v 160741001 p
TRANSCRIPT
7/31/2019 V 160741001 p
http://slidepdf.com/reader/full/v-160741001-p 1/14
D E S C R I P T I O N
R E V
N O .
J O / E W O
D A T E
O P R N S
E N G
G
P M T
C E R T
DATE:
DATE:
DATE:
DATE:
DATE:
D A T E :
B Y :
C O N T R O L N U M B E R
PROJECT
ENGINEER
CONSTRUCTION
AGENCY
DISCIPLINE
ENGINEER
V E R I F I C A T I O N
E D S D
R E V I S I O
N C
E R T I F I C A T E
T H I S I N D I C A T E S T H A T R E V
. N O
.__________
O F T H I S D R A W I N G I S C O V E R E D
, F O R A L L
A P P R O V A L / C E R
T I F I C A T I O N R E Q U I R E M E N T S
,
B Y D R A W I N G C
O M P L E T I O N C E R T I F I C A T E
( D C C ) N O
.____
_________________
OPERATIONS
CERTIFIED
R E V I S I O N C
E R T I F I C A T I O N
1
OF14
DOCK63
A E-
JO / EWO: 00A
BI-25-00013-0002
2 5 - 0 0 0 1 3 4 - 0 0 0 2 - 0 0 1
SAU
KAG
LT
MS
S A U
K A G
L T
M S
B I - 2 5 -
0 0 0 1 3 -
0 0 0 2
STRUCTURAL MOVEMENTS REPORTKING ABDULLAH PETROLEUM STUDIES AND
RESEARCH CENTER – RESEARCH & OFFICE COMPLEX
RIYADH
T H I S D R A W I N G A N D T H E I N F O R M A T I O N C O N T A I N E D H E R E I N A R E T H E S O L E P R O P E R T Y O F S A U D I A R A M C O .
N O R E P R O D U C T I O N I N F U L L O R I N P A R T S H A L L B E O B T A I N E D F R O M T H I S D O C U M E N T W I T H O U T T H E W R I T T E N C O N S E N T O F I T S O W N E R .
EDSD/2616-0399.doc
Saudi Aramco 2616-ENG (03/99)
V 160741
SAUDI ARABIA
REV.NO. SHT.NO. DRAWING NO. INDEX PLANT NO. DWG.TYPE
SAUDI ARABIAN OIL COMPANY
STRUCTURAL MOVEMENTS REPORT
7/31/2019 V 160741001 p
http://slidepdf.com/reader/full/v-160741001-p 2/14
D E S C R I P T I O N
R E V N O .
J O / E W O
D A T E
O P R N S
E N G
G
P M T
C E R T
DATE:
DATE:
DATE:
DATE:
DATE:
D A T E :
B Y :
C O N T R O L N U M B E R
PROJECTENGINEER
CONSTRUCTION AGENCY
DISCIPLINE
ENGINEER
V E R I F I C A T I O N
E D S D
R E V I S I O
N C
E R T I F I C A T E
T H I S I N D I C A T E S T H A T R E V . N O .__________
O F T H I S D R A W I N G I S C O V E R E D , F O R A L L
A P P R O V A L / C E R
T I F I C A T I O N R E Q U I R E M E N T S ,
B Y D R A W I N G C
O M P L E T I O N C E R T I F I C A T E
( D C C ) N O .____
_________________
OPERATIONS
CERTIFIED
R E V I S I O N C
E R T I F I C A T I O N
2
OF14
DOCK63
A E-
JO / EWO: 00A
BI-25-00013-0002
2 5 - 0
0 0 1 3 4 - 0 0 0 2 - 0 0 1
SAU
KAG
LT
MS
S A U
K A G
L T
M S
B I - 2 5 -
0 0 0 1 3 -
0 0 0 2
STRUCTURAL MOVEMENTS REPORTKING ABDULLAH PETROLEUM STUDIES AND
RESEARCH CENTER – RESEARCH & OFFICE COMPLEX
RIYADH
T H I S D R A W I N G A N D T H E I N F O R M A T I O N C O N T A I N E D H E R E I N A R E T H E S O L E P R O P E R T Y O F S A U D I A R A M C O .
N O R E P R O D U C T I O N I N F U L L O R I N P A R T S H A L L B E O B T A I N E D F R O M T H I S D O C U M E N T W I T H O U T T H E W R I T T E N C O N S E N T O F I T S O W N E R .
EDSD/2616-0399.doc
Saudi Aramco 2616-ENG (03/99)
V 160741
SAUDI ARABIA
REV.NO. SHT.NO. DRAWING NO. INDEX PLANT NO. DWG.TYPE
SAUDI ARABIAN OIL COMPANY
CONTENTS PAGE
Introduction ...................................................................................................................................................................... 3 Design assumptions ...................................................................................................................................................... 3 Using this report ........................................................................................................................................................... 4
Research Centre ................................................................................................................................................................ 4 Superstructure Lateral Movements ............................................................................................................................... 4 Floor Slabs at Courtyard Edge ...................................................................................................................................... 4 Floor Slabs at Building Perimeter ................................................................................................................................. 5 Roof Steelwork ............................................................................................................................................................. 5 Foundation Movements ................................................................................................................................................ 5
Library .............................................................................................................................................................................. 6 Superstructure Lateral Movements ............................................................................................................................... 6 Floor Slabs at Courtyard/Atrium Edge ......................................................................................................................... 6 Slab to External Terrace ............................................................................................................................................... 6 Floor Slabs at Building Perimeter ................................................................................................................................. 7 Roof Steelwork ............................................................................................................................................................. 7 Foundation Movements ................................................................................................................................................ 7
Conference Centre ............................................................................................................................................................ 8 Superstructure Lateral Movements ............................................................................................................................... 8 Floor Slabs at Courtyard Edge ...................................................................................................................................... 8 Floor Slabs at Building Perimeter ................................................................................................................................. 8 Roof Steelwork ............................................................................................................................................................. 9 Foundation Movements ................................................................................................................................................ 9
Musalla + IT Center ........................................................................................................................................................ 10 Superstructure Lateral Movements ............................................................................................................................. 10 Roof Steelwork ........................................................................................................................................................... 10 External Courtyard Frame Lateral Movements .......................................................................................................... 11 External Courtyard Roof Steelwork............................................................................................................................ 11 Foundation Movements .............................................................................................................................................. 11
Visitors Center, Gate Houses and Other Ancillary Buildings ............ ........... ......... ............ ......... ........... ......... ........... ..... 12 Superstructure Lateral Movements ............................................................................................................................. 12
Roof ............................................................................................................................................................................ 12
Car Park and Entrance Canopies .................................................................................................................................... 13 Superstructure Lateral Movements ............................................................................................................................. 13 Roof ............................................................................................................................................................................ 13
Movement Joints in Concrete Slabs................................................................................................................................ 14 Lateral Movements ..................................................................................................................................................... 14
7/31/2019 V 160741001 p
http://slidepdf.com/reader/full/v-160741001-p 3/14
D E S C R I P T I O N
R E V
N O .
