APF shelters in Kapchorwa District which had been abandoned for a period of 750 and
726 days, respectively.
The abandonment of contract works was attributed to inadequate financial and equipment capacity
of the contractors, a problem that should have been addressed at the procurement stage.
Delays in completion of works were partly caused by delays in payment of contractors which
ultimately impacted on their cash flows. There was also inadequate supervision of the projects by
the district staff, mainly because of irregular and limited facilitation from the PFT.
The delays by contractors to complete works within the stipulated time deprived the communities
of access to services as originally planned.
As a result of the abandonment of works for the rehabilitation of 5 CARs in Kaptanya Sub
county Kapchorwa District, the works that were previously carried out had deteriorated beyond
rectification. The scope of works needs to be reviewed and works re-tendered. This will result into
a loss of Shs.83, 134,025, which had already been paid to the Contractor.
Picture 16: Kaplak – Water source road surface conditions.
26VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
Liquidated Damages
It was also noted that while the contracts
clauses provide for termination of contracts and
charging of liquidated damages in case works
are delayed by the contractor, management did
not take any steps to enforce these contractual
requirements.
A review of fifteen (15) contracts revealed that
a total of Shs.417,141,734 was not charged to
various contractors in liquidated damages.
Of this, Shs.117,987,845 was in respect of
markets (Appendix x), Shs.195,978,756 for
community access and feeder roads (Appendix
xi and xii)and Shs.103,175,133 for APF shelters
(Appendix xiii).
Conclusion
Delayed completion of works deprives
communities of services and also hampers
the realisation of the overall sector goal of
contributing to poverty reduction and economic
growth in Uganda through commercialisation
of agriculture.
Management Response
The contract period for the execution of civil
works has been standardized to 6 months
for all contracts. Management is well aware
that this period is short but a short contract
period is used so as to exert pressure on the
contractors to prioritize the project works.
Most contracts delayed despite numerous
extensions of completion times due to factors
which, in most cases, are beyond the control
of both the Contractors and the Employers,
namely: vagaries of weather (floods,
mudslides, and drought), limited availability of
gravel material and the difficult terrain in some
project districts.
Management explained that they could not
charge contractors Liquidated damages
because the delays on the other hand
were occasioned by the Client. Payments
to contractors delayed, review of designs
was not carried out on time and sometimes
the right of way was not secured. These,
according to management, are compensation
events, which could have led to the granting of
EOT. It is, therefore, practically impossible to
recover liquidated damages without causing
unnecessary litigations.
Auditor’s Comment
The challenges explained by management
should have been properly documented
and handled in accordance with the basic
principles of contract management. Where
necessary, EOT should have been granted to
avoid counting the delay on the contractor.
Recommendations:
• Management should invoke the relevant
contract clauses for timely execution of
contracts, by charging liquidated damages
and termination of contracts in extreme
cases.
• Management should recover all the amounts
outstanding in liquidated damages.
• Supervision of contracts should be
enhanced and arrangements should be put in
place to ensure that payments processes are
streamlined to avoid delays.
• The client should make site inspection a
mandatory requirement to all contractors
during the bidding process.
• Contractors who do not perform according
to requirements should be black listed by the
client and PPDA to avoid future recurrences.
27VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
4.4 Operation and maintenance of established infrastructure4.4.1 Occupancy of MarketsAs per the agreed contract conditions, the market should be constructed, completed and handed
over to the district authorities for ownership. The obligation falls on the district to ensure occupancy
of the markets.
It was noted through Field visits and interviews that although market structures had been
completed, several markets were not occupied.
Picture 17: Unoccupied market structures in Katosi Market in Mukono District
Picture 18: Bukulula Market in Masaka District.
Picture 19: Informal market operational in the neighbourhood
Picture 20:New market facilities abandoned by the vendors
From the analysis of the markets visited, it was established that inspite of the heavy investment
(Shs.1.33 billion) made as shown in table 2, only 45% of the markets were occupied. 55% of the
markets, valued at Shs.964,206,454 were not occupied hence putting to waste the amount spent
on their construction
28VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
(Table 2). Table 2: Occupancy status of the markets visited
District Subcounty Market Name Contract Price Status
Iganga Namungalwe Kaweete 165,091,920 Not Occupied
Iganga Nakigo Nabitovu 97,753,987 Not Occupied
Mityana Maanyi Maanyi 115,248,184 Occupied/Operates weekly
Mityana Bulera Bulera 131,733,341 Occupied/Operates weekly
MukonoNtenjerru Katosi 210,909,201 Not Occupied
Ntunda Ntunda 98,983,747 Not Occupied
Sembabule Lwebitakuli Lwebitakuli 120,632,481 Occupied/Operates daily
Pallisa Petete Kapunyasi 107,283,776 Not Occupied
MasakaKyawagonya Lwengo 108,214,840 Occupied/Operated weekly
Bukulula Bukulula 89,246,328 Not Occupied
Kapchorwa Mutyoru Motyoru 88,459,219 Not Occupied
Total 1,333,557,024
Non-occupancy of the constructed market structures was attributed to failure by the district
authorities to enforce their occupancy, absence of adequate storage facilities, remote locations
(some of the markets were far from the trading centres or traditional market sites) and non-
operational agro processing facilities, which would have attracted vendors to the markets.
