vac – ctrl sys 8 feb 2012. vac : msrc equipment central area links, to be discussed ion tmp aux
TRANSCRIPT
VAC – CTRL SYS
8 Feb 2012
VAC : MSRC equipment
Number of new control stations
Name of vacuum equipment
Description
4 Cryotraps Each station includes the relevant cryotrap vacuum equipment (pumps, gauges, valves...) & cryogenics devices (essentially temperature and level signals readout + valve status)
0, TBC Links pumps New pumps on enlarged links, their sensors and the valves could be integrated in corresponding towers existing racks (NI, WI, PR, SR), in pace of removed pumps (TSP groups).
0, TBC LN2 tanks Readout of level and pressure inside the LN2 storage tanks, and related alarms. Normally a few signals, perhaps it could be integrated in the cryotraps control stations.
1, TBC Remote scroll It will control the operation of the remote scroll pumps. It should be simple, maybe easier to have a separated rack. Needs anyway interlocks between the different towers.
5, TBD Minitowers A rack for each minitower seems the easier solution. All the same. A ‘remote’ driving console to be discussed
2 300m tube stations To control a TSP pump group added at 300m along the tubes; should be very simple.
Tab.1: Summary of new vacuum systems and relevant control stations for AdV
Central area links, to be discussed
Ion
Ion
Ion
Tmp
Tmp
aux
Notes on central area vacuum changesIB tower: + a turbo group at beginning of MC pipe (move the valve? no)
DT cryotrap: updated cryotrap (new aperture size 200-250mm). Normally we shall integrate its new rack in the general control system.
IB Brewster: Brewster or cryotrap . to be discussed
Towers upper parts : + the possibility of install an Ion pump (For the control, could use the P33 drive)
Towers lower parts: 2 turbo pumps and 3 Ion groups, (plus a service pump for first evacuation and service, normally off, completed with gauge and valves.) These system could be grouped in a single rack (placed where?) or splitted in the relevant tower CC racks (in place of TSP drivers, tbc). The second choice seems better for the operator, give him a complete view of all the systems when in local mode.
Minitower: Separated by a glass window. Pumping system completed to get HV. The CC rack shall not be placed in the clean room, a solution should be found to allow the vacuum team operate the system from the clean room.Double orings .
Minitower pumps
PENDING ACTIONS
Ego, Genova, Nikhef
Prepare a draft layout of the phase separator layout (Nikhef) and cryogenic lines (Genova) . Ego will circulate a dxf of the central building relevant place with walls
Dec 2011
Ego will prepare the baking supplies for the 1st cryotrap July 2012 Ego deliver vacuum pumps for testing the first cryotrap (list attached) Feb-Mar
2012 Ego deliver the simplified control system for vacuum pumps of the first
cryotrap Feb-Mar
2012 Nikhef Purchase phase separator and related accessories for refill
LAL Preferred PLC for the main control station is the Bekhoff one
Nikhef Will provide the type of proposed Siemens PLC including its programming and external communications protocol
Nikhef release the document related to cryotrap PED classification A.Pasqualetti Circulate draft doc of vacuum items interlocks updated for the MSRC
choice https://workarea.ego-gw.it/ego2/virgo/advanced-virgo/vac/control-system/meeting-03may2011/Vac_CTRLSYS_01may.docx/
Nov 2011
Lal + Ego Lal: indicate the more critical board with respect to cooling req.ts, Ego: will check with thermocamera the effect of fans reduction
Dec 2011
Irene F. + Ego
Test of ‘hanged’ rack vs seismic effects. Complete the test of ‘silent’ fans
Feb-Mar 2012
About Crytrap, fix a date for meeting about:
Purchase of the 4 valves
Discuss the designed charriot for the Input traps installation
DN63 ports on 1300mm flanges
Metal seals for the prototype test
End cryotrap feet mechanical frequency result