J O / E W O
D A T E
O P R N S
E N G
G
P M T
C E R T
DATE:
DATE:
DATE:
DATE:
DATE:
D A T E :
B Y :
C O N T R O L N U M B E R
PROJECT
ENGINEER
CONSTRUCTION
AGENCY
DISCIPLINE
ENGINEER
V E R I F I C A T I O N
E D S D
R E V I S I O
N C
E R T I F I C A T E
T H I S I N D I C A T E S T H A T R E V
. N O
.__________
O F T H I S D R A W I N G I S C O V E R E D
, F O R A L L
A P P R O V A L / C E R
T I F I C A T I O N R E Q U I R E M E N T S
,
B Y D R A W I N G C
O M P L E T I O N C E R T I F I C A T E
( D C C ) N O
.____
_________________
OPERATIONS
CERTIFIED
R E V I S I O N C
E R T I F I C A T I O N
3
OF14
DOCK63
A E-
JO / EWO: 00A
BI-25-00013-0002
2 5 - 0
0 0 1 3 4 - 0 0 0 2 - 0 0 1
SAU
KAG
LT
MS
S A U
K A G
L T
M S
B I - 2 5 -
0 0 0 1 3 -
0 0 0 2
STRUCTURAL MOVEMENTS REPORTKING ABDULLAH PETROLEUM STUDIES AND
RESEARCH CENTER – RESEARCH & OFFICE COMPLEX
RIYADH
T H I S D R A W I N G A N D T H E I N F O R M A T I O N C O N T A I N E D H E R E I N A R E T H E S O L E P R O P E R T Y O F S A U D I A R A M C O .
N O R E P R O D U C T I O N I N F U L L O R I N P A R T S H A L L B E O B T A I N E D F R O M T H I S D O C U M E N T W I T H O U T T H E W R I T T E N C O N S E N T O F I T S O W N E R .
EDSD/2616-0399.doc
Saudi Aramco 2616-ENG (03/99)
V 160741
SAUDI ARABIA
REV.NO. SHT.NO. DRAWING NO. INDEX PLANT NO. DWG.TYPE
SAUDI ARABIAN OIL COMPANY
Introduction
The following is a summary of movement limits that have been applied in the design of the primary
structure. These should be considered when connecting any secondary elements to the primary
structure.
Design assumptions
The movements are based on the structural systems as defined in the Structural Report (VE-161172-
001).
The loading allowance for the roof system is:
Cladding System
SDLkN/m
2
GRC Cladding Panel 0.5
Substructure framing 0.35
Insulation +Water proofing 0.4
Metal Decking 0.25
Acoustic Insulation 0.9
Ceiling and Services 0.5
Total 2.9
The external wall cladding loading allowance is:
Cladding System
SDL kN/m2
GRC Cladding Panel 0.5
Substructure framing 0.35
Insulation +Water proofing 0.4
Metal Decking 0.25
Acoustic Insulation 0.9
Total 2.4
Overall building sway limits are based on Saudi Aramco building code SAES-M-100 and is defined as
follows:
Building Type Max. Lateral Drift
Buildings with metal panels, wall cladding and bare frames Height/100
Buildings with partition walls and/or sensitive Height/375
architectural elements attached to or in contact with the building frame
7/31/2019 V 160741001 p
http://slidepdf.com/reader/full/v-160741001-p 4/14
D E S C R I P T I O N
R E V
N O .
J O / E W O
D A T E
O P R N S
E N G
G
P M T
C E R T
DATE:
DATE:
DATE:
DATE:
DATE:
D A T E :
B Y :
C O N T R O L N U M B E R
PROJECT
ENGINEER
CONSTRUCTION
AGENCY
DISCIPLINE
ENGINEER
V E R I F I C A T I O N
E D S D
R E V I S I O
N C
E R T I F I C A T E
T H I S I N D I C A T E S T H A T R E V
. N O
.__________
O F T H I S D R A W I N G I S C O V E R E D
, F O R A L L
A P P R O V A L / C E R
T I F I C A T I O N R E Q U I R E M E N T S
,
B Y D R A W I N G C
O M P L E T I O N C E R T I F I C A T E
( D C C ) N O
.____
_________________
OPERATIONS
CERTIFIED
R E V I S I O N C
E R T I F I C A T I O N
4
OF14
DOCK63
A E-
JO / EWO: 00A
BI-25-00013-0002
2 5 - 0
0 0 1 3 4 - 0 0 0 2 - 0 0 1
SAU
KAG
LT
MS
S A U
K A G
L T
M S
B I - 2 5 -
0 0 0 1 3 -
0 0 0 2
STRUCTURAL MOVEMENTS REPORTKING ABDULLAH PETROLEUM STUDIES AND
RESEARCH CENTER – RESEARCH & OFFICE COMPLEX
RIYADH
T H I S D R A W I N G A N D T H E I N F O R M A T I O N C O N T A I N E D H E R E I N A R E T H E S O L E P R O P E R T Y O F S A U D I A R A M C O .