Non-occupancy of the markets deprives the districts and sub-counties of the potential revenue
from market dues.
The failure to put the markets to their intended use has led to their physical deterioration as a
result of absence of preventive maintenance measures and this has exposed them to vandalism/
theft and misuse as some have been reduced to playgrounds, animal shelters and grazing land.
Picture 21: Vandalised transformer at
Bukulula Market.
Picture 22: Kids playing and Animals grazing in Kapuyansi market
29VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
Conclusion:
Most of the markets inspected were not occupied which anomaly puts the hefty government
investment to waste and jeopardizes the programme intended objective of improving household
incomes through commercialisation of agriculture.
Management Response
There are several reasons that explain the non-occupancy of markets, namely: poor location
(Public land is a distance away from the current trading area), lack of enforcement of the Market
Act by the Local Governments, political interference in the running of markets, reluctance to pay
market dues by the vendors, inadequate produce/commodities to sell in the market during the
off-season periods and the timing of the visit (weekly, bi-weekly and others are monthly markets).
A series of meetings have been held with the Chief Administrative Officers of the affected districts
and an action plan has been developed.
Auditor’s Comment
Some markets remain unoccupied and the developed action plan with CAOs is a matter of future
assessment.
Recommendations:
• Local governments should step up mobilisation and sensitization campaigns, and enact bye-
laws to enforce occupancy and utilisation of the established market facilities.
• Market structures should provide for adequate storage facilities for the end users.
• Management (PFT) should expedite the installation and commissioning of all the APFs; as this
will attract vendors to the market premises.
4.4.2 Functionality of Agro Processing Facilities (APFs)In a bid to address the challenge of post-harvest handling and value addition in the CAIIP
implementing sub counties, the program planned to supply and install several units of assorted
agro-processing equipment which included: maize mills, coffee hullers, rice hullers and milk
coolers. Each beneficiary sub-county was to select an agro-processing facility which befitted/
matched the agricultural produce of the area.
The audit, however, established that the supply and installation of the said facilities delayed and
there were no operational agro-processing facilities in any of the seven (07) CAIIP implementing
districts visited. See Appendix xiv.
The audit inspection further revealed that there was no co-ordination between the contractors
for the shelters and the suppliers of equipment as they delivered equipment before shelters were
fully completed, leaving the equipment lying idle at the respective district/sub county premises.
For example, in Mubende, Kiganda Sub County, a milk cooler was delivered to the sub county
headquarters and left exposed to extreme weather conditions.
30VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
Picture 23: A milk cooler in the compound of Kiganda Sub county headquarters
The non-operationalization of the agro processing facilities was attributed to the delays in
construction of shelters caused by inadequate contract design/packaging and failure by
management to identify the proposed private operators to run the completed facilities.
As a consequence, the non-operationalization of the agro-processing facilities deprived the target
beneficiaries of the expected benefits of value addition to their local agricultural products. It has
also deprived the respective local governments of enhanced revenue collection from the use of
the APFs.
Conclusion
The APFs in all the CAIIP participating districts were not operational, which deprived communities
of benefits of value addition to their products, which would have improved their farm gate prices
and improved household incomes.
Management Response
The operationalization of APFs involved the co-ordination of 4 key service providers, namely: (a)
construction of the shelters, (b) supply and installation of the equipment, (c) supply of power
(extension of the grid) and (d) Certification and issuance of permits from UMEME. The co-ordination
of these stakeholders was very challenging.
In addition, the supply, installation and operationalization of the facilities process faced two
challenges:
Limited resources on the ADB Loan to finance the grid extension, which necessitated negotiating
with IFAD to finance the activity.
Rejection of the letters of credit that were secured by the equipment suppliers from Tropical Africa
Bank in favour of the equipment manufacturers following the events in Libya.
31VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
In spite of all the above, to date, all the 123 facilities (33 rice mills, 37 milk coolers, 14 coffee
hullers and 39 maize mills), together with all the accessories, have been delivered into the country
and the suppliers are in the final stages of installation. 66 of them are currently at the testing and
commissioning stage with 16 of them already in operation.
Auditor’s Comment:
The sampled APF were not operational at the time of audit. Installation of some of the procured
APFs is still on-going.
Recommendations:
• In future, management should ensure that contracts are designed/packaged and scheduled
appropriately to ease their execution.
• Management should expedite the operationalization of the completed and fully installed facilities.
• Management should expedite the installation of the remaining facilities.
4.4.3 Maintenance of infrastructureThe routine and periodic maintenance of the entire infrastructure put in place under the program is
the responsibility of the respective beneficiary districts. The District Administrative and Operational
Guidelines, Manual A (Policy Document for Road Maintenance, October 2003, MoWT) Section A- 2
Declaration No. 1 requires that the district shall make every effort to provide adequate routine
maintenance of all maintainable roads (in particular all roads that have been recently constructed
or rehabilitated) to protect the investments, provide an acceptable level of service necessary for
basic access and road user safety.
