vacuum ejector system

Upload: funshare

Post on 14-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Vacuum Ejector System

    1/11

    CFFP VACUUM EJECTOR SYSTEM

    14/07/06

  • 7/30/2019 Vacuum Ejector System

    2/11

    INTRODUCTION

    CFFP is manufacturing alloy steel castings and

    forgings which include turbine & generatorrotors and casings for steam turbines. CFFP isalso planning to produce 250MW & 500MW IProtors. These products require clean steel.

    The purpose of VOD/VAD/ Vacuum degassing isto ensure hydrogen below 1ppm, oxygen below20ppm and nitrogen below 50ppm for cleansteel production.

    Gas levels and oxide inclusions are highlydependent on vacuum in the refining unit.

  • 7/30/2019 Vacuum Ejector System

    3/11

    Results Achieved After CFD

    Modification

    Vacuum achieved in VAD During vacuum degassing of VAD melt,the vacuum achieved was 3 to 4 torr for

    35 as well as 70tonne melt against therequired vacuum of less than 1 torr.

    Vacuum achieved during vacuum casting:

    During vacuum casting the vacuumachieved was 1.2 to 1.8 torr against arequirement of less than 1 torr

  • 7/30/2019 Vacuum Ejector System

    4/11

    Studies of Corporate R&D at CFFP

    The facilities at CFFP were shown and VAD/VODprocess was explained to Corp. R&D team.

    Witnessed the pouring of VAD heat no. 70297 of 56tonne (Grade Hy 19375, 1Cr MoV turbine rotor)

    under the following conditions.Heating stage: 430mbar, Duration: 40min.Deep degassing: 1.8 torr

    Duration 20 min.Rinsing: 420mbar, Duration: 50 min.One ingot was poured under vacuum (1300 size in pitside) another one (1200 size) bottom poured.Pouring rate :3 ton/min under vacuum for 9 minutes.

    Vacuum: 0.5 torr

  • 7/30/2019 Vacuum Ejector System

    5/11

    Studies of Corporate R&D at CFFP(contd.)

    The vacuum achieved in this heat during deepdegassing is 1.8 torr versus 3 to 4 torr in earlierheats.

    The deterioration in the ejectors earlier was due toclogging, dust loading and leakages.

    Leakages were plugged and cleaning of the nozzles,ejectors were carried out prior to the visit. Thishas improved the performance of the system.

    It has been examined that during vacuum pouringthe time to achieve the desired vacuum shall be 1.5minutes. Other wise it increases the croppercentage due to entrained defects.

  • 7/30/2019 Vacuum Ejector System

    6/11

    Dissolved Gas Analysis of VAD/VOD Heats

    Heat No. Process Material [O]

    ppm

    [N]

    ppm

    [H]

    ppm20614

    26/06/06

    VAD

    36.1tonne

    Generator

    rotor

    57 97 3.5

    7029601/07/06

    VAD51tonne

    Generatorrotor (Ni:3.0,Cr:1.5 Mo:0.4)

    104 81 3.4

    20629

    11/07/06

    VOD

    29.5tonne

    AA 19542

    12%Cr, 4%Ni

    98 170 4.5

    70297

    13/07/06

    VAD

    56tonne

    1CrMoV rotor 41 56 1.8

    The results show that the gas levels are higher than required for clean steel

  • 7/30/2019 Vacuum Ejector System

    7/11

    Vacuum Oxygen Decarburisation at 120 torr for 50 minute duration

    Melt

    Size CO gas Oxygen Ar TotaL Rate/hr

    Dust

    Load,

    kg/hr

    Leakage

    Kg/hr

    Total

    kg/hr

    Add 20%

    Excess

    Capacity

    50 tons 292 690 7 989 1186.8 300 20 1506.8 1808.16

    75 438 1035 10.5 1483.5 1780.2 300 20 2100.2 2520.24

    90 525.6 1242 12.6 1780.2 2136.24 300 20 2456.24 2947.488

    The above values are in Kgs during the process

    Vacuum Decarburisation at 1 torr for 20 minute duraiton

    Melt

    Size CO Gas Ar Gas Total Rate /hr

    Dust

    load Leakage Total 20% Excess

    50 58 15 73 219 25 10 254 304.8

    75 87 22.5 109.5 328.5 25 10 363.5 436.2

    90 104.4 27 131.4 394.2 25 10 429.2 515.04

    GAS CALCULATIONS (BASED ON HITACHI GUIDELINES)

  • 7/30/2019 Vacuum Ejector System

    8/11

    The present vacuum system capacity after

    CFD modifications is 200kg/hr at 1 torr. It is considered that if vacuum requirement

    of VOD/VD is met, it will meet VAD/VDrequirement also. Since we do not have datafor VAD/VD and only VOD/VD available, thecalculation has been carried out for VOD/VDonly.

    The existing vacuum capacity of 200kg/hr isnot sufficient for 50tonne VOD/VD processas against the requirement of 304.8 kg/hr at1 torr as derived from the calculations.

    Studies of Corporate R&D at CFFP(contd.)

  • 7/30/2019 Vacuum Ejector System

    9/11

    The suction capacity used by some wellknown specialty steel makers are as

    follows: Cruseot Loire: For 51 to 95 tonne VADunit, required suction capacity is 235 Kg/hrof dry air @ 200C at 0.5 torr.

    Slovenske Zelezarne Acronis 90T VD/VODunit: the ejector system capacity is250Kg/hr of dry air at 0.5 torr.

    Hitachi suggested for 50Tons VD/VOD unitthe required ejector system capacity as250kg/hr at 0.5 torr.

    Midhanis proposed 25tonne VAD system,:suction capacity of 140Kg/hr at 0.5 torr.

  • 7/30/2019 Vacuum Ejector System

    10/11

    RECOMMENDATIONS

    From the calculation of gas content for theVD/VOD process, the present ejectorcapacity is not adequate for 50tonne andabove. This is also reflected in the dissolvedgases such as hydrogen, nitrogen and oxygencontent in the samples for clean steelproduction.

    The gas calculations were carried out at 1torr. However to remove the dissolved gases

    the vacuum to be achieved shall be 0.5 torr.The recommended capacity of ejector is250kg/hr at 0.5 torr for 50-90tonne meltbased on available VAD/VOD units with userslike Cruseot Loire, Slovenske ZelezarneAcroni and Hitachi.

  • 7/30/2019 Vacuum Ejector System

    11/11

    RECOMMENDATIONS (CONTD.)

    To meet the above requirement of 250kg/hr at 0.5

    torr, following may be considered:a) It is possible to add another similar ejectorsystem to make up the present capacity to 250Kg/hr at 0.5 torr. It will require additionalequipment like boiler, condenser, etc. Howeveroperational constraints may be examined.

    b) It has been observed that users all over theworld prefer a dedicated vacuum system for theirVAD/VOD units.

    c) Since six stations (2VADs, 1VOD, 3 Vacuumpouring units) are being catered by a combinedejector system it leads to operational constraintslike leakages due to more number of valves andlosses due to extra pipe lines .