N O R E P R O D U C T I O N I N F U L L O R I N P A R T S H A L L B E O B T A I N E D F R O M T H I S D O C U M E N T W I T H O U T T H E W R I T T E N C O N S E N T O F I T S O W N E R .
EDSD/2616-0399.doc
Saudi Aramco 2616-ENG (03/99)
V 160741
SAUDI ARABIA
REV.NO. SHT.NO. DRAWING NO. INDEX PLANT NO. DWG.TYPE
SAUDI ARABIAN OIL COMPANY
Most buildings are limited to H/375 with the exception of the Musalla Courtyard and IT Center Courtyard
that are limited to H/100. The courtyards are long span cantilever structures with open sides so there is
no interface with a walling element that would experience the displacement.
Using this reportFor the allowances identified in the body of the report:
• Movements are in both directions unless noted otherwise and can be up to the figures identified.
• -ve is downwards only
• Horizontal movements are always in any direction
• Roof deflections are based on loads for GRC type surface roof finish.
Research Centre
Superstructure Lateral Movements
1.
Movement under wind, up to full height above ground.
Overall height = HHorizontal
+/-
H/375
2.Inter-storey drift. Storey height = h Horizontal
+/-
h/375
Floor Slabs at Courtyard Edge
3. Positional tolerance of slab edgeVertical and
Horizontal
+/-
15mm
4.Slab edge deflection due to super dead load and live
load (typical 8m span with 2m cantilever)
Vertical
Short Term/
Long Term
-15mm/
-30mm
5.Slab edge deflection due to super dead load and live
load for 8m span without cantilever.
Vertical
Short Term
/Long Term
-10mm/
-20mm
6. Relative deflection between adjacent points on a slabdue to super dead load and live load
After installation of cladding
L / 480
7.Ground floor deflection Vertical
After installation of
cladding
- 30mm
7/31/2019 V 160741001 p
http://slidepdf.com/reader/full/v-160741001-p 5/14
D E S C R I P T I O N
R E V N O .
J O / E W O
D A T E
O P R N S
E N G
G
P M T
C E R T
DATE:
DATE:
DATE:
DATE:
DATE:
D A T E :
B Y :
C O N T R O L N U M B E R
PROJECTENGINEER
CONSTRUCTION AGENCY
DISCIPLINE
ENGINEER
V E R I F I C A T I O N
E D S D
R E V I S I O
N C
E R T I F I C A T E
T H I S I N D I C A T E S T H A T R E V . N O .__________
O F T H I S D R A W I N G I S C O V E R E D , F O R A L L
A P P R O V A L / C E R
T I F I C A T I O N R E Q U I R E M E N T S ,
B Y D R A W I N G C
O M P L E T I O N C E R T I F I C A T E
( D C C ) N O .____
_________________
OPERATIONS
CERTIFIED
R E V I S I O N C
E R T I F I C A T I O N
5
OF14
DOCK63
A E-
JO / EWO: 00A
BI-25-00013-0002
2 5 - 0
0 0 1 3 4 - 0 0 0 2 - 0 0 1
SAU
KAG
LT
MS
S A U
K A G
L T
M S
B I - 2 5 -
0 0 0 1 3 -
0 0 0 2
STRUCTURAL MOVEMENTS REPORTKING ABDULLAH PETROLEUM STUDIES AND
RESEARCH CENTER – RESEARCH & OFFICE COMPLEX
RIYADH
T H I S D R A W I N G A N D T H E I N F O R M A T I O N C O N T A I N E D H E R E I N A R E T H E S O L E P R O P E R T Y O F S A U D I A R A M C O .
N O R E P R O D U C T I O N I N F U L L O R I N P A R T S H A L L B E O B T A I N E D F R O M T H I S D O C U M E N T W I T H O U T T H E W R I T T E N C O N S E N T O F I T S O W N E R .
EDSD/2616-0399.doc
Saudi Aramco 2616-ENG (03/99)
V 160741
SAUDI ARABIA
REV.NO. SHT.NO. DRAWING NO. INDEX PLANT NO. DWG.TYPE
SAUDI ARABIAN OIL COMPANY
Floor Slabs at Building Perimeter
8. Positional tolerance of slab edgeVertical and
Horizontal
+/-
15mm
9.Slab edge deflection due to super dead load and live
load (typical 8m span with 2m cantilever)
Vertical
Short Term
/Long Term
-15mm/
-30mm
10.Slab edge deflection due to super dead load and live
load for 8m span without cantilever.
Vertical
Short Term
/Long Term
-10mm/
-20mm
11.Relative deflection between adjacent points on a slab
due to super dead load and live load
After installation of
cladding
L / 480
12. Ground floor deflection Vertical
After installation of
cladding
- 30mm
Roof Steelwork
13.
Construction tolerance on theoretical position (including
self weight deflection)
Vertical and
Horizontal
+30mm/
-80mm
14.
Construction tolerance on relative dimension between
adjacent locations in plan. L= distance between locationsHorizontal
+/-
L/1000
15.Deflection under super dead load (GRC cladding) Vertical and
Horizontal
-35mm
16.Deflection under wind Vertical
+25mm/
-35mm
17.
Deflection under live load (1.0kN/m²)
Not to be considered in combination with maximum wind
condition.