The audit inspections carried out established that there were no maintenance interventions put in
place by the district and sub-county authorities to ensure the sustainability of the infrastructure
put in place by CAIIP. Most of the infrastructures put in place were deteriorating due to lack of
maintenance. For example, the roads constructed in earlier batches of CAIIP I were in bad shape
with potholes, silted culverts and over grown vegetation along the roads reducing their effective
carriage way widths by approximately 0.5 to 1 meter for different sections of the roads as shown
in the pictures:
32VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
Picture 24: silted culvert along Nsambya – Lugusulu Road in Sembabule
Picture 25:section with overgrown vegetation along Radio Uganda – Nasuleta Road in Pallisa District
The markets also exhibited several defects, including: overgrown vegetation in the open spaces,
peeling off of paint and many others as shown in the pictures:
Picture 26: Overgrowth of vegetation at Katosi Market in Mukono
Picture 27:peeling off of paint at Kapunyas market in Petete
The sub-county and district authorities attributed the failure to maintain the roads to inadequate
funding from the Road Fund and absence of agreed arrangements between the Ministry of
Local Government (PFT) and the implementing districts for the maintenance of the established
infrastructure.
Lack of routine maintenance increases the future maintenance cost for the infrastructure and
compromises the safety of road and market users. Without maintenance, the sustainability of the
established infrastructure put in place by the program is bound to remain a challenge and also
hamper the realization of the program objectives.
Conclusion
The infrastructure constructed under the program is not being maintained. This is likely to increase
future maintenance costs and compromise the safety of the users.
3m
33VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
Management Response:
The Government, through the Uganda Road Fund, is releasing resources to sub-counties for
maintenance of Community Access Roads. The Project management submitted a list of all
rehabilitated roads to the Uganda Road Fund to harmonise the prioritisation of the community
roads in the Project Sub-Counties for maintenance. In addition, Government has procured road
equipment which will be distributed to the districts for road maintenance. Management has
taken note and will closely liaise with the Road Fund and the Project Districts to ensure that the
rehabilitated roads are maintained. The rehabilitation of additional roads will be conditioned on
proper maintenance of the completed ones.
The communities are being encouraged, through local leaders, to maintain these roads on
community based (bulungi bwansi) basis and Mityana District is doing it.
Auditor’s Comment:
Programme roads have been neglected by district authorities.
Recommendation
• The respective districts should effect routine and periodic maintenance of infrastructures so as
to prevent them from further deterioration.
• CAIIP management should consider signing a MoU with the implementing districts, committing
them (districts) to maintain the established infrastructure.
• Government, through the Uganda Road Fund, should prioritize allocations to districts and
consider matching the amount of allocation to the stock of roads in a given district.
John F. S. MuwangaAUDITOR GENERAL
34VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
GLOSSARY OF TERMS
“Agricultural Infrastructure” refers to district and community access roads that ease evacuation
of agricultural produce, market place infrastructure that includes; shelters, stalls and agro-
processing facilities that accommodate vendors and create value addition respectively, and the
rural energy solutions that aid the powering of markets and agro-processing equipment.
The “Contract” is the agreement between the Employer and the Contractor to execute, complete,
and maintain the Works.
The “Contractor” is a person or corporate body whose Bid to carry out Works has been accepted
by the Employer and is named as such in the Agreement, and means Provider as defined in the
Public Procurement and Disposal of Public Assets Act, 2003.
The “Employer” is the party named in the Agreement, who employs the Contractor to carry out
the Works and means Procuring and Disposing Entity as defined in the Public Procurement and
Disposal of Public Assets Act, 2003.
The “Contract Price” is the price stated in the Agreement and thereafter as adjusted in accordance
with the provisions of the Contract.
The “Completion date” is the date of completion of works as certified by the Project Manager.
“Bills of Quantities” means the priced and completed bills of quantities forming part of the Bid,
which provides the agreed rates and prices for payment for an Admeasurement Contract.
35VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
APPENDICES
APPENDIX i: Documents reviewed
S/N Document Purpose
1. Project Appraisal reports.To obtain the program background, goals and objectives, project implementation areas and Establish how CAIIP operations are funded.
2. CAIIP Operations Manual Get an understanding of processes and procedures
3. Loan Agreements Understand loan conditions and terms.
4. Project work plans and progress reports.To compare project performance against set targets and obtain information regarding to challenges the project is facing.
5. The Local Government Act To understand the legal frame work of MoLG.
6. Staff structure/ Organogram To establish the staffing and reporting levels
7. Contract Agreements(APFs, Markets, CARs, FRs, agro-shelters) To ascertain contract prices and terms.
8. Project audited accounts Obtain project financing and budget performance.
9. Interim payment certificates (APFs, Markets, CARs, FRs, agro-shelters) Establish amount of money paid per given contract.
10. Prioritization reports for infrastructure To understand how infrastructure was selected targeting beneficiary communities.
11. CAIIP final accounts Extract budgets project funding.
12. Infrastructure designs (Roads, Market shelter, agro-shelters, FRs) To ascertain whether established adhered to designs.
13. Procurement contract management files To establish whether procurements were followed PPDA and donor regulations
14. BOU Bank statements for CAIIP Ascertain payments made for programme activities.
15. MoWT standards for roads. Establish whether established road infrastructure met required standards.
36VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
APPENDIX ii: List of interviews conducted
Section Officer (s) Purpose of the interview
Project facilitation team ( PFT/MoLG)
National Programme Coordinator
To obtain an understanding of community agricultural infrastructural improvement programme, the project coverage, the key stake holders, he funders of this programme, the planning process, the benefits realised from the project, the challenges faced, and possible solutions to the challenges and recommendations.