Vertical
Less
than
wind
18.Movement under temperature variation (+/-30°C) Horizontal
+/-
30mm
Foundation Movements
19.
Differential settlement between adjacent foundation
supports. L= distance between supports.
e.g for support at 8m centers
Vertical
L/500
-15mm
7/31/2019 V 160741001 p
http://slidepdf.com/reader/full/v-160741001-p 6/14
D E S C R I P T I O N
R E V N O .
J O / E W O
D A T E
O P R N S
E N G
G
P M T
C E R T
DATE:
DATE:
DATE:
DATE:
DATE:
D A T E :
B Y :
C O N T R O L N U M B E R
PROJECTENGINEER
CONSTRUCTION AGENCY
DISCIPLINE
ENGINEER
V E R I F I C A T I O N
E D S D
R E V I S I O
N C
E R T I F I C A T E
T H I S I N D I C A T E S T H A T R E V . N O .__________
O F T H I S D R A W I N G I S C O V E R E D , F O R A L L
A P P R O V A L / C E R
T I F I C A T I O N R E Q U I R E M E N T S ,
B Y D R A W I N G C
O M P L E T I O N C E R T I F I C A T E
( D C C ) N O .____
_________________
OPERATIONS
CERTIFIED
R E V I S I O N C
E R T I F I C A T I O N
6
OF14
DOCK63
A E-
JO / EWO: 00A
BI-25-00013-0002
2 5 - 0
0 0 1 3 4 - 0 0 0 2 - 0 0 1
SAU
KAG
LT
MS
S A U
K A G
L T
M S
B I - 2 5 -
0 0 0 1 3 -
0 0 0 2
STRUCTURAL MOVEMENTS REPORTKING ABDULLAH PETROLEUM STUDIES AND
RESEARCH CENTER – RESEARCH & OFFICE COMPLEX
RIYADH
T H I S D R A W I N G A N D T H E I N F O R M A T I O N C O N T A I N E D H E R E I N A R E T H E S O L E P R O P E R T Y O F S A U D I A R A M C O .
N O R E P R O D U C T I O N I N F U L L O R I N P A R T S H A L L B E O B T A I N E D F R O M T H I S D O C U M E N T W I T H O U T T H E W R I T T E N C O N S E N T O F I T S O W N E R .
EDSD/2616-0399.doc
Saudi Aramco 2616-ENG (03/99)
V 160741
SAUDI ARABIA
REV.NO. SHT.NO. DRAWING NO. INDEX PLANT NO. DWG.TYPE
SAUDI ARABIAN OIL COMPANY
Library
Superstructure Lateral Movements
20.
Movement under wind, up to full height above ground.
Overall height = HHorizontal
+/-
H/375
21.Inter-storey drift. Storey height = h Horizontal
+/-
h/375
Floor Slabs at Courtyard/Atrium Edge
22. Positional tolerance of slab edgeVertical and
Horizontal
+/-
15mm
23.Slab edge deflection due to super dead load and live
load
Vertical
Short Term/
Long Term
-15mm/
-30mm
24.Relative deflection between adjacent points on a slab
due to super dead load and live load
After installation of
cladding
L / 480
25.Ground floor deflection Vertical
After installation of
cladding
- 30mm
Slab to External Terrace
26. Positional tolerance of slab level Vertical+/-
15mm
27.Relative deflection between adjacent points on a slab
due to super dead load and live load
After installation of
cladding
L / 480
28.First Floor slab deflection due to super dead load and
live load
Vertical
Short Term/
Long Term
-15mm/
-30mm
7/31/2019 V 160741001 p
http://slidepdf.com/reader/full/v-160741001-p 7/14
D E S C R I P T I O N
R E V N O .
J O / E W O
D A T E
O P R N S
E N G
G
P M T
C E R T
DATE:
DATE:
DATE:
DATE:
DATE:
D A T E :
B Y :
C O N T R O L N U M B E R
PROJECTENGINEER
CONSTRUCTION AGENCY
DISCIPLINE
ENGINEER
V E R I F I C A T I O N
E D S D
R E V I S I O
N C
E R T I F I C A T E
T H I S I N D I C A T E S T H A T R E V . N O .__________
O F T H I S D R A W I N G I S C O V E R E D , F O R A L L
A P P R O V A L / C E R
T I F I C A T I O N R E Q U I R E M E N T S ,
B Y D R A W I N G C
O M P L E T I O N C E R T I F I C A T E
( D C C ) N O .____
_________________
OPERATIONS
CERTIFIED
R E V I S I O N C
E R T I F I C A T I O N
7
OF14
DOCK63
A E-
JO / EWO: 00A
BI-25-00013-0002
2 5 - 0
0 0 1 3 4 - 0 0 0 2 - 0 0 1
SAU
KAG
LT
MS
S A U
K A G
L T
M S
B I - 2 5 -
0 0 0 1 3 -
0 0 0 2
STRUCTURAL MOVEMENTS REPORTKING ABDULLAH PETROLEUM STUDIES AND
RESEARCH CENTER – RESEARCH & OFFICE COMPLEX
RIYADH
T H I S D R A W I N G A N D T H E I N F O R M A T I O N C O N T A I N E D H E R E I N A R E T H E S O L E P R O P E R T Y O F S A U D I A R A M C O .
N O R E P R O D U C T I O N I N F U L L O R I N P A R T S H A L L B E O B T A I N E D F R O M T H I S D O C U M E N T W I T H O U T T H E W R I T T E N C O N S E N T O F I T S O W N E R .
EDSD/2616-0399.doc
Saudi Aramco 2616-ENG (03/99)
V 160741
SAUDI ARABIA
REV.NO. SHT.NO. DRAWING NO. INDEX PLANT NO. DWG.TYPE
SAUDI ARABIAN OIL COMPANY
Floor Slabs at Building Perimeter
29. Positional tolerance of slab edgeVertical and
Horizontal
+/-
15mm
30.Slab edge deflection due to super dead load and live
load
Vertical
Short Term
/Long Term
-15mm/
-30mm
31.Relative deflection between adjacent points on a slab
due to super dead load and live load
After installation of
cladding
L / 480
32.Ground floor deflection Vertical
After installation of
cladding
- 30mm
Roof Steelwork
33.
Construction tolerance on theoretical position (including
self weight deflection)
Vertical and
Horizontal
+30mm/
-80mm
34.
Construction tolerance on relative dimension between
adjacent locations in plan. L= distance between locationsHorizontal
+/-
L/1000
35.Deflection under super dead load (GRC cladding) Vertical and
Horizontal
-35mm
36.Deflection under wind Vertical
+25mm/
-35mm
37.
Deflection under live load (1.0kN/m²)
Not to be considered in combination with maximum wind
condition.
Vertical
Less
than
wind
38.Movement under temperature variation (+/-30°C) Horizontal
+/-
30mm
Foundation Movements
39.
Differential settlement between adjacent foundation
supports. L= distance between supports.
e.g for support at 10m centers
Vertical
L/500
-20mm
7/31/2019 V 160741001 p
http://slidepdf.com/reader/full/v-160741001-p 8/14
D E S C R I P T I O N
R E V N O .
J O / E W O
D A T E
O P R N S
E N G
G
P M T
C E R T
DATE:
DATE:
DATE:
DATE:
DATE:
D A T E :
B Y :
C O N T R O L N U M B E R
PROJECTENGINEER
CONSTRUCTION AGENCY
DISCIPLINE
ENGINEER
V E R I F I C A T I O N
E D S D
R E V I S I O
N C
E R T I F I C A T E
T H I S I N D I C A T E S T H A T R E V . N O .__________
O F T H I S D R A W I N G I S C O V E R E D , F O R A L L
A P P R O V A L / C E R
T I F I C A T I O N R E Q U I R E M E N T S ,
B Y D R A W I N G C
O M P L E T I O N C E R T I F I C A T E
( D C C ) N O .____
_________________
OPERATIONS
CERTIFIED
R E V I S I O N C
E R T I F I C A T I O N
8
OF14
DOCK63
A E-
JO / EWO: 00A
BI-25-00013-0002
2 5 - 0
0 0 1 3 4 - 0 0 0 2 - 0 0 1
SAU
KAG
LT
MS
S A U
K A G
L T
M S
B I - 2 5 -
0 0 0 1 3 -
0 0 0 2
STRUCTURAL MOVEMENTS REPORTKING ABDULLAH PETROLEUM STUDIES AND
RESEARCH CENTER – RESEARCH & OFFICE COMPLEX
RIYADH
T H I S D R A W I N G A N D T H E I N F O R M A T I O N C O N T A I N E D H E R E I N A R E T H E S O L E P R O P E R T Y O F S A U D I A R A M C O .
N O R E P R O D U C T I O N I N F U L L O R I N P A R T S H A L L B E O B T A I N E D F R O M T H I S D O C U M E N T W I T H O U T T H E W R I T T E N C O N S E N T O F I T S O W N E R .
EDSD/2616-0399.doc
Saudi Aramco 2616-ENG (03/99)
V 160741
SAUDI ARABIA
REV.NO. SHT.NO. DRAWING NO. INDEX PLANT NO. DWG.TYPE
SAUDI ARABIAN OIL COMPANY
Conference Centre
Superstructure Lateral Movements
40.
Movement under wind, up to full height above ground.
Overall height = HHorizontal
+/-
H/375
41.Inter-storey drift. Storey height = h Horizontal
+/-
h/375
Floor Slabs at Courtyard Edge
42. Positional tolerance of slab edgeVertical and
Horizontal
+/-
15mm
43.Slab edge deflection due to super dead load and live
load
Vertical
Short Term/
Long Term
-15mm/
-30mm
44.Relative deflection between adjacent points on a slab
due to super dead load and live load
After installation of
cladding
L / 480
45.Ground floor deflection Vertical
After installation of
cladding
- 30mm
Floor Slabs at Building Perimeter
46. Positional tolerance of slab edgeVertical and
Horizontal
+/-
15mm
47.Slab edge deflection due to super dead load and live
load
Vertical
Short Term
/Long Term
-15mm/
-30mm
48.Relative deflection between adjacent points on a slab
due to super dead load and live load
After installation of
cladding
L / 480
49.Ground floor deflection Vertical
After installation of
cladding
- 30mm
7/31/2019 V 160741001 p
http://slidepdf.com/reader/full/v-160741001-p 9/14
D E S C R I P T I O N
R E V N O .
J O / E W O
D A T E
O P R N S
E N G
G
P M T
C E R T
DATE:
DATE:
DATE:
DATE:
DATE:
D A T E :
B Y :
C O N T R O L N U M B E R
PROJECTENGINEER
CONSTRUCTION AGENCY
DISCIPLINE
ENGINEER
V E R I F I C A T I O N
E D S D
R E V I S I O
N C
E R T I F I C A T E
T H I S I N D I C A T E S T H A T R E V . N O .__________
O F T H I S D R A W I N G I S C O V E R E D , F O R A L L
A P P R O V A L / C E R
T I F I C A T I O N R E Q U I R E M E N T S ,
B Y D R A W I N G C
O M P L E T I O N C E R T I F I C A T E
( D C C ) N O .____
_________________
OPERATIONS
CERTIFIED
R E V I S I O N C
E R T I F I C A T I O N
9
OF14
DOCK63
A E-
JO / EWO: 00A
BI-25-00013-0002
2 5 - 0
0 0 1 3 4 - 0 0 0 2 - 0 0 1
SAU
KAG
LT
MS
S A U
K A G
L T
M S
B I - 2 5 -
0 0 0 1 3 -
0 0 0 2
STRUCTURAL MOVEMENTS REPORTKING ABDULLAH PETROLEUM STUDIES AND
RESEARCH CENTER – RESEARCH & OFFICE COMPLEX
RIYADH
T H I S D R A W I N G A N D T H E I N F O R M A T I O N C O N T A I N E D H E R E I N A R E T H E S O L E P R O P E R T Y O F S A U D I A R A M C O .