Project facilitation team ( PFT/MoLG)
Financial ControllerTo obtain an over view of the project funders, the procurement system, the payment system and the accountability process. Benefits of the project, challenges faced, and recommendations.
Project facilitation team (PFT/ MoLG)
Monitoring and Evaluation Specialist
To obtain an over view of the monitoring process, the reporting process, the key stake holders, benefits of the project , challenges ,remedies to the challenges and the recommendations.
Project facilitation team (PFT/ MoLG)
Infrastructural Advisor
To obtain the status of established infrastructure and the maintenance plan of the same. The planning process, selection of the project implementing sub counties, selection of the roads to be rehabilitated. Benefits of the project, challenges faced solutions to the challenges and recommendations if any.
Project facilitation team ( PFT/MoLG)
Rural Energy Specialist
To obtain an understanding of the agro-processing facilities procured and installed, the selection process of the benefiting sub counties, benefits realised, challenges faced, possible solutions and recommendations.
Project facilitation team ( PFT/MoLG)
Community Development Officer
To obtain an understanding of the mobilisation process, the key persons involved, benefits realised, challenges faced, possible solutions and recommendations.
District Chief Accounting Officer (CAO)
Obtain a brief on the benefits of the programme to the district, challenges faced, possible solutions and recommendations.
District Project Support Officer
Obtain a brief on the project implementing sub counties and their selection, the basis for the road choices to be rehabilitated and their maintenance plan, how contractors are procured, benefits realised, challenges, possible solutions and recommendations.
Sub-county Sub-County Chief
To get an understanding of the project implementing sub counties, the key stake holders, the people involved in moblising the communities, the payment of contract works process, the benefits obtained, challenges faced, possible solutions and recommendations.
Sub-county Infrastructure Management Committees
To obtain an understanding about the formation of these committees, their roles in the project implementation, benefits obtained, challenges faced, possible solutions and recommendations.
37VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
Appendix iii: Inconsistencies in BOQs
SN District Contract Name BOQ ITEMS Description Remarks
1 Mukono/Kayunga
Rehabilitation of 45.4 Km of Feeder Roads under the Community Agricultural Infrastructure Improvement Programme 1 (CAIIP-1) in Mukono and Kayunga
3.1.1 Re-shaping of existing road formation including watering and compaction
Items 3.1.1 and 3.2.3 for consistency purposes should equal the length of the road. In this case this was not so with probable results as high contract rates.
3.2.3 Form, water and compact roadbed
2 Mityana/ Mubende
Rehabilitation of 44.2Km of Feeder Roads under the Community Agricultural Infrastructure Improvement Programme 1 in MITYANA and MUBENDE
2.1 (Re)-establishment of road alignment
Items 2.1 and 2.2 should be similar which was not the case for Kalangalo-Kamuliroad,ssese-Kisana and Kibalinga-Lwebyayi-Kaweri roads.
2.2
Clear site of all grass, bushes and boulders (up to 1.5m max. girth) and grub all roots of grass and bushes including excavation of topsoil from road formation
3.1.1Re-shaping of existing road formation including watering and compaction
Items 3.1.1 and 3.2.3 for consistency purposes should equal the length of the road. In this case this was not so with probable results as high contract rates.
3.2.3 Form, water and compact roadbed
3 Masaka/ Sembabule
Rehabilitation of 54.9km of feeder roads under Community Agricultural Infrastructure Improvement Programmes 1 Project (CAIIP 1) in Sembabule and Masaka Districts
2.1 (Re)-establishment of road alignment
Items 2.1 and 2.2 should be similar but this was not the case for Kasambya-Lungusulu Road and Kyamulimbwa-Lusango roadThe sum of items 3.1.1 and 3.2.3 should be equal to the total length of the road, this was not the case for Kasambya-Lungusulu Road and Lwengo– Kyawagonya road
2.2 Clear site of all grass, bushes and boulders
3.1.1Re-shaping of existing road formation including watering and compaction
3.2.3 Form, water and compact roadbed
38VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
APPENDIX iv : Results of Schimid Hummer test
Location/Point
Angl
e of
Im
pact
(deg
)
Acce
ptab
le V
alue
Co-
rela
ted
St
reng
th fr
om g
raph
(psi
)
Actu
al C
oncr
ete
St
reng
th (M
Pa)
Con
cret
e cl
ass
Aver
age
stre
ngth
cla
ss
Spec
ifica
tion
Rem
arks
1-Lwebitakuli Market Stall Slab
LHS -90 27.73 3,500 24.13 C25
C25 C20 Passed RHS -90 27.27 3,500 24.13 C25
2-Bukulula Market Stall Slab
LHS -90 28.20 3,750 25.86 C25
C25 C20 PassedRHS -90 28.20 3,750 25.86 C25
3-Mutyoru Market Stall Slab
LHS - 9 0 25.00 3,000 20.68 C20
C20 C20 Passed
RHS - 9 0 26.40 3,250 22 C20
4-Kapunyasi Market Stall Slab
LHS - 9 0 27.80 3,750 25.86 C25
C25 C20 Passed
RHS - 9 0 27.20 3,500 24.13 C25
5-Kyawagonya Market stall slab
LHS -90 26.40 3,400 23.44 C25 C25 C20 Passed
RHS -90 34.40 4,800 33.09 C35
6-Kawete Cattle market – Loading points
Loading point 1 -90 26.30 2,270 15.65 C15 15 20 Failed
Loading point 2 -90 26.40 3,250 22 C25 25 20 Passed
Loading point 3 -90 25.00 3,000 20.68 C20 20 20 Passed
Loading point 4 -90 25.55 2,095 14.44 C15 15 20 Failed
Source: OAG Analysis
39VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
APPENDIX v: Condition of surface and drainage conditions for Feeder and community access roads
(a) Feeder roads
District Road Name Length(Km) Surface Condition
Drainage Condition
Mukono Ntenjeru-Bbule Rd 19.0 Good Fair
Mubende Kibalinga-Lwebyayi-Kaweeri Rd 22.7 Good Fair
Mityana Bbanda-Lusalira Rd 9.9 Good Fair
Kalangalo-Kamuli Rd 7.5 Good Fair
Sembabule Kasambya-Lugusulu Rd 22.8 Fair Fair
Masaka/Lwengo Lwengo-Kyawagonya Rd 12.3 Good Fair
Masaka/Kalungu Kyamulibwa-Kiwaawo-Lusango Rd 10.9 Fair Fair
Budaka Iki Iki-Kameruka Rd 7.8 Good Fair
Namirembe-Kameruka Rd 9.4 Good Fair
Mailotano-Mugiti Rd 6.1 Good Fair
Pallisa Kamuge-Mudiri-Buseta Rd 10.6 Good Fair
Radio Uganda –Petete Rd 8.8 Good Fair
Butaleja Jobusiba-Namaholo-Lwamboga Rd 7.2 Good Fair
Hasahya-Kaiti-Naboa Rd 7.5 Good Fair
Lusaka-Magongolo-Railway Line Rd 6.6 Good Fair
Tororo Apokor-Kamuli-Petta Rd 9.4 Good Fair
Osia –Kidera Rd 10.1 Good Fair
Iganga Namungalwe –Namukubembe Rd 17.6 Good Fair
CMS-Luyira Rd 6.10 Good Fair
Namutumba-Nabinyonyi Rd 12.5 Good Fair
Nabinyonyi –Nagonde Rd 10.5 Good Fair
Total 235.3
(b) Community Access Roads (CAR)
District Road Name Length(Km) Surface Condition
Drainage Condition
Sembabule Lutunku-Lugusulu Rd 24.5 Good Fair
Kapchorwa Kaplak-Water Source Rd 2.5 Poor Poor
Chebukat-Kaptokwoi Rd 2.6 Poor Poor
Kashabul-Mokotu 5.0 Poor Poor
Ngangata-Kaplelko 7.0 Poor Poor
Molok-Toywo 0.7 Poor Poor
Pallisa Radio Uganada- Nasuleta Rd 6.6 Good Fair
Petete Township Acess Roads 2.1 Good Fair
Bigenzo –Kamenyamugongo Rd 4.4 Good Fair
Iganga Kawete – Nawankonge – Bunyiro road 4.5 Good Fair
Ngobi’s place – Nambale road 5.6 Good Fair
Namungalwe – Kivainuma’s place road 3.9 Good Fair
Kawete – Naguwa – Balumwaki road 4.2 Good Fair
Naluko – Naguwa – Nsinze road 5.6 Good Fair
40VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
Amuru Kinene – Aswa – Lungulu Community access road 19.5 Good Fair
Gulu Labworomor – Karayi – Paibona road 16.6 Good Fair
Kitgum Lai – Agolo – Alaa - Ogoko road 9.3 Poor Poor
Katum HC11 - Lagotonguu road 5.8 Good Fair
Lira Ober PS Jn – Opem PS – Ayamo – Abunga – Obot PS Jn road 19.5 Good Fair
Mityana Sekereni-Nambute swamp (1.8Km) and Nambute swamp-Kiryokya road (26.2km). 28 Good Fair
Mukono Kabanga-Ssungu 4.5 Good Fair
Mpata-Mawoota 6 Good Fair
Lwetega-Katambwa 3 Good Fair
Lugazi-Kulubbi 3.1 Good Fair
Bunnikija-Golomolo 2.0 Good Fair
Kyapa-Nakonge-Katosi 2.5 Good Fair
TOTAL 199
41VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
APPENDIX vi: Over Payments for works
S/N District Contract Name Contractor Overpayments Remarks
1 Mityana/ Mubende
Rehabilitation of 44.2Km of Feeder Roads under the CAIIP-1 in MITYANA and MUBENDE
M/s Kato Investments 15,974,000
Road design gravel width considered against the measurement sheets in the IPCs, All culverts along roads counted during audit; underpayments considered
2 Mukono/ Kayunga
Rehabilitation of 45.4 Km of Feeder Roads under the Community Agricultural Infrastructure Improvement Programme 1 (CAIIP-1) in Mukono and Kayunga
M/s Upland Enterprises Ltd 11,850,660
Road design gravel width considered against the measurement sheets in the IPCs;All culverts counted during audit; Items traded off with 900mm culverts not specified in response hence kept in view;Under payments re-adjusted
3 Iganga/ Namutumba
Rehabilitation of 46.10km of feeder roads under caiip-1 in Iganga and Namutumba districts- CAIIP-1/FRR/Iganga-Namutumba/LOT 9
3,570,000
Under payments considered, design gravel width used; some culverts existed and not shown by consultant;Overpayments adjusted
4 Sembabule/Masaka
Rehabilitation of 54.9km of feeder roads under Community Agricultural Infrastructure Improvement Programmes 1 Project (CAIIP 1) in Sembabule and Masaka Districts
M/s East African Heavy Machinery
28,376,835Under payments considered, Final account reviewed; overpayment adjusted
5 Budaka/ Pallisa
Rehabilitation of 43.8km of feeder roads under Community Agricultural Infrastructure Improvement Programmes 1 Project (CAIIP 1) in Budaka and Pallisa Districts
The Leading Edge Investments
20,874,000Underpayments considered, overpayments due to culverts and road length retained
6 Tororo/ Butaleja
Rehabilitation of 49.6km of feeder roads under Community Agricultural Infrastructure Improvement Programmes 1 Project (CAIIP 1) in Tororo and Butaleja Districts
M/s BMK (U) Ltd 33,569,415
Under payments considered, culverts for all roads re calculated; design gravel width considered; overpayments adjusted
TOTAL 114,214,910
42VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
APPENDIX vii: Overpayments on CARs
SN District/Sub-county Contract Contractor Overpayments Remarks
1 Mityana/Bulera
Rehabilitation of Sekereni-Nambute swamp (1.8Km) and Nambute swamp-Kiryokya road (26.2km).