N O R E P R O D U C T I O N I N F U L L O R I N P A R T S H A L L B E O B T A I N E D F R O M T H I S D O C U M E N T W I T H O U T T H E W R I T T E N C O N S E N T O F I T S O W N E R .
EDSD/2616-0399.doc
Saudi Aramco 2616-ENG (03/99)
V 160741
SAUDI ARABIA
REV.NO. SHT.NO. DRAWING NO. INDEX PLANT NO. DWG.TYPE
SAUDI ARABIAN OIL COMPANY
Roof Steelwork
50.
Construction tolerance on theoretical position (including
self weight deflection)
Vertical and
Horizontal
+30mm/
-80mm
51.
Construction tolerance on relative dimension between
adjacent locations in plan. L= distance between locationsHorizontal
+/-
L/1000
52.Deflection under super dead load (GRC cladding) Vertical and
Horizontal
-35mm
53.Deflection under wind Vertical
+25mm/
-35mm
54.
Deflection under live load (1.0kN/m²)
Not to be considered in combination with maximum wind
condition.
Vertical
Less
than
wind
55.Movement under temperature variation (+/-30°C) Horizontal
+/-
30mm
Foundation Movements
56.
Differential settlement between adjacent foundation
supports. L= distance between supports.
e.g :
for support at 10m centers
for supports at 14m centres
Vertical
L/500
-20mm
-28mm
7/31/2019 V 160741001 p
http://slidepdf.com/reader/full/v-160741001-p 10/14
D E S C R I P T I O N
R E V N O .
J O / E W O
D A T E
O P R N S
E N G
G
P M T
C E R T
DATE:
DATE:
DATE:
DATE:
DATE:
D A T E :
B Y :
C O N T R O L N U M B E R
PROJECTENGINEER
CONSTRUCTION AGENCY
DISCIPLINE
ENGINEER
V E R I F I C A T I O N
E D S D
R E V I S I O
N C
E R T I F I C A T E
T H I S I N D I C A T E S T H A T R E V . N O .__________
O F T H I S D R A W I N G I S C O V E R E D , F O R A L L
A P P R O V A L / C E R
T I F I C A T I O N R E Q U I R E M E N T S ,
B Y D R A W I N G C
O M P L E T I O N C E R T I F I C A T E
( D C C ) N O .____
_________________
OPERATIONS
CERTIFIED
R E V I S I O N C
E R T I F I C A T I O N
10OF14
DOCK63
A E-
JO / EWO: 00A
BI-25-00013-0002
2 5 - 0
0 0 1 3 4 - 0 0 0 2 - 0 0 1
SAU
KAG
LT
MS
S A U
K A G
L T
M S
B I - 2 5 -
0 0 0 1 3 -
0 0 0 2
STRUCTURAL MOVEMENTS REPORTKING ABDULLAH PETROLEUM STUDIES AND
RESEARCH CENTER – RESEARCH & OFFICE COMPLEX
RIYADH
T H I S D R A W I N G A N D T H E I N F O R M A T I O N C O N T A I N E D H E R E I N A R E T H E S O L E P R O P E R T Y O F S A U D I A R A M C O .
N O R E P R O D U C T I O N I N F U L L O R I N P A R T S H A L L B E O B T A I N E D F R O M T H I S D O C U M E N T W I T H O U T T H E W R I T T E N C O N S E N T O F I T S O W N E R .
EDSD/2616-0399.doc
Saudi Aramco 2616-ENG (03/99)
V 160741
SAUDI ARABIA
REV.NO. SHT.NO. DRAWING NO. INDEX PLANT NO. DWG.TYPE
SAUDI ARABIAN OIL COMPANY
Musalla + IT Center
Superstructure Lateral Movements
57.
Movement under wind, up to full height above ground.
Overall height = HHorizontal
+/-
H/375
Roof Steelwork
58.
Construction tolerance on theoretical position (including
self weight deflection)
Vertical and
Horizontal
+30mm/
-80mm
59.Construction tolerance on relative dimension between
adjacent locations in plan. L= distance between locationsHorizontal
+/-
L/1000
60.Deflection under super dead load (GRC cladding) Vertical and
Horizontal
-35mm
61.Deflection under wind Vertical
+25mm/
-35mm
62.
Deflection under live load (1.0kN/m²)
Not to be considered in combination with maximum wind
condition.
Vertical
Less
than
wind
63.Movement under temperature variation (+/-30°C) Horizontal +/-
30mm
7/31/2019 V 160741001 p
http://slidepdf.com/reader/full/v-160741001-p 11/14
D E S C R I P T I O N
R E V N O .