M/s Real Engineering Contractors
14,863,400
Overpayment on reshaping verified, manual problem. Management should use one item in the manual for future use
2 Mukono/ Ntenjerru
Rehabilitation of 21.1Km of Community Access Roads in Ntenjerrusubcounty, Mukono District
M/s Semeo Enterprises 13,560,000
Field verification was carried on March 23, 2013 and the quantities of gravel recalculated. Verification report is attached;Certified length considered
4 Lira/Barr S/C
Rehabilitation of community access roads in Barr sub-county- CAIIP-2/LIRA/CAR-A/LOT 77
Malcom Investments Ltd
835,000 Underpayments considered and trade-offs made
5Kitgum/ Padibe East
Rehabilitation of community access roads in padibe east sub-county,CAIIP-2/KITGUM/CAR-BATCH A/LOT 92
On Time Construction Co Ltd
2,250,000 Works were still on-going;Overpayments to be kept in view
7
Iganga/ Namungalwe S/C
Rehabilitation of community access roads in namungalwe sub-county; CAIIP-1/IGANGA/CAR-B/LOT 43
Peremi Construction Co. Ltd
4,130,000
Design gravel width considered;Underpayments considered to trade-off;Overpayments adjusted
8Sembabule /Lungusulu
Rehabilitation of ofLutunku-Kisekera-Bisese-Lungusulu road in Lungusulu Sub-County
Pribera Civil & Building Contractors Ltd
39,239,500
Design gravel width considered; Management should consider attaching take-off sheets since measurement sheet is shallow;No instruction for transfer of gravel to swamp crossings seen
9 Pallisa/Petete
Rehabilitation/construction of community access roads in Petete Sub county Pallisa District under Community Agricultural Infrastructure Improvement Programme (Lot 49)
The Leading Edge Investments
15,289,500
Design gravel width considered; Gravel for ramps considered; Management should consider attaching take-off sheets since measurement sheet is shallow
10 Kapchorwa/ Kaptanya
Rehabilitation/construction of community access roads in Kaptanya Sub-county, Kapchorwa District under Community Agricultural Infrastructure Improvement Programme
5,472,100Under payments considered;Works covered up by rains kept in view until completed
12 Bukwo/Kabei
Rehabilitation of 21.9Km of Community Access Roads in Kabei Sub-county, BukwoDistrictunder Community Agricultural Infrastructure Improvement Programme
Ms Multiline Construction Company Ltd
3,160,100 Under payments considered
13 Buduuda/ Bushika
Rehabilitation of 21.0Km of Community Access Roads in Bushika Sub-county,Buduuda District under Community Agricultural Infrastructure Improvement Programme
M/s Toni Enterprises 47,256,660
Bridges constructed and seen along the road; Works were still on-going on other road sections; reduction of ETL for one section and presence of fill works not considered pending verification
TOTAL 146,056,260
43VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
APPENDIX viii: Overpayments on Markets
Sn District/ Sub-county Contract Name Contractor Amount Remarks
1 Mityana/Bulera Construction of Market at Bulera
Busenvi Enterprises (U) Ltd
2,000,000
From picture submitted, there is a structure between the two new structures increasing the area of levelling;Galvanised steel pipes used;Authority to change reviewed
3 Mityana/Maanyi Construction of Market at Maanyi
Nyamwire Enterprises 1,500,000
Galvanised steel pipes used;Authority to change reviewed;Splash apron fully constructed as per photo; overpayment re-adjusted
4 Mukono/Ntenjerru
Construction of Katosi Market
GASCO Constryction Ltd 3,000,000
Galvanised steel pipes used;Authority to change reviewed;Issue of keeping tanks to be kept in view subject to physical verification after installation
5 Mukono/Ntunda Construction of Ntunda Market
Trust Industries Ltd 5,015,000
Galvanised steel pipes used;Authority to change reviewed;Overpayment re-adjusted
6 Sembabule/Lugusulu
Construction of Lugusulu Market
M/S West Minister Civil Engineering (U) Ltd
8,173,240
Unexecuted works on effluent treatment, overestimation of steel bars for reinforcement, use of un authorised sheeting material, area of concrete on the floor slab. To be kept in view.
7 Sembabule/Lwebitakuli
Construction of Lwebitakuli Market
M/S Ishaka Muhereza Workshop and Building Construction (U) Ltd
8,839,782
Galvanised pipes found at site, and reinforcement re- adjusted.Communication for change of pipes verified by auditors
8 Masaka/Lwengo Construction of Kyawagonya Market
M/s Ron Engineering Company Ltd
9,610,381
Steel shutters seen on site and authorisation for change received for review; Overpayments re-adjusted
9 Kapchorwa/Kaptanya
Construction of Mutyoru
M/s Bakasuku Agencies Ltd 299,400
Galvanised pipes found at site, and reinforcement re- adjusted.Communication for change of pipes verified by auditors .Shutters were not provided on the stalls
11 Pallisa/Petete Construction of Kapunyasi
M/s Greenland Building Contractors
1,274,289
Galvanised pipes found at site; 20 Metallic shutters installed and garbage bunker constructed
12 Iganga/Namungalwe
Construction of Kawete Cattle Market
M/s Afro General Builders & Carpentry
7,644,000 To be kept in view pending physical verification
TOTAL 47,356,092
44VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
APPENDIX ix: Payments for Unexecuted Works
Sn District Contract Name Unexecuted Works Paid Remarks
Feeder Roads
1 Sembabule/ Masaka
Rehabilitation of 54.9km of feeder roads under Community Agricultural Infrastructure Improvement Programmes 1 Project (CAIIP 1) in Sembabule and Masaka Districts
27,000,000Supply and Installation of 900mm diameter Culverts
2 Pallisa/ Budaka
Rehabilitation of 43.8km of feeder roads under Community Agricultural Infrastructure Improvement Programmes 1 Project (CAIIP 1) in Budaka and Pallisa Districts
9,200,000
Supply and Installation of 900mm diameter Culverts and Stone pitching
3 Tororo/ Butaleja
Rehabilitation of 49.6km of feeder roads under Community Agricultural Infrastructure Improvement Programmes 1 Project (CAIIP 1) in Tororo and Butaleja Districts
14,368,015
Supply and Installation of 900mm diameter Culverts and other erosion protection works
50,568,015
Community Access Roads
1. Bukwo/Kabei SubcountyRehabilitation of 21.9Km of community access roads in Kabei Subcounty.
12,903,000 Construction culvert end structure
Grand Total 63,471,015
APPENDIX x: Delays in market completion
S/N District Sub-county Market Name Start Date Expected
completionActual Completion
Contract Amount
Delays(months)
Un charged liquidated damages
1. Pallisa Petete Kapunyasi 02/06/2010 02/12/2010 18/08/2011 107,283,776 8.5 10,728,837
2. Iganga
Nakigo Nabitovu 17/05/2010 17/11/2010 01/07/2011 97,753,989 7.2 9,775,399
Namungalwe Kaweta 14/05/2010 14/11/2010 01/07/2011 165,091,924 7.1 16,509,192
3. Sembabule
Lugusuulu Lugusuulu 08/06/2010 08/12/2010 Abandoned 105,478,275 NA 10,547,828
Lwebitakuli Lwebitakuli 08/06/2010 08/12/2010 28/04/2011 120,632,481 4.7 12,063,248
4. Masaka
Bukulula Bukulula 15/06/2010 15/12/2010 20/02/2010 89,245,328 2.2 5,354,719
Kyawagonya Lwengo 16/06/2010 16/12/2010 16/12/2010 108,214,840 0 00
5. Mityana
Maanyi Maanyi 29/10/2010 30/04/2011 3/5/2011 115,248,184 0 00
Bulera Bulera 01/07/2009 31/12/2009 14/11/2010 131,733,341 10.6 13,173,334
6. Kapchorwa Mutyoru Mutyoru 14/06/2010 14/12/2010 29/10/2011 88,459,219 10.5 8,845,922
7. MukonoNtenjeru Katosi 17/05/2010 17/11/2010 01/08/2011 210,909,924 7.5 21,090,992
Ntunda Ntunda 11/011/2010 11/04/2011 03/04/2012 98,983,747 12 9,898,374
Total 1,318,402,547 Avg=8 117,987,845=
45VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
APPENDIX xi: Delays in Feeder road construction
SN District Contract Name Start DateExpected Completion date
Actual Completion Date
Delay (Days)
Liquidated damages
1 Mityana/ Mubende
Rehabilitation of 44.2Km of Feeder Roads under the CAIIP-1 in MITYANA and MUBENDE.