J O / E W O
D A T E
O P R N S
E N G
G
P M T
C E R T
DATE:
DATE:
DATE:
DATE:
DATE:
D A T E :
B Y :
C O N T R O L N U M B E R
PROJECTENGINEER
CONSTRUCTION AGENCY
DISCIPLINE
ENGINEER
V E R I F I C A T I O N
E D S D
R E V I S I O
N C
E R T I F I C A T E
T H I S I N D I C A T E S T H A T R E V . N O .__________
O F T H I S D R A W I N G I S C O V E R E D , F O R A L L
A P P R O V A L / C E R
T I F I C A T I O N R E Q U I R E M E N T S ,
B Y D R A W I N G C
O M P L E T I O N C E R T I F I C A T E
( D C C ) N O .____
_________________
OPERATIONS
CERTIFIED
R E V I S I O N C
E R T I F I C A T I O N
11OF14
DOCK63
A E-
JO / EWO: 00A
BI-25-00013-0002
2 5 - 0
0 0 1 3 4 - 0 0 0 2 - 0 0 1
SAU
KAG
LT
MS
S A U
K A G
L T
M S
B I - 2 5 -
0 0 0 1 3 -
0 0 0 2
STRUCTURAL MOVEMENTS REPORTKING ABDULLAH PETROLEUM STUDIES AND
RESEARCH CENTER – RESEARCH & OFFICE COMPLEX
RIYADH
T H I S D R A W I N G A N D T H E I N F O R M A T I O N C O N T A I N E D H E R E I N A R E T H E S O L E P R O P E R T Y O F S A U D I A R A M C O .
N O R E P R O D U C T I O N I N F U L L O R I N P A R T S H A L L B E O B T A I N E D F R O M T H I S D O C U M E N T W I T H O U T T H E W R I T T E N C O N S E N T O F I T S O W N E R .
EDSD/2616-0399.doc
Saudi Aramco 2616-ENG (03/99)
V 160741
SAUDI ARABIA
REV.NO. SHT.NO. DRAWING NO. INDEX PLANT NO. DWG.TYPE
SAUDI ARABIAN OIL COMPANY
External Courtyard Frame Lateral Movements
64.
Movement under wind, up to full height above ground.
Overall height = H, Cantilever Length = L
Horizontal at
column locations +/- H/100
65.
Movement under wind, up to full height above ground.
Overall height = H, Cantilever Length = L
Horizontal at
cantilever tip
+/- (H/100
+ L/360)
External Courtyard Roof Steelwork
66.
Construction tolerance on theoretical position (including
self weight deflection)
Vertical and
Horizontal
+30mm/
-100mm
67.Construction tolerance on relative dimension betweenadjacent locations in plan. L= distance between locations
Horizontal +/-L/1000
68.Deflection under super dead load (GRC cladding) Vertical and
Horizontal
-40mm
69.Deflection under wind Vertical
+50mm/
-35mm
70.
Deflection under live load (1.0kN/m²)
Not to be considered in combination with maximum wind
condition.
Vertical
Less
than
wind
71.
Exposed to temperature variation during construction
and in service. In service temperature range to be
allowed: -5°C to 60°C
Horizontal +/-70mm
Foundation Movements
72.
Differential settlement between adjacent foundation
supports. L= distance between supports.
e.g :
for support at 8m centers
Vertical
L/500
-15mm
7/31/2019 V 160741001 p
http://slidepdf.com/reader/full/v-160741001-p 12/14
D E S C R I P T I O N
R E V N O .
J O / E W O
D A T E
O P R N S
E N G
G
P M T
C E R T
DATE:
DATE:
DATE:
DATE:
DATE:
D A T E :
B Y :
C O N T R O L N U M B E R
PROJECTENGINEER
CONSTRUCTION AGENCY
DISCIPLINE
ENGINEER
V E R I F I C A T I O N
E D S D
R E V I S I O
N C
E R T I F I C A T E
T H I S I N D I C A T E S T H A T R E V . N O .__________
O F T H I S D R A W I N G I S C O V E R E D , F O R A L L
A P P R O V A L / C E R
T I F I C A T I O N R E Q U I R E M E N T S ,
B Y D R A W I N G C
O M P L E T I O N C E R T I F I C A T E
( D C C ) N O .____
_________________
OPERATIONS
CERTIFIED
R E V I S I O N C
E R T I F I C A T I O N
12OF14
DOCK63
A E-
JO / EWO: 00A
BI-25-00013-0002
2 5 - 0
0 0 1 3 4 - 0 0 0 2 - 0 0 1
SAU
KAG
LT
MS
S A U
K A G
L T
M S
B I - 2 5 -
0 0 0 1 3 -
0 0 0 2
STRUCTURAL MOVEMENTS REPORTKING ABDULLAH PETROLEUM STUDIES AND
RESEARCH CENTER – RESEARCH & OFFICE COMPLEX
RIYADH
T H I S D R A W I N G A N D T H E I N F O R M A T I O N C O N T A I N E D H E R E I N A R E T H E S O L E P R O P E R T Y O F S A U D I A R A M C O .
N O R E P R O D U C T I O N I N F U L L O R I N P A R T S H A L L B E O B T A I N E D F R O M T H I S D O C U M E N T W I T H O U T T H E W R I T T E N C O N S E N T O F I T S O W N E R .
EDSD/2616-0399.doc
Saudi Aramco 2616-ENG (03/99)
V 160741
SAUDI ARABIA
REV.NO. SHT.NO. DRAWING NO. INDEX PLANT NO. DWG.TYPE
SAUDI ARABIAN OIL COMPANY
Visitors Center, Gate Houses and Other Ancillary Buildings
Superstructure Lateral Movements
73.
Movement under wind, up to full height above ground.
Overall height = HHorizontal
+/-
H/375
Roof
74.
Construction tolerance on theoretical position (including
self weight deflection)
Vertical and
Horizontal
+25mm/
-20mm
75.
Construction tolerance on relative dimension between
adjacent locations in plan. L= distance between locations
Horizontal+/-
L/1000
76.Deflection under super dead load (GRC cladding) Vertical and
Horizontal
-20mm
77.Deflection under wind Vertical
+/-
15mm
78.
Deflection under live load (1.0kN/m²)
Not to be considered in combination with maximum wind
condition.