12/10/2010 12/03/2011 13/7/2011 120 23,715,671
2 Sembabule/ Masaka
Rehabilitation of 54.9km of feeder roads under CAIIP-1 in Sembabule and Masaka Districts
13/10/2010 14/4/2011 20/7/2011 97 25,406,065
3 Budaka/ Pallisa
Rehabilitation of 43.8km of feeder roads under CAIIP-1 in Budaka and Pallisa Districts
12/10/2010 11/4/2011 28/11/2011 231 23,365,027
Tororo/Butaleja
Rehabilitation of 49.6km of feeder roads under Community Agricultural Infrastructure Improvement Programmes 1 Project (CAIIP 1) in Tororo and Butaleja Districts
11/10/2010 14/04/2011 11/10/2011 180 20,061,289
TOTAL 92,548,052
APPENDIX xii: Delays in construction of CARs
Sn District / Sub-county Contract name Start date
Expected completion date
Actual completion date
Delay in days
Amount for liquidated damages (Shs)
1 Gulu / Palaro S/C
Rehabilitation of community access roads in palaro sub-county (CAIIP-2/GULU/CAR-A/LOT 85)
February 8, 2011
August 7, 2011
October 20, 2011 73 21,619,867
2 Lira / Barr S/CRehabilitation of CARs in Barr sub-county- CAIIP-2/LIRA/CAR-A/LOT 77
April 1, 2011
September 30, 2011
January 11, 2012 103 17,728,300
3 Kitgum / PadibeEast
Rehabilitation of community access roads in padibe east sub-county,CAIIP-2/KITGUM/CAR-BATCH A/LOT 92
January 18, 2011
October 30, 2012 On – going 92 13,442,190
4Iganga / Namungalwe S/C
Rehabilitation of CARs in namungalwe sub-county; CAIIP-1/IGANGA/CAR-B/LOT 43
June 2010 December 2010
February 2011 60 12,071,100
5 Pallisa/ Petete
Rehabilitation/construction of CAR in Petete Sub county Pallisa District under Community Agricultural Infrastructure Improvement Programme (Lot 49)
11/6/2010 7/12/2010 21/12/2010 14 2,069,924
6 Kapchorwa/ Kaptany
Rehabilitation/construction of CAR in Kaptanya Sub-county, Kapchorwa District under CAIIP.
6/7/2010 3/1/2011 abandoned 200 36,499,323
Total 103,430,704
46VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
APPENDIX xiii: Delays in constructions of APF shelters
District Contractor Contract Sum (Shs) Start Date
Expected Completion Date
Actual Completion date
Delays(days)
Uncharged liquidated damages
KapchorwaM/s Topcare Consultant & Engineering Works Ltd
189,456,645 4/10/2010 4/01/2011 Sites abandoned 726 18,945,665
Iganga M/s Kiidha General Services Ltd 277,895,100 4/10/2010 4/01/2011 22/08/2011 228 27,789,510
MityanaM/s Mweka Construction & Engineering Ltd
131,206,425 4/10/2010 4/01/2011 5/10/2011 271 13,120,642
Masaka M/s SMM General Services Ltd 74,337,318 10/12/2010 10/3/2011 01/4/2012 386 7,433,732
Sembabule M/s EMCO Works Ltd 183,812,550 4/10/2010 4/01/2011 Works on-going 726 18,381,255
Pallisa M/s Pall Technical Services Ltd 175,043,295 10/12/2010 10/3/2011 20/10/2011 220 17,504,329
Total 103,175,133
APPENDIX xiv: Status of APFs
S/N District Sub-county APF No. of Units Status of Installation Comments
1. Pallisa Petete Rice Huller 1
Completed and installedThe generator supplied was not matching with the requirements for the machines/ huller.
Not yet commissioned.
2. Iganga
Nakigo Rice huller 1 Completed and installed with no power source. Not yet commissioned.
Cofee huller 1 Completed and installed with no
power supply Not yet commissioned.
Namungalwe Maize mill 1 Installations partially done Not yet commissioned.
Coffee huller 1 Works completed and installations
done Not yet commissioned.
Rice huller 1 Works completed and installation done Not yet commissioned
3. Sembabule
Lugusuulu Milk cooler 2 Works on agro-shelters and installation on-going Not yet commissioned
Lwebitakuli
Milk cooler 1 Construction works and installations complete. Not yet commissioned.
Coffee huller 1 Installations not yet done. Equipment delivered to the
district headquarters.
4. Masaka
Bukulula Maize mill 1 Complete and installed Transformer was vandalized. Commissioning not yet done.
Kyawagonya Maize mill 1 Complete and installed Not yet commissioned.
5. Mityana
Maanyi Coffee huller 1 Complete and installed, generator
shelter not yet constructed. Not yet commissioned
Bulera Maize mill 1 Installation partially done Not yet commissioned
6. Kapchorwa Kaptanya Milk cooler 1 Contract for APF shelters was terminated and retendering done.
Shelters yet to be constructed and equipment not yet delivered.
7. Mukono Ntunda Maize mill 1 Supply and installation not yet done. Not yet commissioned.
47VALUE FOR MONEY AUDIT REPORT ON THE PERFORMANCE OF THE COMMUNITY AGRICULTURAL
INFRASTRUCTURE IMPROVEMENT PROGRAMME (CAIIP I &II) | A REPORT BY THE AUDITOR GENERAL
P.O. Box 7083, Kampala. Tel. +256 414 344 340 Fax. +256 414 345 674
E-mail: [email protected]
OFFICE OF THE AUDITOR GENERAL