Vertical
Less
than
wind
79.Movement under temperature variation (30°C) Horizontal
+/-
20mm
7/31/2019 V 160741001 p
http://slidepdf.com/reader/full/v-160741001-p 13/14
D E S C R I P T I O N
R E V N O .
J O / E W O
D A T E
O P R N S
E N G
G
P M T
C E R T
DATE:
DATE:
DATE:
DATE:
DATE:
D A T E :
B Y :
C O N T R O L N U M B E R
PROJECTENGINEER
CONSTRUCTION AGENCY
DISCIPLINE
ENGINEER
V E R I F I C A T I O N
E D S D
R E V I S I O
N C
E R T I F I C A T E
T H I S I N D I C A T E S T H A T R E V . N O .__________
O F T H I S D R A W I N G I S C O V E R E D , F O R A L L
A P P R O V A L / C E R
T I F I C A T I O N R E Q U I R E M E N T S ,
B Y D R A W I N G C
O M P L E T I O N C E R T I F I C A T E
( D C C ) N O .____
_________________
OPERATIONS
CERTIFIED
R E V I S I O N C
E R T I F I C A T I O N
13OF14
DOCK63
A E-
JO / EWO: 00A
BI-25-00013-0002
2 5 - 0
0 0 1 3 4 - 0 0 0 2 - 0 0 1
SAU
KAG
LT
MS
S A U
K A G
L T
M S
B I - 2 5 -
0 0 0 1 3 -
0 0 0 2
STRUCTURAL MOVEMENTS REPORTKING ABDULLAH PETROLEUM STUDIES AND
RESEARCH CENTER – RESEARCH & OFFICE COMPLEX
RIYADH
T H I S D R A W I N G A N D T H E I N F O R M A T I O N C O N T A I N E D H E R E I N A R E T H E S O L E P R O P E R T Y O F S A U D I A R A M C O .
N O R E P R O D U C T I O N I N F U L L O R I N P A R T S H A L L B E O B T A I N E D F R O M T H I S D O C U M E N T W I T H O U T T H E W R I T T E N C O N S E N T O F I T S O W N E R .
EDSD/2616-0399.doc
Saudi Aramco 2616-ENG (03/99)
V 160741
SAUDI ARABIA
REV.NO. SHT.NO. DRAWING NO. INDEX PLANT NO. DWG.TYPE
SAUDI ARABIAN OIL COMPANY
Car Park and Entrance Canopies
Superstructure Lateral Movements
80.
Movement under wind, up to full height above ground.
Overall height = HHorizontal
+/-
H/375
Roof
81.
Construction tolerance on theoretical position (including
self weight deflection)Vertical
+25mm/
-40mm
82.
Construction tolerance on relative dimension between
adjacent locations in plan. L= distance between locations
Horizontal+/-
L/1000
83.Movement under temperature variation (50°C) Horizontal
+/-
20mm
7/31/2019 V 160741001 p
http://slidepdf.com/reader/full/v-160741001-p 14/14
D E S C R I P T I O N
R E V N O .
J O / E W O
D A T E
O P R N S
E N G
G
P M T
C E R T
DATE:
DATE:
DATE:
DATE:
DATE:
D A T E :
B Y :
C O N T R O L N U M B E R
PROJECTENGINEER
CONSTRUCTION AGENCY
DISCIPLINE
ENGINEER
V E R I F I C A T I O N
E D S D
R E V I S I O
N C
E R T I F I C A T E
T H I S I N D I C A T E S T H A T R E V . N O .__________
O F T H I S D R A W I N G I S C O V E R E D , F O R A L L
A P P R O V A L / C E R
T I F I C A T I O N R E Q U I R E M E N T S ,
B Y D R A W I N G C
O M P L E T I O N C E R T I F I C A T E
( D C C ) N O .____
_________________
OPERATIONS
CERTIFIED
R E V I S I O N C
E R T I F I C A T I O N
14OF14
DOCK63
A E-
JO / EWO: 00A
BI-25-00013-0002
2 5 - 0
0 0 1 3 4 - 0 0 0 2 - 0 0 1
SAU
KAG
LT
MS
S A U
K A G
L T
M S
B I - 2 5 -
0 0 0 1 3 -
0 0 0 2
STRUCTURAL MOVEMENTS REPORTKING ABDULLAH PETROLEUM STUDIES AND
RESEARCH CENTER – RESEARCH & OFFICE COMPLEX
RIYADH
T H I S D R A W I N G A N D T H E I N F O R M A T I O N C O N T A I N E D H E R E I N A R E T H E S O L E P R O P E R T Y O F S A U D I A R A M C O .
N O R E P R O D U C T I O N I N F U L L O R I N P A R T S H A L L B E O B T A I N E D F R O M T H I S D O C U M E N T W I T H O U T T H E W R I T T E N C O N S E N T O F I T S O W N E R .
EDSD/2616-0399.doc
Saudi Aramco 2616-ENG (03/99)
V 160741
SAUDI ARABIA
REV.NO. SHT.NO. DRAWING NO. INDEX PLANT NO. DWG.TYPE
SAUDI ARABIAN OIL COMPANY
Movement Joints in Concrete Slabs
Lateral Movements
The predicted lateral movements at the movement joints due to shrinkage and thermal effects areillustrated in the following sketch.
The sketch illustrates the predicted movements at an indicative cross section through a movement joint(MJ).
The purpose of this sketch is to inform the architectural design of the movement joint.
The figures are in mm and are accurate to ±20%.
The figures are calculated on the basis that the materials and workmanship fully comply with thespecifications
1) T = 0 - Day after slab (B) is cast
2) T = 6 months – Possible date for installation of joint filler
3) In service - coldest day + maximum shrinkage
4) In service – hottest day